Good Industry Practices Guide Book
Good Industry Practices Guide Book
Good Industry Practices Guide Book
The Building and Construction Authoritys (BCA) Construction Quality Assessment System
(CONQUAS) has been widely adopted as the de facto national yardstick for measuring the quality
of building projects. Besides setting standards and measuring the level of workmanship through
CONQUAS, BCA is developing a series of publications of Good Industry Practices Guide for different
trades.
This Good Industry Practices Design and Material Selection for Quality Volume 1 shares with
the industry some of the good practices adopted by developers, practitioners and contractors who
consistently deliver high quality work through thoughtful design and choice of materials in construction,
particularly in residential buildings. These practices are taken from projects that achieved high
CONQUAS/Quality Mark scores. The examples in this guide highlight some of these noteworthy
projects. While the other guides in the series focus on doing things right, this guide focuses on
doing the right thing through careful design choices and materials selection.
This guide is not meant to be a denitive textbook on building design and material selection to achieve
high quality. Neither is it the nal word on quality, as there will be new materials and methods. To
obtain more comprehensive information and guidance, readers should seek advice from professional
designers and material suppliers. We gratefully acknowledge the contributions of these practitioners
and trust that the industry will nd this publication useful in its pursuit of quality excellence. We
welcome any contributions from readers that may add to or improve future editions of this guide.
We would like to thank the following rms for their support, contributions and sharing of knowledge
in making this possible:
We would also like to thank the following organizations and individuals for their valuable feedback in
the review of this guide:
CONTENTS
Introduction 5
INTRODUCTION
Since 1999, the Building and Construction Authority (BCA) have produced a series of 9 Good Industry
Practices Guides. These guides detail work processes and methods of installation for various nishing
trades e.g. ceramic tiling, timber ooring, waterproong works, etc. If the guidelines are followed
closely, one can expect the resultant end product to be a high quality building of workmanship
excellence. These guides have been used as reference standards in quality assessments under
BCAs CONQUAS or Quality Mark (QM) schemes.
While it is possible to achieve high quality standards by following closely these guides, sometimes
the proper design, detailing or choice of material can often reduce the time and effort required during
construction to achieve the same or better end result. Some conventional methods, materials or
designs may require the employment of more skilled workers to work in difcult circumstances and
therefore take a longer time to complete the works. Such skilled workers are invariably in short supply
and as projects usually have to be completed within very tight schedules, workmanship quality is
often sacriced.
Good design is an integral and essential part of construction. Good design facilitates construction work
to be carried out optimally within time and cost constraints. It addresses the following aspects:
Safety
Meeting endusers needs
Functionality
Build Quality
Buildability
Sustainability
Aesthetics
To strike a balance in all the aspects and achieve good quality in the nal product, plans and
specications should be carefully designed, reviewed at each stage and corrected before construction
starts. Overlooking any of these may result in additional time and cost to rectify the works.
This guide attempts to distill many good design practices and material choices observed in various
CONQUAS and QM projects that have achieved workmanship quality excellence as reected in
their high CONQUAS/ QM scores. Industry professionals can learn and apply these practices in
their projects for better quality achievement. As each buildings design objective may be different
from another, it may be necessary to be selective or customize the mentioned practices to meet the
specic needs of the project. This guide has made comparisons with some designs choices that may
be difcult to build or has inherent difculties in achieving quality. This does not mean such designs
cannot be employed. It only means that more time, attention and higher cost may be incurred to
achieve the same quality result.
This guide is the rst of 2 volumes and focuses on good design choices for workmanship excellence.
The subsequent volume will cover other design choices and material selection that impacts quality.
1.0
AN OVERVIEW OF
BUILDABLE DESIGN AND QUALITY
8
Buildabilty is the extent to which the design of a building facilitates ease of construction.
Buildable design often has a direct implication on quality achievement in a project. Projects with
better quality performance (as measured by CONQUAS- Construction Quality Assessment System)
invariably are also those that had adopted good buildable designs. Examples of such projects,
which can be found in I-QUAS (Information on Construction Quality-ref: www.bca.gov.sg) include
commercial, residential, institutional and mixed developments like The Esparis, Monterey Park,
Savannah Park, The Pier, Icon, One Marina and ITE Simei.
The developer, designer and builder each has a signicant role towards achieving better buildable
design and quality in construction. This chapter illustrates examples of good buildable designs and
its contribution to quality.
Fig. 1.1 - Examples of projects with good buildable designs and high quality performance scores.
9
The following are examples from residential projects that adopted good design concepts such as
at plate slab, curtain wall, drywall partitions, prefabricated bathrooms, screed-less oor, etc. All
these buildable systems facilitate ease of construction leading to good quality workmanship.
Drywall
Curtain wall
The fabrication of curtain wall components are carried out in the factory and this reduces site work and
allows greater control over component quality. The site operations require only installation works. The
process of installation is much faster compared to wet trade methods. Since the method of assembly
is a dry process, the required tolerances and workmanship can be controlled closely. When selecting
curtain wall system, considerations should be given to sustainability and environmental factors such
as using Low-E glass panels.
Fig. 1.7- Curtain wall systems: Saves time, better quality facade
Curtain walls
No scaffolding
No wet trades
Less workmanship issues
12
The precast shear wall system eliminates inll work like brick or block work and wet trades like
plastering. External walls have better water tightness against the elements. Proper design and
execution of precast system will give good quality nish surfaces that require minimum preparatory
work before painting. Gondolas, instead of scaffolding, can be used to carry out the nishing work;
this saves costs and expedites the construction process. Other features and advantages of using
precast elements are highlighted in Chapter 4.2.
Fig. 1.9 - External shear walls: Better Fig. 1.10 - No scaffolding and plastering required
water - tightness to get nal nish.
13
Good buildable design requires careful consideration and planning. It should lead to designs that
improve construction processes, ease of construction, reduced dependency on on-site manpower
and improved quality. Although the initial cost of construction of buildable designs may be higher
than conventional methods in some cases, consideration should be given to its benets of higher
productivity, faster completion time and better build quality.
