Chapter 01 PTR
Chapter 01 PTR
Chapter 01 PTR
1.4 ADVANTAGES
1.5 LIMITATIONS
PTR Models
Historically, the cleaning of dirty paint hangers and hooks has been ac
complished with chemical methods, using acid, caustic, or organic chemical
solvents. Disposal of the spent solvents containing the paint residues or
sludge has become more expensive because of environmental concerns and
liability problems relating to disposal ofhazardous chemical wastes. Because
the cleaning is done with heat instead of chemicals. Controlled Pyrolysis^
Furnaces eliminate many or all of the problems of excessive cost, safety,
toxicity, and waste disposal associated with chemical stripping methods.
Explosion Relief
Door
Limit Controller
Thermocouple Furnace Thermocouple Monitors
Inside Furnace Temperature
Power Connection
Main Control
Box Stack Thermocouple
Monitors Stack Temperature
Front Door At Afterburner Exit
Water Spray
System
Gas Inlet to
Burners
Primary (Lower)
Burner Heats
Furnace
R0311-02.DWC
Water Inlet
ATR Models
VPI Models
Historically the stripping of stators has been done with heat: wood fires, gas
torches, open gas bumers, burn-off or bum-out fumaces or ovens often
uncontrolled as to results and as to environmental concems of smoke and
odor. In the early 1970's, pollution laws started to control the smoke and
odors from burning stators for stripping, and some shops tumed to chemicals:
first trichlorethylene, a vapor-degreaser solvent which would soften most
vamishes used in electric motors if the stator is left submerged in its hot
vapors for several hours.
The coming ofbetter vamishes such as epoxy that "trichlor" would not soften,
coupled with increasing knowledge about the harmful effects on workers
exposed to such solvents meant that vapor-degreasing solvents were becom
ing ineffective and even dangerous to workers health. Other chemicals such
as methylene chloride, a cold-stripper, could remove epoxy and all but the
Heat Cleans the Metal Parts by Vaporizing the Paint Residues or Other
Combustible Material on the Parts to Smoke.
After all of the organic residues are vaporized off of the metal parts and no
further smoke is entering the afterburner chamber, this is an indication that
the cleaning cycle is ending. After the oven cycle timer times out and the unit
cools down below 300-400°F, the furnace door(s) may beopened so that the
metal parts will cool down more rapidly so they may be removed.
The Bum-Off Furnace can not remove the inorganic pigments that give a
paint or coating its color. A common example is the white pigment, titanium
dioxide. This inert pigment will be unaffected by the heat which vaporizes
the paint coating off the metal parts. The pigments will fall to the floor as an
ash during the cleaning process, although a small amount may adhere to the
metal parts. If the cleaned part is a paint hanger or hook, no further cleaning
is normally necessary as enough of the pigment will come off in the washer
not to give a problem. However, if a reject painted metal part is cleaned in
the furnace before repainting, it may be necessary to brush or wipe the last
film of pigment off the part under running water to get it clean enough to
repaint.
The Bum-Off Fumace can not remove fiberglass fibers, heavy metals, rust,
or dirt residues. Some type of secondary cleaning operation such as a Jet
Washer, Glass Beading, etc. is required to remove these inorganic residues.
For electric motor stators, the wire is the slots should be very loose with only
ashes remaining. All insulation should be gone (except the fiberglass insula
tion on the lead wires will remain as it is not combustible). The stator slots
should be clean, and the coils should have most of the enamel removed from
the individual wires.
<S)
Controlled Pyrolysis Bum-Off Fumaces are not incinerators. The fur
nace should be used only to reclaim metal parts for salvage and/or rebuilding
by removing conventional hydrocarbon coatings (paint/powder coatings,
oil/grease coatings) from metal parts. Do not use the fumace as an
incinerator to dispose of waste materials or medical or pathological or
nuclear materials.
DANGER: Do not clean any sealed container, pipe, tank, or other vessel
containing any material which may expand when heated and mpture
the vessel. This includes water-jacketed stators, heat exchangers,
coolers, oil-jacketed pipes, or any other sealed vessel. Plugs, caps, or seals
must be removed to prevent explosive forces from rupturing the vessel,
destroying the furnace, destroying the building, and ii\juring or killing
people.
