SA JER PI 801 GCCC 59 0035 Custody Metering System Rev.03
SA JER PI 801 GCCC 59 0035 Custody Metering System Rev.03
SA JER PI 801 GCCC 59 0035 Custody Metering System Rev.03
(GCC)
XX
JUBAIL EXPORT REFINERY PACKAGE 8 3000235451
DOCUMENT NO.
PIPELINES and OFFPLOT FACILITY
SA-JER-PI-801-GCCC-59-0035
SATORP
SAUDI ARAMCO TOTAL REFINING & PETROCHEMICAL COMPANY
REQUISITION
CUSTODY METERING SYSTEM
Page 1 of 17
PROJECT:
JUBAIL EXPORT REFINERY PACKAGE 8
PIPELINES AND OFFPLOT FACILITY
DOCUMENT TITLE:
1.0 REVISIONS
Revision 01
L/I: 001 Corrected. Previously Reviewed Under (JER-35451-LET-PINP-
GCCC-2010-000298
Package Scope Corrected.
Inspection Level Specified.
2. Issued for Review / Acceptance
Revision 02
1. Delete L/I: 002 (Turbine Type)
Update Specification Sheet No. SA-JER-
P1801-GCCC-64-2113 & SA-JER-P1801-
GCCC-64-2202
Add New Specification Sheet No. SA-JER-
2. P1801-GCCC-64-2376 & SA-JER-P1801-
GCCC-64-2415
Update P&ID No. SA-JER-PI-801-GCCC-
3.
48-1027 & SA-JER-PI-801-GCCC-48-1028
4. Delete L/I: 1.03
5. Issued for Review / Acceptance
Revision 03
Update FSD No. SA-JER-P1801-GCCC-64-2113 &
1. SA-JER-P1801-GCCC-64-2415 as Per SATORP
Comments
2. Add JERES-J-503
3. Issued for Review / Acceptance
Page 2 of 17
PROJECT:
JUBAIL EXPORT REFINERY PACKAGE 8
PIPELINES AND OFFPLOT FACILITY
DOCUMENT TITLE:
Table of Contents
1.0 REVISIONS..........................................................................................................................................2
Page 3 of 17
PROJECT:
JUBAIL EXPORT REFINERY PACKAGE 8
PIPELINES AND OFFPLOT FACILITY
DOCUMENT TITLE:
All items not specifically mentioned in this specification, but necessary and required to form
an operational system as described herein, shall be identified and provided by the Vendor
as part of the system.
Any errors or omissions in this specification shall not absolve the Vendor from the
responsibility of designing and providing complete and fully functional equipment as
described in this requisition.
Page 4 of 17
PROJECT:
JUBAIL EXPORT REFINERY PACKAGE 8
PIPELINES AND OFFPLOT FACILITY
DOCUMENT TITLE:
Page 5 of 17
PROJECT:
JUBAIL EXPORT REFINERY PACKAGE 8
PIPELINES AND OFFPLOT FACILITY
DOCUMENT TITLE:
Line DESCRIPTION
Item
JER ENGINEERING STANDARD:
JERES -M-001
JERES -N-001
001 JERES -P-100
JERES -P-104
JERES -P-111
JERES -P-123
JERES -W-011
JERES -Y-103
JERES -Z- 001
JER MATERIAL SPECIFICATIONS:
JERMS-H-9080
JERMS –J-4118
JERMS -J-4119
JERMS –J-4120
JERMS -J-4511
JERMS -J-4517
JERMS -J-4525
JERMS -J-4611
JERMS -J-4711
JERMS -J-4718
JERMS -J-4820
JERMS -J-4821
JERMS -J-4830
JERMS -J-4831
JERMS -J-4913
JERMS -L-1010
JERMS -L-1017
JERMS -L-1038
JERMS -L-2005
JERMS -L-2011
JERMS -L-4001
JERMS -L-4035
JERMS -L-4041
JERMS -L-4042
JERMS -L-4048
JERMS -L-4051
JERMS -M-2007
JERMS -P-7503
JERMS -P-7515
JER STANDARD DRAWINGS:
JERSD-J-0002
JERSD-J-0073
JERSD-J-0048
JERSD-J-0049
JERSD-J-0050
JERSD-J-0080
JERSD-M-0015
JERSD-Y-0001
Page 6 of 17
PROJECT:
JUBAIL EXPORT REFINERY PACKAGE 8
PIPELINES AND OFFPLOT FACILITY
DOCUMENT TITLE:
Line DESCRIPTION
Item
JER INSPECTION AND TESTING:
JERITP-A-000003
JERITP-H-091300
001 JERITP-H-091900
JERITP-J-340100
JERITP-J-340200
JERITP-J-341000
JERITP-J-341900
JERITP-J- 342800
JERITP-J-342900
JERITP-J-343100
JERITP-J-344000
JERITP-J-347600
JERITP-L-010700
JERITP-L-013100
JERITP-L-022501
JERITP-L-026100
JERITP-L-043000
JERITP-L-043600
