Qa QC Plan Facility Site Work Construction

Download as pdf or txt
Download as pdf or txt
You are on page 1of 103

CONSTRUCTION QUALITY CONTROL/QUALITY ASSURANCE PLAN PHASE 1 FACILITY SITE WORK CONSTRUCTION

HUDSON RIVER PCBs SUPERFUND SITE

Prepared For:

GENERAL ELECTRIC
319 Great Oaks Office Boulevard Albany, NY 12203

Prepared By:

GE Company Parsons Project Office 381 Broadway, Bldg 40-2 Fort Edward, NY 12828 Phone: 518-746-5311 Fax 518-746-5307

JANUARY 2007

Construction QC/QA Plan TABLE OF CONTENTS


Page

ACRONYMS AND ABBREVIATIONS.........................................................................V SECTION 1 INTRODUCTION................................................................................... 1-1 1.1 PROJECT SETTING......................................................................................... 1-1 1.2 PHASE 1 CONTRACTS DESCRIPTION........................................................ 1-2 1.3 QUALITY PROGRAM OVERVIEW .............................................................. 1-3 1.4 QUALITY MANAGEMENT PLAN ................................................................ 1-5 1.5 CQAP ORGANIZATION ................................................................................. 1-5 SECTION 2 PROJECT QC/QA ORGANIZATION ................................................ 2-1 2.1 RESPONSIBILITIES AND AUTHORITIES OF ORGANIZATIONS ........... 2-1 2.1.1 Environmental Protection Agency .......................................................... 2-1 2.1.2 General Electric Company ...................................................................... 2-1 2.1.3 Engineer of Record.................................................................................. 2-1 2.1.4 Construction Manager ............................................................................. 2-1 2.1.5 Construction Contractors......................................................................... 2-2 2.2 STRUCTURE OF QC/QA ORGANIZATION ................................................. 2-2 2.3 RESPONSIBILITIES AND AUTHORITIES OF KEY PERSONNEL............ 2-2 2.3.1 Construction Managers Quality Assurance Personnel........................... 2-3 2.3.2 Contractors Quality Control Personnel .................................................. 2-5 SECTION 3 SUBMITTALS ........................................................................................ 3-1 3.1 SUBMITTAL SCHEDULE............................................................................... 3-1 3.2 PROCESS, REVIEW AND ACCEPTANCE.................................................... 3-1 3.3 STORAGE......................................................................................................... 3-3 SECTION 4 PERFORMANCE MONITORING REQUIREMENTS..................... 4-1 4.1 QUALITY OF LIFE PERFORMANCE STANDARDS .................................. 4-1

January 2007

Construction QC/QA Plan TABLE OF CONTENTS (CONTINUED)


Page

4.2 POLLUTION PREVENTION........................................................................... 4-2 4.2.1 Stormwater Pollution Prevention and Dust Control................................ 4-2 4.3 REPORTING..................................................................................................... 4-2 SECTION 5 INSPECTION AND VERIFICATION ACTIVITIES ........................ 5-1 5.1 GENERAL CONSTRUCTION INSPECTION AND VERIFICATION REQUIREMENTS............................................................................................. 5-1 5.1.1 Inspections............................................................................................... 5-4 5.1.2 QC Testing............................................................................................... 5-6 5.1.3 QA Testing .............................................................................................. 5-6 5.2 CONSTRUCTION ACCEPTANCE CRITERIA.............................................. 5-7 5.3 CONSTRUCTION AUDITS............................................................................. 5-7 5.4 COMPLIANCE WITH HANDLING, STORAGE, PACKAGING, PRESERVATION, AND DELIVERY REQUIREMENTS .............................. 5-8 5.5 MATERIAL IDENTIFICATION AND TRACEABILITY.............................. 5-8 SECTION 6 CONSTRUCTION DEFICIENCIES .................................................... 6-1 6.1 DEFICIENCY IDENTIFICATION................................................................... 6-1 6.2 CONTRACTOR QC DEFICIENCY IDENTIFICATION AND CONTROL .. 6-1 6.3 NON-CONFORMANCE REPORT .................................................................. 6-2 6.4 CONTRACTOR QC DEFICIENCY CORRECTION ...................................... 6-2 6.5 PREVENTIVE ACTIONS ................................................................................ 6-2 SECTION 7 DOCUMENTATION.............................................................................. 7-1 7.1 DAILY RECORD KEEPING............................................................................ 7-1 7.2 DAILY CONSTRUCTION REPORT............................................................... 7-1 7.3 INSPECTION AND TESTING REPORT FORMS.......................................... 7-2

January 2007

ii

Construction QC/QA Plan TABLE OF CONTENTS (CONTINUED)


Page

7.4 RECORD DRAWINGS..................................................................................... 7-2 7.4.1 Responsibilities........................................................................................ 7-2 7.4.2 Preparation of As-Built Drawings ........................................................... 7-3 7.4.3 Review of As-Built Drawings ................................................................. 7-3 7.5 CONTROL OF QUALITY RECORDS ............................................................ 7-3 SECTION 8 EPA APPROVALS ................................................................................. 8-1 8.1 REQUIRED SUBMITTALS ............................................................................. 8-1 8.1.1 CQAP ...................................................................................................... 8-1 8.1.2 Phase 1 Work Completion Report........................................................... 8-1 8.2 EPA APPROVAL.............................................................................................. 8-1 SECTION 9 FIELD CHANGES ................................................................................. 9-1 9.1 CQAP CHANGES............................................................................................. 9-1 9.2 QC CHANGES................................................................................................. 9-1 SECTION 10 FINAL REPORTING......................................................................... 10-1 SECTION 11 REFERENCES.................................................................................... 11-1

LIST OF TABLES
Table 1.1 Organization of Phase 1 RA Work Plans........................................................ 1-2 Table 5.1 Sample Inspection and Test Plan .................................................................... 5-2

LIST OF FIGURES
Figure 2.1 Construction Quality Control/Quality Assurance Organization.................... 2-7

January 2007

iii

Construction QC/QA Plan TABLE OF CONTENTS (CONTINUED) LIST OF ATTACHMENTS


ATTACHMENT 1 CQAP STAFFING LIST AND RESUMES

LIST OF APPENDICES
APPENDIX A SAMPLE QUALIFICATION TEST SCHEDULES APPENDIX B SAMPLE INSPECTION SCHEDULES APPENDIX C SAMPLE TESTING SCHEDULES APPENDIX D TYPICAL CONSTRUCTION FORMS

January 2007

iv

Construction QC/QA Plan ACRONYMS AND ABBREVIATIONS


BBL CD CAD CM CMP CPR CQA CQAO CQAP CQCP EIT EPA FDR FE FI FSWC GE GPS HASP HDR IFC MPA NCR NICET NYSDEC O&M Parsons PCBs PE Blasland, Bouck and Lee, Inc. consent decree computer-aided design Construction Manager construction management plan Canadian Pacific Railway construction quality assurance construction quality assurance officer construction quality control / quality assurance plan contractor quality control plan Engineer in Training United States Environmental Protection Agency final design report senior field engineer CM field inspector Facility Site Work Construction (Contract 1 and Contract 2) General Electric Company geosynchronous positioning system health and safety plan HDR Engineering, Inc. issue for construction mass per unit area noncompliance report National Institute for Certification in Engineering Technologies New York State Department of Environmental Conservation operation and maintenance Parsons Engineering of New York, Inc. polychlorinated biphenyls Professional Engineer

January 2007

Construction QC/QA Plan Acronyms and Abbreviations (continued)


PEI PSCP QA QC QCM QMP QMS QoLPS RA RA CD RA HASP RAWP RD AOC RM ROD Site SM SOW SWPPP SPCCP TID Process Equipment Installation (Contract 3a) performance standards compliance plan quality assurance quality control quality control systems manager quality management plan quality management system quality of life performance standards remedial action remedial action consent decree remedial action health and safety plan remedial action work plan Administrative Order on Consent for Hudson River Remedial Design and Cost Recovery river mile record of decision Hudson River Sediment Remediation Site Site Manager scope of work stormwater pollution prevention plan spill prevention, control, and countermeasure plan Thompson Island Dam

January 2007

vi

Construction QC/QA Plan SECTION 1 INTRODUCTION


The United States Environmental Protection Agency (EPA) issued a Superfund Record of Decision (ROD) on February 1, 2002 (EPA, 2002) calling for, among other things, the dredging and disposal of certain sediments from the Upper Hudson River containing polychlorinated biphenyls (PCBs). On August 18, 2003, the General Electric Company (GE) and EPA entered into an Administrative Order on Consent for Hudson River Remedial Design and Cost Recovery (RD AOC) (Index No. CERCLA-02-2003- 2027) (EPA/GE, 2003), under which GE agreed to design the remedy outlined in the ROD. On October 6, 2005, the Consent Decree (CD) for the remedial action (RA) in the Upper Hudson River (Civil Action 1:05-CV-1270) was filed in Federal Court. After an extensive public review and comment period, the court approved and entered the CD as a final judgment on November 2, 2006, when it went into effect (EPA/GE, 2005). GE prepared the Phase 1 Final Design Report (FDR) (BBL, 2006) and submitted it to EPA on March 21, 2006. On May 31, 2006, EPA approved the portion of the FDR that included the facility site work construction (Contract 1) and rail yard construction (Contract 2). However, EPA has not yet approved the designs for the access road and the work support marina. Included as Appendix B to the CD is the Statement of Work for Remedial Action and Operations, Maintenance and Monitoring (SOW) which sets forth a number of requirements for implementing the remedial action set forth in the ROD. Section 2.1.2 of the SOW requires that a Construction Quality Control / Quality Assurance Plan (CQAP) be provided to EPA for review and approval. This document is being submitted to satisfy that requirement. 1.1 PROJECT SETTING The Upper Hudson River is defined as the section of river from the Fenimore Bridge in Hudson Falls to the Federal Dam at Troy, New York. The ROD calls for, among other things, a remedial action to remove and dispose of sediments from the Upper Hudson River. Sediments to be removed are defined based on the PCB mass per unit area (MPA) and surface concentration or characteristic criteria (EPA, 2002). EPA defined three sections of the Upper Hudson River for the sediment remediation activities outlined in the 2002 ROD: River Section 1: Former location of Fort Edward Dam to Thompson Island Dam (TID) (from river mile [RM] 194.8 to RM 188.5; approximately 6.3 river miles);

January 2007

1-1

Construction QC/QA Plan


River Section 2: TID to Northumberland Dam (from RM 188.5 to RM 183.4; approximately 5.1 river miles); and River Section 3: Northumberland Dam to the Federal Dam at Troy (from RM 183.4 to RM 153.9; approximately 29.5 river miles).

The remedial action is to be conducted in two phases, designated Phase 1 and Phase 2. Phase 1 is defined as the first year of dredging and will be completed in a portion of River Section 1. Phase 1 also includes preparation of the land-based sediment processing facility. Phase 2 covers the remaining dredging in the three river sections. 1.2 PHASE 1 CONTRACTS DESCRIPTION The project scope for Phase 1 activities will be conducted under at least seven separate contracts (excluding the rail transport and disposal contracts as well as agreements with the originating rail carrier for infrastructure improvements) and three separate Remedial Action Work Plans (RAWPs). The contracts and RAWPs are described below and summarized in Table 1-1. The table also includes the relationship of construction quality assurance (QA), quality control (QC) and health and safety to other Phase 1 activities. Table 1-1. Organization of Phase 1 RA Work Plans
Phase 1 Contract Packages
Contract 1 Facility Site Work Construction Contract 2 Rail Yard Construction RA Work Plan #2 Contract 3A Processing Facility Construction Contract 3B Processing Facility Operation Contract 4 Dredging Operations Contract 5 Habitat Construction Contract 6 Rail Yard Operations Phase 1 Processing Equipment Installation and Remaining Site Work RA Work Plan #3 Phase 1 Dredging and Facility Operations

Remedial Action Work Plans


RA Work Plan #1 Phase 1 Facility Site Work Construction

Construction Quality Assurance Plans

Remedial Action Health and Safety Plan

Construction Quality Control/Quality Assurance Plan

One umbrella RA Health and Safety Plan

Dredging Construction Quality Control/Quality Assurance Plan

The activities to be performed under Contract 1 (Facility Site Work Construction) and Contract 2 (Rail Yard Construction) are presented in detail in Sections 2 through 7 of RAWP #1,
January 2007

1-2

Construction QC/QA Plan


Remedial Action Work Plan for Phase 1 Facility Site Work Construction (Parsons, 2007). These activities include the following: Contract 1 Facility Site Work Construction includes general civil work, such as grading, placement and compaction of fill and paving. Other work activities include wharf area construction, access road construction, river mooring installation and construction of a support marina. Contract 2 Rail Yard Construction includes rail construction on the processing facility site property, and within the right-of-way of the commercial rail carrier, and rail yard facilities work.

The activities to be performed under Contract 3A Processing Equipment Installation will be described in RAWP #2, Remedial Action Work Plan for Phase 1 Processing Equipment Installation and Remaining Site Work. RAWP #2 covers the remaining site work, such as processing facility buildings, and the installation of process equipment, piping, electrical, instrumentation, communications, and the commissioning of the systems. The scope of work under Contract 3B, Contract 4, Contract 5, and Contract 6 will be addressed in RAWP #3, Remedial Action Work Plan Phase 1 Dredging and Processing Facility Operations. Briefly, RAWP #3 covers the following: Contract 3B Processing Facility Operations, including barge offloading, coarse material separation, sediment dewatering, water treatment (process and stormwater), stormwater management, and staging area management and maintenance. In the off season (when the Champlain Canal is closed), the contractor will winterize the processing facility and operate and maintain the stormwater collection and treatment system. Contract 4 Dredging Operations, including resuspension containment system installation, debris removal, the performance of inventory and residual dredging operations and the transport of loaded sediment barges to the off-loading wharf at the processing facility. After dredging is completed in an area, the contractor will place appropriate backfill, cap, or shoreline stabilization structures. Contract 5 Habitat Construction, including the supply and planting of subaquatic vegetation in certain dredged areas pursuant to habitat reconstruction plans. Contract 6 Rail Yard Operations, including all activities required to operate and maintain the rail yard. This primarily will involve the loading of debris, coarse material and dewatered sediment into empty rail cars, setting up of outbound loaded trains, and receiving of inbound empty trains.

1.3 QUALITY PROGRAM OVERVIEW GE's approach to management of the quality of the RA implementation includes a combination of quality control by the contractor and quality assurance by the Construction
January 2007

1-3

Construction QC/QA Plan


Manager. The CQAP details the systems and controls that GE has put in place so that the quality of the project will meet the requirements specified in the Phase 1 FDR. GE provides definition and overall management of the quality approach to be followed by its contractors and consultants. The quality of the RA implementation will be ensured through an integrated system of quality assurance performed by the Construction Manager and quality control provided by the contractors. GE's Construction Manager is responsible for the day-to-day coordination of quality assurance and quality control measures in the field. This Construction Quality Control/Quality Assurance Plan (CQAP) is a companion document to RAWP #1 and RAWP #2. It establishes: project procedures and general responsibilities for the quality assurance and quality control (QC/QA) program; and protocols to ensure that the Phase 1 Facility Site Work Construction (FSWC) and Process Equipment Installation (PEI) will be executed in accordance with the relevant portions of the Phase 1 FDR.

This CQAP has been developed in accordance with Section 2.1.2 of the SOW. The contractors are responsible for constructing the work in accordance with the plans and specifications. Each contractor is also responsible for controlling the quality of its work to meet contract plans, specifications, and related requirements. The contractors QC is the systematic implementation of a program of inspections, tests, and production controls to attain the required standards of quality and to preclude problems resulting from noncompliance. Pursuant to Technical Specification Section 01400 Quality Requirements, each contractor will establish an independent QC program and write a Contractor Quality Control Plan (CQCP). The CQCP must provide for tests and inspections pursuant to various technical specifications. It will define procedures to ensure that activities affecting quality are properly documented and accomplished in accordance with contract documents; written instructions; and industry standards, codes and procedures. Furthermore, the CQCP will define methods for ensuring that activities affecting quality will be accomplished under controlled conditions. Independently of the contractors, the construction manager (CM) will provide QA through daily monitoring and scheduled inspections to verify the effectiveness of the contractors QC program and assure that the quality and contract requirements are met by the contractors. The CM assures that the contractors QC is working effectively and that the resultant construction complies with the quality requirements established by the contract. The objectives of this CQAP are to: Describe the quality program and organization to be implemented so that the project is constructed in accordance with the contract requirements and industry standards;

January 2007

1-4

Construction QC/QA Plan


Describe guidelines for inspection and documentation of construction activities; Provide reasonable assurance that the completed work will meet or exceed the requirements of the construction drawings and specifications; and Describe how any unexpected changes or conditions that could affect the construction quality will be detected, documented, and addressed during construction.