Do not process wet paint, paint sludge, waste powder from powder
coating operations, paint filters, nitrocellulose paints, solvents, thinners,
waste plastic or polymer, PVC (polyvinyl chloride), lead or rubber
coated scrap wire or parts, wood, paper, trash, waste oil, waste grease,
oUfilters, ammunition, explosives, fertilizer, or anything else which may
overload the furnace and cause a fire or explosion. The furnace is not
designed as an incinerator. It is designed to clean and reclaim metal
parts.
Do not process sludge from hot tanks, cold tanks, trichlor tanks, parts
washers, or jet washers.
Do not use the furnace to process automotive parts or other parts which
have just been rinsed in a volatile solvent such as gasoline, kerosene, or
similar highly volatile solvent
Consult factory before processing varnish drip pans from curing ovens,
varnish racks or carts; oU-soaked transformers; epoxy-encapsulated
coU ends; and other out-of-the-ordinary materials.
Do not process aluminum frame stators in the same load with epoxy-en
capsulated stators because if the epoxy ignites, it may be close enough
to an aluminum frame to overheat it. Aluminum frames should be placed
near the bottom of the furnace cart to keep them out of the flames of
other stators should one ignite.
1.4 ADVANTAGES
PTR Furnaces 1. "Prepping" or prior cleaning of the parts before loading them into the
furnace is not normally necessary.
PTR Furnaces 2. Metal hangers,jigs, trees, and fixtures used to hold parts on conveyorized
painting systems can be cleaned very economically by pyrolysis. Such
cleaning is especially useful in electrostatic paint operations where a good
electrical contact for paint wrap-around is essential. Also, possible hazard
ous sparking between the part and the metal hanger is eliminated when the
hangers are kept clean.
PTR Furnaces 3. Painted parts themselves can be cleaned by pyrolysis if proper secondary
removal of pigment is possible physically and economically. Care must be
taken when cleaningaluminum parts to make sure no ignition takes place in
the fiimace as aluminum melts at 1200°F, much lower than most metals.
Temperatures of800°F (427°C) will anneal and soften aluminum, perhaps
too much for re-use. Always test aluminum parts at lower temperatures to
determine if it is safe to clean them.
VPI Furnaces 4. Electric motor stators can be stripped by hand without any power tools.
Statorslotscan be cleaned quickly by handwith compressed air. "T"frames
and aluminum frames can be safely reclaimed. End bells, junction box
covers, andothercomponents canbesafelycleaned whileyouare processing
stators. Nameplatesare not harmed, so they do not have to be removed.
VP! Furnaces Many shops completely eliminate sandblasting because the stator slots are
free of any residue, and the use of steam cleaners can be drastically reduced
because many parts clean better and easier with heat.
VPI Furnaces Thestripped wire with theenamel removed may command a premium scrap
price. Scrap wire recovery can also be increased by processing stators that
were formerly scrapped with the wire in them.
AIR Furnaces 5. Engine heads and blocks come out of the furnace dry and ready for steel
shot, glass bead peening, or Jet Washers with biodegradable detergents.
ATR Furnaces Safe for aluminum. Heads, blocks, water pumps, oil pans, valve covers, and
other components can be safely cleaned using standard furnace controls with
no technical modifications. The furnace can be used for stress relieving and
pre-heating parts before welding ifthe temperature required is800®F orless.
Carbon deposits are loosened by the cleaning process inside the furnace,
allowing less shot peening time and laborious hand grinding to remove the
carbon on engine heads and blocks. In many cases, the hand grinding
operations associated with cleaning heavy carbon build-up can be eliminated.
All Furnaces 6. Solvents and acids for stripping of parts can be significantly reduced or
eliminated along with the tanks, heaters, fumes, and other safety problems
associated with such chemical cleaning methods.
All Furnaces 7. Open stripping tanks with their odors and ignitable fumes can be
eliminated.
All Furnaces 10. Skin and eye irritation from solvents or acids used in stripping can be
eliminated along with protectivegloves, aprons, etc.
All Furnaces 11. A pre-set Cycle Timer means no attendant is necessary to supervise
processing.
All Furnaces 13. The patented Controlled Pyrolysis System for the furnace prevents
"uncontrollable fires" and thepossibility of partwarpage or otherdamage.
