PM 2
PM 2
PM 2
Scope changes
• four types
Project
Organi
sation
Qua-
Time
lity
Cost
Turner, p.8
Aspects of a project
Project
Scope
Viability Performance
Cost Qua-
lity
Competi-
Effort
tiveness
Time
What kind of supporting technologies
are available?
1. Paper specifications
2. Work breakdown structures
3. Configuration (specification) management
4. Bar charts (planning)
5. Network planning techniques
6. Task - responsibility matrices
7. Performance indicators and measurements
8. Matrix organisation
9. Cost control
10. Contract administration
11. Quality control
12. Human Resource Management
13. Etc. etc. etc.
Will this solve all the problems mentioned?
Work Breakdown Structure
1 2 3 4 Use of
Product
Introduction
• The key to a successful project is in planning
saving time
unclear objectives
bad planning
new technology
insufficient staff
Activity list
Basic resource managing
Network diagram
Duration & resource estimate
Basic critical path calculations
Time-cost adjustment
Time-resource adjustment
Schedule plan for implementation
Is current plan ok
update Field reports
Project complete
What to do?
Communications plan
Who needs to be informed about the project
Scope changes
Atmospheric events
RISK IDENTIFICATION
RISK PRIORITIZATION
RISK
MANAGEMENT RISK MANAGEMENT
PLANNING
RISK MONITORING
Possible risks (software development)
Risk Risk
Risk analysis Risk planning
identification monitoring
Risk avoidance
List of potential Prioritised risk Risk
and contingency
risks list assessment
plans
Effective plans
Include
• Business perspective – financial, technical
commercial
• Deliverable components and the tasks required
• Clearly defined organizational responsibilities
• Product requirements and deliverables
• Risk quantified in $ or hours and risk management
strategy proposed
• Sensible task durations
• Sensible task size
• Defined acceptance criteria.../
Process of project time management
• Activity definition: Identifying the specific activities that the
project team members and stakeholders must perform to
produce the project deliverables.
• Activity sequencing: Identifying and documenting the
relationships between project activities.
• Activity resource estimating: Estimating how many
resources a project team should use to perform project
activities.
• Activity duration estimating: Estimating the number of work
periods that are needed to complete individual activities.
• Schedule development: Analyzing activity sequences,
activity resource estimates, and activity duration estimates to
create the project schedule.
• Schedule control: Controlling and managing changes to the
project schedule.
Activity definitions
• Activity
– Represented by an arrow
• Dummy Activity
3
Lay Dummy
foundatio
n
2 0 Build Finish
house work
3 1
1 2 4 3
6 1
7
Design Order
house and and 1 1
obtain receive Select Select
financing material paint carpet
s
5
Activity on a node
2 4
Finish work
2 3
7
Star 1 1
t 3
Design 6
house and 3
obtain 1 5 1
financing
1 Select carpet
Order and
receive Select paint
materials
Arrow diagram method (ADM)
B
A A must finish before either B or C
can start
C
A
C both A and B must finish before C
B can start
A C both A and C must finish before
B either of B or D can start
D
A B
A must finish before B can start
Dum both A and C must finish before D
my can start….
C
D
Planning techniques
GANTT CHART
•Symbols include:
• The critical path is the longest path through the network diagram
and has the least amount of slack or float.
shows relationships.
improves communications.
resource allocation.
• Generate/ Develop 3
Project Titles/ Topics
• Work/prepare
project proposal on
one of the selected
title (15/02/2015)
THANK
YOU !!