Enigneering Weekly Progress Report (Week Ending 20th OCTOBER 2024

Download as pdf or txt
Download as pdf or txt
You are on page 1of 15

OZMA NIGERIA COMPANYLIMITED

ENGINEERING, PROCUREMENT, CONSTRUCTION, INSTALLATION


& COMMISSIONING OF OZMA LPG PROCESSING PLANT &
MODULAR REFINERY, DELTA STATE
(PIPELINE INFRASTRUCTURE FOR OZMA GAS PRODUCTION
PLANT)

ENIGNEERING WEEKLY PROGRESS REPORT


(WEEKENDING 20 TH OCTOBER, 2024)

DOCUMENT NO.:
OZM-LPMR-ZKL-PJM-WPR-001

P01 20/10/2024 Issued for Information I.U C.N A.E.


ZIKO PMC OZMA
REV. DATE DESCRIPTION
BY CHECKED APPROVED
Project Sequence-
Client Contractor Discipline Doc. Type Rev.
Code Number
Doc. Control No. OZM LPMR ZKL PJM WPR 001 P01

Engineering Weekly Progress Report Page 1 of 15


OZMA NIGERIA COMPANY LIMITED OZM-LPMR-ZKL-PJM-WPR-001
EPCIC OF LPG PROCESSING PLANT & MODULAR REFINERY,
EKROTA, UDU LGA – DELTA STATE Revision No.: P01

REVISION PAGE

Revision Date Description Remarks

Engineering Weekly Progress Report Page 2 of 15


OZMA NIGERIA COMPANY LIMITED OZM-LPMR-ZKL-PJM-WPR-001
EPCIC OF LPG PROCESSING PLANT & MODULAR REFINERY,
EKROTA, UDU LGA – DELTA STATE Revision No.: P01

TABLE OFCONTENTS

REVISION PAGE .................................................................................................................. 2

1.0 INTRODUCTION ......................................................................................................... 4

2.0 KEY PROJECT MILESTONES.................................................................................... 5

3.0 ENGINEERING PROJECT PERFORMANCE DASHBOARD...................................... 6

4.0 FEED DESIGN PROGRESS TABLE ........................................................................... 7

5.0 DED DESIGN PROGRESS TABLE ............................................................................. 7

6.0 PROGRESS HIGHLIGHT FOR THE WEEK ................................................................ 8

7.0 WORK PLANNED (LOOK AHEAD FOR NEXT WEEK) ............................................ 10

8.0 ISSUES, AREA OF CONCERN AND CHALLENGES ............................................... 12

9.0 STATUS OF DOCUMENTATION .............................................................................. 12

10.0 HSE STATISTICS TABLE ......................................................................................... 13

11.0 PROPOSED ACTION PLAN / RECOVERY STRATEGIES ....................................... 14

12.0 CLIENT REQUIRED ACTION.................................................................................... 14

13.0 TECHNICAL QUERIES ............................................................................................. 14

14.0 ATTACHMENTS........................................................................................................ 15

Engineering Weekly Progress Report Page 3 of 15


OZMA NIGERIA COMPANY LIMITED OZM-LPMR-ZKL-PJM-WPR-001
EPCIC OF LPG PROCESSING PLANT & MODULAR REFINERY,
EKROTA, UDU LGA – DELTA STATE Revision No.: P01