2.0
INFLUENCE OF LAYOUTS/SHAPES ON
QUALITY AND CONSTRUCTABILITY
16
Straightforward and uncomplicated design layouts and shapes facilitate ease of construction and
maintenance, enhance productivity and lead to better quality workmanship. There is reduced need
for closer co-ordination between trades and hence less dependency to achieve the desired build
quality. This becomes more signicant where mass production is involved. This chapter shows some
examples of layouts, shapes and details and their inuence on quality and constructability.
Layouts with standard room dimensions, less corners and turns facilitate execution of ne architectural
nishing works like skirtings, painting, silicon seals, etc. The ease of working over straight surfaces
results in consistent and better workmanship. The benets are enhanced where there is repetition
of similar design at every oor.
Fig. 2.2 - Less corners and turns: Easier to carry out architectural nishing works.
17
Regular shapes that are used repeatedly generally facilitate prefabricated components like curtain-
walls, full height windows and drywall partitions to be used. Such factory made components have
better dimensional accuracy and assembly tolerances can be better controlled during erection. This
leads to considerable reduction in site manpower and better quality output.
Creative layouts (see Fig. 2.4) generally have more turns and joints. It poses a greater challenge
to complete the architectural works in internal nishes with the desired quality. More thought and
attention need to be paid to interfacing details, where one trade interfaces with another e.g. joining
of marble and timber oor, termination of wet and dry areas, etc. In addition, ne architectural works
like skirting installation, silicone application to gaps and llings, need to be executed carefully within
the constraints of the unique shape or layout. In many cases, using traditional wet trades that involve
intricate manual cutting of materials to suit the shape or layout may make it more difcult to achieve
workmanship quality in addition to slowing the progress of the works.
Fig. 2.5 - More attention/skill needed to get nal Fig. 2.6 - Too many skirting pieces/joints to get the
shape and nish. required prole.
Fig. 2.7 - Small recesses: Difcult to carry out Fig. 2.8 - Protrusions in aluminium capping due to
works like skirting, etc. too many jointing segments.
Fig. 2.9 - Circular columns with masonry nishes Fig.2.10 - Skirting requires many small segments
require more preparation time. to form curve.
19
Fig. 2.11 - Circular column abuts wall: Jointing line Fig.2.12- Marble needs to be cut manually to suit
is a challenge to nish. prole.
The above examples are not meant to discourage professionals from creative designs. The emphasis
here is to highlight the challenges posed by creative shapes and layouts and its impact on quality and
constructability, particularly where a project has a large number of units which needs to be completed
within a limited time frame. In addition, workers with the right training and skills are needed to carry
out the ne architectural nishing works. Apart from employing workers with the appropriate skills,
the builder also needs to carefully organize and sequence the works so as not to impact construction
progress and its quality.
3.0
QUALITY ISSUES IN
CONVENTIONAL METHODS & MATERIALS
22
Conventional designs that comprise beams, columns, brick/block inlls and plastering have inherent
inefciencies during construction. Brick/block wall inlls are labour-intensive and cement-sand
plastering, a wet process, is often messy and requires more preparatory work. There are also
constraints in concealing and routing M&E services. Apart from using more intensive manpower
and longer construction duration, there are some inherent difculties in achieving high quality. Some
examples of the challenges posed by such conventional design and materials are highlighted in this
chapter.
3.1.1 Traditional formwork system: More joints and poor surface nish
Traditional formwork system has more connections and joints and it requires more manpower to erect,
maintain and dismantle. During erection, close monitoring and supervision is needed to achieve the
desired workmanship quality of the nished concrete. If the formwork is not erected properly, the end
product would not be satisfactory. Often this means another layer of thick plaster is required to cover
the uneven concrete surface.
Fig. 3.2 - Traditional formwork system: More Fig. 3.3 - Poor concrete surfaces: Thicker plaster
housekeeping. is required.
Many services in a building e.g. electrical, ACMV and sanitary plumbing, etc are concealed under
slabs or covered by false ceiling. If there are too many internal beams, especially non-shallow
beams, it may be difcult to locate such services under oor slabs. This may restrict the height of
false ceilings or the oor storey height may need to be increased to accommodate such services.
Fig. 3.4 - More columns and beams: Limits M&E Fig. 3.5 - Internal beams restrict height of false
services run. ceiling.
24
The width of RC column may be different from the width of the brickwall laid against it, especially
in internal partitions, e.g. a 200mm wide column and 100mm thick brickwall. In such situations,
an offset of 100mm will appear wherever an RC column adjoins brickwork resulting in a non-ush
surface with many corners and returns. There will be greater difculty in completing the architectural
nishing works like plastering, skirtings, architraves, etc.
Fig. 3.6 - The offset of RC and brickwork creates Fig. 3.7 - More precise work required for turns and
more turns and corners. corners.
For external surface at RC and brick joints, besides laying metal lath, a layer of waterproong
treatment is required to ensure water tightness. Failure to execute these measures properly may
result in defects such as cracks and seepages. All these measures are needed to ensure quality in
construction and will add to construction time and costs.
Fig. 3.12 - External joints require waterproong Fig.3.13 - Potential water seepage if joints are not
treatment. treated properly.
Although adopting conventional methods and materials may lead to lower construction costs in some
cases, the majority of wet trades pose inherent difculties in achieving quality construction compared
to buildable dry construction. In its place, good buildable design systems that facilitate ease of
construction, depend less on-site labour, improve productivity and quality should be considered.
These are considered in the following chapters.
4.0
QUALITY FEATURES IN
STRUCTURAL ELEMENTS
4.1 STEEL STRUCTURES
4.2 PRECAST CONCRETE ELEMENTS
30
The physical properties of steel e.g. its durability, exibility and strength, lend itself to many varied
uses, one of which is in construction. The choice of structural steelwork system as an alternative to
reinforced concrete structures has many advantages. Steel can be easily formed and joined and its
strength to weight ratio is the highest among common building materials. This makes it lightweight and
yet strong as compared to concrete structures. Steel can also be recycled and is a good alternative
building material that contributes to sustainable construction. The following section highlights the
benets of using steel and its contribution to building quality.
Fig. 4.1 - Steels durability, exibility and strength Fig. 4.2 - Steel framed buildings have many
lend itself to use in construction projects. advantages and contribute to sustainable
construction.
