SUPERVISION GUIDE

For Architectural Works

2012 Edition

architectural I civil I electrical I mechanical I structural

Copyright 2012 Housing & Development Board. All rights reserved.


This publication is reference material for Consultants to develop an effective quality
management system (QMS) in their respective HDB-related projects. It is not a set
of exhaustive standards for Consultants to adhere to in their management of
architectural works. Consultants are responsible for meeting the standards imposed
by the Building Control Act and related Regulations as well as relevant Codes of
Practice, and for observing good industry practices to develop and implement their
QMS.
For the avoidance of doubt, if there is a difference between the contractual
obligations exacted on Consultants and the guidelines set out in this publication,
Consultants will be held to their respective contractual obligations.
This publication may not be reproduced or transmitted in any form or by any means
in whole or in part without the prior written consent of HDB.
While every effort has been made to ensure the accuracy of the information
contained in this publication, HDB and its employees shall not be responsible for any
mistakes or inaccuracies that may be contained here. Any liability and responsibility
to any party for losses or damage arising from this publication are expressly
disclaimed by HDB and its employees.

Foreword
Housing & Development Board (HDB) takes pride in housing more than 80% of the
population in Singapore. Delivering well-designed HDB flats of high quality has always
been our top priority.

HDB started to outsource the consultancy services for the design and supervision of
construction of HDB flats since 2003. We now have more than 100 consultants
participating in HDB projects. To ensure consistency in supervision practice and
standard, HDB has embarked on this project to produce a set of Supervision
Guide. They aim to serve as reference to the consultants in developing a
comprehensive Quality Assurance System for managing our projects.
There are altogether five Guides covering the supervision of architectural, structural
engineering, civil engineering, mechanical engineering and electrical engineering
works. These guides set out our expectations, share HDBs requirements and illustrate
good practices.

These Guides are now available at HDB BGBiz Portal (http://bgbiz.hdb.gov.sg/) for
your easy reference. We hope you will find them useful and informative. We will be
reviewing the guides regularly and we welcome your valuable feedback to further
improve the guides. Lets work together in the pursuit of quality excellence in our
projects.

Thomas Seow
Group Director
Building Quality Group
Housing & Development Board

Contents
1

Introduction

Pg 1

Materials

Pg 2

Workshop Drawings for Specialist Architectural Items

Pg 7

Work Method and Trade Demonstration

Pg 10

Timber Mock Up

Pg 14

Sample Units

Pg 17

In-process Supervision Works

Pg 25

Handing Over of Completed Works

Pg 27

CONQUAS

Pg 28

Annex Quality Checklists

Pg 30

10

Introduction

This guide book is to share with the Consultants on HDBs specific requirements,
quality management system, and some good practices in the supervision of
architectural works in HDB projects.
As part of the consultancy services, Consultants are required to submit their Quality
Assurance System to HDB before commencement of the building project. The
system shall cover the following:
a)

Accountability and responsibility of the Consultant and his team in


supervising the project

b)

Duty and responsibility of the consultant and his team in inspecting the
works at different stages of construction

c)

Quality control system (e.g. checklist, inspection and testing records) and
guidelines put in place for in-process supervision works

Consultants can use this guide book to develop the quality management system
and checklists/forms for supervising architectural works in HDB new development
projects.

2012 Housing & Development Board

Material Selection

2.1 Materials List


HDBs Materials List provides a comprehensive selection of quality products needed
for the HDB construction projects. The Consultant will find the Materials List useful in
helping them select the right quality products for their HDB projects.
The Consultants can also select products that are not listed in the Material List.
However, these products must comply fully with the technical specifications,
standards, approved drawing and/or other statutory requirements.
The Consultants can visit http://ml.eptc.sg/ to view the HDBs Materials List.

2.2 Timeline for Approval of Material


Within 6 weeks after the project starts, the Consultants and Contractor must jointly
compile a complete list of materials required for the project. All materials needed for
the sample units are to be approved by the Consultant within 6 months after the
project starts.

2012 Housing & Development Board

2.3 Display of Approved Materials


The materials approved by the Consultants are
to be displayed in the sample display room.
This is to facilitate the verification of the
materials installed on site against those
approved by Consultants earlier.

2.4 Testing of Materials


The Consultants are to ensure that material tests are carried out on items listed in
the Schedule of Material Tests and Specifications. The purpose of tests is to
ascertain that the material properties or application workmanship comply with the
performance standard as stated in the building specifications.

2.5 Sampling of Materials

All test samples are to be randomly selected from the materials on site and sent to
an accredited laboratory for testing. The samples are to be marked for
identification before sending to the laboratory.
For testing of completed works, the Consultants are required to carry out these
tests in tandem with the progress of works. This is to ensure consistency in quality
of the various batches of supplies and the workmanship achieved.

2.6 Evaluation of Test Report


Routing stamp shall be used to
document the test report
reviewed by Consultant. For
any test failures, HDB is to be
informed of the follow-up
actions taken.
The Consultants are also
required to track the status of
the material testing using the
Material Testing Register.
2012 Housing & Development Board

2012 Housing & Development Board

a) Average Compressive
Strength
b) Shrinkage

a) Tensile Pull out test


b) Tensile Adhesion
strength tests
c) Average Shrinkage
a) Tensile Pull out test
b) Tensile Adhesion
strength tests
c) Average Shrinkage

a) Shrinkage
b) Water absorption
c) Compressive strength
d) Tensile strength
e) Flexural strength
f) Abrasion Resistance

Pre-packed Floor
screed

Pre-packed skimmed
coat (Internal)

Tile grout

a) Average Compressive
Strength
b) Water penetration
c) Shrinkage

Pre-packed
waterproofing screed

)
)
) 1 test per type
)
)
)

