The Court Cannot Adjudicate On Merits of A Dispute Which Are Under The Ambit of The Arbitrator Even If S
The Court Cannot Adjudicate On Merits of A Dispute Which Are Under The Ambit of The Arbitrator Even If S
The Court Cannot Adjudicate On Merits of A Dispute Which Are Under The Ambit of The Arbitrator Even If S
AP/535/2022
BEFORE:
The Hon'ble JUSTICE SABYASACHI BHATTACHARYYA
Date : 27th June, 2024
Appearance:
Mr. Sakya Sen, Adv.
Ms. Nilanjana Adhya, Adv.
…for the petitioner
Act, 1996 that the petitioner did certain work for the respondent authorities. The
indicated that payment had been made up to the second R/A Bill to the tune of
the parties, in particular Clause 7 thereof, the final bill was to be submitted by
the contractor within a month from the date fixed for completion of the work;
2
total amount payable for the work accordingly shall be final and binding on all
parties. It is contended that in view of such provision, unless a final bill was
drawn and/or prepared and also certified by the Engineer-in-Charge, the cause
of action for claiming the final bill amount did not ripen.
already paid the final value of the work done partially, to the tune of
the security deposit amounting to Rs. 11,44,205/- has not yet been paid to the
petitioner.
Learned Counsel for the petitioner, in support of his contention, cites a co-
ordinate Bench judgment in the matter of M.L. Dalmiya and Co. vs. Union of
India reported at AIR 1963 Cal 277 as well as an unreported judgment of a Co-
ordinate Bench in FMA 1093 of 2013. In the said judgment, the Courts, while
of cases relating to work contracts. It was held in M.L. Dalmiya (supra), inter alia,
that in such cases, it is the duty of the Government after doing the work
certificate is given, the contractor cannot submit his bill and the cause of action
for payment in terms of the contract does not arise. Since the Government did
not intimate its decision in the said case, it was held that the time cannot run
before that date. In the unreported judgment of M/s. Biptrade (supra), in FMA
1093 of 2013, the Court, in similar lines, observed that in course of the
3
It was further held that till the final bill is prepared and the same is
certified for payment, the question of limitation generally does not arise in a
works contract. As such, in the present case, it is argued that in view of non-
grant of certificate by the engineer, the cause of action did not mature until
recently, when the petitioner claimed such amount but the same was not
1996 Act was issued on June 2, 2022, thereby setting the ball rolling in respect
Learned senior counsel appearing for the respondent submits that the
at best, the respondent no. 1 – State and the Superintending Engineer, National
Highway Circle-I could be said to be party to the agreement between the parties.
However, respondent no. 2, the Chief Engineer, P.W.D. and the respondent no.
4, Executive Engineer, National Highway Division No. I, are not relevant parties
at all.
due to dearth of the relevant documents since the petitioner sat tight over the
matter and only became alive to the purported issues after about 20 years. It is
4
paragraph 9 of the application where the petitioner admits that the work was
completed and the final bill was drawn and/or prepared; yet the same was not
paid. Again, in paragraph no. 15 of the application, the petitioner admits that
the cause of action for the claim arose first on July 30, 2000 when the work was
the petition which clearly denotes that the work was completed as long back as
annexed at page 19 of the application from which it is evident that the payment,
even if in part, was made in terms of the final bill raised by the petitioner. Thus,
the same pertains to a long-dead claim and should be nipped at the bud.
that the petitioner has stated in paragraph no. 8 of the application that an
amount was paid in part against the “final value of work done”. It is also stated
that the balance amount along with security deposit refund has not yet been
certificate.
that the respondents had admitted that out of the total order value of
conjunction with paragraph no. 9, the petitioner claims that the part payment
was made against the final value of the work done. However, it is not clarified as
In paragraph no. 9, the petitioner states that although the work was
completed and the final bill was drawn and/or prepared, the same was not paid.
The respondents seek to argue that the drawal of the final bill itself would
show that the cause of action of the present claim arose long back, immediately
after the completion of the work, at least on September 6, 2001 on which date a
between the parties. In the final sentence of the said clause, it is provided that
the final bill shall be submitted by the contractor within one month from the
6
date fixed for completion of the work. It goes on further to stipulate that even
otherwise (meaning thereby that even if such bill was not drawn) the Engineer-
in-Charge’s certificate of the measurement and of the total amount payable for
the work accordingly shall be final and binding on all parties. It is not admitted
by the petitioner, nor substantiated at this stage by the respondents, that any
such certificate was issued by the engineer concerned, regarding the total
Insofar as the pleading of the petitioner that a part of the final value of the
work was paid, the same may or may not be linked with a final bill having been
have been made against the R/A Bills or otherwise, before the final bill was
issue.
since it may very well be argued by the petitioner that until and unless a
certification was made by the concerned engineer to the final bill raised by the
petitioner, the cause of action for the claim made by the petitioner would not
ripen. If such view is ultimately established, then the bar of limitation would be
effaced.
7
issued a certificate regarding the total amount payable, in such event, definitely,
and Conciliation Act, 1996, to adjudicate even prima facie on the merits of an
arguable issue involved in the matter, which would fall categorically within the
limitation, the Court sitting under Section 11 cannot decide the same
In such view of the matter, taking into consideration all aspects of the lis,
conclusively decided ex-facie on the materials available before the Court and/or
arbitration.
Even otherwise, the scope of the dispute falls within the ambit of the
arbitration clause in the agreement between the parties and the dispute is
Narayan Rai, Advocate (Mobile No.: 98749 58601) as the sole Arbitrator to
resolve the disputes between the parties, subject to a declaration being obtained
8
under Section 12 of the 1996 Act from the said learned Arbitrator. The
with the provisions of the 1996 Act read with its Schedules. It is clarified that all
issues are kept open for being adjudicated by the learned Arbitrator and the
merits of none of the issues have been entered into by this Court in any manner
whatsoever.
S.Bag/sg/sp/b.pal