Construction Machinery: - Types, Procurement & Maintenance
Construction Machinery: - Types, Procurement & Maintenance
Construction Machinery: - Types, Procurement & Maintenance
P.MADANAIAH
Consultant.
09-12-2015 Centre for Good Governance
CONSTRUCTION MACHINERY
for
Infrastructure Development
P.MADANAIAH
Consultant.
09-12-2015 Centre for Good Governance
Evolution of Construction methods
• Manual Operation: From sickle, shovel, spade, trowel, pans, manual
bar bending/ cutting, etc.
- to hand-mixer, machine-mixer, vibratory rollers, excavators, bar
bending/cutting machines, sand washing machines, etc.
- to the modern day, concrete pavers, computerized concrete
mixing machines, rotary drillers etc. and still evolving
innovations.
• Construction industry - Employ the best possible technology and
machinery as applicable to local conditions to complete the job in
the minimum time and cost.
• Methods involved -Introduction of modern high-powered
earthmoving equipment, rock crushing plants, cranes , concrete
fixing machinery including concrete transport and placing
machinery, etc
• Construction Costs - Formulation of standards and work
specifications and prepare data on “scientific basis” using “The State
of Art technology” in vogue ,by deploying suitable machinery and
technology ,wherever possible and, reduce the component of
manual labour and construction costs with assured best quality
6
construction machinery-necessity
• Increase in size of infrastructure development
projects- large quantities of material inputs
• Increase in complexity of projects involving high
grade materials
• Shortage of Skilled labour and lack of technology
up gradation
• To reduce period of construction- to pass on the
benefits to the user at the earliest
• To cut down construction costs drastically- with
modern machinery with least labour inputs
• External and internal funding agencies specify the
7
use of sophisticated machinery
Market Growth
• India -5th largest and fastest growing construction
equipment market in the world
• Construction Industry employs more than 18 million
people
• Construction equipment accounts -5 to 24% of
construction project costs
• Estimated Global market of construction equipment
- over $ 90 billions in 2013
- Indian sector - US $ 3 billion
• Growth rate in global industry- about 5% per
annum
- India’s growth is around 30%
• India-Total infrastructure expected 10 % of GDP
during the 12th Five Year Plan (2012–17),
compared to 7.6 per cent during the 11th plan
8
(2007–12).
India - Market Growth
As per ICEMA (Indian Construction Equipment manufacturers’ Association)
9
India-Market Growth
• The Indian construction equipment sector -
broadly segments
Earthmoving equipment
Tunnelling & Drilling
Road construction equipment
Concrete equipment
Material handling equipment
Material Processing equipment
10
India- usage of heavy machinery
percentage
11
ECM- India-Market Growth
Earthmoving equipment and road construction
equipment account for about 70 per cent of India's
construction equipment market.
- Backhoe loaders, which comprise tractors, front
shovel/bucket backhoes and small backhoes, account for 65
per cent of the earthmoving equipment and road construction
segment.
Concrete equipment is the second largest segment with a
market share of approximately 14 per cent. It comprises
asphalt finishers, transit mixers, concrete pumps and batching
plants.
Material handling equipment -- 10 per cent
- Cranes are the largest category within the material handling
equipment
material processing equipment account and 6 percent of the
market respectively. 12
Construction Planning and Machinery
Tips for Executive agencies
• Formulate detailed Plan of action and deliverables –priorities
and phases
• To adopt use of machinery wherever possible and reduce
manual labour component
• Select job specific requirements- inputs and machinery
• Prepare work data and use rate on scientific basis, using
“The State of Art technology” in vogue
• To employ the best possible technology and machinery
most suitable to local conditions at optimum costs.
• Deploy where needed the most modern, high powered
earthmoving equipment, rock crushing plants, cranes and
concrete fixing machinery
• Good construction equipment leads to reliable operation and
in turn offers productive and long lasting results in addition to
financial gains
13
Construction machinery and equipment
Prime Categories
• Heavy Earth Moving Machinery: Its the largest segment
and includes products like, shovels/excavators,, backhoe,
loaders, Bulldozers, scrappers ,motor graders loaders,
dumpers etc
18
Construction Machinery &Equipment
27
28
TBM- General Specifications
• Boring Diameter
• Cutter head
Installed power
RPM
Thrust
• Cutters
Numbers,
Tip width,
Diameter ,
Max load/cutter
• Boring Stroke
• Max. turning radius
• Weight
• Other- job specific
29
TBM-Rotary cutters
30
Bulldozer
• Horse power
• Mounting type
• Blade size.