1.4 QUALITY MANAGEMENT PLAN Parsons Engineering of New York, Inc. (Parsons) has been retained to provide construction management services for this project. As GEs managing contractor, Parsons will carry out work on this project in accordance with the Parsons Quality Management Plan (QMP) (Parsons, 2005), which was submitted to EPA on November 1, 2005. 1.5 CQAP ORGANIZATION This CQAP is organized into eleven sections. Section 1 - Introduction: describes the project setting, the Phase 1 contracts and related RAWPs, and the CQAP quality program overview. Section 2 - Project QC/QA Organization: presents the organizations and key personnel involved in the construction of the RA, their responsibilities and authorities, the structure of the QC/QA organization and the minimum training and experience of the Construction Quality Assurance Officer (CQAO) and personnel. Section 3 - Submittals: presents the procedures for processing submittals from Phase 1 contractors and vendors. Section 4 - Performance Monitoring Requirements: addresses QC/QA for performance monitoring requirements applicable to Phase 1 FSWC and PEI. Section 5 - Inspection and Verification Activities: provides procedures for tracking construction inspection and verification activities for the contract, construction acceptance criteria, and construction audits. Section 6 - Construction Deficiencies: describes the procedures for tracking construction deficiencies from identification through acceptable corrective action. Section 7 - Documentation: describes the procedures for the project documents that will be managed through a combination of a secure document filing and storage system and computerized Document Tracking System. Section 8 - EPA Approvals: describes EPA approvals applicable to the Phase 1 FSWC and PEI QC/QA. Section 9 - Field Changes: describes handling of quality plan changes to assure QC/QA objectives are met.

January 2007

1-5

Construction QC/QA Plan


Section 10 - Final Reporting: describes the QC/QA documentation for Phase 1 FSWC and PEI to be submitted to EPA in the Phase 1 Construction Completion Report. Section 11 - References: provides bibliographic references to key documents referred to in the body of the plan.

January 2007

1-6

Construction QC/QA Plan SECTION 2 PROJECT QC/QA ORGANIZATION


This section presents the responsibilities and authorities of organizations and key personnel involved in the construction of the RA, the structure of the QC/QA organization, the minimum training and experience of the QC/QA personnel, and the QC/QA training given to all onsite workers. 2.1 RESPONSIBILITIES AND AUTHORITIES OF ORGANIZATIONS The organizations involved in the Phase 1 FSWC and PEI and their QC/QA roles and responsibilities are as follows. 2.1.1 Environmental Protection Agency EPA is the lead agency responsible for observing and monitoring the progress of the Phase 1 FSWC and PEI in accordance with the CD. As such, EPA exercises approval authority for this CQAP. 2.1.2 General Electric Company GE is responsible for implementing the RA in accordance with the CD and for ensuring that its contractors and subcontractors perform RA construction in accordance with the CD. The CQAP details the systems GE has put in place in order that its responsibilities to quality are met. GE is responsible for verifying that the CM it has retained effectively implements and manages the systems detailed in the CQAP. GE is also responsible for formal communications with and submittals to EPA. 2.1.3 Engineer of Record The Engineer of Record is an independent, duly qualified, licensed design professional, retained directly by GE to provide design and engineering services in connection with the project. This definition includes all subcontractors to the Engineer of Record. Blasland, Bouck and Lee, Inc. (BBL) is the Engineer of Record for Phase 1 except for the rail yard. HDR Engineering, Inc. (HDR) is the Engineer of Record for the rail yard. BBL and HDR provide submittal review and resolution of design issues as they arise during construction. 2.1.4 Construction Manager The CM is a duly qualified entity retained by GE to provide professional construction management and related services in connection with the project. The CM is responsible for implementation of this CQAP. The CM will manage construction contractors on behalf of GE
January 2007

2-1

Construction QC/QA Plan


and serve as the primary point of contact with the contractors for all communications to and from the contractors. The CM will provide Quality Assurance and monitor the day-by-day construction quality control activities performed by construction contractors to verify compliance with the contract plans and specifications. The CM will also manage, coordinate, and administer all QC/QA activities and requirements, including those of subcontractors to the CM. Additionally, the CM may be assigned management of any third party QA inspection and testing firms retained by GE. 2.1.5 Construction Contractors The construction contractors are retained by GE to provide the labor, materials and equipment required to construct the project in accordance with the contract documents. Construction contractors are responsible for the quality control of their constructed work product as well as the necessary inspections and tests required to ensure that their work complies with the contract documents. They exercise authority over their workforce, including QC personnel and their third-party QC support services. Pursuant to Specifications Section 01450, each contractor will submit a QC organization chart developed to show all QC personnel and how these personnel integrate with other management, production and construction functions and personnel. All QC staff members are subject to acceptance by GE. The requirements for the QC organization include a QC Systems Manager and a sufficient number of additional qualified personnel to ensure contract compliance. The contractor is to provide a QC organization that is represented on the site at all times during progress of the work and with authority to take any action necessary to ensure compliance with the contract. 2.2 STRUCTURE OF QC/QA ORGANIZATION The QC and QA functions of the project organizations are functionally integrated although contractually separate. Figure 2.1 shows the functional structure of the project QC/QA team. 2.3 RESPONSIBILITIES AND AUTHORITIES OF KEY PERSONNEL Key personnel involved in the Phase 1 FSWC and PEI and their QC/QA roles and responsibilities are described below in Section 2.3.1 and Section 2.3.2. Pursuant to the CD statement of work, names of QC/QA personnel assigned CQAP functions are to be communicated to EPA; these personnel are the CQAO and CM Field Inspectors. Since personnel assignments are subject to change over time, the CM will maintain a CQAP Staffing List of CQAP personnel assignments including each persons role and organization. This CQAP Staffing List is initially provided in Attachment 1 together with resumes of current CQAP personnel. When personnel changes occur, GE will provide an updated Attachment 1 to EPA.

January 2007

2-2

Construction QC/QA Plan


2.3.1 Construction Managers Quality Assurance Personnel Construction Manager The Construction Manager (CM) is the primary point of contact for GE on all construction management issues. The CM is responsible for the overall management of activities related to the construction program, including the implementation of the CQAP and the health and safety program. As such, the CM will work directly with GE to exercise approval authority over contractor submittals including the CQCP. The CQCP must include the names and qualifications of contractors QC personnel pursuant to Section 2.3.2 below. Site Manager The Site Manager (SM) monitors and works with GE to approve each contractors quality, and progress submittals to ensure that the project is meeting the contract requirements. The SM will manage the field implementation of the CQAP at the project sites under control of the senior field engineer (FE) and the Construction QA Officer. Construction Quality Assurance Officer The CQAO is a full-time employee of the CM. The CQAO should have a minimum of five years of experience in related construction and prior QA experience on a project of comparable size and scope to this project. Additional qualifications for the CQAO include one or more of the following requirements: P.E. with one year of related construction experience acceptable to GE. Engineer in Training (EIT) with two years of related construction experience acceptable to GE. Three years of related experience acceptable to GE with a Bachelor of Science Degree in civil engineering, civil engineering technology, or construction. Construction materials technician certified at Level III by National Institute for Certification in Engineering Technologies (NICET).

The CQAO reports directly to the CM. The CQAO will have full authority delegated by the CM and GE to institute actions necessary for the successful implementation of the QC/QA program to ensure compliance with the contract plans and technical specifications (including stop-work authority). The CQAO is assigned to the project full time. The CQAO works with GE to administer and implement the CQAP. This includes controlling this CQAP, making revisions as necessary, and implementing systematic actions to ensure compliance with the plan. The CQAO coordinates activities with the SM to ensure that the FE, inspection staff, third party inspection and testing firms as well as contractor QC staff carry out the requirements of the CQAP.
January 2007

2-3

Construction QC/QA Plan


The CQAO is supported by Parsons QA Services. Parsons QA staff will provide expertise, on an as-needed or as-requested basis, in the investigation and handling of significant or unique quality issues. The CQAO tracks and reports non-conformances to the CM, SM, and after notification to the CM, to contractor management and contractor QC staff. The CQAO also has full authority to obtain direct access to contractor QC files. Other CQAO responsibilities include: Reviewing contractor QC reports, tests, and inspection results; Facilitating the implementation of the four-phase inspection program and participating in the required inspections; and Ensuring that QA personnel conducting inspections are adequately trained and understand assignment limits and time frames. Senior Field Engineer The Senior Field Engineer (FE) administers the contract requirements, including the CQCP submittals by contractors, and assures that each contractor consistently conforms to its approved CQCP. The FE oversees inspection efforts, provides technical advice, and coordinates support from engineering support, administration, inspection services, safety, and other team members. The FE coordinates resolution of unsatisfactory work items with contractors through final acceptance. The FE assures open noncompliance report (NCR) items are completed and accepted in a timely fashion. Acting in concert with GE, the SM and CQAO, the FE has the authority to require changes to the contractors QC organization and plan as required to address apparent trends, to mitigate future NCRs and to obtain the quality specified in the contract documents. The FE reviews QC and QA testing documentation with contractors, engineers, and inspectors. The FE also reviews plans and specifications for assigned projects and estimates the type and number of QA tests that should be accomplished for each specification section. The FE meets with third-party testing and inspection firms to review test requirements and coordinate testing and inspection services. Field Inspectors CM Field Inspectors (FIs) are responsible to the FE and support the FEs administration of the construction contracts. The FIs will hold a bachelors degree in engineering or construction and have three years experience in the type of work being performed on this project, or will have at least five years of related experience and will hold the construction materials technician certified at Level III by the NICET. Certification at an equivalent level by a state or nationally recognized organization will be acceptable in lieu of NICET certification. For inspection of the NY Route 196 intersection construction, QA inspectors must meet NICET Level II or higher
January 2007

2-4

Construction QC/QA Plan


certification in highway construction. Additional experience and training may be substituted for educational requirements, subject to GEs approval. The FIs will monitor the day-to-day activities of the contractor. This includes ensuring that contractors comply with the plans and specifications, applicable building codes, good workmanship, and the QC requirements of the contract. As part of this effort, FIs will: conduct independent inspections to verify the quality of the work; participate in contractor four phase inspections; review test and inspection reports; and ensure that the required documentation is submitted.

The FIs must be alert to detecting, recording, and reporting any deviation from the contract documents, including calling any deficient item to the attention of the FE, the contractors superintendent, and/or other representative. The FIs must keep accurate and detailed records of the contractors performance and progress, delivery of materials, and other pertinent matters, including the daily inspection report. 2.3.2 Contractors Quality Control Personnel QC Systems Manager The QC Systems Manager (QCM) is a full-time employee of the contractor, or a consultant engaged by the contractor. The QCM should have a minimum of five years of experience in related construction and prior QC experience on a project of comparable size and scope to the contractors scope of work on this project. Additional qualifications for the QCM include at least one of the following requirements: PE with one year of related construction experience acceptable to the CM. EIT with two years of related construction experience acceptable to the CM. An individual with three years of related experience acceptable to the CM, with a Bachelor of Science Degree in civil engineering, civil engineering technology, or construction. Construction materials technician certified at Level III by the NICET. The QCM will have full authority to institute any and all actions necessary for the successful implementation of the QC program to ensure compliance with the contract plans and technical specifications. The QCM shall report directly to a responsible officer of the construction contractor. The QCM is assigned to this project full time. QC Technicians The contractor QC Technicians perform the following functions:
January 2007

2-5

Construction QC/QA Plan


Inspect all materials, construction, plant, and equipment for conformance with the technical specifications; and Perform all QC tests as required by the technical specifications.

Contractor QC Technicians will be engineers, engineering technicians, or experienced craftsmen with qualifications in the appropriate field equivalent to NICET Level II or higher construction materials technician, and will have a minimum of two years of experience in their area of expertise. For inspection of the NY Route 196 intersection construction, QC inspectors must meet NICET Level II or higher certification in highway construction. Certification at an equivalent level by a state or nationally recognized organization will be acceptable in lieu of NICET certification. Additional experience and training may be substituted for educational requirements, subject to GEs approval.

January 2007

2-6

Construction QC/QA Plan

January 2007

2-7

Construction QC/QA Plan SECTION 3 SUBMITTALS


This section describes the procedures for CM processing of submittals from contractors. The CM will administer and control the processing of contractor submittals. After being reviewed for completeness, submittal documents will be transmitted to the relevant project staff for review and verification for compliance with contract requirements. The submittals disposition will be noted on the submittal, which will be signed, dated and returned to the contractor. If required, the contractor will revise the submittal, incorporating the comments and will resubmit it for review and verification for compliance. Submittals will be logged and copies will be retained in the project files. 3.1 SUBMITTAL SCHEDULE The contractor will submit and maintain a submittal schedule. The CM will review and after consulting GE will approve the submittal schedule. The schedule will be initially submitted within 14 days after the award of the contract and then monthly with the monthly baseline schedule updates. The CM shall work with the contractor to prioritize and sequence submittals so that the most critical submittals are received and processed first. The submittal schedule will become the baseline against which receipt of all required submittals will be compared. The approved submittal schedule will be forwarded to the Engineer of Record for resource availability planning. 3.2 PROCESS, REVIEW AND ACCEPTANCE Submittals will be managed as follows: 1. Contractors will number and certify the completeness of all submittals before submitting to the CM; 2. Contractors must also complete submittal transmittal forms and submit six paper copies and one electronic copy of all required submittals to the CMs document manager (the submittal transmittal form will always accompany each submittal package to and from the contractor, the CM and the Engineer of Record); 3. Upon receiving the submittal the CM will log the submittal and provide a review to ascertain whether the package is complete. If the submittal is incomplete the submittal will be returned to the contractor. 4. The original submittal transmittal and all copied attachments will be logged into the document tracking system. The CM will then forward submittals to the appropriate reviewers.

January 2007

3-1

Construction QC/QA Plan


5. If the CM provides a submittal to the Engineer of Record for review, they will review it for general conformance with contract design documents, will coordinate concurrent discipline reviews within the design team, will coordinate concurrent reviews by owner and other entities, and consolidate responses into a single coordinated action. 6. After reviewing the submittal the Engineer of Record (or other designated reviewer) makes the appropriate notations and action taken on the submitted documents and returns the submittal to the CM. 7. The CM will return a minimum of one copy of the submittal to the contractor with an original stamp of the action required. 8. The six actions that may be taken for each submittal are: Approved Submittal meets contract requirements. No additional copies will be required of the contractor. Approved As Noted Submittal meets contract requirements with minor corrections noted. Re-submittal is not required. Contractor must incorporate the required corrections into the work in the field. No additional copies will be required of the contractor. Revise and Resubmit Submittal has some selected areas that do not meet requirements. These areas can be revised to meet requirements, and the entire submittal must be re-submitted for review and approval. No work will begin in the field until the revised submittal has been approved. Rejected Submittal is inadequate and does not meet contract requirements. Revise the complete submittal and resubmit for approval. No work will begin in the field until the revised submittal has been approved. For Information Only Submitted for information only; no response action required Received, No Action Taken Receipt of submittal is noted; no further action required. 9. When a submittal is to be revised and resubmitted, the contractor will revise the submittal and indicate this revision by incrementing the revision number. The contractors submittal process will then be repeated. The CM is responsible for tracking the submittal package during the entire review process and advising all concerned of any schedule impacts to ensure that the review process timeframe is adhered to. The CM will retain copies of all submittal documents and revisions and ensure that an accurate file is available for ready retrieval during the life of the project. The CM will maintain all submittal files. These files will be filed by numeric sequence. Each submittal file will contain a complete submittal copy of the submittal before and after the review process.
January 2007

3-2

Construction QC/QA Plan


3.3 STORAGE The CM will maintain all submittal files via a combination of a secure document filing and storage system, and a computerized document tracking system.

