66 - 230 - 400kV Guidelines 9.1
66 - 230 - 400kV Guidelines 9.1
66 - 230 - 400kV Guidelines 9.1
ABOVE GROUND
TRANSMISSION SUBSTATION BUILDINGS
(For 400kV, 230kV &66kV Standalone Substation only)
Date Issued:
1. GENERAL INFORMATION.................................................................................. 1
1.1 Introduction .................................................................................................. 1
1. GENERAL INFORMATION
1.1 Introduction
1.1.2 The Developer and / or Consultant and their Project Team of Architect and
Professional Engineers are fully responsible for the design and supervision of
construction of the substation building, including all costs for the substation
development.
1.1.3 The Developer's / Consultant's Project Team shall be familiar with all latest
procedures for submission of plans to local Authorities e.g. Building and
Construction Authority (BCA), Fire Safety & Shelter Department (FSSD),
Energy Market Authority (EMA), Ministry of Home Affairs (MHA), etc. The
design and construction of the substation building shall fully meet all
conditions / requirements imposed by all relevant Authorities including EMA /
MHA for security measures.
1.1.4 The Developer’s / Consultant’s Project Team shall follow the Ministry of
Manpower (MOM) and Workplace Safety & Health (WSH) Design for Safety
Guidelines and Building and Construction Authority (BCA) Design for
Maintainability Guidelines.
Edition 9.1
1
400KV, 230KV & 66KV SUBSTATION INTRODUCTION
1.1.6 In the event that the substation is classified as a Critical Infrastructure, the
Developer / Consultant shall engage a Security Consultant with expertise in
blast engineering analysis as part of the Project Team. The appointed
Security Consultant must be familiar with the latest “security by design” (SBD)
process and/or latest security requirements / framework as per directive
issued by EMA / MHA. The Security Consultant shall develop a formal
security plan to address the risks and threats identified. The draft security
report must be submitted and presented to SPPG for clearance two weeks
before formal submission to EMA. Submission of the drawings/documents
for MHA’s approval shall be done by the Security Consultant through EMA /
SPPG / Developer. The Project Team shall fully comply and complete the
SBD process before submitting the substation plans to SPPG for final
endorsement.
1.1.7 The aim of providing the Guidelines / Requirements for Above Ground
Transmission Substation Buildings is to share with the Developer's /
Consultant's Project Team as much information as possible at this early stage
of time on SP PowerGrid's (SPPG’s) current specifications of transmission /
distribution equipment and other functional requirements as required by SP
PowerGrid (SPPG). Our requirements / comments are not complete and do
not include all the conditions / requirements imposed by all relevant
Government and Statutory Authorities.
1.1.9 Developer / Consultant / Project Team shall check with SPPG for any further
new / revised requirements to be incorporated before tender action,
especially for Design & Build (D&B) contract. Developer / Consultant shall
bear all costs related to the new / revised requirements if the Architectural
and Mechanical & Electrical (M&E) drawings are not endorsed by SPPG
before their tender. The costs shall also include measures to comply with
new / revised requirements / conditions of all relevant Authorities. For D&B
contract where construction is in progress concurrently with design, any
variation in design due to new / revised SPPG’s functional and / or “security
by design” (SBD) requirements shall be fully complied with and all cost
variation shall be fully absorbed by the Developer / Consultant if the
Architectural and M&E drawings are not endorsed by SPPG before
construction.
Edition 9.1
2
400KV, 230KV & 66KV SUBSTATION INTRODUCTION
e) Proper and adequate access, with the usage of swept path analysis, to
the site must be available for cable installation and transportation of heavy
equipment by normal means (i.e. truck and trailer). [The slope (if any) of
the access road shall not be steeper than 1:20]
Edition 9.1
3
400KV, 230KV & 66KV SUBSTATION INTRODUCTION
1.1.12 The Developer / Consultant and Project Team are to note that the proposed
substation development of substation project is classified as “Special Facility”
under PUB’s Code of Practice and its design shall comply with the Code.
1.1.13 Any Customer / Developer who require electricity for development / upcoming
development must submit their Supply Application through their Licensed
Electrical Worker (LEW) to SP Services Ltd. All customers are required to
enter into a Consumer Connection Agreement with SPPG and to pay for the
charges.
1.1.14 The Developer / Consultant shall ensure that all requirements shown in the
'Guidelines / Requirements for Above Ground Transmission Substation
Buildings' are fully reflected in the building, M&E and other relevant tender
documents prepared by the Developer's / Consultant's Project Team of
Architect and Professional Engineers.
1.1.15 The Developer / Consultant / Project Team must immediately highlight and
consult SPPG on any deviation from the requirements as stated in the
Guidelines / Requirements for Above Ground Transmission Substation
Buildings Handbook prior to their tender exercise. Failing which, should such
deviations affect substation functional requirements, the Developer /
Consultant has to resolve the issue to the satisfaction and clearance of
SPPG. Any cost incurred in so doing shall be borne by the Developer /
Consultant.
1.1.16 The Developer shall obtain the list of contractors for Command & Control
(C2) from SPPG prior to tender stage.
1.1.18 For addition and alteration modification work, additional requirements which
include provision of temporary control room with mechanical and electrical
installation including air con as well as building works shall be inclusive,
where required.
1.1.18.1 During the duration of addition and alteration modification work, ESCS
systems (C2 MAN / AMI / Internal Telephone) must be continuously
operational. The Contractor has to maintain the operational and
environmental requirements to ensure that the ESCS systems are functioning
normally. Any diversion of power supply (including UPS, if any) or any cabling
that are required to ensure the functionalities of ESCS systems shall be
included in the scope of work.
Edition 9.1
4
400KV, 230KV & 66KV SUBSTATION INTRODUCTION
1.1.18.2 For addition and alteration modification work, if relocation of ESCS racks is
required, all works are deemed to be included in the scope of work. The
system shall be fully tested and commissioned after the relocation. Installation
of new equipment racks are encouraged for all relocation works of the ESCS
racks so as to minimise the downtime for ESCS operation.
