Qa QC Plan Facility Site Work Construction
Qa QC Plan Facility Site Work Construction
Qa QC Plan Facility Site Work Construction
Prepared For:
GENERAL ELECTRIC
319 Great Oaks Office Boulevard Albany, NY 12203
Prepared By:
GE Company Parsons Project Office 381 Broadway, Bldg 40-2 Fort Edward, NY 12828 Phone: 518-746-5311 Fax 518-746-5307
JANUARY 2007
ACRONYMS AND ABBREVIATIONS.........................................................................V SECTION 1 INTRODUCTION................................................................................... 1-1 1.1 PROJECT SETTING......................................................................................... 1-1 1.2 PHASE 1 CONTRACTS DESCRIPTION........................................................ 1-2 1.3 QUALITY PROGRAM OVERVIEW .............................................................. 1-3 1.4 QUALITY MANAGEMENT PLAN ................................................................ 1-5 1.5 CQAP ORGANIZATION ................................................................................. 1-5 SECTION 2 PROJECT QC/QA ORGANIZATION ................................................ 2-1 2.1 RESPONSIBILITIES AND AUTHORITIES OF ORGANIZATIONS ........... 2-1 2.1.1 Environmental Protection Agency .......................................................... 2-1 2.1.2 General Electric Company ...................................................................... 2-1 2.1.3 Engineer of Record.................................................................................. 2-1 2.1.4 Construction Manager ............................................................................. 2-1 2.1.5 Construction Contractors......................................................................... 2-2 2.2 STRUCTURE OF QC/QA ORGANIZATION ................................................. 2-2 2.3 RESPONSIBILITIES AND AUTHORITIES OF KEY PERSONNEL............ 2-2 2.3.1 Construction Managers Quality Assurance Personnel........................... 2-3 2.3.2 Contractors Quality Control Personnel .................................................. 2-5 SECTION 3 SUBMITTALS ........................................................................................ 3-1 3.1 SUBMITTAL SCHEDULE............................................................................... 3-1 3.2 PROCESS, REVIEW AND ACCEPTANCE.................................................... 3-1 3.3 STORAGE......................................................................................................... 3-3 SECTION 4 PERFORMANCE MONITORING REQUIREMENTS..................... 4-1 4.1 QUALITY OF LIFE PERFORMANCE STANDARDS .................................. 4-1
January 2007
4.2 POLLUTION PREVENTION........................................................................... 4-2 4.2.1 Stormwater Pollution Prevention and Dust Control................................ 4-2 4.3 REPORTING..................................................................................................... 4-2 SECTION 5 INSPECTION AND VERIFICATION ACTIVITIES ........................ 5-1 5.1 GENERAL CONSTRUCTION INSPECTION AND VERIFICATION REQUIREMENTS............................................................................................. 5-1 5.1.1 Inspections............................................................................................... 5-4 5.1.2 QC Testing............................................................................................... 5-6 5.1.3 QA Testing .............................................................................................. 5-6 5.2 CONSTRUCTION ACCEPTANCE CRITERIA.............................................. 5-7 5.3 CONSTRUCTION AUDITS............................................................................. 5-7 5.4 COMPLIANCE WITH HANDLING, STORAGE, PACKAGING, PRESERVATION, AND DELIVERY REQUIREMENTS .............................. 5-8 5.5 MATERIAL IDENTIFICATION AND TRACEABILITY.............................. 5-8 SECTION 6 CONSTRUCTION DEFICIENCIES .................................................... 6-1 6.1 DEFICIENCY IDENTIFICATION................................................................... 6-1 6.2 CONTRACTOR QC DEFICIENCY IDENTIFICATION AND CONTROL .. 6-1 6.3 NON-CONFORMANCE REPORT .................................................................. 6-2 6.4 CONTRACTOR QC DEFICIENCY CORRECTION ...................................... 6-2 6.5 PREVENTIVE ACTIONS ................................................................................ 6-2 SECTION 7 DOCUMENTATION.............................................................................. 7-1 7.1 DAILY RECORD KEEPING............................................................................ 7-1 7.2 DAILY CONSTRUCTION REPORT............................................................... 7-1 7.3 INSPECTION AND TESTING REPORT FORMS.......................................... 7-2
January 2007
ii
7.4 RECORD DRAWINGS..................................................................................... 7-2 7.4.1 Responsibilities........................................................................................ 7-2 7.4.2 Preparation of As-Built Drawings ........................................................... 7-3 7.4.3 Review of As-Built Drawings ................................................................. 7-3 7.5 CONTROL OF QUALITY RECORDS ............................................................ 7-3 SECTION 8 EPA APPROVALS ................................................................................. 8-1 8.1 REQUIRED SUBMITTALS ............................................................................. 8-1 8.1.1 CQAP ...................................................................................................... 8-1 8.1.2 Phase 1 Work Completion Report........................................................... 8-1 8.2 EPA APPROVAL.............................................................................................. 8-1 SECTION 9 FIELD CHANGES ................................................................................. 9-1 9.1 CQAP CHANGES............................................................................................. 9-1 9.2 QC CHANGES................................................................................................. 9-1 SECTION 10 FINAL REPORTING......................................................................... 10-1 SECTION 11 REFERENCES.................................................................................... 11-1
LIST OF TABLES
Table 1.1 Organization of Phase 1 RA Work Plans........................................................ 1-2 Table 5.1 Sample Inspection and Test Plan .................................................................... 5-2
LIST OF FIGURES
Figure 2.1 Construction Quality Control/Quality Assurance Organization.................... 2-7
January 2007
iii
LIST OF APPENDICES
APPENDIX A SAMPLE QUALIFICATION TEST SCHEDULES APPENDIX B SAMPLE INSPECTION SCHEDULES APPENDIX C SAMPLE TESTING SCHEDULES APPENDIX D TYPICAL CONSTRUCTION FORMS
January 2007
iv
January 2007
January 2007
vi
January 2007
1-1
The remedial action is to be conducted in two phases, designated Phase 1 and Phase 2. Phase 1 is defined as the first year of dredging and will be completed in a portion of River Section 1. Phase 1 also includes preparation of the land-based sediment processing facility. Phase 2 covers the remaining dredging in the three river sections. 1.2 PHASE 1 CONTRACTS DESCRIPTION The project scope for Phase 1 activities will be conducted under at least seven separate contracts (excluding the rail transport and disposal contracts as well as agreements with the originating rail carrier for infrastructure improvements) and three separate Remedial Action Work Plans (RAWPs). The contracts and RAWPs are described below and summarized in Table 1-1. The table also includes the relationship of construction quality assurance (QA), quality control (QC) and health and safety to other Phase 1 activities. Table 1-1. Organization of Phase 1 RA Work Plans
Phase 1 Contract Packages
Contract 1 Facility Site Work Construction Contract 2 Rail Yard Construction RA Work Plan #2 Contract 3A Processing Facility Construction Contract 3B Processing Facility Operation Contract 4 Dredging Operations Contract 5 Habitat Construction Contract 6 Rail Yard Operations Phase 1 Processing Equipment Installation and Remaining Site Work RA Work Plan #3 Phase 1 Dredging and Facility Operations
The activities to be performed under Contract 1 (Facility Site Work Construction) and Contract 2 (Rail Yard Construction) are presented in detail in Sections 2 through 7 of RAWP #1,
January 2007
1-2
The activities to be performed under Contract 3A Processing Equipment Installation will be described in RAWP #2, Remedial Action Work Plan for Phase 1 Processing Equipment Installation and Remaining Site Work. RAWP #2 covers the remaining site work, such as processing facility buildings, and the installation of process equipment, piping, electrical, instrumentation, communications, and the commissioning of the systems. The scope of work under Contract 3B, Contract 4, Contract 5, and Contract 6 will be addressed in RAWP #3, Remedial Action Work Plan Phase 1 Dredging and Processing Facility Operations. Briefly, RAWP #3 covers the following: Contract 3B Processing Facility Operations, including barge offloading, coarse material separation, sediment dewatering, water treatment (process and stormwater), stormwater management, and staging area management and maintenance. In the off season (when the Champlain Canal is closed), the contractor will winterize the processing facility and operate and maintain the stormwater collection and treatment system. Contract 4 Dredging Operations, including resuspension containment system installation, debris removal, the performance of inventory and residual dredging operations and the transport of loaded sediment barges to the off-loading wharf at the processing facility. After dredging is completed in an area, the contractor will place appropriate backfill, cap, or shoreline stabilization structures. Contract 5 Habitat Construction, including the supply and planting of subaquatic vegetation in certain dredged areas pursuant to habitat reconstruction plans. Contract 6 Rail Yard Operations, including all activities required to operate and maintain the rail yard. This primarily will involve the loading of debris, coarse material and dewatered sediment into empty rail cars, setting up of outbound loaded trains, and receiving of inbound empty trains.