1.0 INTRODUCTION
1.1 Background
OZMA NIGERIA COMPANY LIMITED is embarking on the construction of a state-of-
the-art Liquefied Petroleum Gas (LPG) Production Plant, Storage, and Dispensing
Depot Terminal with a capacity of 20 MMSCFD and Crude Oil Modular Refinery and
Storage Facility of a 20,000 BPD capacity. The facility shall utilize natural gas from
Utorogu gas plant while crude shall be sourced from Abura Field (OML 65). The
entire facility is located at Urhie Egoro Bush, Ekrota Town, Udu Local Government
Area, Delta State.
Upon completion, the LPG plant will generate the following expected product outputs
after fractionation:
1. Methane – Ethane Mixture (NGL): 1,862,000 scfd, to be produced through the
De-methanizer & Ethanizer processes.
2. Propane – Butane Mixture (LPG): 15,398,000 scfd, to be produced through
the De-propanizer & Butanizer processes.
The modular refinery is proposed to hold a throughput capacity of 20,000 bpd of
Crude oil which shall be refined and separated into different fractions based on their
boiling points through fractional distillation.
1.2 Project Objective
As part of her drive for expansion in the oil and gas industry, the facility Owner, OZMA
has indicated readiness to construct the facility with capacity to process up to
20mmscf per day of liquified petroleum gas. The proposed facility is expected to have
the capacity to supply LPG gas to customers and shall upscale production to an
optimized throughput capacity of 52mmscfd upon implementation.
Compressed Natural Gas (CNG) is also expected to be produced as well. The inlet
gas shall be sourced from gas feedstock transported from Utorogu Gas Plant via a
pipeline infrastructure to the proposed facility for processing and thereafter primarily
conveyed for bulk shipment via an export pipeline to a jetty location. Products shall
also be dispatched through Product Distribution Trucks (PDTs) from the Facility
Loading Terminal.

1.3 Purpose
The purpose of this document is to report the weekly progress of the project between
14th OCTOBER – 20th OCTOBER 2024 (weekending 20th OCTOBER, 2024).

1.4 Key Achievements for Weekending 20th OCTOBER, 2024.


For this reporting period, the project key achievements are:

 Submitted Engineering Project Schedule


 Submitted Site Visit Report for IFR
 Submitted Pipeline Basis of Design for IFR
 Submitted Pipeline Design Philosophy IFR
Engineering Weekly Progress Report Page 4 of 15
OZMA NIGERIA COMPANY LIMITED OZM-LPMR-ZKL-PJM-WPR-001
EPCIC OF LPG PROCESSING PLANT & MODULAR REFINERY,
EKROTA, UDU LGA – DELTA STATE Revision No.: P01

 Submitted Process Flow Diagram For IFR


 Submitted Drawing Symbols And Legend Sheet For IFR

2.0 KEY PROJECT MILESTONES

PLANNED RE-FORECAST ACTUAL


S/N ACTIVITY COMPLETION COMPLETION COMPLETION
DATE DATE DATE

1 Kick-off Meeting 30thApr,2024 30thApr,2024


Engineering Scope Verification
2 1stJul, 2024 10thJul, 2024
/Reconciliation
3 FEED Issue-For-Review 9thAug, 2024

4 FEED Issue-For-Approval 27thAug, 2024

DED MDR and Schedule


6 3rdSep, 2024
Submission and Approval
FEED Issue-For-Design / Issuance
5 16thSep, 2024
of FEED Closeout Report

7 DED Issue-For-Review TBD

HAZOP/HAZID/SIL Safety Reviews


8 TBD
&Study Workshop
9 DED Issue-For-Approval TBD
DED Approved-For-Construction &
10 TBD
Signoff

Engineering Weekly Progress Report Page 5 of 15


OZMA NIGERIA COMPANY LIMITED OZM-LPMR-ZKL-PJM-WPR-001
EPCIC OF LPG PROCESSING PLANT & MODULAR REFINERY,
EKROTA, UDU LGA – DELTA STATE Revision No.: P01

3.0 ENGINEERING PROJECT PERFORMANCE DASHBOARD

Level 1 Work Weight Previous This Week Cumulative to Date


Package (Wt. %) Cumulative % Phase % Phase
Planned Completed
Description Planned Actual Planned Actual Planned Actual Variance
% % % % % % %
FEED Engineering 50.00% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 20% 14.6%
Issued for Review 17.50% 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Issued for Approval 17.50% 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Issued for Design 15.50% 0.00 0.00 0.00 0.00 0.00 0.00 0.00
DED Engineering 50.00% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 0.00%
Issued for Review 17.50% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 `
Issued for Approval 17.50% 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Approved for Constr. 15.50% 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Overall Progress 100.00% 0.00% 0.00% 0.00%