1.1.19 The water meter should be fenced up with separate gate for meter reader but
still within the substation boundary. This is to facilitate SP Services officer to
check the water meter readings without entering the substation. Refer
Appendix E for Proposed Water Meter Location
Edition 9.1
5
400KV, 230KV & 66KV SUBSTATION DESIGN DEVELOPMENT PHASE
2.1.1 All architectural, civil & structural, building services including building M&E etc
designs, are to comply fully with latest requirements of local Authorities,
e.g. FSSD, BCA, PUB, NEA etc.
2.1.2 The Developer / Consultant shall demonstrate to SPPG that the latest
requirements of local Authorities e.g. FSSD, BCA, PUB, NEA etc. are met.
2.1.4 The Developer / Consultant shall study all environmental issues including
acoustic impact and recommend suitable mitigation measures. They shall at
their own cost, engage an Acoustic Specialist as part of their Project Team to
carry out acoustic reviews on the substation, ensuring that the building
design comply with the latest NEA’s requirement on noise limits. The Team
shall assume that all transformers and MV system are in operation at the
same time while SPPG will provide noise data from the transformer OEM/s
for the simulation studies.
2.1.5 The Acoustic specialist engaged shall be well established with sufficient
project track records. Recommendation of the Acoustic Specialist shall be
reviewed and accepted by SPPG.
Edition 9.1
6
400KV, 230KV & 66KV SUBSTATION DESIGN DEVELOPMENT PHASE
2.1.7 The EMF Professional shall carry out risk assessment, computer simulations
etc on EMF emission from equipment (e.g. switchgear, shunt reactor,
transformer and power cables) on human safety and report on any health
hazards and issues of concerns associated with the levels of electric and
magnetic fields in relation to the limit of exposure. The EMF Professional
shall recommend and implement suitable mitigation measures if the derived
values exceed allowable limits stipulated in the guidelines from the
International Commission on Non-Ionizing Radiation Protection (ICNIRP) and
SPPG’s requirements. A reference level of 100 µT (microtesla) for general
public exposure to electromagnetic field at power frequency (50Hz) is
recommended by ICNIRP. All cost incurred shall be borne by the Developer /
Consultant.
2.1.8 The Developer I Consultant shall allow sufficient time in the design stage for
obtaining:
2.1.9 The Developer / Consultant / Project Team shall check with SPPG, if waivers
arising from SBD’s recommendation such as omission of vision panels from
the ground level doors of the substation, Firemen Access Panels, ‘Fail-
secure’ system setup of EM locks on ingress / egress points located on the
ground level access points etc. are required from relevant Authorities.
Incorporation of SBD’s requirements or application for waivers shall be done
early in the Design Development Phase at the cost of Developer / Consultant.
2.1.10 Together with the first submission plans to SPPG, the Developer / Consultant
/ Project Team shall provide a copy of MPC approval of the substation
development for SPPG’s record.
2.1.11 All critical or emergency M&E and Fire Protection equipment and its spare
parts shall be easily available, if otherwise, the Vendor shall make sure the
recommended equipment installed have approved alternatives that are easily
available.
Edition 9.1
7
400KV, 230KV & 66KV SUBSTATION DESIGN DEVELOPMENT PHASE
2.1.12 For 1st and subsequent submission, the drawings must be submitted to
SPPG with reference to the distribution list obtained for clearance on the
functional requirements prior to tender action as follows:
a) Architectural
b) Structural
Plans showing the locations and sizes of all beams, columns and floor
openings
c) Electrical
d) Any other relevant details which may affect the installation and
maintenance of SPPG's equipment.
f) Fire Protection
Plans showing the locations of all water sprinkler points, smoke / heat
detectors, clean agent discharge nozzles, fire alarm panels, fire pump
room layout and routings. Single-line schematic diagram of control
panel wiring (showing details of rating, zoning, capacity, type of
components, etc) and hydraulic calculations.
2.1.13 Developer / Consultant / Project Team shall comply fully with all requirements
as stipulated in the Guidelines / Requirements for Above Ground
Transmission Substation Building.
2.1.14 For subsequent submissions, all revisions made on drawings for subsequent
submission shall be highlighted in bright colour (preferably yellow) or
clouded.
Edition 9.1
8
400KV, 230KV & 66KV SUBSTATION DESIGN DEVELOPMENT PHASE
2.1.15 All drawings submitted to SPPG for final approval of functional requirements
must be duly endorsed by the Developer's / Consultant's authorised officers
(Professional Architect, Licensed Electrical Worker [Engineer's Grade] and
Professional Engineer of all Mechanical & Electrical, Civil & Structural
Installation System) prior to tender action.
2.1.17 The Developer / Consultant shall also extend to SPPG one set of final hard
and soft copies drawings which is identical to the sets that are submitted to
the Master Planning Committee / Chief Planner and the Building and
Construction Authority.
2.1.18 All necessary signatures and endorsements that are required by the
authorities shall also be duly affixed on the SPPG's set by the authorised
officers concerned.
2.1.19 Developer / Consultant is required to check with SPPG for any further new /
revised requirements to be incorporated prior to their tender action. Cost
shall be borne by Developer / Consultant for new / revised requirements prior
to the clearance of tender plans / endorsed plans.
2.1.21 Developer / Consultant shall carry out Building Information Modelling (BIM)
subject to the prevailing BIM requirements by local Authorities and SPPG.
Edition 9.1
9
400KV, 230KV & 66KV SUBSTATION MECHANICAL AND ELECTRICAL REQUIREMENTS
3.1.2 All emergency light fittings shall be provided with self-contained battery
pack which shall be integrated together with the normal supply subject to
relevant authorities’ approval.
3.1.3 Self-contained battery back emergency supply system for the emergency
lighting supply shall be rated for 2 hours minimum.