1.3 QUALITY PROGRAM OVERVIEW GE's approach to management of the quality of the RA implementation includes a combination of quality control by the contractor and quality assurance by the Construction
January 2007
1-3
This CQAP has been developed in accordance with Section 2.1.2 of the SOW. The contractors are responsible for constructing the work in accordance with the plans and specifications. Each contractor is also responsible for controlling the quality of its work to meet contract plans, specifications, and related requirements. The contractors QC is the systematic implementation of a program of inspections, tests, and production controls to attain the required standards of quality and to preclude problems resulting from noncompliance. Pursuant to Technical Specification Section 01400 Quality Requirements, each contractor will establish an independent QC program and write a Contractor Quality Control Plan (CQCP). The CQCP must provide for tests and inspections pursuant to various technical specifications. It will define procedures to ensure that activities affecting quality are properly documented and accomplished in accordance with contract documents; written instructions; and industry standards, codes and procedures. Furthermore, the CQCP will define methods for ensuring that activities affecting quality will be accomplished under controlled conditions. Independently of the contractors, the construction manager (CM) will provide QA through daily monitoring and scheduled inspections to verify the effectiveness of the contractors QC program and assure that the quality and contract requirements are met by the contractors. The CM assures that the contractors QC is working effectively and that the resultant construction complies with the quality requirements established by the contract. The objectives of this CQAP are to: Describe the quality program and organization to be implemented so that the project is constructed in accordance with the contract requirements and industry standards;
January 2007
1-4
1.4 QUALITY MANAGEMENT PLAN Parsons Engineering of New York, Inc. (Parsons) has been retained to provide construction management services for this project. As GEs managing contractor, Parsons will carry out work on this project in accordance with the Parsons Quality Management Plan (QMP) (Parsons, 2005), which was submitted to EPA on November 1, 2005. 1.5 CQAP ORGANIZATION This CQAP is organized into eleven sections. Section 1 - Introduction: describes the project setting, the Phase 1 contracts and related RAWPs, and the CQAP quality program overview. Section 2 - Project QC/QA Organization: presents the organizations and key personnel involved in the construction of the RA, their responsibilities and authorities, the structure of the QC/QA organization and the minimum training and experience of the Construction Quality Assurance Officer (CQAO) and personnel. Section 3 - Submittals: presents the procedures for processing submittals from Phase 1 contractors and vendors. Section 4 - Performance Monitoring Requirements: addresses QC/QA for performance monitoring requirements applicable to Phase 1 FSWC and PEI. Section 5 - Inspection and Verification Activities: provides procedures for tracking construction inspection and verification activities for the contract, construction acceptance criteria, and construction audits. Section 6 - Construction Deficiencies: describes the procedures for tracking construction deficiencies from identification through acceptable corrective action. Section 7 - Documentation: describes the procedures for the project documents that will be managed through a combination of a secure document filing and storage system and computerized Document Tracking System. Section 8 - EPA Approvals: describes EPA approvals applicable to the Phase 1 FSWC and PEI QC/QA. Section 9 - Field Changes: describes handling of quality plan changes to assure QC/QA objectives are met.
January 2007
1-5
January 2007
1-6
2-1
January 2007
2-2
The CQAO reports directly to the CM. The CQAO will have full authority delegated by the CM and GE to institute actions necessary for the successful implementation of the QC/QA program to ensure compliance with the contract plans and technical specifications (including stop-work authority). The CQAO is assigned to the project full time. The CQAO works with GE to administer and implement the CQAP. This includes controlling this CQAP, making revisions as necessary, and implementing systematic actions to ensure compliance with the plan. The CQAO coordinates activities with the SM to ensure that the FE, inspection staff, third party inspection and testing firms as well as contractor QC staff carry out the requirements of the CQAP.
January 2007
2-3
2-4
The FIs must be alert to detecting, recording, and reporting any deviation from the contract documents, including calling any deficient item to the attention of the FE, the contractors superintendent, and/or other representative. The FIs must keep accurate and detailed records of the contractors performance and progress, delivery of materials, and other pertinent matters, including the daily inspection report. 2.3.2 Contractors Quality Control Personnel QC Systems Manager The QC Systems Manager (QCM) is a full-time employee of the contractor, or a consultant engaged by the contractor. The QCM should have a minimum of five years of experience in related construction and prior QC experience on a project of comparable size and scope to the contractors scope of work on this project. Additional qualifications for the QCM include at least one of the following requirements: PE with one year of related construction experience acceptable to the CM. EIT with two years of related construction experience acceptable to the CM. An individual with three years of related experience acceptable to the CM, with a Bachelor of Science Degree in civil engineering, civil engineering technology, or construction. Construction materials technician certified at Level III by the NICET. The QCM will have full authority to institute any and all actions necessary for the successful implementation of the QC program to ensure compliance with the contract plans and technical specifications. The QCM shall report directly to a responsible officer of the construction contractor. The QCM is assigned to this project full time. QC Technicians The contractor QC Technicians perform the following functions:
January 2007
2-5
Contractor QC Technicians will be engineers, engineering technicians, or experienced craftsmen with qualifications in the appropriate field equivalent to NICET Level II or higher construction materials technician, and will have a minimum of two years of experience in their area of expertise. For inspection of the NY Route 196 intersection construction, QC inspectors must meet NICET Level II or higher certification in highway construction. Certification at an equivalent level by a state or nationally recognized organization will be acceptable in lieu of NICET certification. Additional experience and training may be substituted for educational requirements, subject to GEs approval.
January 2007
2-6
January 2007
2-7
January 2007
3-1
3-2
January 2007
3-3
RAWP #1 includes contractor work plans for meeting these requirements. Please refer to RAWP #1, the QoLPS FSP, and the referenced specifications for more detail on these requirements, the underlying standards, and the monitoring activities that will be performed to verify compliance.
January 2007
4-1
January 2007
4-2
January 2007
5-1
Support excavation Stress Grade, 02201, ref. Fiber stress of Wood sheeting & 2.01 1,200 PSI Bracing
Each approved source, Density, gradation and ASTM D2487, moisture density 02201, ref D698, D1556 & General fill material relationship per 2.01-C D2922 1000 cubic yard, stockpile or inplace source. Backfilling 02201, ref. Compaction & 3.08 Density Control Moisture ASTM D698, Method D
N/A
January 2007
5-2
02201, ref. Backfilling 3.08-2-b ; 02203, ref. Compaction & Density Control 3.01
95% of Max dry density for structure, Method of ASTM Contractors driveways, roods D 1556 or ASTM testing and sidewalk. D2922 laboratory 90% for other areas. 95% of Max dry density Satisfactory material with plasticity index equal to or less than 12 1 per stockpile and source change 1 per stockpile and source change ASTM D698 Contractors testing laboratory Contractors testing laboratory
N/A
Trenching, 02204, ref. backfilling & 3.02 compacting 02205, ref. Select fill/ Non1.03 & expansive soils 1.04-6 Spec. Select fill/Coarse 02205, ref. aggregate (Grain2.01 B size Distribution) Spec. Select fill/ Fine 02205, ref. Aggregate (Grain2.01 B Size Distribution)
7% - 10% verification test 7% - 10% verification test 7% - 10% verification test 7% - 10% verification test
N/A
ASTM D 4318
N/A
Contractors ASTM D 422 or testing C136, size No. 6 laboratory ASTM C136; C33 and as required Contractors by NYSDOT testing laboratory Spec. 703.02, size no. 56 or 67
N/A
N/A
02207, ref. Restoration of 1.02 & surfaces/ Asphalt 3.01 temporary paving
Asphalt concrete NYSDOT Binder plant mix Maintenance 2 compacted 15.403.2001 thick
Provide Mix design for all material to be verification incorporated plant report in the restoration Provide Mix design for all material to be verification incorporated plant report in the restoration Results of all leakage tests shall submit to CM within 2 working days of test completion. Results of all leakage tests shall submit to CM within 2 working days of test completion.
N/A
02207, ref. Restoration of 1.02 & surfaces/ Asphalt 3.01 permanent paving
Asphalt concrete NYSDOT Binder plant mix Standard 4 compacted Specifications thick
N/A
24-hour test, no visible sign of Tests of all leakage on the 02211, ref. hydraulic structures exterior surface 3.01 non-pressure piping and when the water surface does not drop
ASTM C-828
Refer to the table in section 3.03- D for allowable leakage for nonpressure piping.
ASTM C-828
N/A
January 2007
5-3
Rate of leakage has stabilized for ASTM C-828 3 consecutive 15 minutes intervals
Leakage does not exceed one gallon per vertical foot of depth 24 hours.