January 2007

3-3

Construction QC/QA Plan SECTION 4 PERFORMANCE MONITORING REQUIREMENTS


The performance monitoring requirements applicable to Phase 1 FSWC and PEI consist of the Quality of Life Performance Standards (QoLPS) and the Stormwater Pollution Prevention Plan (SWPPP) requirements. The Contract Technical Specifications impose these requirements upon the FSWC and PEI contractors and require specific plans for contractor compliance and related work-area monitoring. The CM will perform QA oversight of contractor compliance and related work-area monitoring pursuant to the submitted plans. 4.1 QUALITY OF LIFE PERFORMANCE STANDARDS Construction activities will be performed in accordance with the relevant portions of the Phase 1 FDR (BBL, 2006) that address the QoLPS established by EPA for Phase 1 of the Remedial Action in the Upper Hudson River. Those standards address air quality, odor, noise, lighting, and navigation. The portions of the air quality standard relating to polychlorinated biphenyls (PCBs) and to the National Ambient Air Quality Standards (NAAQS) do not apply to the FSWC and PEI activities, although the portion of that standard relating to opacity does. RAWP #1 includes a QoLPS Field Sampling Plan (FSP) - Phase 1 FSWC, which details the QoLPS compliance monitoring activities that will be undertaken during the FSWC to assess and verify achievement of the applicable QoLPS for the FSWC. During construction of the processing facility and rail yard, the contractors will comply with the performance and monitoring requirements established by the following Technical Specification Sections: 01140 - Work Restrictions 02371- Dust, Soil Erosion, and Sediment Control 02935 Lighting from Facility Site Work Construction 02930 Noise from Facility Site Work Construction

RAWP #1 includes contractor work plans for meeting these requirements. Please refer to RAWP #1, the QoLPS FSP, and the referenced specifications for more detail on these requirements, the underlying standards, and the monitoring activities that will be performed to verify compliance.

January 2007

4-1

Construction QC/QA Plan


4.2 POLLUTION PREVENTION During construction of the facility site work and rail yard, the contractors will comply with the pollution prevention performance and monitoring requirements established by the technical specifications. These requirements are summarized below. 4.2.1 Stormwater Pollution Prevention and Dust Control Contractors will comply with the performance and monitoring requirements established by Technical Specification Section 02371 Dust, Soil Erosion & Sedimentation Control. RAWP #1 and RAWP #2 call for contract-specific SWPPPs in accordance with Specification 01460. Please refer to the referenced RAWPs and Specifications for more detail on these requirements and the underlying standards. 4.3 REPORTING QoLPS monitoring data obtained by the CM during the FSWC and PEI work will be included in the monthly progress report under the CD, as described in the RAWP #1 QoLPS FSP. Any exceedance will be reported as described in the RAWP #1 QoLPS FSP.

January 2007

4-2

Construction QC/QA Plan SECTION 5 INSPECTION AND VERIFICATION ACTIVITIES


The contractor QC control, verification, and acceptance testing plans set out the QC inspections and testing for implementation of each technical specification applicable to the contractors scope of work. The plans will cover the type, test standard, frequency, control requirements, and assigned responsibility for inspections and tests. The CM will review and approve these plans as part of the contractor CQCP submittals. After being approved by the CM the contractor CQCPs are available upon request for informational purposes only. Ongoing QA monitoring and oversight of contractor QC inspections and testing will be performed by the CM. In this manner, the inspections and tests required to measure compliance with the relevant portions of the Phase 1 Final Design Report for Contracts 1, 2 and 3A are established and carried out. 5.1 GENERAL CONSTRUCTION INSPECTION AND VERIFICATION REQUIREMENTS Contractors shall perform the inspections and tests as prescribed in the technical specifications for Contracts 1, 2, and 3A. QA inspection and testing will be used to verify the adequacy and effectiveness of the contractor QC program. The QA inspection and testing frequency will be at the discretion of the CQAO based on results of QC tests, evaluation of daily reports, audits of the QC program and verification testing conducted by the CM and owners third party testing firm. Should information become available that indicates a potential problem, the CQAO will review in detail all pertinent information and order additional verification testing if necessary. Contractor QC control, verification, and acceptance testing plans set out the contractors specific QC testing and inspection pursuant to Specification 01450 1.03 B and the relevant design specification. Table 5.1 summarizes the content of such an inspection and testing plan applicable to FSWC. Appendices A, B, and C provide supporting detail for Table 5.1. QA oversight of the contractors QC is also indicated on Table 5.1. Further discussion follows the example. [Note: the example below and Appendices A, B, C are for illustration only and are not intended to replace or modify contract specifications that will form the basis of actual CQCP submittals by contractors.]

January 2007

5-1

Construction QC/QA Plan


Example: Inspection and Testing Plan Materials qualification testing will be done prior to construction to verify that the materials comply with requirements of the specifications. The contractor will obtain representative samples of the materials designated as the proposed source of the materials. Test samples will be sent by the contractor to the Testing Laboratory. The Testing Laboratory will report all test results for determination of material meeting the acceptance criteria. For soils, sampling and analysis will be performed by the contractor on the onsite borrow material source. The CQAO or designee will periodically inspect material being used. If determined that the characteristics of the material being used differ from the material initially tested, the CQAO designees will direct the contractor to repeat the qualification testing. If the new material qualification test results meet the criteria of the technical specification as determined by the Engineer of Record, the new materials may be used for the work; otherwise, previously approved materials must be used or other acceptable materials must be sampled and tested as noted above prior to incorporating into the work. Inspection and testing is summarized in Table 5.1

Table 5-1 Typical Control, Verification and Acceptance Testing Plan


Specifications Item Spec. ref. Item description Quality Control Test type Responsibility Control requirements CM (QA)

Contractor Test standard (QC)


ASTM A328 with minimum thickness of 3/8 Manufactures OHSA Subpart P, certification data report. excavation section 1926.652

Support excavation Stress Grade, 02201, ref. Fiber stress of Wood sheeting & 2.01 1,200 PSI Bracing

Verification by Eng. Of record approval

Permissible deviation by Engineer of Record only.

Each approved source, Density, gradation and ASTM D2487, moisture density 02201, ref D698, D1556 & General fill material relationship per 2.01-C D2922 1000 cubic yard, stockpile or inplace source. Backfilling 02201, ref. Compaction & 3.08 Density Control Moisture ASTM D698, Method D

Contractors testing laboratory

Permissible 7% - 10% deviation by verification Engineer of test Record only.

Contractors testing laboratory

7% - 10% verification test

N/A

January 2007

5-2

Construction QC/QA Plan


Specifications Item Spec. ref. Item description Quality Control Test type Responsibility Contractor Test standard (QC) Control requirements CM (QA)

02201, ref. Backfilling 3.08-2-b ; 02203, ref. Compaction & Density Control 3.01

95% of Max dry density for structure, Method of ASTM Contractors driveways, roods D 1556 or ASTM testing and sidewalk. D2922 laboratory 90% for other areas. 95% of Max dry density Satisfactory material with plasticity index equal to or less than 12 1 per stockpile and source change 1 per stockpile and source change ASTM D698 Contractors testing laboratory Contractors testing laboratory

7% - 10% verification test

N/A

Trenching, 02204, ref. backfilling & 3.02 compacting 02205, ref. Select fill/ Non1.03 & expansive soils 1.04-6 Spec. Select fill/Coarse 02205, ref. aggregate (Grain2.01 B size Distribution) Spec. Select fill/ Fine 02205, ref. Aggregate (Grain2.01 B Size Distribution)

7% - 10% verification test 7% - 10% verification test 7% - 10% verification test 7% - 10% verification test

N/A

ASTM D 4318

N/A

Contractors ASTM D 422 or testing C136, size No. 6 laboratory ASTM C136; C33 and as required Contractors by NYSDOT testing laboratory Spec. 703.02, size no. 56 or 67

N/A

N/A

02207, ref. Restoration of 1.02 & surfaces/ Asphalt 3.01 temporary paving

Asphalt concrete NYSDOT Binder plant mix Maintenance 2 compacted 15.403.2001 thick

Provide Mix design for all material to be verification incorporated plant report in the restoration Provide Mix design for all material to be verification incorporated plant report in the restoration Results of all leakage tests shall submit to CM within 2 working days of test completion. Results of all leakage tests shall submit to CM within 2 working days of test completion.

N/A

02207, ref. Restoration of 1.02 & surfaces/ Asphalt 3.01 permanent paving

Asphalt concrete NYSDOT Binder plant mix Standard 4 compacted Specifications thick

N/A

24-hour test, no visible sign of Tests of all leakage on the 02211, ref. hydraulic structures exterior surface 3.01 non-pressure piping and when the water surface does not drop

ASTM C-828

All tests shall be witnessed by the CM

Refer to the table in section 3.03- D for allowable leakage for nonpressure piping.

02211, ref. Tests on pressure 3.02-B piping

Pressure test 150 PSSI for period of 2 hours.

ASTM C-828

All tests shall be witnessed by the CM

N/A

January 2007

5-3

Construction QC/QA Plan


Specifications Item Spec. ref. Item description Quality Control Test type Responsibility Contractor Test standard (QC)
Results of all leakage tests shall submit to CM within 2 working days of test completion. Results of all leakage tests shall submit to CM within 2 working days of test completion.

Control requirements CM (QA)


Refer to the table in section 3.02- 4, 5 & 6 for allowable leakage for nonpressure piping.

02211, ref. Leakage test for 3.02-C pressure piping

Rate of leakage has stabilized for ASTM C-828 3 consecutive 15 minutes intervals

All tests shall be witnessed by the CM

Manhole & catch 02211, ref. Basin leakage 3.04 testing

Leakage does not exceed one gallon per vertical foot of depth 24 hours.

ASTM C-828

All tests shall be witnessed by the CM

Any leaks detected shall be permanently stopped.

5.1.1 Inspections The contractor shall establish a program for inspection of activities affecting quality and shall cover all construction site and laboratory operations, including both onsite and offsite operations. Inspections shall be performed to verify compliance with documented instructions, drawings, procedures, and specifications as required by the contract. All inspections shall be documented by the contractor as required by Specification Section 01450 3.05. A four-phase inspection program shall be followed for each definable feature of the work. The four phases of inspection are: 1. Preparatory Inspection The contractor and the CM perform preparatory inspections prior to beginning any work on any definable feature of the work. Ensure that preparatory inspections include a review of contract requirements. Ensure that all materials and /or equipment have been tested, submitted, and approved. Ensure that provisions have been made to provide required testing. Examine work area to ascertain that all preliminary work has been completed. Examine materials, equipment, and samples to ensure that they conform to approved shop drawings or submittal data, that all materials and/or equipment are on hand, and that all monitoring and measuring equipment is properly calibrated and in proper working condition. Record preparatory inspections in the contractors QC documentation as required by Specification 01450 Section 3.05.

January 2007

5-4

Construction QC/QA Plan


2. Initial Inspection The contractor and the CM perform an initial inspection as soon as a representative portion of the particular feature of work has been accomplished. Examine the quality of workmanship. Review control testing for compliance with contract requirements. Review dimensional aspects of the work. Record initial inspections in the contractors QC documentation as required by Specification 01450 Section 3.05.

3. Follow-Up Inspection The contractor and the CM perform follow-up inspections daily. Ensure continuing compliance with Contract requirements. Ensure continuing compliance with control testing until completion of particular feature of work. Contractor CQM records follow-up inspection in daily QC reports. The CM inspection staff records follow-up inspections in their daily inspection report. Conduct final follow-up inspections and correct test deficiencies prior to the addition of new features of work.

4. Completion Inspection The contractor and CM perform a completion inspection of the work. Develop a punch list of items that do not conform to the approved plans and specifications. Include the punch list in the construction QC documentation. As required by Specification 01450, Section 3.05, include the estimated date by which the deficiencies will be corrected. Perform a second completion inspection after punch list items have been completed and the CM has been notified by the contractor.

The daily inspection reports shall identify inspections conducted, results of inspections, location and nature of defects found, causes for rejection, and remedial or corrective action taken or proposed. Additional QA inspections may include inspection of third-party lab testing facilities, fabrication facilities, and suppliers. Other inspections outside of the four-phase program described above will be ordered or performed by the CM to verify compliance with building
January 2007

5-5

Construction QC/QA Plan


code and standards of New York State. These inspections shall be performed and conducted at various points of construction that would typically require code compliance inspections. When deficiencies are discovered during the four-phase or other inspection processes, focused inspection shall be considered by the CQAO. When material, performed work, or installation is found on the basis of focused inspections to be deficient and/or does not meet the project specifications, the CQAO will assure deficiency correction is implemented, as discussed in Section 6. 5.1.2 QC Testing As required by the contract specifications, the contractor shall establish a test program to ensure that all required testing is properly identified, planned, documented and performed under controlled and suitable environmental conditions, including cleanliness. Testing shall be performed in accordance with written test procedures in the CQCP. Such test procedures shall incorporate or reference the requirements as contained in the contract technical specifications, codes, and industry standards. Per the CQCP, the contractor shall submit the test procedures to the CQAO for review and acceptance prior to their implementation. The contractor shall be responsible for establishing a system of daily test reports that will record all QC test results. Test results from each days work period shall be submitted to the CQAO prior to the start of the next days work period. When required by the technical specifications, the contractor shall maintain statistical QC charts. The contractors responsible technician and the QCM shall sign the daily test reports. CQAO will review test results on a daily basis and identify any non-conforming test results for discussion with the contractor regarding potential corrective action. 5.1.3 QA Testing The CQAO will be responsible for the QA materials sampling and testing program. QA testing is provided for the verification of the adequacy and effectiveness of the contractors QC testing. QA testing is performed by the CQAO and is independent of and in addition to QC testing performed by contractors. QA testing may be performed on a pre-established schedule or as directed by the CQAO. QA testing will be performed by or under supervision of the QA staff to validate the contractors QC sampling and testing. Such testing may be performed by third party testing services. The typical test frequency will be one (1) QA test for every ten (10) to fifteen (15) of the construction contractors QC tests. More frequent testing during initial startup may be necessary to verify the process is under control and complies with the technical specifications of the construction contracts. In lieu of performing independent tests the CQAO may choose to witness QC testing or conduct tests on split samples from QC testing. When QA and QC test results do not compare or have wide variances, additional testing may be needed to validate the results. Additional tests to be performed by Field Inspectors or the third party testing services will be at the direction of the CQAO. The need for QA testing shall be based on the following considerations:
January 2007

5-6

Construction QC/QA Plan


Importance of the item as to its reliability, etc; Need to perform quality checks for fabrication sequences not available for inspection at completion; and Deficiencies are discovered.

QA testing shall be performed in accordance with the following: The CQAO shall develop a weekly quality test and inspection schedule using the construction activity forecast as a guide. The schedule shall: Identify the QA test activities. Identify the hold points The weekly quality test schedule shall be distributed to the CM and CM field staff. The contractor shall be provided a one-day advance notice of impending hold points. Field Inspectors conducting the quality tests and inspections shall complete the Daily Construction Report included in Appendix D. The Daily Construction Report shall be distributed to the CQAO, FE, CM Site Manager, GE managers, contractor PM and/or QC Systems Manager. The CQAO will review QA tests and maintain files for all field QA documentation, 5.2 CONSTRUCTION ACCEPTANCE CRITERIA Construction acceptance criteria for materials qualifications, inspection, and testing are established by technical specifications as illustrated in the example QC tables included in Appendices A (materials qualifications), B (inspection), and C (testing). Criteria for materials and equipment have been set by the Engineer of Record in accordance with the applicable codes and standards, and by manufacturers recommendations. Contractor submittals are to document conformance with acceptance criteria as detailed in their CQCP (control, verification, and acceptance testing plan). 5.3 CONSTRUCTION AUDITS The contractor shall establish and document an auditing system to verify their (or their sub contractors) implementation of and conformance to the CQCP and contract technical specification requirements. The auditing system shall be used to make a determination regarding the effectiveness of the QC system. The contractors auditing shall be planned, performed and documented in accordance with written instructions, procedures or checks to be included in the CQCP. The audit scope, frequency and methods shall be defined in the CQCP. Audits shall be performed by qualified and properly trained personnel who are familiar with the QC system, auditing procedures and techniques. Selection of auditors and the conduct of audits shall ensure the objectivity and
January 2007

5-7

Construction QC/QA Plan


impartiality of the audit process. Auditors shall not audit their own work. The auditing system shall cover all the quality-affecting activities for construction, as well as laboratories and shall be applicable to the onsite and offsite locations, including all subcontractors. The results of the audits shall be documented and reported to the CM. All non-conformance conditions identified during the audit shall be re-audited to verify the corrective actions taken by the appropriate organization were effective. 5.4 COMPLIANCE WITH HANDLING, STORAGE, PACKAGING, PRESERVATION, AND DELIVERY REQUIREMENTS CM field staff will inspect the construction contractors activities to ensure technical compliance in identification, handling, storage, packaging, preservation, and delivery of materials, parts, assemblies, and end products. Related quality records and documents will be maintained and controlled in accordance with the procedures provided in Section 7 of this CQAP. 5.5 MATERIAL IDENTIFICATION AND TRACEABILITY CM field staff will monitor the construction contractor to ensure that identification and traceability requirements are met. Products and materials shall be traced from receipt through all project stages to installation. Documentation such as project control checklists, material receipts, material tracking forms, procedures, sample and test documentation, and reports will ensure that the applicable material item traceability is maintained. Project specifications and/or procedures define product identification and traceability requirements, which generally include the following: Materials or equipment intended for use in construction are identified and segregated until inspection confirms that they conform to technical and quality requirements, and Materials are traceable to documents attesting to their conformance with technical requirements that are stated in specifications or drawings. Testing of materials will also be conducted as necessary to verify conformance with material specifications.