31
The use of steel structures permits designers to experiment with many architectural forms and
artistic expressions which are more difcult to build in conventional concrete framed structures.
With steel, more challenging and creative designs can now be considered leading to buildings that
are aesthetically distinctive and of high build quality.
Fig. 4.4 - Complicated structures using steel: A dome shaped auditorium (left) and curved skylight entrance (right).
32
Stringent requirements are imposed to ensure quality in steelwork construction. Though there can
be no meaningful comparison between standards for steel and reinforced concrete construction, the
tolerance requirements in CONQUAS are higher for the former. These result in buildings built to
more exact requirements and hence better build quality.
Detailed requirements on quality assurance for steelwork, especially for welding, bolting and
protection, are based on established international or national standards e.g. the National Productivity
& Quality Specications (NPQS), British National Steelwork Specications, etc. To ensure quality
construction, the stringent requirements are required to be met during fabrication and installation.
Fig. 4.5 - Steel structure ofce building with curtain wall envelope: More space without obstructive internal columns
and beams.
Fig. 4.6 - Quality internal nishing can be achieved in a steel structure building.
33
The images below show typical inspections carried out during fabrication and installation of steel
structures.
Fig. 4.7e - During erection checks. Fig. 4.7f - Post erection checks.
Fig. 4.7 - Stringent process checks during fabrication and installation ensure safety and quality in structural steelwork.
34
Structural steel is lighter than other framing materials. This leads to less heavy foundations which
reduces both the time and cost of construction. Productivity is therefore improved and projects can
be completed faster.
Another example is the use of metal decking for oor construction. Once the steel framings are in
place, installation of metal decking can be completed rapidly. Reinforcement design for such slab
is simple and straightforward, and prefabricated reinforcement can be used. As a result, the works
can be completed earlier and there is better assurance of concrete quality because of the system of
construction.
Fig. 4.8 - Metal decking oor: Faster construction and better concrete quality.
35
Steelwork enhances productivity because of its predominantly dry construction method. External wall
cladding systems (aluminium and glass) are used in conjunction with steelwork and this contributes
to rapid construction progress. The stringent tolerances specied for steel framing and cladding
systems contribute to good quality nishing.
Scaffolding can be avoided as installation of external wall systems can be carried out by tower
cranes and maximizing its use. This scaffold-free method saves on construction costs, makes the
site tidier and reduces housekeeping efforts on site.
Fig 4.9 - Scaffold free construction saves time and costs and is less cluttered.
36
The fabrication of the steelwork is done offsite at factory locations where there is skilled labour and
the environment and systems are well controlled and conducive for quality output. This is an essential
consideration when deciding on the use of steel in design or the choice of steel fabricators.
Flexibility in design and the construction method allow many activities to be carried out concurrently
e.g. erection of trusses, metal deck ooring, curtain wall installation and other nishing work, etc, and
this leads to faster completion of the project.
Fig 4.10g
25th month - Completion of curtain wall and other major architectural works.
While there are many advantages in choosing structural steelwork systems, there are also issues
particular to steelwork that need to be considered. The safe erection of structural steelwork requires
concerted effort by many parties during its fabrication and installation. Instances of poor quality
welds and other shortcomings if not detected and rectied early can compromise structural safety.
This can lead to serious consequences especially in long span structures.
Proper fabrication and installation require specialized knowledge, appropriate equipment and
resources and a comprehensive inspection and testing regime. To enhance safety of the installation,
the steelworks should be carried out by accredited steel fabricators, checked by qualied site
supervisors and tested by Independent Testing Agencies.
Precast concrete technology is widely used in the industry to support buildability and improve
construction productivity. Such technology also results in better quality workmanship as the precast
elements are manufactured under controlled factory conditions before its installation at site. BCA has
many publications that provide information on good practices for precasting e.g. Structural Precast
Concrete Handbook, Buildable Solutions for Landed Residential Development and Buildable
Solutions for High-Rise Residential Development. This section highlights the better workmanship
quality that can be achieved when precast technology is integrated in the design of the building.
Precast concrete elements achieve superior dimensional tolerances and nished concrete surfaces
compared to cast in-situ concrete. This is largely due to the favourable environment in factories where
these elements are produced and the stringent quality control measures taken to meet specied or
national standards during production.
Fig. 4.12 - Precast elements are produced in a Fig. 4.13 - Dimensional tolerances and nished
controlled environment. surfaces are generally superior.
39
Fig. 4.14 - Window frame installed by dry method Fig. 4.15 - Controlled gap with proper lling ensures
using backer rod and sealant. better water-tightness at window/ wall joints.
Fig. 4.16 - Difcult to ensure accurate openings Fig. 4.17 - Improper lling may lead to water
with on-site operations. seepage at frame/wall joints.
40
Precasting is often the solution to quality problems when there are difculties in executing the
particular type of work in-situ. Staircases, refuse chutes and lift walls are examples where formwork,
rebar placement and provisions for openings often pose considerable challenges leading to grout
loss, inconsistent joints, surface damages and imperfections. Using pre-cast elements for these
components, such defects can be reduced.
Fig. 4.18 - Precast staircases: Better dimensional accuracy and quality nish.
41
Precast architectural elements such as facades, fascia and gable end walls, parapets, sunshades,
secondary roong panels, bay windows, etc can be used instead of wet in-situ works to achieve
correct dimensional tolerances and better quality nish.
Fig. 4.19 - Architectural precast elements reduce wet works and enhance nish quality.
42
In total precast concrete systems, architectural elements can also perform their structural functions.
It therefore reduces the number of construction operations and trades. Combining architectural and
structural members lead to better organized design and construction. The following precast elements
can be combined for greater efciency and quality:
Columns
Shear wall
Facade walls
Air-conditioning ledge
Sun shades
Bay window
Beams
Planter box
Pipe-duct
Staircase
Household shelter
Refuse chute
PC COLUMN
PC BALCONY
PC BEDROOM BAYWINDOW
PC TOILET BAYWINDOW
PC PLANTERBOX
Fig. 4.20 - Total precast system results in better build quality building.
