2012 Edition
Foreword
Housing & Development Board (HDB) takes pride in housing more than 80% of the
population in Singapore. Delivering well-designed HDB flats of high quality has always
been our top priority.
HDB started to outsource the consultancy services for the design and supervision of
construction of HDB flats since 2003. We now have more than 100 consultants
participating in HDB projects. To ensure consistency in supervision practice and
standard, HDB has embarked on this project to produce a set of Supervision
Guide. They aim to serve as reference to the consultants in developing a
comprehensive Quality Assurance System for managing our projects.
There are altogether five Guides covering the supervision of architectural, structural
engineering, civil engineering, mechanical engineering and electrical engineering
works. These guides set out our expectations, share HDBs requirements and illustrate
good practices.
These Guides are now available at HDB BGBiz Portal (http://bgbiz.hdb.gov.sg/) for
your easy reference. We hope you will find them useful and informative. We will be
reviewing the guides regularly and we welcome your valuable feedback to further
improve the guides. Lets work together in the pursuit of quality excellence in our
projects.
Thomas Seow
Group Director
Building Quality Group
Housing & Development Board
Contents
1
Introduction
Pg 1
Materials
Pg 2
Pg 7
Pg 10
Timber Mock Up
Pg 14
Sample Units
Pg 17
Pg 25
Pg 27
CONQUAS
Pg 28
Pg 30
10
Introduction
This guide book is to share with the Consultants on HDBs specific requirements,
quality management system, and some good practices in the supervision of
architectural works in HDB projects.
As part of the consultancy services, Consultants are required to submit their Quality
Assurance System to HDB before commencement of the building project. The
system shall cover the following:
a)
b)
Duty and responsibility of the consultant and his team in inspecting the
works at different stages of construction
c)
Quality control system (e.g. checklist, inspection and testing records) and
guidelines put in place for in-process supervision works
Consultants can use this guide book to develop the quality management system
and checklists/forms for supervising architectural works in HDB new development
projects.
Material Selection
All test samples are to be randomly selected from the materials on site and sent to
an accredited laboratory for testing. The samples are to be marked for
identification before sending to the laboratory.
For testing of completed works, the Consultants are required to carry out these
tests in tandem with the progress of works. This is to ensure consistency in quality
of the various batches of supplies and the workmanship achieved.
a) Average Compressive
Strength
b) Shrinkage
a) Shrinkage
b) Water absorption
c) Compressive strength
d) Tensile strength
e) Flexural strength
f) Abrasion Resistance
Pre-packed Floor
screed
Pre-packed skimmed
coat (Internal)
Tile grout
a) Average Compressive
Strength
b) Water penetration
c) Shrinkage
Pre-packed
waterproofing screed
)
)
) 1 test per type
)
)
)
1 test
1 test
b) 1 test
b) Compression test
a) 1 test
a)Tensile test
Type OF Test To Be
Carried Out
Type Of Material To Be
Tested
S/N
)
)
) 1 sample per test
)
)
)
1 sample
1 sample
b) 3 samples
a) 3 samples
30-Jul-10
2-Dec-10
2-Dec-09
2-Dec-09
25-Jul-09
Schedule Date
4-Jan-11
26-Nov-09
26-Nov-09
26-Nov-09
4-Aug-09
8-Feb-11
30-Dec-09
31-Dec-09
31-Dec-09
6-Aug-09
Passed
Passed
Passed
Passed
Passed
Result
Trades
Metal Gate
e.g. wrapped with plastic
sheets and cardboard sheets
Timber Door
e.g. wrapped with plastic
sheets, cardboard sheets,
bubble foam or other suitable
materials of adequate
thickness to cushion the door
surface against impact
Window Frame
e.g. wrapped with translucent
self-adhesive tape (nostaining), stout paper,
cardboard or suitable
protective material which could
cushion the surface against
impact
Protection
Trades
Floor Tiles
e.g. covered with thick
polyethylene sheet or other
suitable protective material
which could cushion the
surface against impact
Timber Floor
e.g. covered with thick
polyethylene sheet or other
suitable protective material
which could cushion the
surface against impact
Cementitious pre-packed
materials
e.g stored, stacked and
protected against weather
on site
Protection
The Consultants shall ensure that these items are designed to be easily
constructible, robust, maintainable and durable.
