Power Data Planning Commission

Download as pdf or txt
Download as pdf or txt
You are on page 1of 480

lR;eso t;rs

Report of
The Working Group on Power
for Eleventh Plan (2007-12)
Volume - II
Main Report

Government of India
Ministry of Power
New Delhi
February 2007
Working Group
on Power
for
Eleventh Plan (2007-12)

Volume – II
Main Report
Contents Working Group on Power for 11th Plan

CONTENTS

CHAPTER DESCRIPTION PAGE NO.


PREFACE
INTRODUCTION
EXECUTIVE SUMMARY 1 - 69
DEMAND FOR POWER AND GENERATION 1 - 93
Chapter 1
PLANNING
1.1 10th Plan Review
1.2 Target Capacity Addition during Tenth Plan
1.3 Actual Capacity Addition and Power Supply
Position during 10th Plan (Till date)
1.4 Actual/ Likely Capacity Addition during Tenth
Plan
1.5 Likely Installed Capacity at the end of 10th
Plan i.e. as on 31.03.2007
1.6 Demand for Power
1.7 Approach to Selection of Projects for 11th Plan
1.8 Generation Planning Norms
1.9 Generation Expansion Planning
1.10 Twelfth Plan Perspective (2012-2017)
1.11 Medium Term Plan: 11th Plan (2007-12)
1.12 Long Term Plan: 12th Plan (2012-17)
1.13 New Initiatives
1.14 Captive Power Plants
1.15 Maximising Generation from Existing Plants
and AGS&P
1.16 Energy Efficiency Improvement through
Energy Audit
1.17 Accelerated Generation & Supply Programme
(AGS&P) Scheme
1.18 Non Conventional Energy Sources
1.19 Issues to be Addressed and Strategy to be
adopted for 11th Plan
1.20 Recommendation of the Group
Appendix-1.1: Summary of Capacity Addition
Target of 41,110 MW during 10th Plan
(Region Wise, Sector Wise and Status Wise)
Appendix-1.2 List of Projects Commissioned
th
during 10 Plan upto 31.12.2006
Appendix-1.3 List of Units dropped from 10th Plan
(41110 MW)
Appendix-1.4 List of the Thermal Projects slipping
from 10th Plan (41,110 MW) and included in 11th
Plan (As per 30,641 MW)

Page 1 of Contents
Contents Working Group on Power for 11th Plan

CHAPTER DESCRIPTION PAGE NO.


Appendix-1.5 List of the Hydro Projects slipping
from 10th Plan (41,110 MW) and included in 11th
Plan (As per 30,641 MW)
Appendix-1.6 Details of Best Effort Projects
Appendix-1.7 List of Projects Likely to slip to 11th
Plan
Appendix-1.8 Capacity Addition programme for
11th Plan
Appendix-1.9 Year wise coal requirement for 11th
Plan
Appendix-1.10 Shelf of 12th Plan projects
Appendix 1.11 Comparative Performance of
Partnership in Excellence (PIE) Stations with
NTPC as PIE Partner
Appendix 1.12 State Wise List of Hydro RM&U
Projects Completed in the 10th Plan
Appendix 1.13 State Wise List of ongoing Hydro
RM&U Projects Programmed For Completion In
the 10th Plan
Appendix 1.14 State Wise List of ongoing Hydro
RM&U Projects Programmed for Completion in the
11th Plan
Appendix 1.15 State Wise List of Hydro RM&U
Projects Programmed for Completion in the 11th
Plan but works of which are yet to be taken up for
Implementation

TRANSMISSION PLANNING AND NATIONAL 1 - 66


Chapter 2
GRID
2.1 Review of Transmission System during 10th
Plan
2.2 National Grid
2.3 Eleventh Plan Programme
2.4 Technology Development
2.5 Transmission Requirements for Open Access
and Trading
2.6 Power Exchange with Neighbouring Countries
2.7 Reliability Issues and Grid Operation
2.8 Fund Requirement during 11th Plan for
Transmission System Development and
Related Schemes
Appendix-2.1: HVDC Transmission Bipole, Back-
to-back and Monopole lines and terminal station –
Existing at the end of 9th Plan and programme for
10th Plan 2002-07
Appendix-2.2: Transmission lines and sub-station
at 765kV – Existing at the end of 9th Plan and
programme for 10th Plan 2002-07

Page 2 of Contents
Contents Working Group on Power for 11th Plan

CHAPTER DESCRIPTION PAGE NO.


Appendix 2.3 List of major transmission schemes
completed and programmed under the
development plan of the Regional Grids and
National Grid during the 10th Plan-Northern Region
Appendix 2.4 List of major transmission schemes
completed and programmed under the
development plan of the Regional Grids and
National Grid during the 10th Plan-Western Region
Appendix 2.5 List of major transmission schemes
completed and programmed under the
development plan of the Regional Grids and
National Grid during the 10th Plan-Southern Region
Appendix 2.6 List of major transmission schemes
completed and programmed under the
development plan of the Regional Grids and
National Grid during the 10th Plan-Eastern Region
Appendix 2.7 List of major transmission schemes
completed and programmed under the
development plan of the Regional Grids and
National Grid during the 10th Plan-Inter-Regional
Appendix-2.8: Inter-State Transmission Schemes
For The 11th Plan
Appendix- 2.9: States’ Transmission Schemes for
the 11th Plan Evacuation System for Generation
Projects
Appendix-2.10 State-Wise Details of Normative
Assessment

DISTRIBUTION INCLUDING VILLAGE AND 1 - 57


Chapter 3
HOUSHOLD ELECTRIFICATION
3.0 Overview
3.1 Key Issues in Electricity Distribution Sector
3.2 Distribution Reforms
3.3 New Legal and Policy Framework
3.4 Policy Initiatives
3.5 Distribution of Power in Urban Areas
3.6 Achievements Under APDRP
3.7 Distribution of Power in Rural Areas -
Initiatives in 10th Plan
3.8 Development of Revenue Sustainability -
Franchisees
3.9 Role of Panchayati Raj in Franchisee
Development
3.10 Power Distribution in Rural Areas Through
DDG
3.11 Short Term Strategies for DDG Schemes
3.12 Medium Term and Long Term Strategies
3.13 Cost to Serve/ Delivered Cost

Page 3 of Contents
Contents Working Group on Power for 11th Plan

CHAPTER DESCRIPTION PAGE NO.


3.14 Role of Stakeholders
3.15 Role of REC
3.16 Institutional and Financial Models
3.17 Special Focus Areas for 11th Plan
3.18 New Programmes/Schemes for 11th Plan
3.19 Agriculture Sector - Subsidies and Cross
Subsidies
3.20 Water Energy Nexus
3.21 Open Access in Distribution
3.22 Multi-Year Tariff
3.23 Public Private Partnership
3.24 Impact of Power Sector Reforms – Success
Stories
3.25 Best Practices
3.26 Requirement of Funds
3.27 Recommendations
DEMAND SIDE MANAGEMENT AND ENERGY 1 - 14
Chapter 4
EFFICIENCY
4.0 Introduction
4.1 The Energy Conservation Act
4.2 Energy Saving –Target and Achievement of
10th Plan
4.3 Energy Conservation Strategy in the 11th Five-
Year Plan
4.4 Policy Research for Accelerating Adoption of
Energy Efficiency and DSM Programs
4.5 Budget Outlay for the 11th Plan
4.6 Recommendations
Chapter 5 RESEARCH & DEVELOPMENT 1 - 21
5.0 Introduction
5.1 Overview of R&D
5.2 Technology Development in Power Sector
5.3 Identified Projects for 11th Plan by Central
Utilities
5.4 R&D Project Provisions and Test Facilities for
CPRI
5.5 Major Project Proposals for 11th Five Year
Plan
5.6 Short Listed Short Term & Long Term
Projects
5.7 R&D Funding
5.8 Intellectual Property Rights
5.9 Human Resource Development and
Technical Competence Building
DEVELOPMENT OF POWER SECTOR IN 1 - 11
Chapter 6
NORTH-EASTERN REGION
6.0 Introduction

Page 4 of Contents
Contents Working Group on Power for 11th Plan

CHAPTER DESCRIPTION PAGE NO.


6.1 Status at the beginning of 10th Plan
6.2 Review of Generation Capacity Addition
Programme during 10th Plan
6.3 Reasons for Slow Pace of Project Execution
6.4 Power Demand & Supply Analysis of the
Region
6.5 Generating Capacity Addition Programme in
North Eastern Region/ Sikkim during 11th
Plan
6.6 Development of Transmission System in
North Eastern Region
6.7 Evacuation of Power from Major Generation
Projects in the North-Eastern Region along
with Power from Projects coming up in
Sikkim and Bhutan during the 11th Plan and
early 12th Plan Period
6.8 Special Attention for Distribution in NE
Region
6.9 Fund Requirement
6.10 Policy Initiatives and Recommendations

Chapter 7 HUMAN RESOURCE DEVELOPMENT 1 - 25


7.0 Back Ground
7.1 Elements of HRD Planning
7.2 Assessment of Manpower
7.3 Training
7.4 Funding & Capital Outlay
Appendix 7.1: Training Load during 11th Plan for
Technical Manpower (Includes Infrastructure) in
Thousand-Man-Months (TMM)
Appendix 7.2: Training Load during 11th Plan for
Non-Technical Manpower (Includes Infrastructure)
in Thousand-Man-Months
Appendix 7.3: Training Load (Induction) during
12th Plan for Technical Manpower (Includes
Infrastructure) in Thousand-Man-Months
Appendix 7.4: Training Load (Induction) during
12th Plan for Non-Technical Manpower (Includes
Infrastructure) in Thousand-man-months
Chapter 8 LEGISLATIVE AND POLICY ISSUES 1 - 41
8.0 Back Ground
8.1 Implementation of Provisions of Act and
Policies
8.2 Status of Implementation and Deviations of
Integrated Energy Policy
8.3 National Electricity Policy - Deviations and
Status of Implementation
8.4 Major Issues and Recommendations

Page 5 of Contents
Contents Working Group on Power for 11th Plan

CHAPTER DESCRIPTION PAGE NO.


8.5 Summary of Recommendations
Appendix 8.1: Fund Requirement for Training of
Electricity Regulators and Staff
Appendix 8.2: Comments of Prayas Energy Group
Appendix 8.3: Comments of IIT Kanpur
Chapter 9 KEY INPUTS 1 - 49
9.1 Introduction
9.2 Coal & Lignite
9.3 Transportation of Coal: Available Infrastructure
9.4 Natural Gas
9.5 Key Input Materials
9.6 Generation Expansion Plan
9.7 Material Requirements for Generating Stations
9.8 Material Requirement for Power Transmission
System Network
9.9 Material Requirement for Distribution System
Network
9.10 Material Requirement for Power and
Distribution Transformers
9.11 Other Materials for 11th & 12th Plan Projects
9.12 Total Requirement of Various Materials for
Capacity Addition Planned during 11th & 12th
Plans
9.13 Availability / Supply of Key Materials
9.14 Constraints / Policy Support Required
9.15 Availability / Capability of Manufacturers
9.16 Construction Capability
9.17 Availability/Capability of Construction
Agencies
9.18 Availability of Construction Equipment
9.19 Special Measures for Thermal Projects
9.20 Recommendations
Appendix 9.1: Port wise Projected Traffic and
Capacity Estimation (2013-14)
Appendix 9.2: List of Construction Equipments to
be Augmented for Hydro Projects
Appendix 9.3: Construction Equipment
Availability vis a vis Augmentation required for
adding 14000 MW / per yr.
FINANCIAL ISSUES AND POWER SECTOR 1 - 46
Chapter 10
FINANCING
10.1 Financial Performance of Power Sector
during 10th Plan
10.2 Fund Requirement for 11th Plan
10.3 Renovation and Modernization of Power
Plants
10.4 Transmission Network

Page 6 of Contents
Contents Working Group on Power for 11th Plan

CHAPTER DESCRIPTION PAGE NO.


10.5 Distribution and Rural Electrification
10.6 Human Resource Development
10.7 Research and Technology Development
10.8 Demand Side Management
10.9 11th Plan Estimated Fund Requirement
10.10 Year Wise Fund Requirement
10.11 Sources of Funds
10.12 Estimated Funds Mobilization
10.13 Lenders’ Issues
10.14 Developers’ Concerns
10.15 Recommendations & Implementation
Strategy
10.16 Implementation Mechanisms
Appendix 10.1: Detailed Outlay and Achievement
for Funding 10th Plan - State Sector
Appendix 10.2: Approved Tenth Plan Outlay
Internal and Extra Budgetary Resources Gross
Budgetary Support
Appendix 10.3: Assumptions for Estimation of
Cost of Generation Projects
Appendix 10.4: Projects Under Construction
Appendix 10.5: Committed Projects
Appendix 10.6: Projects to be taken up in 11th
Plan for Likely Benefit in 12th Plan
ACRONYMS

Page 7 of Contents
INTRODUCTION

The Working Group on Power was constituted by the Planning Commission vide
its Office Order No.I-15/1/2005-P&E dated 20th April 2006 (copy enclosed at Appendix-
A) to formulate the power programme for 11th Plan. Secretary (Power) was the
Chairman of the Working Group and Member (Planning), CEA was the Member
Secretary of the Working Group. The Composition and Terms of Reference of the
Working Group for Eleventh Plan are given in Appendix-A.

The first meeting of the Working Group was held on 19th May 2006 under the
Chairmanship of Secretary (Power). It was decided to constitute 8 specialized Sub-
Groups to go into the specific areas to cover comprehensively all the Terms of
Reference of the Working Group. Subsequently, review meetings of the Working Group
were held in MoP on a regular basis to assess the progress of the Sub-Groups from time
to time. During the discussions, it emerged that it was essential to have a separate Sub-
Group on “Human Resource Development” and accordingly Sub Group 9 was
constituted. Details of the various Sub Groups are enclosed in Appendix- B

The Sub-Groups discussed various issues regarding Demand, Generation,


Transmission & Distribution Expansion Planning, Households & Rural Electrification,
Demand Side Management & Energy Efficiency Issues, Research & Development,
Manpower Planning & Training and Fund Requirement. A separate chapter has also
been included on development of North Eastern Region as well as Policy Issues. A
review of and measures for implementation of National Electricity Policy and Integrated
Energy Policy have also been included in the Report.

The report is based on 10th Plan likely capacity addition of 30,641 MW


corresponding to which the 11th Plan capacity addition is 68,869 MW and 12th Plan
capacity addition is 82,000 MW. Subsequent to the finalization of the Report, CEA had
reviewed the likely capacity addition during the 10th Plan. This is now expected to be
around 23,250 MW. The balance 10th Plan capacity would slip to 11th Plan in addition to
68,869 MW planned for 11th Plan. These changes have, however not been effected in
the body of the Report.

Various Sub-Groups submitted their Reports to the main Working Group. Based
on the recommendations of these Sub-Groups the Report of the Working Group for 11th
Plan has been formulated. It is in 2 Volumes- Volume I containing the Executive
Summary of the Report and Volume II containing the main Chapters of the Report. The
Executive Summary has also been made part of Volume II for the sake of completeness
& ease of reference.

New Delhi (V. S. VERMA)


15th Feb. 2007 Member (Planning) CEA and
Member Secretary of the
Working Group on Power
Appendix-A
No.I-15/1/2005-P&E
GOVERNMENT OF INDIA
PLANNING COMMISSION
(POWER & ENERGY DIVISION)
******
Yojana Bhawan
Sansad Marg
New Delhi— 110001.

Dated: 20th April, 2006

ORDER

Subject: Constitution of a Working Group on Power for formulation of Eleventh Five Year Plan
(2007-2012.

It has been decided to constitute a Working Group on Power in the context of preparation
of Eleventh Five Year Plan (2007-2012). The Composition and Terms of Reference of the Group
will be as follows:

A. Composition

Secretary, Ministry of Power - Chairman

Members

1. Adviser (Energy), Planning Commission


2. Chairperson, Central Electricity Authority
3. Representative of Ministry of Non-Conventional Energy Sources
4. Representative of Department of Atomic Energy
5. Representative of Ministry of Coal
6. Representative of Ministry of Petroleum & Natural Gas
7. Representative of Ministry of Environment & Forests
8. Representative of Department of Science & Technology
9. Member (Planning), Central Electricity Authority— Member Secretary

PSUs

1. CMDs, NTPC/NHPC/PGCIL/PFC/REC
2. Chairmen, GRIDCO/APTRANSCO/MSEB/MPEB/TNEB/PSEB

Private Sector Representatives

1. Representative of Reliance Energy Company


2. Representative of Tata Electric Company
3. Representative of Torrent Electric Company
OTHERS

1. Shri Girish Sant, PRAYAS


2. Shri Navroj Dubash, NIPFP
3. Prof. Anoop Singh, lIT Kanpur

B. Terms of Reference

i) To review the Integrated Energy Policy Report and suggest measures to


operationalise its recommendations during the Eleventh Plan Period.
ii) To review the status of various policies notified under the provisions of
Electricity Act, 2003 and identify steps needed to realize the objectives of the
Electricity Act, 2003.
iii) To recommend an industry structure that would enhance the number of players,
promote competition, provide a consistent & transparent pricing regime and raise
conversion, transmission, distribution & end use efficiency.
iv) To review the likely achievement during the Tenth Plan period in meeting targets
set for Generation, Transmission, Distribution and Renovation & Modernisation
R&M). An analysis of the reasons for shortfalls, if any, may be highlighted.
v) To review the current status of captive generation in the country, highlight issues
facing this sub sector and make recommendations for enhancing/reducing
captive generation during the Eleventh Plan period.
vi) To review the effectiveness of Eleventh Plan Schemes such as Accelerated
Generation & Supply Programme (AG&SP), Accelerated Power Development &
Reforms Programme (APDRP) and Rajiv Gandhi Grameen Vidyutikaran Yojana
(RGGVY). To suggest modifications and/or give recommendations for scrapping
these schemes or replacing them with alternative schemes to better address the
desired objectives.
vii) To assess the State-wise/region-wise demand for power in terms of both peak and
energy requirements.
viii) To recommend the optimal mix of additional generating capacity to be created
during the Eleventh Plan period in terms of hydro, thermal (coal, gas, lignite and
liquid fuel) and nuclear generation on the basis of relative economics of different
fuels at different locations. The executing agency of the project i.e. State Sector,
Central Sector or Private Sector should also be identified. A possible listing of the
projects and their phasing for benefits during Eleventh Plan must be prepared.
Advance action to be taken in the Eleventh Plan period for the Twelfth Plan
projects may also be identified.
ix) To assess the potential for improving availability of power from existing power
stations through Renovation & Modernisation/life extension.
x) To maximise benefit from the existing plants by improving their operational
efficiency and capacity utilization, improvement and augmentation of
Transmission and Distribution network and dealing effectively with the problem
of Aggregate Technical & Commercial (AT&C) losses and theft of power.
xi) To review the on-going reform process undertaken by States in the power sector.
xii) To assess if privatisation is an answer to address the ills of the Power Sector.
xiii) To suggest energy conservation measures through Demand Side Management
(DSM) such as staggering of load, time of the day metering and pricing,
reduction in the energy intensity of the large consumers etc.
xiv) To recommend the operational norms for thermal including Gas, Liquid fuel and
nuclear generations.
xv) To develop a work plan to tackle problems in ash disposal, pollution and other
environmental issues.
xvi) To make recommendations regarding S&T programme to be implemented in the
Eleventh Plan period and the institutional arrangements necessary therefore.
xvii) To explore avenues for purchase of power from neighbouring countries through
joint venture schemes.
xviii) To assess the investment requirement for the Eleventh Plan in the Power Sector.
xix) To assess the infra-structural support such as transportation, port facilities,
construction and manufacturing capabilities, roads etc. that would be required for
implementation of the Eleventh and Twelfth five year Plans.

2. In order to assist the Working Group in its task, separate Sub-Groups on specific aspects
may be formed by the Working Group. These Sub-Groups will furnish their reports to the
Working Group
3. The Chairman of the Working Group may co-opt experts as may be considered
necessary.
4. The Working Group will submit its report to the Planning Commission latest by
30th September, 2006
5. Non-official members shall be entitled to payment of TA/DA by the Planning
Commission as per SR 190(a). Official members will be entitled to payment of TAJDA
by their respective Departments/Organizations, as per the rules of entitlement applicable
to them.
6. The name(s) of the Representative(s) of various organizations, as per the above
composition may be communicated to the Member-Secretary of the Working Group
under intimation to Shri Surya P. Sethi, Adviser (Energy), Planning Commission.
7. Shri R.K. Kaul, Joint Adviser, Planning Commission, Room No.503, Yojana Bhavan,
New Delhi-i 10 001 (Telephone No. 2309 6718), shall be the Nodal Officer for this
Working Group and for any further query/correspondence may be made with him.

(K.K. Chhabra)
Under Secretary to the Government of India

Chairman and Members (including Member-Secretary) of the Working Group.

Copy for information to:

1. PSs to Deputy Chainman/ MOS(Planning)/ Members/ Member-Secretary, Planning


Commission.
2. All Principal Advisers/ Advisers/JS(SP&Admn.)
3. Prime Minister’s Office, South Block, New Delhi.
4. Information Officer, Yojana Bhavan.
5. For general information in Yojana Bhavan through e-mail.

(K.K. Chhabra)
Under Secretary to the Government of India
Appendix-B

WORKING GROUP ON POWER FOR 11TH FIVE


YEAR PLAN (2007-2012) – Details of Sub-Groups

SUB-GROUP 1- DEMAND PROJECTION AND GENERATION PLANNING.

Shri Rakesh Nath-Chairperson, CEA- Chairman of Sub-Group


Shri A.S. Bakshi-Chief Engineer (IRP) CEA - Member Secretary of Sub-Group

SUB-GROUP 2- TRANSMISSION PLANNING INCLUDING NATIONAL GRID

Shri V. Ramakrishna - Member (PS) CEA - Chairman of Sub-Group

Shri A.K. Asthana, Chief Engineer (SP&PA), CEA - Member Secretary of Sub-Group
Shri Jiwesh Nandan,Director (PTC & Trans), Ministry of Power - Member Secretary of Sub-
Group

SUB-GROUP 3- DISTRIBUTION INCLUDING VILLAGE & HOUSEHOLD


ELECTRIFICATION

Shri Anil Kr. Lakhina - Chairman , REC - Chairman of Sub-Group


Ms Dharitri Panda, Director (RE), Min. of Power , Member Secretary of Sub-Group

SUB-GROUP 4 - LEGISLATIVE AND POLICY ISSUES – FORMULATION,


IMPLEMENTATION & FEEDBACK

Shri Ajay Shankar Additional Secretary, Ministry of Power - Chairman of Sub-Group


Shri Alok Kumar, Director (R&R), Ministry of Power - Member Secretary of Sub-Group

SUB-GROUP 5 - DEMAND SIDE MANAGEMENT, ENERGY EFFICIENCY & ENERGY


CONSERVATION

Dr. Ajay Mathur- Director General, BEE - Chairman of Sub-Group


Shri K.K.Chakarvarti Energy Economist BEE - Member Secretary of Sub-Group

SUB-GROUP 6 - TECHNOLOGICAL ADVANCEMENT AND RESEARCH &


DEVELOPMENT

Shri A.K.Tripathi - Director General CPRI - Chairman of Sub-Group


Dr. R.R. Sonde, Executive Director (R&D) NTPC- Member Secretary of Sub-Group

SUB-GROUP 7 - ISSUES CONCERNING KEY INPUTS

Shri T. Sankarlingam - CMD NTPC - Chairman of Sub-Group


Shri S.Sheshadri-Chief Engineer (TPIA)CEA - Member Secretary of Sub-Group
SUB-GROUP 8 - FINANCIAL ISSUES

Dr. V.K.Garg - CMD, PFC - Chairman of Sub-Group


Sh. Mukul Modi,Asstt Vice President,SBI Capital Markets Limited- Member Secretary of Sub-
Group

SUB-GROUP 9 - HUMAN RESOURCE DEVELOPMENT AND CAPACITY BUILDING

Shri U.N. Panjiar, Additional Secretary, Ministry of Power - Chairman of Sub-Group,


Shri C.S.Malik , Principal Director, NPTI - Member Secretary of Sub-Group
Chief Coordinator from MoP – Shri Sudhakar Shukla, Director, MoP
th
Executive Summary Working Group on Power-11 Plan (2007-12)

EXECUTIVE SUMMARY

1.0 DEMAND PROJECTION AND GENERATION PLANNING

1.1 TENTH PLAN REVIEW

The capacity addition target of 41,110 MW comprising 14,393 MW hydro, 25,417


MW thermal and 1,300 MW nuclear was fixed for the 10th Plan. The sector wise,
type wise summary of this capacity addition target is given in Table below.

10TH PLAN CAPACITY ADDITION TARGET-SECTOR WISE


(Figures in MW)
SECTOR Hydro Thermal Nuclear Total (%)
CENTRAL 8,742 12,790 1,300 22,832 (55.5%)
STATE 4,481 6,676 0 11,157 (27.2%)
PRIVATE 1,170 5,951 0 7,121 (17.3%)
TOTAL 14,393 25,417 1,300 41,110 (100%)

A moderate target was set for state and private sectors keeping in view the
preparedness of various state power utilities and IPPs.

1.1.2 Actual Capacity Addition (till 31.12.2006)

A capacity addition of 17,995 MW has been achieved during 10th Plan till
31/12/06. The total installed capacity as on 31/12/2006 was 1,27,753 MW
comprising 33,642 MW hydro, 84,020 MW thermal including gas & diesel, 3,900
MW nuclear power plants and 6,191 MW from renewable energy sources
including wind.
(The sector– wise details of installed capacity are given in Table 1.4 in Chapter-1.)

1.1.3 Power supply position in 10th plan

The year-wise actual power supply position during 2002-03, 2003-04, 2004-05
,2005-06 and 2006-07(till Dec-06) of 10th plan is given in Table below

1
th
Executive Summary Working Group on Power-11 Plan (2007-12)

ACTUAL POWER SUPPLY POSITION (ALL INDIA BASIS)

Year Peak Energy


Requir Availab Shortage Require Availability Shortage
ement ility MW (%) ment (MU) MU (%)
(MW) (MW) (MU)
2002-03 81492 71547 9945 (12.2%) 545983 497690 48093 (8.8%)
2003-04 84574 75066 9508 (11.2%) 559264 519398 39866 (7.1%)
2004-05 87906 77652 10254 (11.7%) 591373 548115 43258 (7.3%)
2005-06 93255 81792 11463 (12.3%) 631757 578819 52938 (8.4%)
2006-07 100466 86425 14041 (14.0%) 510223 465149 45074 (8.8%)
(upto
Dec,06)

The likely achievement of capacity addition during the 10th Plan is expected to be
30,641 MW which includes 2,578 MW capacity of projects which have been
included on best effort basis. Any slippage of these best efforts projects from
10th plan would be reckoned as additional capacity in 11th plan over and above
being proposed in this document. In 8th & 9th plan, capacity addition of 16,423
MW and 19,119 MW respectively was achieved. Even though the capacity
addition target of 10th plan could not be achieved, the actual capacity addition is
expected to be much higher than the earlier five year plans. The reasons for the
slippages during the 10th plan have been analysed to learn lessons for capacity
addition planning for future plans.

During the first year of 10th plan itself it became clear that a number of projects
totalling to 3,009 MW in public and private sectors could not be taken up due to
various reasons which included non availability of escrow cover by State
Government to IPP projects and fund constraints. There was also delay in super
critical technology tie-up by BHEL for six units of 660 MW to be taken up by
NTPC which resulted in delay in tendering. Additional projects totalling to 5,008
MW capacity were identified for execution during 10th plan to make up for the
projects which could not take off. However, a total capacity of 12,516 MW
(excluding 3,009 MW projects which could not be taken up) is expected to slip to
11th Plan due to reasons mentioned against each, in the following table:

2
th
Executive Summary Working Group on Power-11 Plan (2007-12)

Sl. No Major Reasons of slippage Capacity slipped (MW)


Thermal Hydro
1. Delay in super critical technology tie up by 3960 -
BHEL
2. Geological Surprises - 510
3. Natural Calamities 450
4. Delay in award of works 998 823
5. Delay in MoE&F clearance - 400
6. Investment decision/ Funds tie up 1500 1400
constraints/ delay in financial closure
7. Delay in Preparation of DPR & signing of - 400
MOU with state govt.
8. ESCROW cover (Private Sector) 500 -
9. R&R issues - 400
10. Court Cases - 675
11. Law & Order problem 500
Total 7458 5058
(The details are given in Para 1.5 of Main Working Group Report)

It is pertinent to point out that a number of projects of 10th plan ordered on BHEL
were delayed due to delayed and non-sequential supply of equipment and
materials and inadequate manpower in commissioning teams. Some of the
projects expected to be commissioned during the last quarter of 2006-07 are also
running behind schedule due to the above reasons.

1.2 GROWTH IN ENERGY GENERATION

1.2.1 Growth in Generation During 10th Plan

The growth in generation has been 3.2%, 5.1%, 5.2% and 5.2% during 2002-03,
03-04, 04-05 and 05-06 respectively. In the year 2006-07(upto Dec-2006) a
growth rate of 7.5 % has been recorded. The Compounded Annual Growth
Rate(CAGR)of generation during the 10th Plan period is expected to be about
5.1%. However, higher growth could have been achieved if adequate gas would
have been available for the existing and new gas based plants commissioned
during 10th plan.

1.2.2 Growth in Generation during 11th Plan

As per the Integrated Energy Policy (IEP), issued by the Planning Commission,
GDP growth rates of 8%-9% have been projected during the 11th Plan. Assuming
a higher growth rate of 9% and assuming the higher elasticity projected by the
IEP of around 1.0, electrical energy generation would be required to grow at 9%
p.a. during the 11th plan period. Also generation has to be collectively met by
utilities, captive plants and Non-conventional energy sources. No reliable plans

3
th
Executive Summary Working Group on Power-11 Plan (2007-12)

about captive power capacity expansion are available but based on indications
available from the manufacturers for addition in captive capacity and present
utilization of available capacity, the generation from captive plants is expected to
increase from 78 BU to 131 BU per annum. Since the load factor of non-
conventional energy sources is very low (about 20% on an average), even
though the capacity projected by MNRE from these sources is about 23,500 MW
by the end of 11th Plan, the expected generation would be only around 41 BU.
The generation from these renewables however has not been taken into account
for planning purposes. Based on these assumptions following scenario emerges:

(i) Likely energy Generation by utilities in 2006-07 663 BU


(ii) Likely Energy Generation by captive plants in 2006-07 78 BU
(iii) Total Likely Generation in 2006-07 741 BU
(iv) Compounded Annual Growth Rate 9%
(v) Required Energy Generation by 2011-12 @ 9% growth rate over 741 BU1140 BU
(vi) Less Estimated Energy Generation by captive plants in 2011-12 131 BU
(vii) Total Estimated Generation Requirement from Utilities by 2011-12 1008 BU

However to meet the objectives of NEP to increase the per capita consumption to
1000 units by the year 2011-12, the requirement of generation works out to 1210
BU, assuming a population of 121 crores in 2011-12 as per projections of
Census 2001. After excluding the generation from captive plants (131 BU) and
that from renewables (41 BU), the requirement of generation from utilities works
out to 1038 BU. This would require a generation growth rate of 9.5% p.a
(CAGR)for utilities.

1.2.3 Growth in generation During 12th Plan

During the 12th Plan period, assuming a GDP growth rate of 9% per annum and
elasticity 0.8 as compared to 1.0 during 11th plan mainly due to adoption of
energy efficient technologies & other Energy Conservation and Demand Side
Management measures being taken up during 11th Plan, electricity demand is
likely to grow @ 7.2% p.a. Keeping this in view, the energy generation should
increase to a level of 1470 BU by 2016-17 from a level of 1038 BU in 2011-12.
However sensitivity analysis have been carried out assuming 8,9 & 10 % GDP
growth rates & GDP-electricity elasticity of 0.9 & 0.8 respectively and the same is
given in table below:

4
th
Executive Summary Working Group on Power-11 Plan (2007-12)

Generation Requirement for 2016-17


( As Per 8,9,10 % GDP Growth)

GDP GDP/ Electricity


Growth Electricity Generation
Elasticity Required
(BU)
8% 0.8 1415
0.9 1470
9% 0.8 1470
0.9 1532
10 % 0.8 1525
0.9 1597

1.3 APPROACH TO SELECTION OF PROJECTS FOR 11TH PLAN

Keeping in view the lessons learnt from 10th plan while planning for capacity
addition during 11th Plan, cautious approach have been adopted while choosing
projects for commissioning in the 11th plan. It has been the endeavour to include
only such projects as have high degree of certainty of implementation during 11th
Plan.

The approach adopted for selection of Hydro, Thermal and Nuclear projects have
been as follows:

1.3.1 Hydro

India is duly concerned about climate change and efforts are on to promote
benign sources of energy. Hydro Power is one such source and is to be
accorded priority also from the consideration of energy security. Irrespective of
size and nature of hydro projects, whether ROR or Storage projects, these are all
renewable technologies. However, execution of hydro projects requires thorough
Survey and Investigation, preparation of DPR, development of infrastructure, EIA
and other preparatory works, which are time consuming and require two to three
years for their preparation. It would take about 5 years to execute a hydro project
after the work is awarded for construction. Thus in order to achieve completion of
a hydro project during 11th plan, the project should either be already under
construction or execution should start at the beginning of the plan. The broad
criteria adopted for selection of hydro projects for 11th plan are as under:

• Those hydro projects whose concurrence has been issued by CEA and
order for main civil works is likely to be placed by March 2007.

5
th
Executive Summary Working Group on Power-11 Plan (2007-12)

• Apart from the above, a few hydro projects of smaller capacity which are
ROR type having surface power houses and where gestation period is
expected to be less than 5 years have also been included. These projects
would need to be rigorously followed up for completion during the 11th
Plan.

Keeping in view the preparedness of various hydro projects, a capacity addition


of 15, 585 MW is envisaged for 11th Plan.

(The details of projects are given in Appendix 1.8- in Chapter-1 of main Working Group Report.)

1.3.2 Nuclear

Nuclear is environmentally benign source of energy and over a period of time,


its proportion in total capacity should increase. Keeping in view the availability
of fuel, a moderate capacity addition of 3,160 MW nuclear plants has been
programmed during the 11th Plan by the Nuclear Power Corporation. All
projects are presently under construction. However, in view of the recent
developments in the Nuclear Sector, capacity addition in nuclear plants during
12th Plan is expected to be much higher.

(The details of projects are given in Appendix 1.8- in Chapter-1 of main Working Group Report.)

1.3.3 Thermal

Gas
Although gas is relatively a clean fuel, at present there is uncertainty about
the availability, period of availability and price of gas. Only 2,114 MW gas
based capacity has been planned for 11th Plan where gas supply has already
been tied up. This does not include NTPC’s gas based projects at Kawas and
Gandhar, totalling to 2,600 MW, for which NTPC says that it has the gas
supply contract but the matter is sub-judice. However more gas based
projects could be taken up for construction as and when there is more clarity
about availability and price of gas.

(The details of projects are given in Appendix 1.8- in Chapter-1 of main Working Group Report.)

Coal & Lignite based Thermal plants

Coal is expected to be main stay of power generation in the years to come.


The following criteria have been adopted for identifying the coal and lignite
based projects for inclusion in the 11th plan.

• Such projects as have already been taken up for execution in the 10th
Plan period itself and are due for commissioning in the 11th Plan period.
• Those thermal projects whose LOA has already been placed by the State
and Central Public Sector Corporations, other inputs also being in place.

6
th
Executive Summary Working Group on Power-11 Plan (2007-12)

• Those thermal projects whose LOA has already been placed and the
financial closure achieved by private developers.
• Those thermal projects whose LOA is expected to be placed by 30th Sept,
2008 and commissioning is expected during the 11th Plan keeping in view
the normal gestation period, the size of the plant & the type(green
field/expansion).

After discussion with the various State Government and Central Generating
Companies, thermal projects with total capacity of 46,635 MW of coal based and
1375 MW lignite based capacity have been identified for capacity addition during
11th plan.

(The details of projects are given in Appendix 1.8- in Chapter-1 of main Working Group Report.)

1.4 CAPACITY ADDITION DURING 11TH PLAN (2007-12)

Based on the preparedness of the projects, it was envisaged that a capacity of


about 68,869 MW is feasible for addition during 11th plan period. The sector wise
break-up of feasible capacity addition during 11th plan is given in Table below:

SECTOR HYDRO TOTAL THERMAL BREAKUP NUCLEAR TOTAL


THERMAL (%)
COAL LIGNITE GAS/LNG
CENTRAL 9685 23810 22060 1000 750 3160 36655
(53.2%)
STATE 2637 20352 19365 375 612 - 22989
(33.4%)
PRIVATE 3263 5962 5210 0 752 - 9225
(13.4%)
ALL-INDIA 15585 50124 46635 1375 2114 3160 68869
(100%)

In addition to above, thermal projects totalling to 11,545 MW have been identified


as best effort projects. These projects would normally be commissioned in the
beginning of 12th Plan but in case of any constraints in taking up of any of the
projects included in 11th plan, some of these projects would be tried for
commissioning during 11th Plan.

Further, a capacity of 13,500 MW has been planned under renewable as per


information given by MNRE.

As can be seen from the above profile of capacity addition plan, central sector
will play a lead role with capacity addition of more than half of the capacity
addition target. There has been a good response from states on the need for

7
th
Executive Summary Working Group on Power-11 Plan (2007-12)

capacity addition to meet their growing demand and the states with IPPs, have
been given target for achieving the balance capacity. The State owned capacity
projected for the 11th Plan is 33.4 % of the total plan as compared to 27% likely
during 10th Plan.

Out of feasible capacity addition of 68,869 MW, projects totalling to 31,345 MW


are already under construction and the balance projects totalling to 37,524 MW
have been committed for implementation by the concerned generating
companies during the 11th Plan. Details are furnished in the Table below:

THERMAL
TOTAL BREAKUP
SECTOR HYDRO NUCLEAR TOTAL
THERMAL
COAL LIGNITE GAS/LNG
Projects Under
11931 16254 14115 1125 1014 3160 31345
Construction
Committed
3654 33870 32520 250 1100 - 37524 *
Projects
Total 15585 50124 46635 1375 2114 3160 68869

(The details of projects are given in Appendix 1.8- in Chapter-1 of main Working Group Report.)

* Note: Out of the projects totalling to 37,524 MW under committed category as given above,
orders for Dadri Unit-6 (490 MW) & Mezia Ph-II (1000 MW) has been recently placed.

The thermal capacity addition comprises of1 unit of 800 MW, 11 units of 660
MW, 53 units of 500/600 MW class, 49 units of 210/250/300 MW class, 7 units of
110/125 MW class.

With the above capacity addition it would be possible to meet the projected
energy requirement of 1038 BU (considering peak demand of 1,51,500 MW) for
meeting per capita consumption of 1000 units at the end of 11th plan. With this
capacity addition it would be feasible to achieve a generation growth rate of 9.5%
p.a. (CAGR)

1.5 FUEL REQUIREMENT

The requirement of various fuels for the thermal plants during the terminal year of
the 11th Plan (2011-12) at normative generation parameters (PLFs and specific
fuel consumption is summarised in the table below. This is based on a thermal
capacity addition of 20,387MW and 50,124MW during the 10th and 11th Plan
respectively.

8
th
Executive Summary Working Group on Power-11 Plan (2007-12)

Fuel Requirement (Tentative) during 2011-12

Fuel Requirement (2011-12)


Coal* 545 MT
Lignite 33 MT
Gas/LNG** 89 MMSCMD

(The details of projects are given in Appendix 1.9- in Chapter-1 of main Working Group Report.)

* From domestic sources, total coal availability is expected to be 482 MT per


annum by 2011-12. Accordingly, imported coal of the order of 40MT,
equivalent to 63 MT of Indian coal, may have to be organised. This quantity
may reduce provided production of domestic coal is increased.

** 89 MMSCMD of gas requirement at 90% PLF has been projected in 2011-


12. At present, the availability of gas is of the order of 40 MMSCMD and
therefore not sufficient to meet the requirement of even existing plants.

1.6 INITIATIVES DURING 11TH PLAN

1.6.1 High Hydro Development

50,000 MW Hydro Initiative was launched in 2003 and Preliminary Feasibility


Report (PFRS) of 162 projects totalling to 48,000 MW were prepared. Out of this
77 projects with total capacity of about 37000 MW for which first year tariff is
expected to be less than Rs.2.50/unit were selected for execution. Hydro
projects have longer gestation period and therefore there is a need to formulate a
10 year plan for hydro projects. In 11th plan a capacity addition of over 15,500
MW has been targeted keeping in view the present preparedness of these
projects. Projects totalling to a capacity of 30,000 MW have been identified for
12th Plan on which necessary preparations have to be made from now onwards
to ensure their commissioning during 12th Plan. Thus the effect of 50,000 MW
initiative would be visible in 12th Plan period. Preparation of DPR and various
clearances and approval etc for these projects are to be obtained during the first
two years of 11th Plan. It is recommended that CEA should closely monitor the
progress of preparedness of DPR of these projects and their further execution.

1.6.2 Initiatives in Thermal Power Development:

Efforts were made to bring in highly efficient super critical technology in the
country for thermal power plants and execution of six super critical units of 660
MW capacity each was taken up during the 10th Plan period. The first unit of 660
MW based on super critical technology is likely to be commissioned during the

9
th
Executive Summary Working Group on Power-11 Plan (2007-12)

first year of 11th Plan i.e. 2007-08. The 11th Plan feasible capacity addition of
coal based plants includes 12 units based on super critical technology with a
capacity of 8060 MW which is about 18% of total coal capacity planned for 11th
Plan. More and more power projects based on super critical technology are
under planning stage and they would yield benefit during the 12th Plan period.
It is envisaged that more than 50-60% of capacity addition of thermal plants
during 12th plan period would be based on super critical units. This would also
help in reducing the Carbon dioxide emission from new coal fired capacity.

1.6.3 Ultra Mega Power Projects (UMPP):

Ministry of Power in the year 2006 has launched an initiative of development of


coal based ultra mega projects with a capacity of 4,000 MW each on tariff based
competitive bidding. Ultra Mega Power projects are either pit head based
projects having captive mine block or coastal projects based on imported coal.
Sasan UMPP, a pithead plant in Chattisgarh based on domestic fuel and Mundra
UMPP in Gujrat based on imported coal have already been awarded for
execution to the respective developers. According to the bids submitted by these
developers only one unit of 660 MW is expected to be commissioned during the
11th Plan and the remaining unit during 12th Plan. Other projects where
considerable progress has been made are coastal projects in Andhra Pradesh
and Tamil Nadu and a pit head based project in Jharkhand. Further the projects
under consideration include pit head projects in Orissa and Chatisgarh and
coastal projects in Maharashtra and Karnataka.

1.6.4 Nuclear Power Development:

11th Plan power programme includes 3160 MW of nuclear power plants all of
which are under construction. Recently, agreement has been signed with USA in
respect of nuclear co-operation which is expected to improve the supply of
nuclear fuel for nuclear power plants. It is also expected that execution of
nuclear projects will also be opened up to enable participation by other PSUs and
private sector. The effect of this is likely to be visible in 12th Plan period. Nuclear
Power Corporation of India has indicated a capacity addition of about 11,000 MW
during 12th plan. In addition, NTPC have also expressed their intention to enter
into the nuclear power arena and have proposed an addition of 2,000 MW during
12th plan period.

1.6.5 Merchant Power Plants:

A merchant power plant does not have long term PPA for sale of its power and is
generally developed on the balance sheet of developers. Government of India
has reserved coal block with reserves of 3.2 Billion Tons of coal for allotment by
Screening Committee of Ministry of coal for merchant and captive plants. About
10,000 MW capacity is expected to be developed through this initiative. This
capacity has not been taken into account while working out the capacity required

10
th
Executive Summary Working Group on Power-11 Plan (2007-12)

in the 9.5% growth in generation scenario. Capacity addition through this route
would further contribute to better economic growth, better reliability of power,
more spinning reserve and above all would promote creation of competition in
the electricity market.

1.6.6 Decentralised Distributed Generation (DDG):

In some of the remote areas, it is not techno-economically feasible to extend the


grid supply. For meeting the demand of such remote areas, it is proposed to set
up some power plants based on local energy sources available. These are small
hydro and non-conventional sources such as Bio-Mass, Wind, DG sets etc
wherein other sources are not available. During the XI plan period a capacity
addition of about 5,000 MW of capacity under DDG is envisaged.
(Refer Para 3.1 of the Report)

1.7 CAPTIVE POWER PLANTS

The generation from captive power plants at the end of X plan (2006-07) is likely
to be about 78 billion units. It is envisaged that during the XI plan period about
12,000 MW capacity power plants would be added to the system which will take
care of the demand of the industry and also supply surplus power to the grid
under Open Access arrangements which has been allowed as per the Electricity
Supply Act, 2003.

It is envisaged that the generation from non utility captive power plants by the
year 2011-12 may be of the order of 131 billion units which results into a CAGR
of 10.5% p.a in captive generation.

1.8 12TH PLAN SCENARIO

The requirement of installed capacity and capacity addition to meet the


generation requirement during the 12th Plan period as discussed in Para 1.2.2 of
this Report are given in Table below:

Capacity addition required during 12th plan (2012-17)

GDP GDP Electricity Peak Installed Capacity Addition


Growth /Electricity Generation Demand Capacity Required During 12th
Elasticity Required (BU) (MW) (MW) PLAN (MW)
8% 0.8 1415 215700 280300 70800
0.9 1470 224600 291700 82200
9% 0.8 1470 224600 291700 82200
0.9 1532 233300 303800 94300
10 % 0.8 1525 232300 302300 92800
0.9 1597 244000 317000 107500

11
th
Executive Summary Working Group on Power-11 Plan (2007-12)

It would be seen from the above table that under various growth scenarios, the
capacity addition required during 12th plan would be in the range of 71,000 -
1,07,500 MW, based on normative parameters.

The Working Group recommends a capacity addition of 82,200 MW for the 12th
Plan based on Scenario of 9% GDP growth rate and an elasticity of 0.8%.

During 12th plan about 30,000 MW capacity addition is likely to be based on


hydro and about 11,000-13,000 MW will be nuclear based. The balance capacity
addition of about 50,000 MW will be from thermal projects. A shelf of projects
totalling over 1,50,000 MW has been identified & listed in main report.

1.9 RENOVATION & MODERNIZATION, LIFE EXTENSION AND PIE


PROGRAMME

A Renovation and Modernisation (R&M) Programme for Thermal Power Stations


was launched by the Government of India all over the country way back in
September 1984 for completion during the Seventh Plan Period. This
programme was successfully completed and intended benefits were achieved. In
the subsequent 8th and 9th Plans, Renovation and Modernisation and Life
Extension (LE) works were carried out on a number of older generating units
which resulted in improvement in their performance and extension of their useful
life.

In the 10th plan life extension of 106 Nos of thermal units totalling to 10,413 MW
was envisaged. However progress was not satisfactory due to high execution
time & cost involved in LE works. The cost of LE was also not economically
feasible considering the age of plants and there was reluctance from power
plants to shut down their units for longer periods due to prevailing power
shortages.

In view of above a new initiatives called Partnership of Excellence was taken up.
Under this programme generating companies who were performing well provide
assistance in improving performance of non-performing units by following
measures;

Phase-I: Toning up of O&M Practices


Phase-II: Comprehensive Overhaul
Phase-III: LE for those units were found techno-economically feasible.

Towards this initiative, CEA identified 22 power stations of 11 utilities, with a


capacity of 7930.5 MW across the country. Out of these, 17 stations with an
operating capacity of 5050 MW were entrusted to NTPC and one stations (280
MW) to TATA power. On remaining 4 stations the respective utilities are taking
their own course of action. The plants entrusted to NTPC recorded an additional
generation of power-3690 MUs- corresponding to an equivalent capacity addition

12
th
Executive Summary Working Group on Power-11 Plan (2007-12)

of 720 MW, considering national average PLF. Capacity addition of this order
requires an investment of around Rs.3,000 crore at a Greenfield project. The
phase-II of the programme, therefore, needs to be continued. Some additional
units have also been identified for R&M and life extension. The decision for
investment for R&M/LE will be based on cost benefit analysis. If not economically
viable installation of new plants at existing sites, may be considered.

(The details of R&M, LE & PIE programme and their status are given in Chapter-1,Para 1.15 of
main Working Group Report)

1.10 NEW AND RENEWABLE ENERGY SOURCES

The Ministry of New and Renewable Energy Sources (MNRE) have chalked out
plan of adding 13,500 MW of renewable power in the country during 11th Plan
period. This would make total installed capacity of these plants at 23,500 MW by
the year 2011-12 which is detailed as below:

Wind - 17000 MW
Bio Mass - 3200 MW
Small Hydro- 3300 MW

Although installed capacity of the plants is high but on an average plant load
factor of wind turbine plants is only of the order of 15-20% and as such this
capacity can generate about 41 billion units at the maximum.

1.11 RECOMMENDATIONS

1. The Working Group recommends generation planning based on growth of


energy generation requirement of 9.5%. Keeping in view the above
objectives and preparedness of various projects the Working Group
recommends capacity addition of 68,869 MW during 11th Plan as per
details given below:

SECTOR HYDRO TOTAL THERMAL BREAKUP NUCLEAR TOTAL


THERMAL (%)
COAL LIGNITE GAS/LNG
CENTRAL 9685 23810 22060 1000 750 3160 36655
(53.2%)
STATE 2637 20352 19365 375 612 - 22989
(33.4%)
PRIVATE 3263 5962 5210 0 752 - 9225
(13.4%)
ALL-INDIA 15585 50124 46635 1375 2114 3160 68869
(100%)
(Detail list is in Appendix-1.8 of main Working Group Report)

13
th
Executive Summary Working Group on Power-11 Plan (2007-12)

2. States are required to take an active role in the capacity addition


programme by their own agencies & by private sector participation through
tariff based competitive bidding route on the lines of developments of
Ultra Mega Power Project. In the 11th plan addition of less than 50% of
total capacity is targeted in states and private sector. It is recommended
that in 12th Plan more than 50% capacity should come through initiative of
the states.
3. Some of the states do not have resources for capacity addition in their
states. Such states should tie up long term PPAs with surplus
states/generation companies.
4. Manufacturing capacity of BHEL needs to be enhanced to meet the
capacity addition programme envisaged in 11th & 12th Plans.
5. A 10 year plan for hydro development is to be pursued in view of higher
gestation period. A hydro capacity of 30,000 MW has been identified for
commissioning during 12th Plan. The survey and investigation, preparation
of DPR, statutory clearances should be vigorously followed up right from
now to enable their commission during 12th Plan. The CEA should closely
monitor progress on these projects. .
6. The Working Group recommends continuation of PIE programme during
11th Plan also.
7. In addition to capacity addition programme, concerted efforts to continue
in regard to:

- Development of captive power plants.


- Maximising Generation from existing plants.
- Energy Efficiency improvement through Energy Audit.
- Better O & M practices.
- RM&U/Partnership in Excellence (PIE) Programme.
- Development of Non-Conventional Energy Sources.

8. Major recommendations for facilitating open access in distribution and


harnessing surplus captive generation in the country are as under:

¾ Reasonable cross subsidy surcharge and other charges to provide


some economic incentive to the generators to avail open access.
¾ The SERCs should allow recovery of some portion of fixed cost in
addition to the variable cost of captive generation. The captive
generators may offer their surplus power on the basis of a firm
schedule. Infirm power from CPP should also be considered for
purchase.
¾ There should be no penalty for reduction of contract demand by any
industry having captive plant.

14
th
Executive Summary Working Group on Power-11 Plan (2007-12)

2.0 TRANSMISSION PLANNING INCLUDING NATIONAL GRID


The transmission system facilities had earlier been planned on regional basis
with provision of inter-regional link to transfer regional surplus power arising out
of diversity in demand. The generation resources in the country are unevenly
located, the hydro in the northern and north-eastern states and coal being mainly
in the eastern part of the country. Development of strong National Grid has
become necessity to ensure reliable supply of power to all. The planning &
operation of the transmission system has thus shifted from regional to national
level. Formation of a strong National Power Grid has been recognized as a
flagship endeavour to steer the development of Power System on planned path
leading to cost effective fulfilment of the objective of ‘Electricity to All’ at
affordable prices. A strong All India Grid would enable exploitation of unevenly
distributed generation resources in the country to their optimum potential by
providing enhanced margins in inter-regional transmission system. These
margins, together with open access in transmission, would facilitate increased
trading in electricity leading to market determined generation dispatches thereby
resulting in supply at reduced prices to the distribution utilities and ultimately to
consumers benefit.

2.1 PROGRAMME OF DEVELOPMENT OF NATIONAL GRID

As on today, the inter-regional transmission capacity of 11,450 MW is existing


and inter-regional energy exchanges of more than 12 billion kWh in a year are
taking place contributing to optimum utilization of generation capacity. The
program is to achieve inter-regional capacity of 15750 MW by the end of 10th
Plan and about 37,150 MW by the end of 11th Plan. Transmission systems
within the regions to support the above inter-regional transmission capacity has
been also planned. The plan for National Power Grid and the schemes have
been identified. (Ref 2.2 of Main Working group Report)

2.2 North Eastern region, Sikkim and Bhutan have vast untapped hydro potential
which is planned for development during 11th plan and beyond. A major
component of this power will be utilised by deficit states in the northern and
western region and for which reliable evacuation system is planned to be
developed. The requirement of transmission system for evacuation of NER hydro
power has been estimated corresponding to the capacity of hydro projects which
may be feasible to develop say in the next about 20 years. This generation is
estimated to be about 35000 MW in NER, about 8000 MW in Sikkim and about
15000 MW in Bhutan. Taking local development at accelerated pace resulting in
demand within the NER, Sikkim and Bhutan to be in the range of 10000 – 12000
MW (presently it is about 1500 MW), the transmission requirement through the
chicken neck works out to be of the order of 45000 MW. The total requirement
including additional circuits for meeting the contingencies and reliability needs,

15
th
Executive Summary Working Group on Power-11 Plan (2007-12)

would work out to 7 or 8 numbers of 800 KV HVDC bi-pole lines and 4 or 5


numbers of 400kV double circuit lines – a total of 12 numbers of high capacity
transmission corridors passing through the chicken neck. For this, RoW
requirement would be about 1.5 Km in width considering minimum distance
between adjacent towers to be such that fall of any tower does not affect the
adjoining line. The first 800kV HVDC bi-pole line has been planned from a
pooling substation at Biswanath Chariyali in North-eastern Region to Agra in
Northern region. This is being programmed for commissioning matching with
Subansiri Lower HEP in 2011-12.

2.3 ASSESSMENT OF TRANSMISSION CAPACITY REQUIREMENT

The focus of transmission system development programme for the XI Plan is to


provide adequate inter-regional and intra-regional transmission capacity so as to
consolidate and strengthen the National Grid network towards a strong All India
Grid. The inter-regional power exchange requirement has been assessed from
possible scenarios of regional surpluses and deficit for the peak and off-peak
conditions of winter, summer and monsoon months. Projections of deficit/surplus
based on which transmission requirement has been assessed are given in
Chapter-8 of this report. The projection based on programme of generation and
anticipated demand aims at estimating the transmission requirement at the inter-
regional level. Grid expansion plan evolved based on this projection would be
able to cater to the needs of various feasible operating scenarios and also
provide required margins to support market oriented power exchanges.

(Ref Para 2.3 of main Working Group Report)

2.4 TRANSMISSION CAPACITY FOR TRADING

The above method adopted for evolving the transmission system expansion plan
provides sufficient transmission capacities which would have inherent margins for
trading transactions. Transmission system implemented on the basis of the
expansion plan evolved in this manner would enable trading across the regional
boundaries towards optimal utilization of generation resources in the country for
ultimate benefit of the consumer. As the system is evolved based on extreme
dispatches, it would facilitate trading most of the time without congestion.
Currently, trading is taking place through short-term bilateral contracts. With
introduction of Power Exchange at National level, which is being envisaged to be
in place in near future, trading would also take place through Power Exchange
which would be day ahead contracts. All the short term as well as Power
exchange transaction would need transmission capacity which would come out of
the spare capacity inbuilt in the transmission system. The reliability and
operational margins in the planned and implemented transmission system
corresponding to the committed long-term transmission needs would provide the
transmission capacity for trading of power.

(Ref Para 2.5 of main Working Group Report)

16
th
Executive Summary Working Group on Power-11 Plan (2007-12)

2.5 TRANSMISSION CAPACITY MARGINS

Transmission capacity through creation of additional transmission system could


be provided based on long-term commitment for the transmission charges. It has
been estimated that reliability and operation margins would be generally of the
order of 25-30% of the transmission capacities required for meeting the firm
transmission needs of the long-term open access. This level of redundancy
would generally provided sufficient margins for trading needs. However, it should
be noted that short-term open access (STOA) transactions operating on these
margins, even if curtailable, cause reduction in the security level. Therefore,
unless margins are increased by design, the system operator would have
tendency to keep cushions by underestimating the operational margins. As such,
and as the system security is of paramount importance, creation of increased
margins by design becomes essential for accommodating STOA.
(Ref para 2.5 of main Working Group Report)

2.6 TRANSMISSION PLANNING CRITERIA

The network expansion has been planned to provide a reliable power system
with sufficient redundancies for secure operation maintaining adequate margins
at all times to maintain system parameters with in such limits that contingencies
do not lead to loss of system integrity. The contingency criteria is based on ‘N-1’
in general and ‘N-2’ for large generating complexes and multi-line corridors.

2.7 TRANSMISSION SYSTEM FOR MERCHANT PLANTS

Merchant plants would sell their power to customers who are not predetermined
through Power exchange contracts. However, they are long term-user of the
transmission system. The transmission system for the connectivity of the
merchant plant as well as for meeting their transmission needs is required to be
planned and built matching with the implementation of the merchant generation
plant. Also, some of the generation plants have only a part of their generation
capacity tied-up in long-term bi-lateral PPAs. When such plants seek long-term
open access only for a part of their full generation capacity, they inherently also
seek connectivity for the remaining capacity which would be available with them
as a merchant plant capacity. As the transmission system in both the cases
would be required to be planned and implemented corresponding to the full
requirement, they are long-term beneficiary of the transmission system. For
proper planning and implementation of transmission system, the merchant
generators need to inform about region(s) in which they would generally sell their
power, so that transmission system requirement for evacuation of their power
and transmitting it to identified load centres could be assessed and any additional
capacity required could be planned. As building the identified transmission
schemes including obtaining necessary approvals by the identified transmission

17
th
Executive Summary Working Group on Power-11 Plan (2007-12)

company /companies would generally require almost same time as that for
implementation generation projects, firming up of sellers and assessment of
transmission requirement should be started at the earliest.

(Ref para 2.5 of main Working Group Report)

2.8 TRANSMISSION SYSTEM UNDER STATE SECTOR

A well planned and reliable transmission system at the National and Regional
level would need to be complemented with development of matching
transmission system at 220kV and 132kV and also the sub-transmission and
distribution system so as to cater to the load growth and ensure proper utilisation
of development in generation and transmission facilities for the ultimate goal of
delivery of the services up to the end consumers in the country.

Inadequate development of sub-transmission and distribution system facilities in


the States of NER has been adversely affecting the reliability of power supply to
the consumers and also hampering the load growth in the region. The
transmission, sub-transmission and distribution systems of states require major
strengthening/up-gradation. Transmission lines that are under outage require
speedy restoration for bringing them into operation so that the states could avail
their central sector shares as well as utilize their own generation without any
constraint.

Inadequacies in the transmission and distribution system had been on account of


slow implementation of schemes due to various factors such as time consumed
in E&F clearances, land acquisition, RoW constraints, fund limitation,
organizational difficulties of state utilities, lack of vendor response due to
locational factors, law and order, terrain specific difficulties, etc. Due to limited
funding capabilities of state utilities, most of the required transmission projects
are generally funded by NEC or by NLCPR under DONER and
investment/funding approval of scheme so funded also takes additional time. All
these issues need to be addressed to achieve the accelerated demand growth in
NER.

2.9 ELEVENTH PLAN PROGRAMME

2.9.1 Evolving the Perspective Transmission System for XI Plan

In transmission system development in the country, the focus of XI Plan


programme is formation of the National Power Grid. A strong All India Grid would
enable exploitation of unevenly distributed generation resources in the country to
their optimum potential. The transmission capacity together with the margins
provided for required redundancies as per planning criteria would provide a
reliable transmission system. This would meet the firm transmission needs and
with open access in transmission, would facilitate increased real time trading in
electricity leading to market determined generation dispatches thereby resulting

18
th
Executive Summary Working Group on Power-11 Plan (2007-12)

in supply at reduced prices to the distribution utilities and ultimately to the


consumers. Development of National Grid has been necessitated by the large
thermal generation potential in eastern part of the country and equally large
hydro generation potential in north-eastern part. It has also been spurred by the
opportunity provided by open access, variation in hydrology / hydro potential and
diversity of load across the country.

It is envisaged to add during the XI plan period new inter-regional capacities of


20700 MW at 220kV and above. This would increase the total inter-regional
transmission capacity of National Power Grid at 220kV and above from 16450
MW of XI Plan beginning to 37150 MW by 2011-12.

(Ref Para 2.3 of main Working Group Report)

2.9.2 Fund Requirement for Transmission System Development and


Related Schemes

Total Fund requirement for transmission system development and related


schemes has been estimated as following:

Rs Crores
Inter State system 75000
Intra State system 65000
TOTAL 140000

(For details please refer to Para 2.8 of main Working Group Report)

2.10 TECHNOLOGY DEVELOPMENT

2.10.1 Adopting New Technologies In Transmission System

New technologies would need to be adopted and implemented in a proactive


manner to achieve the objective of optimum utilization of the available
transmission assets as well as conservation of Right-of-Way, reducing
transmission costs, reduction of losses etc. Some of the new technologies
adopted/being adopted in its transmission system include:

• High capacity 6000MW +800kV HVDC system


• 765kV AC Transmission System
• Ultra High Voltage AC Transmission System(1000kV)
• Application of Series Compensation
• Flexible AC Transmission System (FACTS)
• Upgradation/Uprating of transmission line
• High temperature endurance conductor
• Tall/Multi-circuit & Compact tower
• High Surge Impedance Loading Line (HSIL)

19
th
Executive Summary Working Group on Power-11 Plan (2007-12)

• Remote operation of substation, substation automation and Gas Insulated


substation (GIS)
• All Aluminum Alloy Conductors (AAAC) and Polymer/Composite
Insulators.
• Development of disc insulators of 320kN & 420kN indigenously for both
AC & HVDC applications, as import substitution.
• Indigenous development of semi-conducting glazed insulators (Offering
better pollution performance)
• Introduced source/process inspection of equipment to ensure zero defect
• Airborne Laser Terrain Mapping (ALTM) for detailed route survey
• Thermo-vision scanning of the lines and sub-stations
• Conditional monitoring of equipment
• Preventive maintenance of Transformers using State-of-art Oil testing
laboratories set up by the company
• Emergency Restoration System (ERS)

For modernization of transmission system through latest technology integration,


two pronged strategies have been envisaged as under:

• Enhance capacity and reliability of existing systems.


• Suitable technology for new systems keeping in view the long term
perspective

3.0 DISTRIBUTION INCLUDING VILLAGE & HOUSEHOLD


ELECTRIFICATION

3.1 OVERVIEW OF DISTRIBUTION SECTOR

The electricity distribution section is the most daunting sector due to its interface
with the public at large with different needs and expectations and varying
degrees of capacity to pay. The distribution sector is the cutting edge and as the
need to improve this sector was realized, in the 10th plan the emphasis was on
steps to reduce the huge aggregate technical and commercial losses, control the
theft & pilferage and rationalise the tariff structures. Investment was also made in
the distribution sector and across the states reforms were taken up. Major
schemes like Accelerated Power Development & Reform Program for urban
areas and the Rajiv Gandhi Grameen Vidyutikaran Yojana was also initiated in
the 10th plan which aimed at bringing in investment in urban areas and creating
an electricity infrastructure in rural areas. There is however a pressing need to
continue these efforts in the 11th plan so as to reduce the AT&C losses and to
continue with the reforms in the distribution sector to provide an affordable,
good quality and reliable power supply to the citizen of India, be it in urban or
rural areas.

20
th
Executive Summary Working Group on Power-11 Plan (2007-12)

The distribution of power can be studied in two distinct components viz. ,


(i) Distribution of power in urban areas, and
(ii) Distribution of power in rural areas.

(Refer Para 3.0 of main Working Group Report)

3.2 QUALITATIVE APPROACH

3.2.1 Distribution of power in urban areas

The Accelerated Power Development & Reform Program (ARDRP) was aimed at
bringing about improvement in the urban distribution sector by funding
investment in the distribution network, and by incentivising the states who
performed well in reducing losses. The Ministry of Power constituted a task force
in 2006 under Shri P. Abraham which has recommended that APDRP may be
continued with investment and incentive component beyond the 10th plan.
However the conditions may be made more stringent and reform oriented. While
broadly agreeing with recommendations of the Abraham Committee report, it is
felt that APDRP needs to be continued in 11th plan with revised terms and
conditions. The focus of the programme should be on establishment of base line
data, which shall enable reduction of AT&C losses in major towns of the country
through strengthening , upgradation of sub-transmission and distribution network
and adoption of Information Technology in the areas of energy accounting &
auditing and improvement in consumer services through establishment of Bijlee
Sewa Kendras. The programme may focus on the town and cities covering all
district headquarters and town with population of more than 50,000 and town with
lesser population in special category sates . The investment and incentive
components may be merged and funding may be in form of loan assistance with
the provision of conversion of loan to incentives to the distribution companies on
achieving specified milestones with regard of reforms and reduction of AT&C
losses. There also needs to be a provision of incentive to the employees of the
utilities. The loan assistance may be converted to grant (50 % for general
category states and 90 % for special category states) and the loan should be
from Central Sector with a moratorium of three years on interest and on
repayment. The rate of interest may be as determined by Ministry of Finance
from time to time. ADDRP assistance should be also available to private
distribution companies as the ultimate beneficiary was the consumer. The loan /
grant needs to be funded under Central sector through REC / PFC.

3.2.2 Distribution of power to rural areas

RGGVY (Rajiv Gandhi Grameen Vidyutikaran Yojna) aims to achieve power for
all by 2009 and in the long run accelerate rural development, adequate
employment and eliminate poverty through irrigation, development of small scale
industries, provision of health care and promotion of education and information

21
th
Executive Summary Working Group on Power-11 Plan (2007-12)

technology. RGGVY also aims at bridging the urban rural gap and provide
reliable quality power supplies to rural areas.

However, in order to bring about access to electricity to all rural households,


there would be need to widen the electricity coverage to hamlets / habitations of
the country. In case the funding of RGGVY becomes a constraint it is proposed
that in the first phase all un-electrified villages and hamlets with more than 300
population are covered. Those hamlets with less then 300 populations may be
excluded except those in hilly, forest, desert and tribal areas. The total cost of
phase 1 is estimated at Rs. 24,000 crore. Phase 1 would be completed by 2009
and would reach electricity to all the un-electrified villages and about 3 lakh
hamlets. The second phase would start from 2009 onwards and would reach
electricity to the balance un-electrified hamlets and complete the task of
providing access to all rural households by 2012 . Second phase is estimated
around Rs. 16,000 crores. The two phases is estimated around at Rs. 40,000
crores .

(Refer Para 3.7 of main Working Group Report)

3.2.3 Prioritization of RGGVY

Maximum number of un-electrified villages exist in the under developed States.


RGGVY programme should give top priority in the allocation of funds for these
States. Second priority should be given for intensive electrification of such States
where the household electrification is below the national average. Third priority
should be on the intensive electrification for the remaining States.
(Refer Para 3.7.2 of main Working Group Report)

3.2.4 Public Private Partnership through rural franchisees

Management of rural infrastructure has to be based upon all inclusive growth


model that involves rural set ups and provides the local Panchayat Raj
institutions a supervisory function to ensure the durability and sustainability of
electricity infrastructure.

Franchisee system for management of rural distribution has been made


mandatory under RGGVY to make the revenue model sustainable. RGGVY
allows enterprising individuals, NGOs, private entrepreneurs, co-operatives,
Panchayat Raj institutions to become franchisees. The franchisees system needs
major push in 11th plan with initiatives for capacity building and financial support.

(Refer Para 3.23 of main Working Group Report)

22
th
Executive Summary Working Group on Power-11 Plan (2007-12)

3.2.5 Financial support to Franchisees

Not many people are coming forward for franchiseeship especially from remote
rural areas where loads are small and sustainability difficult. As franchisees will
be mainly rural entrepreneurs, they will have difficulties in raising small funds for
their micro level projects to guarantee their performance or meet working capital
requirements. No funds have been allocated under RGGVY for development of
franchisees. It is necessary to develop institutions that extend micro credit to
meet the franchise level financing needs.

3.2.6 Distribution of power in Rural Areas through Decentralized


Distributed Generation (DDG)

Electricity Act, 2003 provides the requisite framework for accelerating


electrification in rural areas with necessary empowerment. It permits operation of
stand alone systems independent of the regulatory regime. Integrated Energy
Policy 2006 has estimated the requirement of power at 8,00,000 MW by 2031. It
implies that India must add 25000 MW or more every year for a quarter century.
It is a colossal task and would require exploitation of all renewable and fossil
resources. Secondly, the creation of huge rural village and block level electricity
infrastructure will require immediate supply of power. Village level energy
resources like biomass, hydro and solar energy will help to reduce the
dependence on grid based thermal, gas nuclear and hydro power. India has a
potential to generate 10-15000 MW of power from the available biomass. DDG
based on this resource will meet the critical needs of parched villages asking for
timely power. Cost of electricity should be based on cost to serve basis and DDG
to be taken up on a mission mode. Viability gap funding may be adopted in case
of grid interconnected schemes. Bio mass cultivation may be encouraged to
support DDG and bio-fuel cultivation to be funded by Financial Institutions (FIs) /
Banks. However, multifuel technologies may be encouraged.

(Refer Para 3.10 of main Working Group Report)

3.2.7 Pilot Programmes on DDG

The problem of providing power to rural areas would be critical when the
infrastructure under RGGVY becomes ready but remains without the supply of
power. To attract the entrepreneurs, REC may be encouraged to put up pilot
projects in the selective rural areas to have a demonstrative effect. Such
projects could be linked to the neighboring substations and incorporated as the
long-term lease infrastructure under RGGVY on cheaper finance. DDG will go a
long way to ameliorate the shortages of power in rural areas.

Nationwide survey of available resources in each villages to be undertaken in


fixed time frame through a nodal agency like REC.

(Refer Para 3.10 of main Working Group Report)

23
th
Executive Summary Working Group on Power-11 Plan (2007-12)

3.2.8 One Megawatt Power Plants in Rural Areas

To meet the power supply requirements of rural areas stand alone / grid
connected power plants of optimum one megawatt capacity power plants should
be encouraged. REC should act as nodal agency for providing technical and
financial support under the scheme.

(Refer Para 3.18 of main Working Group Report)

3.2.9 Akshay Prakash Yojana

Maharashtra has launched a new programme called Akshay Prakash Yojana


aimed at demand side management. This programme has shown good results in
ensuring quality and reliable supply of power to the villages. Both consumers
and utilities are benefiting under this programme. It is recommended that this
programme should be popularized among other utilities.

3.2.10 Centres for Excellence for Distribution of Power

The Electricity Act has opened new avenues for variety of players to take up
distribution of power. In the changed environment and to seize the new
opportunities REC should set up centres of excellence for distribution of power in
all the states to take up rural distribution by setting up a subsidiary company.

(Refer Para 3.18 of main Working Group Report)

3.2.11 Non Discriminatory Supply Option

RGGVY scheme provides for making adequate arrangements for supply of


electricity and there should be no discrimination in the hours of supply between
rural and urban areas. To achieve this, there should be a clear allocation of
Power Supply for the rural areas.

3.2.12 Agricultural Sector

Agricultural consumption comprises of approx 20% to 40% of the total


consumption of the utility in the states. There is a fear with regard to depletion of
water table due to unrestricted exploitation of the ground water. The adoption of
flat rate pricing for agricultural power is cause for this perverse state of affairs.
Under this system, a farmer pays a fixed price per horsepower per month for
electricity. Therefore, the marginal cost of pumping water is zero. This leads to
energy wastage, over-pumping and inefficient selection of crops. Flat rate
pumping also masks the true cost of power to farmers. Agriculture consumption
is mostly un-metered and this allows manipulation of the loss by the utilities in the
name of Agriculture Consumption therefore, during the 11th plan all agriculture
connections need to be compulsorily metered

24
th
Executive Summary Working Group on Power-11 Plan (2007-12)

3.2.13 Energization of Pumpsets in Eastern Region

Eastern sectors’ irrigation potential should be fully exploited during 11th Plan by
launching a special scheme for energization of pumpsets. It is estimated that
Eastern region has only 10% agricultural consumers. A targeted programme will
not only provide livelihood to the poor farmers but also provide food security to
the nation. Out of 35 lakh pumpsets energisation targeted for 11th Plan, 20 lakh
should be taken up in the Eastern region and other states where huge potential
exists

3.2.14 North-East and Backward Regions

In all the backward and north-eastern States the programme of electricity


distribution projects need to be supported with low cost funds along with
substantial portion of subsidy or grants. Rural Infrastructure Development Funds
(RIDF) available with NABARD should be utilized for the development of
electricity distribution in the North-eastern and other backward regions of the
country. For the System Improvement Schemes in these regions RIDF funds
may be allowed to be utilized for making available cheaper credit for an
accelerated development of these regions.

3.2.15 Tariffs

Performance based regulation through Multi Year Tariff (MYT) framework, is an


important incentive to minimize risks for utilities and consumers, promote
efficiency and rapid reduction of system losses. It would also bring greater
predictability to consumer tariffs by restricting tariff adjustments to known
indicators. Benchmarking should be properly adopted after adequate studies to
establish the desired performance standards. Regular review of the performance
levels also need to be suitably undertaken.

As regards Agricultural tariff it should be in consonance with the sustainable


water management requirements. A higher level of subsidies could be
considered to support poorer farmers of the region where adverse ground water
table condition requires larger quantity of electricity for irrigation purposes but
restricted suitably for maintaining ground water levels for a sustainable usage.
Even a combined tariff in such cases for electricity and water may be an option to
consider.

Differential tariffs for usage during different time of the day i.e. distribution based
on peaking or off peak hours etc. needs to be introduced expeditiously by
introducing Time of the day Metering to flatten the demand curve to more
manageable levels

25
th
Executive Summary Working Group on Power-11 Plan (2007-12)

3.2.16 Open Access

Access to transmission and distribution network is one of the most important


elements of Electricity Act 2003 and National Electricity Policy 2005. At the retail
level the consumers with a minimum requirement of 1 MW are to be granted the
right to avail open access by 2009 in a phased manner. A consumer allowed
open access under the regulations is therefore free to choose any electricity
supplier other than the distribution licensee of its area.

The major issue in making open access operational is the level of cross-subsidy
and other charges applicable to open access consumers.

Most states have released open access regulations with the open access
phasing plan time frame.

The incumbent licensee may not like migration of creamy customers and put
barriers to prevent it. The open access customers may also fear discrimination
on availing supply from alternative source to the current retail supplies. In this
context the regulators have an important role to play in encouraging open
access. The 11th plan should focus on creating awareness, providing
communication, customer protection and promoting open access to the
consumers as envisaged in the Electricity Act 2003. Open access in distribution
should be in place including phasing out of cross subsidy surcharge by end of
11th plan.

3.2.17 Other issues

• Newly created distribution companies (consequent to reorganization of SEBs)


need to be given full autonomy. This should be a condition for release of
central assistance to the states.
• Huge investment is required for distribution network up gradation. The central
govt. should provide resources to the State Utilities with the condition that
large part would be treated as grant if targeted reduction in T&D losses is
achieved. There is a need to popularize TOD tariff.
• Separate distribution companies could be carved out for rural areas so that
subsidy could be targeted to only needy and poor consumers. Forum of
Regulators should come out with a model agreement for distribution of
electricity by distribution licensees through a franchisee in urban area.
• The licensee should have discretion to give rebate to a category of
consumers in the tariff determined by ERCs, if he considers it necessary, for
effectively facing the competition caused by open access in distribution.
• Where applicable , carbon credits should be obtained.
• A business model including simplified tariff determination for generation- cum-
distribution projects in rural areas should be developed to facilitate these
projects.

26
th
Executive Summary Working Group on Power-11 Plan (2007-12)

3.3 QUANTITATIVE ASSESSMENT OF 11TH PLAN PROGRAMME

The expected outcomes from the 11th plan programme is given at Para 3.25 of
the report.

3.4 ISSUES OF INSTITUTIONAL NATURE LIKE CENTRAL , STATE &


PRIVATE SECTOR

3.4.1 Enlarging Role of central Government

Central Government should consider enlarging its role in the area of rural
distribution and generating station to give power to consumers in the vicinity.

Financial Institutions should support bio-diesel plantations, consultancy, R&D,


DPR preparation etc.

The priority sector status available to REC for the energisation of Agricultural
pumpsets etc was recently withdrawn which should be restored in order to
enhance the pumpset energisation programme during the 11th plan to at least 35
lakh pumpsets.

REC/PFC may finance the power equipment manufacturers in their


modernization and expansion plans.
REC/PFC may float Venture Capital Funds to encourage manufacture of critical
quality components used for power infrastructure and promote ready market for
such products at competitive rates.

3.4.2 State

All concessions extended by States for Industrial development may be given for
DDG projects.

A separate Rural Electricity Agency (REA) may be considered for each state to
look into needs of rural areas.

The State Govts., State Utilities/ Discoms and Local administration should create
proper enabling atmosphere to encourage DDG projects.

3.4.3 District Committees/ Local Management

The District Committees should be suitably strengthened, made fully functional


and active during the 11th Plan. This should cover all the districts in the country.
Specific funds should be allotted to the District Committees. Local institutions like

27
th
Executive Summary Working Group on Power-11 Plan (2007-12)

Panchayat, cooperatives, NGOs, SHGs should be encouraged to take up local


management.

3.4.4 Private

The APDRP assistance, both investment and incentive component, may be


extended to the Private Distribution Utilities also. The incentive for loss reduction
by the private utilities may be given to the State instead of the utility.

3.5 TECHNOLOGY ASSESSMENT AND NEEDS

3.5.1 Pre-paid Meters

Pre-paid meters, should be promoted in the 11th Plan. This will enable efficient
use of power for agricultural use and will also eliminate adverse impact on water
table due to excessive exploitation of ground water. Though it involves huge
capital cost the gains from the system would offset such costs in the long run. It
is also expected that large scale use would bring down the cost of the
technologies.

3.5.2 HVDS System

The advantages of HVDS system are well known particularly in containing theft
of electricity. Besides, it improves the quality of power significantly and thereby
customer satisfaction. HVDS system needs to be given a special focus in the
11th Plan to get immediate results in loss reduction. Efforts should be made to
bring down HT/LT ratio during the 11th Plan.
(Refer Para 3.17 of main Working Group Report)

3.5.3 Priority to IT applications

It is well established that IT application can play a major role in AT&C loss
reduction and provide management of distribution utilities. The IT task force
clearly laid out a plan for introduction of IT on a large scale in the power
distribution sector. The task force recommendation should be implemented. It is
also suggested that the incentive fund under APDRP should be re-deployed for
promoting cost effective IT in the entire distribution sector.

3.5.4 Customer Indexing & GIS based Database

Customer indexing is absent in most of the utilities. This is a major impediment


for any reform in the sector. Consumer indexing has been done by some utilities
but incomplete. Consumer indexing based on GIS application needs to be given
priority in the 11th Plan.

3.5.5 Load Management

28
th
Executive Summary Working Group on Power-11 Plan (2007-12)

In the scenario of energy and peak shortages, load management plays a very
important role for efficient use of energy. Feeder separation programme needs
to be given a major push in those states where agricultural consumption is more
than 20%. In addition SCADA/DA should be introduced in all the million plus
towns by the end of 11th Plan.

3.5.6 Demand Side Management & Energy Efficiency

Using of energy efficient devices should be incentivised. The focus should be on


use of efficient pumpsets in the agricultural sector. Use of CFL lighting etc.
should be encouraged. An awareness campaign should be launched to educate
stakeholders at all levels and quantifiable targets should be fixed to improve
energy efficiency gains.

3.5.7 Reliability Monitoring of Power Distribution System

Present reliability of power is carried out by CEA in terms of outages of 11 kV


feeders on monthly basis in respect of State capitals and major urban
conglomeration. There are number of reliability indices which are in practice
internationally. The international practices should be adopted for proper
monitoring of reliability. The reliability monitoring is to be gradually brought in line
with the world practice i.e. to measure the outage in terms of consumer hours
and number of consumer interruptions. The reliability monitoring will become
more fruitful once “Consumer Indexing” i.e. linking of every consumer to the
feeder is completed by all the Discoms /SEBs and will provide a direct index for
customer satisfaction.

3.5.8 Distribution Network Planning

Inadequate network planning is one of the reasons for hap-hazard and un-
scientific development of the distribution system. The utility should move to
proper distribution network planning both for demand forecasting on medium and
long term basis and for determining need for system expansion and improvement
to meet the load growth. Utility should prepare perspective network plan for 10
year period and this should become part of the conditionalities for sanction of
grants under various programmes.

3.5.9 Energy Accounting & Auditing

Energy Accounting & Auditing is done in many utilities but not comprehensive. In
absence of complete energy accounting and auditing, the system losses can not
be measured accurately and also identification of areas of losses becomes
difficult. 11th Plan should make efforts to standardize energy accounting and
auditing practices and incentivize utilities undertakings complete accounting and
auditing exercise.

29
th
Executive Summary Working Group on Power-11 Plan (2007-12)

3.6 ASSESSMENT OF FINANCIAL REQUIREMENTS

The detailed table of quantities and financial requirements for 11th plan are given
at Para 3.25 of report. However, the final summary of the estimated cost is given
below:

1. Sub Transmission & Distribution for Urban & Rural areas: Rs. 1, 97,000 crore
RGGVY Rs. 40,000 crore
Rs. 2, 37,000 crore
2. APDRP & Other Schemes (pumpsets etc.) Rs. 40,000 crore
3. Decentralised Distributed Generation Rs. 20, 000 crore
4. Others Rs. 10,000 crore
TOTAL Rs. 3,07,000 crore

3.7 RECOMMENDATIONS

1. ARPDP to be continued in 11th plan with focus on auditing and accounting


and reducing AT&C losses in major town and cities It
interventions,technological upgradation, control of theft and pilferage, GIS
and consumer indexing and establishment of Bijlee Sewa Kendra.

2. RGGVY needs to be continued with more focus and with regular flow of
funds so that the envisaged benefits reach the rural masses.

3. Franchisees need to be developed in both urban and rural areas. A


scheme of public private partnership for franchisees development may be
encouraged .and adequate financial support through liberal micro credit
schemes needs to be given for encouraging franchisee development.

4. Decentralised distributed generation needs to be taken up in a mission


mode. Pilot projects needs to be set up initially to gain experience. DDG
proposals may be offered capital subsidies under the public private
partnership scheme for viability gap funding nation wide survey may be
undertaken to analyse resources for DDG.

5. One megawatt power plants in rural areas to be encouraged.

6. Centre for excellence in distribution to be set up.

7. Capacity building programmes of franchisees to be vigorously followed.

8. Special programme of energisation of pump sets in eastern region to be


implemented.

30
th
Executive Summary Working Group on Power-11 Plan (2007-12)

9. Open access in distribution section to be encouraged.

10. Multi year tariffs and rationalization of tariff to be implemented.

11. IT applications to be given priority.

12. Prepaid meters, HVDC systems, consumer indexing, GIS based


database, reliability indexing, energy efficiency, demand side
management and energy accounting and auditing to be implemented.

4.0 DEMAND SIDE MANAGEMENT, ENERGY EFFICIENCY &


ENERGY CONSERVATION

4.1 THE ENERGY CONSERVATION ACT AND INTEGRATED ENERGY


POLICY

The 10thplan period (2002-07) marked the enactment of the Energy Conservation
Act, 2001 and setting up of the Bureau of Energy Efficiency (BEE) at the national
level. The Act has given the mandate to BEE to implement the provisions of the
Act, and spearhead the improvement in energy efficiency of the economy
through various regulatory and promotional measures.

The Planning Commission in its recent report on an Integrated Energy Policy


(IEP) laid out a vision of providing energy security to all citizens. IEP emphasizes
energy efficiency & demand side management as essential components of the
natural energy strategy. The Sub-Group report focuses on operationalizing and
implementing the recommendations of the integrated energy policy.

(Refer Para 4.2 of main Working Group Report)

4.2 ENERGY CONSERVATION STRATEGY IN THE 11TH FIVE-YEAR PLAN

The basic aim of the energy conservation strategy in the 11th Five Year Plan is to
create and strengthen institutions at the centre and in the states to carry out the
provisions of the EC Act 2001, in line with the recommendations of the Integrated
Energy Policy. The strategy will strengthen the existing institutional linkages,
pursue the task of consolidating energy conservation information, trends and
achievements, and create a market for energy conservation and for energy
efficient goods and services.

(Refer Para 4.3 of main Working Group Report)

31
th
Executive Summary Working Group on Power-11 Plan (2007-12)

4.2.1 Strengthening of BEE and SDAs

In the 11th Five Year Plan, BEE will be strengthened as a nodal organization at
the national level, and will be empowered to provide direction to the energy
conservation programmes in the States. An ‘Energy Conservation Information
Centre’ (ECIC) will be set up within BEE to collate energy use data, and analyze
energy consumption trends and monitor energy conservation achievements in
the country. Supporting organizational set-up will also be strengthened in the
state designated agencies (SDAs) in various States and Union Territories (UTs).
For this, a matching grant support from Central Government restricted to the
contribution made by the respective States/UTs Governments will be extended to
establish State Energy Conservation Fund as mandated under EC Act.

(Refer Para 4.3.2 of main Working Group Report)

4.2.2. Energy Conservation Programmes in the Targeted Sectors

In the 11th Five Year Plan, BEE will focus energy conservation programmes in
the following targeted sectors:

Targeted sectors

(i) Industrial Sector (Energy Intensive Industries).


BEE will develop 15 industry specific energy efficiency manuals/guides for the
following sectors: Aluminium, Fertilizers, Iron &Steel, Cement, Pulp & Paper,
Chlor Alkali, sugar, textile, chemicals, Railways, Port trust, Transport Sector
(industries and services), Petrochemical &Petroleum Refineries, Thermal Power
Stations & Hydel power stations , electricity transmission companies &
distribution companies. The manuals will cover Specific energy consumption
norms as required to be established under the EC Act, energy efficient processes
and technologies, best practices, case studies etc. Follow up activities will be
undertaken in the States by SDAs and manuals will be disseminated to all the
concerned units in the industries.

(Refer Para 4.3.5 of main Working Group Report)

(ii) Small and Medium Enterprises (SMEs)

SDAs in consultation with BEE will initiate diagnostic studies in 25 number of


SMEs clusters in the country, including 4-5 priority clusters in North East Region,
and develop cluster specific energy efficiency manuals/booklets, and other
documents to enhance energy conservation in SMEs.

(Refer Para 4.3.5 of main Working Group Report)

32
th
Executive Summary Working Group on Power-11 Plan (2007-12)

(iii) Commercial Buildings and Establishments

BEE will prepare building specific energy efficiency manuals covering Specific
energy consumption norms, energy efficient technologies, best practices etc. As
a follow up, SDAs would initiate energy audits and their implementation in 10
Government buildings in each state and 1-2 buildings at UT level. BEE will also
assist SDAs in the establishment and promulgation of energy conservation
building codes (ECBC) in the States, and facilitate SDAs to adapt ECBC.

(Refer Para 4.3.5 of main Working Group Report)

(iv) Residential/Domestic sector

BEE will enhance its on-going energy labeling programme to include 10 other -
appliances - Air conditioners , Ceiling Fans , Agricultural pump-sets , Electric
motors ( general purpose) , CFLs, FTL – 61cm, Television sets , Microwave
ovens, Set top boxes , DVD players and Desk top monitors. To facilitate this
consumer awareness will also be enhanced nation wide.

(Refer Para 4.3.5 of main report)

(v) Street Lighting & Municipal Water Pumping

To promote energy efficiency in municipal areas in various states, SDAs in


association with State utilities will initiate pilot energy conservation projects in
selected municipal water pumping systems and street lighting to provide basis for
designing state level programmes.

(Refer Para 4.3.5 of main Working Group Report)

(vi) Agriculture Sector

In the 11th Plan, SDAs will collect document and disseminate information on
successful projects implemented in some states, launch awareness campaigns in
all regional languages in print and electronic media, and initiate development of
state level programmes along with utilities.

(Refer Para 4.3.5 of main Working Group Report)

(vii) Transport Sector


SDAs with assistance of concerned institutions/agencies will conduct diagnostic
studies to establish the status of energy consumption and conservation in the
sector. BEE will also set up labeling and/or norms for specific fuel consumption
for a few automobile and Transport categories (Services/ Public transport).

(Refer Para 4.3.5 of main Working Group Report)

33
th
Executive Summary Working Group on Power-11 Plan (2007-12)

4.2.3 Demand Side Management Programmes

BEE in association with SDAs will facilitate State Utilities to pursue DSM options
by focusing on orientation workshops for awareness building, setting up of DSM
cells in utilities to conceive and implement DSM programs, support load
research and studies to rationalize the tariff structures, and initiation of DSM
programmes, especially in the residential, agricultural pumping and municipal
water works & street lighting sectors

(Refer Para 4.3.6 of main Working Group Report)

4.2.4 Human Resource Development Programmes

There is a vast potential for energy savings through human intervention. BEE
and SDAs have a major responsibility for stimulating a major change in the
energy efficiency ethos and practices (energy modesty) by directing the national
energy conservation campaign as a mass movement and seeking wide support.
In the 11th Plan, BEE will continue with their campaigns. The initiatives like
capacity building of energy professionals, establishment of Demonstration
centers in 2 industrial estates, and Nationwide campaigns through media and
other modes will be undertaken.

(Refer Para 4.3.7 of main Working Group Report)

4.3. POLICY RESEARCH FOR ACCELERATING ADOPTION OF ENERGY


EFFICIENCY AND DSM PROGRAMS

Policy research on legislative amendments, policy interventions including fiscal


and non- fiscal measures are planned to be undertaken in 11th Plan.

(Refer Para 4.4 of main Working Group Report)

4.4 RECOMMENDATIONS

The target of additional electricity savings which may accrue to the national
economy at the end of 11th Five year plan as a consequence of intensive energy
conservation and DSM drive is expected to be about 5% of the anticipated
energy consumption level in the beginning of 11th Plan. BEE will device a suitable
mechanism for assessing these savings. The outlay for various strategies and
programs as proposed is Rs. 652 Crores. Out of this proposed allocation, Rs
350.5 crs is the estimated requirement for BEE at the centre and the balance Rs.
301.6 crs as the assistance for strengthening the institutional structure at the
State level for effective implementation of EC Act. These initiatives will also seek
funding support from state governments, other complementary programs, user
industry, financial institutions, and other donor agencies besides innovative
financing options.

34
th
Executive Summary Working Group on Power-11 Plan (2007-12)

5.0 TECHNOLOGY ADVANCEMENT AND R&D


There is a need to introduce advanced technology in generation, transmission
and distribution and encourage Research & Development to meet the ambitious
plan of power sector growth during the 11th Plan.

A review of utilization of R&D fund during the 10th Plan period by major players in
the power sector shows that it was less than RS.150 crores against a provision of
Rs.500 crores. This is considered unsatisfactory and needs to be substantially
improved in the 11th plan.

Considering International technology trend and India’s power sector requirement


following broad areas were identified for selecting R&D projects during the 11th
Plan.

a) Introduction of larger size energy efficient thermal generation for Indian


coal with a good mix of fossil and renewable source of energy.

b) Efficient operation of a large grid with 800 kV AC &DC transmission with


high reliability, flexibility and open access in transmission

c) Technology development and demonstration of distributed generation


covering bio mass, bio diesel, solar, wind and focus on microgrids.

d) Reduction of distribution system losses, energy conservation methods and


introduction of large scale automation in distribution sector.

e) Clean technology development

5.1 OVERVIEW OF R&D IN THE PAST

In the generation sector commendable work has been done by NTPC and BHEL
in the areas of stabilization of 210 and 500 MW units, development of pulverized
coal fired boiler for coal with high ash content, efficiency improvement of Thermal
Power Plants, control, instrumentation and loss minimization. Similarly in the
hydro generation, BHEL, NHPC and other hydro utilities have contributed in
uprating of old units, improving turbine design etc. In transmission, Powergrid
and BHEL have introduced many new technologies like Series Compensation,
Thyristor Controlled Series Capacitor, Controlled Shunt Reactor, etc. Powergrid
have contributed to the development of high temperature conductors,
development of insulators, introduction of 800kV AC and planning for ± 800 kV
DC first time in the country.

Many of the development by Powergrid and NTPC have come through project
route in the county and although their R&D units have not shown substantial
expenditure on R&D, the organizations have encouraged new technology.

35
th
Executive Summary Working Group on Power-11 Plan (2007-12)

It is felt that where as some of the available technology abroad are being
introduced in the country, commensurate R&D efforts to get it improved and
sustained through available inhouse resources, has not been pursued. Further,
an institutional mechanism to conduct and monitor National Level R&D Projects
has not been in place to make the indigenous R&D encouraged and its impact
assessed. As a result, there is no technology breakthrough that has actually
taken place in power sector through indigenous route.

5.2 TECHNOLOGY DEVELOPMENT IN POWER SECTOR

Major utilities like NTPC, NHPC and PGCIL have their inhouse R&D setup which
addresses introduction and absorption of new technology primarily through
project routes. Major manufacturers like BHEL, Crompton Greaves have their
own R&D set up, focusing on product development. Central Power Research
Institute (CPRI) is provided with capital funds from the Ministry of Power for
inhouse research as well as disbursement of research funds to utilities, industries
and academic institution. Central Electricity Authority has a role in identification of
appropriate new technology for the country. Recently a few projects under
National Perspective Plan on R&D have been taken up by CPRI which are
collaborative research projects involving more than one organisation. The R&D
policy of the Government recommends R&D projects that help the nation to
become self reliant in technology.

5.3 IDENTIFIED PROJECTS FOR 11TH PLAN BY CENTRAL UTILITIES

NTPC has identified a few good projects for inhouse research where they would
involve other research institutes like BARC, CPRI, CSIR and other consulting
houses. The list of projects identified by NTPC is as follows:

1. Flue gas heat recovery system for a 200 MW Unit.


2. IGCC technology demonstration project.
3. Automated boiler tube inspection system (robotics application).
4. On line condition monitoring of power transformers.
5. Modeling & design of natural draft cooling tower assisted flue gas
dispersion.
6. Technology demonstration for suitable capacity solar (Thermal).
7. 10 KW sterling engine based TDP suitable for distributed generation.

Powergrid has similarly identified a number of inhouse projects a list of which is


as follows:

1. Technology Development for +/- 800 kV HVDC system for transfer of


6000 MW power from NER to NR
2. Aerial route survey using Air borne laser terrain (ALTM) along with
National Remote Sensing Agency (NRSAR)

36
th
Executive Summary Working Group on Power-11 Plan (2007-12)

3. Development of High surge impedance loading line (HSIL) – 400 kV


Purnea – Biharshariff D/C
4. Fault current limiter at 400 kV level
5. Indigenization of polymer insulator
6. Specification of suitable oil for transformer
7. Indigenized development of MOV
R&D in infrastructure development
8. Intelligent grid
9. Converter transformer design
10. Converter transformer less HVDC system
11. 1000 / 1200 kV EHVAC development
12. Residual life assessment of transmission system
13. Indigenous development of GIS
14. Real time digital simulator and studies
15. Indigenous development of high strength insulators like 320 / 420 kN
AC & HVDC
16. 400 kV compact line
17. Lightning mapping

BHEL has identified a few broad based projects in generation, transmission and
distribution which are given as under:

1. Clean coal technologies.


2. Super critical boilers.
3. Ultra High Voltage Equipment.
4. IGBT based drives and controls.

The laboratories of CSIR who also carry out basic and applied research have
following inhouse research programmes identified for the 11th plan:

1. R&D on Photovoltaics and other solar energy applications (NPL, New


Delhi)
2. Energy for cleaner and greener environment (CECRI, Karaikudi).
3. Bio energy technology: Strategy designing of Jatropha curcas for bio
diesel (NBRI).
4. Development of gas to liquid (GTL) processes for DNE & Fischer –
Tropsch fuels (NCL).
5. Hydrogen economy initiative (NCL, Pune).
6. Development of coal to liquid (CTL) technology for synthesis of liquid
from hydrocarbons (CFRI, Dhanabad).
7. Development of a composite approach suitable for clean coal initiatives
(CMRI, Dhanabad).
8. Development of Underground coal gasification and IGCC Technology
in India (CMRI, Dhanabad).

37
th
Executive Summary Working Group on Power-11 Plan (2007-12)

CPRI has identified few areas of research and investment in infrastructure


building which are given below:

a) Development of new ceramic and polymer composites for power sector


application particularly for power capacitors.

b) Research on new material development for turbine blades for hydro


stations and new coating material along with other CSIR Laboratories and
NHPC.

c) Study of thermal mapping of power stations and heat rate improvements.

d) Diagnostic techniques and mulit criteria approach for RLA of EHV


substations.

e) Simulator studies for large AC/DC grids.

Other than the projects listed, a few projects of National interest which are
necessary to be taken up were identified for the following reasons:

a) They are collaborative research projects where more than one agency
have to be involved.

b) Some of them are demonstration projects involving best practices that


would help further research

c) Some of them are new application areas of available technology

A list of projects have been proposed for Generation, Transmission, Distribution


& Environment areas. Details of the same are furnished in Para 5.6 of Working
Group Report.

Estimated cost of R&D projects recommended for 11th plan by the Working group
have been discussed with the PSUs of MOP, BHEL and also shared with CSIR.
Details of the funds are as follows:

Total for Generation : Rs.333.50 crores


Total for Transmission : Rs. 70.00 crores
Total for Distribution : Rs. 25.00 crores
New Projects : Rs. 24.00 crores

(Project wise details of funds are furnished in Para 5.6 of the main Report)

38
th
Executive Summary Working Group on Power-11 Plan (2007-12)

5.4 CPRI’S ROLE AND A NEED FOR RESTRUCTURING

CPRI was established to work as a nodal agency for power sector research but
had a larger role assigned to work as a neutral testing laboratory. Although the
organisation has contributed to encourage R&D in utilities, academic institutions
and in its own laboratories, it has not been able to build up resources to work as
a driver of R&D in the power sector.

It is recommended that a restructuring of CPRI is necessary if it has to play a


proactive role in collaborative research in the country. For this the following are
suggested:

a) Testing and Research have to be separate functions within CPRI.

b) Testing has to sustain on its own and as far as possible government grant
should not be utilized for meeting test facility requirements. The
beneficiaries of test facility, i.e., the manufacturing units and utilities
should largely bear this burden.

c) CPRI should be corporatised to reduce its dependence on Government


funding and have better operational flexibility. This would help CPRI to be
competitive and self reliant. The major utilities like NTPC, PGCIL, NHPC
and PFC should come forward to make it happen.

d) CPRI is to develop its ability to enhance industrial & system related


consultancy work and get more sponsored projects for improving its
financial health.

5.4.1 Assessment of CPRI’s requirements of fund

CPRI gets planned funds for expenditure of capital nature on replacement of old
test facility, addition of new test facility and for research under three heads, viz.
(a) for its own internal research projects, (b) for research projects on Power
(RSOP) to encourage research at utility centers and (c) National Perspective
Plan projects. The 10th Plan utilization of fund by CPRI is Rs.67.0 crores.

For the 11th plan period, CPRI has asked for a major investment under the
following heads

For Test facility - Rs.638.00 crores


For research projects & facilities - Rs.123.0 crores

(Details are furnished in Para 5.4 of the main Working Group Report.)

39
th
Executive Summary Working Group on Power-11 Plan (2007-12)

5.5 FUNDING OF R&D

R&D expenditure of a few world class utilities and industries are given below:

Company 2003 2004 2005


% of
% of R&D % of R&D
R & D Exp Net sales R&D R & D Exp Net sales R & D Exp Net sales
Exp Exp
Exp
GE
2.7 149.7 1.80 3.091 154.481 2.00 3.425 122.886 2.79
(billion Dollar)
Siemens
4.73 69.77 6.78 4.65 70.23 6.62 5.155 75.455 6.83
(Billion Euro)

2003-04 2004-05 2005-2006


Company
% of R&D % of R&D % of R&D
R & D Exp Net sales R & D Exp Net sales R & D Exp Net sales
Exp Exp Exp
Alstom
473 16688 2.834 405 12920 3.13 365 13413 2.72
(million Euro)
Hitachi
371.8 8632.4 4.307 388.6 9027 4.305 405 9464.8 4.279
( billion Yen)
Mitsubishi Electric
136518 3309651 4.125 130548 3410685 3.828 130629 3604185 3.624
(million Yen)
BHEL
1041 103364 1.007 1252 103364 1.211 1517 145255 1.044
(million Rupee)

It may be observed that most of the organizations spend between 1.8 to 6% on


R&D depending on the nature of their business.

Technology advancements and research & development have so far not been
properly addressed. Major organizations like NTPC, NHPC, POWERGRID, on
the generation side and BHEL, ABB, SIEMENS on the manufacturing side must
enhance substantially their budget allocations for research and development.
The utilities should aim at least about 1% of their profit to be utilized for research
and development activities and the manufacturing organizations should consider
3-4% to be provided for technology development.

Networking of R&D resources and expertise would be an important strategy


aimed at getting effective results. CPRI, apart from testing, must reorient its
strategy and activities towards research.

5.6 RECOMMENDATIONS AND POLICY ISSUES.

1. Technology advancements and research & development have so far not


been properly addressed. Major organizations like NTPC, NHPC,
POWERGRID, on the generation side and BHEL , ABB, SIEMENS on the
manufacturing side must enhance substantially their budget allocations for

40
th
Executive Summary Working Group on Power-11 Plan (2007-12)

research and development. The utilities should aim at least about 1% of


their profit to be utilized for research and development activities and the
manufacturing organizations should consider 3-4% to be provided for
technology development.
2. Networking of R&D resources and expertise would be an important
strategy aimed at getting effective results. CPRI, apart from testing, must
reorient its strategy and activities towards research.

3. Ultra Super Critical boiler technology, IGCC technology and oxy-fuel


technology are well researched abroad but have to be developed for
Indian coal. NTPC, the major Indian Central Sector utility should have its
R&D centre strengthened to expedite the work started during 10th plan on
IGCC. It is recommended that this project may be given top priority and
completed with the help of BHEL or with a private party if necessary.

4. There is a need to work with specialized S&T laboratories under CSIR &
other space and nuclear establishments to develop material technology for
advanced boilers, fuel cells, solar power, battery & super conducting
material application in power sector.

5. For the projects of National interest to be taken upon collaborative


research route the estimated R&D expenditure of 452 crores is
recommended. It is also recommended that in future capital fund support
for R&D should be reduced and utilities and industries should collaborate
to fund R&D projects.

6. An institutional change in handling R&D is required. A suggestion is to


have generation, transmission & distribution R&D units to be established
as separate entities in the central sector undertakings or to set up a
corporate technology centre for R&D activities in various areas of power
sector

7. R&D import should be exempted from custom duty to encourage


indigenous R&D

8. Power sector should seriously consider attracting young talents by offering


them challenging opportunities. This will be possible by encouraging R&D
and offering a good package, like many MNCs are offering at present.

9. A High Power Committee in R&D should monitor R&D projects and


regulate funds. This will avoid duplication & ensure competitive R&D.

10. Organisations like CPRI and NPTI should be spared from manpower
optimization rules where vacant positions are surrendered. This is in view
of the depleting cadre of scientists and specialists in these organizations.

41
th
Executive Summary Working Group on Power-11 Plan (2007-12)

6.0 NORTH-EASTERN DEVELOPMENT

The details of Development of Power Sector in North-Eastern Region


have been covered in the respective areas.

7.0 HUMAN RESOURCE DEVELOPMENT AND CAPACITY


BUIDING’

7.1 MANPOWER

The manpower at the end of the 10th Plan will be of the order of 9.50 lakhs, out of
which the technical manpower is 7.16 lakhs and non-technical 2.34 lakhs.

The total manpower by the end of 11th Plan shall be of the order of 11.76 lakhs,
out of which 8.89 lakhs will be technical and 2.86 lakhs, non-technical.

The total manpower by the end of 12th Plan shall be 13.22 lakhs, out of which
10.04 lakhs will be technical and 3.18 lakhs will be non-technical.

(Ref Tables 1 to 22- of Chapter 7 of the main Working Group Report)

7.2 TRAINING LOAD

Overall training load expected during the 11th Plan is 4.65 lakh man-months per
year against the available training infrastructure of only 0.77 lakh man-months
per year.

For the 12th Plan, the expected training load is 4.78 lakh man-months per year.

(Ref Para 7.3.2 of the main Working Group Report)

7.3 MAN-MW RATIO

The Man-MW ratio is expected to gradually decline from 9.42 per MW in the 9th
Plan to about 7 in the 10th Plan and subsequently to 5.82 and 4.93 in the 11th and
12th plans respectively.

(Ref Table 23 of Chapter 7 of the main Working Group Report)

7.4 MAJOR OBSERVATIONS / RECOMMENDATIONS

7.4.1 Training for All

Every employee should be provided refresher training of minimum one-week per


year as mandated in the National Training Policy. Provisions for Refresher
training for O & M personnel has been made in the Indian Electricity Rules.

42
th
Executive Summary Working Group on Power-11 Plan (2007-12)

However provisions for Refresher training for all power sector personnel as per
their requirements may be included.

7.4.2 Induction Level Training

Induction level training should be made compulsory for personnel getting


inducted in all areas viz., Thermal, Hydro, Transmission and Distribution etc.
Statutory provisions for Induction level Distribution Training in the Indian
Electricity Rules is under active consideration and would be notified shortly.
Simulator training should also be necessarily included as one of the modules for
the O & M personnel.

The Induction level training for Thermal, Hydro and Transmission is presently a
Statutory obligation as per the I.E. Rules. This may be made mandatory and in
particular enforced for the personnel working in the State Utilities and Boards.

Formal Induction level training should also be imparted to all non-technical


personnel in power sector. The duration could be three (3) months for executives
and one (1) month for non-executives.

7.4.3 Reporting Training activities to CEA

As many as 51 Training Institutes are recognized by CEA and it is recommended


that all training activities including expenditure incurred on training and personnel
trained should be reported to CEA. Every Utility/Organisation should display the
manpower and the training infrastructure available category-wise on their web-
site.

7.4.4 Strengthening of Existing Training Institutes

Capacity of existing Institutes to be strengthened. Provisions should be made in


the plan budgets for augmenting Training Centres from time to time. Upgradation
of the Training Institute’s Lab facilities may also be reviewed on a regular basis
and funds should be accordingly allocated.

7.4.5 New Training Institutes

All Power Utilities should set up Training facilities encompassing training


infrastructure for Induction level, Linemen and for Distribution Franchisees where
the Govt. of India could provide part funding.

A National Level Training Institute for Transmission with necessary infrastructure


with Central support at HLTC, Bangalore and Power Grid may be created.

A National level training centre for Distribution should be created with Central
Support at PSTI, Bangalore and CIRE, Hyderabad.

43
th
Executive Summary Working Group on Power-11 Plan (2007-12)

Emphasis should be given to Linemen Training. It should be ensured that the


Linemen recruited should be at least 8th class pass with an ITI qualification.

New Linemen Training Centres should be established within the proposed


institutes in the Utilities in line with the recommended requirements of Distribution
training.

Need for training on Hotline LT Distribution lines may also be actively considered
for interruption free maintenance to the consumers.

7.4.6 Capacity Building in Training for Franchisees (RGGVY)

A national program for training and capacity building to be initiated targeting at


enhancing the skill of franchisees and trainers so as to enable them to play the
desired role in improving rural electricity access.

Every major state should have one (1) Training institute for Franchisee training.
Commercial and Legal issues should also be necessarily included in these
training programs.

Training Centres should also be set up in the districts, which are covered under
Rajiv Gandhi Grameen Vidyutikaran Yojna along with Linemen Training Centres

Capacity Building in Training for Franchisees may also be taken up by the


Institutes conducting DRUM training.

7.4.7 Networking

The Sub Group also stressed on Networking and tie-ups with the
Training/Academic institutions like NPTI, IIMs, ASCI, PMI etc., and other reputed
institutions for providing training to power sector personnel and other
stakeholders.

7.4.8 Training for Contract Labour

Adequate training should be made a pre-requisite for the contractor’s labour to


qualify for supply of Labour in power plants. Contract documents should
accordingly be modified.

7.4.9 Training on Attitudinal Changes/ Behavioral Sciences

Apart from the stress put on acquisition of knowledge and upgradation of skill
emphasis should be given on attitudinal changes/behavioural sciences, in order
to develop a sense of belongingness amongst the employees.

44
th
Executive Summary Working Group on Power-11 Plan (2007-12)

7.4.10 Areas of Concern

Inspite of lack of availability of required infrastructure, the available infrastructure


of various Training Institutes remain under utilized

Statutory Induction Level Training is not being taken seriously by the Power
Utilities

Inadequacy of Trainers and insufficient Career Development Opportunities

ITIs and other vocational training institutions have to be substantially expanded in


terms of the number of persons they train and in the number of different skills
and trades they teach. The quality and range of their training will have to keep
pace with the changing needs of the economy and opportunities.

7.4.11 Recurring Investment on Training

As recommended in the National Training Policy, Organizations should allocate


some portion of their salary budget towards training and development.

All the Organizations, which are provided with Grants either from Central or State
Sector, should separately allocate Funds in particular for Training, which should
not be spent for other purposes.

7.5 FUNDING

The Total Plan period outlay is about Rs. 462 Crores. This does not include the
plan fund outlay proposed by other Sub-Groups, which includes setting up of new
training institutes, infrastructure upgradation, provision of incentives for
sponsoring organizations, Technology upgradation, procurement of Simulators
and GIS based training packages etc.

(Ref. Para 7.4 of the main Working Group Report)

8.0 LEGISLATIVE AND POLICY ISSUES – FORMULATION,


IMPLEMENTATION & FEEDBACK

1. Situation is not ripe for procurement through Case-I route since both coal
and gas are not yet freely available in the market. All efforts should be
made to develop new capacity under Case-II procurement.

2. SPV is necessary to develop new generation capacities quickly.

3. There is need to streamline and standardize the procedure to shorten time


cycle for obtaining environmental/forest clearance with greater emphasis
on compliance with laid down standards and conditions.

45
th
Executive Summary Working Group on Power-11 Plan (2007-12)

4. Exploration capacity of CMPDIL may be augmented and also it may be


given more autonomy so that it can discharge its responsibility in fair and
neutral manner. Number of agencies having authorization to undertake
exploration of coal blocks should be increased.

5. Coal blocks to be used for captive coal mining by power projects should
be explored fully at the earliest and GRs should be readily made available
to power project developers on actual cost basis.

6. Appropriate cut-off of gross station heat rate, say 3000 kilo calorie per
unit, can be considered for identifying inefficient old power plants of more
than 25 years age and the sites could be released for setting-up plants of
more efficient and large sized units depending on the scope of expansion
available and with due cost benefit analysis. Coal linkages of the old
power plants should be transferred to new generating units.

7. Till the long-term coal supply contracts emerge in international coal


markets, the option of competitive bids for net heat rate may be explored
for imported coal based stations.

8. In the interests of larger competition aimed at consumer benefits,


procurement from non-conventional energy sources should not be
restricted to within the State but suppliers from outside State should also
be allowed to compete.

9. Procurement from non conventional sources should, unless there are


compelling reasons, be done through competitive bidding process as this
would add to transparency and lower procurement costs.

10. After assessing the stage of development of various non conventional


energy technologies, definite timeframe should be laid down for doing
away with preferential tariff for power generated from such sources.

11. Tariff Policy advises States to rationalize taxes and duties on captive
power consumption. This may be reviewed periodically with States and
made a condition for Central assistance to State power sector.

12. In competitive procurement of power, bidding by CPSUs should be


ensured in initial few projects to encourage competition.

13. CERC could set up benchmarks for capital expenditure to facilitate


accelerated R&M of old power plants.

14. To make available adequate power for open access consumers, there is
need for enabling policy framework for merchant power plants. Size of
MPPs could be up to 1000 MW which may be appropriate considering
greater possibility of financial closure without long-term PPAs for
comparatively smaller sized projects and also of making available

46
th
Executive Summary Working Group on Power-11 Plan (2007-12)

transmission corridors for such MPPs. We could target MPP capacity of


about 10,000 to 12,000 MW by end of 11th Plan. Such merchant capacity
would be without the basis of long term PPAs.

15. Coal linkages should be freely available for power project developers who
come forward to set up such MPPs. In case captive coal blocks are given
to MPPs, there should be a mandatory condition that such the project
developer would not compete in competitive bidding for long-term PPA
based power procurement in order to avoid unequal competition since
only few developers would have such coal blocks. For allocation of linkage
or coal blocks for MPPs, an additional condition should be that captive
mining must begin within a period of 3 to 4 years failing which the
allocation should be cancelled.

16. For providing transmission corridors for such MPPs, adequate redundancy
should be built at the stage of transmission planning. Presently, also there
is a redundancy of about 20-25% in the transmission planning. There is
need to identify the major load centres who would draw power from such
MPP. These load centres would be most likely situated in northern and
western region where many States are deficit in power supply. Therefore,
the required redundancies could be planned from the likely location of the
MPP (which would be in eastern region) to such load centres. The cost of
providing such redundancy should be absorbed in the transmission tariff
by the concerned beneficiaries. This would be in the long-term interests of
consumers who will gain from efficiency arising out of competition among
the generators.

17. Tariff Policy envisages a National Transmission Tariff Framework


sensitive to distance and direction and related to quantum of power
offered. CERC is in the process of developing such a Framework which
needs to be done expedited. This would be a necessary pre-requisite for
promoting open access and power trading.

18. There is urgent need for regulations for providing grid connectivity to
MPPs. The National Electricity Policy already provides that prior
agreements would not be a pre-condition for network expansion and the
transmission utilities should undertake network expansion after identifying
the requirements in consonance with the National Electricity Plan and in
consultation with the stakeholder, and taking up the execution after due
regulatory approvals.

19. The reduction in cost of production of coal on account of higher efficiency


in captive coal mining should be passed on to the consumers through
reduced cost of bulk power. The coal blocks should be offered on the
basis of competitive bidding as part of the integrated coal mine-cum-
power project to achieve this objective. Any other method of allocating

47
th
Executive Summary Working Group on Power-11 Plan (2007-12)

coal blocks for power projects is not likely to pass on the efficiencies of
captive coal mining to the consumers.

20. As long as there is shortage of natural gas and the two major users of gas
fertilizer and power work in a regulated cost plus environment, price of
domestic gas and its allocation should be independently regulated on cost
plus basis including reasonable returns.

21. Like crude oil and coal, natural gas and LNG may also be included in the
category of declared goods so that central sales tax of 4% is levied on
them and exemption from any state sales tax is extended.

22. Import duty on coal has been lowered to 5%. This position needs to be
continued as we would be depending on imported coal for generation.

23. Exemption of import duties available to generation projects under Mega


Policy should be available to all important transmission projects where
imported components form large part of the project cost.

24. Nuclear power stations are likely to be segregated from other strategic
nuclear installations in future. In that case, tariff determination from
nuclear power stations should be done through regulatory mechanism in a
transparent manner adopting two part tariff structure and efficient
operating norms.

25. There is a need to levy cess on the basis of consumptive use of water.
This would encourage closed cooling system which is the need of the hour
considering decreasing availability of water at project sites.

26. Service conditions of staff of the Regulatory Commissions and BEE


should be made attractive. Such staff should be eligible for housing
accommodation, medical facilities etc. on the lines of Government
employees.

27. State Governments should be asked to establish the Regulatory


Commission Funds at the earliest. This could be one of the follow up
points while releasing central assistance to the States.

28. There is a need to put in place a mechanism for periodical training/


reorientation for staff of the Commissions and for newly appointed
regulators. A corpus could be made available to the Forum of Regulators
(FOR) for this purpose income from which could be used for the training
programmes. The training programme and the training institutions should
be settled by FOR after taking into account guidelines issued by the
Central Government in this regard.

29. FOR has been entrusted with number of responsibilities in the Tariff Policy
with a view to ensure consistency in the regulatory approach. For

48
th
Executive Summary Working Group on Power-11 Plan (2007-12)

discharging this role, the FOR would require consultancy for availing
relevant expertise including international experience on various matters.
Central Government should provide funds for this purpose.

30. FOR should also compile periodically various progressive orders of the
SERCs for sharing the best practices. The compilation may also include
important judgments of the Appellate Tribunal for Electricity.

31. To bring in appropriate accountability of the regulatory process, proposed


regulations of the Regulatory Commissions should be examined indepth at
draft stage itself. Further, there is a need for scrutinizing the regulations
for ensuring consistency with the letter and spirit of the law before they are
laid in the Parliament/ State Assembly. This is important since regulations,
once published in the gazette, become sub-ordinate legislation.

32. FOR should also undertake periodical review of implementation of the


National Electricity Policy and Tariff Policy since the law requires the
Commissions to be guided by these policies.

33. High loss making feeders may be franchised by distribution companies.


Towns having ATC losses higher than 35% may be franchised on input
energy basis immediately. Towns having losses between 25-30% should
be observed for improvement for 6 months and if there is no improvement,
these towns should also be franchised.

34. Through appropriate metering and energy audit, feeders incurring high
level of losses (may be more than 20% for urban feeders and more than
35% for rural feeders, this would depend on the stage in which distribution
reforms are in a particular state) should be identified. Performance of the
staff should be then assessed on the basis of Key Performance
Indicators(KPI) which would be primarily loss reduction. ATC loss
reduction of 3% every year in next five years should be targeted. The
Tariff Policy emphasizes on the need of putting in place local area based
incentive/disincentive scheme for the staff linked to distribution losses.
This should be immediately implemented by the SERCs.

35. The robust legal framework contained in the Act for control of theft is being
further strengthened. Annual conferences of power utilities should be
organized at national level for highlighting success stories and
achievement made in different States in controlling theft.

36. To enlist public support for rapid reduction of commercial losses, the list of
high losses feeders should be publicized periodically.