43
Precast components can be custom made to match design requirements. Complex shapes,
sizes and specic technical requirements can be easily fabricated in precast plant. Without such
prefabrication, complex designs may be difcult to build or the desired quality hard to achieve on-
site using conventional construction. Precasting allows greater design exibility and repeated use of
similar shapes and sizes lead to better economy.
Fig. 4.21 - Complex shapes and elements can be fabricated and installed without compromising quality.
Alignment, verticality and surface nish of external elements are critical areas in building facade.
Factory made precast wall panels require minimal surface preparation before nal nish. Scaffolding
is generally not required for the nishing works. This makes the construction site tidier and the works
can be carried out faster, apart from savings in scaffolding cost. Typical quality problems in traditional
plastered external walls such as hollowness, plaster waviness and cracks can be avoided when
precast external facade system is used.
Fig. 4.23 - No scaffolding and plastering required for nal nish of precast facade.
Fig. 4.24 - Traditional formwork construction: Untidy scaffolding and uncertain build quality outcome.
45
To reap the full benets of using pre-cast elements, it is important to ensure that pre-cast elements
are installed properly. Results from CONQUAS assessments show that despite the expected better
nish surfaces, cracks and damages are frequent non-compliances for precast elements. This is
often the result of damage to the components during transportation, lifting and installation.
Fig. 4.25 - Cracks and damages: Result of damage during transportation, lifting and installation.
Attention and planning are needed at the design and execution stage to prevent such damages.
Provision should be made for lifting and handling devices within the pre-cast elements. The capacity
of lifting equipment, gears, rigging arrangement, weight of precast elements, concrete strength and
expertise of the installers are to be considered during transportation, lifting and installation. This will
ensure the benets of using pre-cast elements are not negated during nal installation.
4.2.9 Optimizing design and use of recycled concrete aggregates (RCA) in precast elements
The use of precast concrete elements should incorporate sustainable development practices. This
is in line with trends to optimize the use of natural resources and products and materials that are
environmentally friendly. Recycled concrete aggregates (RCA) can be used to replace natural
aggregates in non-structural components e.g. non-structural precast internal partition walls. This
will reduce the depletion of natural resources by turning wastes into resources through reuse and
recycling.
Where it is not possible to use such alternative materials e.g. in structural precast concrete components,
the design should be optimized to achieve the most efcient sizes and reduced concrete usage.
5.0
QUALITY FEATURES IN
ARCHITECTURAL ELEMENTS
5.1 PREFABRICATED BATHROOMS
5.2 DRYWALL PARTITIONS
48
Prefabrication technology is not new to the construction industry and has been in use for many
years. Prefabrication permits components to be assembled in the factory under strict quality control
before its installation on site. A prefabricated bathroom that integrates many trades can be employed
to achieve consistent and high quality workmanship in a building.
This section features prefabricated bathroom systems currently used in private residential projects in
Singapore, their advantages and contributions to high build quality.
A typical prefabricated bathroom comprises a 100mm thick concrete base slab, four surrounding
walls of galvanized metal plates internally, dry wall partition externally and rock-wool insulation inll.
It may weigh about 3 tonnes and the full bathroom assembly, including sanitary ttings and nishes
are produced at a factory in a controlled environment.
Fig. 5.1- Assembling bathroom in a factory environment: Allows proper coordination and achieves better quality.
49
Fig. 5.2c - Metal panels mount on wall tiles. Fig. 5.2d - Fix metal panels to base slab.
Fig.5.2e - Carry out M&E installation & testing. Fig. 5.2f - Pack and deliver to site.
50
In a typical wet method construction, lippage or unevenness in wall tiling is frequently the result of
unskilled workmanship. More skill is required when the tiles are placed vertically on walls using
adhesives. This dependency on skilled labour is reduced in prefabricated construction where the
tiling work is set out horizontally on a leveled surface and xed to the metal plate using a thin layer
of glue adhesive. The chance of lippage or unevenness is very much reduced if good quality tiles
without manufacturing defects are used.
- No de-bonding or hollowness
Most wet areas including bathrooms need to be built with a gradient towards the oor trap to
discharge waste and prevent water puddling. Typically, the gradient is formed during oor screeding
using cement-sand mortar. In some situations e.g. protrusion of concealed pipes on the oor, it may
be difcult to form the required gradient using the base screed. As a result, the correct gradient is
formed using tile adhesives when laying the tiles. However, this is not a good practice to form the
required gradient.
In prefabricated bathrooms, the tiles are laid directly on the concrete slab without screed. The
correct gradient is formed by the mould and the concrete casting is carried out while the mould
is in reverse position. After curing and removal of the mould, the base slab is turned to its original
position. Therefore no screeding is required and consistent adhesive thickness can be maintained
when laying tiles. The nal gradient is also precise according to design.
53
Mould
Concrete
Fig.5.7 - Floor tiles are laid without screeding. The required gradient is formed while casting base slab.
Fig. 5.9a - A cantilever platform is used to rest and Fig. 5.9b - Simply supported connections secure
direct bathroom into place. bathroom in place.
Prefabricated bathrooms are produced using thin precast walls with a solid base as a frame. This
standardization allows close quality checks before installation. Careful planning, sequencing and
inspection of trade works are carried out in the factory to achieve the required quality. The following
images show the sequence of important activities in the process.
Fig. 5.10a - A standard mould casts precast base and Fig. 5.10b - Precast frames are cured before
walls together for better water-tightness. starting other trades.
55
Fig. 5.10c - Apply waterproof membrane and Fig. 5.10d - Checkered internal surfaces for
water-ponding test. installing tiles without basecoat.
Fig. 5.10g - Delivery and installation by tower Fig. 5.10h - Less intensive manpower needed
crane. during installation.
56
Fig. 5.10i - Tidy and dry construction process. Fig. 5.10j - Quality internal nish.
It is not uncommon for bay windows to be integrated with prefabricated bathrooms. This further
reduces the number of trade activities on site that includes bay window installation. The weight of
such integrated units, about 6 to 8 tonnes each, are heavier but the production, tting, testing and
nishing works can all be carried out in a controlled factory environment leading to better quality
product and workmanship.