Endorsements
by QP & PE
Work
Method
Trade
Demonstration
Sample Unit
Mass Production
10
The work method of the trade has to be approved by the Consultant before
the trade demonstration.
b)
c)
The briefing session is for the understanding and agreement of the work
method amongst all parties concerned.
d)
Any refinement and amendment made to the approved work method during
the trade demonstration are to be recorded in the original method
statements and endorsed by the Consultant.
e)
f)
g)
11
12
7.
8.
9.
13
Timber Mock Up
14
b)
c)
d)
sufficient clearance for access to the air-con ledge for installation and
maintenance of the air-con compressors;
e)
toilet vent and other fittings do not obstruct future installation of shower
screen;
f)
g)
h)
i)
15
Bathroom
Bathroom
Bathroom
Kitchen
Kitchen
2012 Housing & Development Board
16
6 Sample Units
(b)
(c)
(d)
The workmanship standards set in the approved sample units will be used as a
common reference standard when Contractor proceeds with mass production.
Hence, the workmanship set in sample units must comply with Quality Standards
stated in the specifications.
Sample Unit
17
a)
b)
c)
d)
e)
18
a)
19
20
21
22
e) QP Declaration Form
23
Sample unit
recess
Sales brochure
Guide drawing
Sample unit
Building
specifications
Sample unit
24
After the approval of sample units and the commencement of mass production, the
Consultant shall carry out in-process checking during the entire construction stage.
More regular checks shall be carried out when works just commenced or a new
group of workers joins the workforce. This is to ensure that non-compliances are
detected early and minimise the need for rectification works.
The Consultant is required to set the guidelines and develop checklists to guide
the supervisory staff in the supervision of in-process work. The guidelines shall
include the frequency of checks for various trades. For critical trades such as
application of waterproofing membrane, 100% check would be required before the
works are covered up.
25
Investigate
cause
Take
corrective
action
Put control
measures in
place
Example of Non-Conformance
Corrective Action
26
The Consultant shall provide the following information and drawings to the Branch
Office :
Contract particulars
Particulars of the Consultants
Particulars of contractors essential personnel during DLP
Approved method statements on repair of common defects
Estate layout plan
Service road/driveway plan
MSCP plan for all decks
Electrical layout plan of street lighting
List of suppliers for main fixtures/installations
Concealed wiring and piping plans
Brochure for various fixtures and fittings
As-Built drawings (Elevation & Plan View of Block)
27
CONQUAS
a)
b)
c)
Design to CONQUAS e.g. avoid detailing that demand highly on the skills of
workers on site
d)
e)
f)
Check that the Contractor conducts their own Materials and Functional Test
indicated in the CONQUAS Manual before arranging for BCA assessment.
28
Window frame
is flushed with
wall tile.
Window frame is
set in resulting
in many cut tiles.
2) Corners at beam/wall
Too many
edges at
beam/wall.
