TAKING-OFF QUANTITIES
FOR BUILDING & CIVIL
FACULTY OF CIVIL ENGINEERING
ENGINEERING
UITMCJKPG WORKS
3.1.1 Building works:
Concrete, reinforcement
and formworks for:
- Foundation
- Stump/ Column
- Beam
- Slab
COURSE & PROGRAMME
OUTCOMES
CO1:
Evaluate bill of quantities for major elements of building and civil
engineering works in accordance with Malaysian Civil
Engineering Standard Methods of Measurement (myCESMM)
PO2:
Identify and analyse well-defined engineering problems reaching
substantiated conclusions using codified methods of analysis
specific to their field of activity
W6
LESSON OUTCOMES
At the end of the lesson, students should be able to:
2 ND
STAGE : ABSTRACTING
SHEET
W5
2 ND
STAGE : ABSTRACTING
W5
REINFORCEMENT
Concrete is strong in compression, but week in tension.
Therefore reinforcements are used to strengthen the concrete in tension.
The components of this category are:
REINFORCEMENT
Reinforcement For Footing
Reinforcement for Footing 2000x2000x400
7Y16
Length of one bar
Length= 1.500
Less(-) 2 cover
2/0.03
=0.060
1.440
Add (+) 2 bends
2/5.5d @ 2/5.5/0.016
=0.176
1.616 1.62
Reinforcement For Stump
Reinforcement for stump 250x250 of footing 2000x2000x400
Beam
300mm
Length of one reinforcement bar
1.850
Add (+) existing grd. level to grd beam
0.050
1.900
Less (-) cover
0.030
4Y16 1.870
Less (-) 2 footing rebar (both ways)
2/16
2 nos of =0.032
stump 1.838(i)
Add bend 5.5d
5.5/0.016
4nos of bar =0.088
for stump
1.926
Add (+) lap 40d
40/0.016
=0.640
2.566
2.57
2/4/ 2.57 20.56 20.56m of Y16 ø steel bar
Mild steel link for stump 250x250
Length of one link R6- 200
Length
=0.250
Less(-) 2cover
2/0.025 250
=0.050
0.200
250
4/0.200 =
0.800
Add(+) hook 24d
24/ 0.006
=0.144
0.944
Distance that require link
(Length of steel bar from (i)) =1.838
Less (-) Ground beam
0.300
1.538
No. of links
1.538/0.200 +1
=8.68
Reinforcement for stump 200x200
Length of one bar
Length = 1.850
Less(-) grd level to grd beam
0.250
1.600
Add (+) depth of grd beam
0.300
1.900
Less(-) cover
0.030
1.870
Less(-) 2 footing rebar (both way)
2/0.016 =0.032
1.838 (i)
Add (+) bend 5.5d (4Y12)
5.5/0.012 = 0.066
1.904
Add (+) Lap 40d
40/0.012 = 0.480
2.384 2.38
4/4/ 2.38 38.14 38.14m of Y12 ø steel bar
Mild steel link for stump 200x200
Length of one link
0.200
0.050 - cover 2/0.025
0.150
4/0.150 = 0.600
0.144 + hook 24d
0.744 0.74
Distance that require link
1.838 (Length of steel bar from (i))
0.300 - Ground beam
1.538
No. of links = 1.538/0.250 +1
= 7.152, say 8
4/8/ 0.74 23.81 MR of M6 ø link
BILL OF QUANTITIES : Column And Foundation (Footing)
Item
Description Quantity Unit Rate RM
No.
EXCAVATION WORK
1 Excavation of top soil, 150 mm 17.00 cu. m
2 Excavation of trench depth not exceeding 1.5 m 25.50 cu. m
3 Excavation of trench depth exceeding 1.5 m but not
exceeding 3.0 m 4.25 cu. m
CONCRETE WORK
4 Concrete grade 1:3:6 - 20 mm aggregate for footings 6.80 cu. m
5 Concrete grade 1:2:4 - 20 mm aggregate for stumps 0.34 cu. m
FORMWORK
6 Rough surface formwork for footings 16.00 Sq. m
7 Rough surface formwork for side of stump 6.24 Sq. m
REINFORCEMENT
8 Y16, 59.36+64.80+20.56=144.72m,
(3.14x0.0082x144.72x7850) 228.30 Kg.
9 Y12, 38.14m,
(3.14x0.006 x38.14x7850)
2 33.84 Kg.
10 R 6, 17.00+23.81= 40.81m, (3.14x0.0032x40.81x7850) 9.05 Kg.
(Density of steel bar, assume = 7850kg/m3)
Total Bill RM
EXERCISES :
COLUMN