37. To realize the objective of Tariff Policy of supplying uninterruptible


electricity to those consumers who are ready to pay efficient cost, the
distribution tariff should move to distribution margin model which is also
provided in the Tariff Policy. Such distribution margin could be based on

49
th
Executive Summary Working Group on Power-11 Plan (2007-12)

loss reduction trajectory in a MYT framework and the actual power


purchase costs should be paid by the consumers over and above the
distribution margin. Consumers of a particular area should be given option
to collectively choose either uninterruptible supply or otherwise and the
tariff could be determined accordingly.

38. Setting up of peaking power stations should be encouraged to overcome


peaking shortages as the additional power costs of supply from such a
station could be then passed on to the consumers who opt for
uninterruptible supply.

39. Use of electronic meters and spot billing should be expanded rapidly and
State should be emphasized upon to do so.

40. FOR should develop a model agreement for distribution of electricity by


distribution licensee through a franchisee in urban areas outlining the
responsibilities and duties of various parties clearly.

41. There have been some experimental efforts, with good success, for
outsourcing distribution of electricity for an identified feeder by the
licensee to a private entrepreneur selected competitively. This model
needs to be supported fully and replicated in high loss areas.

42. Necessary financial assistance may be provided to consumer groups


having proven track record for facilitating effective representation before
the Regulatory Commission. In addition, Central Government should also
arrange orientation programmes to educate these groups about various
provisions of the law and rules. Such scheme(s) should be administered
by the Department of Consumer Affairs.

43. The Rural Policy provides that standalone systems of upto one MW would
have automatic approval for

a. Land use change for area as per norms

b. Pollution clearance if technology is proven within laid down norms


and

c. Safety clearance on the basis of self certification.

These policy measures need to be implemented by the concerned


authorities at the earliest.

44. Schemes for separation of agricultural feeders in rural areas need to be


promoted. Agricultural consumers could be supplied electricity as per
seasonal demand for agricultural purpose and the tariff could be fixed
taking into view off-peak pricing and uninterruptible supply.

50
th
Executive Summary Working Group on Power-11 Plan (2007-12)

45. Schemes for transferring subsidies directly to consumers may be


encouraged.

46. State Government should set up a dedicated planning cell for developing
electricity plan at the State level including specific projects which could be
posed for investment to the power sector. Such a plan could be on the
lines of National Electricity Plan.

47. With the objective of promoting more efficient use of electricity and also to
provide another payment option to the consumers, use of pre-paid meters
needs to be promoted.

48. In order to assess the progress made in achieving higher energy


efficiency, suitable mechanism should be put in place indicating the clear
cut methodology for computing various parameters in this regard.

49. Statutory rules may provide for periodical refresher training for all the O&M
personnel in different segments i.e. generation, transmission and
distribution. In addition, refresher training may also be provided to all other
personnel in power sector as per the requirement of their work areas.

50. A national programme needs to be launched for training and capacity


building for upgrading and enhancing the skills of franchisee who are
proposed to be deployed on a large scale for rural as well as urban areas.

9.0 ISSUES CONCERNING KEY INPUTS


9.1 FUEL

9.1.1 Coal Requirement / Availability for 11th Plan

Coal Demand – Supply Projection for Power Sector


(11th Plan Period)
(As Projected By CEA)

DESCRIPTION 2006-07 2007-08 2008-09 2009-10 2010-11 2011-12


Installed Capacity 63490 72440 75870 81095 90675 101597.5
Additions 8950 3430 5225 9580 11450 16950
Retirements 0 0 0 0 527.5 259
Total Installed Capacity (MW) 72440 75870 81095 90675 101597.5 118816
Normative Coal Reqmnt 362.20 379.35 405.48 453.38 507.98 594.08
(Linkage) (MT) @

(Details are given in Table 9.7 of main Working Group Report)

51
th
Executive Summary Working Group on Power-11 Plan (2007-12)

@ For calculation of linked coal requirement for the above installed capacity,
average 5 MTPA per 1000 MW of capacity, has been considered. This coal
requirement projection does not include coal requirement for captive power
plants (CPPs).

However, all the units envisaged for capacity addition, as shown above – year-
wise, may not be in full commercial operation for the whole periods of those
particular years, in which these units shall be commissioned. So, considering
that aspect, the following generation level – year-wise has been targeted by
CEA and corresponding coal requirement are worked out as under.

DESCRIPTION 2007-08 2008-09 2009-10 2010-11 2011-12


Total Generation (BU) (^) 499.5 536.0 587.9 660.8 764.5
Total Coal Requirement 354.9 380.4 417.6 470.0 544.5
(MT) including Transit Loss
@1%
Coal Availability
- From CIL (MT) # 287.27 311.55 343.80 376.74 405.79
- From SCCL (MT) $ 27.01 27.19 27.69 28.40 28.97
- From Captive Mines 9.75 23.60 36.47 41.50 47.30
Total Availability (MT) 324.03 362.34 407.96 446.64 482.06
Gap between Supply & -30.87 -18.06 -9.64 -23.36 -62.44
Demand (MT)

(^) Generation is projected (as projected by CEA), assuming PLF of 76% in 2006-07 & 2007-
08 and 77% in subsequent years existing units and 85% for new capacity additions, with
due consideration of initial commissioning period for new units.
# CIL’s projection of Coal Production including their emergency production plan, considered
here, is provided by Working Gr. member from CIL. Distribution of around 72% of CIL coal
to Power Sector (except CPPs) considered here based on historical supply figures and as
considered by CEA for their computation & analysis purpose.
$ SCCL’s projection of Coal Production, considered here, is provided by SCCL. Distribution
of around 71% of SCCL coal to Power Sector (except CPPs) considered here based on
historical supply figures and as considered by CEA for their computation & analysis
purpose.
(X) Coal Production from Captive Mines in the terminal year of 11th. Plan, as projected by CEA. However,
as per projections made in the Draft Report by the Working Group on Coal & Lignite, under the
Chairmanship of Secretary (Coal), out of 127 captive blocks allotted so far, about 60 have already
submitted mine plan to Coal Controller’s organization, indicating production projection of about 104
MT by 2011-12. Remaining block-holders are also expected to submit mine plan shortly. Out of 104
MT of coal production, as projected, around 65.95 MT will be available for Power Sector (Utilities) in
2011-12. However, achievement of this production level or even enhanced level from Captive Mining
are possible subject to expeditious approval of Mining Plan, various notifications for Land
Acquisitions, Environment Clearances & other clearances / approvals, as elaborated in this report,
later on.

52
th
Executive Summary Working Group on Power-11 Plan (2007-12)

9.1.2 Capacity Addition in 11th Plan vis-à-vis Coal Tie-Up (As projected by
CEA)

Description Capacity Normative


(MW) Requirement
(MT)
Coal Linkage Available 32455 162.28
Block Allocated 5830 29.15
Imported Coal tied up 0 0
TOTAL AVAILABLE 38285 191.43
Linkage required to be accorded 4500 22.50
Block required to be Allocated $ 2500 12.50
Imported Coal to be tied up 1350 4.05
TOTAL TO BE TIED UP 8350 39.05
TOTAL COAL BASED CAPACITY ADDITION (MW) 46635 230.475
IN 11th PLAN

$ Projects totaling to 1750 MW have applied / applying for coal blocks, however, during 11th. Plan
it would require tapering coal linkages.

9.1.3 Gas scenario

At present 2114 MW Gas Based Power Project have been included in the 11th
Plan against the target of 50124 MW by thermal capacity. The additional power
could be planned / generated based on the following factors which would
however largely influence the ultimate gas demand in the power sector.

• Assured supply of gas and its time frame


• Price of gas and stability for 15 years
• Expanding the scope of regulator for regulating the price of gas.

9.2 TRANSPORT

9.2.1 Railways: Present Scenario

Important modes of transport of coal in India are Railways, Road, Merry-go-


Round Systems, Conveyor Belts and the Rail-cum-Sea Route. Railways
constitute the major system of coal transportation in India and coal is the largest
single commodity transported by the Railways. The dispatch of coal by rail is
governed by the Preferential Traffic Schedule of the Indian Railways, under
which the program of movement is to be sponsored by the various sponsoring
authorities and accepted by the coal companies. In case of deregulated coal,
Railways have allowed coal companies to sponsor the movement of coal.

Coal requirement of some consumers in Southern India, which include power


stations and cement plants, are met by moving coal by Rail-cum-Sea Route. This

53
th
Executive Summary Working Group on Power-11 Plan (2007-12)

is done in view of the difficulties experienced in moving coal via all Rail Routes
from Bengal-Bihar and Main Line-Talcher Coalfields. The requirement of power
stations of Tamil Nadu Electricity Board (TNEB) is met by Rail-cum-Sea Route.
Haldia, Paradip and Vizag Ports handle the shipments.

¾ Some load center projects have been identified for expeditious


implementation to meet the increased power requirements for the
forthcoming Commonwealth Games-2010 to be held in Delhi. Such
projects of NTPC are Badarpur Expansion (1000 MW), Dadri (Coal)
Expansion (980 MW) and Jhajjar JV Project (1500 MW).

¾ At present 26 rake per day are being moved through over crowded
Railways section between Mughalsarai & Delhi which caters to existing
plants at Badarpur and Dadri (Coal). The number of rakes will increase to
34 rake / day when both of the expansion projects at Dadri and Badarpur
are commissioned. Railways need to gear up to tackle this increased
movement of coal in this section.

¾ In the case of proposed Jhajjar project to be implemented by NTPC in


Joint Venture with Delhi and Haryana, Problem exists in transportation of
coal beyond Mathura up to the plant i.e. the section from Mathura to
Jharli (station nearest to Jhajjar: Total distance is 240 Kms.) is single-
lined. Power project at Hissar in Haryana is also being implemented
during the same time frame which will also be using the same Railways
line. Considering the above and also considering the proposed
requirements of the power stations in the adjoining region this section
needs to be made double-lined.

9.3 PORT FACILITIES

9.3.1 Ports: Present Scenario

Ports form a critical part of transportation infrastructure of our country. India has
about 6000 km. of natural peninsular coastline. There are 12 major and 185
minor ports in India. Major ports handle about 75% of the country’s port traffic.

Present capacity for coal in Indian Ports account for about 65 Million Tonnes (as
on 31.03.2005) and it will be enhanced to about 142.87 Million Tonnes by 2013-
14, as projected by National Maritime Policy on Port & Shipping Sector.

54
th
Executive Summary Working Group on Power-11 Plan (2007-12)

9.3.1.1 Present & Proposed Capacity Additions by Indian Ports


(Commodity-wise)

(In Million Tonnes)


Commodity Existing Capacity requirement Additional Capacity
Capacity as on by 2013-14 Estimated by 2013-14
31-3-2005

POL 157.35 248.56 91.21


Iron Ore 51.00 126.75 75.75
Coal (including 65.00 142.87 77.87
coking coal)
Container Tonnage 49.55 235.56 186.01

Container TEUs 4.13 19.63 15.50


General Cargo 77.10 163.85 86.75
TOTAL: 400.00 917.59 517.59

9.4 CONSTRUCTION AND MANUFACTURING CAPABILITIES

9.4.1 Manpower requirement for Hydro Projects (Supervisory Staff)

Category Estimated Available Augmentation


requirement required
Senior level Executives 550 330 220
Middle level Executives 2000 1200 800
Junior level Executives 4300 2600 1700
Non executives 1700 1000 700
Total 8550 5130 3420

9.4.1.1 Manpower requirement for Hydro Projects (Workers)

Sl No Type of Worker Estimated Available Augmentation


requirement required
01 Skilled 33000 20000 13000
02 Un skilled 50000 30000 20000
Total 83000 50000 33000

55
th
Executive Summary Working Group on Power-11 Plan (2007-12)

9.4.2 Manpower requirement for Thermal Projects (Supervisory Staff)

Category Estimated Available Augmentation


requirement Required
Senior Level Executive 1014 660 354
Middle Level Executive 3702 2400 1302
Junior Level Executive 7308 5040 2268
Supervisors/ Non- 12780 8280 4500
executive
Total 24804 16380 8424

9.4.2.1 Manpower requirement for Thermal Projects (Workers)

Category Estimated Available Augmentation


requirement Required
Mechanics 1770 1200 570
Electricians 1062 720 342
Crane operators 3540 2400 1140
Drivers 8820 5760 3060
LP welders 7080 4800 2280
HP welders 1062 720 342
Aluminium welders 177 120 57
Fitters 10620 7200 3420
Riggers 9570 6020 3550
Insulation 354 240 114
applicators
Cable jointers 885 600 285
Carpenters 3312 2196 1116
Masons 7080 4800 2280
Bar benders 2478 1680 798
Total 55090 37736 17354

9.4.3 Requirement of construction equipment

9.4.3.1 Hydro Projects (Main Equipments)

Main Equipment required to be procured during 11th plan could be summarized


as below:

56
th
Executive Summary Working Group on Power-11 Plan (2007-12)

Sl. Particulars of Estimated Available Augmentation


No equipment Requirement Required
1 Hydraulic Drill Jumbos (1 210 85 125
to 3 boom)
2 Hydraulic Excavators (0.2 520 210 310
to 5.2 cum)
3 Loaders 540 220 320
4 Dozers 420 165 255
5 Dumpers (12T to 35 T) 730 290 440
6 Road Rollers 55 20 35
7 Raise Borer/Climber 45 20 25
8 Concrete Batching plant 210 85 125
(30 to 360 cum/hr)
9 Aggregate Processing 110 40 70
Plant (50 to 600 TPH)
10 Tower Crane (6.5 to 10 120 45 75
T)
11 Shutter with travellers 470 190 280
12 Dry Shotcrete machines 440 180 260
13 Wet Shotcrete machines 130 50 80
14 Cranes (5 T to 60T) 405 160 245
15 EOT/ Gantry Cranes (10T 175 70 105
to 20T)

9.4.3.2 Thermal Projects (Main Equipments)

The major equipment required to be deployed for simultaneous construction of


24 projects of less than 500 MW and 21 projects of more than 500MW is
summarized below.

S.No. Particular of equipment Estimated Available Augmentation


Requirement required
1) 325 T Fm Crane Or Equivalent 47 12 30
2) Sumitomo crane or equivalent 150 t 177 120 57
3) Crawler mounted crane 100 t 90 72 18
4) Crawler mounted crane 75 t 444 312 132
5) Mobile crane - 20 mt / 8 mt 1206 732 474
6) Mobile crane – 40 mt 156 98 58
7) Heavy duty trailer 20-50 mt 1206 732 474
8) Dumpers 3540 3540 --
9) Dozers ( heavy duty d-6 & d-8) 132 68 64
(hydraulic)
10) Vibro compactors 444 312 132
11) Concrete pump 444 312 132
12) Truck mounted concrete pumps 177 100 77

57
th
Executive Summary Working Group on Power-11 Plan (2007-12)

S.No. Particular of equipment Estimated Available Augmentation


Requirement required
with placing boom
13) Transit mixer (min. 5 cum. 884 528 356
Capacity)
14) Batching plant (more than 30 cum. / 288 166 122
hr. Capacity)
15) Rotaritory hydraulic piling rig 177 100 77
16) Compressors 177 100 77
17) DG sets 354 200 154
18) Boring equipment for trench less 45 31 14
construction
19) Welding machines 12060 12060 ---
20) Slip form equipment 45 31 14
21) Strand and jack arrangement for 21 1 20
boiler
22) ETDA cleaning arrangement for 21 1 20
boiler
23) Passenger cum goods lifts for boiler 156 98 58
24) Induction heating machines 156 98 58
25) Gantry Crane 156 98 58
26) Pock lain 444 312 132
27) Tipper 3120 1960 1160

9.5 REQUIREMENT OF KEY INPUT MATERIALS

Total requirement of various materials for Capacity Addition planned during 11th
& 12th Plans
Lakh Tonnes

Material 11th Plan 12th Plan


68,869 MW 82,200MW
Cement 306.3 470.0
Structural Steel 80.4 94.4
Reinforcement Steel 51.3 70.1
CRGO Steel 10.7 13.5
Castings 0.4 0.5
Forgings for TG sets 0.4 0.5
Special Steel for Sub-Stations 3.3 3.3
Steel for Conductors in Transmission 2.7 2.7
system Lines
Steel for Conductors in distribution system 4.5 5.7
Lines
Aluminium 16.0 18.6

58
th
Executive Summary Working Group on Power-11 Plan (2007-12)

Material 11th Plan 12th Plan


68,869 MW 82,200MW
Copper 8.1 8.1
Zinc 1.45 1.51
Thermal Insulation 2.5 3.1
Static Meters with downloading facility 12.44Crores 4.96Crores
(Nos.)

9.6 RECOMMENDATIONS

9.6.1 Coal and Lignite

Domestic coal would continue to be the main stay for thermal power generation
in India. In order to make available the coal and lignite for power generation
following are recommended:

9.6.1.1 Coal Mining

1. Coal Sector may be given “Infrastructure Status” with ‘Tax Holiday’ & Duty
exemptions as at present the total duty incidence on mining
equipment/spares is about 50-55 % after including the countervailing and
other additional duties.
2. Alternatively, the concept of Mega Project may be introduced in the coal
sector also by according Mega Status to Coal Mines of production level of
5 MTPA or above and providing benefits of tax / duty concessions.

3. Deployment of state-of-the-art technology in the Indian mines for


enhancing the productivity and exploitable quantity of coal needs to be
encouraged by liberalization of import policy.
4. All coal blocks with firm Geological Report (GR) may be earmarked with
no reservation / blocking.
5. Mobilization of the investment in coal mining requires inducting and
encouraging more players from both public and private sectors.
6. Reputed International Coal Companies may be encouraged to come to
India which will facilitate introduction of latest mining technologies and
mine safety measures.
7. There is an urgent need to encourage more exploratory agencies and for
relaxation of mandatory supervision by CMPDIL alone.
8. The pace of regional surveys and drilling needs to be accelerated to
complete the comprehensive coal resource assessment exercise at the
earliest.
9. The list of agencies authorized to supervise may be expanded and the
Govt. agencies which are otherwise permitted to under take exploration
without seeking project specific exploration license could also be
authorized to supervise the exploration by other players. Further, new
Public Sector agencies including their joint venture such as JV of NTPC &

59
th
Executive Summary Working Group on Power-11 Plan (2007-12)

SCCL may also be entrusted with the task of new exploration and
accorded exemption from obtaining exploration license.
10. Expeditious environmental clearance needs to be accorded by MOEF on
priority for 11th Plan coal mining projects.
11. Formulation of unified R&R policy and simplification of issuance of
notification and clearances shall help in expeditious development of coal
mining projects.
12. In case of more than one nearby coal mine projects, centralized/
combined forestation at a suitable location needs to be accepted.

9.6.1.2Lignite

1. At present only a small percentage of the total reserves of lignite have


been exploited. This needs to be enhanced to make use of this proven
source of energy. Allocation of Lignite blocks to interested developers
could facilitate faster growth of Lignite Production. If generation target is
enhanced to around 80% PLF, there will likely be shortfall in tune of 2
MTPA.

9.6.2 Railways

1. Railways need to expedite sectoral studies, development of suitable plans


and ensure adequate rail network for coal movement. Dedicated trunk-
routes for coal transport to the power project need to be developed.
Interim measures to be taken if dedicated freight corridor does not come
up in 11th Plan period.
2. Development of new rail links is required to be expedited along with the
Railways connectivity with Ports.
3. Timely establishment of rail links with allotted coal mining blocks.
4. Rail freight rates for coal transport may be rationalized.
5. The Railways, Coal and Power Ministry may work together to draw up a
well conceived model of Fuel Supply & Transport Agreement (FSTA).

9.6.3 Ports

1. Port capacity needs to be augmented to meet the increased infrastructure


requirement.
2. To expeditiously complete the existing projects like captive coal jetty at
New Mangalore Port, Coal Berth at Ennore port, Deepening Channel at
Paradeep port.
3. The major ports of the country may be developed as mega ports with
satellite ports dedicated to cargo like coal.
4. Port connectivity through seamless hinterland road and rail development
needs to be enhanced to meet the requirement of imported coal.

60
th
Executive Summary Working Group on Power-11 Plan (2007-12)

9.6.4 Natural Gas

Natural gas is the fastest growing primary energy source amongst fossil fuel. Gas
supply to the existing gas based power stations has been inadequate and the
plants have been operating at around 58-60% PLF. The gas based stations
comparatively have shorter gestation period and are easier to operate. Following
are recommended in this regard:

1. The Government Quota of Gas from fields allotted / to be allotted under


NELP as per the respective Production Sharing Agreement should first be
utilized to meet the shortfall in supply from the linkage of existing
customers before allocation to others
2. There is need to ensure that assets like Gas Based Power Plants which
have been set up with substantial investment are not stranded / idle or
inadequately utilized on account of constraints of Gas / Infrastructure
availability and should get priority over new units . Therefore, while
granting Open Access for transportation of gas to sectoral players,
preference should be given to existing customers of gas.
3. Planning Commission, Govt. of India should facilitate the allocation of gas
to new gas based projects as well as in setting the reasonable pricing of
gas for power generation.

9.6.5 Key Input Materials

With a view to help industries to plan/ allocate build up their capacities over a
longer time frame, assessment of material requirement for 11th and for 12th Plan
period on a broad basis have been made and on prima facie considerations,
availability of various materials required for capacity addition planned for 11th &
12th Plan may not be a constraint unless requirements get bunched up in any
particular year. Following are recommended in this regard:

1. CRGO being the critical input for transformers and imported item, needs to
be exempt from Customs Duty to bring down the cost of transformers.
This is particularly important in view of the massive distribution system
augmentation planned in the 11th plan.
2. Simultaneously. Domestic producers may be encouraged for production of
CRGO as in the past non-availability of CRGO has led to delay in project
implementation.
3. Detailed analysis of the key materials availability for power sector needs to
be done by Planning Commission considering requirement of other
sectors of the economy.
4. The number of static meters required for 11th Plan is of the order of 12.44
crores. The manufacturers of static meters need to be geared up to meet
such huge requirements.

61
th
Executive Summary Working Group on Power-11 Plan (2007-12)

9.6.6 Capability for manufacture of main plant equipment by indigenous


manufacturers, m/s BHEL for coal based power plants

1. M/s BHEL is the only major manufacturer of main power plant equipment
for thermal and hydro power projects in India. In the 10th Plan , the main
plant equipments for 65% of the thermal capacity addition, are being
supplied by BHEL. In the year 2003-04 BHEL received major orders
totalling to 5125 MW to be commissioned by 2006-07. Some of the units
out of this capacity are found to be slipping from 10th Plan target . This
matter was taken up with BHEL and a study was carried out by CEA for
the reasons leading to the delay. It has been found that it was mainly
due to inadequate manufacturing capacities of its various manufacturing
units , delay in finalization of orders for Balance of Plant (BoP) for EPC
contracts and shortage of construction /commissioning machinery, and
manpower. With the present capacity existing in BHEL manufacturing
plants, BHEL can deliver equipment only up to 3000 MW per year for coal
based projects . This was taken up with BHEL and they are proposing to
increase this capacity to 4675 MW by Dec. 2007 and further to 6475 MW
by the year 2010-11 for coal based power projects. Similarly the
manufacturing capacity for Hydro projects would also need augmentation
to cater to the increased requirements for 11th & 12th plan.

2. Based on the capacity additions planned for coal fired thermal power
projects, the following position emerges:

Sl Year of 2007-08 2008-09 2009-10 2010-11 2011-12 Grand


No. Commissioning/ Total
Details
i) BHEL’s Capabilities 3000 4675 4675 6475 6475 25300
(MW)
ii) (a) Orders received by 2170 2945 5730 6475 6475 23795
BHEL/ likely orders (likely)* (likely)
(MW)
(b) Orders by other 1260 2280 3850 4975 10475 22840
manufacturer (MW)
Total (MW) 3430 5225 9580 11450 16950 46635
* assuming that the full capacity of BHEL would be utilised

1. From the above it is evident that BHEL would be finding it difficult to


meet the commissioning targets for the year 2009-10. Further, for
the years 2010-11 and 2011-12, equipment for huge capacity has
to be supplied by other manufacturers to meet the capacity addition
targets.
2. Accordingly, it is informed that the country needs to develop
additional manufacturers of main plant equipment to meet the
projected capacity addition targets and also to induce competition

62
th
Executive Summary Working Group on Power-11 Plan (2007-12)

in the market for achieving a lower price/tariff. This has also been
emphasised by the Honble Minister of Power in the past, while
finalising the capacity addition programs. BHEL needs a substantial
expansion in the manufacturing capacity for thermal and Hydro
plants.

9.6.7 Construction Capability

Capability of construction agencies, availability of construction equipment,


appropriate construction technology and manpower are vital for implementation
of the capacity addition programme. Construction industry in India has grown
significantly and has acquired adequate experience in the field of construction
and infrastructure projects. Following are recommended in this regard:

1. Construction agencies are available in India (Domestic as well as


International) for taking up hydro as well as thermal power projects in 11th
Five Year Plan. Augmentation of manpower and construction equipment
would be required by the construction agencies to meet the targets.
2. Serious efforts need to be made by the major power companies to
develop vendors for supply and erection of equipment and for taking up
civil construction.
3. Power Projects should be granted infrastructure status for qualifying for
exemption of taxes and duties.
4. Government should consider taking up construction of approach road to
feasible project sites through a common fund to be recovered from the
developers subsequently.
5. Single window clearance should be encouraged with time frame for all the
statutory clearances required by the developers.
6. Immediate action need to be taken to create at least 10 Accredited
Training Institutions at different geographical locations for skill building in
specific areas like HP Welder, Aluminum Welders, Crane Operators,
Cable Jointer etc. vocational training wing of Ministry of Education,
NICMAR and CIDC could play the part of nodal agencies for such
institutions.
7. Cooperation of State Govt. must be ensured to facilitate smooth land
acquisition and implementation of R&R Plan.
8. New technologies like RCC Dam, jet grouting and use of Geotextile/
geosynthetics in place of filter materials should be adopted in Hydro
Projects.
9. Use of latest construction equipment like Tunnel Boring Machine (TBM),
Road Headers, Raise Borers, Forepoling machines, Jet grouting
Equipment, Hydro fraise equipment etc should be encouraged to achieve
fast progress.
10. Low bed wagons for transportation of transformers/generators/stator/boiler
drum need to be augmented at least by 14 Nos.

63
th
Executive Summary Working Group on Power-11 Plan (2007-12)

9.6.8 Integrated Energy Policy

Integrated Energy Policy – Report of the Expert Group under the Chairmanship
of Shri Kirit S. Parikh, Member, Planning Commission, Govt. of India has
addressed wide ranging issues and has suggested policy initiatives to provide
energy availability and security for sustainable economic development. A few of
the important issues delineated in the policy and impacting the power sector
needs to be implemented. Following are recommended in this regard:

1. Standardization of Main Plant equipment in bands of different unit sizes is


desirable particularly from the point of view of faster capacity addition;
however there is a need for an Empowered Committee for centralized
procurement and to bench mark the price for different unit sizes.
2. The rate of return on the investment in power sector has to be adequate to
attract investment and to compete with the opportunities of investment in
other sectors.
3. To ensure capacity addition through tariff based completive bidding there
is a need to create an enabling framework by both State and Central
governments in the areas of allocation of site, water & fuel linkage,
environmental clearance, R&R etc.
4. Coal price for supply of coal under long term agreement should not be
linked with e-auction coal price as it will only push up the coal price.
Further, linking of coal price with the imported coal price would also not be
appropriate. There is an urgent need of Regulator in Coal Sector.
5. The captive coal mining blocks should be fully explored with ready
Geological Report (GR), so as start the production from captive coal
blocks in a timely manner.
6. Opening up of coal sector to promote competition.
7. Allocation of coal mining blocks for generation sector based on least cost
generation.
8. Open access to the Gas network should be ensured to promote
competition in gas sourcing. Role of Regulator in Oil & Gas sector needs
to be expanded to include gas pricing.

64
th
Executive Summary Working Group on Power-11 Plan (2007-12)

10.0 FINANCIAL ISSUES AND POWER SECTOR FINANCING

10.1 During 11th Plan period, the overall generation capacity addition of 68,869
MW is envisaged. (Refer Para 10.2.3 of main Working Group Report)
(MW)
SECTOR HYDRO THERMAL NUCLEAR TOTAL

Projects Under Construction 11,931 16,254 3,160 31,345


Committed Projects 3,654 33,870 0 37,524
Total capacity 15,585 50,124 3,160 68,869

10.2 The overall requirement of funds in 11th Plan has been estimated as Rs.
1,031,600 crore with details as follows: (Refer Para 10.9 main Working Group
Report)
( Rs. Crore)
Particulars State Central Private Total
Generation including Nuclear 1,23,792 2,02,067 85,037 4,10,896
DDG 20,000 20,000
R&M 15,875 15,875
Transmission 65,000 75,000 1,40,000
Distribution including Rural electrification 2,87,000 2,87,000
HRD 462 462
R&D Outlay 1,214 1,214
DSM 653 653
Total Power Sector 4,91,667 2,99,396 85,037 8,76,100
NCES and Captive 22,500 93,000 1,15,500
Merchant Plants 40,000 40,000
Total Funds Requirement 5,14,167 2,99,396 2,18,037 10,31,600

Year wise Funding Requirement for 11th Plan

(Rs. Crore)
2007-08 2008-09 2009-10 2010-11 2011-12 Total
1,32,264 1,74,003 2,24,754 2,52,707 2,47,872 10,31,600

10.3 The details of major sources and estimated mobilization, funding


gap and possible sources of bridging the gap is given below in following
Tables (Refer Para 10.11 of main Working Group Report)

65
th
Executive Summary Working Group on Power-11 Plan (2007-12)

(Rs. Crore)
Description State Central Private Total
Funds required 5,14,167 2,99,396 2,18,037 10,31,600
A) Equity Required (D/E - 70:30) 1,54,250 89,819 65,411 3,09,480
B) Equity Available
1 -Promoters including FDI for IPPs 0 0 25,511 25,511

-Promoters including FDI for NCES & Captive 0 0 27,900 27,900


-Merchant Power Plant 12,000 12,000
2 Internal Resources 0 62,922 0 62,922
3 Govt. Support
3.1 State Govt. 0 0 0 0
3.2 Central Govt. 0 0 0 0
C) Total Equity Available 0 62,922 65,411 1,28,333
D) Additional Equity to be arranged (A-C) 1,54,250 26,897 0 1,81,147
E) Debt Required (D/E - 70:30) 3,59,917 2,09,577 1,52,626 7,22,120
F) Debt Available
1.1 Direct Market Borrowing 10,000 15,000 0 25,000
1.2 Banks and AIFIs 37,173 58,415 10,621 106,210
1.3 PFC 64,960 8,120 8,120 81,200
1.4 REC 47,320 5,915 5,915 59,150
1.5 IIFCL 0 6,000 9,000 15,000
2.1 Multilateral/Bilateral Credits 5,520 19,320 2,760 27,600
2.2 ECA/ECB/Syndicated Loan etc. 0 46,000 11,500 57,500
G) Total Debt Available 1,64,973 1,58,770 47,916 3,71,660
H) Additional Debt to be arranged (E-G) 1,94,943 50,807 1,04,710 3,50,460
I) Additional Equity & Debt required (D+H) 3,49,193 77,704 1,04,710 5,31,607
J) Total Availablity of Debt and Equity 1,64,973 2,21,692 1,13,327 4,99,993
K) Funding by Special Schemes
1 APDRP 40,000 0 0 40,000
2 RGGVY 40,000 0 0 40,000
L) Total shortfall to be arranged (I-K) 2,69,193 77,704 1,04,710 4,51,607

66
th
Executive Summary Working Group on Power-11 Plan (2007-12)

Summary of Funds Requirement and Mobilization for


Different Debt: Equity Scenario
( Rs. Crore)
Description D/E D/E
70:30 80:20
Funds required 10,31,600 10,31,600
Equity Required 3,09,480 2,06,320
Total Equity Available 1,28,333 1,28,333
Additional Equity to be arranged 1,81,147 77,987
Debt Required 7,22,120 8,25,280
Total Debt Available 3,71,660 3,71,660
Additional Debt to be arranged 3,50,460 4,53,620
Additional Equity & Debt required 5,31,607 5,31,607
Less: Funding by Special Schemes 80,000 80,000
Total shortfall to be arranged 4,51,607 4,51,607
Equity required after funding from special schemes 1,21,147 17,987
Debt required after funding from special Schemes 3,30,460 4,33,620

10.4 PROPOSED MEASURES FOR REDUCING FUNDING GAP

1. Modification of ECBs guidelines permitting infrastructure borrowers


including intermediaries PFC, REC, IDFC etc to borrow funds from
overseas market under automatic approval route and Debt Servicing to be
eligible for exemption under Section 10 (15) (iv) of Income Tax Act. (Refer
Para 10.16.1.1 of main Working Group Report)

2. Introduce Power Bonds or Vidyut Vikas Patra, as transferable bearer


instrument for wider retail participation (Refer Para 10.16.1.2 of main Working
Group Report)

3. Additional investment limit of Rs. 50,000 per year for infrastructure bonds
under Section 80C of the Income Tax Act, 1961 over and above existing
limit of Rs. 1,00,000 with a lock in period of at least 5 years. Expected
mobilization over 5 years is estimated at Rs. 1,50,000 crore. (Refer Para
10.16.1.3 of main Working Group Report)

4. Long term Capital Gains Bonds: Allow Section 54EC benefit under Income
Tax Act for bond issuances by PFC & IIFCL in line with REC & NHAI.
(Refer Para 10.16.1.4 of main Working Group Report)

5. Possible Sources of Bridging the Gap

67
th
Executive Summary Working Group on Power-11 Plan (2007-12)

(Rs. Crore)
S. No. Particulars Estimated Amount
Debt
1 Power Bonds 50,000
2 Tax incentive under Section 80 C 1,50,000
3 Bonds under Section 54EC 50,000
4 Insurance 20,000
Sub Total 2,70,000
Equity
5 IPO/FPO 15,000
Grand Total 2,85,000
Net Gap 1,66,607

6. Reinstatement of 10(23) G benefit (tax exemption on interest income from


infrastructure projects) to be reintroduced. (Refer Para 10.16.1.5 of main
Working Group Report)

7. 5% of PF, Gratuity, Pension and Insurance funds must be regulated for


investments in Power Bonds. (Refer Para 10.16.1.7 of main Working Group Report)

10.5 FISCAL AND OTHER MEASURES TO ENABLE CHEAPER POWER:


(REFER PARA 10.16.3)

1. Excise Duty/ CVD on power Generation, Transmission & Distribution


equipment (which is currently at 16%) should be abolished for Projects
with 1,000 MW dispatch on the lines of concession provided to the Mega
Power project.

2. Existing Income Tax exemption for Power Sector projects under section
80IA expiring in March 2010 to be extended till March 2017.

3. Additional depreciation of 20% (WDV) under IT Act available for


investments in plant and machinery in industries other than power to be
made available to power industry also.

10.6 MAJOR RECOMMENDATIONS & POLICY MEASURES

1. IPO by Power companies: Profit making Central/ State Utilities in


generation, transmission & distribution to be encouraged for supply of
PSUs stock in the market by way of IPOs/ FPOs (Follow-on Public Offer)/
Offer for sale. (Refer Para 10.15.1 of main Working Group Report)

2. Public Private Participation models: PPP on the lines of UMPP where


Govt. undertakes to get the various clearances before the bidding

68
th
Executive Summary Working Group on Power-11 Plan (2007-12)

facilitates quicker financial closure. (Refer Para 10.15.2 of main Working Group
Report)

3. Relaxation in Companies (Issue of Share Capital with Differential Voting


Rights) Rules, 2001, for issuing Equity Shares with Differential Voting
Rights: Waive requirement of having distributable profit for three financial
years. (Refer Para 10.15.3 of main Working Group Report)

4. Equity support by State Governments through Budget Allocation: State


Government should allocate funds through its budget for providing equity
support to State Utilities in Power Sector (Refer Para 10.15.4 of main Working
Group Report)

5. Specialized debt funds for infrastructure financing (Refer Para 10.15.5.2 of


main Working Group Report)

6. Development of a Venture Capital / PE fund to invest in equity of power


projects. (Refer Para 10.15.6 of main Working Group Report)

7. Development of Primary Markets for Bonds and Corporate Debt by


enhancing issuer base and investor base (Refer Para 10.15.7 of main Working
Group Report)

8. Development of Hydro Power Viability Fund which finances the deferred


component of the power tariff of the first five years and recovers its money
during 11th to 15th year of the operation. (Refer Para 10.15.8 of main Working
Group Report)

9. Viability Gap Fund (for Remote areas) which finances the deferred
component of the power tariff of the first five years and recovers its money
during 11th to 15th year of the operation. (Refer Para 10.15.9 of main Working
Group Report)

**********

69
Demand for Power and Generation Planning Working Group on Power for 11th Plan

Chapter 1
DEMAND FOR POWER AND GENERATION PLANNING

1.0 TENTH PLAN REVIEW

The total installed capacity at the beginning of the 10th Plan i.e. 1.4.2002 was 1,05,046
MW comprising 26,269 MW hydro, 74,429 MW thermal (including gas and diesel), 2,720
MW nuclear and 1,628 MW wind-based power plants. The region-wise details of installed
capacity as on 1.4.2002 are given in Table 1.1

Table 1.1
Summary of Installed Capacity at the Beginning of 10th Plan (1.4.2002)
(Figures in MW)
Thermal Renewable
Sector Hydro Nuclear Energy Total
Coal Gas Diesel Total
Sources
State 22,639 36,722 2,662 558 39,941 0 61 62,642
Private 581 3,991 4,082 577 8,651 0 1,567 10,799
Central 3,049 21,418 4,419 0 25,837 2,720 0 31,605
ALL INDIA 26,269 62,131 11,163 1,135 74,429 2,720 1,628 1,05,046

At the beginning of 10th Plan the country was facing peak shortages of 12.6% and energy
shortage of 7.5%, with lowest of 3.7% in Eastern Region and highest at 16.9% in Western
Region in terms of peak and 1% to 10.4% in terms of Energy.

1.1 TARGET CAPACITY ADDITION DURING TENTH PLAN

Taking into account the preparedness of the projects and resources available, a feasible
capacity addition target of 41,110 MW comprising 14,393 MW hydro, 25,417 MW thermal
and 1,300 MW nuclear was fixed for the 10th Plan as detailed below.

Table 1.2
10th Plan Capacity Addition Target-Sector Wise
(Figures in MW)
SECTOR Hydro Thermal Nuclear Total
CENTRAL 8,742 12,790 1,300 22,832
STATE 4,481 6,676 0 11,157
PRIVATE 1,170 5,951 0 7,121
TOTAL 14,393 25,417 1,300 41,110

Page 1 of Chapter 1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

10th PLAN CAPACITY ADDITION TARGET


(41,110 MW) - BY SECTORS

7,121 MW
PRIVATE
SCTOR
17%

STATE SECTOR
27%

11,157 MW 22,832 MW

CENTRAL
SECTOR
56%

Region wise/ Status wise Summary of this capacity addition target is furnished in
Appendix 1.1.

1.2 STRATEGY FOR ACHIEVING 10TH PLAN TARGET

The capacity addition achieved during the 9th Five Year Plan was below 20,000 MW and
the best performance during any plan in the past was 21,400 MW added during the 7th
plan period. The goal of capacity addition of 41,110 MW during 10th Plan was a great
challenge to the central, state and private sector generating companies. MOP and CEA
formulated a strategy for achieving the planned target of capacity addition during the 10th
Plan by carrying out rigorous monitoring of the progress of construction of the projects.
The efforts of CEA and MOP have yielded good results. Critical projects not making
satisfactory progress have been identified and focused efforts have been made to remove
constraints in their implementation. However, in spite of best efforts by project authorities,
CEA and MOP, a few projects in hydro and thermal are still likely to slip from the 10th Plan.

At the same time, action has also been taken to add new additional capacity which was
initially not included in the target for the 10th plan. This was done to supplement the effort
as some of the plants included in the target were likely to slip.

1.3 ACTUAL CAPACITY ADDITION AND POWER SUPPLY POSITION DURING 10TH
PLAN (TILL DATE)

1.3.1 Actual Capacity Addition

A capacity addition of 17,995 MW has been achieved during 10th Plan till 31-12-
06.Yearwise details of the target and actual capacity addition during 10th Plan up to
31.12.06 is given in Table 1.3

Page 2 of Chapter1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

Table 1.3

Year wise Capacity Addition During 10th Plan up to 31.12.2006 ( All India)

(Figures in MW)
Actual
Year (MW) Type Target
Achievements
Hydro 607 649***
Thermal 3502 2,223
Coal 710 1210
2002-03 Lignite 795 460
Gas 1977 515
Oil 20 38
Nuclear 0 0
Total 4,109 2,872
Hydro 3,765 2,590
Thermal 1,437 1,362
Coal 735 945
2003-04 Lignite 420 210
Gas 259 207
Oil 23 0
Nuclear 0 50*
Total 5,202 4002
Hydro 2,585 1,015
Thermal 2,661 2,934
Coal 2000 2710
Lignite 460 125
2004-05
Gas 173 70
Oil 28 29
Nuclear 0 0
Total 5,246 3,949
Hydro 2886 1340
Thermal 3436 1589
Coal 1790 830
Lignite 250 125
2005-06
Gas 1396 634
Diesel 0 0
Nuclear 590 590**
Total 6912 3519
Hydro 3884 1316
2006-07
Thermal (Coal, Lig, 13123 1811
Up to 31st
December, 2006
Gas & Diesel)
Nuclear 760 540
Total 17767 3667
Grand Total 17995
(Up to 31st December 2006)
* and **Additional capacity 50 MW each due to uprating of MAPS-1 &2 (Nuclear)
***- Includes projects of 12 MW capacity not included in the target viz. Potteru
(6 MW) & Likimiro (8 MW).

Page 3 of Chapter 1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

The Year-wise details of projects already commissioned during 10th Plan are given in
Appendix 1.2

1.3.2 Installed Capacity as on 31.12.2006

The total Installed Capacity as on 31.12.2006 was 1,27,753 MW comprising 33,642 MW


hydro, 84,020 MW thermal including gas & diesel, 3,900 MW nuclear based power plants
and 6,190 MW from renewable energy sources including wind. The sector– wise details of
installed capacity is given in Table 1.4

Table 1.4
Summary of Installed Capacity as on 31.12.2006

(Figures in MW)
Thermal
Sector Hydro Nucl. R.E.S.@ Total
Coal Lig Gas$ Oil© Total
CENTRAL 6,672 24,020 2,490 5,899 0 32,409 3,900 0 42,981
STATE 25,664 37,386 465 3,500 1,239 42,589 0 2,568 70,821
PRIVATE 1,306 2,831 500 4,183 1,507 9,022 0 3,523 13,951
TOTAL 33,642* 64,237** 3,455 13,582 2,746 84,020 3,900 6,191 1,27,753
Source: DMLF Division, CEA
@ R.E.S. = Renewable Energy Sources includes Small Hydro Project(SHP), Biomass Gas (BG),
Biomass Power (BP) Urban and Industrial waste power (U&I) & Wind Energy
* Includes ROR- 15,143 MW, PSS- 664 MW, Storage- 17,835 MW
** 21,759 MW Pithead & 42,478 MW Load Center/ Non Pit Head
$ Includes Liquid Fuel based Kayamkulam Project-350 MW
© 1544 MW Dual firing stations included in oil.

1.3.3 Power supply position in 10th plan

The year-wise actual power supply position during 2002-03, 2003-04, 2004-05 ,2005-06
and 2006-07(till Dec-06) of 10th plan is given in Table 1.5

Table 1.5
Actual Power Supply Position ( All India Basis )

Year Peak Energy


Require- Availabi- Surplus Shortage/ Requirem Availability Surplus Shortage
ment lity (+)/Short- Surplus ent (MU) (MU) (+)/Shortage /Surplus
(MW) (MW) age (-) % (-) %
(MW) (MU)
2002-03 81,492 71,547 - 9,945 -12.2 5,45,983 4,97,690 -48,093 -8.8
2003-04 84,574 75,066 -9,508 -11.2 5,59,264 5,19,398 -39,866 -7.1
2004-05 87,906 77,652 -10,254 -11.7 5,91,373 5,48,115 -43,258 -7.3
2005-06 93,255 81,792 -11,463 -12.3 6,31,757 5,78,819 -52,938 -8.4
April–Dec
1,00,466 86,425 -14,041 -14.0 5,10,223 4,65,149 -45,074 -8.8
2006

Page 4 of Chapter1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

1.4 ACTUAL/ LIKELY CAPACITY ADDITION DURING TENTH PLAN

A capacity of 17,995 MW has been commissioned till date(31.12.2006) during the 10th
Plan and a capacity of 12,646 MW is expected to be commissioned during the balance
period (Jan.07-March07) of 10th Plan. Year wise capacity addition is given in Table 1.6.

Table 1.6
Year wise Capacity Addition During 10th Plan (All India Basis)
(Figures in MW)
Type 2002-03* 2003-04* 2004-05* 2005-06* 2006-07@ Total
Hydro 635 2,590 1,015 1,340 3,274 8,854
Thermal 2,223 1,362 2,934 1,588 12,280 20,387
Nuclear 0 50 0 590 760 1,400
Total 2,858 4,002 3,949 3,518 16,314 30,641
*Actual, @ likely, (Excluding wind & Res.)

The target set for capacity addition during the 10th Plan was 41,110 MW. Even though
stringent monitoring of projects has been done, the likely capacity addition during 10th Plan
has been assessed to be about 30,641 MW out of which about 17,995MW has already
been commissioned as on 31-12-06. The details of projects included in original 10th plan
target and their present status are given in Appendix 1.3

As per latest indication, out of 30,641 MW a capacity of 5,727 MW may further slip to 11th
Plan because of various reasons including delay in supply and execution by BHEL. Any
slippage of the projects from 10th plan would be reckoned as additional capacity in 11th plan
over and above being proposed in this document. The details of 5,727 MW capacity
expected to slip to 11th Plan is given in Appendix 1.4.

During the first year of 10th plan itself it became clear that a number of projects totalling to
3,009 MW in public and private sectors could not be taken up due to various reasons which
included non availability of escrow cover by State Government to IPP projects and fund
constraints. Certain projects totalling to a capacity of 12,516 MW comprising 7,458 MW
thermal and 5,058 MW hydro as included in the 10th Plan target of 41,110 MW are slipping
to 11th Plan. Further 5,056 MW capacity additional projects comprising of 4,956 MW
thermal and 100 MW nuclear (uprating) originally not included in the 10th Plan target have
been additionally identified for benefits during 10th Plan by expediting the process of
project implementation and compression of the construction schedule to make up for the
projects which could not take off. This has been possible through extraordinary efforts
made by CEA & Ministry of Power in pursuing the developers and other Stake holders A
summary of the slippages and additional projects identified is given in Table 1.7.

Page 5 of Chapter 1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

Table 1.7
Summary of Likely Capacity Addition during 10th Plan
(Figures in MW)
Thermal Hydro Nuclear Total
Original programme 25,417 14,393 1,300 41,110
Dropped 2,528 481 0 (-)3,009
Capacity slipping to 11th plan 7,458 5,058 0 (-)1,25,16
Back up capacity likely to be 4,956 - 100 5,056
added
Total 20,387 8,854 1,400 30,641**

**This includes a capacity of 2578 MW which were the best efforts projects. This also
includes a further capacity of 2445 MW which would need extra ordinary efforts for
completion during 10th plan mainly due to constraints on the side of BHEL.

1.5 LIKELY INSTALLED CAPACITY AT THE END OF 10TH PLAN I.E. AS ON


31.03.2007

The likely Installed Capacity at the end of 10th Plan i.e. as on 31.03.2007 is 1,40,571 MW
comprising 35,600 MW hydro, 94,660 MW thermal including gas & diesel, 4,121 MW
nuclear based power plants and 6,191 MW from renewable energy sources including wind.
The sector– wise details of this is given in Table 1.8.

Table 1.8
Summary of Likely Installed Capacity as on 31.03.2007

(Figures in MW)
Sector Hydro Thermal Nucl. Wind/RES Total
Coal Lignite Gas Oil Total
CENTRAL 75,62 27,728 2,490 4,419 0.0 34,637 4,120 0.0 46,319
STATE 26,745 41,631 665 3,760 1,239 47,294 0 2,568 76,607
PRIVATE 1,293 3,081 500 7,641 1,507 12,730 0 3,623 17,645
TOTAL 35,600 72,440 3,655 15,820 2,746 94,660 4,120 6,191 1,40,571

1.5.1 Analysis of reasons for 10th plan slippages

The causes for slippages and delays in implementation of 10th plan power projects is
discussed below:

It has emerged that out of 41,110 MW capacity addition target during 10th plan over 12,500
MW was not feasible within 10th Plan because of inadequate preparedness. Some of the
major groups in this category are as follows:

(a) About 3960 MW (660 MW unit size ) projects of NTPC based on super critical
technology were not found feasible to be commissioned during 10th plan as originally,
NTPC was of the view that indigenous manufacturer BHEL would tie up collaboration
agreement and participate in tender for development of these projects, which BHEL
had not done even till middle of 2003.

Page 6 of Chapter1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

(b) 10th plan target included over 3,300 MW hydro projects in case of which
preparedness in terms of crucial inputs like Techno-economic clearance, PIB,
Environmental clearances, etc were not in place.

(c) In case of private sector projects , the reasons of slippages are due to escrow cover
not being given by State Government and financial closure not achieved by the
developers. Such projects add up to 900 MW.

(d) In case of thermal projects under execution during 10th Plan, the main reason of
slippage is delay in placement of main plant order by the utilities. The other reason of
delay is non-sequential supply of material by the manufacturers.

(e) Some of the Hydro projects slipped from original 10th Plan mainly due to delay in
award of works, delay in investment decisions, forest clearance. Some of the Hydro
projects in state sector are delayed due to funds constraints as well.

(f) Two gas based project of NTPC namely Kawas and Gandhar were also included as
additional projects but are not likely to take off on account of bleak gas availability
scenario.

Table 1.9 indicates the major reasons of slippage and the capacity slipped due to each of
these reasons:

Table-1.9

Sl. Major Reasons of slippage Capacity slipped (MW)


No Thermal Hydro
1. Delay in super critical technology tie up 3,960 -
by BHEL
2. Geological Surprises - 510
3. Natural Calamity - 450
4. Delay in award of works 998 823
5. Delay in MoE&F clearance - 400
6. Delay in clearance/ Investment decision / 1,500 1,400
Funds tie up constraints/delay in financial
closure
7. Delay in Preparation of DPR & sign up of - 400
MOU between HP&SJVNL
8. ESCROW cover (Private Sector) 500 -
9. R&R issues - 400
10. Court Cases - 675
11. Law & Order problem 500
Total 7,458* 5,058*
* This does not include 3009 MW projects dropped from 10th Plan

It is pertinent to point out that a number of projects of 10th plan ordered on BHEL were
delayed due to delayed and non-sequential supply of equipment and materials and
inadequate manpower in commissioning teams. Some of the projects expected to be
commissioned during the last quarter of 2006-07 are also running behind schedule due to
the above reasons.

Page 7 of Chapter 1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

An analysis was carried out of the projects slipping from 10th Plan. Detail of the thermal
and hydro projects which are expected to slip from the original target are given in the
following Appendices:

Appendix-1.5 List of projects dropped from original 10th Plan target (41,110 MW).

Appendix -1.6 List of the thermal projects slipping from 10th plan target (41,110 mw)

Appendix -1.7 List of the hydro projects slipping from 10th plan target (41110 mw)

1.6 DEMAND FOR POWER

1.6.1 Growth in Generation During 10th Plan


The growth in generation has been 3.2%, 5.1%, 5.2% and 5.2% during 2002-03, 03-04, 04-
05 and 05-06 respectively. In the year 2006-07(upto Dec-2006) a growth rate of 7.5 % has
been recorded. The Compounded Annual Growth Rate(CAGR)of generation during the 10th
Plan period is expected to be about 5.1%. However, higher growth could have been
achieved if adequate gas would have been available for the existing and new gas based
plants commissioned during 10th plan.

1.6.2 Growth in Generation During 11th Plan

Assessment of generation requirement during the 11th Plan is important to work out the
generation capacity requirement to be planned for the 11th Plan. Demand projections of
various utilities are done by the Electric Power Survey (EPS) Committee. The last power
demand projections were made by 16th EPS in 2000 and the 17th EPS Report is under
finalization by the Committee. Besides the EPS, Integrated Energy Policy stipulates
generation to grow at 9% p.a. during 11th Plan. Also, as per National Electricity Policy
(NEP), the per capita electricity consumption is to increase to 1000 units by the year 2011-
12. The Working Group has assessed the generation requirement according to the above
Committee Report/ Policies. Since the requirement worked out to meet the objectives of
National Electricity Policy is higher, the same has been adopted for planning purposes.
Details of the above three assessments are given below:-

(i) 16th EPS Report

The energy requirement by Utilities in 2011-12 is 975 BU at the busbar. Considering about
6.5% - 7% auxiliary consumption, the gross energy requirement is about 1040 BU.

(ii) Integrated Energy Policy (IEP)

As per the Integrated Energy Policy (IEP), issued by the Planning Commission, GDP
growth rates of 8%-9% have been projected during the 11th Plan. Assuming a higher
growth rate of 9% and assuming the higher elasticity projected by the IEP of around 1.0,
electrical energy generation would be required to grow at 9% p.a. during the 11th plan
period. Also generation has to be collectively met by utilities, captive plants and Non-
conventional energy sources. No reliable plans about captive power capacity expansion
are available but based on indications available from the manufacturers for addition in

Page 8 of Chapter1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

captive capacity and present utilization of available capacity, the generation from captive
plants is expected to increase from 78 BU to 131 BU per annum. Since the load factor of
non-conventional energy sources is very low (about 20% on an average), even though the
capacity projected by MNRE from these sources is about 23,500 MW by the end of 11th
Plan, the expected generation would be only around 41 BU. The generation from these
renewables however has not been taken into account for planning purposes. Based on
these assumptions following scenario emerges:

(i) Likely energy Generation by utilities in 2006-07 663 BU


(ii) Likely Energy Generation by captive plants in 2006-07 78 BU
(iii) Total Likely Generation in 2006-07 741 BU
(iv) Compounded Annual Growth Rate 9%
(v) Required Energy Generation by 2011-12 @ 9% growth rate 1140 BU
over 741 BU
(vi) Less Estimated Energy Generation by captive plants in 2011-12 131 BU
(vii) Total Estimated Generation Requirement from Utilities by 2011- 1008 BU
12

(iii) National Electricity Policy (NEP)

(i) Likely Population by 2011-12 (Census 2001) 121 Crores


(ii) Generation Required if Per Capita Consumption is to be 1210 BU
1000 kwh/yr
(iii) Likely Generation from Captive Plants in 2011-12 131 BU
(iv) Likely Generation from Renewable Plants in 2011-12 41 BU
(v) Requirement of Generation from Utilities (ii-iii-iv) 1038 BU

Requirement of Generation from Utilities by 2011-12 from various methods has been
summarized as below:-

16th EPS Report About 1040 BU


Integrated Energy Policy Report 1008 BU
National Electricity Policy 1038 BU

The requirement of generation as per 16th EPS & National Electricity Policy(NEP) are more
or less same and greater than the requirement as per Integrated Energy Policy. Since the
NEP is the guiding document for the power sector, requirement of generation (from utilities)
for planning purpose adopted is 1038 BU. This would require a generation growth rate of
9.5 % p.a. (CAGR) for utilities. The 16th EPS report stipulates peak demand of 1,57,000
MW by 2011-12 and 1,51,000 MW considering interregional diversity. This has been
considered while assessing the 11th Plan capacity addition.

1.6.3 Growth in generation During 12th Plan


During the 12th Plan period, assuming a GDP growth rate of 9% per annum and elasticity
0.8 as compared to 1.0 during 11th Plan mainly due to adoption of energy efficient
technologies & other Energy Conservation and Demand Side Management measures
being taken up during 11th Plan, electricity demand is likely to grow @ 7.2% p.a. Keeping
Page 9 of Chapter 1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

this in view, the energy generation should increase to a level of 1470 BU by 2016-17 from
a level of 1038 BU in 2011-12. However sensitivity analysis have been carried out
assuming 8,9 & 10 % GDP growth rates & GDP-electricity elasticity of 0.9 & 0.8
respectively and the same is given in table below:

Table 1.10

Generation Requirement for 2016-17


( As Per 8,9,10 % GDP Growth)

GDP GDP/ Electricity


Growth Electricity Generation
Elasticity Required
(BU)
8% 0.8 1415
0.9 1470
9% 0.8 1470
0.9 1532
10 % 0.8 1525
0.9 1597

1.7 APPROACH TO SELECTION OF PROJECTS FOR 11TH PLAN:

An analysis of the reasons for slippages of projects from the 10th Plan target has been
carried out above. In order to avoid such slippages while planning for capacity addition
during 11th Plan, efforts have been made to set 11th Plan targets realistically.

The approach adopted for selection of Hydro, Thermal and Nuclear projects have been as
follows:-

1.7.1 Hydro
India is duly concerned about climate change and efforts are on to promote benign sources
of energy. Hydro Power is one such source and is to be accorded priority also from the
consideration of energy security. Irrespective of size and nature of hydro projects, whether
ROR or Storage projects, these are all renewable technologies. However, execution of
hydro projects requires thorough Survey and Investigation, preparation of DPR,
development of infrastructure, EIA and other preparatory works, which are time consuming
and require two to three years for their preparation. It would take about 5 years to execute
a hydro project after the work is awarded for construction. Thus in order to achieve
completion of a hydro project during 11th plan, the project should either be already under
construction or execution should start at the beginning of the plan. The broad criteria
adopted for selection of hydro projects for 11th plan are as under:

• Those hydro projects whose concurrence has been issued by CEA and order for
main civil works is likely to be placed by March 2007.
• Apart from the above, a few hydro projects of smaller capacity which are ROR type
having surface power houses and where gestation period is expected to be less

Page 10 of Chapter1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

than 5 years have also been included. These projects would need to be rigorously
followed up for completion during the 11th Plan.

Keeping in view the preparedness of various hydro projects, a capacity addition of 15, 585
MW is envisaged for 11th Plan.

1.7.2 Nuclear
Nuclear is environmentally benign source of energy and over a period of time, its
proportion in total capacity should increase. Keeping in view the availability of fuel, a
moderate capacity addition of 3,160 MW nuclear plants has been programmed during
the 11th Plan by the Nuclear Power Corporation. All projects are presently under
construction. However, in view of the recent developments in the Nuclear Sector,
capacity addition in nuclear plants during 12th Plan is expected to be much higher.

1.7.3 Thermal

Gas

Although gas is relatively a clean fuel, at present there is uncertainty about the
availability, period of availability and price of gas. Only 2,114 MW gas based capacity
has been planned for 11th Plan where gas supply has already been tied up. This does
not include NTPC’s gas based projects at Kawas and Gandhar, totalling to 2,600 MW,
for which NTPC says that it has the gas supply contract but the matter is sub-judice.
However more gas based projects could be taken up for construction as and when
there is more clarity about availability and price of gas.

Coal & Lignite based Thermal plants

Coal is expected to be main stay of power generation in the years to come. The
following criteria have been adopted for identifying the coal and lignite based projects
for inclusion in the 11th plan.

• Such projects as have already been taken up for execution in the 10th Plan period
itself and are due for commissioning in the 11th Plan period.
• Those thermal projects whose LOA has already been placed by the State and
Central Public Sector Corporations, other inputs also being in place.
• Those thermal projects whose LOA has already been placed and the financial
closure achieved by private developers.
• Those thermal projects whose LOA is expected to be placed by 30th Sept, 2008 and
commissioning is expected during the 11th Plan keeping in view the normal gestation
period, the size of the plant & the type(green field/expansion).

After discussion with the various State Government and Central Generating Companies,
thermal projects with total capacity of 46,635 MW of coal based and 1375 MW lignite
based capacity have been identified for capacity addition during 11th plan.

Page 11 of Chapter 1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

1.8 GENERATION PLANNING NORMS

The Indian Power Sector comprises of units of different type of power plants i.e. hydro,
coal, lignite, gas based, DG Sets and nuclear power plants. The unit size of coal based
plants has also been steadily increasing over the years from 30 to 50 to 67.5 MW during
the 70’s to 500 MW at present. During the 11th & 12th Plan periods supercritical units of
660 MW and 800 MW have also been planned. In respect of nuclear plants, 200-220 MW
unit size plants are in operation and 540 MWe reactors have recently been put in operation
during the 10th Plan. 1000 MW units are also under construction by the Nuclear Power
Corporation. In this Chapter Planning Norms have been evolved for different type of plants
with varying unit sizes.

1.8.1 Objective of evolving Norms

In the Planning exercise, generation norms are used as representative performance


parameters of various types of generation sources to estimate the availability of peaking
power and energy from each generating unit. These norms are then used to assess the
availability of energy from each source of generation and thus assess generation capacity
addition required to meet the stipulated demand.

The planning studies require accurate performance parameters of various type of


generating units to assess their availability and energy generation capabilities. Availability
and generation capacity are important parameters for meeting the projected demand in the
country and also in various regions. Availability and PLF are key performance factors
required for the planning studies. Other features used for planning studies are the Auxiliary
Power Consumption and Heat Rate of the generating units, etc. Different types of
generating units have varied operational performance and accordingly different norms have
been used for thermal (coal), gas, hydro and Nuclear projects to make a fare assessment
of the generation capacity requirement.

The impact of size, age and design of plant has been considered while arriving at the
norms. The actual operating data for past 5 years has been collected for all individual units
operating in the country and their average performance worked out. The norms have been
arrived at only after very detailed exercise and analysis of a large data on performance of
various units.

1.8.2 Parameters covered by Norms

Norms for thermal, hydro and nuclear stations have been evolved as all India average
figures. The parameters covered under Norms are as follows:

(a) Availability
(b) Auxiliary Power Consumption
(c) Unit Heat Rate
(d) Plant Load Factor

(a) Availability

The Availability (gross) of the various types of generating units is given in Table 1.11

Page 12 of Chapter1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

Table 1.11
Availability

Availability (%)
Unit Size
Existing Units Future Units
Thermal 800/660 MW
- 85
(Coal/ lignite)
500/250/210/200 MW 85 85
Below 200 MW 75 85
Below 200 MW operating
below 20 % PLF at 50 -
present
Gas Based OCGT all sizes 90 90
CCGT all sizes 88 88
DG Sets All sizes 75 75
Nuclear All sizes 85 85
Hydro All sizes 87.5 87.5

(b) Auxiliary Power Consumption (APC)

After deliberations, it was concluded that the auxiliary power consumption for 800 MW and
660 MW supercritical units is expected to be in the same range as for other coal based
units of 200 MW class and above. These would be different for units adopting turbine
driven feed pump, motor driven feed pump and for units with or without cooling towers. The
values indicated in the Table 1.12 for coal based units are for units with Turbine driven
Boiler Feed Pumps (BFPs) and using cooling tower for Cooling Water system. Values will
be lower by 0.5% for units without cooling tower. However, values will be higher by 1.5%
for units with Motor driven BFPsThe auxiliary consumption of the various types of
generating units considered is given in Table 1.12

Table 1.12
Auxilliary Power Consumption

Type Unit size A.P.C (%)


Coal-based power 800/660 MW supercritical 7.5%
stations: 500/ 200/210/250 MW 7.5%
Less than 200 MW 12%
Gas-based power Combined Cycle GT 3%
stations Stations
Open Cycle GT Stations 1%
Hydro Stations 0.5%

c) Unit Heat Rate

The Unit heat rates (Gross) used for planning studies for thermal units of various capacities
as arrived at by the past average data are given in Table 1.13

Page 13 of Chapter 1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

Table 1.13
Unit Heat Rates

Unit Size (MW) Heat Rate kcal/kwh


Coal based plants 800(247 kg/cm2, 565C 2325
/592 C)
800(247 kg/cm2,535 C/565 2400
C)
660 2400
500 2425
200/210/250 (KWU) 2460
200/210 (LMZ) 2500
100 MW class 2750
50 MW class 3000
30 MW class 3300
Lignite 200 MW class 2750
Gas Turbine Units Combined Cycle 2000
Open Cycle 2900

(d) Plant Load Factor

The Plant Load Factor (PLF) to be adopted for thermal units of various capacities are
furnished in Table 1.14

Table 1.14
Plant Load Factor

Units PLF
Type Remarks
(%)
800/660 MW 80 Future Units
Coal Based 500/250/210/200 MW 80 Existing and Future Units
Below 100/110 MW 60 80% for future units
Units in ER and NER
40 operating Below 20%
PLF.
125/ 200/250 MW
Lignite Based 75
CCGT 80
Gas Based
OCGT 33
All units Normative capacity
Nuclear Units 68.5
factor

For hydro units it was agreed that the energy generation shall be taken as the designed
energy generation in a 90 % dependable year.

Page 14 of Chapter1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

1.9 GENERATION EXPANSION PLANNING

1.9.1 Eleventh Plan Programme (2007-2012)

To meet the energy requirement of 1038 BU and a peak load of 1, 51,648 MW with
diversity & 5% spinning reserve, a capacity addition of about 72,000 MW is required.
However, based on the preparedness of the projects, it was envisaged that a capacity of
about 68,869 MW is feasible for addition during 11th plan period. These projects have been
categorized as Projects under construction and Committed Projects and summarized in
Table 1. 15 . Details are given at Appendix -1.8

Table 1.15
THERMAL
TOTAL BREAKUP
SECTOR HYDRO NUCLEAR TOTAL
THERMAL
GAS/
COAL LIGNITE
LNG
Projects Under
11,931 16,254 14,115 1,125 1,014 3,160 31,345
Construction
Committed
3,654 33,870 32,520 250 1,100 - 37,524
Projects
Total 15,585 50,124 46,635 1,375 2,114 3,160 68,869

(The above does not include Merchant Power Plants which may additionally come during 11th plan period.)

* Note: Out of the projects totalling to 37,524 MW under committed category as given above, orders for Dadri
Unit-6 (490 MW) & Mezia Ph-II (1000 MW) has been recently placed.

The sector wise break-up of feasible capacity addition during 11th plan is given in Table
1.16.

Table 1.16
SECTOR HYDRO TOTAL THERMAL BREAKUP NUCLEAR TOTAL
THERMAL (%)
COAL LIGNITE GAS/LNG
CENTRAL 9,685 23,810 22,060 1,000 750 3,160 36,655
(53.2%)
STATE 2,637 20,352 19,365 375 612 - 22,989
(33.4%)
PRIVATE 3,263 5,962 5,210 0 752 - 9,225
(13.4%)
ALL-INDIA 15,585 50,124 46,635 1,375 2,114 3,160 68,869
(100%)

In addition to above, thermal projects totalling to 11,545 MW have been identified as best
effort projects. These projects would normally be commissioned in the beginning of 12th
Plan but in case of any constraints in taking up of any of the projects included in 11th plan,
some of these projects would be tried for commissioning during 11th Plan itself.

Page 15 of Chapter 1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

A capacity of 13,500 MW has been planned under renewable as per information obtained
from MNRE.

It can be seen from the above profile of capacity addition plan that central sector will play a
lead role with capacity addition of more than half of the capacity addition target. There has
been a good response from states on the need for capacity addition to meet their growing
demand and the states with IPPs, have been earmarked the balance capacity for
execution.. The State owned capacity projected for the 11th Plan is 33.4 % of the total plan
as compared to 27% likely during 10th Plan.

The thermal capacity addition comprises 1 unit of 800 MW, 11 units of 660 MW, 53 units of
500 MW class, 49 units of 210/250/300 MW class, 7 units of 110/125 MW class.

1.9.2 Projects under Construction:

Projects totalling to 31,345 MW are already under construction for likely benefits during
11th plan. The type wise, sector wise details are given in Table 1.17

Table 1.17
Projects under Construction as on 01.01 2007

TOTAL THERMAL BREAKUP


SECTOR HYDRO NUCLEAR TOTAL
THERMAL COAL LIGNITE GAS/LNG
CENTRAL 7,633 7,200 6,450 750 0 3,160 17,993
STATE 2,107 5,852 5,215 375 262 - 7,959
PRIVATE 2,191 3,202 2,450 0 752 - 5,393
ALL-INDIA 11,931 16,254 14,115 1,125 1,014 3,160 31,345

The details are given in Appendix-1.8

1.9.3 Committed Projects:


In addition to projects under construction, a number of projects are under various stages of
development for which necessary inputs are being arranged by the implementing agencies.
Various clearances required for setting up these projects are being obtained which include
environment and forest clearance, cooling water availability, land acquisition, DPR
preparation, concurrence of CEA/ State Government (wherever required), financial tie ups/
CCEA clearance from government, fuel linkages etc. Important milestones towards
obtaining these clearances are being closely monitored and therefore there is reasonable
certainty of these projects materializing during 11th plan. There is commitment from the
Power Companies/ states to implement the projects during 11th Plan. Based on present
status, it emerges that a total capacity of 37,524 MW could be considered as committed
capacity for benefits during 11th plan comprising of 3,654 MW hydro and 33,870 MW
thermal. The details are given in Table 1.18

Page 16 of Chapter1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

Table 1.18
Committed Capacity
(Orders yet to be placed)

TOTAL THERMAL BREAKUP


SECTOR HYDRO NUCLEAR TOTAL
THERMAL
COAL LIGNITE GAS/LNG
CENTRAL 2,052 16,610 15,610 250 750 0 18,662
STATE 530 14,500 14,150 0 350 - 15,030
PRIVATE 1,072 2,760 2,760 0 0 - 3,832
ALL-INDIA 3,654 33,870 32,520 250 1,100 0 37,524
** Order for 1490 MW namely Mezia Ph-II (1000 MW) & Dadri U-6 (490 MW) have recently been placed.

The details are given in Appendix-1.8

All the hydro projects included under Committed category have been accorded
concurrence by CEA/State Government except four number projects totalling to 485 MW
viz. Vyasi, 120 MW in Uttaranchal (HRT fully excavated, Power House and Dam area
partially excavated), UBDC III, 75 MW in Punjab (DPR prepared earlier being revised,
alloted to Malana Power Company on BOO basis, Tendring in Process), Lower Jurala, 240
MW in Andhra Pradesh (Tendering in process, commissioning period around 4 years, DPR
ready) and Tangu Romai HEP, 50 MW in Himachal Pradesh.

Taking into account the uncertainty in the availability of Gas and prevailing high price of
petroleum products, the thermal capacity addition is predominantly coal based. If gas
becomes available at reasonable price more gas based projects may materialize during
later half of 11th plan.

1.9.4 Projects with Additional Efforts:

In addition to 68,869 MW capacity addition feasible during 11th plan, a capacity of 11,545
MW Thermal can come up during 11th plan with additional efforts. The details are given in
Table 1.19. These projects also form part of shelf of 12th plan projects.

Table1.19
Thermal Projects with Additional Efforts

TOTAL THERMAL BREAKUP


SECTOR NUCLEAR TOTAL
THERMAL
COAL LIGNITE GAS/LNG
CENTRAL 4,190 4,190 0 0 0 4,190
STATE 3,300 2,300 1,000 0 - 3,300
PRIVATE 4,055 4,055 0 0 - 4,055
ALL-INDIA 11,545 10,545 1,000 0 0 11,545

Page 17 of Chapter 1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

1.9.5 Decentralised Distributed Generation (DDG)

In some of the areas, it is not possible to extend the grid connected supply of electricity for
meeting the demand of such remote areas, it is proposed to set up some power plants
based on local energy sources available which may be small hydro, non-conventional
sources such as Bio-Mass, Wind, etc and DG sets wherein other sources are not available.
During the XI plan period, it is proposed to add about 5,000 MW of capacity under DDG.

1.9.6 Fuel Requirement

Fuel Requirement during terminal year of 11th Plan (2011-12), considering 68,869 MW
capacity addition during 11th plan and normative PLFs is summarized in Table 1.20. This
is based on a thermal capacity addition of 20,387MW and 50,124MW during the 10th and
11th Plan respectively.

Details regarding coal requirement calculation are given in Appendix-1.9 The actual gas
supplied to power sector at present is of the order of 40 MMSCMD as against requirement
of 61 MMSCMD during current year (2006-07). The requirement of Gas at 90% PLF would
worke out to about 89 MMSCMD.

Table 1.20
Fuel Requirement Estimated during 2011-12

Fuel Requirement (2011-12)


Domestic Coal* 545 MT
Lignite 33 MT
Gas/LNG ** 89 MMSCMD

* The total coal availability from domestic sources is expected to be 482 MT per annum
by 2011-12. Accordingly, imported coal of the order of 40MT, equivalent to 63 MT of
Indian coal, may have to be organised. This quantity may reduce provided production of
domestic coal is increased.

** 89 MMSCMD of gas requirement at 90% PLF has been projected in 2011-12. At


present, the availability of gas is of the order of 40 MMSCMD and therefore not
sufficient to meet the requirement of even existing plants.

1.9.7 Thermal Projects

The capacity of thermal power projects totalling to 50,124 MW (projects under construction
and committed) in terms of their location i.e. pithead, load centre and coastal and also in
terms of unit sizes regionwise is given in Table 1.21 and 1.22.

Page 18 of Chapter1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

Table 1.21
Details of Thermal Power Projects-By Type

PIT HEAD * LOAD COASTAL TOTAL LIGNITE GAS TOTAL


COAL CENTRE COAL COAL /LNG
COAL
NORTHERN 2,500 9,105 11,605 625 110 12,340
WESTERN 6,430 6,620 500 13,550 250 1,102 14,902
SOUTHERN 500 3,850 3,800 8,150 500 92 8,742
EASTERN 10,870 1,710 12,580 12,580
NORTH
EASTERN 750 750 810 1,560
ALL-INDIA 20,300 22,035 4,300 46,635 1,375 2,114 50,124

* Pit Head stations are those plants having their own dedicated coal transportation system
(MGR/Rope way) and are not dependent upon Railways for coal movement.

Table 1.22
Details of Thermal Power Projects-By Unit Size

800/660 MW 500 MW 210/250 110/125 MW TOTAL GAS/LNG TOTAL


UNITS UNITS 300 MW UNITS MODULE
UNITS
NORTHERN 16 14 5 35 1 36
WESTERN 4 13 17 2 36 3 39
SOUTHERN 1 13 5 19 1 20
EASTERN 7 11 10 28 28
NORTH
EASTERN 3 3 4 7
ALL-INDIA
(NOS.) 12 53 49 7 121 9 130
ALL-INDIA
(MW) 8060 26460 12615 875 48010 2114 50124

1.9.8 Status of Fuel Linkage

Coal
Out of the total likely coal based capacity addition of 46,635 MW,

¾ 32,455 MW have been allocated linkage;


¾ 5,830 MW have been allocated captive coal blocks ;
¾ 4,500 MW linkages are yet to be allocated and 2,500 MW Coal Blocks to be
allocated
¾ 1350 MW are likely to be on imported coal for which formal fuel supply
arrangements are yet to be made.
¾ 20,300 MW capacity is pithead based ;
Page 19 of Chapter 1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

¾ 22,035 MW is load centre based and


¾ 4,300 MW coastal power plants.

In the present day scenario, the transmission of electricity from pithead power plants to
load centre works out to be a cheaper option compared to load centre power plant for a
distance of 300 kms onwards at current price level of coal and railway transportation tariffs.
However, following considerations warrant setting up of load centre thermal power plants
as well.

¾ System stability/Security
¾ Security of state grid and emergency supplies to various critical systems in the
state e.g. Railway, Hospital, Airports etc.
¾ To take care of emergencies in case of transmission systems failure
¾ Dispersion of environmental degradation
¾ Problems of right-of-way in case of construction of new transmission lines

Consequently, in the 11th Plan about 42 % coal based capacity is likely to be set up at load
centres.

1.9.9 Gas Scenario:

Due to uncertainty in availability of gas and its high price only about 2,114 MW gas based
projects have been included for benefits during 11th Plan. These projects have already tied
up the gas supply.

At present domestic production of natural gas is around 32-33 BCM. On rough indications
in 2007-08, the target of natural gas production by public sector companies of ONGC and
OIL limited will be 25.23 BCM which might increase to 26.12 BCM in 2011-12. The likely
natural gas production in private sector and through joint ventures is estimated at around
8.60 BCM in 2007-08 which might increase to 23 BCM in 2011-12, if the newly discovered
fields get into commercial production on schedule. Therefore, in the terminal year of the
11th Plan in the Base-Case Scenario in the indigenous production of gas would be of the
order of 49 BCM per annum.

The India Hydro Carbon forum 2025 estimated that by 2011-12 demand for gas would be
313 MMSCMD (equivalent to 114 BCM p.a). Therefore, it is reasonable to expect that
sizeable quantity of Natural Gas would need to be imported to meet the demand in future,
either as LNG or through Trans-national pipelines. Going by the progress of present
negotiations with the natural gas suppliers (Qatar, Iran, Australia), it is expected that about
54 MMSCMD of natural gas (about 19 BCM p.a.) could become available by 2011-12.
However, the investment plans for improvement of LNG infrastructure in future include:

Dahej : 7.5 MMTPA


Dabhol : 5.0 MMPTA
Cochin : 2.5 MMPTA
Hajira : 2.5 MMPTA

and additional 2.5 MMPTA capacity each for Dahej, Cochin and Hazira.

Page 20 of Chapter1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

Pricing of Gas

1) Gas Pricing in the APM: Due to dominance of National Oil Companies, namely,
ONGC and OIL, the pricing in India has been administered on cost plus basis. The
gas price payable to ONGC and OIL for its nomination fields is much below the
market price. There will be no further gas available under APM mechanism.

2) Pre NELP Contract: The prices were negotiated between sellers and buyers and
generally linked to fuel oil prices.

3) Gas Pricing in NELP: Contractors including ONGC and Oil have the freedom to sell
the gas at market rated prices. Government approval is required in the gas prices
formally to be used for evaluation of gas for calculating the various non tax dues to the
Government.

4) Pricing of LNG: Pricing of LNG is done at market rates. In future also, the same
principle will be made applicable.

5) Status of development of gas discoveries: The normal process after a discovery


decision on commerciability and submission and approval of development plan of the
commercial discovery. The commercialization of discovery is monitored by DGH
(Director General, Hydrocarbons) and Ministry of Petroleum and Natural Gas with
respect to time frame stipulated in respective PSCs (Production Sharing Contracts).

(i) Reliance (RIL) Fields: The initial development plan of Dhirubhai 1 and 3
discoveries has been approved by the management committee. The DGH
approved original gas in place (OGIP) at 5.5 TCF. The envisaged rate of
production is 40 MMSCMD for a 10 year period. The date of availability of
indigenous gas has been indicated as June, 2008 and no delay has been
reported by DGH based on current work progress.

(ii) Gujarat State Petroleum Corporation (GSPC) field: The block is located in
Krishna Godavari shallow water offshore. The contractor is yet to submit the
appraisal programme for the discovery. No reserve or production can be
realistically estimated until the completion of appraisal of discovery.

(iii) ONGC:ONGC is currently developing G1 and G15 discoveries in Central Gujarat


basin. The production of gas is expected in March, 2007 and the estimated gas
production from the above two fields is about 2.1 MMSCMD for the period of 7
years.

1.9.10 Hydro Projects:

Out of the total hydro capacity of 15,585 MW included in the 11th Plan,

¾ 11,931 MW are under construction.


¾ 3,169 MW have been accorded concurrence by CEA/State Government and
are awaiting investment decision/work award.
¾ 485 MW the DPR is ready and concurrence of CEA/State Government is
awaited.

Page 21 of Chapter 1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

The details of hydro projects in terms of storage/run-of-river (ROR)/pumped storage (PSS)


is given in Table 1.23.

Table 1.23
Details of Hydro Power Projects

ROR STORAGE PSS TOTAL


NORTHERN 6,145 1,320 1,000 8,465
WESTERN 520 400 0 920
SOUTHERN 653 525 0 1,178
EASTERN 1,623 0 675 2,298
NORTH EASTERN 40 2,684 0 2,724
ALL-INDIA 8,981 4,929 1,675 15,585

1.10 TWELFTH PLAN PERSPECTIVE (2012-2017)

The requirement of installed capacity and capacity addition to meet the generation
requirement during the 12th Plan period as discussed in Para 1.6.3 of this Report are given
in Table below:

Table 1.24

Capacity addition required during 12th plan (2012-17)

GDP GDP Electricity Peak Installed Capacity


Growth /Electricity Generation Demand Capacity Addition
Elasticity Required (BU) (MW) (MW) Required
During 12th
PLAN
(MW)
8% 0.8 1,415 2,15,700 2,80,300 70,800
0.9 1,470 2,24,600 2,917,00 82,200
9% 0.8 1,470 2,24,600 2,917,00 82,200
0.9 1,532 2,33,300 3,03,800 94,300
10 % 0.8 1,525 2,32,300 3,02,300 92,800
0.9 1,597 2,44,000 3,17,000 1,07,500

It would be seen from the above table that under various growth scenarios, the capacity
addition required during 12th plan would be in the range of 70,000 - 1,07,500 MW, based
on normative parameters.

The Working Group recommends a capacity addition of 82,200 MW for the 12th Plan
based on Scenario of 9% GDP growth rate and an elasticity of 0.8%.

This is very close to the projection of draft 17th EPS report based on requirement of about
86,000 MW during 12th Plan.

During 12th plan about 30,000 MW capacity addition is likely to be based on hydro and
about 11,000-13,000 MW will be nuclear based. The balance capacity addition of about
Page 22 of Chapter1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

50,000 MW will be from thermal projects. Shelf of projects identified for likely benefits
during 12th plan is given at Appendix 1.10. The projects indicated in Appendix 1.8 as
projects with best efforts will also form part of 12th plan shelf of projects. Shelf of projects
for likely benefits during 12th plan is summarized in Table 1.25.

Table 1.25
Shelf of Projects for 12th Plan

TYPE MW Capacity likely in 11th


plan with best efforts
(MW)
Hydro 40,658 0
Thermal 1,14,018 11,545
Coal 94,185 10,545
Lignite 4,250 1,000
Gas/LNG 15,583 -
Nuclear 12,800 -
Total 1,67,476 11,545

The Working Group recommends the following for 11th and 12th plan capacity additions.

1.11 MEDIUM TERM PLAN: 11TH PLAN (2007-12)

It has been estimated that depending upon the preparedness of various projects about
68,869 MW capacity addition is feasible during 11th plan (15,585 MW hydro, 50,124 MW
thermal and 3,160 MW nuclear). This comprises 46,635 MW coal based plants, 2,114 MW
gas/LNG based plants and 1,375 MW lignite based plants. In addition renewable energy
sources (MNRE has projected a grid connected renewable capacity addition of 13,500 MW
during 11th plan) would also contribute towards augmenting the power generation.
Demand side management and energy efficiency measures would also help in this
direction. Efforts shall also be made to realize benefits from 12th plan projects which can
be brought with additional efforts during 11th plan (Projects indicated as Best Efforts in
Appendix 1.8). Efforts are also underway to tap surplus power from new captive power
plants of about 12000 MW into the grid. A 5% spinning reserve would give a comfortable
margin since normally during an emergency situation, capacity equivalent to the highest
size unit and the next highest size unit in the system would suffice as reserve. Total coal
requirement during 2011-12 would be about 545 million tones per annum.

1.12 LONG TERM PLAN: 12TH PLAN (2012-17)

Under various growth scenarios, the capacity addition required during 12th plan would be in
the range of 71,000 - 1,07,500 MW, based on normative parameters.

The Working Group recommends a capacity addition of 82,200 MW for the 12th Plan based
on Scenario of 9% GDP growth rate and an elasticity of 0.8%.

During 12th plan about 30,000 MW capacity addition is likely to be based on hydro and
about 11,000-13,000 MW will be nuclear based. The balance capacity addition of about

Page 23 of Chapter 1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

50,000 MW will be from thermal projects. A shelf of projects totalling over 1,50,000 MW
has been identified and given in Appendix 1.10

All necessary inputs for projects need to be tied up well in advance, which may pose
very big challenge for power sector as a whole.

1.13 NEW INITIATIVES

1.13.1 Initiatives in Thermal Power Development

Efforts were made to bring in highly efficient super critical technology in the country for
thermal power plants and execution of six super critical units of 660 MW capacity each was
taken up during the 10th Plan period. The first unit of 660 MW based on super critical
technology is likely to be commissioned during the first year of 11th Plan i.e. 2007-08. The
11th Plan feasible capacity addition of coal based plants includes 12 units based on super
critical technology with a capacity of 8060 MW which is about 18% of total coal capacity
planned for 11th Plan. More and more power projects based on super critical technology
are under planning stage and they would yield benefit during the 12th Plan period. It is
envisaged that more than 50-60% of capacity addition of thermal plants during 12th plan
period would be based on super critical units. This would also help in reducing the Carbon
dioxide emission from new coal fired capacity.

1.13.2 Ultra Mega Power Projects

Ministry of Power in the year 2006 has launched an initiative of development of coal based
ultra mega projects with a capacity of 4,000 MW each on tariff based competitive bidding.
Ultra Mega Power projects are either pit head based projects having captive mine block or
coastal projects based on imported coal. Sasan UMPP, a pithead plant in Chattisgarh
based on domestic fuel and Mundra UMPP in Gujrat based on imported coal have already
been awarded for execution to the respective developers. According to the bids submitted
by these developers only one unit of 660 MW is expected to be commissioned during the
XIth plan and the remaining unit during 12th Plan. Other projects where considerable
progress has been made are coastal projects in Andhra Pradesh and Tamil Nadu and a pit
head based project in Jharkhand. Further the projects under consideration include pit head
projects in Orissa and Chatisgarh and coastal projects in Maharashtra and Karnataka.

To facilitate tie-ups of inputs and clearances project specific Shell companies are set up/to
be set up as wholly owned subsidiaries of the Power Finance Corporation Ltd. These
companies will undertake preliminary studies and obtain necessary clearances including
water, land, fuel, power selling tie-up etc. prior to award of the Project to the successful
bidder.

Initially five sites were identified by CEA in different states for the proposed Ultra Mega
Power Projects. These include two pithead sites one each in Madhya Pradesh and
Chhattisgarh and three coastal sites in Gujarat, Karnataka & Maharashtra. On the request
of the State Govts of Orissa & Andhra Pradesh, two more locations have been identified for
Ultra Mega Projects consisting of a pithead location in Ib-Valley coalfield in Orissa and a
coastal site at Krishnapatnam in Andhra Pradesh. It is proposed to set up pithead projects

Page 24 of Chapter1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

as integrated proposals with corresponding captive coal mines. For the coastal projects
imported coal shall be used.

The projects are to be developed with a view to result in minimum cost of power to the
consumers. Because of bigger capacity, the cost of the project would be lower due to
economy of scale, these projects would be environmental friendly as supercritical
technology is proposed to be adopted to reduce emissions. Further, a time bound action
plan for preparation of project report, tie-up of various inputs/clearances, appointment of
consultants, preparation of RFQ/RFP is being followed. Once the developer is selected, the
ownership of the Shell companies shall be transferred to the successful bidder.

Following six shell companies as 100% subsidiaries of Power Finance Corporation have
already been formed:

a) Sasan Power Limited (Madhya Pradesh)- Pithead


b) Coastal Gujarat Power Limited (Gujarat)
c) Coastal Maharashtra Mega Power Limited (Maharashtra)
d) Coastal Karnataka Power Limited (Karnataka)
e) Akaltatra Power Limited (Chhattisgarh)-Pithead specific.
f) Coastal Andhra Power Ltd.

The name of seven ultra mega power projects proposed in various states is as follows:

i) Sasan Ultra Mega Project (Madhya Pradesh)


ii) Mundra Ultra Mega Project (Gujarat)
iii) Akaltara Ultra Mega Project (Chhattisgarh)-
iv) Tadri Ultra mega project (Karnataka)
v) Girye Ultra Mega project (Maharashtra)
vi) Krishnapatnam Ultra Mega Power Project (Andhra Pradesh)
vii) Orissa Ultra Mega Power Project (Orissa)

The inputs of above projects are tied up by Shell companies. As soon as developers/
bidders are selected, the ownership shall be transferred to them. The likely commissioning
period Ultra Mega projects is 69 months from the signing of agreement, which is expected
in February, 2007.

1.13.3 High Hydro Development

50,000 MW Hydro Initiative was launched in 2003 and Preliminary Feasibility Report
(PFRS) of 162 projects totalling to 48,000 MW were prepared. Out of this 77 projects with
total capacity of about 37000 MW for which first year tariff is expected to be less than
Rs.2.50/unit were selected for execution. Hydro projects have longer gestation period and
therefore there is a need to formulate a 10 year plan for hydro projects. In 11th plan a
capacity addition of over 15,500 MW has been earmarked keeping in view the present
preparedness of these projects. Projects totalling to a capacity of 30,000 MW have been
identified for 12th Plan on which necessary preparations have to be made from now
onwards to ensure their commissioning during 12th Plan. Thus the effect of 50,000 MW
initiative would be visible in 12th Plan period. Preparation of DPR and various clearances
and approval etc for these projects are to be obtained during the first two years of 11th

Page 25 of Chapter 1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

Plan. It is recommended that CEA should closely monitor the progress of preparedness of
DPR of these projects and their further execution.

1.13.4 Decentralised Distributed Generation (DDG)

In some of the remote areas, it is not techno-economically feasible to extend the grid
supply. For meeting the demand of such remote areas, it is proposed to set up some power
plants based on local energy sources available. These are small hydro and non-
conventional sources such as Bio-Mass, Wind, DG sets etc wherein other sources are not
available. During the XI plan period a capacity addition of about 5,000 MW of capacity
under DDG is envisaged.

1.13.5 Merchant Power Plants

A merchant power plant does not have long term PPA for sale of its power and is generally
developed on the balance sheet of developers. Government of India has reserved coal
block with reserves of 3.2 Billion Tons of coal for allotment by Screening Committee of
Ministry of coal for merchant and captive plants. About 10,000 -12000 MW capacity is
expected to be developed through this initiative. This capacity has not been taken into
account while working out the capacity required in the 9.5% growth in generation scenario.
Capacity addition through this route would further contribute to better economic growth,
better reliability of power, more spinning reserve and above all would promote creation of
competition in the electricity market.

1.13.6 Coal Bed Methane

The Directorate General of Hydrocarbons has estimated the country’s resource base or
Coal Bed Methane (CBM) to be between 1400 BCM (1260 Mtoe) and 2500 BCM (2340
Million Tonnes Oil Equivalent). To give impetus to exploration and production, the
government has formulated the CBM policy. Based on two rounds of bidding under this
policy, contracts have been signed with PSUs/private companies for the exploration and
production of CBM in 13 blocks. An additional three blocks have been taken up for
development on the basis of nomination. The estimated investment in these blocks is
about Rs.560 crore and the likely CBM resources generated is estimated as 850 BCM (765
Mt). ONGC maintains that commercial production of CBM from some of these blocks will
start in 2007. Thus at the very low current rate of production, the proven gas and CBM
reserves, together, can last for some 50 years.

1.13.7 Coal Gasification

In-situ coal gasification can significantly increase the extractable energy from India’s vast
in-place coal reserves. This is so because in-situ coal gasification can tap energy from
coal reserves that cannot be extracted economically based on available open
cast/underground extraction technologies. However, in-situ gasification has not yet been
deployed commercially anywhere in the world. ONGC is engaged in trials to establish the
feasibility and economics of this technology for Indian coal and lignite in collaboration with
Russia. Neyveli Lignite Corporation has tied up with an Australian group to pursue in-situ
gasification of lignite. In-situ gasification has many environmental advantages. The
problems of overburden removal and ash disposal faced by conventional coal mining and
use are eliminated. Gasification is the first step towards a clean coal technology since

Page 26 of Chapter1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

carbon can be captured from the syn-gas produced and sequestered in the mine or
pumped back in oil or gas fields to enhance oil or gas recovery. In-situ coal gasification,
with or without carbon sequestration could be eligible for carbon credits. Finally, using this
process at abandoned coalmines might provide an economically attractive option for full
extraction of energy from in-place reserves. Clearly, the potential for domestic energy
supply based on in-situ coal gasification can be large but it has not yet been assessed.

1.14 CAPTIVE POWER PLANTS

Large number of captive plants including co-generation power plants of varied type and
sizes exist in the country which are either utilized in process industry or used for in-house
power consumption. A number of industries have set up their own captive plants so as to
get reliable and quality power. Some Captive plants are also installed as stand-by units for
operation only during emergencies when the grid supply is not available. The installed
capacity of CPPs has increased from 588 MW in 1950 to 19,103 MW in March 2005.
Captive plants including co-generation power plants could, therefore, play a supplementary
role in meeting the country’s power demand.

After the enactment of Electricity Act 2003, there is a renewed interest in captive
generation. Surplus power, if any, from captive power plants could be fed into the grid as
the new act (Electricity Act 2003) provides for open access, in non-discriminatory way.

It is envisaged that the generation from non utility captive power plants by the year 2011-12
may be of the order of 131 billion units which results into a CAGR of 10.5% p.a in captive
generation.

1.14.1 Provisions of Electricity Act and National Electricity Policy

Electricity Act, 2003 defines “Captive Generating Plant” as a power plant set up by any
person to generate electricity primarily for his own use and includes a power plant set up
by any co-operative society or association of persons for generating electricity primarily for
use of members of such co-operative society or association.

The captive power plant can be set up as stipulated under Section 9 of the Act. Provision of
which are as below:

(1) Notwithstanding anything contained in this Act, a person may construct, maintain
or operate a captive generating plant and dedicated transmission lines:

Provided that the supply of electricity from the captive generating plant through the
grid shall be regulated in the same manner as the generating station of a generating
company.

(2) Every person, who has constructed a captive generating plant and maintains and
operates such plant, shall have the right to open access for the purposes of
carrying electricity from his captive generating plant to the destination of his use:

Provided that such open access shall be subject to availability of adequate transmission
facility and such availability of transmission facility shall be determined by the Central
Transmission Utility or the State Transmission Utility, as the case may be:

Page 27 of Chapter 1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

Provided further that any dispute regarding the availability of transmission facility shall be
adjudicated upon by the Appropriate Commission.

The Electricity Rules issued by MoP notification dated 8.6.2005 prescribes that
No power plant shall qualify as a 'captive generating plant' under Section 9 read with
clause (8) of section 2 of the Act unless:

a. In case of power plant –

(i) not less than twenty six percent of the ownership is held by the captive
user(s), and

(ii) not less than fifty one percent of the aggregate electricity generated in such
plant, determined on an annual basis, is consumed for the captive use:

Provided that in case of power plant set up by registered cooperative


society, the conditions mentioned under paragraphs at (i) and (ii) above
shall be satisfied collectively by the members of the co-operative society;
Provided further that in case of association of persons, the captive user(s) shall
hold not less than twenty six percent of the ownership of the plant in aggregate
and such captive user(s) shall consume not less than fifty one percent of the
electricity generated, determined on annual basis, in proportion to their shares in
ownership of the power plant within a variation not exceeding ten percent;

b. In case of a generating station owned by a company formed as special purpose vehicle


for such generating station, a unit or units of such generating station identified for
captive use and not the entire generating station satisfy(s) the conditions contained in
paragraphs (i) and (ii) of sub-clause (a) above including -

Explanation:-
1. The electricity required to be consumed by captive users shall be determined with
reference to such generating unit or units in aggregate identified for captive use
and not with reference to generating station as a whole; and
2. The equity shares to be held by the captive user(s) in the generating station shall
not be less than twenty six per cent of the proportionate of the equity of the
company related to the generating unit or units identified as the captive generating
plant.
3. It shall be the obligation of the captive users to ensure that the consumption by the
captive users at the percentages mentioned in sub-clauses (a) and (b) of sub-rule
(1) above is maintained and in case the minimum percentage of captive use is not
complied with in any year, the entire electricity generated shall be treated as if it is
a supply of electricity by a generating company.

On the captive power generation the National Electricity Policy stipulates as under:-

Para 5.2.24: The liberal provision in the Electricity Act, 2003 with respect to
setting up of captive power plant has been made with a view to not only securing
reliable, quality and cost effective power but also to facilitate creation of
employment opportunities through speedy and efficient growth of industry.

Page 28 of Chapter1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

Para 5.2.25: The provision relating to captive power plants to be set up by group
of consumers is primarily aimed at enabling small and medium industries or
other consumers that may not individually be in a position to set up plant of
optimal size in a cost effective manner. It needs to be noted that efficient
expansion of small and medium industries across the country would lead to
creation of enormous employment opportunities.

Para 5.2.26: A large number of captive and standby generating stations in India
have surplus capacity that could be supplied to the grid continuously or during
certain time periods. These plants offer a sizeable and potentially competitive
capacity that could be harnessed for meeting demand for power. Under the Act,
captive generators have access to licensees and would get access to consumers
who are, allowed open access. Grid inter-connections for captive generators
shall be facilitated as per section 30 of the Act. This should be done on priority
basis to enable captive generation to become available as distributed generation
along the grid. Towards this end, non-conventional energy sources including co-
generation could also play a role. Appropriate commercial arrangements would
need to be instituted between licensees and the captive generators for
harnessing of spare capacity energy from captive power plants. The appropriate
Regulatory Commission shall exercise regulatory oversight on such commercial
arrangements between captive generators and licensees and determine tariffs
when a licensee is the off-taker of power from captive plant.

1.14.2 Captive Generation

At present, the Installed Capacity of Captive Power Plants (1MW and above) is about
19,000 MW. The energy generation from captive power plants (1MW and above) during the
year 2004-05 has been about 72 billion units. The growth of captive plant capacity during
the period 2001-02 to 2004-05 and the growth of energy generation from captive plants
during this period has been 3.67% and 5.01% respectively. During the year 2004-05
surplus power of 4.2 BU from captive was fed into the grid. Further, a capacity addition of
about 12,000 MW from Captive plants is expected during the 11th Plan based on
information/details received from captive power plant manufacturers and about 20% of
12,000 MW is expected to be surplus and available to be fed into the grid. However, to
harness surplus capacity from captive power plants it is essential that various bottlenecks
being faced are addressed and technical and commercial issues are resolved to make the
export arrangements attractive and commercially viable.

It is envisaged that the generation from non utility captive power plants by the year 2011-12
may be of the order of 131 billion units which results into a CAGR of 10.5% p.a.

1.14.3 Discussions with Forum of Regulator (FOR)

The issue of various charges levied by SERCs was taken up by Ministry of Power with
Forum of regulators (FOR). During the meeting of FOR, it was decided to constitute a Sub-
group consisting of CERC, State Regulators of Gujarat, Karnataka, Chhattisgarh, Andhra
Pradesh, Delhi, Orissa, Rajasthan, Haryana, MoP and CEA. A meeting of the Sub-group
was held on 16th-17th November, 2005 and these issues were discussed and various
measures were recommended for facilitating open access in distribution and harnessing

Page 29 of Chapter 1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

surplus captive generation in the country. Major recommendations of the Sub-group are as
under:

¾ Reasonable cross subsidy surcharge and other charges to provide some


economic incentive to the consumers to avail open access.

¾ The procedure for grant of open access should be simple enough to encourage
the consumer to exercise his choice.

¾ All future Captive generation capacity need not be fully locked in long term
PPAs. 15-20% of the future capacity could be kept out of long term PPAs so that
it is available to open access consumers or in the market.

¾ The SERCs should allow recovery of some portion of fixed cost in addition to the
variable cost of captive generation. The captive generators may offer their
surplus power on the basis of a firm schedule. Infirm power from CPP should
also be considered for purchase.

¾ Benchmark tariff for generators using different fuels may be indicated by the
Appropriate Commission for purchase of power from CPP of up to 15 MW plant
size.

¾ There should be no penalty for reduction of contract demand by any captive


plant

¾ For computation of wheeling charges and losses, the Sub-Group recommended


the following methodology:

The transmission charges should be specified on the basis of voltage level of


transmission.
Only technical losses should be taken into account while specifying
transmission losses
Losses should be applied in kind, i.e., the drawal schedule of the Open
Access Consumer shall be the injection schedule adjusted for losses.

¾ The Group felt that reactive energy charges from the open access consumers or
captive power plant owners may be levied by the licensee of the area at par with
other users.

1.14.4 Status of Various issues Identified

Various Regulatory/Technical/Commercial issues raised during regional level meetings as


well as meetings in CEA held with CPPs/Industry Associations etc. along with the status of
action taken is given as under.

Page 30 of Chapter1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

Sl. Issues Action/Status


No.
1. Open Access, which is the key provision to attract investment in new Most of the SERCs have already
generation/ transmission/distribution projects, should be made issued regulations.
effective as per the provisions of Electricity Act, 2003 and National
Electricity Policy,
2. Surcharge/ Cross Subsidy Surcharge in some States is very high Tariff policy notified by GoI on 6th
January, 2006
3. Very high, discriminate electricity duty imposed on captive power Sub group recommends that
generation and imposition of cess on captive power generation by electricity duty should not be imposed
some State Govts. on generation of power from captive
power plant. This may be considered
by State Govts.
4. Reduction in contract demand by CPP not allowed by state DISCOM Recommended by Sub group
resulting in higher demand charges
5. Demand charges levied on connected load irrespective of actual Recommended by Sub group
drawal from DISCOM.
6. Exorbitant wheeling charges for intra-state transmission system for Recommended by Sub group
transfer of surplus power from captive plant.
7. Other charges levied on CPPs by Regulatory Commissions. Recommended by Sub group
– Additional surcharge
– Parallel operation charge
– Contract Demand Charge/ Annual Minimum Guarantee
Charge
– Transmission Charge
– Fixed Charge for electricity connection
– SLDC charge
– Reactive energy charge
– Banking charge

1.14.5 Recommendations for

The Working Group discussed various recommendations of the Regional level meetings
held with CPPs/ Industry Associations etc. and workshop held by MoP & CEA and feels
that Captive/group captive generation should be encouraged as envisaged in the National
Electricity Policy and Integrated Energy Policy. To further address the problems faced by
the captive generators and harnessing surplus power from the CPPs, following
recommendations are made by the Sub-group.

(A) General- Captive & Renewable/ Cogeneration Plants

i) To initiate action through Energy Departments of all the States to identify the surplus
capacity available from the captive power plants and approach State
Utilities/Discoms to buy the surplus power available from the captive power plants.

ii) As one of the option, CPP may be given tariff at frequency based UI rates under
ABT mechanism.

At present the UI rates are as under:


Frequency UI Rate (Rs.)
49.0 Hz 5.70
49.5 Hz 3.45
50.0 Hz 1.50
50.5 Hz. 0.00

Page 31 of Chapter 1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

iii) Single Window at State level to handle all issues relating to installation of Captive
plants i.e. environment clearance, open access etc):

(As per amended Electricity Act CPPs have been freed from licensing. However,
permission needs to be obtained in respect of environmental clearance as well as
third party sale of power (Open Access). The single window to handle all such
issues will greatly facilitate in obtaining the required clearance within a stipulated
period).

iv) Electricity duty plus cess to be reduced as it is high in certain States i.e. AP–
25p/unit; Chattisgarh- 10p/unit; West Bengal- 20p/unit.

v) Electricity duty to be imposed on consumption and not on generation

vi) Custom duty on import of all fuels (coal, gas and Furnace oil) to be fixed at
reasonable rates.

vii) Open access to be allowed in phases by SECRs who have issued regulations

Connected demand 10 MW and above – June 2005/April 2006


Connected demand 1 MW and above – April 2007/ December 2008

viii) Monitoring of capacity addition and generation from captive/co-generation plants is


required to be strengthened. In this exercise a methodology is required to be
worked out in association with Ministry of Non-Conventional Energy Sources as
there is an apprehension that the co-generation plants and renewable energy
sources plants which are captive also are included in the Installed Capacity of Utility
as well as in Captive Plants Capacity.

(B) Renewable/Co-generation Plants

i) SERCs to encourage and specify minimum percentage for purchase of power from
renewable and co-generation plants.

ii) Mandating the distribution utilities in the State to purchase renewable energy to
reach at least a target of 5% of total energy consumption in the area of each
DISCOM/licensee by the year 2012.

iii) Co-generation power is to be given “Must Run” status. Co-generation power should
be treated at par with non-conventional energy sources such as wind energy.
Therefore, no backing down of the co-generation power be resorted to by the off
taking distribution utilities except in events of force majeure.

iv) Provision of banking facility may be considered and withdrawal of banked energy
may not be linked with grid frequency and time of day in respect of renewable
energy sources captive/co-generation plants.

iv) There should be no cross-subsidy surcharge on surplus power to be supplied by a


renewable source based captive/Co-generation plant.

Page 32 of Chapter1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

1.15 MAXMISING GENERATIOM FROM EXISTING PLANTS AND AGS&P

Optimization of generation from the existing generation capacity is of utmost importance in


the resource crunch environment. The installation of new power projects involves large
investment and long gestation period. Among various options considered by the Working-
Group, following options are recommended:

1. Renovation & Modernization and Life Extension of Power Plants


2. Energy Audits
3. Better O & M practices

1.15.1 Renovation & Modernization and Life Extension of Power Plants

The main objective of Renovation & Modernization (R & M) of power generating units is to
make the old operating units well equipped/ modified/ augmented with a view to improve
their performance in terms of efficiency, output, reliability, safety and availability as
compared to the original values. It involves replacement and modification of various
systems/equipment and overcoming design deficiencies, if any, & obsolescence. It also
involves activities relating to viable technological up gradation.

1.15.2 R&M and LE of Thermal Power Plants

A Renovation and Modernisation (R&M) Programme for Thermal Power Stations was
launched by the Government of India all over the country way back in September 1984 for
completion during the Seventh Plan Period. This programme was successfully completed
and intended benefits were achieved. In the subsequent 8th and 9th Plans, Renovation and
Modernisation and Life Extension (LE) works were carried out on a number of older
generating units which resulted in improvement in their performance and extension of their
useful life by about 15 to 20 years. This is evident from the fact that the average plant load
factor (PLF) of these thermal power stations increased from 53.9% in the year 1990-91 to
74% during the year 2006-07 (upto Nov. ).

At the beginning of the 10th plan, 106 old thermal units aggregated to a capacity of about
10413 MW were identified for Life Extension works at an estimated cost of Rs.9200 crores
for completion during 10th Plan. However progress was not satisfactory due to high
execution time & cost involved in LE works. The cost of LE was also not economically
feasible considering the age of plants and there was reluctance from power plants to shut
down their units for longer periods due to prevailing power shortages.

In view of above a new initiatives called Partnership of Excellence was taken up the details
of which is given in following paragraphs.

1.15.3 PARTNERSHIP IN EXCELLANCE (PIE) PROGRAMME

Under this programme generating companies who were performing well provide assistance
in improving performance of non-performing companies. Towards this initiative, CEA
identified 22 power stations of 11 utilities, with a capacity of 7930.5 MW across the country.
Out of these, 17 stations with an operating capacity of 5050 MW were entrusted to NTPC
and one stations (280 MW) to TATA power. On remaining 4 stations the respective utilities

Page 33 of Chapter 1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

are taking their own course of action. The plants entrusted to NTPC recorded an additional
generation of power-3690 MUs corresponding to an equivalent capacity addition of 720
MW, considering national average PLF. Capacity addition of this order requires an
investment of around Rs.3,000 crore at a Greenfield project. Some additional units have
also been identified for R&M and life extension. The decision for investment for R&M/LE
will be based on cost benefit analysis. If not economically viable installation of new plants
at existing sites, may be considered.

Steps involved in implementation of PIE Programme

‘PIE’ programme is envisaged to be implemented in 3 phases as under:

Phase-I : Toning up of O&M practices and training of operating personnel

Phase-II: Procuring essential spares from Original Equipment Manufacturers (OEM),


carrying out comprehensive Capital Overhauling and doing essential R&M works
to improve PLF above 60 % .

Phase-III : Residual Life Assessment ( RLA) studies and major Renovation &
Modernisation / Life Extension ( R&M / LE ) works based on techno-economic
viability.

Present status of progress

The following steps have been taken / are being taken on identified stations:

• Agreements with concerned power utilities have been signed by better performing
Partners viz. NTPC and Tata Power between October 2005 to December 2005.

• NTPC has already deputed 136 executives at 13 stations and has also set up head
office at Patna for implementation and monitoring of ‘PIE’ programme. On remaining
2 PIE stations of NTPC namely Bandel and Santaldih, PIE activities could not be
undertaken due to lack of interest from WBPDCL as reported by NTPC. As informed
by NTPC, WBPDCL has planned to phase out Bandel TPS (unit 1 to 4) due to
ageing of these units. Santaldih TPS has been operating at low PLF due to
inadequate capacity of Coal Hahdling Plant.

• Tata Power has deputed its executives at Dhuvran station (units-1 & 2) of GSECL
for effective implementation and monitoring of ‘PIE’ programme.

• Phase-I activities of improved O&M practices and minimum overhauling have been
mostly completed on 13 PIE stations by NTPC and 1(one) PIE station by Tata
Power.

• Implementation of management practices as per NTPC’s O&M system Manual is in


progress.

• Phase-II activity of Comprehensive overhauling has been initiated on 13 PIE


stations by NTPC. In order to accelerate the pace of supply of spares and obviate
the need for signing of MOUs with the concerned power utilities, a system of
placement of Open Order on BHEL by power utilities has been introduced. Most of
Page 34 of Chapter1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

the power utilities have placed open order for supply of spares on BHEL in Oct- Nov
2006.

• The details of PLF and Generation in December 2006 and during April to December
2006 on various stations covered under PIE programme as well as same during the
corresponding period last year are given in Annexure-1.11 . It can be seen that 10
stations under PIE programme with partnership with NTPC and Tata Power have
shown marked improvement in Generation and PLF during the period April to
December 2006 as compared to corresponding period last year.

Achievements

The programme has started showing results in the form of improvement in PLF. In
December 2006, 8 (eight) stations achieved PLF above 65% as shown below:

Sl Utility Power Capacity under Plant Load Factor ( % )


no. Station PIE (MW) during
Dec, 05 Dec, 06
1. JSEB Patratu units 80 MW 38.00 83.15
1&2
2. DVC Durgapur 350 MW 42.23 81.29
units-3 &4
3. IPGCL Rajghat 135 MW 84.31 81.17
units-1 &2
4. DVC Chandrapura 390MW 70.98 78.04
units-1,2 &3
5. TNEB Ennore units 280 MW 21.37 73.49
2,3 &5
6. TVNL Tenughat 420 MW 45.73 72.33
TPS units-
1&2
7. UPRVUNL Parichha 220 MW 26.49 71.28
Units-1,2 of
8. DVC Bokaro ‘B’ 630MW 65.03 68.58
units-1,2 &3

Most of other stations also showed improvement in their PLF. This improvement in
performance has been achieved through implementation of phase-I activities of PIE
programme. Further, improvement in PLF is expected on completion of phase-II activities.
The phase-II of the programme, therefore, needs to be continued and new stations which
are perpetually running at PLF below 60% and have sufficient remaining lifetime (Details
given in table 1.26) can be considered for inclusion under PIE programme.

Page 35 of Chapter 1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

Table 1.26
Stations running at PLF lower that 60% to be considered for
Inclusion under PIE

Name of the Cap. (MW) PLF( %) up to


Station Dec
05-06 06-07
Faridabad Extn. 3x60 =180 50.3 40.9
(HPGC)
Chandrapur 4x210+3x500=2340 68.4 58.0
(MSEB)
Neyveli Lig. St. II 7x210 = 1470 74.7 58.3
( NLC )

1.15.4 R&M and Uprating of Hydro Plants:

The normal life expectancy of a hydroelectric power plant is 30 to 35 years after which it
needs life extension. Many of the existing hydro power stations could be modernized to
generate reliable and higher yield by minor modifications. By adopting modern equipment
like static excitation, micro-processor based controls, electronic-micro processor based
governors, high speed static/Numerical relays, data logger, optical instruments for
monitoring vibrations, air gaps, silt content in water etc. availability of hydro power stations
could be improved and outages minimized.

In situations like run-of-the river schemes in Himalayan and Sub-Himalayan region,


excessive silt contained in the inflows causes enormous damage to the under water
parts of turbines, requiring rehabilitation almost every year.

Upgrading of hydro plants calls for a systematic approach in view of a number of


influencing parameters pertaining to the prime mover besides its repercussions on the total
hydro electric development which itself may be a sub system of an integrated power
development. A number of hydraulic, mechanical, electrical and above all economic factors
play a vital role in deciding the course of action and the modalities of an upgrading /
uprating programme. Uprating of hydro power plant cannot thus be considered in isolation.
It has to be strategically planned, may be in certain steps, keeping in view all the techno-
economic considerations.

(a) Review of 10th Plan Programme of R&M and LE – Hydro

The Group reviewed the Hydro R&M & Uprating Programme as well as the achievements
during the 10th Plan. A Summary of the projects planned, completed and on which work is
ongoing in the 10th Plan is as furnished in Table 1.27

Page 36 of Chapter1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

Table 1.27
Summary of R&M and Life Extension Programme and Achievements for 10th Plan –
Hydro

Description R&M LE
No. of Projects Covered 37 16
Capacity (MW) 5257.85 642.25
Estimated Cost (Rs. Crores) 1116.11
Expenditure incurred (Rs. Crores) till
1032.83
5/06
Targeted Benefits (MW ) 137.83 636.25
Actual Benefits achieved 114.4 498.75

Project-wise details of projects completed during 10th Plan is furnished at Appendix 1.12
and of ongoing projects programmed for completion during 10th are furnished in Appendix
1.13.

(b) Programme for 11th Plan – Hydro

The Group deliberated on the 11th Plan programme for hydro R&M & Uprating Schemes
and a Summary of 11th Plan programme as well as ongoing projects and those projects on
which work is yet to commence is furnished in Table 1.28.

Table 1.28
Summary of R&M and Life Extension Programme and Achievements for 11th Plan -
Hydro

Description R&M LE
No. of projects Covered 60 41
Capacity (MW) 11278.15 4025.2
Estimated Cost (Rs. Crores) 3478.5.5
Expenditure incurred (Rs. Crores) till
232.827
5/06
Targeted Benefits (MW) 302.25 4025.21
Actual Benefits achieved

Project-wise details of ongoing hydro RM&U projects for completion in 11th Plan are
furnished in Appendix 1.14. Project-wise details of hydro RM&U projects for completion in
11th Plan but works on which are yet to be taken up for implementation are furnished in
Appendix 1.15.

1.15.5 R&M and Plant Life Extension of Nuclear Plants

During the course of the operating life of a Nuclear Power Plant, it goes through a series of
routine and several safety reviews, based on which periodic improvement/safety upgrades
are implemented. The coolant channel of older units (which commenced commercial
operation in 1993) Pressurized Heavy Water Reactors need replacement. After about 10
years of operation at full power, these coolant channels are replaced during a long shut
down. Advantage of this shut down is taken for safety upgrades and plant life extension, as
required.
Page 37 of Chapter 1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

Such R&M activities have been completed for Rajasthan Atomic Power Station Unit-2 and
Madras Atomic Power Station Unit-1&2.

R&M activities as above have been taken up on NAPS-1 and are expected to be
completed during 2006-07. Similar work is planned for NAPS-2 and KAPS-1 in the 11th
Plan. Details of financial outlay in respect of these projects are given in Table 1.28.

Table 1.28
Summary of R&M and Life Extension Programme and Achievements for 11th Plan –
Nuclear
(Figs in Rs cr.)
Name of Estd. Anticipated 2007-08 2008-09 2009-10 2010-11 2011-12 Total 11th
project Completion exp. by Plan
cost 10th Plan
end
NAPS - 247 171 105 105
1&2
KAPS-1 133 5 66 54 119

1.16 ENERGY EFFICIENCY IMPROVEMENT THROUGH ENERGY AUDIT

As per Energy Conservation Act 2001, Energy audit means the verification, monitoring and
analysis of use of energy including submission of technical report containing
recommendations for improving energy efficiency with cost benefit analysis and an action
plan to reduce energy consumption. Also under the provision of Energy Conservation Act
2001, all designated consumers declared by the Government would have to undertake
mandatory Energy Audit studies by accredited Energy Auditors.

Energy Audit studies aim at determining the present level of performance of main power
plant equipment and selected sub-systems and comparing them with design figures.
Reasons for deterioration are analysed. The studies may also involve review of design of
various equipment to see if these are over-designed. Techno-economic viability of
introducing new efficient technologies is also included in the energy audit studies. In fact
the basic objective is to reduce the consumption of various inputs (coal, oil, power, water)
per unit of power generation.

Areas normally covered in a power plant are:

ƒ Boiler efficiency
ƒ Air heater performance
ƒ Mills performance
ƒ Furnace radiation losses
ƒ Turbine heat rate
ƒ Regenerative system performance
ƒ HP/IP cylinder efficiency
ƒ Condenser performance
ƒ Auxiliary power consumption
ƒ Lighting systems
ƒ DM water consumption
Page 38 of Chapter1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

ƒ Secondary fuel oil consumption


ƒ Any other sub-system i.e. air compressor, air conditioning etc.

In view of the foregoing, it is suggested that “Energy Efficiency Cell” shall be created at all
thermal power stations. This cell shall be responsible for the following:

¾ Internal Energy Audit groups shall be set up in each power plant. Capacity
building of the efficiency group must be done to enable them to carry out
Energy Audit tests on their own.

¾ Regular audits shall also be got conducted from accredited Energy Auditors.

¾ All recommendations that emerge from these audits must be implemented if


these are techno-economically feasible. Short term measures can be made
part of the annual plan/annual overhaul of the unit whereas long term
measures can be taken up under the R&M schemes of these stations.

¾ Energy Efficiency Awareness campaign shall be taken up among staff of the


power plant.

Better O&M practices

Better O&M practice is also an effective tool to improve the performance of existing plants
major ones being as follows:

1. Run the machines at parameters near to design parameters.


2. Keep proper fuel/air mixture to reduce high carbon loss in ash .
3. Replacement of air heater seal to avoid air ingress in Air preheaters.
4. Maintain the recommended fineness of Pulverized coal.
5. Reduce the excessive R/H spray & enforce burner tilt mechanism to control
reheat temperature.
6. Instrumentation needs to be checked and calibrated regularly. Wide variation
in readings may be observed and corrected.
7. Control CW flow to check under cooling of condensate.
8. Attend air ingress into condenser.
9. Keep the condenser tubes clean.

1.17 ACCELERATED GENERATION & SUPPLY PROGRAMME (AGS&P) SCHEME

Under the AGS&P Scheme, MOP is providing interest subsidy through financial institution
(PFC & REC) with an objective to reduce the rate of interest on the term loans for R&M of
State Sector thermal power grants.

1.17.1 Scope of the scheme

The Scope of the AGS&P Scheme is as follows:

• The Scheme covers all States/UTs.


• The financial support, to be provided for the renovation/modernization and uprating
works undertaken by the Utilities in Government /Public Sector.