ASTM C-828
5.1.1 Inspections The contractor shall establish a program for inspection of activities affecting quality and shall cover all construction site and laboratory operations, including both onsite and offsite operations. Inspections shall be performed to verify compliance with documented instructions, drawings, procedures, and specifications as required by the contract. All inspections shall be documented by the contractor as required by Specification Section 01450 3.05. A four-phase inspection program shall be followed for each definable feature of the work. The four phases of inspection are: 1. Preparatory Inspection The contractor and the CM perform preparatory inspections prior to beginning any work on any definable feature of the work. Ensure that preparatory inspections include a review of contract requirements. Ensure that all materials and /or equipment have been tested, submitted, and approved. Ensure that provisions have been made to provide required testing. Examine work area to ascertain that all preliminary work has been completed. Examine materials, equipment, and samples to ensure that they conform to approved shop drawings or submittal data, that all materials and/or equipment are on hand, and that all monitoring and measuring equipment is properly calibrated and in proper working condition. Record preparatory inspections in the contractors QC documentation as required by Specification 01450 Section 3.05.
January 2007
5-4
3. Follow-Up Inspection The contractor and the CM perform follow-up inspections daily. Ensure continuing compliance with Contract requirements. Ensure continuing compliance with control testing until completion of particular feature of work. Contractor CQM records follow-up inspection in daily QC reports. The CM inspection staff records follow-up inspections in their daily inspection report. Conduct final follow-up inspections and correct test deficiencies prior to the addition of new features of work.
4. Completion Inspection The contractor and CM perform a completion inspection of the work. Develop a punch list of items that do not conform to the approved plans and specifications. Include the punch list in the construction QC documentation. As required by Specification 01450, Section 3.05, include the estimated date by which the deficiencies will be corrected. Perform a second completion inspection after punch list items have been completed and the CM has been notified by the contractor.
The daily inspection reports shall identify inspections conducted, results of inspections, location and nature of defects found, causes for rejection, and remedial or corrective action taken or proposed. Additional QA inspections may include inspection of third-party lab testing facilities, fabrication facilities, and suppliers. Other inspections outside of the four-phase program described above will be ordered or performed by the CM to verify compliance with building
January 2007
5-5
5-6
QA testing shall be performed in accordance with the following: The CQAO shall develop a weekly quality test and inspection schedule using the construction activity forecast as a guide. The schedule shall: Identify the QA test activities. Identify the hold points The weekly quality test schedule shall be distributed to the CM and CM field staff. The contractor shall be provided a one-day advance notice of impending hold points. Field Inspectors conducting the quality tests and inspections shall complete the Daily Construction Report included in Appendix D. The Daily Construction Report shall be distributed to the CQAO, FE, CM Site Manager, GE managers, contractor PM and/or QC Systems Manager. The CQAO will review QA tests and maintain files for all field QA documentation, 5.2 CONSTRUCTION ACCEPTANCE CRITERIA Construction acceptance criteria for materials qualifications, inspection, and testing are established by technical specifications as illustrated in the example QC tables included in Appendices A (materials qualifications), B (inspection), and C (testing). Criteria for materials and equipment have been set by the Engineer of Record in accordance with the applicable codes and standards, and by manufacturers recommendations. Contractor submittals are to document conformance with acceptance criteria as detailed in their CQCP (control, verification, and acceptance testing plan). 5.3 CONSTRUCTION AUDITS The contractor shall establish and document an auditing system to verify their (or their sub contractors) implementation of and conformance to the CQCP and contract technical specification requirements. The auditing system shall be used to make a determination regarding the effectiveness of the QC system. The contractors auditing shall be planned, performed and documented in accordance with written instructions, procedures or checks to be included in the CQCP. The audit scope, frequency and methods shall be defined in the CQCP. Audits shall be performed by qualified and properly trained personnel who are familiar with the QC system, auditing procedures and techniques. Selection of auditors and the conduct of audits shall ensure the objectivity and
January 2007
5-7
January 2007
5-8
January 2007
6-1
6-2
January 2007
6-3
7-1
7.4 RECORD DRAWINGS Contractors will submit draft record drawings to the CM for review and prepare final record drawings based on CM comments. The draft record drawings shall be submitted on one set of CD-ROM disks. Record drawings submitted on CD-ROM shall be the latest version of AutoCAD by AutoDesk, Inc. 7.4.1 Responsibilities The CM working with the contractor will be responsible for assuring that red-line record drawings are maintained daily throughout the construction process. These red-line record
January 2007
7-2
These records will be stored in files maintained in the project document control files. All original documents pertaining to project information will be maintained in the project file located at the project office in Fort Edward, New York. The CM and SM have primary responsibility for the centralized document control files for the project and construction documentation. Pursuant to the contract specifications, the contractor provides an electronic or paper copy (suitable for scanning) of QC documentation associated with the work to document control within three business days of the generation of such documents; and one electronic copy of all required submittals to CMs document manager. All contractors shall maintain a fire-resistant storage facility at the processing facility site. The facility shall contain all inspection reports, test records, contract documents, project, and daily field reports.
January 2007
7-3
January 2007
7-4
EPA will not modify a submission without providing at least one notice of deficiency and 21 days to correct the deficiency. Following the correction process, the plan, report, or other item will be resubmitted for approval.
January 2007
8-1
January 2007
9-1
January 2007
10-1
United States Environmental Protection Agency and General Electric Company. 2003. Administrative Order on Consent for Hudson River Remedial Design and Cost Recovery. Index No. CERCLA-02-2003- 2027. United States Environmental Protection Agency and General Electric Company. 2005. Consent Decree in United States v. General Electric Company, Civil Action No. 1:05-cv-1270, lodged in United States District Court for the Northern District of New York October 6, 2005; final judgment entered November 2, 2006.
January 2007
11-1
January 2007
1-26-2007___ Date
January 2007
Firm
Parsons
Years of Experience 24 Education University of Alabama, Birmingham, 1983: Bachelor of Science in Civil Engineering ISO 9001:2000 Lead Auditor Course Certificate No. 4573341-26429 Certificate of Quality Assurance and Quality Control in Transit Projects 2005 Training Certificate from Corp of Engineers Construction Quality Management for Contractors 2001 Training Certificate - OSHA update Seminar 1995 Training Certificate - 100% Fall Management 1994 Certificate of Completion NUCA Competent Person 1994: NUCA Confined Space Entry Program Courses for Computer (PC), Windows XP, MS Office 2000 Affiliations American Society of Civil Engineers Special Skills Fluent in Arabic, English.
Senior Quality Assurance Engineer/QA Manager PARCOMM & PTG/ South Corridor Light Rail projectCharlotte, NC
Conducting internal project technical quality audits and presents audit reports to management and project team. Responsible for scheduling audits; preparing the audit checklists; conducting the pre-audit meeting; issuing findings (when required); preparing and issuing the final audit report, recommending opportunities for improvement; and following up to verify that the appropriate corrective actions have been completed. Responsibilities include implementation and maintenance of design quality management plan and procedures; auditing of design QA/QC activities to ensure conformance with the project requirements and certifying that all design submittals have been processed in accordance with the project quality management plan. Senior Quality Assurance Engineer Responsible for conducting quality assurance audits for the following programs and projects: Northrop Grumman Ship Systems - Construction Management - Facility Modernization Gulfport & Pascagoula MS. And New Orleans, LA. Evaluation of alternatives for South Effluent Treater (SET) Shell Project - Environmental Remediation Project Houston, TX. EMAAR Development Project, Emirates Hills, Construction Management- Dubai, UAE. Wastewater treatment and reuse system at Amgens Juncos - Construction Performance Support Services - Puerto Rico biotech plant.