Engineering Weekly Progress Report Page 6 of 15


OZMA NIGERIA COMPANY LIMITED OZM-LPMR-ZKL-PJM-WPR-001
EPCIC OF LPG PROCESSING PLANT & MODULAR REFINERY,
EKROTA, UDU LGA – DELTA STATE Revision No.: P01

4.0 FEED DESIGN PROGRESS TABLE

Base Wt. in Previous Current Cumulative To- FEED


Activity in FEED Engineering Weight Engineering Cumulative Achievement date Variance Progress
(%) Phase Summary
Plan Actual Plan Actual Plan Actual
FEED Engineering 100.00% 50.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Engineering Project Management 5.00% 2.50% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Process Engineering 20.00% 10.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
14.6%
Pipeline Engineering 45.00% 22.50% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
MCC Engineering 30.00% 15.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
TOTAL 100.00% 50.00% 0.00% 0.00% 0.00% 0.00% 0.00%

5.0 DED DESIGN PROGRESS TABLE

Base Wt. in Previous Current Cumulative To- FEED


Activity in FEED Engineering Weight Engineering Cumulative Achievement date Variance Progress
(%) Phase Summary
Plan Actual Plan Actual Plan Actual
FEED Engineering 100.00% 50.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Engineering Project Management 5.00% 2.50% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Process Engineering 20.00% 10.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00%
Pipeline Engineering 45.00% 22.50% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
MCC Engineering 30.00% 15.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
TOTAL 100.00% 50.00% 0.00% 0.00% 0.00% 0.00% 0.00%

Engineering Weekly Progress Report Page 7 of 15


OZMA NIGERIA COMPANY LIMITED OZM-LPMR-ZKL-PJM-WPR-001
EPCIC OF LPG PROCESSING PLANT & MODULAR REFINERY,
EKROTA, UDU LGA – DELTA STATE Revision No.: P01

6.0 PROGRESS HIGHLIGHT FOR THE WEEK

6.1 ENGINEERING PROJECT MANAGEMENT


 The following tabulated deliverable were issued for review

Document Number Document Title Type Status

OZM LPMR ZKL PJM SCH 001 Engineering Project PDF IFR
Schedule

OZM LPMR ZKL PJM RPT 003 Pipeline Route Selection PDF IFR
Report

OZM LPMR ZKL PJM RPT 001 PDF IFR


Site Visit Report

 The following tabulated deliverable were issued for approval

Document Number Document Title Type Status

OZM LPMR ZKL PJM XXX XXX XXXXX XXXXX XXXX XXX XXX

6.2 PROCESS
 The following tabulated deliverable were issued for Review

Document Number Document Title Type Status

Process Basis of
Design(Feed Gas and
OZM LPMR ZKL E00 PRO BOD 001 PDF IFR
Export Gas)

Process Flow
Diagram(PFD)-Overall
OZM LPMR ZKL E01 PRO PDF 001 PDF IFR
Process

 The following tabulated deliverable were issued for Approval

Engineering Weekly Progress Report Page 8 of 15


OZMA NIGERIA COMPANY LIMITED OZM-LPMR-ZKL-PJM-WPR-001
EPCIC OF LPG PROCESSING PLANT & MODULAR REFINERY,
EKROTA, UDU LGA – DELTA STATE Revision No.: P01