3 tests per block

1 test

1 test

b) 1 test

b) Compression test

a) 1 test

Frequency Of Test For Each


Type Of Test

a)Tensile test

Scaffold wall ties

Type OF Test To Be
Carried Out

Type Of Material To Be
Tested

S/N

)
)
) 1 sample per test
)
)
)

5 spots per test

1 sample

1 sample

b) 3 samples

a) 3 samples

No. Of Samples Per


Test

30-Jul-10

2-Dec-10

2-Dec-09

2-Dec-09

25-Jul-09

Schedule Date

Example on Material Testing Register

4-Jan-11

26-Nov-09

26-Nov-09

26-Nov-09

4-Aug-09

8-Feb-11

30-Dec-09

31-Dec-09

31-Dec-09

6-Aug-09

Date Sent for


Testing Date
Testing

Passed

Passed

Passed

Passed

Passed

Result

2.7 Protection of Materials


All materials including pre-packed materials are to be stored, stacked and
protected properly on site. Improper protection and storage of material will affect
the quality of the finished product. The Consultants are required to conduct
regular checks on material storage.
S/No

Trades

Metal Gate
e.g. wrapped with plastic
sheets and cardboard sheets

Timber Door
e.g. wrapped with plastic
sheets, cardboard sheets,
bubble foam or other suitable
materials of adequate
thickness to cushion the door
surface against impact

Window Glazing with Frame


e.g. wrapped with stout paper,
cardboard or other protective
material which could cushion
the surface against impact

Window Frame
e.g. wrapped with translucent
self-adhesive tape (nostaining), stout paper,
cardboard or suitable
protective material which could
cushion the surface against
impact

Protection

2012 Housing & Development Board

Examples on Protection of Materials


S/No

Trades

Floor Tiles
e.g. covered with thick
polyethylene sheet or other
suitable protective material
which could cushion the
surface against impact

Timber Floor
e.g. covered with thick
polyethylene sheet or other
suitable protective material
which could cushion the
surface against impact

Cementitious pre-packed
materials
e.g stored, stacked and
protected against weather
on site

Protection

2012 Housing & Development Board

3 Workshop Drawings for Specialist Architectural Items

3.1 Workshop Drawings


Workshop drawings are required for Specialist Architectural Items. These items are
proprietary/non-standard in nature and require Contractors Professional Engineer
(Specialist) to design.
The Consultants are required to supervise the installation of these items and
ensure that it is done according to the approved workshop drawings. Any
deviations from the approved workshop drawing or specifications are to be
highlighted and resolved so as to minimize subsequent design adjustments on site.

Example of Shop Drawing

3.2 Timeline for Submission and Approval


The Consultants shall make provision in the Contractors construction planning for
the submission of workshop drawings for the specialist architectural items.
The Consultant shall ensure approval is obtained for the submitted workshop
drawings, preferably 3 months before the commencement of the specialist
architectural works.

2012 Housing & Development Board

3.3 Endorsement of Workshop Drawings


The workshop drawings of specialist architectural items are to be jointly endorsed
by the Contractors PE (Specialist) and the Consultants. The Contractors PE
(Specialist) and Consultants are fully responsible for these designs.

The Consultants shall ensure that these items are designed to be easily
constructible, robust, maintainable and durable.
Endorsements
by QP & PE

3.4 Examples of Specialist Architectural Items


The examples of these Specialist Architectural Items are :

Non-standard aluminium windows (non cast-in type)


height/full height aluminium windows (non cast-in type)
Laminated safety glass and grilles
Grille panel, railing, aluminium louvre, perforated aluminium panel at lift lobby
Perforated aluminium infill panel for stainless steel railing

2012 Housing & Development Board

3.5 Examples of Good Installation


1) Window Friction Stay Rivet

Rivet must be properly tightened

Rivet easily removed

2) Safety Stopper for Sliding Window

Two safety stoppers installed for single panel window

Only one safety stopper installed for single panel


window

3) Cast-In Bolt and Nut

Sufficient cast in bolt

Insufficient cast in bolt

4) Impact Anchor for Non Cast-In Aluminum Window Frame

Anchor to be fully embedded

Anchor not fully embedded

2012 Housing & Development Board

Work Method and Trade Demonstration

4.1 Work Method and Trade Demonstration


The approval of work method and trade demonstration is to ensure the works are
carried out in accordance to the specifications and drawings.
It is important that work demonstration is carried out prior to mass production. This
would prevent abortive work and reduce defects.

Work
Method

Trade
Demonstration

Sample Unit

Mass Production

Trade demonstrations are to be conducted for architectural trades e.g. ferrolite


partition wall installation, waterproof membrane application etc., prior to mass
production. The Consultants are responsible for the inspection and approval of the
work methods and workmanship. When approved, the Contractor may then proceed
with the works according to the approved work methods.

Trade demonstration on the application of waterproofing membrane


The demonstration on work method will enable the supervisory staff from Consultants and
Contractor to know what to look out for during the mass production stage.

2012 Housing & Development Board

10

4.2 Procedures for Trade Demonstration


a)

The work method of the trade has to be approved by the Consultant before
the trade demonstration.

b)

The trade demonstration should be preceded by a briefing by the


Contractor.

c)

The briefing session is for the understanding and agreement of the work
method amongst all parties concerned.

d)

Any refinement and amendment made to the approved work method during
the trade demonstration are to be recorded in the original method
statements and endorsed by the Consultant.

e)

Copies of the method statements are to be distributed to Consultant and


Contractor supervisory staff for reference and supervision.

f)

The trade demonstration is to be conducted at the actual work area. This is


to simulate the real work situation such that practical problems/constraints
can be dealt with prior to mass production stage.

g)

Photographs of the various steps in the trade demonstration are be


displayed in the site meeting room to serve as records and reference for
supervision.

2012 Housing & Development Board

11

4.3 Example on Trade Demonstration on Floor Tiling Works


TRADE DEMO-FLOOR TILING

1. Sweep and clean floor before


laying screed.