JERITP-M-120100
JERITP-P-170200
JERITP-P-173700
Page 7 of 17
PROJECT:
JUBAIL EXPORT REFINERY PACKAGE 8
PIPELINES AND OFFPLOT FACILITY
DOCUMENT TITLE:
Any design changes recommended by the manufacturer, which will affect this
Requisition and/or Specifications, drawings, etc., shall be brought to the buyer’s
attention for buyer’s written approval before proceeding with the work.
3.2 Marking
3.3 Interpretation
In any instance where the name of a particular manufacturer appears herein, such
shall be interpreted to mean the product of that manufacturer or its equivalent
(unless purchase of a particular manufacturer’s product is shown as mandatory).
3.4 Packing
Vendor shall pack material to ensure environmental and transit protection of the
equipment and shall submit packing design and packing details for buyer’s approval.
The shipping marks are as follows:
Page 8 of 17
PROJECT:
JUBAIL EXPORT REFINERY PACKAGE 8
PIPELINES AND OFFPLOT FACILITY
DOCUMENT TITLE:
Vendor shall provide shipping weights and volume per each equipment.
3.6 Tagging
Vendor shall provide and install stainless steel tags with all referenced engineering
tag numbers in accordance with the required attachments.
In case of any conflict between the requirements of this document and the attached
specification or data sheet or deviations from the relevant SATORP Standard, the
conflict, deviation or exception shall be brought to the attention of the buyer for
resolution. Vendor shall provide listing of the exceptions, deviations or conflicts to
all Standards referred herein. Listing is to refer to number, name and section of the
standard to which reference is made. If no exceptions, conflicts or deviations to a
Standard, the Vendor is to state the same.
Vendor shall provide a point by point compliance to the applicable SATORP Material
specifications (JERMS). Any deviations and/or exceptions should be noted in the
point by point submission.
Any exclusions I exceptions are not indicated in the proposal it will be understood
the proposal is in full agreement with the specification
3.9 Inconsistencies
Page 9 of 17
PROJECT:
JUBAIL EXPORT REFINERY PACKAGE 8
PIPELINES AND OFFPLOT FACILITY
DOCUMENT TITLE:
“Vendor and GCC (Gulf Consolidated Contractors Co. Ltd.) understand that GCC
(Gulf Consolidated Contractors Co. Ltd.) is contracting with Seller for the purchase of
goods hereunder for ultimate transfer to, and use by, the Saudi Aramco TOTAL
Refining & Petrochemical Company (SATORP) in Saudi Arabia. Therefore, Seller
agrees that, in any event, all rights of GCC (Gulf Consolidated Contractors Co. Ltd.)
for any failure to meet specifications, or any other breach of warranty, shall run to the
benefit of and be fully enforceable by SATORP.
Vendor shall consider the Environmental Conditions at the site(s) as per SATORP
Standard JERES-A-112.
Page 10 of 17
PROJECT:
JUBAIL EXPORT REFINERY PACKAGE 8
PIPELINES AND OFFPLOT FACILITY
DOCUMENT TITLE:
Special Tools required for the Erection of the Equipment or Materials shall be
included in the scope of supply.
Vendor shall quote separately for vendor representation in event it is required during
Erection.
3.18 Reporting
Progress Reporting shall be on a bi weekly basis starting one week from the date of
issue of the Requisition until fulfillment by the Vendor of all its duties and obligations
under the Purchase Order.