January 2007

5-8

Construction QC/QA Plan SECTION 6 CONSTRUCTION DEFICIENCIES


This section provides procedures for tracking construction deficiencies (noncompliance) from identification through acceptable corrective action. It defines the controls and related responsibilities and authorities for dealing with noncompliant products or services. 6.1 DEFICIENCY IDENTIFICATION Deficiency occurs when a material, performed work, or installation does not meet the plans and/or specifications for the project. 6.2 CONTRACTOR QC DEFICIENCY IDENTIFICATION AND CONTROL When material, performed work, or installation is found deficient, the CQAO (or designee) shall ensure that the non-conforming material, work, or installation is identified and controlled to prevent unintended use or delivery. The CM will notify the contractor of any noncompliance with any of the foregoing requirements. The contractor shall, after receipt of such notice, immediately take corrective action. Minor deficiencies noted during test or inspection are verbally reported to the contractors representative and noted on the Daily Construction Report. Minor deficiencies are items that do not require significant rework or repair work to correct, and will not result in significant deviations from required quality standard if corrected immediately. Control and disposition of such deficiencies shall be by the originator of the Daily Construction Report and the contractors supervisor responsible for the work and do not require formal action by the contractors QC System Manager or the CM. Ideally, such minor deficiencies can be corrected on the spot by agreement with the contractors supervisor. Non-conformances are major deviations from the contract requirement and/or accepted standard of quality, which must be formally documented for corrective action by CM field staff or the third party testing group. Failure by a contractor to correct a minor deficiency after having been put on notice will also result in a non-conformance if it is not corrected within 5 days of notification. Nonconformances shall be formally documented on the example NCR form shown in Appendix D. A log shall be maintained for all NCRs in accordance with the example form shown in Appendix D. The NCR shall be distributed to the contractor QCM, GE, CM, SM and CQAO. The CQAO shall follow up on the NCR as required to verify that corrective action has been completed. The CM or a designated FE shall verify and accept the corrected work by actual inspection.

January 2007

6-1

Construction QC/QA Plan


6.3 NON-CONFORMANCE REPORT The NCR is a formal notification to the contractor that work does not meet the plans or the specifications for the project. Any item of work found to be deficient - out of conformance with the construction drawings and/or specifications - will be identified by the inspector on the nonconformance report as described in this section. Non-conformance reports will be included on the non-conformance log and tracked through verification that the non-conformance has been corrected. 6.4 CONTRACTOR QC DEFICIENCY CORRECTION When material, performed work or installation is found to be deficient and/or does not meet the project specifications, the CQAO will assure deficiency correction is implemented. The CQAO designee shall ensure that the non-conforming material, work or installation is identified and controlled to prevent unintended use or delivery. The non-conforming material or item shall be tagged and segregated by the construction contractor, when practical, from conforming material or items to preclude their inadvertent use. If segregation is impractical or impossible because of the physical characteristics of the item or other reasons, the non-conformance tag shall be displayed prominently to preclude inadvertent use. The CQAO is responsible for documenting the non-conformance in a NCR as specified in Section 6.3. The construction contractor will implement corrective actions to remedy work that is not in accordance with the drawings and specifications. The corrective actions will include removal and replacement of deficient work using methods approved by the CM. Removal must be done in a manner that does not disturb work that meets QC/QA criteria; otherwise, the disturbed material must also be removed and replaced. Replacement must be done in accordance with the corresponding technical specifications. Replacement will be subjected to the same scope of QC/QA inspection and testing as the original work. If the replacement work is not in accordance with the drawings and specifications, the replacement work will be removed, replaced, reinspected, and re-tested. 6.5 PREVENTIVE ACTIONS Preventive actions are taken to eliminate the cause of a potential non-conformity. For example, defects that appear on the surface of concrete during construction or within a relatively short time after completion are usually caused by poor quality materials, improper mix design, lack of proper placing and curing procedures, or poor workmanship. The contractor and QC/QA team shall take preventive actions as necessary to eliminate the causes of potential deficiencies so as to prevent their occurrence. Contractors CQCPs are to include quality improvement practices to continually improve construction practices and address quality problems at their source. The CM and CQAO are to monitor, inspect, and audit processes used to prevent erroneous information or construction products from being passed to the owner. The CM and CQAO have the authority to implement, verify and review the projects preventive and
January 2007

6-2

Construction QC/QA Plan


corrective action effectiveness. They are empowered to improve the projects work processes to eliminate the causes of potential non-conformities.

January 2007

6-3

Construction QC/QA Plan SECTION 7 DOCUMENTATION


The Technical Specification 01450 includes documentation and reporting requirements. Contractors QC documentation must cover all aspects of QC program activities, and includes Daily Inspection Reports and Daily Test Reports. After CQCP approval by the CM, the contractors will document the QC activities pursuant to the CQCP. Ongoing QA oversight will be documented by the CM. Beyond the data reporting required in Section 4.3 of this document, GE proposes that the results of QC/QA procedures conducted to confirm that construction activities meet applicable design criteria, plans and specifications for the FSWC and PEI will not be included on a routine basis in the monthly progress reports under the CD. 7.1 DAILY RECORD KEEPING Project documents will be managed through a combination of a secure document filing and storage system and a computerized document tracking system. Sufficient records shall be prepared and maintained as work is performed to furnish documentary evidence of the quality of construction and laboratory analysis and of activities affecting quality. Each contractor QC technician shall maintain a daily log of all inspections performed for both contractor and subcontractor operations on a form acceptable to the CM. The Daily Inspection and Daily Test reports shall be signed by the responsible QC technician and the QCM. The CM shall be provided at least one copy of each daily inspection and test report on the work day following the day of record. 7.2 DAILY CONSTRUCTION REPORT A daily construction report will be prepared and signed by each FE and FI. The report will include a summary of the contractors daily construction activities. Supporting inspection data sheets will be attached to the daily report where needed. Example forms are provided in Appendix D. At a minimum, the daily construction report will include the following information: Date, project name, location, and other identification Description of weather conditions, including temperature, cloud cover, and precipitation Reports on any meetings held and their results Record of visitors to site
January 2007

7-1

Construction QC/QA Plan


Locations of construction underway during that day Equipment and personnel working in each activity, including subcontractors Descriptions of work being inspected Decisions made regarding approval of units of material or of work, and corrective actions to be taken Description of problems or delays and resolution Communications with contractor staff Construction activities completed and/or in progress Progress photos, where applicable Signature of the report preparer As described in Section 7.6, the daily construction reports will be routed on a daily basis to the project QC/QA files and will be maintained as part of the permanent project record. These reports are reviewed by the CM and FE, and also distributed to the CQAO and GE 7.3 INSPECTION AND TESTING REPORT FORMS Report forms will be completed for inspections and tests conducted. The forms vary depending on inspection or test type. Representative forms for several types of inspection and testing reports are included in Appendix D. These forms include: Description or title of the inspection activity Location of the inspection activity or location from which the sample was obtained Recorded observation or test data Results of the inspection activity Personnel involved in the inspection activity Signature of the inspector

7.4 RECORD DRAWINGS Contractors will submit draft record drawings to the CM for review and prepare final record drawings based on CM comments. The draft record drawings shall be submitted on one set of CD-ROM disks. Record drawings submitted on CD-ROM shall be the latest version of AutoCAD by AutoDesk, Inc. 7.4.1 Responsibilities The CM working with the contractor will be responsible for assuring that red-line record drawings are maintained daily throughout the construction process. These red-line record

January 2007

7-2

Construction QC/QA Plan


drawings will be used to update the design drawings to as-built status at the completion of the work. 7.4.2 Preparation of As-Built Drawings The contractor will be responsible for red-lining construction drawings in the field as preparation for as-built drawings. The as-built drawings will record approved actual field conditions upon completion of the work. The original design drawings will be marked up by the contractor as the project progresses to indicate as-built conditions. Where there was a change to a specified material, dimension, location, or other feature, the as-built drawing will indicate the work performed. 7.4.3 Review of As-Built Drawings Upon the completion of the as-built red-line drawings, the contractor will submit the red-line mark-up drawings to the CM for review. The CM will provide the mark-ups to the Engineer of Record who will incorporate the mark-ups and issue the final as-built drawings to GE and the CM. 7.5 CONTROL OF QUALITY RECORDS The CQAO verifies QA record accuracy and maintains copies of all quality-related documentation. This includes, but may not be limited to: Daily construction QA logs and records; Inspection checklists and reports; Surveillance reports; Non-conformance reports; Material receiving reports; and Monitoring and test data.

These records will be stored in files maintained in the project document control files. All original documents pertaining to project information will be maintained in the project file located at the project office in Fort Edward, New York. The CM and SM have primary responsibility for the centralized document control files for the project and construction documentation. Pursuant to the contract specifications, the contractor provides an electronic or paper copy (suitable for scanning) of QC documentation associated with the work to document control within three business days of the generation of such documents; and one electronic copy of all required submittals to CMs document manager. All contractors shall maintain a fire-resistant storage facility at the processing facility site. The facility shall contain all inspection reports, test records, contract documents, project, and daily field reports.
January 2007

7-3

Construction QC/QA Plan


All records shall be available for inspection and audit, at any time, by the CM and GE.

January 2007

7-4

Construction QC/QA Plan SECTION 8 EPA APPROVALS


This section addresses EPA approvals associated with construction quality aspects of the Phase 1 FSWC and PEI. 8.1 REQUIRED SUBMITTALS Submittals required for EPA approval applicable to QC/QA of FSWC and PEI are this CQAP and the Phase 1 Work Completion Report pursuant to CD Paragraph 58 (EPA/GE 2005). EPA approval is not required for FSWC and PEI contractor submittals other than those submitted to EPA as part of the FSWC and PEI RAWPs. 8.1.1 CQAP GE will submit this CQAP for EPA approval prior to commencement of Phase 1 FSWC. The CQAO is responsible for maintaining this CQAP during the FSWC and PEI process. Revisions to the CQAP will be approved in the same manner as the original. 8.1.2 Phase 1 Work Completion Report GE will include quality related documents for Phase 1 FSWC and PEI via the Phase 1 Work Completion Report at completion of Phase 1. The quality related documents to be included in the Phase 1 Work Completion Report are further described in Section 10. 8.2 EPA APPROVAL EPA response to any plan, report, or other item that requires approval is described in the CD (paragraphs 45, 46, and 47). EPA, following a review, may: Approve the submission, in whole or in part; Approve the submission with specified conditions; Modify the submission to cure deficiencies; Disapprove the submission; or Any combination of these provided that any such modification or direction would not materially expand the SOW.

EPA will not modify a submission without providing at least one notice of deficiency and 21 days to correct the deficiency. Following the correction process, the plan, report, or other item will be resubmitted for approval.

January 2007

8-1

Construction QC/QA Plan SECTION 9 FIELD CHANGES


Field changes for QC/QA will be limited to CQAP and CQCP changes. Changes to construction processes or design plans and specifications are governed by the RAWPs and design change order procedures. 9.1 CQAP CHANGES GE, the CM, SM, or CQAO may initiate revisions to this CQAP. The CQAP may be revised when it becomes apparent that the CQAP procedures or controls are inadequate to support work being produced in conformance with the specified quality requirements or are deemed to be more excessive than required to support work being produced in conformance with the specified quality requirements. Changes to QA procedures necessitating modification to this CQAP will be initiated by the CQAO for CM and GE approval. EPA review and approval will then be accomplished as described in Section 8, EPA Approvals. Updates to CQAP staffing will be made by GE notification to EPA as described in Section 2.3 without submission of a fully revised CQAP. 9.2 QC CHANGES The contractors CQCP required by Technical Specification 01450 may require revisions as necessary to correct unsatisfactory performance. At any time after approval by the CM, GE and the CM may require the contractor to make changes to the CQCP, including personnel changes, as necessary to obtain the quality specified. Moreover, the contractor may initiate CQCP changes to correct QC process problems, and is required to notify the CM in writing of any desired changes; all changes are subject to GE and CM acceptance. Revisions to the CQCP will not be submitted to EPA for approval.

January 2007

9-1

Construction QC/QA Plan SECTION 10 FINAL REPORTING


The following quality related documents will be generated during Phase 1 FSWC and PEI and will be submitted to EPA as part of the Phase 1 Work Completion Report: record (as-built) drawings; operation and maintenance manuals; and results of the Start-up and Testing Plan and the Commissioning Plan implemented for each major piece of equipment or system before system turnover, in accordance with Specification 01810.

January 2007

10-1

Construction QC/QA Plan SECTION 11 REFERENCES


Blasland, Bouck & Lee, Inc. 2006. Phase 1 Final Design Report Hudson River PCBs Superfund Site (including Contract drawings and specifications). March, 2006 Parsons. 2005. GE Response to US EPA Region 2 Consent Order Item 10b Parsons Commercial Technology Group Inc. Quality Management Plan (QMP). October 7, 2005. Parsons. 2007. Remedial Action Work Plan for Phase 1 Facility Site Work Construction Hudson River PCBs Superfund Site. January, 2007 United States Environmental Protection Agency. February 1, 2002. 2002. Superfund Record of Decision.

United States Environmental Protection Agency and General Electric Company. 2003. Administrative Order on Consent for Hudson River Remedial Design and Cost Recovery. Index No. CERCLA-02-2003- 2027. United States Environmental Protection Agency and General Electric Company. 2005. Consent Decree in United States v. General Electric Company, Civil Action No. 1:05-cv-1270, lodged in United States District Court for the Northern District of New York October 6, 2005; final judgment entered November 2, 2006.

January 2007

11-1

Construction QC/QA Plan

ATTACHMENT 1 CQAP STAFFING LIST AND RESUMES

January 2007

Construction QC/QA Plan CQAP STAFFING LIST


Construction Quality Control/Quality Assurance Plan (CQAP) Phase 1 Facility Site Work Construction Hudson River PCBs Superfund Site Revision: 0, Date: 1-26-07 The following personnel are assigned CQAP functions effective as indicated below. Periodic updates to this chart are to be issued by the Construction Manager. FUNCTION Construction QA Officer Field Inspector Field Inspector QA Field Inspector NAME Ziad A. Nabulsi (TBD) (TBD) (TBD) CM CM CM CM ORGANIZATION

/s/ Larry Hartman_____________________________ CM Approval

1-26-2007___ Date

January 2007

Firm
Parsons

ZIAD A. NABULSI Senior Quality Assurance Engineer


Summary of Relevant Qualifications
Senior Quality Assurance Engineer/Civil Engineer/ construction with over twenty years of experience in construction of commercial, municipal, and transportation works, to include: concrete structures, paving, underground utilities, earthen structures and tunnels. Conducts internal project technical quality audits and presents audit reports to management and the project team. Prepares the audit checklists; conducts the pre-audit meeting; issues findings (when required); prepares and issues the final audit report, recommending opportunities for improvement; and follows up to verify that the appropriate corrective actions have been completed. Work Experience Selected Projects

Years of Experience 24 Education University of Alabama, Birmingham, 1983: Bachelor of Science in Civil Engineering ISO 9001:2000 Lead Auditor Course Certificate No. 4573341-26429 Certificate of Quality Assurance and Quality Control in Transit Projects 2005 Training Certificate from Corp of Engineers Construction Quality Management for Contractors 2001 Training Certificate - OSHA update Seminar 1995 Training Certificate - 100% Fall Management 1994 Certificate of Completion NUCA Competent Person 1994: NUCA Confined Space Entry Program Courses for Computer (PC), Windows XP, MS Office 2000 Affiliations American Society of Civil Engineers Special Skills Fluent in Arabic, English.