• Cutting blade section
• Effective lift for material say,1 meter.
• Reach of ground 0.8 meter
• Attachments (specify)
31
Bulldozer (Dozer)
32
Bulldozer
bulldozer blades-shapes &usage
• A Straight Blade ("S-Blade") -short and
has no lateral curve, no side wings, and
can be used for fine grading.
• A Universal Blade ("U-Blade") -tall and
very curved, and has large side wings to
carry more material.
• A "S-U“ -used for pushing piles of large
rocks
33
Ripper
34
Excavators
Excavators –usage
• Digging of trenches, holes, foundations
• Demolition
• General grading/landscaping
• Heavy lift, e.g. lifting and placing of pipes
• River dredging
• Mining- opencast mining,
• Loading, etc
35
Hydraulic excavator
Example
• Engine Rated Power--
400 HP
• Operating Weight : 45t
36
DRAG LINE EXCAVATOR
37
WHEEL – LOADER
38
loading shovel
example:
39
loading shovel
40
Front end loader-Tyre mounted
41
DUMPER TRUCKS -Types
Side dumper
Bottom Dumpers
Rear dumper
Articulated dumper
Transfer dumper
42
CONSTRUCTION MACHINERY
DUMPERS
Specifications
(example)
-- Rated Power - 400 HP
-- Maximum Gross
weight - 45 Tons
-- Payload with Standard
Equipment -30 tons
43
Rear Dumper
44
backhoe-attachment
45
Back hoe for excavation
• Loading height
• Digging Depth
• Maximum reach
• Bucket working angle --170 deg.
• Boom Swing ---165 deg.
• King Post Travel ---2.5 ft.
• Bucket out side width- 1 ft /2 ft.
46
BACKHOE- Excavator with Loader
47
48
BACKHOE LOADER
49
EXCAVATION&TRIMMING
50
51
SCRAPER
52
Scraper with Pusher
53
Grader
54
55
Road Roller/Roller Compactor
Specifications
56
Vibratory Compactors
Specifications (Common)
– Operating weight:
– Drum width
– Drum Diameter
– BHP
– TYRE Size
– Vibratory Frequency - Standard 31/34 Hz (
Say 1000 vpm)
and other features as in Road rollers
57
Vibratory compactors
58
Batching Plant
59
Batching plant specifications
Technical Data Model
60
TRANSIT MIXURES
61
Transit mixers
Technical Specifications
NOMINAL CAPACITY
TOTAL GEOMETRIC VOLUME
FILLING RATIO
ENGINE
POWER
DRUM SPEED
WATER TANK
WATER PUMP
LENGTH OF MIXER
WIDTH OF MIXER
HEIGHT OF MIXER (W/o. Truck)
WEIGHT OF MIXER ONLY
62
CC Mixer
63
CC MixersSPECIFICATIONS
SPECIFICATIONS- CC Mixer
10/7 (drum 7/5
cap)unmixed/mixe
d
Capacity (unmixed) 300 Ltrs. 200 Ltrs
64
cable ropeway
65
concrete placing boom
66
TOWER CRANE
67
CANAL LINING MACHINE
68
Mobile Hot Mix Plant
69
Telescopic (Boom) mobile crane
70
Wheel Mounted Cranes
71
72
EOT Cranes
73
Jib cranes
74
FORKLIFTS
75
76
Piling Rig
77
Piling Rig
78
Hydraulic Pile driver
79
Heavy pile Rig
80
Hydraulic Pile driver
81
Pile Hammer
82
Diaphragm wall machine
83
Sheet piling
84
Sheet piling
• Sheet piling is a form of driven piling
- Thin interlocking sheets of steel used,to
obtain a continuous barrier in the ground.
• Main application of sheet piles
- Temporary supportive wall/ Retaining walls
and coffer dams.
• General Machinery:
- vibrating hammer,
- crane
- crawler drill 85
Sheet piling
86
Tracked Paver
87
Bitumen Sprayer
TECHNICAL DATA (An example)
• Bitumen tank
• Model : ABS - 4000 / ABS - 6000 - ABS - 8000 / ABS – 10000
• Capacity :4000 / 6000 / 8000 / 10000 Litres
• Tank Shape :Oval
• Insulation :50 mm thick glass wool
• Temperature gauge :0-300° C
• Mounting :Tank mounted on any truck chassis of wheel base 176”/166”
• Spray bar Length :2.4 Mtr. Length with extension :4.20 Mtr.
