78313
78313
78313
Abstract
An innovative completion method was recently used to
complete a well in the Skua oil field in the central area of the
North Sea. The Skua field is part of the ETAP (Eastern Trough
Area Project) and is borderline high-pressure/high-temperature
(HP/HT) with a reservoir pressure of 9,350 psi and a reservoir
temperature of 307 F. The initial field development plan was
to have one subsea well with a horizontal reservoir section of
2,000 ft to drain the prospect. Production would be tied back
to a central processing platform.
The completion design for this well had to address
several challenges.
1. What method could be selected for sand control in the long
horizontal section
2. What equipment would maintain integrity in near HP/HT
well conditions
3. What configuration would allow the completion to be run
underbalanced without completion isolation devices.
Several completion options were reviewed. A new gundeployment system based on production packer technology
was chosen because it appeared to offer the best option for
meeting all the well requirements. The system would also
allow the tubing-conveyed perforating (TCP) guns to be
recovered if they failed to fire or malfunction.
Orientated perforating guns were used to mitigate sand
production. The gun system was deployed from a novel
polished bore receptacle (PBR) and permanent packer system
that allowed for retrieval of the guns should they fail to fire or
malfunction after the packer had been set. The polished bore
receptacle and hydraulically set permanent packer were
designed with the guns hung off the seal assembly of the
polished bore receptacle and the tailpipe run through the
permanent packer to the TCP guns.
A significant feature of the hydraulically set packer-TCP
gun deployment system is that it allows contingencies for
recovery of the completion and TCP guns from the well in the
event of a total or partial perforation misfire. This was a
necessary requirement in view of the fact that a long
perforation gun string was to be deployed in a hightemperature reservoir where there would be an increased risk
of gun failure due to the ambient reservoir conditions.
The Skua well was completed with a fully cemented liner.
The completion and TCP guns were run, and the well was
successfully completed and perforated underbalanced (without
an isolation device) in a single trip.
Introduction
This paper will describe the selection method as well as the
development, testing, and implementation of a new TCP
permanent production packer system.
The Skua field is operated by Shell U.K. Exploration and
Production on behalf of Shell and Exxon Mobil and situated in
the Central North Sea block 22/24a (Fig 1). The subsea
development well, Skua S1, was successfully drilled and
completed with first oil produced in October of 2001. The well
was designed for an initial production rate of 25,000 BOPD.
The well is a subsea tieback exporting oil production via
flowline to the BP operated central processing facility. (See
Fig. 2)
Skua is a near-HP/HT field with initial reservoir pressure
of 9,350 psi and 307o F bottomhole temperature (Table 1).
The Skua reservoir fluid is a highly pressured, undersaturated
light oil of 42 degrees API gravity. The Skagerrak reservoir is
located at a depth of 11,735 ft TVDSS, 13,170 ft along hole
below drill floor (AHBDF) and is accessed with a 2000 ft
horizontal liner section to maximize production from
compartmentalized zones.
Principle Completion Design Parameters
The required design parameters were developed as follows:
Production at an initial rate of 20-25 k BOPD, maximum
design rate of 30 k BOPD.
SPE 78313
SPE 78313
Contingency Operation
The special TCP packer configuration contains a 5 -in. x 4in. x 3 -in. internal string from which the TCP perforating
gun string is supported. Therefore, the completion can be run
as a conventional TCP deployment operation. In a worst-case
scenario, should the guns misfire, the design would allow a
tubing overpull to shear out the shear ring from the PBR. The
upper completion, inner string and mis-fired guns could then
be pulled back through the packer, leaving the PBR sealbore
and packer set downhole. A backup packer system can then be
re-run with a replacement packer set above, leaving the
original packer redundant.
Development and Qualification
The detailed design review for the selected packer included
the criteria required for the testing and qualifying program to
assure compliance with the Shell quality assurance plan. The
qualification and prototype testing program was formulated to
closely reflect the well life-cycle operating conditions to
which the packer would be exposed in Skua S1.
The required test design envelope was determined from the
tubing stress analysis and thermal model (Fig. 6). Packer
differential pressure and thermal modeling data provided input
parameters for developing the testing program. Thus, the
prototype test conditions would closely emulate the predicted
maximum and minimum environmental conditions for various
stages of the well life and would allow safety factors to be
verified within the design stress envelope. The other
completion equipment had a similar qualification regime
applied or been field proven in similar well conditions in the
North Sea.
The Packer/PBR system was qualified to ISO 14310 V3 at
325F and was tested in the actual 9-7/8-in. casing used for
Skua. Also, cyclic temperatures and pressures were applied
after the PBR shear ring was sheared to simulate life of well
operations such as scale squeeze.