Page 39 of Chapter 1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

• The Scheme is applicable to thermal power stations of station capacity

Note: Release of AG & SP funds under new loans sanctioned at Stage II and Stage III
shall take place only after appointed consultant/ partner confirms that the O&M practices
have reached satisfactory level.

1.17.2 Salient features of the scheme

The salient features of the scheme extension of Accelerated Generation & Supply
Programme to Tenth Five Year Plan period and Govt. directions/Guidelines thereto are as
under:-

a) The assistance under the AG&SP scheme shall be limited to only state sector R&M
generation projects including those based on non-conventional energy sources.
Interest subsidy under AG&SP schemes will be admissible for D.V.C.’s R&M
projects also.

b) Only those States, which perform satisfactorily with respect to the agreed milestones
of the reform MoUs entered into with the Ministry of Power and of the Action Plans
to achieve commercial viability in accordance with the Reform programme, would be
eligible for funding under AG&SP. The better performing states would be given
preference. The milestones of Action Plans would be stringent and will aim at
progressively reducing the gap between the cost per unit and the revenue collected
per unit of electricity.

c) The total assistance under the Scheme will be limited to the budget provision in the
Tenth Five Year Plan.

d) Interest subsidy under the scheme has been reduced from 4% in Ninth Plan to 3%
in Tenth Plan i.e. 1.4.2002 to 31.3.2007. The subsidy for projects in North-Eastern
Region would be 4%. Interest Subsidy would be restricted to difference of lending
rate and benchmark rate subject to a maximum of 3% and 4% respectively.. The
benchmark rate would be rate of interest on 12 years’ Government security for that
financial year.

e) Grants under the AG&SP scheme will be provided to State Electricity Boards
(SEBs), State Generating Corporations (SGCs) and state Power Departments
(SPDs) for carrying out studies which help to achieve policy objectives of the
Government relating to Power sector. These include Power sector Reform and
Restructuring Studies, System Studies, Renovation & Modernisation (R&M) Studies,
Life Extension (LE) Studies, retainer consultancy for R&M and Environment/social
studies. Distribution studies which are covered under the proposed APDRP
Scheme will not be eligible for grant of assistance under AG&SP Scheme. some
minimum expenses relating to overall power sector reforms and restructuring
studies on a need based approach would be considered for funding under the
AG&SP Programme. To this extent guidelines issued in OM No. 32024/23/2001-
PFC dated 24.12.2002 and 7th March, 2003 and supplemented for the sanction of
appropriate level of funds within the overall allocation of the 10th Plan as budgeted
from year to year.

Page 40 of Chapter1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

f) Interest subsidy in respect of generation project covered under AG&SP will be


reduced in proportion to the delay in commissioning of the project in following
manner:

Reduction %Delay(D/X) Reduction


0% - 10% Nil >55% - 70% 2%
>10%-25% 0.5% >70% - 85% 2.5%
> 25% - 40% 1.0%
>40% - 55% 1,5% Above 85% 3.0%

D is delay (in days) = Actual Commissioning date- agreed Commissioning Date


X (in days) = Agreed Commissioning Date – Date of sanction of loan.

The reduction in interest subsidy will be applicable from the actual date of
commissioning or the date of 85% delay, whichever event occurs earlier. Wherever
the interest subsidy is less than 3%, the same would be spread over seven slabs
proportionately as per formula laid down above and the concerned lending institution
will account for it to the Ministry of Power as interest subsidy is front ended.

(g) All generation projects which are estimated to be commissioned in Tenth Plan
period would be eligible for assistance under AG&SP

1.17.3 Eligibility criteria for the scheme

(a) The project authority are to ensure that there has been annual overhaul of the plant
on regular basis. In case, this has not been done so, the same have to be done by
the project authority In case, if it is found that improvement can be affected by
making a change in the management of the plant, that should be resorted to by the
project authority without any delay.

(b) Emphasis will be on the rehabilitation of core and essential equipments of the plant.
However, while accepting replacement of major items, clear evidence of failure or
frequent operational trouble will form the main criteria.

(c) The replacement of minor items which could otherwise be covered under the routine
and preventive maintenance of power stations, shall not be covered under this
scheme.

(d) The R&M Report should contain brief history of the project, technical details, unit-
wise annual generation data since commissioning, details of forced outages,
modifications/replacement works undertaken earlier, problem now encountered and
the reasons for poor performance. The report should also indicate the nature &
scope of the R&M works involved, cost estimates and the cost benefits analysis etc,

(e) The proposals shall be considered subject to their merits, techno-economic viability
and availability of funds

1.17.4 Procedure for availing interest subsidy

Page 41 of Chapter 1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

i) If the project is found suitable for renovation/modernization work, leading to optimum


generation of power. The State Government/ SEBs will then be firm up the cost
estimates of the identified works so as to fix the financial requirements for the R&M
activities to be undertaken. A firm time schedule will be worked out to complete the
work. The project authority/State 0Government must furnish a certificate that loans
for R&M absolutely necessary .

ii) The PFC and R.E.C. shall have to include a clause in their Term Loan Agreement
with the Project authorities to recover the subsidy amount along with the penal
interest of 3% more alongwith the recovery of Term Loan for cases of default where
the interest subsidy is cancelled by MOP for violation of terms of conditions of this
circular. Loan can be recalled by the FIs before project completion or where project
is not completed for whatever reason. They shall create a ‘pari-passu’ charge for the
recoveries to be made by them for refund of subsidy amount to MOP. The un -
disbursed amount of interest subsidy released by MOP to the FIs along with the
penal interest as above will, be returned immediately in all such cases.

iii) MOP will examine the proposal received from the financial institution and approve
interest subsidy on the basis of overall viability of the proposal, fulfilment of general
terms and conditions, availability of funds and general policies of MOP.

iv) All expenses towards the cost of the project, over and above the Ministry’s support
agreed to, including escalations in the cost, if any, will have to be met by the
Executing Agencies.

It is recommended that R&M schemes shall be continued during 11th and 12th Plan also.
However it must be ensured that routine maintenance activities are not included in these
schemes. Only activities which aim at increasing the efficiency of the unit or improve the
availability or are required to meet environmental norms or are aimed at renovating
obsolete equipment- Controls and Instrumentation are included in R & M schemes. Further
for Life Extension schemes, a cost benefit analysis should be carried out vis-à-vis
installation of new unit at the same site.

The Group recommends that the AGS&P Scheme shall continue.

1.18 NON CONVENTIONAL ENERGY SOURCES

Our country has significant potential for generation of power from Non Conventional
Energy Sources such as Wind, Small Hydro, Bio mass and Solar Energy. Limited
availability of fossil fuel like coal and gas has further highlighted the importance of power
from these sources. In addition, these sources provide a particularly attractive solution for
meeting requirement of power at remote locations, in case of which it is not feasible to
extend the grid. All efforts are therefore being made to tap these resources for generation
of power to supplement power from Conventional Sources.

1.18.1 Development of Non-Conventional Energy Resources

The total estimated medium-term potential (2032) for power generation from renewable
energy sources such as wind, small hydro, solar, waste to energy and biomass in the
country is about 1,83,000 MW. The grid interactive installed capacity from renewable is

Page 42 of Chapter1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

likely to increase from about 3,500 MW at end of 9th Plan to 23,500 MW at the end of 11th
Plan. The grid interactive Installed Capacity as on 30.09.2006 is 8996 MW. Source wise
details of Potential and Installed Capacity as on 30.09.2006 are furnished in Table 1.29

Table 1.29
Potential and Installed Capacity of Renewable Power
(AS ON 30.09.06)
(Figures in MW)
Sources / Systems Estimated mid- Cumulative
Term (2032) Installed Capacity
Potential (As on 30.09.2006)
Wind Power 45,000 6070.20
Bio- Power(Agro residues & 61,000 466.50
Plantations)
Co-generation Baggasse 5,000 571.83
Small Hydro (up to 25 MW) 15,000 1849.78
Waste to Energy 7,000 34.95
Solar Photovoltaic 50,000 2.74
TOTAL 1,83,000 8996.00
Source MNRE

Sector-wise details of renewable energy sources are as follows:

1.18.2 Tenth Plan – Target and Achievement

A target of 3075 MW was set for the 10th Plan in respect of grid interactive renewable
power against which an achievement of 4635 MW has been made during the 1st four years
of the 10th Plan and a target of 1888 MW has been set for 2006-07 i.e. last year of the 10th
Plan. Source wise details are furnished in Table 1.30.

Table-1.30
10th Plan Targets and Achievements for Grid Interactive Renewable Power

(Figures in MW)
Sources / Systems Achievement Target
Target (2002-03 to 2005- 2006-07
06)
As on 31.03.2006
Wind Power 1500 3665 1515
Biomass Power Baggasse Co- 700 532 228
generation Biomass Gasifiers
Small Hydro (up to 25 MW) 600 388 132
Waste to Energy -MSW 80 28 13
-Industrial Waste
Solar Power 145 0.73 0.00
TOTAL 3075 4614 1888
Source MNRE

Page 43 of Chapter 1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

11th Plan Target

Details of 11th Plan target of Grid Interactive renewable power are furnished in Table 1.31.
Table 1.31
11th Plan Tentative Targets for Grid Interactive Renewable Power

(Figures in MW)

Sources / Systems Target for 11th plan

Wind Power 10,000


Biomass Power 2,100
Baggasse Co-generation
Biomass Gasifiers
Small Hydro 1,400
(up to 25 MW)
TOTAL 13,500
Source MNES

The above target of 13,500 MW for grid interactive renewable power does not include 1000
MW from Distributed Renewable Power System (DRPS).

The programme is based on the draft report of the Working group on Non- Conventional
Energy Sources for 11th Plan

1.18.3 Summary of Installed Capacity

Considering the 10th Plan and tentative 11th Plan capacity addition as detailed above,
Summary of Installed Capacity is furnished below:

Installed capacity by the end of 9th Plan (As on 31.3.2002) 3,475 MW


Installed capacity by the end of 2005-06 (As on 31.3.2006) 8,088 MW

Programme for 2006-07 1,888 MW


th
11 Plan programme for 2007-12 13,500 MW
Total Installed Capacity by the end of 11th plan 23,476 MW

Say 23,500 MW
Reliable figures for generation from these projects are not available but assuming average
PLF of 20%, this will generate about 131 BU by 2011-12.

1.19 ISSUES TO BE ADDRESSED AND STRATEGY TO BE ADOPTED FOR 11th


PLAN

Transition of the Indian Power Sector from the era of SEBs to separate generation,
transmission and distribution utilities, independent regulatory bodies and entry of private
and foreign players is expected to fundamentally transform the power scenario. However,
since this restructuring is still under the process of evolution, a number of crucial issues

Page 44 of Chapter1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

need to be addressed and sorted out. A conducive environment needs to be created to


fructify the benefits expected from the Acts and the Policies of the Government.

With a view to achieve the above as also learning from experiences during the past Plans,
it is essential to identify Issues, both direct and indirect involving infrastructural constraints.
These Issues need to be addressed to facilitate the planned capacity of about 68,869 MW
during the 11th Plan. Some of the Issues pertaining to Capacity addition and maximizing
generation from existing plants are as follows:

1.19.1 Analysis and Close monitoring of 11th Plan projects

In order to fulfill the Government’s Mission of providing power to all by the end of 11th Plan
i.e.2012, a detailed analysis of the status of 11th Plan projects has been carried out with a
view to tie up all requisite inputs and to remove all bottlenecks in their implementation.
Details of the analysis given in Table 1.32.

Table 1.32
Status of 11th Plan Projects
Figures in MW
Under Construction 31,345
Hydro 11,931
Thermal 16,254
Nuclear 3,160
Committed projects 37,524
Feasible for benefit during 11th Plan 68,869

In so far as projects under construction are concerned, no difficulty is foreseen in


implementation of these projects

1.19.2 Status of Committed Capacity in 11th Plan on which construction is yet to


start are given in Table-1.33
Table-1.33
Figures in MW
Hydro 3,654
Thermal 33,870
Coal 32,520
Lignite 250
Gas 1,100
Total 37,524

1.19.2 Preparedness of Projects on which Construction is yet to start are given in


Table-1.34 & Table 1.35.

Page 45 of Chapter 1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

Table-1.34
Hydro
Status MW
Projects awaiting investment 3,169
decisions/work award
Concurrence to be accorded by 485
CEA/State Government
Total 3,654

Table-1.35
Thermal
Status MW
Coal blocks/linkages yet to be 7,000
allocated
Total 7,000

In case of above projects, for each project a milestone time-schedule has been created
which would ensure timely completion of each activity. This should be adhered to avoid
bunching of projects in the last two year of 11th plan and to ensure that plan targets are
met.

1.19.3 Augmentation of Infrastructural facilities

Implementation of this large capacity would call for augmentation of manufacturing


capabilities in the various input sectors namely,

¾ Main Plant and equipments - BHEL has drawn up a Plan for capacity augmentation
from 6,000 MW to 10,000 MW with an investment of Rs 1600 crs. This programme
is in an advanced stage of implementation and is expected to be completed by
2007. BHEL plans to further enhance its capacity as deemed necessary, on receipt
of sustained capacity addition programme along with the mix in the 11th & 12th Plan
periods.

¾ Key inputs - This would call for augmentation in manufacturing capacities of steel,
cement, aluminum and also in the manufacturing capabilities of various associated
equipment like, large motors, coal handling plants, water treatment plant, ash
handling and ash utilizing facilities, etc.

¾ Construction agencies – This area also needs large augmentation as at present


there is lack of qualified contractors for taking up construction of large hydro and
thermal power plants.

1.19.4 Arrangement for fuel requirement

Coal based capacity of about 46,635 MW has been identified for commissioning during
11th Plan period and the requirement of coal during 2011-12 has been assessed as 545
Million tons per annum. Details of total requirement of coal viz-a-viz indigenous production
plans are given in Table 1.36 & Appendix 1.9

Page 46 of Chapter1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

Table 1.36
Fuel Requirement (Tentative) during 2011-12

Fuel Requirement (2011-12)


Coal* 545 MT
Lignite 33 MT
Gas/LNG** 89 MMSCMD

* From domestic sources, total coal availability is expected to be 482 MT per annum by
2011-12. Accordingly, imported coal of the order of 40MT, equivalent to 63 MT of Indian
coal, may have to be organised. This quantity may reduce provided production of
domestic coal is increased.

** 89 MMSCMD of gas requirement at 90% PLF has been projected in 2011-12. At


present, the availability of gas is of the order of 40 MMSCMD and therefore not
sufficient to meet the requirement of even existing plants.

¾ On an average, power sector is being supplied 70-75% of the coal produced by Coal
India Ltd. The above requirement of coal also includes the coal produced by
individual organizations from captive blocks allotted to them.

¾ Tie up of coal requirement as per the above schedule shall be ensured

As regarding requirement of gas 2114 MW gas based projects have been planned during
11th Plan and these projects have firm tie up of gas.

1.19.5 Summary of Fund Requirement for Generation Projects

The details of the overall capacity addition programme of 68,869 MW during 11th Plan and
fund requirement of Rs 4,10,897 crore including start-up projects for capacity addition in
12th Plan are tabulated in Table 1.37.

Table 1.37
th
11 Plan Capacity addition & Fund Requirement (including advance action funds for
12th plan projects)
Sector Fuel Type Likely capacity Fund Requirement
addition (MW) (Rs. crore)
Central Hydro 9,685 27,231
Thermal 22,310 74,782
Nuclear 3,160 8,970
Total 35,155 1,10,982
State Hydro 2,637 4,349
Thermal 21,852 75,278
Total 24,489 79,627
Private Hydro 3,263 13,234

Page 47 of Chapter 1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

Sector Fuel Type Likely capacity Fund Requirement


addition (MW) (Rs. crore)
Thermal 5,962 17,858
Total 9,225 31,092
All India Hydro 15,585 44,814
Thermal 50,124 1,67,918
Nuclear 3,160 8,970
Funds for projects
Total 68,869 2,21701
benefiting in 11th Plan
Funds for projects Hydro 31,734 86,291
benefiting in 12th Thermal 47,225 81,877
Plan Nuclear 12,800 21,208
Total 91,759 1,89,195
Grand Total 1,52,963 4,10,896

The overall requirement of funds in 11th Plan has been estimated as Rs. 10,31,600 crore
including NCES, Captive and Merchant Power Plants. The details along-with sources of
funds are given in Chapter 10 of the report.

1.19.6 Manpower Requirement

In order to facilitate a capacity addition of 68,869 MW during the 11th Plan, trained and
qualified manpower is the most essential requirement. Recruitment of proper personnel
and necessary training facilities and programmes need to be made available. However
quantification of the same is given in Chapter-7 on Manpower Requirement.

1.20 RECOMMENDATION OF THE GROUP

1. The Working Group recommends generation planning based on growth of energy


generation requirement of 9.5%. Keeping in view the above objectives and
preparedness of various projects the Working Group recommends capacity addition
of 68,869 MW during 11th Plan as per details given below:
Table 1.38

TOTAL THERMAL BREAKUP TOTAL


SECTOR HYDRO NUCLEAR
THERMAL COAL LIGNITE (%)
GAS/LNG
36655
CENTRAL 9685 23810 22060 1000 750 3160
(53.2%)
22989
STATE 2637 20352 19365 375 612 -
(33.4%)
9225
PRIVATE 3263 5962 5210 0 752 -
(13.4%)
68869
ALL-INDIA 15585 50124 46635 1375 2114 3160
(100%)

Page 48 of Chapter1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

2. States are required to take an active role in the capacity addition programme by
their own agencies & by private sector participation through tariff based competitive
bidding route on the lines of developments of Ultra Mega Power Project. In the 11th
plan addition of less than 50% of total capacity is targeted in states and private
sector. It is recommended that in 12th Plan more than 50% capacity should come
through initiative of the states.
3. Some of the states do not have resources for capacity addition in their states. Such
states should tie up long term PPAs with surplus states/generation companies.
4. Manufacturing capacity of BHEL needs to be enhanced to meet the capacity
addition programme envisaged in 11th & 12th Plans.
5. A 10 year plan for hydro development is to be pursued in view of higher gestation
period. A hydro capacity of 30,000 MW has been identified for commissioning during
12th Plan. The survey and investigation, preparation of DPR, statutory clearances
should be vigorously followed up right from now to enable their commission during
12th Plan. The CEA should closely monitor progress on these projects. .
6. The Working Group recommends continuation of PIE programme during 11th Plan
also.
7. In addition to capacity addition programme, concerted efforts to continue in regard
to:

- Development of captive power plants.


- Maximising Generation from existing plants.
- Energy Efficiency improvement through Energy Audit.
- Better O & M practices.
- RM&U/Partnership in Excellence (PIE) Programme.
- Development of Non-Conventional Energy Sources.

8. Major recommendations for facilitating open access in distribution and harnessing


surplus captive generation in the country are as under:

¾ Reasonable cross subsidy surcharge and other charges to provide some


economic incentive to the generators to avail open access.
¾ The SERCs should allow recovery of some portion of fixed cost in addition to the
variable cost of captive generation. The captive generators may offer their
surplus power on the basis of a firm schedule. Infirm power from CPP should
also be considered for purchase.
¾ There should be no penalty for reduction of contract demand by any industry
having captive plant.

********

Page 49 of Chapter 1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

Appendix –1.1

SUMMARY OF CAPACITY ADDITION TARGET OF 41,110 MW DURING 10th PLAN


(REGION WISE, SECTOR WISE AND STATUS WISE)

(Figures in MW)
HYDRO THERMAL NUCLEAR TOTAL
A SECTOR WISE

CENTRAL 8,742 12,790 1,300 22,832


STATE 4,481 6,676 0 11,157
PRIVATE 1,170 5,951 0 7,121
TOTAL 14,393 25,417 1,300 41,110
B REGION WISE

NORTHERN 7,274 5,046 0 12,320


WESTERN 3,752 6,604 1,080 11,436
SOUTHERN 1,158 5,998 220 7,376
EASTERN 1,860 7,075 0 8,935
NORTH EASTERN 349 669 0 1,018
A & N Islands 0 25 0 25
TOTAL 14,393 25,417 1,300 41,110

C STATUS WISE

SANCTIONED ON
GOING 8088 7,634 1,300 17,022
CEA CLEARED 3504 9,327 0 12,831
STATE CLEARED 130 648 0 778
NEW SCHEMES 2671 7,808 0 10,479
TOTAL 14393 25,417 1,300 41,110

Page 50 of Chapter1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

Appendix 1.2

LIST OF PROJECTS COMMISSIONED DURING 10TH PLAN UPTO 31.12.2006

(2002-03)

Capacity
Name of the Project Sector/State Type
(MW)
THERMAL
Pragati CCPP S.S/Delhi Gas 121.2
Pragati CCPP S.S/Delhi Gas 104.6
Ramgarh CCGT-2 S.S/Rajasthan Gas 75.3
Simhadri TPS C.S./A P Coal 500
Neyveli FST Ext. C.S/Tamilnadu Lignite 210
Peddapuram CCGT P.S/ A P Gas 78
Raichur U-7&8 SS/Karnataka Coal 210
NLC-II Ext U-0 PS/ Tamilnadu Lignite 250
Valuthur CCGT SS/ Tamilnadu Gas 94
Talcher-II CS/Orissa Coal 500
Rokhia II U- SS/Tripura Gas 21
Baramura GT Ext. SS/ Tripura Gas 21
Likakhong DG SS/Manipur Diesel 18
Bamboo flat DG PS/A&N Diesel 20
Sub-Total (Thermal) 2223.1
HYDRO
Baspa-II PS/HP Hydro 200
Sardar Sarovar SS/Guaratj Hydro 100
Bansagar Tons-III SS/MP Hydro 20
Bansagar Tons-II SS/MP Hydro 15
Srisailam LBPH SS/AP Hydro 300
Sub-Total (Hydro) 635
Total (Thermal + Hydro) (2002-03) 2858.1
(2003-04)
Thermal
Kota TPS St-IV SS/Rajasthan Coal 195
Suratgarh III SS/ Rajasthan Coal 250
Dhuvaran CCGT SS/Gujarat Gas 106.6
Neyveli FST Ext. CS/Tamilnadu Lignite 210
Kutralam CCPP SS/Tamilnadu Gas 100
Talcher – II CS/Orissa Coal 500
Sub-total (Thermal) 1361.6
Hydro
Nathpa Jhakri CS/HP Hydro 1500
Chamera-II CS/HP Hydro 300
Baspa-II PS/HP Hydro 100
Indira Sagar JV CS/MP Hydro 500
Srisailam LBPH SS/AP Hydro 150
Almattti Dam SS/Karnataka Hydro 15
Page 51 of Chapter 1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

Kopili ST-II CS/Assam Hydro 25


Sub-Total (Hydro) 2590

NUCLEAR
MAPS-2 Uprating CS/Tamilnadu Nuclear 50
Sub-Total (Nuclear) 50

Total(Thermal + Hydro+Nucl.) (2003-04) 4001.6

(2004-05)
Thermal
Rihand-II CS/UP Coal 500
Panipat U-7&8 SS/Haryana Coal 500
Akrimota TPP SS/Gujarat Coal 125
Ramagundam CS/AP Coal 500
Karuppur CCPP PS/Tamilnadu Gas 70
Mezia U-4 CS/DVC Coal 210
Talcher-II CS/Orissa Coal 1000
Bairabi HFO SS/Mizoram Diesel 22.9
Rangat Bay SS/A&N Diesel 6.0
Sub-Total (Thermal) 2933.9

HYDRO
Indira Sagar JV CS/MP Hydro 500
Sardar Sarovar SS/Gujarat Hydro 350
Almatti Dam PH SS/Karnataka Hydro 165
Sub Total (Hydro) 1015.0
Grand Total (T+H) 2004-05 3948.9

(2005-06)
Thermal
Rihand-II CS/UP Coal 500
Akrimota TPP SS/Gujarat Coal 125
Karuppur CCPP PS/Tamilnadu Gas 49.8
Jojobera PS/Jharkhand Coal 120
Valentharvi PS/Tamilnadu. Gas 38
Jagrupadu CCPP PS/AP Gas 220
Paricha Extn. SS/UP Coal 210
Dhuvaran SS/Gujarat Gas 72
Vemagiri-I PS/AP Gas 233
Rokhia GT SS/Tripura Gas 21
Sub-Total (Thermal) 1588.8

NUCLEAR
TAPP Unit 3&4 CS/Maharashtra Nuclear 540
MAPS-1 Uprating CS/TN Nuclear 50
Sub-Total (Nuclear) 590

Page 52 of Chapter1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

HYDRO
Dhauliganga SS/Uttranchal Hydro 280
Sardar Sarovar Ss/Gujarat Hydro 800
Almatti Dam PH SS/Karnataka Hydro 110
Pykara Ultimate ST SS/Tamilnadu Hydro 150
Sub-total (Hydro) 1340

Grand Total (T+N+H) 2005-06 3518.8

2006-07 Upto 31.12.06


Thermal
Valentharvi PS/Tam Gas 14.8
Vemagiri-I CCGT PS/AP Gas 137
Ratnagiri Gas (JV) JV/Maha Gas 740
Vindhyachal NTPC Thermal 500
Unchahar III NTPC Thermal 210
Paricha Extn. SS/UP Coal 210
Sub-Total (Thermal) 1811.8
Nuclear
Tarapur 3 & 4 CS/Maha Nuclear 540
Sub-Total (Nuclear) 540
Hydro
Vishnuprayag PS/Uttranchal Hydro 400
Tehri I THDC Hydro 500
Larji SS/HP Hydro 126
Bhawani Kathalai Tam Hydro 30
Sardar Sarovar SS/Guj. Hydro 200
Bansagar-IV MP/SS Hydro 20
Marikheda MP/SS Hydro 40
Sub-Total (Hydro) 1316
Grand Total (T+N+H) 3667.8
ALL INDIA -10TH PLAN CAPACITY
ADDITION TILL DATE
Thermal (Coal+Gas+Diesel) 9919
(Hydro) 6896
(Nuclear) 1180
GRAND TOTAL MW UP TO 31.12.06 17995

Page 53 of Chapter 1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

Appendix-1.3

LIST OF POWER PROJECTS FOR BENEFITS DURING 10TH PLAN


(Central, State & Private Sector)
SUMMARY

Plant Name ORIGINAL TARGET PRESENT STATUS

HYDRO 14393 8854


CENTRE 8742 4495
STATE 4481 3659
PRIVATE 1170 700

THERMAL 25417 20387


CENTRE 12790 10284
STATE 6676 7348
PRIVATE 5951 2755

NUCLEAR 1300 1400

TOTAL-ALL-INDIA 41110 30641


CENTRE 22832 16179
STATE 11157 11007
PRIVATE 7121 3455

NOTE:
1. PROJECTS AND FIGURES IN RED COLOR ARE THOSE SLIPPING FROM ORIGINAL TARGET
OF 41,110 MW

2. PROJECTS AND FIGURES IN GREEN CLOUR ARE ADDITIONAL PROJECTS AND BENEFITS AS
PER MID TERM REVIEW

3. FIGURES IN BLUE ARE AS PER PRESENT STATUS IN NOVEMBER 2005

SOG-Sanctioned on Going C-Central Sector


CEA- Cleared by CEA S-State Sector
SC-State Cleared P-Private Sector
NEW- Yet to be cleared JV-Joint Venture

Page 54 of Chapter1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

LIST OF POWER PROJECTS FOR BENEFITS DURING 10TH PLAN


(Central, State & Private Sector)
Plant Name Fuel Type Sector Capacity MW ORIGINAL PRESENT Likely date of
TARGET STATUS commissioning

NORTHERN REGION

CENTRAL SECTOR

NHPC
CHAMERA II HYDRO C 300 300 300 Commissioned
DULHASTI HYDRO C 390 390 390 U 2-Feb 07,
U 1&3-Mar 07
DHAULI GANGA HYDRO C 280 280 280 Commissioned
SEWA II HYDRO C 120 120
SUB-TOTAL (NHPC) 1090 1090 970

NJPC
NATHPA JHAKRI HYDRO C 1500 1500 1500 Commissioned
RAMPUR HYDRO C 400 400
SUB-TOTAL (NJPC) 1900 1900 1500

NTPC
RIHAND II COAL C 1000 1000 1000 Commissioned
UNCHAHAR III COAL C 210 210 210 Commissioned
DADRI II COAL C 490 490
SUB-TOTAL (NTPC) 1700 1700 1210
NPC
RAPP U-5 NUCLEAR C 220 0
SUB-TOTAL (NPC) 220 0 0

THDC
TEHRI I HYDRO C 1000 1000 1000 U 2,3&4-
Commissioned
U 1 -Mar 07
KOTESHWAR HYDRO C 400 400 0
TEHRI PSS PSTOR C 1000 1000 0
SUB-TOTAL (THDC) 2400 2400 1000

NLC
BARSINGSAR LIGNITE C 500 250

TOTAL NR (CENTRAL 7590 7340 4680


SECTOR)

STATE SECTOR
DELHI
PRAGATI (GT2 +ST) GAS S 225.78 225.78 225.78 Commissioned
SUB TOTAL (DELHI) 225.78 225.78 225.78

HARYANA
YAMUNANAGAR COAL S 600 0
PANIPAT U 7&8 COAL S 500 500 500 Commissioned
SUB TOTAL (HARYANA) 1100 500 500

Page 55 of Chapter 1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

HP
LARGI HYDRO S 126 126 126 Commissioned
KASHANG -I HYDRO S 66 66
SUB TOTAL (HP) 192 192 126

J&K
BAGHALIHAR HYDRO S 450 450 0
SUB TOTAL (J & K) 450 450 0

PUNJAB
GHTPP-II COAL S 500 500 500 U 1-Mar 07
U 2- May 07*
SHAHPURKANDI HYDRO S 168 168
SUB TOTAL (PUNJAB) 668 668 500

RAJASTHAN
RAMGARH-2 GAS S 75.32 75.32 75.32 Commissioned
DHOLPUR CCGT GAS S 330 220 GT 1&2-Mar 07
ST - Aug 07*
GIRAL LIG U-1 LIGNITE S 125 125 February-07
MATAHANIA CCPP LNG S 140 140
KOTA TPS ST IV COAL S 195 195 195 Commissioned
SURATGARH III COAL S 250 250 250 Commissioned
SUB TOTAL (RAJASTHAN) 1115.3 660.32 865.32
UP
PARICHHA EXTN COAL S 420 210 420 Commissioned
ANPARA C COAL S 1000 500 0
SUB TOTAL (UP) 1420 710 420
UTTARANCHAL
MANERIBHALI II HYDRO S 304 304 304 U 1 - Sep 07*
U 2 - Oct 07*
U 3 - Nov 07*
U 4 - Dec 07*
SUB TOTAL(UTTARANCHAL) 304 304 304
TOTAL NR (STATE SECTOR) 5475.1 3710.1 2941.1

PRIVATE SECTOR
PUNJAB
GOINDWAL SAHIB COAL P 500 500 0
SUB TOTAL (PUNJAB) 500 500 0

HP
BASPA HYDRO P 300 300 300 Commissioned
DHAMVARI SUNDA HYDRO P 70 70
SUB TOTAL (HP) P 370 370 300

UTTARANCHAL
VISHNU PRAYAG HYDRO P 400 400 400 Commissioned
SUB TOTAL (UTTARANCHAL) P 400 400 400
TOTAL NR PRIVATE SECTOR 1270 1270 700
TOTAL (NORTHERN REGION) 14335 12320.1 8321.1

* On best efforts being included in X Plan Capacity Addition

Page 56 of Chapter1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

WESTERN REGION

CENTRAL SECTOR
NPC
TARAPUR U3&4 NUCLEAR C 1080 1080 1080 Commissioned

NTPC
SIPAT I COAL C 1980 1320 0
SIPAT II COAL C 660 660 0
SIPAT ST II U-4,5 COAL C 660 . 1000 U 4 - Mar 07
U 5 - May 07
VINDHYACHAL III COAL C 1000 500 1000 U 9 - Comm.
U 10 - Feb 07
GANDHAR CCGT GAS C 1300 March-07
KAWAS CCGT GAS C 1300
RATNAGIRI GAS (JV) LNG C 1444 1444 1444 740 MW-Comm.
704 MW-Mar 07
SUB TOTAL (NTPC) 4300 2480 3444

NHPC
BAV-II HYDRO C 37 37 0

SUB TOTAL (NHPC) 37 37 0

NHDC
OMKARESHWAR HYDRO JV 520 520 0
INDIRA SAGAR HYDRO JV 1000 1000 1000 Commissioned

SUB TOTAL (NHDC) 1520 1520 1000


SUB TOTAL WR (CENTRAL SECTOR) 6937 5117 5524

STATE SECTOR

GUJARAT
SAR.SAROVAR-2 HYDRO S 1450 1450 1450 Commissioned
AKRIMOTA LIGNITE S 250 250 250 Commissioned
KLTPS EXTN(Panan) LIGNITE S 75 75 75 U 4 - July 07*
DHUVRAN GAS S 112 112 GT-Comm.
ST- Feb 07
DHUVRAN GAS S 106.62 106.62 106.62 Commissioned
SUB TOTAL (GUJARAT) 1993.6 1881.62 1993.62

MAHARASTRA
GHATGHAR PSTOR S 250 250 250 U 1-May 07
U2-July 07*
PARAS TPS EXT. U-I COAL S 250 250
PARLI TPP EX. ST-I COAL S 250 250 250 March-07
SUB TOTAL (MAHARASHTRA) 750 500 750

* On best efforts being included in X Plan Capacity Addition


MP
BIRSINGPUR EXT COAL S 500 500 500 U 5 - Feb 07
AMARKANTAK U-5 COAL S 210 0
BANSAGAR II HYDRO S 30 15 15 Commissioned
BANSAGAR III HYDRO S 20 20 20 Commissioned
MARIKHEDA HYDRO S 40 40 40 Commissioned

Page 57 of Chapter 1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

BANSAGAR IV HYDRO S 20 20 20 Commissioned


SUB TOTAL (MP) 820 595 595

CHHATTISGARH
KORBA EAST EXT. COAL S 420 420 500 U 1 - Mar 07
U 2 - May 07
SUB TOTAL(CHHATTIS) 420 420 500
SUB TOTAL WR (STATE SECTOR) 3983.6 3396.62 3838.62

PRIVATE SECTOR

CHHATTISGARH
RAIGARH TPP U-1 COAL P 1000 250 June 07*
SUB TOTAL 1000 0 250
(CHHATISGARH) P

GUJARAT
JAMNAGAR REFRES P 500 500
AKHAKHOL CCPP BLK-I GAS P 365 365
SUB TOTAL (GUJARAT) P 865 500 365

MP
MAHESHWAR HYDRO P 400 400 0
BINA COAL P 578 578 0
SUB TOTAL (MP) P 978 978 0

SUB TOTAL WR (PRIVATE SECTOR) 2843 1478 615


TOTAL (WESTERN REGION) 13764 9991.62 9977.62

SOUTHERN REGION

CENTRAL SECTOR

NLC
NEYVELI EXT LIGNITE C 420 420 420 Commissioned
NEYVELI II EXP LIGNITE C 500 500
SUB TOTAL (NLC) 920 920 420

NPC
KUDANKULAM U-1 NUCLEAR C 1000 0
KAIGA U3 NUCLEAR C 220 220 220 March-07
MAPP UPGRADING NUCLEAR C 100 Commissioned
SUB TOTAL (NPC) 220 220 320

NTPC
SIMHADRI COAL C 1000 500 500 Commissioned
RAMAGUNDAM III COAL C 500 500 500 Commissioned

SUB TOTAL (NTPC) 1500 1000 1000


SUB TOTAL SR (CENTRAL SECTOR) 2640 2140 1740

STATE SECTOR
AP
RAYALSEMA-II COAL S 420 420 420 Commissioned
U 4 - Mar 07
SRISAILAM LBPH HYDRO S 450 450 450 Commissioned

Page 58 of Chapter1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

JURALA PRIYA HYDRO S 235 78.2 39 June 07*


SUB TOTAL (AP) 1105 948.2 909

KARNATAKA
RAICHUR U7 COAL S 210 210 210 Commissioned
ALMATI DAM HYDRO S 290 290 290 Commissioned
BELLARY COAL S 500 500 500 March-07
SUB TOTAL (KARNATAKA) 1000 1000 1000

KERALA
KUTTIYADI AUG. HYDRO S 100 100 0
SUB TOTAL (KERALA) 100 100 0

TAMILNADU
PYKARA ULTIMATE HYDRO S 150 150 150 Commissioned
PERUNGULAM GAS S 94 94 94 Commissioned
(VALUTHUR)
BHAWANI KATHALAI 1&2 HYDRO S 90 90 30
KUTRALAM GAS GAS S 100 100 100 Commissioned
SUB TOTAL (TAMILNADU) 434 434 374

* On best efforts being included in X Plan Capacity Addition


PONDICHERRY
KARAIKAL CCGT GAS S 100 100

SUB TOTAL SR (STATE 2739 2582.2 2283


SECTOR)

PRIVATE SECTOR

AP
PEDDAPURAM CCGT GAS P 220 78 78 Commissioned
VEMAGIRI-I GAS P 370 370 370 Commissioned
GAUTAMI GAS P 464 464 464 GTs- Feb 07
ST - Mar 07
RAMGUNDAM BPL COAL P 520 520
JEGRUPADU-EXT 1 GAS P 230 230 220 Commissioned
KONASEEMA GAS P 445 445 445 GT 1&2- Feb 07
ST - Mar 07
SUB TOTAL (AP) P 2249 2107 1577

KARNATAKA
HASSAN LNG P 189 189 0
KANIMINKE CCPP NAPHTHA P 108 108 0
SUB TOTAL (KARNATAKA) P 297 297 0

TAMILNADU
KURUPPUR GAS P 119.8 119.8 Commissioned
VALENTHARAVAI GAS P 52.8 52.8 Commissioned
NEYVELI ZERO LIGNITE P 250 250 250 Commissioned
SUB TOTAL (TAMILNADU) P 422.6 250 422.6

SUB TOTAL SR (PRIVATE SECTOR) 2968.6 2654 1999.6

TOTAL (SOUTHERN REGION) 8347.6 7376.2 6022.6

Page 59 of Chapter 1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

EASTERN REGION

CENTRAL SECTOR

DVC
MEZIA-U4 COAL C 210 210 210 Commissioned
MEZIA-U5 COAL C 250 250 250 March-07
MEZIA-U6 COAL C 250 250 May 07*
MAITHON-RBC COAL JV 1000 1000
CHANDRAPURA U7&8 COAL C 500 500 0
SUB TOTAL (DVC) 2210 1960 710

NHPC
TEESTA V HYDRO C 510 510 0
PURLIA PSS PSTOR JV 900 900 225 March-07
TEESTA LOW DAM III HYDRO C 132 132
TEESTA LOW DAM IV HYDRO C 168 168
SUB TOTAL (NHPC) 1710 1710 225

NTPC
TALCHER-II COAL C 2000 2000 2000 Commissioned
NORTH K PURA COAL C 1980 660
KAHALGAON U-5,6&7 COAL C 1500 1500 U5 - Feb 07
U6 - Mar 07
U7 - Jun 07*
KAHALGAON II COAL C 1320 660
BARH COAL C 1980 660
SUB TOTAL (NTPC) 8780 3980 3500

SUB TOTAL ER (CENTRAL SECTOR) 12700 7650 4435

STATE SECTOR

JHARKHAND
TENUGHAT EXT COAL S 630 210 0
SUB TOTAL (JHAR) 630 210 0

ORISSA
BALIMELA II HYDRO S 150 150 150 March-07
SUB TOTAL (ORISSA) 150 150 150

WEST BENGAL
SAGARDIGHI-I COAL S 500 250 600 U 1 - Mar 07
U 2 - Apr 07
DPL EXTENSION COAL S 300 300 U 7 - Mar 07
SANTALDIH COAL S 250 250 June 07*
BAKRESHWAR 4,5 COAL S 420 420 210 U 4 - Jul 07
SUB TOTAL (WB) 1470 670 1360

SUB TOTAL ER (STATE SECTOR) 2250 1030 1510

* On best efforts being included in X Plan Capacity Addition

Page 60 of Chapter1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

PRIVATE SECTOR

BIHAR
BIHTA TPS COAL P 135 135 0
SUB TOTAL (BIHAR) P 135 135 0

JHARKHAND
JOJOBERA COAL P 120 120 120 Commissioned
SUB TOTAL (JHAR) P 120 120 120

SUB TOTAL ER (PRIVATE SECTOR) 255 255 120

TOTAL (EASTERN REGION) 15205 8935 6065

NORTH EASTERN REGION

NEEPCO
TUIRIAL HYDRO C 60 60
KOPILI II HYDRO C 25 25 25 Commissioned
TRIPURA GAS GAS C 500 500 0
SUB TOTAL (NEEPCO) 585 585 25

SUB TOTAL NER (CENTRAL SECTOR) 585 585 25

STATE SECTOR
ASSAM
KARBI LANGPI HYDRO S 100 100 100 Commissioned U2
- Feb 07
LAKWA WH GAS S 38 38
SUB TOTAL (ASSAM) 138 138 100

MEGHALAYA
MYNTDU(LISKA) HYDRO S 84 84
BYRNIHAT HFO S 24 24
MENDIPATHAR HFO S 24 24
SUB TOTAL (MEGHALAYA) 132 132 0

MIZORAM
BAIRABI (THERMAL) HFO S 22.92 22.92 22.92 Commissioned
BAIRABI HYDRO HYDRO S 80 80
SUB TOTAL (MIZORAM) 102.92 102.92 22.92

NAGALAND
DIMAPUR DGPP HFO S 22.9 0
SUB TOTAL (NAGALAND) 22.9 0 0
TRIPURA
BARMURA GT GAS S 21 21 21 Commissioned
ROKHIAU7 GAS S 21 21 42 Commissioned
SUB TOTAL(TRIPURA) 42 42 63

MANIPUR
MANIPUR DG DIESEL S 18 18 18 Commissioned

SUB TOTAL NER (STATE SECTOR) 432.92 432.92 203.92

TOTAL (NORTH EASTERN REGION) 1017.9 1017.92 228.92

Page 61 of Chapter 1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

A&N ISLAND
BAMBOO FLAT DIESEL P 20 20 20 Commissioned
RANGIT BAY DIESEL S 5 5 6 Commissioned
SUB TOTAL(A&N) 25 25 26

TOTAL (ALL INDIA) 52694 39665.84 30641.24

Page 62 of Chapter1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

Appendix-1.4
LIST OF PROJECTS LIKELY TO SLIP TO 11th
(Due to constrains on BHEL side)

Project Name Total Likely Slipping Likely date of


Capacity during to 11th Commissioning
10th
Hydro
Maneri Bhal-II 304 0 304 Sept.07-Dec.07
Ghatghar PSS 250 125 125 July-07
Jurala Priya 39 0 39 June 07
Balimela 150 0 150 May-07
Sub-total (Hy) 618
Thermal
GHTPP-II 500 250 250 May ,07
Sipat II 1000 500 500 May-07
Kahalgaon-II 1500 500 500 June-07
Korba East Ext. 500 250 250 May-07
Raigarh 250 0 250 May-07
Bakreshwer U 4&5 210 0 210 July-07
Mejia U-5&6 500 250 250 May2007
Rayalseema 420 210 210 May2007
Bellary 500 0 500 April2007
Sagardighi 600 300 300 April2007
Santaldih 250 0 250 June2007
Kutch Lignite TPS 75 0 75 July 2007
Dholpur 220 110 110 August2007
GH TPP –II 250 0 250 May 2007
Kahalgaon 1500 500 500 June 2007
Dabhol-II 704 704 704 June 2007
Sub-total (Th) 5109
Total (Hy+Th.) 5727

Page 63 of Chapter 1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

Appendix 1.5

LIST OF UNITS DROPPED FROM 10th PLAN (41,110 MW)

THERMAL PROJECTS

Name of the Agency Name of the Project MW


Rajasthan (RRECL) Mathania ISCC GTs+ST 140
Jharkand Tenughat TPP II Unit 3 210
Pondicherry Karaikal CCPP GT+ST 100

Meghalaya Byrnihat DGPP 24


Meghalaya Mendipathar DGPP 24
Bihta TPPU-1 135
Bihar
Gujarat Jamnagar TPP U-!&2 2x250 500
Karnataka Hassan CCPP GT+ST 189
Karnataka Kaniminike CCPP GT+ST 107.6
M.P Bina TPP U-!&2 2x289 578
A.P Ramagundam TPP BPL U-!&2 520
SUB TOTAL THERMAL 2527.6

HYDRO PROJECTS

Name of the Agency NAME OF THE PROJECT MW


NHPC Bav II Maharashtra 37
NEEPCO Tuirial Mizoram 60
PIW/PSEB Shahpurkandi,Punjab 168
HPSEB Kashang – I 66
Dhamwari Power Dhamwari Sunda HEP 70
P&E Dept. Mizoram Bairabi Dam, Mizoram 80

SUB TOTAL HYDRO 481.0

GRAND TOTAL 3008.6

Page 64 of Chapter1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

Appendix 1.6

LIST OF THE THERMAL PROJECTS SLIPPING FROM 10th PLAN


(41,110 MW) AND INCLUDED IN 11TH PLAN (As per 30,641 MW)

THERMAL PROJECTS:-

Name of the Name of the Project IC (MW)


Agency
NTPC Barh STPP 660
Kahalgaon STPS Stage II Ph-I U-5 160

North Karanpura TPP U-1 660

Sipat STPP-I 2x660 U-1&2 1320

Dadri TPS 1x490 490

Sipat STPS II U-4 160

NLC Neyveli TPS II Exp 2*500 U-1&2 500

NLC Barsingsar lignite TPP U-1 250

DVC Maithon RBC TPP 4x250 U-1 to 4 1000

DVC Chandrapura TPS Extn. U-7&8 500

NEEPCO Monarchak CCPP GT+ST 500

UP. Anpara ( c ) TPS U-1 500


Assam ( Lakwa WH ST 38
ASEB)
West Bengal Bakreshwer TPS-II U-5 210
Punjab Goindwal TPP U-I&2 500
A.P. Jegurupadu CCPP EXT. GT 10
TOTAL 7458

Page 65 of Chapter 1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

Appendix 1.7

LIST OF HYDRO PROJECTS SLIPPING FROM 10th PLAN (41,110 MW)


AND INCLUDED IN 11TH PLAN (As per 30,641 MW)

Name of the Agency NAME OF THE PROJECT IC(MW)


NHPC Sewa –II J&K 120
NJPC Rampur (J.V.) 400
THDC Tehri St-.II (PSS) 1000
NHPC WB Teesta Low Dam -IV 168 *
NHPC/ WBPDCL Purlia PSS 675
NHDC Omkaresswer MP 390
Meghalaya Myntdu (Leiska) – I 84
SMHPC Maheshwar 400
A.P. Jurala Priya 39
Tamil Nadu Bhawani Kathalai 60
THDC Koteshwer THDC 400
TVL Teesta Low Dam III (IPP) 132
J&K Baglihar 450
Kerala Kuutiyadi Aug. 100
Sikkim Teesta -V 510
NHDC Omkareshwar 130
TOTAL HYDRO 5058

* capacity changed to 160 MW

Page 66 of Chapter1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

Appendix 1.8
SUMMARY OF CAPACITY ADDITION PROPOSED DURING 11TH PLAN

TOTAL THERMAL BREAKUP


HYDRO NUCLEAR TOTAL
THERMAL
COAL LIGNITE GAS

A. PROJECTS UNDER CONSTRUCTION


CENTRAL SECTOR 7633 7200 6450 750 0 3160 17993
STATE SECTOR 2107 5852 5215 375 262 0 7959
PRIVATE SECTOR 2191 3202 2450 0 752 0 5393
ALL-INDIA 11931 16254 14115 1125 1014 3160 31345
B. PROJECTS WHERE LOA IS YET TO BE PLACED (COMMITTED PROJECTS)
CENTRAL SECTOR 2052 16610 15610 250 750 0 18662
STATE SECTOR 530 14500 14150 0 350 0 15030
PRIVATE SECTOR 1072 2760 2760 0 0 0 3832
ALL-INDIA 3654 33870 32520 250 1100 0 37524
TOTAL FEASIBLE AT PRESENT
CENTRAL SECTOR 9685 23810 22060 1000 750 3160 36655
STATE SECTOR 2637 20352 19365 375 612 0 22989
PRIVATE SECTOR 3263 5962 5210 0 752 0 9225
ALL-INDIA 15585 50124 46635 1375 2114 3160 68869
C. PROJECTS WITH BEST EFFORTS
CENTRAL SECTOR 0 4190 4190 0 0 0 4190
STATE SECTOR 0 3300 2300 1000 0 0 3300
PRIVATE SECTOR 0 4055 4055 0 0 0 4055
ALL-INDIA 0 11545 10545 1000 0 0 11545
TOTAL SHELF OF PROJECTS
CENTRAL SECTOR 9685 28000 26250 1000 750 3160 40845
STATE SECTOR 2637 23652 21665 1375 612 0 26289
PRIVATE SECTOR 3263 10017 9265 0 752 0 13280
ALL-INDIA 15585 61669 57180 2375 2114 3160 80414

Page 67 of Chapter 1
Appendix 1.8 (contd.)
LIST OF PROJECTS PROPOSED FOR LIKELY BENEFITS DURING 11TH PLAN --HYDRO
ULTIMAT EQUIPMENT
BENEFITS ORDER
SECT E 2007- 2008- 2009- 2010- 2011-
Sl.No. PLANT NAME STATE AGENCY TYPE IN 11TH LOA DATE AGENCY
OR CAPACIT 08 09 10 11 12
PLAN
Y (MW)

PROJECTS UNDER CONSTRUCTION


1 PARBATI - II HP NHPC C 800 ROR 800 400 400 SEPT,02 DEC,02 BHEL
2 CHAMERA-III HP NHPC C 231 ROR 231 231 SEP, 05 JAN,07 ALSTOM
3 PARBATI - III HP NHPC C 520 ROR 520 520 SEP,05 DEC,06 BHEL
4 SEWA-II J&K NHPC C 120 ROR 120 120 SEPT, 03 JUNE,06 BHEL
5 URI-II J&K NHPC C 240 ROR 240 240 SEPT,05 DEC,06 ALSTOM
6 OMKARESHWAR MP NHDC C 520 ROR 520 520 JUNE, 03 JUNE,03 SIEMENS
7 TEESTA V SIK NHPC C 510 ROR 510 510 DONE NOV,01 MITSUI
8 TEESTA LOW DAM-III WB NHPC C 132 ROR 132 132 OCT,03 JULY,04 VA TECH
9 TEESTA LOW DAM-IV WB NHPC C 160 ROR 160 160 DEC 05. MAR, 07
10 SUBANSIRI LOWER AR.PR. NHPC C 2000 STO 2000 2000 DEC,03 FEB,05 ALSTOM
11 KOTESHWAR UKND THDC C 400 STO 400 400 AUG,02 MAR,03 BHEL
12 KAMENG AR.PR. NEEPCO C 600 STO 600 600 DEC,04 DEC,04 BHEL
13 KOL DAM HP NTPC C 800 STO 800 600 200 JUNE, 03 JULY,04 BHEL
14 LOHARI NAGPALA UKND NTPC C 600 ROR 600 600 JULY,06 SEP.07
15 UHL - III HP HPJVVNL S 100 ROR 100 100 SEPT.05 FEB,07
16 BAGLIHAR-I J&K JKPDC S 450 ROR 450 450 DONE JULY,99 SIEMENS
17 JURALA PRIYADARSHNI AP APGENCO S 234 STO 195 195 April, 04 MAR,04 CEMC, CHINA
18 NAGARJUNA SAGAR TR AP APGENCO S 50 STO 50 50 MAY, 05 MAY,06 BHEL
19 VARAHI EXTN. KAR KPCL S 230 ROR 230 230 NOV, 05 MAY,06 VA TECH
20 ATHIRAPALLI KERL KSEB S 163 ROR 163 163 MAY,05/ DEC,06 MAY,05 BHEL
21 KUTAYADI EXT. KERL KSEB S 100 ROR 100 100 AWARDED OCT,03 BHEL
22 BHAWANI BARRAGE II & III TN TNEB S 60 ROR 60 60 AWARDED NOV,06
23 PURLIA PSS WB WBSEB S 900 PSS 675 675 JUNE, 01 JULY,2000 MITSUI
24 MYNTDU St-I MEGH MeSEB S 84 STO 84 84 MAR,04 NOV,05 VA TECH
25 BUDHIL HP LANCO IPP P 70 ROR 70 70 AWARDED JULY,06 DONGFANF ELC.

26 ALLAIN DUHANGAN HP RSWML P 192 ROR 192 192 NOV, 05 NOV,05 BHEL
27 MALANA II HP EVREST PC P 100 ROR 100 100 JAN, 06 MAR,07
28 KARCHAM WANGTOO HP JPKHCL P 1000 ROR 1000 1000 AWARDED MAR,07
29 SRINAGAR UKND GVK P 330 ROR 330 330 MAR, 07 2007-08
30 MAHESHWAR MP IPP P 400 STO 400 400 AWARDED 2007-08
31 CHUJACHEN SIKKIM GATI P 99 ROR 99 99 AWARDED DEC,06 ALSTOM
SUB-TOTAL ( UNDER CONSTRUCTION) 12195 11931 2450 2328 1909 3314 1930
C: Central Sector; S: State Sector; P: Private Sector; ROR : Run of River; STO: Storage; PSS: Pumped Storage

Page 68 of Chapter 1
Appendix 1.8 (contd.)
LIST OF PROJECTS PROPOSED FOR LIKELY BENEFITS DURING 11TH PLAN --HYDRO
ULTIMAT EQUIPMENT
BENEFITS ORDER
SECT E 2007- 2008- 2009- 2010- 2011-
Sl.No. PLANT NAME STATE AGENCY TYPE IN 11TH LOA DATE AGENCY
OR CAPACIT 08 09 10 11 12
PLAN
Y (MW)

PROJECTS WHERE LOA IS YET TO BE PLACED


1 RAMPUR HP SJVNL C 412 ROR 412 412 FEB, 07
2 TEHRI PSS UKND THDC C 1000 PSS 1000 500 500 JULY, 07 AUG,07
3 TAPOVAN VISHNUGARH UKND NTPC C 520 ROR 520 520 DEC,06 2007-08
4 VYASI UKND NHPC C 120 STO 120 120 JUNE,07 2008-09
5 SAWARA KUDDU HP PVC S 110 ROR 110 110 JUNE, 07 2007-08
6 PALLIVASAL KERL KSEB S 60 ROR 60 60 MAR, 07 2007-08
7 MANKULAM KERL KSEB S 40 STO 40 40 MAR, 07 2007-08
8 THOTTIAR KERL KSEB S 40 ROR 40 40 MAR, 07 2007-08
9 LOWER JURALA AP APGENCO S 240 STO 240 240 MAY, 07 2008-09
10 NEW UMTRU MEGH MeSEB S 40 ROR 40 40 MAR,07 2007-08
11 LAMBADUG HP IPP P 25 ROR 25 25 MAR, 07 2008-09
12 SORANG HP SORAND PC P 100 ROR 100 100 MAR, 07 2008-09
13 TIDONG-I HP PCP/IPP P 100 ROR 100 100 JULY, 07 2007-08
14 TANGU ROMAI HP PCP/IPP P 50 ROR 50 50 JULY, 07 2008-09
15 UBDC- III PUN MALANA POWER P 75 ROR 75 75 JUNE,07 2007-08
16 SADAMANDER SIK GATI P 71 ROR 71 71 JUNE, 07 2007-08
17 BHASMEY SIK GATI P 51 ROR 51 51 SEP, 07 2007-08
18 TEESTA III SIK TEESTA URJA P 1200 ROR 600 600 MAR, 07 FEB,07
SUB-TOTAL ( COMMITTED) 4254 3654 0 0 146 1016 2492
TOTAL FEASIBLE HYDRO PROJECTS 16449 15585 2450 2328 2055 4330 4422
C: Central Sector; S: State Sector; P: Private Sector; ROR : Run of River; STO: Storage; PSS: Pumped Storage
Note: Orders in respect of Rampur HEP, 412 MW & Tapovan Vishnugarh HEP, 520 MW has been recently placed
11931 2450 2328 1909 3314 1930
STATUS WISE
3654 0 0 146 1016 2492
DETAILS
15585 2450 2328 2055 4330 4422

SUMMARY
8981 1580 1244 1205 1390 3562
4929 195 1084 850 2440 360
TYPE WISE DETAILS
1675 675 0 0 500 500
15585 2450 2328 2055 4330 4422

Page 69 of Chapter 1
Appendix 1.8 (contd)
LIST OF PROJECTS PROPOSED FOR LIKELY BENEFITS DURING 11TH PLAN --THERMAL
ULTIMATE BENEFITS COAL COAL LOA DATE
SECTO
Sl.No PLANT NAME STATE AGENCY CAPACITY TYPE IN 11TH 2007-08 2008-09 2009-10 2010-11 2011-12 LINKAGE COMPA (E&M AGENCY
R (MW) EQPT.)
PLAN STATUS NY

PROJECTS UNDER CONSTRUCTION


1 DADRI EXT(U-5) UP NTPC C 490 LC 490 490 LINKAGE CCL JUL,06 BHEL
2 SIPAT I CHG NTPC C 1980 PH 1980 660 1320 LINKAGE SECL APR,04 KOREA+ RUSSIA
3 BHILAI JV CHG NTPC C 500 PH 500 500 LINKAGE SECL MAR, 05 BHEL
4 KORBA III CHG NTPC C 500 PH 500 500 BLOCK MAR, 06 BHEL
5 BARH-I BIH NTPC C 1980 PH 1980 660 660 660 LINKAGE CCL MAR, 05 RUSSIA
6 FARAKKA STAGE-III WB NTPC C 500 PH 500 500 LINKAGE ECL OCT,06 BHEL
7 CHANDRAPUR JHAR DVC C 500 PH 500 500 LINKAGE BCCL JUN,06 BHEL
8 BARSINGSAR LIG RAJ NLC C 250 PH-LIG 250 250 LIGNITE DEC,05 BHEL
9 NEYVELI - II LIG TN NLC C 500 PH-LIG 500 500 LIGNITE AUG,05 BHEL
10 YAMUNA NAGAR HAR HPGCL S 600 LC 600 600 LINKAGE CCL AUG,05 CHINA
11 GIRAL U-2 RAJ RRVUNL S 125 PH-LIG 125 125 LIGNITE NOV,05 BHEL
12 CHABRA TPS RAJ RRVUNL S 500 LC 500 500 LINKAGE SECL MAR,06 BHEL
13 KOTA U7 RAJ RRVUNL S 195 LC 195 195 LINKAGE SECL JUN, 06 BHEL
14 SURATGARH EXT RAJ RRVUNL S 250 LC 250 250 LINKAGE SECL AUG,06 BHEL
15 DHOLPUR RAJ RRVUNL S 330 GAS/LNG 110 110 JUN,04 BHEL
16 PARICHHA EXT UP UPRVUNL S 500 LC 500 500 LINKAGE BCCL JUN,06 BHEL
17 HARDUAGANJ UP UPRVUNL S 500 LC 500 500 LINKAGE CCL JUN,06 BHEL
18 SURAT LIGNITE EXT GUJ GIPCL S 250 PH-LIG 250 250 LIGNITE MAR,06 BHEL
19 AMARKANTAK MP MPGENCO S 210 LC 210 210 LINKAGE SECL JUN, 04 BHEL
20 PARLI EXT U-2 MAH MAHA GEN S 250 LC 250 250 LINKAGE MCL AUG, 06 BHEL
21 PARAS EXT U-2 MAH MAHA GEN S 250 LC 250 250 LINKAGE MCL AUG, 06 BHEL
22 KAKTIYA AP APGENCO S 500 LC 500 500 LINKAGE SECL JUL, 05 BHEL
23 VIJAYWADA TPP AP APGENCO S 500 LC 500 500 LINKAGE MCL JUL, 05 BHEL
24 BELLARY TPS U-2 KAR KPCL S 500 LC 500 500 LINKAGE REQUIRED AUG, 06 BHEL
25 RAICHUR U 8 KAR KPCL S 250 LC 250 250 LINKAGE MCL SEP, 06 BHEL
26 VALUTHUR EXT TN TNEB S 92 GAS/LNG 92 92.2 MAY, 06 GEA ENERGY

27 BAKRESHWAR U-5 WB WBPDCL S 210 LC 210 210 LINKAGE ECL NOV.04 BHEL+JAPAN
28 LAKWA WH ASM ASGENCO S 37.2 GAS/LNG 37.2 37.2 MAR, 06 BHEL
29 DIMAPUR DG NAG ELECT.DEPT. S 23 GAS/LNG 23 23 JUL, 03 BHEL
30 RAIGARH PH II CHG JIN. POWER P 750 PH 750 750 BLOCK JUN, 04 BHEL
31 PATHADI (LANCO) U1 CHG LANCO-IPP P 300 PH 300 300 LINKAGE SECL JUL, 05 CHINA
32 PATHADI (LANCO) U2 CHG LANCO-IPP P 300 PH 300 300 LINKAGE SECL JUL, 05 CHINA
33 SUGEN TORRENT GUJ TORRENT P 1128 GAS/LNG 752 752 JUN, 05 SIEMENS
34 TROMBAY TPS MAH TATAPOWER P 250 LC 250 250 IMPORTED COAL JUL, 06 BHEL
35 TORANGALLU KAR JINDAL P 600 LC 600 300 300 IMPORTED COAL JUN,06 CHINA
36 BUDGE-BUDGE EXT WB CESC P 250 LC 250 250 BLOCK REQUIREDSEP, 06 BHEL
SUB-TOTAL ( UNDER CONSTRUCTION) 16850 16254 4407 6387 4500 960 0
C: Central Sector; S: State Sector; P: Private Sector; LC: Load Center; PH: Pit Head; PH-LIG: Lignite based

Page 70 of Chapter 1
Appendix 1.8 (contd)
LIST OF PROJECTS PROPOSED FOR LIKELY BENEFITS DURING 11TH PLAN --THERMAL
ULTIMATE BENEFITS COAL COAL LOA DATE
SECTO
Sl.No PLANT NAME STATE AGENCY CAPACITY TYPE IN 11TH 2007-08 2008-09 2009-10 2010-11 2011-12 LINKAGE COMPA (E&M AGENCY
R (MW) EQPT.)
PLAN STATUS NY

PROJECTS WHERE LOA IS YET TO BE PLACED


1 BADARPUR-X DELHI NTPC C 980 LC 980 490 490 LINKAGE MCL FEB,07
2 DADRI EXT(U-6) UP NTPC C 490 LC 490 490 LINKAGE CCL DEC, 06 BHEL
3 TPS for DELHI/JHAJJAR HAR NTPC C 1500 LC 1500 500 1000 LINKAGE MCL FEB,07
4 MAUDA MAH NTPC C 1000 PH 1000 1000 LINKAGE MCL NOV,07
5 SIMHADRI-EXT AP NTPC C 1000 COASTAL 1000 500 500 LINKAGE MCL JUN,07
6 ENNORE-JV TN NTPC C 1000 COASTAL 1000 500 500 LINKAGE MCL JUN,07
7 BARH II BIH NTPC C 1320 PH 1320 1320 BLOCK MAY,07
8 NABINAGAR BIH NTPC C 1000 PH 750 250 500 LINKAGE CCL JAN,08
9 NORTH K PURA JHAR NTPC C 1320 PH 1320 1320 LINKAGE CCL OCT,07
10 BONGAIGAON ASM NTPC C 750 LC 750 500 250 LINKAGE NEC/ECL AUG,07
11 MEJIA PH II (DELHI) WB DVC C 1000 PH 1000 500 500 BLOCK DEC, 06. BHEL
BOKARO REPLACEMENT
12 JHAR DVC C 500 PH 500 500 LINKAGE CCL FEB,07
(DELHI)
13 KODERMA U1&2 (DELHI) JHAR DVC C 1000 PH 1000 1000 LINKAGE MCL FEB,07
14 DURGAPUR STEEL WB DVC C 1000 PH 1000 500 500 LINKAGE ECL AUG,07
15 MAITHAN RBC JHAR DVC C 1000 PH 1000 500 500 LINKAGE BCCL FEB,07
16 BARSINGSAR EXT RAJ NLC C 250 PH-LIG 250 250 LIGNITE JUL,08
17 TUTICORIN JV TN NLC C 1000 COASTAL 1000 500 500 LINKAGE MCL DEC,07
18 TRIPURA GAS ILFS TRI ONGC C 750 GAS/LNG 750 750 JUN,07
19 HISSAR TPS I HAR HPGCL S 500 LC 500 250 250 LINKAGE MCL MAR,07
20 HISSAR TPS II HAR HPGCL S 500 LC 500 500 LINKAGE MCL JUN,08
21 TALWANDI SABO PUN PSEB S 1500 LC 500 500 LINKAGE REQUIRED JAN,08
22 KALISINDH TPS RAJ RRVUNL S 1000 LC 500 500 BLOCK REQUIRED JAN,08
23 ANPARA-D UP UPRVUNL S 1000 PH 1000 1000 LINKAGE REQUIRED JAN,08
24 OBRA REP UP UPRVUNL S 1000 PH 500 500 LINKAGE REQUIRED JAN,08
25 KORBA WEST EXT CHG CSEB S 600 PH 600 600 LINKAGE SECL FEB,07
26 UTRAN GUJ GSECL S 350 GAS/LNG 350 350 FEB,07
27 SIKKA EXT GUJ GSECL S 500 COASTAL 500 500 IMPORTED COAL OCT,07
28 UKAI EXT GUJ GSECL S 500 LC 500 500 LINKAGE REQUIRED JAN,08
29 KHAPER KHEDA EX MAH MAHA GEN S 500 LC 500 500 LINKAGE MCL FEB,07
30 BHUSAWAL MAH MAHA GEN S 1000 LC 1000 1000 LINKAGE MCL JUN,07
31 KORADI REP& OTHERS MAH MAHA GEN S 585 LC 500 500 LINKAGE JUN,07
32 KORADI EXT MAH MAHA GEN S 1000 LC 1000 1000 LINKAGE REQUIRED JAN,08
33 CHANDRAPUR MAH MAHA GEN S 500 PH 500 500 BLOCK FEB,07
34 MALWA MP MPGENCO S 1000 LC 1000 1000 LINKAGE SECL JUN,07
35 SATPURA EXT MP MPGENCO S 500 LC 500 500 LINKAGE REQUIRED JAN,08
36 KOTHAGUDEM ST-V AP APGENCO S 500 PH 500 500 LINKAGE MCL FEB,07

Page 71 of Chapter 1
Appendix 1.8 (contd)
LIST OF PROJECTS PROPOSED FOR LIKELY BENEFITS DURING 11TH PLAN --THERMAL
ULTIMATE BENEFITS COAL COAL LOA DATE
SECTO
Sl.No PLANT NAME STATE AGENCY CAPACITY TYPE IN 11TH 2007-08 2008-09 2009-10 2010-11 2011-12 LINKAGE COMPA (E&M AGENCY
R (MW) EQPT.)
PLAN STATUS NY

37 KRISHNAPATNAM AP APGENCO S 1600 COASTAL 800 800 LINKAGE MCL DEC,07


38 KAKATIYA EXT AP APGENCO S 500 LC 500 500 BLOCK JAN,08
39 NORTH CHENNAI EXT TN TNEB S 500 LC 500 500 LINKAGE MCL AUG,07
40 METTUR EXT TN TNEB S 500 LC 500 500 LINKAGE MCL MAR,07
41 SAGARDIGHI EXT WB WBPDCL S 1000 LC 1000 500 500 BLOCK REQUIRED DEC,07
42 SANTHALDIH EXT (U 6) WB WBPDCL S 250 LC 250 250 BLOCK REQUIRED FEB,07
43 GOINDWAL SAHIB PUN GVK P 600 LC 600 600 BLOCK JAN,08
44 ANPARA-C UP LANCO P 1000 PH 1000 500 500 LINKAGE NCL NOV,07
45 BARA UP IPP P 1000 LC 500 500 BLOCK REQUIRED JAN,08
46 ULTRA MEGA SASAN MP LANCO P 3960 LC 660 660 BLOCK JAN,08
SUB-TOTAL ( COMMITTED) 40805 33870 0 350 5830 10740 16950
TOTAL FEASIBLE THERMAL PROJECTS 57655 50124 4407 6737 10330 11700 16950
C: Central Sector; S: State Sector; P: Private Sector; LC: Load Center; PH: Pit Head; PH-LIG: Lignite based; COASTAL : Coastal Stations
Note: Orders in respect of Dadri Ext (U 6), Mezia PH II ,Bhusawal,Khaperkheda Ext,Kothagudem and Hissar has been recently placed
UNDER
CONSTRUCTION
16254 4407 6387 4500 960 0
STATUS WISE LOA TO BE PLACED
33870 0 350 5830 10740 16950
DETAILS
TOTAL FEASIBLE 50124 4407 6737 10330 11700 16950
660/800 8060 660 1980 660 660 4100
500 26460 0 1000 5470 8990 11000
300 3000 600 300 1200 300 600
UNIT SIZE GROUP 210/250 9615 2170 2445 2250 1500 1250
WISE DETAILS 110/125 875 0 625 0 250 0
Gas 2114 977 387 750 0 0
TOTAL FEASIBLE 50124 4407 6737 10330 11700 16950
SUMMARY OF THERMAL
PH 20300 2410 2280 4560 4410 6640
CAPACITY ADDITION TYPE WISE LC 22035 1020 2945 5020 5040 8010
DETAILS OF COAL COASTAL 4300 0 0 0 2000 2300
PLANTS
TOTAL COAL 46635 3430 5225 9580 11450 16950
LINKAGE AVAILABLE 32455 2680 4975 7280 9150 8370
LINKAGE REQUIRED 4500 0 0 500 0 4000
BLOCK ALLOTED 5830 750 0 1000 1000 3080
STATUS OF COAL
AVAILABILITY BLOCK REQUIRED 2500 0 0 500 500 1500

IMPORTED COAL 1350 0 250 300 800 0

TOTAL COAL 46635 3430 5225 9580 11450 16950

Page 72 of Chapter 1
Appendix 1.8 (contd)
LIST OF PROJECTS PROPOSED FOR LIKELY BENEFITS DURING 11TH PLAN --THERMAL
ULTIMATE BENEFITS COAL COAL LOA DATE
SECTO
Sl.No PLANT NAME STATE AGENCY CAPACITY TYPE IN 11TH 2007-08 2008-09 2009-10 2010-11 2011-12 LINKAGE COMPA (E&M AGENCY
R (MW) EQPT.)
PLAN STATUS NY

PROJECTS UNDER BEST EFFORTS


1 RIHAND-X UP NTPC C 500 PH 500 500 LINKAGE REQUIRED DEC,07
2 NORTH K PURA JHAR NTPC C 660 PH 660 660 LINKAGE CCL AUG,07
3 INTEGRATED PROJECT DARIPALI ORS NTPC C 3200 PH 800 800 BLOCK SEP,07
4 NABINAGAR BIH NTPC C 1000 PH 250 250 LINKAGE CCLJAN,08
5 BOKARO STEEL JHAR DVC C 500 PH 500 500 LINKAGE REQUIRED JUN,07
6 RAGHUNATH PUR WB DVC C 1000 PH 1000 1000 BLOCK REQUIREDDEC,07
7 MARGHERITA ASSAM NEEPCO C 480 PH 480 480 LINKAGE REQUIRED JAN, 08
8 CHHABRA II RAJ RRVUNL S 500 LC 500 500 BLOCK REQUIREDJAN, 08
9 GUJARAT LIGNITE GUJARAT NLC JV S 1000 PH-LIG 1000 1000 LIGNITE JAN, 08
10 DPL TPS U7A WB WBPDCL S 300 LC 300 300 BLOCK REQUIREDAUG,07
11 DPL TPS U8 WB WBPDCL S 500 LC 500 500 BLOCK REQUIREDOCT,07
12 BAKRESHWAR EXT WB WBPDCL S 500 LC 500 500 BLOCK REQUIREDJAN,09
13 MUZAFFARPUR EXT BIHAR SHALI POW S 500 LC 500 500 LINKAGE REQUIRED JAN, 08
14 ROSA UP OSA POWE P 600 PH 600 600 LINKAGE REQUIRED JAN, 08
15 BHAIYATHAN CHG IPP P 1600 PH 800 800 BLOCK JUN,07
16 LANCO NAGARJUNA KAR NPCL-IPP P 1015 COASTAL 1015 1015 IMPORTED COAL FEB, 07
17 HALDIA PH I WB CESC P 600 LC 600 600 LINKAGE REQUIRED SEP, 08
NAVABH
18 MALAXMI ORISSA P 1040 PH 1040 1040 LINKAGE (2.404 MT); JAN,08
ARAT
SUB-TOTAL ( BEST EFFORTS) 15495 11545 0 0 0 0 11545
ADDITIONAL PROJECT IDENTIFIED BY STATES
1 Yamuna Nagar EXT HAR S 300 300 Linkage Required JUN,07
2 Jhajjar TPS (Case 2) HAR P 1200 1200 Linkage Required
3 Shankargarh UP P 1000 1000 Block Required
4 Dopaha UP P 1000 1000 Block Required
5 Chhabra III RAJ P 500 500 Block Required
6 Kawai RAJ P 1000 1000 Block Required
7 Dopawe MAH P 1600 1600 Imported Coal
8 Marwa TPS CHG S 1500 1500 Block Available SEP,07
9 Korba South CHG S 1000 1000 Linkage Required
10 Godhna CHG S 2000 2000 Linkage Required
11 Ennore EXP TN S 500 500 Linkage Required
12 Tuticorin Ext TN S 1000 1000 Linkage Required DEC,07
13 Cuddalore TN P 2000 1000 Imported Coal
14 Kudgi KAR S 1000 1000 Block Requitred DEC,07
15 Barauni TPS BIH S 500 500 Linkage Required
SUB-TOTAL ( ADDITIONAL IDENTIFIED) 16100 15100 0 0 0 0 0
C: Central Sector; S: State Sector; P: Private Sector; LC: Load Center; PH: Pit Head; PH-LIG: Lignite based; COASTAL : Coastal Stations

Page 73 of Chapter 1
Appendix 1.8 (contd.)
LIST OF PROJECTS PROPOSED FOR LIKELY BENEFITS DURING 11TH PLAN -NUCLEAR

ULTIMATE BENEFITS IN
NO.OF UNIT
Sl.No. PLANT NAME STATE AGENCY SECTOR CAPACITY TYPE 11th PLAN 2007-08 2008-09 2009-10 2010-11 2011-12
UNITS SIZE
(MW) (2007-12)

PROJECTS UNDER CONSTRUCTION


1 RAPP U5&6 RAJ NPC C 2 220 440 PHWR 440 220 220
2 KUDANKULAM U 1,2 TN NPC C 2 1000 2000 LWR 2000 1000 1000
3 PFBR(Kalapakkam) TN NPC C 1 500 500 FBR 500 500
4 KAIGA U-4 KAR NPC C 2 220 440 PHWR 220 220
TOTAL NUCLEAR(UNDER CONSTRUCTION) 7 3380 3160 1440 1220 0 500 0
C: Central Sector
UNDER CONSTRUCTION 11931 2450 2328 1909 3314 1930
HYDRO LOA TO BE PLACED 3654 0 0 146 1016 2492
FEASIBLE 15585 2450 2328 2055 4330 4422

UNDER CONSTRUCTION 16254 4407 6387 4500 960 0


THERMAL LOA TO BE PLACED 33870 0 350 5830 10740 16950
TYPE WISE STATUS WISE FEASIBLE 50124 4407 6737 10330 11700 16950
SUMMARY
NUCLEAR UNDER CONSTRUCTION 3160 1440 1220 0 500 0

UNDER CONSTRUCTION 31345 8297 9935 6409 4774 1930


TOTAL LOA TO BE PLACED 37524 0 350 5976 11756 19442
TOTAL FEASIBLE 68869 8297 10285 12385 16530 21372

Page 74 of Chapter 1
Appendix 1.9

YEAR-WISE COAL REQUIREMENT FOR 11th PLAN (tentative)-Utilities


2006-07 11th Plan details
INSTALLED CAPACITY(MW) Programme 2007-08 2008-09 2009-10 2010-11 2011-12 2012-13
EXISTING CAPACITY 63490 63490 63490 63490 63490 63490 63490
PLF(%) 76.0 76.0 77.0 77.0 77.0 77.0 77.0
GENERATION 422.7 422.7 428.3 428.3 428.3 428.3 428.3
ADDITIONS 8950 3430 5225 9580 11450 16950 0
RETIREMENTS 0 0 0 0 527.5 259
PLF(%) 85 85 85 85 85 85 85
GENERATION 26.7 76.9 107.7 159.6 232.6 336.2 413.9
TOTAL INSTALLED CAPACITY 72440 75870 81095 90675 101597.5 118816 118816
TOTAL GENERATION(BU) 449.3 499.5 536.0 587.9 660.8 764.5 842.1
COAL REQUIREMENT (Million Tons) 319.0 349.7 375.2 411.5 462.6 535.1 589.5

TRANSIT LOSS @ 1% 3.2 3.5 3.8 4.1 4.6 5.4 5.9


CUMULATIVE STOCK 17.7 19.4 20.8 22.8 25.6 29.6 32.6
ADDITIONAL STOCK 7.2 1.7 1.4 2.0 2.8 4.0 3.0

TOTAL COAL REQUIREMENT 329.4 354.9 380.4 417.6 470.0 544.5 598.4
Note:
1.Total installed capacity of coal fired stations at the end of 2011-12 = 1,18,816 MW
2. Requirement of coal in the year 2011-12 for the coal fired capacity indicated above = 545 MT
3.The above assumes only 40% generation from the new capacity addition during the year .
4.The requirement of coal for the total installed capacity of 1,18,816 MW at the end of 11th plan ,in the year first year of 12th plan i.e.2012-
13 would be about 600 MT
5. Any new capacity addition during the year 2012-13 shall need additional coal

Page 75 of Chapter 1
Appendix 1.10

Shelf of Projects for Likely benefits during 12th plan

Best Effort 12th Plan


Total Shelf of
Type Projects of Projects
Projects (MW)
11th plan (MW)
Hydro 0 40658 40658
Thermal 11545 102473 114018
Coal 10545 83640 94185
Lignite 1000 3250 4250
Gas/LNG 15583 15583
Nuclear 12800 12800
Total 11545 155931 167476

Page 76 of Chapter 1
Appendix 1.10 (contd)

SHELF OF HYDRO PROJECTS FOR LIKELY BENEFITS DURING 12 th PLAN

Likely
Benefit in
Sl. No Name of scheme State Agency Sector Type IC (MW)
12th Plan
(MW)
1 Bharmour HP IPP P ROR 45 45
2 Bajoli Holi HP IPP P ROR 180 180
3 Chirgaon (Majhgaon) HP HPSEB S ROR 46 46
4 Dhaula Sidh HP IPP P ROR 40 40
5 Dhamvari Sunda HP HPSEB S ROR 70 70
6 Harsar HP IPP P ROR 60 60
7 Jhangi Thopan HP IPP P ROR 480 480
8 Kutehr HP IPP P ROR 260 260
9 Kashang-II HP HPSEB S ROR 60 60
10 Luhri HP SJVNL C ROR 770 770
11 Pudital Lassa HP IPP P STO 36 36
12 Renuka Dam HP HPSEB S STO 40 40
13 Sainj HP HPSEB S ROR 100 100
14 Tidong-II HP IPP P ROR 70 70
15 Thopan Powari HP IPP P ROR 480 480
16 Kashang - I & III HP HPJVVNL S ROR 195 195
17 Shongtong Karcham HP HPSEB S ROR 402 402
18 Nimoo Bazgo J&K NHPC C ROR 45 45
19 Chutak J&K NHPC C ROR 44 44
20 Baglihar-II J&K PDC S ROR 450 450
21 Kiru J&K To be decided To be decided ROR 600 600
22 Kishan Ganga J&K NHPC C STO 330 330
23 Kawar J&K To be decided To be decided ROR 320 320
24 Parnai J&K PDC S ROR 37.5 37.5
25 Pakhal Dul J&K NHPC C STO 1000 1000
26 Ratle J&K To be decided To be decided ROR 560 560
27 Sawalkot J&K PDC S ROR 1200 1200
28 Kotli Bhel I A UKND NHPC C ROR 195 195
29 Kotli Bhel I B UKND NHPC C ROR 320 320
30 Kotli Bhel II UKND NHPC C ROR 530 530
31 Lata Tapovan UKND NTPC C ROR 171 171
32 Vishnugad Pipalkoti UKND THDC C ROR 444 444
33 Arkot Tiuni UKND UJVNL S ROR 70 70
34 Alaknanda (Badrinath) UKND IPP P ROR 140 140
35 Bogadiyar Sirkari Bhyal UKND IPP P ROR 170 170
36 Mapang Bogudiyar UKND IPP P ROR 200 200
37 Bowala Nand Prayag UKND UJVNL S ROR 132 132
38 Devsari Dam UKND SJVNL C STO 690 690
39 Hanol Tiuni UKND IPP P ROR 42 42
40 Jakhol Sankari UKND SJVNL C ROR 33 33
41 Jelam Tamak UKND THDC C ROR 60 60
42 Lakhwar UKND NHPC C STO 300 300
43 Maleri Jhelam UKND THDC C ROR 55 55
44 Mori Hanol UKND IPP P ROR 60 60
45 Nand Prayag Lingasu UKND UJVNL S ROR 141 141
46 Naitwar Mori (Dewra Mori) UKND SJVNL C ROR 33 33
47 Pala Maneri UKND UJVNL S ROR 480 480
48 Rupsiyabagar Khasiyabara UKND NTPC C ROR 260 260
49 Sirkari Bhyal Rupsiabagar UKND UJVNL S ROR 210 210
50 Singoli Bhatwari UKND IPP P ROR 60 60

Page 77 of Chapter 1
Appendix 1.10 (contd)

SHELF OF HYDRO PROJECTS FOR LIKELY BENEFITS DURING 12 th PLAN

Likely
Benefit in
Sl. No Name of scheme State Agency Sector Type IC (MW)
12th Plan
(MW)
51 Tamak Lata UKND UJVNL S ROR 280 280
52 Taluka Sankri UKND UJVNL S ROR 140 140
53 Tuini Plasu UKND UJVNL S ROR 42 42
54 Dhauli Ganga Intermediate UKND NHPC C ROR 210 210
55 Gauri Ganga St III-A UKND NHPC C ROR 120 120
56 Shahpur Kandi PUN PSEB S STO 168 168
57 Hoshangabad MP NHDC C ROR 60 60
58 Handia MP NHDC C ROR 51 51
59 Borus MP NHDC C ROR 55 55
60 Matnar CHG CSEB S ROR 60 60
61 Dummugudem AP APID S STO 320 320
62 Pollavaram MPP AP APID S STO 960 960
63 Chinnar KERL KSEB S ROR 28 28
64 Achenkovil KERL KSEB S STO 30 30
65 Kundah PSS TN TNEB S PSS 500 500
66 Gundia KAR KPCL S ROR 400 400
67 Ramam St-III WB NTPC C ROR 120 120
68 Ramam St-I WB WBSEB S ROR 36 36
69 Panan SIK IPP P ROR 280 280
70 Dikchu SIK IPP P ROR 96 96
71 Rolep SIK IPP P ROR 60 60
72 Rangit-II SIK IPP P ROR 60 60
73 Rangit-IV SIK IPP P ROR 120 120
74 Lachen SIK NHPC C ROR 210 210
75 Rangyong SIK IPP P ROR 80 80
76 Rukel SIK IPP P ROR 33 33
77 Rongnichu SIK IPP P STO 96 96
78 Teesta St.-I SIK IPP P ROR 280 280
79 Teesta St.-II SIK IPP P ROR 480 480
80 Teesta St.-IV SIK NHPC C ROR 495 495
81 Teesta-VI SIK IPP P ROR 500 500
82 Teesta-III SIK Teesta Urja P ROR 1200 600
83 Pare Ar Pr NEEPCO C STO 110 110
84 Siang Middle (Siyom) Ar Pr IPP P STO 1000 1000
85 Dibbin Ar Pr To be decided To be decided ROR 100 100
86 Badao Ar Pr To be decided To be decided ROR 60 60
87 Kapak Leyak Ar Pr To be decided To be decided ROR 160 160
88 Talong Ar Pr To be decided To be decided STO 160 160
89 Etalin Ar Pr NTPC C STO 4000 4000
90 Attunli Ar Pr NTPC C ROR 500 500
91 Siang Lower Ar Pr IPP P STO 1600 1600
92 Nyamjunchhu St-I Ar Pr IPP P ROR 98 98
93 Nyamjunchhu St-II Ar Pr IPP P ROR 97 97
94 Nyamjunchhu St-III Ar Pr IPP P ROR 95 95
95 Dibang (Joint venture) Ar Pr NHPC C STO 3000 3000
96 Tawang-II Ar Pr NHPC C STO 750 750
97 Tawang-I Ar Pr NHPC C STO 750 750
98 Lohit Ar Pr To be decided To be decided STO 3000 3000
99 Subansiri Upper Ar Pr NHPC C STO 2000 2000
100 Subansiri Middle Ar Pr NHPC C STO 1600 1600

Page 78 of Chapter 1
Appendix 1.10 (contd)

SHELF OF HYDRO PROJECTS FOR LIKELY BENEFITS DURING 12 th PLAN

Likely
Benefit in
Sl. No Name of scheme State Agency Sector Type IC (MW)
12th Plan
(MW)
101 Lower Kopili ASM AGENCO S ROR 150 150
102 Upper Borpani ASM AGENCO S ROR 60 60
103 Tipaimukh MANI NEEPCO C STO 1500 1500
104 Umiam Umtru-V MEGH MeSEB S ROR 36 36
105 Ganol MEGH MeSEB S ROR 25 25
106 Mawhu MEGH NEEPCO C ROR 120 120

TOTAL 40657.50
Note: C: Central Sector; S: State Sector; P: Private Sector; ROR: Run of River; STO: Storage

Page 79 of Chapter 1
Appendix 1.10 (contd)
SHELF OF COAL AND LIGNITE BASED PROJECTS FOR LIKELY BENEFITS DURING
12th PLAN
ULTIMATE
LIKELY BENEFITS
S.NO NAME STATE AGENCY CAPACITY
IN 12th PLAN (MW)
(MW)
1 YAMUNANAGAR EXT HAR HRVUNL 300 300
2 JHAJJAR HAR IPP 1200 1200
3 TALWANDI SABO PUN PSEB 1500 1000
4 NABHA PUN PSEB 1000 1000
5 LEHRA GHAGGAR PUN PSEB 1000 1000
6 CHHABRA II @ RAJ RRVUNL 500 500
7 CHHABRA III RAJ IPP 500 500
8 KALISINDH TPS RAJ RRVUNL 1000 500
9 KAWAI RAJ IPP 1000 1000
10 JALIPA/ KAPURDI- LIGNITE RAJ IPP 1000 1000
11 RIHAND EXT@ UP NTPC 500 500
12 MAYURPUR (SONEBHADRA) UP UPRVUNL 2000 2000
13 ROSA @ UP ROSA P.C. 600 600
14 BARA TPS UP UPRVUNL 1000 500
15 OBRA REPLACEMENT UP UPRVUNL 1000 500
16 SHANKARGARH UP IPP 1000 1000
17 DOPAHA UP IPP 1000 1000
18 ULTRA MEGA AKALTARA CHG IPP 4000 4000
19 INTEGRATED PROJECT LARA CHG NTPC 4000 4000
20 BHAIYATHAN @ CHG IPP 1600 1600
21 MARWA CHG CSEB 1500 1500
22 KORBA SOUTH CHG CSEB 1000 1000
23 GODHANA CHG CSEB 2000 2000
24 ULTRA MEGA MUNDRA GUJ IPP 4000 4000
25 BHAVNAGAR LIGNITE GUJ NIRMA 250 250
26 GUJARAT LIGNITE @ GUJ NLC 1000 1000
27 PIPAVAV POWER PROJECT GUJ GPCL JV 900 900
28 ULTRA MEGA GIRYE MAH IPP 4000 4000
29 DOPAWE MAH IPP 1600 1600
30 ULTRA MEGA SASAN MP LANCO 3960 3300
31 SHAHPUR BHITONI MP MPGEN 1000 1000
32 ULTRA MEGA KRISHNAPATNAMA P IPP 4000 4000
33 KRISHNAPATNAM AP APGENCO 1600 800
34 LANCO NAGARJUNA @ KAR IPP 1015 1015
35 ULTRA MEGA TADRI KAR IPP 4000 4000

Page 80 of Chapter 1
Appendix 1.10 (contd)
SHELF OF COAL AND LIGNITE BASED PROJECTS FOR LIKELY BENEFITS DURING
12th PLAN
ULTIMATE
LIKELY BENEFITS
S.NO NAME STATE AGENCY CAPACITY
IN 12th PLAN (MW)
(MW)
36 RAICHUR NEW KAR KPCL 1000 1000
37 KOWSHIKA TPP KAR KPCL 1000 1000
38 KUDGI TPP KAR KPCL 1000 1000
39 NANDUR TPP KAR KPCL 1000 1000
40 NEYVELI III LIGNITE TN NLC 1000 1000
41 JAYANKONDAM LIGNITE TN NLC 1000 1000
42 ENNORE EXT TN TNEB 500 500
43 TUTICORIN EXT TN TNEB 1000 1000
44 CUDDALORE TN IPP 2000 2000
45 ULTRA MEGA CHEYYUR TN IPP 4000 4000
46 NABINAGAR JV @ BIHAR NTPC 1000 250
47 MUZAFFARPUR EXT JV @ BIHAR VAISHALI POWER 500 500
48 BARAUNI EXT BIHAR BSEB 500 500
49 KATIHAR BIHAR BSEB 1000 1000
50 NABINAGAR BIHAR BSEB 2000 2000
51 PIRPIANTI BIHAR BSEB 2000 2000
52 ULTRA MEGA JHARKHAND BIHAR IPP 4000 4000
53 NORTH KARAN PURA @ JHAR NTPC 1980 660
54 BOKARO STEEL @ JHAR DVC 500 500
55 TENUGHAT EXT JHAR TVNL 630 630
56 COAL BASED TPP PHASE I JHAR CESC 500 500
57 COAL BASED TPP PHASE II JHAR CESC 500 500
58 ULTRA MEGA ORISSA ORI IPP 4000 4000
INTEGRATED PROJECT
59 ORI NTPC 3200 3200
DARIPALLI @
60 NUELPOI ORI CESC 1320 1320
61 RENGALI ORI NLC 1000 1000
62 OPGCL JV ORI OPGCL 1200 1200
63 MALAXMI @ ORI NAVBHARAT 1040 1040
64 HALDIA I @ WB CESC 600 600
65 KATWA WB WBPDCL 1200 1200
66 RAGHUNATH PUR @ WB DVC 1000 1000
67 DPL U7A @ WB WBPDCL 300 300
68 DPL U8 @ WB WBPDCL 500 500
69 BAKRESHWAR EXT @ WB WBPDCL 500 500

Page 81 of Chapter 1
Appendix 1.10 (contd)
SHELF OF COAL AND LIGNITE BASED PROJECTS FOR LIKELY BENEFITS DURING
12th PLAN
ULTIMATE
LIKELY BENEFITS
S.NO NAME STATE AGENCY CAPACITY
IN 12th PLAN (MW)
(MW)
70 BARGOLOI TPS ASM ASEB 250 250
71 BADARPUR JV ASM ASEB 180 180
72 CHANDRAPUR JV ASM ASEB 100 100
73 MARGHERITA TPP @ ASM NEEPCO 480 480
74 GARO HILL MEGH NEEPCO 720 720
75 WEST KHASI HILLS TPP MEGH NEEPCO 240 240
TOTAL 98435
@ BEST EFFORT PROJECTS DURING 11TH PLAN
NOTE: THE LIST INCLUDES 11545 MW PROJECTS INCLUDED AS PROJECTS WITH BEST EFFORTS
IN 11TH PLAN

Page 82 of Chapter 1
Appendix 1.10 (contd)

IDENTIFIED GAS BASED PROJECTS FOR LIKELY BENEFITS DURING 12th PLAN

ULTIMATE LIKELY
SECTO
Sl.No. PLANT NAME STATE AGENCY CAPACITY BENEFITS IN
R
(MW) 12th PLAN (MW)

1 KAYAMKULAM KERL NTPC C 1950 1950

2 KAWAS II GUJ NTPC C 1300 1300

3 GANDHAR II GUJ NTPC C 1300 1300

4 PRAGATI II DELHI PRAGATI POWER S 330 330

5 PRAGATI III (BAWANA) DELHI PRAGATI POWER S 1000 1000

6 URAN MAH MAHAGENCO S 1040 1040

7 RELIANCE-DADRI UP RELIANCE ENERGY P 5600 5600

8 PYGUTHAN GUJ GPECL P 1050 1050

9 ESSAR HAZIRA GUJ ESSAR POWER P 1500 1500


KANNUR POWER
10 KANNUR KERL PVT LTD
P 513 513

TOTAL 15583
Note: If Gas/LNG becomes available at reasonable price, some of the above mentioned gas based projects may
yield benefits during 11th plan

Page 83 of Chapter 1
Appendix 1.10 (contd)

SHELF OF NUCLEAR PROJECTS FOR LIKELY BENEFITS


DURING 12th PLAN
LIKELY
BENEFITS IN
S.NO. NAME STATE AGENCY
12th PLAN
(MW)
1 KUDANKULAM U3,4 TN NPC 2000
2 KUDANKULAM U5,6 TN NPC 2000
3 JAITAPUR 1,2 GUJ NPC 2000
4 RAPP EXT RAJ NPC 1400
5 KAPP 3&4 KAR NPC 1400
6 LWR 3,4 NPC 2000
Sub total (NPCIL) 10800
7 NEW NUCLEAR NTPC 2000
Sub total (NTPC)
TOTAL 12800

Page 84 of Chapter 1
Demand for Power and Generation Planning Working Group on Power for 11th Plan
Appendix 1.11
COMPARATIVE PERFORMANCE OF PARTERNERSHIP IN EXCELLENCE (PIE) STATIONS NTPC AS PIE PARTNER

Sl Station Unit No. Capacit Generat Dec'05 Dec'06 Apr-Dec'05 Apr-Dec'06 Change in 'Apr-Dec' period
No. y under ing
PIE MW Cap. Act Gen Act PLF Act Gen Act PLF Act Gen Act PLF Act Gen Act PLF Generation change PLF change
(MW)
MU % Net %
1 Tenughat 1,2 420 420 142.89 45.73 226.01 72.33 960.61 34.65 1957.52 70.62 996.91 103.78 35.96 103.78
2 Ennore 2,3,5 280 280 44.51 21.37 153.10 73.49 485.93 26.29 1059.71 57.34 573.78 118.08 31.05 118.08
3 Bokaro 'B' 1,2,3 630 630 304.79 65.03 321.43 68.58 1987.44 47.80 2470.6 59.42 483.16 24.31 11.62 24.31
4 Parichha 1,2 220 220 43.36 26.49 116.67 71.28 557.91 38.42 874.53 60.23 316.62 56.75 21.81 56.75

5 Durgapur DVC 3,4 350 350 109.96 42.23 211.67 81.29 1256.54 54.40 1536.91 66.53 280.37 22.31 12.14 22.31

6 Harduaganj 3,7 (4)* 215 160 34.76 21.73 64.06 53.81 335.39 23.64 573.82 54.34 238.43 71.09 30.70 129.90

7 RPH 1,2 135 135 84.68 84.31 81.53 81.17 386.63 43.39 564.44 63.35 177.81 45.99 19.96 45.99

8 Chandrapura 1,2,3 390 380 205.95 70.98 220.64 78.04 1464.83 56.91 1487.5 59.31 22.67 1.55 2.40 4.22
9 IP 2,3,4,5 247.5 247.5 94.94 51.56 80.55 43.74 716.10 43.84 671.27 41.09 -44.83 -6.26 -2.74 -6.26
10 Panki 3,4 210 210 77.29 49.47 66.52 42.58 738.39 53.27 664.92 47.97 -73.47 -9.95 -5.30 -9.95
11 Obra 7 to 13 1188 1188 506.43 57.30 423.72 47.94 3990.37 50.89 3926.18 50.07 -64.19 -1.61 -0.82 -1.61
12 Patratu 1,2 (9,10)* 350 80 22.62 38.00 49.49 83.15 182.59 34.58 254.38 48.18 71.79 39.32 13.60 39.32
13 Durgapur DPL 1 to 6 390 390 204.00 70.31 117.00 40.32 1609.05 62.51 1408.89 54.74 -200.16 -12.44 -7.78 -12.44
Total 5026 4690.5 1876.18 50.18 2132.39 61.10 14671.78 44.23 17450.67 56.37 2778.89 18.94 12.14 27.44

* Units are under long shut down.

Page 85 of Chapter 1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

Appendix-1.12
(Page 1 of 2)
STATE WISE LIST OF HYDRO RM&U PROJECTS COMPLETED IN THE 10TH PLAN
(PHASE I PROJECTS* & PHASE II PROJECTS)
As on 31.7.2006
S. Project, Inst. Cap. Cost (Rs. in Crs.) Benefits Category Year of
No Agency (MW) (MW) completion
Estima- Actual
ted
Himachal Pradesh
1. Pong, BBMB 6x60 17.70 17.79 36.00 RM&U 2003-04
(U)
Punjab
2. Shanan Ph.A, 4x15+ 1x50 11.35 10.93 - R&M 2003-04
PSEB
Karnataka
3. Nagjhari, U- 2x135 26.12 22.29 30.00 RM&U 2002-03
1&3, KPCL (U)
4. Supa PH, 2x50 2.64 2.47 - R&M 2002-03
KPCL
5. Mahatma 4x12+4x18 44.66 43.13 19.20 RMU&LE 2002-03
Gandhi*, (U) +
VVNL 120.00
(LE)
6. Munirabad, 2x9+1x10.3 3.64 3.53 28.30 RM&LE 2002-03
VVNL (LE)
7. Mani Dam, 2x4.5 1.00 1.00 - R&M 2002-03
KPCL
8. Shivasamudr 6x3+4x6 68.38 73.17 42.00 RM&LE 2004-05
am, VVNL (LE)
9. Bhadra, 1x2 3.30 1.96 2.00 (LE) RM&LE 2005-06
Ph.II, KPCL
Kerala
10. Pallivasal, 3x5+3x7.5 94.00 37.50 RM&LE 2002-03
KSEB (LE)
11. Sengulam, 4x12 114.00 371.71 48.00 RM&LE 2002-03
KSEB (LE)
12. Panniar, 2x15 62.00 30.00 RM&LE 2002-03
KSEB (LE)
Tamilnadu
13. Pykara*, 3x6.65+1x11+ 26.06 20.147 58.95 RM&LE 2004-05
TNEB 2x14 (LE)
14. Papanasam* 4x7 27.05 22.55 4.00 (U) RMU&LE 2005-06
, TNEB + 28.00
(LE)

Page 86 of Chapter 1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

Appendix-1.12
(Page 2 of 2)

S. Project, Inst. Cap. Cost (Rs. in Crs.) Benefits Category Year of


No Agency (MW) (MW) completion
Estima- Actual
ted
Orissa
15. Hirakud-I, U- 2x24 126.13 111.18 16.00(U)+ RMU&LE 2005-06
3&4*, OHPC 48.00(LE)
West Bengal
16. Maithon, U- 1x20 42.08 35.9828 20.00(LE) RMU& 2004-05
2*, DVC +3.20(U) LE
Maharashtra
17. Bhira Tail 2x40 1.60 0.70 - R&M 2003-04
Race,
MSPGCL
18. Tillari, 1x60 4.50 4.24 6.0 (U) RM&U 2004-05
MSPGCL
19. Koyna Gen. 4x70+4x80+ 12.00 11.50 - R&M 2004-05
Complex, 4x80
MSPGCL
Meghalaya
20. Umium St.I* 4x9 81.88 84.21 36.00(LE) RM&LE 2002-03
MeSEB
21. Khandong, 2x25 4.00 3.3499 - R&M 2003-04
NEEPCO
Total 2457.75 774.09 841.8397 613.15
[114.40 (U)
+ 498.75
(LE)]

Abbreviations: R&M – Renovation & Modernisation;


RM&U – Renovation, Modernisation & Uprating,
RM&LE – Renovation, Modernisation & Life Extension
RMU&LE – Renovation, Modernisation, Uprating & Life Extension;
R&M+Res.-Renovation & Modernisation + Restoration;
RM&LE+Res.- Renovation, Modernisation & Life Extension + Restoration;
RM&U+Res. – Renovation, Modernisation & Uprating + Restoration.
MW – Mega Watt; Res – Restoration; U – Uprating; LE – Life Extension
Phase I Projects started in 1987; Phase II Projects started in 1998

Page 87 of Chapter 1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

Appendix-1.13
(Page 1 of 2)

STATE WISE LIST OF ONGOING HYDRO RM&U PROJECTS PROGRAMMED FOR COMPLETION IN
THE 10TH PLAN (PHASE I PROJECTS* & PHASE II PROJECTS)
As on 31.7.2006
S. Project, Inst. Cap. Cost (Rs. in Crs.) Benefits Category Completion
No Agency (MW) (MW) Schedule
Estima- Expend.
ted cost Incurred
Jammu & Kashmir
1. Sumbal 2x11.3 22.32 0.654 - R&M 2006-07
Sindh*, (as on
J&KPDC 30.4.06)
Punjab
2. Ganguwal,U- 1x29.25 51.28 25.89 RM&LE+R 2006-07
1, BBMB (incl. (LE) es.
IDC +2.10
58.98
6.28) (Res)
(as on
3. Kotla, U-1, 1x29.25 51.28 26.61 RM&LE+R 2006-07
30.6.06)
BBMB (incl. (LE) es.
IDC +2.33
6.28) (Res)
4. Anandpur 4x33.5 3.68 0.1157 - R&M 2006-07
Sahib, PSEB (as on
30.6.06)
Rajasthan
5. Jawahar 3x33 16.55 N.A - R&M 2006-07
Sagar,
RRVUNL
6. Rana Pratap 4x43 20.70 N.A - R&M 2006-07
Sagar,
RRVUNL
Uttaranchal
7. Chibro, 4x60 12.00 9.09 - R&M 2006-07
UJVNL (as on
30.6.06)

8. Khodri, 4x30 8.00 2.845 - R&M 2006-07


UJVNL (as on
30.6.06)
9. Chilla, 4x36 25.00 18.196 - R&M 2006-07
UJVNL (as on
30.6.06)
Andhra Pradesh
10. Lower Sileru, 4x115 8.75 N.A - R&M 2006-07
APGENCO
Karnataka
11. Varahi, 2x115 2.57 3.62 (as - R&M 2006-07
KPCL on
12.7.06)

Page 88 of Chapter 1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

Appendix-1.13
(Page 2 of 2)

S. Project, Inst. Cap. Cost (Rs. in Crs.) Benefits Category Completion


No Agency (MW) (MW) Schedule
Estima- Expend.
ted Incurred
12. Sharavathy, 10x103.5 5.22 3.24 - R&M 2006-07
Ph.A, KPCL (31-5-05)
Kerala
13. Neriamanga- 3x15 58.00 49.96 45.00 RMU&LE 2006-07
lam* KSEB (as on (LE) +9.00
30.3.06) (U)
Tamil Nadu
14. Mettur Dam*, 4x10 30.17 24.16 (as 10.00(U)+ RMU& 2006-07
TNEB on 40.00(LE) LE
31.5.06)
Orissa
15. Hirakud-I - 9.85 15.88 - R&M 2006-07
(Sw.yard)*, (as on
OHPC 24.5.06
Maharashtra
16. Koyna St.III, 4x80@ 16.65 4.25 - R&M 2006-07
MSPGCL (tentativ (as on
e) 31.3.06)
Total 2800.10@ 342.02 190.9907 160.93
[19.00(U) +
137.5(LE) +
4.43 (Res.)]

@- Installed Capacity Koyna St. III at Sl. No. 16 not included in the total, as the
same has already been accounted for at Sl. No. 19 of Appendix 6.4 under Koyna
Gen. Complex.

Page 89 of Chapter 1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

Appendix-1.14
(Page 1 of 2)
State wise List of Ongoing Hydro RM&U Projects programmed for completion in
the 11th Plan (Phase I Projects* & Phase II Projects)
As on 31.7.2006
S. Project, Inst. Cap. Cost (Rs. in Crs.) Benefits Category Completion
No Agency (MW) (MW) Schedule
Estima- Expend.
ted Incurred
Himachal Pradesh
1. Bhakra LB, 5x108 488.00 - 540.00 RMU&LE 2011-12
BBMB (LE) +
90.00
(U)
2. Bassi, HPSEB 4x15 28.60 Nil 6.0(U)+ RMU&LE 2008-09
60 (LE)
Jammu & Kashmir
3. Lower 3x35 101.3 12.57 15.00 R&M+ 2008-09
Jhelum*, (as on (Res.) Res.
J&KPDC 30.4.06
4. Chenani, 5x4.66 34.90 - 23.30 RM&LE 2009-10
J&KPDC (LE)
5. Salal Ph. II, 3x115 + 91.46 - - R&M 2009-10
NHPC 3x115
Punjab
6. Shanan, Ph.B, 4x15 + 35.95 10.867 60.00 RM&LE 2007-08
PSEB 1x50 (as on (LE) (LE for 15
30.6.06) MW units +
R&M for 50
MW unit )
7. UBDC I&II, 3x15 + 7.89 0.87 45.00 RM&LE (LE 2007-08
PSEB 3x15.45 (as on (LE) for 3x15 MW
30.6.06) & R&M for
3x15.45 MW
8. Mukerian St.I, 3x15 6.04 4.29 - R&M XIth Plan
PSEB (as on
30.6.06)
Uttar Pradesh
9. Matatila, 3x10.2 92.35 1.00 15(U) + RMU&LE 2008-09
UPJVNL (as on 30.6 (LE)
30.4. 06)
10. Obra, UPJVNL 3x33 14.50 4.56 99.00 RM&LE 2008-09
(LE)
11. Rihand, 6x50 136.27 11.58 300.00 RM&LE 2009-10
UPJVNL (LE)

Page 90 of Chapter 1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

Appendix-1.14
(Page 2 of 2)
S. Project, Agency Inst. Cap. Cost (Rs. in Crs.) Benefits Category Completion
No (MW) (MW) Schedule
Estima-ted Expend.
Incurred (Till
date)
Andhra Pradesh
12. Nagarjuna Sagar, 1x110+ 33.35 - - R&M & 2007-08
(Ph.I) APGENCO 7x100.8 # Refurbishm-
ent of Units
1, 2, 4 & 5
13. Upper Sileru, APGENCO 4x60 4.20 - - R&M XIth Plan
14. Srisailam RB, 7x110 16.70 - - R&M 2007-08
APGENCO
Karnataka
15. Nagjhari, 3x135 $ 41.16 5.96 45.00 RM&U 2008-09
U-4to6, KPCL (U)
16. Sharavathy 10x103.5 15.73 - - R&M 2009-10
Ph.B, KPCL
17. Supa, KPCL 2x50 1.55 3.73 - R&M 2009-10
18. Nagjhari, U1 to 6, KPCL 3x150 + 17.23 1.15 - R&M 2008-09
3x135 $ (as on
12.7.06)
19. Lingnamakki, KPCL 2X27.5 5.26 0.14 - R&M 2008-09
(as on 12.7.06)
Kerala
20. Sabirigiri*, KSEB 6x50 98.56 57.00 300.00 RMU&LE 2008-09
(as on 31.3.06) (LE) +
35.00 (U)
Tamil Nadu
21. Sholayar-I, TNEB 2x35 40.68 - 14.00(U) RMU&LE 2008-09
+70.00
(LE)
Orissa
22. Hirakud-II*, OHPC 3x24 125.52 54.46 72.00 (LE) RM&LE 2008-09
(as on 24.5.06)
West Bengal
23. Jaldhaka St.I*, WBSEB 3x9 52.17 4.31 27.00(LE) RM&LE 2008-09
(as on 6/2006)
Maharashtra
24. Koyna St.I & II, MSPGCL - 75.50 60.34(for P.H.) - R&M 2007-08
(Incl. & 0.34 (for Sw.
12.50 for yd.) (as on
Sw. Yd.) 31.3.06)
Manipur
25. Loktak*, NHPC 3x35 19.755 - 15.00 R&M + Res. 2008-09
(Res)
Total 7138.85 $ 584.625 232.827 1861.90
[205.0 (U) +
1626.9 (LE) +
30.0(Res.)]
$ - Installed Capacity of Nagjhari (U-4 to 6) at Sl. No. 15 not included in the total, as the
same has already been accounted for at Sl. No. 18.

Page 91 of Chapter 1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

Appendix-1.15
(Page 1 of 2)

State wise List of Hydro RM&U Projects programmed for completion in the 11th Plan
but works of which are yet to be taken up for implementation
(Phase I Projects* & Phase II Projects)
As on 31.7.2006
S.No. Project, Inst. Cap. Estimated Benefits Category Completion
Agency (MW) Cost (MW) Schedule
(Rs. in Crs)
Himachal Pradesh
1. Dehar,(Ph-A) 6x165 11.00 - R&M 2008-09
BBMB
2. Giri, HPSEB 2x33 8.28 66.00 (LE) RM&LE XI th Plan
Jammu & Kashmir
3. Ganderbal, 2x3+2x4.5 34.20 15.00 (LE) RM&LE 2008-09
J&KPDC
Uttaranchal
4. Dhakrani, 3x11.25 55.00 33.75 (LE) RM&LE 2010-11
UJVNL
5. Dhalipur, 3x17 80.00 51.00 (LE) RM&LE 2010-11
UJVNL
6. Tiloth, UJVNL 3x30 130.00 90 (LE) RM&LE 2010-11
7. Khatima, 3x13.8 100.00 41.40 (LE) RM&LE 2009-10
UJVNL
8. Pathri, UJVNL 3x6.8 60.00 20.40 (LE) RM&LE 2009-10
9. Kulhal, UJVNL 3x10 30.00 30(LE) RM&LE 2010-11
10. Ramganga, 3x66 40.00 18.00(Res) R&M+Res. 2009-10
UJVNL
Andhra Pradesh
11. Hampi, 2x9(St.I) & 25.00 36.00 (LE) RM&LE XI th Plan
APGENCO 2x9(St.II)
12. Machkund *, 3x17(St.I) 124.45 15.25(U) RMU&LE XI th Plan
APGENCO & 3x21.25 +114.75(LE)
(St.II)
13. Tungabhadra, 4x9 25.00 36(LE) RM&LE XI th Plan
APGENCO
14. Nagarjuna 1x110 + 15.00 - R&M & XI th Plan
Sagar, Ph.II 7x100.8 # Refurbishm-
APGENCO ent of Units
3,6,7 & 8
15. Upper Sileru, 4x60 10.00 - R&M XI th Plan
Ph.II
APGENCO

Page 92 of Chapter 1
Demand for Power and Generation Planning Working Group on Power for 11th Plan

Appendix-1.15
(Page 2 of 2)

S.No. Project, Agency Inst. Estimated Benefits Category Completion


Cap. Cost (MW) Schedule
(MW) (Rs. in Crs)
Karnataka
16. Bhadra, KPCL 2x12 4.75 24(LE) RM&LE 2008-09

Kerala
17. Sholayar, KSEB 3x18 54.00 54.00 (LE) RM&LE XI th Plan
18. Poringal-kuthu*,KSEB 4x8 9.55 32.00 (LE) RM&LE XI th Plan
Tamil Nadu
19. Periyar,TNEB 4x35 73.8 140.00 RMU&LE 2009-10
(LE) +
28.00(U)
20. Moyar, TNEB 3x12 18.00 36.00 (LE) RM&LE XI th Plan
21. Kundah St.I, TNEB 3x20 50.00 60.00 (LE) RM&LE XI th Plan
22. Kundah St.II, TNEB 5x35 75.00 175.00 (LE) RM&LE XI th Plan
23. Kundah St.III, TNEB 3x60 70.00 180.00 (LE) RM&LE XI th Plan
24. Kundah St.IV, TNEB 2x50 35.00 100.00 (LE) RM&LE XI th Plan
25. Kundah St.V, TNEB 2x20 13.00 20.00 (LE) RM&LE of XIth Plan
Unit-1 & R&M
of U-2
26. Kodayar Ph.I, TNEB 1x60 30.00 60.00 (LE) RM&LE XIth Plan
Jharkhand
27. Subernrekha, JSEB 2x65 65.00 130.00 (LE) RM&LE XI th Plan
(Being
Revised)
28. Panchet, 1x40 44.96 40.00(LE) RM&LE 2008-09
U-1*, DVC
Orissa
29. Balimela, OHPC 6x60 160.00 360.00 (LE) RM&LE XI th Plan
30. Hirakud-I* U5&6, 2x37.5 92.37 75.00 (LE) RM&LE 2009-10
OHPC
West Bengal
31. Maithon U1&3, DVC 2x20 49.05 40.00 (LE) RM&LE XI th Plan
Maharashtra
32. Koyna-III, MSPGCL 4x80 150.00 320.00 (LE) RM&LE XIth Plan
Assam
33. Kopili, NEEPCO 2x50 + 36.01 (Likely - R&M & XI th Plan
2x50 to be Rev.) Refurbishm-en
of Units
1&2
Meghalaya
34. UmiumSt.II*, MeSEB 2x9 90.46 18.00 (LE) RM&LE 2008-09
35. Kyrdemkulai*, MeSEB 2x30 25.00 6.00 (U) RM&U XI th Plan
Total 4139.30 # 1893.88 2465.55
[49.25 (U) +
2398.3 (LE)
+18.0 (Res.)]

Page 93 of Chapter 1
Transmission Planning & National Grid Working Group on Power for 11th Plan

Chapter-2
TRANSMISSION PLANNING AND NATIONAL GRID

2.0 INTRODUCTION

The transmission system facilities had earlier been planned on regional basis with
provision of inter-regional link to transfer regional surplus power arising out of
diversity in demand. The generation resources in the country are unevenly located,
the hydro in the northern and north-eastern states and coal being mainly in the
eastern part of the country. Development of strong National Grid has become
necessity to ensure reliable supply of power to all. The planning & operation of the
transmission system has thus shifted from regional to national level. Formation of a
strong National Power Grid has been recognized as a flagship endeavour to steer the
development of Power System on planned path leading to cost effective fulfilment of
the objective of ‘Electricity to All’ at affordable prices. A strong All India Grid would
enable exploitation of unevenly distributed generation resources in the country to
their optimum potential by providing enhanced margins in inter-regional transmission
system. These margins, together with open access in transmission, would facilitate
increased trading in electricity leading to market determined generation dispatches
thereby resulting in supply at reduced prices to the distribution utilities and ultimately
to consumers benefit.

2.1 REVIEW OF TRANSMISSION SYSTEM DURING 10TH PLAN

The development of transmission system requirement during the 10th Plan was taken
up along with the development of the generation programme for 10th Plan. The
transmission system required for evacuation of power from each of the generation
project, as per the planning criteria adopted, had been identified as well as the
system required for strengthening of the network for delivery of power to the load
centres had also been identified. The identified transmission programme has been
reviewed from time to time to take into account any revision in the generation
programme and variations in development of load at various load centres in the State
systems. Generally, there had been no constraint in intra-regional transmission
systems. However, need of more capacities in the inter-regional systems was
increasingly felt. Transmission schemes for providing more inter-regional capacities
had already been initiated in the 9th Plan and the programme was accelerated during
10th Plan. This has resulted in consolidating the National Grid. The inter-regional
transmission capacity at 200kV and above increased from 5050 MW at the beginning
of 10th Plan i.e. by March 2002, to 11,450 MW by August 2006, and against revised
target of 16,450MW it is likely to reach 15,450 MW by the end of 10th Plan (i.e. by
March 2007).

Based on the list of generation projects corresponding to the programme of 41,110 k


transmission requirements at 132 kV level and above including the power evacuation
system as well as network strengthening were identified. This transmission
programme became the basis for taking up detailed planning exercise and finalizing

Page 1 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

of their transmission development programme by the Central Transmission Utility and


the State Transmission Utilities corresponding to the actual pace of 10th Plan
development happening in generation and the actual area-wise load growths.
Accordingly, the 10th Plan transmission programme had to be reviewed and targets
reworked to match the generation programme. Apart from changes in associated
transmission system corresponding to deferred/slipped/changed generation,
transmission strengthening in power delivery networks had also to be reviewed to
take care of variation in projected demand growth and the actual/updated projections
of demand growth. Accordingly, the transmission programme taken-up for execution
was revised as per the actual needs matching with generation projects.

2.1.1 Achievements in Transmission during First Four Years of 10th Plan

At the end of 9th five year Plan, corresponding to the total installed generation
capacity of 105 GW as on 31st March 2002 and peak demand of 73 GW, the
transmission system in the country at 765/HVDC/400/230/220/132/110 kV stood at
257 thousand circuit kilometres (Tckm) of transmission lines and 292 GVA of
substation capacity. The corresponding sub-transmission system and distribution
system stood at 302 Tckm and 115 GVA at 66/33/22kV, 1758 Tckm at
15/11/6.6/3.3/2.2kV, 176 GVA of distribution transformers and 3680 Tckm of LT lines.
[Ref: General Review 2002, CEA]

Summary of updated 10th Plan transmission programme targeted based on actual


progress during the first four years and the updated targets for the remaining year, is
tabulated below:
Table 2.1

As at the end Added Achieved To be Target for


of 9 Plan
th during as at the added the End of
Transmission System 2002-06 during
Unit i.e. March end of 10th Plan
Type / Voltage Class
2002 (four years) 2005-06 i.e. 2006-07 i.e.
* March 2006 March 2007
TRANSMISSION LINES
(a) 765 kV ckm 971 186 1157 996 2153
(b) HVDC ± 500kV ckm 3138 2738 5876 0 5876
(c) 400 kV ckm 49378 13773 63151 14403 77554
(d) 230/220kV ckm 96994 10593 107587 12017 119604
(e) HVDC 200kV ckm 162 0 162 0 162
Total of (a), (b), (c),(d) & (e) ckm 150643 27290 177933 27416 205349
SUBSTATIONS
(a) 765 kV MVA 0 0 0 3000 3000
(b) 400 kV MVA 60380 20540 80920 12120 93040
(c) 230/220 kV MVA 116363 28758 145121 12348 157469
Total of (a), (b) & (c) 176743 49298 226041 27468 253509
HVDC
(a) Bi-pole link capacity MW 3000 2000 5000 500 5500
(b) Back-to back capacity MW 2000 1000 3000 0 3000
(c) Mono-pole link capacity MW 200 0 200 0 200
Total of (a), (b) & (c) MW 5200 3000 8200 500 8700

[* General Review 2002, CEA]

Page 2 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

2.1.2 Programme of Inter-Regional Transmission Capacity in 10th Plan

At the end of the 9th Plan, the inter-regional transmission capacity at 200kV and
above was 5050 MW. The original programme corresponding to X Plan generation
programme of 41,000 MW was to add 18600 MW during 10th Plan. The revised target
programme for 10th plan is to add 11400 MW out of which 4400 MW has been added
during the first four years that is 2002-06 MW and 7000 MW is the target for 2006-07
so as to achieve 16450 MW in the end of 10th plan. Out of this target of 7000 MW,
Muzaffarpur-Gorakhpur 400kV D/C quad line with TCSC of 2000 MW was added in
August 2006. However, as per the progress, likely achievement is expected to be
1000 MW less due to slipping of Ranchi-Sipat 400kV D/C line. With this, the inter-
regional transmission capacity by the end of 10th Plan is anticipated to increase to
15450 MW by 2006-07.