Senior Quality Assurance Engineer/QA Manager PARCOMM & PTG/ South Corridor Light Rail projectCharlotte, NC
Conducting internal project technical quality audits and presents audit reports to management and project team. Responsible for scheduling audits; preparing the audit checklists; conducting the pre-audit meeting; issuing findings (when required); preparing and issuing the final audit report, recommending opportunities for improvement; and following up to verify that the appropriate corrective actions have been completed. Responsibilities include implementation and maintenance of design quality management plan and procedures; auditing of design QA/QC activities to ensure conformance with the project requirements and certifying that all design submittals have been processed in accordance with the project quality management plan. Senior Quality Assurance Engineer Responsible for conducting quality assurance audits for the following programs and projects: Northrop Grumman Ship Systems - Construction Management - Facility Modernization Gulfport & Pascagoula MS. And New Orleans, LA. Evaluation of alternatives for South Effluent Treater (SET) Shell Project - Environmental Remediation Project Houston, TX. EMAAR Development Project, Emirates Hills, Construction Management- Dubai, UAE. Wastewater treatment and reuse system at Amgens Juncos - Construction Performance Support Services - Puerto Rico biotech plant.

Ziad A. Nabulsi Continued


Project Manager/Civil Engineer Parsons Infrastructure and Technology-TSSC III; Atlanta, GA Manage the Pre-Bid and Pre-Construction Meetings in conjunction with scheduling engineer availability during the startup of construction, and estimating the cost requirements. Ensures compliance with ISO 9001 procedures by implementing policies and programs through Quality Control. Conduct quality audits of field project/job sites to ensure the Contractors approach is fully satisfactory and compliant with the contract. Also conduct internal office quality audits. Civil Engineer Lockheed-Martin Services; Atlanta, GA Prime consulting assignment as a civil engineer responsible for evaluating the readiness and condition of Federal Aviation Administration (FAA) facilities implementing newer airway management platforms. Duties included nationwide travel, to numerous airport facilities to evaluate, trouble-shoot, and plan improvements for system repairs, building renovations and new construction. Field Engineer/ Quality Control Engineer Parsons Constructors Inc., Newport, IN Responsible for field oversight of Quality Control procedures for Parsons and subcontractor work force. Reviewed and interpreted design drawings and specifications to ensure current revision level and correct technical execution of work. Provided progress data to Resident Engineer and Construction Manager. Responded to subcontractor RFIs maintained As-Built drawings verified and approved monthly pay applications. Civil Superintendent/ Quality Control Engineer PARSONS Communications; Atlanta, GA Managed construction of civil, structural, and architectural works for $63 million, AT&T Web Hosting Facility. Managed subcontractor work force. Inspected progress of work for conformance to contract documents. Devised and implemented field corrections to design errors, impact issues, and unforeseen conditions. Responded to subcontractor RFIs, reviewed submittals, maintained As-Built drawings, Quality Control, verified and approved monthly pay applications, evaluated and processed change orders. Civil and Structural Inspector/Quality Control Desmear Systems, Inc. and Parsons Brinkerhoff/Tudor Responsible for monitoring quality activities in accordance with contract documents. Coordinated surveys and material testing of soils, concrete, paving, structural steel, and architectural finishes.

Construction QC/QA Plan

APPENDIX A SAMPLE QUALIFICATION TEST SCHEDULES

January 2007

Construction QC/QA Plan


TABLE A-1 Example Qualification Test Schedule Onsite Borrow Materials

Test Parameter Soil Classification Atterberg Limits Grain- Size Distribution Moisture Content

Test Method ASTM D2487 ASTM D4318 ASTM D422 or C136 ASTM D2216/ D2974

Minimum QC Testing Frequency by contractor 1 per 1,000 cubic yard and source change 1 per 1,000 cubic yard and source change 1 per 1,000 cubic yard and source change 1 per 1,000 cubic yard and source change

Acceptance Criteria (verified by QA) GW, GP, GM, GC, SW, SP, SM, SC, or ML In accordance with Section 02205 In accordance with Section 02205. Article 2.01.I In accordance with Section 02201 through 02205 and Section 02911

Notes: 1. Borrow soil must be from approved on-site borrow source with test results provided in Section 02205. Any change in material must be consistent with approved material characteristics as determined by CM. New moisture content curves will need to be plotted for change in material. 2. Note: this table is for illustration only and is not intended to replace or modify contract specifications that will form the basis of actual CQCP submittals by contractors

January 2007

Page A1

Construction QC/QA Plan


TABLE A-2 Example of Qualification Test Schedule Aggregate Materials

Test Parameter Coarse Aggregate Grain-Size Distribution

Test Method

Minimum QC Testing Frequency by Contractor

Acceptance Criteria (verified by QA)

ASTM D422 or C136 ASTM D2974

1 per stockpile and In accordance with table source change in Article 2.01B in Section 02205 1 per stockpile and As reported for source change establishing the range of optimum moisture content 1 per stockpile and As reported for source change establishing the range of optimum compaction

Moisture Content

Compaction Characteristics Fine Aggregate Grain-Size Distribution

ASTM D1557

ASTM D422 or C136 ASTM D2974

1 per stockpile and In accordance with table source change in Article 2.01 B in Section 02205 1 per stockpile and As reported for source change establishing the range of optimum moisture content

Moisture Content

1 per stockpile and As reported for source change establishing the range of optimum compaction Note: this table is for illustration only and is not intended to replace or modify contract specifications that will form the basis of actual CQCP submittals by contractors

Compaction Characteristics

ASTM D1557

January 2007

Page A2

Construction QC/QA Plan


TABLE A-3 Example Qualification Test Schedule Cementatious Materials

Test Parameter Portland Cement Chemical & Physical Requirements

Test Method

Minimum QC Testing Frequency by Contractor

Acceptance Criteria (verified by QA)

ASTM C150

Prior to use in concrete mix in absence of material certification

In accordance with tables in ASTM C150 for Type II Low Alkali

Fluidized Bed Ash In accordance with tables in ASTM C311 for Class F material, except loss on ignition shall not exceed 4% Note: this table is for illustration only and is not intended to replace or modify contract specifications that will form the basis of actual CQCP submittals by contractors. Chemical & Physical Requirements ASTM C311 Prior to use in concrete mix in absence of material certification

January 2007

Page A3

Construction QC/QA Plan


TABLE A-4 Example Qualification Test Schedule Stone Aggregate Materials

Test Parameter Sieve Analysis

Test Method ASTM C136; C33 and as required by NYSDOT Specification 703.02

Minimum QC Testing Frequency by Contractor Prior to use in concrete mix and whenever character or source is changed

Acceptance Criteria (verified by QA) Max coarse aggregate size of No. 57 or 67 gradation per ASTM C33. Fine aggregate shall pass No. 4 sieve, gradation to conform with ASTM C33 and NYSDOT as specified in Article 2.01- C in Section 03001 Fine aggregate not darker than reference standard color per ASTM C40. Sand exhibiting a color darker than the referenced color shall be rejected. Loss resulting after 5 cycles not to exceed 8% for coarse aggregate or 10% for fine aggregate when using sodium sulfate solution or 11% for coarse aggregate or 14% for fine aggregate when using magnesium sulfate per ASTM C33 Loss not to exceed 10.5% after 100 revolutions, 42% after 500 revolutions

Organic Impurities

ASTM C40

Prior to use in concrete mix and whenever character or source is changed Prior to use in concrete mix and whenever character or source is changed

Soundness

ASTM C33

Abrasion

ASTM C131

Prior to use in concrete mix and whenever character or source is changed Prior to use in concrete mix and whenever character or source is changed

Deleterious Materials

ASTM C33

In accordance with tables in ASTM C33

January 2007

Page A4

Construction QC/QA Plan


TABLE A-4 (cont.) Example Qualification Test Schedule Stone Aggregate Materials

Test Parameter Material Finer 200 Sieve Than

Test Method ASTM C117

Minimum QC Testing Frequency by Contractor Prior to use in concrete mix and whenever character or source is changed Prior to use in concrete mix and whenever character or source is changed Prior to use in concrete mix and whenever character or source is changed

Acceptance Criteria (verified by QA) Not to exceed 1% for gravel or 1.5% for crushed aggregate per ASTM C33 Aggregates considered innocuous in accordance with ASTM C289

Alkali Reactivity

ASTM C227

Quality not less than 75 for average of three Specification identical samples nor less 703.02 than 70 for an individual sample Note: this table is for illustration only and is not intended to replace or modify contract specifications that will form the basis of actual CQCP submittals by contractors

Cleanliness and Sand Equivalent

NYSDOT

January 2007

Page A5

Construction QC/QA Plan


TABLE A-5 Qualification Test Schedule Concrete Mix

Test Parameter Compressive Strength

Test Method ASTM C39

Minimum QC Testing Frequency by Contractor Preliminary testing of mix design; test at 28 days

Acceptance Criteria (verified by QA) Min 5000 PSI Min 4000 PSI Min 3000 PSI Min 2500 PSI

Water/Cement Ratio

Preliminary testing of mix design

Limit to 0.35, 0.45,0.58 and max by weight accordance with section 03001 article 2.05 All concrete not containing a high range water-reducing admixture (super plasticizer) shall conform to these Max. slump values: Reinforced concretegeneral 4, Non-reinforced concrete 3, pavement, sidewalk 3, Slab on grade 3 and Floor toppings 2.

Slump Test

ASTM C143

1 per batch prior to pouring concrete

Notes 1. Preliminary testing of the mix design will be performed by Construction Contractors Independent Testing Laboratory (Third Party lab services). 2. This table is for illustration only and is not intended to replace or modify contract specifications that will form the basis of actual CQCP submittals by contractors

January 2007

Page A6

Construction QC/QA Plan

APPENDIX B SAMPLE INSPECTION SCHEDULES

January 2007

Construction QC/QA Plan


TABLE B-1 EXAMPLE INSPECTION SCHEDULE ONSITE BORROW MATERIALS PLACEMENT Minimum QC Inspection Frequency by Contractor Continuous Continuous

Inspection Parameter Soil Texture and Color Presence of Foreign Objects and Materials Maximum Clod Size Equipment Size and Type Method of Placement Lift Thickness for Earthen Berm

Acceptance Criteria (verified by QA) Similar to approved material Free of visible contamination, organic material, rubbish, debris, and other unsatisfactory materials No fragments larger than 3-inch that will not breakdown under hand compression. In accordance with approved Work Plan In accordance with approved Work Plan First lift 12-inch max. loose, subsequent lifts 8-inch max. loose, final lift 4-inch max loose, hand placed lifts 3-inch max. loose Max. 8-inch loose per lift

Continuous Daily Daily 1 per lift

Lift Thickness for all other applications

1 per lift

Note: this table is for illustration only and is not intended to replace or modify contract specifications that will form the basis of actual CQCP submittals by contractors

January 2007

Page B1

Construction QC/QA Plan


TABLE B-2 EXAMPLE OF INSPECTION SCHEDULE AGGREGATE PLACEMENT Minimum QC Inspection Frequency by Contractor

Inspection Parameter Coarse Aggregate Material Characteristic Maximum Size Equipment Size and Type Method of Placement Lift Thickness Fine Aggregate Material Characteristic Maximum Size Equipment Size and Type Method of Aggregate Placement

Acceptance Criteria (verified by QA)

Continuous Continuous Daily Daily 1 per lift

NYSDOT Type 2, may include up to 50% of reclaimed materials 1 -inch In accordance with approved Work Plan In accordance with approved Work Plan 8-inch loose per lift

Continuous Continuous Daily Daily

NYSDOT Type 2, may include up to 50% of reclaimed materials -inch In accordance with approved Work Plan In accordance with approved Work Plan

Lift Thickness 1 per lift Min. 8-inch loose per lift Note: this table is for illustration only and is not intended to replace or modify contract specifications that will form the basis of actual CQCP submittals by contractors

January 2007

Page B2

Construction QC/QA Plan


TABLE B-3 EXAMPLE OF INSPECTION SCHEDULE STEEL H- PILES (ASTM A 36/ A 36M) Inspection Parameter Material Condition Minimum QC Inspection Frequency by Contractor Upon receipt at Site

Acceptance Criteria (verified by QA) Inspect piles for excessive camber and sweep and damage before transporting them from the storage area to driving area. Max permissible camber and / or sweep shall be 2-inch over the length of the pile. In accordance with approved Work Plan, the impact hammers shall be steam, air or diesel-power pile hammers of single-acting, double-acting. The rate driving energy of hammers shall be limited to minimum of 30,000 foot-pounds. The refusal criteria, hard driving in excess of 20 blows per 25mm inch and accordance with Section 02315 Article 3.01. A final variation in rotation of the pile about the center line of the web of not more than 7.5 degrees will be permitted. A vertical deviation of not more than 1-inch from the correct cutoff elevation shown will be permitted. Max 1-inch heave, otherwise re-drive piles to original elevations

Equipment and Type

Size

Daily

Alignment

After driving each production pile

Heave Checks

After driving first pile group and on selected pile groups as directed by CMs Geotechnical Engineer After driving each production pile

Production Piles

Piles damaged or not located properly or exceeding the maximum limits for rotation, lateral and vertical deviation, or variation in alignment shall be pulled and new piles redrive, or provide additional piles, at a location directed at no additional cost to the Owner. 1. Inspection will be performed by Contractor QC and verified by CM staff & QA staff. 2. This schedule is for illustration only and is not intended to replace or modify contract specifications that will form the basis of actual CQCP submittals by contractors.

January 2007

Page B3

Construction QC/QA Plan


TABLE B-4 EXAMPLE OF INSPECTION SCHEDULE REINFORCING, FORMWORK AND CAST-IN-PLACE CONCRETE

Inspection Parameter Reinforcing Material Condition Reinforcing Bundle Identification Reinforcing Material Storage In-Place Reinforcing

Minimum QC Inspection Frequency by Contractor Upon receipt at Site Upon receipt at Site Daily Prior to closing forms and continuous during pouring Prior to pouring of concrete

Acceptance Criteria (verified by QA) No visible defects or damage, no unscheduled kinks or bends Bundled and tagged with information as specified in Section 03200 In accordance with Manufacturers recommendations & approved Work Plan In accordance with approved Work Plan, free of old mortar, oils, mill scale and other encrustations or coatings In accordance with approved Work Plan; no excess water, hardened concrete, debris or foreign materials inside of forms, wet wood forms sufficiently to tighten up cracks Load accompanied by weightmaster bonded certificate, water container full, water added to concrete mixture in accordance with Section 03301

In-Place Formwork

Concrete Truck

Upon arrival at Site

Prior to pouring of Fine grade earth and aggregate smooth concrete and level Note: this table is for illustration only and is not intended to replace or modify contract specifications that will form the basis of actual CQCP submittals by contractors

Subgrade Preparation

January 2007

Page B4

Construction QC/QA Plan


TABLE B-4 (cont.) EXAMPLE OF INSPECTION SCHEDULE REINFORCING, FORMWORK AND CAST-IN-PLACE CONCRETE

Inspection Parameter Concrete Placement

Minimum QC Inspection Frequency by Contractor Continuous during pouring of concrete

Acceptance Criteria (verified by QA) In accordance with approved Work Plan, height of concrete drop not to exceed 5 feet, place and compact within 60 minutes after water is first added, do not place after evidence of initial set In accordance with approved Work Plan Max. 18 inches per lift in continuous approximately horizontal layers 1/4-inch from 10-foot straightedge for exposed finishes, no low spots to impound water Forms maintained in wet condition until removed, concrete continuously moist for min of 7 days after pouring Fill holes and patch surfaces in accordance with Section 03301

Equipment Size and Type Concrete Lift Thickness Maximum Deviation

Continuous during pouring of concrete Continuous during pouring of concrete Continuous during compaction of concrete Daily during curing of concrete After finishing of concrete

Formed Concrete Curing

Formed Concrete Finishing

Slabs and Flatwork Daily during curing of Concrete continuously wet for entire Curing concrete curing period Note: this table is for illustration only and is not intended to replace or modify contract specifications that will form the basis of actual CQCP submittals by contractors

January 2007

Page B5

Construction QC/QA Plan

APPENDIX C SAMPLE TEST SCHEDULES

January 2007

Construction QC/QA Plan


TABLE C-1 EXAMPLE OF TESTING SCHEDULE ONSITE BORROW MATERIAL PLACEMENT

Test Parameter Compaction for Earthen Berm Compaction for all other applications In-Place Density

Test Method ASTM D1557

Minimum QC Testing Frequency by Contractor 1 per lift

Acceptance Criteria (verified by QA) 90% max. dry density in accordance with ASTM D1557 95% max. dry density in accordance with ASTM D1557 In accordance with ASTM 2922 +/- 2% of optimum moisture content in accordance with Attachments 02200-1 through 02200-4

ASTM D1557

1 per lift

ASTM D2922/ or D1556 ASTM D3017

1 per compacted lift but not less than 1 per 2,500 SF 1 per compacted lift but not less than 1 per 2,500 SF

In-Place Moisture Content

1. Borrow soil must be from approved on-site borrow source with test results provided in Section 02200. Any change in material must be consistent with the approved material characteristics as determined by the Construction Manager. New moisture content curves will need to be plotted for change in material
2.