Load Cases. The Skua well was modeled to determine all the
load cases during the life of the well, and these included
pressure tests, early production, late production with
maximum annulus pressure (washwater injection), hot
evacuation, and scale squeeze. The PBR seal assembly was
designed to remain static during life of the well operations and
to shear during cold kill or scale squeeze only. A 150,000 lbf
shear ring was selected to meet these requirements.
Wet-Stab, Polished Bore Receptacle. The well was
considered HP/HT, and thus, precautions were taken to
mitigate trapped atmospheric pressure between the seals. To
eliminate this concern, the seals were stabbed into the PBR
submerged in a bath of silicon oil. This removed any air
between the seals and the potential for an
atmospheric chamber.
After a review of the wet stabbing procedure, it was
decided to complete this operation in a horizontal position
during the assembly stage rather than use a test rig and wet
stab in the vertical position. This involved designing a special
SPE 78313
chamber to attach to the top of the PBR and hook up to the test
ram. The seal mandrel was installed in the horizontal position
and wet stabbed at the same time. This eliminated any health ,
safety and environmental risks primarily associated with
manual handling of equipment at height, as it avoided using a
complicated stack up of equipment at a test well facility.
Hydraulic-set TCP Packer. The packer/PBR system had to
be qualified to the Skua load conditions. A 9-7/8-in.
permanent packer, 6-in. PBR, and ratch latch were selected
and modified to accommodate the inner string running down
through the inside of the packer to the TCP guns. The
permanent packer was a 10,000-psi-rated packer with a Nitrile
element and metal back-up rings. The bottom sub of the
packer was extended for a 4.5-in. seal bore to allow the packer
to be set conventionally with an additional seal mandrel on the
inner string. Viton, Teflon, and Ryton vee packing was
used on the PBR and ratch latch to maintain pressure integrity
over the wide range of temperatures.3 Inconel 718 alloy
material was used for the well conditions.4
Existing equipment was available but this had to be
modified to suit the Skua well conditions and the new concept
for running the TCP guns. The modifications included:
A PBR seal mandrel crossover from 5 -in.x 4-in. x 3
-in. and extended through packer ID
Additional moulded seals added to the seal mandrel
for setting packer
A packer bottom sub extended for 4.5-in. seal bore
A 20-ft stroke, one-piece PBR
A prototype PBR with the stroke reduced to 10 ft to fit
into the deep well simulator.
Three systems were manufactured: primary and backup
production systems for the Skua well and a prototype system
for testing.
Testing. The packer/PBR assembly was pressure tested
individually before assembly make-up of the PBR, ratch latch,
packer and seal mandrel. A 10,000-psi internal body test at
ambient was completed on the assembly prior to the
envelope test.
The following conditions were identified for qualifying
and testing the packer/PBR system to the Skua
well conditions:
ISO 14310 V3 Packer/PBR system test at 325 F, 8500
psi, with tension and compression. A 200 F
thermal cycle.
Overpull PBR and shear 150,000 lbf PBR shear ring
at 325 F.
PBR thermal/dynamic tests at 325 F/125 F and stroking
the seals 4-ft under constant pressure. Repeat cycle
3 times.
TCP guns interface trials.
The ISO 14310 V3 test was completed on the prototype
system at the deep well simulator in Dallas. The complete
assembly measured 46 ft including the top and bottom pup
SPE 78313
joints. For testing purposes, a 10-ft PBR was used to allow the
assembly to be lifted into the deep well simulator. The 9-7/8in. casing was installed, and the test fixtures made up to the
hydraulic jack (shown in Fig. 7). The prototype assembly was
manufactured with exactly the same materials and elastomers
that would be used in the production units.
The packer/PBR system was tested in the Skua 9-7/8-in.
casing joint with test fixtures to allow make up to the
hydraulic jack. The temperature in the deep-well simulator can
be controlled at 325 F and allows independent application of
pressure above or below the packer with applied tubing loads,
either tensile or compressive. Before setting the packer, the
test fixture was tested at temperature to ensure pressure
integrity. A pump-out plug was used to set the packer, and this
was expended after the packer was tested. The packer
operating envelope was traced with differential pressures of
8,500 psi. The tensile axial load was limited to 120,000 lbf due
to the rating of the PBR shear ring. The compressive axial
load was 200,000 lbf. This envelope covered all the pertinent
Skua load cases. The temperature was reduced to 120F and
tested with pressure below and tensile axial load. The
temperature was increased to 325 F, and the test was repeated
with pressure below and the tensile axial load. A surface
readout provided data points of pressure, axial load, stroke
and temperature.