2. Set tile layout according to


approved shop-drawing.

3. Clean screed surface before


laying floor tile.

4. Sort tiles to consistent size


before laying.

5. Mix tile adhesive according to


manufactures instruction.

6. Apply tile adhesive on screed


surface using notch trowel.

2012 Housing & Development Board

12

Example on Trade Demonstration on Floor Tiling Works (cont)


Cont Trade Demo-Floor Tiling

7.

Apply tile adhesive onto the back


of tile and spread it uniformly.

8.

Tap tile using rubber hammer


to ensure full contact.

9.

Adjust the tile position within 5


minutes of laying.

10. Insert tile spacer to achieve


consistent joint width.

11. Fill tile joint between floor tiles


with tile grout.

12. Remove excess grout using


spreader and damp cloth.

2012 Housing & Development Board

13

Timber Mock Up

5.1 Construction of Timber Mock Up


The construction of the timber mock up for kitchen, toilet and service yard is to
identify any issues related to design, maintenance and practicality of the proposed
layout. It is important to confirm the layout, sanitary fitting arrangement and
locations of M&E services so that the openings and recess for these services can
be finalised before the approval of precast workshop drawings.
The timber mock up will help to minimise subsequent changes in precast
components and prevent abortive works during construction stage.

5.2 Timeline for Completion of Timber Mock Up


The timber mock up for toilet, kitchen and service yard are to be erected within 3
months after the commencement of work.

2012 Housing & Development Board

14

5.3 Inspection of Timber Mock Up


The timber mock-up must show the provision of all sanitary pipes and fixtures
position, marking of water supply pipes layout, power points and switches locations,
electrical water heater socket locations and provision of UPVC entry pipe for water
supply using gas water heater. Actual UPVC sanitary pipes, wash basin and
pedestal pan; and mock-up of ceiling duct, doors, vanity top (if any) and clothes
drying racks shall be installed with respect to the architectural and structural layout.
Marking of beams, wall tiles, floor tiles, window layout must also be shown.
The timber mock-ups must be built accurately to facilitate resolution of the following
common issues:
a)

floor waste/trap not obstructed by structural beam;

b)

lighting points not obstructed by ceiling-mounted clothes drying rack,


beams;

c)

use of external clothes drying rack not hindered by air-con ledge;

d)

sufficient clearance for access to the air-con ledge for installation and
maintenance of the air-con compressors;

e)

toilet vent and other fittings do not obstruct future installation of shower
screen;

f)

opening of door not obstructed by pedestal, wash basin or sanitary pipe;

g)

sufficient clearance for installation of heater and washing machine (to be


installed by resident);

h)

piping arrangement is optimal and facilitate future maintenance; and

i)

any other practical considerations.

The inspection of timber mock up must be carried out in the presence of


Architectural, C&S, and M&E Consultants. The layout of the timber mock-up must
conform to Sales Brochure (e.g. no deviation on the locations of pedestal, wash
basin and door)

2012 Housing & Development Board

15

5.4 Examples of Timber Mock Up

Bathroom

Bathroom

Bathroom

Service Yard and A/C Ledge

Kitchen

Kitchen
2012 Housing & Development Board

16

6 Sample Units

6.1 Construction of Sample Units


Sample units are to be constructed for all flat types with different layout. The
objectives of setting up the sample units are to :
(a)

Ensure each flat type is constructed according to specifications &


drawings before mass production

(b)

Eliminate any discrepancies between drawings and sales brochures

(c)

Minimise subsequent design adjustment and

(d)

Serve as visual reference for workmanship standard for finishing works.

The workmanship standards set in the approved sample units will be used as a
common reference standard when Contractor proceeds with mass production.
Hence, the workmanship set in sample units must comply with Quality Standards
stated in the specifications.

Sample Unit

2012 Housing & Development Board

17

6.2 Timeline for Completion of Sample Units


The sample unit construction shall commence when casting slab reaches 5 th storey
and be completed within 3 months. For a typical 20-storey development, the sample
shall be completed one year after commencement of the works

The approval of sample unit by Consultant is a critical milestone. The Consultant is


required to track the works and approve it timely so as not to hold back the mass
production.

6.3 Documents for Sample Unit Inspection


The sample units are to be approved by Consultant first before arranging HDB to
view it. The following documents are to be ready before the viewing of the sample
unit by HDB :

a)
b)
c)
d)
e)

Site layout plan


List of materials used in sample units
Sales brochure unit layout
Sales brochure general specifications
QP declaration form

2012 Housing & Development Board

18

a)

Site Layout Plan

2012 Housing & Development Board

19

b) Example on List of Materials Used in Sample Unit

2012 Housing & Development Board

20

c) Sales Brochure Unit Layout

2012 Housing & Development Board

21

d) Sales Brochure General Specifications

2012 Housing & Development Board

22

e) QP Declaration Form

2012 Housing & Development Board

23

6.4 Examples of Non-conformance in Sample Units

1) Column profile at sample unit differs from sales brochure

Sample unit

recess

Sales brochure

2) Base plate of metal gate differs from guide drawing

Guide drawing

Sample unit

3) Tile at main entrance ramp differs from specifications

Building
specifications

Sample unit

Smooth tile is used

Textured /structured tile is


specified.

2012 Housing & Development Board

24

InProcess Supervision Works

7.1 Quality Control System


Work method demonstration, sample unit inspection, materials testing, work
sequence inspections and functional testing of completed works are key processes
of good quality assurance system. This is to ensure that acceptable quality
materials are used, right work procedures are employed and a high level of
workmanship standard is executed to produce a quality finished product.

7.2 Guide and Checklist for In-process Supervision

After the approval of sample units and the commencement of mass production, the
Consultant shall carry out in-process checking during the entire construction stage.
More regular checks shall be carried out when works just commenced or a new
group of workers joins the workforce. This is to ensure that non-compliances are
detected early and minimise the need for rectification works.
The Consultant is required to set the guidelines and develop checklists to guide
the supervisory staff in the supervision of in-process work. The guidelines shall
include the frequency of checks for various trades. For critical trades such as
application of waterproofing membrane, 100% check would be required before the
works are covered up.