Note: this table is for illustration only and is not intended to replace or modify contract specifications that will form the basis of actual CQCP submittals by contractors

January 2007

Page C1

Construction QC/QA Plan


TABLE C-2 EXAMPLE TESTING SCHEDULE AGGREGATE MATERIAL PLACEMENT

Test Parameter Coarse Aggregate Compaction

Test Method

Minimum QC Testing Frequency by Contractor

Acceptance Criteria (verified by QA)

ASTM D1557

1 per compacted lift

95% max. dry density in accordance with ASTM D1557 In accordance with ASTM D2922 +/- 1% of optimum moisture content in accordance with ASTM D3017

In-Place Density In-Place Moisture Content

ASTM D2922 ASTM D3017

1 per compacted lift 1 per compacted lift

Fine Aggregate Compaction ASTM D1557 1 per compacted lift 95% max. dry density in accordance with ASTM D1557 In accordance with ASTM D2922

In-Place Density In-Place Moisture Content

ASTM D2922 ASTM D3017

1 per compacted lift 1 per compacted lift

+/- 1% of optimum moisture content in accordance with ASTM D3017/ D2974 Note: this table is for illustration only and is not intended to replace or modify contract specifications that will form the basis of actual CQCP submittals by contractors

January 2007

Page C2

Construction QC/QA Plan


TABLE C-3 EXAMPLE TESTING SCHEDULE STEEL H-PILES Minimum QC Testing Frequency by Contractor Prior to driving production piles

Test Parameter Load Test

Test Method ASTM D1143

Acceptance Criteria (verified by QA)

A compressive load of 300% of design load shall be applied to each compressive load test pile. Note: this table is for illustration only and is not intended to replace or modify contract specifications that will form the basis of actual CQCP submittals by contractors

January 2007

Page C3

Construction QC/QA Plan


TABLE C-4 EXAMPLE TESTING SCHEDULE CONCRETE Minimum QC Testing Frequency by Contractor 1 per 50 CY or fraction thereof from each days placing; test at 7 and 28 days

Test Parameter Compressive Strength

Test Method ASTM C39

Acceptance Criteria (verified by QA) Min 5000 psi Min 4000 psi Min 3000 psi Min 2500 psi

Air Content Slump Test

ASTM C231 or C172 ASTM C143

When compression test cylinders are cast When compression test cylinders are cast

In accordance with ASTM C231 or C172 In accordance with ASTM C143. Slump values:

Reinforced concretegeneral 4 inches, Nonreinforced concrete 3 inches, pavement, sidewalk 3 inches, Slab on grade 3 inches and Floor toppings 2 inches. Note: this table is for illustration only and is not intended to replace or modify contract specifications that will form the basis of actual CQCP submittals by contractors

January 2007

Page C4

Construction QC/QA Plan

APPENDIX D TYPICAL CONSTRUCTION FORMS

January 2007

Construction QC/QA Plan

The following typical forms are included in this appendix: D-1 D-2 D-3 D-4 D-5 D-6 D-7 D-8 D-9 Daily Construction Report Quality Inspection Report Receiving Inspection Report (Not Used) Field Inspection Checklist Earthwork Field Inspection Checklist Solidification Field Inspection Checklist Structural Steel Erection Daily Concrete Inspection Report Concrete Placement Checklist Field Inspection Checklist Placing, Consolidation, Finishing, Curing and Repair of Concrete

D-10 Field Inspection Checklist Pre-Cast and Cast-in-Place Concrete Piles D-11 Field Inspection Checklist Critical Piping D-12 Electrical Inspection/Test Sheet Ground Rod Earth Resistance Test D-13 Electrical Inspection/Test Sheet Ground Grid Earth Resistance Test D-14 Electrical Inspection/Test Sheet Light Installation D-15 Electrical Inspection/Test Sheet Combination Starter, PB and Selector Switches Control System Components D-16 Electrical Inspection/Test Sheet Continuity Test of all Fixture Bodies to Ground D-17 Electrical Inspection/Test Sheet Cable Test Procedures D-18 Electrical Inspection/Test Sheet Conduit and Junction/Outlet Boxes Installation D-19 Electrical Inspection/Test Sheet Cable and Cable Accessories/Panelboard/ Wiring Devices D-20 Electrical Inspection/Test Sheet Electrical Service and Distribution System D-21 Electrical Inspection/Test Sheet Molded Case Circuit Breaker Test Record

January 2007

Construction QC/QA Plan

D-22 Electrical Inspection/Test Sheet Cable Test Record D-23 Electrical Inspection/Test Sheet Motor Test Record D-24 Inspection Notification Form D-25 Non-conformance Report D-26 Non-conformance Report Log D-27 Contractor Non-Conformance Letter (Sample) The format, layout, content and method used to fill out the forms will be reviewed periodically during the course of construction and modified as required to ensure that the necessary information required for management of the construction contracts and controlling the progress and quality of the work is being obtained.

January 2007

Parsons
DAILY CONSTRUCTION REPORT PHASE 1 FACILITY SITE WORK CONSTRUCTION/ HUDSON RIVER
DAILY CONSTRUCTION REPORT
REPORT NO. DATE:

JOB NAME: JOB LOCATION: LOCATION OF CONSTRUCTION UNDERWAY: CONTRACTOR:

Page of

WEATHER CONDITION:

Hi
CONTRACTORS SUPERINTENDENT: SUBCONTRACTORS (*):

PRECIPITATION: GROUND CONDITIONS: TIMES: START STOP

AM / PM f / Lo f

INCH(S)

0000AM
CLASSIFI CATION

0:00 PM
HOU RS

NAME / COMPANY

EQUIPMENT

TIMES:

START

STOP

0000AM

0:00 PM

MEETING:

WORK BEING INSPECTED:

PROBLEM/DELAYS/CORRECTIVE ACTION TO BE TAKEN:

D-1

Parsons
DAILY CONSTRUCTION REPORT PHASE 1 FACILITY SITE WORK CONSTRUCTION/ HUDSON RIVER WORK PERFORMED Work started at 00:00 am.
CONSTRUCTION ACTIVITIES COMPLETED AND /OR IN PROGRESS:

COMMUNICATION WITH CONTRACTOR STAFF:

PROGRESS PHOTOS:

Departed job site at 00:00 pm. Visitors: Inspector Name: Field Engineer Name: Signature: Signature:

D-1

Job Number Quality Inspection Report

Project

Page of 1/1

CONTRACTOR: _____________________________________________ TYPE OF INSPECTION: Preparatory Inspection. Initial Inspection.

REPORT NUMBER: ________________ Follow-up Inspection. Completion Inspection.

DESCRIPTION/INTENT OF INSPECTION: _____________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ COMPONENTS/MATERIALS REVIEWED: ____________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ CONTRACTOR PERSONNEL CONTACTED: __________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ APPLICABLE CONTRACTOR PROCEDURES, CHECK LISTS, INSTRUCTIONS: ____________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ RESULTS OF INSPECTION: _________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ DEFICIENCIES NOTED: ____________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ RECOMMENDED CORRECTIVE ACTION: ____________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ NON-CONFORMANCES: ___________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________

QA Inspector Signature:

Date:

D-2

Job Number Receiving Inspection Report

Project

Page of 1/1

PURCHASE ORDER _______________ SPECIFICATION _________________

C.O. _______________________ REV. ________

REPORT NUMBER ______________ REV. _________

DRAWING ___________________

SUPPLIER _________________________________

ITEM ____________________

QUANTITY ____________

DOCUMENTATION

DOCUMENTS COMPLETE PER CONTRACTUAL REQTS: __________________ DOCUMENTS TRACEABLE TO ITEMS RECD: _______________

LEGIBLE: ________________

STAMPED BY SURV. REP: _____________

LIST DOCUMENT PKG. DISCREPANCIES (IF ANY): ___________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ RESOLUTION: ____________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ DOCUMENT PKG. ACCEPTABLE: ________________ QC SIGNATURE: _________________________________ DATE: __________________________________________ REMARKS: _______________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________

PHYSICAL INSPECTION

CHECK LIST NO: __________________

ITEMS PROPERLY TAGGED/MARKED: ________________________

ENTER SERIAL AND/OR HEAT NO: _________________________________________________________________ RESULTS OF INSPECTION: _________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ DEFICIENCY NO. (IF ANY): _____________________ DEFICIENCY RESOLVED: _________________________

INSPECTION ACCEPTABLE TAG ATTACHED: ________________________________________________________

QC SIGNATURE: ____________________________________________________

DATE: _____________________

D-3

Job Number Field Inspection Checklist Earthwork

Project

Page of 1/2

CONTRACTOR: ______________________________________________

CONTRACT NO: ___________________

REFERENCES (DRAWING, SPECIFICATION, PROCEDURE): _____________________________________________ ATTRIBUTE A 1. 2. 3. 4. 5. GENERAL Is area released for work? Is equipment adequate? Are existing structures and utilities adequately protected? Is removed material properly dispositioned? Dust and dirt control: a) Haul routes maintained for dust control by water or chemicals? b) All paved areas kept clean? B 1. 2. 3. C 1. EXCAVATION OF TRENCHING Does completed depth and configuration comply with drawings and specifications? Required shoring and bracing in place? Existing utilities protected? PLACING AND COMPACTING FILL Excavation properly compacted and verified by test lab? a) All sleeves, pipe cable, grounding, conduit installed and approved? 2. 3. 4. 5. D 1. Approved fill material is used? Is fill being placed in level lifts within thickness limits? Is proper compaction attained and verified by test lab? Have contaminated (and spongy) areas been cut out, filled and compacted with approved material? BEDDING AND BACKFILL OF PIPE AND UTILITY TRENCHES Approved bedding and backfill material is used? a) Is bedding fully compacted to support pipe or utility at line, grade, and slope required and verified by inspector? E 1. GRADING Approved grading material used? a) Final shaping/compacting and blade and 3-wheel rollers of 8-10 ton? 2. Sufficient slope for positive drainage away from structures to drainage system? YES NO N/A

D-4

Job Number Field Inspection Checklist Earthwork

Project

Page of 2/2

CONTRACTOR: ______________________________________________

CONTRACT NO: ___________________

REFERENCES (DRAWING, SPECIFICATION, PROCEDURE): _____________________________________________

ATTRIBUTE 3. 4. Is rough grading reasonably even and free of irregularity and allowance made for finish grading? Is finished grade: a) Cleaned of all loose and foreign material? b) Smooth and even in profile (= 1 in 10) and not more than 1 from true elevation?

YES

NO

N/A

REMARKS: _______________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________

QC SIGNATURE: ____________________________________________________

DATE: _____________________

D-4

Job Number Field Inspection Checklist Solidification

Project

Page of 1/1

CONTRACTOR: ______________________________________________

CONTRACT NO: ___________________

REFERENCES (DRAWING, SPECIFICATION, PROCEDURE): _____________________________________________

ATTRIBUTE A 1. 2. 3. 4. 5. B 1. GENERAL Is area released for work? Is equipment adequate? Adequate dust control maintained? Appropriate mix proportions? Appropriate mixing time and speed? SAMPLING AND TESTING Collection, curing and testing in accordance with requirements?

YES

NO

N/A

REMARKS: _______________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________

QC SIGNATURE: ____________________________________________________

DATE: _____________________

D-5

Job Number Field Inspection Checklist Structural Steel Erection CONTRACTOR: ______________________________________________

Project

Page of 1/2

CONTRACT NO: ___________________

REFERENCES (DRAWING, SPECIFICATION, PROCEDURE): _____________________________________________ ATTRIBUTE A 1. 2. 3. 4. 5. B 1. 2. 3. 4. 5. 6. 7. 8. C 1. 2. 3. 4. D 1. 2. 3. 4. 5. STORAGE Storage provided adequate? Drainage provided? Steel properly blocked and stacked? Evidence of excessive rusting? Faying surfaces properly protected? High strength bolting segregated from common fasteners? BOLTING Bolts, nuts, washers square with mating surface? No paint or foreign material on contact surfaces? Correct material and size used on high strength connections? Evidence of distorted metal or enlarged bolt holes from improper alignment? Evidence of enlarging holes by burning? High strength bolts torqued to specification requirements? Means provided to indicate which joints/bolts have been torqued? periodically calibrated? Torque wrench YES NO N/A

Status of completed high strength connections recorded on drawings and appropriate records? ERECTION Members accurately shimmed, wedged, plumbed and aligned prior to final connection? Shims used are actual shim stock? Entry holes through members are authorized by drawing? Anchor bolts proper size, setting and location? WELDING Welders, weld procedures qualified to requirements of AWS D1.1, Structural Welding Code, Section 5? Qualifications records available maintained? Correct weld wire, size and type, used? Correct weld machine settings used? Weld joints properly prepared, aligned, free from cracks, scale, grease, etc. prior to welding?

D-6

Job Number Field Inspection Checklist Structural Steel Erection

Project

Page of 2/2

CONTRACTOR: ______________________________________________

CONTRACT NO: ___________________

REFERENCES (DRAWING, SPECIFICATION, PROCEDURE): _____________________________________________

ATTRIBUTE 6. 7. 8. 9. 10. 11. E 1. 2. 3. 4. Root opening tolerances not exceeded? Pre-heat and interpass temperature requirements complied with? Repair of defective welds performed to approved weld procedure requirements? Completed welds meet the visual and dimensional requirements? Weld filler material returned to storage at close of shift? Records for weld inspection prepared and retained? PAINTING Temporary braces, clips, etc. removed prior to painting or field touch-up? Weld splatter, slag removed prior to touch up? Damaged paint area properly prepared and touched up? Correct primer used?