29
10 ANNEX
Example: Inspection Checklist for Internal Waterproofing Works
PROJECT TITLE:
PROJECT NO.:
BLOCK NO.:
UNIT NO. / COMMON AREA (*delete where necessary):
Verification
Complied
1. Records and
a) Proper supervision records by Consultant Site Supervisor
Documentation by b) Testing of material according to specification (e.g. pre-packed
Consultant
waterproofing screed)
2. Material
3. Substrate
Preparation
4. Waterproofing
Membrane
Application
6. Water Test
Yes/No/NA
Yes/No/NA
Yes/No/NA
Yes/No/NA
Yes/No/NA
Yes/No/NA
b) Pipe / floor openings fitted with temporary caps so that debris cannot
enter and cause chokage
Yes/No/NA
Yes/No/NA
Yes/No/NA
Yes/No/NA
Yes/No/NA
a) Application of 1st coat with a roller or brush (allow first coat to dry to
touch)
Yes/No/NA
Yes/No/NA
Yes/No/NA
Yes/No/NA
Yes/No/NA
Yes/No/NA
Yes/No/NA
Yes/No/NA
Yes/No/NA
Yes/No/NA
5. Curing &
a) Adequate curing between 1st & 2nd coat application
Protective Screed b) Application of approved pre-packed waterproof screed to protect the
waterproof membrane
Remarks
Yes/No/NA
Yes/No/NA
Yes/No/NA
Yes/No/NA
Yes/No/NA
Yes/No/NA
Yes/No/NA
Yes/No/NA
Yes/No/NA
30
PROJECT TITLE:
PROJECT NO.:
BLOCK NO.:
UNIT NO.:
LOCATION:
Verification
ITEM
Complied
Yes/No/NA
Yes/No/NA
Yes/No/NA
Yes/No/NA
2. Material
Yes/No/NA
3. Alignment
Control
Yes/No/NA
Yes/No/NA
4. Surface
Preparation
Yes/No/NA
Yes/No/NA
Yes/No/NA
Yes/No/NA
Yes/No/NA
Yes/No/NA
Yes/No/NA
Yes/No/NA
Yes/No/NA
Yes/No/NA
a) Surface even
Yes/No/NA
Yes/No/NA
1. Records and
Documentation
by Consultant
5. *Plastering /
Skimming
6. Alignment &
Workmanship
Remarks
31
PROJECT TITLE:
PROJECT NO.:
BLOCK NO.:
UNIT NO. / COMMON AREA (* Delete where necessary):
LOCATION:
Verification
ITEM
1. Preparation
2. Laying of Mortar
Rendering
Yes / No
Yes / No
Yes / No
d) Background dampened
Yes / No
Yes / No
Yes / No
Yes / No
Yes / No
e) Lighting provided
Yes / No
f)
3. Laying of Wall
Tiles
4. Workmanship
Complied
Yes / No
Yes / No
Yes / No
Yes / No
Yes / No
Yes / No
f)
Yes / No
Remarks
Yes / No
h) Lighting provided
Yes / No
i)
Yes / No
Yes / No
Yes / No
c) No tonal variation
Yes / No
Yes / No
Note: Site Supervisor shall inform Architect of defects or non-compliance found during routine inspections. Site
Supervisor shall follow up on remedial action recommended by the Architect to ensure rectification works are carried out
by the Contractor.
32
PROJECT TITLE:
PROJECT NO.:
BLOCK NO.:
UNIT NO. / COMMON AREA (*Delete where necessary):
LOCATION:
Verification
(100% checks on all floors)
ITEM
Complied
1. Waterproofing
Membrane
Preparation
Yes / No
b) Wall rendered
Yes / No
Yes / No
d) Damp
Yes / No
e) Cleanliness
Yes / No
2. Waterproofing
a) Used approved material
Membrane Application b) Used of mechanical mixer (if 2 part component)
3. Protection Screed
Yes / No
Yes / No
Yes / No
Yes / No
f) Thickness ________
Yes / No
g) Protection
Yes / No
Yes / No
Yes / No
Yes / No
Yes / No
Yes / No
Yes / No
Yes / No
Yes / No
Yes / No
Yes / No
Yes / No
e) Applied bedding mortar (mix 2 OPC : 1 fine sand) 4mm max on substrate &
2mm max on back of tile
Yes / No
Yes / No
g) Height of kitchen floor tile above living room floor level = 45mm
Yes / No
Yes / No
i)
Yes / No
7. Workmanship
Yes / No
c) Applied upturn (50mm onto pipes, 100mm onto kerb & walls)
Remarks
Yes / No
Yes / No
Yes / No
Yes / No
Yes / No
b) No tonal variation
Yes / No
Yes / No
Yes / No
Note: Site Supervisor shall inform Architect of defects or non-compliance found during routine inspections. Site Supervisor shall follow up on
remedial action recommended by the Architect to ensure rectification works are carried out by the Contractor.