January 2007
Test Parameter Soil Classification Atterberg Limits Grain- Size Distribution Moisture Content
Test Method ASTM D2487 ASTM D4318 ASTM D422 or C136 ASTM D2216/ D2974
Minimum QC Testing Frequency by contractor 1 per 1,000 cubic yard and source change 1 per 1,000 cubic yard and source change 1 per 1,000 cubic yard and source change 1 per 1,000 cubic yard and source change
Acceptance Criteria (verified by QA) GW, GP, GM, GC, SW, SP, SM, SC, or ML In accordance with Section 02205 In accordance with Section 02205. Article 2.01.I In accordance with Section 02201 through 02205 and Section 02911
Notes: 1. Borrow soil must be from approved on-site borrow source with test results provided in Section 02205. Any change in material must be consistent with approved material characteristics as determined by CM. New moisture content curves will need to be plotted for change in material. 2. Note: this table is for illustration only and is not intended to replace or modify contract specifications that will form the basis of actual CQCP submittals by contractors
January 2007
Page A1
Test Method
1 per stockpile and In accordance with table source change in Article 2.01B in Section 02205 1 per stockpile and As reported for source change establishing the range of optimum moisture content 1 per stockpile and As reported for source change establishing the range of optimum compaction
Moisture Content
ASTM D1557
1 per stockpile and In accordance with table source change in Article 2.01 B in Section 02205 1 per stockpile and As reported for source change establishing the range of optimum moisture content
Moisture Content
1 per stockpile and As reported for source change establishing the range of optimum compaction Note: this table is for illustration only and is not intended to replace or modify contract specifications that will form the basis of actual CQCP submittals by contractors
Compaction Characteristics
ASTM D1557
January 2007
Page A2
Test Method
ASTM C150
Fluidized Bed Ash In accordance with tables in ASTM C311 for Class F material, except loss on ignition shall not exceed 4% Note: this table is for illustration only and is not intended to replace or modify contract specifications that will form the basis of actual CQCP submittals by contractors. Chemical & Physical Requirements ASTM C311 Prior to use in concrete mix in absence of material certification
January 2007
Page A3
Test Method ASTM C136; C33 and as required by NYSDOT Specification 703.02
Minimum QC Testing Frequency by Contractor Prior to use in concrete mix and whenever character or source is changed
Acceptance Criteria (verified by QA) Max coarse aggregate size of No. 57 or 67 gradation per ASTM C33. Fine aggregate shall pass No. 4 sieve, gradation to conform with ASTM C33 and NYSDOT as specified in Article 2.01- C in Section 03001 Fine aggregate not darker than reference standard color per ASTM C40. Sand exhibiting a color darker than the referenced color shall be rejected. Loss resulting after 5 cycles not to exceed 8% for coarse aggregate or 10% for fine aggregate when using sodium sulfate solution or 11% for coarse aggregate or 14% for fine aggregate when using magnesium sulfate per ASTM C33 Loss not to exceed 10.5% after 100 revolutions, 42% after 500 revolutions
Organic Impurities
ASTM C40
Prior to use in concrete mix and whenever character or source is changed Prior to use in concrete mix and whenever character or source is changed
Soundness
ASTM C33
Abrasion
ASTM C131
Prior to use in concrete mix and whenever character or source is changed Prior to use in concrete mix and whenever character or source is changed
Deleterious Materials
ASTM C33
January 2007
Page A4
Minimum QC Testing Frequency by Contractor Prior to use in concrete mix and whenever character or source is changed Prior to use in concrete mix and whenever character or source is changed Prior to use in concrete mix and whenever character or source is changed
Acceptance Criteria (verified by QA) Not to exceed 1% for gravel or 1.5% for crushed aggregate per ASTM C33 Aggregates considered innocuous in accordance with ASTM C289
Alkali Reactivity
ASTM C227
Quality not less than 75 for average of three Specification identical samples nor less 703.02 than 70 for an individual sample Note: this table is for illustration only and is not intended to replace or modify contract specifications that will form the basis of actual CQCP submittals by contractors
NYSDOT
January 2007
Page A5
Minimum QC Testing Frequency by Contractor Preliminary testing of mix design; test at 28 days
Acceptance Criteria (verified by QA) Min 5000 PSI Min 4000 PSI Min 3000 PSI Min 2500 PSI
Water/Cement Ratio
Limit to 0.35, 0.45,0.58 and max by weight accordance with section 03001 article 2.05 All concrete not containing a high range water-reducing admixture (super plasticizer) shall conform to these Max. slump values: Reinforced concretegeneral 4, Non-reinforced concrete 3, pavement, sidewalk 3, Slab on grade 3 and Floor toppings 2.
Slump Test
ASTM C143
Notes 1. Preliminary testing of the mix design will be performed by Construction Contractors Independent Testing Laboratory (Third Party lab services). 2. This table is for illustration only and is not intended to replace or modify contract specifications that will form the basis of actual CQCP submittals by contractors
January 2007
Page A6
January 2007
Inspection Parameter Soil Texture and Color Presence of Foreign Objects and Materials Maximum Clod Size Equipment Size and Type Method of Placement Lift Thickness for Earthen Berm
Acceptance Criteria (verified by QA) Similar to approved material Free of visible contamination, organic material, rubbish, debris, and other unsatisfactory materials No fragments larger than 3-inch that will not breakdown under hand compression. In accordance with approved Work Plan In accordance with approved Work Plan First lift 12-inch max. loose, subsequent lifts 8-inch max. loose, final lift 4-inch max loose, hand placed lifts 3-inch max. loose Max. 8-inch loose per lift
1 per lift
Note: this table is for illustration only and is not intended to replace or modify contract specifications that will form the basis of actual CQCP submittals by contractors
January 2007
Page B1
Inspection Parameter Coarse Aggregate Material Characteristic Maximum Size Equipment Size and Type Method of Placement Lift Thickness Fine Aggregate Material Characteristic Maximum Size Equipment Size and Type Method of Aggregate Placement
NYSDOT Type 2, may include up to 50% of reclaimed materials 1 -inch In accordance with approved Work Plan In accordance with approved Work Plan 8-inch loose per lift
NYSDOT Type 2, may include up to 50% of reclaimed materials -inch In accordance with approved Work Plan In accordance with approved Work Plan
Lift Thickness 1 per lift Min. 8-inch loose per lift Note: this table is for illustration only and is not intended to replace or modify contract specifications that will form the basis of actual CQCP submittals by contractors
January 2007
Page B2
Acceptance Criteria (verified by QA) Inspect piles for excessive camber and sweep and damage before transporting them from the storage area to driving area. Max permissible camber and / or sweep shall be 2-inch over the length of the pile. In accordance with approved Work Plan, the impact hammers shall be steam, air or diesel-power pile hammers of single-acting, double-acting. The rate driving energy of hammers shall be limited to minimum of 30,000 foot-pounds. The refusal criteria, hard driving in excess of 20 blows per 25mm inch and accordance with Section 02315 Article 3.01. A final variation in rotation of the pile about the center line of the web of not more than 7.5 degrees will be permitted. A vertical deviation of not more than 1-inch from the correct cutoff elevation shown will be permitted. Max 1-inch heave, otherwise re-drive piles to original elevations
Size
Daily
Alignment
Heave Checks
After driving first pile group and on selected pile groups as directed by CMs Geotechnical Engineer After driving each production pile
Production Piles
Piles damaged or not located properly or exceeding the maximum limits for rotation, lateral and vertical deviation, or variation in alignment shall be pulled and new piles redrive, or provide additional piles, at a location directed at no additional cost to the Owner. 1. Inspection will be performed by Contractor QC and verified by CM staff & QA staff. 2. This schedule is for illustration only and is not intended to replace or modify contract specifications that will form the basis of actual CQCP submittals by contractors.
January 2007
Page B3
Inspection Parameter Reinforcing Material Condition Reinforcing Bundle Identification Reinforcing Material Storage In-Place Reinforcing
Minimum QC Inspection Frequency by Contractor Upon receipt at Site Upon receipt at Site Daily Prior to closing forms and continuous during pouring Prior to pouring of concrete
Acceptance Criteria (verified by QA) No visible defects or damage, no unscheduled kinks or bends Bundled and tagged with information as specified in Section 03200 In accordance with Manufacturers recommendations & approved Work Plan In accordance with approved Work Plan, free of old mortar, oils, mill scale and other encrustations or coatings In accordance with approved Work Plan; no excess water, hardened concrete, debris or foreign materials inside of forms, wet wood forms sufficiently to tighten up cracks Load accompanied by weightmaster bonded certificate, water container full, water added to concrete mixture in accordance with Section 03301
In-Place Formwork
Concrete Truck
Prior to pouring of Fine grade earth and aggregate smooth concrete and level Note: this table is for illustration only and is not intended to replace or modify contract specifications that will form the basis of actual CQCP submittals by contractors
Subgrade Preparation
January 2007
Page B4
Acceptance Criteria (verified by QA) In accordance with approved Work Plan, height of concrete drop not to exceed 5 feet, place and compact within 60 minutes after water is first added, do not place after evidence of initial set In accordance with approved Work Plan Max. 18 inches per lift in continuous approximately horizontal layers 1/4-inch from 10-foot straightedge for exposed finishes, no low spots to impound water Forms maintained in wet condition until removed, concrete continuously moist for min of 7 days after pouring Fill holes and patch surfaces in accordance with Section 03301
Continuous during pouring of concrete Continuous during pouring of concrete Continuous during compaction of concrete Daily during curing of concrete After finishing of concrete
Slabs and Flatwork Daily during curing of Concrete continuously wet for entire Curing concrete curing period Note: this table is for illustration only and is not intended to replace or modify contract specifications that will form the basis of actual CQCP submittals by contractors
January 2007
Page B5
January 2007
Test Parameter Compaction for Earthen Berm Compaction for all other applications In-Place Density
Acceptance Criteria (verified by QA) 90% max. dry density in accordance with ASTM D1557 95% max. dry density in accordance with ASTM D1557 In accordance with ASTM 2922 +/- 2% of optimum moisture content in accordance with Attachments 02200-1 through 02200-4
ASTM D1557
1 per lift
1 per compacted lift but not less than 1 per 2,500 SF 1 per compacted lift but not less than 1 per 2,500 SF
1. Borrow soil must be from approved on-site borrow source with test results provided in Section 02200. Any change in material must be consistent with the approved material characteristics as determined by the Construction Manager. New moisture content curves will need to be plotted for change in material
2.
