Schedulingandsequencing-140424065526-Phpapp02 1
Schedulingandsequencing-140424065526-Phpapp02 1
Schedulingandsequencing-140424065526-Phpapp02 1
G A -
LIN
U
D CI NG
E
H EN
SC U
E Q
S
Presented by
VARUN BABU
Scheduling
02/07/23 bvarun.weebly.com 2
Introduction
Operations scheduling is critical to the success of an organization;
however, it can be a very complicated task. Effective schedules are
needed to meet promised customer delivery dates or inventory targets.
02/07/23 bvarun.weebly.com 3
Work Centre
02/07/23 bvarun.weebly.com 4
Performance Measures
From the manager’s perspective, identifying the performance
measures to be used in selecting a schedule is important. If the
overall goals of the organization are to be achieved, the schedules
should reflect managerially acceptable performance measures. The
following list describes the most common performance measures
used in operations scheduling.
Job Flow Time: The amount of shop time for the job is called job
flow time. It is the sum of the moving time between operations,
waiting time for machines or work orders, process time (including
setups), and delays resulting from machine breakdowns,
component unavailability, and the like.
02/07/23 bvarun.weebly.com 5
Performance Measures
Makespan: The total amount of time required to complete a group
of jobs is called makespan.
Past Due: The measure past due can be expressed as the amount of
time by which a job missed its due date (also referred to as
tardiness) or as the percentage of total jobs processed over some
period of time that missed their due dates.
02/07/23 bvarun.weebly.com 6
Performance Measures
Total Inventory: The sum of scheduled receipts and on-hand inventories
is
the total inventory.
02/07/23 bvarun.weebly.com 7
Manufacturing Process
02/07/23 bvarun.weebly.com 8
Objectives of Operations
Scheduling
• Making efficient use of the labour.
02/07/23 bvarun.weebly.com 9
Objectives of Operations
Scheduling
• Maximizing the delivery performance i.e. meeting the
delivery dates.
02/07/23 bvarun.weebly.com 10
Functions of Operations Scheduling
02/07/23 bvarun.weebly.com 11
Functions of Operations Scheduling
• Specifying the start and the end time for each job (actively
scheduled).
02/07/23 bvarun.weebly.com 12
Types of Scheduling
02/07/23 bvarun.weebly.com 13
Types of Scheduling
• Activities are scheduled from the date or the planned receipt date.
• Time of the start of the last task is considered as the time for the start
of the previous activity.
02/07/23 bvarun.weebly.com 14
Shop Floor Control (SFC)
• Sequencing - release work orders to shop and issue dispatch lists for
individual machines
02/07/23 bvarun.weebly.com 15
Loading
02/07/23 bvarun.weebly.com 16
Sequencing
02/07/23 bvarun.weebly.com 17
Sequencing Jobs
• Operations schedules are short-term plans
designed to implement the sales and operations
plan
• An operation with divergent flows is often called a
job shop
– Low-to medium-volume production
– Utilizes job or batch processes
– The front office would be the equivalent for a service
provider
– Difficult to schedule because of the variability in job
routings and the continual introduction of new jobs to
be processed
02/07/23 bvarun.weebly.com 18
Sequencing Jobs
02/07/23 bvarun.weebly.com 19
Job Shop Sequencing
Shipping Department
Raw Materials
Legend:
Batch of parts
Workstation
Figure J.1 – Diagram of a Manufacturing Job Shop Process
bvarun.weebly.com
02/07/23 20
Priority Sequencing Rules
• First-come, first-served (FCFS)
• Earliest due date (EDD)
• Critical ratio (CR)
(Due date) – (Today’s date)
CR = Total shop time remaining
bvarun.weebly.com
02/07/23 21
Priority Sequencing Rules
• Shortest processing time (SPT)
• Slack per remaining operations (S/RO)
Due Today’s Total shop
date – date – time remaining
S/RO =
Number of operations remaining
bvarun.weebly.com
02/07/23 22
Sequencing One Workstation
• Single-dimension rules
• A job’s priority assignment based only on
information waiting for processing at the
individual workstation (e.g., FCFS, EDD, and SPT)
bvarun.weebly.com
02/07/23 23
Multiple-Dimension Rules
• The priority rules CR and S/RO incorporate information
about the remaining workstations
S/RO is better than EDD with respect to the percentage of jobs past
due but usually worse than SPT and EDD with respect to average
job flow times
CR results in longer job flow times than SPT, but CR also results in
less variance in the distribution of past due hours
bvarun.weebly.com
02/07/23 24
Multiple Workstations
bvarun.weebly.com
02/07/23 25
Scheduling a Two-Station Flow Shop
bvarun.weebly.com
02/07/23 26
Scheduling Jobs for
Multiple Workstations
• Priority sequencing rules can be used to schedule more than one
operation. Each operation is treated independently.
• Identifying the best priority rule to use at a particular operation
in a process is a complex problem because the output from one
process becomes the input for another.
• Computer simulation models are effective tools to determine
which priority rules work best in a given situation.
• When a workstation becomes idle, the priority rule is applied to
the jobs waiting for that operation, and the job with the highest
priority is selected.
• When that operation is finished, the job is moved to the next
operation in its routing, where it waits until it again has the
highest priority.
02/07/23 bvarun.weebly.com 27
Scheduling Problems
02/07/23 bvarun.weebly.com 28
One machine, many jobs
02/07/23 bvarun.weebly.com 29
Two machines, many jobs
02/07/23 bvarun.weebly.com 30
Johnson’s Rule
• Minimizes makespan when scheduling a group of jobs on
two workstations
Step 1: Scan the processing time at each workstation and
find the shortest processing time among the jobs not yet
scheduled. If two or more jobs are tied, choose one job
arbitrarily.
Step 2: If the shortest processing time is on workstation 1,
schedule the corresponding job as early as possible. If the
shortest processing time is on workstation 2, schedule the
corresponding job as late as possible.
Step 3: Eliminate the last job scheduled from further
consideration. Repeat steps 1 and 2 until all jobs have been
scheduled.
bvarun.weebly.com
02/07/23 31
Gantt Progress Chart
Start activity
Scheduled activity time
Finish activity Current
date Actual progress
Nonproductive time
Job 4/17 4/18 4/19 4/20 4/21 4/22 4/23 4/24 4/25 4/26
Ford
Plymouth
Pontiac
02/07/23 bvarun.weebly.com 32
Gantt Workstation Chart
02/07/23 bvarun.weebly.com 33
Thank You
02/07/23 bvarun.weebly.com 34