All Furnaces 14. In the unlikely event of an explosion or ignition inside the fiimace
pressurizing it, the Top Relief door(s) provide explosion relief and then
automatically close to seal air from the furnace. There are no spring loaded
doors to blow open and remain open to let air ignite the hot parts.
All Furnaces 15. The loading cart and outside tracks are furnished. There are no acces
sories to buy.
All Furnaces 16. The light-weight high temperaturestack sections (chimney pieces) allow
quick and easy erection of the exhaust stack. Overhead hoists, cranes, or
rigging are normally not needed.
All Furnaces 17. Operating and safety controls required by most state and local codes are
standard. Special requirements such as Factory Mutual standards and In
dustrial Risk Insurers standards are available at extra cost where required by
the insurance underwriter.
1.5 LIMITATIONS
PTR Furnaces This furnacecannotremovethe pigmentthat gives a paint or coating its color
if that pigment is inert, such as the most common white pigment, titanium
dioxide. Ti02 falls to the floor as an ash after burning, but a small amount
may adhere to the part. If the part is a paint hanger, no further cleaning is
usually necessary as enough of the TiOz will normally come off in the washer
not to give a problem. However, if a reject painted part is cleaned in the
furnace before repainting, it may be necessary to brush or wipe the last film
of Ti02 off the part under running water to get it clean enough to repaint.
PTR Furnaces Some aluminum parts can be cleaned in the furnace while others can not.
Generally, this depends on the required cleaning temperature as well as the
geometry of the parts themselves. Some aluminum parts may tend to warp
or distort at the furnace cleaning temperatures. Temperatures of 800°F and
above will anneal and soften many aluminum alloys. When in doubt, it is a
good idea to test a few sample parts to see how they are affected by the
cleaning process.
VPI Furnaces Stator frames or other parts made of zinc, "pewter", or "die-cast" can not be
burned in this furnace since this material melts between 600 and 800
dependingon the alloy.Fortunately, such stators are from usually very small
motors, on the order of 1/6 HP or smaller. If there is any doubt about the
material being zinc or aluminum, a simple test with concentrated nitric acid
diluted 50/50withwaterwill tell thedifference. (Nitricacid can be obtained
All Furnaces This furnace can not remove or "bum-off' the rust on the parts as rust is an
inorganic material. However, the fumace loosens the rust for easier removal
during secondary cleaning operations.
All Furnaces This furnace is not designedfor use as a solvent-drying oven. It may be used
for water-drying only if desired. The reasons behind the recommendation
that it not be used to cure painted parts or vamished stators are: After use as
a stripping furnace, the fumace floor and walls contain fine particles of ash
which are stirred up when the furnace is operating and may contaminate the
freshly painted or varnished parts, ruiningthem.Also, the exhaustsystemon
the fumace is due to a natural draft set up by the afterbumer instead of a
fan-forced exhaust as on a conventional bake-oven, and may not prove
adequate to remove the solvent fumes at the proper rate. DANGER: At
tempting to use the furnace for solvent drying, or as a curing oven can
lead to a fire or explosion in the fumace. Circulation within the fumace
is also due to naturalconvectionand may have a greater temperature gradient
than required to properly cure paint or varnish.
This system is automatic and is interlocked so that the lower burner on the
furnace cannot come on if there is insufficient water pressure for the C.P.S.
For VPI Models, experience has shown that most electric motor stators can
be adequately processed at a stator temperature of 750°F (400°C). The
amount of time required depends primarily on the weight of the stator and
the cross-section of its thickest part. The furnace temperature controller
indicates and controls the furnace temperature by the furnace air tempera
ture. The stator temperature will lag behind the air temperature sometimes
for an hour or more if it is a large stator, and the stator temperature must get
to 750°F for the insulation and varnish to be decomposed, so the time for a
good jobwill begreater than just the time ittakes the furnace togetto750°F.
The furnace is equippedwith a 0-12 Hr. adjustable timer to allow time cycle
changes. The timer has two scales, the black figures showing the correct
settings if the electricity supply is 60 hertz and the red figures for 50 hertz
supplies. The temperature indicator-controllers are also dual-frequency
models. All controls and motors are set up at the Factory to operate at the
customer's specified supply frequency.