Note: this table is for illustration only and is not intended to replace or modify contract specifications that will form the basis of actual CQCP submittals by contractors
January 2007
Page C1
Test Method
ASTM D1557
95% max. dry density in accordance with ASTM D1557 In accordance with ASTM D2922 +/- 1% of optimum moisture content in accordance with ASTM D3017
Fine Aggregate Compaction ASTM D1557 1 per compacted lift 95% max. dry density in accordance with ASTM D1557 In accordance with ASTM D2922
+/- 1% of optimum moisture content in accordance with ASTM D3017/ D2974 Note: this table is for illustration only and is not intended to replace or modify contract specifications that will form the basis of actual CQCP submittals by contractors
January 2007
Page C2
A compressive load of 300% of design load shall be applied to each compressive load test pile. Note: this table is for illustration only and is not intended to replace or modify contract specifications that will form the basis of actual CQCP submittals by contractors
January 2007
Page C3
Acceptance Criteria (verified by QA) Min 5000 psi Min 4000 psi Min 3000 psi Min 2500 psi
When compression test cylinders are cast When compression test cylinders are cast
In accordance with ASTM C231 or C172 In accordance with ASTM C143. Slump values:
Reinforced concretegeneral 4 inches, Nonreinforced concrete 3 inches, pavement, sidewalk 3 inches, Slab on grade 3 inches and Floor toppings 2 inches. Note: this table is for illustration only and is not intended to replace or modify contract specifications that will form the basis of actual CQCP submittals by contractors
January 2007
Page C4
January 2007
The following typical forms are included in this appendix: D-1 D-2 D-3 D-4 D-5 D-6 D-7 D-8 D-9 Daily Construction Report Quality Inspection Report Receiving Inspection Report (Not Used) Field Inspection Checklist Earthwork Field Inspection Checklist Solidification Field Inspection Checklist Structural Steel Erection Daily Concrete Inspection Report Concrete Placement Checklist Field Inspection Checklist Placing, Consolidation, Finishing, Curing and Repair of Concrete
D-10 Field Inspection Checklist Pre-Cast and Cast-in-Place Concrete Piles D-11 Field Inspection Checklist Critical Piping D-12 Electrical Inspection/Test Sheet Ground Rod Earth Resistance Test D-13 Electrical Inspection/Test Sheet Ground Grid Earth Resistance Test D-14 Electrical Inspection/Test Sheet Light Installation D-15 Electrical Inspection/Test Sheet Combination Starter, PB and Selector Switches Control System Components D-16 Electrical Inspection/Test Sheet Continuity Test of all Fixture Bodies to Ground D-17 Electrical Inspection/Test Sheet Cable Test Procedures D-18 Electrical Inspection/Test Sheet Conduit and Junction/Outlet Boxes Installation D-19 Electrical Inspection/Test Sheet Cable and Cable Accessories/Panelboard/ Wiring Devices D-20 Electrical Inspection/Test Sheet Electrical Service and Distribution System D-21 Electrical Inspection/Test Sheet Molded Case Circuit Breaker Test Record
January 2007
D-22 Electrical Inspection/Test Sheet Cable Test Record D-23 Electrical Inspection/Test Sheet Motor Test Record D-24 Inspection Notification Form D-25 Non-conformance Report D-26 Non-conformance Report Log D-27 Contractor Non-Conformance Letter (Sample) The format, layout, content and method used to fill out the forms will be reviewed periodically during the course of construction and modified as required to ensure that the necessary information required for management of the construction contracts and controlling the progress and quality of the work is being obtained.
January 2007
Parsons
DAILY CONSTRUCTION REPORT PHASE 1 FACILITY SITE WORK CONSTRUCTION/ HUDSON RIVER
DAILY CONSTRUCTION REPORT
REPORT NO. DATE:
Page of
WEATHER CONDITION:
Hi
CONTRACTORS SUPERINTENDENT: SUBCONTRACTORS (*):
AM / PM f / Lo f
INCH(S)
0000AM
CLASSIFI CATION
0:00 PM
HOU RS
NAME / COMPANY
EQUIPMENT
TIMES:
START
STOP
0000AM
0:00 PM
MEETING:
D-1
Parsons
DAILY CONSTRUCTION REPORT PHASE 1 FACILITY SITE WORK CONSTRUCTION/ HUDSON RIVER WORK PERFORMED Work started at 00:00 am.
CONSTRUCTION ACTIVITIES COMPLETED AND /OR IN PROGRESS:
PROGRESS PHOTOS:
Departed job site at 00:00 pm. Visitors: Inspector Name: Field Engineer Name: Signature: Signature:
D-1
Project
Page of 1/1
DESCRIPTION/INTENT OF INSPECTION: _____________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ COMPONENTS/MATERIALS REVIEWED: ____________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ CONTRACTOR PERSONNEL CONTACTED: __________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ APPLICABLE CONTRACTOR PROCEDURES, CHECK LISTS, INSTRUCTIONS: ____________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ RESULTS OF INSPECTION: _________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ DEFICIENCIES NOTED: ____________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ RECOMMENDED CORRECTIVE ACTION: ____________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ NON-CONFORMANCES: ___________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________
QA Inspector Signature:
Date:
D-2
Project
Page of 1/1
DRAWING ___________________
SUPPLIER _________________________________
ITEM ____________________
QUANTITY ____________
DOCUMENTATION
DOCUMENTS COMPLETE PER CONTRACTUAL REQTS: __________________ DOCUMENTS TRACEABLE TO ITEMS RECD: _______________
LEGIBLE: ________________
LIST DOCUMENT PKG. DISCREPANCIES (IF ANY): ___________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ RESOLUTION: ____________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ DOCUMENT PKG. ACCEPTABLE: ________________ QC SIGNATURE: _________________________________ DATE: __________________________________________ REMARKS: _______________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________
PHYSICAL INSPECTION
ENTER SERIAL AND/OR HEAT NO: _________________________________________________________________ RESULTS OF INSPECTION: _________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ DEFICIENCY NO. (IF ANY): _____________________ DEFICIENCY RESOLVED: _________________________
QC SIGNATURE: ____________________________________________________
DATE: _____________________
D-3
Project
Page of 1/2
CONTRACTOR: ______________________________________________
REFERENCES (DRAWING, SPECIFICATION, PROCEDURE): _____________________________________________ ATTRIBUTE A 1. 2. 3. 4. 5. GENERAL Is area released for work? Is equipment adequate? Are existing structures and utilities adequately protected? Is removed material properly dispositioned? Dust and dirt control: a) Haul routes maintained for dust control by water or chemicals? b) All paved areas kept clean? B 1. 2. 3. C 1. EXCAVATION OF TRENCHING Does completed depth and configuration comply with drawings and specifications? Required shoring and bracing in place? Existing utilities protected? PLACING AND COMPACTING FILL Excavation properly compacted and verified by test lab? a) All sleeves, pipe cable, grounding, conduit installed and approved? 2. 3. 4. 5. D 1. Approved fill material is used? Is fill being placed in level lifts within thickness limits? Is proper compaction attained and verified by test lab? Have contaminated (and spongy) areas been cut out, filled and compacted with approved material? BEDDING AND BACKFILL OF PIPE AND UTILITY TRENCHES Approved bedding and backfill material is used? a) Is bedding fully compacted to support pipe or utility at line, grade, and slope required and verified by inspector? E 1. GRADING Approved grading material used? a) Final shaping/compacting and blade and 3-wheel rollers of 8-10 ton? 2. Sufficient slope for positive drainage away from structures to drainage system? YES NO N/A
D-4
Project
Page of 2/2
CONTRACTOR: ______________________________________________
ATTRIBUTE 3. 4. Is rough grading reasonably even and free of irregularity and allowance made for finish grading? Is finished grade: a) Cleaned of all loose and foreign material? b) Smooth and even in profile (= 1 in 10) and not more than 1 from true elevation?
YES
NO
N/A
REMARKS: _______________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________
QC SIGNATURE: ____________________________________________________
DATE: _____________________
D-4
Project
Page of 1/1
CONTRACTOR: ______________________________________________
ATTRIBUTE A 1. 2. 3. 4. 5. B 1. GENERAL Is area released for work? Is equipment adequate? Adequate dust control maintained? Appropriate mix proportions? Appropriate mixing time and speed? SAMPLING AND TESTING Collection, curing and testing in accordance with requirements?