The images below show the key sequences in fabrication and installation of the integrated system:
Fig. 5.11a - Precast base and bay window unit. Fig. 5.11b - Apply waterproong on metal wall panels.
Fig. 5.11i - False ceiling erection. Fig. 5.11j - Install window inner frames.
To maximize the benets of using prefabricated bathrooms, the project team should consider
integrating such systems during the early stages of the project (concept and scheme design). Once
the scheme design has been nalised, there is limited scope and value in exploring prefabrication
options. In fact, it may cause disruptions to the original design and this can delay the project.
Large prefabricated sections require heavy-duty cranes capable of handling and precise maneovreing
to place it in position. A proper sequence of erection and inspection should be established to ensure
quality in fabrication and installation. When adopting metal panel wall systems, attention has to
be paid to the strength, corrosion-resistance and treatment of joints on the panels to avoid future
malfunctions.. Furthermore, proper guidelines should be given to end-users when they wish to retrot
tiles and other ttings in the bathroom in future.
60
Drywalls are light weight leading to signicant reduction in dead loads. This allows designers to
design for lighter structures and foundations, leading to savings in structural cost. The wall system is
able to resist high impact forces and it can support loads such as TV, cabinets, shelves, etc. attached
to it.
Fig. 5.14 - Proper anchorage system facilitates mounting of TV, shelves and cabinets on drywall partitions.
Enhance productivity
Internal wall nishes is one of the elements assessed under CONQUAS. The pie chart shows non-
compliance data on internal wall nishes collated from private residential projects assessed under
CONQUAS from 2005 to 2007. Among the 5 items assessed, the most frequent non-compliances
are in nishing and joints. The frequency of such defects are generally higher in cement-based
plastered walls.
A separate study on projects (see Chapter 8) with high CONQUAS scores reveals that adopting
drywall systems signicantly reduced the non compliances on internal walls. The quality of the
nishing works that can be attained is better than conventional plastering works.
The following highlights the inherent advantages in drywall systems leading to better workmanship
quality.
Rough surfaces and inconsistent paint nishes are the most frequent non-compliances in plastered
walls. The smoothness, consistency and texture in paint work are very much dependent on the
substrate surface. If the substrate is smooth and not wavy, it will be easier to achieve good paint
work either by roller or spray method. Drywall systems present an even board surface which can be
prepared easily with a thin layer of putty and sanding it before painting.
Fig. 5.23 - Smooth drywall substrate surface aids Fig. 5.24 - Consistency in nished surface.
good paint nish.
66
No plaster hollowness
In conventional brickwork, thick coats of plastering may be required to compensate for bricks not
properly laid and to get a balanced smooth nish. This often results in hollowness and de-bonding
when the plaster work is too thick or not carried out properly. In drywalls, only a thin layer of skim coat
is sufcient to get a smooth surface. There is no risk of hollowness or de-bonding.
Fig. 5.25 - Thick plaster coat is main cause of Fig. 5.26 - No hollowness risk in drywall
hollowness in conventional masonry work. skim coat.
During erection of studs for drywalls, alignment and verticality can be easily controlled. Once the
studs are properly installed, the boards can be xed on them evenly. There is no need for thick
plastering to get an even surface.
Fig. 5.27 - Alignment and verticality are controlled Fig. 5.28 - Less occurrence of mis-alignment and
when erecting studs. unevenness.
67
In wet plastering works, more manual skill is required to make a joint between two straight walls
notwithstanding the use of additional aids like angle and inner beads to achieve a neat joint. This is
due to difculties in trying to combine two or three layers of plaster together. In drywall systems, only
a thin coat of joint compound is required as straightness and alignment are controlled during stud
erection leading to neat and straight joints at wall intersections.
Fig. 5.29 - A thin corner-bead helps make corner Fig. 5.30 - A neat and straight internal wall joint.
straight.
To derive maximum benets from using drywall systems to achieve workmanship quality, it is
important to pay attention to certain details.
Cracks can also appear at the joint between two different materials due to differential expansion
and contraction of the materials and temperature changes.
To prevent this, some projects use a drywall board to cover the RC surface (see Fig. 5.32).
Conventional detailing
RC Column
Drywall Drywall
Joint tape
Potential crack
Proactive detailing
RC Column
Drywall Drywall
This detailing will minimize the appearance of cracks at joints. In addition, the whole premises will
have a uniform nish and it is also easier to carry out the subsequent works like application of joint
compound and painting. However, this detailing may reduce the space in the room (by the boards
thickness of about 12 to 19mm).
69
To prevent distortions and sagging of openings, the studs need to be stronger to cope with the weight
of the door and forces caused by slamming. Typically this would involve boxing the studs or sleeving
them with a channel, as well as including timber inserts. The standard details for forming door jambs
are illustrated in Fig.5.33, although other suitable timber framing assemblies may be required to
adequately support heavier doors. For large openings, a stronger lintel (Fig.5.34) may be required. It
is also important to ensure openings are accurately formed to prevent uneven gaps or creaks caused
by movement between ill tting members.
Plasterboard
Door frame
Top track
Intermediate stud
min. 150mm
Fig. 5.34 - Timber insert at top acts as lintel for door frame.
70
In some projects, the whole inner RC surface areas are clad with drywalls to have a uniform nish
throughout the unit. In practice, RC walls require a skim-coat nish while drywalls require a joint
compound nish. Adoption of this method is to avoid using two different nishing materials for different
surfaces in the same unit. This system will reduce the internal area slightly and increase the cost.
However the surface appearance and paint nishes will be consistent throughout the unit.
Fig. 5.35 - Drywall cladding over inner perimeter Fig. 5.36 - Uniform surface nish throughout the
of RC walls. premises.
Some boards are now fabricated with moisture resistant properties and are suited for use in wet
areas. The boards are also coated for bonding with tile adhesives and waterproong membranes
and are resistant to mould growth. It has a homogeneous structure that impedes de-lamination under
moist conditions. Although widely compatible adhesives are available in the market, it is a good
practice to carry out compatibility test prior to use. In addition, installing studs on concrete kerb in wet
areas is also a good practice to prevent consequences from stagnant water.
Fig. 5.37 - Stud erection on a concrete kerb in wet Fig. 5.38 - Drywall partition with waterproong
areas. membrane.