TABLE I
52 2-4 200-400
88 2-6 400-600
Note: Ifyour furnace is equipped with the Automatic Time Cycle feature
and you are cleaning parts which are not very massive, such as paint hangers
and hooks,a settingof 1 to 2 hourson the Cycle Timer is generally adequate,
as the temperature of these parts will generally follow the temperature of the
furnace fairly closely. If youarecleaning largemassive partssuchas engine
blocks, dies, etc., the actual temperature of the parts may lag behind the
temperature of the furnace considerably. For parts such as these, you will
need to select a longer time on the Cycle Timer in order to insure that the
parts have had time to reach temperature before the Cycle Timer starts. See
Chapter 2 for a more in depth description of how the Automatic Time Cycle
feature operates.
Furnaces are equipped to comply with most local building codes, but
sometimes there will be requirements which the factory has no way of
knowing unless told before shipment. If such requirements become known
after receipt of the furnace, please contact the manufacturer before authoriz
ing any work to change anything so that we may fully explain to local
authorities details of our unit, and also for us to understand their require
ments. If the manufacturer was not notified in advance of any special
requirements, then any changes will be at the expense of the customer.
Furnaces should be selected by size depending on the size and shape of the
parts to be processed. The parts must fit within the confines of the cart that
is furnished with the furnace. The Factory cart must be used instead of
customer-supplied carts, baskets, or other containers as such other containers
may block the proper flow of air within the furnace and lead to problems in
processing.
Parts to be processed must not be nested or stacked so that they touch each
other over an appreciable area as this retards the decomposition of the
combustible material due to inadequate air flow around the parts. Inadequate
air flow may cause "coking" or transformation of the combustible material
on the parts to hard charcoal (carbon) with the result that the charcoal must
combine with oxygen on the part, perhaps raising the part temperature higher
than it should be. Getting rid of the charcoal in this way is a slower process.
Therefore, if parts are allowed to coke, processing time must be increased.
The quantity of parts to be processed also affect furnace size selection and
cycle time. In cooperation with the customer, the factory will "custom"
design at extra cost a cart suitable to hold and process the customer's parts.
This will require sample parts being sent in (preferred) or drawings of the
parts, quantities to be processed and the time frame of customer's operations
so that a proper cart can be designed. Of particular interest will be the amount
of combustible material on the sample parts. This can be determined by the
factory or by the customer by carefully weighing coated parts before and
after cleaning.
Most companies who use metal hangers for paint spraying operations know
that by conventional means(paint stripping by acid or chemical agents), the
cleaning process is looked upon as a dirty, time consuming, laborious job
not to be done until absolutely necessary. Sometimes this means a 1/2" or
more build-up of paint on the metal hangers before cleaning takes place.
With the use of this fiimace these extra large build-ups of paint can be
cleaned; however, the first loads, until the extra large build-up is off, must
be reduced to less than the normal number of hangers. Once the majority of
the metal hangers have been cleaned by the furnace, then the normal number
of hangers per load can be started.
Figure 1-4 shows the basic lay-out of the main control box, while Figure 1-5
shows the components of the water spray control system.
Refer to the drawings labeled "ATR, VPI, & PTR Installation Drawing" for
details regarding placement and installation of the furnace.
Diagnostic Panel
Limit Controller
Rg401-05.DWC
Bypass Valve
Primary Water Spray
Bypass Valve
Back—up Water Spray
Pressure Relief Valve
Automatic Valve
Primary Water Spray Water Pressure Gage
Normally Open
Automatic
Water Pressure Switch Back—up Water
Spray Valve
Automatic Valve
Primary Water Spray
Normally closed 0
9401-06.DWG
•p
I t9V/«0Hz
4
i
El
-1 n (. 28>
A
I TOP RELIEF
h-» PLAN V EW
00
POLLUTION CONTROL
S mHbX'
PRODUCTS CO. DALUS. TEXAS
CLEARANCE TO ROLL
CART OUT
24*C.6n MINIMUM TO SET CONTROLS «. SERVICE
GENERAL INSTALLATION DRAWING
FOR MODEL DC. PTR. ATR, VPI.