3.1.4 All emergency light fittings shall be clearly labelled and comply with the
following:
Edition 9.1
10
400KV, 230KV & 66KV SUBSTATION MECHANICAL AND ELECTRICAL REQUIREMENTS
3.1.7 Emergency Diesel Generator comes with skid tank as whole unit shall be
preferred to be used to save day tank space and minimise the risk of fuel
leakage along the pipes / tubes. If the designed diesel capacity is too
much where the Emergency Diesel Generator (with skid tank) cannot be
met, the preferred shall be Emergency Diesel without skid tank used and
would purely relied on the diesel day tank.
3.1.8 The Emergency Diesel Generator shall have the essential system fault
detection capabilities (e.g. leakage detection, high temperature detection,
battery charger fault, battery fault, low level diesel level etc.).
3.1.9 The Emergency Diesel Generator exhaust pipe shall be of brand new set
instead of re-conditioned set and shall have the shortest external route to
the external of the room.
3.1.11 The design for the capacity of the diesel tank is preferred to be kept below
1500 litres if possible.
3.1.12 If fuel tube is to be used near the termination point, it shall be of fire
resistant (time is depending on the design it is used to support for those
emergency services / load), or steel braided material.
Edition 9.1
11
400KV, 230KV & 66KV SUBSTATION MECHANICAL AND ELECTRICAL REQUIREMENTS
3.2.1 An illumination of average 300 lux is required for the following rooms:
a) All switchrooms
e) Lift Shaft
3.2.2 An illumination of average 500 lux is required for the following rooms:
a) Control room
b) Communication room
3.2.3 External lighting for the substation building and security lighting of
approved design / type within substation compound shall be controlled by a
time-switch or other approved method. Light fittings shall be accessible by
maintenance personnel. They shall be located or wall-mounted at
approved locations.
3.2.4 Unless otherwise specified, all illumination shall be complied with the
Singapore Standard (SS) latest Code of Practice:
Edition 9.1
12
400KV, 230KV & 66KV SUBSTATION MECHANICAL AND ELECTRICAL REQUIREMENTS
3.2.5 All light fittings shall be provided with LED type (both sides live/neutral)
with minimum 50,000 burning hours.
3.2.6 For the lighting system that is running 24 hours a day, 7 days per week, all
the time or 12 hours and more per day, the light fitting shall be provided
with LED type.
3.2.7 All light fittings installed outside building shall be weather-proof (IP65).
3.2.8 Locations of all fittings shall be easily accessible for use and maintenance.
The outgoing and incoming cables of minimum 1 loop length to be placed
within the lighting junction box. Switches shall be located beside the door
opening entrances of each room. Proper engraved labelling from DB to
individual switches shall be provided.
3.2.9 Approved light indicator switches for lights with two or more ways ON /
OFF switching system shall be used.
3.2.11 All main switches controlling the lighting shall be installed beside the door
opening entrances of the following areas:
b) Control Rooms
3.2.12 The schematic layout of fittings, power points, etc shall be shown in the
drawings. Substation lighting and power circuits shall be controlled by
distribution units with main switches and MCB facilities to authorities'
requirements. Calculations shall be furnished to SPPG for review.
3.2.13 The Developer / Consultant shall include the supply and installation of LV
cables between the building main switchboard (provided by the Developer /
Consultant) and SPPG's LV board in his contract. The LV cables shall be
of the following standard type used by SPPG:
Edition 9.1
13
400KV, 230KV & 66KV SUBSTATION MECHANICAL AND ELECTRICAL REQUIREMENTS
3.2.16 All substation wiring shall be run in trunkings, cable trays or exposed triple
layer coated GI conduits.
3.2.18 All power sockets shall be protected with approved RCCB unless otherwise
specified. Please do not position any power socket or other switches
behind narrow auxiliary floor openings which are located close to walls.
3.2.23 Nameplates of laminated sandwich type having black surfaces and white
core with description “Substation Building Main Switchboard” shall be
installed on the said board.
3.2.24 All other sub-main boards shall be properly labelled with similar
nameplates.
3.2.25 All power sockets and switches shall be labelled with similar nameplates to
indicate their respective distribution boards.
3.2.26 The cables or wirings for emergency services (e.g. mechanical ventilation
fans, air cons, fire shutter, fire alarm, fire sprinkler, perimeter lightings etc.)
shall be of fire resistance type.
3.2.27 Insulation mat shall be provided for all main switch board, LV board etc.
(front and back).
Edition 9.1
14
400KV, 230KV & 66KV SUBSTATION MECHANICAL AND ELECTRICAL REQUIREMENTS
3.2.28 All electrical wiring shall be labelled at every passing structure hole and
termination point for ease of visible tracing.
3.2.29 All control panels shall come with lamp test capability, a clear panel door
and key lock to prevent easy access to the control by unauthorised
personnel.
Edition 9.1
15
400KV, 230KV & 66KV SUBSTATION MECHANICAL AND ELECTRICAL REQUIREMENTS
3.3.2 The earth electrode resistance measured at each inspection pit shall have
earthing resistance value of less than ten ohms.
3.3.3 The lightning lead down conductor together with the conductor tape clip is
recommended to be concealed in the building wall. The down conductor
(copper tape) shall ensure a low impedance path for the lightning
discharge. Provision shall be made to prevent concrete spalling / damage
after discharge of lightning. The test clamp shall be located at 1.5m above
ground level.
3.3.4 The inspection pit shall be of IP65 and above, it shall also be of heavy duty
type.
3.3.5 The inspection label shall show the last inspected date, next inspection
date and the ohm reading.
3.4.1 Substation earthing protection system shall comply with all local
regulations and authorities requirements, including the Code of Practice
SS551 – Code of Practice for Earthing (latest edition) and IEEE Standard
80 – IEEE Guide for Safety in AC Substation Grounding.
3.4.2 Substation earthing system shall be designed to withstand fault currents of:
a) 80kA for 1 sec for 400kV substations (or 50kA for 3 sec whichever is
more stringent),
b) 63kA for 1 sec for 230/66kV substations (or 50kA for 3 sec whichever is
more stringent) and
3.4.3 Developer shall provide substation earthing system and submit its design
to SPPG for acceptance before substation building tender stage at their
own cost. SPPG Site Engineer-in-charge’s approval shall be secured prior
to the commencement of earthing grid and system installation.