3.19 Alternatives
Page 11 of 17
PROJECT:
JUBAIL EXPORT REFINERY PACKAGE 8
PIPELINES AND OFFPLOT FACILITY
DOCUMENT TITLE:
4.1 Language
4.3 Identification
All drawings, literatures, data sheets, certifications, etc., supplied by vendor shall
show the following information:
(a) SATORP Requisition No.: SA-JER-PI-801-GCCC-59-0035
(b) Purchaser Line Item Nº: 001
(c) Purchaser Plant Nº: 801
(d) Vendor’s Order Nº:
(e) Vendor’s name and address:
(f) Vendor’s Drawing Number:
(g) NRM Number:
Page 12 of 17
PROJECT:
JUBAIL EXPORT REFINERY PACKAGE 8
PIPELINES AND OFFPLOT FACILITY
DOCUMENT TITLE:
ISSUE
DOCUMENT SHT. REV. TITLE
DATE
SA-JER-PI-801-GCCC-59-0035 1~17 03 06/2010 Requisition (This document)
Page 13 of 17
PROJECT:
JUBAIL EXPORT REFINERY PACKAGE 8
PIPELINES AND OFFPLOT FACILITY
DOCUMENT TITLE:
ISSUE
DOCUMENT SHT. REV. TITLE
DATE
JERES-A-112 1 ~ 12 3 1/29/2009 Meteorological and Seismic Design Data
JERES-B-019 1 ~ 11 1 9/15/2008 Portable, Mobile and Special Fixed Firefighting
Access, Egress and Materials Handling for Plant
JERES-B-054 1 ~ 17 2 4/14/2009
Facilities
JERES-B-055 1 ~ 41 3 3/5/2009 Plant Layout
JERES-B-058 1 ~ 14 1 12/20/2008 Emergency Shutdown, Isolation & Depressuring
JERES-B-067 1 ~ 14 1 4/15/2009 Safety Identification and Safety Colors
JERES-B-068 1 ~ 66 1 10/22/2008 Determination of Explosion Hazard Zones 0,1,2
JERES-H-001 1 ~ 93 5 5/22/2009 Coating Selection & Application Requirements
JERES-H-102 1 ~ 12 1 2/3/2009 Safety Requirements for Coating Applications
JERES-J-002 1 ~ 76 5 5/22/2009 Regulated Vendors List for Instruments
JERES-J-003 1~8 0 4/28/2008 Instrumentation – Basic Design Criteria
JERES-J-200 1~11 0 4/29/2008 Pressure
JERES-J-400 1~17 1 5/07/2009 Temperature
JERES-J-503 1~123 1 09/15/2008 Process connection for Instruments & Analyzers
JERES-J-902 1 ~ 28 2 10/2/2008 Electrical Systems for Instrumentation
JERES-L-105 1 ~ 403 5 5/20/2009 Piping Material Specification
JERES-L-108 1 ~ 36 5 5/15/2009 Selection of Valves
Structural Design Criteria For non-Building
JERES-M-001 1 ~ 41 3 5/12/2009
Structure
JERES-N-001 1 ~ 22 3 2/10/2009 Basic Criteria for Industrial Insulation
JERES-P-100 1 ~ 53 4 4/21/2009 Basic Power System Design Criteria
JERES-P-104 1 ~ 32 3 4/21/2009 Wiring Methods and Materials
JERES-P-111 1 ~ 42 1 1/27/2009 Grounding
JERES-P-123 1 ~ 14 0 4/28/2009 Lighting
JERES-W-011 1 ~ 51 4 2/10/2009 Welding Requirements for On-Plot Piping
JERES-Y-103 1 ~ 136 2 9/26/2008 Royalty / Custody Metering of Hydrocarbon Liquid
JERES-Z-001 1 ~ 32 1 10/27/2008 Process Control Systems
Page 14 of 17
PROJECT:
JUBAIL EXPORT REFINERY PACKAGE 8
PIPELINES AND OFFPLOT FACILITY
DOCUMENT TITLE:
ISSUE
DOCUMENT SHT. REV. TITLE
DATE
JERMS-J-4517 1 ~ 14 0 4/28/2008 Density Meters
Automatic Sampling Systems for Crude Oil and
JERMS-J-4525 1 ~ 29 1 9/30/2008 Refined Products
Safety Relief Valves Conventional and Balanced