PRC, ARC, VRC FURNACES
NONE RLB 1-9-95
S9501-05
A B C D E r G A B C D E r G
MODEL MODEL
IN. M IN. M IN. M IN. M IN. M IN. M IN. M IN. M IN. M IN. M IN. M IN. M IN. M IN. M
DCl 59 1. SO 66 1. 68 43 1. 09 101 2. 57 28 . 71 10-1/2 . 27 N/A N/A 330 85 2. 16 189 4. 29 88 2. 19 124 3. 15 38 . 97 18-1/2 . 42 188 4. 73
125 88 1. 73 137 3. 48 55 1. 40 95 2. 41 27 . 69 10-1/2 . 27 108 2. 85 504 109 2. 77 134 3. 40 122 3. 10 180 4. 08 38 . 97 18-1/2 . 42 188 4. 27
14] 83 2. 11 83 2. 16 91 2. 36 129 3. 28 26 . 68 15-1/2 . 39 94 2. 39 512 121 3. 07 134 3. 40 110 2. 79 148 3. 76 38 . 97 18-1/2 . 42 164 4. 17
150 83 2. 11 97 2. 46 85 2. 16 123 3. 13 26 . 88 15-1/2 . 39 128 3. 20 539 109 2. 77 170 4. 32 98 2. 49 138 3. 48 38 97 18-1/2 . 42 192 4. 88
177 83 2. 11 97 2. 46 97 2. 46 143 3. 63 26 . 86 15-1/2 . 39 126 3. 20 549 121 3. 07 134 3. 40 118 3. 00 155 3. 94 38 . 97 16-1/2 . 42 164 4. 17
188 83 2. 11 85 2. 16 112 2. 85 ISO 3. 81 26 . 66 15-1/2 . 39 94 2. 39 585 131 3. 33 134 3. 40 110 2. 79 148 3. 76 38 . 97 16-1/2 . 42 170 4. 32
222 85 2. 18 121 3. 07 85 2. 16 117 2. 97 28 . 86 15-1/2 . 39 138 3 51 577 121 3. 07 148 3. 71 110 2. 79 148 3. 78 38 . 97 18-1/2 . 42 178 4. 47
225S 97 2. 46 109 2. 77 89 2. 26 125 3. 18 26 . 66 15-1/2 . 39 (1) < l> 608 121 3. 07 134 3. 40 128 3. 25 166 4. 22 38 . 97 16-1/2 . 42 164 4. 17
228 133 3. 38 93 2. 38 73 1. 85 123 3. 13 28 . 88 15-1/2 . 39 148 3. 71 812 208 5. 23 82 2. 08 117 2. 97 165 4. 19 98 2. 44 40 1. 02 ( 1) < n
240 109 2. 69 93 2. 36 95 2. 41 133 3. 38 26 . 66 15-1/2 . 39 126 3. 20 622 109 2. 77 188 4. 22 110 2. 80 148 3. 76 38 . 97 16-1/2 . 42 188 4. 78
243 97 2. 46 97 2. 46 103 2. 82 141 3. 58 26 . 88 15-1/2 . 39 128 3 20 840 121 3. 07 158 4. 01 110 2. 79 148 3. 78 38 . 97 18-1/2 , 42 188 4. 78
280 91 2. 31 121 3. 07 97 2. 46 142 3.61 38 . 97 18-1/2 . 42 138 3. 51 880 121 3. 07 158 4. 01 117 2. 97 154 3. 91 38 . 97 18-1/2 . 42 188 4. 78
290 97 2. 46 121 3. 07 97 2. 46 136 3. 46 38 . 97 16-1/2 . 42 138 3. 51 699 131 3. 33 168 4. 27 98 2. 49 136 3. 46 38 . 97 18-1/2 . 42 204 5. 18
300 85 2. 16 157 3. 99 88 2. 18 124 3. 15 38 . 97 18-1/2 . 42 174 4. 42 714 121 3. 07 164 4. 17 117 2 97 154 3. 91 38 . 97 18-1/2 . 42 194 4. 93
REV. 0 1-27-97 CORRECTED DIM. G rOR 539
308S 9/ 2. 46 109 2. 77 117 2. 97 166 4. 22 38 . 97 18-1/2 . 39 (1) < n 748 121 3. 07 170 4. 32 117 2. 97 154 3. 91 38 . 97 16-1/2 . 42 200 5. 08 REV. C 12-16-96 SEE EIR 145 (CART ROLL OUTS)