Edition 9.1
16
400KV, 230KV & 66KV SUBSTATION MECHANICAL AND ELECTRICAL REQUIREMENTS
3.4.5 Developer shall rectify any deficiency or defects of the substation earthing
system at its own cost, subject to SPPG’s acceptance.
3.4.6 All earth conductor temperature shall not exceed 200 degree Celsius after
conducting the fault current for bolted type, insulated type or embedded in
the wall. The magnitudes of fault currents shall take into consideration
when sizing the earthing conductor. Other requirements such as
mechanical strength, etc shall also be considered. The earthing conductor
size shall be at least 600mm² (e.g. by using 2x300mm² copper tapes). All
earthing conductors shall be soft drawn tinned copper tape. Stranded
copper cable length shall be minimise where practical and where flexibility
of complex bending necessitates it, subjects to SPPG ’s approval.
Earthing conductor conducting the main fault current for 400kV, 230kV,
66kV and 22kV equipment shall be of tape type, unless it is precluded due
to installation constraint. All joints between earthing conductors shall be by
means of exothermic welding, subject to SPPG’s approval. Equipment
earthing tie-in points to earthing conductors provided by substation shall be
located at the ground level.
3.4.7 The earthing conductor of not less than 2x300mm² shall run to various
floors and shall loop, if applicable, in the form of ring circuit with
interconnecting earthing tapes to the earthing bars provided by the
Developer in each floor. A minimum of six vertical risers through every
floor of each 400kV & 230kV, 66kV and 22kV substation respectively. The
Developer shall provide and install earthing bars at all switchrooms (e.g.
400kV, 230kV, 66kV and 22kV and all cable chambers), relay room, control
rooms, communication rooms, battery rooms, charger rooms, L.V. rooms,
supervisory control rooms, and the like.
3.4.8 The ‘SP GROUP’ label and logo shall be stamped on all earthing bars at
30cm intervals.
Edition 9.1
17
400KV, 230KV & 66KV SUBSTATION MECHANICAL AND ELECTRICAL REQUIREMENTS
3.4.9 The depth of burial of the earthing grid conductors shall be at 3 metres
from the ground level, or 0.5 metres clear from ground beam / structure if
deeper than 3 metres from ground level.
3.4.10 Four (4) earthing inspection pits at 20 metres interval along each side of
substation building shall be provided. The pits shall be corrosion proof and
able to withstand heavy vehicle loading of minimum 5000kg and each
earthing inspection pit shall directly linking to the main earth grid.
3.4.12 The main earth conductor in first storey linking to the main earth grid and
between earthing bars shall be tinned copper tapes.
3.4.14 All earthing bars shall have at least 12 holes and mounted on insulators.
Final locations of the earthing bars and inspection pits in the various
rooms, transformer / NGR bays, etc shall be subject to SPPG’s site
engineer’s approval.
3.4.15 Suitable of size earthing mesh or BRC embedded in concrete floor screed
layer shall be provided at MV, HV and EHV equipment rooms and cable
floors and cable termination floors (e.g. 400kV, 230kV, 66kV and 22kV
switch board rooms and cable floors) shall be connected to the earthing
bar of the respective floor to ensure safety of personnel against step and
touch voltage during electrical fault conditions.
3.4.16 If the roof trusses are directly on top of the switchrooms and are internally
exposed, the complete roof trusses shall be suitably earthed.
3.4.17 If the earth potential rise voltage due to fault current exceeds the Tolerable
Step and Touch Voltage of a 50kg human on wet concrete / ground (as
defined in IEEE Standard 80), isolating element 600mm long UPVC pipe
spool with 2 times each potential rise voltage rating shall be installed near
to the substation boundary to electrically isolate all electrically conductive
pipes connecting between the substation and external installation. All
boundary fences, gates, external firefighting water tanks, fire-fighting
sprinklers pipes etc. shall also be adequately earthed locally separately
from substation earthing system for the safety of personnel and to the
public.
Edition 9.1
18
400KV, 230KV & 66KV SUBSTATION MECHANICAL AND ELECTRICAL REQUIREMENTS
3.5.2 Lifting hoist shall be provided where equipment are located at upper
storeys of a multi-storey substation building. The building can be so
designed that only one hoist is required for various equipment. In such
case, lifting hoist of the greatest capacity and clearance height required
shall be used.
3.5.3 The following table shows the type and capacity of lifting hoists required for
respective switchgear / transformer equipment:
Edition 9.1
19
400KV, 230KV & 66KV SUBSTATION MECHANICAL AND ELECTRICAL REQUIREMENTS
3.5.4 The minimum clearance height of crane & hoist shall be at least 1000mm
from the finished floor level to the underside of crane / hoist hook when the
wire is fully extended.
3.5.5 The remote control "pendent" of crane & hoist shall also include the
"EMERGENCY STOP" and "RESET" buttons. The control "pendent" shall
hang-down to about one metre above floor level. Wall-mounted holder for
the control "pendent" shall be provided.
3.5.6 For hoist & crane, the overload and other trip contact reset switches are to
be brought to 1.2m above switchgear floor or maintenance platform level
and to be housed in a lockable control box with locks and 3 nos. of keys
provided. Control and reset electrical devices installed near the moving
hoist and crane motors are not acceptable. All hoist shall be installed with
lightning surge arrestor. Any outdoor hoist shall be installed with ultra
sonic bird deterrent devices at the strategic location suggested by Vendor
or Consultant and approved by SPPG.
3.5.7 All terminations and relays in the control box shall be properly labelled for
ease of maintenance. Circuit diagrams shall be framed next to the control
box.
3.5.8 In addition to the use of a damper to stop the hoist / crane, a limit switch
shall also be installed to cut off the power supply when necessary.