33
OBSERVATION
1. Records and
a) Date of last check by SS
Documentation by b) No. of non- compliance detected by SS for the past working days
Consultant
c) No. of non-compliance detected by SS to-date
d) Accumulative checks to date
e) Approval of method statement by Consultant
f) Approval of work demonstration by Consultant
2. Laying of Floor
Screed
3. Laying of Timber
Strips
a) Screed cured for min. 14 days, no hollowness and even, within 3mm in 2 m
b) Screed moisture content not more than 6-10%
c) Prior to laying strips, adjacent flooring completed no wet trades and windows installed
d) Sorting of strips
- Width : 0.75mm
- Thickness : 0.40mm
remove those with knots and saps
e) Check moisture content of strips not more than 15%
Moisture reading: ________________
f) Application of adhesive
g) Laid in butt joints
h) Minimum 14 days curing before sanding.(floor should not covered)
4. Sanding
5. Varnishing
6. Timber Skirting
7. Workmanship
8. Material control
34
ITEM
1.
Records and
Documentation by
Consultant
Complied
a)
Yes / No
b)
Yes / No
c)
Yes / No
2.
Material
a)
Yes / No
3.
Storage and
Transportation
a)
Yes / No
b)
Yes / No
c)
Proper storage of door leaves (not exposed to dampness and not directly on
floor)
Yes / No
d)
Yes / No
a)
Yes / No
b)
Yes / No
c)
Yes / No
II)
Yes / No
4.
5.
6.
7.
8.
Installation Of MS
Door Frame (Main
& internal doors in
DU)
Workmanship of
Timber Door
Yes / No
Yes / No
V)
Yes / No
Yes / No
d)
Yes / No
e)
Yes / No
a)
Yes / No
b)
Yes / No
c)
Yes / No
Yes / No
Yes / No
Moisture content (10% & 15% & difference not exceed 3% per unit)
Yes / No
Yes / No
e)
Yes / No
f)
Yes / No
g)
When close, gap between door & finished floor 10mm max
Yes / No
h)
When close, eye viewer at 1.5m ht (ext) & not blocked by MS gate
Yes / No
i)
Yes / No
a)
Yes / No
b)
Flush bolts
Yes / No
c)
Yes / No
d)
Yes / No
a)
Surface blemishes
Yes / No
b)
Tonal variation
Yes / No
c)
Yes / No
Installation of Solid a)
Timber Main
b)
Entrance
c)
Door (DU)
d)
Ironmongery
Remarks
Note: Site Supervisor shall inform Architect of defects or non-compliance found during routine inspections. Site Supervisor shall follow up
on remedial action recommended by the Architect to ensure rectification works are carried out by the Contractor.