The Inter-Regional transmission capacities programmed for the 10th Plan are:

¾ HVDC Back to-back stations at Gazuwaka (500 MW),


¾ HVDC Back to-back station at Sasaram (500MW),
¾ Talcher-Kolar HVDC Bipole (2000 MW), and
¾ Rourkela-Raipur 400kV D/C line with TCSC (1400 MW)
¾ Muzaffarpur-Gorakhpur 400kV D/C quad line with TCSC (2000 MW)
(* This line was charged on 26-08-2006, thereby establishing synchronous
connections between NER-ER-WR-NR.)
¾ Biharshariff-Balia 400kV quad line (1200 MW),
¾ Patna-Balia 400kV quad line (1200 MW),
¾ Agra-Gwalior 765kV line operated at 400kV, and
¾ Ranchi-Sipat 400kV D/C line with 40% series compensation (1000 MW)

2.1.3 Development of HVDC Systems during 10th Plan:

Talcher – Kolar HVDC + 500kV Bipole of 2000 MW capacity, Sasaram HVDC back-
to-back of 500 MW capacity and Gazuwaka HVDC back-to-back second module of
500 MW capacity were added during the X Plan. A summary of development of
HVDC systems in India during first four years and also programme for the last year
i.e. 2006-07 is given at Appendix-2.1

2.1.4 Development of 765kV Systems during 10th Plan:

Currently all of the 765 kV systems in the country are operated at 400kV, the
transmission system for Sipat that would be completed in 2006-07, would be
operated at 765kV, thus setting a new milestone in development of transmission
system in the country. A summary of development of 765kV transmission system in
India during first four years and also programme for the last year i.e. 2006-07 of 10th
Plan is given at Appendix --2.2

2.1.5 Development of Regional Grids during 10th Plan

List of major transmission schemes completed and programmed under the


development plan of the Regional Grids and National Grid during the 10th Plan are
given at Appendix --2.3 to Appendix --2.7.

Page 3 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

2.1.6 Fund Requirement and Utilization during 10th Plan

Initially, based on the 41 GW generation addition programme for 10th Plan, a total of
Rs 74400 crore was estimated for transmission schemes in 10th Plan. Out of this, a
sum of about Rs 40300 crore was to be spent for development of Regional grids and
Nation grid by Powergrid on its own and also through joint venture schemes.
However, because of slippage/deferment of generation programme over the span of
10th plan and consequent reduction in the transmission programme, only about Rs
20780 Crore (Rs 19168 crore by PGCIL alone and Rs 1912 crore through joint
venture) would be spent during X plan. Under state sector, the estimate was to spend
Rs 34100 crore for 66kV and above schemes (this estimate does not include the
schemes in J&K, Sikkim, Goa, Mizoram and Uttaranchal). Based on current estimate,
about Rs 28900 crore would be spent by the state utilities. (These estimates are for
220kV above schemes and do not include states of J&K and Sikkim). Thus with the
updated generation addition estimate of about 31 GW in five years of X Plan, an
amount of Rs 49680 crore would be spent.

2.1.7 Difficulties and constraints in implementation of Transmission Schemes

It may mentioned that due to sustained efforts by Central PSUs and States, and
close coordination by Ministry of Power/CEA with CPSUs and States the
transmission Schemes meant for evacuation of power from Generating stations,
strengthening schemes and sub-transmission schemes etc for absorption of power
from Generating Stations by the states had been commissioned well in time. Hence
by and large there was no bottling up, as such, of power from Generating stations
and the States were capable of absorbing the additional power capacity added during
these years. Not withstanding the above, transmission utilities faced some difficulties
in implementation and completion of their schemes. A case-wise analysis of
difficulties and constraints experienced by them is detailed in following paragraphs.

The CPSUs and States had experienced difficulties during construction of


transmission schemes. Noticeably, in case of Dhauliganga- Bareilly 400 kV D/C line,
Dadri- Panipat, 400kV S/C line, LILO of 400 kV Dadri-Ballabgarh D/C line at Noida,
Tehri –Meerut 765kV S/C line, Pykara-Arasur 230 kV D/C line some difficulties were
experienced.

¾ In case of Dhauliganga(NHPC)- Bareilly (initially to be charged at 220 kV),


progress in Ascot wild life area adversely affected since October, 2003 due to
refusal of permission for working in Ascot Wild Life Sanctuary.

¾ In case of Dadri-Panipat 400 kV S/C line, there were severe Right of Way
constraints and law & order problems. The problems were resolved through
the intervention of Senior Govt. Officials of Uttar Pradesh and the line was
commissioned in March 06.

¾ In case of LILO of 400 kV Dadri-Ballabgarh at Noida, work was held as


clearance was not received from NOIDA Authority in NOIDA. Matter pursued

Page 4 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

with NOIDA Authority /State Administrator to resolve the issue. Line is being
re-routed and work has re-commenced..

¾ Tehri-Meerut 765kV Ckt.-I was completed in August 2004 ahead of generation


project i.e. Tehri Stage-I HEP(4x250 MW). But, the Tehri-Meerut 765kV S/C
Ckt.-II, was completed in March 2006. Work in Rajaji National Park was not
allowed by forest authorities until clarification was received from Hon’ble
Supreme Court,

¾ In case of Pykara-Arasur 230 kV D/C, the proposal for transmission line falling
in forest area the clearance from Hon’ble Supreme Court received on 30th
Jan. 2004. There was further delay due to large scale tree cutting under the
direct supervision of Regional Conservator of Forests.

2.2 NATIONAL GRID

2.2.1 Introduction

Formation of a strong National Power Grid has been recognized as a flagship


endeavour to steer the development of Power System on planned path leading to
cost effective fulfilment of the objective of ‘Electricity to All’ at affordable prices. A
strong All India Grid would enable exploitation of unevenly distributed generation
resources in the country to their optimum potential by providing enhanced margins in
inter-regional transmission system. These margins, together with open access in
transmission, would facilitate increased real time trading in electricity leading to
market determined generation dispatches thereby resulting in supply at reduced
prices to the distribution utilities and ultimately to consumers benefit.

2.2.2 Emergence of Inter-Regional Systems

During the 1980s, the regional grids developed with construction of power evacuation
lines planned and implemented as associated transmission system of central sector
generation schemes for benefits within the regions. The initial set of inter-regional
links developed under the Centrally sponsored programme for building inter-state
infrastructure of State utilities, was utilized to facilitate exchange of operational
surpluses among the various Regions in a limited manner because the Regional
Grids operated independently and had different operational frequencies and the
power exchanges on these inter-regional links could take place only in radial mode.

In 1989, transmission wings of Central generating companies were separated to set


up Power Grid Corporation of India (POWERGRID) to give thrust to implementation
of transmission system associated with Central generating stations and inter-
Regional transmission programme based on perspective planning done by CEA.
Considering the prevailing operational regime at that time, it was decided to establish
initially asynchronous connection between the Regional Grids to enable exchange of
regulated quantum of power and asynchronous HVDC back-to-back links of 500MW
between the Northern Region and the Western Region at Vindhyachal, 1000MW
between Western Region and Southern Region at Bhardawati, 1000MW between

Page 5 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

Eastern Region and Southern Region and 500MW between Eastern Region and
Northern Region at Sasaram were provided during 90s and early 2000s.

2.2.3 Formation of National Grid

The Eastern Region and the North-Eastern Region have been operating in parallel
since 1992 being connected by a 220 kV double circuit transmission line and more
recently by a 400 kV D/C transmission line. Western Region was interconnected to
ER-NER system synchronously through 400kV Rourkela-Raipur D/C line in 2003,
operationalising the Central India system consisting of ER-NER-WR. With
installation of TCSC, the transmission capacity of Rourkela-Raipur 400kV D/C line
was increased to 1400MW.

The Northern region, which till August 2006 had asynchronous radial mode and
HVDC back-to-back inter-regional transmission connectivity of 600 MW with the
Eastern region, and 1000 MW with the Western region, was also synchronously
integrated with the ER/NER/WR system with commissioning of the 400kV
Muzaffarpur-Gorakhpur line on 26th August 2006. The Muzaffarpur – Gorakhpur
400kV D/C quad line with fixed series capacitor and TCSC has added 2000 MW to
the ER-NR inter-regional transmission capacity.

Towards the Southern region, asynchronous interconnections of 1700 MW between


SR and WR and 600 MW between SR and ER providing a total of 2300 MW of inter-
regional transmission capacity was existing at the beginning of the X plan. With 2000
MW Talcher-Kolar HVDC Bipole line, and second 500 MW HVDC back-to back
module at Gazuwaka, both between SR and ER, the total inter-regional capacity
connecting to SR has increased to 4800 MW. As of now all inter-regional
transmission links of the Southern region are either asynchronous radial mode lines
or HVDC inter-connections. Synchronous integration of the Southern region with rest
of Indian grid would be firmed up after having experience of synchronous operation
of NR+ER+NER+WR system. One point AC interconnection through Parli – Raichur
400kv link supplemented with HVDC links has been proposed for this. The target is to
firm up this scheme in the first year of 11th Plan so that synchronous interconnection
of All India system could be realized with in the 11th Plan period.

2.2.4 Programme of Development of National Grid

As on today, the inter-regional transmission capacity of 11,450 MW is existing and


inter-regional energy exchanges of more than 12 billion kWh in a year thus
contributing to greater utilization of generation capacity. The program is to achieve
inter-regional capacity of 15750 MW by the end of 10th Plan and about 37,150 MW by
the end of 11th Plan. Additional 3000 MW through creation of Siliguri HVDC terminal
on Bishwanath Chariyali – Agra 800kV HVDC bi-pole line is also being considered
during 11th Plan itself. This would increase the target of inter-regional capacity by
2011-12 from 37150 MW to 40150 MW.

The table given below gives the programme of Inter-regional Transmission Capacity
up to 2011-12.

Page 6 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

Details of inter-regional transmission –

Existing, under construction and Planned:


Table 2.2

Power Transfer Capacity (MW)

Name of system At the end Additions At the end Additions At the


of 9th Plan during of 10th during end of
i.e. end of 10th Plan Plan i.e. 11th Plan 11th
2001-02 2002-07 end of 2007-12 Plan i.e.
2006-07 end of
2011-12
ER – SR :
Gazuwaka HVDC back to 500 500 1000 1000
back
Balimela-Upper Sileru 220kV 100 100 100
S/C
Talcher-Kolar HVDC Bipole 2000 2000 2000
Upgradation of Talcher– 500 500
Kolar HVDC bipole
ER-SR 600 2500 3100 500 3600
total
ER –NR :
Muzaffarpur - Gorakhpur 2000 2000 2000
400kV D/C
(Quad Moose) with series
comp
Dehri-Sahupuri 220kV S/C 100 100 100
Sasaram HVDC back to 500 500 500
back
Biharshariff-Balia 400kV D/C 1600 1600 1600
quad increased loadability
with series capacitor in
associated lines in NR sys
Patna-Balia 400kV D/C quad 1600 1600 1600
increased loadability with
series capacitor in
associated lines in NR
system
Barh-Balia 400kV D/C quad 1600 1600
increased loadability with
series capacitor in
associated lines in NR
system
Sasaram–Fatehpur 765kV 2300 2300
S/C (40% SC)

Page 7 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

Name of system At the end Additions At the end Additions At the


of 9th Plan during of 10th during end of
i.e. end of 10th Plan Plan i.e. 11th Plan 11th
2001-02 2002-07 end of 2007-12 Plan i.e.
2006-07 end of
2011-12
Sasaram-Balia 400kV D/C 1600 1600
quad increased loadability
with series capacitor in
associated lines in NR sys
ER-NR total 100 5700 5800 6700 11300
ER - WR :
Rourkela-Raipur 400kV D/C 1000 1000 1000
(without SC)
TCSC on Rourkla-Raipur 400 400 400
400kV DC
Budhipara-Korba220kV 400 400 400
D/C+S/C
Ranchi-Sipat 400kV D/C 1000 1000
(40% SC)
Ranchi-Rourkela-Raipur 1400 1400
400kV D/C
North Karanpura-Sipat 2300
765kV S/C
ER-WR 400 1400 1800 4700 6500
total
ER - NER :
Birpara-Salakati 220kV D/C 250 250 250
Malda-Bongaigaon 400kV 1000 1000 1000
D/C
Bongaigaon-Siliguri 400kV 1000 1200
D/C Quad

ER-NER 1250 1250 1000 2250


total
NR - WR :
Vindhychal HVDC back to 500 500 500
back
Auria-Malanpur 220kV D/C 250 250 250
Kota-Ujjain 220kV D/C 250 250 250
Agra-Gwalior 765kV S/C 1100 1100 1100
line-1 400kV op.
Agra-Gwalior 765kV line-1 1200 1200
765kV op
Agra-Gwalior 765kV line-2 2300 2300
Kankroli-Zerda 400kV D/C 1000 1000
RAPP-Nagda 400kV D/C 1000 1000
NR-WR 1000 1100 2100 5500 7600
total

Page 8 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

Name of system At the end Additions At the end Additions At the


of 9th Plan during of 10th during end of
i.e. end of 10th Plan Plan i.e. 11th Plan 11th
2001-02 2002-07 end of 2007-12 Plan i.e.
2006-07 end of
2011-12
WR-SR :
Chandrapur HVDC back to 1000 1000 1000
back
Barsur–L.Sileru 200kV 200 200 200
HVDC mono pole
Kolhapur-Belgaum 220kV 250 250 250
D/C
Ponda – Nagajhari 220kV 250 250 250
D/C
Parli-Raichur 400kV D/C 1000 1000
WR-SR total 1700 1700 1000 2700
NER-NR/WR :
Bishwanath Chariyali–Agra 3000 3000
HVDC bi-pole 800kV
NER-NR/WR total 3000 3000
TOTAL ALL INDIA 5050 10700 15750 21400 37150

Additional 3000 MW through creation of Siliguri HVDC terminal on NER-NR/WR


inter-connector, which would increase the target of inter-regional capacity by 2011-12
from 37150 MW to 40150 MW.

2.2.5 Transmission System for Evacuation of Power from Hydro Projects in


NER, Sikkim & Bhutan

North Eastern Region, Sikkim and Bhutan have vast untapped hydro potential which
is planned for development during 11th plan and beyond. A major component of this
power will be utilised by deficit states in the northern and western region and for
which reliable evacuation system is planned to be developed. The requirement of
transmission system for evacuation of NER hydro power has been estimated
corresponding to the capacity of hydro projects which may be feasible to develop say
in the next about 20 years. This generation is estimated to be about 35000 MW in
NER, about 8000 MW in Sikkim and about 15000 MW in Bhutan. Taking local
development at accelerated pace resulting in demand within the NER, Sikkim and
Bhutan to be in the range of 10000 – 12000 MW (presently it is about 1500 MW), the
transmission requirement through the chicken neck works out to be of the order of
45000 MW. The total requirement including additional circuits for meeting the
contingencies and reliability needs, would work out to 7 or 8 numbers of 800 kV
HVDC bi-pole lines and 4 or 5 numbers of 400kV double circuit lines – a total of 12
numbers of high capacity transmission corridors passing through the chicken neck.
For this, RoW requirement would be about 1.5 Km in width considering minimum
distance between adjacent towers to be such that fall of any tower does not affect the
adjoining line. The first 800kV HVDC bi-pole line has been planned from a pooling
substation at Biswanath Chariyali in North-eastern Region to Agra in Northern region.

Page 9 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

This is being programmed for commissioning matching with Subansiri Lower HEP in
2011-12.

2.2.6 Regional system matching with inter-regional transmission system

Transmission systems within the regions to support the above inter-regional


transmission capacity is also planned. For example, together with Muzaffarpur-
Gorakhpur 400kV D/C line, Siliguri-Purnia-Muzaffarpur 400kV D/C in the Eastern
region and Gorakhpur-Lucknow 400kV D/C and Bareilly-Mandola 400kV D/C lines in
Northern region have also been provided. Similarly, together with inter-regional
transmission lines that would bring power from Kahalgaon and Barh in Eastern region
to Balia in Northern region, transmission system from Balia onwards towards western
part of Northern region has been planned. In the Western region, major system
strengthening scheme has been programmed for onwards transmission of power to
be received through ER-WR inter-regional links. Similarly, transmission system has
also been planned on both sides of inter-regional links between NR and WR and
between ER and SR.

2.2.7 Implementation of National Power Grid – Financing and Tariff Issues

The plan for National Power Grid and the schemes have been identified.
Implementation of these schemes would require, apart from investment decisions
and arranging finances, urgent needs for addressing transmission tariff related
issues. The total transmission charges payable to the Central Transmission Utility are
worked out on cost plus basis. In case of transmission system through private
participation on competitive basis, this would be as per bid-based tariff. The present
method of apportionment of the total transmission charges among the beneficiaries is
to allocate the regional pooled transmission charges in proportion to their shares in
Central Sector generation. This mechanism was evolved during the late seventies
when major Central initiatives were taken in generation and associated regional
transmission system. The formula has, by and large, worked satisfactorily. With each
addition in generation resources and associated transmission system in Central
Sector, the States had been getting their shares in more or less same ratio as the
allocations that existed prior to the incremental additions. However, with shift towards
market determined allocations, new dimensions have been added on account of - (a)
surpluses in Eastern region, (b) higher deficit in Northern region and Western region;
and (c) coming up of generation projects for cross-regional benefit and (d) merchant
generation plants without long-term power allocations or PPAs and intending to sell
on short-term basis to different customers utilizing open access in transmission.
Consequently, allocation of Central sector generation is no more taking place as per
earlier practice/formula. In this changed scenario, the existing methodology of
apportionment of Central Transmission Charges among the beneficiaries on regional
pool basis is causing distortion. As the cost of incremental facilities is generally
substantially higher than that of existing facilities, beneficiaries seeking lower or no
allocation from new Central generation see this transmission charge pooling and
apportionment arrangement to be disadvantageous to them, while the beneficiaries
seeking higher shares in new generation capacities find it advantageous to them.
Consequently, the States getting lower share in new Central generation are reluctant
to commit transmission charges for the incremental transmission system. This
difficulty is severe for those elements of transmission network which go towards

Page 10 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

improved system reliability and margins for open access and for supporting non-
committed transaction such as utilization of operational surpluses and incremental
cost merit based dispatch optimization. This gets further complicated in case of
projects with cross-regional or multi-regional benefits.

It is also important that the finances for the Transmission Schemes of the National
Grid are arranged at low cost. With focus on system reliability and building margins
for open access in the transmission system, the per unit investment in transmission
system at Regional and National level is set to increase considerably. This would
further increase on account of harnessing remotely located Hydro resources in the
Northern Region and North-Eastern Region. The impact of harnessing North-Eastern
Region Hydro resources would be much more as the power would have to be
transmitted across the North-Eastern and Eastern Regions to bring it to
Northern/Western/Southern Regions where it can be actually absorbed. As such, the
transmission charges may go up considerably.

2.2.8 Synchronous Inter-Connection of Southern Region with rest of Indian


Grid

Integration of the Southern region with rest of Indian grid was considered to be
programmed during 11th Plan period. The proposal is to connect SR and WR
synchronously through one 400kV D/C quad line between Parli and Raichur. Fixed
Series Capacitor as well as TCSC would also be provided on this link. The link would
have transmission capacity of the order of 2000 MW per quad D/C line under system
contingency with normal transmission capacity limited to 1000 MW, due to this being
only synchronous inter-connection between Southern region and rest of Indian grid.
The balance inter-regional transmission capacity for SR would come from existing
and future HVDC links.

POWERGRID is of opinion that further 11th Plan links to Southern Region should be
through HVDC and synchronous interconnection of Southern Region with rest of the
Indian grid should be considered after having a few years of experience of operating
the NR-WR-ER-NER system synchronously.

Synchronous inter-connection of Southern region with rest of Indian grid would be of


advantage to all as it would enable widening of real time power market allowing
optimization of generation resources on all India level. For realizing this at the
earliest, the proposal is being discussed so as to firm-up the scheme and achieve
synchronous interconnection of Southern grid within 11th Plan.

2.3 ELEVENTH PLAN PROGRAMME

2.3.1 Assessment of Transmission Capacity Requirement

The focus of transmission system development programme for the XI Plan is to


provide adequate inter-regional and intra-regional transmission capacity so as to
consolidate and strengthen the National Grid network towards a strong All India Grid.
The inter-regional power exchange requirement has been assessed from possible
scenarios of regional surpluses and deficits for the peak and off-peak conditions of
winter, summer and monsoon months. The surplus/deficit projections based on

Page 11 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

programme of generation and anticipated demand aims at estimating the


transmission requirement at the inter-regional level. Grid expansion plan evolved
based on this projection would be able to cater to the needs of various feasible
operating scenarios and also provide required margins to support market oriented
power exchanges. Transmission system programme for 11th Plan have been worked
out based on this methodology.

2.3.2 Transmission System Programmes for 11th Plan

For the development of transmission system in the country, the following


programmes have been identified to be taken-up during the 11th Plan:

Central Sector Schemes:


➢ Transmission schemes for inter-state transmission system
➢ Load dispatch schemes for National and Regional dispatch centres
➢ National level Power Exchange
➢ Comprehensive upgrading of protection system for total integrated
system for security of National and Regional grids
th
➢ Evolving perspective transmission plan for the 12 Plan period
➢ Augmentation of test facilities

State Sector Schemes:


➢ Transmission schemes for intra-state transmission system
➢ Load dispatch schemes for State and Area dispatch centres
➢ Schemes for upgrading of protection systems for security of State grids

2.3.3 Evolving the Perspective Transmission System for 11th Plan

In transmission system development in the country, the focus of 11th plan programme
is formation of the national power grid. A strong all India grid would enable
exploitation of unevenly distributed generation resources in the country to their
optimum potential. The transmission capacity together with the margins provided for
required redundancies as per planning criteria would provide a reliable transmission
system. this would meet the firm transmission needs and with open access in
transmission, would facilitate increased real time trading in electricity leading to
market determined generation dispatches thereby resulting in supply at reduced
prices to the distribution utilities and ultimately to the consumers. Development of
national grid has been necessitated by the large thermal generation potential in
eastern part of the country and equally large hydro generation potential in north-
eastern part. It has also been spurred by the opportunity provided by open access,
variation in hydrology / hydro potential and diversity of load across the country.

2.3.4 Assessment of National and Regional Transmission Requirements

For assessing the inter-regional power exchange requirements, possible scenarios of


regional surpluses and deficit corresponding to each year upto the end of 11th plan
(i.e. Each year upto 2011-12) has been projected for the peak and off-peak
conditions of winter, summer and monsoon months. The projection based on

Page 12 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

programme of generation and anticipated demand aims at estimating the


transmission requirement at the inter-regional level. The national grid system evolved
on this projection would be able to cater to the needs of various feasible operating
scenarios and also provide required margins to support market oriented power
exchanges.

Region-wise assessment of import(-)/export(+) need based on projection of


availability and demand corresponding to various seasonal scenarios of 2011-12,
which forms the basis for assessing the transmission requirement and evolving of the
national grid network is summarized in the following table:

Table 2.3
Assessment of Regional Exchange of Power

(All Figures in MW)


Winter
Winter Off Peak Winter Peak
Regions Availability Surplus(+) Availability Surplus(+)
Demand Demand
Deficit (-) Deficit (-)
Northern 30336 34468 -4132 39555 49240 -9685
Western 39368 36624 2744 42993 52320 -9327
Southern 28091 26922 1169 33493 38460 -4967
Eastern 30576 11844 18732 32675 16920 15755
North-Eastern 2638 1862 776 4218 2660 1558
Total 131010 111720 19290 152935 159600 -6665

Monsoon
Monsoon Off Peak Monsoon Peak
Regions Availability Surplus(+) Availability Surplus(+)
Demand Demand
Deficit (-) Deficit (-)
Northern 45477 34468 11009 47782 44316 3466
Western 39665 36624 3041 41277 47088 -5811
Southern 31530 26922 4608 33931 34614 -683
Eastern 30189 11844 18345 31239 15228 16011
North-Eastern 5658 1862 3796 6053 2394 3659
Total 152519 111720 40799 160281 143640 16641

Summer
Summer Off Peak Summer Peak
Regions Availability Surplus(+) Availability Surplus(+)
Demand Demand
Deficit (-) Deficit (-)
Northern 41364 44316 -2952 44821 49240 -4419
Western 39516 36624 2892 41934 52320 -10387
Southern 30111 26922 3189 33712 38460 -4748
Eastern 30383 11844 18539 31957 16920 15037
North-Eastern 4613 1862 2751 5403 2660 2743
Total 145987 121568 24419 157827 159600 -1773

Page 13 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

2.3.5 Identification of Transmission Systems for 11th Plan

Identification of transmission expansion plan was done based on power system


studies corresponding to the scenario at the end of 11th plan. The implementation
programme was subsequently worked out matching the evacuation and
strengthening schemes with associated generation and load growth. Most of the 11th
plan schemes have been discussed and firmed-up in the regional standing
committees on transmission planning. Investment approvals for some of the schemes
have also been obtained and construction started. Some of the schemes are in
investment approval stage. Some of the schemes are under final stages of firming-
up.

2.3.6 Inter-Regional System

It is envisaged to add during the XI Plan period new inter-regional capacities of


20700 MW at 220kV and above. This would increase the total inter-regional
transmission capacity of national power grid at 220kV and above from 16450 MW of
XI Plan beginning to 37150 MW by 2011-12.

Additional inter-regional transmission capacity of 1200 MW by enhancing


transmission capacity of each of the Barh-Balia, Patna-Balia and Biharsharif-Balia
400kV quad D/C lines from 1200MW to 1600MW by provision of series compensation
and SVC in Northern region and Eastern regional system has also been planned.

2.3.7 765kV Transmission System

Existing 765kv transmission system at the beginning of 11th plan would be:
Table 2.4

765kV Transmission Lines


Anpara-Unnao (UPPCL) S/C ckm 409
Kishenpur-Moga L-1(W) S/C ckm 275
Kishenpur-Moga L-2(E) S/C ckm 287
Tehri-Meerut Line-1 S/C ckm 186
Tehri-Meerut Line-2 S/C ckm 184
Sipat-Seoni Line-1 S/C ckm 336
Sipat-Seoni Line-2 S/C ckm 336
Agra-Gwalior Line-1 S/C ckm 140
TOTAL ckm 2153
765kV Sub-stations 765/400kV
Sipat Generation 2x1000 MVA 2000
Seoni 2x1500 MVA 3000
TOTAL MVA 5000

Page 14 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

765kV transmission line and substation programme for the 11th Plan period is:

Table 2.5

765kV Transmission Lines ckm / MVA


Sasaram-Fatehpur S/C ckm 400
Fatehpur-Agra S/C ckm 330
Agra-Gwalior Line-2 S/C ckm 140
SipatPP-Seoni Line-3 S/C ckm 340
SipatPP-Sipat S/C ckm 30
Seoni-Bina S/C ckm 330
Seoni-Wardha Line-1 S/C ckm 210
Seoni-Wardha Line-2 S/C ckm 210
Gwalior-Bina Line-1 S/C ckm 300
Gwalior-Bina Line-2 S/C ckm 300
Sasaram-North K. Pura S/C ckm 180
North K. Pura-SipatPP S/C ckm 350
TOTAL 5273
765kV Sub-stations 765/400kV
Unnao (UPPCL) MVA 2000
Agra MVA 3000
Meerut MVA 3500
Fatehpur MVA 3000
Gwalior MVA 3000
Bina MVA 2000
Seoni 3rd transformer MVA 1500
Wardha MVA 4500
Sasaram MVA 2000
TOTAL 24500
* In State Sector (UPPCL)

2.3.8 HVDC Transmission System

HVDC Bi-Pole, Mono-Pole and Back-to-Back transmission at the beginning of 11th


Plan:
Table 2.6

ckm (2xroute MW
HVDC Bi-pole System km) Capacity
Chandrapur-Padghe(MSTCL) ± 500kV 1504 1500
Rihand-Dadri ± 500kV 1634 1500
Talcher-Kolar ± 500kV 2738 2500
TOTAL HVDC bi-pole 5876 5500
HVDC Monopole
Barsur-Lower Sileru 200kV 162 200
HVDC Back-to-back
Vindhachal 500

Page 15 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

Chandrapur 1000
Gazuwaka 1000
Sasaram 500
TOTAL back-to-back 3000

HVDC transmission system programme for the 11th Plan period is:

11th Plan Programme


ckm (2xroute MW
HVDC Bi-pole System km) Capacity
Balia-Bhiwadi ± 500kV 1800 2500
Biswanath-Siliguri-Agra ± 800kV 3600 6000
TOTAL 5400 8500

2.3.9 Inter-State Transmission Schemes – Status

All of the 11th plan inter-state transmission schemes to be commissioned by 2009


have already been firmed-up and are under execution. Most of schemes required by
2009-11 have also been evolved, discussed in the regional standing committees on
power system planning, firmed-up and are to be taken-up for execution so as to
complete and commission as per the target. However, a few transmission schemes,
particularly those required for evacuation system and regional system strengthening
schemes corresponding to those newly identified/uncertain generation projects where
execution/beneficiaries are yet be firmed-up are yet to be firmed-up. Process to firm-
up these remaining 11th plan transmission schemes which may be required for
completion towards the last years of the 11th plan is under way.

List of 11th Plan Inter-State Transmission Scheme is given at Appendix-2.8

2.3.10 Other Related Important Schemes in the Central Sector

¾ Load dispatch schemes for National and Regional dispatch centres


With integrated operation of all-India system, state of art load dispatch system
at the national level would need to be established. The regional level load
dispatch would also require up-gradation, both qualitative as well as
quantitative, to meet the requirement of growing size of the system and
emerging complexities of power system operation.

¾ Comprehensive upgrading of protection system for total integrated


system for security of National and Regional grids
A unified scheme covering comprehensive upgrading of protection system for
total integrated system is proposed under the 11th Plan programme. This
scheme to be taken-up in the Central sector for implementation by Power Grid
Corporation of India would provide for overhaul and upgrading of protection
system and equipment covering all the system elements including those in the
States' system, which have direct bearing on the security of the National and
Regional grids.

Page 16 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

¾ National Power Exchange System


For facilitation trading through double-sided bidding on a national platform
towards optimum utilization of generation resources, establishment of a Power
Exchange at National level is envisaged to be implemented during the early
years of 11th Plan.
th
¾ Evolving perspective transmission plan for the 12 Plan
With freer market system and number of merchant generation plants
increasing, transmission planning for the 12th Plan period would pose new
challenges. Transmission system would have to be evolved with much higher
uncertainty in projected generation-demand match-up scenario. Towards
meeting this challenge, it is proposed to take-up the transmission planning for
12th Plan as a planned scheme in which the system evolved by the in-house
expertise with in the country would be discussed with utilities of other
developed and fast developing countries and international experts before
firming-up the development program. In this scheme, software for Power
System Planning would also be upgraded to the state of art software.

¾ Augmentation of test facilities


Augmentation of facilities for testing of transmission equipment within the
country is needed for enabling timely procurement of reliable equipment in
transmission based on improved and tested designs.

2.3.11 Transmission System under State Sector

A well planned and reliable transmission system at the National and Regional level
would need to be complemented with development of matching transmission system
at 220kV and 132kV and also the sub-transmission and distribution system so as to
cater to the load growth and ensure proper utilisation of development in generation
and transmission facilities for the ultimate goal of delivery of the services up to the
end consumers in the country.

Inadequate development of sub-transmission and distribution system facilities in the


States of NER has been adversely affecting the reliability of power supply to the
consumers and also hampering the load growth in the region. The transmission, sub-
transmission and distribution systems of states require major strengthening/up-
gradation. Transmission lines that are under outage require speedy restoration for
bringing them into operation so that the states could avail their central sector shares
as well as utilize their own generation without any constraint.

Inadequacies in the transmission and distribution system had been on account of


slow implementation of schemes due to various factors such as time consumed in
E&F clearances, land acquisition, RoW constraints, fund limitation, organizational
difficulties of state utilities, lack of vendor response due to locational factors, law and
order, terrain specific difficulties, etc. Due to limited funding capabilities of state
utilities, most of the required transmission projects are generally funded by NEC or by
NLCPR under DONER and investment/funding approval of scheme so funded also
takes additional time. All these issues need to be addressed to achieve the
accelerated demand growth in NER.

Page 17 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

Transmission schemes for intra-state transmission system, load dispatch schemes


for state and area dispatch centres and schemes for upgrading of protection systems
for security of state grids are also required to be firmed-up by the state transmission
utilities.

Intra-state transmission schemes for evacuation of power from generation schemes


in the state sector are given at Appendix 2.9.

2.4 TECHNOLOGY DEVELOPMENT

2.4.1 Needs for Technology Development

Indian Power System is growing at a rapid pace with the mission to achieve “Power
to all by 2012”. For transfer of power from the generation resources to unevenly
distributed major load centres, Regional grids have been developed and integration
of all the five (5) Regional Grids to form a strong National Grid is also going on with
increasing pace. Today, National Grid of 11,500 MW inter-regional capacity is under
operation, which shall be enhanced to about 37150 MW by end of XI Plan i.e. 2011-
12. Except Southern Region, all the other four regions are now connected
synchronously, thus forming a 88 GW synchronous grid. To ensure secure and
reliable operation of the large integrated grid on a real time basis use of latest
technology and search and development of new technologies to inevitable. Five
regional load dispatch centres equipped with modern State-of-the-Art technology
along with dedicated communication facilities are in operation and work on a National
Load Dispatch centre is in progress.

Establishment and real time operation of large T&D infrastructure of present day
technology poses challenges for conservation of eco-sensitive Right of Way,
environment & forest, implementation time, automation of substation, project cost and
grid management. Therefore, it is necessary to modernize the power transmission
network by integrating latest technologies suitably into the development plan to
ensure maximum utilization of existing transmission infrastructure, provision of open
access, phase-wise generation development and implementation in a time bound
and cost effective manner.

2.4.2 Adopting New Technologies in Transmission System

New technologies should be adopted and implemented in a proactive manner to


achieve the objective of optimum utilization of the available transmission assets as
well as conservation of Right-of-Way, reducing transmission costs, reduction of
losses etc. Some of the new technologies adopted/being adopted in its transmission
system include:

• High capacity 6000MW +800kV HVDC system


• 765kV AC Transmission System
• Ultra High Voltage AC Transmission System(1000kV)
• Application of Series Compensation
• Flexible AC Transmission System (FACTS)
• Upgradation/Uprating of transmission line

Page 18 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

• High temperature endurance conductor


• Tall/Multi-circuit & Compact tower
• High Surge Impedance Loading Line (HSIL)
• Remote operation of substation, substation automation and Gas Insulated
substation (GIS)
• All Aluminium Alloy Conductors (AAAC) and Polymer/Composite Insulators.
• Development of disc insulators of 320kN & 420kN indigenously for both AC &
HVDC applications, as import substitution.
• Indigenous development of semi-conducting glazed insulators (Offering better
pollution performance)
• Introduced source/process inspection of equipment to ensure zero defect
• Airborne Laser Terrain Mapping (ALTM) for detailed route survey
• Thermo-vision scanning of the lines and sub-stations
• Conditional monitoring of equipment
• Preventive maintenance of Transformers using State-of-art Oil testing
laboratories set up by the company
• Emergency Restoration System (ERS)

For modernization of transmission system through latest technology integration, two


pronged strategies have been envisaged as under:

ƒ Enhance capacity and reliability of existing systems through:


ƒ Suitable technology for new systems keeping the long term perspective

2.4.3 Modernisation of Existing Transmission Infrastructure

To ensure maximum utilization of existing infrastructure, a number of technologies


have been implemented.

¾ Series compensation and facts


¾ Upgradation of lower voltage to higher voltage line
¾ Re-conductoring of transmission line
¾ Technology adoption for new transmission system
¾ Enhancement of conductor maximum temperature limits
¾ High capacity 400kV multi-conductor and 765kV system
¾ Compact towers
¾ High capacity HVDC system
¾ Ultra high voltage (1000kV) AC transmission system
¾ Modern line route survey technique
¾ Substation compaction, GIS, automation and remote operation
¾ High surge impedance loading line(HSIL)
¾ Fault current limiting reactor
¾ Grid operation and management
¾ Intelligent Grid
¾ Wide Area Monitoring System(WAMS)

Page 19 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

2.4.4 Search for New Technologies

New technologies are also needed to find solution to some the problems being faced
in the transmission system. Currently important issues are stability enhancement,
engineering and design for the next higher voltage, and reduction of right of way
requirement for transmission lines. FACTS and PSS tunings should be considered in
this context. The failure of extra high voltage transformers is also a matter of concern.
Power transformers and converter transformers have failed in large numbers in the
country and through appropriate research and development input, this is required to
be corrected.

2.4.5 Open Access

It is also important that the finances for the Transmission Schemes of the National
Grid are arranged at low cost so that required reliability and margins for open access
could be provided in the transmission system with in acceptable costs.

The evolved transmission system expansion plan provides sufficient transmission


capacities with inherent margins for trading transactions. This also meets the intra-
regional transmission needs. Taking-up the execution of the transmission schemes
for timely completion would depend on timely tie-up of pre-construction activities and
thereafter construction being ensured within specified time period. Agreement on the
proposal together with commercial tie-up for payment of transmission charges based
on long-term open access application becomes a critical issue in this context.

As the Merchant plants would basically be long term-user of the transmission system,
the transmission system for their connectivity and meeting their primary transmission
needs can be planned and taken-up for construction based on commitment for the
transmission charges by the developers of the Merchant plants. The process for long-
term open access application and tying-up the transmission schemes should be done
at the earliest as building the transmission system including obtaining necessary
approvals, pre-construction and construction/commissioning activities for the
transmission schemes require almost same time, if not more, as that for
implementation generation projects.

2.5 TRANSMISSION REQUIREMENTS FOR OPEN ACCESS AND TRADING

2.5.1 Assessment of Transmission Capacity Requirement

The focus of transmission system development programme for the XI Plan is to


provide adequate inter-regional and intra-regional transmission capacity so as to
consolidate and strengthen the National Grid network towards a strong All India Grid.
The inter-regional power exchange requirement has been assessed from possible
scenarios of regional surpluses and deficits for the peak and off-peak conditions of
winter, summer and monsoon months, and projections assessed. The projection
based on programme of generation and anticipated demand aims at estimating the
transmission requirement at the inter-regional level. Grid expansion plan evolved
based on this projection would be able to cater to the needs of various feasible

Page 20 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

operating scenarios and also provide required margins to support market oriented
power exchanges.

2.5.2 Transmission Capacity for Trading

The above method adopted for evolving the transmission system expansion plan
provides sufficient transmission capacities which would have inherent margins for
trading transactions. Transmission system implemented on the basis of the
expansion plan evolved in this manner would enable trading across the regional
boundaries towards optimal utilization of generation resources in the country for
ultimate benefit of the consumer. As the system is evolved based on extreme
dispatches, it would facilitate trading most of the time without congestion, and
occasionally, under outage contingencies or severe loading condition with some
degree of congestion which should be acceptable. Currently, trading is taking place
through short-term bilateral contracts. With introduction of Power Exchange at
National level, which is being envisaged to be in place in near future, trading would
also take place through Power Exchange which would be day ahead contracts. All
the short term as well as Power exchange transaction would need transmission
capacity which would come out of the spare capacity inbuilt in the transmission
system. The reliability and operational margins in the planned and implemented
transmission system corresponding to the committed long-term transmission needs
would provide the transmission capacity for trading of power.

2.5.3 Pre-construction tie-ups are Critical

The comprehensive transmission system evolved on national basis and also meeting
the intra-regional transmission needs, has been assigned under various schemes –
power evacuation schemes matching with generational capacity addition programme
and system strengthening schemes matching with anticipated growth in demand in
the various areas. Agreement on the proposal together with commercial tie-up for
payment of transmission charges based on long-term open access application
becomes a critical issue in this context.

Generation capacity used for trading transactions should have commitment for
long-term transmission charges

The short-term or Power exchange transactions may take place out of generation
capacities for which transmission system have been provided based on commitment
of long-term transmission charges to be paid either by the generator or by the
identified beneficiary having long-term PPAs from such generation. The short-term or
Power exchange transactions may also take place out of generation capacities for
which there is no commitment of long-term transmission charges. The transactions of
the second kind would reduce the reliability margins of the transmission system
provided based on long-term commitments. Inter-regional trading transactions out of
generation capacities for which transmission system is provided only in the region
where the generation is located and not in the region where the transacted power is
sold are also akin to the second kind for the importing region as well for the inter-
regional transmission. In a developing system, depletion or reduction of reliability of
the transmission system by generators intending to sell through short-term trading
without tying-up and committing for the transmission charges corresponding to their

Page 21 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

full requirement would be harmful. As such, it would be necessary that all generation
capacities intended to be utilization through trading transactions should provide
commitment for long-term transmission charges.

2.5.4 Transmission Charges for Short-Term Open Access

Levy of open access transmission charges at reduced rates would be justified for
short-term or Power exchange transactions of the first kind that is those taking place
out of such generation capacity for which long-term transmission charges have also
to be paid. However, levy of open access transmission charges at reduced rates may
not be justified for short-term or Power exchange transactions of the second kind,
that is those taking place out of such generation capacity which are created without
commitment for long-term transmission charges.

2.5.5 Transmission Capacity Margins

Transmission capacity through creation of additional transmission system could be


provided based on long-term commitment for the transmission charges. It has been
estimated that reliability and operation margins would be generally of the order of 25-
30% of the transmission capacities required for meeting the firm transmission needs
of the long-term committees. This level of redundancy would generally provide
sufficient margins for trading needs. However, it should be noted that short-term open
access (STOA) transactions operating on these margins, even if curtailable, cause
reduction in the security level. Therefore, unless margins are increased by design,
the system operator would have tendency to keep cushions by underestimating the
operational margins. As the system security is of paramount importance, creation of
increased margins by design becomes essential for accommodating STOA. This
involves costs which are in addition to the cost of incremental losses caused by
STOA. Both these costs should be recovered from STOA customers. Lesser
charges for STOA would dissuade long-term commitments for transmission
charges leading to retarded growth in transmission system.

2.5.6 Transmission System for Merchant Plants

Merchant plants would sell their power to customers who are not predetermined
through Power exchange contracts. However, they are long term-user of the
transmission system. The transmission system for the connectivity of the merchant
plant as well as for meeting their transmission needs is required to be planned and
built matching with the implementation of the merchant generation plant. Also, some
of the generation plants have only a part of their generation capacity tied-up in long-
term bi-lateral PPAs. When such plants seek long-term open access only for a part of
their full generation capacity, they inherently also seek connectivity for the remaining
capacity which would be available with them as a merchant plant capacity. As the
transmission system in both the cases would be required to be planned and
implemented corresponding to the full requirement, they are long-term beneficiary of
the transmission system. For proper planning and implementation of transmission
system, the merchant generators need to inform about region(s) in which they would
generally sell their power, so that transmission system requirement for evacuation of
their power and transmitting it to identified load centres could be assessed and any
additional capacity required could be planned. As building the identified transmission

Page 22 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

schemes including obtaining necessary approvals by the identified transmission


company /companies would generally require almost same time as that for
implementation generation projects, firming up of sellers and assessment of
transmission requirement should be started at the earliest.

2.5.7 Need for Revising Transmission Tariff Design

As, the merchant plants would not have long-term commitments for selling of their
power, a transmission tariff design is needed in which such generators could share
the transmission charges proportionate to their generation capacity. Also, there
is an urgent need for National concept in transmission tariff so as to address the
issue of high transmission charges in the North-eastern region as well enabling
expeditious development of long-haul inter-regional transmission corridors. However,
National pooled transmission tariff should not be on flat postage stamp method.

We know that the flat postage stamp method applied in the regional pooled
transmission tariff puts the load centric generation at a disadvantage, but is
acceptable in the regional system on account of its simplicity and generation
resources within the region being fairly dispersed and thus moderating the effect of
distortion. However, application of flat postage stamp method in National pool
tariff would totally distort the economics of load centric generation as the
physical disposition of generation resources in the country is quite uneven and the
transmission distances quite large. Also, the techno-economic considerations
highlight the need of directional sensitivity in transmission tariff design. A pragmatic
change in the transmission tariff design is needed so as to capture the sensitivity of
locating and dispatching the generation resources and give proper tariff signals
towards optimizing the choices. Zonal Matrix Transmission Tariff design suggested
by CEA should be considered in this context. Regulations for connectivity of
merchant generation capacity, transmission capacity of Power exchange and need
for new transmission tariff design are all related issues which seek a comprehensive
solution towards facilitation trading coupled with optimal choices in locating and
dispatching generation and also attracting investments in strengthening transmission
network that would be needed to top-up the system reliability effected by market
determined transactions.

2.6 POWER EXCHANGE WITH NEIGHBORING COUNTRIES

India has bilateral cooperation for power exchange with Nepal and Bhutan. The
terms of co-operations with Bhutan also includes development of hydro power
projects and power system in Bhutan which has fructified in accelerated
development of the projects in Bhutan. With other South Asian Nations, namely
Bangladesh, Pakistan, Myanmar, Thailand and Sri Lanka, discussions have been
held from time to time on possible road map for co-operation between the South
Asian Nations in the forum of SAARC and BIMSTEC initiatives. The discussions
have covered many areas including power. However, as yet, there is no agreed co-
operation for exchange of power with any other Nation except Bhutan and Nepal.

Page 23 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

2.6.1 India-Bhutan

India and Bhutan have terms of cooperation for development of hydro generation and
power system in Bhutan and power supply to India for mutual benefit of both the
countries. Hydro Projects at Chukha (336 MW), Kurichu (60 MW) and Tala
(1020MW) in Bhutan have been implemented with technical and financial assistance
of India. Transmission system for export from Bhutan to India has also been
developed with these hydro generation projects. The transmission system developed
with these projects is: 220 kV Chukha (Bhutan)-Birpara (India) (3 circuits) and 132 kV
Kurichu-Gelphu (Bhutan) – Bongaigaon/Salakati (India) (single circuit) lines.

Tala HEP (6x170 = 1020 MW) is also being implemented with Indian technical and
financial assistance. As the internal demand in Bhutan is much less as compared to
capacity of the generation projects, most of power from Tala HEP would also be
exported to India. Two nos. of 400 kV double circuit lines from Tala HEP (Bhutan) to
Siliguri (India) have been provided along with the generation project. The first unit of
170 MW at Tala HEP has been commissioned on 29.7.2006 and the other units are
being commissioned progressively and it is expected that all units at Tala HEP will
be commissioned by the end of this year.

Phunatsanchhu-I (1000MW), Phunatsanchhu-II (1000MW) and Mangdechhu


(600MW) hydro electric projects in Bhutan have also been envisaged to be
developed with Indian cooperation and investigation/DPR activities have been taken-
up. Comprehensive transmission system for power evacuation from these projects
have been tentatively evolved and would be firmed-up and developed in a phased
manner matching with phased development of the generation projects.
Commissioning of these projects is being tentatively programmed during 2011-14.
Power imported from these projects would be pooled at Siliguri and further
transmission to the stated of Northern region and Western region is planned through
HVDC system.

India also exports power to Bhutan during winter period when there is reduced hydro
generation in Bhutan.

Power import from Bhutan in the last 3-years is as under:

Year Total power import by India from


Bhutan (MU)
2003 1748
2004 1735
2005 1764

Following transmission lines are existing between India and Bhutan:

• 400kV 2xD/C Tala(Bhutan) – Siliguri(West Bengal, India)


• 220 kV,1xD/C, Chukha(Bhutan)-Birpara ( West Bengal, India)
• 220 kV,1xS/C, Chukha(Bhutan) -Birpara( West Bengal, India)
• 132 kV,1xS/C, Kurichu(Bhutan) -Gelephu(Bhutan)-Salakati
(Assam,India)

Page 24 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

• 33kV(operated at 11kV),1xS/C,Tamulpur(Bhutan)-Rangia(Assam, India)


• 11 kV, 1xS/C,Udalguri(Bhutan) -Daifam(Assam, India)
• 11 kV, 1xS/C,Banarhat(Bhutan) -Samtse(West Bengal, India)
• 11 kV, 1xS/C,Jaldhaka(Bhutan) - Sibsoo(West Bengal,India)

2.6.2 India-Nepal

India has terms of co-operation for exchange of power with Nepal. The inter-border
exchange of power between India and Nepal has been taking place for mutual
assistance in supplying to border areas of the two countries. Bilateral exchange of
power between India and Nepal is taking place since 1971, between contiguous
areas on the border of India and Nepal. These bilateral exchanges between India
and Nepal take place through various interconnecting lines at 11 kV, 33 kV and 132
kV between Nepal and the bordering States of India viz. Bihar, Uttaranchal and U.P.
The exchange of power between the two countries is taking place between Nepal
Electricity Authority (NEA) and U.P. Power Corporation Ltd (UPPCL), Uttaranchal
Power Corporation Ltd (UPCL), Bihar State Electricity Board (BSEB). Only Bihar has
bi-directional exchanges with Nepal. While UP and Uttaranchal only export power to
Nepal.

Quantum of power exchange between the bordering States of India and Nepal
during the last three years is the following:-

BSEB (Bihar)-NEA (Nepal)

Year Import from Nepal Export to Nepal


(MU) (MU)
2003 166 82
2004 102 131
2005 114 204

UPPCL (Uttar Pradesh, India NEA (Nepal)

Year Export to Nepal


(MU)
2002 15.5
2003 13.3
2004 6.1

Transmission lines between Nepal and Bordering States of India

BSEB(Bihar)- Nepal:

132kV Gandak- Ramnagar


132kV Bhantabri – Duhabi
132kV Gandak east – Gandak
33kV Bhadrapur – Thakurganj
33kV Birganj – Raxaul
33kV Kataiya – Biratnagar

Page 25 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

33kV Kataiya – Rajbiraj


33kV Sitamarhi – Jaleshwer
11kV Biratnagar – Jogbani
11kV Jainagar – Siraha
11kV Birgania – Gaur

UPPCL(UP)- Nepal:

33kV Pallia-Dhangarhi
33kV Itwa-Krishnanagar
33kV Anandnagar-Bhairwan
33kV Nanpara-Nepalganj
11kV Tulsipur-Koilabasa

UPCL(Uttaranchal)- Nepal:

33kV Lohiahead – Mahendranagar


11kV Pithoragarh – Baitadi
11kV Dharchula – Jaljibe
11kV Dharchula – Pipale

2.6.3 India-Pakistan

No transmission link is existing between India and Pakistan. During 1998-1999,


Government of India considered a proposal from Pakistan for export of power from
Pakistan to India. However, no progress was made as the talks got bogged down on
issues relating to tariff for power to be purchased from Pakistan.

2.6.4 India-Bangladesh

No transmission link is existing between India and Bangladesh. During 1997-98


proposal for exchange of power between India and Bangladesh was considered
under the aegis of ADB. Though couple of meetings was held in the past between
the two governments no progress/agreement has since then taken place.

2.6.5 India-Sri Lanka

No proposals have been formally discussed between the two countries. A study on
viability of inter-connection with Sri Lanka was carried out in 2002 by M/s Nexant
under USAID, SARI/E program. Recently, Nuclear Power Corporation of India
Limited has mooted a proposal for supply 400 MW to Sri Lanka for which HVDC
inter-connection has been proposed. However, there has been no discussion with Sri
Lanka on these proposals.

2.6.6 India-Myanmar

Talk of co-operation had been in reference to Tamanthi HEP (tentative 1200 MW) in
Myanmar from which power was also proposed to come to India.

Page 26 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

2.6.7 Formation of SAARC Grid

SAARC has number of technical committees to implement, coordinate and monitor


the programmes in their respective areas of co-operation. There is a technical
committee for co-operation on energy. First meeting of SAARC technical committee
was held in Dhaka on 17-18 Nov. 2002 in which various issues including possibility of
creation of regional power grid between India, Bhutan, Nepal and Bangladesh was
discussed. The Indian position in this regard was that creation and growth of cross
border transmission links depended on identification of commercially viable electricity
flows from generating stations to load centres. The flows through the Indian grid
could take place through displacement. The meeting recommended that the matter
might be discussed further between the countries of India, Nepal, Bhutan and
Bangladesh with a view to evolving suitable arrangements in that regard. No
progress/agreement has since then taken place.

2.6.8 BIMSTEC

BIMSTEC (Bay of Bengal Initiative for multi-sectoral technical & economic co-
operation) has members from Bangladesh, Bhutan, Nepal, Myanmar, India, Sri
Lanka, and Thailand. The first BIMSTEC Energy Ministers Conference was held in
New Delhi on 4th October 2005. Subsequently, a workshop on BIMSTEC Energy
Centre was held in New Delhi on 25-27 January, 2006 as per the agreed Plan of
Action for energy co-operation in BIMSTEC. The concept note on BIMSTEC Energy
Centre is under consideration. It is proposed that the India would be the host country
for the BIMSTEC Energy Centre. Draft MoU for the BIMSTEC grid interconnection
circulated during the task force meeting for BIMSTEC Power Exchange and
development Project held on 28-29th March’06 in Bangkok inter-alia included
principles and objectives, institutional arrangements which would form a framework
for the member countries to cooperate works towards the implementation of grid
interconnection for the trade in electricity in the BIMSTEC region. The next (second)
BIMSTEC Summit is likely to be held in February 2008.

2.7 RELIABILITY ISSUES AND GRID OPERATION

2.7.1 Planning for a Reliable Power System


The key to a reliable power system is made up of the following levers:

➢ Adequacy of the provisions with planned level of redundancies sufficient to


deliver the desired reliability
➢ Secured operation maintaining sufficient margins at all times so as to
maintain system loading within such limits that contingencies do not lead to
loss of system integrity
➢ Best practices in maintenance – both preventive as well as restorative

To facilitate orderly growth and development of the power sector and also for
secure and reliable operation of the grid, adequate margins in transmission
system should be created. A Reliable power system can be planned through
centralised planning of Regional and National grid systems coupled with
matching development in the State grid systems. This would require adequate

Page 27 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

and timely investments with coordinated action for implementing the schemes.
The needs are:
• Augmenting transmission capacity matching with generation additions
• Adequate redundancies as per specified criteria to provide the desired
reliability margins
• Development of transmission system for power evacuation as well as
system strengthening

11th Plan transmission plan/programme has been evolved meeting the above
requirement. Transmission capacities have been planned to cater to the
specified redundancy levels as per the planning criteria adopted in line with
international standards and practices.

The major highlights of transmission planning criteria in are:


➢ The transmission system planned in an integrated manner optimizing the
total network including that under the CTU as well as that for the STU(s).
➢ Criteria for mesh/loop network:
• 'N-1' adopted in general. 'N-2' adopted for transmission system from
large generating complex (3000 MW or above) and multi line
corridors (3 D/C lines or more), on case to case basis.
• In 'N-1' system adequacy without necessitating load shedding or
rescheduling of generation during steady state operation.
• In 'N-2' system adequacy without necessitating load shedding but
could be with rescheduling of generation during steady state
operation.
• 'N-1' withstand without necessitating load shedding or rescheduling
of generation during steady state operation –
• Outage of a 132kV D/C line, or
• Outage of a 220kV D/C line, or
• Outage of a 400kV S/C line, or
• Outage of single Interconnecting Transformer, or
• Outage of one pole of HVDC Bipole line, or
• Outage of a 765kV S/C line without series compensation.
• 'N-2' withstand without necessitating load shedding but could be with
rescheduling of generation during steady state operation -
• Outage of a 400kV S/C line with TCSC, or
• Outage of a 400kV D/C line, or
• Outage of both poles of HVDC Bipole line, or
• Outage of a 765kV S/C line.
• The above contingencies considered with a pre-contingency system
depletion (Planned Outage) of another 220kV D/C line or 400kV S/C
line in another corridor and not emanating from the same substation.
Operation of all the Generating Units within their reactive capability
curves and the network voltage profile within voltage limits specified.
➢ For requirement of reliability, planning criteria for evacuation system for
Nuclear power station is to consider outage of one circuit assuming pre-
contingency depletion of another circuit from the same station. This is
effectively N-2 without rescheduling but with no other pre-contingency.
➢ 'N-2' also for large cities with a power demand of 2000 MW or above

Page 28 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

➢ Inter-regional transmission capacity based on requirement arising on


account of regional variation in surpluses and deficits during the peak
and off-peak hours of different seasons viz.: Summer Peak Load;
Summer Off-peak Load; Winter Peak Load; Winter Off-peak Load;
Monsoon Peak Load; Monsoon Off-peak Load; Dispatch scenarios for
maximizing transfer in specific inter-regional corridors considered to
determine the adequacy of transmission system to take care of
requirement of regional diversity in inter-regional export / import.
Sensitivity in respect of generation dispatch or load demand causing
increased burden on transmission system considered.

2.7.2 Growth Objectives


A well planned and reliable transmission system will ensure not only optimal
utilization of transmission capacities but also of generation facilities and would
facilitate achieving ultimate objective of cost effective delivery of power.
Development of the transmission system thus planned would meet the
following objectives:

‹ Similar level of development of transmission system across the country


‹ Transmission system for optimally utilizing the hydro-thermal mix of
generation resources taking into account the concentration of coal in the
eastern part of the country and hydro power sources in the north - eastern
and northern parts of the country.
‹ Obtaining the advantages of diversity based exchanges of power; that is,
exchanges on account of regional variations in generation and demand
pattern arising due to geographical, seasonal, time of day and operational
diversities.
‹ Formation of National Power Grid that would enable exploitation of
unevenly distributed generation resources in the country to their optimum
potential. For the full utilization of the generating capacity in the eastern part
of the country, an adequate transmission system has been planned linking
the North-eastern and Eastern part of the country with the Northern,
Western Southern regions aiming that no generating capacity is rendered
idle due to transmission constraints.
‹ Continued development of Regional Grids so as to meet the transmission
needs within each of the regions catering to the power evacuation from
generation capacity additions and strengthening in the regional grids
addressing requirements of specific areas.
‹ Transmission system strengthening schemes to overcome the deficiencies
and provide a reliable transmission grid that has margins for open access
and also provides to cater to changes in the pattern of power flows for inter-
state transmission arising on account of capacity additions for intra-state
benefits.

2.7.3 Development Needed in State sector


A well planned and reliable transmission system at the National and Regional
level would need to be complemented with development of matching
transmission system at 220kV and 132kV and also the sub-transmission and
distribution system so as to cater to the load growth and ensure proper
utilisation of development in generation and transmission facilities for the

Page 29 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

ultimate goal of delivery of the services up to the end consumers in the


country.

2.7.4 Timely Implementation to Ensure Delivery of a Reliable Power System to


the System Operators
If the desired reliability is to be achieved, all the utilities, both in the Central
sector as well as State sector would need to ensure timely implementation of
the schemes. A task force under the chairmanship of Member (Power
Systems), CEA constituted by Ministry of Power, in its report of August 2005
has recommended the following:

(1) Parallel Processing of Activities


A transmission project involves various activities from concept to
commissioning. The Task Force observed that major reduction in project
implementation schedule is possible by undertaking various preparatory
activities (viz. surveys, design & testing, processing for forest & other
statutory clearances, tendering activities etc.) in advance/parallel to
project appraisal & approval phase and go ahead with construction
activities once Transmission Line Project sanction/approval is received.

(2) Packaging Concept


Total transmission project should be broken down to clearly defined
packages such that the packages could be procured & implemented
requiring least co-ordination & interfacing and at same time it attracts
competition facilitating cost effective procurement. The size & scope of
the different packages will therefore depend on magnitude & location of
project. However, the packages should be few and supply-cum-erection
type contracts should be preferred to avoid co-ordination problems. The
Task Force suggested typical packages for procurement / construction of
Transmission system.

(3) Standardization of Designs


To avoid repetitive work and uncertainties during testing, the tower
designs should be standardized. It is desirable that the designs are
standardized and development by Utilities prior to floating of tenders for
tower fabrication and construction so that 6-12 months or more time can
be saved in project execution. Standardization of designs/drawings for
other transmission line materials & substation structures, equipments,
control room building etc. also should be standardized to the extent
possible.

(4) Qualifying requirements for Vendors/Bidders


In order to select contractors of appropriate capability & capacity it is
required that Qualifying requirements in respect of technical resources,
financial capability, production capacity, tools & plants etc are stipulated
in bidding documents and contractors are selected accordingly.

(5) Bidding Document & Bidding Philosophy


The bidding documents should furnish all information necessary for a
prospective bidder to prepare a bid for the goods and works/services to

Page 30 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

be provided. The technical specifications and conditions of contract need


to be unambiguous. Considering volatility of the input cost, it is desirable
that contracts are invited with suitable price variation provisions such that
contract price is adjusted based on published indices of raw materials &
labour. Single stage bidding may be practiced for transmission line &
substation works with appropriate packaging and qualification
requirement.

(6) Route Alignment, Detailed Survey & Soil Investigations


It is desirable that the project is defined to finer details to the extent
possible at the FR / Notice Inviting Tender (NIT) stage for effective
planning and scheduling of project(s) besides optimization of resources.
New technology/ techniques such as use of satellite imagery, GPS, total
stations, computer-aided tower spotting etc. for getting realistic
information/details leading to selection of optimum route alignment and
facilitating realistic estimation of bill of quantities have been suggested.
To avoid large quantity variations during execution stage, which can be a
cause of dispute/delay, it would be desirable to carryout detailed survey
before NIT.

(7) Mechanization in Construction, Quality Management System etc.


Thrust is to be given towards use of new technologies & mechanized
means for construction of transmission projects to reduce time. Besides
implementation of standardized Manufacturing & Field Quality Plans,
utilities should also adopt prompt and transparent Inspection
Management System for smooth implementation of the project.

(8) Environment, Forest Clearance and Rehabilitation & Resettlement


(R&R)
Advance action should be taken for processing forest clearances. With
adoption of modern survey t9chniques, it is possible to minimize the
infringement with forest as various alternatives can be analyzed. It is also
helpful in convincing the concerned Authorities for expediting clearances,
as better evaluation of forest involvement is possible. It is also desirable
that Environment & Social Policy & Procedures (ESPP) are required to
be framed by utilities through consultative process. Such initiatives would
assist in settlement of R&R and environmental issues expeditiously and
avoid delays on this account.

(9) Vendor Development


A large number of projects would be taken up by many utilities
concurrently for construction due to the large transmission programme to
be implemented in limited time frame. It is, therefore, recommended that
active vendor development initiatives are to be taken by all utilities so that
indigenous capabilities are effectively developed and adequate supplier/
vendor base is created to have competitive prices and timely completion
of projects.

Page 31 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

(10) Project Monitoring


A master network for the entire project from concept to commissioning
need to be prepared and monitored regularly with reference to the target
and required actions are taken. Similar detailed network is also to be
prepared for each package for monitoring activities at micro level.
Regular reviews should be done at Project Manager level and quarterly
review at Chief Executive level also is recommended.

(11) Various aspects as brought out above were deliberated in depth by the
Task Force, however, project authorities need to review and adopt
depending upon the size nature, location and complexities of the project
on case-to-case basis. A reasonable time schedule for a specific project
is required to be tailor-made for each project element like transmission
line, substations, HVDC terminals etc. depending on its size, nature &
complexity. Further, in case of large projects where many such project
elements are involved, suitable time periods need to be provided for each
element and the overall project completion schedule is to be accordingly
decided.

2.7.5 Load Dispatch and Communication Facilities


The availability of adequate load dispatch and communication facilities is
necessary for the smooth interconnected operation of the power system. The
would require a full fledged National Load Dispatch Center apart from
upgrading the existing Regional Load Dispatch Centers and State Load
Dispatch Centers. For enabling him to operate the system in a secured and
reliable manner, the load dispatcher should be provided with state of art tools
equipped with required telemetry, communication, computerized real-time data
acquisition systems and necessary supervisory control facilities for efficient
operation of the power system. At the National level, practically all the system
starting from the functional specification, is to be developed picking the
telemetry from Regional systems and building all the application functions
needed for the National Load Dispatch Center. At the regional level though
considerable data acquisition and communication facilities have been created,
these are not yet sufficient for implementation of state of art functions such as
state-estimation/data validation, contingency evaluation, optimal load flow,
security margin estimation, etc. For improving the operational reliability while
utilising the system to its fullest potential, it is necessary to upgrade the
Regional load dispatch system to the state of art. At the state level there are
deficiencies in many cases which require to be quickly removed so as to
facilitate smooth integrated operation of the power system.

System reliability also depends on quick restoration following any


contingencies. In case there is partial or total system collapse, re-energisation
and restoration of the system would be possible in a short time only if
adequate load dispatch and communication facilities were available.

As there would be a large number of organizations whose power systems


would be connected in parallel efficient voice communication facilities would
also be needed between the load dispatch centers and the control rooms of
the various utilities. When Power exchange is put in place, necessary

Page 32 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

communication facilities linking the Power exchange and the National Load
Dispatch Center as well as Regional Load dispatch centers would also be
needed.

2.7.6 Protection System


Power systems operating in synchronism should be provided with adequate
defence measures such as islanding schemes and automatic load shedding
schemes, so that following major incidents in the system, the system could
continue to operate without cascade failure leading to black out in large areas.
The protection schemes for the transmission lines, transformers, bus bars,
generators and other important power equipments should be of the highest
quality and should be properly coordinated. In order to cater to contingencies
of loss of generation, under - frequency relays for load shedding (both flat
frequency relays and rate of change of frequency relays) should be provided
for shedding load automatically. Inter-regional flows should also be used for
triggering appropriate protective action. This would prevent distress in the
system from spreading. In case a part of the power system is under acute
distress, it should be isolated out automatically from the remaining healthy part
of the system in such a way that as much a part of the system as possible
continued to operate. With such schemes, procedures for reconnecting the
power systems in actual operation would also have to be devised. In this
regard, the international experience of operating vast power systems in
synchronism should also be drawn upon.

It has been noted that there would be heavy power flow from the north -
eastern and eastern parts of the country and the hydro-electric projects in the
northern part of the country to other parts of the country. With integration of
systems in synchronous mode creating combined system of large power
number, the parameters determining level of grid security have changed. The
variation in grid frequency has reduced and therefore, in integrated
NR/ER/NER/WR system the frequency of 49.5 is like the frequency of 49.0 of
the NR or WR system. Therefore under-frequency relays need to be reset at
higher frequency cut-offs and the system should be considered in Alert state at
those frequencies which were not so critical in earlier regional system
operation. Also, the inter-regional and inter-area tie-line flows have become
critical parameters for monitoring the security of the grid and the grid security
is now to be judged more by the power flows rather than frequency. The
system operators should therefore realign their strategies accordingly.

The synchronous interconnection has also thrown open a vast horizon of


operational opportunities for dispatch optimization utilizing inter-regional
diversities. There is paradigm shift in system operation requiring a new set of
practices and procedures for operational planning, scheduling, monitoring and
grid security etc. which have to evolve with consolidation of experience of
operating the large synchronously interconnected system.

2.7.7 Grid Operation and Management


In view the growing complexities and change in market mechanism, it is
necessary to continuously upgrade and modernize the Grid operation &
control and communication facilities to operate large grid on real-time basis

Page 33 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

dynamically with safety, security and reliability. Towards this, it is envisaged to


develop Intelligent Grid with State-of-the-art features like wide area
measurement, adoptive islanding, probabilistic assessment, Dynamic Stability
Assessment (DSA) & Voltage Stability Assessment (VSA) technique, self
healing grids etc. on a pilot scale.

2. 7.8 Best practices in Maintenance


The transmission utilities should maintain a high level of system availability
and at the base level of system availability by adopting best practices.
Emphasis should be given on both preventive as well as restorative
maintenance. Emphasis should also be give to R&M programme, Residual
Life Assessment and restoration efficiencies in Transmission.

2.8 FUND REQUIREMENT DURING 11TH PLAN FOR TRANSMISSION SYSTEM


DEVELOPMENT AND RELATED SCHEMES

2.8.1 Total Fund requirement for transmission system development and related
schemes has been estimated as following:

Rs Crore

Central Sector (Inter State Transmission System) 75000


State Sector (State Transmission System) 65000

TOTAL 140000

2.8.2 Fund Requirement during 11th Plan – Central sector schemes

Development of National and Regional grids and related systems would require
the following types of schemes:

¾ XI Plan Transmission Schemes for power evacuation and system


strengthening for Central sector generation capacity requiring inter-state
transmission

¾ Transmission schemes for IPP Generation Capacity seeking open access


from CTU for inter-state transmission

¾ Spill over expenditure of X Plan transmission schemes and advance action


for XII Plan transmission schemes

¾ Other related important schemes in Central sector

Fund requirement for above types of schemes during XI plan is estimated to be


as following:

Page 34 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

Rs Crores
Estimated Requirement
XI Plan Transmission Schemes for 44000 MW of Central 59200
sector generation capacity requiring inter-state
transmission
Transmission schemes for IPP Generation Capacity of 8000
6000MW seeking open access from CTU for inter-state
transmission
Spill over expenditure of X Plan transmission scheme And 7000
advance action for XII Plan transmission schemes
Total Central Sector Transmission Schemes 74200

Other related important schemes in the Central Sector

¾ Load dispatch schemes for National and Regional dispatch centres 500
¾ Comprehensive upgrading of protection system for total integrated 200
system for security of National and Regional grids
¾ National Power Exchange System 50
th
¾ Evolving perspective transmission plan for the 12 Plan 10
¾ Augmentation of test facilities 40
¾ Total other related important schemes in Central Sector 800

¾ Total Central Sector 75000

2.8.3 Fund Requirement during XI Plan – State Sector Schemes

Development of State grids and related systems would require the following types of
schemes:

¾ XI Plan Transmission Schemes of STUs for evacuation of state sector


generation including intra-state open access to IPP Generation in state sector
¾ STUs transmission schemes at 220kV, 132kV and 66kV to meet the
transmission needs of growth in demand
¾ Spill over expenditure of X Plan transmission scheme and advance action for
XII Plan transmission schemes
¾ Other related important schemes in the State sector for Renovation and
modernization of aging transmission system, State/Area load dispatch system,
Protection system up-gradation, and Software for planning and management
information system.

Fund requirement for above types of schemes during XI plan is estimated to be as


following:

Page 35 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

Rs Crore
Estimated Requirement
XI Plan Transmission Schemes for 16000 MW of State 14400
sector and IPP generation capacity requiring intra-state
transmission.
STU transmission schemes at 220kV, 132kV and 66kV to 28800
meet the transmission needs of growth in demand.
(State-wise details of normative assessment is given at
Appendix 2.10)
Transmission schemes for 220kV, 132kV and 66kV 6000
system in states of Assam, Nagaland, Bihar, Jharkhand,
Goa and Uttar Pradesh for strengthening of transmission
system in these states so that these states may cater to a
demand level of at least 50% of National average.
(Details of this assessment is also given in Appendix 2.10)
Spill over expenditure of X Plan transmission scheme and 7800
advance expenditure on XII Plan transmission scheme
Other related important schemes in the State sector for 8000
Renovation and modernization of aging transmission
system, State/Area load dispatch system, Protection
system up-gradation, and Software for planning and
management information
Total State Sector Transmission Schemes 65000
Total 1,40,000

**********

Page 36 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

Appendix-2.1

HVDC Transmission Bipole, Back-to-back and Monopole lines and terminal


station – Existing at the end of 9th Plan and programme for 10th Plan 2002-07

As at the
As at the end of
end of 9th 10th Plan
Plan i.e. 2002- 2003- 2004- 2005- 2006- i.e.
3/2002 03 04 05 06 07 3/2007
HVDC Bipole Line
Chnadrapur-Padghe ± 500kV MSEB ckm 1504 1504
Rihand-Dadri ± 500kV PGCIL ckm 1634 1634
Talcher-Kolar ± 500kV PGCIL ckm 2738 2738
TOTAL 3138 2738 0 0 0 0 5876

HVDC Bi-pole
Transmission Capacity
Chnadrapur-Padghe bipole MSEB MW 1500 1500
Rihand-Dadri bipole PGCIL MW 1500 1500
Talcher-Kolar bipole PGCIL MW 1000 1000 500 2500
TOTAL 3000 1000 1000 0 0 500 5500

HVDC Back-to-back
Transmission Capacity
Vindhachal b-t-b PGCIL MW 500 500
Chandrapur b-t-b PGCIL MW 1000 1000
Gazuwaka b-t-b PGCIL MW 500 500 1000
Sasaram b-t-b PGCIL MW 500 500
TOTAL 2000 500 0 500 0 0 3000

HVDC Monopole Line


CSEB/
APTRAN
Barsur-Lower Sileru 200kV SCO ckm 162 162
TOTAL 162 0 0 0 0 0 162

HVDC Mono-pole
Transmission Capacity
CSEB/
Mono- APTRAN
Barsur-Lower Sileru pole SCO MW 200 200
TOTAL 200 0 0 0 0 0 200

Page 37 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

Appendix-2.2

Transmission lines and sub-station at 765kV – Existing at the end of 9th Plan
and programme for 10th Plan 2002-07

As at the As at the
end of end of
9th Plan 10th Plan
i.e. 2002- 2003- 2004- 2005- 2006- i.e.
3/2002 03 04 05 06 07 3/2007
765kV Transmission Lines
Anpara-Unnao S/C UPPCL ckm 409 409
Kishenpur-Moga L-1(W) S/C PGCIL ckm 275 275
Kishenpur-Moga L-2(E) S/C PGCIL ckm 287 287
Tehri-Meerut Line-1 S/C PGCIL ckm 186 186
Tehri-Meerut Line-2 S/C PGCIL ckm 184 184
Agra-Gwalior Line-1 S/C PGCIL ckm 140 140
Sipat-Seoni Line-1 S/C PGCIL ckm 336 336
Sipat-Seoni Line-2 S/C PGCIL ckm 336 336
TOTAL 971 0 0 0 186 996 2153

765kV Sub-stations
(765/400kV)
Seoni PGCIL MVA 3000 3000
Sipat PGCIL MVA 2000 2000
TOTAL 5000 5000

Page 38 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

Appendix-2.3

Northern Region

In Northern Region following inter-state transmission schemes have been planned


and are under execution for benefit during X plan.

S. Name of Scheme Scheme Description


N.
1. Series Comp + TCSC on In this scheme 40 % fixed series compensation and 15 %
Kanpur-Ballabhgarh 400kV S/C variable compensation is proposed on Kanpur-Ballabhgarh
400 kV S/C line. This would increase the power transfer
capability from Eastern to Western part of Northern Grid
and improve stability of Northern Grid.
2. System Strengthening in a) Opening of existing 400 kV line between
Singrauli-Vindhyachal corridor Vindhyachal-Kanpur at Vindhyachal end and
connecting it to Singrauli end so as to form Singrauli-
Kanpur 400 kV S/C (3rd ckt)
b) Singrauli-Vindhyachal 400 kV S/C (2nd ckt) to utilize
the vacant bay as created above
3. Transmission system a) Dhauli Ganga- Bareilly 400 kV D/C (initially operated
associated with Dhauli Ganga at 220 kV)
4. Northern Region System a) Kanpur-Auraiya 400 D/C
strengthening scheme-I b) Bareilly Switching station of PG, 400kV
c) LILO of Lucknow-Moradabad 400 kV S/C at Bareilly
(PG)
d) LILO of Bareilly-Mandola 400kV D/C at Bareilly (PG)
2xD/C
e) Bareilly (PG)-Moradabad 400kV S/C
f) LILO of Sultanpur-Lucknow 400kV S/C at Lucknow
PG
5. Northern Region System a) Fixed series compensation of 40% on Allahabad-
strengthening scheme-II Mainpuri 400 kV D/C line designed for 95oC
b) Agra-Jaipur 400 kV DC
c) Wagoora 400/220 kV, 3rd transformer
6. Transmission system a) Dulhasti-Kishenpur 400 kV S/C
associated with Dulhasti b) Kishenpur-Wagoora 400 kV D/C
c) Kishenpur 315 MVA 400/220 kV S/S

Page 39 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

S. Name of Scheme Scheme Description


N.
7. Transmission system a) Rihand-Allahabad 400 kV D/C
associated with Rihand-II b) Dadri - Panipat 400 kV S/C - 2nd ckt
c) Patiala- Malerkotla 400 kV S/C
d) LILO of 400 kV Nalagarh -Hissar one Ckt at Kaithal
S/S
e) LILO of 400 kV Nalagarh -Hissar one Ckt at Patiala
S/S
f) Rihand- Mainpuri-Ballabgarh 400 kV D/C
g) Kaithal 630 MVA 400/220 kV S/S
h) Patiala 630 MVA 400/220 kV S/S
i) Mainpuri 315 MVA 400/220 kV S/S (Aug.)
j) Abdullapur 315 MVA 400/220 kV S/S 3rd ICT (Aug.)
8. Northern Region System a) Malerkotla – Ludhiana-Jullundhar 400kV S/C
strengthening scheme-III b) LILO of one ckt Moga-Hissar 400kV D/C
c) Ludhiana 400/220kV S/, 2x315 MVA
d) Fatehabad 400/220kV S/, 2x315 MVA

9. Transmission system a) Sewa -Hiranagar 132 kV D/C


associated with Sewa-II b) Sewa - Khatua 132 kV via Mahanpur
10. Transmission system a) Parbati-Nalagarh 400 kV 2xS/C (Quad)
associated with Parbati-II
11. Transmission system
a) Koteshwar-Tehri PoolingPoint 400 kV D/C line
associated with Koteshwar b) LILO of Tehri-Meerut at Tehri PP
c) Series comp. of 50% on TehriPP-Meerut 2xS/C
d) Tehri GIS Pooling Station
12. Northern Region System a) Provision of SVC support in NR system. (Total
strengthening scheme-IV quantum of compensation, their size and location
would be identified after further studies.)
13. Transmission system a) RAPP-Kankroli 400 kV D/C
associated with RAPP-5&6 b) RAPP-Kota 400 kV S/C
c) Kota 400/220 kV 3x250 MVA S/S
d) Kankroli 400/220 kV 3x315 MVA S/S
14. Northern Region System a) LILO of 400 kV Hissar-Jaipur at Bhiwadi
strengthening scheme-V b) Bhiwadi-Agra 400kV D/C
c) Bhiwadi-Moga 400kV D/C
15. System strengthening in a) Establishment of Roorkee 1x315 MVA 400/220 kV
Roorkee S/S by LILO of Rishikesh- Muzaffarpur S/C line at
Roorkee S/S
16. Additional transformers at Moga a) Moga 400/220 kV 1x250 MVA (Aug) 3rd transformer
and Amritsar b) Amritsar 400/220 kV 1x315 MVA (Aug) 3rd
transformer

Page 40 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

S. Name of Scheme Scheme Description


N.
17. Tala Transmission System for a) Gorakhpur-Lucknow (new) 400 kV D/C
NR b) Lucknow (New)-Unnao 400 kV D/C
c) Bareilly- Mandola 400 kV D/C
d) LILO of 400 kV Dadri-Samaypur D/C line at Maharani
Bagh-2xD/C
e) Gorakhpur (new)-Gorakhpur (UP) interconnection
400 kV D/C
f) Gorakhpur 1x315 MVA 400/220 kV S/S (new) with
2x63 MVAR L/R
g) New Lucknow 1x315 MVA 400/220 kV S/S(new)
h) Maharani Bagh 2x315 MVA 400/220 kV S/S (new)
18. Tala Supplementary a) Jullandhar-Amritsar 400kV S/C line and 400/220kV
Transmission System in NR 1x315 MVA s/s at Amritsar
b) Bahadurgarh 400/220kV 1x315 MVA s/s by LILO of
Bawana-Bhiwani 400kV line
c) 2nd 315 MVA 400/220kV transfrmr at Gorakhpur
19. Supplementary Transmission a) Kota-Merta 400 kV D/C
system associated with RAPP- b) Kankroli-Jodhpur 400 kV S/C
5&6
20. Associated Tr. System of a) Balia-Mau 400 kV D/C
Kahalgaon-II Phase-I(2x500 b) Balia-Lucknow (PG) 400 kV D/C with ser cap
MW) and Phase-II (1x500 MW) c) Lucknow (PG)-Bareilly (PG) 400 kV D/C.
in NR

Page 41 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

Appendix-2.4

Western Region

In Western Region following inter-state transmission schemes have been planned


and are under execution for benefit during X plan.

S. N. Name of Scheme Description


1. Associated Transmission a) Tarapur-Boisar 400kV D/C
System of TAPP 3&4 b) TAPP(Extn.)-Boisar 220kV S/C (For start up power)
c) Tarapur-Padghe 400kV D/C
d) LILO of Gandhar-Padghe 400 kV S/C at Vapi (PG)
e) LILO of Gandhar-Padghe 400 kV S/C at Boisar (PG)
f) Vapi (PG) 2x315 MVA 400/220 kV S/S
g) Boisar (PG) 2x315 MVA 400/220 kV S/S
2. Raipur-Bhadrawati 400kV D/C a) Raipur-Bhadrawati 400 kV D/C
3. Bhadrawati-Chandrapur 400kV a) Bhadrawati-Chandrapur 400kV D/C
D/C
4. Associated Tr. System of a) Vindhyachal-Satna-Bina 400 kV D/C
Vindhyachal-III (2x500 MW) b) LILO of both ckts of Rourkela-Raipur 400 kV D/C line
at Raigarh
c) LILO of both ckts of Satna-Bina (MPSEB) 400 kV
D/C line at Bina (PG)
d) Raigarh 2x315 MVA 400/220 kV S/S
e) Bina (PG) 400/220kV Switching sub-station
5. Vindhyachal-Korba 400 kV S/C a) Vindhyachal-Korba 400 kV S/C line (2nd ckt.)
line (2nd ckt.)
6. Bina-Nagda 400 kV D/C line a) Bina-Nagda 400 kV D/C line
7. Associated Tr. System of Sipat-I a) Sipat-Seoni 765 kV 2X S/C
(3x660 MW) b) Seoni-Khandwa 400 kV D/C (Quad AAAC)
c) Nagda-Dehgam 400 kV D/C
d) LILO of Korba-Raipur at Sipat 400 kV D/C
e) LILO of Satpura-Bhilai at Seoni 400 kV D/C
f) LILO of both ckts of S. Sarover-Nagda 400 kV D/C
line at Rajgarh
g) Seoni 7x500 MVA 765/400 kV and 2x315 MVA
400/220 kV S/S
h) Rajgarh 2x315 MVA 400/220 kV S/S
8. Associated Tr. System of Sipat- a) Khandwa-Rajgarh 400 kV D/C
II (2x500 MW) b) Bina-Gwalior 765 kV S/C (initially op. at 400 kV)
c) Seoni 765/400 kV 3x500 MVA (Aug.)
d) LILO of 400 kV Korba-Raipur 400 kV line at
Bhatapara.
e) Bhatapara 2x315 MVA 400/220 kV S/S
9. Sipat-Raipur 400 kV D/C line a) Sipat-Raipur 400 kV D/C

Page 42 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

S. N. Name of Scheme Description


10. Transmission System a) Gandhar (NTPC)-Rajkot (GEB) 400 kV D/C
associated with Gandhar-II b) Gandhar (NTPC)-Kawas 400 kV D/C
(1350 MW) c) LILO of both circuits of Bina-Nagda 400 kV D/C line
at Shujalpur
d) Establishment of 2x315 MVA 400/220 kV substation
at Shujalpur
11. Transmission System a) Kawas-II-Vapi (PG) 400 kV D/C Quad
associated with Kawas-II (1350 b) Vapi (PG)- Navi Mumbai 400 kV D/C
MW) c) LILO of Lonikhand – Kalwa 400 kV S/C line at Navi
Mumbai,
d) Vapi (PG)-Khadoli (DNH) 220 kV D/C
e) Establishment of 400/220 kV 2x315 MVA S/S at Navi
Mumbai (GIS in case adequate land is not available).
f) LILO of Apta-Kalwa and Kharghar-Kandalgaon 220
kV D/C lines at Navi Mumbai. (LILO works under
preview of MSEB, 220 kV bay provision at Navi
Mumbai by PGCIL)
g) Installation of 400/220 kV 1x315 MVA 3rd transformer
at Vapi
12. To provide direct linkage to DNH Construction of multi circuit 2xD/C line between Vapi (PG)
and Daman & Diu from regional and line alignment of the 220 kV lines from Bhilad-
Vapi 400/220 kV s/s. Kharadpada & Bhilad-Magarwada thereby creating Vapi
(PG)–Magarwada 220 kV D/C and Vapi (PG)–
Kharadpada 220 kV D/C line by bypassing both the lines
at Bhilad.
13. Sipat-II Supplementary a) Seoni-Wardha, 765kV S/C line (initially op. at 400kV)
Transmission Scheme b) Wardha-Akola, 400kV D/C line
c) Akola-Aurangabad, 400kV D/C

Page 43 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

Appendix-2.5

Southern Region

In Southern Region following inter-state transmission schemes have been planned


and are under execution during X plan.

S. N. Name of Scheme Description


1. Talcher-II evacuation System in a) Kolar-Hoody 400kV D/C
SR that is 40okV System for b) Kolar-Chennai(SPBudur) 400kV S/C
power dispersal from Kolar c) Kolar-Hosur-Salem 400kV S/C
d) Salem-Udumalpet 400kV S/C
e) LILO of Cuddapah-Somanhalli at Kolar
f) 400kV s/s at Hosur 2x315 MVA
g) 400kV Kolar s/s 2x315MVA
2. Series Comp on Nagarjuna a) 50% series compensation on both the circuits of
Sagar-Cuddapah and Gooty- Gooty-Bangalore 400 kV 2xS/C and Nagarjuna
Neelnamangla 400 kV lines Sagar-Cuddapah 400 kV D/C
3. Kaiga-Narendra 400 kV D/C a) Kaiga-Narendra 400 kV D/C
4. Establishment of Narendra a) Establishment of 2x315 MVA 400/220 kV S/S at
400/220 kV S/S Narendra
5. Southern Region System a) LILO of Nagarjunasagar-Raichur 400 kV S/C line at
strengthening scheme-IV Mehboobnagar
b) LILO of both the circuits of Nellore-Sriprumbudur 400
kV D/C line at Alamatti 400kV S/S
6. Neelamangla-Mysore a) Neelamangala-Mysore 400 kV D/C line
transmission system b) Mysore 2x315MVA 400/220 kV S/S
7. Madurai-Thiruvananthapuram a) Madurai-Thiruvananthapuram 400 kV D/C line
b) Thiruvananthapuram 400/220kV 2x315MVA
substation
8. Transmission system a) Ramagundam-Hyderabad 400kV D/C line
associated with Ramagundam- b) Hyderabad-Kurnool-Gooty 400kV S/C line
III c) Khammam-Nagarjunasagar 400kV S/C line
d) Gooty-Neelamangala 400kV S/C line
9. Southern Region System a) Augmentation of Transformer capacity by 1x315
strengthening scheme-V MVA at Munirabad, Cuddapah, Gooty, Khammam,
Gazuwaka and 3x167 MVA at Kolar 400 kV
Substations
b) 1x80 MVAR Bus reactor at Nellore 400kV S/S
10. Southern Region System a) Raichur-Gooty 400 kV D/C (Quad) line
strengthening scheme-III b) Neelamangala- Somanahaly 400 kV D/C
11. Southern Region System a) LILO of both the circuits of Gazuwaka-Vijayawada
strengthening scheme-VI 400kV D/C line at Vemagiri 400 kV S/S
b) 2nd 1x315 MVA 400/220kV Transformer at
Vijayawada

Page 44 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

Appendix-2.6

Eastern Region

In Eastern Region following inter-state transmission schemes have been planned and
are under execution during X plan.

S. N. Name of Scheme Description


1. LILO of Silliguri-Gangtok 132 kV a) LILO of one ckt of Silliguri-Gangtok 132 kV D/C line at
line at Melli Melli
2. Installation of 2nd ICT at a) Indravati 1x315 MVA 400/220 kV 2nd Trf. (Aug.)
Indravati OHPC
3. LILO of Rangit-Silliguri at a) LILO of one ckt of 132 kV Rangit-Silliguri at Gangtok
Gangtok
4. Tala Transmission System (ER) a) Bhutan border to Siliguri 400kV 2xD/C
b) Siliguri-Purnia 400kV quad D/C
c) Purnia-Muzzafpur 400kV quad D/C
d) Muzaffarpur 400kV s/s with inter-connection to 220kV
s/s
5. Transmission system associated e) Teesta-Silliguri 400 kV D/C
with Teesta-V
6. Tala Supplementary Scheme for a) Biharsharif – Muzaffarpur 400kV D/C-129km
ER b) 2x315 MVA, 400/220kV S/S at Subhasgram
c) 2nd 315 MVA, 400/220kV ICT at Siliguri
7. Associated Tr. System of a) Kahalgaon-Patna 400 kV D/C quad
Kahalgaon-II Phase-I(2x500 b) Maithon (PG)-Ranchi 400 kV D/C
MW) and Phase-II (1x500 MW) c) 2x315 MVA 400/220 kV Patna s/s
in ER d) 2x315 MVA 400/220 kV Ranchi s/s

Page 45 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

Appendix-2.7
Inter-Regional Schemes

The following inter-regional transmission schemes have been planned and have
been commissioned and/or are under execution during X plan.

S. Name of Scheme Description Status


N.
1. ER-WR a) Rourkela-Raipur 400kV D/C completed
interconnection b) TCSC on Rourkela-Raipur 400kV D/C
2. ER-NR a) Sasaram HVDC back-to back 500MW completed
interconnection b) Biharsharif-Sasaram 400kV D/C
c) Sasaram-Allahabad 400kV D/C
3. Talcher-II a) Talcher-Kolar 2000 MW HVDC bi-pole line completed
evacuation System b) Increasing capacity of Talcher-Kolar HVDc bi-
pole line from 2000MW to 2500MW
4. ER-SR link a) Second 500MW HVDC back-to back at completed
strengthening Gazuwaka
b) b) Series Capacitors on 400kV lines in ER for
increasing transmission capacity to
Gazuwaka
5. ER-NR inter- a) Muzaffarpur-Gorakhpur 400kV quad D/C with completed
connector with Tala TCSC
Transmission
System
6. Associated Tr. a) Patna-Balia 400kV D/C quad Under
System of b) Biharsharif-Balia 400kV D/C quad construction
Kahalgaon-II c) Ranchi-Sipat 400 kV D/C with 40 % series
Phase-I(2x500 MW) compensation
and Phase-II (1x500 d) Agra-Gwalior 765 kV S/C (initially op. at 400
MW) kV)

Page 46 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

Appendix-2.8

INTER-STATE TRANSMISSION SCHEMES FOR THE XI PLAN

Region Scheme/ scheme group Transmission system


NR EVACUATION SYSTEM FOR TRANSMISSION SYSTEM FOR KOLDAM
KOLDAM (800 MW), PARBATI- 1. Koldam-Nalagarh 400 kV D/C Quad.
II (800 MW) AND PARBATI-III 2. Koldam-Ludhiana 400 kV D/C line
(520 MW)
TRANSMISSION SYSTEM FOR PARBATI II
1. Parbati II - Koldam 400 kV S/C (quad) 1st ckt
2. Parbati II to Koldam 400 kV S/C (quad) 2nd ckt
3. Opening of one ckt Koldam-Nalagarh 400 kV D/C
line at Koldam and joining with Parbati II-Koldam 2nd
ckt so as to form i) Parbati II-Nalagarh 400 kV S/C
line ii) Parbati II-Koldam 400 kV S/C line

TRANSMISSION SYSTEM FOR PARBATI III


1. LILO of Parbati II-Koldam 400 kV S/C line at Parbati
III
2. Establishment of switching station at Panarsa by
LILO of Parbati II – Nalagarh 400 kV line and by
LILO of Parbati III-Koldam 400 kV S/C line at
Panarsa
3. Panarsa-Amritsar 400 kV D/C line
NR Evacuation System for 1. CREATION OF 400/220 KV POOLING STATION
Chamera- III (231 MW) NEAR HAMIRPUR
2. Chamera III-Chamera Pooling Station 220 kV D/C
line
3. Chamera Pooling Station-Jullundur 400 kV D/C line
NR Evacuation System for Uri-II 1. URI-I- URI-II 400 KV S/C
HEP (240 MW) 2. Uri-II-Wagoora 400 kV S/C line
NR Evacuation System for Rampur 1. LILO of Nathpa Jhakri - Nalagarh 400 kV D/C at
HEP (434 MW) Rampur HEP
2. Ludhiana - Patiala 400 kV D/C
3. LILO of Patiala -Hissar 400 kV line at Kaithal
4. LILO of Nalagarh - Kaithal 400 kV line at Patiiala

Page 47 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

NR Evacuation System for Tehri With Koteshwar


PSS (1000 MW) & Koteshwar 1. Establishment of 400kV GIS Tehri Pooling Station
(400 MW), Lohari Nagpala HEP 2. LILO of Tehri – Meerut 765kV at Tehri Pooling Point
(600 MW) 3. Koteshwar – Tehri Pooling Point , 400kV D/C line
4. Series Compensation 50 % on the Tehri – Meerut
765kV 2xS/C lines (charged at 400kV)

WITH TEHRI PSS


1. TEHRI – TEHRI POOLING STATION, 400KV S/C
(QUAD) LINE
2. LILO OF BAREILLY – MANDAULA 400KV D/C LINE
AT 400KV MEERUT S/S
3. Charging Tehri Pooling Stn – Meerut line at 765kV
4. Tehri Pooliong Station (GIS) 765/400kV ,
3x1500MVA
5. Meerut S/S (GIS) 765/400kV, 3x1500MVA
6. Modification of Series capacitors on the Tehri-Meerut
lines for 765kV operation

With Lohari Nagpala


1. Lohari Nagpala HEP – Tehri/Koteshwar Pooling Point
400kV D/C line (triple moose)
2. Meerut – Agra 765kV S/C line
3. Second 765/400kV transformer at Agra 765kV S/S
NR Evacuation System for Tapovan 1. Tapovan Vishnugad – Roorkee 400kv D/C line (the
Vishnugad HEP (520 MW) line to be routed via Kuwari Pass where a 400/132kV
pooling station is proposed)
NR Evacuation System for RAPP U 1. Rapp – kankroli 400kv d/c line
5&6 APP (440 MW) 2. Rapp – kota 400kv s/c line
3. Kota 400/220kv s/s 2x315 mva
4. Kankroli 400/220kv s/s, 3x315 mva
Supplementary regional schemes to match with RAPP
5&6
1. Kota – Merta 400kV D/C line
2. Kankroli – Jodhpur 400kV S/C line
NR Evacuation System for Sewa-II 1. Sewa-Hira Nagar 132 kV D/C
(120 MW) 2. Sewa-Khatua 132 kV D/C one ckt via Mahanpur
NR Evacuation System for Nimboo 1. Nimboo Bazgo-Leh 33 KV 2XD/C
Bazgo (45 MW)
NR Evacuation System for Chutak 1. Chutak-Kargil 33 KV 2XD/C
(44 MW)
NR Evacuation System for Lakhwar 1. Lakhwar Vyasi-Dehradun 220 KV D/C
Vyasi (420 MW)

Page 48 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

NR Evacuation System for Kotlibhel With Kotlibhel ST-IA


st-IA (195 MW), Kotlibhel st-IB 1. LILO Kotlibhel-ST1B-Roorkee 1st CKT at Kotlibhel-
(320 MW), Kotlibhel st-II (440 ST1A 400 KV D/C
MW),
With Kotlibhel ST-IB
1. Kotlibhel-ST1B-Roorkee 400 KV D/C

With Kotlibhel ST-II


1. LILO Kotlibhel-st1B-Roorkee 2nd ckt at Kotlibhel-st
II 400 kV D/C

NR Evacuation System for 1. LILO one ckt Kuwari Pass-Pithoragarh line at


Vishnugarh Pipalkoti (400 MW) Vishnugarh Pipalkoti 400 kV D/C

NR Evacuation System for Lata 1. LILO of one ckt of Vishnuprayag-Muzzaffar Nagar


Tapovan (162 MW) D/C line at Kunwari Pass 400 kV D/C
2. Lata Tapovan-Kunwari Pass 220 kV D/C
NR Evacuation System for 1. Barsingsar-Nagaur 220 kV 2xS/C
Barsinghsar (250 MW) & 2. Barsingsar-Phalodi 220 kV S/C
Barsinghsar Extn. 250 MW 3. Barsingsar-Bikaner 220 kV S/C
NR Northern Region System 1. Establishment of 400/220 kV 2x315 MVA GIS at
Strengthening -VI Gurgaon by LILO of Samaypur-Bhiwadi 400 kV S/C
line
NR Northern Region System 1. Augmentation of Ludhiana S/S by 3rd 315 MVA
Strengthening -VII transformer
2. Augmentation of Wagoora S/S by 4th 315 MVA
transformer
NR Northern Region System 1. Establishment of 400/220 kV 2x315 MVA S/S at
Strengthening -VIII Bhinmal by LILO of both ckts of Kankorli-Zerdai 400
kV D/C line
2. Augmentation of Hissar S/S by 3rd 315 MVA
transformer
NR Northern Region System 1. Establishment of 400/220 kV S/S at Roorkee by
Strengthening -IX LILO of Rishikesh-Muradnagar 400 kV S/C
2. Opening of Roorkee-Muzzaffarnagar portion of
Roorkee-Muradnagar line from location near
Muzzaffarnagar and extending it to Meerut so as to
form Roorkee-Meerut 400 kV S/C line and Meerut-
Muzzaffarnagar S/C line (under Tehri stage-I)
NR Northern Region System 1. Kankroli-Jodhpur 400 kV S/C
Strengthening -X 2. Kota-Merta 400 kV D/C

NR Northern Region System 1. 400/220 kV 315 MVA 3rd Trf. at Amritsar (Aug.)
Strengthening -XI 2. 400/220 kV 315 MVA 3rd Trf. at Moga (Aug.)

Page 49 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

NR NR system Strengthening 1. Jullundhar-Amritsar 400 kV S/C-65 km


Scheem (formerly part of Tala 2. LILO of Bawana-Bhiwani 400 kV S/C at
Supplementary Scheme) Bahadurgarh-9 km
3. Establishment of 1x315 MVA 400/220 kV S/S at
Amritsar
4. Establishment of 1x315 MVA 400/220 kV S/S at
Bahadurgarh
5. Augmentation of Gorakhpur 400/220 kV S/S by
1x315 MVA trf.
NR System Strengthening Scheme 1. LILO of one ckt of Dhauliganga-Bareilly 400 kV D/C
in Uttaranchal (charged at 220 kV) at Pithoragarh
2. LILO of one ckt of Tanakpur-Bareilly 220 kV D/C
line at Sitarganj
3. Establishment of 6x33.3 MVA 220/132 kV S/S at
Pithoragarh
4. Establishment of 2x100 MVA 220/132 kV S/S at
Sitarganj
NR System Strengthening Scheme 1. Singrauli-suitable LILO point near existing
in Singrauli-Vindhyachal corridor Vindhyachal-Kanpur 400 kV S/C line 400 kV D/C.
The existing Vindhyachal-Kanpur 400 kV S/C line
would be opened up at LILO point and one end be
connected to one ckt going towards Kanpur and
other toward Vindhyachal
2. Diversion of existing Vindhyachal-Singrauli 132 kV
S/C line
NR NR- Strengthening (For 1. Gorakhpur-Lucknow (new) 400 kV D/C
increased import due to Tala 2. Lucknow (New)-Unnao 400 kV D/C
HEP) JV of PGCIL with TATA 3. Bareilly-Mandola 400 kV D/C
Power 4. LILO of Dadri-Samaypur 400 kV D/C line at
Maharani Bagh-2xD/C
5. Gorakhpur (new)-Gorakhpur (UP) interconnection
400 kV -D/C
6. Gorakhpur (new) 400/220 kV 315 MVA S/S with
2x63 MVAR L/R
7. Lucknow (New) 400/220 kV 315 MVA S/S
8. Maharani Bagh 400/220 kV 630 MVA S/S
9. Bareilly (new) 400/220 kV 315 MVA S/S with 2x50
MVAR L/R

Page 50 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

Region Scheme/ Scheme Group Transmission System


WR Evacuation System for Sipat- ATS with Sipat-I (3x660 MW)
II+I (1000 + 1980 MW) 1. Sipat-Seoni 765 kV 2X S/C
2. Seoni-Khandwa 400 kV D/C (Quad AAAC)
3. Nagda-Dehgam 400 kV D/C
4. LILO of Korba-Raipur at Sipat 400 kV D/C
5. LILO of Bhilai-Satpura at Seoni 400 kV D/C
6. Seoni 765/400 kV 7x500 MVA and 400/220 kV 2x315
MVA s/s
7. Rajgarh 400/220 kV 2x315 MVA s/s by LILO of
both ckts of Sardar Sarovar-Dhule D/C line

ATS with Sipat-II (2x500 MW)


1. Khandwa-Rajgarh 400 kV D/C
2. Bina-Gwalior 765 kV S/C (initially op. at 400 kV)
3. Seoni 765/400 kV 3x500 MVA (Aug.)
4. Bhatapara 400/220 kV 2x315 MVA s/s by LILO of
Korba-Raipur line

Sipat-II Supplementary Tr. System


1. Seoni-Wardha 765 kV S/C (initially op. at 400 kV)
2. Wardha-Akola 400 kV D/C
3. Akola-Aurangabad 400 kV D/C
4. Wardha 400/220 kV 2x315 MVA s/s
WR Evacuation System for ATS with Gandhar-II
Kawas-II (725 + 575 MW) 1. Gandhar (NTPC)-Rajkot (GEB) 400 kV D/C
and Gandhar-II (725 + 575 2. Gandhar (NTPC)-Kawas 400 kV D/C
MW) 3. LILO of both circuits of Bina -Nagda 400 kV D/C line
at Shujalpur
4. Establishment of 2x315 MVA 400/220 kV substation
at Shujalpur

ATS with Kawas-II


1. Kawas-II-Vapi (PG) 400 kV D/C Quad
2. Vapi (PG)- Navi Mumbai 400 kV D/C
3. LILO of Kalwa-Pune (PG) 400 kV S/C line at Navi
Mumbai,
4. Vapi (PG)-Khadoli (DNH) 220 kV D/C
5. Establishment of 400/220 kV 2x315 MVA S/S at Navi
Mumbai (GIS in case adequate land is not available).
6. LILO of Apta-Kalwa and Kharghar-Kandalgaon 220
kV D/C lines at Navi Mumbai. (LILO works under
preview of MSEB, 220 kV bay provision at Navi
Mumbai by PGCIL)
7. Installation of 400/220 kV 1x315 MVA 3rd transformer
at Vapi

Page 51 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

WR Western Region For absorbing import in eastern and central part of WR


System Strengthening grid
Scheme -II 1. Seoni-Wardha 765 kV S/C (2nd ckt 400 kV
operation).
2. Raipur-Wardha 400 kV D/C with series compensation
of 25% fixed.
3. Bhadrawati-Parli (PG) 400 kV D/C
4. Wardha-Parli (PG) 400 kV D/C Quad
5. Parli (PG)-Parli (MSEB) 400 kV D/C.
6. Parli (PG)-Pune (PG) 400 kV D/C
7. LILO of Lonikhand-Kalwa 400 kV line at Pune (PG)
near Chinchwad)
8. Pune (PG)-Aurangabad 400 kV D/C
9. Powergrid 400/220 kV 2x315 MVA substation at
Pune.

For regional strengthening in southern Maharashtra


1. LILO of Sholapur-Karad at Sholapur (PG) 400 kV D/C
2. Sholapur (PG) 400/220 kV 2x315 MVA s/s.
3. Parli (PG)- Sholapur (PG) 400 kV D/C
4. Sholapur (PG)-Kolhapur 400 kV D/C

For regional strengthening in Gujarat


1. Rajgarh-Karamsad 400 kV D/C line with 25%
fixed series compensation
2. Limbdi-Ranchhodpura-Zerda 400 kV D/C.

For regional strengthening in northern Madhya Pradesh


1. Korba-Damoh-Bhopal 400 kV D/C.

WR Western Region 1. Powergrid 400/220 kV, 2x315 MVA substation at


System Strengthening Damoh.
Scheme -IV
WR Evacuation System for 1. LILO of Barwaha-Khandwa D/C at Omkareshwar
Omkareshwar (520 MW) 220 kV 2xD/C
2. Omkareshwar-Sanawad 220 kV D/C

Page 52 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

Region Scheme/ Scheme Transmission System


Group
SR Evacuation System for 1. Kudankulam (NPC) – Tirunelveli (PG)
Kudankulam U1&2 400kv 2XD/C line-I & II (quad)
(2000 MW) 2. tirunelveli (pg) – udumalpet 400kv d/c line
3. Tirunelveli (PG) – Edamon (KSEB) 400kV
D/C line, (multi circuit line)
4. Edamon – Muvattupuzha(PG) 400kV quad
D/C line
5. Muvattupuzha – North Tricur (PG) 400kV
quad D/C line
6. LILO of both circuits of Madurai (PG) –
Trivendram (PG) 400kV D/C line at
Tirunelveli
7. 400/220kV S/S at Tirunveli, 2x315 MVA
8. 400/220kV S/S at Muvattupuzha, 2x315
MVA
9. Trivendram 400/220kV S/S Extn. – 3rd
1x315 MVA transformer
10. Udumalpet 400/220kV S/S Extn. – 3rd
1x315 MVA transformer
11. 2x63 MVAR bus reactor at Tirunveli and
1x63 MVAR bus reactor at Muvattupuzha
400 kV S/Ss
12. 1x63 MVAR line reactor at each end of
each circuit of Tirnuveli – Muvattupuzha
400kV D/C line
13. 1x63 MVAR switchable line reactor at
each end of each circuit of Tirnuveli –
Udumalpet 400kV D/C line
SR Evacuation System for 1. KPFBR – Kancheepuram 230kV D/C line
Kalpakkam PFBR (500 2. KPFBR – Arni 230kv D/C line
MW) 3. KPFBR – Sirucheri 230kV D/C line
4. KPFBR – MAPS 230kV S/C (with one
spare phase) Cable link

Page 53 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

SR Evacuation system for 1. Narendra (PG) – Davanagere (KPTCL)


Kaiga U3&4 (220 + 220 400kv D/C line
MW) 2. Mysore (PG) – Kozhikode (PG) 400kV D/C
line
3. Lilo of Kolar – Sriperumbudur (PG)
400kvVs/c at melakottaiyur (PG)
4. Melakottaiyur 400/220kV s/s 2x315 mva
5. Kozhikode 400/220kV S/S 2x315 mva
6. Hiriyur 400/220kv S/S extn- 1x315 mva
7. Narendra 400/220kV S/S bay extn.
8. Mysore 400/220kV S/S bay extn.
9. Davanagere 400/220kV S/S bay extn.
10. 1x50 mvar switchable line reactor at
melakottaiyur end of kolar –
sriperumbudur 400kV S/C line to be
LILOed at melakottaiyur

SR Evacuation System for 1. neyveli ts-ii expansion (nlc) – neyveli ts-ii


Neyveli TPS II (500 existing (nlc) 400kv 2xs/c line
MW) 2. neyveli ts-ii(nlc) – pugalur (pg) 400kv d/c
line
3. Pugalur (PG) – Madurai (PG) 400kV D/C
line
4. Udumalpet – Arasur (PG) 400kV D/C line
5. LILO of Neyveli – Sriperumbudur 400kV
S/C line
6. LILO of Ramagundam – Khammam 400kV
S/C line at Warangal (PG)
7. Pugalur 400/220kV S/S 2x315 MVA
8. Warangal 400/220kV S/S 2x315 MVA
9. Arasur 400/220kV S/S 2x315 MVA
10. Pondicherry 400/220kV S/S 2x315 MVA
11. Madurai 400/220kV S/S bay Extn.
12. Udumalpet 400/220kV S/S bay Extn.
13. 1x50 MVAR switchable line reactor for
each circuit, at Pugalur end of Neyveli –
Pugalur 400kV D/C line.

SR Evacuation System for 1. LILO of Tirunelveli-Muvathapuzha (Quad)


Kayamkulam II LNG at Kayamkulam 400 kV 2xD/C
(1950 MW) 2. Kozhikode-Trissur 400 kV D/C
3. Kayamkulam TPS 400/220 kV 2x315 MVA
S/S
4. Kayamkulam TPS-Kayamkulam 220 kV
D/C
SR For Talcher-II back-up TENTATIVE
in ER 1. Talcher-II – Rourkela 400 kVD/C
2. Baripada-Berhampur-Gazuwaka 400 kV
D/C

Page 54 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

SR Southern Region 1. LILO of Nagarjunasagar (AP)-Raichur 400


System Strengthening kV S/C line at Mehboobnagar (AP)
Scheme–IV 2. LILO of both the circuits of Nellore (AP)-
Sriprumbudur (TN) 400kV D/C line at
Alamatti 400 kV S/S (TN)
SR Southern Region 1. Augmentation of Transformer capacity by
System Strengthening 1x315 MVA at Munirabad, Cuddapah (AP),
Scheme–V Gooty(AP), Khammam (AP),
Gazuwaka(AP) and 3x167 MVA at Kolar
400 kV Substations
2. 1x80 MVAr Bus reactor at Nellore (AP)
400kV S/S
SR Southern Region 1. (LILO of both the circuits of Gazuwaka
System Strengthening (AP)-Vijayawada (AP) 400 kV D/C line at
Scheme–VI Vemagiri 400 kV S/S (AP)
2. 2nd 1x315 MVA 400/220kV Transformer at
Vijayawada (AP)
SR Southern Region 1. LILO of one circuit of Talaguppa-
System Strengthening Neelamangala 400kV D/C line at Hassan
Scheme–VII 2. Hassan 400/220 kV 2x315 MVA substation
3. LILO of one circuit of Madurai (TN)-Trichy
(TN) D/C line at Karaikudi (TN)
4. Karaikudi 400/220 kV 2x315 MVA
substation
SR Neelamangala-Mysore 1. Neelamangala-Mysore 400 kV D/C line
Transmission scheme 2. 400/220 kV 2x315 MVA S/S at Mysore

Page 55 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

Region Scheme/ Scheme Transmission System


Group
ER Evacuation System for With North Karanpura:
North Karanpura (1980 1. North Karanpura – Sasaram 765kV S/C
MW) and Maithon RB line with 2x1500MVA, 765/400kV s/s at
(1000 MW) Sasaram
2. North Karanpura – Ranchi 400kV D/C line
3. North Karanpura – WR pooling Station
near Sipat 765kV S/C line with
2x1500MVA, 765/400kV s/s at WR pooling
station near Sipat
4. WR pooling station near Sipat – Sipat
765kV S/C line
5. WR pooling station near Sipat – Seoni
765kV S/C line

With Maithon RB:


1. Maithon RB-Maithon PG 400kV D/C line
2. Maithon RB – Ranchi 400kV D/C line
3. Biharsharif – Sasaram 400kV D/C line

With North Karanpura or Maithon RB for the


Northern Region:
1. Sasaram-Fatehpur 765kV S/C line
2. Fatehpur-Agra 765kV S/C line
3. 765kV Agra s/s, 2x1500 MVA 765/400kV
4. 765kV Fatehpur s/s, 2x1500 MVA
765/400kV & 2x315 MVA 400/220 kV
5. LILOs of Singrauli/Allahabad –
Kanpur/Mainpuri 400kv lines at Fatehpur.
6. Sasaram – Balia 400kV quad D/C

ER Evacuation System for 1. LILO of Kahalgaon – Patna 400kV D/C


Barh (1980 MW) quad line at Barh
2. Barh – Balia 400kV D/C quad line
3. Balia – Bhiwadi 2500 MW + 500kV HVDC
Bipole line
4. Seoni – Bina 765kV S/c line (to be initially
operated at 400kV)
5. Balia 400kV S/S extn
6. Bhiwadi 400kV S/S extn
7. Seoni 400kV S/s extn
8. Bina 400kV Sw. Stn. Extn.
9. Balia and Bhiwadi HVDC Converter
Stations

Page 56 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

ER Evacuation System for 1. Teesta Stage III – New Jalpaiguri, 220kV


Teesta Low Dam III &IV S/C line with Twin-Moose conductor.
(292 MW) 2. Teesta Stage III – Teesta Stage IV S/S,
220kV S/C line with Moose conductor.
3. Teesta Stage IV – New Jalpaiguri, 220kV
D/C line.
(These lines would be constructed by
WBSEB, as the whole of the power would
be absorbed by West Bengal.)
ER Evacuation System for 1. LILO of one ckt of Mangan-Melli 400 kV
Teesta IV (495 MW) D/C at Teesta IV
ER Evacuation System for 1. Existing system adequate
Farakka III (500 MW)
ER System Strengthening-I 1. Higher capacity conductr on Siliguri-Purnia
ER System Strengthening-II 1. Purlia-Jamshedpur 400kV D/C
2. Jamshedpur-Baripada 400kV D/C
3. Baripada –Mendhalsal (Bhuwanashwar)
400kV D/C
ER For Talcher-II back-up TENTATIVE
in ER 1. Talcher-II – Rourkela 400 kVD/C
2. Baripada-Berhampur-Gazuwaka 400 kV
D/C
ER Evacuation System for TENTATIVE
Bokaro (500 MW) 1. Bakaro-North Karanpura 400 kV D/C Quad
ER Evacuation System for TENTATIVE
Kodarma (500 MW) 1. Kodarma-Sasaram D/C 400 kV D/C Quad
ER Evacuation System for TENTATIVE
Hirma-II (2000 MW) 1. Hirma II-Raipur 400 kV 2xD/C (Quad)
2. Hirma-Sipat PP 2xD/C (Quad)

Page 57 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

Region Scheme/ Scheme Transmission System


Group
NER Evacuation System for 1. LILO Ranganadi-Balipara at Biswanath
Kameng HEP (600 MW) Chariyali 400 kV 2xD/C
2. Kameng HEP-Biswanath Chariyali 400 kV
D/C
3. Biswanath Chariyali -Bongaigaon 400 kV
D/C
NER Evacuation System for 1. Ranganadi HEP I-Ranganadi HEP II 132
Ranganadi II (130 MW) kV S/C
2. LILO of Ranganadi HEP I-Ziro at
Ranganadi HEP II 132 kV D/C
NER Evacuation System for 1. Dikrong-Ranganadi HEP-I 132 kV D/C
Dikrong (110 MW)
NER Evacuation System for 1. Biswanath Chariyali to be developed as a
Subnasiri Lower HEP pooling station in NER
(2000 MW) 2. Subansiri – Biswanath Chariyali 400kV
2xD/C Quad lines.
3. Biswanath Chariyali – Agra, HVDC Bipole,
+/- 600kV, 4000 MW.
NER System Strengthening 1. 220kV and 132kV works for Aizwal,
Sch-I Dimapur, Kopili, Khandong

Page 58 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

Appendix- 2.9

STATES’ TRANSMISSION SCHEMES FOR THE XI PLAN EVACUATION SYSTEM


FOR GENERATION PROJECTS

States of Northern Region

Gen. Project State sector generation projects


Transmission scheme/proposal
HP
UHL-III • UHL-Bassi 132 kV D/C
(100MW) • UHL-Hamirpur D/C
KASHANG I & • LILO of Bhabha-Kunihar S/C at Kashang 220 kV D/C
II
(126MW)
SAINJ • Through Parbati Transmission system
(100 MW)
SHONGTONG • Shongtong Karcham-Karcham Pooling Station 400 kV D/C
KARCHAM • Karcham Pooling Station-NR load centers to be decided
(402 MW) after firming up of generation in the complex
HARYANA
YAMUNA • Yamuna Nagar TPS-Yamuna Nagar 220 kV 2xD/C
NAGAR U1&2 • Yammuna Nagar TPS-Tepla 220 kV D/C
(500 MW) • Yammuna Nagar -Ladwa 220 kV D/C
• Ladwa-Nissing 220 kV D/C
• Ladwa 220/132 kV 100 MVA S/S
UP
ANPARA C • Charging of Anpara-Unnao 765 kV S/C line at 765 kV
(1000 MW) • Anpara 765/400 kV 2x630 MVA S/S
• Unnao 765/400 kV 3x630 MVA S/S
ROSA • Rosa-Shahjahanpur 220 kV 2xS/C
(600 MW) • Rosa-Hardoi 220 kV D/C
• Rosa-Badaun 220 kV S/C
• Hardoi 220/132 kV 2x100 MVA S/S
RAJASTHAN
GIRAL U-1&2 • Giral-Barmer 220 kV D/C
(250 MW) • LILO Barmer-Amar Sagar at Giral 220 kV D/C
CHHBRA TPS • Chabra TPS-Swaimadhopur 400 kV D/C
(500 MW) • Swaimadhopur 400/220 kV 2x315 MVA S/S
KOTA U-7 • Step up generation voltage at 220 kV
(195 MW) • Split existing KTPS bus with U 6&7 on one section and rest
on other section
• KTPS 6&7 section-Kota (PG) 220 kV D/C with twin moose
UTTARANCH
AL

Page 59 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

TUINIPALASU • LILO one ckt Arakot Tuni-Mori at Tuinipalasu 220 kV D/C


(42 MW)
BAWALA • Bawala Nand Prayag – Karanpryag 132 kV D/C line
NAND
PRAYAG
(132MW)
PALAMANERI • LILO one ckt Lohari Nagpala-Tehri Poling Point at
(480 MW) Palamaneri 400 kV D/C

Gen. Project Private sector generation projects


Transmission scheme/proposal
HP
ALLAN • ALLAIN DHUANGAN – NALAGARH 220 KV D/C
DHUNGAN
(192MW)
KARCHAM • LILO OF BASPA – NATHPA JHAKRI D/C LINE AT
WANGTOO KARCHEM WANGTOO
(1000MW) • KARCHEM WANGTOO – ABDULLAPUR 400 KV D/C
• BEYONG ABDULLAPUR TR. SYSTEM HAS TO BE
EVOLVED
DHAMVARI • DHAMWARI SUNDA - MALIANA 2XS/C+D/C
SONDA
(70MW)
SAWARA NOT YET IDENTIFIED
KUDDU
(110 MW)
Punjab
GOVINDWAL • GOINDWAL-TATHASAHIB 220 KV D/C
SAHEB • GOINDWAL-TARNTARAN 220 KV D/C
(500 MW) • LILO OF JAMSHER-VERPAL D/C AT
GOINDWALSAHIB-220 KV 2XD/C
• GOINDWAL 220/132 KV 100 MVA S/S
UTTRANCHAL

VISHNU NOT YET IDENTIFIED


PRAYAG (400
MW)

Page 60 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

States of Western Region

Gen. Project State sector generation projects


Transmission scheme/proposal
GUJARAT
UTRAN CCGT • UTRAN-KOSAMABA 220 KV 2XD/C
(350MW)
PAGUTHAN •
PAGUTHAN-KASOR 400 KV D/C
(350+700 MW) •
PAGUTHAN-FEDRA 400 KV D/C

SYSTEM STRENGTHENING BELOW FEDRA 400 KV S/S
YET TO BE IDENTIFIED BY GETCO
Sikka Repl. Ext. TRANSMISSION SYSTEM YET TO BE IDENTIFIED
(500MW)
Surat Lignite TRANSMISSION SYSTEM YET TO BE IDENTIFIED
Ext. (250MW)
MP & GUJ.
MALWA TRANSMISSION SYSTEM YET TO BE IDENTIFIED
(1000 MW)
MAHARASHTRA
PARLI EXT. • LILO OF BOTH CKTS OF PARLI-BEED D/C LINE AT
STAGE-II PARLI EXTN. 220 KV 2XD/C
(250 MW) • LILO OF NANDED-GIRWALI LINE AT PARLI EXTN. 220
KV D/C
PARAS EXT. U- • LILO OF BOTH CKTS OF AKOLA-CHIKLI D/C LINE AT
II PARAS EXTN. 220 KV 2XD/C
(250 MW) • PARAS EXTN.-AKOLA 220 KV D/C
KHAPER • LILO OF CHANDRAPUR-KORADI S/C LINE AT
KHEDA KHAPERKHEDA 400 KV D/C
EXT (500MW) • KHAPERKHEDA 400/220 KV 1X315 MVA S/S
• KHAPERKHEDA II- KHAPERKHEDA 220 KV D/C
CHHATISGARH
KORBA WEST • KORBA (W)-BHILAI (KHEDAMARA) D/C KORBA (W)-
EXT (600MW) BHILAI (KHEDAMARA) 400 KV D/C
• BHILAI (KHEDAMARA)-RAJNANDGARH 220 KV D/C
• BHILAI (KHEDAMARA)-BEMATARA 220 KV D/C
• RAJNANDGAON 220/132 KV 1X160 MVA S/S

Page 61 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

MARWA • MARWA-RAIPUR (NEW) 400 KV D/C


(1000 MW) • LILO OF KORBA-KHEDAMARA S/C AT MARWA 400 KV
D/C
• MARWA 400/220 KV 1X315 MVA S/S
• RAIPUR (NEW) 400/220 KV 1X315 MVA S/S
• MAHASAMUND-GURUR 220 KV D/C
• RAIPUR (NEW)-DOMA 220 KV D/C
• RAIPUR (NEW)-SILTARA 220 KV D/C
• RAIPUR (NEW)-URLA 220 KV D/C
• RAIPUR (NEW)-MAHASAMUND 220 KV D/C
• MARWA-MOPKA 220 KV D/C
• DOMA 220/132 KV 1X160 MVA S/S
• DOMA (220 KV)-KACHNA 132 KV D/C
• DOMA (220 KV)-KURUD 132 KV D/C
MATNAR • EVACUATION AT 132 KV LEVEL
(60 MW)
BODHGHAT • BODHGHAT (BARSOOR)-KHEDAMARA 400 KV D/C
(500 MW)
IGTPP • BHAIYATHAN-BILASPUR 400 KV D/C
BHAYTHAN • BILASPUR-RAIPUR 400 KV D/C
(1320 MW) • BHAIYATHAN-BISHRAMPUR 220 KV D/C
• BILASPUR-MOPKA 220 KV D/C
• BHAIYATHAN-PENDRAROAD-BAIKUNTHPUR 220 KV
D/C
• MOPKA-MUNGELI 220 KV D/C
• BHAIYATHAN 400/220 KV 1X315 MVA S/S
• BILASPUR 400/220 KV 1X315 MVA S/S
• MUNGELI 220/132 KV 1X160 MVA S/S
• BAIKUNTHPUR 220/132 KV 1X160 MVA S/S
• MUNGELI (220 KV)-MUNGELI 132 KV D/C
• BAIKUNTHPUR (220 KV)-BAIKUNTHPUR 132 KV D/C
PRIVATE SECTOR GENERATION PROJECTS
GUJARAT
AKHAKHOL- • LILO OF KAWAS-GANDHAR 400 KV D/C AT AKHAKHOL
PAGUTHAN • AKHAKHOL-DEHGAM 400 KV D/C
(730MW)
ESSAR-HAZIRA TRANSMISSION SYSTEM YET TO BE IDENTIFIED
EXT. (1460MW)
BHAVNAGAR TRANSMISSION SYSTEM YET TO BE IDENTIFIED
(NIRMA JV)
(250 MW)
MAHARASHTRA
VILE-TATA TRANSMISSION SYSTEM YET TO BE IDENTIFIED
(1000 MW)

Page 62 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

CHHATISGARH
RAIGARH TRANSMISSION SYSTEM YET TO BE IDENTIFIED
(750MW)
PATHDI TPS- TRANSMISSION SYSTEM YET TO BE IDENTIFIED
LANCO
(1200MW)
MP

MAHESHWAR • Maheshwar-Pithampura 220 kV D/C


(400MW) • Maheshwar-Rajgarh 220 kV D/C
• Maheshwar-Julwania 220 kV D/C

States of Southern Region

Gen. Project State sector generation projects


Transmission scheme/proposal
AP
VIJYAWADA • VTPS - Yeddumailaram 400kV D/C
TPP • VTPS - Narasaraopeta 400kV D/C
(660MW) • Tadikonda - Narasaraopeta 400kV S/C
• 1x315 MVA, 400/220 kV Transf at VTPS switchyard
JAURALA • Jurala HEP- Mehboobnagar 220kV D/C
PRIYA
(195MW)
N. SAGAR TP • Existing system
DAM (50MW)
KARNATAKA
BIDADI YET TO BE IDENTIFIED
(1400MW)
NAGARJUNA • Nagarjuna TPP-Hassan 400 kV D/C
TPP • Hassan-Bidadi 400 kV D/C
(1015 MW) • LILO 2nd ckt Talaguppa-Neelamangla at Hassan 400 kV
D/C
RAICHUR U-8 • Existing system adequate
(210 MW)
BELLARY YET TO BE IDENTIFIED
EXT.
(500 MW)
GUNDIA EXT. YET TO BE IDENTIFIED
(300 MW)
KERALA
ADIRAPALLI YET TO BE IDENTIFIED
(163MW)

Page 63 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

TAMIL NADU
BHAWANI • Existing system adequate
KATHLAI U2
(60MW)

Gen. Project Private sector generation projects


Transmission scheme/proposal
AP
BHOPALPALLI YET TO BE IDENTIFIED
(500MW)

States of Eastern Region


Gen. Project State sector generation projects
Transmission scheme/proposal
WEST BENGAL

PURULIA PSS • Purulia-Bidhannagar 400 kV D/C


(225+675 MW) • Purulia-Arambag 400 kV D/C
SAGARDIGHI-II • LILO of Farakka-Jeerat-Subhashgram 400 kV S/C at
(1000MW) Sagardighi TPS.
• Sagardighi TPS-Durgapur 400 kV S/C

BAKRESHWAR • Existing 400kV and 220kV transmission system will be


U5 (210MW) adequate.
DPL TPS • DPL-Durgapur 400 kV D/C
(500 MW)
BAKRESHWAR • Bakreshwar-Jagatballavpur 400 kV S/C
U6 • Jagatballavpur 400/220 kV 2x315 MVA S/S
(210MW) • Jagatballavpur-Domjur 220 kV D/C
Katwa TPP • Katwa-Maithon 400 kV D/C
(1000 MW)
JHARKHAND
TENUGHAT • Tenughat TPS-Ranchi 400kV D/C-200ckms.
EXT • Existing TenughatTPS-Biharsariff 400kV S/C line will
(630MW) be charge at 400 kV.