3.5.9 To provide a maintenance platform for crane or hoist of size 2 metres (min)
width x 3 metres (min) length. However, these dimensions should be
measured from the outermost face of any wall / beam / column to the
internal face of the railing. In addition, the size and shape of the
maintenance platform must enable all electrical / mechanical parts of the
crane / hoist to be safely accessible for maintenance purposes. The height
from the maintenance platform to underside of crane / hoist hook shall be
between 1 metre (min) and 1.2 metres (max). The travelling cables of the
proposed crane must be installed on the opposite side of the maintenance
platform for ease of operation.
3.5.11 The hoisting hook block and cable shall be able to park within the
maintenance platform when it is not in use.
3.5.12 Safe Working Load (SWL) to be marked on the beams and labelled on the
hooks of the hoists and cranes.
3.5.13 Professional Engineer (P.E) Sticker to be pasted on the panel and on the
holder for the “Pendent”. Load Test Certificate shall be provided during
handover stage.
Edition 9.1
20
400KV, 230KV & 66KV SUBSTATION MECHANICAL AND ELECTRICAL REQUIREMENTS
3.5.16 Cranes and hoists shall comply with the latest safety requirements from
Ministry of Manpower (MOM).
3.5.17 Double C-channel I-beam is not acceptable for hoisting works using I-beam
trolley.
3.5.18 I-beam must be certified by Authorised Examiner that I-beam is fit for the
lifting of the proposed objects and also that the proposed lifting device can
be safely installed on the I-beam.
3.5.19 All certified cranes and hoists are to be registered under SP PowerAssets
Ltd as a non-notifiable workplace.
3.6.1 Oil interceptors shall be provided adjacent to transformer pits. The oil
interceptor(s) is / are not to be connected to the sewerage system but to
the surface drains via a valve and shall be complied with NEA’s latest
requirements.
3.7.1 All heavy-duty 2-hour fire rated mild steel in galvanised finish roller shutters
or sliding and folding doors shall be provided with both electrical and
manual operations. The overall operations shall be able to operate at floor
level (e.g. using chain, linkages).
3.7.2 All roller shutters or sliding and folding doors shall be designed to
withstand 10-minutes wind speed of not more than 42.5km/h. Wind speed
is to measure on site at different points of the proposed shutter installation
for 10 minutes for all substation near coastlines, offshore stations and
areas with strong winds. After then Consultant and Vendor to counter
proposed the appropriate shutters to be installed subjected to SPPG
approval.
3.7.3 All the electrical control boxes for roller shutters or sliding and folding doors
shall be installed inside the room and lockable with padlock (3 keys shall
be provided to each pad lock).
3.7.4 Chain link shall be provided for opening and closing of the shutter in the
event of a power failure or when the electric motor is defective.
3.7.5 The manual operation must be easy for the operators. (e.g. The distance
for the shutter travel horizontally must be equal or more than the distance
of the pull of the chain)
Edition 9.1
21
400KV, 230KV & 66KV SUBSTATION MECHANICAL AND ELECTRICAL REQUIREMENTS
3.7.6 There shall be no chaffing of the manual chain or linkage to the structure of
the shutter enclosure.
3.7.7 There shall be access panel(s) for maintenance to all necessary parts that
shall be maintained.
3.7.9 The fire shutter shall not be able to open again after it is closed during the
fire alarm activation.
3.7.10 The shutter shall not be able to respond to any control buttons during fire
alarm activation, but only closing mode.
3.7.11 Fire shutter shall be connected to the Fire Alarm Panel and close once fire
alarm is activated.
Edition 9.1
22
400KV, 230KV & 66KV SUBSTATION MECHANICAL AND ELECTRICAL REQUIREMENTS
3.8.2 All fire extinguishers shall have the “PASS” sign mounted on the wall on
top of them.
3.8.3 The provision of portable fire extinguisher shall comply with SS 578 latest
edition “Code of practice for use and maintenance of portable fire
extinguishers”.
3.8.4 Dry Powder fire extinguishers shall be used as the primary extinguisher for
fighting class A and B hazard. They shall be sized and distributed in
compliance with the coverage and reach requirements as stipulated in
SS578. The capacity of each fire extinguisher is preferred not to exceed
9kg. No trolley type fire extinguisher shall be installed unless required by
the authority and left with no other alternative.
3.8.5 Portable carbon dioxide or other approved type of fire extinguishers shall
be provided at prominent locations near switch room entrances or any
other approved locations to supplement the coverage against Class A and
B fire hazards with the electrical and control rooms.
3.8.6 The fire extinguisher inventory label tag shall be installed on the wall above
the location of the fire extinguisher. The fire extinguisher shall be label
with their individual identified inventory number. This is to facilitate the
accounting of fire extinguisher and prevent misplaced.
3.8.8 The clean gas system shall comply with NFPA 2001, latest edition and
shall have the following characteristics:
Edition 9.1
23
400KV, 230KV & 66KV SUBSTATION MECHANICAL AND ELECTRICAL REQUIREMENTS
c) Suitable for use in human occupied rooms, i.e. the gas at its designed
discharged concentration will be safe to human and shall not affect their
visibility that is necessary for evacuation to human in the discharged
room. The clean agent’s thermal decomposition products shall not be
hazardous to humans.
d) The gas is widely used in Singapore and around the world in last five
years.
3.8.9 The Vendor shall conduct an actual discharge test after the completion of
the fire suppression work to ensure the system is functioning properly and
meet the requirement.
3.8.10 The suppression cylinder shall be installed on the floor that can hold its
weight.
3.8.11 The pressure resulted from the activation of the cylinder shall not damage
any equipment, items or structures in the protected room.
3.8.12 The cylinders shall be housed in fire rated compartment with bricks and
door for accessibility for maintenance and replacement.
3.8.13 The Sprinkler system shall comply with Fire code latest edition and CP 52
latest edition.
3.8.14 The Developer / Consultant shall provide and design a sprinkler water
storage tank with a proper fire pump room capable of pumping sufficient
water to the interfacing pipe connections located at each end of the
transformer bay with automatic deluge system. The automatic deluge
system shall be designed and installed in accordance with the latest edition
of Singapore Standard CP 52 Code of Practice for Automatic Fire Sprinkler
System and NFPA 15 – Standard for Water Spray Fixed Systems for Fire
Protection based on the followings:
Note: Maximum area of operation refers to the total surface area of the
transformer to be protected. The size of transformer is approximately 13m
Length x 6m Width x 6m Height for 400kV and 230kV transformers and 6m
Length x 4.5m Width x 4m Height for 66kV transformers. Latest available
transformer size shall be requested from SPPG before the design stage.
