Unit 6

Download as ppt, pdf, or txt
Download as ppt, pdf, or txt
You are on page 1of 24

Risk Management

UNIT -6

Topic Outline: Risk Management



Project risks and risk management Identification of risks Risk assessment and risk analysis Contingency planning Time and cost padding Expected values

Risk management exercise


PERT analysis Computer simulation analysis

Project Risks
Uncertainty a random chance that something will
Risk an uncertain event or condition that could
negatively impact project performance Each risk has a likelihood, or probability, of occurring and possible outcomes if it does occur happen, with no way to control whether it happens

Managing Risks
Since the project manager is responsible for project success, he or she can increase the likelihood of success by better managing risks Risk management is a proactive approach to dealing with uncertainties rather than a reactive approach Some risks can be disregarded and some can be avoided, but others should be planned for

Project Risk Management


Risk management in projects involves:

Identifying risks Assessing and analyzing the likelihood and

impacts of risks Trying to reduce the uncertainties (by gathering more information or making different decisions) Trying to lessen the impacts of risks Developing contingency plans for critical risks Monitoring risks as the project progresses

PMIs View of Risk Management


Risk management consists of 6 subprocesses: Risk Management Planning

Risk Identification Qualitative Risk Analysis

How to approach and conduct risk mgmt. activities

Quantitative Risk Analysis

Assessing likelihoods and possible outcomes Computer simulations; decision tree analysis; etc.

Risk Response Planning Risk Monitoring and Control

Identification of Risks
Identifying all of the possible events or conditions that might occur and may negatively impact project performance A brainstorming session with the project team can be a helpful way to ensure that all important risks are identified Determining symptoms or warning signs that indicate when the risk is about to occur Determining root causes of the risk

Risk Assessment
This info. should be developed for each risk: Description of risk All the possible outcomes of the risk The magnitude or severity of the outcomes Likelihood (probability) of the risk occurring, and likelihood of each possible outcome When the risk might occur during the project Interaction of the risk outcomes with other parts of this project or other projects

Risk Assessment Matrix


Risk System Crash Software Glitches Users Dissatisfied Hardware Malfunction Likelihood Low High Medium Low Severity High Low Medium Medium

Detection Difficulty
High Medium Low Medium

When Startup PostStartup PostStartup Startup

Risk Analysis Tools


Probability analysis Decision tree analysis Monte Carlo

simulation analysis Life-cycle cost analysis Delphi techniques for consensus

Technology

forecasting Game theory analysis PERT analysis Sensitivity analysis Expected value analysis

Reducing Risks
Try to reduce uncertainties (collect more
information, use more reliable vendors, design for easy production, dont use leading edge technologies, etc.)

Try to reduce the severity of potential

outcomes (purchase insurance, convince customer to share the risk impacts, train employees how to respond quickly, etc.)

Contingency Planning
A contingency plan is an alternative plan used if a risk event or condition occurs. Examples: Having a backup supplier for a key material Carrying a safety stock for a key part Having an alternate distribution channel to send products to China (air instead of boat) Having hurricane evacuation plans

Time and Cost Padding


Padding is a commonly used approach to address risks, since it is very easy to implement and since it protects against most minor risks Padding refers to inflating the original time or cost estimates for activities or for the project Unfortunately, this leads to longer project durations and higher costs

Time and Cost Padding


People will generally use up as much time and money as they are allowed (if you dont use it you lose it!) Student syndrome if extra padding is built into activity time estimates, some people are likely to procrastinate getting started, and then the protection against risk is lost Although padding can be useful in reducing the severity of risk, it can also lead to inefficiencies and waste

Expected Values
A construction manager is trying to decide what size crew to schedule for tomorrow based on weather: Weather Probability: 10% 20% 30% 40% Expected Alternative Nice Cold Rain Snow Value Large crew $860 $710 $160 $-350 $136 Med. crew 520 430 190 -120 $147 Small crew 280 240 170 130 $179 sample calculation:
Large .10(860)+.20(710)+.30(160)+.40(-350) = 136

Risk Management Exercise


Nelson Mandela Bridge case (25 minutes)

Divide into small groups Read case Discuss the issues and answer these questions:
How would you have identified the risks? Using the table provided, discuss how the risks were addressed and/or how risks could have been addressed. Also, indicate any additional risks you can think of. Indicate whether the risks listed are internal or external. Describe how you would determine the expected values of the risks listed. Do you think that risk was adequately managed in this project? Why?

Uncertain Task Durations


Probability distributions Discrete, uniform, triangular, normal, beta, etc. Most common way to consider task uncertainty

is to estimate the most likely, pessimistic, and optimistic durations. PERT analysis assumes a Beta distribution for each task

Estimating Task Times (with PERT)


Activity duration estimates: a=optimistic, m=most likely, b=pessimistic time
Expected task duration: Te = (a + 4m + b)/6 Variance of task duration: Var = [(b a)/6]2

PERT Example
Task Pred. Opt. Most Likely a -3 4 b -2 3 c a 3 3 d a 2 2 e b 4 6 f b 3 0.028 g c,d 1 1 h e 4 4 i f 3 5 j e,g 3 6 k h,i 1 1 Te = (a + 4m + b)/6 Pess. 6 4 5 2 11 4 2 4 8 10 2 Var Te 4.167 3.000 3.333 2.000 6.500 4 1.167 4.000 5.167 6.167 1.167 = [(b Var 0.250 0.111 0.111 0.000 1.361 3.833 0.028 0.000 0.694 1.361 0.028 a)/6]2

PERT Example
Use Te values for task durations on project
network to compute slack values. The results of the new computations still shows path b-e-j as the critical path, with an expected project duration of Tcp = 3.000 + 6.500 + 6.167 = Varcp = 0.111 + 1.361 + 1.361 = StdDevcp = sqrt(2.833) = MS Project with 3 task durations

Computer Simulation Analysis


General purpose simulation software can
model how many products flow through all the machines in a factory and on to the warehouse. This capability is much more than what is needed to simulate projects. Monte Carlo simulation is much simpler type of simulation analysis that we can use to model the uncertainty of task durations and costs. Crystal Ball and @RISK are two such packages.

Crystal Ball and Project Analysis


Crystal Ball allows you to specify any type of
probability distribution for each task. You specify all precedence relationships. It then shoots random numbers into your probability distributions to simulate thousands of completions of the project. The result is a probability distribution of the total duration of the project, from which you can answer the what-if questions about how long the project might actually take.

Goldratts Critical Chain


Assuming that an activity duration is known

leads to underestimating project durations Because of this, people tend to pad their time estimates This may result in the student syndrome What is that? This in turn leads to procrastination, which can then result in missing the finish date

Goldratts Critical Chain


Add safety time buffers at strategic points in the

project network Safety time buffer at end of critical path is called a project buffer Safety time buffer just before where noncritical paths feed into the critical path is called a feeding buffer.

You might also like