Checklist and Inspection


Record for in-process
supervision.
Refer to Annex for sample
of checklists.

2012 Housing & Development Board

25

7.3 Control Of Non-Conforming Products


It is important to check for irregularities while the works are in progress as failure
to detect these irregularities may lead to potential latent defects. In addition, by
stopping the wrong practice during the in-process supervision, it will educate the
Contractor the concept of Do It Right The First Time.
When non-conforming procedures, materials or workmanship are discovered,
the Consultants are required to investigate the cause of the non-conformance
and take corrective actions promptly to rectify it. In addition, the Consultant must
also review with Contractor to identify shortcomings and take measures to
prevent recurrence.
Non
compliance
detected

Investigate
cause

Take
corrective
action

Put control
measures in
place

Example of Non-Conformance

Corrective Action

Sanitary pipes were damaged in some toilets.

Damaged pipes had been replaced and ponding


test was conducted to the toilets.

Fish tail bracket was not properly secured


using bolt and nut.

Fish tail bracket was secured with bolt and nut


and tag welding.
2012 Housing & Development Board

26

Handing Over of Completed Works

8.1 Handing Over Inspection


The completed residential blocks will be taken over on a block by block basis. The
Consultants must ensure that Temporary Occupation Permit (TOP) is obtained and
the block passed HDBs inspection before certifying completion for the block.
8.2 Pre-Inspection Briefing
The Consultant is required to attend the "pre-inspection briefing by HDBs
Building Inspection Team (BIT). The briefing is to prepare the project team on the
requirements and procedures for proper handing over of the completed blocks.
The briefing will cover BIT inspection procedures, critical functional tests, lockingup inspection and handing over of keys to HDB and Town Council.
8.3 Site Showround
Consultant is required to conduct a site showround for the Branch Office and Town
Council before handing over of first block. This is to prepare and facilitate the
management of defects during the defects liability period (DLP) by the contractor,
Branch Office and Town Council.

The Consultant shall provide the following information and drawings to the Branch
Office :
Contract particulars
Particulars of the Consultants
Particulars of contractors essential personnel during DLP
Approved method statements on repair of common defects
Estate layout plan
Service road/driveway plan
MSCP plan for all decks
Electrical layout plan of street lighting
List of suppliers for main fixtures/installations
Concealed wiring and piping plans
Brochure for various fixtures and fittings
As-Built drawings (Elevation & Plan View of Block)

2012 Housing & Development Board

27

CONQUAS

9.1 Role of Consultant


BCAs CONQUAS Score is a Quality Benchmark for new development project. The
Consultant is required to be actively involved in raising the CONQUAS Score of the
project. This includes:

a)

Be trained and familiarized with the CONQUAS 21 assessment procedures


and the Quality Standards.

b)

Work with HDB to seek commitment from Contractors Senior Management


during the Construction Programme signing Ceremony to set high CONQUAS
Target.

c)

Design to CONQUAS e.g. avoid detailing that demand highly on the skills of
workers on site

d)

Put in place a monitoring system and resolve quality issues

e)

Conduct pre-assessment of the completed works before contractor proceeds


to book for BCA assessment.

f)

Check that the Contractor conducts their own Materials and Functional Test
indicated in the CONQUAS Manual before arranging for BCA assessment.

2012 Housing & Development Board

28

9.2 Examples of detailing that can help to improve CONQUAS Score


1) Window frame setting

Window frame
is flushed with
wall tile.

Window frame is
set in resulting
in many cut tiles.

2) Corners at beam/wall

Too many
edges at
beam/wall.

3) Cut-tile below beam

Small cut-tile below beam

2012 Housing & Development Board

29

10 ANNEX
Example: Inspection Checklist for Internal Waterproofing Works
PROJECT TITLE:
PROJECT NO.:
BLOCK NO.:
UNIT NO. / COMMON AREA (*delete where necessary):
Verification

WATERPROOFING WORKS AT INTERNAL WET AREAS

Complied

1. Records and
a) Proper supervision records by Consultant Site Supervisor
Documentation by b) Testing of material according to specification (e.g. pre-packed
Consultant
waterproofing screed)

2. Material
3. Substrate
Preparation

4. Waterproofing
Membrane
Application

6. Water Test

Yes/No/NA

c) Approval of method statement by Consultant

Yes/No/NA

d) Approval of work demonstration by Consultant

Yes/No/NA

a) Use of correct type of waterproofing system under HDBs materials list

Yes/No/NA

b) Use of mechanical mixer (for two-part system)

Yes/No/NA

a) Substrate in sound condition (surface flat & even / adequate fall to


outlets & wetted to damp)

Yes/No/NA

b) Pipe / floor openings fitted with temporary caps so that debris cannot
enter and cause chokage

Yes/No/NA

c) Wall rendered flat and even

Yes/No/NA

d) 45o mortar fillet to edge between floor and wall or pipes

Yes/No/NA

e) No surface ponding or running water

Yes/No/NA

f) Cleanliness (free of dust & laitance)

Yes/No/NA

a) Application of 1st coat with a roller or brush (allow first coat to dry to
touch)

Yes/No/NA

b) Application of 2nd coat in perpendicular direction to the 1st coat

Yes/No/NA

c) Corners and pipe properly coated with the aid of a brush

Yes/No/NA

d) Upturn of at least 200 mm onto walls

Yes/No/NA

e) Upturn of at least 50 mm onto pipes

Yes/No/NA

f) Upturn onto the kerb as shown in the drawing

Yes/No/NA

g) No air entrapped in the membrane

Yes/No/NA

h) Kitchen/service yard outlets coverage of 400mm radius from the


centre of outlet

Yes/No/NA

i) Thickness according to manufacturers recommendation

Yes/No/NA

j) Proper protection (after completion cordoned off the areas till


protective covering or screed has been laid)

