HT Cable Testing Procedure

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 5

Document No.

Solution Centre India


SE-SCI-CON-S-54 Design & Engineering Procedure
Revision No. 00
Department – Design & Engineering
Date: 01/01/2013

HT CABLE
1.0 Introduction
The following test procedure has been prepared for the testing and commissioning of
the HT Cable at ……………………………………………. project India.
All Testing and Commissioning documentation must be produced in accordance with all
relevant codes of practice of India and international standard.

2.0 Test Equipment


The following test instrumentation & tools will be required to undertake the tests
details.
A Megger (5 KV)
HV Test Kit (dc or ac) along with leakage
B
current measuring instrument

3.0 Testing and Commissioning


 The installation of equipment is substantially complete, and is live. Equipment
and System Testing and Commissioning documentation must be provided to
verify the following tests and inspections have been carried out.
 All testing and commissioning documentation, including manufacturers
recommended procedures, shall be supplied to the commissioning management
team to confirmed
 Wear insulating gloves. Perform the discharge and grounding of the circuit at the
conclusion of each test.
 The following steps shall have been carried out:

CAUTION: - Hard copy of this document is for information purposes only. The content of the procedures
may be changed with out notification. The controlled procedures are those only on the SCI server. P1 of 5
Document No. Solution Centre India
SE-SCI-CON-S-54 Design & Engineering Procedure
Revision No. 00
Department – Design & Engineering
Date: 01/01/2013

4.0 Visual Checks – General.

 Visual checks for physical installation against Approved drawings.


 Check the Equipment ratings are in accordance with the approved working
drawings
 Check general construction and standard of finishing are acceptable.
 Check leveling and alignment are correct and acceptable.
 Check equipment properly mounted as per manufacturers recommendations,
 Check ear thing bar and connections are provided and correct.
 Check bolts, nuts, screws etc for supports, insulators and connections have been
tightened correctly and torque tightened where applicable.
 Check operating handles and keys c/w mounting cabinet have been provided.
 Check rubber insulating mats have been provided to front and rear of panels.
 Check ‘As Built’ record schematic diagrams have been installed in the room. The
schematics to be framed and wall mounted.
 Check operation sequence instructions have been provided for interlock facilities

CAUTION: - Hard copy of this document is for information purposes only. The content of the procedures
may be changed with out notification. The controlled procedures are those only on the SCI server. P2 of 5
Document No. Solution Centre India
SE-SCI-CON-S-54 Design & Engineering Procedure
Revision No. 00
Department – Design & Engineering
Date: 01/01/2013

5.0 Commissioning Tests

5.1 Insulation Resistance Test (IR Value)

5.1.1 Circuit Diagram:

5.1.2 Procedure:

An ‘Insulation Resistance’ (IR) or ‘Megger’ test can ensure that the insulation between
isolated conductors will remain a resistance that limits the flow of leakage current to an
acceptable value where high voltage is applied. Typically, the acceptable leakage current
for an electrical product is defined in standards published by a governing safety agency.
The objective of the IR test is to ensure that the cable, cord or component is suitable:-
[A] For safe use by an end user
[B] For correct performance when installed into the product or operating environment

Typically, IR testing is conducted at voltages above 250V DC. The test fails when the
product’s insulation resistance falls below the acceptable limit while a test voltage is
applied for a specific time period. IR failure typically occurs well before an arc between
conductors occur

5.1.3 Test Report:

Before HV Test After HV Test


Description
(GIGA OHM) (GIGA OHM)
“R” Ph to Earth
“Y” Ph to Earth
“B” Ph to Earth

CAUTION: - Hard copy of this document is for information purposes only. The content of the procedures
may be changed with out notification. The controlled procedures are those only on the SCI server. P3 of 5
Document No. Solution Centre India
SE-SCI-CON-S-54 Design & Engineering Procedure
Revision No. 00
Department – Design & Engineering
Date: 01/01/2013

5.2 High Voltage Test

5.2.1 Circuit Diagram:

5.2.2 Procedure:

For this test a high voltage test kit is used. The line terminal of the high voltage test kit is
connected to the HT Cable & the earth terminal of the test kit is earthed.
For dc, the minimum voltage is 1.5 times the rated voltage & for ac the minimum
voltage is 1.2 times the rated voltage

5.2.3 Testing Report:

Description Applied Voltage(KV) Leakage Current (mA)


“R” Ph to Earth
(Y+B+Earth)
“Y” Ph to Earth
(R+B+Earth)
“B” Ph to Earth
(R+Y+Earth)

CAUTION: - Hard copy of this document is for information purposes only. The content of the procedures
may be changed with out notification. The controlled procedures are those only on the SCI server. P4 of 5
Document No. Solution Centre India
SE-SCI-CON-S-54 Design & Engineering Procedure
Revision No. 00
Department – Design & Engineering
Date: 01/01/2013

6.0 RECORDS

 HT Cable Test Report


 Pre Commissioning Check List
 Loto Check Sheet
 Energizing Protocol

7.0 DOCUMENT CONTROL

Revision No Revision Date Changes Prepared By Reviewed By Approved By

00 Original HOD Head-BPE GM-


Release Construction Operations