REV. 8 11-8-98 ADD NEW MODELS & UPDATE CHART
308 91 2. 31 121 3. 07 110 2. 80 159 4. 04 38 . 97 18-1/2 . 42 138 3. 51 806D 288 8. 78 118 3. 00 117 2. 97 158 3. 98 128 3. 20 50 1. 27 < 1) < 1> REV. A 3-15-95 t i t l e block t NOTES
( 1) MODELS 225S, 306S 612D, 806D ARE FORK LIFT LOADED. PRODUCTS CO. DALLAS. TEXAS
<3) NUMBERS UNDER COLUMN 'M- =METERS SCAUC NONE OR. by PLB DATB 1 "9-95
DLC. JMOI-Oi
( 4) MODEL DCl IS S•UPPLIED WITH A STATIONARY INTERNAL RACK. LA«(«> CHAV1 IMO. s r a cmm BY DATE
I 0)
h-njQ
(D
EXHAUST EXHAUSX,
I STACK STACK
ELECTRICAL
w
PLAN VIEW
CONTROL
BOX
inlet CAS
3/4' NRT
CONTROL BOX
63T 46 58 1.47 98 2.50 134 3.40 26 .66 .28 48 1.22 43 1.09 25 .64 65 1.66
72T 46 58 1.47 no 2.80 146 3.71 26 .66 .28 48 1.22 46 1.17 25 65 1.66
84T 46 70 1.78 98 2.50 134 3.40 26 .66 .28 48 1.22 43 1.09 33 65 1.66 POLLUTION CONTROL
M PJ
I yQ
NJ CD
o
CART FRAME DIMENSIONS
I p
tSjlQ
•"-» (D
SQUARE OPENING
CHIMNEY SECTION
INSUUTED CHIMNEY SECTION
ADJUSTABLE PUSHING
1-1/2"(38) CRIMP FITS
INSIDE SECTION ABOVE.
EACH SECTION MAKES
(D UP TO 34-1/2"(876).
I
ro
bo
TYPICAL VIEW A-A
36"
(920)
RAIN CAP
STORM COLUR ,
Slide Down Over
60" MIN.
(1520)
NOTES: 4-HOLES 1/4" DIA.
2"(51) INSUUTION EVENLY SPACED TO
(*) REFERS TO MODEL 26D-680 IGG OR OLDER
MASTIC SEALER KAOWOOL SLEEVE SECURE SECTIONS
FURNACES HAVING G2T OR J-8D/81/82 BURNERS
TOGETHER.
KAOWOOL
NUMBERS IN BRACKETS ( ) OR 60" MIN. \ l.
UNDER COLUMN 'M' = MILLIMETERS ADJUSTABLE PUSHING
(1520) KAOWOOL
DIM. C REFERENCES A SQUARE OPENING
THROUGH THE INSTALUTION STRUCTURE'S ROOF. OUTER MATERIAL
26 GA. STAINLESS STEEL
INSTALLER:
SQUARE WEIGHT/INSUUTED SECTION
FOR ANY LENGTH LESS THAN 36"(.92)
CUT CHIMNEY SECTION AT BOTTOM. OPENING 36 LBS. (16.33 KG.)
SQUARE
OPENING
A B C
MODELS
IN. M. IN. M. IN. M.
DC-1/27 INSUUTED STACK
8 200 12 300 19 480 36"(.91) LONG SECTIONS «tv.B •-»«-<» tacto rviMciz wtm ueisee on o-n
DC-2/SP-13
SNAPS TOGETHER MV.C i-»-w
DC-3, DC-4, FASTENS WITH SCREWS IttV.B I-IT-M *00[D VIIW A-A * MUOt OUMt
netjk n-s-t« cw i o (Euinmre nomii mnitium
52-150, TALLBOYS 10 250 14 360 21 530
SCTR 6-15
POLLUTION CONTROL
(•>260-680 PRODUCTS CO.
FLAT ROOFS PITCHED ROOFS DAUAS. TEXAS
WITH J-8X OR 12 300 16 410 23 580
G2T BURNERS
EXHAUST STACK TYPICAL INSTALUTION
260 & UP FOR ALL FURNACES, INSTALLED THRU
WITH J-121-3 14 360 18 460 25 630 NON-COMBUSTIBLE ROOFS ONLY
BURNERS
FURNACES WITH
RLE: 1950301 D.DWC
LCI500 OR 0-57 16 406 20 508 27 686 UYER: STACINST ua_
BURNERS PLOT DATE: 8-24-05 19503-01