Page 64 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

Gen. Project Private Sector Generation Projects

ORISSA
IB STAGE-II • IB TPS-Meramundali 400 kV D/C – 400kV operation.
U5&6 (THE LINE IS TO BE INITIALLY OPERATED AT
(2X250MW) 220KV UNDER STAGE-I. THE LINE IS UNDER
CONSTRUCTION)
JORDA • Jorada Nuelpoi-Ib TPS 400 kV D/C
NUELPOI, CESC
(500 MW)
AURANGA TPP, • Auranga TPP-Maithon (PG) 400 kV D/C
TATA POWER
(1000 MW)
WEST BENGAL
BUDGE BUDGE • Existing system adequate
EXTN.
WB+CESC JV
(250 MW)

States of North-Eastern Region


Gen. Project State sector generation projects
Transmission scheme/proposal
ASSAM
LAKWA W. H. • EXISTING SYSTEM ADEQUATE
(38 MW)
MEGHALYA
MYNTDU • MYNTDU-KHLIEHRIAT 132KV D/C LINE.
STAGE-I
(84MW)

Gen. Project Private Sector Generation Projects


TRIPURA
TRIPURA GAS • TRIPURA GAS-SILCHAR 400 KV D/C QUAD
ONGC • SILCHAR-BONGAIGAON 400 KV D/C QUAD
(1050MW) • BONGAIGAON-SILLIGURI 400 KV D/C QUAD
• PURNEA-BIHARSHARIF 400 KV D/C QUAD
• TRIPURA GAS 400/132 KV SWITCHYARD AND 132 KV
LINES TO GRID
• SILCHER 400/132 KV S/S AND 132 KV LINES TO GRID

Page 65 of Chapter 2
Transmission Planning & National Grid Working Group on Power for 11th Plan

Appendix-2.10

STATE-WISE DETAILS OF NORMATIVE ASSESSMENT

REGION
STATE
Peak Peak Increase Projected Additional Normative Investment Total
Demand Demand in peak population in demand Investment needed in States' investment
level 2006- 2011-12 at demand 2012 growth to needed in 220,132,66kV needed in
07 at start end of XI during the come up to States' System for States'
of XI Plan Plan XI Plan atleast 50% 220,132,66kV accelerated 220,132,66kV
period of National System for growth to come System
average trend growth up to 50% of
National average

Number in
MW MW MW MW Rs Crores Rs Crores Rs Crores
crores

0.50 0.60 0.60


Northern
Delhi 3900 5665 1765 1.90 0 1059 0 1059
Haryana 4200 6101 1901 2.59 0 1140 0 1140
Himachal Pradesh 800 1162 362 0.68 0 217 0 217
Jammu and Kashmir 1600 2324 724 1.19 0 434 0 434
Punjab 7700 11184 3484 2.80 0 2091 0 2091
Rajasthan 5000 7263 2263 6.89 0 1358 0 1358
Uttar Pradesh 7800 11330 3530 20.43 1909 2118 1146 3263
Uttranchal 1000 1453 453 1.01 0 272 0 272
Chandigarh 220 320 100 0.15 0 60 0 60

Northern Region 32220 46800 14580 38 8748 1146 9894


NR Peak With Diversity 30981 45000 14019

Western
Chhattisgarh 1900 2805 905 2.46 0 543 0 543
Goa 70 103 33 0.18 13 20 13 33
Gujarat 11000 16242 5242 5.98 0 3145 0 3145
Madhya Pradesh 7000 10336 3336 7.33 0 2001 0 2001
Maharastra 16500 24362 7862 11.42 0 4717 0 4717
Dadar & Nagar Haveli 400 591 191 0.04 0 114 0 114
Daman & Diu 250 369 119 0.03 0 71 0 71

Western Region 37120 54808 17688 27 10613 13 10626


WR Peak With Diversity 35692 52700 17008

Southern
Andhra Pradesh 9500 13317 3817 8.55 0 2290 0 2290
Karnataka 6800 9532 2732 6.00 0 1639 0 1639
Kerala 2900 4065 1165 3.48 0 699 0 699
Tamil Nadu 8000 11215 3215 6.79 0 1929 0 1929
Pondicherry 250 350 100 0.15 0 60 0 60

Southern Region 27450 38480 11030 25 6618 0 6618


SR Peak With Diversity 26394 37000 10606

Eastern
Bihar 1200 2224 1024 9.90 4191 615 4191 4806
DVC 1800 3337 1537 2.00 0 922 0 922
Jharkhand 700 1298 598 2.19 122 359 122 480
Orissa 2600 4820 2220 4.11 0 1332 0 1332
Sikkim 60 111 51 0.06 0 31 0 31
West Bengal 4300 7971 3671 8.03 0 2202 0 2202

Eastern Region 10660 19760 9100 26 5460 4313 9773


ER Peak With Diversity 10250 19000 8750

Page 66 of Chapter 2
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

Chapter- 3

DISTRIBUTION INCLUDING VILLAGE AND HOUSHOLD


ELECTRIFICATION

3.0 OVERVIEW

Distribution is the key segment of electricity supply chain. The distribution sector
caters to rural and urban areas. Rural distribution segment is characterized by wide
dispersal of net work in large areas with long lines, high cost of supply, low paying
capacity of the people, large number of subsidized customers, un-metered flat rate
supply to farmers, non metering due to high cost and practical difficulties, low load
and low rate of load growth. Urban distribution is characterized by high consumer
density, and higher rate of growth of load. The consumer mix in urban areas is
mostly commercial, residential, and industrial, whereas consumer mix in rural areas
is mainly agriculture and residential. Both segments are distinct with different
problems and issues. Electricity Act 2003 has recognized Rural Electrification as a
separate entity.

The biggest challenge of the power sector is the high T&D losses. A combination of
technical and non-technical factors is contributing to high Transmission and
Distribution losses. Lack of consumer education, political interference, and inefficient
use of electricity is further aggravating the problem. As T&D loss figures did not
capture the gap between the billing and the collection, the concept of Aggregate
Technical & Commercial (AT&C) loss was introduced in 2001-2002 to capture total
performance of the utility.

The AT&C losses are presently in the range of 18% to 62% in various states. The
average AT&C loss in the country is at 34%. There is wide variation of losses among
the states and variation among the Discoms within the states. The major portion of
losses are due to theft and pilferage, which is estimated at about Rs.20, 000 crore
annually. Apart from rampant theft, the distribution sector is beset with poor billing
(only 55%) and collection (only 41%) efficiency in almost in all States. More than 75-
80% of the total technical loss and almost the entire commercial loss occur at the
distribution stage. It is estimated that 1% reduction in T&D losses would generate
savings of over Rs.700 to Rs.800 crores. Reduction of T&D loss to around 10% will
release energy equivalent to an additional capacity of 10,000-12,000 MW.

Page 1 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

Table 3.1
State-wise AT&C Losses
Less than 20% Between 20-30% Between 30-40% Above 40%
Goa Andhra Pradesh Karnataka Delhi
Tamil Nadu Gujarat Kerala Uttar Pradesh
West Bengal Assam Bihar
Himachal Pradesh Rajasthan Jharkhand
Maharashtra Haryana Madhya Pradesh
Tripura Meghalaya Arunachal Pradesh
Punjab Chhattisgarh Manipur
Uttaranchal Mizoram Nagaland

The Sub-transmission and Distribution systems have been the thrust areas during
10th Plan. The reduction of AT&C losses with improvement of quality and reliability
were given special attention during the 10th Plan. In line with this, Accelerated Power
Development and Reform Programme was launched with thrust on AT&C loss
reduction through techno-commercial interventions to achieve commercial viability.
For rural areas Rajiv Gandhi Grameen Vidyutikaran Yojna has been launched in April
2005 with 90% grant to achieve 100% electrification of villages.

3.1 KEY ISSUES IN ELECTRICITY DISTRIBUTION SECTOR

The problems in Distribution sector have accumulated over the years mainly due to
lack of investment, commercial orientation, excessive T&D losses, distorted tariff
policies etc. Following are the key issues / key factors effecting overall performance
of the distribution sector:

3.1.1 State Government related

Uncertain commitment of State Governments is key impediment to the ongoing


reform process. This includes delay in unbundling and restructuring of State
Electricity Boards, minimal/no financial support to unbundled utilities during transition
period, inadequate financial support for providing subsidised power to domestic and
agricultural consumers, inadequate administrative support in curbing theft of power
etc. Frequently changing policies of the State Governments in regard to
subsidies/free power to farmers adversely affecting the revenue recovery and cost
coverage of utilities.

3.1.2 Regulatory process related issues

SERCs are inadequately staffed with poor infrastructure. Due to lack of competency
and resources in Discoms, tariff filings are often delayed. In several cases, SERC
asks Discoms to revise their filings on account of data gaps or improper information.

There is no central repository of data in electronic form which leads to delay in filing
petitions and responding to queries from the regulator. The distribution licensees
have not been able to fully implement regulations and directives due to various
reasons like lack of skilled human resources, resource constraints or inadequate
training/awareness.

Page 2 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

3.1.3 Corporate governance and institutional issues

Most of the distribution companies formed as a result of unbundling of SEB are still
not fully autonomous. In many cases, unbundling is limited to operational and
technical segregation. Segregation of accounts, cash flow, human resources is not
complete. Successor companies are highly dependent on their parent company (i.e.
residual SEB or single buyer/trade co or Transco) for financials/cash flow, human
resources, investment decisions and other administrative matters and therefore, the
focus on efficiency improvement from respective entities is lacking.
Due to in-adequate network expansion commensurate with load growth, many power
transformers, distribution transformers, 33kV lines and 11kV feeders are overloaded.
Reinforcement of existing network in the form of new transformers, new lines and
augmentation of existing transformers and lines is poor. Most of the distribution
networks in India are quite old which results in to reduced reliability, increased R&M
expenses and poor quality of supply. The system also suffers low HT/LT ratio.
The consumer awareness about Demand Side Management (DSM) is limited which
results in to higher consumption and increased losses. DSM initiatives such as local
reactive power compensation, use of energy efficient devices, Time of Day tariff, use
of renewable sources etc. are lacking.

3.1.4 Commercial issues

Commercial losses are primarily due to improper energy accounting and billing
processes, faulty metering, under-billing, theft and pilferage of energy and lack of
accountability within the organization. Commercial losses are estimated at about Rs.
26,000 crore during 2000-01 and theft of electricity is estimated to cost the country at
about Rs. 20,000 crore per year (Source: MoP). The chart shows overall T&D losses
in India.
40
35
30
% Losses

25
20
15
10
5
0
FY 92 FY 94 FY 96 FY 98 FY 00 FY 02 FY 04
Source: MoP Presentation July 19, 2005

Only 87% of the total consumers in India are metered (Source: Mop, 2004-05). Many
states have undertaken 100% metering programs, but not yet completed. The chart
below indicates consumer metering level in some of the states. This does not include
defective meters.

Page 3 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

Consumer metering till FY 05


100% 100%
80% 80%
60% 60%
40% 40%
20% 20%
0% 0%
AP MP Raj. UP Mah Kar
States All India
High AT&C losses are due to high T&D losses coupled with low collection efficiency.
Low level of collection is attributable to lack of employees accountability, inadequate
collection facilities, limited usage of advanced systems and technology (e.g. payment
through ECS, credit/debit cards, special centres like e-Seva centres), billing errors,
political/administrative interference etc. The chart below shows level of collection
efficiency in select Discoms.

Collection Efficiency (%) (2004-05)


99.7% 99.5% 96.7% 97.0%
100% 90.0% 91.3% 92.4% 94.8%

78.5%
80%
62.3% 60.3%
60%

40%

20%

0%
CPDCL

EPDCL

NPDCL
BRPL

BYPL

NDPL

SPDCL
Agra

Varanasi
Meerut
Lucknow

Delhi Uttar Pradesh Andhra Pradesh

Source: PFC Report on Performance of the State


Power Utilities for the Years 2002-03 to 2004-05

3.1.5 Operational issues

Due to inadequate metering and data collection system in place, utilities have not
been able to conduct energy audit, which is crucial for any energy business.
Discoms do not have proper load monitoring and control mechanisms (e.g. SCADA,
Distribution Control Centre, telecommunications etc.), which results in to haphazard
control of the demand and often leads to loss of revenue and inconvenience to the
consumers.

3.1.6 Human resources and training issues

In many of the state owned utilities, recruitment has been either stopped or restricted
since last 15 years. Average age of employee in most SEBs is more than 50 years.
Lack of fresh talent and domain expertise (e.g. in area of IT, communication, SCADA)
impedes development of the sector and efficiency improvement. Induction of new
technology in the field and office level also needs proper training for staff for efficient

Page 4 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

handling. Discoms need to undertake training need analysis and roll out training
programmes for employees working in different areas. In a typical SEB, ratio of field
staff to support/office staff is 54:46. However, customer facing staff is inadequate.
Also, ratio of meter readers to consumers on the other hand ranges from 1:3000 to
1:7000.

No. of Distribution Em ployees per lakh


consum ers
400

300

200
100

Rajasthan
AP

UP

MP

Orissa

Assam
Source: Companies Annual
Report for FY'05

Productivity of the employees: The chart below shows some of the key parameters
of select entities / state to assess productivity of the employees in distribution sector.
(Note: Pink bar indicates private player, blue bar indicates government owned
Distribution Company) (Source: Websites/Tariff Orders of respective utilities)

Private players Versus State owned


300 1.200

250 1.000
Rs./Unit and MU/Employee
Rs Thousands

200 0.800

150 0.600

100 0.400

50 0.200

0 0.000
Orissa
NDPL

AP

UP

MP
Yamuna

Rajdhani
BSES

BSES

Expense per employee Expense per unit sold


MU sold per employee

3.1.7 Technological issues

Many of the distribution utilities in India are still lacking most basic requirements –
consumer database and asset database which can be addressed through IT and
communication solutions. Utilities do not have complete record of all consumers,
which results in to direct revenue loss. Most utilities maintain manual records of
consumers (in the form of register) especially in rural areas. Electromechanical
meters, manual reading of meters, manual bill preparation and delivery and
inadequate bill collection facilities result in to overall delay in revenue collection and
revenue leakage. Conventional complaint handling process results in delayed
redressal and increased dissatisfaction among customers.

Page 5 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

Regular monitoring and testing of critical assets such as 11kV feeders, 11/0.4kV
distribution transformers and 415V feeders etc. are very important in ensuring reliable
supply. Monitoring of consumer energy metering systems is critical to overall
revenue. Asset database is crucial in efficient management of assets and claiming
depreciation under annual revenue requirement.
Almost all distribution companies do not have real-time monitoring system and
typically use phone or radio communication for demand management. Most Discoms
do not have distribution control centre which can manage load shedding and
instructions from SLDC. Discoms need to plan implementation of SCADA in long
term keeping in view capital cost and benefits.

3.2 DISTRIBUTION REFORMS

3.2.1 In the power sector reform process, the significant initiatives during 10th Plan
are enactment of Electricity Act 2003, notification of National Electricity Policy, Tariff
Policy and Rural Electrification Policy. Distribution segment was identified as the key
area for reform for putting the sector on the right track. Distribution Reforms involve
System up-gradation, Loss reduction, Theft control, Consumer orientation,
Commercialization and adoption of I T.

3.2.2 Six Level Intervention Strategy

In order to achieve commercial viability, Ministry of Power has formulated a six level
intervention strategy that encompasses initiatives at national level, state level, SEB/
utility level, distribution circle level, feeder level and consumer level as part of
distribution reforms. These are:

i) National level intervention-Relates to policy, legislation frame work, uniform


standards, energy conservation, accounting etc.
ii) State level intervention-Formation of SERCs, issuance of regular tariff order,
providing legislative support, removal of Tariff anomalies, subsidies and
budgetary support.
iii) SEB level intervention-Restructuring, accountability, commercial accounting,
integrated MIS, benchmarking of parameters, Grid discipline and TOD
metering.
iv) Distribution Circle level intervention-in the billing, reducing energy handling
cost, circle to function as independent business unit
v) Feeder level intervention-100% metering at 11 kV feeder, total accounting of
energy & quality power supply
vi) Consumer level intervention-Mandatory metering including billing, consumer
satisfaction & energy conservation.

3.3 NEW LEGAL AND POLICY FRAMEWORK

3.3.1 Electricity Act 2003

Electricity Act-2003 was notified in June 2003 with Competition, Protection of


Consumers interests & Power for all Areas, as objectives. The Act provides liberal
framework for power development and creates competitive environment to facilitate
private investment. It has de-licensed generation and in rural areas, stand alone

Page 6 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

generation and distribution has been de-licensed. It provides for multiple licensing in
Distribution and stringent provisions for controlling theft of electricity. It obliges states
to restructure Electricity Boards. The Regulatory Commissions will determine tariffs.
It provides for open access in Transmission from outset and open access in
Distribution to be allowed by State Electricity Regularity Commissions (SERCs) in
phases. The cross subsidies will have to be gradually phased out. Trading has
become a distinct licensed activity to promote development of electricity market.
Electricity Act-2003 provides for notification of National Electricity Plan by Central
Electricity Authority for short-term framework of 5 years while also projecting a 15-
year perspective.

3.3.2 Energy Conservation Act, 2001

Energy Conservation Act was enacted on October 1, 2001. The Act lays down
concrete measures to ensure efficient use of energy and its conservation. The Act
came into effect on March 1, 2002. The Bureau of Energy Efficiency (BEE) has been
set up to make wide ranging regulations to further the objectives of the Act. The
Central and State Governments have been empowered to facilitate and enforce
efficient use of energy and its conservation.

3.4 POLICY INITIATIVES

In compliance with provisions of the Electricity Act 2003, National Electricity Policy,
National Tariff Policy and National Rural Electrification Policy as have been notified
by the Ministry of Power.

3.4.1 National Electricity Policy (2005)

The National Electricity Policy aims at laying guidelines for accelerated development
of the power sector, providing supply of electricity to all areas and protecting interests
of consumers and other stakeholders. The policy envisages multi-year tariff; private
sector participation in distribution, open access in distribution, segregation of
technical and commercial losses through energy audits, standards for reliability and
quality of supply in line with an international practice by year 2012, implementation of
modern information technologies system on priority basis with special emphasis on
consumer indexing and GIS mapping, promotion of HVDS system, sub-station
automation and effective implementation of anti theft provisions of Electricity Act
2003.

3.4.2 The National Tariff Policy (2006)

The National Tariff Policy has been notified in January 2006. As per the policy all
future requirement of power needs to be procured competitively by distribution
licensees except in cases of expansion of existing projects or where there is a State
controlled/owned company developer. It provides framework for performance based
cost of service regulation in respect of aspects common to generation, transmission
as well as distribution. Multi-year tariff framework is to be adopted for tariff to be
determined from April 1, 2006. The policy envisages suitable performance norms of
operations with incentives and dis-incentives along with appropriate arrangement for
sharing the gains of efficient operations with the consumers. Electricity is to be made
available for 24 hours particularly for those consumers who are willing to pay tariff

Page 7 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

which reflects efficient costs. The policy emphasizes giving subsidy in transparent
and targeted manner and the cross subsidies for different consumers should be
brought within the range of +20% of average of the supply by the end of the year
2010-2011. The tariff fixation should ensure sustainable use of ground water
resources. The cross subsidy surcharge to be computed in a way so that open
access becomes a reality.

3.4.3 Rural Electrification Policy (2006)

The Rural Electrification Policy envisages provision of access to electricity to all


households by the year 2009 and minimum lifeline consumption of 1 unit per
household per day as merit good by year 2012, promotion of decentralized
distribution generation, rural electrification plan by State Governments to achieve the
goal of providing access to all households, setting up of the District Committees,
implementation of Franchisee system as mandated by RGGVY for distribution
management, If state Government / SERC decides to permit licensee to use assets
created with subsidy the benefit of capital subsidy to be passed on to consumers.
Government of India to evolve model schemes in consultation with NABARD and RBI
to encourage widespread participation by lending community in RE initiatives, Energy
efficiency to be promoted as mass campaign in rural areas. Government of India
should evolve programmes for encouraging use of economically viable energy
efficient farm equipment – irrigation pumpsets and use of IT for supply of electricity
should be encouraged.

3.4.4 Integrated Energy Policy (IEP)

Some of the important recommendations relate to the following areas:

• Transparent and targeted subsidies;


• Improved efficiencies.
• On the power sector the key high priority recommendations of the energy policy
relate to power sector reforms to focus on controlling aggregate technical and
commercial losses of the transmission and distribution utilities. In order to
reduce AT&C losses the Committee recommended APDRP to be restructured
to ensure energy flow auditing at the distribution transformer level through
• Automated meter reading, Geographical Information System (GIS) mapping of
the network & consumers and separation of feeders for agricultural pumps.

• Investment in developing a Management Information System (MIS) that can


support a full energy audit for each distribution transformer is essential for
reduction in AT&C losses. This will also fix accountability and provide a
baseline which is an essential prerequisite to management reform and/or
privatization.

• Introduce time-of-day pricing with shift to electronic meters.

• For all loads above say 50 kWh, introduce intelligent meters that permit real
time and remote recording of data and allow remote control over the power

Page 8 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

supplied by each meter. This would help effective management of connected


load and the reported pilferage by large consumers.

• The improvements listed above and the base line data generated as a result
would bring greater transparency in the process of privatization (if pursued) and
provide a better estimate of the transition funding needs under outcome driven
privatization models that seek to restore the viability of distribution.

• All central assistance to state governments for the power sector must be
linked exclusively to loss reduction and improved viability.

• The restructured APDRP can, in the very least, help create an authentic base
line. The revised APDRP will provide incentives to State Electricity Boards
(SEBs) that are linked to performance outcomes and will also include incentives
to staff for reduction in AT&C losses.

• The Committee also recommended that liberal captive and new captive regime
foreseen under the Electricity Act 2003 be realized to derive economic benefits
from availability of distributed generation. It will also set competitive wheeling
charges to supply power group to captive consumers. This will pave the way for
open access to distribution networks. To achieve these objectives, the
Committee feels that it is essential to separate the cost of pure wire business
carriage to energy business content in both transmission and distribution at
different voltages. The wires business within the distribution segment is also a
natural monopoly and must be regulated.

• The Committee recommended introduction of availability based tariffs (ABT) for


intra-state sales and upgradation of state load dispatch centres to the technical
level of regional load dispatch centres.

• Committee recommended that gross subsidy surcharge; wheeling charge and


back-up charges are set properly to make the utilities viable after high value
paying customers migrated to new suppliers due to Open Access. These
charges need to be periodically revised and independently regulated.

• Committee recommended that the regulators should set Multi Year Tariff.

• To make RGGVY sustainable the committee recommended that, a business


plan with a viable revenue model needs to be elaborated. A clear pricing and
subsidy policy and the mission’s target to be announced soon and the
franchisees should run the local network.

• The Committee suggested generation of electricity through wood gasifier or by


burning surplus bio-gas from the community bio-gas plants. Such distribution
generators may be able to take electricity to villages sooner than the grid and
tariff should be formulated for such distributed generation for both household
and productive uses including agriculture.

• The Committee has emphasized energy efficiency and demand side


management. The Committee feels that with an aggressive pursuit of energy
efficiency and conservation, it is possible to reduce India’s energy intensity up

Page 9 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

to 25% from the current level. Some of the recommended initiates of the
Committee for quick yield returns are as follows:

¾ Regulatory commissions can allow utilities to factor EE/DSM expenditure


into the tariff.
¾ Each energy supply company/utility should set up an EE/DSM cell.
¾ All utilities should introduce TOD tariffs for large industrial and
commercial consumers to flatten the load curve. Utilities should support
load research to understand the nature of different sectoral load profiles
and the price elasticities of these loads between different time periods to
correctly assess the impact of differential tariffs during the day.
¾ Enforce mandatory purchase of electricity at fixed prices from co
generators (at declared avoided costs of the utility) by the grid to
encourage cogeneration.
¾ Improving efficiency of industrial, municipal and agricultural water
pumping.
¾ Instituting an efficient motors programme. This initiative should focus on
manufacturers/rewinding shops and target market transformation, by
providing incentives to supply energy efficient motors.
¾ Instituting an efficient boiler programme.
¾ Promoting Solar Hot Water Systems. This programme should aim at
both industrial and household needs of hot water.
¾ Undertaking efficient lighting initiative.
¾ Making energy audits compulsory for all loads above 1 MW
The Group agrees with recommendations of the IEP and some of the implementation
strategies are contained in this report.

3.5 DISTRIBUTION OF POWER IN URBAN AREAS

3.5.1 Accelerated Power Development and Reforms Programme (APDRP)

Accelerated Power Development Programme (APDP) programme is part of the six


level intervention strategies for accelerating distribution reforms. In 2001, the
Government of India introduced the Accelerated power development programme
(APDP), with the objective of initiating a financial turnaround in the performance of
the State owned power sector. The Programme was formulated to finance specific
projects for up-gradation of sub-transmission and distribution (ST&D) network and
Renovation and Modernization R&M) of power projects (Thermal & Hydro). During
the year 2000-01 and 2001-02, the Government has provided budgetary allocation of
Rs.1000 crore and Rs.1500 crore respectively to the State Governments as
Additional Central Assistance under APDP. In 2000-01 project costing Rs.1456.78
crore were sanctioned and the Government released Rs.786.29 crore in one
installment. The utilities have utilized Rs. 1306.57 Crore.

In the year 2002-03 the programme was rechristened as Accelerated Power


Development and Reforms Programme (APDRP) and the assistance was linked to

Page 10 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

reforms. Initially the programme covered 63 distribution circles including 3 circles in


Delhi out of the 400 distribution circles in the country. Later the focus has shifted to
densely electrified zones i.e. urban and industrial areas. The programme aims at
strengthening and up-gradation of the Sub-transmission and Distribution system in
the country with the objective of reducing Aggregate Technical and Commercial
(AT&C) losses, improving quality of supply of power, increasing revenue collection
and improving consumer satisfaction. The strategy envisages technical, commercial,
financial and IT intervention, organization and restructuring measures and incentive
mechanism for reducing T&D and cash loss reduction.

3.5.2 The expected benefits from the programme are as follows:

i) Reduction of AT&C losses from the existing around 60% to around 15% in five
years to begin with in the urban areas and high density/ consumption areas.
ii) Significant improvement in revenue realization by reduction of commercial
losses leading to realization of an additional Rs.20, 000 Crore approximately
over a period of 4-5 years.
iii) Reduction of technical losses would result in additional energy equivalent to
nearly 6,000 – 7,000 MW to the system, avoiding the need of 9,000 to 11,000
MW of fresh capacity addition besides avoiding investments to the tune of
Rs.40,000 to Rs.60,000 Crore;
iv) Quality of supply and reliable, interruption- free power will encourage usage of
energy efficient equipments / appliances, which will further lead to improvement
in availability of energy.
v) Reduction in cash losses on a permanent basis to the tune of Rs.15, 000 Crore.
vi) Distribution reform as envisaged above will help States to avoid heavy
subsidies, which are given to SEBs / State Utilities by State Governments.

3.5.3 Financial Progress

The total fund planned under APDRP in the 10th Plan is around Rs. 40,000 crores
with investment component estimated to be around Rs 20,000 Crores and incentive
for cash loss reduction at Rs.20, 000 crores.. Under investment component 583
projects were sanctioned with cost of Rs.19180.46 Crore against this Rs.6131.70
crores were released. The Counter-Part funds tied up were Rs. 7044.34 Crore and
funds drawn were Rs. 4087.04 Crore and Funds utilized were Rs. 9518.13 Crore.
Incentive for reduction of cash loss amounting to Rs.1536.64 Crore has been paid to
Andhra Pradesh, Gujarat, Haryana, Kerala, Maharashtra, Rajasthan, West Bengal
and Punjab for showing cash loss reduction of Rs. 3446.60 crore.

Page 11 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

Table 3.2
Allocation of Funds Under APDP

(Rs. in Crore)
Year BE RE Actual Expenditure
2002-03 3500.00 1089.00 Investment – 1755.52
Incentive – 379.28
Total - 2134.80
2003-04 3500.00 3300.00 Investment – 2356.51
Incentive – 503.30
Total – 2859.81
2004-05 3500.00 1700.00 Investment- 1428.73
Incentive – 73.00
Total – 1501.73
2005-06 1172.00 - Investment – 331.56
(Grant only) Incentive – 515.78
Total – 847.34

The details of the cash loss reduction and incentives released to various states under APDP
are given in Table 3.3 (As on 31st March 2006) :

Table 3.3
Cash Loss Reduction & Incentives REleased
(Rs. in Crore)
Sl. State Year Cash loss Incentive
No. reduction released
1 Gujarat 2001-02 472.74 236.37
2002-03 296.16 148.08
2 Maharashtra 2001-02 275.78 137.89

3 Haryana 2001-02 210.98 105.49


4 Rajasthan 2001-02 275.78 137.71

5 Andhra 2002-03 530.22 265.11


Pradesh
6 West 2002-03 146 73
Bengal 2003-04 605.52 302.76
7 Kerala 2002-03 129.88 64.94
8 Punjab 2003-04 503.88 65.28
Total 3446.6 1536.64

3.6 ACHIEVEMENTS UNDER APDRP

3.6.1 Reduction in AT&C losses:

The AT&C losses which were about 36.81% in the year 2001-02 have reduced to
33.82 % in the year 2004-05. Power Utilities in the states of Andhra Pradesh,
Arunachal Pradesh, Delhi, Goa, Haryana, Himachal Pradesh, Karnataka,

Page 12 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

Maharashtra, Mizoram, Nagaland, Orissa, Punjab, Sikkim, Tripura, Uttar Pradesh


and West Bengal have shown reduction in their AT&C loss. 313 towns covered
under APDRP have shown reduction in the AT&C loss. 212 APDRP towns have
brought down AT&C losses below 20 percent. 169 towns have shown loss below
15% and 38 towns have achieved AT&C loss between 15 & 20% (AP-96, TN-36,
Karnataka-31, Punjab-11, Gujarat-11, Chattisgarh-2, HP-6, Maharashtra-8, Kerala-4,
Rajasthan-3, Goa-1, Tripura-1).

The overall commercial loss (without subsidy) of the utilities reduced from Rs. 29,331
Crore during 2001-02 to Rs. 19,722 Crore during 2003-04. However, the same
increased to Rs. 22,126 Crore during 2004-05. Cash loss reduction of Rs.3447
crores was achieved by states of AP, Gujarat, Kerala, Maharashtra, Punjab,
Rajasthan and West Bengal. The states which are still incurring high losses are
Assam, Bihar, Haryana, Jharkhand, J&K, Karnataka, Punjab, Rajasthan, Tamilnadu
and Uttar Pradesh.

3.6.2 Progress of Metering

(a) 11 kV feeders metering:

At national level 96% feeders have been metered as of now, as against 81% metered
during 2001-02. 100% feeder metering has been achieved in 18 states namely in
Assam, Delhi, Goa, Gujarat, Haryana, Karnataka, Kerala, Madhya Pradesh,
Maharashtra, Meghalaya, Punjab, Rajasthan, Sikkim, Tamilnadu, Tripura, Uttar
Pradesh, Uttaranchal & West Bengal. Union Territories of Chandigarh, Daman &
Diu and Pondicherry have also achieved 100% feeder metering.

(b) Distribution Transformer Metering:

The distribution transformer metering is a prerequisite for carrying out energy audits
and identifies the high loss area in the LT system. The overall DT metering in the
country is still low in most of the states. The maximum extent of DTR metering is
around 25% for the states of Karnataka and Maharashtra.

(c) Consumer metering:

During 2001-02 the consumer metering was at 78%. It has now increased to 92%
during 2005-06, 100% consumer metering has been achieved in the states of Delhi,
Himachal Pradesh and Kerala. Union Territories of Chandigarh and Daman & Diu
have also completed 100% consumer metering. Andhra Pradesh, Assam, Goa,
Gujarat, Haryana, Mizoram, Rajasthan, Sikkim, Uttar Pradesh, West Bengal and
Pondicherry have achieved more than 90%. Majority of the un-metered consumers
belong to agriculture and flat rate categories.

3.6.3 Control of theft and pilferage

Anti theft provisions were introduced in Electricity Act 2003. 13 states have set up
special courts and five states have set up special police stations to deal with theft.
AP, Assam, Delhi, Gujarat, HP, Karnataka, MP, Maharashtra, Orissa, Rajasthan, UP,
Utrtaranchal, WB have set up special courts. Gujarat, Karnataka, Orissa, Rajasthan,

Page 13 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

WB have set up special police stations. Around 12 lakh cases were detected, and in
about 10,000 cases conviction and about Rs.600 crores were realized.

3.6.4 Other initiatives and improvements

• 24 states have constituted Electricity Regulatory Commission and 20 have


also issued tariff order (AP, Assam, Chhattisgarh, Delhi, Gujarat, Haryana,
HP, Jharkhand, Karnataka, Kerala, MP, Maharashtra, Orissa, Punjab,
Rajasthan, TN, Tripura, UP, Uttaranchal, WB).
• 13 states have unbundled, restructured and corporatized SEBs (AP, Assam,
Delhi, Gujarat, Haryana, Karnataka, MP, Maharashtra, Orissa, Rajasthan,
Tripura, UP, Uttaranchal).
• Computerized billing was introduced in most of the states; Spot billing
machines for issuing bill at the time of meter reading were introduced in
several states (AP, Assam, Bihar, Delhi, Goa, Gujarat, Haryana, HP,
Karnataka, Kerala, Maharashtra, Orissa, Punjab, TN, UP, Uttaranchal).
• Customer information about metering billing and collection on websites
introduced in AP, Delhi, Maharashtra, Karnataka, Tamil Nadu.
• Customer care centres opened in several states (AP, Assam, Delhi, Goa,
Gujarat, Haryana, HP, Jharkhand, Karnataka, Kerala, Maharashtra, MP,
Orissa, Punjab, Rajasthan, TN, Tripura, Uttaranchal, UP, WB).
• A number of Distribution utilities mobile repair vans have been launched in AP
and Delhi.
• In number of states headquarters, SCADA has been introduced (Hyderabad in
AP, NDPL in Delhi, Vadodara in Gujarat, BEST & REL in Maharashtra,
Chennai in TN, Jaipur in Rajasthan, Trivandrum in Kerala).
• Introduction of consumer index linking along with geographical information
system has started in some of the states.
• Local communities like self help groups, gram vidyut pratinidhi, franchisees,
and local entrepreneurs are involved in distribution of electricity.

3.6.5 Capacity Building

Capacity building of utilities personnel at all levels has been taken up to train them in
latest technologies and methods of operation and maintenance, project formulation,
project management etc. PMI (NTPC) & NPTI have trained more than 1800
personnel from various utilities. Training of around 25,000 utility personnel has been
taken up under Distribution Reform Up-grade Management (DRUM) in association
with USAID. The training themes include AT&C loss reduction, O&M practices,
demand side management, Safety aspects, performance benchmarking, quality
management, financial management, project development etc. An MBA course for
the distribution managers was introduced under the DRUM training programme at
MDI, Gurgaon.

3.6.6 Addition to sub-transmission and distribution network during 10th Plan

The extent of Sub transmission and Distribution systems at the beginning of 10th plan
on an all India basis was 5769739 km of lines and 176026 MVA of distribution
transformer capacity. This has increased to 6570823 Km of 33 kV, 11 kV and LT
lines and 236070 MVA of Distribution transformation capacity by 31st March 2005.

Page 14 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

This is an increase of 801084 Km of lines and 60044 MVA Distribution transformer


capacities. It will further increase by the end of 10th plan with completion of ongoing
schemes. The addition envisaged by the Working Group on 10th Plan was 828863 km
of 33 KV, 11 kV and LT lines and 65505MVA of Distribution transformer capacity.

3.6.7 Independent evaluation of APDRP Schemes

The Ministry of Power got the evaluation of APDRP carried out through independent
agencies namely TERI (The Energy Resource Institute), SBI Capitals, Tata
Consultancy Services, Indian Institute of Management Ahmedabad (IIMA) and ASCI
(Administrative Staff College of India), Hyderabad to assess the benefits accrued
from APDRP projects vis a vis- expected benefits from the APDRP programme. In
the first phase, evaluation has been carried out for 66 projects, where more than 50%
work has been completed.

The evaluating agencies suggested that information technology should be used


effectively to enhance the benefits, funds should be released directly to the Utility /
SEB concerned, to cut down approval & disbursement time, funding from the Govt.
must be linked to achievement of specific benchmark parameters, rather than based
on the incurred expenditure, project plan with time schedule for different activities
should be pre-defined at DPR stage only, project implementation should be done on
turnkey basis and measures for increasing accountability and measuring
performance should be the main focus areas for attaining commercial turnaround.

In accordance with the above recommendation emphasis is given to GIS based


consumer indexing and distribution transformer based energy auditing for increased
accountability, adoption of information technology for efficiency improvement,
focused monitoring on key performance parameters, to cover all district headquarters
under the programme on priority and establishment of consumer care centers/ Bijlee
Seva Kendras.

3.6.8 Task Force on APDRP

The ministry of power has constituted a Task Force under the Chairmanship of Shri
P. Abraham, Chairman, Maharashtra State Power Generation Co. Ltd comprising of
Members from utilities from different zones and other eminent persons with the
following terms of reference:
i) To assess the current efforts under APDRP;

ii) Analyze the current reforms initiatives that are being pursued by the
states with reference to the objectives of APDRP;

iii) To assess the need for modifications in the light of independent


evaluations and other feed back;

iv) Suggest measures to achieve the objectives of APDRP

Page 15 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

3.6.9 The observations of Task Force

The Task Force observed that some of the utilities adopted feeder approach to make
field officers accountable and measuring their performance achieved very good
results in the form of improvement in all the key performance indicators. The
monitoring of achievements has improved expenditure in many utilities. The Task
Force observed that increase in commercial loss of utilities has not only been
arrested but there is downward trend at the national level. Though reduction in AT&C
losses and DT failure rate has been reported in most of the towns where APDRP
work has been considerably completed the significant reduction was only in few
states. In the feeders where augmentation has been done and the energy
accounting has started outages have reduced and significant improvement has been
achieved in respect of AT&C losses and DT failure rate. The Task Force observed
that AT&C losses of 5.06% was reduced at national level during 3 years i.e. 1.68%
reduction per year as against a target of 9% per year and this achievement can not
be considered as small, as actual implementation after the programme started quite
late. The Task Force observed that improvement in billing and collection efficiency
has taken place in most of the utilities. The Task Force felt that APDRP is still at
initial stage and the full benefits of the programme can not be expected at this stage.
The assessment of benefits from the programme should be made after covering all
the district headquarters at least and when sufficient work has been completed.

3.6.10 Summary of Recommendations of the Task Force

The recommendations of the Task Force are:


a. ARPDP to be continued in XI th plan with focus on auditing and accounting
and reducing AT&C losses in major town and cities It interventions,
technological up gradation, control of theft and pilferage, GIS and consumer
indexing and establishment of Bijlee Sewa Kendra.
b. The conditions for availing assistance under the programme may be made
more stringent with an objective to make States/Utilities to adopt reforms. The
primary conditions as mentioned in the report will have to be fulfilled by the
states for becoming eligible for the APDRP. The states will also have to
commit achievement targets for secondary conditions as approved by the
Ministry, which will be based on the present performance level of the Utilities.
c. The APDRP assistance, both investment and incentive component, may be
extended to the Private Distribution Utilities also. The incentive for loss
reduction by the private utilities may be given to the State instead of the utility.
d. The Task Force recommends following targets for reduction in AT&C losses
by the Utilities:
i) Utilities having AT&C losses above 40%: Reduction by 4% per year;
ii) Utilities having AT&C losses between 30 & 40%: Reduction by 3% per
year;
iii) Utilities having AT&C losses between 20 & 30%: Reduction by 2% per
year;
iv) Utilities having AT&C losses below 20%: Reduction by 1% per year.

Page 16 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

e. The projects taken up under the programme should be aimed at reducing


AT&C losses, improvement in quality and reliability of power and improvement
in consumer services.
f. Utilities should prepare a roadmap with priorities for works to be taken up
under the investment component and execute the work by adopting best
practices.
g. Each Distribution Company may be considered for calculation of incentive
against cash loss reduction. Ministry may devise additional methods also for
incentivizing Utility and Utility employees for improvement in performance.
h. Under the investment component of the programme, the grant may be
increased to 50% of the project cost for the general category states.
i. In order to keep the focus of the states and Utilities towards reforms and the
improvement in the sector, Government should commit sufficient non-lapsable
fund for the programme.
j. The programme may be converted into a Central scheme for speedy
implementation.
k. The assistance under the programme should focus mainly on such activities,
which will help in quick reduction of AT&C loss and improvement in customer
services,
l. The programme should have a provision of 5% for training the Utility
personnel, hiring consultants, undertaking studies, project evaluation etc.
m. The DPRs for the new projects should be made more realistic. The tender
documents and specifications should be standardized by the AcCs in
consultation with the Utilities. It should contain a quality plan and also
provisions for price variations during execution. A variation of plus or minus
10% to 15% may be allowed in quantity or value of items within overall
sanctioned cost of the scheme.
n. Execution of all the schemes should be on turnkey system only by adopting
standard specifications, except in cases where approval of the Ministry is
taken in advance.
o. Utilities, AcCs and Ministry of Power should closely monitor the
implementation of APDRP projects and progress of the Utilities towards
achievement of the set targets.

3.7 DISTRIBUTION OF POWER IN RURAL AREAS - INITIATIVES IN 10th PLAN

During the first four years of the 10th Plan, the PFC has sanctioned financial
assistance of Rs. 8383.83 crore to various States under various schemes for rural
electrification.

A number of initiatives were taken during the X plan period, successively for
household and village electrification viz

(i) Kutir Jyoti Yojana, 2002-04,


(ii) Pradhan Mantri Gramin Yojana 2002-05,
(iii) Minimum Needs Programme 2002-04,
(iv) Accelerated Rural Electrification Programme 2003-04,

Page 17 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

(v) Accelerated Electrification of One Lakh Village and One Crore Households
2004-2005.
(vi) Rajiv Gandhi Grameen Vidyutikaran Yojna was launched from April 2005 and
all the above mentioned schemes were merged in it.

Definition of Village Electrification

At the advent of this scheme, the definition of village electrification was changed.

A brief history of these definitions of village electrification is as follows:

Prior to October 1997

A village should be classified as electrified if electricity is being used within its


revenue area for any purpose whatsoever.

In 1997, the definition of village electrification was modified to provide for the use of
electricity to village habitations. Accordingly, the new definition said:

After October 1997

A village will be deemed to be electrified if the electricity is used in the


inhabited locality, within the revenue boundary of the village, for any purpose
whatsoever.

In Feb. 2004, the definition was made even more encompassing as also target
specific.

New Definition (2004-05)

A village would be declared as electrified if:

(i) Basic infrastructure such as distribution transformer and distribution lines are
provided in the inhabited locality as well as the dalit basti/hamlet where it
exists. (For electrification through Non-Conventional Energy Sources a
distribution transformer may not be necessary)
(ii) Electricity is provided to public places like schools, panchayat offices, health
centres, dispensaries, community centres etc. and
(iii) The number of households electrified should be at least 10% of the total
number of households in the village.

With each change of definition, the number of electrified and unelectrified villages
was set to change.

3.7.1 Progress of rural electrification during X Plan

Out of a total of 593732 inhabited villages as per 2001 Census in the country,
439165 villages have been electrified by February 2006. Similarly, against the
potential of 196 Lakhs irrigation electric pumpsets, 148 lakhs pumpsets have been
electrified as on 31.03.2006.

Page 18 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

In the X Plan document it was proposed to electrify all the balance unelectrified
villages i.e. 97,559 during the Plan. However, in the first four years of the Plan only
19,460 villages have been electrified. Year wise achievement of villages electrified
and pumps sets energized during first four year of X Plan are given in Table 3.4:

Table 3.4
Village Electrified & Pump sets Energised

Years Villages electrified Pump sets energized


2002-03 2626 651095
2003-04 2781 322968
2004-05 3884 329573
2005-06 10169 357995
Total 19460 1661631

3.7.2 Implementation of RGGVY :

RGGVY had originally envisaged electrification of 125000 (based on 1991


consensus) unelectrified villages 7.8 crore in unelectrified households (including 2.34
crore BPL households) in the country. The estimated cost of RGGVY was to be Rs.
16,000 crore, of which Rs. 14750 crore (90%) was expected to be subsidy
component. Out of the total of 29 States in the country, 27 States agreed to
participate in RGGVY (except State of Goa and Delhi). The participating States have
concluded the necessary arrangements amongst REC, State Governments, State
Power Utilities and CPSUs.

3.7.3 Achievements

Under the scheme, works for the electrification of 9819 unelectrified villages in the
States of Bihar, UP, West Bengal, Rajasthan, Uttranchal and Karnataka and 350
electrified villages (intensive electrification) in the States of Karnataka have been
completed during 2005-06 and 9151 unelectrified villages have been electrified
during 2006-07 as on September 30, 2006.

Table 3.5
Achievements under RGGVY

(As on 16.10.2006)
DPRs Sanctioned for 218 districts in 24 States covering 219 Projects
• Un-electrified villages 59441
• Electrified villages 97391
• Households 9910686
• BPL Households 6407226
• Total Project Cost Rs. 8383.83 cr.

Page 19 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

Quantum of major works covered under sanctioned projects


• New 33/11 kV Sub-stations 352
• Aug. of existing 33/11 kV S/Stns. 527
• New 33 kV Lines (km) 6171
• New 11 kV Lines (km) 209735
• New Distribution Transformers 243896
• New LT Lines 87725.13
• Metered Connections (BPL HH) 6407235

Turnkey contracts awarded


• Un-electrified Villages 50706
• Electrified villages 47279
• Households 4978683
• Total Project Cost Rs. 5248.13 cr.
• Total Awarded Cost Rs. 7283.80 cr.

3.7.4 Need for continuation of RGGVY

RGGVY has truly become the engine of rural electrification programme in all States
of India., DPRs from all States are going to be available by 2007. Works have been
started in 153 districts. RGGVY should be continued in the XI plan to achieve the
objective of ‘Power to all by 2012

3.8 DEVELOPMENT OF REVENUE SUSTAINABILITY - FRANCHISEES

RGGVY scheme envisages management of rural distribution through franchisees


who could be NGOs, User Associations, and individual entrepreneurs, cooperatives
or Panchayats. As per the Electricity Act, a Franchisee means a person authorized
by a distribution licensee to distribute electricity on its behalf in a particular area
within its area of supply. Deployment of input based Franchisees is a requirement
under RGGVY scheme to receive funds under the scheme.

Fifteen State Governments have taken action for deployment of franchisees. About
thirty eight thousand villages are covered under franchisee arrangement till October
2006. The majority of these franchisees are in Karnataka, West Bengal, Assam,
Uttaranchal, Uttar Pradesh, and Nagaland. Other states including Bihar, Rajasthan,
Chhattisgarh, Haryana etc. are at various stages of deployment of Franchisees.
Uttar Pradesh has engaged consultants for 6 pilot projects and 15 transaction
projects to develop Input Based Franchisees. These franchisees are mostly revenue
based where the activities are limited to meter reading, billing, bill distribution,
revenue collection, attending to complaints, maintenance of records, minor repairs
etc. The states have committed to convert revenue based franchisees to input based
franchisee.

Page 20 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

3.8.1 Franchisee Experience in the states

¾ The institutional design and structure of Franchisee models vary from state to
state. In Nagaland, the traditional structure of Village Council has been used to
form a sub-committee called Village Electricity Management Board (VEMB) to
function as a Franchisee. Electricity is billed to VEMB on Single Point Metering
(SPM) basis. The objective of SPM is to reduce Technical and Commercial
losses and to involve village community to work as business partner with Power
Department. The VEMB gets 20% financial benefit on the every unit of energy
they sold. The tariff fixed by Govt. for VEMB is Rs. 1.60 per unit and VEMB in
turn sell @ Rs. 2.00 per unit to village consumers. To get full financial benefit
VEMB has to ensure that whatever is the energy supplied through SPM is billed
from consumers in the village, this has resulted in reduction of theft and other
commercial losses in the supply area of VEMB. At present VEMBs are in place
in 452 villages.

¾ In Karnataka, Gram Panchayats have been involved to identify Grameen Vidyut


Pratinidhi (GVP) to function as Franchisee. The GVP is a local unemployed
youth from the same Panchayat. They are working as revenue franchisee and
there is a provision of commission on amount realized above baseline targets
apart from retainer ship fee for achieving the baseline targets. At present 3425
GVPs are already working in 5605 Panchayats falling under all the five
ESCOMs covering 17125 villages.

¾ In Assam, the utility initiated the Single Point Supply Scheme (SPSS) and
appointed input based franchisees and collection franchisees at distribution
transformers. The Single Point Power Supply (SPPS) through franchisee was
first introduced in Digboi division in upper Assam and looking to the success of
the programme it was extended in the entire State. Initially 22 villages with
distribution transformers ranging from 16 KVA to 100 KVA were taken-up for the
programme where 80% of the connected load is in domestic category, now the
programme is in place for 816 villages and efforts are being made to engage
franchisees for another 816 villages. The franchisee can be NGO, user’s
association, a village body or an individual. The mechanism of payment to
franchisee is very simple 10% distribution losses and 15% commission is
allowed.

¾ In West Bengal and Uttaranchal, women Self-Help Groups (SHGs) have been
engaged to function as Franchisee. These are at present revenue franchisees.
The franchisee and people working with franchisee are mostly resident of the
same locality. In Uttaranchal 5321 villages are under franchisee arrangement
and in West Bengal this number has reached to 1169 villages.

¾ Deployment of franchisee is in progress in other states like Uttar Pradesh, Bihar,


Haryana, Rajasthan, Madhya Pradesh etc.

Page 21 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

3.8.2 Impact of Franchisees

While there is a variation in the institutional design of Franchisees across the states,
most of the operational Franchisees at present are either Collection Franchisee or
Input Based Franchisees. Since the formation of the Franchisees in the states, no
systematic evaluation has been undertaken to assess the impact of these on
improvement in management of rural electrification. It is therefore critical to undertake
an Independent Verification and Evaluation study. However, there has been to some
extent documentation of the experiences and internal review of the Franchisee
experience in the state these are summarized below:

(i) Improvement in Collection Efficiency – Experience from all the states shows
that the collection efficiency in these states where Franchisee either as Collection or
as IBF has been implemented has improved.

(ii) Improvement in customer services – Customer services in the rural areas have
improved since the formation of Franchisees. The improvements pertain to billing and
collection and services of minor repair and maintenance. Since the franchisee and
the people working with the Franchisee are mostly residents of the same locality,
there is saving in time and money for the customer.

(iii) Employment Generation – Deployment of Franchisees has also resulted in


employment generation in the local areas.

The key lessons identified from Franchisee experience which are important for
developing future course of replication and up-scaling Franchisee implementation in
the states are:

(i) Simple Arrangement Works - One of the key reason for rapid expansion in
implementation of SPSS scheme in Assam was ease of implementation
arrangement, it was easy to understand (the calculation of commission, standardized
loss levels) and standardized across franchisees. The simplicity of the arrangement
made it easier for the Franchisees to comprehend that irrespective of the distribution
transformer they adopt, the allowed loss would be 10% and the commission would be
15%. This helped in quick implementation.

(ii) Pre-implementation Financial viability of Franchisee Essential - There is a


need for pre-project studies to evaluate the financial viability of the franchisee.
Review of the Franchisees in Assam shows that there are disputes on "Permissible
Loss Levels" and some of the franchisees have started surrendering their areas. The
key reason for the dispute in loss levels is that, initially when they signed the
agreement, only a few were involved in any kind of activity related to the electricity
business. It is only after taking over of the transformers that the Franchisees realized
the actual condition of the distribution system. Also some of the franchisees have
reportedly suffered losses due to following reasons:

ƒ The franchisees that are not technically sound, find it difficult to identify issues
such as meter bypass and unauthorized hooking.

Page 22 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

ƒ In few Franchisee areas, Franchisees are not powerful enough to take action
against those whom they know are getting unauthorized power. Similar
lessons have also been drawn from review of GVPs in Karnataka.

(iii) Franchisee Management Information System (FMIS) is required -


Development of a FMIS to track franchisee performance, learn from experience, their
adherence to contractual requirements and to take early corrective actions is
required. None of the states which have set-up Franchisees have such MIS system.
A similar FMIS is also required to be developed for REC to monitor the performance
of Franchisees across the country.

(iv) Up scaling from Collection Franchisee to Input Based Franchisee (IBF)


necessary – Review of Franchisee implementation by most of the states show that
they have opted for Collection Franchisee. While the choice of Franchisee model is
left open, it has been emphasized that eventually the most effective model would be
an IBF model.

3.8.3 Capacity Building of franchisee

REC has circulated guidelines for formulating the franchisee system and has
prepared a comprehensive document on the possible franchisee models, field
experience shows that in the absence of any formal training, existing franchisees are
facing technical and managerial problems during actual operation. Apart from the
technical aspects of electricity distribution, it is imperative for prospective franchisees
to understand the business opportunities in the system, its management and keep it
profitable. In order to ensure that the franchisee model is sustainable in the long run,
it becomes critical to build capacities of these franchisees. A national programme for
training and capacity building targeted at enhancing the skill set of existing and
potential franchisees and trainers to enable them to play a proactive role in improving
rural electricity access in the country may, therefore, be launched during XI plan
period. Capacity building should go in tandem with electrification of villages so that
adequate numbers of trained people are available to take up franchisees in the newly
electrified and other electrified villages. Capacity building should precede awareness
campaign to educate people about franchisee system for management of rural
distribution and its potential.

3.9 ROLE OF PANCHAYATI RAJ IN FRANCHISEE DEVELOPMENT

The Franchisee Guidelines issued by REC envisage that the Panchayati Raj
Institutions (PRIs) would have a supervisory / advisory role in management of rural
distribution through franchisees. The state Government could also encourage the
Panchayati Raj Institutions to take on responsibility of franchisee as and when such
institutions have developed to the extent that they can undertake contractual
obligations, raise resources from market and can discharge associated legal
responsibilities. PRIs may also be closely associated with the franchisee
arrangement as link between the franchisee and the villagers / consumers as well as
concerned state authorities.

As the PRIs are going to play the key role in development of franchisees for
management of rural distribution, participation of Ministry of Panchayati Raj in

Page 23 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

capacity building at all levels is imperative. Keeping this in view, the committee
recommends that:

¾ The Ministry of Power in collaboration with Ministry of Panchayati Raj may


formulate an integrated capacity building plan including franchisee
development with the scope of wide application across the country to meet the
national goal consistent with the RGGVY scheme.

¾ The capacity building plan may include all aspects of energy/power sector
covering primary education on electricity / energy, energy efficiency, repair
and maintenance of rural electricity infrastructure, metering arrangement,
social engineering, legal and regulatory aspects, MIS for effective monitoring &
control, commercial operations of utility viz. meter reading, billing, revenue
collection, book keeping, disconnections, theft control etc.

¾ For taking up the programme at the country level, establishment of institutions


in each state with regional headquarters and branches at district level may be
considered. For 11th Plan, target should for creation of such institutions in at
least 20 states in different regions and 115 district centers in collaboration with
Ministry of Panchayati Raj and Ministry of Rural Development.

¾ For kick start, established institutions in the area of providing technical


education like ITI, Polytechnic etc. at regional level may also be involved. In
association with established institutions, Certificate courses on such subjects
may also be formulated so as to provide this education on continual basis.

¾ Appointment of a specialized agency / consultant like TERI, Productivity


Council, CBIP, PWC, E & Y, etc. for preparation of course modules / training
capsules on above mentioned aspects with proper documentation of course
material may also be considered. Special attention may be paid to the desired
operational skills for franchisee. The course material should be more
illustrative, inter-active and computer friendly. These materials should be
available for use in any part of the country. A comparative analysis of the
various franchisees in different states be included in the course module.

¾ Initially, the core groups at state level may be trained as ‘trainers’ through a
specialized agency / consultant which in turn may provide training to trainees
in identified institutes in various states / districts.

¾ Association of power utilities should also be encouraged to make this


programme a success and necessary training should also be provided to the
field officers/staff of utilities associated with franchisee management for
effective implementation of franchisee system.

¾ Once the franchisee is appointed, they may be provided on the job operational
training by the field officers of the utilities

Page 24 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

3.10 POWER DISTRIBUTION IN RURAL AREAS THROUGH DDG

3.10.1 Definition of DDG

Decentralized Distributed Generation (DDG) is defined as installation and operation


of small modular power generating technologies that can be combined with energy
management and storage systems, and used to improve the operations of the
electricity delivery systems at or near the end user. These technologies can be
utilized for off-grid as well as grid based.

DDG programme is relevant for India to cover cent percent village and household
electrification in order to meet peak load shortages and to supply quality power at
more economical rate on cost to serve basis. For meeting the rural developmental
needs various types of DDG schemes are required. Each type of DDG caters to a
specific need of an area for which technological solutions may be different and they
call for different institutional arrangements and financing policies.

3.10.2 Potential for DDG

There is a potential to add 10,000 to 15,000 MW capacity through decentralized


distributed generation in 11th and 12th plan. The DDG projects would help both in
electrifying the villages and households and also in generating local employment.
Approximately 2000 substations can be linked with 2 -5 MW DDG projects, adding a
capacity of 4000- 5000 MW during 11th plan. The total cost involved will be Rs. 25000
crore approximately.

3.10.3 Challenges for DDG Projects

DDG is yet to be tried on a large scale in rural electrification projects. There are still
many barriers—technical, financial, regulatory, and institutional—that need to be
addressed adequately. In other words, a clear and well-established framework is
required to design, implement, and encourage DDGs as these are expected to be
aligned to the following policy/programme guidelines:

- Universal access to electricity in India.


- All BPL families to be provided single point free connection.
- Revenue sustainability through SEBs /franchisees.
- Affordable power to remote areas through cost effective DG projects.
- Utilization of locally available, environmentally benign renewable energy
- Sources for providing power either to the grid nearer the load or on stand-
alone basis.
- Gainful utilization of the infrastructure created under RGGVY.
- 24 Hour power supply through reliable quality power.
- Facilitate development of rural load at an accelerated pace.
- Creation of viable and sustainable franchisee development.
- Availability of low cost funds and International acceptance of REC
standards.

Page 25 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

3.11 SHORT TERM STRATEGIES FOR DDG SCHEMES

a. Stand Alone

i) These projects to be implemented by MNER/REC through NTPC, IREDA or


other agencies by setting up Joint Ventures or by any other agency
independently or any other acceptable mode.
ii) The funds available under RGGVY be utilized for the same for village
electrification and / or household electrification etc.
iii) All available technologies of bio diesel/ SPV/ biomass/ mini-micro hydel/ micro
turbines etc. could be considered to provide affordable power to rural areas.
iv) Involvement of local bodies like panchayat, NGOs, SHG or VECs etc in
managing the DDG projects in rural areas.
v) Selection of Rural Electricity Supply providers/ franchisees.
vi) Cost of electricity to be based on cost to serve or avoided cost basis and
affordability.
vii) Capital Subsidy for DDG projects.
viii) Manufacturers of equipment may install and operate the plants for a fixed
duration.

b. Grid Interconnected

Central and State level Government Agencies may participate in the equity of the
grid-connected projects, along with established Private Agencies to form a Public
Private Partnership in setting up various projects in the country. Independent power
producers may also set up such projects. The ownership of the DDG Projects will rest
with the project promoters/ equity holders. The following method may be adopted for
construction:
1. BOT
2. BOOT
3. BOLT

At least 100 “Pilot Projects“ in various states of the country should be commissioned
during the first 2 years of the 11th plan to give large scale impetus to DDG
programme. These “Pilot Projects” should be driven by “Public Private Partnership”
programme.

DDG project owners should be offered the distribution activity in the vicinity by the
leasing of the distribution network to achieve efficiency, cutting losses and adding to
project viability

All projects be selected from the predetermined areas and offer for PPP on
competitive, transparent basis with any or all of attributes:

1. These schemes may range up to 5 MW in order to meet the supplementary


power demand in rural and semi- urban areas.
2. Corporate agencies be encouraged to undertake such projects
3. Suitable standardized size packs may be used in order to reduce production
costs.

Page 26 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

4. All available commercialized technologies whether conventional or non-


conventional may be utilized.
5. Cost of electricity to be on Cost to Serve/ Delivered Cost or Avoided cost basis
for working out viability. Life Cycle Costs Approach can also be considered.
6. Multifuel technologies may be adopted for sustainability.
7. Exemption to be given for income tax, customs and excise duties etc.
8. All concessions extended by states for industrial development also to be
extended for DDG projects.
9. Viability gap funding may be appropriate methodology.
10. Financial Institutions support for energy plantations. Which would meet the
feedstock needs of biomass power/ bio fuels/ bio- diesel plants. For the pilot
projects, support also needs to be extended for R&D efforts and preparation of
DPRs

3.12 MEDIUM TERM AND LONG TERM STRATEGIES

1. R&D on fuel Cell technology to considerably bring down the costs.


2. R&D on all existing technologies to improve the product quality as well as
efficiency levels of the systems to make them more durable and affordable
cost of power.
3. Training of local youth in maintenance of the DDG equipment locally.
4. Improvement in the quality and life of batteries.
5. Biomass cultivation and development of short duration (cycle) high yield
varieties of biomass suitable for bio- methanation / gasification / direct
combustion/ bio-fuels production”

3.13 COST TO SERVE/ DELIVERED COST

The shortage of electricity leads to larger power cuts in rural areas due to more than
double the quantity required to be fed in the grid for a particular delivered quantity
and quality of Power in far off rural areas due to heavy transmission, distribution and
collection losses. In order to bridge the gap between rural and urban areas,
extension of grid through RGGVY is under implementation which only takes care of
the infrastructure issues but does not address the issue of quality and quantity of
power supply. One of the options in this regard is the supply of electricity through
Decentralized Distributed generation method whether off grid or through the grid
nearer the load centres.

3.14 ROLE OF STAKEHOLDERS

i. State Government

• Provide an enabling framework for streamlined implementation and operation of


the DDG scheme.
• Publicize and make aware the stakeholders about potential sites/ locations for
implementing the DDG schemes.
• Target for and incentivise for taking up the DDG schemes in potential areas
including development of supply providers. Make necessary provisions in the
State Budget suitably.
• To provide land on nominal lease.

Page 27 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

• Maintain system of constant checks and controls through local administration


with involvement of the beneficiaries for more participative interaction.

ii. State Utility/Discom

• Assist the Supply provider during identification and execution of the scheme.
• Support the supply provider during the initial operations and ‘stabilization’
period.
• Lease/sell the substation infrastructure to DDG operators

iii. Local Administration

• Act as trustee of beneficiaries interest w.r.t the investments made, security of


assets, continuity of the system and stakeholders.
• Provide for quality of service measures and controls ensuring streamlined
operation of the system without any undue interference.

iv. Supply Provider

a) Technical

• Operation and Maintenance of the main plant and equipment.


• Breakdown maintenance and repairs of HT & LT lines.
• Maintenance of Transformers and other equipments.
• Maintaining the reasonable stock of line and sub-station materials required for
repairs.
• Replacement of failed transformers and equipments.
• Install meters to all unmetered installations.
• Attend to consumer’s complaints and grievances.
• Prevent pilferage and thefts of energy
• Receive application for new connect ions.
• Prepare feasibility report and estimate for new connections.
• Sanction estimates for new connections as per norms and approved
policies/procedures.
• Prepare estimates and drawings for extension and improvement works to bring
down energy losses to acceptable levels, check theft and energy accounting.
• Servicing of new installation with meters.
• Execution of improvement works.
• Identify inefficient pumpsets and arrange for replacement with efficient
pumpsets by bringing in necessary investments.
• Submission of prescribed reports to the Distcom/Government.
• Identifying unauthorized installations and take suitable action.
• To follow the provisions relating to safety and electricity supply.

b) Revenue

• Meter Reading
• Billing
• Collection

Page 28 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

• Maintenance of records
• Submission of monthly accounts and statistics to respective Discom/
Government.
• Reply to audit queries.
• Use necessary hardware/software for issuing computerized billing and
generating reports.
• Collecting government charges/ levies and paying the same to the Government.

c) General

• To educate consumers in its jurisdiction on the efficient use of equipments such


as lighting, pump sets etc. for conserving energy.

EDUCATE COMMUNITY ON SAFE USE OF ENERGY

3.15 ROLE OF REC

REC may be declared the nodal agency for DDG schemes to provide single window
support during project formulation, seeking clearances, appraisal, approval and even
ensuring financial closure. It will assist in selection of rural electricity supply provider,
training of village youth and vendor development for providing reliable services.

Commercially viable projects in DDG sector will be either directly financed by REC or
through the route of refinance facility to banks, state Corporations, RRBs, State
Cooperative Banks, SIDBI etc

REC may also take up nation wide survey of various sources of energy available in
the villages & towns in a time bound manner by engaging State/ private agencies in
different zones. REC may accordingly select suitable sites, setup pilot projects at its
own cost and subsequently transfer them on BOT, BOOT or BOLT basis. REC may
also engage itself in Public Private Partnership to setup such projects. REC may
suitably engage various consultants and construction agencies

3.16 INSTITUTIONAL AND FINANCIAL MODELS

The programme should provide medium and long-term financing to private project
developers, non-governmental organizations (NGOs), micro financing institutions
(MFIs) and community cooperatives etc. for decentralized distributed electrification
schemes. The funds are to be made available to private enterprises, NGOs, MFIs
and community cooperatives for projects up to about 5 MW. The different financial
models may be based on:

• Capital subsidy/ Viability Gap funding


• Revenue subsidy
• Bundling of services
• Linkages with existing programme

Page 29 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

3.17 SPECIAL FOCUS AREAS FOR 11TH PLAN

3.17.1 Separation of Agriculture Feeders

It involves installing a separate feeder to supply to the agricultural load as distinct


from the feeder supplying the non-agricultural loads in rural areas. This facilitates
proper accounting and removes distortions in loss measurement due to un-metered
agricultural loads and load management during peak hours. Andhra Pradesh,
Gujarat and Punjab have initiated steps to separate agriculture feeders.
The working group recommends that a programme should be launched for
separation of feeders in those states where the percentage of agriculture
consumption is more than 20% of power. In other states single phasing of rural
mixed load feeders may be taken up which involves use of change-over switches at
sub-stations. The approach envisages supplying single phase rural lighting load
through three nos. of single phase transformers. During the normal operation, the
agricultural load continues to be supplied from the three phase transformers. On
operation of the changeover switch, there will be no supply to the 3-phase load on
the 11 KV distribution network whereas single phase supply is available to the
lighting and fan load. On revising changeover switch, normal 3-phase supply shall be
restored. Cost and time go in favor of this approach. Integrated energy Policy also
recommends bifurcation of agriculture pumping load from the non-pumping load in all
rural feeders. It further recommends using of available technological options to limit
and measure the amount of agriculture pumping energy provided.

There is also an urgent need to improve the efficiency of the pumpsets by way of
changing over to high quality BIS certified pumpsets. Farmers have to be educated
on the benefits of efficient pumps. They should be provided necessary finance for
replacement of pumpsets.

3.17.2 Metering of Agricultural Consumers

The system of un-metered supply at flat rates for agricultural consumers is a major
stumbling block in the way of accountability and improvement in efficiency of
distribution system. This system makes it difficult to have estimates and actual
consumption and precise estimate of losses. This effects two sectors, power and
water resources. Un-metered supply leads to unrestricted exploitation of the ground
water and rapid depletion of the water table.

In most of the states it is difficult to segregate rural electricity consumption on the


basis of its use in agricultural, commercial, domestic and industrial segment in the
absence of appropriate metering system. Although agricultural consumption is the
most significant one, reliable data on agricultural consumption is not available.
There are 1,44,45,014 pumpsets/tubewells in the country as on 31st March 2005.
The average capacity and electricity consumption per pump set was 3.91 KW and
6131 KWh per annum respectively. The electricity consumption during 2004-05 in
agriculture sector is third highest being 22.93% of total consumption of electricity in
the country. Whatever is not billed in domestic, commercial and industrial categories
is often treated as consumption under agriculture. Power theft is hidden under
agricultural consumption. Utilities may also deliberately overestimate the un-metered

Page 30 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

agricultural consumption to get higher subsidy from the State Govt. and also project
reduction in losses.

One study has found that owners of electric tube-wells paying flat rate tariff operated
their pumps for 40% – 250% greater hours per year as compared to diesel tube-well
owners which proves the fact that flat rate leads to wastage of electricity with adverse
impact on the water table. Metering of agricultural consumption allows quantifiable
supply to agriculture which is a necessary condition for transparent subsidy
mechanism.

Though new legal framework provides for compulsory metering of electricity supply,
most of the agricultural consumers are supplied un-metered power on flat rate basis
(Rupees/HP/Month). Unmetered supply on flat rate basis has adverse implications
for accounting and auditing of energy besides inefficient use of power and over
exploitation of ground water resources. Section 55 of the Electricity Act provide that

“No licensee shall supply electricity, after the expiry of two years from the appointed
date, except through installation of a correct meter in accordance with regulations to
be made in this behalf by the Authority:
Provided further that the State Commission may, by notification extend the said
period of two years for a class or classes of persons or for such area as may be
specified in that notification.”

Despite all these provisions, power supply to agriculture continues to be un-metered


on flat rate basis in most of the states. Besides, resistance for installation of meters,
the cost and practical difficulties in regular billing and collection are the stated
reasons for not providing meters for agricultural consumers. In this context there is a
need for alternative approaches for metering agricultural consumers. It also requires
full support from the Government/ Political establishments.

The working group recommends that power supply for agricultural purposes should
be hundred percent metered in phased manner to remove distortion in the data
regarding consumption, losses, and subsidies.

3.17.3 Conversion to HVDS System

Over the years, large scale expansion of urban system and rural electrification
program in the country, has resulted in considerable expansion of Low Tension
distribution network. To meet the increasing demand due to load growth, size of the
DTR’s has been constantly increasing. As a result the lengthy of LT lines/circuits is
also increasing resulting in high load losses in LT lines, excessive voltage drops and
frequent faults on LT network and higher rate of failure of distribution transformers. It
is estimated that for the same power demand or load , the current in LT system is 28
times in the 11 KV system. Thus, with switchover to 11 KV systems, load losses are
scaled down 800 times and voltage drops are reduced to a negligible level. High
Voltage Distribution System (HVDS) envisages running 11 KV lines right up to the
loads and setting up small sized distribution transformers and extend supply with
least LT lines. Many states are introducing HVDS system. The benefits of HVDS
system are, theft control, sharp reduction in system losses, effective utilization of
transformer capacity as it would free the transformation capacity from feeding the

Page 31 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

power losses in the downstream LT lines, reduction in voltage drops, reduction in


failure rate of DTR due to large transformers, long lines and weak load monitoring.
Reduction in DTR failure rate results in enormous savings in cost and time for
repairs, replacement and outages. Since HVDS caters to 5-6 consumers it gives a
sense of ownership to the consumers and the system is well secured. Several
studies revealed that distribution losses can be brought down considerably by this
system.

Though, large scale implementation of HVDS would entail huge investment, the
benefits from it are huge, immediate and sustainable and they offset the investment
burden given the high level of losses and the potential of HVDS to reduce losses.
This system is best suited to meet the problems associated with scattered loads and
to effectively deal with theft of energy by hooking directly from LT lines which is very
common in rural and urban areas. Already states of AP, Delhi, Gujarat, Maharashtra,
UP, WB and Karnataka are implementing HVDS. The 11th plan should focus on
switching over to HVDS system through a suitable investment strategy in a phased
manner in order to bring down the HT: LT ratio to 1: 1 from the present estimate level
of 1:2.5. Attempts should be made to avail CDM benefits from the scheme.

3.17.4 Priority to IT Applications

There is a need for widespread application of IT in the power sector with a focus on
distribution. Ministry of Power has set up IT Task Force with a view to use IT as a
strategy to improve commercial and operational performance of distribution and for
its effective implementation. Today, a number of utilities are using IT applications to
improve their commercial and operational performance. However, adoption of IT as
a tool for automation and efficiency improvement is sporadic and lacks focus. There
is a wide variation in the states in application of IT tools.
The Task Force recommended creation of comprehensive IT blue print for the Indian
power sector that incorporate the global best practices. The task force suggested a
3-5 years IT implementation road map with both short term and long term IT
initiatives. In short term, priority should be use of IT in commercial process and in
improving the quality of supply in selected areas. The long term area should cover
the business process. Asset and work management, outage management and
distribution automotive should be implemented in parallel. Material management and
support process such as human resource, finance, accounts, should be IT enabled in
the phase. The task force also felt that SEBs should also have an effective
management information system for decision, support, improved decision making.
The committee suggested that implementation should be done by accredited
agencies. No concerted effort has been made to implement the recommendations of
the Task Force. The Task Force recommendation should be implemented in the 11th
Plan.

The electricity Act, 2003 ,National Electricity Policy and Tariff policy envisage
development of Open Access, ABT and Energy Accounting at the state level. These
involve emergence of new market mechanisms having complex commercial
arrangements. IT application will facilitate implementation of such complex
commercial arrangements. Therefore priority should be given to set up IT
infrastructure at various levels in the distribution business in the 11th Plan. The blue
print for IT of the utilities should take into account the future market structure, the

Page 32 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

operational requirement and have IT as a key component of business strategies in


the long term business plans. There is need for complete mapping of IT usage in the
Distribution Segment of the country. The working group recommends that a
comprehensive IT blue print should be prepared and the focus should be on
integrated approach to get the best results from the IT applications.

Under APDRP, utilities should spend the incentive grant on cost effective IT related
solutions in the distribution sector. The states/ utilities that have made significant
advance in IT applications should move towards complete integration of various sub-
systems and for adopting the best international practices.
Implementation of IT based billing and collection systems should be introduced to
obtain immediate results in commercial loss reduction. A comprehensive Business
Process Re-engineering (BPR) of all commercial processes needs to be done to
ensure tapping of all revenue leakages and systematic implementation of IT based
tools. Many states have employed these tools and gained significant improvements.

From customer point of view, customer information is very important which usually
includes billing and accounting functions. Priority should be given to improve
customer care through IT solutions. Andhra Pradesh has set up 336 customer
service centres which handle services such as new service connection, additional
loads, name change, category change, line shift, DTR shift, billing complaints, meter
problems, broken poles etc. The cost of one CSC to serve 2 lakh customers is 15
lakh one time and Rs.84,000 recurring cost per month. The working group
recommends all utilities should set up customer service centres in all the towns on
priority. The total urban population of the country as per 2001 census is 28.37
crores. If we assume that household has five persons, there are 5.67 crore urban
households. To cover entire urban population with customer service centres on the
lines of Andhra Pradesh, the cost would be around Rs. 42 crores.

3.17.5 Consumer Indexing and GIS Based Database

Geospatial database developed through GIS based Consumer Indexing and asset
codification integrated with business processes of utility provides the utility a
wherewithal to reengineer business process for transparent and quick decision
making process. It helps in addressing metering and billing issues, new connection
release, fuse off call etc. under the aegis of customer care centre. Surveyed and
validated Feeder overlaid on satellite imagery with landmarks would enable
preparation of correct estimated works and consequently faster implementation
without contractual litigations.

Many utilities have used GIS for improvement in performance. What is required is
integrated solutions. In the 11th Plan integrated GIS mapping and Consumer
Indexing should be given priority in all the towns.

3.17.6 Reliability Monitoring of Power Distribution Systems

Normally power is generated at a voltage of 10-20 kV AC in a power station and


stepped up by power transformer to a transmission voltage of 132/220/400 kV for
transmission through transmission lines, to a power sub-station near the load centre.

Page 33 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

In this sub-station, power is then stepped down to 66/33/11 kV level. From this sub-
station, 33 kV/11 kV feeders are laid for supplying power to the high voltage
consumers or to distribution transformers, which convert it to medium voltage level of
415 V, for providing service connections to consumers at 415 V (3 phase) or to low
voltage consumers at 230 V (1 phase) through a combination of 415 V lines up to
the pole and then on through service connections to the consumers by underground
cables/overhead cables.

3.17.7 Reliability Index

This is defined as the ratio of Customer-hours available over a given period of


time to the total number of Customer-hours that should have been available over
the same time period.

At present CEA carries out reliability monitoring of power distribution systems of


Distribution Companies (Discoms)/State Electricity Boards ( SEBs), in terms of
outages of 11 kV feeders, on monthly basis, in respect of State Capitals and
major urban agglomerations. The reliability monitoring is based on the following
two parameters relating to an outage. Outage indicates all ‘No supply conditions’
due to grid constraints, planned shut downs and forced shut downs including
momentary shutdowns:

1. Outage duration per outage ( in Hours), which is the ratio of total outage duration
of the 11kV feeders to the number of outages of 11 kV feeders and indicates the
‘No Supply Duration of an Outage’. This is analogous to CAIDI.

2. Number of outages per feeder, i.e. total number of outages of feeders divided by
total number of 11 kV feeders, thereby indicating the ‘Average number of Outages
of an 11 kV feeder in the system.’ This is analogous to SAIFI.

The reliability monitoring is to be gradually brought in line with the world practice
i.e. to measure the outage in terms of consumer hours and number of consumer
interruptions. The reliability monitoring will become more fruitful once ‘Consumer
Indexing’ i.e. linking of every consumer to the feeder is completed by all the
Discoms/ (SEBs) and will provide a direct index for customer satisfaction.

3.17.8 Akshay Prakash Yojana

Maharashtra Distribution Company has launched Akshay Prakash Yojana (APY).


The programme is based on collective responsibility of the inhabitants of the village
and is carried out voluntarily for ensuring better quality of supply and other social
benefits. The villages are not pre identified and the adoption of APY entirely depends
on the initiative and awareness of the persons staying in villages.

Under the scheme, villagers voluntarily restrict the use of any 3 phase load during 5
pm – 11 pm on week days. Only lighting load is utilized. During 5 pm – 11 pm the
load is restricted to 20% of full load.

Page 34 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

Load restrictions are supplemented by removal of hooks and unauthorized heavy


consumption devices like heaters and hotplates. Apart from this the scheme
envisages adoption of energy saving lighting, pumps and use of capacitors.

Surveillance committees for monitoring electricity use (Veej Dakshata Committee -


VDC) are formed by the villagers. These committees supervise removal of all
unauthorized connections. Patrol are organized by villagers to uncover theft and
misuse of power. All the consumers voluntarily adopt metered connections. The
villages bodies like Gram Sabhas pass resolutions to carry out the activities required
for implementation of the scheme.

Awareness levels in villages is the most important factor that enables adoption of
APY by villages. Communicating effectively to the villagers that electricity is a scarce
commodity and stressing on the need for conservation has been crucial for the
success of the scheme. The scheme has support of the top management of the
utility and the State Government.

3.17.8 Programme on Decentralised Distributed Generation (DDG)

DDG for village electrification in remote areas and also for overcoming shortage of
power. Supplementary Power supply needs are essential for protecting the already
created infrastructure under RGGVY. This programme will cater to all such needs.
Pilot projects should be set up initially to gain experience and to instill confidence.
Thereafter, a National Programme on DDG be launched under the PPP.

REC/PFC may introduce reform to result programmes by extending large value, long
term loans as the mutually agreed reform conditionality.

DDG be offered capital subsidies or viability gap funding under the PPP programme.

REC to set up a wing to lay down the specifications / standards for the equipment
suppliers.

REC/PFC may finance the power equipment manufacture in their modernization and
expansion plans.

REC/PFC may float a Venture Capital Funds to encourage manufacture of critical


quality components used for power infrastructure and provide ready market for such
products at competitive rates

3.17.10 Mobile vans with GSM connectivity

This will enable prompt communication and detection of faults and speedier
restoration of supply. Five thousand vans can be inducted to start with. More
numbers can be added to have a target of atleast 10,000 such vans in the country in
the 11th plan to start with.

3.17.11 e- Seva / Bijli Seva Kendra/ Customer Care centre

Page 35 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

These are tools for better customer service and to bridge the digital divide in the rural
areas for providing access through Information technology for services to the people
living in rural areas. These type of centres can offer different services like payment of
bill/ taxes, registration of complaints, providing of information, booking for
connections etc. These kinds of centres can solely be managed by women through
self help groups.

3.17.12 Energy Accounting and Auditing

Measurement of technical and commercial losses is the first step in the direction of
reducing T&D losses. Energy accounting is essentially a tool for energy management
and helps in breaking down the total energy consumption into all its components.
Energy auditing would provide the means to identify the areas of leakage, wastage or
inefficient use. This would help in identifying high loss areas and measures suitable
for reduction of T&D losses.

Preparation of an effective energy account will be possible only if:

• Meters are installed on both sides of each element of the network.


• All the consumer installations are installed with accurate energy meters.
• Energy meter readings are taken at sending end and at all the consumer
installations.
• Similar accuracy class meters are installed both for measuring input to system
and energy sales.
• Meters are regularly tested and calibrated.
• Electronic trivector meters with data logging facilities are provided on the 11
KV feeders/ secondary side of distribution transformers to record load curve
which facilitates assessment of load factors and loss load factors.

The following energy audits will be essential for targeting loss reduction initiatives:

• Sub-Transmission system losses


• Voltage level wise losses
• Geographical area wise up to smallest Administrative unit loss measurement (/
Zone/ Circle/ Division/ Sub-Division etc. depending on the terminology in use
by the utilities)
• 11 KV Feeder wise losses
• Distribution Transformer wise losses

For proper measurement of losses, metering is very critical. The biggest constraint
today is absence of 100% metering at various stages. Though in the 10th plan there
has been significant improvement in metering at consumer level and 11KV level, the
metering at Distribution transformer level, which is primary requirement for effective
energy auditing metering, is very poor even in progressive states like AP (less than
9%) and Karnataka (24%).

Many states have taken various steps for energy audit by providing inter-phase
metering but still the proportion of units billed on metering basis as percentage of
total energy input is about 50% in most of the states. In Andhra and Maharashtra it is
52 %, in Gujarat and Karnataka it is below 50%, in Rajasthan it is 42% and Punjab it

Page 36 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

is 54% and in Haryana it is 44% to mention a few important states. Kerala however
has 74% metered sales. The high percentage is mainly because of unmetered sale to
agricultural consumers.

Another issue is replacement and repair of defective meters promptly to ensure


proper accounting of energy. It is important to ensure installation of high precision
tamper proof electronic meters. Any meaningful energy accounting and auditing is
possible only if these conditions are met.

The focus of the 11th Plan should be to standardize energy accounting and auditing
practices and incentivising efforts of utilities undertaking complete accounting and
auditing exercise. The metering at various levels and providing a code to each
consumer will give complete and accurate baseline data. By the end of 11th Plan
Utilities should put in place complete Energy Accounting and auditing practices by
ensuring metering at all levels.

3.17.13 Load Management

The current installed capacity in India is around 1,26,800 MW which is inadequate to


meet the increasing demand. Today we are having energy and peak power
shortage. With targeted annual GDP growth of 8% the energy requirements of the
country are expected to go at a higher pace. In this scenario load management is
important to ensure supply to feeders feeding critical emergency loads and curtail
supply to other loads. Load management will also enable supply of power to higher
revenue feeders while curtailing supply to low revenue feeders. It is also critical for
system stability. For effective load management, utility should adopt load
management at 11 KV feeder level rather than 33 KV feeder level.

The distribution automation is a key requirement for load management. SCADA is an


important tool for load management. Some distribution utilities have already drawn
plans for introduction of SCADA. Hyderabad city is now fully controlled through
SCADA system. SCADA also helps in fault localization, facility management and
trouble call management. In the 11th Plan all the million plus cities (27) should be
covered under SCADA. The cost per introduction of SCADA in Hyderabad was

Page 37 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

estimated Rs. 40 crores which has a population of 36.37 lakhs as per 2001 census.
If we introduce SCADA in all the million plus towns, the total fund requirement would
be around Rs.1000 crores. Other tools for load management such as micro-
processor based load limiters to restrict supply to agricultural feeders and Automated
Meter devices to monitor feeder, DTR or consumers for consumption curve analysis
should be encouraged.

3.18 NEW PROGRAMMES/SCHEMES FOR 11TH PLAN

3.18.1 Special Scheme for Urban Poor

In the urban areas people below poverty line live in slums. 2001 census has
provided slum demography based on actual count. It is based on areas notified as
slums by the state / local Government, recognized as slums by state / local
Government and those areas which have at least population of 300 living in
congested tenements in poor living conditions. As per the Census 640 cities/towns in
26 states/union territories have reported slum population. Andhra Pradesh has the
largest number of towns (77) reporting slums followed by Uttar Pradesh (69), Tamil
Nadu (63) and Maharashtra (61). A total of 42.6 million Population live in slums.
This constitutes 15 per cent of the total urban population of the country and 22.6
percent of the urban population of the states/union territories reporting slums. 17.7
million Slum population has been reported in the 27 cities with million plus population.
Most of the slum dwellers are living below poverty line and can not afford the initial
cost of electric connection. There is need for a special scheme to provide assistance
to the urban poor. Most of the people in slums are living in unauthorized colonies.
There are 4.62 crore slum dwellers. Assuming that the average family size is five the
total households will be 92.40 lakhs. If we assume that fifty percent of them do no
have electricity in their dwelling units the total targeted households for providing free
electric connection will be 46.20 lakh households. At the present rate of Rs 1500 per
household connection as per RGGVY norm, the total cost for providing free electric
connection along with a meter will be Rs 693 crores.

The Working Group recommends that a special scheme should be introduced in the
11th plan to provide 100% subsidy for the urban poor for electric connection. The
scheme should cover all those families living in regularized colonies and in the
houses provided under Valmiki Ambedkar Awas Yojana (VAMBAY) scheme of
ministry of urban employment and poverty alleviation.

3.18.2 One MW Power Plants for Distribution of Electricity in the Rural Area

Rural areas have been recognized as distinct entity in the Electricity Act, 2003 for
electricity supply. More than 70% of the population lives in rural areas and very large
part of the rural population are without access to electricity. There is wide regional
variation among the states regarding access to electricity. The Electricity Act
mandates the Government to endeavor to supply electricity to all areas including
villages and hamlets. The important provisions relating to rural supply are :

Section 13 – license exempted for any local authority, Panchayat Institution, users’
association, cooperative societies, non-governmental organizations and franchisees
to supply in the rural areas.

Page 38 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

Section 14 - No license required to generate and distribute in a notified rural area.


Rural areas to be notified by the State Government.

Most of state government have delayed in notifying rural areas. However the
redeeming feature is now most of the state governments have notified rural area.
Now the efforts have to be made to promote generation and distribution of electricity
in the rural areas by private enterprises and other bodies. To start with power plants
with optimum one MW capacity should be encouraged in the rural areas. In line with
Rural Electrification policy these projects should get automatic approval for land use
change pollution clearance, safety clearance on the basis of certification. They
should also get priority for grid connectivity if requested. REC should frame schemes
for promoting optimum 1 MW power plants for providing necessary technical and
financial support. Suitable subsidy has to be built into the scheme to make it
attractive and viable. Efforts should be made to align these schemes with Waste
Land Development schemes of Rural Development and Forest and Environment
Ministries to ensure coordinated approach.

3.18.3 Centres of Excellence for Distribution of Power

The Electricity Act has opened new avenues for bringing private participation in the
distribution sector. The proviso to Section 14 of the Electricity Act states that:

“in a case where a distribution licensee proposes to undertake distribution of


electricity for a specified area within his area of supply through another person, that
person shall not be required to obtain any separate license from the concerned State
Commission and such distribution licensee shall be responsible for distribution of
electricity in his area of supply”

Accordingly, a person who undertakes the distribution of electricity for a specified


area on behalf of the Distribution Licensee will not be required to obtain any separate
license from the concerned State Commission.

Legal frame-work is in place for variety of actors to participate in electricity


distribution business. There is a need for setting up centres of excellence for
distribution in various parts of the country. These centres should be provided
complete support to emerge as models for other intending players in electricity
distribution, particularly in the rural areas. Today, REC is the nodal agency for
implementing RGGVY scheme. REC has a long experience in financing and
providing other technical support to the state utilities in the rural sector. REC is in a
sound financial position with a paid up share capital of Rs.780 crores and net worth
of Rs.3779 crores and it figures among the top ten PSUs in the country. The
business per employee ratio of REC is 21.98 crores and it has paid highest dividend
of 30% during 2004-05. REC’s contribution in village electrification is well known. It
has contributed for electrification of more than 5 lakh villages and energisation of 143
lakh pumpsets. Cumulatively, Rs.44, 550 crores disbursed under REC financed
schemes up to 31st March 2005. To capture the new opportunities, REC should play
a major role in electricity distribution business. The Committee recommends that
REC should set up centres of excellence for distribution in all the states to take up

Page 39 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

rural distribution by setting up a subsidiary company. In the 11th Plan 500 such
centres should be set up.

3.19 GRICULTURE SECTOR - SUBSIDIES AND CROSS SUBSIDIES

Agricultural consumption constitute substantial portion of consumption of electricity.


The tariff for agriculture consumers is one of the most contentious issues. In the pre-
reform period, State Government determined virtually all tariffs to be levied by the
state owned vertically integrated State Electricity Boards even though legally, utilities
were empowered to determine their own tariffs. Agricultural tariff is politically
sensitive in nature. As a result, most of the State either heavily subsidize agricultural
consumption or provide free power.
More than 23 percent of total energy sale of the utilities goes to Agricultural
consumers. It is estimated that against average cost of supply of Rs. 3.60/KWh for
energy made available to the consumers, average price of Electricity to Agriculture
consumers is barely 42 Paise/KWh. Cross Subsidy on energy sales has been
increasing over the years because of the policy of the some of the states to provide
electricity at subsidized rates to agriculture and domestic consumers. While some
state governments partly compensate the SEB’s for the subsidized sales of electricity
to agricultural and domestic sectors, others do no provide any compensation at all. It
is recovered through the cross-subsidy mechanism.

Subsidy to agricultural consumers will continue to be the major issue in the sector as
it has political implications. Since subsidies are likely to continue in the near future,
the focus should be on efficient administration of subsidies by using prepaid metering
technologies including smart cards to provide life line energy to the poor section. The
subsidies should be administered by the irrigation or agriculture departments of the
states.

3.20 WATER ENERGY NEXUS

Efficient use of water in Agriculture could result in considerable saving in energy.


The agriculture sector in India uses 85% of the country’s available fresh water.
However, irrigation efficiency is only 20-50%. In other words, Indian agriculture

Page 40 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

wastes up to half of the country’s fresh water supply. Although from a basin
perspective, much of the wasted water is reused, significant amount of water is
wasted primarily due to irrigation inefficiencies. There are inefficiencies on the energy
front as well. Agriculture accounts for about 24% of the total electricity consumption
in India. The consumption is somewhat higher in the states like Andhra Pradesh,
Gujarat, Madhya Pradesh, Uttar Pradesh, Karnataka, and Haryana, where
agricultural electricity use is between 35-45%. However, sale of this electricity
amounts to no more than 5-10% of the state electricity boards’ revenues.

The adoption of flat rate pricing for agricultural power is cause for this perverse state
of affairs. Under this system, a farmer pays a fixed price per horsepower per month
for electricity. Therefore the marginal cost of pumping water is zero. This leads to
energy wastage, over-pumping and inefficient selection of crops. Flat rate pumping
also masks the true cost of power to farmers. The tariff structure and the poor
combination of technology and management are responsible for water loss,
unsustainable exploitation of groundwater and the high energy losses associated
with the distribution and end-use of electricity in irrigation water pumping. Significant
energy losses are associated with the distribution of electricity and in the poor
selection, installation, maintenance and operation of the electrical motor pump
system. A vicious cycle operates two sub-systems in tandem: the electrical
distribution system and the water pumping system.

The performance of the Indian power sector is increasingly dependent on how


efficiently irrigation water is used and paid for. Water withdrawal is an energy
intensive operation performed throughout the agricultural sector that results in a third
of the power consumption in the country being used for the roughly 50% of the
national irrigation consumption extracted from groundwater resources. Highly
subsidized power supply policies for agriculture have major implications for the
overall condition of the power sector and associated water resource.

The level of attention paid to water use efficiency is directly proportional to the prices
charged for water servicing. Rising prices lead to increasing attention to water use
and, in the long run, more efficient use of water.

Addressing water and energy use efficiencies in the Indian agricultural sector
requires a strategic combination of several interdependent components. There has to
be central and state policy dialogue on power and water sector reform to develop an
energy and water framework. Commercial practices have to be introduced in rural
power distribution in order to expand the domain of power planning beyond the
customer side of the electrical meter to encompass the water well, the exploitation
and recharge of aquifers and the management of the watershed as a whole. It is also
essential to involve the rural consumer in partnership to advance energy and water
use efficiency, thereby improving reform prospects.

¾ The approach paper of the planning commission for 11th plan indicates a
growth of 4% in Agriculture from 2% at present. This would mean large scale
exploitation of irrigation potential. Special efforts are needed for better
utilization of ground water potential especially in U.P., Uttaranchal, Jharkhand,
Bihar, Orissa and West Bengal.

Page 41 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

¾ In areas where level of ground water exploitation is nearing saturation point or


where there is a need for conservation of power and water, a new approach is
called for. Fixing the quantum of water required for raising crops in relation to
areas cultivated, power needed to draw out ground water from varying depths
could help set standards in conservation of water and power. There is a case
for levy of a combined charge for water and power to secure water
conservation and energy use efficiency.
¾ The priority sector status available to REC for the energisation of Agricultural
pumpsets etc was recently withdrawn which should be restored in order to
enhance the pumpset energisation programme during the 11th plan to at least
35 lakh pumpsets.
¾ Diesel pumpsets presently being utilized should be substituted by biofuels so
that use of diesel is avoided. The bio fuels can be produced locally and a road
map may be set up by the States for cultivation of Jatropha or other plants for
producing biofuels for substitution which are renewable and environment
friendly. CDM benefits could also be claimed.
¾ Feeders for Agriculture should be separated and to counter the inductive
loads, capacitor banks may need to be installed. Feeder separation would
allow regulation of operation hours of the pumpsets.
¾ The subsidy extended on Agricultural tariff should be fully compensated by the
states. Free power if extended by the states should target small and marginal
farmers only.
¾ The Agricultural pumpsets should be of international standards with focus on
energy efficiency and the benchmark standards of the indigenous equipment
should be raised accordingly and use of the same to be made mandatory/
obligatory wherever free power or subsidized power is made available.
Relaxation may be permitted only if the consumers are ready to pay a suitable
minimum tariff.
¾ In the Agricultural Sector, the pumpsets of high quality and the water delivery
system engineered for high efficiency would be promoted Motors and drive
systems are the major source of high consumption in Agricultural and
Industrial sector.
¾ Stringent check on the pumpset installation, sealing of the units installed and
strict penalties may bring discipline in this sector. This would call for utmost
political will.
¾ Command area development using drip and sprinkler irrigation for water
management should go hand in hand with the pump sets energisation policy
of the States.

3.21 OPEN ACCESS IN DISTRIBUTION

The two critical areas for private sector investment are open access and multi-year
tariff principle to give certainty to tariffs principles. Open access in distribution has
not materialized though regulations have been issued by SERCs. Multi-year Tariff
which has been provided in the Electricity Act would be an important structural
incentive in minimizing risk for utilities and consumers.
Access to transmission and distribution network is one of the most important
elements of Electricity Act 2003 and National Electricity Policy 2005. At the retail
level that consumers with a minimum requirement of 1 MW are to be granted the right
to avail open access by 2009 in a phased manner. A consumer allowed open access

Page 42 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

under the regulations is therefore free to choose any electricity supplier other than
the distribution licensee of its area. Competition in Generation and Distribution can
be successful only through the access to the Transmission and Distribution networks.
The provision of open access would allow generating companies to sell directly to
multiple distribution and trading licensees and to the consumers. This will enable
development of power market with participation from multiple buyers and sellers in
competitive environment. Electricity Act 2003 makes open access mandatory. It has
also been envisaged that the amount of cross subsidies charged and additional
surcharge to be levied from consumers who are permitted open access should not
become so onerous that it eliminate competition.

It is important for open access that the distribution network is adequate. The current
state of distribution system which often operates at low frequencies limits operation of
Open Access. The upgradation and augmentation of the grid is therefore necessary.
Though distribution licensees have an obligation to provide non-discriminatory open
access to the network, there is no obligation on the licensees to expand their network
capacity to accommodate demands. Under the Electricity Act, the Regulatory
Commission’s role is to develop regulations permitting open access, to determine
commercial parameters such as charges for wheeling of power and surcharges
applicable to open access customers and to resolve any technical disputes on
availability of transmission capacity.

In order to meet the rising demand for electricity, especially from industrial
consumers, the Act provides incentives for captive and cogeneration plants. Captive
power plants are given open access to transmission and distribution lines to carry
power from the captive generating plant to the destination of their own use without
the payment of surcharge, which is to be paid by other open access users as
provided in the Act and used to meet the cost of cross-subsidies.

The major issue in making open access operational is the level of cross-subsidy and
other charges applicable to open access consumers. If the charges are set at a level
which works out expensive than the grid tariff the whole purpose of providing open
access will be defeated. Another factor that influence price of power through open
access is the rate at which power is available from the generators. Even if various
charges are set at higher level, the consumers may be able to get power supply at a
competitive price from a cheap source and find it cheaper than the tariff of the
licensee.

3.22 MULTI-YEAR TARIFF

The system of cost plus approach for tariff determination has not been very effective
in providing the utility with adequate incentive to improve its performance. Cost
based approach provides a rate of return to SEBs/Utilities based on costs that
include inter-alias, fuel and power purchase, investments in the network and energy
losses. In this system SERCs found it difficult to arrive at appropriate level of energy
losses that could be allowed as part of tariff fixation process which is done annually.
The main draw-back of this approach is uncertainty of tariffs.

Performance based regulation through Multi Year Tariff (MYT) framework, is an


important incentive to minimize risks for utilities and consumers, promote efficiency

Page 43 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

and rapid reduction of system losses. It would also bring greater predictability to
consumer tariffs by restricting tariff adjustments to known indicators. Multi-year tariff
provides regulatory certainty on cost of tariff which is essential for investor interest in
utilities.

Electricity Act 2003, National Electricity Policy and National Tariff Policy envisages
introduction of Multi-year tariff framework. As per Tariff policy, MYT framework is to
be adopted for any tariffs to be determined from April 1, 2006. The MYT framework
covers capital investments and an incentive framework to share the benefits of
efficiency improvement between the utilities and the beneficiaries.

One of the challenges before the regulators is the determination of efficient targets
for the utilities as part of performance based tariff setting. Another problem regulator
faces is obtaining accurate historic data and information regarding utility operation.
The key issues in MYT approach is determination of key parameters to be monitored
for programme and the constraints in determining an efficient level of operation for
utilities. In the public utilities the question arises as how to motivate the management
for improving performance in performance based approach. Another question is how
the quality of supply provided to the consumers should be factored into performance
based framework for regulation.

Benchmarking should be properly adopted after adequate studies to establish the


desired performance standards. Regular review of the performance levels also need
to be suitably undertaken. Subsidies in the tariff given by the State Governments
should be fully compensated upfront instead of cross subsidies.

3.23 PUBLIC PRIVATE PARTNERSHIP

Development of power sector requires large investment that can not be met solely by
public finance. Electricity Act 2003 has provided a legal frame-work to attract private
sector participation in the power sector. However, the present conditions prevailing
in the power sector, particularly in the distribution segment are unlikely to attract
private investment unless reform pace accelerates. In this context, the distribution
sector should focus on public private partnership model for resource mobilization and
efficiency gains. The strengths of both public and private sector should be combined
to achieve the ambitious goals set in the National Electricity Policy. A private
participation could help to bring technical and managerial expertise for improving
operating efficiency and customer orientation, besides supplementing the efforts of
the Government to invest in the sector.

A public private partnership is already emerging in the form of franchisees in rural


areas where villages have been electrified under Rajiv Gandhi Grameen Vidyutikaran
Yojna (RGGVY). But, on a larger scale, to meet the huge investment and efficiency
gaps in the distribution sector, there is a need to create right environment for public
private partnership in the 11th Plan. The State Government should provide necessary
ground for smooth implementation of public private partnership. For this necessary
legal and regulatory frame-work should be designed. Since distribution sector is
exclusively within the purview of the State Government, a strong political support is
necessary for introducing PPP model in the distribution sector. State Governments
support is also required in aspects such as law and order, land acquisition,

Page 44 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

rehabilitation and resettlement, shifting of utilities and forest and environment


clearances. In the distribution sector, the availability of information and huge gaps in
data is a major challenge for promoting public private partnership. The major issue in
promoting PPP model in power distribution sector is the commercial viability due to
high subsidies to certain categories of consumers which at present the State
Governments are not able to fully compensate to utilities due to their poor finances.
Consensus building is also vital to the success of PPP. It is important to mobilize
support from all the stakeholders for effective implementation of PPP models.

A clear path has to be laid addressing various issues in successful implementation of


PPP model in the power distribution. The risks to the private players and the utilities
have to be clearly identified and allocation of risks has to be done in a rational and
the contractual document should suitably incorporate them. In the 11th Plan efforts
should be made to introduce PPP model in major urban areas along with surrounding
rural areas in the proximity. The State Government should be encouraged to
implement PPP in select towns. The model for PPP should learn from successful
PPPs like NDPL of Delhi.

3.24 IMPACT OF POWER SECTOR REFORMS – SUCCESS STORIES

Andhra Pradesh

Andhra Pradesh has been in the fore-front of power sector reform. It has achieved
significant improvements in transmission & distribution loss reduction and brought
about significant improvements in the functioning of power sector. Transmission &
distribution losses have reduced by about 12% in the last five years and collection
efficiency has increased to 100% level which helped in financial turn around of the
sector in the year 2005-06. Andhra Pradesh is consistently campaigning against
theft and initiated strict action against theft cases. In the financial year 2003 more
than one lakh prosecutions relating to theft of electricity were done. Similarly, in the
year 2004 about 90,000 prosecutions have been done. Distribution transformer
failure rate have substantially reduced from 29% in 2001 to 11% in 2004.

Karnataka

Karnataka has also reduced losses from 38% in the financial year 2000 to 31% in
2004. Collection efficiency has improved from 91% in the financial year 2002 to 99%
in the financial year 2004. The financial health of the Corporation has improved with
a decline in revenue deficit per unit from 109 paise to 73 paise.

Orissa

In Orissa the trend of T&D losses is towards reduction for all the Discoms. It varies
from 41% to 36% in the case of WESCO, 44 % to 41% in the case of NESCO 42% to
40% in the case of SOUTHCO and 45% to 40% in the case of CESCO from the year
2000 to 2004.

Page 45 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

Delhi NDPL Experience

Aggregate technical and commercial losses have reduced and collection efficiency
has reached 100% after privatization of Delhi Discoms. The losses have reduced
from 51% to 35% from 2002 to 2005. Similarly, the collection efficiency has gone up
from 92.80% to 100.30% during the same period. Other states have also started
showing improvement due to number of initiatives at various levels.

3.25 BEST PRACTICES

Certain actions are required as a prerequisite for attaining the AT&C loss reduction
which have given the best results. List of such best practices which can be adopted
across the country are listed below:

1) Consumer Indexing
2) Assets Codification
3) GIS mapping & integrating GIS with other business process
4) Spot billing
5) Automated Meter Reading
6) Meter reading through computerized meter reading instruments
7) Web based billing & collection
8) Online collection for depositing bills at any counter
9) Collection through ATM equipments
10) Online payment through credit cards
11) Cheque drop boxes
12) Preventive Maintenance
13) Overhead/underground routine maintenance
14) DTC maintenance
15) Turn Key execution
16) Project Management Teams
17) Quality Management through ISO/TQM
18) S/stn .Data logging/SCADA/DMS
19) Online Material Management & Inventory Management
20) Out sourcing of O & M activities
21) Rural franchisee.
22) HVDS
23) 100% metering
24) Energy accounting & auditing
25) Theft control
26) Management Information Systems.
27) Identification & monitoring through Key Performance Indicators
28) Call Centers
29) Customer Facilitation Centre

Out of the above list the best practices adopted by some of the states utilities are
given below. All these states have been successful in reducing the AT&C loses.

Page 46 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

Best Practices – ANDHRA PRADESH (AP DISCOMS)

1) Consumer Indexing
2) Key Performance Indicators (KPIs) for monitoring performances
3) GIS mapping
4) Automated Meter Reading
5) Meter reading through computerized meter reading instruments
6) Collection through computerized meter reading instruments
7) HVDS
8) 100% DTC metering
9) MIS System
10) SCADA
11) Call Centre
12) Customer Care Centre
13) Spot billing

Best Practices – NEW DELHI (NDPL)


1) HVDS
2) Capacitors
3) Standardization of cable sizes
4) GIS mapping
5) Distribution automation
6) Use of planning software tools
7) Electronic meters
8) Customer Care & Cash Collection Centers
9) Mobile Maintenance crews
10) Mobile Transformer unit
11) Replacement of Cable: Ring Mains Unit
12) Use of Package Sub-stations
13) Meter Installations: Outsourced
14) Computerisation of all activities
15) Commercial wing separate from maintenance wing
16) ‘Sampark’ Communication with Consumer.
17) ‘Sarthi’ communication with employers
18) Automated Meter Reading (AMR)

Best Practices – KARNATAKA (BESCOM)


1) Energy Accounting at DTC level with synchronized meter reading
schedule
2) System improvement work
3) 11kV and LT re-conductoring
4) Rural load management system
5) HVDS
6) Gram Vidyut Pradinithi
7) Distribution of CFL lamps in DSM program

Best Practices – RAJASTJAN (Jaipur Vidyut Vitaran Nigam Ltd.)


1) Creation of more 33 kV Sub-stations
2) Renovation of existing 11 kV feeders
3) Establishment of Consumer Grievance Redressal mechanism

Page 47 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

4) Releasing new connections within time frame


5) Reduction of AT & C losses
6) HVDS for rural areas
7) Energy metering of 100% consumers
8) Meters mounted on base of meter boxes & cover having push fit
arrangement after making electric connections
9) Meter box to have number seal

Best Practices – CESC Limited (West Bengal)

1) Development of consumer database with pilferage history and


ongoing IT based monitoring of their consumption pattern.
2) Installation of meter pillar boxes in pilfer-prone pockets.
3) Blocking of service cutouts and installation of cutout less service with
MCCBs.
4) Holographic seal and imported ferrule seal on all meters.
5) 24 hours monitoring and surveillance by Loss Control Engineers
against theft/pilferage of electricity particularly through night drives.
6) IT based surveillance against theft and pilferage of electricity.
7) Meter reading of all the HV & CT operated MV meters by
computerized meter reading instrument.
8) Monthly meter reading and billing of 100% consumers with rotation of
meter readers in each cycle.
9) Energy auditing and accounting in MVAC distribution transformers
through Automated Meter Reading (AMR).
10) Very high collection efficiency with intensive follow-up for outstanding
realization.
11) Fully computerized consumer indexing system (CIS).
12) Documented maintenance and operation practices with ISO
certification for Distribution Office Operation.
13) Extensive training facility at distribution training institute to hone up
the technical skills and impart the training on best practices to ground
staffs, supervisory level and Engineer / Sr. Engineer level.
14) Diagnostic fault analysis to prevent recurrence.
15) Installation of Compact Sub-stations with Gas-insulated Switchgears.
16) Fully mobile maintenance crews with mobile communication
equipment operating round the clock.
17) GIS covering of HVAC & MVAC network.
18) Integration between Commercial and Engineering database with ERP
software.
19) Fully integrated 1 GBPS intranet optical fiber communication
backbone network.
20) Application of Six Sigma for improvement of operations.
21) Structured Grievance Redressal Mechanism with computer aided
monitoring.
22) Unified Call Centre operation for all supply related complaints. 24
hours help desk for all consumers.
23) Dissemination of consumer awareness messages at regular intervals
along with the consumption bills and periodic visits to target
segments.

Page 48 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

THRUST OF THE 11th PLAN IN DISTRIBUTION AND RURAL ELECTRIFICATION

EXPECTED OUTCOMES
Urban Areas

1. Consumer Indexing - 2000 towns


2. House holds will have access to electricity - 100%
(Including urban poor)
3. Development of PPPs – Major towns
4. Customer Care Centres – to cover all urban consumers - All towns
5. SCADA in - 27 cities
6. IT usage - all Towns

Rural Areas

1. Villages to be electrified - 100%


2. Households will have access to electricity -100%
3. One or more 33/11 kV ( or 66/11 kV) substations in every Block
4. One or more Distribution Transformers in every village
5. SC/ST bastis to be electrified - 100%
6. BPL households to be electrified -100%
7. Schools, Panchayat offices, health centres, dispensaries,
Community centres to be electrified - 100%
8. Street Lights in every village - 100%
9. DDG schemes through grid inter connections - 1000 Nos.
10. Setting up e-seva centres/ customer care centres - 1000 Nos.
11. Direct employment generation - 1 million
12. Development of Franchisees - 2,50,000
villages
13. Centres of Excellence in rural distribution - 500

Losses

1. Reduce AT&C losses - up to 15-20%


Urban Areas - 15%
Rural Areas - 20%
• Feeder separation in states which consume high energy for agriculture for
improved load management & proper accounting.
• Improved T&D network in all NE states
• Introduction of HVDS system to bring down HT:LT ratio
• Energy Accounting & Auditing In all Utilities.

2. Metering
• all feeders - 100%
• all distribution transformers - 100%
• all industrial consumers - 100%
• domestic consumers -100%

Page 49 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

• prepaid metering system pilot projects in all states for rural areas and urban
areas.

Energisation of Pumpsets

1. Agricultural Pumpsets to be energized - 35 lakhs

Turnaround Targets for State Utilities

1. Reform process and perceptible turnaround of State Utilities - 50 utilities


2. Energy Conservation and Demand Side Management on
Priority Time of the Day metering - 15 States
Management
1. Public Private Partnership Towns & Cities - 500
Villages - 2,50,000
2. Inclusive growth Supervisory role for all gram
Panchayats/ local bodies
Other Reforms
1. Open Access operational In all states
2. Multi Year Tariff In all states
3. Integration of IT applications In all states
Human Resource Development
1. Human Resource Development – Upgrading CIRE Hyderabad
into National Training Centre
for distribution related activities.