YES

NO

N/A

REMARKS: _______________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________

QC SIGNATURE: ____________________________________________________

DATE: _____________________

D-6

Job Number Daily Concrete Inspection Report

Project

Page of 1/1

CONTRACTOR: ______________________________________________________________________________________________ SPECIFIC LOCATION: AREA OR BUILDING ____________________________________________ STATION: ______________________ T/OFFS: _________________________ TO STATION: _______________________ ELEVATION: _______________________ MIX NO: _____________ LIFT NO: ______________

OFFSET: __________________________ TO ELEV: ________________________

CONCRETE TYPE: _________________________

ADDITIVES: ___________________________

TYPE OF DELIVERY: _________________________________________________________________________________________ DELIVERY EQUIPMENT IDENTIFICATION/NUMBER: ____________________________________________________________ PLACEMENT STARTED: PLACEMENT COMPLETED: DATE _______________________ DATE _______________________ TIME ________________ TIME ________________ SHIFT ___________________ SHIFT ___________________

WEATHER CONDITIONS: _____________________________________________________________________________________ TOTAL CONCRETE PLACED: __________________________________________________________________________________ TOTAL CONCRETE WASTED: _______________ REASON: ______________________________________________________

BATCH TICKET NOs: _________________________________________________________________________________________ AVERAGE SLUMP: ______________________ TEMPERATURE: ______________ % AIR CONTENT: _________________

TEST CYLINDERS PREPARED: ________________________________________________________________________________ TRUCK IDENT: ____________________ TOTAL CYLINDERS: _________________ CYL IDENT: ____________________

TYPE CONVEYANCE USED: __________________________________________________________________________________ SURFACE CONDITION PRIOR TO PLACING: ____________________________________________________________________ MAXIMUM FREE FALL OF CONCRETE: _______________________ AMOUNT VIBRATORS: ______________________________ PROPER CONSOLIDATION: _____________________

VIBRATORS IDENT/RPM: ______________________________ LOCATION ______________________________________

DISCHARGE POINTS: NUMBER ___________________________

REINFORCING DISTURBED/REPLACED/REPAIRED: _____________________________________________________________ TYPE FINISH SPECIFIED: _____________________________________________________________________________________ FINISHING STARTED: FINISHING COMPLETED: DATE ______________________ DATE ______________________ TIME ________________ TIME ________________ SHIFT ______________________ SHIFT ______________________

CONDITION OF FINISH: ______________________________________________________________________________________ TYPE OF CURING: ___________________________________________________________________________________________ DELAYS (INDICATE TYPE AND REASON: PERSONNEL, EQUIPMENT OR PLANNING): _______________________________ _____________________________________________________________________________________________________________ _____________________________________________________________________________________________________________ _____________________________________________________________________________________________________________ OBSERVATIONS/REMARKS: __________________________________________________________________________________ _____________________________________________________________________________________________________________ _____________________________________________________________________________________________________________ _____________________________________________________________________________________________________________ CONCRETE INSPECTOR: _______________________________________________________ DATE: _____________________

D-7

Job Number Concrete Placement Checklist

Project

Page of 1/1

CONTRACTOR _______________________________________________________________________________________________ SPECIFIC LOCATION: AREA OR BUILDING __________________________ STATION _________________________ T/OFFS. ________________________ CONCRETE TYPE _______________ LIFT NO. ___________ SHIFT ____________

TO STA. ___________________________ ELEVATION _________________________

OFFSET __________________________ TO ELEV. _________________________ COMPUTED QTY _________

MIX NO. _________

ADDITIVES ________________

LOCATION SKETCH PROVIDE SPECIAL DIRECTIONS, DETAILS, FLOW DIRECTION, ETC.

REPLACEMENT VERIFICATION 1. ELECTRICAL SUPERVISOR: ITEMS TO BE CHECKED CABLES/GROUND WIRE CONDUIT BOXES REV. ________ OTHER __________ DATE

COMPLETE/ACCEPTABLE TO DRAWING _____________

___________________________ SIGNATURE

2. MECH./PIPING SUPERVISOR: ITEMS TO BE CHECKED MECHANICAL INSERTS PIPING SLEEVES MECH. FRAMES REV. ________ OTHER __________ DATE

COMPLETE/ACCEPTABLE TO DRAWING _____________

___________________________ SIGNATURE

3. CIVIL/STRUCT. SUPERVISOR: ITEMS TO BE CHECKED ROCK CROSS SECTIONS TAKEN SCREEDS SET FORMS ALIGNMENT INTERIOR SURFACE BRACING/SHORING RELEASE AGENT ROCK SURFACES PREPARED LINE AND GRADE ESTABLISHED REINFORCING STEEL CORRECT SIZE/GRADE LAPS. ADEQ. SECURED WATER STOPS LOCATION LEAN

CONSTRUCTION JOINTS PREPARED

WIRE TIES/FORM RODS

PLACEMENT/CONSOLIDATION EQUIPMENT AVAILABLE/ADEQUATE SAFETY PRECAUTIONS OBSERVED FINAL CLEANING ACCEPTABLE COMPLETE/ACCEPTABLE TO DRAWING _____________ REV. ________ ___________________________ SIGNATURE QUALITY CONTROL INSPECTION VERIFICATION ___________________________ SIGNATURE __________ DATE __________ DATE ICE, SNOW, WATER REMOVED

OBSERVATIONS/REMARKS ___________________________________________________________________________________ _____________________________________________________________________________________________________________ AUTHORIZATION FOR PLACEMENT ___________________________________________ CONSTRUCTION MANAGER _________________ DATE

D-8

Job Number Field Inspection Checklist Placing, Consolidation, Finishing, Curing and Repair of Concrete CONTRACTOR: ______________________________________________

Project

Page of

CONTRACT NO: ___________________

REFERENCES (DRAWING, SPECIFICATION, PROCEDURE): _____________________________________________ ATTRIBUTE A 1. 2. 3. 4. 5. 6. 7. B 1. 2. 3. PLACING Pre-placement checklist completed? Placement authorized? Concreting surfaces cleaned, moistened when required? Conveying equipment suitable for placement? Conveying equipment clean, properly maintained? Vertical drop limits not exceeded? Horizontal layers not exceeding two-feet in depth? Flow of placement per sketch details? CONSOLIDATION Vibrators previously tested and approved? Systematic pattern used during vibration? Vibrators: a) b) c) d) C 1. 2. 3. 4. D 1. 2. 3. 4. 5. Penetrating previous layer? Not used for horizontal movement of concrete? Withdrawn slowly? Not over vibrating? YES NO N/A

FINISHING Surface top properly screened, when required? Finishing tools used for intended purpose? Desired finish obtained? Even, smooth and level? Joints, edges, corners properly finished? CURING Forms left in place per construction specifications requirements? Curing operations started immediately, adequate? Curing protection periodically checked and maintained? Curing is continuous to specified length of curing process? Traffic and loading over surfaces controlled during curing?

D-9

Job Number Field Inspection Checklist Placing, Consolidation, Finishing, Curing and Repair of Concrete

Project

Page of 2/2

CONTRACTOR: ______________________________________________

CONTRACT NO: ___________________

REFERENCES (DRAWING, SPECIFICATION, PROCEDURE): _____________________________________________

ATTRIBUTE E 1. 2. 3. REPAIR Surfaces inspected? Serious defects documented? Cosmetic repairs made? Structural defects repaired in accordance with approved procedures?

YES

NO

N/A

REMARKS: _______________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________

QC SIGNATURE: ____________________________________________________

DATE: _____________________

D-9

Job Number Field Inspection Checklist Pre-Cast Concrete Piles CONTRACTOR: ______________________________________________

Project

Page of 1/2

CONTRACT NO: ___________________

REFERENCES (DRAWING, SPECIFICATION, PROCEDURE): _____________________________________________ ATTRIBUTE 1. Receipt inspection performed including: a) Dimensions? b) Visual? c) Material test reports for cement, concrete, reinforcing steel, shells, mix test reports, etc.? d) Reinforcing steel for spacing, clearance, size, dowel and tendon extensions? 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. 20. Piles properly handled, stored, and placed? Safety conditions observed? Contractors approved procedures complied with? Test piles required? Driven? Definition of refusal understood, pre-drilling required? Jetting allowed? Proper protection, pre-cautions taken for adjacent structures, utilities? Piles properly placed, sequenced according to plan, and plumb? Splices properly prepared, completed? Piles driven without interruption, driven to required depth to obtain bearing capacity? Piles, shells damaged during driving? Mis-aligned? Over-driven? Tops deformed? Inside properly cleaned, cross section verified, bottom interior cleaned of loose materials? Concrete delivery method approved? (tremie, pump, limited free fall) Concrete fill placed in single, uninterrupted operation? Top of pile properly consolidated? Volume of concrete properly measured and checked? Concrete properly cured, protected from freezing and physical damage? Piles cut-off to specified elevation? Cut-off level? Load test (if required) performed to approved procedures? Load test results evaluated, approved? Contractors Daily Report includes: a) Identification of Contractors Supervisory personnel? b) Pile type, length, splices, location, calculated safe load? c) Penetration under last five hammer blows? YES NO N/A

D-10

Job Number Field Inspection Checklist Pre-Cast and Cast-In-Place Concrete Piles

Project

Page of 2/2

CONTRACTOR: ______________________________________________

CONTRACT NO: ___________________

REFERENCES (DRAWING, SPECIFICATION, PROCEDURE): _____________________________________________

ATTRIBUTE d) Unusual conditions, obstructions, replaced piles, etc.? e) Results of tests, if any? 21. Inspectors records include: a) Make, model of hammer b) Energy source c) Weight of striking parts d) Height of fall of striking parts e) Weight of pile f) Blows per unit of penetration

YES

NO

N/A

REMARKS: _______________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________

QC SIGNATURE: ____________________________________________________

DATE: _____________________

D-10

Job Number Field Inspection Checklist Critical Piping Assembly Inspection Test CONTRACTOR: ______________________________________________

Project

Page of 1/2

CONTRACT NO: ___________________

REFERENCES (DRAWING, SPECIFICATION, PROCEDURE): _____________________________________________ ATTRIBUTE A 1. 2. 3. 4. B 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. C 1. STORAGE Assemblies, fittings, etc. stored/protected per procedure requirements? Pipe caps and plugs taped in place? Assemblies properly shored to prevent damage/deterioration? Material segregated, when required? IN-PROCESS Welders qualified, certified? Qualification records current? Welders using qualified procedure? Weld wire control adequate? Correct type and size? Welding machine settings within procedure requirements? Welders applying individual identification on welded joints? Unused weld wire returned to proper storage? Weld preps per ANSI B31.1 and procedure requirements? Weld root opening within tolerance? Weld joint alignment within tolerance? Pre-heat applied properly? Visual and dimensional inspection performed? Heat treatment performed to procedure requirements? Weld adequately prepared for nondestructive examination? NDE performed, evaluated, documented to procedure requirements? NDE operator qualified/certified? Qualification records current? Defective welds adequately repaired, retested and records updated? Open pipe ends protected during and after installation? Valves, valve internals protected during welding? FINAL Bolted flanges: a) Face to face opening consistent? b) Gasket properly compressed? YES NO N/A

D-11

Job Number Field Inspection Checklist Critical Piping Assembly Inspection Test

Project

Page of 2/2

CONTRACTOR: ______________________________________________

CONTRACT NO: ___________________

REFERENCES (DRAWING, SPECIFICATION, PROCEDURE): _____________________________________________

ATTRIBUTE c) Bolts/studs correct material? d) Bolts/studs completely engaging nuts? 2. 3. 4. 5. 6. 7. Completed weld records properly filed, maintained? Authorized Inspector notified of ASME designated hold points? System properly prepared and supported for hydrostatic testing? ASME Code Data Report completed? Approved by authorized inspector? Temporary attachments removed after hydrostatic testing? System restored to normal? Completed system cleaned per specification and procedure requirements?

YES

NO

N/A

REMARKS: _______________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________

QC SIGNATURE: ____________________________________________________

DATE: _____________________

D-11

Job Number Electrical Inspection / Test Sheet Ground Rod Earth Resistance Test CONTRACTOR: ______________________________________________

Project

Page of 1/1

CONTRACT NO: ___________________

REFERENCES (DRAWING, SPECIFICATION, PROCEDURE): _____________________________________________ GROUND ROD EARTH RESISTANCE TEST PROCEDURE (FALL OF POTENTIAL METHOD) 1. 2. 3. 4. After ground rods are installed to the correct depth measure the earth resistance of each individual rod. Install and connect reference electrodes and test equipment as per manufacturers test procedure. Measure earth resistance and record below. Maximum acceptable earth resistance as per Specification Section 19690 is 25 ohms.

GROUND ROD EARTH RESISTANCE TEST RESULTS


SERVICE: _______________________________________________ EQUIPMENT NO: _________________________________________ CONNECTED: ____________________________________________ TEST EQUIPMENT USED: MAKER: _________________________________________________ MODEL NO: ______________________________________________ RANGE: __________________________________________________ SERIAL NO: ______________________________________________ TEST RESULTS: AMBIENT TEMP: ________________________________ HUMIDITY % RH: ________________________________ WEATHER: _____________________________________ LOCATION: _____________________________________ RFI NO: ________________________________________ DATE: _____________________________________

TEST ITEMS

EARTH RESISTANCE

REMARKS

Maximum Earth Resistance for Ground Rod = 25 ohms

QC SIGNATURE: ____________________________________________________

DATE: _____________________

D-12

Job Number Electrical Inspection / Test Sheet Ground Grid Earth Resistance Test CONTRACTOR: ______________________________________________

Project

Page of 1/1

CONTRACT NO: ___________________

REFERENCES (DRAWING, SPECIFICATION, PROCEDURE): _____________________________________________ GROUND GRID EARTH RESISTANCE TEST PROCEDURE (FALL OF POTENTIAL METHOD) 1. 2. 3. 4. After ground rods and ground conductors installation is completed and interconnected, measure the earth resistances of the grounding grid. Install and connect reference electrodes and test equipment as per manufacturers test procedure. Measure earth resistance of ground grid and record below. Maximum acceptable earth resistance as per Specification Section 16960 is 1 ohm.

GROUNDING GRID EARTH RESISTANCE TEST RESULTS


SYSTEM: ________________________________________________ EQUIPMENT: _____________________________________________ CONNECTED: ____________________________________________ TEST EQUIPMENT USED: MAKER: _________________________________________________ MODEL NO: ______________________________________________ RANGE: __________________________________________________ SERIAL NO: ______________________________________________ TEST RESULTS: AMBIENT TEMP: ________________________________ HUMIDITY % RH: ________________________________ WEATHER: _____________________________________ LOCATION: _____________________________________ RFI NO: ________________________________________ DATE: _____________________________________

TEST ITEMS

EARTH RESISTANCE

REMARKS

Maximum Earth Resistance for Interconnected Grounding System = 1 ohms

QC SIGNATURE: ____________________________________________________

DATE: _____________________

D-13

Job Number Electrical Inspection / Test Sheet Light Installation

Project

Page of 1/1

CONTRACTOR: ______________________________________________

CONTRACT NO: ___________________

REFERENCES (DRAWING, SPECIFICATION, PROCEDURE): _____________________________________________

ATTRIBUTE 1. 2. 3. 4. 5. 6. 7. 8. Installed lighting fixtures comply with fixture schedule drawing? Lighting fixture location is correct as shown on the design approved shop drawing? Lighting fixture and fittings are installed correctly and tightly as specified in the specification? Lighting fixture fitted with fuse holder and enclosure cover? Cable wire color code is correct and identification tags installed at panel board? Continuity and grounding test completed? All wire entries are sealed with a non-setting sealant? Lighting photo cell control is correctly installed?

YES

NO

N/A

REMARKS: _______________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________

QC SIGNATURE: ____________________________________________________

DATE: _____________________

D-14

Job Number Electrical Inspection / Test Sheet Combination Starter, PB and Selector Switches Control System Components

Project

Page of 1/1

CONTRACTOR: ______________________________________________

CONTRACT NO: ___________________

REFERENCES (DRAWING, SPECIFICATION, PROCEDURE): _____________________________________________

ATTRIBUTE 1. 2. 3. 4. 5. 6. Equipment/components installed per approved drawings and material submittals? Equipment/components installed at correct location and elevation? Cable/wire color code correct and tagging identification installed? Control wiring connected per approved drawing? Auto-off-manual selector operation is correct? Panel/door grounding checked?

YES

NO

N/A

REMARKS: _______________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________

QC SIGNATURE: ____________________________________________________

DATE: _____________________

D-15

Job Number Electrical Inspection / Test Sheet Continuity Test of all Fixture Bodies to Ground CONTRACTOR: ______________________________________________

Project

Page of 1/1

CONTRACT NO: ___________________

REFERENCES (DRAWING, SPECIFICATION, PROCEDURE): _____________________________________________


INSTRUMENT USED: __________________________________________ LOCATION: __________________________________

CIRCUIT NO.

FIXTURE NO.

CABLE ROUTE

TO

FROM

FIXTURE BODY TO GROUND

REMARKS

REMARKS: _______________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________

QC SIGNATURE: ____________________________________________________

DATE: _____________________

D-16

Job Number Electrical Inspection / Test Sheet Cable Test Procedures CONTRACTOR: ______________________________________________

Project

Page of 1/2

CONTRACT NO: ___________________

REFERENCES (DRAWING, SPECIFICATION, PROCEDURE): _____________________________________________ INSULATION RESISTANCE WITH ABSORPTION INDEX TEST PROCEDURE 1. 2. 3. 4. 5. 6. The test equipment shall be connected properly. The voltage of 500V held for a period of one (1) minute and results recorded below. Each conductor is to be measured to ground and to the three other conductors. The test shall be performed after cable installation and terminations are completed and witnessed by the QA Engineer. The absorption index is calculated as: Absorption Index = 60 sec IR reading / 30 sec IR reading The insulation resistance shall be compared for similar results of the other conductors and feeders.