YES
NO
N/A
REMARKS: _______________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________
QC SIGNATURE: ____________________________________________________
DATE: _____________________
D-5
Job Number Field Inspection Checklist Structural Steel Erection CONTRACTOR: ______________________________________________
Project
Page of 1/2
REFERENCES (DRAWING, SPECIFICATION, PROCEDURE): _____________________________________________ ATTRIBUTE A 1. 2. 3. 4. 5. B 1. 2. 3. 4. 5. 6. 7. 8. C 1. 2. 3. 4. D 1. 2. 3. 4. 5. STORAGE Storage provided adequate? Drainage provided? Steel properly blocked and stacked? Evidence of excessive rusting? Faying surfaces properly protected? High strength bolting segregated from common fasteners? BOLTING Bolts, nuts, washers square with mating surface? No paint or foreign material on contact surfaces? Correct material and size used on high strength connections? Evidence of distorted metal or enlarged bolt holes from improper alignment? Evidence of enlarging holes by burning? High strength bolts torqued to specification requirements? Means provided to indicate which joints/bolts have been torqued? periodically calibrated? Torque wrench YES NO N/A
Status of completed high strength connections recorded on drawings and appropriate records? ERECTION Members accurately shimmed, wedged, plumbed and aligned prior to final connection? Shims used are actual shim stock? Entry holes through members are authorized by drawing? Anchor bolts proper size, setting and location? WELDING Welders, weld procedures qualified to requirements of AWS D1.1, Structural Welding Code, Section 5? Qualifications records available maintained? Correct weld wire, size and type, used? Correct weld machine settings used? Weld joints properly prepared, aligned, free from cracks, scale, grease, etc. prior to welding?
D-6
Project
Page of 2/2
CONTRACTOR: ______________________________________________
ATTRIBUTE 6. 7. 8. 9. 10. 11. E 1. 2. 3. 4. Root opening tolerances not exceeded? Pre-heat and interpass temperature requirements complied with? Repair of defective welds performed to approved weld procedure requirements? Completed welds meet the visual and dimensional requirements? Weld filler material returned to storage at close of shift? Records for weld inspection prepared and retained? PAINTING Temporary braces, clips, etc. removed prior to painting or field touch-up? Weld splatter, slag removed prior to touch up? Damaged paint area properly prepared and touched up? Correct primer used?
YES
NO
N/A
REMARKS: _______________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________
QC SIGNATURE: ____________________________________________________
DATE: _____________________
D-6
Project
Page of 1/1
CONTRACTOR: ______________________________________________________________________________________________ SPECIFIC LOCATION: AREA OR BUILDING ____________________________________________ STATION: ______________________ T/OFFS: _________________________ TO STATION: _______________________ ELEVATION: _______________________ MIX NO: _____________ LIFT NO: ______________
ADDITIVES: ___________________________
TYPE OF DELIVERY: _________________________________________________________________________________________ DELIVERY EQUIPMENT IDENTIFICATION/NUMBER: ____________________________________________________________ PLACEMENT STARTED: PLACEMENT COMPLETED: DATE _______________________ DATE _______________________ TIME ________________ TIME ________________ SHIFT ___________________ SHIFT ___________________
WEATHER CONDITIONS: _____________________________________________________________________________________ TOTAL CONCRETE PLACED: __________________________________________________________________________________ TOTAL CONCRETE WASTED: _______________ REASON: ______________________________________________________
BATCH TICKET NOs: _________________________________________________________________________________________ AVERAGE SLUMP: ______________________ TEMPERATURE: ______________ % AIR CONTENT: _________________
TEST CYLINDERS PREPARED: ________________________________________________________________________________ TRUCK IDENT: ____________________ TOTAL CYLINDERS: _________________ CYL IDENT: ____________________
TYPE CONVEYANCE USED: __________________________________________________________________________________ SURFACE CONDITION PRIOR TO PLACING: ____________________________________________________________________ MAXIMUM FREE FALL OF CONCRETE: _______________________ AMOUNT VIBRATORS: ______________________________ PROPER CONSOLIDATION: _____________________
REINFORCING DISTURBED/REPLACED/REPAIRED: _____________________________________________________________ TYPE FINISH SPECIFIED: _____________________________________________________________________________________ FINISHING STARTED: FINISHING COMPLETED: DATE ______________________ DATE ______________________ TIME ________________ TIME ________________ SHIFT ______________________ SHIFT ______________________
CONDITION OF FINISH: ______________________________________________________________________________________ TYPE OF CURING: ___________________________________________________________________________________________ DELAYS (INDICATE TYPE AND REASON: PERSONNEL, EQUIPMENT OR PLANNING): _______________________________ _____________________________________________________________________________________________________________ _____________________________________________________________________________________________________________ _____________________________________________________________________________________________________________ OBSERVATIONS/REMARKS: __________________________________________________________________________________ _____________________________________________________________________________________________________________ _____________________________________________________________________________________________________________ _____________________________________________________________________________________________________________ CONCRETE INSPECTOR: _______________________________________________________ DATE: _____________________
D-7
Project
Page of 1/1
CONTRACTOR _______________________________________________________________________________________________ SPECIFIC LOCATION: AREA OR BUILDING __________________________ STATION _________________________ T/OFFS. ________________________ CONCRETE TYPE _______________ LIFT NO. ___________ SHIFT ____________
ADDITIVES ________________
REPLACEMENT VERIFICATION 1. ELECTRICAL SUPERVISOR: ITEMS TO BE CHECKED CABLES/GROUND WIRE CONDUIT BOXES REV. ________ OTHER __________ DATE
___________________________ SIGNATURE
2. MECH./PIPING SUPERVISOR: ITEMS TO BE CHECKED MECHANICAL INSERTS PIPING SLEEVES MECH. FRAMES REV. ________ OTHER __________ DATE
___________________________ SIGNATURE
3. CIVIL/STRUCT. SUPERVISOR: ITEMS TO BE CHECKED ROCK CROSS SECTIONS TAKEN SCREEDS SET FORMS ALIGNMENT INTERIOR SURFACE BRACING/SHORING RELEASE AGENT ROCK SURFACES PREPARED LINE AND GRADE ESTABLISHED REINFORCING STEEL CORRECT SIZE/GRADE LAPS. ADEQ. SECURED WATER STOPS LOCATION LEAN
PLACEMENT/CONSOLIDATION EQUIPMENT AVAILABLE/ADEQUATE SAFETY PRECAUTIONS OBSERVED FINAL CLEANING ACCEPTABLE COMPLETE/ACCEPTABLE TO DRAWING _____________ REV. ________ ___________________________ SIGNATURE QUALITY CONTROL INSPECTION VERIFICATION ___________________________ SIGNATURE __________ DATE __________ DATE ICE, SNOW, WATER REMOVED
OBSERVATIONS/REMARKS ___________________________________________________________________________________ _____________________________________________________________________________________________________________ AUTHORIZATION FOR PLACEMENT ___________________________________________ CONSTRUCTION MANAGER _________________ DATE
D-8
Job Number Field Inspection Checklist Placing, Consolidation, Finishing, Curing and Repair of Concrete CONTRACTOR: ______________________________________________
Project
Page of
REFERENCES (DRAWING, SPECIFICATION, PROCEDURE): _____________________________________________ ATTRIBUTE A 1. 2. 3. 4. 5. 6. 7. B 1. 2. 3. PLACING Pre-placement checklist completed? Placement authorized? Concreting surfaces cleaned, moistened when required? Conveying equipment suitable for placement? Conveying equipment clean, properly maintained? Vertical drop limits not exceeded? Horizontal layers not exceeding two-feet in depth? Flow of placement per sketch details? CONSOLIDATION Vibrators previously tested and approved? Systematic pattern used during vibration? Vibrators: a) b) c) d) C 1. 2. 3. 4. D 1. 2. 3. 4. 5. Penetrating previous layer? Not used for horizontal movement of concrete? Withdrawn slowly? Not over vibrating? YES NO N/A
FINISHING Surface top properly screened, when required? Finishing tools used for intended purpose? Desired finish obtained? Even, smooth and level? Joints, edges, corners properly finished? CURING Forms left in place per construction specifications requirements? Curing operations started immediately, adequate? Curing protection periodically checked and maintained? Curing is continuous to specified length of curing process? Traffic and loading over surfaces controlled during curing?
D-9
Job Number Field Inspection Checklist Placing, Consolidation, Finishing, Curing and Repair of Concrete
Project
Page of 2/2
CONTRACTOR: ______________________________________________
ATTRIBUTE E 1. 2. 3. REPAIR Surfaces inspected? Serious defects documented? Cosmetic repairs made? Structural defects repaired in accordance with approved procedures?