2. Establishment of Training centres for capacity building20 state level


115 district centres

A. The requirement of funds for sub transmission and distribution have been worked
out on the following assumptions:

1. The total capacity addition planned during 11th plan has been taken as 70,000
MW and the transformer capacities have been worked out on that basis for an
appropriate system with proper loading pattern.
2. The total line length adopted is based on the actual progress achieved up to
31.03.2005 and the rate of growth per year to estimate the likely achievement
in 10th plan. The quantities have been increased by over 10% for the 11th Plan.
3. Since access has to be provided to all households has been taken for
estimation purpose. Similarly other quantities have been assumed.
4. The costs adopted in various states are different under various schemes and
as such a reasonable cost has been assumed also keeping in view escalation
over next five to six years.

B. Under APDRP balance amount has been estimated at Rs. 25000 crores at the
end of 10th plan. Agricultural pumpsets connections for about 35 lakhs pumpsets
have been estimated @ Rs. 45000/- per pumpsets including additional infrastructure
requirements. Accordingly, a provision of Rs. 15000 crores has been estimated.

Page 50 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

C. A total of 4000 MW under DDG has been considered @ Rs. 5 crore/ MW and
accordingly the estimate worked out to Rs. 20000 crores.

D. Reforms process is to continue during the 11th plan and a suitable provision has
been considered for transitional finance. A modest provision of Rs. 10000 crore has
been kept accordingly.
Table 3.6

Financial
Name of Physical
Sl. Units 2007-12 (Rs.
Segment 2007-12
Lakhs)
I Lines
(i) 33 KV Ckt Kms 150000 810000
(ii) 11 KV Ckt Kms 675000 2025000
(iii) LV Ckt Kms 675000 1518750
II Sub-Station
(i) 33/11 KV MVA 130000 2600000
(ii) 11/0.4 KV MVA 162000 5184000
III Capacitors MVAR 15565 77825
Service
IV Connections to
(i) Domestic
Installations Nos. 70000000 1162000
(ii) Commercial
Installations Nos. 3500000 66500
(iii) Industrial
Installations
(a) HT Nos. 500000 90000
(b) LT Nos. 50000 2000
(iv) Public Light Nos. 750000 18750
(v) Agriculture Nos. 3500000 140000
Total (I to IV) 13694825
A. Re-
conductoring of
V Lines
(i) 33 KV Ckt. Kms 100000 378000
(ii) 11 KV Ckt. Kms 2200000 4620000
(iii) LV Ckt. Kms 700000 1106000
Total V (A) 6104000
B.
Augmentation
of S/Ss
(i) 33/11 KV MVA 88000 1408000
(ii) 11/0.4 KV MVA 110000 2530000
Total V (B) 3938000
Total (V) 10042000
Grand Total 23736825

Page 51 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

3.26 REQUIREMENT OF FUNDS

Table 3.7

Rs. Crore
1. Sub Transmission & Distribution for Urban & 1, 97,000
Rural areas
RGGVY 40,000
2, 37,000
2. APDRP & Other Schemes (pumpsets etc.) 40,000
3. Decentralised Distributed Generation 20, 000
4. Others 10,000
TOTAL 3,07,000

3.27 RECOMMENDATIONS

APDRP
1. APDRP should be continued beyond the 10th plan and all the
recommendations made by the Task Force under the Chairmanship of Shri P.
Abraham, Chairman, MSPGCL need to be implemented.
2. APDRP should mainly focus on Class 1, 2 and 3 towns comprising of total
1945.
3. The 11th Plan should target at reducing AT&C losses to 15% in 1000 (first
three categories of towns.)
4. In order to give the push to the APDRP programme like in case of RGGVY,
REC should be made the nodal agency.

AT&C Losses
1. Development and Implementation of Distribution System Plan should be
regularly pursued.
2. The following steps are required to be taken for reducing the AT&C loss level :

I. Introduction of new and improved materials and equipment (e.g. AAA


conductors, amorphous core transformers, gas insulated switchgear, Arial
Bunched Cables, better quality joints, SF6 Breakers etc.)
II. In order to move ahead with the implementation of anti-theft regulations the
State Governments need to set up Special courts, Special Police Stations
and appoint assessing officers and compounding officers.
III. Introduction of High voltage distribution system (HVDS) and installation of
large number of lower capacity distribution transformers at the consumer
load centers.
IV. Installation of capacitors to improve power factor/ voltage profile and to
reduce energy losses in the system.
V. Installation of Electronic Meters (with AMR for 15 KVA & above
consumers) for all consumers including Agricultural connections and Street
lighting points.
VI. The utilities need to increase enforcement activities, deploy adequate flying
squads, carry out timely meter testing, conduct downloaded meter data
analysis, conduct new connection camps in theft prone areas, Metering in

Page 52 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

Pillar Box based systems and conduct awareness campaigns in targeted


areas.

Energy Audit and Accounting & GIS


1. The focus on the 11th Plan should be to standardize energy accounting and
auditing practices and incentivizing efforts of utilities undertaking complete
accounting and auditing exercise and metering.
2. GIS and consumer indexing in distribution system needs to be introduced in
all utilities.

IT Intervention
1. IT Blue print should be prepared and focus on integrated approach to get the
best results.
2. Installation of SCADA and distribution automation is to be taken up in all major
cities/towns.
3. Improvement in billing by using modern meter reading technologies (AMR,
CMRI etc.), billing database correction/ strengthening, and implementation of
IT based Billing system.
4. Mobile van with GSM connectivity needs to be introduced in all districts.
5. e-seva Kendra’s to be set up in all districts.
6. Customer service centers should be introduced in all urban areas.

Reliability Index
1. All reliability indices for quality and reliability of supply should be adopted and
measured.
2. Standards of performance to be enforced by SERCs.
3. Proper trouble calls management to be adopted in all States by the end of 11th
Plan.

Distribution Reforms
1. Unbundling of SEBs, Privatization of loss making utilities, and handing over of
high loss feeders need to be pursued further.

RGGVY Programme
2. The programme requires continuous support from all the agencies concerned,
with regular flow of funds and constant monitoring to ensure that the
envisaged benefits reach the rural masses well before the targeted date.
3. To develop an appropriate Monitoring and Evaluation (M&E) framework with
measurable indicators for implementation and long-term sustainability of
RGGVY.
4. To benchmark procedures and practices for designing sustainable projects.
5. There is also need to introduce wide spread use of prepaid cards, hand held
meters for the spot billing, anti theft microchip devices in meters and
metering at distribution transformer level so as to enhance collection efficiency
in rural distribution and to reduce theft and pilferage.
6. Use of energy saving lamps e.g. CFL be encouraged.

Page 53 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

Franchisee Development
1. Various avenues for financial support to franchisee which should include
financial support from rural banks, cooperative banks and other financial
institutions.
2. Loans given to franchisee can be refinanced by Apex bank, NABARD and
model schemes could be developed in consultation with RBI in order to
encourage wide spread participation by lending community.
3. Rural Infrastructure Development Fund (RIDF) of NABARD provides funds to
States for infrastructure development purposes. Franchisees should be given
funds from RIDF at a concessional interest rate, for financing expenditure
involved in collection of bills, O&M etc.
4. Micro-financing agencies nowadays are providing small loans to the tune of
around Rs. 20,000/- without security. These agencies may be empanelled
and made known to franchisees so that whenever they require funds they can
approach these agencies.
5. Corporate sector can play an important role in handholding the franchisees.
Not only power sector CPSUs, which have network all over the country but
also corporate leaders like Infosys, Wipro, Reliance, HLL, L&T etc. be
encouraged to help SHGs in the development of franchisees.

Capacity Building
1. It is essential that institutes are identified at Central and State level for
undertaking capacity building in a systematic manner.
2. Proper human resource development and capacity building requirements to be
given special attention for a sustainable development.

Decentralized Distributed Generation


1. DDG scheme implementation should be taken up on a mission mode.

Stand Alone
2. Stand alone projects up to 1 MW size to be implemented by MNES through
NTPC, IREDA or other agencies by setting up Joint Ventures.
3. The funds available under RGGVY can be utilized for such stand alone
schemes with a capital subsidy.

Grid Inter Connected


4. Grid Interconnected Schemes to be implemented for supplementary power
needs. These schemes may be up to 5 MW capacity.
5. Corporate Agencies may take up such grid interconnected DDG schemes on
competitive bidding basis. Public Private Partnership to be encouraged.
Viability Gap funding may be adopted.

Cost
6. Cost of electricity should be based on cost to serve/ avoided cost.

Technologies
7. All available commercial technologies (both conventional and non
conventional) may be utilized.
8. Suitable standard size packs may be used in order to reduce production costs.

Page 54 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

9. Multi-fuel technologies may be adopted for sustainability of DDG projects.

Biomass Plantation
10. Biomass cultivation and development of short duration (cycle) high yielding
varieties of biomass for combustion/ gasification/ bio-fuels be encouraged with
minimum support price.
11. Financial Institutions should support bio-diesel plantations, consultancy, R&D,
DPR preparation etc.

Policy Issues
12. DDG projects should be exempted from income tax, excise duties or customs
duties or accelerated depreciation benefits be provided.
13. All concessions extended by States for Industrial development may be given
for DDG projects.
14. Clear allocation of power for rural areas be ensured, so that there is no
discrimination in the hours of supply between rural and urban areas.
15. A separate Rural Electricity Agency (REA) may be considered for each state
to look into needs of rural areas.
16. The State Govts., State Utilities/ Discoms and Local administration should
create proper enabling atmosphere to encourage DDG projects.
17. Priority Sector lending status and long term loans up to 25 years through
International Agencies may be provided for DDG projects.

Survey
18. Urgent need for comprehensive survey of available resources in each village
should be taken and be completed in eighteen months.

R&D
19. R&D on fuel cells, efficiency of other existing systems etc be encouraged by
extending financial support or Income Tax benefits.
20. Improvement in quality and life of batteries is very essential; R&D is required
in this area.

Capacity Building
21. Suitable capacity building measures be adopted like training of local youth in
the maintenance of DDG equipment at local levels.

Nodal Agency
22. REC should act as Nodal Agency for Grid Interconnected DDG schemes and
Survey of villages.

Other issues
23. All subsidies to be based on outcomes and not outlay.
24. Carbon Credit benefits to be utilized by use of DDG projects.
25. The electricity should be provided through Rural Electricity Supply Providers/
franchisees.

Local Management & Monitoring

Page 55 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

26. District Committees be strengthen & empowered suitably. Local Institutions


like Panchayats, NGOs, Cooperatives, SHGs may be activated to coordinate
or participate in the DDG projects.

Other Issues on Distribution

Open Access
1. Open access in distribution should be fully operationalised including phasing
out cross subsidy surcharge by end of 11th plan.

Tariffs
2. Multi year tariff framework to be adopted by all states.
3. Benchmarking for MYT should be properly adopted after adequate studies to
establish the desired performance standards. Regular review of the
performance levels also need to be suitably under taken.
4. The subsidy for agriculture needs to be reduced in line with the National
Electricity Policy to a level of + 20% of average cost of supply by 2010-11.
However, it needs a strong political will.
5. Combined tariff for electricity and water may need to be considered for
judicious use and conservation of both.

Agriculture
6. Mandatory/ obligatory requirement to be made for international standard
Agricultural pumpsets based on least energy requirements.
7. Command area development using drip and sprinkler irrigation for water
management should go hand in hand with the pumpsets energisation policy of
the States.
8. Diesel pump sets should be replaced by non-conventional sources of energy
including bio-fuels.
9. Agriculture Feeder separation programme to be launched.
10. Agriculture consumers to be metered.

Other Issues
11. The priority sector status available to REC for the energisation of Agricultural
pumpsets etc was recently withdrawn which should be restored in order to
enhance the pumpset energisation programme during the 11th plan to at least
35 lakh pumpsets.
12. Wherever applicable Carbon credit benefits be obtained.
13. India must improve their equipment standards by raising the benchmark levels
to that of international standards in order to reduce technical losses and no. of
outages.

New Programmes for Introduction in the 11th Plan

In order to implement various recommendations there is a need to adopt


comprehensive schemes on the following besides continuation of APDRP and
RGGVY.

1. One Megawatt Power plant Programme for Rural electricity supply


2. Setting up of Centres of Excellence for Rural Distribution

Page 56 of Chapter 3
Distribution Including Village & Household Electrification Working Group on Power for 11th Plan

3. Consumer awareness programme on the lines of Akshay Prakash Yojana of


Maharashtra
4. Special Programmes for Capacity Building of franchisee
5. Special Agriculture Pumpset Energisation Programme
6. Special Schemes for Urban Poor
7. Special Programmes for Development of North East
8. Programme on Decentralized Distributed Generation (DDG) for village
electrification in remote areas and also for overcoming shortage of power.
Supplementary Power supply needs are essential for protecting the already
created infrastructure under RGGVY. This programme will cater to all such
needs. Pilot projects should be set up initially to gain experience and till
instill confidence. Thereafter, a National Programme on DDG be launched
including under the PPP model.
9. REC/PFC may introduce reform to result programmes by extending large
value, long term loans as the mutually agreed reform conditionality.
10. REC to set up a wing to lay down the specifications / standards for the
equipment suppliers.
11. REC/PFC may finance the power equipment manufactures in their
modernization and expansion plans.
12. REC/PFC may float Venture Capital Funds to encourage manufacture of
critical quality components used for power infrastructure and promote ready
market for such products at competitive rates.

**********

Page 57 of Chapter 3
Demand Side Management & Energy Efficiency Working Group on Power for 11th Plan

Chapter- 4

DEMAND SIDE MANAGEMENT AND ENERGY EFFICIENCY

4.0 INTRODUCTION

In rapidly growing economy of India, the energy requirements have been increasing
at a very fast pace. Indian economy has been gradually reforming itself with the
developments taking place in the dynamic global energy scenario as well as with the
advancements in technologies worldwide. The Government of India at the highest
level is giving top priority to the attainment of nation’s long-term energy security.

India ranks 5th in the world in terms of primary energy consumption, accounting for
about 3.5% of the world commercial energy demand in the year 2003. The total
commercial energy consumption of various sectors stood at 218 million toe (2003-
04).The share of energy by different end-use sectors is given in Figure 1.

15 (7%)

30 (14%)

Agriculture
20 (9%)
Industry
Transport
93 (42%) Residential
26 (12%) Other energy uses
Non-energy uses

35 (16%)

Figure 1. Sectoral share of commercial energy consumption (mtoe) (2003-04)


If it perseveres with sustained economic growth, achieving 8-10% of GDP growth per
annum through 2030, its primary energy supply, at a conservative estimate, will need
to grow 3 to 4 times and electricity supply by 5 to 7 times of present consumption. Its
power generation would increase to 780,000 MW from a current level of about
120,000 MW and annual coal demand would be in excess of 2000 million tons from a
current level of 350 million tons. This extraordinary growth in energy demand will
place great stress on the financial, managerial and physical resources of the country.

For meeting desired growth rate of the economy, the country faces formidable
challenges in meeting its energy needs and in providing adequate energy in various
forms to users in a sustainable manner and at reasonable costs. While it is essential
to add new power generation capacity as well as ensure availability of substantial
commercial fuels to meet the nation’s growing energy requirements, it is equally
important to look out for options that help in reducing energy demand by various end-
use sectors. The need for enhancing energy conservation efforts has become very
important.

Page 1 of Chapter 4
Demand Side Management & Energy Efficiency Working Group on Power for 11th Plan

4.1 THE ENERGY CONSERVATION ACT

The planning process so far has been leaning heavily towards the supply side
strategies. Efforts made to implement DSM, energy conservation and energy
efficiency measures were symbolic, lacked continuity due to absence of a well knit
institutional mechanism at the national and state levels. The 10thplan period (2002-
07) is marked by enactment of the Energy Conservation Act, 2001 and setting up of
the Bureau of Energy Efficiency (BEE) at the national level. The Act has given
mandate to BEE to implement the provisions of the Act, and spearhead the
improvement in energy efficiency of the economy through various regulatory and
promotional measures. Some key activities that BEE is pursuing include the
development of energy efficiency labels for refrigerators and other mass produced
equipment, certification of energy managers and auditors, assisting industry in the
benchmarking of their energy use, and energy audits of prominent government
buildings. A beginning has been made by the State Governments in designating
agencies to oversee implementation of the Energy Conservation Act and deliver
energy efficiency services including through public-private partnership. BEE was
provided with a one-time grant of Rs.50 Crores and it utilizes the interest earned on
the same to institutionalize energy conservation activities by the Government of India.

The Planning Commission in its recent report on an Integrated Energy Policy (IEP)
laid out a vision of providing energy security to all citizens. IEP emphasizes energy
efficiency & demand side management as essential components of the natural
energy strategy. The Group report focuses on operationalizing and implementing the
recommendations of the integrated energy policy.

4.2 ENERGY SAVING –TARGET AND ACHIEVEMENT OF 10TH PLAN

4.2.1 Energy Conservation Target

The 10th Five Year Plan (2002-07) targeted energy savings of 95 BU(13% of
estimated demand) in the industrial, agricultural, domestic and commercial sectors
against the expected electricity demand of 719 BU in the terminal year of the Plan i.e.
2006-07. The 10th Plan highlighted the need for institutional arrangement to
coordinate different programmes on energy conservation. It also stressed the
mobilization of resources for funding the energy conservation programs. The 10th
Plan however did not provide any specific budget allocation to meet and validate the
energy saving targets. ( Planning Commission, Government of India (2006), Report
of the Expert Committee on Integrated Energy Policy)

4.2.1 Energy Conservation in the 10th Plan

Authentic and updated database is not available due to which it is difficult to assess
the potential and achievements made. A rough attempt to assess energy savings
achieved during 2002-05, puts this figure at 1170MW comprising of 508 MW from
electric power savings achieved in industrial sector (participating units of National
Energy Conservation Award for the years 2002-03, 03-04 and 04-05), 181 MW from
supply side in Power Sector and 481 MW due to penetration of energy efficient CFL
& 36W tube lights.

Page 2 of Chapter 4
Demand Side Management & Energy Efficiency Working Group on Power for 11th Plan

Authentic and updated database of energy consumption patterns and energy saving
potential are not available for majority of the energy consuming sectors. The data
availability is limited to a few units/sub-sectors based on some specific studies or
interventions and thus can not be extrapolated to arrive at national figures. Such
database is vital for providing direction to policy makers and other stakeholders with
regard to augmentation of additional capacity requirements in generation and
transmission. The centrally available database would also be useful for other
stakeholders who are directly or indirectly involved in the end-use consuming sectors
(industry, transport, buildings, agriculture). There is a need to develop and implement
energy conservation programmes, setting up of energy saving targets and an
effective monitoring of energy savings achievements periodically.

4.3 ENERGY CONSERVATION STRATEGY IN THE 11TH FIVE-YEAR PLAN

The basic aim of the energy conservation strategy in the 11th Five Year Plan will be to
prioritize and implement the provisions under the EC Act 2001 by decentralizing the
energy conservation programmes at the State level. The strategy will strengthen the
existing institutional linkages, and pursue the task of consolidating the energy
conservation information, trends and achievements and create a market for energy
conservation and for energy efficient goods and services.

Keeping in view the provisions of the Act, an appropriate institutional mechanism and
energy database will be developed in the 11th Plan by BEE. As a part of the
mechanism, a fully dedicated ‘Energy Conservation Information Centre’ (ECIC) with
Information Technology facilities will be set up within BEE and Central Energy
Conservation Fund as mandated under EC Act will be established by the
Government of India.

4.3.1 Energy Conservation and Information Centre (ECIC) at BEE

Information/ database availability on sectoral/ sub-sectoral trends on energy


consumption and energy conservation potential is not readily available at a
centralized place for all the sectors of Indian economy. As mentioned earlier, this
can be mainly attributed to the absence of any institutional mechanism that enables
collection of the information from various users and then to undertake detailed
analysis that can feed into decision-making processes at the policy level. Substantial
resources (manpower, infrastructure, funds and time) will be required if the
information on energy conservation related activities is to be made available at
national level from a single source. Collection of such information is a mammoth task
and requires systematic handling and coordination of efforts of various agencies.

4.3.2 Strengthening of BEE and SDAs

In the 11th Five Year Plan, BEE will be strengthened as a nodal organization at the
national level, and will be empowered to provide direction to the energy conservation
programmes in the States. An appropriate institutional mechanism and a fully
dedicated ‘Energy Conservation Information Centre’ (ECIC) will be set up within BEE
to analyze energy consumption trends and monitor energy conservation
achievements in the country on the basis of data received from the states through

Page 3 of Chapter 4
Demand Side Management & Energy Efficiency Working Group on Power for 11th Plan

State Development Agencies (SDAs, notified by the State Governments under the
Act). BEE will also take the responsibility of disseminating information in the public
domain. To carry out these tasks, BEE will be strengthened with additional
professional staff and expertise.

Supporting organizational set-up will also be strengthened at SDAs in various States


and Union Territories (UTs). For this, a matching grant support from Central
Government restricted to the contribution made by the respective States/UTs
Governments will be extended to establish State Energy Conservation Fund as
mandated under EC Act. To facilitate various functions of BEE and SDAs, a national
level network of institutions will be developed by BEE.

4.3.3 Institutional Network

BEE will strengthen its existing institutional linkages with SDAs, and formalize its
association with various other national level institutions such as PCRA, NPC, TERI,
CEA, energy centres in academic institutes/universities, etc. with a view to utilize
their expertise and knowledge in the field of energy conservation. In its institutional
network, BEE will also include a number of sector specific associations and research
institutions, and private organizations in various states, and will delegate specific
tasks to facilitate the implementation of energy conservation programmes.

Funding support proposed is Rs. 320 Crores (for BEE Rs 150 Crores and for SDAs
Rs. 170 Crores). Details are furnished in Cl.4.5.

4.3.4 Energy Conservation Programmes in the Targeted Sectors

In the 11th Five Year Plan, BEE will focus energy conservation programmes in the
following targeted sectors:

4.3.5 Targeted sectors

(a) Industrial Sector (Energy Intensive Industries).

Industry sector offers maximum potential for energy conservation. The Government
of India has recognized this when a number of energy intensive industries have been
included as designated consumers in the EC Act. To bridge the efficiency gaps in the
various units within the same industrial sub sector, BEE in association with SDAs,
industry associations and research institutions, will develop 15 industry specific
energy efficiency manuals/guides for the following sectors: Aluminum, Fertilizers, Iron
&Steel, Cement, Pulp & Paper, Chlor Alkali, sugar, textile, chemicals, Railways, Port
trust, Transport Sector ( industries and services), Petrochemical &Petroleum
Refineries, Thermal Power Stations &hydel power stations , electricity transmission
companies & distribution companies.

The manuals will cover Specific energy consumption norms as required to be


established under the EC Act, energy efficient process and technologies, best
practices, case studies etc. Follow up activities will be undertaken in the States by
SDAs. and manuals will be disseminated to all the concerned units in the industries.

Page 4 of Chapter 4
Demand Side Management & Energy Efficiency Working Group on Power for 11th Plan

Funding support proposed is Rs.21.8 Crores (BEE Rs.15 Crores and SDAs Rs. 6.8
Crores). Details are furnished in Cl.4.5

(b) Small and Medium Enterprises (SMEs)

Many of the energy intensive SMEs clusters located in various states of the country
are said to have large potential for energy savings. In quantitative terms, there is very
little authentic information and data is available with respect to their energy
consumption and energy saving opportunities. SDAs in consultation with BEE will
initiate diagnostic studies in 25 number of SMEs clusters in the country, including 4-5
priority clusters in North East Region, and develop cluster specific energy efficiency
manuals/booklets, and other documents to enhance energy conservation in SMEs.

Clusters tentatively proposed for these activities are: Warn gal (AP) rice mills,
Bhimavaram (AP) ice plants, Surat (Gujarat) textile, Jamnagar ( Gujarat) Brass,
Jagadhri (Haryana) Plywood, Sambalpur (Orissa) rice mills, Bhubneshwar (Orissa)
utensils, Pali (Rajsathan) textile, Jodhpur (Rajsathan) textile, Balhotra (Rajasthan)
textile, Kota (Rajasthan) textile, Jaipur (Rajasthan) textile, Tripur (TN) textile, West
Coast (TN) rice mill, Coimbatore (TN) foundry, Kanur (UP) textile, Bhadoi (UP)
carpet, Bundre (UP) khandsari, Dehradun (Utranchal) Plywood, Howrah (WB)
foundry , Agra (UP) foundry , Ferozabad (UP) Glass, Bodhjungnagar (Tripura) agri-
processing, Kamrup (Assam) forest/agro based industry, Dibrugarh (Assam) light
engineering , Dimapur (Nagaland) Timber-bamboo products

Funding support proposed is Rs.19.3 Crores (BEE Rs.12.5 Crores and SDAs Rs. 6.8
Crores). Details are furnished in Cl.4.5

(c) Commercial Buildings and Establishments

Government and public buildings constitute a very large sub-sector but so far very
little organized efforts have been put in to save energy in the same. In the 11th Plan,
BEE will initiate comprehensive studies in selected buildings/establishments such as
office buildings, hotels, hospitals and shopping malls to prepare building specific
energy efficiency manuals covering Specific energy consumption norms, energy
efficient technologies, best practices, case studies, model energy performance
contracts, model monitoring and verification protocol for implementation of ESCO
projects etc. As a follow up, SDAs in association would initiate energy audits and
their implementation in 10 Government buildings in each state and 1-2 buildings at
UT level. BEE will also assist SDAs in the establishment and promulgation of energy
conservation building codes (ECBC) in the States, and facilitate SDAs to adapt
ECBC to the local conditions and make them ready for implementation at municipal
levels. In addition, BEE will also strengthen a few test laboratories for testing of
building materials and building utility systems for ECBC compliance.

Funding support proposed is Rs.41 Crores (BEE Rs.14 Crores and SDAs Rs. 27
Crores). Details are furnished in Cl.4.5

Page 5 of Chapter 4
Demand Side Management & Energy Efficiency Working Group on Power for 11th Plan

(d) Residential/Domestic sector

BEE has been working to introduce energy efficiency standards and labeling
programme to facilitate consumers in selecting energy efficient domestic appliances.
For promoting energy efficiency programmes in this sector, SDAs will actively involve
Electric Utilities/ Distribution Companies. Emphasis would be to encourage the
consumers to adopt energy efficient lighting systems, air conditioners, refrigerators,
water heating systems and other domestic appliances. BEE will enlarge its on-going
energy labeling programme for ‘frost free refrigerators’ and ‘tubular fluorescent lamps’
to 10 other appliances - Air conditioners , Ceiling Fans , Agricultural pump-sets ,
Electric motors ( general purpose) , CFLs, FTL – 61cm (2ft) , Television sets ,
Microwave ovens, Set top boxes , DVD players , Desk top monitors

To facilitate this, 10 testing laboratories will be strengthened, and consumer


awareness will be enhanced nation wide.

Funding support proposed is Rs. 84 Crores (BEE Rs. 50 Crores and SDAs Rs. 34
Crores). Details are furnished in Cl.4.5

(e) Street Lighting & Municipal Water Pumping

Street lighting and municipal water pumping put excessive pressure on electric
utilities. Quite a few of studies/projects have been successfully demonstrated in some
states. In the 11th Plan, such projects will be identified, documented and
disseminated nation wide. Further, to promote such projects in various states, SDAs
in association with State utilities will initiate pilot energy conservation projects in
selected municipal water pumping systems and street lighting to provide basis for
designing state level programmes.

Funding support proposed is Rs.10.5 Crores (BEE Rs.2.0 Crores and SDAs Rs. 8.5
Crores). Details are furnished in Cl.4.5

(f) Agriculture Sector

Increasing energy consumption trend is being seen in irrigation systems in the sector.
Due to low power tariff for the sector in majority of the States, it is not in the farmers’
financial interest to buy efficient pumps, but it may be in the utility’s interest to
promote their use.

In the 11th Plan, SDAs will collect, document and disseminate information on
successful projects implemented by some states, launch awareness campaign in all
regional languages in print and electronic media and follow up work in initiating state
level programmes along with utilities.

SDAs with assistance of concerned institutions will also develop suitable energy
conservation models which will take into consideration measures like introduction of
subsidy in replacement of inefficient pump sets with efficient ones, power factor
improvement by installation of capacitor banks, rebate for optimum usage of pumps,
energy efficiency labeling of pumps, etc. These models will be subsequently

Page 6 of Chapter 4
Demand Side Management & Energy Efficiency Working Group on Power for 11th Plan

promoted through the electricity utilities/distribution companies and SDAs with


involvement of State Regulatory Commissions.

Funding support proposed is Rs. 10 Crores (BEE Rs.5.0 Crores and SDAs Rs 5.0
Crores). Details are furnished in Cl.4.5

(g) Transport Sector

The sector is mainly dependent on the petroleum products. In the 11th Five-Year
Plan, SDAs will develop linkages with State Road Transport Undertakings and private
enterprises owning large fleet of trucks/buses to establish the status of energy
consumption and conservation in the sector. SDAs with assistance of concerned
institutions/agencies will conduct diagnostic studies to support urban bodies and
transport research organizations in adopting multi modal public transport system
which shall shift demand from personalized to public transport. SDAs will develop
linkages with the state transport undertakings to establish the status of energy
consumption and conservation potential and support studies to promote public
transportation systems. BEE will also set up norms for specific fuel consumption for a
few automobile and Transport models (Services/ Public transport).

Funding support proposed is Rs 10.5 Crores (BEE Rs. 2.0 Crores and SDAs Rs 8.5
Crores). Details are furnished in Cl.4.5.

4.3.6 Demand Side Management Programmes

DSM programmes driven by State Utilities has made a beginning in India, though
these are yet to pick up momentum. In the 11th Plan, BEE in association with SDAs
will facilitate State Utilities to pursue DSM options more intensely by focusing on the
following:

• Orientation workshops for awareness building on DSM amongst the State


Electricity Regulatory Commissions (SERCs) and the chief executives and
senior engineers of utilities/ DISCOMs.
• Setting up of DSM cells in utilities to conceive and implement DSM programs.
• Support load research and studies to rationalize the tariff structures to
encourage options such as time-of-use rates or interruptible rates to capture
the needs and opportunities of different market segments.
• Initiation of DSM programmes especially in the sectors (such as residential,
agricultural pumping, municipal water works & street lighting) where customers
are paying tariff far below the marginal cost of power
• Utilization of private sector energy service providers to market DSM program
to consumers to maximize uptake, participation and Implementation of DSM
programmes through ESCO route
• Development of pilot tariff based incentive schemes to reward utilities/
DISCOMs through Megawatt (Watts saved) through Ministry of Power for
Megawatt savings implemented (actual realized after implementation &
verification by SERCs).
• Utilities that have established appropriate DSM cells would be rewarded by
state electricity regulators for initiatives involved in DSM bidding, load research
studies, impact monitoring while fixing tariffs.

Page 7 of Chapter 4
Demand Side Management & Energy Efficiency Working Group on Power for 11th Plan

• For supplementing DSM programs, supply side initiatives such as segregation


of feeders, high voltage distribution system (HVDS), etc will be taken up with
support under the state funding and other programs such as Accelerated
Power Development and Reform Program (APDRP) on a case-to-case basis.

For DSM programs, Funding support proposed is Rs. 15 Crores (BEE and SDAs).
Distribution companies are expected to be supported by electricity regulators through
tariff fixation as well as use ESCO route for implementing the programs. Details are
furnished in Cl.4.5

4.3.7 Human Resource Development Programmes

There is a vast potential for energy savings through human intervention. BEE and
SDAs have a major responsibility for stimulating a major change in the energy
efficiency ethos and practices (energy modesty) by directing the national energy
conservation campaign as a mass movement and seeking wide support. In the 11th
Plan, BEE will continue with their campaigns. In addition Central government will
partially fund the SDAs for their respective campaigns in the States. The following
initiatives will be taken in the area of HRD:

I. Capacity building: a) Officials of BEE & SDAs in abroad/ India; b) Code


officials from SDAs , urban & municipal bodies for promoting & enforcement
of energy conservation building codes; c) Orientation programs every year for
senior officials from Central & State Govt. departments to review the
achievements, impediments and strategies to step up the tempo of energy
conservation.
II. Capacity building for new breed of professionals: a) energy managers/auditors
being developed under the EC Act from 2003 by BEE through National
Certification Examination by offering Refresher training modules for life long
training for Energy Auditors & Managers; b) Tutorial /help-line support for
prospective candidates in the national examination for energy
managers/auditors.
III. Demonstration centers in 2 industrial estates to show case and convince the
entrepreneurs & plant engineers/technicians for industrial energy efficiency
products /technologies
IV. Orientation workshops on energy efficiency for top management , middle level
executives and shop floor operating personnel
V. Farmers training by display of energy efficient pump-sets & other relevant
products
VI. Training to drivers in road transport on fuel efficient driving
VII. Nationwide campaigns: a) through media; b) awareness programs for general
public & institutions in state capitals and other locations; c) painting
competition for school children; d) Eco clubs activities for youth clubs
VIII. Introduction of the modules on energy efficiency/ DSM in the curricula of a)
schools b) technical institutes engineering colleges c) other degree/ post
graduate courses including MBA programs.

For HRD programs, funding support proposed for HRD programs to be administered
by BEE and SDAs is Rs 110.4 Crores. Details are furnished in Table below:

Page 8 of Chapter 4
Demand Side Management & Energy Efficiency Working Group on Power for 11th Plan

Table 1
Fund Requirements during 11th plan - HRD for DSM, EE & EC

Sl Description Nos Rate Amount Purpose


No Rs. Rs. Cr.
Lakhs
1 Capacity building

1a Capacity building of 30 2 0.6


officials of BEE –alternate
years abroad/ India
1b Training of State Nodal 102 2 2.04
Agency officers (34)
1d Code officers’ training for 150 0.1 0.15
ECBC
1e Orientation programs – 5 0.6 0.03
Central Govt. officials
1f Orientation programs – 5 x 34 0.6 1.02
State Govt. officials
2a Refresher training and 3000 0.02 0.6 Partial funding
continuing education for
Energy Auditors &
Managers,
2b Support for prospective 10000 0.01 1.0
candidates for energy
managers/auditors
3 Knowledge Network Rs. 1 100 5.0 Supplementary
through internet for crore/year efforts to be
implementation of Energy reviewed every
Efficiency- year.
3c Top Management 20 2.5 0.50 partial funding
awareness workshops
3d Middle Management 100 1 1.0 partial funding
awareness workshops programs
3e Operator level Awareness 100 1.0 1.0 Partial funding
& Training programs
4 Energy efficiency 2 300 6.0 Additional
demonstration centres support from
industry also to
be sought
5. Farmers training 30 events 5 1.5 Additional
support from
industry also to
be sought
7. Drivers training 200 0.5 1.0
programs
8. Publicity campaigns to Every year 1700 85.0 sponsors to

Page 9 of Chapter 4
Demand Side Management & Energy Efficiency Working Group on Power for 11th Plan

create awareness in supplement


public & institutions, efforts also
painting competition for needed
school children, Eco clubs
9. Introduction of DSM, EE One 400 4.0
and EC concepts in project
School and College
Curricula.
Total 110.44

4.4 POLICY RESEARCH FOR ACCELERATING ADOPTION OF ENERGY


EFFICIENCY AND DSM PROGRAMS

The energy conservation Act does not have specific provisions regarding an Energy
Efficiency Policy Research. Such a program, however would complement the other
provisions and thereby support the basic objective of the Act itself. Key among these
includes legislative amendments, establishing norms, policy interventions including
fiscal and non- fiscal measures. Among key result areas include:

4.4.1 Legislative measures

So far, enforcement of the EC Act has not been pursued during the tenth five year
plan. These efforts would have to be intensified during the eleventh five year plan.
There is a perceived need to have a fresh look at the EC Act to review the
implementation of various provisions. A review committee consisting of professionals,
legal experts and concerned agencies /stake holders will be constituted by BEE to
look into this. It may be established on a continuing basis with a mechanism to
receive feedback from the stake holders on the EC act and suggestions for
improvement. BEE will also adequately support the activities to establish &review
energy consumption norms for the notified designated consumers.

4.4.2 Identify the barriers for improving energy efficiency and propose fiscal
and other measures

Business firms often claim that that they do not have the financial means to
implement the EC measures and consequently the government should provide
financial assistance. Lack of access to capital, perceived uncertainty concerning
savings, a high private discount rate and limited avenues to vet the energy efficiency
measures and inadequacy of a reliable measurement and verification regime are
the major barriers impeding implementation of energy efficiency projects.

Customers are unwilling to invest their own funds in what is considered a “non-core”
activity. Financial institutions are unfamiliar with energy efficiency investments and
perceive them as risky. Energy services organizations are inadequately funded.
Creation of an energy efficiency fund can provide needed resources to implement
pilot or demonstration energy efficiency projects, help reduce risk perceptions,
stimulate the ESCO market, and fund projects in the public sector.

Page 10 of Chapter 4
Demand Side Management & Energy Efficiency Working Group on Power for 11th Plan

Financing and information programs can play a central role in promotion of energy
efficiency. To promote energy efficiency, there is an imperative need to create an
appropriate set of incentives through pricing and other policy measures. For a
chronically electricity-short situation, short-turnover-period technologies should be
the primary candidates for implementation followed by the planting of energy
efficiency seeds that will yield longer term benefits. Short term measures can be
supported by public policy measures such as information & demonstration, standards
and labeling, R&D, market transformation, taxes/tariffs. Long term measures can
be fostered & promoted on business line by demonstration/pilots, Energy
Performance Contracting in Govt. buildings, aggregation of projects (similar to
approach being followed for bundling small CDM projects), demonstration/pilots and
standard ESCO contracts. Financial institutions would be roped in for promoting
ESCO businesses.

Among non- fiscal measures may be award schemes similar to national energy
conservation awards recognizing performing units. A rating scheme may also be
evolved to rank the performance of units other than best performers and publicize the
same to the share holders of the company.

4.4.3 Other strategies

Among other strategies include the following:

• Track emerging trends in energy efficient technologies and device plans to


support research, development and deployment by end users in the
designated consumer and other sectors
• Encourage planners & regulators related to energy sector to adopt integrated
resource planning in the entire value chain of activities, right from extraction
or procurement, conversion to final end use.
• Rationalizing pricing for various forms/sources of energy to encourage
promoting efficient choices and appropriate substitution in tune with the
Electricity Policy, Tariff Policy and Rural Electrification (RE Policy ) of Govt. of
India.

Funding support proposed for the policy measures is Rs 10 Crores (BEE). It does not
include provision for fiscal measures.

4.5 BUDGET OUTLAY FOR THE 11TH PLAN

The total budget requirement for a period of five years for the overall establishment
and functioning of the identified activities/ projects on DSM, EE and EC has been
estimated to be Rs 653 Crores and the details of the same are given below:

Page 11 of Chapter 4
Demand Side Management & Energy Efficiency Working Group on Power for 11th Plan

Funds Requirements - 11th Plan

No. Focus Area/Sector Activity Funds Requirements


in Rs. Crores
At At Total
BEE SDAs
1. Strengthening of Establishment of Central 150 170 320
Institutional Set up in Energy Conservation Funds
BEE and SDAs under EC Act

Organizational strengthening
of BEE, and Establishment of
Energy Conservation and
Information Centre (ECIC)
within BEE

Establishment of State level


Energy Conservation Funds
under EC Act

2 EC Programs in targeted sector


A Industrial Sector Comprehensive Studies in 15 15 6.8 21.8
(Energy Intensive sub-sectors including
industries as development of specific
covered in the EC energy consumption norms
Act)
B Small & Medium Comprehensive Studies in 25 12.5 6.8 19.3
Enterprises clusters sub-sectors,
including 3 clusters in North
Eastern Region )

C Commercial Comprehensive Studies in 4 17 21


Buildings & commercial buildings covering
Establishments office buildings, hotels,
hospitals and shopping malls

Expertise development of 10 10 20
energy auditors, architects,
builders, municipalities, etc for
promotion /development of
ECBC in states,
d Domestic/Residential Undertaking of studies by 50 34 84
Sectors SDAs to efficient appliances,
labeling of 10 more
appliances/equipment,
Strengthening of 10 testing
labs, Awareness campaigns
on labeling program by BEE
and SDAs

Page 12 of Chapter 4
Demand Side Management & Energy Efficiency Working Group on Power for 11th Plan

E Street lighting and Dissemination of information 2 8.5 10.5


Municipal water on successful projects
pumping implemented by some of the
states, Pilot energy audits and
projects in states and follow
up work in initiating and
implementation of state level
EC programmes
F Agriculture Sector Collection, documentation and 5 5 10
dissemination of information
on successful projects
implemented by some states,
launching of awareness
campaign in all regional
languages in print and
electronic media and

G Transport Sector Setting up of norms for 2 8.5 10.5


specific fuel consumption for
automobile and Transport
(Services/Public transport)
and promotional studies for
public transportation systems.

3. DSM PROGRAMS Orientation Programs for 15 (for 15


regulators & DISCOMs -, BEE
Design of pilot scheme for and
Negawatt savings for SDAs)
DISCOMs

4. HRD PROGRAMS Orientation programmes for 75(for 35 110.44


Government departments/ BEE
Ministries, Cadre for energy and
managers/auditors, SDAs)
Programmes and awareness
campaigns for schools,
colleges, farmers, NGOs,
Public, industrial operators,
drivers, etc. (Details at Table-
1)
5 Policy Research Policy Research for 10 10
Accelerating Adoption of
Energy Efficiency and DSM
Programs
Total 350.5 301.6 653

Page 13 of Chapter 4
Demand Side Management & Energy Efficiency Working Group on Power for 11th Plan

4.6 RECOMMENDATIONS

The target of additional electricity savings which may accrue to the national economy
at the end of 11th Five year plan as a consequence of intensive energy conservation
and DSM drive is expected to be about 5% of the anticipated energy consumption
level in the beginning of 11th Plan. BEE will device a suitable mechanism for
assessing these savings. The outlay for various strategies and programs as
proposed is Rs. 652 Crores. Out of this proposed allocation, Rs 350.5 crs is the
estimated requirement for BEE at the centre and the balance Rs. 301.6 crs as the
assistance for strengthening the institutional structure at the State level for effective
implementation of EC Act. These initiatives will also seek funding support from state
governments, other complementary programs, user industry, financial institutions,
and other donor agencies besides innovative financing options.

*******

Page 14 of Chapter 4
Research & Development Working Group on Power for 11th Plan

Chapter 5

RESEARCH & DEVELOPMENT

5.0 INTRODUCTION

With the twin cries of depletion of energy resources and environmental pollution, it
has become more crucial to develop efficient & clean power plants and their delivery
system. These plants should be capable of effective utilization of resources such as
coal, natural gas & other sources of energy. Thus, in order to meet India centric
requirements, various sectors related to the field of energy have been identified for
segregating different research avenues. The depletion of fuel resources has resulted
into the need of exploring renewable power generation. Similarly, the application of
distributed power generation may be useful for electrification of remotely located
unelectrified villages. Apart from this, application of new technologies in the field of
generation, transmission & distribution also needs to be given utmost emphasis.

In view of the above, it is proposed to categorize the R&D initiatives into three
different sectors, viz. Generation, Transmission and Distribution. Generation will
have 7 Subgroups. Necessary emphasis is given to each sector. In each sector
various technologies will be taken up for demonstration & development. The list of
different sectors can be enumerated as below:

1. Generation Sector
¾ Thermal
¾ Hydro
¾ Fuel
¾ Environment
¾ Renewables
¾ Distributed Generation
¾ Nano materials
2. Transmission sector
3. Distribution sector

Considering that certain overlaps between different sectors such as fuel,


environment and renewables are unavoidable, they have been put under one head
of Generation.

5.1 OVERVIEW OF R&D

R&D in the power sector is presently in the domain of following organizations:

i) R&D wings of Corporations like the NTPC, NHPC, PGCIL and other units of the
Ministry of Power (MoP).

Page 1 of Chapter 5
Research & development Working Group on Power for 11th Plan

ii) Applied R&D under MoP schemes like RSoP, in-house Research projects of
CPRI and the National Perspective Plan projects recommended recently.
iii) R&D laboratories of CSIR working on energy related areas and sponsored projects
of DST.
iv) Industrial R&D by organizations like BHEL and other equipment manufacturers.

In the generation sector commendable work has been done by NTPC and BHEL in the
areas of stabilization of 210 and 500 MW units, development of pulverized coal fired boiler
for coal with high ash content, efficiency improvement of Thermal Power Plants, control,
instrumentation and loss minimization. Similarly in the hydro generation, BHEL, NHPC and
other hydro utilities have contributed in uprating of old units, improving turbine design etc.
In transmission, PGCIL and BHEL have introduced many new technologies like Series
Compensation, Thyristor Controlled Series Capacitor, Controlled Shunt Reactor, etc.
PGCIL have contributed to the development of high temperature conductors, development
of insulators, introduction of 800kV AC and planning for ± 800 kV DC first time in the
country.

Many of the developments by PGCIL and NTPC have come through project route in the
county and although their R&D units have not shown substantial expenditure on R&D, the
organizations have encouraged new technology.

It is noticed that where as some of the available technology abroad are being introduced in
the country, commensurate R&D efforts to get it improved and sustained through available
inhouse resources, has not been pursued. As a result, there is no technology
breakthrough that has actually taken place in power sector through indigenous route.

5.2 TECHNOLOGY DEVELOPMENT IN POWER SECTOR

The in-house R&D setups of major utilities like NTPC, NHPC and PGCIL address
introduction and absorption of new technology primarily through project routes. Major
manufacturers like BHEL, Crompton Greaves have their own R&D set up, focusing on
product development. Central Power Research Institute (CPRI) is provided with capital
funds from the Ministry of Power for inhouse research as well as disbursement of research
funds to utilities, industries and academic institution. Central Electricity Authority has a role
in identification of appropriate new technology for the country. Recently a few projects
under National Perspective Plan on R&D have been taken up which are collaborative
research projects involving more than one organisation. The R&D policy of the
Government is to promote R&D projects that help the nation to become self reliant in
technology.

R&D by the PSUs has so far been at a low level. It is only in late 10th Five Year Plan
NTPC and PGCIL have taken up a few good research projects mainly oriented towards
performance improvement of generating stations and National grid. Government initiative
in the distribution under APDRP scheme and in the area of renewables has initiated good
research work by many organizations involving academia, utilities, NGOs, equipment
suppliers and research laboratories. This spur in R&D in the field of distribution of power
which is attributed to a large investment in this area could also pave way for higher R&D
initiative in transmission and generation.

Page 2 of Chapter 5
Research & Development Working Group on Power for 11th Plan

Looking at the R&D expenditure in India it is learnt that the R&D expenditure by
organizations like the NTPC with turn over of more than Rs.28000 crore and profit above
Rs. 6000 crore is less than Rs.7 crore in last 2 years. PGCIL’s R&D expenditure is still
less. BHEL has been spending on R&D 1.0% of its turn over for the last 2 to 3 years and
plans to increase it to 1.5% The expenditure by CPRI in the Xth Plan is around Rs. 67
crore. The RGGVY scheme of MOP launched in 2005 has earmarked Rs.160 crore
amounting to Rs.1% of scheme cost, for enabling activities including technology
development. The expenditure on R&D incurred by Coal India Ltd. during the X Plan was
Rs.7.5 crore and none of the work undertaken by it was related to Power Sector.

5.3 IDENTIFIED PROJECTS FOR 11TH PLAN BY CENTRAL UTILITIES

An interaction was made with NTPC, BHEL, PGCIL, DSIR to find out their R&D plan
for the XI Plan period. The projects identified by Central Sector Units viz. NTPC,
Powergrid, BHEL and CSIR are listed below:

NTPC has identified a few projects for inhouse research where they would involve
other research institutes like BARC, CPRI, CSIR and other consulting houses. The
list of projects identified by NTPC is as follows:

1. Development of Flue gas heat recovery system for a 200 MW Unit.


2. IGCC technology demonstration project.
3. Development of Automated boiler tube inspection system (robotics
application).
4. On line condition monitoring of power transformers.
5. Modelling & design of natural draft cooling tower assisted flue gas
dispersion.
6. Technology demonstration for suitable capacity solar (Thermal).
7. Development of 10 KW sterling engine based TDP suitable for distributed
generation.

PGCIL has also identified a number of inhouse projects for research which are as
follows:

1. Technology Development for +/- 800 kV HVDC system for transfer of 6000
MW power from NER to NR
2. Aerial route survey using Air borne laser terrain (ALTM) along with
National Remote Sensing Agency (NRSAR)
3. Development of High surge impedance loading line (HSIL) – 400 kV
Purnea – Biharshariff D/C
4. Development of Fault current limiter at 400 kV level
5. Indigenization of polymer insulator
6. Specification of suitable oil for transformer
7. Intelligent grid
8. Design of Converter transformer
9. Development of Converter transformer-less HVDC system
10. Development of 1000 / 1200 kV EHVAC
11. Residual life assessment of transmission system

Page 3 of Chapter 5
Research & development Working Group on Power for 11th Plan

12. Indigenous development of GIS


13. Real time digital simulator and studies
14. Indigenous development of high strength insulators like 320 / 420 kV AC &
HVDC
15. Development of 400kV compact line
16. Lightening mapping

BHEL has identified a few broad based projects in generation, transmission and
distribution which are given as under:

1. Clean coal technologies.


2. Super critical boilers.
3. Ultra High Voltage Equipment.
4. IGBT based drives and controls.

The laboratories of CSIR who also carry out basic and applied research have identified
following inhouse research programmes related to Power Sector for the 11th plan:

1. R&D on Photovoltaics and other solar energy applications (NPL, New


Delhi)
2. Energy for cleaner and greener environment (CECRI, Karaikudi).
3. Bio energy technology: Strategy designing of Jatropha curcas for bio
diesel (NBRI).
4. Development of gas to liquid (GTL) processes for fuels (NCL).
5. Hydrogen economy initiative (NCL, Pune).
6. Development of coal to liquid (CTL) technology for synthesis of liquid from
hydrocarbons (CFRI, Dhanabad).
7. Development of a composite approach suitable for clean coal initiatives
(CMRI, Dhanabad).
8. Development of Underground coal gasification and IGCC Technology in
India (CMRI, Dhanabad).

5.4 R&D PROJECT PROVISIONS AND TEST FACILITIES FOR CPRI

CPRI, Bangalore has proposed various in-house & collaborative research activities.
Budget allocation for carrying out such functions & developing a world class test labs
along with the enabling infrastructure has already been proposed. CPRI proposes an
allocation in the range of Rs. 731 crores to be made available in 11Ith Five Year Plan. The
detailed break up is:

Page 4 of Chapter 5
Research & Development Working Group on Power for 11th Plan

A Investment on Dielectric Material, Diagnostic Rs. 25.80 crores


Testing & Simulation Techniques
B R&D Projects (In-house, RSoP and National Rs. 61.20 crores
PowerPlan)
C Facility addition to upgrade laboratories to test Rs. 94.00 crores
400 kV breakers, etc.
D Expenditure on Spill over schemes from X Plan Rs. 36.00 crores
E High Power Test Facility Addition and Creation Rs.514.00 crores
of new facilities of CPRI
F Upgradation of Ultra High Voltage Test Facility Rs.30.00 crores
at Hyderabad
Total Rs.761.00 crores

5.4.1 Need for restructuring of CPRI

CPRI was established to work as a nodal agency for power sector research but had
a larger role assigned to work as a neutral testing laboratory. Although the
organisation has contributed to encourage R&D in utilities, academic institutions and
in its own laboratories, it has not been able to build up resources to work as a driver
of R&D in the power sector.

It is recommended that a restructuring of CPRI is necessary if it has to play a


proactive role in collaborative research in the country. For this the following are
suggested:

a) Testing has to sustain on its own and as far as possible government grant
should not be utilized for meeting test facility requirements. The beneficiaries
of test facility, i.e., the manufacturing units and utilities should largely bear
this burden.

b) CPRI should be corporatised to reduce its dependence on Government


funding and have better operational flexibility. This would help CPRI to be
competitive and self reliant. The major utilities like NTPC, PGCIL, NHPC and
PFC should come forward to make it happen.

c) CPRI is to develop its ability to enhance industrial & system related


consultancy work and get more sponsored projects for improving its financial
health.

5.5 MAJOR PROJECT PROPOSALS FOR 11TH FIVE YEAR PLAN

5.5.1 IGCC Technology

IGCC technology, using coal gasification, allows the environmental benefits of a


natural gas fueled plant and the thermal performance of a combined cycle. Coal is
gasified with either oxygen or air and the resulting synthesis gas (or syn. Gas)
consisting primarily of hydrogen and carbon monoxide is cooled, cleaned and fired in

Page 5 of Chapter 5
Research & development Working Group on Power for 11th Plan

a gas turbine. The hot exhaust from the gas turbine feeds a heat recovery steam
generator (HRSG) where it produces steam that drives a steam turbine.

IGCC plants are reported to work well with bituminous coals (262 MW Wabash
River, 250 MW Tampa USA and others). Other features are high sulphur removal,
total volatile mercury removal, production of 40% lesser solid -products by and
consume 40% less water compared to PC plants. Entrained flow gasifiers are used
in IGCC plants abroad, which deliberately operates in the higher temperature
slagging regime to avoid tar formation.

Further it is noted from the reports that Wabash River IGCC plant showed a drop in
the performance owing to reduction in fuel quality to sub-bituminous and lignite
variety. The moisture content in the coal seems to play a role in slurry concentration
combined with the increased ash content in the lower rank coals. The energy
density of the slurry deteriorates markedly. Generally, it is felt that there is a greater
need to demonstrate and improve the performance of IGCC for low rank sub-
bituminous coal. While entrained flow gasifier appears to accommodate all ranks of
coal there is a marked increase in cost and reduction in performance with low rank
and high ash coals.

For Indian conditions pressurized fludized bed gasification is preferred. Efforts are in
progress in the country for the development of125 MW IGCC Unit (gross efficiency
39.5%). The technical approach to scale up is yet to be established and the
commercial utility size IGCC Unit is likely to be operational by 2011. One IGCC
Project on this route has already been launched and it is recommended that it
should be speeded up, by NTPC with its own funds.

5.5.2 Steam Generator Condition Assessment Model Through Neutron


Activation Techniques
The objective of the proposal is to development of a comprehensive Boiler Condition
& Performance Assessment. Boiler Condition asessment shall be done through a
combinatorial program of Neutron Activation Technique, Electro-Mechanical
Acoustic Transducer, Fiber Optic embedded Raman Scattering Technique. The
entire proposal is to be executed in an integrated manner. The nature of the project
is such that the elements mentioned below are neither modular nor discreete, rather
they are intrinsically intermingled and interdependent and hence cannot be taken up
in a serial manner. Though interdependent, the main elements of technology
development in the project shall be following:
It would involve complete, identify the required competence areas and potential
collaborating institutes for each of the following technologies and initiation of its
execution:
i. Neutron Activated Tomography for scanning of Boiler Tube Thickness.
ii. Electro-Mechanical Acoustic Transducer based scanning of Boiler Tube
Thickness.
iii. Fiber Optic embedded Raman Scattering Technique or any other
alternate technology for scanning of Boiler Tube Metal Temperature.
iv. Neutron Activation based combustion visualization technology.

Page 6 of Chapter 5
Research & Development Working Group on Power for 11th Plan

Technologies are available for boiler condition assessment. However the major
issue involved is to make it suitable & approachable, when it comes to real life
situation in a boiler. The main deliverable for the project is to demonstrate these
technologies in an integrated manner for true assessment of boiler condition.

5.5.3 Advanced RLA methodologies (Robotic corrosion mapping, phased


array technology, remote eddy current, temper embrittlement and
electro magnetic acoustic transducers)

Robotic based Corrosion mapping system for water wall tubes through Magnetic
Inductance Bridge based robotic system. The water wall tubes in the primary pass of
thermal power plant boiler are subjected to severe corrosion problems especially in
the burner zones leading to loss in thickness. The wall thickness of each tube needs
to be monitored during annual shutdown periods for ascertaining their suitability for
continued service and schedule for replacement if necessary. In view of the short
shut down periods, it is not possible to measure the thickness of all tubes using
conventional ultrasonic technique. In a robotic based system, the probe/magnetizing
coil is supported on robotic device which can crawl along the whole length of the
water wall tubes and maps the corrosion thickness.

The high temperature boiler tube during service forms coherent oxide layer on the
outer surface due to oxidation. The presence of this oxide layer on the outside of
tubes interferes with ultrasonic wall thickness measurement and prevents proper
sound coupling during conventional UT technique. The application of EMAT probes
permits enables direct measurement without any surface cleaning of the boiler.
When coupled with a robotic device, large no. of tubes and different elevations can
be covered in a short shut down period.

Phased array technique is a specialized type of testing that utilizes multi element
array transducers and software controls for steering the ultrasonic beam. In view of
complexity in shape & geometry of component of turbine components such as
blades, rotor steeple and disk rim attachments, the conventional techniques suffer
by reliability, accuracy & reproducibility. The advanced linear phased array ultrasonic
technology wherein multiple UT probes mounted in a single holder is used to for this
purpose and reported that the reliable and redundant results can be obtained in
respect of defect detection, sizing and shape.

HP / IP rotors suffer in-service degradation from rotor material temper embrittlement.


The rotor material fracture toughness, which governs the size of the critical flaw for
fracture, is hence adversely affected. A reliable assessment of the fracture
toughness properties of steam turbine rotor requires sampling of material from in-
service rotor. A miniature sample removal and small punch testing technique for
direct estimation of fracture toughness provides a rational basis for reduction of
conservatism during RLA of rotor.

The remote eddy current/CCTV system is capable of examining the trailing and
attachment areas of L-0 and L-1 turbine blades without turbine disassembly. Eddy
current tests have also been successfully used to detect cracks in the area of the
satellite wear strips on the leading edge of last stage blades and for inspection of

Page 7 of Chapter 5
Research & development Working Group on Power for 11th Plan

turbine casing bolt and bolt holes. Critical turbine components must be evaluated to
assure safe operation during their lifetime.

The adoption of advanced RLA methodologies leads to the emergence of


sophisticated practice in RLA with reliable and upgraded assessment technologies in
the short time available during periodic maintenance, application of Robotics,
improved deterministic routes and evolution of technology options.

The project envisages development of state-of-art technology in the area and adopts
them in a few thermal power stations. The project will support a number of spin off
research in the related area.

5.5.4 Combustion modeling and technologies for utilization of fly ash


unburnt carbon in pressurized fluidized bed gasifier

The objective of the project is to demonstrate pressurized fluidized bed char


combustor in a pilot scale facility & to explore other ways of separating char from fly
ash of pressurized fluidized bed gasifier.

Pressurized fluidized bed gasifier operating in a bubbling mode normally gives lower
carbon conversion efficiency in the range of 90-91% only. The attributing factors are
particle attrition & elutriation from the bed. Freeboard reaction is normally limited due
to dearth of oxidant resulting in 15% combustibles in fly ash. The fly ash recycling is
another option to reduce the overall combustible in ash. For high ash Indian coal,
large amount of ash recycling is always a big threat in a pressurized system.
Another option is to separate char from fly ash & utilize the char in a separate
furnace. Various separation methodologies are still in developmental stage only.
Tribo-electrostatic separation, & dry fluidization separation are among few
technologies, which have been tried so far. However research work needs to be
carried for demonstration of such technologies for Indian coal.

The third option is to put the fly ash in a pressurized fluidized bed combustor to
produce steam & the hot gases i.e. a mixture of nitrogen & carbon dioxide at around
1000C can be reintroduced back to main gasifier. The heat carried over with the flue
gas will sustain the endothermic reaction & carbon dioxide can be used as a
gasifying agent in the gasification process.

The project would have deliverables in three stages. Modelling of the char
combustor with actual fly ash constituent as an input would be the first deliverable.
Next would be a development of a bench scale pressurized char combustor & final
will be its integration with main gasifier.

The cost of the project has been estimated as 19 crores & project is expected to be
completed in six years.

Page 8 of Chapter 5
Research & Development Working Group on Power for 11th Plan

5.5.5 Carbon Dioxide Storage In Geological Formations

The objective of the project is to study the possibility of long-term storage of CO2 in
geological formations such as basalt & other sedimentary rocks for CO2
sequestration.

Global warming, due to CO2 emission from different anthropogenic activities


including power plants is one of the major environmental problems, the world is
facing today. Carbon sequestration, consists of CO2 capture, transport and
permanent storage, is one of the pathways to contain CO2 emission. Establishment
of environmentally safe and permanent storage of CO2 is a major issue of the whole
carbon sequestration activity. Geological storage is considered to be most available
and safe for long term CO2 storage. CO2 storage in basalt or sedimentary formation
will be explored to demonstrate the possibility of CO2 storage in these formations.
Initially noninvasive technologies like 2D/3D & MT studies, bore hole sampling,
physical and chemical characterization of formations, kinetic studies, wire logging for
temperature & pressure profile, geological modelling etc. will be carried out to
establish the feasibility of CO2 storage in the identified formation. Subsequently CO2
will be injected at appropriate depth through bore hole and the movement of injected
CO2 will be monitored through surface and subsurface measurement. Detailed
modelling will be carried to predict the fate of CO2 in geological storage system in
long term.

Final deliverable for the project would be to demonstrate the process in field. The
cost of the project will approximately be 15 crores & duration is expected to be
seven years.

5.5.6 Value Added Products Technology For Fly Ash Utilization


The establishment of technology demonstration and production centers for value
added products from fly ash at six thermal power plants in India shall involve
introduction of state of art plant and machinery for manufacture of fly ash based
building products to demonstrate the techno economic viability for
commercialization. Certain separation and beneficiation facilities are also proposed
to be established for the benefit of power plants in terms of adding value to fly ash
as a raw material, which will lead to sale of fly ash as a commodity to various user
industries. Facilities are also planned at these centres, to ensure quality assurance
of fly ash products. The six centres proposed shall be at Ennore Thermal Power
Station, Tamil Nadu, Vijayawada Thermal Power Station, Andhra Pradesh,
Wanakbori Thermal Power Station, Gujarat, Koradi Thermal Power Station,
Maharashtra, Badarpur Thermal Power Station, Delhi and Ropar Thermal Power
Station, Punjab.

The implementation of the project will lead to dissemination of home grown


technologies and showcasing of product centers, revealing the features of fly ash
products, promoting widespread use of indigenous plant and machinery, promoting
energy efficient building concepts with fly ash products leading to zero energy
philosophy. Industry – Institute interactions for entrepreneur development,
awareness, training programmes and workshops, organized from time to time at

Page 9 of Chapter 5
Research & development Working Group on Power for 11th Plan

these centers will lead to promoting environment friendly value added utilization of
fly ash in India.

5.5.7 Fuel Cells: Demonstration Of Direct Alcohol/ Polymer Electrolyte Fuel


Cell Plant

There are many technical challenges, the fuel cell R&D work must cover wide
application in distributed generation market, embodying co-generation. The positive
technological implications, which would create the tendency towards more
economical fuel cell systems, hold the key. Further the significant technical
challenges with regard to integrating fuel cell system with available infrastructure,
reducing the capital cost through volume manufacturing and achieving widespread
use in various sectors needs to be addressed. The key points to be addressed
regarding cost reduction include (i) materials, (ii) complexity of integrated systems,
(iii) temperature constraints, (iv) manufacturing processes, (v) power density
(footprint reduction), and (vi) benefit from economies of scale (volume) through
increased market penetration. Under fuel flexibility the R & D topics are (i) non-
traditional fuel storage (H2), (ii) transportation fuel reforming, (iii) renewable fuels
processing (reforming, gasifying, clean-up), (iv) biogas operation, and (v) tolerance
to gas supply variation. Further, the RD & D occurring today for specific systems
and system integration include (i) power inventers, (ii) power conditioners, (iii)
hybrid system designs, (iv) hybrid system integration and testing, (v) operation and
maintenance issues, and (vi) robust controls for integrated systems.
Direct Alcohol –methanol based fuel cells are of interest as a future source of
power, because of two reasons. These are in early stages of development. Firstly
methanol is easier to transport, distribute and store than hydrogen. Secondly , when
produced from biomass sources it is almost CO2 neutral to the environment. These
are an excellent candidate for very small to mid-sized applications, such as cellular
phones, PCs up to automobile power plants.The challenges in R&D are both at the
level of system integration and also at the more fundamental level of researching
better catalysts and membranes that are less leaky to the methanol. Cost
optimization is also needed. Improvements are needed in expensive catalysts
presently used. The R&D project shall address these concerns by using a multi-
disciplinary effort and suitable networking with CSIR labs and institutions abroad.
The project includes integration of a two/five kW output fuel cell stack and its
evaluation under various practical environmental conditions.

5.5.8 Distributed Generation


Although substantial development is being carried out in various institutions with
support from MNES and a number of designs based on biomass gasification, bio
fuels, are available, the penetration into the India market has been poor. Small units
of distributed generation in unit sizes of 10 – 20 kW shall be able to complement
village electrification but cannot be a stand alone reliable source of power supply. In
order to contribute to power sector, the size has to be up to 0.5 - 1 MW which would
need to have connection to the grid. For large scale use of distributed generation
using biomass gasification as primary method and its integration with other
generation based on solar, diesel and grid, the scaling up issues, reliability issues,
capacity building, revenue models, fuel linkages, etc. are to be addressed at a much
larger scale.

Page 10 of Chapter 5
Research & Development Working Group on Power for 11th Plan

It is proposed to have a 2 stage implementation strategy during the. 11th Five Year
Plan. At the end of 1st year of 11th Plan, the package solution to ‘Distributed
Generation’ will be found for different alternatives which will suit the rural resource
base (including solar energy). Five demonstration projects will be made fully
functional with 100 to 1000 kW rating by end of 3rd year. The R&D will address
biomass generator efficiency improvement, biomass gasification, solar, diesel and
grid connectivity and optimum use of the option for energy saving. The issues of
fuel linkage and maintenance would also be addressed. The project shall support a
number of small prototypes taken on experimental basis depending on R&D content.

IIT, Guwahati and NIT, Silchar shall be associated in engineering and research
activities of projects for North-East.

The R&D programme in 1st stage would be a confidence building exercise to refine
and optimize the technology which would lead to mass production in 2nd stage.
Following schemes shall be designed and demonstrated:

1) Stand alone Biomass based generation


2) Biomass based generation connected to the grid
3) Biomass based generation that can be integrated with solar-PV, solar thermal
based or diesel based generation by a suitable micro or mini grid.

The above would have the benefits of being able to provide access to electricity,
depending on local conditions in rural areas.

A group of five to ten Distributed Generation units spread over different villages that
are reasonably close together would form a cluster. This is aimed at providing
necessary technology and service support to the individual villages. The service
cum technology centre for a cluster would have necessary skilled manpower, tools
instruments and spares. Good monitoring of individual projects during installation,
and commissioning to achieve sustained operation would also be done. This
approach is considered essential for the success of the programme.

Typical project cost is between Rs. 2 crore to Rs. 20 crore and the total allocation for
this scheme is estimated to be Rs. 75 crore.

5.5.9 Nano Material Applications – For Power Sector

Research on Nano materials in various fields of science is promising and needs to


be directed towards practical and useful application. This project will be exploratory
in nature to promote research in Nano materials for power system applications.

Application – 1

Super Capacitors : High energy storage compact super- capacitors are available for
small energy long duration applications. It is expected that larger size capacitors
would be available in market. Large number of capacitors in series and parallel can
work for energy storage devices in voltage source converters which has a large
number of application. In larger sizes, these capacitors can be substituted for super
conducting magnetic energy storage devices (SMES) for providing grid stability.

Page 11 of Chapter 5
Research & development Working Group on Power for 11th Plan

Application - 2

Carbon fibers reinforced aluminum conductors for transmission line application could
be promising for high temperature application. Research needs to be promoted in
this areas.

Application – 3

Nano Composite Polymer and Ceramic research - In ceramic and polymer


applications use of additives shows promise. Research in this area should be
focused to practical power system application such as high strength ceramic
insulators, dielectric material with high dielectric control for capacitors etc. Ceramic
based nano material paint can work better than photo voltaic cells for solar power
generation. Nano materials hold promise in CO2 capturing and sequestration.

Application – 4

MEMS and Sensors – Nano material application in sensor development has shown
promise. Sensors of all types, temperature, pressure, strain gauges andfor
electrical qualities can have much better efficiency using nano materials. Research
in these areas have to be promoted and directed to Power System application.

Although good work is being carried out in IITs and IISc the funding is too meagre to
support useful research. The production technology of nano material is complicated
and equipments are expensive. Unless high quality research is carried the
institutions having good infra structure, the impact of the technology will not be
substantial

As knowledge in nano science grows, application in thermal power engineering ash


handling, environment control, un-burnt carbon detection, etc. can be increased.

Although Science & Technology Department would be focusing on Nano material


research, it is felt that MoP should contribute to give it an application orientation. A
budget of Rs.100 crores is proposed in the 11th Plan for supporting Nano materials
research for power system applications.

5.5.10 Advanced Power Electronics Technologies for Transmission

There are a number of technologies under FACTS controllers which provide


flexibility to power transmission and are considered important in view of open access
being introduced. We have in India TCSC (Thyrister Controlled Series
Compensation) already introduced. Other promising technologies are:

i. Static Synchronous Series Capacitor (SSSC)


ii. Static Compensator (STATCOM)
iii. Unified Power Flow Controller (UPFC)
iv. Thyrister Controlled Phase Angle Regulator (TCPAR)

Page 12 of Chapter 5
Research & Development Working Group on Power for 11th Plan

The design of equipments, controllers for these devices need extensive research.
One major demonstration project is recommended to be taken up on R&D route with
private participation.

5.5.11 AC/ DC Microgrid Demonstration Project By Deploying Various


Distributed Energy Sources, Energy Storage Systems, Communication
Systems, AMR, DVR, STATCOM, HVDC Light

Distributed power generation system is emerging as a complementary infrastructure


to the traditional central power plants. This infrastructure is constructed on the basis
of decentralized generation of electricity close to consumption sites using Distributed
Generation (DG) sources. The increase in DG penetration depth and the presence
of multiple DG units in electrical proximity to one another have brought about the
concept of the micro-grid. A micro-grid is a portion of a power system which includes
one or more DG units capable of operating either in parallel with or independent
from a large utility grid, while providing continuous power to multiple loads and end-
users. The idea supporting the formulation of the micro-grid is that a paradigm
consisting of multiple generators and aggregated loads is far more reliable and
economical than a single generator serving a single load.

India being geographically diverse country with habitation spread over all kind
terrains such as, hilly inaccessible areas, desert lands, small islands etc, providing
reliable power at affordable price is a challenging task. At the same time, India is
endowed with different kinds of renewable sources like solar, hydro, bio-mass etc.
Micro grid system encompassing locally available one or more resources for power
generation could offer possible solution to the challenges of a nation to provide
energy to the remote locations.

The demonstration micro-grid project would also include energy storage systems to
supply power to critical loads and also for emergency system start-up power. These
projects incorporating concepts of microgrid would include suitable communication
system required for AMR. Research on AMR technology is needed to optimize cost
of overall distribution system.

The advantages of VSC based HVDC system can be best utilized for applications
like:

¾ Deep river crossings


¾ Power supply to isolated loads (supply to distant town, mine, island or even
production platform in the sea needing power from main land),
¾ Feeding Power from small isolated generation (wind, small hydro, tidal solar
etc.) to a grid or to a separate load without affecting power quality of receiving
network.

The implementation of technology developed in the area of power distribution is also


envisaged. Here, power electronics devices such as DVR, STATCOM etc. based on
VSC based converters would be developed. These would be included in the feeders
to improve power quality. These demonstration systems would have suitable AMR

Page 13 of Chapter 5
Research & development Working Group on Power for 11th Plan

system to monitor energy supplied to customers. The deliverables from the project
would result in demonstration of high quality power distribution systems.

The selection and development of suitable power electronics devices and a field
show casing as stated above forms an integral part of the project.

The project would pave the way for design of future rural energy network, where
distributed generation sources are likely to be deployed and would act as a
benchmark.

5.6 SHORT LISTED SHORT TERM & LONG TERM PROJECTS

The projects identified to be taken for R&D during the 11th Plan are;

Duration Budget
Sr. Project Definition Sector of the (in
No project Crores)
1
GENERATION SECTOR 333.50

A THERMAL GENERATION

Generation technology, Fuels and


1.1
Environment
Development of sensor systems for
online fuel calorific value & unburnt
Generation Short
1.1 carbon in ash 3*
Thermal term
measurement(Deployment in 5 units)

Steam Generator condition


Generation Long
1.2 assessment model through neutron 20 *
Thermal term
activation techniques

Development of desalination
Generation Short
1.3 technology with LP exhaust steam/ 16 *
Thermal term
Solar heat source (10 cubic m/hr)

Advanced RLA methodologies


(Robotic based corrosion mapping
system – Phased array ultrasonic
technique – Hydrogen embrittlement – Generation Long
1.4 25 *
Remote eddy current technique – Thermal term
Temper embrittlement of rotors –
Electromagnetic Acoustic
Transducers for boiler inspection )

B HYDRO SECTOR
Excavation of large size Caverns with Generation Short
1.5 1.5*
appropriate stabilization technology Hydro term

Page 14 of Chapter 5
Research & Development Working Group on Power for 11th Plan

Duration Budget
Sr. Project Definition Sector of the (in
No project Crores)

Generation Short
1.6 Soft rock tunneling 1.5*
Hydro term

Application of GIS / GPS in river Generation Short


1.7 1.5*
inflow / discharge measurements, Hydro term
flood forecasting, etc.

C FUELS AREA
Combustion modeling and
technologies for utilizing unburnt Long
1.8 Fuel 19*
carbon in ash in PFB gasification term

Development of multiple feed


Short
1.9 conditioning system for biomass fired Fuel 2*
term
boiler
Advanced circulating pressurized
Long
1.10 fluidized bed gasifier Fuel 10*
term

D ENVIRONMENTAL AREA

Technology development of flue gas


desulphurization system for NE high
Short
1.11 sulphur coal through electron beam Environment 6*
Term
(SO2 to SO3 conversion)

CO2 storage in geological formations


Long
1.12 like Basalt and Sedimentary rocks Environment 15*
term
Value added products technology
demonstration and 6 production
centers for fly ash
Long
1.13 utilization(Production technology, Environment 20*
Term
state of art plant and machinery, fly
ash beneficiation schemes, quality
assurance measures)
Emission control technologies for
Short
1.14 NOx, SOx Environment 3*
Term
E RENEWABLES AREA
Demonstration of direct
Short
1.15 alcohol/polymer electrolyte fuel cell Renewables 3*
term
plant(5 kw/2kw) and exploratory work

Page 15 of Chapter 5
Research & development Working Group on Power for 11th Plan

Duration Budget
Sr. Project Definition Sector of the (in
No project Crores)
on Deep coal beneficiation and Ultra
Super Critical Technology

Demonstration of LED lighting for


Short
1.16 rural electrification of one model Renewables 1*
term
village
Solar bio photovoltaic cells for
generation of Hydrogen, methane Long
1.17 Renewables 10*
using hybrid organic / inorganic term
system
Development of geothermal power Long
1.18 Renewables 1*
generation technology term
Distributed Long
1.19 Distributed Generation – Major Project 75.00
Generation term
NANOMATERIAL APPLICATIONS FOR Long
F Material 100.00
POWER SECTOR term

2 TRANSMISSION 70.00

Wide area measurements for grid Long


2.1 Transmission 10*
protection & control term

Testing and simulation laboratory for Short


2.2 Transmission 7.5*
SCADA (Complying with IEEE 61850) term
& demonstration projects

Development of online monitoring


Short
2.3 systems for substation equipments Transmission 4*
term
(like transformers, breakers, CTs, etc.)
to get early warning of failures

Long
2.4 Advanced power electronic Transmission 48.5*
technologies for transmission Term

3 DISTRIBUTION
25
AC / DC Micro-grid demonstration
project by deploying various
distributed energy resources, energy
storage systems, communication Long
3.1 Distribution 20*
systems, AMR, HVDC light, DVR, term
STATCOM, etc. for improving
reliability and power quality

Page 16 of Chapter 5
Research & Development Working Group on Power for 11th Plan

Duration Budget
Sr. Project Definition Sector of the (in
No project Crores)

Company 2003 2004 2005


% of
R&D Net % of R&D % of R&D
Net sales R&D R & D Exp R & D Exp Net sales
Exp sales Exp Exp
Exp
GE
2.7 149.7 1.80 3.091 154.481 2.00 3.425 122.886 2.79
(billion Dollar)
Siemens
4.73 69.77 6.78 4.65 70.23 6.62 5.155 75.455 6.83
(Billion Euro)
2003-04 2004-05 2005-2006
Company
R&D % of R&D Net % of R&D % of R&D
Net sales R & D Exp R & D Exp Net sales
Exp Exp sales Exp Exp
Alstom
473 16688 2.834 405 12920 3.13 365 13413 2.72
(million Euro)
Hitachi
371.8 8632.4 4.307 388.6 9027 4.305 405 9464.8 4.279
( billion Yen)
Mitsubishi Electric
136518 3309651 4.125 130548 3410685 3.828 130629 3604185 3.624
(million Yen)
BHEL
1041 103364 1.007 1252 103364 1.211 1517 145255 1.044
(million Rupee)
Energy storage schemes for
Short
3.2 improving the reliability of sensitive Distribution 5*
term
loads
NOTE: figures in last column with suffix * indicates sub components of the budget indicated for the
area of research.

New Projects yet to be identified : Rs. 24.00 crores

SUMMARY

Total for Generation : Rs.333.50 crores


Total for Transmission : Rs. 70.00 crores
Total for Distribution : Rs. 25.00 crores
New Projects yet to be identified : Rs. 24.00 crores
Total : Rs.452.50 crores

5.7 R&D FUNDING

R&D expenditures of some major utilities and manufacturers in the field of power are
indicated below:

It may be observed that most of the organizations spend between 1.8 to 6% of net
sales on R&D depending upon the nature of their business. Compared to this, the
R&D expenditure in India is very low.

Page 17 of Chapter 5
Research & development Working Group on Power for 11th Plan

NTPC has identified and taken up New Technology Development which started
during the Xth Plan. About Rs. 400 crore in IGCC project was proposed out of
which expenditure has been very little. NTPC has further envisaged to spend 0.5%
of its profit (i.e. about Rs. 30 crore per year) in new R&D projects. The list of such
project areas is given in para 5.3.1.

PGCIL has envisaged an expenditure of Rs.190 crore for R&D during 2007-12 in the
areas of EHV transmission, monitoring of Substations, and power flow enhancement
and grid availability. A list of projects identified by PGCIL is given in para. The
provisions for R&D activities are built into the transmission projects to be taken up
and do not reflect in separate R&D budget.

BHEL’s R&D efforts are directed towards development of technology in areas of


their commercial /business interest BHEL have indicated that it is spending 1 to
1.5% of turn over on R&D and are prepared to participate in national level R&D
projects in any of the following ways:

a) If BHEL invests, they need some assurance of business and some relaxation
in qualifying norms.

b) BHEL shall participate in national level R&D without issues on commercial


right or IPR provided that the entire funding is by the central government.

BHEL’s interest in R&D areas during 11th plan is listed in para 5.3.3

CSIR has identified a few projects for the XI Plan which are listed in para 5.3.4.
CSIR has a scheme ‘New Millennium Technology Development Scheme’ in which it
provides R&D funding to manufacturers without any IPR issues. At present, it is
recommending funding to organizations like BHEL in technology development areas
and IGCC.

Coal India would continue its work on Coal Bed Methane(CBM) which was taken up
through CMPDI during X Plan. The expenditure on R&D incurred by Coal India Ltd.
during the X Plan was Rs. 7.5 crores and none of the work was in the areas related
to Power Sector.

5.7.1 R&D Budget for 11th Plan

A substantial increase is recommended for the present level of R&D expenditure. As


the investment in the Power Sector is going to be upwards of Rs.9 lakh crore, the
Group recommends a budget approval of a modest 0.25% of it, which is around Rs.
1213 crore in 5 years.

The requirement of funds required for R&D during the 11th Plan would be Rs.
1213.50 crore.

Page 18 of Chapter 5
Research & Development Working Group on Power for 11th Plan

Sl Item Budget
No ( Rs in Crores)
1 R&D on Thermal& Hydro Generation, Fuels & 158.50
Environment
2 Distributed Generation – R&D and Demonstration 75.00
3 Nano materials applications for power sector 100.00
4 Transmission 70.00
5 Distribution 25.00
6 New Projects yet to be identified 24.00
7 CPRI( Details in Para 5.4) 761.00
TOTAL 1213.50

5.8 INTELLECTUAL PROPERTY RIGHTS

A few of the IPR issues both in public & private domain have been reviewed. As a
matter of fact, Government of India is the main funding agency & various institutions
& industry are also contributing in terms of technical assistance, the IPR needs to be
a shared model, specifically developed to match the present need. A general
guideline of the proposed IPR model is given below.

Since Government as such can’t own the IPR, a corporate body is supposed to be
constituted for the purpose. Complying with proposed institutional mechanism of
project implementation, the IPR of individual research component (Sub project) will
be owned jointly by the corporate body & individual research institute, carrying out
the sub-project.

If the executed project is a new technology demonstration, comprising of more than


one research components involving system integration, the IPR for the developed
technology as a whole will be owned by the corporate body & the project deploying
agency (P1). The detailed mode of sharing the IPR & technology licensing for each
project will be specific to the project & will be given a final shape only at the time of
signing MOU between project implementation committee & individual research
partners.

5.9 HUMAN RESOURCE DEVELOPMENT AND TECHNICAL COMPETENCE


BUILDING

India is on its accelerated path to become a global leader in power sector. It is not
only anticipating additional capacity, but also expecting more competitive
technologies both in terms of lower operating cost as well as lesser environmental
pollution. In order to comply with the growth rate, it needs both skilled manpower for
operating those plants as well as highly qualified research personnel to sustain a
steady growth in technology development. The manpower requirement research
centers are very specialized as fundamental research calls for a lot of dedication,
clarity of concept, innovation and patience. It is very difficult to get this breed of
researchers not only at induction level but also at middle and senior level. In order to
match it research program, XI plan envisages certain expenditure for human
resource development in power sector. Few of the proposed schemes are
enumerated below.

Page 19 of Chapter 5
Research & development Working Group on Power for 11th Plan

• Special fellowship scheme for research scholar employed for the purpose of
carrying out research both at individual research centres as well as at
project deployment stage. On completion of project, the researchers would
be given an opportunity to get absorbed in the agencies, where the project
would be deployed.
• Some of the research institutes should be assisted for developing them to
Centre of Excellence (COE) with all required infrastructure.

The success of the R&D projects will largely depend upon quality manpower,
freedom for research and continuity of work. The budget for HRD is not specifically
mentioned but included in the project cost. It is expected that project implementation
authorities will have sufficient autonomy given to them for selection of research
fellows.

5. 10 RECOMMENDATIONS AND POLICY ISSUES.

1. Technology advancements and research & development have so far not been
properly addressed. Major organizations like NTPC, NHPC, POWERGRID,
on the generation side and BHEL , ABB, SIEMENS on the manufacturing side
must enhance substantially their budget allocations for research and
development. The utilities should aim at least about 1% of their profit to be
utilized for research and development activities and the manufacturing
organizations should consider 3-4% to be provided for technology
development.
2. Networking of R&D resources and expertise would be an important strategy
aimed at getting effective results. CPRI, apart from testing, must reorient its
strategy and activities towards research.

3. Ultra Super Critical boiler technology, IGCC technology and oxy-fuel


technology are well researched abroad but have to be developed for Indian
coal. NTPC, the major Indian Central Sector utility should have its R&D
centre strengthened to expedite the work started during 10th plan on IGCC. It
is recommended that this project may be given top priority and completed
with the help of BHEL or with a private party if necessary.

4. There is a need to work with specialized S&T laboratories under CSIR & other
space and nuclear establishments to develop material technology for
advanced boilers, fuel cells, solar power, battery & super conducting material
application in power sector.

5. For the projects of National interest to be taken upon collaborative research


route the estimated R&D expenditure of 452 crores is recommended. It is
also recommended that in future capital fund support for R&D should be
reduced and utilities and industries should collaborate to fund R&D projects.

6. An institutional change in handling R&D is required. A suggestion is to have


generation, transmission & distribution R&D units to be established as
separate entities in the central sector undertakings or to set up a corporate
technology centre for R&D activities in various areas of power sector

Page 20 of Chapter 5
Research & Development Working Group on Power for 11th Plan

7. R&D import should be exempted from custom duty to encourage indigenous


R&D
8. Power sector should seriously consider attracting young talents by offering
them challenging opportunities. This will be possible by encouraging R&D
and offering a good package, like many MNCs are offering at present.

9. A High Power Committee in R&D should monitor R&D projects and regulate
funds. This will avoid duplication & ensure competitive R&D.

10. Organisations like CPRI and NPTI should be spared from manpower
optimization rules where vacant positions are surrendered. This is in view of
the depleting cadre of scientists and specialists in these organizations.

*********

Page 21 of Chapter 5
Development of Power Sector in NER Working Group on Power for 11th Plan

Chapter -6

DEVELOPMENT OF POWER SECTOR IN NORTH-EASTERN


REGION

6.0 INTRODUCTION

The North Eastern Region of the country comprises of 7 states; namely Arunachal
Pradesh, Assam, Manipur, Meghalaya, Mizoram, Nagaland, Tripura and Sikkim. It is
a land-locked region with ninety eight percent of its border being international. The
land -locked area which constitutes 8 percent of the total area of the country is
connected with the main land through chicken-neck across West Bengal.

In view of the slow growth of the region, special focus has been laid on economic
development of North-Eastern Region and Sikkim. Accordingly strategies have been
formulated for removal of infrastructure bottlenecks and creating a conducive
environment for overall progress of the region including private investment etc

6.1 STATUS AT THE BEGINNING OF 10TH PLAN

The Installed Capacity of North-Eastern Region was 2,230.3 MW at the beginning of


10th Plan. This Installed Capacity comprises of 1089.9 MW from Hydro, 1,140.2MW
from Thermal and 0.2 MW from Renewable Energy Sources. In addition, the Installed
Capacity of Sikkim was 107.9 MW including shares from Central Sector power
stations at the beginning of 10th Plan. State-wise details of Installed Capacity and
Power Supply Position are given Table 6.1 and6.2 respectively:

Table-6.1
Installed Capacity at the Beginning of 10th Plan.

(All figures in MW)


Thermal Renewable
State Hydro Coal Gas Diesel Total Energy Total
Sources
Assam 322.00 330.00 447.00 20.70 797.70 0.00 1119.70
Arunachal Pradesh 114.50 0.00 21.00 15.90 36.90 0.00 151.40
Meghalaya 257.70 0.00 26.00 2.00 28.00 0.00 285.70
Tripura 76.00 0.00 97.50 4.80 102.30 0.00 178.30
Manipur 82.20 0.00 26.00 27.40 53.40 0.00 135.6
Nagaland 72.20 0.00 19.00 2.00 21.00 0.20 93.4
Mizoram 41.30 0.00 16.00 28.90 44.90 0.000 86.20
Central Unallocated 124 0.00 56.00 0.00 56.00 0.00 180.00
Total(NER) 1089.9 330.00 708.50 101.70 1140.20 0.20 2230.3
Sikkim 44.9 58.00 0.00 5.00 63.00 0.00 107.9
Total (NER+Sikkim) 1134.8 388.00 708.00 106.7 1203.2 0.20 2338.2

Page 1 of Chapter 6
Development of Power Sector in NER Working Group on Power for 11th Plan

Table-6.2
Power Supply Position at the Beginning of 10th Plan

State Peak Energy


Shortage / Surplus Shortage / Surplus
(MW) (%) (MU) (%)
Assam -70 -10.2 -25 -0.7
Aru’chal Pradesh -0 -0.0 -2 -1.2
Meghalaya -5 -3.0 5 0.7
Tripura -16 -10.3 -34 -5.3
Manipur -4 -4.1 -16 -3.5
Nagaland -3 -4.9 -2 -0.7
Mizoram -2 -2.7 -6.0 -2.1
Total(NER) -105 -9.1 -80.0 -1.4
Sikkim -200 -5.5 -95 -0.5

6.2 REVIEW OF generation CAPACITY ADDITION PROGRAMME DURING


10TH PLAN

Planning Commission had set a generation capacity addition target of 1017.92 MW in


NER and 510 MW in the state of Sikkim during Tenth Plan. Out of these targets only
128 MW could be achieved during the 10th Plan. Capacity addition of 100 MW is
likely to be achieved during balance period of 2006-07. The State-wise details of
capacity addition target and achievement during tenth plan is given in table 6.3
below:

Table 6.3

S. State/Central Generation Capacity addition (MW)


No. Sector Target Achievement
From Expected Total
2002-03 to from
31.12..2006 1.1..2007
to
31.03.2007
1 Assam 138.00 - 100.00 100.00
2 Manipur 18.00 18.00 - 18.00
3 Meghalaya 132.00 - - -
4 Mizoram 102.92 22.92 - 22.92
5 Tripura 42.00 42.00 - 42.00
6 Arunachal - - - -
Pradesh
7 Nagaland - - - -
A State Sector 432.92 103.92 100.00 203.92
B Central Sector 585.00 25.00 - 25.00
C Total NER 1017.92 128.92 100.00 228.92

In addition to the target set by Planning Commission, Rokhia GT Ext. (21 MW) is also
commissioned during 10th plan

Page 2 of Chapter 6
Development of Power Sector in NER Working Group on Power for 11th Plan

INSTALLED CAPACITY AS ON 31.12.2006

The total Installed Capacity of NE Region (excluding Sikkim) as on 31.12.2006 was


2404.2 MW comprising 1113.1 MW hydro and 1244.2 MW thermal (including gas and
diesel) and 46.9 MW from Renewable Energy Sources., The total installed capacity
of Sikkim as on 31.12.2006 was 116.1 MW comprising 44 MW hydro and 63 MW
thermal (including gas and diesel) and 9.1 MW from Renewable Energy Sources.
The State-wise details of Installed Capacity as on 31.12.2006 are given in Table 6.4

Table-6.4
(All figures in MW)
Thermal Renewable Total
State Hydro Coal Gas Diesel Total Energy
Sources
Assam 332.0 330.0 447.0 20.7 797.7 0.2 1129.9
Arunachal Pradesh 116.5 0.0 21.0 15.9 36.9 26.0 179.4
Meghalaya 260.6 0.0 26.0 12.0 28.0 1.5 290.1
Tripura 78.0 0.0 160.5 4.8 165.3 1.1 244.4
Manipur 81.5 0.0 26.0 45.4 71.4 4.0 156.9
Nagaland 78.5 0.0 19.0 2.0 21.0 3.2 102.7
Mizoram 38.0 0.0 16.0 51.9 67.9 10.9 116.8
Central Unallocated 128.0 0.0 56.0 0.0 56.0 0.0 184.0
Total(NER) 1113.1 330 771.5 142.7 1244.2 46.9 2404.2
Sikkim 44.0 58.0 0.0 5.0 63.0 9.1 116.1
Total (NER+Sikkim) 1157.1 388.0 771.5 147.7 1307.2 56.0 2520.3

ACTUAL POWER SUPPLY POSITION AS ON 31.12.2006

The State-wise actual power supply position as on 31.12.2006 is given in table 6.5
below:

Table-6.5
Power Supply Position as on 31.12.2006

State Peak Energy


Shortage / Surplus Shortage / Surplus
(MW) (%) (MU) (%)
Assam -83 -10.8 -232 -7.1
Arunachal -1.0 -1.3 -7.0 -3.7
Pradesh
Meghalaya -145 -42.3 -215 -20.4
Tripura -27.0 -16.0 -58 -9.1
Manipur -5.0 -4.7 -16 -4.4
Nagaland 0.0 0.00 -10 -3.8
Mizoram -2.0 -2.9 -8 -4.7
Total(NER) -241 -17.1 -546 -9.2
Sikkim 0.0 0.00 -3 -1.9

Page 3 of Chapter 6
Development of Power Sector in NER Working Group on Power for 11th Plan

6.3 REASONS FOR SLOW PACE OF PROJECT EXECUTION

Overall development of N.E region has been very slow. The basic infrastructure is
inadequate and this is one of the reasons for development of various industries as
well as power projects in this region. The sub-group deliberated on the reasons for
the slow pace of power project execution, major ones is as follows:

• Difficulties faced in obtaining Environment & forest clearance, land


acquisition, R&R issues.
• Hydro electric project sites are inaccessible and have very difficult approach/
maintenance of access roads.
• Lack of Infrastructural facility
• Inter State Aspects
• Geological surprises
• Inadequate Survey & Investigation
• Law and Order problems
• Shortage of Funds
• Inadequate organisational set in state sector for implementation of projects
• Decision of Arunachal Pradesh regarding type of Hydro schemes.

6.4 POWER DEMAND & SUPPLY ANALYSIS OF THE REGION

An analysis has been carried out to assess the gap between power demand and
supply position of the region. Data of the hourly generation and demand met has
been examined and it is observed that there is shortage of power even during off
peak hours of the winter season. It is estimated that by the year 2011-12(at the end
of 11th plan) the demand of the North Eastern Region will be of the order of 2800
MW. To meet the peak shortages and even off-peak shortages during the winter
season when the hydro availability is low, it is essential that NER should have base
load generation capacity or alternatively allocation may be made from central thermal
stations of the Eastern Region

6.5 GENERATING CAPACITY ADDITION PROGRAMME IN NORTH


EASTERN REGION/ SIKKIM DURING 11TH PLAN

Tentative capacity addition programme of 5615MW has been envisaged in North


Eastern Region (including Sikkim) for the 11th Plan. This comprises of 4055 MW
hydro and 1560 MW of thermal power.

Page 4 of Chapter 6
Development of Power Sector in NER Working Group on Power for 11th Plan

Table-6.6
(Capacity in MW)
N E Region 11th Plan Total
Hydro Thermal
Coal Gas Diesel Total
Assam 750 37 - 787 787
Manipur - - - - -
Meghalaya 124 - - - - 124
Mizoram - - - - -
Ar. Pradesh 2600 - - - - 2600
Nagaland - 23 - 23 23
Tripura - 750 - 750 (*)750
Total(NER) 2724 750 810 - 1560 4284
Sikkim 1331 - - - - 1331
Total(NER+ 4055 750 810 - 1560 5615
Sikkim)

The State-wise/Project-wise details are given at Annexure- 6.1


(*) It is learnt that power from this station will be sold to PTC

6.6 DEVELOPMENT OF TRANSMISSION SYSTEM IN NORTH EASTERN


REGION

6.6.1 Power System in NER

The North Eastern Regional Power Grid comprises of transmission network of seven
States of Arunachal Pradesh, Assam, Manipur, Meghalaya, Mizoram, Nagaland and
Tripura with Central Sector system superimposed on it. Due to low magnitude of
demand levels in most of the states, the growth and development of state
transmission systems has been primarily at 132kV and 66kV levels. Due to its
geographical location, Power System of Assam wheels power to other NER states
through many of its transmission elements. The inter-state lines wheeling through
Assam grid have been constructed as centrally sponsored schemes. Till regional grid
of North-eastern region is developed to provide full connectivity to all the states, the
wheeling of power to other states through Assam grid would continue.

6.6.2 Meeting the Power Supply Requirement of NER

The power supply situation in NER remains better during monsoon period when
availability from hydro-generating stations are good. During non-monsoon period and
particularly during winters, shortage, both in terms of MW and MWh, are much higher
due to low generation at hydro stations in the region.
To meet the requirement of power in NER, it would be necessary that sufficient
power from base load thermal stations located in Easter-region is allocated to the
states of NER and major part of power from higher sized hydro station in NER such
as Subansiri Lower (2000MW) and Kameng(600MW), is allocated to states outside
NER. This would help the states of NER in two ways. While the additional allocation

Page 5 of Chapter 6
Development of Power Sector in NER Working Group on Power for 11th Plan

from thermal projects located outside NER to the states of NER would help in
meeting their demand during low hydro generation period of winter months, allocation
from hydro projects in NER to outside NER would help to regulate the surpluses
during monsoon period when there is over-all higher availability in all the regions.
Allocation from hydro projects in NER to states in NR/WR would also facilitate the
development of the NER – NR/WR inter-connecting HVDC transmission system.

While considering allocation of power from generation projects in NER to outside


NER and from thermal generation projects outside to NER to the states of NER, it
needs to kept in view that the benefit of hydro development in NER is adequately
passed on to the states of NER by leaving out sufficient surpluses with the NER
states which they could trade profitably in the opened-up bulk power market. This
would help in improving the commercial health of the NER states. However, if the
surpluses are higher, and that too in monsoon period, trading of such power may not
be profitable. Therefore, an optimum power allocation strategy needs to be adopted.

6.6.3 Regional Transmission System in NER

Till 1984, the transmission network in the region was essentially comprised of 132kV
and underlying networks, both in State as well as Central sector. Since then, with the
planning of various hydro projects in the region, 220 kV transmission system was first
commissioned in 1984 under Central sector for evacuation of power from Kopili
Stage-I HEP (200MW). Subsequently, 400 kV Kathalguri-Mariani -Misa D/C line
(operated at 220kV) and Misa-Balipara-Bongaigaon 400 kV D/C line as part of
evacuation for Kathalguuri GBPP in Central sector, and Bongaigaon-Malda 400kV
D/C line as an inter-regional line between ER and NER, were developed by 2000.
This provided 400kV interconnectivity with the Eastern region. Subsequently,
Ranganadi-Balipara 400kV D/C line was commissioned along with Ranganadi-I-HEP.
Also, the Bongaigaon-Malda 400kV D/C line has been LILOed at Siliguri (one ckt in
July 2002, other ckt in March 2005) and Purnea (one ckt in November 2003, other ckt
in September 2005) in Eastern region.. The North-eastern regional grid has also
been developed with 220kV and 132kV lines established in Central sector as
associated transmission system for various generation projects viz. Loktak HEP,
Agartala GBPP, Kopili HEP Extn, etc.

Per unit cost of regional transmission in NER has been much higher as compared to
other parts of the country. Five factors responsible for this are - (1) the cost of
building transmission lines in NER is much higher due to uneven terrain and area
specific factors; (2) the PLF of hydro stations, being inherently low, makes per unit
cost of transmission higher; (3) higher cost in NER due to law and order problem; (4)
due to delay in completion of Ranganadi-I HEP, while the 400kV Misa-Balipara-
Bangaigaon lines were completed, the resulting under utilization of transmission
system leading to higher per unit charges; and (5) 50% transmission charges for
Bongaigaon-Malda 400kV D/C line on account of NER while Siliguri-Purnea-Malda
section of the link utilized as part of eastern grid. It may be noted that factor (4) has
since been addressed and (5) can also be addressed by appropriate revision of
transmission tariff. Government and public efforts may also fructify to address the
factor (3). However, factor (1) and (2) are inherent and would continue to push up the
transmission tariff in NER. To the issue of higher transmission tariff in NER, Zonal
Matrix Transmission Tariff method for location, distance and flow direction related

Page 6 of Chapter 6
Development of Power Sector in NER Working Group on Power for 11th Plan

allocation of National pooled transmission charges amongst the beneficiaries could


be adopted as an effective solution.

CERC has capped the regional transmission charges in NER at 35 paise/kWh. As a


result, PGCIL is not recovering its full transmission charges. Due to non-recovery of
its full transmission charges, PGCIL has not been making further investment in the
NER transmission system and system strengthening in the regional/inter-state
transmission system had been suffering. The issue needs to be addressed urgently.

With intervention from MOP and CEA, urgent strengthening requirements in the
regional system have been identified and taken-up for implementation by
POWERGRID under scheme titled ‘NER System Strengthening Scheme – I’. within
existing transmission tariff ceiling of 35 paise/kWh. Works covered under this
schemes are:

NER System Strengthening Schemes – I

(i) 132 kV Kopili HEP – Khandong HEP 2nd circuit


(ii) Extension of Kopili S/S by 1x160 MVA, 220/132 kV transformer (3x53.3
MVA single phase units).
(iii) LILO of Dimapur (Nagaland) – Kohima 132 kV S/C at Dimapur (PG)
(iv) Augmentation of Dimapur (PG) S/S by 1x100 MVA, 220/132 kV
transformer.

6.6.4 Power Evacuation from North East

Development of generation projects in NER envisaged during the XI plan period


would add hydro as well as gas based generation capacity in NER. Generation from
this capacity would be partly utilized locally to the extent of meeting the increasing
load demands with development in the area and the balance, which would be the
major part of the additional generation capacity, would need to be evacuated outside
the region.
For meeting power requirements for the states of NER, the component of allocation
from these projects within NER would be utilized locally for which adequate
transmission system with in NER – both inter-state as well as intra-state – would be
required.

6.6.5 Transmission System Under State Sector

Inadequate development of sub-transmission and distribution system facilities in the


States of NER has been adversely affecting the reliability of power supply to the
consumers and also hampering the load growth in the region. The transmission, sub-
transmission and distribution systems of states require major strengthening/up-
gradation. Transmission lines that are under outage require speedy restoration for
bringing them into operation so that the states could avail their central sector shares
as well as utilize their own generation without any constraint.

Inadequacies in the transmission and distribution system had been on account of


slow implementation of schemes due to various factors such as time consumed in
E&F clearances, land acquisition, RoW constraints, fund limitation, organizational

Page 7 of Chapter 6
Development of Power Sector in NER Working Group on Power for 11th Plan

difficulties of state utilities, lack of vendor response due to locational factors, law and
order, terrain specific difficulties, etc. Due to limited funding capabilities of state
utilities, most of the required transmission projects are generally funded by NEC or by
NLCPR under DONER and investment/funding approval of scheme so funded also
takes additional time. All these issues need to be addressed to achieve the
accelerated demand growth in NER.

6.7 EVACUATION OF POWER FROM MAJOR GENERATION PROJECTS IN


THE NORTH-EASTERN REGION ALONG WITH POWER FROM PROJECTS
COMING UP IN SIKKIM AND BHUTAN DURING THE 11TH PLAN AND
EARLY 12TH PLAN PERIOD

Generation projects of 10000 MW have been envisaged during the 11th Plan and
early 12th Plan in the NER, Sikkim and Bhutan. The projects are Tripura Gas (750
MW), Bongaigaon Thermal (750 MW), Kameng HEP (600 MW), Subansiri Lower
HEP (2000 MW), Siang Middle HEP (1000 MW), Tipaimukh HEP (1500 MW),
Teesta- I, II, III, IV & VI HEPs in Sikkim (2700 MW), Phunatsangchu-I & II and
Mangdechu HEPs in Bhutan (2600MW). The generation from these projects would
be utilized in the NER, Sikkim and Bhutan, only to the extent of meeting the
increasing load demands in the area. However, even with accelerated growth in local
demand, substantial power from these projects would need to be exported to the
power deficit regions that is the Northern Region and the Western Region. In order to
have an optimum system and addressing the transmission corridor constraints in the
chicken neck area (the ‘chicken-neck’ refers to the area between Siliguri and Bidhan
Nagar in West Bengal), a comprehensive transmission system has been evolved.

The requirement of power evacuation through the chicken neck has been estimated
corresponding to the capacity of hydro projects which may be feasible to develop say
in the next 20-25 years. This generation is estimated to be about 35000 MW in NER,
about 8000 MW in Sikkim and about 15000 MW in Bhutan. Taking local development
at accelerated pace resulting in demand within the NER, Sikkim and Bhutan to be in
the range of 10000 – 12000 MW (presently it is about 1500 MW), the transmission
requirement through the chicken neck works out to be of the order of 45000 MW.
With 800kV HVDC, each bi-pole line of 6000 MW capacity could be planned. The
400kV AC D/C lines with quad conductor in the hybrid system would be of 2000 MW
transmission capacity. Multi-circuit of higher transmission capacity would also be
considered in chicken-neck area. The total requirement including additional circuits
for meeting the contingencies and reliability needs, would work out to 7 or 8 numbers
of HVDC bi-pole lines and 4 or 5 numbers of 400kV double circuit lines – a total of 12
numbers of high capacity transmission corridors passing through the chicken neck.
For this, RoW requirement would be about 800 m and considering minimum distance
between adjacent towers to be such that fall of any tower does not affect the
adjoining line, a width of about 1.5 km would be needed.

The option of 765kV transmission system has not found favor that besides a wider
RoW, we have to take into account nature of hydro generation. While the system
would need to be planned for full generation capacity, in winter months, when the
generation would be much less and restricted to just peak hours, the lines can’t be
kept energized due to reactive power management and resulting high voltage
problem. This would require frequent switching of the lines resulting in loss of

Page 8 of Chapter 6
Development of Power Sector in NER Working Group on Power for 11th Plan

reliability and also reduced life of equipment. Therefore 765kV bulk transmission
would not be recommended choice in this case.

The option of hybrid network of HVDC, and high capacity 400kV line has been found
to be most suitable from cost, corridor, operational and phased development
consideration. As the transmission distance from NER upto NR/WR is quite long –
2000 – 2500 kms, the requirement of keeping losses within reasonable and cost
effective limits, suggests strongly in favor of adopting as high a HVDC transmission
voltage as possible. At present the HVDC voltage for bi-pole transmission in India is
500kV. The highest HVDC system in world is at 600kV at Itaipu, Brazil, which is in
operation since 1987. The next higher voltage of 800kV HVDC is under final stages
of development.

The first 800kV HVDC bi-pole line has been planned from a pooling substation at
Biswanath Chariyali in North-eastern Region to Agra in Northern region. This is being
programmed for commissioning matching with Subansiri Lower HEP in 2011-12. The
transmission line would be for 6000 MW capacity and HVDC terminal capacity would
be 3000 MW between Biswanath Chariyali and Agra and, for transmission of power
from hydro projects at Sikkim and Bhutan pooled at Siliguri, another 3000 MW
terminal modules would be added between Siliguri and Agra. It is envisaged to take-
up the proposed 800kV, 6000MW HVDC bi-pole line from Biswanath Chariyali to
Agra under a scheme titled ”Inter-regional Transmission system for power export
from NER to NR/WR”. This would the first scheme of its kind in the world and this
would be a flagship endeavor towards a quantum leap in the Indian Power System.

To supply the power from the various generation schemes catering to increasing
demand within the North-eastern Region, system strengthening within the NER would
also to be needed. The requirement of the system strengthening would depend on
trend of demand growth in the states. The strengthening network in NER would also
provide local anchoring of the network which would improve the reliability of the
National Grid. Provision for system strengthening within NER would be kept in each
of the generation related transmission schemes.

6.8 SPECIAL ATTENTION FOR DISTRIBUTION IN NE REGION

The North East region is lagging behind in the development of the power sector
compared to other regions. The region offers immense potential for the development
of the electricity sector due to the huge hydro potential in the North East. The
investments in and growth of transmission, sub-transmission and distribution systems
have not matched the increase in generation capacity. As a result, there are
constraints in electricity evacuation from generation stations. CEA has estimated that
the share of the North East region is only 2.5%.

In the consumer profile, domestic consumers accounted for 75% of the total
consumers followed by commercial consumers which accounted for 11% of the total.
Agricultural consumers accounted for 10% of the total while industrial consumers
were 2.5%. As much as 40% of the Electricity consumers reside in Southern India,
followed by Western India which accounts for 27% of the electricity consumers.
Northern India accounts for 23% of the total electricity consumers while the East &

Page 9 of Chapter 6
Development of Power Sector in NER Working Group on Power for 11th Plan

North East together account for only 10% of the consumers. North East accounts for
only 1.6% of all consumers.

The above figures reflect the position of North East in the power sector development
in the country. This regional imbalance needs to be corrected. In APDRP and
RGGVY this region should get priority. In all the backward and north-eastern States
the programme of electricity distribution projects need to be supported with low cost
funds along with substantial portion of subsidy or grants.
It is also felt that performing Middle/Senior level managerial personnel from the most
progressive utilities may be deputed to utilities in North-eastern states to ensure
quick deployment of initiatives already deployed in the progressive states. Also,
personnel from Utilities in North-eastern states should be deputed in other utilities. All
such deputation should range from a period of at least 6 months to 3 years.

In all the backward and north-eastern States the programme of electricity distribution
projects need to be supported with low cost funds along with substantial portion of
subsidy or grants. Rural Infrastructure Development Funds (RIDF) available with
NABARD should be utilized for the development of electricity distribution in the North-
eastern and other backward regions of the country. For the System Improvement
Schemes in these regions RIDF funds may be allowed to be utilized for making
available cheaper credit for an accelerated development of these regions.

6.9 FUND REQUIREMENT

The requirement of funds during XI Plan for generation projects has been estimated
as about Rs. 15,375 crore. In addition, the matching Transmission and Distribution
shall also need similar quantum of funds and thus overall requirement is estimated to
be about Rs. 30,750 crore.

6.10 POLICY INITIATIVES AND RECOMMENDATIONS

Following recommendations are made to overcome major problems being faced in


project implementation in the N.E. Region and overcome the slow pace of
development.

ƒ The Survey & Investigation works, preparation of DPR, clearance from


various organizations including MoEF have to be taken up and a time bound
programme for clearance of hydro projects from various agencies including
MoEF has to be formulated.

ƒ A comprehensive plan for adequate road network be formulated taking into


consideration various development projects including remote located hydro
power station sites.

ƒ Non availability of construction materials like cement steel etc and long
procurement time makes the Hydro Projects costly and unviable. Setting up
of Industries for construction material including Cement Industry may be
encouraged in the North Eastern Region.

Page 10 of Chapter 6
Development of Power Sector in NER Working Group on Power for 11th Plan

ƒ Availability of power in NE Region reduces during winter season due to


reduction in generation from hydro projects. Gap between demand and
supply is of the order of 400-500 MW. Therefore, NE Region has shortage of
power during winters even during off-peak hours. Therefore, NE Region
should have base load generation capacity i.e. thermal generation or
allocation from central sector thermal stations of Eastern Region.

ƒ For achieving accelerated load growth in NER, efforts are needed on all
fronts. Specific efforts are needed in development in transmission at the
regional level as well in the transmission, sub-transmission and distribution
system at the state level.

ƒ To supply the power from the various generation schemes catering to


increasing demand within the North-eastern Region, system strengthening
within the NER would be needed. The required transmission system in NER
needs to be developed along with the power evacuation system.

ƒ Hydro power development in NER would requirement of power to other


regions through the chicken neck. The total requirement would be 7 or 8
numbers of HVDC bi-pole lines and 4 or 5 numbers of 400kV double circuit
lines – a total of 12 numbers of high capacity transmission corridors for
which a total width of about 1.5 km in two or three corridors would be
needed. The total right of way in chicken neck area needs to be reserved on
priority.

ƒ Establishment of manufacturing units for the electro-mechanical equipments


in the region. This will help the region in establishment of a heavy industry,
which will also generate considerable employment.

ƒ ADB or any other suitable developmental agency to be engaged for


comprehensive development of power projects in the NE Region.

ƒ Extension of Rural Infrastructure Development Funds (RIDF) available with


NABARD should be made available for the development of electricity
distribution in the North-eastern and other backward regions of the country in
order to get cheaper credit for an accelerated development of these regions.

ƒ A national level training center for Distribution should be created in at least


one of the North-eastern states by a Central Government Institution/body.

**********

Page 11 of Chapter 6
Human Resource Development Working Group on Power for 11th Plan

Chapter - 7

HUMAN RESOURCE DEVELOPMENT

7.0 BACK GROUND

Human Resource Development and capacity building, in the present power scenario,
demands a very comprehensive and pragmatic approach to attract, utilize, develop
and conserve valuable human resources. Training, re-training and career prospects
are some of the important elements of human resources development. The reforms
in the power sector have led to change in the role of Senior Engineers from a purely
Government controlled technical management to business management in a
corporatised framework.

Technically trained manpower comprising of skilled engineers, supervisors, artisans,


and managers etc. is required in every sphere of the power supply industry. Growing
concern over environmental degradation and depletion of the conventional energy
sources has made the task of electricity generation even more challenging and
therefore quality standard of the manpower is becoming increasingly essential. The
technical knowledge acquired from engineering colleges, polytechnics, industrial
training institutes and other technical institutions provides the basic foundation, but
the same needs to be supplemented with applied engineering skills in the various
spheres i.e. power generation, its transmission and distribution aspects. All these
skills are to be regularly updated to cope with the rapidly advancing technologies and
very often the speed of obsolesce overtakes the rate of acquisition of particular skill
and knowledge. It has been noticed that due to the introduction of more sophisticated
technology and automation, the Man/MW ratio is declining over the years. The
Man/MW ratio in thermal sector has reduced from 4.71 in 6th Plan to about 1.78 at the
end of 9th Plan; it is projected to touch 1.44 towards the end of 10th Plan and is
further expected to go down during the subsequent plans. The same trend is
observed in the Hydro Power Sector also, where the Man/MW ratio of 6.04 in the
Sixth Plan has come down to 2.2 at the end of Ninth Plan; it is expected to go down
further to about 1.95 towards the end of 10th Plan and even reduce in the subsequent
Plans. The overall Man/MW ratio which was 9.42 at the end of 9th Plan is expected
to go down to 7.00 at the end of 10th Plan and 5.82 at the end of 11th Plan. This
indicates the increasing importance of each individual, the man behind the machine.

The HRD/Training needs of Technical, Non-Technical and Supporting Staff should be


addressed keeping in view the National Training Policy for the Power Sector.

In this Chapter, the existing manpower and training facilities in the Power Sector
have been reviewed. A broad assessment has been made of the manpower
requirements for construction, commissioning, O&M of Generation, Transmission,
Distribution system during 11th & 12th Plans, taking into account present staffing
pattern, requirements arising out of proposed capacity and network expansions, staff
out turns on account of retirements and expected changes in technology etc. A

Page 1 of Chapter 7
Human Resource Development Working Group on Power for 11th Plan

review and assessment of training arrangements required have been made as well
as measures for training of staff in various categories. have been suggested. The
financial requirement of manpower planning and training arrangements during the
11th & 12th Plans have also been worked out.

7.1 ELEMENTS OF HRD PLANNING

Comprehensive HRD planning involves the following elements:

Organization:
Organizational structure, position descriptions, responsibility and authority, delegation
etc.

Skills and Trades:


Qualitative and quantitative assessment of skills and trades required at various points
of time in future.

Productivity and Performance:


Utilization, control, performance appraisal, productivity development etc.

Working Conditions and Facilities:


Working environment, safety, health, fatigue, rest and facilities to workers, both inside
and outside the factory.

Salary and Wages:


Working classification, wage structure, salary, administration, service conditions and
fringe benefits.

Recruitment:
Recruitment, training, placement, phasing of recruitment and blending of
requirements at different stages of construction, operation and growth.

Motivation:
Personnel development, promotion incentive, morale, satisfaction and attitudes.

Industrial Relations:
Trade Unionism, discipline, social, economic and political environment, group
dynamics etc.

7.2 ASSESSMENT OF MANPOWER

7.2.1 Capacity Addition – Plan-wise

Assessment of manpower during the plan periods is based on capacity addition


during the respective plans and the norms for manpower. Besides this, 20%
reduction of personnel during the plan period due to retirement, death, change of
profession etc. and assumed recouping @ 7.5% during the plan due to wastage,
decommissioning etc is also made.

Details of capacity addition during various Plans are furnished below:

Page 2 of Chapter 7
Human Resource Development Working Group on Power for 11th Plan

Table 1

Sector Capacity in MW
End of Addition End of Additio End of Addition End of
9th Plan in 10th 10th n in 11th 11th Plan in 12th 12th Plan
Plan Plan Plan Plan
Thermal 74,429 20,387 94,816 50,124 1,44,940 40,200 185,140
Hydro 26,269 8,854 35,123 15,585 50,708 30,000 80,708
Nuclear 2,720 1,400 4,120 3,160 7,280 12,000 19,280
Addition 19119 30,641 * 68,869 82,200
during
the Plan
Grand 1,05,046 1,35,68 2,04,556 2,86,756
Total (1628 7
Wind )

*- This includes 2578 MW on best efforts basis and further additional capacity of
2445 MW to require extra efforts. However in current scenario this capacity would slip
to 11th Plan and would therefore not change the capacity at end of 11th Plan. As per
latest indication, a capacity of 5,727 MW may slip to 11th Plan because of various
reasons including delay in supply and execution by BHEL

7.2.2 Growth of Manpower – Present Trend

According to the National Electricity Plan, the total Manpower (Technical and Non-
Technical) available at the beginning of 9th Plan i.e. 1-4-1997 was of the order of
1,061.7 thousands. During the 9th Plan a capacity addition of 19,119 MW was
achieved for which an additional manpower is estimated to be 60.9 thousands. The
manpower available at the end of the 9th Plan i.e. 31-3-2002 was of the order of
989.9 thousands. This takes into account 20% reduction of personnel during the plan
period due to retirement, death, change of profession etc. and assumed recouping @
7.5% during the plan due to wastage & decommissioning etc.

7.2.3 Manpower Assessment for 10th Plan

The actual capacity addition expected during the 10th Plan is of the order of 30,641
MW*. The total manpower calculated at the end of 10th Plan is estimated to be 9.50
lakhs for the total installed capacity of 1,35,687 MW. Details of calculations and
assumptions are furnished in Tables 2 to 8.

7.2.4 Manpower Assessment for 11th Plan

Considering the proposed capacity addition of 68,869 MW during 11th Plan (Table
1), the additional manpower requirement will be of the order of 3.44 lakhs out of
which 2.62 lakhs will be technical and 0.81 lakhs Non-Technical. The total manpower
at the end of 11th Plan has been estimated at 11.76 lakhs for the total installed
capacity of 2,04,556 MW. Details of calculations and assumptions are furnished in
Tables 9 to 16.

Page 3 of Chapter 7
Human Resource Development Working Group on Power for 11th Plan

7.2.5 Manpower Assessment for 12th Plan

Considering the proposed capacity addition of 82,200 MW during 12th Plan


(Table 1), the additional manpower requirement will be the order of 3.27 lakhs out of
which 2.52 lakhs will be technical and 0.75 Non-Technical. The total manpower at the
end of XII Plan has been estimated as 13.22 lakhs. Details of calculations and
assumptions are furnished in Tables 17 to 22.
Table 2

Estimated manpower employees in power supply industry


(utilities) as on 1.4.2002 (beginning of 10th plan)

(Figures in Thousands)
S.No. Formation Technical Non- Total
Technical
1. Thermal 98.2 34.4 132.6
Generation*
2. Hydro Generation 38.3 19.5 57.8
3. Nuclear 7.3 3.5 10.8
4. Power System*
Transmission 30.01 9.42 39.43
Distribution 570.28 178.98 749.26
Total 744.1 245.8 989.9

These estimates do not include persons employed in civil construction works of


power generation projects.

*This includes steam, Gas and Diesel plants.