3.8.15 The Developer / Consultant shall provide the followings:
Edition 9.1
24
400KV, 230KV & 66KV SUBSTATION MECHANICAL AND ELECTRICAL REQUIREMENTS
c) Size the sprinkler pumps for the furthest Transformer Bay based on the
highest flow rate and pressure loss
3.8.16 The Developer / Consultant shall also provide primary and secondary
power supplies to ensure that the water sprinkler system at the transformer
bay be able to operate at all times even when there is a power failure. The
system shall fully comply with CP 52 and Public Utilities (Water Supply)
Regulations (Latest Edition) for the security and maintenance of the water
tanks.
3.8.17 The sprinkler system shall also serve and protect the covered driveway
adjacent to the transformer bays and sprinkler pump room. The deluge
valves serving each transformer bay shall be located outside of the
transformer bay. The valve signal shall be monitored by MAP / SAP.
3.8.18 The deluge system for the transformer bay shall be activated upon fire
detection by the sprinkler bulb head. The type of sprinkler bulb head used
shall be designed and calculated by the Developer / Consultant.
3.8.19 The deluge system for the transformer bay shall be activated upon fire
detection by the sprinkler bulb head. The type of sprinkler bulb head used
shall be designed and calculated by the Developer / Consultant.
3.8.20 The water discharge pipe of the deluge system shall be discharge into the
transformer bay.
3.8.21 The design of the pipe layout (especially the distance between the pipe
and the surface of the transformer) after the deluge valve shall be checked
and verified by SPPG on top of compliance with CP 52.
3.8.22 The supporting brackets and structure for the sprinkler pipes after the
deluge valve shall not contact the transformer and its supporting structure.
3.8.23 Sprinkler tanks are to be installed with pilot operated ball float valves where
the pilot control mechanism / valves with the control mechanism outside
the tanks (material shall be of corrosion resistance type). The sprinkler
water tank shall also come with heavy duty steel caged cat ladder and a
localised standing platform with side railings for the future access of access
panels.
3.8.24 The top of firefighting water tank shall be barricade along the perimeter to
prevent workers from falling.
Edition 9.1
25
400KV, 230KV & 66KV SUBSTATION MECHANICAL AND ELECTRICAL REQUIREMENTS
3.8.26 The water tank cover and its top material shall be of that allows working
personnel to walk pass. There shall be a red float indicator in the water
level indication tube. Capacity of the water tank shall be labelled on the
water tank.
3.8.27 The discharge line of the sprinkler system shall be returned to the water
tank to save water during maintenance or testing. Water tank shall come
with a Vortex Inhibitor.
3.8.28 In the event that the building is to be designated as a sprinkler building, the
cable floor shall be designed to be served by automatic deluge system.
3.8.29 Manual call point shall have provision of a second protective lid. Call
points exposed to weather or outdoor shall be weather proof type.
3.8.30 Fire alarm bell exposed to weather or outdoor shall be weatherproof type.
3.8.31 Hose reels shall be provided throughout the station except all the
equipment rooms (e.g. switchrooms, control room, battery room, battery
charger room, communication room, LV switchroom etc). The hose reel
and dry riser system shall comply with SS575 latest edition. Developer /
Consultant / Project Team shall obtain the necessary approval from FSSD
and to propose alternative solution if necessary.
3.8.32 Hose reel, standby fire hose, breeching inlet and fire extinguisher shall be
placed inside a knob type steel cabinet / box. For hash environment, for
example substations near to sea or industrial areas, stainless steel cabinet
/ box for hose reel, standby fire hose, breeching inlet and fire extinguisher,
is required.
3.8.33 Hose reels and breeching inlet shall be labelled with the last service date,
next servicing date, name and signature of the maintenance worker.
3.8.34 The cabinet / box shall be a full enclosure with no water seeping into it.
3.8.36 Hose reels pipes, hydrant pipes and sprinkler pipes shall be painted red in
accordance with the standard of painting work. The direction of the water
shall be painted in white. The labelling of the pipe “Hydrant”, “Hose reels”,
“Sprinkler”, etc shall be painted in white.
3.8.37 The pipes in the PUB incoming bulk chamber shall be painted and label to
indicate their services.
Edition 9.1
26
400KV, 230KV & 66KV SUBSTATION MECHANICAL AND ELECTRICAL REQUIREMENTS
3.8.39 Pressure vessel for hose reel system must have pressure gauge to
indicate the pressure of the vessel. Label on the threshold pressure of the
vessel must be pasted on the vessel.
3.8.40 No stickers shall be used for all external equipment, pipe, items, etc.
3.8.41 There shall be check valve installed before the sprinkler wet breeching
inlet.
3.8.42 If required by Fire Safety & Shelter Department (FSSD), suitable detectors
may be installed at approved locations. Smoke detectors shall be installed
in controlled environment like air-conditioned Battery Charger, Control and
Communication rooms. Heat detectors shall be installed in dusty
environment such as cable basement, cable floors and corridor. Fibre
optic linear heat detection system shall be installed at areas with high
ceiling (more than 5-metre height) such as switchgear room, NGR,
transformer and other locations where applicable. Fibre optic linear heat
detectors cables and controller shall design to last for 30 years. Supplier to
substantiate with proper documentation from manufacturer to substantiate
the life span. Smoke or heat detectors shall not be installed on high
ceilings of switchrooms, transformers and other locations where applicable.
Smoke detectors shall be photoelectric sensor based type. Each Linear
Heat Detector zones shall have a loop with protection box at human height
level for future maintenance testing
3.8.43 All detectors must have LED for self-checking purpose. When alarm is
activated, the affected detector must be easily identified.