Yes/No/NA

5. Curing &
a) Adequate curing between 1st & 2nd coat application
Protective Screed b) Application of approved pre-packed waterproof screed to protect the
waterproof membrane

Remarks

Yes/No/NA

Yes/No/NA
Yes/No/NA

c) Use of mechanical mixer & water measuring gauge

Yes/No/NA

d) Adequate fall towards outlets

Yes/No/NA

e) Minimum screed thickness = 15mm

Yes/No/NA

f) Provision of screed with rough surface

Yes/No/NA

a) A minimum depth of 10mm water flooding test for 24 hours within 1


month after application of waterproofing membrane and protective
screed
Time Start:_______, Time End: _______

Yes/No/NA

b) A minimum depth of 10mm water flooding test for 24 hours within 1


month before handing over inspection
Time Start:_______, Time End: _______

Yes/No/NA

2012 Housing & Development Board

30

Example: Inspection Checklist for Internal Plastering and Skimming Works

PROJECT TITLE:
PROJECT NO.:
BLOCK NO.:
UNIT NO.:
LOCATION:
Verification

ITEM

Complied

a) Proper supervision records by Consultant Site Supervisor

Yes/No/NA

b) Testing of material according to specification

Yes/No/NA

c) Approval of method statement by Consultant

Yes/No/NA

d) Approval of work demonstration by Consultant

Yes/No/NA

2. Material

a) Use of materials under HDBs materials list

Yes/No/NA

3. Alignment
Control

a) Verticality measurement submitted by contractor

Yes/No/NA

b) Structural repair, if any, completed

Yes/No/NA

4. Surface
Preparation

a) Sealed tie-bolt & wall plug holes with non-shrink grout

Yes/No/NA

b) Cleaned using high pressure water jet

Yes/No/NA

c) No loose particles, organic growth, residual form oil etc

Yes/No/NA

d) Precast panel joint brackets

Yes/No/NA

a) Used approved pre-packed mortar mix

Yes/No/NA

b) Used mechanical mixer

Yes/No/NA

c) Used water measuring gauge

Yes/No/NA

d) *Plaster (1st coat) cured 12 hrs

Yes/No/NA

e) Wetted surface prior to *plastering / skimming

Yes/No/NA

f) *Plaster total thickness max 18mm / Skim coat thickness


max 6mm

Yes/No/NA

a) Surface even

Yes/No/NA

b) Surface not rough

Yes/No/NA

1. Records and
Documentation
by Consultant

5. *Plastering /
Skimming

6. Alignment &
Workmanship

Remarks

2012 Housing & Development Board

31

Example: Inspection Checklist for Wall Tiling Works

PROJECT TITLE:
PROJECT NO.:
BLOCK NO.:
UNIT NO. / COMMON AREA (* Delete where necessary):
LOCATION:
Verification

ITEM
1. Preparation

2. Laying of Mortar
Rendering

a) Sealed wall-plug holes with non-shrink grout

Yes / No

b) Background free from loose particles

Yes / No

c) Fixed 150mm wide galv. metal strip lath


at joints between different base materials

Yes / No

d) Background dampened

Yes / No

a) Used approved pre-packed mortar mix

Yes / No

b) Used mechanical mixer

Yes / No

c) Used water measuring gauge

Yes / No

d) Control pegs provided

Yes / No

e) Lighting provided

Yes / No

f)
3. Laying of Wall
Tiles

4. Workmanship

Complied

Mortar thickness 10mm

Yes / No

a) Mortar rendered substrate set 12 hrs

Yes / No

b) Used *tile adhesive / polymer additive

Yes / No

c) Tiles soaked for 12 hrs

Yes / No

d) Applied bedding mortar (mix 1 OPC : 1 fine sand) 4mm


max on substrate & 2mm max on back of tile

Yes / No

e) Used mechanical mixer

Yes / No

f)

Yes / No

Grid lines indicated on walls

Remarks

g) Used tile spacers

Yes / No

h) Lighting provided

Yes / No

i)

Tilers are of certified worker

Yes / No

a) Surface even & no sharp edges

Yes / No

b) Even alignment of joints

Yes / No

c) No tonal variation

Yes / No

d) Tile cutting neat

Yes / No

Note: Site Supervisor shall inform Architect of defects or non-compliance found during routine inspections. Site
Supervisor shall follow up on remedial action recommended by the Architect to ensure rectification works are carried out
by the Contractor.

2012 Housing & Development Board

32

Example: Inspection Checklist for Floor Tiling Works

PROJECT TITLE:
PROJECT NO.:
BLOCK NO.:
UNIT NO. / COMMON AREA (*Delete where necessary):
LOCATION:
Verification
(100% checks on all floors)

ITEM

Complied
1. Waterproofing
Membrane
Preparation

a) Surface flat / adequate fall to outlets

Yes / No

b) Wall rendered

Yes / No

c) 45o mortar fillet

Yes / No

d) Damp

Yes / No

e) Cleanliness

Yes / No

2. Waterproofing
a) Used approved material
Membrane Application b) Used of mechanical mixer (if 2 part component)

3. Protection Screed

4. Water Test (24hr)


5. Laying Of Floor Tiles

Yes / No
Yes / No

d) Kitchen/balcony outlets - 400mm radius from centre

Yes / No

e) Adequate curing between 1st & 2nd coat application

Yes / No

f) Thickness ________

Yes / No

g) Protection

Yes / No

a) Membrane sufficiently cured

Yes / No

b) Used approved pre-packed screed

Yes / No

c) Used mechanical mixer & water measuring gauge mixer

Yes / No

d) Gradient provided on screed

Yes / No

e) Minimum thickness = 10mm

Yes / No

a) Min. water depth = 10mm

Yes / No

b) No leakage to underside of slab

Yes / No

a) Grid lines provided on screed

Yes / No

b) Screed cured 3 days

Yes / No

c) Bedding on substrate < 1 sq metre

Yes / No

d) Used *tile adhesive / polymer additive

Yes / No

e) Applied bedding mortar (mix 2 OPC : 1 fine sand) 4mm max on substrate &
2mm max on back of tile