• Fully circulating of pre-heated bitumen- Bitumen spraying pressure :0-4 Kg./
cm2
• Bitumen pump2" x 2" size positive displacement gear pump with output of
400 Ltrs. / Min
• Air compressor: Standard make 2 Cyl. air compressor
• Burner Fuel consumption : 20 Ltr. / Hr.
• Fuel tank- 50 Ltrs. capacity
• Fuel tank 100 Ltrs. Capacity
• Engine Standard make, Air cooled diesel engine,.
88
Bitumen Sprayer
89
Tracked pavers
• Maximum paving width --11.0 - 13.0
meters
• Paving speed 20 meters/min
• Propulsion --Tracked
• Dead weight
90
Bituminous Sprayer
91
Dredging
• Dredging is the removal of sediments and debris
from the bottom of lakes, rivers, harbors, and
other water bodies.
• A cutter-suction dredger's (CSD) suction tube
has a cutting mechanism at the suction inlet.
• The cutting mechanism loosens the bed material
and transports it to the suction mouth.
• The dredged material is usually sucked up by a
wear-resistant centrifugal pump and discharged
either through a pipe line or to a barge.
92
Dredger
93
94
final phase of buddha statue installation
95
Use Rate /Hire Charges of machinery
97
Hire charges of construction machinery
PART-A
• Capital cost of machinery / equipment --C
100
working Use rate of machinery and SR for Canal works
Excavation in soft rock without blasting including boulders above 0.30 m upto 0.6 m dia. for
canals, seating of embankment, filter drain / catch water drains etc., including dressing of
bed and sides to required level and profile, cost of all materials, machinery, labour, placing the
excavated soft rock neatly in dump area or for formation of service road as directed etc.,
complete with lead upto 1 km and all lifts.
102
working Use rate of machinery and SR-Canal
103
working Use rate of machinery and SR--Canal
104
105
Procurement of Construction Machinery
Pre requisites
• Type of job/work
• Quantity
• Scheduled program of work
• Group of machinery- for optimum out turn
• Approach to work place
• Transportation/Conveyance constraints
• Availability of Electric Power
• Economy- Life and efficiency of machine
• Availability of machinery
- with executive agency
- Market and downtime
- For Hire
- alternates
106
Procurement-Process
Role or Area of Construction of the Company or
contractor--Roads, Bridges, Buildings,Dams, Canals,
Industries ,Special Civil Constructions jobs etc.
Work Schedule - Committed dates of
commencement and completion
Financial capacity and sources of funding
Contract specific/Work specific requirements,
quantity, scheduled time
Machinery requirement
Equipment on hand- make, model, balance estimated
life
Condition of Existing equipment- Good, Fair or
Poor condition
107
Balance machinery required
Procurement or Hiring of Machinery
Renting has a strong potential in India,
particularly for smaller equipment
Hiring of Machinery avoids large capital
expenditure
Saves on maintenance and storage cost
Provides access to broad selection of
equipments.
Enable to adopt for the job/ work the best
equipment
Take decision to buy/hire only on working out
economics
108
Procurement-Tips
Detailed specifications
Grouping of machinery for optimum out puts
Select Standard manufacturers with Proven record in the market for
the similar machines
Preferable to procure the machinery of same make/manufacturer
already in use, to reduce O&M costs, inventory and down time costs
Check for Warranties & Guarantees
O&M aspects- role of company and facilities
Thoroughly examine the conditions of supply agreements and
conditions
Payment conditions
Training to operational & maintenance staff
Company’s record of litigations and Legal issues
Do not just jump to the lowest offered rate, unless the above
requirements are met with
Economy - considerations
109
Maintenance Aspects
110
Types of Maintenance
• Planned Maintenance
– Ensure maintenance charts for each machine
– plans / preparedness to meet emergency repairs and
replacements
• Types of Maintenance
Preventive Maintenance
• Daily Checks
• Weekly checks on week holidays
• Scheduled maintenance by manufacturer or technicians -
Monthly/half yearly/yearly or on using specified or fixed
hours of running, or both
• Special Maintenance
– Corrective maintenance
– Predictive maintenance
Reactive maintenance – Non plan - On failure only
111
Maintenance-plans
• Ensure supply of updated maintenance charts – Display
in field offices /workshops
• Indicate clearly the back logs of maintenance
• Check and display warranty and guarantees of
Suppliers
• Standby/ spare machinery availability
• Field maintenance facility for day to date maintenance
• Maintenance staff - stationed in the field
• Maintenance contract with manufacturer /dealer
• Manufacturer maintenance schedule at site workshops
• Location of dealer workshops and types of jobs
• Fuel efficiency: As per manufacturer
- present fuel efficiency
112
- Adopt best practices
113