Enigneering Weekly Progress Report (Week Ending 20th OCTOBER 2024
Enigneering Weekly Progress Report (Week Ending 20th OCTOBER 2024
Enigneering Weekly Progress Report (Week Ending 20th OCTOBER 2024
DOCUMENT NO.:
OZM-LPMR-ZKL-PJM-WPR-001
REVISION PAGE
TABLE OFCONTENTS
14.0 ATTACHMENTS........................................................................................................ 15
1.0 INTRODUCTION
1.1 Background
OZMA NIGERIA COMPANY LIMITED is embarking on the construction of a state-of-
the-art Liquefied Petroleum Gas (LPG) Production Plant, Storage, and Dispensing
Depot Terminal with a capacity of 20 MMSCFD and Crude Oil Modular Refinery and
Storage Facility of a 20,000 BPD capacity. The facility shall utilize natural gas from
Utorogu gas plant while crude shall be sourced from Abura Field (OML 65). The
entire facility is located at Urhie Egoro Bush, Ekrota Town, Udu Local Government
Area, Delta State.
Upon completion, the LPG plant will generate the following expected product outputs
after fractionation:
1. Methane – Ethane Mixture (NGL): 1,862,000 scfd, to be produced through the
De-methanizer & Ethanizer processes.
2. Propane – Butane Mixture (LPG): 15,398,000 scfd, to be produced through
the De-propanizer & Butanizer processes.
The modular refinery is proposed to hold a throughput capacity of 20,000 bpd of
Crude oil which shall be refined and separated into different fractions based on their
boiling points through fractional distillation.
1.2 Project Objective
As part of her drive for expansion in the oil and gas industry, the facility Owner, OZMA
has indicated readiness to construct the facility with capacity to process up to
20mmscf per day of liquified petroleum gas. The proposed facility is expected to have
the capacity to supply LPG gas to customers and shall upscale production to an
optimized throughput capacity of 52mmscfd upon implementation.
Compressed Natural Gas (CNG) is also expected to be produced as well. The inlet
gas shall be sourced from gas feedstock transported from Utorogu Gas Plant via a
pipeline infrastructure to the proposed facility for processing and thereafter primarily
conveyed for bulk shipment via an export pipeline to a jetty location. Products shall
also be dispatched through Product Distribution Trucks (PDTs) from the Facility
Loading Terminal.
1.3 Purpose
The purpose of this document is to report the weekly progress of the project between
14th OCTOBER – 20th OCTOBER 2024 (weekending 20th OCTOBER, 2024).
OZM LPMR ZKL PJM SCH 001 Engineering Project PDF IFR
Schedule
OZM LPMR ZKL PJM RPT 003 Pipeline Route Selection PDF IFR
Report
OZM LPMR ZKL PJM XXX XXX XXXXX XXXXX XXXX XXX XXX
6.2 PROCESS
The following tabulated deliverable were issued for Review
Process Basis of
Design(Feed Gas and
OZM LPMR ZKL E00 PRO BOD 001 PDF IFR
Export Gas)
Process Flow
Diagram(PFD)-Overall
OZM LPMR ZKL E01 PRO PDF 001 PDF IFR
Process
OZM LPMR ZKL E01 PRO XXX XXX XXXXX XXXXX XXXX XXX XXX
6.3 PIPELINE
The following tabulated deliverable were issued for Review
OZM LPMR ZKL E00 PPL BOD 001 Pipeline Basis of Design PDF IFR
OZM LPMR ZKL E01 PPL PHI 001 Pipeline Design Philosophy PDF IFR
OZM LPMR ZKL E01 PPL XXX XXX XXXXX XXXXX XXXX XXX XXX
OZM LPMR ZKL E01 PPL XXX XXX XXXXX XXXXX XXXX XXX XXX
7.0 WORK PLANNED (LOOK AHEAD FOR NEXT WEEK,ENDING 20th OCTOBER,
2024)
OZM LPMR ZKL PJM XXX XXX XXXXX XXXXX XXXX XXX XXX
OZM LPMR ZKL PJM XXX XXX XXXXX XXXXX XXXX XXX XXX
OZM LPMR ZKL PJM XXX XXX XXXXX XXXXX XXXX XXX XXX
OZM LPMR ZKL PJM XXX XXX XXXXX XXXXX XXXX XXX XXX
7.2 PROCESS
Issue documents as reviewed by Client/PMC on the deliverables listed below;
OZM LPMR ZKL E01 PRO XXX XXX XXXXX XXXXX XXXX XXX XXX
OZM LPMR ZKL E01 PRO XXX XXX XXXXX XXXXX XXXX XXX XXX
OZM LPMR ZKL E01 PRO XXX XXX XXXXX XXXXX XXXX XXX XXX
OZM LPMR ZKL E01 PRO XXX XXX XXXXX XXXXX XXXX XXX XXX
7.3 PIPELINE
Issue documents as reviewed by Client/PMC on the deliverables listed below;
OZM LPMR ZKL E01 PPL XXX XXX XXXXX XXXXX XXXX XXX XXX
OZM LPMR ZKL E01 PPL XXX XXX XXXXX XXXXX XXXX XXX XXX
OZM LPMR ZKL E01 PPL XXX XXX XXXXX XXXXX XXXX XXX XXX
OZM LPMR ZKL E01 PPL XXX XXX XXXXX XXXXX XXXX XXX XXX
OZM LPMR ZKL E01 COR XXX XXX XXXXX XXXXX XXXX XXX XXX
OZM LPMR ZKL E01 COR XXX XXX XXXXX XXXXX XXXX XXX XXX
OZM LPMR ZKL E01 COR XXX XXX XXXXX XXXXX XXXX XXX XXX
OZM LPMR ZKL E01 COR XXX XXX XXXXX XXXXX XXXX XXX XXX
Days
Document Number Title Transmittal No. Due Date Overdue
PIPELINE 32 0 0 0 0 0 0
TOTAL 362 0 0 0 0 0 0
1 Man-Hours (ZKL) 0 0 0
2 Incident Free Man-Hours (IFMH) 0 0 0
3 Lost Time Injury (LTI) 0 0 0
8 Near Miss (NM) 0 0 0
9 Unsafe Act (UA) 0 0 0
10 Unsafe Condition (UC) 0 0 0
11 Road Traffic Accident (RTA) 0 0 0
12 Community/Security Issues 0 0 0
13 Toolbox Talks/Inductions/Safety Brief 0 0 0
15 Safety Reviews/Studies/Analyses 0 0 0
16 Permit to Work (PTW) 0 0 0
11.0 P
ROPOSED ACTION PLAN / RECOVERY STRATEGIES
14.0 ATTACHMENTS
- Engineering Project Measurement System (Week Ending 20-OCT-2024)
- Updated Master Document Register