The Quantities in this bill are measured off from the As Built
Drawing and other details were read off on site after proper
investigation of the building
ELEMENT NR. 1
SUB-STRUCTURE- ALL PROVISIONAL
D Groundwork
D20 EXCAVATING AND FILLING
ExcavatIion
Top soil to remove vegetable soil for preservation 150mm
A 245 m2 900 220,500.00
average depth
Disposal
Cart away surplus excavated materials away from excavation
E to a temporary spoil heap for reuse. 60 m3 600 36,000.00
Backfilling
Filling with selected excavated materials to sides of
F excavations well rammed and compacted; obtained from site 90 m3 800 72,000.00
spoil heaps
Earthwork
Earthwork Support to sides of excavation exceeding 1m deep,
G 252 m2 0 -
not exceeding 2m between faces.
To Collection 1,174,700.00
Laterite Filling
Filling to make up level over 250mm average thick obtained
N 180 m3 4,500 810,000.00
off site watered and well compacted in 150mm layers.
To Collection 11,453,850.00
Hardcore
Filling to make up levels over 150 average thick; obtained off
A 25 m3 7,500 187,500.00
site.
F. MASONRY/BLOCKWORK
F10 BRICK/BLOCK WALLING
225mm thick vibrated hollow sandcrete blockwall laid in
strecher bond and fixed with cement and sand mortar 1:5 with
B 175 m2 10,500 1,837,500.00
hollow cavity filled solid with weak concrete as blockwork in
substructure.
To Collection 2,943,000.00
COLLECTION
MB/PAGE 1 1,174,700.00
MB/PAGE 2 11,453,850.00
MB/PAGE 3 2,943,000.00
ELEMENT NR. 2
FRAMES
E IN SITU CONCRETE/LARGE PRECAST CONCRETE
E10 IN SITU CONCRETE
Reinforced; concrete Grade 25.5; developing minimum
25.5N/mm2 work strength in 28 days
F Roof beam (2 sides) 300mm high on section 600mm total girth. 35 m2 4,500 157,500.00
ELEMENT NR. 3
UPPER FLOOR
D Bars 10-12mm diameter nominal in suspended floor slab. 2,800 kg 1800 5,040,000.00
ELEMENT NR. 4
STAIRCASE
ELEMENT NR. 5
EXTERNAL AND INTERNAL WALLS
F. MASONRY/BLOCKWORK
F10 BRICK/BLOCK WALLING
225mm thick vibrated hollow sandcrete blockwall laid in
strecher bond and fixed with cement and sand mortar 1:5. on
;
ELEMENT NR. 6
ROOF WORK
CARCASSING
CARPENTRY/TIMBER FRAMING
Sawn hardwood, well seasoned to required quality, treated
with anti-termite treatment solignum or other equal approved
timber preservatives
8mm diameter rods as anchor for wall plate cast into roof
K beam. 70 Nr 500 35,000.00
ELEMENT NR.7
DOORS
L.20 DOORS/SHUTTERS/HATCHES
ENTRANCE DOORS
Natural Anodised Aluminium double swing door with 8mm
clear factory fitted glazing fixed complete with accessories
and iron mongery including assembling of components parts,
plugging and screwing frames to concrete/blockwork.
INTERNAL DOORS
TIMBER DOORS
Flush: Purpose made solid core single leaf, single swing flush
door with full jamb frame, sub-frame and architrave installed
completely with all accessories and iron mongery
GLAZED DOORS
Purpose made slide door with full jamb frame, sub-frame and
architrave installed completely with all accessories and iron
mongery
ELEMENT NR.8
WINDOWS
Burglary Proofing
Burglary proofing with external framing 38 x 38mm square
pipe, internal framing 25 x 25mm square pipe framing; in
strip pattern with slugs built into blockwall, and painted with
gloss paint on;
ELEMENT NR.9
WALL FINISHES
M Surface Finishes
M20 PLASTERED/RENDERED/ROUGH CAST COATINGS
M40 STONE/CONCRETE/QUARRY/CERAMIC
TILING/MOSAIC
Ceramic Tiling; Premium Quality Glazed cushioned edge wall
tiling of approved colour B.S. 1281 bedded in cement mortar
on screeded backing (measured seperately) and pointed in
white cement; internally;
Walls over 300 wide; in size 300 x 150 x 8mm thick; to Walls
E 135 m2 12,500 1,687,500.00
in toilets and kitchen reaching ceiling level
ELEMENT NR.10
FLOOR FINISHES
M40 STONE/CONCRETE/QUARRY/CERAMIC
TILING/MOSAIC
Ceramic Tiling; Glazed cushioned edge floor tiling of
approved colour B.S. 1281 bedded in cement mortar on
screeded backing (measured seperately) and pointed in white
cement; internally;
ELEMENT NR.11
CEILING FINISHES
SURFACE FINISHES
M20 PLASTERED/RENDERED/ROUGH CAST COATING
Render: 19mm thick Cement and Sand (1:4) rendered,
trowelled smooth internally and externally on;
A Soffit of suspended floor slab over 300mm wide. 180 m2 1850 333,000.00
ELEMENT NR. 12
FITTINGS AND FIXTURES ALL PROVISIONAL
Handrail
Wardbrobes
Allow a lumpsum to cover for fabricating and installation of
B HDF wardbrobes in rooms 5 Nr 365,000 1,825,000.00
Kitchen Cabinet
Allow a lumpsum to cover for fabricating and installation of
C HDF with marble top kitchen cabinet 1 Nr 455,650 455,650.00
ELEMENT NR. 13
ELECTRICAL INSTALLATION-ALL PROVISIONAL
MAIN SUPPLY/INSTALLATION
EQUIPMENT AND CONTROL GEAR
Supply and install complete the following including all
necessary fittings; Sum 10,000,000.00
ELEMENT NR. 14
PLUMBING AND MECHANICAL INSTALLATIONS
ALL PROVISIONAL Sum 15,000,000.00
1 SUBSTRUCTURE 15,571,550.00
2 FRAMES 15,051,500.00
4 STAIRCASE 1,732,000.00
6 ROOFWORK 8,815,500.00
7 DOORS 5,134,500.00
8 WINDOWS 8,939,050.00
EXECUTIVE SUMMARY N K
SUBTOTAL 130,155,112.50
SUBTOTAL 131,155,112.50