Document Number Document Title Type Status

OZM LPMR ZKL E01 PRO XXX XXX XXXXX XXXXX XXXX XXX XXX

6.3 PIPELINE
 The following tabulated deliverable were issued for Review

Document Number Document Title Type Status

OZM LPMR ZKL E00 PPL BOD 001 Pipeline Basis of Design PDF IFR

OZM LPMR ZKL E01 PPL PHI 001 Pipeline Design Philosophy PDF IFR

 The following tabulated deliverable were issued for Approval

Document Number Document Title Type Status

OZM LPMR ZKL E01 PPL XXX XXX XXXXX XXXXX XXXX XXX XXX

OZM LPMR ZKL E01 PPL XXX XXX XXXXX XXXXX XXXX XXX XXX

Engineering Weekly Progress Report Page 9 of 15


OZMA NIGERIA COMPANY LIMITED OZM-LPMR-ZKL-PJM-WPR-001
EPCIC OF LPG PROCESSING PLANT & MODULAR REFINERY,
EKROTA, UDU LGA – DELTA STATE Revision No.: P01

7.0 WORK PLANNED (LOOK AHEAD FOR NEXT WEEK,ENDING 20th OCTOBER,
2024)

7.1 PROJECT MANAGEMENT


 Issue documents as reviewed by Client/PMC on the deliverables listed below;

Document Number Document Title Type Status

OZM LPMR ZKL PJM XXX XXX XXXXX XXXXX XXXX XXX XXX

OZM LPMR ZKL PJM XXX XXX XXXXX XXXXX XXXX XXX XXX

 Issue documentson IFR as listed below;

Document Number Document Title Type Status

OZM LPMR ZKL PJM XXX XXX XXXXX XXXXX XXXX XXX XXX

OZM LPMR ZKL PJM XXX XXX XXXXX XXXXX XXXX XXX XXX

7.2 PROCESS
 Issue documents as reviewed by Client/PMC on the deliverables listed below;

Document Number Document Title Type Status

OZM LPMR ZKL E01 PRO XXX XXX XXXXX XXXXX XXXX XXX XXX

OZM LPMR ZKL E01 PRO XXX XXX XXXXX XXXXX XXXX XXX XXX

 Issue documentson IFR as listed below;

Document Number Document Title Type Status

Engineering Weekly Progress Report Page 10 of 15


OZMA NIGERIA COMPANY LIMITED OZM-LPMR-ZKL-PJM-WPR-001
EPCIC OF LPG PROCESSING PLANT & MODULAR REFINERY,
EKROTA, UDU LGA – DELTA STATE Revision No.: P01

OZM LPMR ZKL E01 PRO XXX XXX XXXXX XXXXX XXXX XXX XXX

OZM LPMR ZKL E01 PRO XXX XXX XXXXX XXXXX XXXX XXX XXX

7.3 PIPELINE
 Issue documents as reviewed by Client/PMC on the deliverables listed below;

Document Number Document Title Type Status

OZM LPMR ZKL E01 PPL XXX XXX XXXXX XXXXX XXXX XXX XXX

OZM LPMR ZKL E01 PPL XXX XXX XXXXX XXXXX XXXX XXX XXX

 Issue documentson IFR as listed below;

Document Number Document Title Type Status

OZM LPMR ZKL E01 PPL XXX XXX XXXXX XXXXX XXXX XXX XXX

OZM LPMR ZKL E01 PPL XXX XXX XXXXX XXXXX XXXX XXX XXX

7.4 MATERIAL & CORROSION CONTROL


 Issue documents as reviewed by Client/PMC on the deliverables listed below;

Document Number Document Title Type Status

OZM LPMR ZKL E01 COR XXX XXX XXXXX XXXXX XXXX XXX XXX

OZM LPMR ZKL E01 COR XXX XXX XXXXX XXXXX XXXX XXX XXX

 Issue documentson IFR as listed below;

Engineering Weekly Progress Report Page 11 of 15


OZMA NIGERIA COMPANY LIMITED OZM-LPMR-ZKL-PJM-WPR-001
EPCIC OF LPG PROCESSING PLANT & MODULAR REFINERY,
EKROTA, UDU LGA – DELTA STATE Revision No.: P01