71
The concealed services in wet areas like water and sanitary pipes can be installed without untidy
hacking and patch-up. This is a faster and less cluttered process. However, the use of board systems
for wet areas is only a recent trend and its performance should be further monitored and evaluated
based on end-user feedback.
Fig. 5.39 - Installation of wall nish on board Fig. 5.40 - A completed toilet with wall nish on
partition by using adhesive. board partitions.
To achieve maximum benet in drywall construction, the manufacturers guidelines should be strictly
followed during the installation process. Some detailing may need to be revised to suit the project
and this should be claried with the supplier or specialist professionals. It is also advisable to provide
an instruction manual to the end-user illustrating, among other things, how to anchor and install TV,
cabinets or shelves on the board partitions.
6.0
DESIGN AND DETAILING FOR QUALITY
IN ARCHITECTURAL COMPONENTS
Door is an essential element in buildings. Some door designs and detailing inherently lend itself
to good quality outcome. This section illustrates some such examples which can be considered to
improve workmanship quality.
Pocket door (also called slide and hide) system is now widely used in residential projects. The sliding
door panel is hidden within the hollow section between walls and operated on a track and roller
system xed at the top of the door panel (Fig. 6.1). This system enhances spaciousness in the unit,
as the sliding door is hidden from view when it is open.
However, in most cases it is not feasible to provide tracks at the bottom of the door panel as this is
xed on the oor and may cause inconvenience to users e.g. tripping or creating a barrier. Dirt and
dust can also accumulate inside the track and this needs to be cleaned periodically. Most designs
therefore specify the track to be installed at the top only.
In such designs, the door panels are typically about 2.1m high and the whole panel hangs from the
top track. When the doors are in closed position and butt against each other, any misalignment can
be noticed easily due to uneven butt gap and different levels of the adjoining panels (Fig 6.2).
Fig. 6.1 - A pocket door system hung on top track Fig. 6.2 - When door is closed and butt against
enhances spaciousness in a unit. each other, any misalignment is easily noticed.
75
The inherent difculty in aligning top-hung pocket door panel system can be overcome or minimized
by introducing a tongue and grove prole on the butt edges of adjoining door panels (Fig. 6.3 & 6.4).
It provides a better t of the butt ends and less possibility of gaps or misalignment when the door is
in closed position.
Fig. 6.3 - Tongue and grove prole at butt edges in a pocket door system.
To get round this challenge, a sub-frame system which is widely used in private residential projects
but less so in public housing and commercial buildings, can be employed. A door sub-frame is rst
built into the wall construction and the main frame is installed at a later stage i.e. after completion of
the major wet trades. This reduces the risk of damage by other trades during construction. The other
advantages of such a system are:
The main frames are less likely to shrink and warp since it is not directly in contact with any
masonry structures.
The oor nish below the frame can be installed more easily. It need not be cut to suit the door
frames prole since the frame is installed after the oor nishing works.
Fig. 6.6 - Door sub-frames installed before main Fig. 6.7- Main frame installed after completion of
frames: Adjoining oor installation need not be cut oor nish. A neat joint is achieved below the door
to door frame prole. frame.
77
Fig. 6.9 - Better alignment consistency between door frame and panel.
The lift-up hinges system allows the door, together with the hinges, to be fabricated off site and
slotted into place after the nishing trades have been completed. (Fig. 6.11)
Fig. 6.11 - Lift-up hinge allows door panels to be installed late in construction. This reduces damage on doors by
other trades.
Functionality (1.8%)
Alignment
Inconsistent alignment between a frame and a door panel is usually the result of warpage and
twisting in the panel or frame. This could be due to inherent characteristics of the timber material
used and its tendency to warp/twist is more likely when longer lengths of panel or frame are used.
In such cases, the panel will not be aligned exactly with the frame, making it more noticeable. To
minimize such defects, it is important to use materials that are properly treated and protected from
moisture ingress and provision of better detail and prole on door panels.
Fig. 6.14 - Warpage and twist in door panel is easily noticeable in standard door design.
80
The typical components in a residential project include wardrobe, kitchen and vanity cabinets, shoe
rack, wash basin, shower screen and water closet (W.C.). This section highlights and compares the
advantages in using preassembled (modular) system components over components that are cut and
assembled on site. It also highlights how the selection of materials, accessories and its installation
impacts the quality of the component.
There are many types of nishes available for use in cabinets. The common nishes include:
Veneer
Melamine
Laminate
Polykem
Vinyl
These nishing materials can be installed on-site by manual labour or integrated into the component
by machines in the factory. The following highlights the challenges in ensuring quality of the nished
component when installation is carried on-site.
Imprecise cutting
Air bubbles in lamination xing
Uneven lap or mitre joints.
Very often, the installation work has to be carried out in narrow or conned spaces. The conned
space is not a favourable environment for the workman to carry out ne or precision work. This may
be compounded where there are many trade activities in the same area. In such situations, lower
quality workmanship and productivity are often the result.
If the site environment is dusty or polluted, it The more complicated the layout e.g. more
may affect on-site lamination process. There turns, corners, odd shapes, etc. more care and
is possibility of de-bonding, blistering and the in-depth planning is required before producing
nish surface may not be sufciently smooth. shop drawings. The installer should be capable
At the same time, it is also necessary to take of reading, interpreting and executing the
precautions during installation to avoid damage designs according to the specications. A
to other sensitive nishing trades like natural proper cutting schedule needs to be prepared
stone or timber ooring. and adequate skill is required to assemble
the works to minimize wastage during onsite
installation.
Fig. 6.22 - A typical on-site installation Fig. 6.23 - Turns and odd shapes: Need more
environment. attention.
Materials can be easily damaged if they are not properly stored and protected against dust or wet
and damp conditions. For certain products, improper storage and insufcient ventilation may affect
the moisture content of the material leading to warpage and twist.
Factory assembled components generally have consistent joints and smooth nish especially
in critical areas like rounded edges and mitre joints. The factory environment with good quality
control results in better and more consistent component quality compared to on-site fabrication and
assembly.
Fig. 6.25 - Joints at turns are smooth and precise in factory assembled cabinets.