Yes / No

f) Used tile spacers

Yes / No

g) Height of kitchen floor tile above living room floor level = 45mm

Yes / No

h) Clearance of blast door from RC floor level = 70mm (min)

Yes / No

i)

Yes / No

6. Grouting To Tile Joints a) Done within 7 days of tile fixing

7. Workmanship

Yes / No

c) Applied upturn (50mm onto pipes, 100mm onto kerb & walls)

Kerb height from tiles floor = 75mm max

Remarks

Yes / No

b) Used approved material

Yes / No

c) Used of mechanical mixer

Yes / No

d) Used proper tooling

Yes / No

a) Flatness of surface/proper fall & no stagnation

Yes / No

b) No tonal variation

Yes / No

c) No cracks & chip

Yes / No

d) Good & neat alignment of joints

Yes / No

Note: Site Supervisor shall inform Architect of defects or non-compliance found during routine inspections. Site Supervisor shall follow up on
remedial action recommended by the Architect to ensure rectification works are carried out by the Contractor.

2012 Housing & Development Board

33

Example: Inspection Checklist for Timber Flooring Works


PROJECT TITLE:
PROJECT NO.:
BLOCK NO.:
UNIT NO.:
LOCATION:
ITEM

OBSERVATION

1. Records and
a) Date of last check by SS
Documentation by b) No. of non- compliance detected by SS for the past working days
Consultant
c) No. of non-compliance detected by SS to-date
d) Accumulative checks to date
e) Approval of method statement by Consultant
f) Approval of work demonstration by Consultant
2. Laying of Floor
Screed

a) Alignment of RC elements and walls


b) Surface preparation
c) Control screed level, evenness and thickness ,within 3mm in 2 m

3. Laying of Timber
Strips

a) Screed cured for min. 14 days, no hollowness and even, within 3mm in 2 m
b) Screed moisture content not more than 6-10%
c) Prior to laying strips, adjacent flooring completed no wet trades and windows installed
d) Sorting of strips
- Width : 0.75mm
- Thickness : 0.40mm
remove those with knots and saps
e) Check moisture content of strips not more than 15%
Moisture reading: ________________
f) Application of adhesive
g) Laid in butt joints
h) Minimum 14 days curing before sanding.(floor should not covered)

4. Sanding

a) Correct and proper usage of sand paper


b) Correct rounds of sanding carried out proper sequence and directions
c) Sanding to corners and edges of wall
d) No gaps or unevenness
e) Matching colour putty

5. Varnishing

a) Surface vacuum clean


b) Brush used
c) Coats of varnish
d) Protection to timber flooring after varnishing

6. Timber Skirting

a) Alignment of RC elements and wall


b) Sorting of skirting
c) Apply adhesive fully
d) Joints neat and even
e) Patch up all gaps and nail heads on skirting and floor
f) Coats of varnish

7. Workmanship

a) No surface blemishes and unevenness. Not more than 3mm per 2 m


b) No misalignment and flush with adjacent tiles
c) Joints 0.5mm,No gap between timber strips
d) No gap between wall/ skirting & floor/skirting
e) Varnish neat and even
f) Acceptable tonal difference
g) Exposed end of skirting sanded smooth and varnished
h) No hollowness

8. Material control

a) Material approved by Consultants


b) Condition of storage area acceptable, ventilation, dry condition

2012 Housing & Development Board

34

Example: Inspection Checklist for MS and Timber Door Frame Works


PROJECT TITLE:
PROJECT NO.:
BLOCK NO.:
UNIT NO. / COMMON AREA (*Delete where necessary):
LOCATION:
Verification

ITEM
1.

Records and
Documentation by
Consultant

Complied

a)

Proper supervision records by Consultant Site Supervisor

Yes / No

b)

Testing of material according to specification (e.g. pre-packed waterproofing


screed)

Yes / No

c)

Approval of method statement by Consultant

Yes / No

2.

Material

a)

Approval of work demonstration by Consultant

Yes / No

3.

Storage and
Transportation

a)

Door supplier under HDBs material list

Yes / No

b)

Proper protection with wrapping etc, at delivery

Yes / No

c)

Proper storage of door leaves (not exposed to dampness and not directly on
floor)

Yes / No

d)

Doors brought up to upper floors using lift

Yes / No

a)

Frame installed after completion of blockworks (preferred method)

Yes / No

b)

Frame secured properly & braced

Yes / No

c)

Fixing :- *RC / blockwork / LWP


I) Galvanised steel bracket with masonry drive pins

Yes / No

II)

Yes / No

4.

5.

6.

7.

8.

Installation Of MS
Door Frame (Main
& internal doors in
DU)

Infill To Mild Steel


Door Frame

Workmanship of
Timber Door

Yes / No

IV) MS holdfast w/CED primer

Yes / No

V)

Yes / No

3 nos galvanised holdfast

VI) 3 nos MS holdfast w/CED primer

Yes / No

d)

Correct nos of holdfast / brackets as in drawings

Yes / No

e)

CED primer in good condition

Yes / No

a)

Grouting with approved material

Yes / No

b)

Grout compacted & frame not hollow

Yes / No

c)

Verticality within tolerance 3mm

Yes / No

Proper protection with wrapping etc, at delivery

Yes / No

Proper storage of door leaves

Yes / No

Moisture content (10% & 15% & difference not exceed 3% per unit)

Yes / No

Both leaves aligned when close, offset 3mm

Yes / No

e)

Align with frame when close, no warp, offset 3mm

Yes / No

f)