Document Number Document Title Type Status

OZM LPMR ZKL E01 COR XXX XXX XXXXX XXXXX XXXX XXX XXX

OZM LPMR ZKL E01 COR XXX XXX XXXXX XXXXX XXXX XXX XXX

8.0 ISSUES, AREA OF CONCERN AND CHALLENGES

8.1 PROJECT MANAGEMENT / GENERAL


S/NO AREA OF CONCERN PRIORITY
8.2 P
R 1
O 2
C
ESS
S/NO AREA OF CONCERN PRIORITY
8.3 P
I 1
P 2
E
LINE
S/NO AREA OF CONCERN PRIORITY
8.4 C
O 1
R 2
R
OSION
S/NO AREA OF CONCERN PRIORITY
1
2

Engineering Weekly Progress Report Page 12 of 15


OZMA NIGERIA COMPANY LIMITED OZM-LPMR-ZKL-PJM-WPR-001
EPCIC OF LPG PROCESSING PLANT & MODULAR REFINERY,
EKROTA, UDU LGA – DELTA STATE Revision No.: P01

9.0 STATUS OF DOCUMENTATION

9.1 STATUS OF OVERDUE DOCUMENTS(FEED)


It is critical for Contractor to receive a response to these as soon as possible to allow
us to maintain project progress. These responses are overdue on the 5-day review
cycle.

Days
Document Number Title Transmittal No. Due Date Overdue

Nil Nil Nil Nil Nil

Nil Nil Nil Nil Nil

9.2 STATUS OF PLANNED VS ACTUAL GATES ACHIEVED PER DISCIPLINE AS


AT 20TH OCTOBER 2024.
DISCIPLINE TOTAL IFR IFA AFD
DELIVERABLE
PLAN ACTUAL PLAN ACTUAL PLAN ACTUAL
COUNT
PROJECT 7 0 0 0 0 0 0
MANAGEMENT
PROCESS 48 0 0 0 0 0 0

PIPELINE 32 0 0 0 0 0 0

TOTAL 362 0 0 0 0 0 0

10.0 HSE STATISTICS TABLE

Engineering Weekly Progress Report Page 13 of 15


OZMA NIGERIA COMPANY LIMITED OZM-LPMR-ZKL-PJM-WPR-001
EPCIC OF LPG PROCESSING PLANT & MODULAR REFINERY,
EKROTA, UDU LGA – DELTA STATE Revision No.: P01

REPORTING PERIOD (WEEK ENDING OCTOBER 20TH, 2024)

S/N Description Previous Week This Week Cumulative

1 Man-Hours (ZKL) 0 0 0
2 Incident Free Man-Hours (IFMH) 0 0 0
3 Lost Time Injury (LTI) 0 0 0
8 Near Miss (NM) 0 0 0
9 Unsafe Act (UA) 0 0 0
10 Unsafe Condition (UC) 0 0 0
11 Road Traffic Accident (RTA) 0 0 0
12 Community/Security Issues 0 0 0
13 Toolbox Talks/Inductions/Safety Brief 0 0 0
15 Safety Reviews/Studies/Analyses 0 0 0
16 Permit to Work (PTW) 0 0 0
11.0 P
ROPOSED ACTION PLAN / RECOVERY STRATEGIES

S/NO ACTION/RECOVERY PLAN DUE DATE


1
2
3

12.0 CLIENT REQUIRED ACTION

S/NO ACTION REQUIRED DUE DATE


1

13.0 TECHNICAL QUERIES

Engineering Weekly Progress Report Page 14 of 15


OZMA NIGERIA COMPANY LIMITED OZM-LPMR-ZKL-PJM-WPR-001
EPCIC OF LPG PROCESSING PLANT & MODULAR REFINERY,
EKROTA, UDU LGA – DELTA STATE Revision No.: P01

TQ TECHNICAL QUERY CLIENT/PMC RESPONSE ISSUE RESPONSE


NO DESCRIPTION DATE DATE
001
002

14.0 ATTACHMENTS
- Engineering Project Measurement System (Week Ending 20-OCT-2024)
- Updated Master Document Register

Engineering Weekly Progress Report Page 15 of 15

You might also like