Fig. 6.27 - Pre-assembled modular kitchen cabinet system generally gives good nish, quality and dimensional
accuracy.
86
To maximize the benets of using factory assembled components, it is necessary to pay attention
to design and detailing when installing the components on site. The following examples show how
such benets can be maximized.
The traditional way of mounting a cabinet on a wall is by drilling and plugging. The small gap between
cabinet and wall is then lled with silicone material. If the quality of silicone used is inferior, it will
deteriorate and discolour with time. The jointing consistency will also depend on the skill of the
applicator. If the gap between wall and component is too wide or inconsistent, the operation becomes
more difcult. Very often this results in a joint that is not neat and aesthetically pleasing.
To overcome this, a PVC / rubber strip insert is placed at the joint instead of silicone inll in some
modular system cabinets. It results in a neat, simple and consistent joint.
Fig. 6.28 - Gap between wall and component Fig. 6.29 - A PVC strip introduced in the gap
sealed by silicone material applied manually. results in consistent and neat nish.
Fig. 6.31 - Additional magnetic catches help to hold the door in position for taller panels.
Fig. 6.33 - Provision of in-lay to carcass cushions Fig. 6.34 - Gap between door panel and carcass is
against noise and prevents damage. consistent and neat with in-lay.
88
In many cases, any warp in door panels becomes more noticeable when the adjoining gaps are
wide. A rebated door panel prole can be introduced to make this less noticeable when the door is
in closed position.
Fig. 6.35 - Door panels with rebate feature can make gaps better aligned and consistent.
To minimize such problems, some acrylic polymer materials that are suitable for counter tops and
which come in long sizes together with backsplash can be used. The homogenous material generally
has good resistance to liquid ingress and can be polished if there are any minor scratches on the
surface. Less jointing is required and it gives a better quality nish appearance.
Fig. 6.37 - Long counter top with integrated Fig. 6.38 - Fewer joints facilitate easy installation
backsplash: No on-site joint required. and better quality nish.
Wash basins are usually xed to a vanity counter using a bracket system. The joints between the
basin and counter top are then sealed with silicone material to prevent water ingress. Some projects
eliminate this sealing process by using factory made integrated counter top with built-in basin and
sink as a single component. This reduces site work and results in a uniform and quality nish.
Fig. 6.39 - Integrated vanity counter and Fig. 6.40 - Integrated kitchen top, back - splash
washbasin. and sink.
To reap the benets of high productivity and quality by using pre-assembled components, careful
planning is required at the design stage. The plinths, kerbs, room dimensions and other spaces
should be constructed accurately to suit the components. Once the components are fabricated,
it would not be possible to alter or modify dimensions and sizes to suit changes in site conditions
without additional time, cost and impact on quality.
7.0
DESIGN AND DETAILING FOR QUALITY
AT ADJOINING LOCATIONS/
TRADES
The design at adjoining locations i.e. where one architectural element meets another often has an
adverse impact on quality, if little consideration is given as to how it is to be executed or maintained
during use. Some designs are complicated and difcult to construct and may require more skill,
planning and co-ordination among trades. Such designs should be reviewed at the shop drawing or
mock-up stage and a simpler detail that facilitates construction and subsequent maintenance should
be considered. The following examples illustrate such situations and suggest how the design and
detailing can be modied to achieve better constructability and quality.
Generally, door frames are installed within the wall opening. However, when the frame is positioned
too close to the adjacent wall running perpendicular to it, the gap between the wall and frame may
become too narrow (about 15mm or less) and this may pose difculty to complete the other nishing
trades e.g. skirting, painting, etc. at this gap location (Fig 7.1 & 7.2). The same constraints will also
occur when two adjoining door frames are positioned close to each other resulting in a narrow gap
between them (Fig. 7.4).
Fig. 7.1 - Difcult to install skirting or carry out Fig.7.2 - Filling for the narrow gap is difcult and
painting in the narrow gap. looks untidy.
Fig. 7.3 - Too small space: Difcult to seal by a Fig. 7.4 - More time and skill required to nish the
skirting piece. gap.
93
These situations can be avoided by positioning one side of door frame touching or very near the wall
instead of leaving a gap. As the frame nearly touches the adjacent wall, any remaining gap can be
easily lled with materials like silicone.
Fig. 7.5 - One side of the frame touches the wall and the other side has more working space. This facilitates
execution of other nishing trades.
To prevent such situations, the architrave should terminate above the oor level e.g. at threshold
level. It is also good practice to install sub-frames above the screed level to reduce the chance of
water ingress from the wet oor through the masonry works.
Fig. 7.7 - Sub-frame is installed above screed to Fig. 7.8 - Architrave terminates at threshold to
avoid rising damp. minimize water contact.
Fig. 7.10 - Water penetration damages timber oor and door frame.
95
Fig. 7.12 - A small kerb below the screed may reduce water ingress.
96
Fig. 7.17 - Forming grooves on masonry works: Challenging and time-consuming to maintain consistency.
Skirting can be considered to avoid such complications. Timber skirting is one of the options to cover
joint between oor and wall and offers the following advantages:
Fig.7.18 - Marble ooring with timber skirting: No wet works required for skirting installation.
Fig. 7.19 - Granite oor with timber skirting: Less joints on skirting.
99
Good interfacing design and detailing not only address quality issues but also facilitate constructability
and minimize maintenance difculties. However, to derive maximum benet, a thorough review of
interfacing design and detailing should be done early during the shop drawing or mock-up development
stage.
100
Building services that are to be embedded or concealed should be properly planned and coordinated
with other structural and architectural works to ensure they are functional and aesthetically pleasing.
The locations and interfaces of the services with other trades should be determined early to avoid
undesirable consequences during construction and maintenance. The examples below highlight some
practices in positioning, concealing or embedding service pipes, their weaknesses and deciencies,
and some practical measures to overcome them.
Fig. 7.21 - Half moon position affects liquid ow, Fig. 7.22 - Additional traps cannot be installed if
functionality and maintainability. sleeve opening is partially blocked.
101
Dimensions and locations of oor traps and sleeves can be clearly dened in shop drawings. However,
with many different trades involved during construction, it may not be possible to achieve accurate
positioning unless there is sufcient planning, coordination and strict control during construction.