3.8.44 All detectors below the raised floor must be indicated on the raised floor
permanently with non-faded coating. Raised floor detectors shall be
installed near to the raised floor height instead at the low height nearer to
the floor slab, to have an early response activation time from fire smoke.
3.8.45 All type of detectors is to come with the maintenance and testing kit /
equipment.
3.8.47 The end of line shall be indicated on the zone chart and on the detectors.
3.8.48 The detectors shall be labelled with its zones and numbers.
Edition 9.1
27
400KV, 230KV & 66KV SUBSTATION MECHANICAL AND ELECTRICAL REQUIREMENTS
3.8.50 The Main Alarm Panel (MAP) and the Master Mimic Panel (MM) shall be
installed at the Fire Command Centre or at an approved location on the 1st
storey and be lockable with good quality locks. The MAP / SAP shall not
be placed near to the transformer bay. The Sub Alarm Panel (SAP) and
the Floor Mimic Panel (FM) shall be installed at the fire fighting lobby of
each floor. A minimum number of 3 keys shall be handed over to SPPG.
Also a key box with breakable glass for fireman's accessibility to the key is
to be provided.
3.8.51 All operational switches / buttons shall be installed inside the wall mounted
fire alarm indication panel unless otherwise approved by SPPG.
3.8.52 For aesthetic reasons, due consideration must be given in installing all
M&E panels in the main approach lobby or lift lobby of the substation
building. However, Main Fire Alarm Panels shall be prominent located and
accessible at all times. The Main Alarm Panel can be recessed and flush to
the external wall with glass door panel for viewing purpose. Location of the
Main Fire Alarm Panel and Sub Alarm Panel shall be located away from
direct sunlight and rain.
3.8.53 Source of incoming supply to all fire alarm panel shall be clearly displayed
on fire alarm panel.
3.8.54 Fire Alarm Panel shall be addressable type. The system shall be able to
perform diagnostic functions (health state of the panel and detectors) to
prompt the operator to perform predictive maintenance of detectors. The
system shall also come with touch screen panel / controller to indicate the
location of faults and alarm log..
3.8.55 The touch screen controller shall contain and display all alarm zone
activation event with date and time recorded and store up to minimum
1000 events. The MCPU provided shall be held in non-volatile memory
(EEPROM) and all events stored shall not be lost during system power
failure.
3.8.56 The MCPU shall be supervised and monitored for software processing.
Audio and visual signal shall be indicated in the events of processor fault.
3.8.57 All loop devices installed per loop module / card shall not exceed 70% of
the loop module / card maximum capacity for future upgrading or
expansion works.
3.8.58 Zone module shall be made available in multiple of 4. The system shall
meet the minimum requirement of NFPA 72 Class A detection wiring (4
wiring system). Class X detection wiring (4 wiring system) will be
considered depends on the environment (e.g. humid environment, etc.).
3.8.59 A Common type standard detector base shall be provided to be able to fit
different type of detectors allowing flexibility and interchangeability.
Edition 9.1
28
400KV, 230KV & 66KV SUBSTATION MECHANICAL AND ELECTRICAL REQUIREMENTS
3.8.60 The standard detector base shall be equipped with wiring terminals only,
capable of securing wire sizes minimum of 1.5mm².
3.8.61 Lightning Surge arrestors must be provided inside the Main Alarm Panel
and Sub Alarm Panels.
3.8.64 Outline key plans showing the sprinkler system, locations of fire
extinguishers, hosereels, etc shall be prominently displayed at approved
locations.
3.8.65 For 400/230/66kV & 230/66kV substations, a duplicate fire alarm indication
panel shall be installed in the Control Room.
3.8.66 Please refer to Attachment D for the requirements for fire alarm monitoring
for transmission substation.
3.8.67 All alarm panels shall have the alarm verification features link to the
detectors. It shall not link to the manual call points..
3.8.68 The main and sub alarm panels, detectors and other fire related equipment
shall comply with CP10 (Latest Edition) and approved by relevant
authorities.
3.8.69 Battery and Battery Charger must be provided in all alarm panels.
3.8.70 Two numbers of Electric Fire sprinkler Pumps shall be provided and back
up by emergency standby generator set.. Fire pumps are to be fitted with
flexible stainless steel coupling at suction and discharge sides. All tanks
shall have fix rigid metal ladder come with cage and standing platform with
metal railing for safe access of maintenance purpose.
3.8.71 All downstream fire pipes (e.g. hydrant sprinkler, hosereel) after bulk
meters shall be install above ground. Underground pipe crossing the
driveway is allowable with considerations of weight and vibration of
vehicles, haunching shall be done for such underground pipes.
3.8.73 Opening of the pipes shall be meshed to prevent unwanted objects from
entering into the pope line system.
Edition 9.1
29
400KV, 230KV & 66KV SUBSTATION MECHANICAL AND ELECTRICAL REQUIREMENTS
3.8.74 Material of the check valves used shall be of heavy duty type (e.g. no
plastic flap in the valve is allowed) and shall meet the requirement of the
system flow and pressure.
3.8.77 Certified calibration label shall be stick on all measuring equipment (e.g.
pressure gauge, flow meter etc.). Documents or information shall be
provided to advice on the frequency of the calibration.
3.8.78 Strainers shall be installed at the pipe system. All installation shall not be
forced-fit installation to prevent concentrated stress on the pipe, joints,
bolts etc.
3.8.79 Corrosion prevention method shall be done while connecting or joining two
material or parts to prevent dissimilar metal corrosion, crevice corrosion,
oxidation, etc.
3.8.80 The pump and the pipe system installation shall have no major vibration /
acoustic issue and meet the OEM installation requirement and the CP. This
is to prevent any fatigue stress to the system. Pump skid shall have shock
absorber to dampen the vibration.
3.8.81 The hanging brackets for pipes shall have absorber to dampen the
vibration.
3.8.82 Rotating parts shall be covered at all times, unless there are limitation and
such must be approved by SP.
3.8.83 Non-rising Stem Gate Valve shall be used instead of OS&Y Gate Valve to
save space and reduce knocking hazards.