**Personnel working in Transmission are considered 5% of the total working in
Transmission and Distribution together.

Table 3
th
Manpower available for the 10 Plan after 20% reduction (due to retirement, death,
change of profession etc. @ 4% per year)

(Figures in Thousands)
Sl.No. Formation Technical Non- Total
Technical
1. Thermal 78.56 27.52 106.08
Generation
2. Hydro Generation 30.64 15.6 46.24
3. Nuclear 5.84 2.8 8.64
4. Power System
Transmission 24.01 7.54 31.55
Distribution 456.22 143.18 599.40
Total 595.28 196.64 791.92

Page 4 of Chapter 7
Human Resource Development Working Group on Power for 11th Plan

Table 4

7.5% Manpower recouped during 10th Plan @ 1.5% per year


(Figures in Thousands)
Sl.No. Formation Technical Non- Total
Technical
1. Thermal Generation 7.3 2.58 9.88
2. Hydro Generation 2.87 1.46 4.33
3. Nuclear 0.54 0.26 0.8
4. Power System
Transmission 2.25 0.71 2.96
Distribution 42.77 13.42 56.19
Total 55.73 18.43 74.16

Against the wastage of 4%, the intake will be of the order of 2% in view of
improvement in quality, technology advancement and redundancy available in
technical manpower at semi/unskilled level. It is also assumed that 0.5% of the total
capacity is decommissioned annually and the manpower available from these units
shall be utilized at other units thus the effective recouping of 1.5% every year.

Table 5

Manpower available during the 10th Plan after considering retirement of 20% and
7.5% recouping etc.

(Figures in Thousands)
Sl.No. Formation Technical Non- Total
Technical
1. Thermal Generation 85.9 30.1 116.0
2. Hydro Generation 33.5 17.1 50.6
3. Nuclear 6.4 3.1 9.5
4. Power System
26.26 8.24 34.50
Transmission 49.90 15.66 65.56
Distribution* - Hilly 449.14 140.94 590.08
10% 525.3 164.9 690.2
- Plains
90%
Sub-
Total
Total 651.1 215.1 866.3
*In Distribution 10% assumed for Hilly Terrains and 90% for Plains

Table 6

Page 5 of Chapter 7
Human Resource Development Working Group on Power for 11th Plan

Norms for Manpower (for 10th Plan) Central & State Sectors per MW

(Figures in Thousands)
Sl.No. Formation Technical Non-Technical
Central State Central State
1. Thermal (Total)
500 MW Unit 0.60 0.82 0.18 0.3
< 500 MW Unit 0.7 1.15 0.21 0.61
Gas/Liquid Fuel 0.35 0.36 0.11 0.17
2. Hydro 1.66 1.53 0.50 0.26
3. Nuclear 1.35 - 0.58 -
4. Power System - 0.30 -
1.12

For Central & Private Sectors as per NTPC & NHPC


For State Sector as per National Electricity Plan
For T&D for 10th Plan norms as per National Electricity Plan

Table 7

Additional Manpower required due to capacity addition of 30,641 MW in 10th Plan,


T&D Line length of 8,26,863 ckt kms & 20 Crore consumers for Distribution

(Figures in Thousands)
Sl. Formation Technical Non- Total
No. Technical
Centr State Centr State Central State
al al
1. Thermal Generation
500 MW Unit 4.20 0.41 1.26 0.15 5.46 0.56
Below 500 MW Unit 3.36 5.38 1.01 2.85 4.37 8.23
Gas/Liquid Fuel 0.74 0.46 0.23 0.22 0.97 0.68
2. Hydro Generation 8.62 5.59 2.59 0.95 11.21 6.54
3. Nuclear 1.89 - 0.81 - 2.70 -
4. Power System
Transmission(41443 1.72 0.46 2.18
ckm)* 3.26 - 0.87 - 4.13 -
Distribution - Hilly 29.34 7.86 37.12
- Plains 34.32 9.19 43.51
Sub-Total
Total 53.13 11.84 15.09 4.17 68.22 16.01
84.23
Grand Total
*Combined Lines of HV, EHV & UHV

Page 6 of Chapter 7
Human Resource Development Working Group on Power for 11th Plan

Table 8

Total Manpower available at the end of 10th Plan i.e. on 1.4.2007

(Figures in Thousands)
Sl.No. Formation Technical Non- Total
Technical
1. Thermal Generation 100.45 35.82 136.27
2. Hydro Generation 47.71 20.64 68.35
3. Nuclear 8.29 3.91 12.20
4. Power System
Transmission(41,443 ckm) 27.98 8.70 36.68
Distribution - Hilly 53.16 16.53 69.69
- Plains 478.48 148.80 627.28
Sub-Total 559.62 174.03 733.65

Total 716.07 234.40 950.47

Table 9

Manpower available during the 11th Plan after 20% reduction (due to retirement,
death, change of profession etc. @ 4% per year)

(Figures in Thousands)
Sl.No. Formation Technical Non- Total
Technical
1. Thermal Generation 80.36 28.66 109.02
2. Hydro Generation 38.17 16.51 54.68
3. Nuclear 6.63 3.13 9.76
4. Power System
Transmission 22.38 6.96 29.34
Distribution - Hilly 42.53 13.22 55.75
- Plains 382.78 119.04 501.82
Sub-Total 447.69 139.22 586.91
Total 572.85 187.52 760.37

Page 7 of Chapter 7
Human Resource Development Working Group on Power for 11th Plan

Table 10

7.5% Manpower recouped during 11th Plan @ 1.5% per year


(Figures in Thousands)
Sl.No. Formation Technical Non- Total
Technical
1. Thermal Generation 7.53 2.69 10.22
2. Hydro Generation 3.58 1.55 5.13
3. Nuclear 0.62 0.29 0.91
4. Power System
Transmission 2.09 0.65 2.74
Distribution - 3.98 1.24 5.22
Hilly 35.88 11.16 47.04
- 41.95 13.05 55.00
Plains
Sub-
Total
Total 53.68 17.58 71.26

Table 11

Manpower available during the 11th Plan after considering retirement of 20% and
7.5% recouping etc.
(Figures in Thousands)
Sl.No. Formation Technical Non- Total
Technical
1. Thermal Generation 87.89 31.35 119.24

2. Hydro Generation 41.75 18.06 59.81


3. Nuclear 7.25 3.42 10.67
4. Power System

Transmission 24.47 7.61 32.08


Distribution - Hilly 46.51 14.46 60.97
- Plains 418.66 130.20 548.86
Sub- 489.64 152.27 641.91
Total
Total 626.53 205.10 831.63

Page 8 of Chapter 7
Human Resource Development Working Group on Power for 11th Plan

Table 12

Norms for Manpower (for 11th Plan)


(10% reduction due to Technological Achievements)

(Figures in Thousands)
Sl. Technical Non-Technical
No.
Central State Central State
1. Thermal (Total)
500 MW Unit & above 0.54 0.74 0.16 0.27
Below 500 MW Unit 0.63 1.03 0.19 0.55
Gas/Liquid Fuel 0.32 0.32 0.10 0.15
2. Hydro 1.49 1.38 0.45 0.23
3. Nuclear 1.22 - 0.52 -
4. Power System
Transmission 1 Employee 30% of the -
for 3.83 ckm - Technical
Manpower
Distribution - Hilly 2.00 per 1000
Consumers -do-
- Plains 1.00 per 1000
Consumers

Table 13

Additional Manpower required due to envisaged Capacity Addition of 68,869 MW in


11th Plan, HV, EHV, UHV Transmission Line lengths of about 1,00,000 Ct.kms and
an estimated 16 crore Distribution Consumers for Central and Private Sectors

(Figures in Thousands)
Sl.No. Capacity (MW) Technical Non-Technical Total
1. Thermal
500 MW Unit & 34,520 10.75 3.18 13.93
above
Below 500 MW 13,490 5.37 1.62 6.99
Unit
Gas/Liquid Fuel 2,114 0.48 0.15 0.63
2. Hydro 15,585 21.68 6.54 28.22

3. Nuclear 3160 3.85 1.64 5.49

4. Power System 1 lakh Ckms & 26.11 7.83 33.94


Transmission 16 crore
Distribution consumers 32.00 9.6 41.60
Hilly Plains considered 144.00 43.2 187.20
Sub-Total 202.11 60.63 262.74
Total 244.24 73.76 318.00

Page 9 of Chapter 7
Human Resource Development Working Group on Power for 11th Plan

In Central & Private Sectors capacity addition through 500 MW and above is
estimated at about 70% of total Thermal of Central & Private

Table 14

Manpower required for State Sector


(Figures in Thousands)
Sl.No. Capacity Technical Non- Total
(MW) Technical
1. Thermal (Total)
> 500 MW 13300 3.45 1.25 4.70
Unit
< 500 MW Unit 6440 11.20 5.98 17.18
Gas/Liquid Fuel 612 0.19 0.09 0.28
Hydro 2637 3.64 0.60 4.24

In the State Sector Capacity Additions through 500 MW and above is estimated at
about 30% of total Thermal in State Sector.

Table 15

Additional Manpower required due to Envisaged Capacity Addition of 68,869 MW in


11th Plan and HV, EHV & UHV Transmission Line Lengths of about 1,00,000 Ct.kms
and an estimated 16 crores Distribution Consumers.
(Figures in Thousands)
Sl.No. Technical Non-Technical Total
Central State Central State
1. Thermal Generation
> 500 MW Unit 10.75 3.45 3.18 1.25 18.63
< 500 MW Unit 5.37 11.20 1.62 5.98 24.17
Gas/Liquid Fuel 0.48 0.19 0.15 0.09 0.91
2. Hydro 21.68 3.64 6.54 0.60 32.46
3. Nuclear 3.85 - 1.64 - 5.49
4. Power System
Transmission 26.11 - 7.83 - 33.94
Distribution – Hilly 32.00 9.60 41.60
- Plains 144.00 43.20 187.20
202.11 60.63 262.74
Total 244.24 18.48 73.76 7.92 344.40

Page 10 of Chapter 7
Human Resource Development Working Group on Power for 11th Plan

Table 16

Total Manpower required by the end of 11th Plan (Beginning of 12th Plan) i.e., on 1-4-
2012

(Figures in Thousands)
Sl.No. Technical Non- Total
Technical
1. Thermal Generation 119.33 43.62 162.85
2. Hydro Generation 67.07 25.20 92.27
3. Nuclear 11.10 5.06 16.16
4. Power System

Transmission 50.58 15.44 66.02


Distribution - Hilly 78.51 24.06 102.57
- Plains 562.66 173.40 736.06
Sub-Total 691.75 212.90 904.65
Total 889.25 286.78 1176.03

Table 17

Manpower available for the 12th Plan after 20% reduction (Due to retirement, death,
change of profession etc. @ 4% per year)
(Figures in Thousands)
Sl.No. Technical Non- Total
Technical
1. Thermal Generation 95.46 34.89 130.35

2. Hydro Generation 53.65 20.16 73.81

3. Nuclear 8.89 4.05 12.94

4. Power System

Transmission 40.46 12.35 52.81


Distribution - 62.81 19.25 82.06
Hilly 450.13 138.72 588.85
- 553.40 170.32 723.72
Plains
Sub-
Total
Total 711.40 229.42 940.82

Page 11 of Chapter 7
Human Resource Development Working Group on Power for 11th Plan

Table 18

7.5% Manpower required during 12th Plan due to recouping @ 1.5 per year

(Figures in Thousands)
Sl.No. Technical Non- Total
Technical
1. Thermal Generation 8.95 3.27 12.22
2. Hydro Generation 5.03 1.89 6.92
3. Nuclear 0.83 0.38 1.21
4. Power System
Transmission 3.79 1.16 4.95
Distribution - 5.89 1.80 7.69
Hilly 42.20 13.00 55.20
- 51.88 15.97 67.85
Plains
Sub-
Total
Total 66.69 21.50 88.19

Table 19

Manpower available for the 12th Plan after 20% retirement and 7.5%

(Figures in Thousands)
Sl.No. Technical Non- Total
Technical
1. Thermal Generation 104.41 38.16 142.57
2. Hydro Generation 58.68 22.05 80.73
3. Nuclear 9.72 4.43 14.15
4. Power System
Transmission 44.25 13.51 57.76
Distribution - 68.70 21.05 89.75
Hilly 492.33 151.72 644.05
- 605.28 186.29 791.56
Plains
Sub-
Total
Total 778.09 250.92 1029.01

Page 12 of Chapter 7
Human Resource Development Working Group on Power for 11th Plan

Table 20
Norms for 12th Plan

Sl.No. Technical Non-


Technical
1. Thermal (Total)
> 500 MW Unit 0.67 0.25
< 500 MW Unit 0.93 0.50
Gas/Liquid Fuel 0.29 0.14
2. Hydro 1.25 0.21
3. Nuclear 1.10 0.47
4. Power System 1 Employee for 3.83 ckm 30% of
2 Employees per 1000 the
Consumers in Hilly Terrain Technical
1 Employee per 1000 Manpower
Consumers in Plains

Norms for the 12th Plan have been chosen as per the practice in CPSUs

Table 21

Additional Manpower in the 12th Plan for the envisaged Capacity Addition of 82,200
MW, Transmission Ct. Kms of 63,000 and about 14 crore Distribution Consumers

(Figures in Thousands)
Sl.No. Technical Non- Total
Technical
Thermal Generation
1. Thermal 40,200 26.93 10.0 36.93
2. Hydro 30,000 37.5 6.3 43.8
3. Nuclear 12,000 13.2 5.64 18.84
4. Power System 148.37 45.06 193.43

Total 82,200 226.0 67.0 293.0

Page 13 of Chapter 7
Human Resource Development Working Group on Power for 11th Plan

Table 22
Manpower required at the end of 12th Plan (Table 19 + 21)

(Figures in Thousands)

Formation Technical Non- Total


Technical
1. Thermal Generation 131.34 48.16 179.5
2. Hydro Generation 96.18 28.35 124.53
3. Nuclear 22.92 10.07 32.99
4. Power System 753.65 231.35 985.0

Total 1004 318 1322

Based on the above estimation it is noted that the man/MW figure decreases as
illustrated below

Table 23

Man/MW Ratio during various Plan Periods

End of
Plan Power
Period Overall Thermal Hydro Nuclear System
9th 9.42 1.78 2.2 3.97 7.5
10th 7.00 1.44 1.95 2.96 5.41
11th 5.82 1.16 1.76 2.22 4.47
12th 4.93 0.97 1.52 1.77 3.77

7.3 TRAINING

Training is an organized activity for increasing the knowledge and skill of people for a
definitive purpose. It should involve systematic procedures for transferring technical
know-how to the employees for doing specific jobs with proficiency and to bring about
improvement in their performance. It plays an important role in human resource
development and is necessary, useful and productive for all categories of the
organisation. Trained personnel are like valuable assets of an organisation and are
responsible for the progress and stability of the organisation.

7.3.1 Training Strategy

The Working Group has come to the conclusion that the most important component
of the strategy should be “Training for All” irrespective of the level in the hierarchy. At
least one week of training in a year must be provided to every individual. Five days

Page 14 of Chapter 7
Human Resource Development Working Group on Power for 11th Plan

training per annum per technical person based on National Training Policy is being
implemented selectively at some utilities. This needs to be strictly implemented.

The Strategy includes training at following levels:

i) Induction level training for new recruits


ii) Refresher/advanced training for existing personnel
iii) Management training to the Senior Executives/Managers

i) Induction Level Training:

Induction level training is mandatory under Indian Electricity Rules for thermal and
hydro power stations. Training is to be imparted in recognized training institutes and
is of 52 weeks duration for Engineers, Operators, Technicians engaged in Thermal
Generation. The training is of 39 weeks for Engineers and 26 weeks for Supervisors
and Technicians working in Hydro Power Stations. In case of Power systems, the
training is of 52 weeks for graduate Engineers and 26 weeks each for Supervisors
and Technicians.

ii) Refresher/Advanced Training

The post employment training provides opportunities for personnel at different levels
of organizations to gain new skills and take up new responsibilities and keep pace
with advancement in technology. Also, specialized programs must be organized for
improving the workmen’s skill mainly in maintenance work.

Training must be arranged for each individual on promotion, which calls for
performing new/different roles and working conditions.

Upgradation of skills at periodic intervals is necessary to keep pace with


developments in the scientific world. This phenomena has entered into all areas of
human life, but the need has been felt acutely, particularly in fields involving use of
expensive, complex equipment like SCADA and for good O&M processes.

The advent of automation and extensive use of computers has resulted in the
creation of SIMULATORS. They have been found to be indispensable in periodic
training of personnel in Thermal and Hydro Power Stations and also in Power System
Networks. Simulators give a feel of the whole system to the trainee. Simulators need
not necessarily be envisaged only for training in operation of equipment but also for
systems, incorporating various experiences undergone by different personnel.
Simulator happens to be a cost effective tool to provide highly interactive and high
quality training to the operation personnel

In view of the above the Working-Group recommends that Simulator training should
be made compulsory for operation and maintenance staff of the Power Plants,
including refresher training at suitable intervals.

Page 15 of Chapter 7
Human Resource Development Working Group on Power for 11th Plan

iii) Management Training

Continuous development of Executives/Managers, specially at the transition period in


their career and in the context of constantly changing business environment is of
utmost importance. It has been noticed that while there are a large number of
capable and knowledgeable engineers available in the Power Sector, their
managerial ability needs to be improved. Due to process of reforms, restructuring,
unbundling, privatization etc. the role of Managers have gained more importance.
Executives in Finance and Management with non-technical background should also
be provided technical orientation through suitable training programs.

iv) Training for Nuclear Power Personnel

Due to stringent safety requirements and other national and international regulations,
every personnel working in Nuclear Power Sector is exposed to very specialized
training. To meet the multi-disciplinary needs the Department of Atomic Energy
(DAE) has built in-house training facilities both for professionals and Non-
professionals and the well-established Nuclear Training Centre (NTC) at RAPS,
MAPS and the TAPS. These Training Centres impart specialized training to their
personnel.

DAE has also established a few Nuclear Power Plant Simulators to impart
specialized training to their personnel.

Nuclear Power Corporation is fulfilling its training needs requirements in a long-term


perspective.

v) Training in Demand Side Management, Energy Efficiency And Energy


Conservation

There is a vast potential for energy savings through Human Resource Intervention.
BEE has a major responsibility for simulating a major change in the energy efficiency
ethos and practices (energy modesty) by directing the national energy conservation
campaign as a mass movement and seeking wide support.

In the 11th Plan, BEE will continue with their campaigns. In addition it will guide and
partially fund the SDAs for their respective campaigns in the states.

A few target groups to be addressed by BEE include the Central Government


Officials in the administrative Ministries and Departments by triggering ideas for
accelerating energy conservation drive and addressing of Policy Barriers impeding
the same. Round Tables on energy policy sponsored by MoP will be organized to
deliberate on the related issues.

At the state level, SDAs will develop synergistic partnerships to spread the activities
in the interior locations with active involvement of the local community, chambers of
industry and Commerce, DISCOMs, Professionals and the media.

SDAs will organize energy conservation interactive meets and senior officials of the
state Ministries and Govt. departments and state Govt. enterprises. The meets would

Page 16 of Chapter 7
Human Resource Development Working Group on Power for 11th Plan

focus on Policy support needed to step up the tempo of energy conservation


movement in the states.

• Cadre of energy managers and energy auditors

BEE is conducting examinations for certifying energy managers and energy


auditors in collaboration with National Productivity Council. These efforts will be
continued and periodically reviewed. BEE will also augment these efforts through
distance learning programs, tutorial support to the prospective candidates for the
national examination besides refresher programs to the certified energy
managers/energy auditors.

• Orientation Programs: Top Level Industry –personnel

Energy efficiency improvement in India is still considered to be the engineer’s


domain, and CEOs and Chief Finance Officers are not yet aware that energy
efficiency improvement has to improve the profitability of their companies.
Industry bodies will be roped in by the SDAs for orienting top executives from the
industry.

• Demonstrative Training – operators

SDAs may support skill development for operators on efficient energy use through
demonstrative approach involving exposure of the participants to the best
practices. This may also include setting up of two demonstration centers to show
case energy efficient products through models, field visits and video presentations
to simulate shop floor conditions.

• Farmers awareness programs

Ministry of Power had mounted awareness programs with the support of


manufacturers to demonstrate the energy efficient agricultural pumps in various
Trade Fairs as well as local Fairs. Such efforts will be continued with the support
of SDA, DISCOMs and other voluntary agencies.

• Drivers training

PCRA has been very active in imparting drivers on fuel-efficient driving practices.
It also has award schemes to motivate drivers and state transport agencies to
achieve maximum fuel efficiency includes best kilometer per liter. These efforts
will be extended.

• Campaign for General public & Youth

National wide campaign on Energy Conservation will be mounted to publicize the


simple ways of saving energy by involving the general public, the youth,
government agencies, public and private sector, professionals. BEE will utilize
mass media effectively for conveying the message of energy conservation.
Yardsticks for evaluation of awareness campaigns will be developed.

Page 17 of Chapter 7
Human Resource Development Working Group on Power for 11th Plan

• Energy conservation in curriculum

There is a need for introducing module on energy conservation (EC) in the


curriculum in schools and colleges. The EC concept will be introduced by
modifying existing text of related subjects in school & college curriculum. Active
involvement of NCERT, State Boards, Academic institutions, Universities will be
ensured for review of the existing curriculum, training and sensitization of
teachers and principals.

Efforts would be put in for training /equipping the teachers of vocational schools,
Industrial Training Institutes on inducting energy efficiency modules in the
compulsory and optional subjects. The curricula for graduation /post –graduation in
engineering levels needs to suitably modify. Suitable modules will be included for the
management education as well as finance, science and humanities streams (for
subjects such as social sciences, economics, environmental education, etc.

vi) Training in Information Technology

Information technology has pervaded all spares of life, adequate training according to
the job requirement should be provided in the field of information technology. Use of
IT should be promoted and maximum number of personnel should be made
computer literate. As information technology is also developing very fast, the training
should be dynamic in nature to ensure that knowledge and skill of people are in tune
with latest development in the field of IT. Employees should also be made aware of
the Right to Information Act.

vii) Introduction of Training on attitudinal changes/ behavioral sciences.

Attitude of an individual plays an extremely important role in contributing to his/her


performance level. Thus, in spite of availability of the best of knowledge and skill, the
ability of providing the desired services may still be found wanting in individuals if
they are not imbued with appropriate attitudinal disposition. It has been observed that
the training is presently concentrated mainly in the area of acquisition of knowledge
and upgradation of skill and very little emphasis is given on attitudinal
changes/behavioral sciences as it is high time to introduce this aspects of training in
the management curriculum of induction level training as well as retraining programs.
In some of the Utilities behavioral science has achieved very good results particularly
with respect to the attitudinal change of the lower category of personnel. After
undergoing such training, the personnel develop a sense of belongingness to the
organization.

In Addition To Technical Skills, Power Professionals, Need To Have Life Skills Such
As:

¾ Communication Skills
¾ Time Management
¾ Team Work
¾ Technical Writing
¾ Ethics

Page 18 of Chapter 7
Human Resource Development Working Group on Power for 11th Plan

7.3.2 Training Load

Training requirement for 11th and 12th Plans have been worked out on the basis of
manpower projections with the following assumptions:

i) Induction training to all freshly recruited technical persons as per statutory


requirements under Indian Electricity Rules.

ii) For all freshly recruited non-technical staff induction training of three
months for executives and one month for non-executives.

iii) Minimum one week training (Refresher/Managerial/Attitudinal) every year


for all personnel.

Overall training load during 11th Plan is estimated as 4.65 lakh man-months/year
against the available training infrastructure of 0.77 lakh man-months/year. Out of the
total, training load for technical people is estimated as 3.64 lakh man-months/year
(Appendix 7.1). The estimation for non-technical personnel is 0.73 lakh man-
months/year (Appendix 7.2).
While assessing the above, Assumptions made are:

1. One week refresher training for all employees.


2. Fresh Manpower on account of re-coupment and capacity addition not
considered for refresher training.
3. For Non-Technical staff induction level training duration is 3 months for
Executives & 1 month for Non-Executives.
4. 20% of the refresher training load is taken as training load for Management
training including behavioural component

Overall training load during 12TH Plan is estimated as 4.78 lakh man-months/year
against the available infrastructure of 0.80 lakh man-months/year. Out of the total
training load for technical people is estimated as 3.98 lakh man-months/year
(Appendix 7.3). The estimation for non-technical personnel is 0.80 lakh man-
months/year (Appendix 7.4).

While assessing the above, Assumptions made are:

1. One week refresher training for all employees.


2. Fresh Manpower on account of re-coupment and capacity addition not
considered for refresher training.
3. For Non-Technical staff induction level training duration is 3 months for
Executives & 1 month for Non-Executives.
4. 20% of the refresher training load is taken as training load for Management
training including behavioural component

Basically three types of training infrastructure/facilities are available:

i) Training institutes recognized by CEA for imparting statutory induction


training

Page 19 of Chapter 7
Human Resource Development Working Group on Power for 11th Plan

ii) Lineman Training Institutes

Other Training facility (Class/board rooms for refresher/ management programs)


including networking with academic/training institutions outside power sector.

7.3.3 Training Infrastructure-Requirements vis-à-vis availability

It may be seen from Appendix 7 .1 that during 11th Plan the availability of
infrastructure is about 0.77 lakh man-months against the requirement of 3.40 lakh
man-months/year i.e., a deficit of about 77%. It may be noted that inspite of such a
situation of lack of availability of required infrastructure, quite often a number of
training institutes remain under utilized.

The Sub Group also stressed on Networking with the training/academic institutions
like NPTI, IIMs, ASCI and other reputed institutions for providing training to power
sector personnel and other stakeholders.

7.4 FUNDING & CAPITAL OUTLAY

Establishing and sustaining a continuous training initiative needs adequate funds.


Decision makers must appreciate that training is an investment and not a mere
expenditure towards a ritual.

The funds required for training can broadly be categorized under two heads, ‘Capital
outlay (Plan)’ and “Recurring Expenditure (Non Plan). The fund required for creating
training infrastructure is booked under the first one while expenses towards salaries,
TA/DA training fee etc. comes under the second.

10 major states should set up State Level Training Institutes encompassing training
infrastructure for Induction level, Linemen and for Franchisees. GoI may provide part
funding of Rs 10 Crores for each state.

An incentive to the sponsoring organization @ Rs 2000 per man-week of Refresher


Training (towards part Training Fee Component only) may be provided by GoI to the
institute providing training. Approximate outlay during the 11th Plan will be 100
crores.

Central assistance of about Rs 140 Crores may be provided for setting up National
Level Transmission, Distribution and a Hydro Institute.

GIS Based Electrical Distribution Systems to be set-up in various regions for training.
Budgetary allocation of Rs 6.00 crores is proposed.

For Upgradation of various labs and Infrastructure of National Institutes, 100 crores is
proposed.

A 660 MW Super Critical Power Plant Simulator at a cost of Rs. 16.00 Crores is also
proposed.

Page 20 of Chapter 7
Human Resource Development Working Group on Power for 11th Plan

The Total Plan period outlay is about Rs 462 Crores. This does not include the plan fund
outlay proposed by other Sub-Groups

The Working Group recommends Training Institutes and Centers to enter into
bilateral/multilateral agreements with various funding agencies such as UNDP,
USAID, GTZ, World Bank, ADB, Japanese Aid etc., through appropriate forums such
as MoP, State Boards /Utilities for the development of state-of-the-art training
facilities.

Recurring Expenditure

5% of Salary budget should be earmarked exclusively for training by every


organization.

Expenditure towards training may be included while costing for power tariff like other
essential cost heads like servicing of capital, fuel charges, salary, insurance etc. and
this expenditure should be reflected in the annual balance sheet of the organization.

7.5 MAJOR RECOMMENDATIONS

Every employee should be provided refresher training of minimum one week per year
as mandated in National Training Policy. Statutory rules provide for periodical
refresher training for all O&M personnel in different segments. In addition, refresher
training to all power sector personnel as per their requirement should also be
included. A national programme also needs to be launched for training and capacity
building for upgrading and enhancing the skills of franchisee who are proposed to be
deployed on a large scale for small as well as urban areas.

**********

Page 21 of Chapter 7
Human Resource Development Working Group on Power for 11th Plan
Appendix 7.1
th
Training Load during 11 Plan for Technical (Includes Infrastructure) in Thousand-Man-Months (TMM)
S. Category Manpower to Average Total for Per year On-Job Infrastructure Infrastructur Surplus
th
No. Area be trained in duration 11 Plan Thou- compone required per e available (+)
Thousands in Months Thou-Man- Man- nt 50%of year in 10th Plan Deficit
Months Months (A) (TMM) + 5% (TMM) (-)
(A)
1. Thermal
(Induction)
Engrs – 30% Engineers 11.69 12 140.28 28.06 14.03 14.03 12.85 -1.18
Opers – 15% Op/Sup/JEs 5.84 12 70.08 14.01 7.00 7.00 10.95 +3.94
Tech – 55% Technicians 21.43 12 257.16 51.43 25.71 25.71 15.05 -10.66
Sub-Total 38.97 467.52 93.50 46.74 46.74 38.86 -7.88
2. Hydro(Induction)
Engrs – 20% Engineers 5.78 9 52.02 10.40 5.20 5.20 0.64 -4.56
Oper – 35% Op/Sup/JEs 10.11 6 60.66 12.13 6.06 6.06 1.43 -4.63
Tech – 45% Technicians 13.00 6 78.00 15.6 7.8 7.8 2.18 -5.62
Sub-Total 28.90 190.68 38.13 19.06 19.06 4.26 -14.80
3. Power System
(a) Transmission
(Induction)
Engrs – 10% Engineers 2.82 12 33.84 6.77 3.38 3.38 2.40 - 0.98
Oper – 20% Op/Sup/JEs 5.64 6 33.84 6.77 3.38 3.38 1.76 -1.62
Tech – 70% Technicians 19.75 6 118.50 23.70 11.85 11.85 9.82 -2.03
Sub-Total 28.21 186.18 37.24 18.62 18.62 13.98 -4.64
(b) Distribution
(Induction)
Engrs – 10% Engineers 21.59 6 129.54 25.91 12.95 12.95 2.40 -10.55
Oper – 20% Op/Sup/JEs 43.18 3 129.54 25.91 12.95 12.95 1.76 -11.19
Tech – 70% Technicians 151.10 1 151.10 30.22 15.11 15.11 9.82 -5.29
Sub-Total 215.86 410.18 82.04 41.01 41.01 13.98 -27.03
4. Refresher Course Refresher 566.22 1.25 566.22 113.24 0 113.24 4.53 -108.71
Course
5. Management Management 566.22 141.55 28.31 0 28.31 1.50 -26.81
Training (20%)
Grand Total 878.16 1820.78 364.15 125.43 266.92 77.13 -189.79

Page 22 of Chapter 7
Human Resource Development Working Group on Power for 11th Plan
Appendix 7.2
Training Load during 11th Plan for Non-Technical (Includes Infrastructure) in Thousand-Man-Months
S. Area Category Manpower to Average Total for Per year On-Job Infrastructur Infrastructu Surplus (+)
No. be trained in duration 11th Plan Thou- component e required re available Deficit
th
Thousands in Thou-Man- Man- 50%of (A) per year in 10 Plan (-)
Months Months Months (TMM) + 5%(TMM)
(A)
1. Thermal (Induction)
Exec – 20% Executives 2.99 3 8.97 1.79 0 1.79 0 -1.79
Non-Exec – 80% Sup/UDCs 11.97 1 11.97 2.39 0 2.39 0 -2.39
/LDCs etc.
Sub-Total 14.96 20.94 4.18 0 4.18 0 -4.18
2. Hydro(Induction)
Exec – 20% Executive 1.74 3 5.22 1.04 0 1.04 0 -1.04
Non-Exec – 80% Sup/UDCs 6.95 1 6.95 1.39 0 1.39 0 -1.39
/LDCs etc.
Sub-Total 8.69 12.17 2.43 0 2.43 0 -2.43
3. Power System
(a) Transmission
(Induction)
Exec – 20% Executive 1.69 3 5.07 1.01 0 1.01 0 -1.01
Non-Exec – 80% Sup/UDCs 6.79 1 6.79 1.35 0 1.35 0 -1.35
/LDCs etc.
Sub-Total 8.48 11.86 2.36 0 2.36 0 -2.36
(b) Distribution
(Induction)
Exec – 20% Executive 13.04 3 39.12 7.82 0 7.82 0 -7.82
Non-Exec – 80% Sup/UDCs 52.16 1 52.16 10.43 0 10.43 0 -10.43
/LDCs etc.
Sub-Total 65.20 91.28 18.25 0 18.25 -18.25
4. Refresher Course Refresher 184.39 1.25 184.39 36.87 0 36.87 0 -36.87
Course
5. Management Management 184.39 46.09 9.22 0 9.22 0 -9.22
Training (20%)
Grand Total 281.72 366.73 73.31 0 73.31 -73.31

Page 23 of Chapter 7
Human Resource Development Working Group on Power for 11th Plan
Appendix 7.3
Training Load (Induction) during 12th Plan for Technical (Includes Infrastructure) in Thousand-Man-Months

S. Area Category Manpower to Averag Total for Per year On-Job Infrastructure Infrastructure Surplus
No. be trained in e 12th Plan Thou- componen required per available in (+)
th
Thousands duratio Thou- Man- t 50%of year 11 Plan + Deficit
n Man- Months (A) (TMM) 5% (TMM) (-)
in Months (A)
Month
s
1. Thermal
(Induction)
Engrs. – 30% Engineers 9.92 12 119.04 23.81 11.90 11.90 13.49 +1.59
Oper – 15% Op/Sup/JEs 4.96 12 59.52 11.90 5.95 5.95 11.49 +5.54
Tech – 55% Technicians 18.19 12 218.28 43.66 21.82 21.82 15.80 +6.03
Sub-Total 33.08 396.84 79.37 39.68 39.68 40.78 +1.10
2. Hydro
(Induction)
Engrs. – 20% Engineers 6.00 9 54.00 10.80 5.40 5.40 0.67 -4.73
Oper – 35% Op/Sup/Jes 10.51 6 63.06 12.61 6.30 6.30 1.50 --4.80
Tech – 45% Technicians 13.51 6 81.06 16.21 8.10 8.10 2.28 -5.82
Sub-Total 30.03 198.12 39.62 19.80 19.80 4.45 -15.35
3. Power System
(a) Transmission
(Induction)
Engrs. – 10% Engineers 2.02 12 24.24 4.85 2.43 2.43 2.52 -0.09

Oper – 20% Op/Sup/JEs 4.04 6 24.24 4.85 2.43 2.43 1.85 -0.58
Tech – 70% Technicians 14.17 6 85.02 17.00 8.50 8.50 10.30 -1.80
Sub-Total 20.24 133.50 26.70 13.36 13.36 14.67 -2.47
(b) Distribution
(Induction)
Engrs. – 10% Engineers 20.21 6 121.26 24.25 12.12 12.12 2.52 -9.60
Oper – 20% Op/Sup/JEs 40.42 3 121.26 24.25 12.12 12.12 1.85 -10.27
Tech – 70% Technicians 141.46 1 141.46 28.29 14.14 14.14 10.30 -3.84
Sub-Total 202.09 383.98 76.79 38.38 38.38 14.67 -23.71
4. Refresher Course Refresher Course 702.51 1.25 702.51 140.50 0 140.50 4.75 -135.75
5. Management Management 702.51 175.62 35.12 0 35.12 1.57 -33.55
Training (20%)
Grand Total 987.95 1990.57 398.11 111.22 286.84 80.89 -205.95

Page 24 of Chapter 7
Human Resource Development Working Group on Power for 11th Plan
Appendix 7.4
Training Load (Induction) during 12th Plan for Non-Technical (Includes Infrastructure) in Thousand-man-months
S. Area Category Manpower to Average Total for Per year On-Job Infrastructur Infrastructure Surplus (+)
No. be trained in duration 12th Plan Thou- compone e required available in 11th Deficit
Thousands in Thou- Man- nt 50%of per year Plan +5% (-)
Months Man- Months (A) (TMM) (TMM)
Months (A)
1. Thermal
(Induction)
Exec – 20% Executives 2.57 3 7.71 1.54 0 1.54 0 -1.54
Non-Ex – 80% Sup/UDCs 10.28 1 10.28 2.06 0 2.06 0 -2.06
/LDCs etc.
Sub-Total 12.85 18.20 3.60 0 3.60 0 -3.60
2. Hydro(Induction)
Exec – 20% Executives 1.22 3 3.66 0.73 0 0.73 0 -0.73
Non-Exec – 80% Sup/UDCs 4.87 1 4.87 0.97 0 0.97 0 -0.97
/LDCs etc.
Sub-Total 6.09 8.53 1.70 0 1.70 0 -1.70
3. Power System
Transmission
(Induction)
Exec– 20% Executives 1.22 3 3.66 0.73 - 0.73 0 -0.73
Non-Exec – 80% Sup/UDCs 4.88 1 4.88 0.97 - 0.97 0 -0.97
/LDCs etc.
Sub-Total 6.10 8.54 1.70 1.70 -1.70
Distribution
(Induction)
Exec– 20% Executives 12.20 3 36.60 7.32 - 7.32 0 -7.32
Non-Exec – 80% Sup/UDCs 48.80 1 48.80 9.76 - 9.76 0 -9.76
/LDCs etc.
Sub-Total 61.00 85.40 17.08 17.08 -17.09
4. Refresher Course Refresher 225.37 1.25 225.37 45.07 0 45.07 0 -45.07
Course
5. Management Management 225.37 56.34 11.27 0 11.27 0 -11.27
Training (20%)
Grand Total 311.41 402.38 80.42 80.42 -80.42

Page 25 of Chapter 7
Legislative and Policy Issues Working Group on Power for 11th Plan

Chapter-8

LEGISLATIVE AND POLICY ISSUES

8.0 BACK GROUND

The Electricity Act 2003 has put in place a liberal and progressive framework for the
development of electricity sector in the country. Its main objectives are promoting
competition, Protecting interest of consumers, Supply of electricity to all areas,
Rationalization of electricity tariff and ensuring transparent policies regarding
subsidies.

The National Electricity Policy and the Tariff Policy have been notified under the
provisions of the Act. The National Electricity Policy, inter-alia, aims at Providing
access to electricity to all in next five years, Overcoming energy and peaking
shortages and having adequate spinning reserves by year 2012 for fully meeting the
demand, Supply of reliable and quality power of specific standards in an efficient
manner and at reasonable rates.

The Tariff Policy aims at ensuring financial viability of the sector and promoting
transparency, consistency and predictability in regulatory approaches. It also aims at
promoting competition and efficiency in operation and meeting quality of supply.

The Working–Group deliberated on the specific recommendations made in the


Integrated Energy Policy and National Electricity Policy and recommended measures
for their implementation.

The Integrated Energy Policy and the National Electricity Policy endeavor to
fundamentally change the Power Sector to function in an open, competitive regime
under regulatory oversight. The provisions of these Policies must be implemented
within the stipulated time in order to make power available at affordable cost to all by
2012. This Chapter includes the provisions of the Policies and measures
recommended by the Working-Group for their implementation. In certain cases
provisions of the Policies are countered by the Working-Group, in case of which the
Government may take appropriate action. Comments of Prayas Energy Group are
enclosed at Appendix 8.2 and IIT Kanpur are enclosed at Appendix 8.3.

8.1 IMPLEMENTATION OF PROVISIONS OF ACT AND POLICIES

The legal provisions of the Act, National Electricity Policy, Tariff Policy and the
Integrated Energy Policy provide an appropriate legislative and policy framework for
the development of the country. There is a need to implement these at the earliest to
achieve the stated goals.

Page 1 of Chapter 8
Legislative and Policy Issues Working Group on Power for 11th Plan

8.2 STATUS OF IMPLEMENTATION AND DEVIATIONS OF INTEGRATED


ENERGY POLICY

The Integrated Energy Policy announced by the Government aims at overall


development of the Energy Sector. It is essential that its recommendations are
implemented within the stipulated time period in order to realize the benefits
envisaged, Details of the recommendations of the Policy and the status of their
recommendations are as furnished below:

1. Recommendation : Bifurcate agricultural pumping load from the non-pumping


load in all rural feeders and use available technological
measures to limit and measure the amount of energy
supplied to pumps.

Position Being recommended by the Working Group

2. Recommendation : To introduce automatic meter reading at distribution


transformers to pinpoint theft of electricity. To introduce
an incentive scheme for staff whereby they share
additional revenue collected in their distribution circle.

Position Tariff Policy (para 8.2.1(2)) provides that SERCs may


encourage suitable local area based incentive and
disincentive scheme for the staff of the utility linked to
reduction in losses. Further, States are being advised to
introduce suitable incentive schemes for rewarding
informers who assist in control of theft.
3. Recommendation : The data about AT&C losses should be disseminated to
the public to create support for corrective action.

Position The National Electricity Policy (para 5.12.2) provides that


the data reliable index should be compiled and published
by the Central Electricity Authority. Similar action should
be taken in respect of feederwise AT&C losses.

4. Recommendation : For all loads above 50 kWh, intelligent metering to


facilitate real time and remote recording should be
adopted.
Position The National Electricity Policy (para 5.4.10) provides
adoption of modern IT systems with due consideration to
costs and benefits.

5. Recommendation : Introduce time-of-day pricing with shift to electronic


meters.

Page 2 of Chapter 8
Legislative and Policy Issues Working Group on Power for 11th Plan

Position CEA’s Metering Regulations provide that all new


consumer meters would be of electronic type. The Tariff
Policy (para 8.4) provides that time differentiated tariff
shall be introduced on priority for large consumers (above
1 MW) within one year.

6. Recommendation : All Central assistance to States in power sector must be


linked exclusively to loss reduction and improved viability.

Position Being recommended by Working Group.

7. Recommendation : Management reforms particularly in the distribution sector


are as important as a liberal captive and open access
regime.

Position Working Group has given specific recommendations in


this regard.

8. Recommendation : Involve stakeholders for successful regulation. Appoint an


office of “Consumer Advocate” at State level.

Position Working Group has recommended encouraging


participation of consumer organizations in the regulatory
process. The Electricity Act provides for Ombudsman to
look into settlement of consumer grievances. The
Electricity Rules, 2005 provide for six monthly report of
the ombudsman to the Regulatory Commission in this
regard.

9. Recommendation : Strength of dominant public sector can be effectively


leveraged to introduce competition that extracts efficiency
gains in generation, transmission and distribution.

Position The Working Group has also recommended that the


public sector companies should be encouraged to
participate in the competitive bids.

10. Recommendation : In case of tariff determination based on costs and norms,


the Regulatory Commission may adopt either ROE
approach or ROC approach whichever is considered
better in the interest of consumers.

Position Tariff Policy (para 5.3(a)) provides for this.

11. Recommendation : Distribution should be bid on the basis of distribution


margin or paid for by a regulated distribution charge.

Page 3 of Chapter 8
Legislative and Policy Issues Working Group on Power for 11th Plan

Position Tariff Policy (para 5.3(a)) provides that the SERC may
consider “distribution margin” as basis for allowing return
in distribution.

12. Recommendation : All generation and transmission projects should be


developed through competitive route with a transition
window of 5 years for public sector.

Position Tariff Policy (para 5.1) already provides for this.

13. Recommendation : Liberal captive and group captive regime should be


realized on the ground on the basis of competitive
wheeling charges.

Position Tariff Policy provides for this and Forum of Regulators


has been requested to expedite this.

14. Recommendation : Any subsidy given to poor households or farmers should


be funded from the State Government budget.

Position Section 65 of the Electricity Act already provides for this.

15. Recommendation : Existing projects and future investment which are not
competitively bid must comply with CERC tariff
guidelines.

Position This is already provided in section 61 of the Act which


makes it mandatory to follow CERC’s principles and
methodologies in respect of tariff for generation and
transmission.

16. Recommendation : Regulators should set tariff for a number of years and
differentiate them by time-of-day.

Position Tariff Policy (para 5.3(h)) provides that the Multi Year
Tariff is to be adopted for tariffs to be determined from
April 1, 2006. The policy also provides for TOD tariffs.

17. Recommendation : Respective regulators should adopt best international


practices for harnessing distributed generation with waste
heat recovery, Demand Side Management and energy
conservation.

Position This is already provided in the National Electricity Policy


and needs to be implemented.

18. Recommendation : Regulators must establish feed-in-tariffs for power from


renewable energy sources. Such tariffs should provide
Time of day benefits.

Page 4 of Chapter 8
Legislative and Policy Issues Working Group on Power for 11th Plan

Position Tariff Policy in its para 6.4 provides for competitive


procurement of power from non-conventional sources of
energy. The policy envisages bidding among the
suppliers from same sources of non-conventional energy.
To elaborate, bids are required to be called separately for
energy from solar based plants, wind based plants,
biomass based plants etc. The Tariff Policy also provides
that the Appropriate Commission may introduce
differential rates of fixed charges for peak and off-peak
power for better management of load.
19. Recommendation : Separate content from carriage in both transmission and
distribution with regulated caps for wheeling charges at
different voltages and distribution margins for consumers.
Introduce competition in building transmission capacity on
the basis of wheeling tariffs and in distribution on the
basis of distribution margins.

Position The Act debars Central Transmission Units (CTU) from


trading. Tariff Policy already provides for developing
transmission projects through competitive bidding. The
policy also gives option of adopting “distribution margin”
as a method for regulating distribution.

20. Recommendation : Transmission lines critical for inter-state flows of power


and for system stability should be managed by the
Central body even if such lines are entirely in one State.

Position CERC has full jurisdiction over inter-state transmission of


electricity. Such inter-state transmission includes
conveyance of electricity within a State also.

21. Recommendation : Independent and/or fully transparent load dispatch is


required to create level playing field.

Position RLDC is under the control of the Central Commission.


Presently, RLDCs are being operated by CTU i.e. Power
Grid. This function of CTU could be ring fenced
adequately to ensure transparency.

22. Recommendation : An independent planning body is necessary for


transmission networks.

Page 5 of Chapter 8
Legislative and Policy Issues Working Group on Power for 11th Plan

Position According to section 3 of the Electricity Act, 2003, CEA


has to prepare the National Electricity Plan in accordance
with the National Electricity Policy. The National Electricity
Policy provides that CEA shall prepare short-term and
perspective plan. Further the plan has to include
transmission planning also. The National Electricity Policy
(para 5.3.2) provides that the CTU and the STU shall
discharge responsibility of network planning and
development based on the National Electricity Plan in
coordination with all concerned agencies as provided in
the Act. This arrangement takes care of planning by an
expert body CEA and necessary coordination in network
expansion by the respective transmission utility.

23. Recommendation : Require the State Governments to notify rural areas


under section 14 of the Act.

Position The Rural Electrification Policy (para 8.2) provides that


the State Governments would notify the rural area for this
purpose within two months. 23 States have already
issued notifications.
24. Recommendation : To facilitate distributed generation and promote
renewable sources of energy, make mandatory setting up
grid interconnections for feeding surplus power into the
grid at the grid’s avoided cost.

Position Tariff Policy (para 6.4) provides for competitive


procurement of power from non-conventional sources of
energy.

25. Recommendation: Encourage the organized sector to adopt rural


communities in their areas of operation for setting up off-
grid and distributed generation facilities and involve local
community.

Position The Rural Electrification Policy (para 8.8) provides for a


special enabling dispensation for setting up standalone
system upto one MW using locally available resources.
This needs to be implemented at the earliest.

26. Recommendation : Augment exploration/drilling capacity of CMPDIL and it


should also be given more autonomy. Open up coal
exploration for other players also.

Position Working Group has given recommendations in this


regard.

Page 6 of Chapter 8
Legislative and Policy Issues Working Group on Power for 11th Plan

27. Recommendation : Allocate coal blocks in competitive and transparent way


creating a level playing field with a condition that these
blocks be brought into production by year 2011-12..
Transfer pricing of coal from captive mines needs to be
established both for assessing royalties as well as tariffs
in a regulated sector such as power wherein coal cost is a
pass through.

Position Working Group has recommended allotment of captive


coal blocks in a transparent and competitive manner.to
power generation projects based on competitive bidding
for lowest cost of electricity.

28. Recommendation : Rail freight rates for coal transport should be rationalized.

Position Working Group recommends implementation of this


measure as it is essential for lowering the cost of power

29. Recommendation : Simplify procedures for preparation of EMPs for coal


mining. Create a reserve of compensatory afforestation in
advance.

Position Working Group recommends implementation of this


measure as it is necessary to accelerate captive coal
mining.

30. Recommendation : A regulator in coal sector for regulating allotment and


exploitation of coal blocks, for approving coal price
revisions.

Position Working Group recommends implementation of this


measure.

31. Recommendation : Coal linkages should be made tradable in the first


instance with long term objective of replacing the current
coal linkages for power plants with fuel supply and
transport agreements.

Position Working Group opines that there is a requirement to


convert the coal linkages into formal fuel supply contracts
catering to full requirement of the power plant. However,
there is a need to be cautious in implementation of this
recommendation for making coal linkages tradable as
there is a possibility of speculative trading leading to
increase in price of fuel.
32. Recommendation : Include natural gas and LNG in the category of declared
goods so that only central sales tax of 4% is levied.

Page 7 of Chapter 8
Legislative and Policy Issues Working Group on Power for 11th Plan

Position Working Group recommends implementation of this


measure.

33. Recommendation : In the present scenario price of domestic natural gas, its
allocation should be independently regulated on a cost
plus basis including reasonable returns.

Position Working Group has also recommended this.

34. Recommendation : The Integrated Energy Policy gives two options for
ensuring environmental impact. First option is to impose
environmental tax and give subsidies. Second option is
setting up emission and energy conservation standards
on the equipments.

Position The Integrated Energy Policy provides for optional


strategies. Second option of setting emission and energy
conservation standards on equipments is more suitable
for power sector and can be implemented easily. The
National Electricity Policy also provides that all generating
stations should ensure full compliance with prescribed
environmental norms and standards. This is considered to
be a better option than imposing environmental tax.
Environmental tax would raise the cost of electricity which
is a basic infrastructure requirement and would adversely
affect development of our economy. Instead of taxes,
penalties should be imposed on those who fail to comply
with the laid down standards.

35. Recommendation: Institutionalize the selection of regulators and their impact


assessment under the regulatory academy.

Position Setting up the suggested regulatory academy would be


appropriate for capacity building in the staff of various
regulatory bodies. The selection of the regulators is
governed by the relevant provision of law. However, there
is a genuine concern about the outcome of the selection
process in case of some of the State Electricity
Regulatory Commissions. Since the electricity is a
concurrent subject, ways and means to strengthen and
improve the selection process at State level needs to be
discussed in depth with the State Governments.
Assessment of impact of regulatory process is being done
by NGOs and other similar organizations.

36. Recommendation : Mandate training for all regulators.

Position Recommended by the Working Group.

Page 8 of Chapter 8
Legislative and Policy Issues Working Group on Power for 11th Plan

37. Recommendation : Grant financial autonomy to regulatory institutions.

Position The Electricity Act already provides for a fund for each
Regulatory Commission.

38. Recommendation : Make regulators accountable to the Parliament and


mandate annual reports.

Position This is already provided in the Act. Format of the reports


has been laid down in the rules.

39. Recommendation : With reference to Mega Power Policy, there should be no


discrimination in available incentive based on the size or
type of technology or fuel used .

Position Working Group opines that this needs further


examination.

40. Recommendation : The Central Government and the State Governments and
FIs should develop long term (20 years plus) debt
instrument.

Position This would be necessary in view of the provisions of the


Tariff Policy to dispense with advance against
depreciation.

41. Recommendation : Special policies for encouraging renewable energy should


be for a well defined period or upto a well defined limit in
a way that encourages outcome and not just outlays.

Position Working Group has given specific recommendation in this


regard.

42. Recommendation : The environmental subsidy for renewables could be


financed by a cess on non-renewables and fuels causing
environmental damage.

Page 9 of Chapter 8
Legislative and Policy Issues Working Group on Power for 11th Plan

Position This would increase the cost of electricity across the


board. The Electricity Act provides for preferential
purchase from non-conventional sources to the extent
specified by the Regulatory Commission taking into
account local situation. The National Electricity Policy
provides for preferential charges for procuring energy
from non-conventional sources in view of the fact that
such non-conventional technologies would take some
time to compete with conventional sources in terms of
cost. The Tariff Policy stipulates that these technologies
would compete with conventional sources in the long term
in terms of full costs. Some of the non-conventional
sources like wind have almost reached the stage of self-
sustainability. To promote non-conventional source
further, there is a need to provide for a long term
financing because initial capital cost is higher in these
cases.

43. Recommendation : Supply companies/ entrepreneurs could be free to set up


micro grid and recover revenues from customers.

Position The Rural Electrification Policy (para 8.8) provides for a


special enabling dispensation for setting up standalone
system upto one MW using locally available resources.
Working Group also recommends that this needs to be
implemented at the earliest.

44. Recommendation : A charge of Rupee one per unit for the first 30 units per
month could be levied on poor households.

Position National Electricity Policy (para 5.5.2) provides for cross


subsidized tariff for 30 units per month for BPL
households.

45 More Effective Planning & Implementation

Recommendation in Policy (Pg. 114 Cl 18) -

Policy stipulates “In order to avoid shortages and take timely action, annual electricity
requirements should be projected and year-wise targets for generation capacity be
set for seven years. Each project should be monitored along with a number of
milestones ………..”

Working-group – Implementation

The achievements in capacity addition during 8th & 9th plan periods have been
merely 50% of the plan target. Also during 10th Plan the actual capacity addition is
expected to be about 31,000 MW against the plan target of 41,110 MW. The
Working-Group deliberated on the reasons for this large variation and recommended
as follows:-

Page 10 of Chapter 8
Legislative and Policy Issues Working Group on Power for 11th Plan

The status of preparation and approvals etc. for each of scheme included in the 11TH
Plan must be realistically assessed and the sponsoring entity must indicate 5 to 6
time based milestones for each scheme.

Plan document should indicate scheme wise commissioning targets for 7 years (5
years of the Plan period and first two years of the next plan) and monitoring should
be done for all these schemes so that substantial capacities are commissioned from
the first year of the Plan onward. However, for 11th Plan, five year plan period may
be considered.

Since Hydro & Nuclear Projects have comparatively larger Gestation period, planning
for their projects shall be for a period of 10 years.

In order to facilitate timely implementation of projects, capacity building in respect of


infrastructural requirements like road, railways, erection, manufacturing etc. is
essentially to be ensured. Well structured plans need to be evolved to ensure this
aspect.

Demand adopted for Planning

46. Recommendation in Policy ( Pg 20, Table 2.5)

Policy has projected the following installed capacity requirements during the
subsequent Plans corresponding to 8% and 9% GDP growth:

(Fig. in GW)
Plan 8% GDP Growth 9% GDP Growth
11th 220 233
12th 306 337
13th 425 488
14th 575 685
15th (till 2031-32) 778 960

Working- group – deviation

The Working-Group recommends that generation capacity addition shall be planned


by adopting demand projections as per the current Report of Electric Power Survey
rather than GDP growth rate. The Electric Power Surveys assess the demand based
on a systematic, detailed analysis of electric utilization in various sectors of
consumption and the expansion plans of various sectors. These figures are also
validated by econometric model. However for Plans beyond that covered by the
current EPS, growth as per Government’s GDP growth plans and elasticity figures
could be adopted. For 12th Plan we have worked out demand taking 7%, 8% & 9%
growth with elasticity of 0.9 & 1.0 in each case. The demand as per the EPS Reports
has therefore been found to be very close to the actual demand and therefore its
adoption for working out the generation capacity addition would be more accurate
then assuming the same GDP growth for each sector of our economy.

Page 11 of Chapter 8
Legislative and Policy Issues Working Group on Power for 11th Plan

47. Use of Washed Coal

Recommendation in Policy (Pg.xv Cl i) –

Policy stipulates that “washed coal must become the norm and use of unwashed coal
must become the exception. “

Working-group - recommendation

In this connection, the Working-Group opined that the major problems faced on
account of coal are related to inconsistency of indigenous coal quality and lack of
appropriate quality control measures at mining end. Such measures would effectively
control the menace of excessive overburden and extraneous matter in the coal as
supplied to power stations. Use of washed coal would be imperative for power
stations located at a farther distance from the coal source and/or in those cases
where cost of coal washing gets neutralized by improvement in plant performance.
Therefore, Working group recommends that use of washed coal has to be
appropriately adopted based on overall cost economics taking into account the low
washing yields for most of our coals.

48. Improvement in Efficiency of Generating Plants

Recommendation in Policy (Pg xxi Cl vii) –

Policy envisages to “ Increase the gross efficiency in power generation from the
current average of 30.5% to 34%. All new plants should adopt technologies that
improve their gross efficiency from the prevailing 36%to at least 38-40%”.

Working-group – recommendation

Working-Group concluded that towards implementation of stipulation of Policy, units


of 500 MW and supercritical units of higher sizes have been considered during 11th
Plan onwards, which would be able to meet the criteria of designed efficiency of 38-
40% depending on coal quality envisaged.

49. Captive Power Generation

Recommendation in Policy (Pg xvi, Cl iv)

The Policy stipulates “The Committee also recommends that the liberal captive and
group captive regime foreseen under Electricity Act 2003 be realized on the ground”

Working-group - implementation

India’s liberal captive regime will not only derive economic benefits from the
availability of distributed generation but will also set competitive wheeling charges to
supply power to group captive consumers. This will pave the way for open access to
distribution networks. It will also facilitate private generation that limits its interface
with the host utility to the use of the distribution network for a fee and thus can be
realised even before AT&C losses are reduced. The Working-Group discussed the

Page 12 of Chapter 8
Legislative and Policy Issues Working Group on Power for 11th Plan

issues to be reckoned with i.e. open access, wheeling and banking and duties and
made recommendations to solve these issues.

50. Imported coal based coastal plants

Recommendation in Policy (Pg.xiv, Cl i)

Policy mentions that “….needed infrastructure must be created to facilitate thermal


coal imports. This will facilitate coastal power generation capacity based on imported
thermal coal…..”

Working-group- recommendation
Some Coastal Ultra Mega Projects based on imported coal are already being
conceived.

51 Standardization of Unit Size and Bulk Procurement

Recommendation in Policy (Chapter X clause 5) –


“MOP should seek global tenders for large-scale (20,000 MW or more) National
Power Projects that seek to exploit objectives such as standardised (super critical
800 MW units or better) bulk orders to reduce capital costs, internationally
comparable conversion/energy efficiencies, coastal locations with dedicated facilities
for handling domestic coal moved by sea or imported coal, improved emission
standards etc.”

Working-group- recommendation

As regards bulk procurement, it may be stated that presently the invitation of the
tenders/procurement of the projects for capacity addition are being taken up by
different Power Generation companies such as NTPC, SEBs/ State generation
companies, IPPs etc. For Bulk procurement to be undertaken, a Centralized
Procurement Body would be required. Further, for bulk procurement to be tendered
on global basis, clearances for all the projects would be required concurrently. While
undertaking bulk procurement, the competition angle would also have to be borne in
mind as it is felt that presently only a few players would be in a position to offer bids
in case of bulk procurement. It is proposed that to benchmark the Price for different
Unit Sizes, an Empowered Committee may be nominated.

52. Rate of Return

Recommendation in Policy ( Chapter X, clause 16)

Policy provides that where the cost plus regime cannot be avoided and payment
security mechanism under TPA is available, rate of return should be linked to long-
term Govt. bonds.

Page 13 of Chapter 8
Legislative and Policy Issues Working Group on Power for 11th Plan

Working-group- Deviation

Any policy while deciding the rate of return in power sector must consider present
scenario of the power sector. The need of the time is to provide attractive return for
power utilities.

Return is an issue of tariff determination and as per Electricity Act, 2003, tariffs are to
be determined by the Regulatory Commissions. In doing so, they are to be guided by
the provisions of National Electricity Policy and Tariff Policy issued by Govt. of India.
Accordingly, GOI has already issued these policy documents for setting out guiding
principles for the regulatory commissions. Mention of such provisions in different
policy documents will only lead to confusion. Hence, the provisions of the Integrated
Energy Policy may be reviewed.

53. Coal pricing

Recommendation in Policy(Chapter XI clause 22) regarding coal prices

Policy provides that “Pit-head price of coal under FSTAs should be revised annually
by coal regulator based on the formula that reflects prices obtained through e-
auction, FOB price of imported coal and production cost inclusive of return based on
efficiency standards.”

Working-group- Deviation

Linking coal price to price obtained through e-auction will only push up coal price and
is not advisable in view of goal of providing power to all at affordable price. Linking
the coal price with the imported coal price also would not be appropriate as the prices
there are quite volatile and vary in line with oil prices and as such would have
adverse impact on electricity prices. If at all it has to be linked, it should be linked to
the pit-head price of imported coal with respect to the pit-head price of Indian coal on
heat value basis.

In view of the above, it is suggested that coal price for supply under FSTA should be
fixed by Regulator based on cost of production inclusive of return based on efficiency
standards. Further, once the utilities develop the captive mines allocated to them, the
same can be used for benchmarking the coal prices.

54. Allocation of Coal mining Blocks

Recommendation in Policy “Domestic coal production should be stepped up by


allotting coal blocks to central and state public sector units and for captive mines to
notified end users. Coal blocks held by Coal India Limited (CIL) which CIL cannot
bring into production by 2016-17, either directly or through joint ventures, should be
made available to other eligible candidates for development and bringing into
production by 2011-12.”

Working-group- Deviation –

Page 14 of Chapter 8
Legislative and Policy Issues Working Group on Power for 11th Plan

It is suggested that the allocation of coal blocks should be in an orderly and


transparent manner. There is a need to enroll more specialist agencies to conduct
exploration of blocks and prepare GRs, so that production from blocks can start in a
timely manner.

Support of the State Govt. in providing required statutory clearances and


administrative support for law and order is essential for creating conducive
environment for captive mining.

8.3 NATIONAL ELECTRICITY POLICY - DEVIATIONS AND STATUS OF


IMPLEMENTATION

i. Availability and Security of Power

POLICY(Pg.2 Cl 2.0)

Policy aims at achieving the following objectives :

Access to Electricity - Available for all households in next five years


Availability of Power - Demand to be fully met by 2012. Energy and peaking
shortages to be overcome and adequate spinning reserve to be available.
Supply of Reliable and Quality Power of specified standards in an efficient manner
and at reasonable rates.
Per capita availability of electricity to be increased to over 1000 units by 2012.
Minimum lifeline consumption of 1 unit/household/day as a merit good by year 2012.
Financial Turnaround and Commercial Viability of Electricity Sector.
Protection of consumers’ interests.

Also (Pg 5, Cl 5.2.3)“In addition to enhancing the overall availability of Installed


Capacity to 85%, a spinning reserve of at least 5% at national level, would need to be
created to ensure grid security and quality and reliability of power supply”.

WORKING-GROUP – RECOMMENDATION

The Working-Group has considered these objectives of the National Electricity Policy
and the generation capacity requirements for 11TH & 12th Plans recommended by
the Working-Group take into account these objectives. The reserve of 5% has also
been included in the capacity requirement calculations. By maintenance and
modernization of power plants, the overall availability of already installed capacity
shall be improved to about 85%. The Working-Group also feels that a spinning
reserve is very much on higher side, since after formation of National Grid, only
tripping of the highest unit size must be the appropriate spinning reserve to be
catered to. This could be corrected in future after the system becomes more
commercially established.

Spinning reserve of around 1000 MW will be created at the end of 11th Five Year
Plan. In addition to this, there would be capacity available from non-conventional as

Page 15 of Chapter 8
Legislative and Policy Issues Working Group on Power for 11th Plan

well as surplus of captive power plants to meet total spinning reserve of 5% as


specified in National Electricity Policy.

ii. Suggested Areas/Location of Generation Capacity Addition & Transmission


System

POLICY (Pg 3, Cl 3.2)-


Policy stipulates “National Electricity Plan would be for a short-term framework of five
years while giving a 15 year perspective and would include :

Short term and long term demand forecast for different regions.
Suggested areas/locations for capacity additions in generation and transmission
keeping in view the economics of generation and transmission……….”.

WORKING-GROUP – IMPLEMENTATION

CEA has prepared National Electricity Plan considering demand as per 16th EPS and
the above parameters. The Working-Group has discussed and decided to include
generation expansion plan as contained in NEP. NEP is expected to be finalized
shortly. Other aspects like economics of generation, setting up of power plants at pit
head, load centre requirement, environment considerations taking into account the
allocation and capacity of the power plants have also been included in the
recommendations of the Working-Group.

(iii) National Electricity Plan

POLICY (Pg.3, Cl 3.1)

Policy mentions that “Plan prepared by CEA and approved by Central Government
can be used by perspective generating companies, transmission utilities and
transmission/distribution licensees as reference document.”

WORKING-GROUP – DEVIATION

The Working-Group opined that development of hydro power is a crucial issue


requiring a comprehensive development plan comprising of a balanced development
of Run of the River projects as well as Storage Schemes. Storage schemes assume
importance in view of their capability to provide peaking power. However, since
development of Storage schemes also involve a number of clearances etc., generally
developers find it more hassle free and attractive to develop storage sites also as
Run of the River schemes. The Working group recommends that hydro projects
developed, their siteing, capacity and type (whether storage or/RoR) shall be in
accordance with the National Electricity Plan. The projects to be developed by the
developers shall generally be from amongst the projects included in NEP.

Page 16 of Chapter 8
Legislative and Policy Issues Working Group on Power for 11th Plan

(iv) Monitoring and Adjustment in Capacity Addition Plans

POLICY (Pg.5, Cl 5.2.4)

Policy states that “The progress of implementation of capacity addition plans and
growth of demand would need to be constantly monitored and necessary
adjustments made from time to time. In creating new generation capacities,
appropriate technology may be considered keeping in view the likely widening of the
difference between peak demand and the base load.”

WORKING-GROUP – IMPLEMENTATION

Working-Group feels that there is need for extensive and intensified monitoring of
implementation of capacity addition plans and the growth of demand at regular
intervals. However, considerations like non-availability of gas have made the task of
choosing appropriate technology more difficult. Super critical technologies and
higher size units have been considered. Pump storage schemes in Northern region
and Eastern region are being implemented and also storage type hydro projects are
being planned where ever possible.

(V) Hydro Generation

POLICY (Pg.6, Cl 5.2.5)

Policy stipulates that “Maximum emphasis would be laid on the full development of
the feasible hydro potential in the country. The 50,000 MW hydro Institute has
already been launched and is being vigorously pursued ……………..”

WORKING-GROUP – DEVIATION

An analysis has been carried out to assess the projects which can materialize during
the 11th Plan. The Working group opines that even with best efforts, about 15,585
MW hydro projects are possible during 11th Plan.

(vi) Lignite based Plants

POLICY(Pg.6, Cl 5.2.14)

The Policy mentions that “significant Lignite resources in the country are located in
Tamil Nadu, Gujarat and Rajasthan and these should be increasingly utilized for
power----------------------.”

WORKING-GROUP - IMPLEMENTATION

The Working-Group agrees that lignite extraction technology needs to be improved.


There are plans to add a total capacity of 1375 MW based on lignite during 11TH
Plan.

Page 17 of Chapter 8
Legislative and Policy Issues Working Group on Power for 11th Plan

(vii)Gas based Plants(Pg.6, Cl 5.2.15)

POLICY

Policy mentions that “Use of gas as a fuel for power generation would depend upon
its availability at reasonable prices. Natural gas is being used in Gas
Turbine/Combined Cycle Gas Turbine (GT/CCGT) stations which currently accounts
for about 10% of total capacity”.

WORKING-GROUP - IMPLEMENTATION

The Working-Group states that due to non-availability of gas/LNG at a favorable price


not much gas based generation capacity is expected during 11th Plan. However, the
position could be reviewed as and when gas prices are favorable and the availability
of gas improves.

(viii)R&M Schemes

POLICY(Pg.7, Cl 5.2.22 & 5.2.23)

The Policy mentions that “If economic operation does not appear feasible through
R&M, then there may be no alternative but to closure of such plants as the last resort.
In case of plants with poor O&M record and persisting operational problems,
alternatives strategies including change of management may need to be considered
so as to improve the efficiency to acceptable levels of these power stations.

WORKING-GROUP - IMPLEMENTATION

Working-Group has recommended that R&M/LE schemes should only be considered


if they are economically viable. If cost analysis show that closure of the plant and
installation of a new unit is more economical, this alternative shall be considered.
Working-Group opines that in case the management of the Plant continuously has
poor O&M record, this shall be changed by way of joint ventures with central
undertakings like NTPC or State Sector undertakings like APGENCO.

8.4 MAJOR ISSUES AND RECOMMENDATIONS

Major Issues deliberated and recommendations of the Working Group are as follows:

¾ Capacity Building
¾ Promoting Open Access & Trading
¾ Controlling the Cost of Electricity
¾ Making Regulatory Process more effective
¾ Improving Distribution Segment
¾ Empowering Consumers
¾ Rural Electricity Supply
¾ Planning at State Level

Page 18 of Chapter 8
Legislative and Policy Issues Working Group on Power for 11th Plan

8.4.1 Capacity Building

The National Electricity Policy aims at overcoming energy and peaking shortages and
having 5% spinning reserves by year 2012. The Tariff Policy stipulates that all future
requirement of power is to be procured competitively by distribution licensees except
the expansion projects and public sector projects for which a five year window has
been envisaged after which all the generation and transmission projects would be
developed through competitive route. In accordance with the provisions of section 63
of the Act, the Central Government has already issued the competitive bidding
guidelines for:

¾ Procurement of power by distribution licensees and


¾ Procuring transmission services

To facilitate competitive procurement of power, the Central Government has already


issued standard bidding documents for development of power projects at a specific
given site and based on a particular fuel (Case-II of the bidding guidelines). The
competitive bidding guidelines also envisage procurement of power without
specifying any specific location or fuel (Case-I procurement). The Working Group is
of the view that situation is not yet ripe for procurement through Case-I route because
fuel, both coal and gas, are not yet freely available in the market. Therefore, all
efforts should be made to develop new capacity through developing new power
projects under Case-II procurement. This route is fully feasible and successful as
has been demonstrated by tariff based competitive bidding in Uttar Pradesh for
Anapara-C expansion project. The Central Government has also taken up major
initiative for developing Ultra Mega Power Projects through Case-II procurement.
Few coastal power stations based on imported coal can be set up based on the
option of competitive bids for net heat rate

Experience in the past has shown that projects had got delayed considerably
because of difficulties in tying-up various inputs like land, fuel, water and clearances
particularly environmental and forest clearance. Since we are envisaging private
sector participation at a large scale, the Working -Group recommends that Special
Purpose Vehicle(SPV) route would be necessary to develop new generation
capacities quickly. The SPV is responsible for arranging necessary inputs such as
land, fuel and water and also tying-up initial clearances and offering the project for
tariff based competitive bidding. Important areas for further improvement are
environmental/ forest clearance and geological report for coal blocks. In the area
of environmental clearance, the experience has been that the procedure takes a long
time. Therefore, there is a need to streamline and standardize the procedure to
shorten the time cycle for obtaining environmental/forest clearance with greater
emphasis on compliance with laid down standards and conditions imposed while
granting environmental clearance. Regarding the geological report of the coal blocks,
it is being felt that the blocks being made available for power project development
are not adequately explored which is leading to longer project preparation cycle and
uncertainties. Presently, CMPDI is the main agency for exploration of coal reserves.
The Working -Group recommends that the exploration capacity of the CMPDIL needs
to be augmented and it needs to be given more autonomy so that it can discharge its
responsibility in a fair and neutral manner. Number of agencies having authorization
to undertake exploration of coal blocks also needs to be increased.

Page 19 of Chapter 8
Legislative and Policy Issues Working Group on Power for 11th Plan

The Working - Group also recommends the possibility of making available power
projects sites quickly by scrapping those small sized old power generation units
which are operating at significantly higher heat rates. An appropriate cut-off of gross
station heat rate, say 3000 kilo calorie per unit, can be considered for identifying
inefficient old power plants of more than 25 years age and these sites could be
released for setting-up power plants of more efficient and large sized units depending
upon the scope of expansion available and with due cost benefit analysis. Coal
linkages of the old power plants should also be transferred to the new generating
units.

Regarding the promotion of non-conventional energy sources, the Tariff Policy


provides that minimum percentage for procurement of energy from such sources by a
licensee should be made applicable immediately for the tariffs to be determined by
the SERCs. The Policy further states that procurement of future requirement of
power from non-conventional energy sources shall be done as far as possible
through competitive bidding process u/s 63 of the Act among the suppliers offering
energy from same type of non-conventional sources. The Policy provides that in the
long-term, these technologies would need to compete with other sources in terms of
full costs. In view of these provisions in the Tariff Policy, a Sub Group recommends:

In the interest of larger competition aimed at consumer benefits, the procurement


from non-conventional energy sources should not be restricted to only within that
State but suppliers from outside State should also be allowed to compete.

Procurement from non conventional sources should invariably ,unless there are
compelling reasons, be done through the competitive bidding process as this would
add to transparency and lower procurement costs.
After assessing the stage of development of various non conventional energy
technologies, a definite timeframe should be laid down after which preferential tariff
for power generated from such sources would not be available. Such an
arrangement is already in place in Germany.

For encouraging captive generators to supply surplus power to grid, the


Implementation of recommendations of Forum of Regulators for rationalising various
charges such as parallel operation charge, minimum demand charge, start-up power
charge etc. on captive power generators could be a made a condition which may be
linked to Central assistance to the State power sector.

With a view to encourage Renovation & modernization (R&M) of old power plants
additional benefits after R&M are clearly identified and shared with consumers who
will bear the burden of servicing additional capital expenditure. It is required to be
seen that depreciation is allowed to the power producer and normal maintenance and
replacement should be funded from such depreciation amount. The Working Group
recommends that CERC could set up benchmarks for capital expenditure on R&M.

8.4.2 Promoting Open Access & Trading

The key features of the Electricity Act 2003 for promoting competition and providing
choice to the consumers are open access in transmission from outset and for phased

Page 20 of Chapter 8
Legislative and Policy Issues Working Group on Power for 11th Plan

introduction of open access in distribution. Most of the State Electricity Regulatory


Commissions (SERCs) have notified open access regulations and many of them
have also notified cross-subsidies surcharge.

Open access in distribution would become a realty only if certain pre-requisites are
met. These are availability of power beyond long-term PPAs, adequate transmission
facilities and an appropriate transmission tariff

To make available adequate power for open access consumers, there is a


requirement of having an enabling policy framework for merchant power plants which
could be in the size of up to 1000 MW. This size is considered appropriate from the
view point of greater possibility of financial closure without long-term PPAs and also
of making available transmission corridors for such merchant power plants. We
could target a merchant capacity of about 10,000 to 12,000 MW by the end of 11th
Five Year Plan. Working Group recommends that coal linkages should be made
freely available for power project developers to come forward to set up such
merchant power projects. In case captive coal blocks are considered to be given to
such merchant power plants, it should be a mandatory condition that such a power
project developer would not compete in competitive bidding for long-term PPA based
power procurement in order to avoid unequal competition (because only few
developers would have such coal blocks and others would not). For allocation of
both coal linkage or coal blocks for merchant power plants, an additional condition
should be that captive coal mining must begin within a period of three to four years
failing which the allocation should be cancelled.

For providing transmission corridors for such merchant power plants, the Working
Group recommends that adequate redundancy should be built at the stage of
transmission planning with the approval of Appropriate Regulatory Commission. The
National Electricity Policy already provides that prior agreement with the beneficiaries
would not be a pre-condition for network expansion and that CTU/STU should
undertake network expansion after identifying the requirements in consultation with
stakeholders and taking up the execution after due regulatory approvals. There is a
need to identify the major load centres who would be drawing power from such
merchant power plants and the required redundancies could be planned. The cost of
providing such redundancy should be absorbed in the transmission tariff by the
concerned region / zone and should be shared by all the beneficiaries.

A rationale transmission tariff framework is essential for facilitating optimum network


use and promoting power trade. Presently, the pricing principle applied to the
transmission systems have differentiated between the inter-regional, regional and
State level flows with such tariffs applied for each component of network used. This
has led to ‘pancaking’ of the network. Realizing this problem fully, the Tariff Policy
envisages a National Transmission Tariff Framework which is sensitive to distance
and direction and related to quantum of power offered.

Regarding the regulation of tariff of merchant power, the Electricity Act 2003 provides
regulation by SERC of cost of power purchased by the licensees under section 86 (1)
(b) of the Act. The Act further provides that in case of open access is availed by the
consumer; the price would be as mutually agreed by the consumer and the supplier.

Page 21 of Chapter 8
Legislative and Policy Issues Working Group on Power for 11th Plan

However, there is an urgent need for regulations for providing grid connectivity to the
merchant power plants.

8.4.3 Controlling cost of bulk power

Main efficiency gains leading to reduction in the cost of bulk power would come
through procurement of power through tariff based competitive bidding. In addition to
competitive procurement, cost of power could be reduced by reducing the fuel cost
as major part of the cost of bulk power is fuel cost. Captive coal mining has been
permitted for power sector The Working Group recommends that the coal blocks
should be offered on the basis of competitive bidding as part of the integrated coal
mine-cum-power project to achieve this objective.

Natural gas is another fuel which could be used for power production if it is available
at reasonable prices. Due to shortage of gas, the Working Group recommends that
the price of domestic natural gas and its allocation should be independently regulated
on a cost plus basis including reasonable return.

Incidence of various taxes on power sector projects and fuel used for power
generation needs to be rationalized. Therefore, Working Group recommends
following:

In line with crude oil and coal, natural gas and LNG may also be included in the
category of declared goods so that a central sales tax of 4% is levied on them and
exemption from any state sales tax is extended.

Lowering of Import duty on coal to 5% needs to be continued.

Exemption of import duties is available to power generation projects under the Mega
Power Policy. Similar dispensation should be made available to all important
transmission projects where imported components forms a large part of the project
cost.

It is likely that nuclear power stations would be segregated from other strategic
nuclear installations in future. In that case determination of tariff from nuclear power
stations needs to be done through regulatory mechanism in a transparent manner
adopting two part tariff structure and efficient operating norms.

It is understood that the cess being levied on water used by power stations for
cooling purposes is on gross volume basis i.e. no consideration is given for the
quantity of water actually consumed. There is a need to move to levy cess on the
basis of consumptive use of water. This would encourage the closed cooling system
which is a need of hour in view of the decreasing availability of water at power project
sites.

8.4.4 Making regulatory process more effective

The CERC and the SERCs are discharging a very important role in power sector
reforms by bringing in close scrutiny of the data furnished by the licensees and also
enhancing transparency in the whole process. It is therefore essential to attract

Page 22 of Chapter 8
Legislative and Policy Issues Working Group on Power for 11th Plan

regulatory personnel with required background and also to provide training to raise
regulatory capacity in terms of the required expertise and skill sets.

The Working Group recommends the following measures to make the regulatory
approach more effective:

Service conditions of the staff of the Regulatory Commissions as well as BEE i.e.
providing housing accommodation, medical facilities etc need to be made attractive.
State Governments should be asked to establish the Regulatory Commission Funds
at the earliest. This could be one of the follow up point while releasing central
assistance to the States.
There is a need to put in place a mechanism for periodical training/ reorientation for
the staff of the Regulatory Commission and for the newly appointed regulators. A
broad estimation has been done about the requirement of funds for this pupose. The
total cost per year for training 25 regulators and 50 staff is about Rs 40 lakhs. Total
expected expenditure for the next five years is about Rs 2 crores 21 lakhs. Details of
the above estimation are furnished in Appendix 8 .1. A corpus could be made
available to the Forum of Regulators for this purpose, income from which could be
used for these training programmes.

The FOR has been entrusted with number of responsibilities in the Tariff Policy with a
view to ensure consistency in the regulatory approach. For discharging this role, the
FOR would require consultancy for availing relevant expertise including international
experience on various matters. The Central Government should provide funds for this
purpose.

8.4.5 Improving Distribution Segment

It is well known that making distribution segment efficient and financially viable is the
key to the power sector reforms. This would not only improve the consumer services
including the power tariffs but also be critical for mobilization of investment in
generation and transmission segment.

The Working Group has deliberated indepth on various possible measures for
reducing distribution losses and improving quality of supply to the consumers. For
reducing AT&C losses, larger investments would be required for upgradation of
distribution networks and a special drive would be necessary for identifying high loss
areas and controlling commercial losses in such areas. Following is recommended by
the Working Group in this regard:

i. High loss making feeders need to be franchised by the distribution


companies. Towns having ATC losses higher than 35% need to be
franchised on input energy basis immediately whereas towns having
losses between 25-30% should be observed for improvement for six
months and if there is no improvement then these towns should also
be franchised.

ii. Through appropriate metering and energy audit, feeders incurring


high level of losses (may be more than 20% for urban feeders and
more than 35% for rural feeders, this would depend on the stage in

Page 23 of Chapter 8
Legislative and Policy Issues Working Group on Power for 11th Plan

which distribution reforms are in a particular state) should be


identified. Performance of the staff should then be assessed on the
basis of Key Performance Indicators(KPI) which would be primarily
loss reduction. AT&C loss reduction of 3% every year in next five
years should be targeted.

iii. The Tariff Policy emphasizes on the need for putting in place local
area based incentive/disincentive scheme for the staff linked to
distribution losses. This should be immediately implemented by the
SERCs.

iv. To realize the objective of Tariff Policy of supplying uninterruptible


electricity to those consumers who are ready to pay efficient cost, the
Working Group recommends that distribution tariff should move to
distribution margin model which is also provided in the Tariff Policy.
Such distribution margin could be based on loss reduction trajectory
in a MYT framework and the actual power purchase costs should be
paid by the consumers over and above the distribution margin.
Consumers of a particular area should be given option to collectively
choose either uninterruptible supply or otherwise and the tariff could
be determined accordingly.

v. The Working Group also recommends that setting up of peaking


power stations should be encouraged to overcome peaking shortages
as the additional power cost of supply from such a station could then
be passed on to the consumers who opt for uninterruptible supply.

vi. Correct metering and billing is crucial to reducing distribution losses


and also for ensuring that consumers pay according to their
consumption. CEA has notified metering regulations which mandate
that all new consumer meters would be of static type (electronic).
These meters measure the consumption correctly over a long period
of time. The Working Group recommends that use of electronic
meters and spot billing needs to be expanded rapidly and the State
should be emphasized to do so. Also, with the objective of promoting
more efficient use of electricity and also to provide another payment
option to consumers, use of pre-paid meters needs to be promoted.

vii. The Electricity Act gives discretion to the licensees to undertake


supply for a specified area within his area of supply through a
franchisee. The Working Group recommends that the Forum of
Regulators should develop a model agreement for distribution of
electricity by distribution licensee through a franchisee in urban areas
outlining the responsibilities and duties of various parties clearly.

8.4.6 Empowering Consumers

The Electricity Act has many important provisions for protecting consumer interests
and for redressal of their grievances. These are:

Page 24 of Chapter 8
Legislative and Policy Issues Working Group on Power for 11th Plan

¾ Setting up of Forums for redressal of consumer grievances


¾ Ombudsman to supervise and oversee the Forum
¾ Standards of performance for licensee with provision of penalty for non-
fulfillment.
¾ Advisory Committees to the Regulatory Commissions.

It is utmost important that consumers are involved fully in the regulatory process.
National Electricity Policy emphasizes on capacity building of consumer groups and
their effective representation before the Regulatory Commission. The Working Group
recommends that necessary financial assistance could be provided to consumer
groups having proven track record for facilitating their effective representation before
the Regulatory Commission. In addition to the financial assistance, the Central
Government should also arrange orientation programmes to educate these groups
about various provisions of the law and rules. Such scheme(s) should be
administered by the Department of Consumer Affairs.

8.4.7 Rural Electricity Supply

The Central Government is already implementing the ambitious nationwide


programme of RGGVY for providing access to electricity to all the households. Need
is felt to take up programmes to ensure supply of quality power at reasonable cost to
the rural areas. The Rural Electrification Policy notified by the Government under the
Electricity Act provides for a facilitative framework for encouraging local resources
based decentralized distributed generation systems. Most of the States have already
notified rural areas for the purpose of section 14 of the Act. Now there is a need to
promote such decentralized distributed generation system.

8.4.8 Planning at State Level

Prior to reorganization of SEBs, the planning for electricity sector at State level was
used to be done by the SEBs. Working Group opines that there is a need to
institutionalize a framework for indicative planning at State level post restructuring of
SEBs so that steps could be taken in time for necessary planning and execution of
projects. This becomes all the more important as generation projects are now to be
developed through competitive route for inviting power sector investment and
therefore initiative is to be taken at the State Government level. Similarly, advance
planning is required for augmenting the State level transmission network for catering
to new generation capacity and also for enabling open access. Therefore, the
Working Group recommends that State Government should set up a dedicated
planning cell for developing electricity plan at the State level including specific
projects which could be posed for investment to the power sector. Such a plan could
be on the lines of National Electricity Plan.

8.4.9 Agriculture Sector- Subsidies and Cross subsidies

Besides agriculture, domestic consumers are also provided subsidized tariff in most
the States. The Electricity Act 2003 and subsequent policy statements require
gradual elimination of cross subsidies. Section-61(G) of Electricity Act states that
appropriate commissioning shall be guided by the following while determining tariffs:

Page 25 of Chapter 8
Legislative and Policy Issues Working Group on Power for 11th Plan

“that the tariff progressively reflects the cost of supply of electricity and also, reduces
and eliminates cross subsidies within the period to be specified by the Appropriate
Commission”

Clause 8.3 of the National Tariff Policy (NTP) states,

“1. In accordance with the National Electricity Policy, consumers below poverty line
who consume below a specified level, say 30 units per month, may receive a special
support through cross subsidy. Tariffs for such designated group of consumers will
be at least 50% of the average cost of supply. This provision will be re-examined
after five years.

2. For achieving the objective that the tariff progressively reflects the cost of
electricity, the SERCs would notify roadmap within six months with a target that latest
by the end of year 2010-2011 tariffs are within + 20% of the average cost of supply.
The road map would also have intermediate milestones, based on the approach of a
gradual reduction in cross subsidy.”

Most of the SERCs are yet to specify the trajectory for reduction of cross subsidies in
accordance with the provisions of NTP. Given the fact that the prevailing agricultural
tariff are significantly lower than the average cost of supply tariffs towards cost of
supply will lead to steep upward movement of bringing tariffs for the agricultural and
residential consumer categories which is bound to be resisted by the affected groups.

National Electricity Policy and tariff policy provides for creation of life line category for
consumers below poverty line including those consuming less than 30 units per
month. These categories will also face steep increase in tariff as the present level of
subsidy is far below the average cost of supply. There will also be practical
difficulties in administering the provision. In these circumstances, it may not be
feasible to eliminate cross subsidies completely in the near future, though it can be
gradually reduced over time.
Some of the steps that can be taken to ensure that the agricultural tariffs are
reflective of the costs incurred and appropriate tariff signals are given to the
consumers, are:

• Energy audits based on scientific sampling methods, to assess electricity


consumption for agriculture across regions, crops, ground water level, etc.
• Higher tariffs for higher capacity pumpsets
• Tariffs linked to acreage under cultivation
• Tariffs linked to cost-to-serve, rather than average cost of supply or voltage
level cost of supply.

Clause 8.3 of the NTP states,

“3. While fixing tariff for agricultural use, the imperatives of the need of using ground
water resources in a sustainable manner would also need to be kept in mind in
addition to the average cost of supply. Tariff for agricultural use may be set at
different levels for different parts of a state depending of the condition of the ground
water table to prevent excessive depletion of ground water. Section 62 (3) of the Act
provides that geographical position of any area could be one of the criteria for tariff

Page 26 of Chapter 8
Legislative and Policy Issues Working Group on Power for 11th Plan

differentiation. A higher level of subsidy could be considered to support poorer


farmers of the region where adverse ground water table condition requires larger
quantity of electricity for irrigation purposes subject to suitable restrictions to ensure
maintenance of ground water levels and sustainable ground water usage.”

Alternative mechanism for cross-subsidies is provision of subsidy by the State


Governments which intend to provide supply of power to certain categories at less
than the prevailing average cost of supply. If cross-subsidy has to be reduced and
no tariff increase is planned for the subsidized categories, the State Governments will
have to bear the financial burden by providing subsidy to the utilities. Since the gap
between average cost of supply and tariffs for agricultural consumer is large the
burden is bound to be significant on the State Governments which are already
providing capital subsidy in many states. The Electricity Act provides that State
Governments should provide such subsidies in advance to the utilities.

Section 65 of the EA 2003 states,

“If the State Government requires the grant of any subsidy to any consumer or class
of consumers in the tariff determined by the State Commission under section 62, the
State Government shall, notwithstanding any direction which may be given under
section 108, pay, in advance in the manner as may be specified by the State
Commission, the amount to compensate the person affected by the grant of subsidy
in the manner the State Commission may direct, as a condition for the licensee or
any other person concerned to implement the subsidy provided for by the State
Government.”

Clause 5.5.4 of the National Electricity Policy (NEP) notified in February 2005, states,

“The State Governments may give advance subsidy to the extent they consider
appropriate in terms of section 65 of the Act in which case necessary budget
provision would be required to be made in advance so that the utility does not suffer
financial problems that may affect its operations. Efforts would be made to ensure
that the subsidies reach the targeted beneficiaries in the most transparent and
efficient way.”

Clause 8.2.1 (3) of the National Tariff Policy (NTP) notified in January 2006 states,

“Section 65 of the Act provides.. To ensure implementation of the provision of the


law, the State Commission should determine the tariff initially, without considering the
subsidy commitment by the Sate Government and subsidized tariff shall be arrived at
thereafter considering the subsidy by the State Government for the respective
categories of consumers.”
Clause 8.3 of the NTP states,

“The State Governments can give subsidy to the extent they consider appropriate as
per the provisions of section 65 of the Act. Direct subsidy is a better way to support
the poorer categories of consumers than the mechanism of cross-subsidizing the
tariff across the board. Subsidies should be targeted effectively and in transparent
manner. As a substitute of cross-subsidies, the State Government has the option of

Page 27 of Chapter 8
Legislative and Policy Issues Working Group on Power for 11th Plan

raising resources through mechanism of electricity duty and giving direct subsides to
only needy consumers. This is a better way of targeting subsidies effectively.”

Considering the stretched finances of most State Governments, the provision of this
subsidy affects investments and expenditure in other areas. The huge losses
incurred by utilities due to various technical and commercial reasons is aggravating
the financial position of the utilities making them unviable and force them to depend
on the State Government for support. To withstand this financial burden, State
Governments will have to look for additional revenue sources. Direct subsidy will
eliminate various issues associated with cross subsidy as the burden of subsidy
shifts to general tax payers in the State.

8.5 SUMMARY OF RECOMMENDATIONS

1. Situation is not ripe for procurement through Case-I route since both coal and
gas are not yet freely available in the market. All efforts should be made to
develop new capacity under Case-II procurement.

2. SPV is necessary to develop new generation capacities quickly.

3. There is need to streamline and standardize the procedure to shorten time


cycle for obtaining environmental/forest clearance with greater emphasis on
compliance with laid down standards and conditions.

4. Exploration capacity of CMPDIL may be augmented and also it may be given


more autonomy so that it can discharge its responsibility in fair and neutral
manner. Number of agencies having authorization to undertake exploration of
coal blocks should be increased.

5. Coal blocks to be used for captive coal mining by power projects should be
explored fully at the earliest and GRs should be readily made available to
power project developers on actual cost basis.

6. Appropriate cut-off of gross station heat rate, say 3000 kilo calorie per unit,
can be considered for identifying inefficient old power plants of more than 25
years age and the sites could be released for setting-up plants of more
efficient and large sized units depending on the scope of expansion available
and with due cost benefit analysis. Coal linkages of the old power plants
should be transferred to new generating units.

7. Till the long-term coal supply contracts emerge in international coal markets,
the option of competitive bids for net heat rate may be explored for imported
coal based stations.

8. In the interests of larger competition aimed at consumer benefits, procurement


from non-conventional energy sources should not be restricted to within the
State but suppliers from outside State should also be allowed to compete.

Page 28 of Chapter 8
Legislative and Policy Issues Working Group on Power for 11th Plan

9. Procurement from non conventional sources should, unless there are


compelling reasons, be done through competitive bidding process as this
would add to transparency and lower procurement costs.

10. After assessing the stage of development of various non conventional energy
technologies, definite timeframe should be laid down for doing away with
preferential tariff for power generated from such sources.

11. Tariff Policy advises States to rationalize taxes and duties on captive power
consumption. This may be reviewed periodically with States and made a
condition for Central assistance to State power sector.

12. In competitive procurement of power, bidding by CPSUs should be ensured in


initial few projects to encourage competition.

13. CERC could set up benchmarks for capital expenditure to facilitate


accelerated R&M of old power plants.

14. To make available adequate power for open access consumers, there is need
for enabling policy framework for merchant power plants. Size of MPPs could
be up to 1000 MW which may be appropriate considering greater possibility of
financial closure without long-term PPAs for comparatively smaller sized
projects and also of making available transmission corridors for such MPPs.
We could target MPP capacity of about 10,000 to 12,000 MW by end of 11th
Plan. Such merchant capacity would be without the basis of long term PPAs.

15. Coal linkages should be freely available for power project developers who
come forward to set up such MPPs. In case captive coal blocks are given to
MPPs, there should be a mandatory condition that such the project developer
would not compete in competitive bidding for long-term PPA based power
procurement in order to avoid unequal competition since only few developers
would have such coal blocks. For allocation of linkage or coal blocks for
MPPs, an additional condition should be that captive mining must begin within
a period of 3 to 4 years failing which the allocation should be cancelled.

16. For providing transmission corridors for such MPPs, adequate redundancy
should be built at the stage of transmission planning. Presently, also there is a
redundancy of about 20-25% in the transmission planning. There is need to
identify the major load centres who would draw power from such MPP. These
load centres would be most likely situated in northern and western region
where many States are deficit in power supply. Therefore, the required
redundancies could be planned from the likely location of the MPP (which
would be in eastern region) to such load centres. The cost of providing such
redundancy should be absorbed in the transmission tariff by the concerned
beneficiaries. This would be in the long-term interests of consumers who will
gain from efficiency arising out of competition among the generators.

17. Tariff Policy envisages a National Transmission Tariff Framework sensitive to


distance and direction and related to quantum of power offered. CERC is in
the process of developing such a Framework which needs to be done

Page 29 of Chapter 8
Legislative and Policy Issues Working Group on Power for 11th Plan

expedited. This would be a necessary pre-requisite for promoting open access


and power trading.

18. There is urgent need for regulations for providing grid connectivity to MPPs.
The National Electricity Policy already provides that prior agreements would
not be a pre-condition for network expansion and the transmission utilities
should undertake network expansion after identifying the requirements in
consonance with the National Electricity Plan and in consultation with the
stakeholder, and taking up the execution after due regulatory approvals.

19. The reduction in cost of production of coal on account of higher efficiency in


captive coal mining should be passed on to the consumers through reduced
cost of bulk power. The coal blocks should be offered on the basis of
competitive bidding as part of the integrated coal mine-cum-power project to
achieve this objective. Any other method of allocating coal blocks for power
projects is not likely to pass on the efficiencies of captive coal mining to the
consumers.

20. As long as there is shortage of natural gas and the two major users of gas
fertilizer and power work in a regulated cost plus environment, price of
domestic gas and its allocation should be independently regulated on cost
plus basis including reasonable returns.

21. Like crude oil and coal, natural gas and LNG may also be included in the
category of declared goods so that central sales tax of 4% is levied on them
and exemption from any state sales tax is extended.

22. Import duty on coal has been lowered to 5%. This position needs to be
continued as we would be depending on imported coal for generation.

23. Exemption of import duties available to generation projects under Mega Policy
should be available to all important transmission projects where imported
components form large part of the project cost.

24. Nuclear power stations are likely to be segregated from other strategic nuclear
installations in future. In that case, tariff determination from nuclear power
stations should be done through regulatory mechanism in a transparent
manner adopting two part tariff structure and efficient operating norms.

25. There is a need to levy cess on the basis of consumptive use of water. This
would encourage closed cooling system which is the need of the hour
considering decreasing availability of water at project sites.

26. Service conditions of staff of the Regulatory Commissions and BEE should be
made attractive. Such staff should be eligible for housing accommodation,
medical facilities etc. on the lines of Government employees.

27. State Governments should be asked to establish the Regulatory Commission


Funds at the earliest. This could be one of the follow up points while releasing
central assistance to the States.

Page 30 of Chapter 8
Legislative and Policy Issues Working Group on Power for 11th Plan

28. There is a need to put in place a mechanism for periodical training/


reorientation for staff of the Commissions and for newly appointed regulators.
A corpus could be made available to the Forum of Regulators (FOR) for this
purpose income from which could be used for the training programmes. The
training programme and the training institutions should be settled by FOR after
taking into account guidelines issued by the Central Government in this
regard.

29. FOR has been entrusted with number of responsibilities in the Tariff Policy
with a view to ensure consistency in the regulatory approach. For discharging
this role, the FOR would require consultancy for availing relevant expertise
including international experience on various matters. Central Government
should provide funds for this purpose.

30. FOR should also compile periodically various progressive orders of the
SERCs for sharing the best practices. The compilation may also include
important judgments of the Appellate Tribunal for Electricity.

31. To bring in appropriate accountability of the regulatory process, proposed


regulations of the Regulatory Commissions should be examined indepth at
draft stage itself. Further, there is a need for scrutinizing the regulations for
ensuring consistency with the letter and spirit of the law before they are laid in
the Parliament/ State Assembly. This is important since regulations, once
published in the gazette, become sub-ordinate legislation.

32. FOR should also undertake periodical review of implementation of the National
Electricity Policy and Tariff Policy since the law requires the Commissions to
be guided by these policies.

33. High loss making feeders may be franchised by distribution companies. Towns
having ATC losses higher than 35% may be franchised on input energy basis
immediately. Towns having losses between 25-30% should be observed for
improvement for 6 months and if there is no improvement, these towns should
also be franchised.

34. Through appropriate metering and energy audit, feeders incurring high level of
losses (may be more than 20% for urban feeders and more than 35% for rural
feeders, this would depend on the stage in which distribution reforms are in a
particular state) should be identified. Performance of the staff should be then
assessed on the basis of Key Performance Indicators(KPI) which would be
primarily loss reduction. ATC loss reduction of 3% every year in next five years
should be targeted. The Tariff Policy emphasizes on the need of putting in
place local area based incentive/disincentive scheme for the staff linked to
distribution losses. This should be immediately implemented by the SERCs.

35. The robust legal framework contained in the Act for control of theft is being
further strengthened. Annual conferences of power utilities should be
organized at national level for highlighting success stories and achievement
made in different States in controlling theft.

Page 31 of Chapter 8
Legislative and Policy Issues Working Group on Power for 11th Plan

36. To enlist public support for rapid reduction of commercial losses, the list of
high losses feeders should be publicized periodically.

37. To realize the objective of Tariff Policy of supplying uninterruptible electricity to


those consumers who are ready to pay efficient cost, the distribution tariff
should move to distribution margin model which is also provided in the Tariff
Policy. Such distribution margin could be based on loss reduction trajectory in
a MYT framework and the actual power purchase costs should be paid by the
consumers over and above the distribution margin. Consumers of a particular
area should be given option to collectively choose either uninterruptible supply
or otherwise and the tariff could be determined accordingly.

38. Setting up of peaking power stations should be encouraged to overcome


peaking shortages as the additional power costs of supply from such a station
could be then passed on to the consumers who opt for uninterruptible supply.

39. Use of electronic meters and spot billing should be expanded rapidly and State
should be emphasized upon to do so.

40. FOR should develop a model agreement for distribution of electricity by


distribution licensee through a franchisee in urban areas outlining the
responsibilities and duties of various parties clearly.

41. There have been some experimental efforts, with good success, for
outsourcing distribution of electricity for an identified feeder by the licensee to
a private entrepreneur selected competitively. This model needs to be
supported fully and replicated in high loss areas.

42. Necessary financial assistance may be provided to consumer groups having


proven track record for facilitating effective representation before the
Regulatory Commission. In addition, Central Government should also arrange
orientation programmes to educate these groups about various provisions of
the law and rules. Such scheme(s) should be administered by the Department
of Consumer Affairs.

43. The Rural Policy provides that standalone systems of upto one MW would
have automatic approval for

a. Land use change for area as per norms

b. Pollution clearance if technology is proven within laid down norms and

c. Safety clearance on the basis of self certification.

These policy measures need to be implemented by the concerned authorities


at the earliest.

44. Schemes for separation of agricultural feeders in rural areas need to be


promoted. Agricultural consumers could be supplied electricity as per seasonal
demand for agricultural purpose and the tariff could be fixed taking into view
off-peak pricing and uninterruptible supply.

Page 32 of Chapter 8
Legislative and Policy Issues Working Group on Power for 11th Plan

45. Schemes for transferring subsidies directly to consumers may be encouraged.

46. State Government should set up a dedicated planning cell for developing
electricity plan at the State level including specific projects which could be
posed for investment to the power sector. Such a plan could be on the lines of
National Electricity Plan.

47. With the objective of promoting more efficient use of electricity and also to
provide another payment option to the consumers, use of pre-paid meters
needs to be promoted.

48. In order to assess the progress made in achieving higher energy efficiency,
suitable mechanism should be put in place indicating the clear cut
methodology for computing various parameters in this regard.

**********

Page 33 of Chapter 8
Legislative and Policy Issues Working Group on Power for 11th Plan

Appendix 8.1

FUND REQUIREMENT FOR TRAINING OF ELECTRICITY


REGULATORS AND STAFF

TRAINING FOR STAFF OF ERCS

• There are 25 SERCs including CERC


• It is proposed to give training to 2 staff per ERC
• Total staff to be trained in a year is 50
• 2 training programme in a year each batch with 25 persons
• Duration of Training Programme : 9 days

Details of Expenditure

Expenditure Item Projected Expenditure (Rs.)


Professional Cost 4,31,750
Communication and local conveyance 20,000
Logistics (including accommodation and 7,97,500
meals)
Sub-Total 12,49,250
Overheads 12,495
Service tax @12.24% 1,66,199
Grand Total 15,42,374 (Approx. Rs.16
lakhs)
Cost for one Training Programme (25 Rs.16 lakhs
persons per batch)
Cost for two Training Programme (25 Rs.32 lakhs
persons per batch)

TRAINING FOR REGULATORS OF ERCS

• 25 Regulators to be trained in a year


• One training programme in a year each batch with 25 Regulators
• Duration of training programme: 3 days

Page 34 of Chapter 8
Legislative and Policy Issues Working Group on Power for 11th Plan

Details of Expenditure

Expenditure Item Projected Expenditure (Rs.)


Professional Cost 259200
Communication and local conveyance 1000
Logistics (including accommodation and 338000
meals)
Sub-Total 607200
Overheads 60720
Service tax @12.24% 81753
Grand Total 749673 (Approx. Rs.8 lakhs)
Cost for one Training Programme (25 Rs.8 lakhs
persons per batch)

Total cost per year for training 25 Regulators and 50 Staff : Rs.32 lakhs + Rs.8 lakhs
= Rs.40 lakhs

Total expected expenditure for the next five years:

Year Expected Expenditure


(Including escalation @
5%)
Rs.
2006-07 40 lakhs
2007-08 42 lakhs
2208-09 44.1 lakhs
2209-10 46.3 lakhs
2010-11 48.6 lakhs
Total Rs.2 crores 21 lakhs

Page 35 of Chapter 8
Legislative and Policy Issues Working Group on Power for 11th Plan

Appendix 8.2

REF: PEG/2006/296 Dated: 30h Dec 2006

To,
Shri R. V. Shahi,
Chairman Working Group on Power,
Ministry of Power

Subject: Comments / suggestions on the draft report of the Working Group on Power

Sir,

On behalf of Prayas Energy Group, I wish to thank you for the opportunity to comment on
the Draft report of the Working Group. As per your suggestion I have attempted to keep it
short.
There were limitations in our inputs earlier arising from (1) some of the sub-groups (that
we were involved in, could not have meeting to discuss the draft report, (2) only after
reading all reports, one could develop an holistic picture, (3) we have limited support for
such work. In light of this, I request you to allow little longer comments.

Larger Comments
- As elaborated in Box at the end, the estimate of MW and Rs Crore investment is on an
optimistic side. This has a material impact while recommending the policies necessary to
raise the required funds. Hence, these estimates should be reviewed.
- There is a large increase in kind and quantity of central government subsidy schemes
(RGGVY, DDG, 1 MW stand along systems etc.). A well-balanced committee should be
established to transparently monitor the targets and operation of these schemes and a
separate committee to find ways in which performance of REC / PFC can be further
improved to meet the sector objectives.
- Draft report suggests several different roles for REC. Considering the potential conflict of
interest among these roles we strongly suggest institutional separation of roles.
- Success SPV route adopted for Ultra-mega should be further enhanced. A mechanism
should be created to develop projects for Case-2 Tariff bidding. These projects then
could be offered to Discoms for competitive bidding.
- Consumer funding should be done at multi-level (state and national) which is well
aligned with activity & agency work.
- A committee should be constituted to look into the options for meeting intermediate and
peak load demand in the most economic manner. This could help remove the critical
planning gap during Advance Actions for the 12th plan.
- Tariff impact of the proposed schemes should be included in the report.
The remaining comments are given chapter-wise.

Demand-Supply:
- The capital cost of projects over the last 10 years should be plotted as a scatter diagram
(Rs/MW and year), with each project shown as one point. Two separate graphs for coal
and CCGT could be drawn.
- It appears that the energy demand forecast does not consider generation by addition of
CPP (estimated addition of 12,000 MW), NCES (~10,000 MW), or co-generation plants.

Page 36 of Chapter 8
Legislative and Policy Issues Working Group on Power for 11th Plan

It is possible that these would generate 85,000 MU/yr. In which case, it would be equal
to a third of the incremental energy demand (on the grid) during the XIth plan. The
expected increase in MU generation (due to additional CPP) should be clearly specified
and cross-checked with total industrial demand (met from grid and CPP). Generation
from NCES should be considered in the grid.
- The 210 / 250 MW units have large variation in heat rates. The bottom 10% units with
highest heat rates and the top 5 units with least heat rate should be audited to draw
lessons.
- CERC tariff should provide incentive for Heat rate improvement, based on report of
energy audit & heat rate verification for all power plants. This report should be put up on
Website by all utilities. This could be a condition for R&M assistance.

Transmission:
- It may be useful to represent the addition of inter-regional transmission capacities, major
Transmission lines on national map.
- The capital cost of Rs 140,000 Cr seems on a high side for the projected increased in
grid capacity as well as the incremental energy sales. Annual fixed charges of
Transmission investment (@15% of 140,000 Cr) translates to a wheeling cost of 90
Paisa/unit – based on incremental sales of 290,000 MU. This is quite large.

Distribution:
- Role of REC: It is proposed that (1) REC be nodal agency for several programs – like
DDG (subsidy of Rs 20,000 Cr), RGGVY (Rs 40,000 Cr), APDRP (Rs 40,000 Cr,
including pump energization). (2) REC would fund the equipment manufacturers – for
expansion and modernisation, (3) REC would set up venture capital fund for equipment
manufacturers, (4) REC would set standards for equipment manufacturers. The role of
REC has undergone a major change with RGGVY and more radical changes are
proposed. We suggest that (a) In light of likely conflict of interest among the multiple
roles proposed for REC – such a move is not desirable. REC may have invested in some
equipment manufacturer either through venture capital fund or simply given it a loan.
REC would be setting equipment standards and REC would also be a major buyer of the
distribution equipment (under RGGVY, DDG, etc.). The potential conflict of interest
between different roles - facilitator, nodal agency for implementation, financing agency,
and regulator (setting standards) may be large and these roles should NOT be integrated
in one institution (b) performance of REC as nodal / implementation agency for the large
subsidized schemes (e.g. RGGVY) should be reviewed to identify areas that need
strengthening. A committee could be constituted for this.
- REC / PFC giving reform loans: The conditions to be imposed by REC / PFC should be
approved in writing by MoP. The states may accept a shorter list of these conditions as
mutually approved by REC / PFC and the recipient.
- Role of REC/ PRF: The Planning Commission should appoint an oversight committee to
transparently evaluate possible ways in which these agencies can better meet their and
power sector objectives.
- RGGVY: (1) The revised cost estimation of RGGVY should be mentioned along with its
basis (2) Scope of RGGVY - electricity connection to all houses by year 2012 – should be
reaffirmed in accordance with the government’s mandate.
- DDG – (a) Business model of DDG is not yet fully clear. A group should be formed to
monitor these projects. (b) The cost effectiveness of DDG would come from utilizing them
in say co-generation mode or linked to waste heat applications – a 5 MW size is high for
this purpose. (c) Title of section 3.13 is “Cost to Serve/ Delivered Cost”. It should be

Page 37 of Chapter 8
Legislative and Policy Issues Working Group on Power for 11th Plan

modified to suite content. The Tariff policy does not advocate the “Cost to Serve” as basis
for Tariff. (d) Consumers are not listed in the description of “Role of Stakeholders”. At
least in initial experimental 100 cases there should be annual survey of consumer
experience. The cost of such survey can be minimized and accuracy enhanced by giving
a Response Form to all consumers as bill-insert (to be mailed to the independent survey
agency).
- Water-electricity nexus: The suggestion from Prayas was to form a ‘Task force’ on this
issue to create wider awareness of negative implications of free-power and ground water
depletion. The members of task force should come from agriculture, ground water,
irrigation and power sectors.

DSM, Energy Efficiency and BEE:


- MoP has taken a broader mandate through BEE, to improve efficiency of not just power
consumption but also oil, gas and coal consumption. MoP has responsibility to fulfill this
mandate.
- The BEE proposed budget of 650 Cr is less than 0.1% of the overall budget of the
sector. This should be given as grant in aid (linked to activity plan)
- The BEE should be made accountable for its performance, while making it autonomous.
A steering group of six / seven persons should be appointed for a period of 3 or 5 years,
for this task. The steering group should have mandate of approving BEE schemes and
taking an annual review of its performance. Members of steering group should be on
contract from MoP.
- There is an urgent need to encourage technical institutions / engineering colleges to
carry out R&D related to energy efficiency. Improved linkage of industry need-funding-
manpower resources is necessary.
- Need for improved appliance standards should be explained with an example such as
one given here – “We are adding about 100 million CFLs in the system each year – this
number is doubling in less than 3 years. With such a large addition of CFLs,
improvement in their quality is urgent. Raising the Power Factor of CFLs from 50% to
85% by adding passive PF correction in the electronic ballast would reduce 10,000 MVA
demand in the XI th plan period. This will reduce the need for addition in Distribution
Transformers capacity by nearly 10% of planned addition.”

R&D:
- Following topics should be added to the focus areas for R&D:
o Assessment of needs of the 10 crore very poor consumers (including to be
consumes)
o Soft technologies like DSM, improved use of IT for accountability of utilities,
better forecasting models, and power plant dispatch planning.
o On-line detection of faults to improve plant availability
- Clear process for evaluation / effectiveness of public money spent on R&D should be
initiated
- The plan for spending 1% of RGGVY money reserved for evaluation, training and R&D
should be developed by MoP through an open and consultative process.

Key inputs
- Land (forest and non-forest land) and water requirement for power plants are critical
inputs for the sector. The chapter should estimate total land requirements (by projects)
and the persons likely to be displaced.

Page 38 of Chapter 8
Legislative and Policy Issues Working Group on Power for 11th Plan

- Coal requirement: It has been worked out assuming base-load PLF (~ 85% for new
power plants). This would generate about 300,000 MU, but as seen in Box –1, the
energy demand forecast indicates additional energy requirement of only 290,000 MU.
The coal requirement may be reasonable if it is clarified that it also includes the
requirement of 12,000 MW of CPP capacity addition. Table 9.7 would need
corresponding modification.

Finance:
- Capitalization of dividend in construction period: Rather than a piecemeal adjustment,
the treatment given to equity should be comprehensively reconsidered by MoP. In some
countries equity is returned (along with loan) to reduce the tariff in later years. Such
aspects can be integrated in the review.
- Estimation of MU, MW and Rs Cr: On the conservative side the MU and MW addition
numbers can be considered on a higher side. The same when done about finance can
have negative impacts (See Box 1 at the end for details). If the fund requirement is not
Rs 9.67 Trillion but say Rs 6 Trillion, then required financing adjustments may be much
different than what is proposed.
- Banking norms: If relaxation of lending norms is to be considered, at the minimum there
should be complete transparency in terms of which banks are using the relaxed norms
for which corporate groups and for which specific projects.

Policy:
- E-Act: Ministry of Power should do a review of E Act when five years are complete. The
review should be broad based to be able to remove the difficulties being faced, such as
the legal precedence being created by ATE and court orders that are contrary to the
intent of the Act.
- Coal pricing and allocation of mines:
o It is welcome idea to give mines to integrated ‘mine-power project’ that intends to
sell power to utilities. This will pass the benefit of mining efficiency to small
consumers – that are going to face a large tariff hike.
o The coal pricing should be directly linked with calorific value (on delivered basis)
rather than grades of coal.
- Merchant Plants:
The draft report recommends that merchant plants be encouraged through measures
such as giving coal blocks, so as to create the liquidity necessary to make markets
function. We think this is not a good idea for large-scale promotion, for the following
reasons:
o Experience of merchant plants in other countries shows problems. For example,
the merchant plant industry in USA has been almost decimated. Initial optimism
about the industry led to many projects being announced. However, as
conditions in the market changed and investors began to understand the real
risks in building merchant plants and trading electricity, the share prices of these
companies plummeted. Many of the proposed projects were either postponed
indefinitely or cancelled.
o On a priority basis, the coalmines should be allocated to projects that will supply
electricity to utilities under a long-term contract. If they are allocated to merchant
plants, then the benefits go to the plant owner.
o Utilities (hence small consumers) should not be burdened for creating
redundancies in Transmission system for facilitating the merchant plants. Benefit
and cost sharing under this would be unfair.

Page 39 of Chapter 8
Legislative and Policy Issues Working Group on Power for 11th Plan

o If inspite of this experience, the government decides to give coal blocks to


merchant plant developers then it should lay down three conditions (1) if the
plants does not come up or stops operation, then the coal blocks must be
returned and (2) the coal block should be given to the developer through a price
bid, (3) such a promotion should be limited to only a handful demonstration
projects by PSUs.
- SERCs: It should be clarified that fundamental duties of SERCs include monitoring the
demand-supply situation and ensure that utilities meet the power demand.
- Separation of Agricultural consumption: Example of “Akshay Prakash’ in Maharashtra is
a noteworthy example, where this is achieved, in addition to theft reduction – at not cost
to the utility. This should be included in the Box in Policy chapter.
- Consumer Funding: It is much safer to have multiple mechanisms for consumer funding.
It is only natural to have different mechanism for state level education, national training,
and intervention and policy analysis support. [Refer to the note submitted by Prayas and
Dr Navroz Dubash.]
- Real time meter Reading: Remote reading of all 33/11 KV (or 66/11 KV) substations
should be the first priority. This will give exact amount of load shedding and help
establish 11 KV energy audits. Remote reading of DTs should not be mixed with this, as
this may increase the work burden exponentially. Remote reading of all consumers
above 50 KW is utility’s commercial priority but remote reading at substation is a priority
for public accountability of utilities.
- Captive plants: The captive plants should pay wheeling charges and transmission losses
by voltage level (reference saying that ‘captive plants should pay only the technical
losses in Transmission system’ should be removed).
- Public Sector improvement: In association with some state distribution utilities the MoP
should test the results of ‘incentive-disincentive’ scheme for employees and managers of
utility. This could be implemented as a part of APDRP scheme.

Box 1: MU, MW, and Rs Cr investment linkage


MU-MW linkage:
Chapter 1 states the demand forecast on the basis of expected increase in sales by
290,000 MU (on the grid - Ex bus) and plans addition of 71,000 MW. The implicit net-PLF of this
71,000 MW capacity would be below 50% (for 290,000 MU sales). This is unlikely. Following
factors need to be looked into:
- The MU generation of 10,000 MW of NCES (nearly 26,000 MU @ 30% PLF) should be
accounted for in grid supply in chapter 1.
- Spinning reserve should be considered as ‘capacity of the two largest units in the region’.

Rs. Crore investment estimate


The total investment of Rs 967,000 Crore projected in the XI th plan would result in a
fixed cost of Rs 175,000 Cr p.a. (fixed cost @ 18% p.a.) Dividing this by the incremental sales of
290,000 MU implies a capacity charge of Rs 6/unit. The fuel cost would be additional. This is
an anomaly. And the financing need should be pegged at a lower level.

Miscellaneous Issues

Distribution
- Lack of accountability of utilities: Take the case of Sec 3.6.2 in the Chapter on
Distribution – where Maharashtra is said to have achieved 100% metering of 11 KV

Page 40 of Chapter 8
Legislative and Policy Issues Working Group on Power for 11th Plan

feeders. In fact MoP data shows that Maharashtra has achieved 100% metering of 11 KV
feeders several years ago. But MSEDCL submitted data to MERC is contradictory. In the
recent ARR submitted to MERC, MSEDCL indicates following:
o 11 KV feeders with meter – 80% (of 8500 feeders of MSEDCL)
o 11 KV feeders with reliably working meter – 68%
o Only 570 meters have data download facility – but the facility is not used.
This raises doubts about the validity of data submitted by utility to MoP and / or to the
SERC.
- HVDS, GIS and consumer indexing etc.: When some states have implemented the
scheme – a post-factor Cost:Benefit analysis should be the basis for recommendation by
Planning Commission. Simple articulation of claimed benefits is inadequate for
recommending such high cost schemes for all utilities.
- Experience of Reforms: Orissa is not really a success in terms of reduction in T&D loss. It
is better to remove that from the list (section 3.24)
- It would be useful to mention that utilities should be able to demonstrate that they are
meeting Standards of Performance Regulations of the regulatory commissions.
- Rs / employee: (a) It needs to be clarified that some utilities are concentrated urban
utilities while some are low-density rural utilities. (b) It would be good to clarify that it
excludes cost of contract labor and also franchisees. (c) The AP numbers should be
given for different Discoms – instead of one number for the state, (d) Year for which the
data is given should be indicated.

I wish to thank you once again for this opportunity and hope that you will give due
consideration to the points raised.

Thanking you,

(Girish Sant)
for Prayas Energy Group

CC: Dr Sethi (Planning Commission), Addn Sec (MoP), CEA.

Page 41 of Chapter 8
Financial Issues & Power Sector Financing Working Group on Power for 11th Plan

Chapter 10

FINANCIAL ISSUES AND POWER SECTOR FINANCING

10.0 The Tenth Plan outlay approved for the power sector was Rs. 2,70,276 crore
or 18.2% of the total public sector outlay of Rs.14,84,131 crore.