When close, gap between frame & door consistent, 3 to 5mm

Yes / No

g)

When close, gap between door & finished floor 10mm max

Yes / No

h)

When close, eye viewer at 1.5m ht (ext) & not blocked by MS gate

Yes / No

i)

PSB label intact (for FR door)

Yes / No

a)

4 nos brass hinges with matching screws (102x76x3mm)

Yes / No

b)

Flush bolts

Yes / No

c)

Antique brass finish door viewer

Yes / No

d)

Bronze colour door closer

Yes / No

a)

Surface blemishes

Yes / No

b)

Tonal variation

Yes / No

c)

Lockset / flush bolt functioning

Yes / No

Installation of Solid a)
Timber Main
b)
Entrance
c)
Door (DU)
d)

Ironmongery

MS bracket w/CED primer

III) Galvanised holdfast

Remarks

Note: Site Supervisor shall inform Architect of defects or non-compliance found during routine inspections. Site Supervisor shall follow up
on remedial action recommended by the Architect to ensure rectification works are carried out by the Contractor.

2012 Housing & Development Board

35

Example: Inspection Checklist for Window


PROJECT TITLE:
PROJECT NO.:
BLOCK NO.:
UNIT NO.:
LOCATION:
Verification
ITEM
1. Records and
Documentatio
n by
Consultant

2. Installation of
Outer Frame

3. Fixing of
Fasteners

4. Mortar Infill
between
Frame &
Abutting Wall

5. Sealant
/Mastic
Pointing

6. Functionality

7. Joints

8. Accessories
Defects

Complied

a)

Proper supervision records by Consultant Site Supervisor

Yes / No / NA

b)

Testing of material according to specification (e.g. laminated safety


glass for fixed panel below cill height)

Yes / No / NA

c)

Approval of method statement by Consultant

Yes / No / NA

d)

Approval of work demonstration by Consultant

Yes / No / NA

a)

Control of wall opening < 15mm

Yes / No / NA

b)

Surface preparation

Yes / No / NA

c)

Used approved pre-packed mortar

Yes / No / NA

d)

Levelled mortar base

Yes / No / NA

a)

Correct number of fasteners

Yes / No / NA

b)

Type of fastener used:


I) anchor bolts

Yes / No / NA

II)

Yes / No / NA

galvanized steel brackets

c)

Damage existing wall surface

Yes / No / NA

d)

Alignment of outer frame

Yes / No / NA

a)

Appropriate tool used

Yes / No / NA

b)

Joint free of debris/dust wall/frame

Yes / No / NA

c)

Used backing piece for infill

Yes / No / NA

d)

Used approved pre-packed mortar mechanically mixed

Yes / No / NA

e)

Compaction of infill mortar

Yes / No / NA

f)

Consistent groove joint formed min 6mm

Yes / No / NA

a)

Used approved type of sealant

Yes / No / NA

b)

Sufficient curing of cement mortar

Yes / No / NA

c)

Sealant of sufficient thickness

Yes / No / NA

d)

Neat flush joint with frame

Yes / No / NA

a)

Water seepage through joints between window frame & wall

Yes / No / NA

b)

Difficulty in open/close of casement glass panels

Yes / No / NA

c)

Difficulty in sliding of window panels

Yes / No / NA

a)

Untidy joint between window frame & wall

Yes / No / NA

b)

Poor frame finish

Yes / No / NA

c)

Physical damages/scratches on frame / glazing

Yes / No / NA

d)

Stained glazing

Yes / No / NA

e)

Mortar dropping / paint drip on frame

Yes / No / NA

a)

Loose or improperly installed gaskets

Yes / No / NA

b)

Missing screws / safety device

Yes / No / NA

c)

Defective handle / locking device

Yes / No / NA

d)

Damaged window stays

Yes / No / NA

Remarks

2012 Housing & Development Board

36

Example: Inspection Checklist for Brick and Block Works

PROJECT TITLE:
PROJECT NO.:
BLOCK NO.:
UNIT NO. / COMMON AREA (*Delete where necessary):
LOCATION:

ITEM
1. Surface &Brick
Preparation

a)

Patched tie bolt & wall plug holes in RC


members

Yes / No / NA

b)

Bricks & receiving surface clean

Yes / No / NA

c)

Wetted bricks before laying

Yes / No / NA

Applied polyurethane sealant (min 13mm) with


backer rod

Yes / No / NA

b)

Formed 15mm groove

Yes / No / NA

c)

Provided expansion joint (for wall > 4.5m


length)

Yes / No / NA

a)

Used approved pre-packed mortar mix

Yes / No / NA

b)

Used mechanical mixer

Yes / No / NA

c)

Used water measuring gauge

Yes / No / NA

d)

Use of Exmet started from 2nd course & laid


at every 3rd course, min lap length of 100mm

Yes / No / NA

e)

Sufficient mortar at joints, no void

Yes / No / NA

f)

Joint width 10 2mm

Yes / No / NA

a)

Surface & edges plane & vertical (Plumb <


10mm per storey height)

Yes / No / NA

b)

No crack & chip

Yes / No / NA

2. Brick wall flush with a)


RC member

3. Laying of Brick

4. Workmanship

Verification
Complied

Remarks

Note: Site Supervisor shall inform Architect of defects or non-compliance found during routine inspections. Site Supervisor
shall follow up on remedial action recommended by the Architect to ensure rectification works are carried out by the
Contractor.