JERMS-J-4611 1 ~ 11 0 4/29/2008 Types
JERMS-J-4711 1 ~ 19 2 4/16/2009 Control Valve
JERMS-J-4718 1 ~ 15 0 4/29/2008 Electric Motor Operated Valve Actuators
JERMS-J-4820 1 ~ 23 0 4/29/2008 Instrument Control Cabinets- Indoor
JERMS-J-4821 1 ~ 11 0 4/29/2008 Instrument Control Cabinets- Outdoor
JERMS-J-4830 1 ~ 20 1 9/24/2008 Programmable Logic Controller
JERMS-J-4831 1 ~ 30 2 9/24/2008 Instrumentation for Packaged Units
JERMS-J-4913 1 ~ 14 2 2/2/2009 Instrumentation and Thermocouple Cable
JERMS-L-1010 1 ~ 15 0 4/28/2008 Fabricated Carbon Steel Piping
JERMS-L-1017 1 ~ 15 1 5/20/2008 Auxiliary Pipeline for Mechanical Equipment
JERMS-L-1038 1 ~ 10 0 4/28/2008 Small Direct Charge Purchases of Pipe
JERMS-L-2005 1 ~ 16 0 4/28/2008 Butt Welding Pipe Fittings
JERMS-L-2011 1 ~ 27 2 10/31/2008 Forged Steel Weld Neck Flanges
JERMS-L-4001 1 ~ 16 1 5/20/2008 Gate Valves
JERMS-L-4035 1 ~ 18 2 10/31/2008 General Requirements for Valves
JERMS-L-4041 1~9 1 5/20/2008 Expanding Plug Valve
JERMS-L-4042 1~8 0 4/28/2008 4-Way Diverter Valve
JERMS-L-4048 1 ~ 11 0 4/28/2008 Valve Inspection and Testing Requirements
JERMS-L-4051 1 ~ 12 1 5/20/2008 Ball Valves, API SPEC 6D
JERMS-M-2007 1 ~ 30 3 5/12/2009 Fabrication of Structural and Miscellaneous Steel
Severe Duty, Totally Enclosed Squirrel Cage
JERMS-P-7503 1~2 1 11/5/2008 Induction Motors to 500 HP
Auxiliary Electrical Systems for Skid-Mounted
JERMS-P-7515 1 ~ 26 0 4/28/2008 Equipment
Page 15 of 17
PROJECT:
JUBAIL EXPORT REFINERY PACKAGE 8
PIPELINES AND OFFPLOT FACILITY
DOCUMENT TITLE:
ISSUE
DOCUMENT SHT. REV. TITLE
DATE
SA-JER-P1801-GCCC-64-2113 1-65 00 05/2010 Specification for Benzene Product Line
SA-JER-P1801-GCCC-64-2202 1-65 00 05/2010 Specification for Propylene Product Line
SA-JER-P1801-GCCC-64-2415 1-60 00 05/2010 Specification for Liquid Sulphur Product Line
Failure to submit the documents listed below shall cause the supply to be considered
unfulfilled.
Page 16 of 17
PROJECT:
JUBAIL EXPORT REFINERY PACKAGE 8
PIPELINES AND OFFPLOT FACILITY
DOCUMENT TITLE:
All documents, even if preliminary, shall be stamped and signed by the supplier and show
SATORP Requisition number.
6.1 Non Material Requirements (Attached NRM-7907, 7918, 7919, 7923, 7925, 7927. 7930)
Vendor should submit NMR to GCC for verification and approval. SATORP should
approve any modification.
Vendor shall meet the Technical & Quality Requirements of the Work.
Vendors Quality System shall meet the appropriate ISO 9000 system requirements; The
Vendor shall be evaluated, approved and listed as accepted supplier by GCC and
SATORP prior to placing the purchase order.
Vendor shall prepare a Quality Control Plan for Review and Approval according to the
requirements of the Requisition, and Particularly SATORP JERITP FORMS.
Note: The ITP is required to be submitted by vendor along with the bid submission.
Page 17 of 17