YES
NO
N/A
REMARKS: _______________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________
QC SIGNATURE: ____________________________________________________
DATE: _____________________
D-9
Job Number Field Inspection Checklist Pre-Cast Concrete Piles CONTRACTOR: ______________________________________________
Project
Page of 1/2
REFERENCES (DRAWING, SPECIFICATION, PROCEDURE): _____________________________________________ ATTRIBUTE 1. Receipt inspection performed including: a) Dimensions? b) Visual? c) Material test reports for cement, concrete, reinforcing steel, shells, mix test reports, etc.? d) Reinforcing steel for spacing, clearance, size, dowel and tendon extensions? 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. 20. Piles properly handled, stored, and placed? Safety conditions observed? Contractors approved procedures complied with? Test piles required? Driven? Definition of refusal understood, pre-drilling required? Jetting allowed? Proper protection, pre-cautions taken for adjacent structures, utilities? Piles properly placed, sequenced according to plan, and plumb? Splices properly prepared, completed? Piles driven without interruption, driven to required depth to obtain bearing capacity? Piles, shells damaged during driving? Mis-aligned? Over-driven? Tops deformed? Inside properly cleaned, cross section verified, bottom interior cleaned of loose materials? Concrete delivery method approved? (tremie, pump, limited free fall) Concrete fill placed in single, uninterrupted operation? Top of pile properly consolidated? Volume of concrete properly measured and checked? Concrete properly cured, protected from freezing and physical damage? Piles cut-off to specified elevation? Cut-off level? Load test (if required) performed to approved procedures? Load test results evaluated, approved? Contractors Daily Report includes: a) Identification of Contractors Supervisory personnel? b) Pile type, length, splices, location, calculated safe load? c) Penetration under last five hammer blows? YES NO N/A
D-10
Job Number Field Inspection Checklist Pre-Cast and Cast-In-Place Concrete Piles
Project
Page of 2/2
CONTRACTOR: ______________________________________________
ATTRIBUTE d) Unusual conditions, obstructions, replaced piles, etc.? e) Results of tests, if any? 21. Inspectors records include: a) Make, model of hammer b) Energy source c) Weight of striking parts d) Height of fall of striking parts e) Weight of pile f) Blows per unit of penetration
YES
NO
N/A
REMARKS: _______________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________
QC SIGNATURE: ____________________________________________________
DATE: _____________________
D-10
Job Number Field Inspection Checklist Critical Piping Assembly Inspection Test CONTRACTOR: ______________________________________________
Project
Page of 1/2
REFERENCES (DRAWING, SPECIFICATION, PROCEDURE): _____________________________________________ ATTRIBUTE A 1. 2. 3. 4. B 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. C 1. STORAGE Assemblies, fittings, etc. stored/protected per procedure requirements? Pipe caps and plugs taped in place? Assemblies properly shored to prevent damage/deterioration? Material segregated, when required? IN-PROCESS Welders qualified, certified? Qualification records current? Welders using qualified procedure? Weld wire control adequate? Correct type and size? Welding machine settings within procedure requirements? Welders applying individual identification on welded joints? Unused weld wire returned to proper storage? Weld preps per ANSI B31.1 and procedure requirements? Weld root opening within tolerance? Weld joint alignment within tolerance? Pre-heat applied properly? Visual and dimensional inspection performed? Heat treatment performed to procedure requirements? Weld adequately prepared for nondestructive examination? NDE performed, evaluated, documented to procedure requirements? NDE operator qualified/certified? Qualification records current? Defective welds adequately repaired, retested and records updated? Open pipe ends protected during and after installation? Valves, valve internals protected during welding? FINAL Bolted flanges: a) Face to face opening consistent? b) Gasket properly compressed? YES NO N/A
D-11
Job Number Field Inspection Checklist Critical Piping Assembly Inspection Test
Project
Page of 2/2
CONTRACTOR: ______________________________________________
ATTRIBUTE c) Bolts/studs correct material? d) Bolts/studs completely engaging nuts? 2. 3. 4. 5. 6. 7. Completed weld records properly filed, maintained? Authorized Inspector notified of ASME designated hold points? System properly prepared and supported for hydrostatic testing? ASME Code Data Report completed? Approved by authorized inspector? Temporary attachments removed after hydrostatic testing? System restored to normal? Completed system cleaned per specification and procedure requirements?
YES
NO
N/A
REMARKS: _______________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________
QC SIGNATURE: ____________________________________________________
DATE: _____________________
D-11
Job Number Electrical Inspection / Test Sheet Ground Rod Earth Resistance Test CONTRACTOR: ______________________________________________
Project
Page of 1/1
REFERENCES (DRAWING, SPECIFICATION, PROCEDURE): _____________________________________________ GROUND ROD EARTH RESISTANCE TEST PROCEDURE (FALL OF POTENTIAL METHOD) 1. 2. 3. 4. After ground rods are installed to the correct depth measure the earth resistance of each individual rod. Install and connect reference electrodes and test equipment as per manufacturers test procedure. Measure earth resistance and record below. Maximum acceptable earth resistance as per Specification Section 19690 is 25 ohms.
TEST ITEMS
EARTH RESISTANCE
REMARKS
QC SIGNATURE: ____________________________________________________
DATE: _____________________
D-12
Job Number Electrical Inspection / Test Sheet Ground Grid Earth Resistance Test CONTRACTOR: ______________________________________________
Project
Page of 1/1
REFERENCES (DRAWING, SPECIFICATION, PROCEDURE): _____________________________________________ GROUND GRID EARTH RESISTANCE TEST PROCEDURE (FALL OF POTENTIAL METHOD) 1. 2. 3. 4. After ground rods and ground conductors installation is completed and interconnected, measure the earth resistances of the grounding grid. Install and connect reference electrodes and test equipment as per manufacturers test procedure. Measure earth resistance of ground grid and record below. Maximum acceptable earth resistance as per Specification Section 16960 is 1 ohm.
TEST ITEMS
EARTH RESISTANCE
REMARKS
QC SIGNATURE: ____________________________________________________
DATE: _____________________
D-13
Project
Page of 1/1
CONTRACTOR: ______________________________________________
ATTRIBUTE 1. 2. 3. 4. 5. 6. 7. 8. Installed lighting fixtures comply with fixture schedule drawing? Lighting fixture location is correct as shown on the design approved shop drawing? Lighting fixture and fittings are installed correctly and tightly as specified in the specification? Lighting fixture fitted with fuse holder and enclosure cover? Cable wire color code is correct and identification tags installed at panel board? Continuity and grounding test completed? All wire entries are sealed with a non-setting sealant? Lighting photo cell control is correctly installed?
YES
NO
N/A
REMARKS: _______________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________
QC SIGNATURE: ____________________________________________________
DATE: _____________________
D-14
Job Number Electrical Inspection / Test Sheet Combination Starter, PB and Selector Switches Control System Components
Project
Page of 1/1
CONTRACTOR: ______________________________________________
ATTRIBUTE 1. 2. 3. 4. 5. 6. Equipment/components installed per approved drawings and material submittals? Equipment/components installed at correct location and elevation? Cable/wire color code correct and tagging identification installed? Control wiring connected per approved drawing? Auto-off-manual selector operation is correct? Panel/door grounding checked?
YES
NO
N/A
REMARKS: _______________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________
QC SIGNATURE: ____________________________________________________
DATE: _____________________
D-15
Job Number Electrical Inspection / Test Sheet Continuity Test of all Fixture Bodies to Ground CONTRACTOR: ______________________________________________
Project
Page of 1/1
CIRCUIT NO.
FIXTURE NO.
CABLE ROUTE
TO
FROM
REMARKS
QC SIGNATURE: ____________________________________________________
DATE: _____________________
D-16
Job Number Electrical Inspection / Test Sheet Cable Test Procedures CONTRACTOR: ______________________________________________
Project
Page of 1/2
REFERENCES (DRAWING, SPECIFICATION, PROCEDURE): _____________________________________________ INSULATION RESISTANCE WITH ABSORPTION INDEX TEST PROCEDURE 1. 2. 3. 4. 5. 6. The test equipment shall be connected properly. The voltage of 500V held for a period of one (1) minute and results recorded below. Each conductor is to be measured to ground and to the three other conductors. The test shall be performed after cable installation and terminations are completed and witnessed by the QA Engineer. The absorption index is calculated as: Absorption Index = 60 sec IR reading / 30 sec IR reading The insulation resistance shall be compared for similar results of the other conductors and feeders.
D-17
Job Number Electrical Inspection / Test Sheet Cable Test Procedures CONTRACTOR: ______________________________________________
Project
Page of 2/2
REFERENCES (DRAWING, SPECIFICATION, PROCEDURE): _____________________________________________ CONDUCTOR PHASING TEST PROCEDURE 1. 2. 3. 4. 5. 6. Conductors are identified color mode. Phasing checks are to be performed when the cable installation is completed and before conductors are terminated. Conductors are to be phase checked individually. Confirm the phasing of each conductor with a continuity tester (ohmmeter). Conductors not under test must be clear of ground. Test results will be recorded below.
TEST 1
PHASE L1
CONNECTION L1 EARTHED L2 UNEARTHED L3 UNEARTHED N UNEARTHED L1 UNEARTHED L2 EARTHED L3 UNEARTHED N UNEARTHED L1 UNEARTHED L2 UNEARTHED L3 EARTHED N UNEARTHED L1 UNEARTHED L2 UNEARTHED L3 UNEARTHED N EARTHED
L2
L3
MANUFACTURER: _______________________________
D-17
Job Number Electrical Inspection / Test Sheet Conduit and Junction / Outlet Boxes Installation
Project
Page of 1/1
CONTRACTOR: ______________________________________________
ATTRIBUTE A 1. 2. B 1. 2. 3. 4. 5. C 1. 2. 3. 4. D 1. 2. 3. 4. SUPPORTS Conduit adequately supported? Support alignment checked? CONDUITS Installed conduits in accordance with shop drawing in a workman like manner? Bends free of damage? Oxide inhibitor used on threaded connection? Conduit & fittings correct size & type? Identification of conduits installed? JUNCTION / OUTLET BOXES Boxes installed are the correct size & type? Boxes are properly supported and installed at correct elevation? Proper identification on box? Pull/splicing box installed at accessible location? GROUNDING Metallic conduit solidly grounded? Conduit grounding bushing installed? Pull boxes and junction conduit grounded? Bonding wire grounding connections completed?