Accurate alignment is made more difcult when the concealed sleeve is the same size as the grating
opening, which leaves no margin for any error. This challenge becomes more acute in large scale
operations and where heavy reliance is placed on skilled labour to ensure consistent positioning.
To overcome the challenge, a sleeve larger than the gratings opening can be considered. It gives
some tolerance (about 15mm) all round for errors in positioning. This also provides exibility in
aligning the oor trap grating cover with the sleeve to achieve the full pipe opening without hacking
the screed or concrete.
Fig. 7.25 - Funnel shaped cast-in pipe/socket Fig. 7.26 - Flexibility in achieving full opening.
sleeve.
Discharge pipes leading from ttings to oor traps are often designed to be concealed in the oor.
For proper ow and discharge, they have to be sufciently sized and installed with a gradient. If such
pipes are not properly integrated during construction, they have to be installed after the concrete slab
has been cast. The concrete slab surface has to be hacked to a certain depth to receive the pipe.
The usual size (diameter) of the pipe is 40mm or more and it is not possible to provide a full recess in
the slab without affecting the reinforcement cover. Hence the maximum recess can only be about 15
to 20mm. The rest of the pipe protrusion will need to be concealed within the cement- sand screed.
As the screed needs to slope towards the oor trap, it will be thinner near the oor trap and may not
fully cover the protrusion of the pipe.
Eventually, any pipe protrusion not concealed by the screed will be covered by tiling adhesives. This
means some portions of the tiles are directly resting on the pipes without a screed base. Such areas
have weak bonds resulting in hollowness in the oor tiling.
103
Pipe Protrusion
Fig. 7.27 - Washing machine drain pipe of 40mm Fig. 7.28 - Screeding may not fully cover pipe
diameter connects to oor trap. protrusion due to forming gradient.
Fig. 7.31 - Concealed sleeves with pipes after Fig. 7.32 - No risk of de-bonding of tiles on fully
casting. embedded pipes.
Discharge pipes (eg. washing machine discharge) are usually placed near wall corners to maximize
working space. In some circumstances, due to increase in plaster thickness, misalignment of wall or
inaccuracy in sleeve installation the sleeve position becomes too close to the wall. This will hinder or
obstruct other architectural works like oor skirting, wall painting, applying sealant, etc. in its vicinity.
This can be minimized by positioning the pipe a short distance away from the walls.
Fig. 7.33 - Pipe sleeve obstructs other Fig. 7.34 - A small clearance between wall and pipe
architectural works in its vicinity. facilitates execution of other trades.
105
Fig. 7.36 - Concealed pipes are erected before Fig. 7.37 - Pipe cast with concrete to ensure
construction of brick walls. strength and water-tightness.
106
Air-conditioning drain pipe design usually starts with the pipe from the FCU (Fan Coil Unit) passing
through a wall and oor slab to a wet area oor trap. The vertical and horizontal pipes are concealed
in the wall and oor screed. As a gradient is required in wet oor areas, the screed often becomes
thinner nearer the oor trap. This may result in de-bonding of oor tiles near to the oor trap (Fig.
7.29).
Similarly, where drain pipes pass over drops between wet and dry areas e.g. bedroom and toilet, the
protrusion has to be covered by the screed and it will result in a shallower drop. This may lead to
water ingress to the adjacent dry area.
Fig. 7.38 - Running air-con drain pipes across Fig. 7.39 - Floor screed cannot cover high
drop leads to shallower drop. air-con pipe protrusion at oor trap.
The drain pipes are to be properly supported and insulated before connecting to the discharge stack.
It should be laid to an adequate gradient and tested before closing the false ceiling. A cleaning eye
provision before the main discharge should be considered for maintenance purpose. The works
should be properly sequenced and coordinated with other architectural works.
Fig. 7.41 - Drain pipes are properly insulated, Fig. 7.42 - Drain pipe connects to stack pipes
supported and laid to required gradient. above false ceiling.
The incorporation of embedded/concealed services requires careful planning at the design stage.
Locations and interfaces of the services should be determined in the early stage of construction
to avoid unpleasant consequences during construction and maintenance. The embedded services
positions and routes should be properly documented in the as-built drawings for end-users future
reference and maintenance purposes.
8.0
EXAMPLE PROJECTS
The good design practices in this guide are based on observations of various projects
with high CONQUAS/Quality Mark scores (Quality Mark Scheme is applicable only to residential
projects). These projects invariably employ some or more of the good design and material
selection practices in this guide to achieve better quality outcomes. Seven of these projects are
highlighted here. It should be noted that the material for this guide also came from many other
high scoring projects but due to space constraints, it is not possible to highlight all.
110
CONQUAS
Score: 94.1
Average Quality
Mark Score: 86.6
Prefabricated components:
Precast planks: Full height windows:
Off-site production and better
Better atness of oors. Minimize wet trades processes.
quality.
CONQUAS
Score: 92.3
Average Quality
Mark Score: 86.6
CONQUAS
Score: 90.4
Average Quality
Mark Score: 83.6
CONQUAS
Score: 88.7
Average Quality
Mark Score: 81.2
CONQUAS
Score: 88.3
Average Quality
Mark Score: 85.3
CONQUAS
Score: 88.0
CONQUAS
Score: 87.6
4. Good Industry Practices Guide Series: Singapore: Building and Construction Authority.
6. http://www.bca.gov.sg
7. http://www.wbdg.org/wbdg
8. http://www.factorysteelbuildings.com
9. http://www.ciria.org.uk
10. http://www.allsteelbuildingcomponents.com
11. http://www.strescon.com
12. http://www.metal-buildings-guide.com
13. http://www.cement.org/newsroom/greenbuild_2006/precast.htm
14. http://www.livingsteel.org/features/replacement-not-displacement
15. http://www.steelbuildingadvice.com
16. http://www.theamericas.org/steel_frame.advantages.html
17. http://www.mapaprecast.org/precast-wall.asp
18. http://test.wecims.com/pages/managementservies
19. http://www.qualitydigest.com
20. http://www.kajima.co.jp/success/design/index.html
21. http://www.emeraldinsight.com