35
2. Installation of
Outer Frame
3. Fixing of
Fasteners
4. Mortar Infill
between
Frame &
Abutting Wall
5. Sealant
/Mastic
Pointing
6. Functionality
7. Joints
8. Accessories
Defects
Complied
a)
Yes / No / NA
b)
Yes / No / NA
c)
Yes / No / NA
d)
Yes / No / NA
a)
Yes / No / NA
b)
Surface preparation
Yes / No / NA
c)
Yes / No / NA
d)
Yes / No / NA
a)
Yes / No / NA
b)
Yes / No / NA
II)
Yes / No / NA
c)
Yes / No / NA
d)
Yes / No / NA
a)
Yes / No / NA
b)
Yes / No / NA
c)
Yes / No / NA
d)
Yes / No / NA
e)
Yes / No / NA
f)
Yes / No / NA
a)
Yes / No / NA
b)
Yes / No / NA
c)
Yes / No / NA
d)
Yes / No / NA
a)
Yes / No / NA
b)
Yes / No / NA
c)
Yes / No / NA
a)
Yes / No / NA
b)
Yes / No / NA
c)
Yes / No / NA
d)
Stained glazing
Yes / No / NA
e)
Yes / No / NA
a)
Yes / No / NA
b)
Yes / No / NA
c)
Yes / No / NA
d)
Yes / No / NA
Remarks
36
PROJECT TITLE:
PROJECT NO.:
BLOCK NO.:
UNIT NO. / COMMON AREA (*Delete where necessary):
LOCATION:
ITEM
1. Surface &Brick
Preparation
a)
Yes / No / NA
b)
Yes / No / NA
c)
Yes / No / NA
Yes / No / NA
b)
Yes / No / NA
c)
Yes / No / NA
a)
Yes / No / NA
b)
Yes / No / NA
c)
Yes / No / NA
d)
Yes / No / NA
e)
Yes / No / NA
f)
Yes / No / NA
a)
Yes / No / NA
b)
Yes / No / NA
3. Laying of Brick
4. Workmanship
Verification
Complied
Remarks
Note: Site Supervisor shall inform Architect of defects or non-compliance found during routine inspections. Site Supervisor
shall follow up on remedial action recommended by the Architect to ensure rectification works are carried out by the
Contractor.
37
PROJECT TITLE:
PROJECT NO.:
BLOCK NO.:
UNIT NO. / COMMON AREA (*Delete where necessary):
LOCATION:
Verification
ITEM
1. Records and
Documentation
by Consultant
Complied
a)
Yes / No / NA
b)
Yes / No / NA
c)
Yes / No / NA
d)
Yes / No / NA
e)
Yes / No / NA
a)
Yes / No / NA
b)
Yes / No / NA
a)
Yes / No / NA
b)
Gratings for floor trap fixed at 5mm below graded floor level
Yes / No / NA
c)
Yes / No / NA
d)
Yes / No / NA
e)
Yes / No / NA
f)
Yes / No / NA
a)
Yes / No / NA
b)
Yes / No / NA
c)
Yes / No / NA
d)
Yes / No / NA
e)
Yes / No / NA
a)
Yes / No / NA
b)
Yes / No / NA
Yes / No / NA
7. Concealed
Copper Pipes
a)
Yes / No / NA
b)
Yes / No / NA
c)
Yes / No / NA
a)
Yes / No / NA
b)
Yes / No / NA
c)
Yes / No / NA
2. Material
3. Floor Trap
4. Casting of
Sanitary
Openings
5. Supports For
Sanitary Pipes
Remarks
Note: Site Supervisor shall inform Architect of defects or non-compliance found during routine inspections. Site Supervisor
shall follow up on remedial action recommended by the Architect to ensure rectification works are carried out by the
Contractor.
38
BLOCK NO.:
Unit No.
450
451
452
453
454
455
Storey No.
Remarks
(Architect / Project Manager
to endorsed for units
checked)
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
Reference
LD
A,B
Location
10/8/05
(15/08/05)
Date Checked
(Date Rectified)
- Complied
- Non-compliance
Frequency:
All units
Location Reference:
LD
MB
BR1
BR2
K
MT
CT
HS
SY
OT
39
PROJECT NO.:
BLOCK NO.:
Unit No.
450
Storey No.
451
452
453
454
455
Remarks
(Architect / Project Manager to
endorsed for units checked)
20
19
18
17
16
15
14
13
12
11
10
Reference
LD
A,B
Location
Item Checked
10/8/05
(15/08/05)
Date Checked
(Date Rectified)
- Complied
- Non-compliance
Location Reference:
LD
MB
BR1
BR2
K
MT
CT
HS
SY
OT
40
41
Acknowledgements
The Supervision Guides Editorial Team would like to express its thanks and
appreciation to Mr Tan Eng Seng, Ms Tan Hwee Yong, Ms Tiew Siew Sien, Mr
Andrew Ting Lai Ong, Mr Sam Leong Kwong Yew, Mr Goh Meow Wee and all
others who have in one way or another contributed towards the success of
this Guidebook.
2012 Edition