YES
NO
N/A
QC SIGNATURE: ____________________________________________________
DATE: _____________________
D-18
Job Number Electrical Inspection / Test Sheet Cable & Cable Accessories / Panelboard / Wiring Devices
Project
Page of 1/1
CONTRACTOR: ______________________________________________
ATTRIBUTE 1. 2. 3. 4. 5. 6. 7. 8. 9. Panelboard installed at proper elevation and circuit breaker accessories provided are per approved drawings and submittals? Installed wiring devices and plates with approved material submittals? Cable wire correct size and type? Low voltage power cable in outlet box and panelboard properly connected? Cable size color code is correct and identification tags are installed at panelboard/outlet boxes? Installed terminal lugs are correct size and application? All conduit and outlet boxes and panelboard properly grounded? Continuity and grounding test complete? Circuit index directory installed inside panelboard?
YES
NO
N/A
REMARKS: _______________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________
QC SIGNATURE: ____________________________________________________
DATE: _____________________
D-19
Job Number Electrical Inspection / Test Sheet Electrical Service and Distribution System CONTRACTOR: ______________________________________________
Project
Page of 1/1
REFERENCES (DRAWING, SPECIFICATION, PROCEDURE): _____________________________________________ MOLDED CASE CIRCUIT BREAKER RECORD
PANEL BOARD NO: _____________________________________ LOCATION: ________________________________________ CABLE NO: ____________________________________________ CABLE SIZE: _______________________________________ 1.0 CIRCUIT BREAKER DATA: 1.1 MANUFACTURER __________________________________________ 1.2 1.3 1.4 2.0 TYPE _____________________________________________________ AMPERE THERMAL STRIP SETTING _________________________________ AMPERE INSTANTANEOUS MAGNETIC TRIP RANGE ___________________
CONNECTED LOAD DATA: 2.1 2.2 2.3 2.4 2.5 2.6 MANUFACTURER ___________________________________________ NUMBER OF MOTOR / TRANSFORMERS _______________________ TOTAL KVA / KW / HP _______________________________________ VOLTAGE __________________________________________________ VOLTAGE RATED FREQUENCY ________________________________________ HZ FULL LOAD CURRENT (FLC) _________________________________ AMPERE
3.0
TRIP SETTINGS: 3.1 THERMAL ( 3.2 MAGNETIC ( ( ( ) FIXED ) VARIABLE ) % FLC ) AMPERES _______________________________
QC SIGNATURE: ____________________________________________________
DATE: _____________________
D-20
Job Number Electrical Inspection / Test Sheet Molded Case Circuit Breaker Test Record CONTRACTOR: ______________________________________________
Project
Page of 1/1
TEST DATA
SPECIFIED MAGNETIC TRIP SETTING: PHASE A TEST RESULTS CURRENT TRIP TIME STD CURRENT TRIP TIME MIN. TRIP CURRENT TRIP TIME AS FOUND AS LEFT MAGNETIC TRIP RATING: PHASE B AS FOUND AS LEFT PHASE C AS FOUND AS LEFT
LTD
ACCESSORIES
Mechanical Lock Out Key Lock Out Bell Alarm Current Limiting Fuses
Trip/Close Indicator Trip/Close Lights Motor Operated Mech Field Discharge Contact
D-21
Job Number Electrical Inspection / Test Sheet Cable Test Record CONTRACTOR: ______________________________________________
Project
Page of 1/1
CABLE DATA
MANUFACTURER NAME: YEAR MANUFACTURED: SIZE: TYPE OF INSULATION: NO. OF COND.: TRADE NAME: YEAR INSTALLED: INSUL. CLASS KV: VARNISH/CAMBRIC
RUBBER(LIKE)
NO
PAPER
OTHER SPECIFY
TEST DATA
TEST EQUIPMENT MANUFACTURER AND TYPE: TEST VOLTAGE: WEATHER CONDITIONS: TEST TYPE: KV A.C. KV D.C. TIME: MIN.
PH
BEFORE INSTALL.
PH
AFTER INSTALL.
PH
ROUTINE
1/2 1 2 3 5 10
PHASE FAILURES KV CURRENT TIME
D-22
Job Number Electrical Inspection / Test Sheet Motor Test Record CONTRACTOR: ______________________________________________
Project
Page of 1/1
TEST DATA
MEGGER TEST EQUIPMENT: TEST VOLTAGE: WEATHER: TEST TYPE: HIGH POTENTIAL TEST EQUIPMENT: TEST VOLTAGE: WEATHER: WINDING RESISTANCE TEST EQUIPMENT: WINDING TEMP.: WEATHER:
TEST TYPE:
TEST TYPE:
WITH CABLES CONNECTED WITHOUT CONNECTED TIME (MIN) 1/2 1 2 3 5 10 CABLES MEGOHMS
15 30 45 60 90 120
A-B BC CA
TIME (SEC)
CURRENT
RESISTANCE (OHMS)
FIELD
D-23
Project
Page of 1/1
OTHER COMMENTS: ______________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________
DATE: ___________________
D-24
Project
DATE
Page of 1/1
PART I To be completed by the inspector who detects a deviation. DESCRIPTION OF NON-CONFORMANCE: __________________________________________________________________________________________________________ __________________________________________________________________________________________________________ __________________________________________________________________________________________________________ __________________________________________________________________________________________________________ RECOMMENDED DISPOSITION: USE AS IS REWORK REPAIR SCRAP ___________________________________________________________________________________________________________________ ___________________________________________________________________________________________________________________ ___________________________________________________________________________________________________________________ ___________________________________________________________________________________________________________________ SIGNED ______________________________________________________________________ DATE ___________________________ PARSONS FIELD ENGINEER PART I I To be completed by the contractor who proposed the corrective action. DESCRIPTION OF PROPOSED CORRECTIVE ACTION: ___________________________________________________________________________________________________________________ ___________________________________________________________________________________________________________________ ___________________________________________________________________________________________________________________ ___________________________________________________________________________________________________________________ ___________________________________________________________________________________________________________________ ___________________________________________________________________________________________________________________ ___________________________________________________________________________________________________________________ ___________________________________________________________________________________________________________________ ___________________________________________________________________________________________________________________ SIGNED ______________________________________________________________________ DATE ____________________________ CONSTRUCTION ENGINEER PART III To be completed by the Engineer of Record. RECOMMENDATION AND REMARKS: __________________________________________________________________________________________________________ __________________________________________________________________________________________________________ __________________________________________________________________________________________________________ __________________________________________________________________________________________________________ Proposed corrective action status: Approved Rejected ___________________________________________________________________________________________________________________ ___________________________________________________________________________________________________________________ ___________________________________________________________________________________________________________________ ___________________________________________________________________________________________________________________ SIGNED ______________________________________________________________________ DATE ____________________________ ENGINEER OF RECORD PART IV QUALITY CONTROL DISPOSITION (To be determined by QC System Manager (Construction Engineer) DECISION AND DISPOSITION INSTRUCTIONS: USE AS IS REWORK REPAIR SCRAP __________________________________________________________________________________________________________________ __________________________________________________________________________________________________________________ __________________________________________________________________________________________________________________ SIGNED _____________________________________________________________________ DATE ____________________________ PARSONS FIELD ENGINEER SIGNED _____________________________________________________________________ DATE ____________________________ PARSONS CONSTRUCTION MANAGER PART V ENGINEERING DISPOSITION METHOD OF APPROVALS: TELEPHONE MEMORANDUM TELEX SPEC. CHANGE DRAWING CHANGE CONVEYED BY PROJECT MANAGER ______________________________________________ DATE _____________________________________ PROJECT MANAGER ______________________________________________ DATE _____________________________________ PART VI DISPOSITION VERIFICATION CORRECTIVE ACTION WAS ACCOMPLISHED ON _____________________________ SIGNED ______________________________________________________________________ DATE ____________________________________ PARSONS FIELD ENGINEER SIGNED ______________________________________________________________________ DATE ____________________________________ PARSONS CONSTRUCTION MANAGER
D-25
Job Number
Project
Page of
NCR No.
CONDITION DESCRIPTION
ORIGINATOR
DATE RECORDED
DATE TO CONTRACTOR
DISPOSITION DATE
DISPOSITION VERIFICATION BY
D-26
Attention: ___________________________________
Gentlemen:
Please review and take appropriate action to remedy this situation, also changing any procedures, methods and/or personal necessary to preclude similar problems in the future. Your attention is specifically drawn to Item 10, disposition date.
cc:
Program Manager Project Manager Construction Manager Quality Assurance Department Contract File
D-27