At 325F, an overpull with the hydraulic jack, sheared the
PBR shear ring and allow the seals to travel in the PBR
seal bore.
Thermal dynamic tests were performed by stroking the
seals 4-ft up and down the seal bore at constant differential
pressures of 4,500 psi. The tests were performed both at 325
F and 125 F and pressure tested to 8,500 psi at the end of each
stroke. The stroke test was repeated 6 times before cooling the
test fixture down to ambient temperature. The casing and
packer/PBR system were removed from the deep-well
simulator and laid horizontally. The test fixtures were
removed (cut) with the slick joint, leaving only the
packer/PBR assembly inside the 9 7/8-in. casing. The casing
was cut for access, leaving only the casing around the packer.
In the final test, the TCP assembly was made up to the
bottom of the 3-in. pup joint below the packer, the assembly
was pulled through the packer to ensure that no hang up
points/shoulders would prevent the TCP guns from traveling
through the packer. This operation was repeated in
both directions.
After the tests were completed, the casing was milled and
split to provide access to the packer/PBR for inspection. All
the components were inspected and found to be within
tolerance with no damage to any of the seals or elements.
Completion Installation
Specifically selected 9-7/8-in. casing was inspected and used
at the packer setting depth. Prior to running the completion, a
scraping operation to clean the casing was performed and an
ultrasonic inspection log run. After the casing and liner were
run and cemented, the well was inflow and pressure tested
with inhibited fresh water.
The completion was run, spaced out, and the hanger was
landed. A slickline plug was set in the nipple below packer,
and the tubing pressure was tested to 5000 psi to set the
packer. After the plug was retrieved, the packer was tested
from above and below. Tubing hanger plugs were set, and the
BOP stack retrieved. The Xmas tree was run and tested, and
the tubing-hanger plug was retrieved. The TCP gun firing head
was deployed on slickline, and a 500-psi underbalance was set
to perforate the well with time delay initiation. The well was
cleaned up and performance evaluated. The completion was
run without incident and successfully commissioned.
Conclusions
From the success of this installation, the following conclusions
have been made:
1. An alternative cost-efficient and safe method for
successfully completing and perforating long horizontal
sections underbalanced has been qualified and field proven.
2. The method optimizes the completion design and allows
completions to be carried out in a single trip for both standard
and HP/HT applications. Low-pressure systems are also being
used for the Penguin project, another subsea development
consisting of 4 wells with an average bottomhole pressure of
7,200 psi. These systems are also utilising permanent
packer/PBR configurations (rated for 6,000 psi) that are
similar to those used in the Skua well.
3. The extensive development and test program for the Skua
well conditions contributed to the successful installation of the
hydraulic-set TCP packer.
4. The use of a PBR in a near HP/HT well can offer the
benefits of a static seal during the life of the well operations as
well as the flexibility of a dynamic seal for contingencies
or workovers.
5. Provides additional Risk mitigation measures when running
long TCP assemblies.
Acknowledgements
The authors wish to thank Shell U.K. Exploration and
Production and Esso Exploration and Production UK Ltd, and
Halliburton Energy Services, Inc., for their encouragement and
permission to publish this paper. The authors also wish to
acknowledge the Skua well project team and associated
service companies for their contribution to the successful
delivery of the Skua well.
References
1.
2.
3.
4.
SPE 78313
Skagerrak
11735TVD, 12500 MD
2000 ft
9350 psi
307 F
41.8 API
2940 psi
815 scf/stb
0.93 mol %
<5 ppm
250000 mg/l
Mungo
Aberdeen
Monan
Marnock
Mirren
Skua
Egret
Scoter
Heron
Machar
Shearwater
Elgin
Franklin
Puffin
Erskine
SPE 78313
Sandface Completion
open hole
screens
completion isolation valve
sandface packer
production packer
CT perforate
cemented liner
permanent packer
CT perforate
SPE 78313
SPE 78313
320ft
9 7/8" Casing
Electrical PDHG
11410ft
4.437" AO F Nipple
11467ft
11497ft
PBR (Latched)
11510ft
2.562" AO F Nipple
11602ft
11617ft
11700ft
16088ft =TD
2,000 ft of 2 7/8" Oriented Guns
Bottom Shot Ca. 15591ft
10
Seal Assembly
Packer
CN05832
to TCP Guns
SPE 78313
SPE 78313
300000
PRESSURE (psi)
Above
11
Below
Tensile
200000
D
-8000
0
-6000
-4000
-2000
2000
4000
6000
-100000
Compression
-10000
FORCE (lbs)
100000
-200000
-300000
Fig. 6 Test design stress envelope determined from modeling and analysis
8000
10000
12
SPE 78313
3337
Packer