2012 Housing & Development Board

37

Example: Inspection Checklist for Sanitary and Plumbing Installation

PROJECT TITLE:
PROJECT NO.:
BLOCK NO.:
UNIT NO. / COMMON AREA (*Delete where necessary):
LOCATION:
Verification

ITEM
1. Records and
Documentation
by Consultant

Complied

a)

Proper supervision records by Consultant Site Supervisor

Yes / No / NA

b)

Testing of material according to specification

Yes / No / NA

c)

Approval of mock up by Consultant

Yes / No / NA

d)

Approval of method statement by Consultant

Yes / No / NA

e)

Approval of work demonstration by Consultant

Yes / No / NA

a)

Use of correct type of pipes, fittings and accessories under


HDBs materials list

Yes / No / NA

b)

Solvent cement in compliance with BS 4346:Part 3

Yes / No / NA

a)

UPVC grating having 30mm collar protrusion

Yes / No / NA

b)

Gratings for floor trap fixed at 5mm below graded floor level

Yes / No / NA

c)

Provision of cast in floor trap

Yes / No / NA

d)

No debris in floor trap

Yes / No / NA

e)

Floor trap not damaged / not misalignment

Yes / No / NA

f)

Mosquitoes device not missing

Yes / No / NA

a)

Surface of UPVC pipes roughened at openings

Yes / No / NA

b)

Provision of trimming bar at openings

Yes / No / NA

c)

Alignment of sanitary pipes after connection

Yes / No / NA

d)

Proper formworks and propping provided

Yes / No / NA

e)

Approved grout used for casting (G40)

Yes / No / NA

a)

Provision of horizontal support at max. 1.4m span

Yes / No / NA

b)

Provision of vertical support at max. 1.8m span

Yes / No / NA

6. Leakage Test for a)


Concealed Stack
Pipes

A minimum depth of 10mm water flooding test for 2 hours within


1 week after connection of stack pipes for every storey

Yes / No / NA

7. Concealed
Copper Pipes

a)

Correct pipes routing

Yes / No / NA

b)

Correct pipe sizes used

Yes / No / NA

c)

Adequate provision of pipe supports

Yes / No / NA

a)

Pump in water into copper pipe at 24 bar and maintain for 15


mins

Yes / No / NA

b)

No water leakage at the joints and bends

Yes / No / NA

c)

Copper pipes concealed with non shrink grout after test

Yes / No / NA

2. Material

3. Floor Trap

4. Casting of
Sanitary
Openings

5. Supports For
Sanitary Pipes

8. Leakage Test for


Concealed
Copper Pipes

Remarks

Note: Site Supervisor shall inform Architect of defects or non-compliance found during routine inspections. Site Supervisor
shall follow up on remedial action recommended by the Architect to ensure rectification works are carried out by the
Contractor.

2012 Housing & Development Board

38

Example: Inspection Record for In-Process Supervision for Waterproofing Membrane


WATERPROOFING MEMBRANE
PROJECT NO.:

Name & Signature of RTO:

BLOCK NO.:
Unit No.
450

451

452

453

454

455

Storey No.

Remarks
(Architect / Project Manager
to endorsed for units
checked)

20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1

RTO to record findings as follow:


Example

Reference

LD

A,B

Location

10/8/05
(15/08/05)

Date Checked
(Date Rectified)

Critical Items Reference:


A - Surface flat / adequate fall to outlets
B - Wall rendered, 45 degree mortar fillet
Item
C - Mechanical mixer (if 2 part component)
Checked D - Applied upturn (50mm onto pipes, 100mm onto kerb & walls)
E - Kitchen / balcony outlets 400mm radius from centre
/
F - Thickness per coat / adequate curing between 1 st & 2nd coat application / protection

- Complied
- Non-compliance

Frequency:
All units

Location Reference:
LD
MB
BR1
BR2
K
MT
CT
HS
SY
OT

-Living / Dining room


-Master bedroom
-Bedroom 1
-Bedroom 2
-Kitchen
-MB toilet
-Common toilet
-Household shelter
-Service Yard
-Others

2012 Housing & Development Board

39

Example: Inspection Record for In-Process Supervision for Concealed Water


Pipe/ Pressure Test
QUALITY INSPECTION RECORD FOR IN-PROCESS SUPERVISION

CONCEALED WATER PIPE INSTALLATION / PRESSURE TEST


Name & Signature of RTO:

PROJECT NO.:
BLOCK NO.:

Unit No.
450

Storey No.

451

452

453

454

455

Remarks
(Architect / Project Manager to
endorsed for units checked)

20

19

18

17

16

15

14

13

12

11

10

RTO to record findings as follow:


Example

Reference

LD

A,B

Location

Item Checked

10/8/05
(15/08/05)

Date Checked
(Date Rectified)

- Complied
- Non-compliance

Critical Items Reference:


A - Copper pipe Type Y with 22mm (28mm top most 2 storey) and 1.2mm wall thickness, 15mm dia and
1.0mm wall thickness at tap fitting
B - Copper brackets not more than 1m c/c
C - Compression fitting capping 50mm wall
D - Pipes seal with approved non-shrink mortar
E - Hydrostatic test conducted : 7 bars for 24 hours before sealing up
F - Check for position of conceal piping
Frequency:
All units

Location Reference:
LD
MB
BR1
BR2
K
MT
CT
HS
SY
OT

-Living / Dining room


-Master bedroom
-Bedroom 1
-Bedroom 2
-Kitchen
-MB toilet
-Common toilet
-Household shelter
-Service Yard
-Others

2012 Housing & Development Board

40

Example: Inspection Record for Water Test

2012 Housing & Development Board

41

Acknowledgements
The Supervision Guides Editorial Team would like to express its thanks and
appreciation to Mr Tan Eng Seng, Ms Tan Hwee Yong, Ms Tiew Siew Sien, Mr
Andrew Ting Lai Ong, Mr Sam Leong Kwong Yew, Mr Goh Meow Wee and all
others who have in one way or another contributed towards the success of
this Guidebook.

The Editorial Team


Mr Neo Poh Kok
Ms Magdalene Tan Ee Yin
Mr Lim Kee Thiam
Ms Fauziah Bte Jaafar
Ms Kelly Foo Siew Lin

Together, we provide excellent project management to deliver


quality homes in a sustainable environment.