INSULATION RESISTANCE WITH ABSORPTION INDEX TEST RESULTS


FEEDER NO: _____________________________________________ CORE L1 TO GND L2 TO GND L3 TO GND N TO GND L1 TO L2, L3, N L2 TO L1, L3, N L3 TO L1, L2, N N TO L1, L2, L3 LENGTH (KM) TIME (SEC) 30 60 30 60 30 60 30 60 30 60 30 60 30 60 30 60 VOLTAGE (KV) 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 HUMIDITY: _____________________________________ MANUFACTURER: _______________________________ CABLE SIZE: ____________________________________ ABSORPTION INDEX R1 (G-OHM) R1 (G-OHM/KM)

AMBIENT TEMP: _________________________________________ TEST INSTRUMENT: ______________________________________

REMARKS: _______________________________________________________________________________________ __________________________________________________________________________________________________

D-17

Job Number Electrical Inspection / Test Sheet Cable Test Procedures CONTRACTOR: ______________________________________________

Project

Page of 2/2

CONTRACT NO: ___________________

REFERENCES (DRAWING, SPECIFICATION, PROCEDURE): _____________________________________________ CONDUCTOR PHASING TEST PROCEDURE 1. 2. 3. 4. 5. 6. Conductors are identified color mode. Phasing checks are to be performed when the cable installation is completed and before conductors are terminated. Conductors are to be phase checked individually. Confirm the phasing of each conductor with a continuity tester (ohmmeter). Conductors not under test must be clear of ground. Test results will be recorded below.

CONDUCTOR PHASING TEST RESULTS


FEEDER NO: ______________________ CABLE SIZE: _____________________ CABLE LENGTH: _____________________ PHASE CHECKING TO BE CARRIED OUT BEFORE STARTING ANY OTHER TEST:

TEST 1

PHASE L1

CONNECTION L1 EARTHED L2 UNEARTHED L3 UNEARTHED N UNEARTHED L1 UNEARTHED L2 EARTHED L3 UNEARTHED N UNEARTHED L1 UNEARTHED L2 UNEARTHED L3 EARTHED N UNEARTHED L1 UNEARTHED L2 UNEARTHED L3 UNEARTHED N EARTHED

RESULT (OK/NOT OK)

L2

L3

TEST INSTRUMENT: ______________________________________

MANUFACTURER: _______________________________

REMARKS: _______________________________________________________________________________________ __________________________________________________________________________________________________ QC SIGNATURE: ____________________________________________________ DATE: _____________________

D-17

Job Number Electrical Inspection / Test Sheet Conduit and Junction / Outlet Boxes Installation

Project

Page of 1/1

CONTRACTOR: ______________________________________________

CONTRACT NO: ___________________

REFERENCES (DRAWING, SPECIFICATION, PROCEDURE): _____________________________________________

ATTRIBUTE A 1. 2. B 1. 2. 3. 4. 5. C 1. 2. 3. 4. D 1. 2. 3. 4. SUPPORTS Conduit adequately supported? Support alignment checked? CONDUITS Installed conduits in accordance with shop drawing in a workman like manner? Bends free of damage? Oxide inhibitor used on threaded connection? Conduit & fittings correct size & type? Identification of conduits installed? JUNCTION / OUTLET BOXES Boxes installed are the correct size & type? Boxes are properly supported and installed at correct elevation? Proper identification on box? Pull/splicing box installed at accessible location? GROUNDING Metallic conduit solidly grounded? Conduit grounding bushing installed? Pull boxes and junction conduit grounded? Bonding wire grounding connections completed?

YES

NO

N/A

REMARKS: _______________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________

QC SIGNATURE: ____________________________________________________

DATE: _____________________

D-18

Job Number Electrical Inspection / Test Sheet Cable & Cable Accessories / Panelboard / Wiring Devices

Project

Page of 1/1

CONTRACTOR: ______________________________________________

CONTRACT NO: ___________________

REFERENCES (DRAWING, SPECIFICATION, PROCEDURE): _____________________________________________

ATTRIBUTE 1. 2. 3. 4. 5. 6. 7. 8. 9. Panelboard installed at proper elevation and circuit breaker accessories provided are per approved drawings and submittals? Installed wiring devices and plates with approved material submittals? Cable wire correct size and type? Low voltage power cable in outlet box and panelboard properly connected? Cable size color code is correct and identification tags are installed at panelboard/outlet boxes? Installed terminal lugs are correct size and application? All conduit and outlet boxes and panelboard properly grounded? Continuity and grounding test complete? Circuit index directory installed inside panelboard?

YES

NO

N/A

REMARKS: _______________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________

QC SIGNATURE: ____________________________________________________

DATE: _____________________

D-19

Job Number Electrical Inspection / Test Sheet Electrical Service and Distribution System CONTRACTOR: ______________________________________________

Project

Page of 1/1

CONTRACT NO: ___________________

REFERENCES (DRAWING, SPECIFICATION, PROCEDURE): _____________________________________________ MOLDED CASE CIRCUIT BREAKER RECORD
PANEL BOARD NO: _____________________________________ LOCATION: ________________________________________ CABLE NO: ____________________________________________ CABLE SIZE: _______________________________________ 1.0 CIRCUIT BREAKER DATA: 1.1 MANUFACTURER __________________________________________ 1.2 1.3 1.4 2.0 TYPE _____________________________________________________ AMPERE THERMAL STRIP SETTING _________________________________ AMPERE INSTANTANEOUS MAGNETIC TRIP RANGE ___________________

CONNECTED LOAD DATA: 2.1 2.2 2.3 2.4 2.5 2.6 MANUFACTURER ___________________________________________ NUMBER OF MOTOR / TRANSFORMERS _______________________ TOTAL KVA / KW / HP _______________________________________ VOLTAGE __________________________________________________ VOLTAGE RATED FREQUENCY ________________________________________ HZ FULL LOAD CURRENT (FLC) _________________________________ AMPERE

3.0

TRIP SETTINGS: 3.1 THERMAL ( 3.2 MAGNETIC ( ( ( ) FIXED ) VARIABLE ) % FLC ) AMPERES _______________________________

REMARKS: _______________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________

QC SIGNATURE: ____________________________________________________

DATE: _____________________

D-20

Job Number Electrical Inspection / Test Sheet Molded Case Circuit Breaker Test Record CONTRACTOR: ______________________________________________

Project

Page of 1/1

CONTRACT NO: ___________________

REFERENCES (DRAWING, SPECIFICATION, PROCEDURE): _____________________________________________ EQUIPMENT IDENTIFICATION


UNIT NO: CIRCUIT NO: LOAD RATING: EQUIPMENT NO: EQUIPMENT NAME: FULL LOAD AMPS:

EQUIPMENT NAMEPLATE DATA


MANUFACTURER NAME: FRAME TYPE: FRAME SIZE: THERMAL TRIP RATING: MAGNETIC TRIP RATING:

TEST DATA
SPECIFIED MAGNETIC TRIP SETTING: PHASE A TEST RESULTS CURRENT TRIP TIME STD CURRENT TRIP TIME MIN. TRIP CURRENT TRIP TIME AS FOUND AS LEFT MAGNETIC TRIP RATING: PHASE B AS FOUND AS LEFT PHASE C AS FOUND AS LEFT

LTD

MEGGER TO FRAME MEGGER LINE TO LOAD CONTACT RESISTANCE

ACCESSORIES

Short Trip UV Release Reverse Trip Ground Limiter Current Current

Auxiliary Switch Mechanical Interlock Electrical Interlock Electrical Lock Out

Mechanical Lock Out Key Lock Out Bell Alarm Current Limiting Fuses

Trip/Close Indicator Trip/Close Lights Motor Operated Mech Field Discharge Contact

REMARKS: _______________________________________________________________________________________ __________________________________________________________________________________________________ QC SIGNATURE: ____________________________________________________ DATE: _____________________

D-21

Job Number Electrical Inspection / Test Sheet Cable Test Record CONTRACTOR: ______________________________________________

Project

Page of 1/1

CONTRACT NO: ___________________

REFERENCES (DRAWING, SPECIFICATION, PROCEDURE): _____________________________________________ EQUIPMENT IDENTIFICATION


UNIT NO: CIRCUIT NO: EQUIPMENT NO: EQUIPMENT NAME:

CABLE DATA
MANUFACTURER NAME: YEAR MANUFACTURED: SIZE: TYPE OF INSULATION: NO. OF COND.: TRADE NAME: YEAR INSTALLED: INSUL. CLASS KV: VARNISH/CAMBRIC

RUBBER(LIKE)

NO

PAPER

OTHER SPECIFY

TYPE OF SHEATH OR JACKET: SHIELDED YES

EST. LENGTH OF RUN:

TYPE OF DUCT: MOISTURE CONDITIONS IN DUCT: PER SHEATH PER PHASE

NUMBER OF CABLES PER DUCT: NUMBER OF CONDUCTORS:

TEST DATA
TEST EQUIPMENT MANUFACTURER AND TYPE: TEST VOLTAGE: WEATHER CONDITIONS: TEST TYPE: KV A.C. KV D.C. TIME: MIN.

PH

BEFORE INSTALL.

PH

AFTER INSTALL.

PH

ROUTINE

CURRENT READINGS (MICRO AMPS D.C. OR AMPS A.C.)


MINUTES PH PH PH

1/2 1 2 3 5 10
PHASE FAILURES KV CURRENT TIME

REMARKS: _______________________________________________________________________________________ QC SIGNATURE: ____________________________________________________ DATE: _____________________

D-22

Job Number Electrical Inspection / Test Sheet Motor Test Record CONTRACTOR: ______________________________________________

Project

Page of 1/1

CONTRACT NO: ___________________

REFERENCES (DRAWING, SPECIFICATION, PROCEDURE): _____________________________________________ EQUIPMENT IDENTIFICATION


UNIT NO: CIRCUIT NO: EQUIPMENT NO: EQUIPMENT NAME:

EQUIPMENT NAMEPLATE DATA


MANUFACTURER NAME: TYPE: S.F.: INNER BEARING NO.: H.P.: CODE: R.P.M. SERIAL NO.: DUTY: VOLTS: OUTER BEARING NO.: FRAME: MODEL: AMPS:

TEST DATA
MEGGER TEST EQUIPMENT: TEST VOLTAGE: WEATHER: TEST TYPE: HIGH POTENTIAL TEST EQUIPMENT: TEST VOLTAGE: WEATHER: WINDING RESISTANCE TEST EQUIPMENT: WINDING TEMP.: WEATHER:

BEFORE INSTALL. AFTER INSTALL. ROUTINE

TEST TYPE:

BEFORE INSTALL. AFTER INSTALL. ROUTINE

TEST TYPE:

BEFORE INSTALL. AFTER INSTALL. ROUTINE

WITH CABLES CONNECTED WITHOUT CONNECTED TIME (MIN) 1/2 1 2 3 5 10 CABLES MEGOHMS


15 30 45 60 90 120

WITH CABLES CONNECTED WITHOUT CONNECTED CABLES


A-B BC CA

WITH CABLES CONNECTED WITHOUT CONNECTED CABLES

TIME (SEC)

CURRENT

RESISTANCE (OHMS)

POLARITY INDEX 10/1

FIELD

REMARKS: _______________________________________________________________________________________ __________________________________________________________________________________________________ QC SIGNATURE: ____________________________________________________ DATE: _____________________

D-23

Job Number Inspection Notification Form

Project

Page of 1/1

CONTRACTOR: ___________________________________________________ DATE: _______________________

TYPE OF INSPECTION REQUESTED: ________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________

DATE AND TIME OF INSPECTION REQUESTED: _____________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________

LOCATION OF INSPECTION REQUESTED: ___________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________

OTHER COMMENTS: ______________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________ __________________________________________________________________________________________________

CONTRACTOR SIGNATURE: ___________________________________________

DATE: ___________________

D-24

Job Number Non-Conformance Report


CONTRACTOR SPECIFICATION/DRAWING NO. ITEM REPORT NO.

Project
DATE

Page of 1/1

PART I To be completed by the inspector who detects a deviation. DESCRIPTION OF NON-CONFORMANCE: __________________________________________________________________________________________________________ __________________________________________________________________________________________________________ __________________________________________________________________________________________________________ __________________________________________________________________________________________________________ RECOMMENDED DISPOSITION: USE AS IS REWORK REPAIR SCRAP ___________________________________________________________________________________________________________________ ___________________________________________________________________________________________________________________ ___________________________________________________________________________________________________________________ ___________________________________________________________________________________________________________________ SIGNED ______________________________________________________________________ DATE ___________________________ PARSONS FIELD ENGINEER PART I I To be completed by the contractor who proposed the corrective action. DESCRIPTION OF PROPOSED CORRECTIVE ACTION: ___________________________________________________________________________________________________________________ ___________________________________________________________________________________________________________________ ___________________________________________________________________________________________________________________ ___________________________________________________________________________________________________________________ ___________________________________________________________________________________________________________________ ___________________________________________________________________________________________________________________ ___________________________________________________________________________________________________________________ ___________________________________________________________________________________________________________________ ___________________________________________________________________________________________________________________ SIGNED ______________________________________________________________________ DATE ____________________________ CONSTRUCTION ENGINEER PART III To be completed by the Engineer of Record. RECOMMENDATION AND REMARKS: __________________________________________________________________________________________________________ __________________________________________________________________________________________________________ __________________________________________________________________________________________________________ __________________________________________________________________________________________________________ Proposed corrective action status: Approved Rejected ___________________________________________________________________________________________________________________ ___________________________________________________________________________________________________________________ ___________________________________________________________________________________________________________________ ___________________________________________________________________________________________________________________ SIGNED ______________________________________________________________________ DATE ____________________________ ENGINEER OF RECORD PART IV QUALITY CONTROL DISPOSITION (To be determined by QC System Manager (Construction Engineer) DECISION AND DISPOSITION INSTRUCTIONS: USE AS IS REWORK REPAIR SCRAP __________________________________________________________________________________________________________________ __________________________________________________________________________________________________________________ __________________________________________________________________________________________________________________ SIGNED _____________________________________________________________________ DATE ____________________________ PARSONS FIELD ENGINEER SIGNED _____________________________________________________________________ DATE ____________________________ PARSONS CONSTRUCTION MANAGER PART V ENGINEERING DISPOSITION METHOD OF APPROVALS: TELEPHONE MEMORANDUM TELEX SPEC. CHANGE DRAWING CHANGE CONVEYED BY PROJECT MANAGER ______________________________________________ DATE _____________________________________ PROJECT MANAGER ______________________________________________ DATE _____________________________________ PART VI DISPOSITION VERIFICATION CORRECTIVE ACTION WAS ACCOMPLISHED ON _____________________________ SIGNED ______________________________________________________________________ DATE ____________________________________ PARSONS FIELD ENGINEER SIGNED ______________________________________________________________________ DATE ____________________________________ PARSONS CONSTRUCTION MANAGER

D-25

PARSONS Non-Conformance Report Log CONTRACTOR PROPOSED CORRECTIVE ACTION BY CONTRACTOR

Job Number

Project

Page of

NCR No.

CONDITION DESCRIPTION

ORIGINATOR

DATE RECORDED

DATE TO CONTRACTOR

PROPOSED APPROVED BY ENGINEER

DISPOSITION DATE

DISPOSITION VERIFICATION BY

D-26

Construction QC/QA Plan


Job Number Contractor Non-conformance Letter (Sample) Project Page of 1/1

Attention: ___________________________________

Subject: Non-conformance Report No. _____________

Gentlemen:

The attached Non-conformance Report (NCR) details discrepancies on your contract.

Please review and take appropriate action to remedy this situation, also changing any procedures, methods and/or personal necessary to preclude similar problems in the future. Your attention is specifically drawn to Item 10, disposition date.

We are available to discuss the attached with you.

Very truly yours, PARSONS

_________________________________ Construction Manager

cc:

Program Manager Project Manager Construction Manager Quality Assurance Department Contract File

D-27

You might also like