Table10. 1
Power Sector Outlay of 10th Plan
(Rs. crore)
Sector Generation including R&M T&D including RE etc Total
State 32,216 61,010 93,226
Central 150,373 26,677 177,050
Total 182,589 87,687 270,276

The detailed breakup of various State sector outlay for the 10th Plan is placed at
Appendix-10.1. The breakup of the Central sector financial resources of
Rs.1, 77,050 crore is as under and detailed breakup is placed at Appendix-10.2.

Table 10.2
Central Sector Financial Resources for 10th Plan
(Rs. crore)
INTERNAL AND EXTRA BUDGETARY RESOURCES GROSS BUDGETARY SUPPORT
I.R. BONDS DFI OTHERS IEBR EAB DBS GBS UOTLAY
MOP 14138 59546 11622 33093 118399 0 25000 25000 143399
NLC 2804 5204 0 0 8008 0 0 0 8008
DAE 2271 7536 0 0 9807 5654 10183 15837 25644
TOTAL 19212 72286 11622 33093 136214 5654 35183 40837 177050

Note: Outlay = (IEBR + GBS)

10.1 FINANCIAL PERFORMANCE OF POWER SECTOR DURING 10TH PLAN

The likely investment in the power sector is estimated as Rs. 1,83,166 crore
(67.77%) of the total outlay of Rs. 270,276 crore by the end of 10th Plan including the
investment by NLC and DAE. The State sector expenditure is likely to be Rs. 90,101
crore (96.65%) and the Central sector expenditure is likely to be Rs. 93,065 crore
(52.56%) of their respective outlays during 10th Plan. Details of the same are as
under:

Page 1 of Chapter 10
Financial Issues & Power Sector Financing Working Group on Power for 11th Plan

Table 10.3
th
10 PLAN BUDGET VS. ACHIEVEMENT

(All figures in current prices and in Rs. crore)


Year Central State Total
1 Tenth Plan approved 177,050 93,226 270,276
2 Actuals for the year:
2002-03 10,993 17,103 28,096
2003-04 14,327 17,837 32,164
2004-05 17,040 17,035 34,075
2005-06 20,734 17,406(RE) 38,140
Total 63,094 69,381 1,32,475
3 2006-07 (Estimated) 29,971 20,720 50,691
4 Likely investment during 93,065 90,101 1,83,166
10th Plan
5 % Utilisation 52.56% 96.65% 67.77%
Source: Planning Commission

The short fall in fund utilization in the Central sector outlay is on account of few main
reasons which are as under:

• During the first two years, there was a delay in according investment approval
for various projects such as Teesta Low Dam-III & IV, Sewa-II, Omkareshwar,
Subansari Lower, Parbati-III, Purulia PSP, Chamera HEP-III, Uri-II, Tripura
Gas etc.

• In case of NTPC, an outlay of about Rs. 3,000 crore was included as Gross
Budgetary support to be utilized if need be. However, it was decided to fund
the projects from its internal resources and gas projects like Kawas and
Gandhar could not takeoff;

¾ Average lead time for 500 MW unit was reduced from 49 months to 38
months e.g. Ramagundam STPS III and from 32 months to 28 months
for 210/250 MW e.g. Raichur TPS etc thus new benchmarks were set
without cost and time overruns.
¾ Further, capital cost of new projects and tariffs is lower than the
anticipated and Cost per MW do not escalate and remained around Rs
4 crore per MW in new coal fired thermal power Stations mainly due to
prevailing low interest regime and compressed cycle of execution of
projects under best effort scenario.

Thus, even with low utilization of funds (~53.7%) the physical targets achievement
during 10th Plan is likely to be between 75% to 80%.Region-wise expenditure likely
to be incurred during 10th Plan in Transmission Schemes in both State and Central
sector is as follows:

Page 2 of Chapter 10
Financial Issues & Power Sector Financing Working Group on Power for 11th Plan

Table 10.4
Regional expenditure incurred during 10th Plan in Transmission Schemes
(Rs. crore)
Name of the Transmission Works
Utility Actual Actual Actual Actual Estimated Total
2002-03 2003-04 2004-05 2005-06 2006-07 10th plan
State Sector
Northern 938 1,027 1,129 1,834 1,815 6,743
Region
Western 827 1,107 1,065 1,432 3,020 7,450
Region
Southern 994 1,205 1,097 1,356 1,693 6,346
Region
Eastern Region 995 1,004 1,264 1,785 2,337 7,385
N-E Region 50 56 120 125 238 590
State sector 3,804 4,399 4,675 6,532 9,103 28,513
Central Sector 2,671* 2,351* 3,218* 4,111* 4,849 17,200
Total all India 6,475 6,750 7,893 10,643 13,952 45,713

Source : CEA; * actual

10.1.1 Distribution

The extent of sub-transmission and Distribution systems at the beginning of 10th Plan
on all India basis was 57,69,739 ckm of lines and 1,76,026 MVA of distribution
transformer capacity. This has increased to 65,70,823 ckm of 33 kV, 11 kV and LT
lines and 2,36,070 MVA of Distribution capacity by March 31, 2005, which implies
an increase of 8,01,084 ckm of network and 60,044 MVA addition of Distribution
capacity in the first 4 years of the Plan. It is expected that the addition envisaged by
the Working Group on 10th Plan of 8,28,863 ckm of 33 kV, 11 kV and LT lines and
2,36,070 MVA of Distribution capacity would be surpassed.

10.1.2 Accelerated Power Development & Reforms Programme (APDRP)

The Govt. of India has launched the Accelerated Power Development & Reforms
Programme (APDRP) since FY’2002. It focuses on Upgradation/ improvement of
Sub-Transmission and Distribution networks in densely electrified zones in the urban
and industrial areas with an aim to reduce AT&C losses, enhance customer
satisfaction and improve commercial viability of DISCOMs/ State Electricity Boards.
It has following two components:

I. Investment component for strengthening and Upgradation of the sub-


transmission and distribution system (Outlay of Rs. 20,000 crore for 10th Five
Year Plan).
II. Incentive component to encourage/ motivate utilities to reduce cash losses
(Outlay of Rs. 20,000 crore for 10th Five Year Plan).

Page 3 of Chapter 10
Financial Issues & Power Sector Financing Working Group on Power for 11th Plan

Under investment component 583 projects were sanctioned with cost of Rs.19180.46
Crore against this Rs.6131.70 crores were released. The Counter-Part funds tied up
were Rs. 7044.34 Crore and funds drawn were Rs. 4087.04 Crore and Funds
utilized were Rs. 9518.13 Crore.

10.1.3 Rajiv Gandhi Grameen Vidhyutikaran Yojana (RGGVY)

The RGGVY was launched in April, 2005 to provide access to electricity to all un-
electrified rural households by 2009. The scheme envisages electrification of over
1,00,000 villages and provide access to electricity to 7.8 crore rural household
through creation of (i) Rural Electricity Distribution Backbone (REDB) with at least
one 33/11 kV (or 66/11 kV) sub-station in each block; (ii) Village Electrification
Infrastructure (VEI) with at least one distribution transformer in each village/
habitation; (iii) Decentralized Distributed Generation (DDG) Systems where grid
supply is not feasible or cost-effective.

RGGVY is being implemented in two phases. The first phase will cover the village
headquarter and its at-least one hamlet. The 2nd phase will cover the balance
number of hamlets that have a population of 300 or less. Given the experience of the
awarded cost of about 200 DPRs received from the State and the CPSUs, the total
project cost for phase one is expected to be Rs. 24,000 crore and Rs. 21,000 for the
phase two. The phase one will be completed by 2009 and will reach electricity to all
the unelectrified villages and 3 lakhs unelectrified hamlets. The 2nd phase, starting
from 2009 onwards will reach the electricity to the balance unelectrified hamlets and
complete the task of providing access to all unelectrified rural households in the
electrified villages and hamlets by 2012.

10.2 FUND REQUIREMENT FOR 11TH PLAN


10.2.1 Generation Schemes

It has been estimated that 30,641 MW is likely to be added during 10th Plan period
and feasible capacity addition of about 68,8691 MW is likely during 11th Plan. These
have been categorized as under:

1. Projects Under Construction


2. Committed Projects

The funding requirement for generation Schemes under Central, State and Private
sector had been worked out based on various assumptions (placed at Appendix-
10.3 w.r.t. cost and phasing of expenditure for various types of schemes. The
funding requirements for the projects categorized above are as follows.

10.2.2 Projects Under Construction

A capacity addition of 17,743 MW has been achieved during 10th Plan till 31st
October, 2006, and 12,898 MW is expected to be commissioned during balance
period of 10th Plan. Based on the status of various projects, about 31,345 MW
capacity is under construction for likely benefit during 11th plan.

1
Excluding NCES & Captive

Page 4 of Chapter 10
Financial Issues & Power Sector Financing Working Group on Power for 11th Plan

Table 10.5
Summary of Projects under Construction

Sector Type Likely capacity Fund


addition Requirement
(MW) (Rs. crore)
Central Hydro 7,633 18,929
Thermal 7,200 16,917
Nuclear 3,160 8,970
Total 17,993 44,816
State Hydro 2,107 1,935
Thermal 5,852 14,308
Total 7,959 16,244
Private Hydro 2,191 8,835
Thermal 3,202 6,818
Total 5,393 15,653
Total Under Hydro 11,931 29,700
Construction
Thermal 16,254 38,043
Nuclear 3,160 8,970
Grand Total 31,345 76,713
Source: CEA

(Note: The aggregate capital cost of these projects is Rs 147,096 crore of which Rs.
76,713 crore is to be expended in 11th plan).

10.2.3 Committed Projects

In addition to projects under construction, a number of projects are under various


stages of development for which necessary inputs are being arranged by the
implementing agencies and various clearances required for setting up these projects
are being obtained such as environment and forest clearance, cooling water
availability, land acquisition, DPR preparation, concurrence of CEA/ State
Government (wherever required), financial tie ups/ CCEA clearance from govt., fuel
linkages etc.. Based on present status, a capacity of 37,524 MW could be
considered as committed capacity for benefit during 11th plan comprising of 3,654
MW Hydro and 33,870 MW Thermal.

Page 5 of Chapter 10
Financial Issues & Power Sector Financing Working Group on Power for 11th Plan

Table 10.6
Summary of Committed Projects

Sector Type Likely Fund Requirement


capacity (Rs. crore)
addition (MW)
Central Hydro 2,052 8,301
Thermal 15,110 57,865
Total 17,162 66,166
State Hydro 530 2,414
Thermal 16,000 60,970
Total 16,530 63,384
Private Hydro 1,072 4,399
Thermal 2,760 11,040
Total 3,832 15,439
Total Hydro 3,654 15,114
Committed
Thermal 33,870 1,29875
projects
Grand Total 37,524 1,44,988
Source: CEA

Table 10.7
Summary of 11th plan capacity addition (In MW)
SECTOR HYDRO THERMAL NUCLEAR TOTAL

Projects Under Construction 11,931 16,254 3,160 31,345


Committed Projects 3,654 33,870 0 37,524
Total capacity 15,585 50,124 3,160 68,869

10.2.4 Shelf of Projects to be taken up in 11th Plan for likely benefit in 12th Plan
In addition to above projects, a shelf of projects benefiting in 12th Plan of about
91,759 MW (31,734 MW Hydro, 47,225 MW Thermal and 12,800 MW Nuclear) has
also been considered for funding that would be at various stages of implementation
during 11th Plan.

10.2.5 Summary of Fund Requirement for Generation Projects


The details of the overall capacity addition programme of 68,869 MW during 11th
Plan and fund requirement of Rs 4,10,897 crore including start-up projects for
capacity addition in 12th Plan are tabulated in Table 10.8.

Page 6 of Chapter 10
Financial Issues & Power Sector Financing Working Group on Power for 11th Plan

Table 10.8
11th Plan Capacity addition & Fund Requirement (including advance action
funds for 12th plan projects)

Sector Fuel Type Likely capacity Fund Requirement


addition (MW) (Rs. crore)
Central Hydro 9,685 27,231
Thermal 22,310 74,782
Nuclear 3,160 8,970
Total 35,155 1,10,982
State Hydro 2,637 4,349
Thermal 21,852 75,278
Total 24,489 79,627
Private Hydro 3,263 13,234
Thermal 5,962 17,858
Total 9,225 31,092
All India Hydro 15,585 44,814
Thermal 50,124 1,67,918
Nuclear 3,160 8,970
Funds for projects Total 68,869 2,21701
th
benefiting in 11 Plan
Funds for projects Hydro 31,734 86,291
benefiting in 12th Thermal 47,225 81,877
Plan Nuclear 12,800 21,208
Total 91,759 1,89,195
Grand Total 1,60,628 4,10,896

10.2.6 Decentralized Distributed Generation

In addition to the fund requirement for conventional generation projects, an


investment of Rs. 20,000 crore is envisaged under Decentralized Distributed
Generation projects, some of which would be for grid interconnected schemes.

10.2.7 Non-Conventional Energy Resources

The estimated potential by FY 2032 for power generation from renewable energy
sources such as wind, small hydro, solar, waste to energy and biomass in the
country is estimated of about 183,000 MW. A capacity of 13,500 MW is expected
from renewable energy source during 11th plan. This shall comprise of around 75%
from wind (10,000 MW), 10% from small hydro power (1,400 MW) and 15% from bio
energy (2,100 MW).

The details of cumulative potential and achievements of - Renewable Grid Interactive


Power and 10th plan Targets and Achievements and 11th Plan tentative targets are
given in Table 10.9, Table 10.10 and Table 10.11.

Page 7 of Chapter 10
Financial Issues & Power Sector Financing Working Group on Power for 11th Plan

Table 10.9
Renewable Grid Interactive Power and 10th plan Targets vs. Achievements and
11th plan tentative targets
(Figures in MW)
Sources / Systems Estimated Cumulative Installed
Potential Capacity
(by 2032) (As on 31.3.2006)
Wind Power 45,000 5,310
Bio-Power(Agro residues & 61,000 46
Plantations)
Co-generation Bagasse 5,000 867
Small Hydro (up to 25 MW) 15,000 1,826
Waste to Energy 7,000 34
Solar Photovoltaic 50,000 2
TOTAL 183,000 8,088

Table 10.10
10th Plan Targets and Achievements of renewable power
(Figures in MW)
Sources / Systems Target Achievement (2002- Target
03 to 2005-06) 2006-07
Wind Power 1,500 3,684 1,515
Biomass Power Bagasse Co- 700 532 228
generation Biomass Gasifiers
Small Hydro (up to 25 MW) 600 388 132
Waste to Energy 80 25 13
-MSW
-Industrial Waste
Solar Power 145 1
TOTAL 3,075 4,630 1,888

Thus there has been a significant achievement in all sources except solar power

Table 10.11
11th Plan Tentative Targets of Grid interactive renewable power

(Figures in MW)
Sources / Systems Target for 11th plan
Wind Power 10,000
Biomass Power, Bagasse Co-generation 2,100
Biomass Gasifiers
Small Hydro (up to 25 MW) 1,400
TOTAL 13,500

Page 8 of Chapter 10
Financial Issues & Power Sector Financing Working Group on Power for 11th Plan

™ Installed capacity by the end of 9th Plan (As on 31.3.2002) 3,475 MW


™ Installed capacity by the end of 2005-06 (As on 31.3.2006) 8,088 MW
™ Program for 2006-07 1,888 MW
™ 11th Plan program for 2007-12 13,500 MW
™ Total Installed Capacity by the end of 11th plan 23,476 MW
(Say 23,500 MW)
10.2.8 Captive Power Plants

At present, the Installed Capacity of Captive Power Plants (1MW and above) is about 19,000
MW. The energy generation from captive power plants (1MW and above) during the year
2004-05 has been about 72 billion units. Further, a capacity addition of about 12,000 MW
from Captive plants is expected by 2012 based on information/ details received from power
plant manufacturers.

The estimated cost of Non-Conventional Energy Sources and Captive power projects during
11th Plan period is estimated as follows:

™ NCE Sources (13,500 MW @ Rs. 5 crore/MW) Rs. 67,500 crore


™ Captive Power Plants (12,000 MW @ Rs. 4 crore/MW) Rs. 48,000 crore

10.2.9 Merchant Power Plants

A Merchant power plant does not have long term PPA for sale of its power and is
generally developed on balance sheet of the developer. Government of India has
reserved coal blocks with reserves of 3.2 bn Tonnes for allotment by the screening
committee of Ministry of Coal for merchant plants and captive plants. About 10,000
MW capacity is expected to be developed through this initiative. Estimated funds
required thereof is as follows:

™ Merchant Power Plants (10,000 MW @ Rs. 4 crore/MW) Rs. 40,000 crore

10.3 RENOVATION AND MODERNIZATION OF POWER PLANTS

Based on current price level the fund requirement for R&M of Thermal and Hydro
Power Stations for the 11th Plan is estimated as Rs. 15,875 crore, the details of
which are given in Table 10.12.

Table 10.12
R&M Estimated Costs

Item Capacity in MW Estimated Cost


(Rs. crore)
R&M of Hydro Power 11,278 3,478
R&M of Thermal Power 12,389 12,397
TOTAL 15,875

10.4 TRANSMISSION NETWORK

Total Fund requirement for transmission system development and related schemes
has been estimated as following:

Page 9 of Chapter 10
Financial Issues & Power Sector Financing Working Group on Power for 11th Plan

Rs Crore

Inter-State 75,000
Intra-State 65,000
TOTAL 1,40,000

Central sector/ Inter-State schemes during 11th Plan

Development of National and Regional grids and related systems would require the
following types of schemes:

¾ 11th Plan Transmission Schemes for power evacuation and system


strengthening for Central sector generation capacity requiring inter-state
transmission
¾ Transmission schemes for IPP Generation Capacity seeking open access
from CTU for inter-state transmission
¾ Spill over expenditure of 10th Plan transmission schemes and advance action
for 12th Plan transmission schemes
¾ Other related important schemes in Central sector

State Sector/ Intra-State Schemes during 11th Plan

Development of State grids and related systems would require the following types of
schemes:

ƒ 11th Plan Transmission Schemes of STUs for evacuation of state sector


generation including intra-state open access to IPP Generation in state sector

ƒ STUs transmission schemes at 220kV, 132kV and 66kV to meet the transmission
needs of growth in demand

ƒ Spill over expenditure of 10th Plan transmission scheme and advance action for
12th Plan transmission schemes

ƒ Other related important schemes in the State sector for Renovation and
modernization of aging transmission system, State/Area load dispatch system,
Protection system up-gradation, and Software for planning and management
information system.

10.5 DISTRIBUTION AND RURAL ELECTRIFICATION

It is estimated that to transmit the generation capacity to end consumers envisaged


in 11th Plan, a matching distribution network of about 15,00,000 ckm of 33 kV, 11 kV
and LV lines and 2,92,000 MVA of distribution capacity will need to be established in
addition to installation of capacitors and re-conductoring of sub-transmission/
distribution network of about 30,00,000 ckm and augmentation of distribution
capacity of 1,98,000 MVA of various sub-stations. In addition to the above the

Page 10 of Chapter 10
Financial Issues & Power Sector Financing Working Group on Power for 11th Plan

estimated fund requirement of various other initiatives like Rajiv Gandhi Gramin
Vidyut Yojna (RGGVY) under rural electrification and APDRP etc. is as follows:

Table 10.13
Distribution and Rural Electrification Estimates
(Rs. crore)
Particulars Amount
Sub-transmission and Distribution 1,97,000
RGGVY 40,000
APDRP & Other Schemes (pump sets etc.) 40,000
Others 10,000
TOTAL 2,87,000

10.6 HUMAN RESOURCE DEVELOPMENT

Based on the assumed norms and additional capacity addition during 11th Plan and
to set up facilities by NPTI in NER, hydro power training institute at Nagal,
technology upgradation schemes etc. an outlay of Rs. 462 crore has been made
which is to be sourced from governmental assistance and other sources.

10.7 RESEARCH AND TECHNOLOGY DEVELOPMENT

The funding requirement of about Rs. 1,214 crore in 11th Plan Period has been
made for various schemes to be undertaken by Central Power Research Institute
(CPRI). The schemes include investment in new technology demonstration in
thermal generation 400 MW stations, R&D and demonstration in distributed
generation, Gas cum solar hybrid project, Nano materials applications for power
sector, Transmission & distribution, High power test facility addition, Upgradation of
laboratory to test 400 kV breakers etc., R&D Projects (In-house, RsoP & NPP), UHV
laboratory Hyderabad etc.

10.8 DEMAND SIDE MANAGEMENT

To strengthen existing institutional set-up in Bureau of Energy Efficiency (BEE) and


State Designated Agencies (SDA) & other energy conservation programmes, an
outlay of Rs. 653 crore has been estimated during the 11th plan period.

10.9 11TH PLAN ESTIMATED FUND REQUIREMENT

The total requirement of funds in 11th Plan has been estimated as Rs. 10,31,600
crore as given in the following tables:

Page 11 of Chapter 10
Financial Issues & Power Sector Financing Working Group on Power for 11th Plan

Table 10.14
Total Fund Requirement
(Rs. Crore)
Particulars State Central Private Total
Generation including Nuclear 1,23,792 2,02,067 85,037 4,10,896
DDG 20,000 20,000
R&M 15,875 15,875
Transmission 65,000 75,000 1,40,000
Distribution including Rural 2,87,000 2,87,000
electrification
HRD 462 462
R&D Outlay 1,214 1,214
DSM 653 653
Total Power Sector 4,91,667 2,99,396 85,037 8,76,100
NCES and Captive 22,500 93,000 1,15,500
Merchant Plants 40,000 40,000
Total Funds Requirement 5,14,167 2,99,396 2,18,037 10,31,600

10.10 YEAR WISE FUND REQUIREMENT:


The year wise fund requirement during 11th Plan has been given in Table
10.15.
Table 10.15
Year wise Funding Requirement for 11th Plan
(Rs. Crore)
2007-08 2008-09 2009-10 2010-11 2011-12 Total
1,27,804 1,74,611 2,27,280 2,55,656 2,46,249 10,31,600

10.11 SOURCES OF FUNDS

10.11.1 Introduction

A Debt: Equity (D/E) ratio of 70:30 has been taken based on the current financial
practices for funding of power sector. A scenario has also been developed at D/E of
80:20. The possible sources of funding are commercial banks, public financial
institutions, dedicated infrastructure/power finance institutions (PFC, IIFCL, IDFC
and REC), insurance companies, overseas markets, bilateral/ multilateral credit,
bond markets and equity markets. The issues regarding each of these agencies and
the possible sources of funds are enumerated below.

10.11.6 Commercial Banks / AIFIs

As per the prevalent guidelines/ prudential norms, the financing limits applicable for
Banks/ AIFIs are:

Page 12 of Chapter 10
Financial Issues & Power Sector Financing Working Group on Power for 11th Plan

10.11.6.1 Exposure Ceilings of Banks for Individual/ Group Borrowers

Credit exposure to borrowers belonging to a group may exceed the exposure norm
of 40% of the bank’s capital funds by an additional 10% (i.e. up to 50%), provided
the additional credit exposure is on account of extension of credit to infrastructure
projects. Credit exposure to single borrower may exceed the exposure norm of 15%
of the bank’s capital funds by an additional 5% (i.e. up to 20%) provided the
additional credit exposure is on account of infrastructure. Banks may, in exceptional
circumstances, with the approval of their Boards, consider enhancement of the
exposure to a borrower up to a further 5% of capital funds. As per the guidelines on
exposure norms, the banks may further fix internal limits for aggregate commitments
to specific sectors / industries.

10.11.6.2 Exposure Ceilings of Financial Institutions for Individual /Group


Borrowers

As per the prudential norms, the credit exposure to single borrowers shall not exceed
15% of capital funds of the AIFI. However, the exposure may exceed by additional
5% (i.e. up to 20%) provided the additional credit exposure is on account of
infrastructure projects. AIFIs may, in exceptional circumstances, with the approval of
their Boards, consider enhancement of the exposure to a borrower up to a further
5% of capital funds (i.e. 25% of capital funds for infrastructure projects and 20% for
other projects).

The credit exposure to the borrowers belonging to a group shall not exceed 40% of
capital funds of the AIFI. However, the exposure may exceed by additional 10% (i.e.
up to 50%) provided the additional credit exposure is on account of infrastructure
projects. AIFIs may in exceptional circumstances, with the approval of their Boards,
consider enhancement of the exposure to a borrower up to a further 5% of capital
funds (i.e. 55% of capital funds for infrastructure projects and 45% for other
projects). The AIFIs may fix internal limits for aggregate commitments to specific
sectors.

The policy of funding infrastructure projects by Domestic Commercial Banks (DCBs)


is typically governed by the prudential guidelines prescribed by Reserve Bank of
India (RBI) and further limited by the internal credit policy of each bank. As per RBI
guidelines for funding infrastructure projects, maximum exposure to a single
borrower and to a single group is limited to 20% and 50% respectively of the bank’s
networth. With the approval of the Board of Directors, an additional 5% could be
sanctioned for both the categories. Some banks also have an internal cap broadly on
the following lines:

i. Maximum term loans not to exceed 30% (of total time / term deposits / total
non food advances) at any time
ii. Terms loans per industry at a maximum of 10% of non-food advances
iii. Maximum limit for infrastructure advances at 7% of non-food advances

As per data complied by RBI, as on 31st March 2006, the Aggregate Time Deposits
of Scheduled Commercial Banks stood at approx. Rs 17,40,419 crore and total credit

Page 13 of Chapter 10
Financial Issues & Power Sector Financing Working Group on Power for 11th Plan

at Rs 14,96,474 crore. Out of the at Rs 14,96,474 crore, the infrastructure credit was
Rs. 2,24,471 crore representing about 15% of total credit.

10.11.7 Insurance Companies

While considering the other major category of investment institutions - the insurance
companies, it may be observed that the Insurance Regulatory and Development
Authority of India (IRDA) have mandated the pattern of investments to be followed by
the various insurance companies. Investments in Government securities, approved
securities, approved investments and in infrastructure and social sectors have been
prescribed in the Insurance Act, 1938 and the regulations have been framed
thereunder. IRDA has also specified that every insurer carrying on the business of
life insurance shall invest and at all times keep invested its controlled fund (other
than funds relating to pension and general annuity business and unit-linked life
insurance business) in the prescribed manner.

Currently, IRDA has specified the following limits for the investments that are to be
maintained by life insurance companies.

(Source: Insurance Regulatory and Development Authority).

Table 10.16
Limits for investments by Life Insurance Companies
S.No Type of Investment % of fund
i) Government securities or other approved securities Not less than 50%
-Government securities 25%
ii) Approved Investments as specified in Schedule – 1
a) Infrastructure and Social Sector Not less than 15%
b) Others to be governed by Exposure Norms. (Investments in Not exceeding 35%
`Other than in approved Investments' in no case exceed 15% of
the Fund)

For general insurance companies, IRDA has specified the following sectoral caps for
investments:

Table 10.17
Limits of Insurance specified for General Insurance companies
S No. Type of Investment Percentage
i) State Government Securities and other guaranteed securities being 30%
not less than
-Central Government securities being not less than 20%
ii) Housing and Loans to State Government for Housing and Fire 5%
Fighting equipment being not less than
iii) Investments in Approved Investments
a) Infrastructure and Social Sector Not less than 10%
b) Others to be governed by Exposure Norms. However the Not exceeding 55%
investments in `Other than in Approved Investments' in no case
exceed 25% of the Assets

Page 14 of Chapter 10
Financial Issues & Power Sector Financing Working Group on Power for 11th Plan

The total aggregate incremental investments in the infrastructure sector were Rs.
70,000 – Rs. 80,000 crore in FY 2003-04 and FY 2004-05. Estimated amount that
can be invested in the infrastructure sector after complying the prudential norms
stands at Rs. 10,000 crore p.a. Assuming 40% of the infrastructure exposure is in
the power sector, the annual availability for it is estimated at around Rs. 4,000 crore
on an yearly basis.

10.11.8 Overseas Markets: ECBs

As regards financing from overseas markets is concerned, while there is no paucity


of funds, the same need to be appropriately channelized towards the power sector,
either in the form of syndicated debt, tied financing / supplier’s credit, or assistance
from multilateral agencies. However, the availability of long-term funds in overseas
markets too is an issue, with the lenders generally preferring to limit their exposure to
5 years tenures.

ECB for investment in infrastructure sector falls under the Automatic Route i.e. it will
not require RBI/ Government approval. Borrowers can raise ECB from internationally
recognized sources such as international banks, international capital markets,
multilateral financial institutions, export credit agencies and suppliers of equipment,
foreign collaborators and foreign equity holders.

However, the following are the limits in regards to the amount and duration of ECBs
raised through automatic route:

i. ECB up to USD 20 million or equivalent with minimum average maturity of three


years
ii. ECB above USD 20 million and up to USD 500 million or equivalent with
minimum average maturity of five years.
iii. The maximum amount of ECB, which can be raised by an eligible borrower under
the Automatic Route, is USD 500 million during a financial year. Moreover as per
the credit policy announced in October 2006, these borrowers can raise
additional $250 million with average maturity of 10 years under the approval
route.
iv. ECB up to USD 20 million can have call/put option provided the minimum
average maturity of 3 years is complied before exercising call/put option.

The RBI indicates the all-in-cost ceilings for ECB from time to time. The following
ceilings will be valid currently:

Table 10.18
Ceilings for ECB Lending

Minimum Average Maturity Period All-in-cost Ceilings over six month


LIBOR*
Three years and up to five years 200 basis points
More than five years 350 basis points
* For the respective currency of borrowing or applicable benchmark.

Page 15 of Chapter 10
Financial Issues & Power Sector Financing Working Group on Power for 11th Plan

While the depth of ECB market is not perceived to be a problem, the issue remains
that the tenure of ECB borrowings is usually short, and the impact the shorter tenure
has on the returns to the Developer on account of the Depreciation norms allowed as
part of tariffs being lower than the actual loan repayment. As can be seen above,
Developers can explore this route more aggressively of raising loans from
international markets at competitive rates and for a longer tenure.

10.11.9 Multilateral Agencies

Some of the concerns that need to be addressed, related to funding of projects from
multilateral agencies, such as World Bank, Asian Development Bank etc. are:

i. Significant emphasis on Environment and Social Issues with added costs of


audits and certifications.
ii. Comparatively lengthy and time consuming appraisal and due diligence
exercise, conducted by multilateral agencies.

The above can be attributed to the requirement on the part of multilateral agencies
regarding the risk profile of the project and past experiences of the progress of
power sector reforms in the country. Further, inadequate returns due to poor
financial health of the SPUs/ SEBs; announcements of free power by State
Governments implications; lack of comprehensive payment security mechanism etc.
are acting as deterrents to advancement of financing by multilateral agencies to the
sector in a big way.

10.11.10 Bond Market

The Indian Financial system does not have large active and liquid debt market. The
Corporate Debt Market in India is in its infancy both in terms of microstructure as well
as market outcomes. Primary market is dominated by financial sector and relatively
small amount of funds are raised by manufacturing and other service industries. The
government securities market has grown exponentially during last decade due to
many structural changes introduced by the government and Reserve Bank of India.
However, secondary market activities in corporate bonds have not picked up as in
the case of government securities. The Debt Markets in India are dominated by
Government securities, which account for 70 - 75% of the outstanding value of
issued securities and 90-95% of the trading volumes in the Indian Debt Markets.
State Government securities & Treasury Bills account for around 3-4 % of the daily
trading volumes. The trading activity in the G-Sec. Market is also very concentrated
currently (in terms of liquidity of the outstanding G-Sec.) with the top 10 liquid
securities accounting for around 70% of the daily volumes.

The primary market in corporate debt is basically a private placement market with most of
the corporate bond issues being privately placed among the wholesale investors i.e. the
Banks, Mutual Funds, Provident Funds & other large investors like LIC, etc. The proportion
of public issues in the total quantum of debt capital issued annually has substantially
decreased in the last few years. For example, as per SEBI, in 2005-06 corporate sector
raised more than Rs. 83,000 crore from the bond markets, most of which was through
private placements.

Page 16 of Chapter 10
Financial Issues & Power Sector Financing Working Group on Power for 11th Plan

RBI to take steps to develop corporate bond market with screen based trading, rating
of Bonds and Government to encourage the same.

10.12 ESTIMATED FUNDS MOBILIZATION

The details of major sources and estimated mobilization, funding gap and possible
sources of bridging the gap is given below in following Tables alongwith details as
under:
Table 10.19
Estimated Funding for 11th Plan
(Rs. Crore)
Description State Central Private Total
Funds required 5,14,167 2,99,396 2,18,037 10,31,600
A) Equity Required (D/E - 70:30) 154,250 89,819 65,411 3,09,480
B) Equity Available
1 -Promoters including FDI for IPPs 0 0 25,511 25,511
-Promoters including FDI for NCES & Captive 0 0 27,900 27,900
-Merchant Power Plant 12,000 12,000
2 Internal Resources 0 62,922 0 62,922
3 Govt. Support
3.1 State Govt. 0 0 0 0
3.2 Central Govt. 0 0 0 0
C) Total Equity Available 0 62,922 65,411 1,28,333
D) Additional Equity to be arranged (A-C) 1,54,250 26,897 0 1,81,147
E) Debt Required (D/E - 70:30) 3,59,917 2,09,577 1,52,626 7,22,120
F) Debt Available
1.1 Direct Market Borrowing 10,000 15,000 0 25,000
1.2 Banks and AIFIs 37,173 58,415 10,621 106,210
1.3 PFC 64,960 8,120 8,120 81,200
1.4 REC 47,320 5,915 5,915 59,150
1.5 IIFCL 0 6,000 9,000 15,000
2.1 Multilateral/Bilateral Credits 5,520 19,320 2,760 27,600
2.2 ECA/ECB/Syndicated Loan etc. 0 46,000 11,500 57,500
G) Total Debt Available 1,64,973 1,58,770 47,916 3,71,660
H) Additional Debt to be arranged (E-G) 1,94,943 50,807 1,04,710 3,50,460
I) Additional Equity & Debt required (D+H) 3,49,193 77,704 1,04,710 5,31,607
J) Total Availablity of Debt and Equity 1,64,973 2,21,692 1,13,327 4,99,993
K) Funding by Special Schemes
1 APDRP 40,000 0 0 40,000
2 RGGVY 40,000 0 0 40,000
L) Total shortfall to be arranged (I-K) 2,69,193 77,704 1,04,710 4,51,607

Page 17 of Chapter 10
Financial Issues & Power Sector Financing Working Group on Power for 11th Plan

Table 10.20
Summary of Funds Requirement and Mobilization for
Different Debt: Equity Scenario

( Rs. Crore)
Description D/E D/E
70:30 80:20
Funds required 10,31,600 10,31,600
Equity Required 3,09,480 2,06,320
Total Equity Available 1,28,333 1,28,333
Additional Equity to be arranged 1,81,147 77,987
Debt Required 7,22,120 8,25,280
Total Debt Available 3,71,660 3,71,660
Additional Debt to be arranged 3,50,460 4,53,620
Additional Equity & Debt required 5,31,607 5,31,607
Less: Funding by Special Schemes 80,000 80,000
Total shortfall to be arranged 4,51,607 4,51,607
Equity required after funding from special schemes 1,21,147 17,987
Debt required after funding from special Schemes 3,30,460 4,33,620

The above estimates are based on the following norms and assumptions:

10.12.6 Debt Equity Mix

Debt Equity Mix for power projects taken to be 70:30.

10.12.7 Exchange Rate

An exchange rate of Rs. 46 per USD has been assumed for the plan period.

Based on a 70:30 debt-equity ratio and considering the availability of Rs 40,000


crore from APDRP and Rs 40,000 crore from RGVVY, the overall gap in funding is
Rs. 4,51,607 crore comprising equity gap of Rs 1,21,1472 crore and debt gap of Rs
3,30,460 crore. Further, for a debt-equity ratio of 80:20, overall gap in funding
remains the same with equity gap of Rs. 17,987 crore and debt gap of Rs. 4,33,620
crore.

10.12.8 Sources of Equity:

10.12.8.1 Promoters’ Equity including FDI in Private Sector

It has been assumed that equity portion of the total funding required for generation
(including nuclear & DDG) and transmission in the private sector, will be met through

2
RGVVY funding is considered a part of Equity funding whereas APDRP funding is split equally between
Equity and Debt.

Page 18 of Chapter 10
Financial Issues & Power Sector Financing Working Group on Power for 11th Plan

FDI and brought by the promoters in the private sector through own sources. FDI
during the plan period has been assumed to be USD 360 Million per annum.

10.12.8.2 Gross Budgetary Support by Central Government

Planned Budgetary Outlay by Central Government is assumed to grow at CAGR of


19% over Budgeted Estimates (BE) of 2006-07 (CAGR of BE from 2002-03 to 2006-
07 being 19.64%). Actual Outlay is assumed at 73% of BE (based on average
performance during 2002-03 to 2004-05), 80% of Actual Outlay is assumed in the
form of IEBR and 20% in the form of GBS (based on BE of 2006-07). Internal
Sources as a part of IEBR has been estimated as Rs. 62,922 crore during 11th plan
period.

10.12.9 Sources of Debt:

10.12.9.1 Direct Borrowings

The Direct Borrowings include direct fund raising through bonds and other
instruments by companies such as NTPC, NHPC, PGCIL, DVC, NEEPCO, SJVNL,
THDC and SEBs which are subscribed by provident and pension funds, gratuity
trusts, insurance companies, mutual funds, individuals etc. but excludes subscription
by banks which are separately included in funding by banks and AIFIs. The annual
aggregate issuance through these instruments is estimated to be about Rs. 5,000
crores.

10.12.9.2 Banks, NBFCs and AIFIs

a) Deployment of Non-food Gross Bank Credit in Infrastructure sector during FY


2005-06 and FY 2004-05 was Rs. 29,778 Crore and Rs. 21,829 Crore
respectively, indicating a growth of 36%. Assuming the base figure of Rs 29,778
crore for FY 2005-06 and assuming a growth in infrastructure sector credit at
15% p.a.3 and share of power sector in infrastructure credit be 40%, funding
under this source during the plan period comes to Rs. 106,210 Crore.

b) Funding by Banks exclude the funds channelised through PFC & REC, which
PFC & REC borrow from Banks & AIFIs in the form of Term Loans

c) Reserve Bank of India has issued guidelines on the subject of Financial


regulation of systemically important NBFCs (with asset size of more than Rs. 100
crores) and Banks’ relationship with them vide circular no. RBI/2006-07/204 and
RBI/2006-07/205 dated December 12, 2006. Consequently, lending by
systemically important NBFCs to a single borrower (15% of Networth) and a
group borrower (25% of Networth) is capped by the exposure norms as laid down
in the aforesaid guidelines. This will affect the ability of the institutions (such as
PFC, REC, IREDA etc) to fund the power sector. Besides, the exposure to be
taken by a bank on a single NBFC has also been capped at 15% of Bank’s

3
Though growth last year was 36%, the average growth of industrial credit from year 2000 to year 2005 has
been 13% per annum and hence a growth of 15% per annum in infrastructure sector credit growth has been
taken.

Page 19 of Chapter 10
Financial Issues & Power Sector Financing Working Group on Power for 11th Plan

Capital Funds. These guidelines also indicate that Banks may also consider fixing
internal limits for their aggregate exposure to all NBFCs put together. This in-turn
will affect the ability of the institutions such as PFC, REC, IDFC, IREDA etc to
mobilize the resources from the Indian financial system and channelise funds to
the power sector. All the affected NBFCs are required to give a roadmap to RBI
to comply with these guidelines by March 31, 2007. Thus, these guidelines are
expected to have an unfavorable impact on the availability of funds to the power
sector and impact of these restrictive guidelines is not ascertainable at this stage.

10.12.9.3 PFC

PFC has disbursed Rs. 37,404 Crore during first 4 years of the 10th Plan. Its
disbursements during FY 2005-06 and FY 2004-05 stood at Rs. 11,680 Crore and
Rs. 9,409 Crore respectively indicating a growth rate of 24% p.a. Assuming the
same growth rate, expected Disbursement by PFC during 11th Plan Period is
estimated at about Rs. 81,200 crore approximately. It is assumed that term loans will
be about 80% of total Disbursements. The fund allocation to State, Central & Private
sector is estimated in the ratio of 80%, 10% and 10% respectively.

10.12.9.4 REC

REC has disbursed Rs 20,508 Crore during first 3 years of the 10th Plan. CAGR of its
disbursements during FY 1999-2000 to FY 2004-2005 stands at 20.91%. Assuming
the same growth rate, expected disbursement by REC during 11th Plan Period is
pegged at Rs. 59,150 Crore. It is assumed that term loans will be about 80% of total
Disbursements. The fund allocation to State, Central & Private sector is estimated in
the ratio of 80%, 10% and 10% respectively.

10.12.9.5 IIFCL

It has been assumed that IIFCL will fund Rs. 15,000 Crore during the 11th Plan Period to
Central & Private Sector in the ratio of 40:60.

10.12.9.6 Multilateral/Bilateral Credit

It has been assumed that World Bank & ADB each will fund USD 600 million per annum.
During the plan period fund allocation to State, Central & Private sector is estimated in the
ratio of 20%, 70% and 10% respectively.

10.12.9.7 ECA, ECBs

It is assumed that funding through ECA & ECBs will be to the tune of USD 2,500
million per annum during the plan period and the fund allocation to Central and
Private sector is estimated in the ratio of 80% and 20% respectively.

10.13 LENDERS’ ISSUES

i. It may be noted that the estimates made in Table - 25 above for funding
infrastructure projects could at best be viewed as indicative as they do not
take into account competing demands of various sectors that the lenders may
decide to fund based on perceived risk and return criteria. Further, banks

Page 20 of Chapter 10
Financial Issues & Power Sector Financing Working Group on Power for 11th Plan

need to comply with prudent Asset Liability Management guidelines


prescribed by RBI while taking up long term exposures. Dedicated institutions
set up for funding the power sector, namely, Power Finance Corporation that
typically supports SEBs, APDRP and IPPs and Rural Electrification
Corporation that has its thrust on funding Rural Electrification projects, are
however, not constrained in this regard.

ii. Power projects are also plagued by lack of suitable fuel linkage, evacuation,
off take and payment security mechanisms. Environment as well as
Rehabilitation and Resettlement issues also need to be taken care of. Many a
time, as a parallel process, loans are approved by lenders pending
satisfactory arrangements in this regard. Any delay in achieving these
milestones could delay disbursement leading to cost and time overrun and
ultimate viability of the project.

iii. The off takers of power are mostly SEBs and almost all of them (and their
successor DISCOMS) continue to make cash losses. The lenders are
extremely concerned over this and continue to seek a credible payment
security mechanism that often entails suitable credit enhancement as may be
required. While the situation varies from State to State, few States like Delhi,
Andhra Pradesh, Gujarat and Tamil Nadu have managed to reduce their
AT&C losses substantially and come close to break even levels. However, till
the time these entities start making cash profit, the concerned Governments
may need to provide suitable comfort to the lenders by signing/
operationalising satisfactory escrow agreements or required changes in other
project documents (PPA etc).

iv. It is also necessary for the Government authorities to expedite critical


clearances, especially those pertaining to environmental clearances; land
acquisition and related Rehabilitation and Resettlement (R&R) issues; water
drawal permissions etc. Most states have till date, not put in place a single
window clearance mechanism to assist in obtaining these clearances in an
expeditious manner. Needless to say that delays and uncertainties, in
allocation of fuel linkage also adds to avoidable cost and time overrun in these
projects.

10.13.1 Credit Enhancing Mechanisms For Enhancing Comfort To Lenders

It must be re-emphasized that the utilities in the power sector need to generate
profits through levy of adequate user charges/recovery so that the Lenders are
enthused to lend to the entities in the sector. Whenever the sector becomes self-
sufficient, the lending and security payment mechanism will be based on commercial
negotiations between the lenders and the borrowers, as in other infrastructure
sectors like telecom, roads, ports, oil & gas etc. However, till the time this happens,
the governments will have to provide required comfort regarding payment security to
the lenders and the developers.

The lenders have been requesting the Government that the payment security to
CPSUs and Private Developers should be on the same footing. This would enable a

Page 21 of Chapter 10
Financial Issues & Power Sector Financing Working Group on Power for 11th Plan

quicker financial close and give adequate comfort to lenders. It is the Governments’
argument that the offer of incremental escrow might be sufficient as it expects the
sector to break even in the next few years. In any case, if this is the case, the
Government can extend the same benefits as those extended to CPSUs as anyway
this will become redundant whenever the turnaround happens. Thus, developers and
lenders are, demanding the payment security such as direct RBI debit facility that is
currently available to CPSUs for the projects to be considered satisfactorily
attractively & safe, as far as payment security is concerned.

Government may also consider allowing credit enhancement from select specified
multilateral and development agencies without attracting the need to get specific
approval from RBI for such structured obligations. This will bring down the cost of
funds and help reduce the cost of generation.

Grant to SEBs by the State Government should be provided upfront for meeting the
shortfall in the debt servicing rather than guaranteeing the entire debt.

10.13.2 Regulatory Framework Issues - Banking Sector

i. It is being often suggested that prudential norms for exposure to a particular


Sector/ Group be relaxed. It may be mentioned that for some of the exposure
limits, the Boards of the Banks can decide on the same and are willing to do so
on commercial principles considering promoters’ background and financial
strength of off-takers.
ii. However, prudential guidelines of RBI in respect of single borrower and single
Group exposure are tied to the networth of the lender and tinkering with this
measure that serves to mitigate the credit concentration risk is not in the
interest of the banking system and the economy, and as such may not be
acceptable to RBI/ MoF. However, recent changes by RBI in respect of single
client and single group exposure limits for Infrastructure dedicated NBFCs,
needs to be reviewed and brought back to original limits specified earlier.
iii. In order to supplement the domestic resources, banks and NBFCs may be
allowed to raise ECBs under the automatic approval route and on-lend them to
developers of power projects including Ultra Mega Power Projects, preferably
with proper hedging as these projects do not provide natural export cover.
iv. Explicit exemptions would be needed in respect of stamp duty to encourage
take out financing so as to enable lenders take long term position in power
projects.
v. Banks should be allowed to augment their capital base through innovative
instruments as most exposure norms are linked to the bank’s networth.
Moreover, definition for exposure limit as a % of regulatory capital as applicable
to Banks/AIFIs should also be applicable to NBFCs thereby allowing NBFCs to
use their tier II capital for calculating exposure limits.

10.13.3 Regulatory Issues related to ERCs, Government Policies

(i) Only a few states have come out with Multi-year Tariff Principles that encourage
developers and lenders to take a long term view. For generation projects
developed on a cost-plus basis, the norms for RoE, depreciation, etc should be
frozen on the date of signing of agreements, as any change directly impacts

Page 22 of Chapter 10
Financial Issues & Power Sector Financing Working Group on Power for 11th Plan

lenders’ ratios as well as developers’ ratios. Adverse changes, while benefiting


off-takers in the short term actually reduce interests of developers and lenders in
the long run and thus should be avoided.

(ii) Similarly, in Distribution, a long term loss reduction trajectory should be specified
by the ERC so that lenders have an idea of the time to achieve break-even. The
Financial Restructuring Plans prepared for these entities should be made
available to lenders enable them to take a view.

(iii) Most ERCs have not specified levels of cross-subsidy surcharge to be charged,
and the time table for reduction of the same. This discourages development of an
open multi-buyer model and discourages capacity addition for supplying to
consumers directly.

(iv) There is a significant uncertainty regarding applicability of Section 63 of Electricity


Act 2003. Many states have sought multiple extensions and have received the
same. It creates uncertainty in minds of lenders over the overall direction in which
the power sector is progressing. Further, principles like open access etc are
compromised if utilities are not unbundled. Any further extension of time for
unbundling should not be entertained to reduce the uncertainties.

(v) Most States had signed MoUs to privatize distribution in large cities. However,
there is almost nil progress on that front. Privatization model of Delhi, where the
ATC losses have come down by the promised levels (and even over-achieved in
one DISCOM) & the sector is close to the break-even levels, could be followed in
various cities and states should be encouraged to go for the same. The Central
Government, in order to encourage such steps, could promise to bring in
transition funding in case of privatization of DISCOMS.

10.14 DEVELOPERS’ CONCERNS

Some of the specific concerns of the equipment suppliers & developers, in relation to
the attractiveness of the power sector, issues in bringing in the required equity
finances & problems faced at the time of financial closure are as follows.

a) In order to achieve the 11th Plan Capacity addition target of the 11th Plan and to
avoid bunching of the schedules during last years of the Plan period, Ministry of
Power is emphasizing on a time schedule for finalization of orders. However, past
experience shows that some of the projects are not able to take off even after all
settlement between the developer and EPC contractor, mainly because of delay
in the financial closures of the project. In view of this, there is a need to look into
a short-term arrangement to meet the funds requirement for initiating the project
till the project achieves the final financial closure.

b) Power projects being capital intensive in nature and due to a mismatch between
the depreciation rates (as allowed in the CERC regulations and Companies Act)
most developers desire to have longer tenure repayment (say 15 years or more),
for a comfortable cash flow situation in the initial years of the Project. However,
the Indian banking sector as on date, is not in a position, to provide such long

Page 23 of Chapter 10
Financial Issues & Power Sector Financing Working Group on Power for 11th Plan

tenor loans. Long term financing, exceeding 10 years repayment tenure is


required because in a bidding scenario, shorter duration of debt causes front
loading of tariff resulting in high tariff in the initial years. Insurance Companies,
Financial Institutions should be encouraged/provided incentives to invest in
longer dated securities to evolve an optimal debt structure to minimize the cost of
debt servicing. This would ensure lowest tariff structure and maximum financial
viability. Option of a moratorium for an initial 2 to 5 years may also reduce tariff
structure during the initial years.

c) MoF may be required to allow a structure where banks take up loans having
tapering payment (major repayments in initial 10 years) whereas institutions like
IIFCL/Insurance Companies etc. accept ballooning repayment (major repayments
after 10th year). This would entail funding of a project in such a fashion that
major portion of bank loan is repayable in initial years while major portion of
IIFCL/Insurance Companies loans are repayable after 10 years. Such a structure
would fit into banks ALM repayment when specialized institutions like IIFCL
promoted for specific objective of priority Infrastructure projects lending can
accept repayment which are back ended.

d) In case of a competitive bidding scenario, difficulties are being faced by


developers to achieve financial closure. It is quite difficult to convince lenders to
grant sanctions and approve credit facilities for projects where off-take is not fully
tied up, at the time of approaching lenders. The dilemma of whether to appraise
the project on the basis of its marketing arrangements or whether to conduct an
appraisal of the cost of generation of the project (i.e. whether the project is
generating power at competitive rates) needs to be addressed by the bankers.

10.15 RECOMMENDATIONS & IMPLEMENTATION STRATEGY

10.15.1 Policy Measures for Equity Participation

IPO by Power companies: Profit making Central/ State Utilities in generation as


well as transmission & distribution to be encouraged for supply of PSUs stock in the
market by way of IPOs/ FPOs (Follow-on Public Offer)/ Offer for sale. If there is an
Offer for sale coupled with a raising of fresh equity, the money received through offer
for sale could be channelized to a Power Investment Fund or to a Power Finance
holding company which will use such funds solely for investments in the Power
Sector. It is estimated that an amount of Rs. 10,000 -15,000 crore can be raised over
the plan period.

Allow lower risk weightage of 100% (equivalent to normal commercial lending) to the
primary equity investment/ capital market exposure directly or through an
Infrastructure Fund by Banks and AIFIs as against the risk weightage of 150%
recently enhanced by RBI. Despite an excellent performance of such investments in
the past, Banks and IFIs are reluctant to take exposure in any Indian Infrastructure
Development Fund due to increased risk weightage. In view of the need for
channelising additional resources for infrastructure development, the increased risk
weightage for such investment should not be applicable to equity investments made
in Infrastructure dedicated Companies or Funds.

Page 24 of Chapter 10
Financial Issues & Power Sector Financing Working Group on Power for 11th Plan

10.15.2 Public Private Participation models: PPP on the lines of UMPP


where Govt. undertakes to get the various clearances before the bidding
facilitates the quicker financial closure.

10.15.3 Relaxation in Companies (Issue of Share Capital with Differential


Voting Rights) Rules, 2001, for issuing Equity Shares with Differential Voting
Rights

i. The power sector has a huge equity requirement for funding the power
projects and the ability of the promoters to put in equity is limited. The
possibility of the promoters to invite other financial investors to bridge the
equity gap is also restricted as it would dilute their controlling stake due to
participation of other equity investors with equal voting rights. However, if by a
practicable mechanism the balance equity (with differentiated voting rights)
can be infused without diluting controlling stake of the existing promoters, it
would facilitate bridging the equity funding gap.

ii. As per Section 86(a) (ii) of the Companies Act, 1956, a company can issue
equity shares with differential rights as to dividend, voting or otherwise subject
to Companies (Issue of Share Capital with Differential Voting Rights) Rules,
2001. However, under Rule 3 (1) of the above said Rules require a company
to have distributable profits in terms of Section 205 of the Companies Act,
1956 for three financial years in which it was decided to issue such shares.
This makes it impracticable to use this proviso for bringing equity Funds in a
new Power Company/ Project.

iii. In case of power companies (esp. SPVs) the construction period spans over a
longer period with huge capital requirement, therefore, the above condition of
having distributable profits will restrict the ability to issue such shares by
power companies. Therefore, it is proposed that Rule 3 (1) of Companies
(Issue of Share Capital with Differential Voting Rights) Rules, 2001 may be
waived for power companies for issuing equity shares with differential voting
rights before the date of commissioning of the project. A relaxation to this
effect will help power companies to bridge the equity funding gap and allow
faster off take of the power projects.

10.15.4 Equity support by State Governments through Budget Allocation:


The State Government should allocate funds through its budget for providing equity
support to State utilities in power sector. The recent RBI Study on State finances
clearly indicates improvement in finances of major States. This is also reflected in
RBI’s move to allow better off States to buy back guaranteed bonds from institutional
investors. More over States who have availed direct loans from institutions have also
come forward to prepay the loans.

10.15.5 Sector Specific Funds

From time to time, GoI introduces sector specific funds with specific objective of
making funds available to a particular sector from the respective fund. Some of these

Page 25 of Chapter 10
Financial Issues & Power Sector Financing Working Group on Power for 11th Plan

funds which can be considered potential source of funds for the infrastructure sector
are:

10.15.5.1 Scheme For Financing Viable Infrastructure Projects

GoI has decided to put into effect the Scheme for financing Viable Infrastructure
Projects for providing financial support to improve the viability of infrastructure
projects. The scheme is being administered by the Ministry of Finance through the
India Infrastructure Finance Company Ltd (IIFCL), a company incorporated under the
Companies Act, 1956. Apart from its equity, the IIFCL is being funded through
long-term debt raised from open market. This debt can be any or all of the following:

i. Rupee debt raised from the market through suitable instruments created for
the purpose; the IIFCL would ordinarily raise debt of maturity of 10 years and
beyond.
ii. Debt from bilateral or multilateral institutions such as the World Bank and
Asian Development Bank. However, the conditions of multilateral agencies
include conditions like ADB generally stipulates that the its loan proceeds be
utilized for procurement in member countries of ADB, to comply with various
covenants on resettlement and environment difficult to implement by
borrowers etc.
iii. Foreign currency debt, including through external commercial borrowings
raised with prior approval of the Government.

The IIFCL would raise funds as and when required, for on lending, in consultation
with the Department of Economic Affairs. The magnitude of funds raised would be
determined by demand from viable infrastructure projects. To the extent of any
mismatch between the raising of funds and their disbursement, surplus funds would
be invested in marketable government securities.

The borrowings of IIFCL may be guaranteed by the Government of India. The extent
of guarantees to be provided shall be set at the beginning of each fiscal year by the
Ministry of Finance, within the limits available under the Fiscal Responsibility &
Budget Management Act. However bonds issued by IIFCL, unless otherwise directed
by Government of India, will not be included against Statutory Liquidity Ratio
requirements. For year 2005-06, as per guidelines laid down for IIFCL, extent of
guarantee to be provided by Government of India will be Rs. 10,000 crore.

The total lending by the IIFCL to any Project Company shall not exceed 20% of the
Total Project Cost. Loans will be disbursed in proportion to debt disbursements from
Banks and AIFIs and it has been estimated that IIFCL exposure as a proportion of
Banks and AIFIs would be around 14% to 15%. Further, IIFCL shall finance only
commercially viable projects.

10.15.5.2 Specialized Debt Funds For Infrastructure Financing

Creation of specialized long-term debt funds to cater to the needs of the


infrastructure sector. A regulatory and tax environment that is suitable for attracting
investments is key for channelizing long-term funds into infrastructure development.

Page 26 of Chapter 10
Financial Issues & Power Sector Financing Working Group on Power for 11th Plan

i. RBI may look into the feasibility of not treating investments by banks in such
close-ended debt funds as capital market exposure.
ii. IRDA may consider including investment in SEBI registered debt funds as
approved investments for insurance companies.
iii. FII may also be allowed to participate in SEBI registered infrastructure debt
funds. This could be done by modifying SEBI foreign VC regulations 2000 to
extend its purview to cover debt FIIs such that these are allowed to invest /
commit contributions to rupee denominated infrastructure debt funds
registered with SEBI along the same lines as applicable for domestic QIBs.

10.15.6 Venture Fund/ Private Equity Fund (PE)

Development of a Venture Capital / PE fund to invest in equity of power projects is


also an option that needs to be explored, as a possible source of equity funds
available to the projects. The features of the fund can be as follows:

Development of Power Venture/ PE Fund is a very viable and sound value


proposition to help meet energy security needs of the country. Coupled with this,
allowing power companies to issue equity shares with differential voting rights along
with a relaxation to have distributable profits as indicated in above para 10.14.3,
such arrangement can be a potent source of funds for the development of Power
Infrastructure.

i. It can participate in equity of new projects


ii. An initial corpus can be contributed from corporate sector, domestic and
international investors.
iii. Consortium and joint ventures between developers, promoters, end user,
contractors, mine developer to be encouraged.
iv. The infusion of equity capital by the Venture Capital/ PE Funds in power
companies may be facilitated by allowing power companies to issue equity
shares with differential voting rights along with a relaxation of the Rule 3 (1) of
Companies (Issue of Share Capital with Differential Voting Rights) Rules,
2001 on having distributable profits as indicated in para 4.2.5. This would
create space for Financial Investors to infuse funds in the Projects without
threatening the ownership pattern of the Developer.
v. Financial institutions involvement in equity funding of the power projects or
contributing towards the corpus of Power Fund should not attract the recently
modified Risk weightage of 150% for equity investment and Govt. should
consider the same weightage as is assigned for normal commercial lending.
For this, Norms/ policies need to be re-looked by RBI.

There is a space for raising and deploying Energy focused Private Equity Fund (India
Power Fund) in line with Infrastructure Development Fund (Rs 930 crore fund)
managed by IDFC Private Equity Company Limited and deployed in airports, ports,
roads, power plants, gas pipelines etc in its portfolio and IDFC Private Equity (Rs.
2,000 crore in June 2006) being deployed in various infrastructure sectors including
Power.

Page 27 of Chapter 10
Financial Issues & Power Sector Financing Working Group on Power for 11th Plan

IDFC Private Equity has raised IDFC Private Equity Fund II of $440m approx. Rs
2000 crore in June 2006 and the same is being deployed in various infrastructure
sectors including Power. Since the need for Power sector is significant, there exists
a potential for raising and deploying Energy focus private Equity Fund.

10.15.7 Development Of Primary Markets For Bonds And Corporate Debt


A robust primary market ensures supply of quality papers to the secondary markets
leading to growth of secondary market. The issues those need to be addressed for
development of primary market in corporate bonds are listed below:

10.15.7.1 Enhancing issuer base

Currently corporates have no compulsions to access the market for raising funds.

i. It would be in the interest of banks that the corporates meet at least part of
their requirement through the bond route as they would be in a better position
to manage balance sheet related risks (ALM, credit exposure, etc).
ii. Banks’ entry into the retail bond market would greatly facilitate in bringing
good quality paper to the market through MBS (Mortgage Backed Securities)
and ABS (Asset Backed Securities) which provide major impetus for
developing corporate debt market.

10.15.7.2 Enhancing investor base

i. Allowing all cooperative banks to invest in quality corporate bonds would be


helpful as cooperative banks have large deposits.
ii. Retail investors should be encouraged to participate in the market through
stock exchanges by providing fiscal incentives for such investments.
iii. Encouraging the foreign investor to participate in subordinate/hybrid debt
instruments

10.15.8 Hydro Power Viability Fund

In case of Hydro Power Projects, the high cost of generation in the initial 4-5 years is
comparatively much higher than in the later years. It is suggested that for long term
contracts, a component (say 25%) in the tariff of hydro power projects for the first
five years after start of commercial operation is deferred and not recovered from
the buyers but is added in the tariff from 11 - 15 years. To operationalise such
schemes, lenders will need to initiate a scheme which finances the deferred
component of the power tariff of the first five years and recovers its money during
11th to 15th year of the operation. For this, a Fund can be set up by AIFIs which cater
to payments and receipts. The responsibility of developing and operating the Hydro
Project Viability Fund can be vested with financial intermediaries like PFC etc. This
will also rationalize the gap between the tariff of hydro and thermal in the initial
years of operations. Any extra financing cost incurred on such viability gap
financing should also be permitted as a pass on in the tariff by regulators.

Page 28 of Chapter 10
Financial Issues & Power Sector Financing Working Group on Power for 11th Plan

10.15.9 Viability Gap Fund (for Remote areas)

The power projects especially in generation or Transmission and Distribution


schemes in remote areas like Northeastern region, J&K etc and other difficult
terrains need financial support in the form of a viability gap for the high initial cost
of power which is difficult to be absorbed in the initial period of operation. A scheme
may be implemented in the remote areas as a viability gap fund either in the form of
subsidy or on the lines of hydro power development fund a loan which finances the
deferred component of the power tariff of the first five years and recovers its money
during 11th to 15th year of the operation. Any extra financing cost incurred on such
viability gap financing should also be permitted as a pass through in the tariff by
Regulators.

10.16 IMPLEMENTATION MECHANISMS

Some of the implementation mechanisms aimed at channelising more funds into the
power sector, for the recommendations made in the report have been discussed
ahead.

10.16.1 Policy Interventions & Financial Measures For Reducing Funding Gap

10.16.1.1 Change In External Commercial Borrowing Guidelines

Modification of ECBs guidelines permitting infrastructure borrowers including


intermediaries PFC, REC, IDFC etc to borrow funds from overseas market under
automatic approval route of ECB Guidelines of the RBI.
Debt Servicing to be eligible for exemption under Section 10 (15) (iv) of Income Tax
Act - Presently, the ECBs raised by infrastructure companies like power are required
to gross up interest payment with the tax amount and deposit the Tax in India on
interest servicing done to foreign lenders. This additional liability does not arise in
case of multilateral loans or certain export credit loans from countries with which
India has double taxation avoidance treaties. The borrowing by power companies,
raised during the 11th Plan period (even if the repayment continues beyond 11th
Plan) should be notified to be eligible for exemption under Section 10 (15) (iv) of the
Income Tax Act

10.16.1.2 Instruments for wider retail participation

Introduce Power Bonds or Vidyut Vikas Patra, as transferable bearer instrument


admissible on the lines of erstwhile Indira Vikas Patra with a lock in period of at least
3-5 years to enable wider participation of retail segment in the domestic market for
investment in the power sector which can be issued by financial intermediaries such
as PFC, REC, IDFC and Banks etc. The money raised through these bonds may be
channelized to the power sector. Respective institutions may monitor the project
implementation.

Another variant of Vidyut Vikas Patra could be a tax-free bond of 15 – 20 years to


mobilize small savings for long tenor. Amount expected to be mobilized during 11th
Plan is Rs. 50,000 crore i.e. Rs. 10,000 crore per year. (During the last 3 years

Page 29 of Chapter 10
Financial Issues & Power Sector Financing Working Group on Power for 11th Plan

amount mobilized through Kisan Vikas Patra was to the tune of over Rs. 20,000
crore per year)

10.16.1.3 Tax incentives on investments

A higher economic growth can only be sustained through investment in the


infrastructure sector. For garnering additional funds for the sector to introduce
additional investment limit of Rs. 50,000 per year for infrastructure bonds under
Section 80C of the Income Tax Act, 1961 over and above existing limit of Rs.
1,00,000 with a lock in period of at least 5 years. Assuming a subscriber base of 15
million (~ 33% of total tax payers) out of a tax payer base of 45 million people, the
amount mobilized p.a. is estimated as Rs. 75,000 crore p.a. Assuming a 40% flow to
the power sector out of the above, the mobilization over 5 years is estimated at Rs.
1,50,000 crore. The loss of tax revenue from this step would be compensated by
higher tax revenue in future due to higher GDP growth rate. Such a step can be
supported at this junction as we expect higher tax collection due to a growing
economy.

10.16.1.4 Low Cost Long term Capital Gains Bonds

Allow Section 54EC benefit under Income Tax Act for bond issuances by PFC &
IIFCL in line with REC & NHAI at Rs. 5,000 crore p.a. which shall facilitate
mobilization of Rs. 25,000 crore per organization during 11th Plan period. This will
enable additional low cost funds for this sector.

The possible sources of bridging the gap is given below :

Table 10.21
Possible Sources of Bridging the Gap

(Rs. Crore)
S. No. Particulars Estimated Amount
Debt
1 Power Bonds 50,000
2 Tax incentive under Section 80 C 1,50,000
3 Bonds under Section 54EC 50,000
4 Insurance 20,000
Sub Total 2,70,000
Equity
5 IPO/FPO 15,000
Grand Total 2,85,000
Net Gap 1,66,607

10.16.1.5 Reinstatement of 10(23) G benefit (tax exemption on interest income


from infrastructure projects) to be reintroduced with following provision:
“Exemption should be extended to all categories of investors (lenders)
and in all kinds of investments (whether by way of shares, loans, cash
credit limit, public deposits etc) with a lock in period of at least 5 years.”
The provision of Tax incentive will facilitate low interest lending and

Page 30 of Chapter 10
Financial Issues & Power Sector Financing Working Group on Power for 11th Plan

shall accelerate investment in the power sector as otherwise increased


cost of financing in power sector results in higher power tariffs.

10.16.1.6 All investments in Power Bonds should be considered for SLR


computation and accorded SLR status. This measure will enable
investment in Power bonds by the banks. It will also promote trading of
power bonds in the secondary market.

10.16.1.7 5% of pf, gratuity, pension and insurance funds must be regulated for
investments in power bonds. power bonds may be included in the
designated securities for the purpose of income tax in cpf investment
guidelines. this measure will enable investment in power bonds by pf,
gratuity, pension and insurance funds. it will also promote trading of
power bonds in the secondary market. 10% of power bonds issued by
each entity must necessarily be of smaller denomination through public
issues to promote their further trading by small investors in the
secondary market which shall encourage retail participation in the debt
segment.

10.16.2 Institutional / Regulatory Interventions

10.16.2.1 Proper security mechanism


a. Commitment of escrow upfront as in case of successful UMPPs to
be provided
b. Alternatively, to provide access to large industrial consumers on
payment of wheeling charges, in case of default, as adequate
security in lieu of ESCROW.

10.16.2.2 Uniform rules for cross subsidy and additional surcharges to be levied by
SEB on sale of power by an IPP in that state to a third party

10.16.2.3 Postal stamp Transmission/Wheeling charges by IPPs in various states


with access for pooling for power fund.

10.16.2.4 In line with the National Electricity Policy, states should be encouraged to
follow Intra - State ABT regime such that they are eligible for 14%
return on equity. This would encourage better discipline even within the
States and shall enhance internal resources for deployment in
R&M/capacity expansion.

10.16.3 Fiscal and other Measures to enable cheaper power

10.16.3.1 Excise duty/ CVD on power generation, transmission & distribution


equipment (which is currently at 16%) should be abolished for projects
with 1000 mw dispatch on the lines of concession provided to the mega
power project as per para 8.3 of the foreign trade policy (2004-09). This
is required, as power sector has no advantage of “cenvat” credit as
there is no excise on power, which increases the cost of power.

Page 31 of Chapter 10
Financial Issues & Power Sector Financing Working Group on Power for 11th Plan

10.16.3.2 The import duty relaxation presently available for generation equipments
may also be extended to include all equipment related to power
transmission, distribution metering and energy conservation so that the
supply of equipments at reasonable cost is available to continue with
Distribution reforms which are being supported by schemes like
APDRP etc.

10.16.3.3 Existing Income tax exemption for Power Sector projects under section
80IA expiring in March 2010 to be extended till March 2017, i.e. end of
12th plan period.

10.16.3.4 Additional depreciation of 20% (WDV) under IT Act is available for


investments in plant and machinery in industries other than power.
Same depreciation should be made available to power industry also.

10.16.3.5 Technology transfer for developing and enhancing existing manufacturing


facilities in India so that Indigenous vendor development is facilitated
for high-tech supplies in future.

**********

Page 32 of Chapter 10
Financial Issues & Power Sector Financing Working Group on Power for 11th Plan

Appendix 10.1
DETAILED OUTLAY AND ACHIEVEMENT FOR FUNDING X PLAN - STATE
SECTOR
(In Rs. Crore)
State / UTs Tenth 2002-03 2002-03 2003-04 2003-04 2004-05
Plan (Appd.) (Actual) (Appd.) (R.E.) (Appd.)
(Appd.)
States

Andhra 7139.47 3122.69 2167.96 2175.55 2012.33 2125.86


Pradesh
Arunachal 491.19 121.24 72.77 114.52 114.52 155.30
Pradesh
Assam 835.42 187.11 82.77 191.42 182.92 290.48
Bihar 2719.58 275.30 131.68 493.68 389.17 667.88
Chhattisgarh 99.19 20.05 13.75 30.81 43.81 157.17
Goa 400.00 55.22 58.53 71.82 66.81 98.99
Gujarat 5958.49 792.24 571.39 762.24 580.14 635.45
Haryana 1395.33 261.40 202.97 280.00 212.00 470.00
Himachal 1235.00 202.46 363.79 155.70 155.90 57.50
Pradesh
Jammu & 2879.49 411.91 437.75 611.29 688.55 719.89
Kashmir
Jharkhand 814.00 150.00 138.80 204.50 204.50 380.63
Karnataka 2206.99 886.30 860.06 1094.94 1169.69 2711.89
Kerala 3425.00 589.00 743.01 619.00 542.10 693.00
Madhya 5503.78 913.76 566.11 814.75 572.07 916.92
Pradesh
Maharashtra 10149.71 730.56 1260.49 413.48 349.05 382.43
Manipur 228.86 62.73 10.43 71.00 71.00 61.20
Meghalaya 501.37 135.47 55.81 118.08 109.39 157.11
Mizoram 192.80 41.32 38.98 45.40 53.74 57.86
Nagaland 247.95 34.78 21.40 46.60 47.10 65.48
Orissa 2858.54 1003.27 322.16 671.21 571.79 502.25
Punjab 5963.65 782.69 751.22 576.00 626.44 783.92
Rajasthan 6674.22 1114.00 1220.07 1186.00 1653.71 1816.18
Sikkim 240.00 41.20 37.49 39.50 39.50 90.75
Tamil Nadu 8000.00 905.00 1197.78 1294.81 1294.81 1255.53
Tripura 223.30 44.43 28.53 53.87 34.96 43.69

Page 33 of Chapter 10
Financial Issues & Power Sector Financing Working Group on Power for 11th Plan

State / UTs Tenth 2002-03 2002-03 2003-04 2003-04 2004-05


Plan (Appd.) (Actual) (Appd.) (R.E.) (Appd.)
(Appd.)
Uttar Pradesh 9082.49 981.56 1046.31 965.83 965.83 835.78
Uttaranchal 1847.05 303.67 194.38 310.67 278.67 253.84
West Bengal 7846.45 1558.33 754.92 1222.74 700.50 1567.48
Sub Total 89159.32 15727.69 13351.31 14635.41 13731.00 17954.46
(States)
Union Territories
A & N Islands 193.80 32.00 20.78 25.00 24.80 29.10
Chandigarh 108.94 15.66 16.52 19.60 19.60 19.95
Dadra & Nagar 77.50 18.88 18.85 12.81 12.81 9.36
Haveli
Daman & Diu 51.26 19.24 19.30 12.71 12.72 10.44
Delhi 3456.00 1413.00 1575.86 1462.25 1748.94 932.50
Lakshadweep 13.89 10.78 2.78 2.00 7.75 2.09
Pondicherry 165.00 27.53 24.97 27.00 26.66 28.00
Sub Total 4066.39 1537.09 1679.06 1561.37 1853.28 1031.44
(UTs)
Total (States 93225.71 17264.78 15030.37 16196.78 15584.28 18985.90
& UTs)

Page 34 of Chapter 10
Financial Issues & Power Sector Financing Working Group on Power for 11th Plan

Appendix 10.2
APPROVED TENTH PLAN OUTLAY
INTERNAL AND EXTRA BUDGETARY RESOURCES
GROSS BUDGETARY SUPPORT
(Rs Crore)

ORGANISATION I. R. BONDS DFA OTHERS IEBR EAB DBS GBS OUTLAY

NTPC 8356 41266 0 9058 58680 0 3000 3000 61680

NHPC 1159 15602 794 470 18026 0 14200 14200 32226

POWERGRID 2938 0 8214 9218 20370 0 1000 1000 21370

DVC 1601 1928 0 9981 13510 0 10 10 13520

THDC 0 0 1150 1897 3047 0 600 600 3647

NJPC 84 0 0 2470 2554 0 700 700 3254

NEEPCO 0 750 1463 0 2213 0 2011 2011 4224

PFC 0 0 0 0 0 0 0 0 0

REC 0 0 0 0 0 0 0 0 0

MOP (MISC.) 0 0 0 0 0 0 3479 3479 3479

TOTAL MOP 14138 59546 11622 33093 118399 0 25000 25000 143399

NLC 2804 5204 0 0 8008 0 0 0 8008

DAE 2271 7536 0 0 9807 5654 10183 15837 25644

TOTAL (C. S ) 19212 72286 11622 33093 136214 5654 35183 40837 177051

Page 35 of Chapter 10
Financial Issues & Power Sector Financing Working Group on Power for 11th Plan

Appendix 10.3

ASSUMPTIONS FOR ESTIMATION OF COST OF GENERATION PROJECTS

1. Thermal generation projects


a. Coal based @Rs. 4.00 crore per MW
b. Gas based @ Rs. 3.00 crore per MW
2. Hydro generation projects
a. Run of the river @Rs. 4.50 crore per MW for on-going projects
@Rs. 5.00 crore per MW for new projects
b. Storage based @Rs. 5.50 crore per MW for on-going projects
@Rs. 6.00 crore per MW for new projects
c. Storage based @Rs. 6.00 crore per MW for on-going projects
(J&K, NE<100 MW) @Rs. 7.25 crore per MW for new projects
d. Pump Storage @Rs. 5.00 crore per MW
@Rs. 2.50 crore per MW for Tehri PSS
3. Nuclear projects @Rs. 6.50 crore per MW

Assumptions for phasing of expenditure of generation projects:

¾ Thermal generation projects & gas based project <= 1000 MW plant capacity
1-4 years @ 15%, 25%, 30% & 30%.
¾ Thermal generation projects > 1000 MW plant capacity
1-5 years @ 10%, 20%, 30%, 25% & 15%.
¾ Hydro generation projects
1-6 years @ 10%, 15%, 20%, 20%, 25% & 10%.

¾ Hydro generation projects taken up in XI Plan for benefiting in XII Plan, the
commissioning is assumed as 7 yrs after DPR is prepared for < 100 MW and 9
yrs for > 100 MW

Page 36 of Chapter 10
Financial Issues & Power Sector Financing Working Group on Power for 11th Plan

Appendix 10.4
PROJECTS UNDER CONSTRUCTION

S. PLANT NAME STATE AGENCY SECTOR Type BENEFITS XI LIKELY


no. PLAN (MW) YEAR OF
BENEFIT
1 ALLAIN DUHANGAN HP RSWML P HYG 192 2008-09
2 AMARKANTAK MP MPGENCO S THG 210 2007-08
3 ATHIRAPALLI KERL KSEB S HYG 163 2010-11
4 BAGLIHAR-I J&K JKPDCL S HYG 450 2007-08
5 BAKRESHWAR U-5 WB WBPDCL S THG 210 2007-08
6 BARH U1 BIH NTPC C THG 660 2008-09
7 BARH U2 BIH NTPC C THG 660 2009-10
8 BARH U3 BIH NTPC C THG 660 2010-11
9 BARSINGSAR LIG RAJ NLC C THG 250 2008-09
10 BELLARY TPS U-2 KAR KPCL S THG 500 2009-10
11 BHAWANI BARRAGE II & III TN TNEB S HYG 60 2009-10
12 BHILAI JV CHG NTPC C THG 500 2007-08
13 BHOPALAPALLY (KAKTIYA) AP APGENCO S THG 500 2008-09
14 BUDGE-BUDGE EXT WB CESC P THG 250 2009-10
15 BUDHIL HP LANCO IPP P HYG 70 2008-09
16 CHABRA TPS RAJ RRVUNL S THG 500 2008-09
17 CHAMERA-III HP NHPC C HYG 231 2010-11
18 CHANDRAPURA JHAR DVC C THG 500 2007-08
19 CHUJACHEN SIKKIM GATI P HYG 99 2009-10
20 DADRI EXT (U-5) UP NTPC C THG 490 2009-10
21 DHOLPUR RAJ RRVUNL S THG 110 2007-08
22 DIMAPUR DG MEGH MeSEB S THG 23 2007-08
23 FARAKKA STAGE-III WB NTPC C THG 500 2009-10
24 GIRAL*U-2 RAJ RVUNL S THG 125 2008-09
25 HARDUAGANJ UP UPRVUNL S THG 500 2009-10
26 JURALA PRIYADARSHNI* AP APGENCO S HYG 195 2007-08
27 KAIGA* KAR NPC C Nucl 220 2007-08
28 KAMENG AR.PR. NEEPCO C HYG 600 2009-10
29 KARCHAM WANGTOO HP JPKHCL P HYG 1000 2011-12
30 KOL DAM HP NTPC C HYG 600 2008-09
31 KOL DAM HP NTPC C HYG 200 2009-10
32 KORBA III CHG NTPC C THG 500 2009-10
33 KOTA U7 RAJ RRVUNL S THG 195 2008-09
34 KOTESHWAR UTTAR'L THDC C HYG 400 2008-09
35 KUDANKULAM U 1,2 TN NPC C Nucl 1000 2007-08
36 KUDANKULAM U 1,2 TN NPC C Nucl 1000 2008-09
37 KUTYADI EXTN KERL KSEB S HYG 100 2007-08
38 LAKWA WH ASM ASGENCO S THG 37.2 2008-09
39 LOHARI NAGPALA UTTAR'L NTPC C HYG 600 2011-12
40 MAHESHWAR MP IPP P HYG 400 2010-11
41 MALANA II HP EVREST PC P HYG 100 2008-09
42 MYNTDU St-I MEGH MeSEB S HYG 84 2008-09
43 NAGARJUNA SAGAR TR AP APGENCO S HYG 50 2009-10
44 NEYVELI - II TN NLC C THG 500 2008-09
45 OMKARESHWAR MP NHDC C HYG 520 2007-08

Page 37 of Chapter 10
Financial Issues & Power Sector Financing Working Group on Power for 11th Plan

S. PLANT NAME STATE AGENCY SECTOR Type BENEFITS XI LIKELY


no. PLAN (MW) YEAR OF
BENEFIT
46 PARAS EXT U-2 MAH MAHA GEN S THG 250 2008-09
47 PARBATI - II (a) HP NHPC C HYG 400 2008-09
48 PARBATI - II (b) HP NHPC C HYG 400 2009-10
49 PARBATI - III HP NHPC C HYG 520 2010-11
50 PARICHHA EXT. UP UPRVUNL S THG 500 2009-10
51 PARLI EXT U-2 MAH MAHA GEN S THG 250 2008-09
52 PATHADI (LANCO) CHG LANCO-IPP P THG 300 2009-10
53 PATHADI (LANCO) CHG LANCO-IPP P THG 300 2008-09
54 PFBR(Kalapakkam) TN NPC C Nucl 500 2010-11
55 PURLIA PSS* WB WBSEB S HYG 675 2007-08
56 RAICHUR U 8 KAR KPCL S THG 250 2008-09
57 RAIGARH PH II (OP Jindal) CHG JIN. POWER P THG 750 2007-08
(250 MW in 10th plan)
58 RAPP U5&6 RAJ NPC C Nucl 220 2007-08
59 RAPP U5&6 RAJ NPC C Nucl 220 2008-09
60 SEWA-II J&K NHPC C HYG 120 2008-09
61 SIPAT U 1 CHG NTPC C THG 660 2007-08
62 SIPAT U 2 CHG NTPC C THG 1320 2008-09
63 SRINAGAR UTTAR'L GVK P HYG 330 2011-12
64 SUBANSIRI LOWER AR.PR. NHPC C HYG 2000 2010-11
65 SUGEN TORRENT (365 MW GUJ TORRENT P THG 752 2007-08
in 10th plan)
66 SURAT LIGNITE EXT GUJ GIPCL S THG 250 2008-09
67 SURATGARH EXT RAJ RRVUNL S THG 250 2008-09
68 TEESTA LOW DAM-III WB NHPC C HYG 132 2008-09
69 TEESTA LOW DAM-IV WB NHPC C HYG 160 2009-10
70 TEESTA V SIKKIM NHPC C HYG 510 2007-08
71 TORANGALLU KAR JINDAL P THG 300 2009-10
72 TORANGALLU KAR JINDAL P THG 300 2010-11
73 TROMBAY TPS MAH TATAPOWER P THG 250 2008-09
74 UHL - III HP HPJVVNL S HYG 100 2009-10
75 URI-II J&K NHPC C HYG 240 2009-10
76 VALUTHUR EXTN. TN TNEB S THG 92 2007-08
77 VARAHI EXTN. KAR KPCL S HYG 230 2008-09
78 VIJAYWADA TPP AP APGENCO S THG 500 2008-09
79 YAMUNA NAGAR HAR HPGCL S THG 600 2007-08
Total 31345

Page 38 of Chapter 10
Financial Issues & Power Sector Financing Working Group on Power for 11th Plan

Appendix 10.5
COMMITTED PROJECTS

S. PLANT NAME STATE AGENCY SECTOR Type BENEFITS XI LIKELY YEAR


no. PLAN (MW) OF BENEFIT
1 ANPARA-C UP LANCO P THG 500 2010-11
2 ANPARA-C UP LANCO P THG 500 2011-12
3 ANPARA-D UP UPRVUNL S THG 1000 2011-12
4 BADARPUR-X I DELHI NTPC C THG 490 2009-10
5 BADARPUR-X II DELHI NTPC C THG 490 2010-11
6 BARA UP IPP P THG 500 2011-12
7 BARH II BIH NTPC C THG 1320 2011-12
8 BARSINGSAR EXT RAJ NLC C THG 250 2010-11
9 BHASMEY SIKKIM GATI P HYG 51 2010-11
10 BHUSAWAL MAH MAHAGEN S THG 1000 2010-11
11 BOKARO REPLACEMENT JHAR DVC C THG 500 2009-10
12 BONGAIGAON U 1 & 2 ASSAM NTPC C THG 500 2010-11
13 BONGAIGAON U3 ASSAM NTPC C THG 250 2011-12
14 CHANDRAPUR MAH MAHAGEN S THG 500 2010-11
15 DADRI EXT (U-6) UP NTPC C THG 490 2009-10
16 DELHI/JHAJJAR TPS CHG/HAR JV DELHI S THG 500 2009-10
17 DELHI/JHAJJAR TPS CHG/HAR JV DELHI S THG 1000 2010-11
18 DURGAPUR STEEL WB DVC C THG 500 2010-11
19 DURGAPUR STEEL WB DVC C THG 500 2011-12
20 ENNORE-JV TN NTPC+ C THG 500 2010-11
TNEB
21 ENNORE-JV TN NTPC+ C THG 500 2011-12
TNEB
22 GOINDWAL SAHIB PUN GVK P THG 600 2011-12
23 HISSAR TPS I HAR HPGCL S THG 250 2009-10
24 HISSAR TPS I HAR HPGCL S THG 250 2010-11
25 HISSAR TPS II HAR HPGCL S THG 500 2011-12
26 KAKATIYA EXTN AP APGENCO S THG 500 2011-12
27 KALISINDH RAJ RRVUNL S THG 500 2011-12
28 KHAPER KHEDA EX MAH MAHA S THG 500 2009-10
GEN
29 KODARMA U1& U2 JHAR DVC C THG 1000 2010-11
30 KORADI MAH MAHA S THG 500 2010-11
GEN
31 KORADI EXTN MAH MAHA S THG 1000 2011-12
GEN
32 KORBA WEST EXT CHG CSEB S THG 600 2009-10
33 KOTHAGUDEM ST-V AP APGENCO S THG 500 2009-10
34 KRISHNAPATNAM AP APGENCO S THG 800 2011-12
35 LAMBADUG HP IPP P HYG 25 2010-11
36 LOWER JURALA AP APGENCO S HYG 240 2011-12
37 MAITHAN RBC JHAR DVC C THG 500 2009-10
38 MAITHAN RBC JHAR DVC C THG 500 2010-11
39 MALWA MP MPGENCO S THG 1000 2011-12
40 MANKULAM KERL KSEB S HYG 40 2010-11
41 MAUDA MAHA NTPC C THG 1000 2011-12
42 METTUR EXT TN TNEB S THG 500 2010-11
43 MEZIA EXT WB DVC C THG 500 2009-10
44 MEZIA EXT WB DVC C THG 500 2010-11
45 NABINAGAR BIH NTPC C THG 250 2010-11

Page 39 of Chapter 10
Financial Issues & Power Sector Financing Working Group on Power for 11th Plan

S. PLANT NAME STATE AGENCY SECTOR Type BENEFITS XI LIKELY YEAR


no. PLAN (MW) OF BENEFIT
46 NABINAGAR BIH NTPC C THG 500 2011-12
47 NEW UMTRU MEGH MeSEB S HYG 40 2010-11
48 NORTH CHENNAI EXT TN TNEB S THG 500 2011-12
49 NORTH K PURA JHAR NTPC C THG 1320 2011-12
50 OBRA REPLACEMENT UP UPRVUNL S THG 500 2011-12
51 PALLIVASAL KERL KSEB S HYG 60 2010-11
52 RAMPUR HP SJVNL C HYG 412 2011-12
53 SADAMANDER SIKKIM GATI P HYG 71 2009-10
54 SAGARDIGHI EXT WB WBPDCL S THG 500 2010-11
55 SAGARDIGHI EXT WB WBPDCL S THG 500 2011-12
56 SANTHALDIH EXT WB WBPDCL S THG 250 2009-10
57 SATPURA MP MP S THG 500 2011-12
58 SAWARA KUDDU HP PVC S HYG 110 2010-11
59 SIKKA EXT GUJ GSECL S THG 500 2010-11
60 SIMHADRI-EXT AP NTPC C THG 500 2010-11
61 SIMHADRI-EXT AP NTPC C THG 500 2011-12
62 SORANG HP SORAND P HYG 100 2011-12
PC
63 TALWANDI PUNJAB PSEB S THG 500 2011-12
64 TANGU ROMAI HP PCP/IPP P HYG 50 2010-11
65 TAPOVAN VISHNUGARH UTTAR'L NTPC C HYG 520 2011-12
66 TEESTA III SIKKIM TEESTA P HYG 600 2011-12
URJA
67 TEHRI PSS UTTAR'L THDC C HYG 500 2010-11
68 TEHRI PSS UTTAR'L THDC C HYG 500 2011-12
69 THOTTIAR KERL KSEB S HYG 40 2010-11
70 TIDONG-I HP PCP/IPP P HYG 100 2010-11
71 TRIPURA GAS ILFS TRI ONGC C THG 750 2009-10
72 TUTICORIN JV TN NLC+ C THG 500 2010-11
TNEB
73 TUTICORIN JV TN NLC+ C THG 500 2011-12
TNEB
74 UBDC III PUN MALANA P HYG 75 2009-10
POWER
CO.
75 UKAI EXTN. GUJ GSECL S THG 500 2011-12
76 ULTRA MEGA SASAN MP LANCO P THG 660 2011-12
77 UTRAN GUJ GSECL S THG 350 2008-09
78 VYASI UTTAR'L NHPC C HYG 120 2011-12

Total 37524

Page 40 of Chapter 10
Financial Issues & Power Sector Financing Working Group on Power for 11th Plan

Appendix 10.6

PROJECTS TO BE TAKEN UP IN XI PLAN FOR LIKELY BENEFIT IN XII PLAN

S. no. PLANT NAME STATE AGENCY SECT Type BENEFITS


OR XII PLAN
(MW)
1 ACHENKOVIL KERALA KSEB S HYG 30
2 BADAO ARUNACHAL PRADESH NEEPCO C HYG 60
3 BAGLIHAR-II JAMMU & KASHMIR PDC S HYG 225
4 BAIRABI MIZORAM PDD S HYG 80
5 BAJOLI HOLI HIMACHAL PRADESH IPP P HYG 180
6 BAKRESHWAR EXT WB WBPDCL S THG 500
7 BALIMELA DPH ORISSA IPP P HYG 60
8 BARA UP IPP P THG 500
9 BHARMOUR HIMACHAL PRADESH IPP P HYG 45
10 BHAVNAGAR LIGNITE GUJARAT NIRMA P THG 250
11 BOGADIYAR SIRKARI UTTARANCHAL IPP P HYG 170
BHYAL @
12 BOKARO STEEL JHAR DVC C THG 500
13 BORUS MP NHDC C HYG 55
14 CHAMBA HIMACHAL PRADESH IPP P HYG 126
15 CHHABRA II RAJASTHAN RRVUNL S THG 500
16 CHINNAR KERALA KSEB S HYG 28
17 CHIRGAON HIMACHAL PRADESH HPSEB S HYG 46
(MAJHGAON)
18 CHUTAK J&K NHPC C HYG 44
19 DHAULA SIDH HIMACHAL PRADESH IPP P HYG 40
20 DIBBIN ARUNACHAL PRADESH NEEPCO C HYG 100
21 DPL TPS WB WBPDCL S THG 300
22 DPL TPS WB WBPDCL S THG 500
23 EMCO MAHARASHTRA IPP P THG 270
24 ENNORE EXT TN TNEB S THG 500
25 GANOL MEGHALAYA MeSEB S HYG 25
26 GOHANA TAL UTTARANCHAL THDC C HYG 60
27 GUJRAT LIGNITE U 1 GUJ NLC C THG 500
28 GUNDIA KARNATAKA KPCL S HYG 200
29 HALDIA PH I WB CESC P THG 600
30 HANDIA MP NHDC C HYG 51
31 HANOL TIUNI UTTARANCHAL Sunflag P HYG 42
32 HOSHANGABAD MP NHDC C HYG 60
33 IFFCO SARGUJA CHG CSEB JV S THG 500
34 IGTPP BHAIYATHAN CHG CSEB S THG 800
35 INTEGRATED ORISSA NTPC C THG 800
PROJECT DARIPALLI
36 JADH GANGA UTTARANCHAL THDC C HYG 50
37 JAKHOL SANKARI UTTARANCHAL SJVNL C HYG 33
38 JELAM TAMAK UTTARANCHAL THDC C HYG 60
39 KAKARAPAR EXT. GUJARAT NPCIL C Nuclear 700
40 KALISINDH RAJ RRVUNL S THG 500
41 KAPAK LEYAK ARUNACHAL PRADESH NEEPCO C HYG 160
42 KARMOLI UTTARANCHAL THDC C HYG 140

Page 41 of Chapter 10
Financial Issues & Power Sector Financing Working Group on Power for 11th Plan

S. no. PLANT NAME STATE AGENCY SECT Type BENEFITS


OR XII PLAN
(MW)
43 KARMOLI LUMTI UTTARANCHAL NHPC C HYG 55
TALLI
44 KASHANG-I & III HIMACHAL PRADESH HPJVNL S HYG 195
45 KASHANG-II HIMACHAL PRADESH HPSEB S HYG 60
46 KOTLIBHEL-St IA UTTAR'L NHPC C HYG 195
47 KOTLIBHEL-St II UTTAR'L NHPC C HYG 530
48 KOTLIBHEL-St.IB UTTAR'L NHPC C HYG 320
49 KRISHNAPATNAM AP APGENCO S THG 800
50 LAKHWAR UTTARANCHAL NHPC C HYG 210
51 LANCO NAGARJUNA KAR NPCL-IPP P THG 1015
TPP
52 LATA TAPOVAN UTTAR'L NTPC C HYG 171
53 MALAXMI ORISSA NAVBHAR P THG 1040
AT
54 MAPANG BOGUDIYAR UTTARANCHAL IPP P HYG 200
@
55 MARGHERITA ASSAM NEEPCO C THG 480
56 MAWHU MEGHALAYA NEEPCO C HYG 120
57 MORI HANOL UTTARANCHAL Krishna P HYG 60
Tech
58 MUZAFFARPUR EXT BIHAR S THG 500
59 NABINAGAR BIH NTPC C THG 250
60 NIMOO BAZGO J&K NHPC C HYG 45
61 NORTH K PURA JHAR NTPC C THG 660
62 OBRA REPLACEMENT UP UPRVUNL S THG 500
63 PAKHAL DUL JAMMU & KASHMIR NHPC C HYG 500
64 PAMBAR KERALA KSEB S HYG 40
65 PANIPAT REF HARYANA IPP P THG 250
66 PARE AR.PR. NEEPCO C HYG 110
67 PARNAI JAMMU & KASHMIR PDC S HYG 38
68 PUDITAL LASSA HIMACHAL PRADESH IPP P HYG 36
69 RAGHUNATHPUR WB DVC C THG 1000
70 RAMMAM ST III WB NTPC C HYG 120
71 RANGIT-II SIKKIM IPP P HYG 60
72 RANGIT-IV SIKKIM IPP P HYG 90
73 RIHAND-X UP NTPC C THG 500
74 ROLEP SIKKIM IPP P HYG 36
75 ROSA UP ROSA PC P THG 600
76 RUPSIYABAGAR UTTARANCHAL NTPC C HYG 260
KHASIYABARA
77 SAINJ HIMACHAL PRADESH HPSEB S HYG 100
78 SHAHPUR KUNDI PUNJAB PSEB S HYG 168
79 SHAMNOT JAMMU & KASHMIR NHPC C HYG 370
80 SINGOLI BHATWARI UTTARANCHAL L&T P HYG 60
81 TALONG ARUNACHAL PRADESH NEEPCO C HYG 160
82 TALWANDI PUNJAB PSEB S THG 1000
83 TANDA-X UP NTPC C THG 1000
84 TEESTA III SIKKIM TEESTA P HYG 600
URJA
85 TIDONG-II HIMACHAL PRADESH IPP P HYG 70

Page 42 of Chapter 10
Financial Issues & Power Sector Financing Working Group on Power for 11th Plan

S. no. PLANT NAME STATE AGENCY SECT Type BENEFITS


OR XII PLAN
(MW)
86 TURIAL MIZORAM NEEPCO C HYG 60
87 ULTRA MEGA GUJARAT IPP P THG 800
MUNDRA
88 UMIAM UMTRU-V MEGHALAYA MeSEB S HYG 36
89 VISHNUGADPIPALKO UTTAR'L THDC C HYG 444
TI
90 BAGLIHAR-II JAMMU & KASHMIR PDC S HYG 225
91 BOKANG BALING UTTARANCHAL THDC C HYG 330
92 BOWALA NAND UTTARANCHAL UJVNL S HYG 132
PRAYAG
93 DEODI UTTARANCHAL IPP P HYG 60
94 DHAMVARI SUNDA HIMACHAL PRADESH HPSEB S HYG 70
95 DIKCHU SIKKIM IPP P HYG 105
96 GONDHALA HIMACHAL PRADESH IPP P HYG 144
97 GUJRAT LIGNITE U 2 GUJ NLC C THG 500
98 GUNDIA KARNATAKA KPCL S HYG 200
99 HARSAR HIMACHAL PRADESH IPP P HYG 60
100 IFFCO SARGUJA CHG CSEB JV S THG 500
101 IGTPP BHAIYATHAN CHG CSEB S THG 800
102 INTEGRATED ORISSA NTPC C THG 800
PROJECT DARIPALLI
103 KAKARAPAR EXT. GUJARAT NPCIL C Nuclear 700
104 KUDANKULAM- U 3 & TAMILNADO NPCIL C Nuclear 2000
4
105 KUTEHR HIMACHAL PRADESH IPP P HYG 260
106 LAKHWAR UTTARANCHAL NHPC C HYG 210
107 LINGZA SIKKIM IPP P HYG 120
108 LOWER KALNAI JAMMU & KASHMIR PDC S HYG 50
109 LOWER KOPILI ASSAM AGENCO S HYG 150
110 MALERI JHELAM UTTARANCHAL THDC C HYG 55
111 MATNAR CHHATTISGAD CSEB S HYG 60
112 NAITWAR MORI UTTARANCHAL SJVNL C HYG 33
(DEWRA MORI)
113 NAND PRAYAG UTTARANCHAL UJVNL S HYG 141
114 NEW GANDERBAL JAMMU & KASHMIR PDC S HYG 90
115 NEYVELI III LIGNITE TN NLC C THG 500
116 NONGKOLAIT MEGHALAYA MeSEB S HYG 120
117 PAKHAL DUL JAMMU & KASHMIR NHPC C HYG 500
118 PANAN SIKKIM IPP P HYG 200
119 PARKHACHIK JAMMU & KASHMIR PDC S HYG 60
PANIKAR
120 PARLI REPLACEMENT MAH MAHAGEN S THG 250
121 RAMAM ST-I W BENGAL WBSEB S HYG 36
122 RANGANADI-II ARUNACHAL PRADESH NEEPCO C HYG 130
123 RANGYONG SIKKIM IPP P HYG 141
124 RAPP EXT. RAJASTHAN NPCIL C Nuclear 700
125 RENGALI TPP ORS NLC C THG 500
126 RONGNICHU SIKKIM IPP P HYG 95
STORAGE
127 RUKEL SIKKIM IPP P HYG 33

Page 43 of Chapter 10
Financial Issues & Power Sector Financing Working Group on Power for 11th Plan

S. no. PLANT NAME STATE AGENCY SECT Type BENEFITS


OR XII PLAN
(MW)
128 SHONGTONG HIMACHAL PRADESH HPSEB S HYG 402
KARCHAM
129 TALEM SIKKIM IPP P HYG 75
130 TEESTA ST.-I SIKKIM IPP P HYG 280
131 TEESTA ST.-II SIKKIM IPP P HYG 330
132 THOPAN POWARI HIMACHAL PRADESH IPP P HYG 480
133 ULTRA MEGA GUJARAT IPP P THG 1600
MUNDRA
134 ULTRA MEGA SASAN MP IPP P THG 1600
135 ALAKNANDA UTTARANCHAL IPP P HYG 140
(BADRINATH)
136 BARA BHANGAL HIMACHAL PRADESH IPP P HYG 200
137 BHARELI LIFT DAM-I ARUNACHAL PRADESH NEEPCO C HYG 510
138 BHUSAWAL MAH MAHAGEN S THG 250
REPLACEMENT
139 BODGHAT CHHATTISGAD CSEB S HYG 500
140 CHHUNGER CHAL UTTARANCHAL NHPC C HYG 240
141 DIBANG ARUNACHAL PRADESH NHPC C HYG 500
142 GARBA TAWA GHAT UTTARANCHAL NHPC C HYG 630
143 GARO HILL MEGHALAYA MeSEB S THG 360
144 GHAROPA HIMACHAL PRADESH IPP P HYG 114
145 HIRONG ARUNACHAL PRADESH IPP P HYG 500
146 INTEGRATED ORISSA NTPC C THG 800
PROJECT DARIPALLI
147 JAITAPUR MAHARASHTRA NPCIL C Nuclear 1000
148 JAITAPUR MAHARASHTRA NPCIL C Nuclear 1000
149 JHANGI THOPAN HIMACHAL PRADESH IPP P HYG 480
150 KHOKSAR HIMACHAL PRADESH IPP P HYG 90
151 KISHAU DAM UTTARANCHAL THDC C HYG 300
152 KUNDAH PSS TAMIL NADU TNEB S HYG 500
153 LACHEN SIKKIM NHPC C HYG 210
154 LUHRI HIMACHAL PRADESH SJVNL C HYG 700
155 MARWA CHG CSEB S THG 1000
156 NAYING ARUNACHAL PRADESH IPP P HYG 500
157 NEYVELI III LIGNITE TN NLC C THG 500
158 NONGNAW MEGHALAYA MeSEB S HYG 50
159 PAKHAL DUL JAMMU & KASHMIR NHPC C HYG 1000
160 PALA MANERI UTTARANCHAL UJVNL S HYG 480
161 PARAS MAH MAHAGEN S THG 250
REPLACEMENT
162 RANGMAW MEGHALAYA MeSEB S HYG 65
163 RAPP EXT. RAJASTHAN NPCIL C Nuclear 700
164 SIRKARI BHYAL UTTARANCHAL UJVNL S HYG 210
RUPSIABAGAR
165 TAMAK LATA UTTARANCHAL UJVNL S HYG 280
166 TATO-II ARUNACHAL PRADESH IPP P HYG 350
167 TEESTA ST.-IV SIKKIM NHPC C HYG 495
168 TEESTA ST.-VI SIKKIM LANCO P HYG 500
169 TUINI PLASU UTTARANCHAL UJVNL S HYG 42
170 ULTRA MEGA GUJARAT IPP P THG 1600

Page 44 of Chapter 10
Financial Issues & Power Sector Financing Working Group on Power for 11th Plan

S. no. PLANT NAME STATE AGENCY SECT Type BENEFITS


OR XII PLAN
(MW)
MUNDRA
171 ULTRA MEGA SASAN MP IPP P THG 1600
172 ARKOT TIUNI UTTARANCHAL UJVNL S HYG 70
173 ATTUNLI ARUNACHAL PRADESH NTPC C HYG 500
174 BHARELI LIFT DAM-I ARUNACHAL PRADESH NEEPCO C HYG 510
175 BURSAR JAMMU & KASHMIR NHPC C HYG 250
176 DIBANG ARUNACHAL PRADESH NHPC C HYG 500
177 DUMMUGUDEM ANDHRA PRADESH APID S HYG 320
178 ETALIN u1 ARUNACHAL PRADESH NTPC C HYG 500
179 ETALIN u2 ARUNACHAL PRADESH NTPC C HYG 500
180 INTEGRATED PROJ CHG NTPC C THG 800
LARA
181 INTEGRATED ORISSA NTPC C THG 800
PROJECT DARIPALLI
182 KAMENG DAM ARUNACHAL PRADESH NEEPCO C HYG 300
183 KIRTHAI-I JAMMU & KASHMIR PDC S HYG 240
184 KISHAU DAM UTTARANCHAL THDC C HYG 300
185 KORBA SOUTH CHG CSEB S THG 500
186 NAYING ARUNACHAL PRADESH IPP P HYG 500
187 RENGALI TPP ORS NLC C THG 500
188 SONAMARG JAMMU & KASHMIR PDC S HYG 165
189 TALUKA SANKRI UTTARANCHAL UJVNL S HYG 140
190 TATO-II ARUNACHAL PRADESH IPP P HYG 350
191 TIPAIMUKH MANIPUR NEEPCO C HYG 500
192 ULTRA MEGA CHHATISGARH IPP P THG 800
AKALTARA
193 ULTRA MEGA AP AP IPP P THG 800
194 ULTRA MEGA KAR IPP P THG 1600
KARNATAKA
195 ULTRA MEGA ORISSA ORISSA IPP P THG 800
196 ULTRA MEGA MAHARASHTRA IPP P THG 800
SINDHUDURG
197 BURSAR JAMMU & KASHMIR NHPC C HYG 250
198 ETALIN u3 ARUNACHAL PRADESH NTPC C HYG 500
199 ETALIN u4 ARUNACHAL PRADESH NTPC C HYG 500
200 INTEGRATED PROJ CHG NTPC C THG 800
LARA
201 KAMENG DAM ARUNACHAL PRADESH NEEPCO C HYG 300
202 KIRTHAI-II JAMMU & KASHMIR PDC S HYG 360
203 KIRU JAMMU & KASHMIR NHPC C HYG 430
204 KISHAN GANGA JAMMU & KASHMIR NHPC C HYG 330
205 KUDANKULAM- U 5 &6 TAMILNADO NPCIL C Nuclear 2000
206 LWR 3 & 4 C Nuclear 2000
207 MAYURPUR UP UPRVUNL S THG 500
(SONEBHADRA)
208 NEW NUCLEAR NTPC NTPC C Nuclear 2000
209 RENUKA DAM HIMACHAL PRADESH HPSEB S HYG 40
210 SELIM MEGHALAYA CWC C HYG 170
211 TIPAIMUKH MANIPUR NEEPCO C HYG 500
212 ULTRA MEGA CHHATISGARH IPP P THG 1600

Page 45 of Chapter 10
Financial Issues & Power Sector Financing Working Group on Power for 11th Plan

S. no. PLANT NAME STATE AGENCY SECT Type BENEFITS


OR XII PLAN
(MW)
AKALTARA
213 ULTRA MEGA AP AP IPP P THG 1600
214 ULTRA MEGA KAR IPP P THG 800
KARNATAKA
215 ULTRA MEGA ORISSA ORISSA IPP P THG 1600
216 ULTRA MEGA MAHARASHTRA IPP P THG 1600
SINDHUDURG
217 UMDUNA MEGHALAYA CWC C HYG 57

Total 91759

Page 46 of Chapter 10
Acronyms Working Group on Power for 11th Plan

ACRONYMS

ACRONYMS EXPANSION
AAAC All Aluminium Alloy Conductor
ABS Asset Backed Securities
ABT Availability Based Tariff
AC Alternating Current
ADB Asian Development Bank
AG&SP Accelerated Generation & Supply Programme
AHWR Advance Heavy Water Reactor
AIIMS All India Institute of Medical Sciences
ALM Asset Liability Mismatch
ALTM Airborne Laser Terrain Mapping
AMD Atomic Minerals Directorate
APC Auxiliary Power Consumption
APDRP Accelerated Power Development & Reform Programme
APH Air Pre Heater
APM Administered Price Mechanism
APY Akshay Prakash Yojna
AREP Accelerated Rural Electrification Programme
AT&C Aggregate Technical & Commercial
BARC Bhabha Atomic Research Centre
Bcum, BCM
Billion cubic meter
Bm3
BE Budget Estimates
BEE Bureau of Energy Efficiency
BFP Boiler Feed Pump
BHEL Bharat Heavy Electricals Ltd.
Bay Of Bengal Initiative For Multi-Sectoral Technical &
BIMSTEC
Economic Co-orporation
BOOL Built Own Operate Lease
BOOT Built Own Operate & Transfer
BOT Built Operate & Transfer
BPCL Bharat Petroleum Corporation Limited
BPR Business Process Re-engineering
BSEB Bihar State Electricity Board
BSES Bombay Suburban Electric Supply
BU Billion units or Billion Kwh
C&I Control & Instrumentation
CAD & CAM Computer Aided Design & Computer Aided Management
CAGR Compounded Annual Growth Rate
CBIP Central Board of Irrigation & Power
CBM Coal Bed Methane
CCEA Cabinet Committee On Economic Affaires
CCGT Combined Cycle Gas Turbine
CD Compact Disc
CDAC Centre for Development of Advance Computing

Page 1 of Acronyms
Acronyms Working Group on Power for 11th Plan

ACRONYMS EXPANSION
CDM Clean Development Mechanism
CEA Central Electricity Authority
CERC Central Electricity Regulatory Commission
CFBC Circulating Fluidized Bed Combustion
CFL Compact Florescent Lamp
CFL Compact Fluorescent Lamp
CFRI Central Fuel Research Institute
CIDC Construction Industry Development Council
CIL Coal India Ltd.
CIRE Centre For Insurance Research & Education
ckm Circuit Kilometer
CLA Central Loan Assistance
CMPDIL Central Mine Planning & Design Institute Limited
COE Centre Of Excellence
CPP Captive Power Producer
CPRI Central Power Research Institute
CPSU Central Public Sector Undertaking
CRGO Cold Rolled Grain Oriented
Crs Crores
CS Central Sector
CSIR Council for Scientific and Industrial Research
CSMRS Central Soil & Materials Research Station
CTU Central Transmission Utilities
CVD Counter Veiling Duty
CWC Central Water Commission
CWS Circulating Water System
D/C Double Circuit
D/E Debt : Equity
DAE Department of Atomic energy
DC Direct Current
DCB Domestic Commercial Banks
DDG Decentralised Distributed Generation
DFI Domestic Financial Institution
DG Set Diesel Generating Set
DGH Director General Hydro Carbon
DISCOM Distribution Company
DMLF Data Management & Load Forecasting
DONER Development of North Eastern Region
DOPT Department of Personnel & Training
DPR Detailed Project Report
DPRS Distributed Renewable Power System
DRUM Distribution Reform Upgrade Management
DSM Demand Side Management
DST Department of Science & Technology
DSTATCOM Distribution Static Compensation
DTR Distribution Transformer Metering
DVC Damodar Valley Corporation

Page 2 of Acronyms
Acronyms Working Group on Power for 11th Plan

ACRONYMS EXPANSION
DVR Dynamic Voltage Restorer
E&F Environment And Forest
EA 2003 Electricity Act 2003
EAB External Aided Borrowing
EAP External Aided Projects
EC Energy Conservation
ECB External Commercial Borrowing
ECBC Energy Conservation Building Code
ECIC Energy Conservation & Information Centre
ECIL Electronic Corporation of India Ltd.
ECL Eastern Coal Fields Limited
EGEAS Electric Generation Expansion Analysis System
EHV Extra High Voltage
ENS Energy Not Served
EPC Engineering Procurement Contract
EPS Electric Power Survey
ERC Electricity Regulatory Commission
ERDA Electric Research & Development Association
ERS Emergency Restoration System
ESCO Energy Service Company
ESP Electro Static Precipitator
FACTS Flexible Alternating Current Transmission System
FAUP Fly Ash Utilisation Programme
FBC Fluidised Bed Combustion
FMIS Finance Management Information System
FO Forced Outage
FOR Forum Of Regulators
FPO Follow-on Public Offer
FSTA Fuel Supply And Transport Agreement
FY Financial Year
GAIL Gas Authority Of India Limited
GBS Gross Budgetary Support
GCV Gross Calorific Value
GDP Gross Domestic Product
GHG Green House Gas
GIS Gas Insulated Substation
GOI Government Of India
GPS Geographic Positioning System
GR General Review
GSPC Gujarat State Petroleum Corporation
GT Gas Turbine
GVA Gega Volt Ampere
GVP Grameen Vidyut Pratinidhi
GW Gega Watt
GWe Gega Watt (Electrical)
HBJ Hazira-Bijapur-Jagdishpur ( pipeline)
HEP Hydro Electric Project

Page 3 of Acronyms
Acronyms Working Group on Power for 11th Plan

ACRONYMS EXPANSION
HFO Heavy Fuel Oil
HPS Heavy Petroleum Stock
HRD Human Resource Development
HRT Head Race Tunnel
HSD High Speed Diesel
HSIL High Surge Impedance Loading
HT High Tension
HVDC High Voltage Direct Current
HVDS High Voltage Distribution System
IBF Input Based Franchisee
ID Induced Draft
IEBR Internal and Extra Budgetary Resource
IEEMA Indian Electrical & Electronics Manufacturers’ Association
IEP Integrated Energy Policy
IGCAR Indira Gandhi Centre for Atomic Research
IGCC Integrated Gasification Combined Cycle
IIFCL India Infrastructure Financial Corporation
IISC Indian Institute of Science
IIT Indian Institute of Technology
IOCL Indian Oil Corporation Limited
IPO Initial Public Offer
IPP Independent Power Producer
IPR Intellectual Property Rights
IR Internal Resources
IRDA Insurance Regulatory And Development Authority
IS Indian Standard
ISCC Integrated Solar Combined Cycle
ISO International Standard Organisation
ISPLAN Integrated System Planning
IT Information Technology
KAPS Kalpakkam Atomic Power Station
kCal Kilo Calorie
kg Kilogram
KKNPP Kudankulam Nuclear Power Project
kV Kilo Volts
kW Kilo Watt
kWh Kilo Watt hour
LEP Life Extension Programme
LF Load Factor
LILO Loop In Loop Out
LNG Liquefied Natural Gas
LOA Letter Of Award
LOLP Loss of Load Probability
LP Linear Programming
LRVI Loss Reduction & Voltage Improvement
LSHS Low Sulphur Heavy Stock
LT Low Tension

Page 4 of Acronyms
Acronyms Working Group on Power for 11th Plan

ACRONYMS EXPANSION
LWR Light Water Reactor
M&E Monitoring And Evaluation
MAPS Madras Atomic Power Station
MBS Mortgage Backed Securities
MCFC Mother Carbonate Fuel Cell
Mcm Million cubic meter
MFGs Micro Financing Institutions
MHD Magneto Hydro Dynamics
MMSCMD Million Metric Standard Cubic Meter per Day
MNP Minimum Need Programme
MNRE Ministry of New & Renewable Energy
MoEF Ministry of Environment & Forest
MoP Ministry of Power
MOU Memorandum Of Understanding
MT Million Tonne
MToe Million Tonnes Oil equivalent
MTPA Million Tonnes Per Annum
MU Million Units
MVA Mega Volt Ampere
MW Mega Watt
Mwe Mega Watt electric
MYT Multi Year Tariff
NABRD National Bank For Agriculture & Rural Development
NAPS Narora Atomic Power Station
NCL Northern Coal Fields Limited
NCPS National Capital Power Station
NDT Non Destructive Test
NEA Nepal Elecricity Authority
NEC North Eastern Council
NELP New Exploration Liscencing Policy
NEP National Electricity Policy
NFC Nuclear Fuel Complex
NGOs Non-Governmental Organisations
NHAI National Highways Authority Of India
NHPC National Hydroelectric Power Corporation
NICMAR National Institute Of Construction Management & Research
NIT National Institute Of Technology
NLC Neyveli Lignite Corporation
NMDC National Mineral Development Corporation
NML National Metallurgical Laboratory
NOX Oxides of Nitrogen
NPC National Productivity Council
NPCIL
Nuclear Power Corporation of India Ltd.
NPTI National Power Training Institute
NSC National Steering Committee
NTC Nuclear Training Centre

Page 5 of Acronyms
Acronyms Working Group on Power for 11th Plan

ACRONYMS EXPANSION
NTP National Tariff Policy
NTPC National Thermal Power Corporation
O&M Operation & Maintenance
OCGT Open Cycle Gas Turbine
OGIP Original Gas In Place
OIL Oil India Limited
ONGC Oil & Natural Gas Commission
PAFC Phosphoric Acid Fuel Cell
PC Pulverized Coal
PCRA Petroleum Conservation Research Association
PFBC Pressurised Fluidized Bed Combustion
PFC Power Finance Corporation
PFR Preliminary Feasibility Report
PGCIL Power Grid Corporation of India
pH Hydrogen Ion concentration
PHWR Pressurised Heavy Water Reactor
PIB Public Investment Board
PIC Programme & Implementation Committee
PIE Partnership In Excellence
PLF Plant Load Factor
PMGY Pradhan Mantri Gramodaya Yojna
PMI Power Management Institute
PMO Prime Minister’s Office
PPA Power Purchase Agreement
PPM Parts Per Million
PPP Public Private Partnership
PRI Panchayati Raj Institute
PRC Project Review Committee
PRM Project Review Meetings
PS Private Sector
PSC Production Sharing Contract
PSP Power Supply Position
PSS Pumped Storage Schemes
PSTI Power System Training Institute
PSU Public Sector Undertaking.
QIB Qualified Institutional Bidder
R&D Research & Development
R&M Renovation & Modernisation
R&M Renovation & Modernisation
RAPP Rajasthan Atomic Power Project
RAPS Rajasthan Atomic Power Station
RBI Reserve Bank Of India
RCC Roller Compacted Concrete
REA Rural Electricity Agency
REB Regional Electricity Board
REC Rural Electrification Corporation
REDB Rural Electricity Distribution Backbone

Page 6 of Acronyms
Acronyms Working Group on Power for 11th Plan

ACRONYMS EXPANSION
RES Renewable Energy Sources
RFP Request For Proposal
RFQ Request For Qualification
RGGVY Rajiv Gandhi Grameen Vidyutikaran Yojna
RHE Rural Household Electrification
RIDF Rural Infrastructure Development Fund
RIL Reliance Industries Limited
RLA Résiduel Life Assesment
RM Reserve Margin
RSOP Research Scheme On Power
S/C Single Circuit
SAARC South Asian Association for Regional Corporation
SCADA Supervisory Control & Data Acquisition
SCCL Singereni Collieries Company Limited
SDA State Development Agency
SEB State Electricity Board
SECL South Eastern Coal Fields Limited
SERC State Electricity Regulatory Commission
SGC State Generation Corporation
SHG Self Help Group
SLR Statutory Liquidity Ratio
SMEs Small And Medium Enterprises
SOG Sanctioned & Ongoing
SOX Oxides of Sulphur
SPIC Southern Petro India Chemicals Ltd.
SPM Suspended Particulate Matter
SPM Single Point Metering
SPS Single Point Supply
SS State Sector
SSB Solid State Breakers
SSTS Solid State Transfer Switches
ST&D Sub Transmission Distribution
STOA Short Term Open Access
STPP Super Thermal Power Project
STPS Super Thermal Power Station
T&D Transmission & Distribution
TAPP Tarapur Atomic Power Project
TAPS Tarapur Atomic Power Station
TCF Terra cubic Feet
Tckm Thousand Circuit Kilometre
TCSC Thyristorised Controlled Series Compensation
TERI The Energy Research Institute
TG Techo Generator
TIFAC Technology Information Forecasting & Assessment Council
TOD Time Of Day
TOU Time of Use
TPS Thermal Power Station

Page 7 of Acronyms
Acronyms Working Group on Power for 11th Plan

ACRONYMS EXPANSION
U Up rating
UCIL Uranium Corporation of India Ltd.
UI Unscheduled Interchange
UMPP Ultra Mega Power Project
UN United Nations
UNDP United Nation Development Programme
UPCL Uttaranchal Power Corporation Limited
UPPCL Uttar Pradesh Power Corporation Limited
UT Union Territory
VAMBAY Valmiki Ambedkar Awas Yojna
VEI Village Electrification Infrastructure
VEMB Village Electricity Management Board
WAMS Wide Area Monitoring System
WBPDCL West Bengal Power Development Corporation

Page 8 of Acronyms

You might also like