3.8.85 There shall be pump performance test capability in the pump room. The
whole test line (e.g. Venturi flow meter, gate valves, etc) shall be installed
along the discharge line at ergonomic level for taking the reading and
operating the valve at floor. The venturi flow meter shall be installed at a
location where there are laminar flow in order to achieve an accurate
reading.
3.8.86 The OH tables, the designed and actual operating flow and pressure tables
shall be installed on the wall near the control valves, including those
serving the transformer bays. (in acrylic)
3.8.87 The pumps cut in cut out table shall be install on the wall near the system
test rack. (in acrylic)
Edition 9.1
30
400KV, 230KV & 66KV SUBSTATION MECHANICAL AND ELECTRICAL REQUIREMENTS
3.8.88 The pump performance test curve and report shall be install on the wall
near the system test rack. It shall be a transparent acrylic with slot to hold
the above.
3.8.89 The pressure switches connected to jockey, duty and standby pump shall
be label.
3.8.90 The pipe shall be label in paint accordingly to the services that they are
serving.
3.8.91 Water Proving Test Set shall be installed at all control valves areas
including those serving the transformer bay.
3.8.92 The Sprinkler System shall comply with latest edition of Singapore Civil
Defence Force Fire Code and Singapore Standard CP 52.
3.8.93 For sprinkler pump, the “pump run” signal need to be sent to RTU room
similarly to the “fire alarm” signal. The monitoring centre shall be able to
pick up the “pump run” signal when sprinkler pump (duty and standby) is /
are running. These cables shall be linked from the pumps to the panel
module card; and panel module card to marshalling box to monitoring
centre via SCADA.
3.8.94 Video Image Fire Detection System (VIFDS) consists of a digital video
camera coupled with a computer running video analytic software which can
recognize smoke and fire in the image, systems can monitor large volumes
to look for visible indications of a fire and send signal to MAP shall be
installed at all Transmission switch rooms, in accordance with latest
SS645. It shall also comply with the Company’s latest IT Security
requirements
3.9.1 The battery, control and communication room must be housed in separate
fire rated compartment and shall be protected with Clean Agent fire fighting
suppression system. Control and communication room shall be installed
with smoke detector and battery room shall be installed with either heat or
smoke detector is to be advised by Consultants. In addition, hydrogen
sensors shall be installed in Battery rooms.
3.9.2 The functional requirements for Clean Agent fire fighting suppression
system shall be designed based on the following criteria:
Edition 9.1
31
400KV, 230KV & 66KV SUBSTATION MECHANICAL AND ELECTRICAL REQUIREMENTS
c) Clean Agent Fluid shall not contain any of these greenhouse gases or
any other greenhouse gases that are not mentioned herewith:
i. Perfluorocarbons (PFCs),
d) Clean agent shall have a minimum safety factor of 60% between the
design concentration percentage and the No Observed Adverse Effect
Level (NOAEL) for acute toxicity, including cardiac sensitization of 10%.
f) The name of the manufacturer, part numbers and serial numbers shall
appear on all major suppression system components.
h) Room integrity test shall be performed for all rooms with the
endorsement of a Professional Engineer.
i) The room shall be able to seal and secure the protected space(s)
against agent loss and / or leakage during the hold time of at least ten
(10) minutes. Passing the room integrity test in accordance with
Appendix C of NFPA 2001 or equal shall validate room integrity. Fan
test utilizing blower to pressurize the space and an air measuring
system to determine the leakage is the responsibility of the contractor.
3.10.1 For substation building, in the vicinity of air-fields, approved warning lights
of sufficient numbers shall be installed. Provision of obstruction markings
at the topmost point of the substation building may also be required by the
relevant aviation authority.
3.10.2 Light sensors and timer switch shall be provided to control the lights.
Provision shall be made for the choice of using either one option when
necessary.
Edition 9.1
32
400KV, 230KV & 66KV SUBSTATION MECHANICAL AND ELECTRICAL REQUIREMENTS
3.10.3 Warning lights shall be mounted in such a way that they are easy to
maintain. Detailed description on how maintenance on lighting is done and
also safety of maintenance personnel shall be considered (i.e. not to fall off
from the roof of the building). All details are to be submitted to SPPG for
clearance.
3.10.4 Warning light shall have 2 hours self-contained battery pack and at least
two pairs of normally open voltage free contacts. The cables shall be at
least 1.5mm sq in size and each core shall be multiple-stranded directly to
Communication Room - Supervisory Control Marshalling Box.
Edition 9.1
33
400KV, 230KV & 66KV SUBSTATION MECHANICAL AND ELECTRICAL REQUIREMENTS
3.11.1 The following A/C supply with approved isolation shall be provided for high
voltage equipment testing at approved locations direct from the main
switchboard without RCCB:
Edition 9.1
34
400KV, 230KV & 66KV SUBSTATION MECHANICAL AND ELECTRICAL REQUIREMENTS
3.12.1 Approved drainage system with automatic submersible pumps shall consist
of 1 duty and 1 standby submersible pump with control panel at each sump
pit location. Each Submersible pump shall be installed with hour run meter
to monitor the runtime.
3.12.2 Sufficient weatherproof lighting of 500 lux (based on mean life) for
maintenance purpose shall be provided in / within all submersible pump
locations.
3.12.3 A bracket come with chain link shall be provided for the hoisting of the
pump for maintenance. Discharge piping shall be installed with a set of
valve and non-return valve for each submersible pump to prevent backflow
into the pit
3.12.6 Metal railing barriers shall be considered depending on the location of the
sump pit or the safety of the operator. (e.g. sump pit near driveway)
3.12.7 Closed Circuit Television (CCTV) shall be provided to monitor the sump pit.
A pair of normally close voltage free contacts shall be provided in the main
sump pump control panel for each panel that is required to be monitored
and shall be wired from each control panel to the designated area as
shown in Schematic Diagram below on the monitoring points required for
reference. The cables shall be at least 1.5 mm sq. in size and each core
shall be multi-stranded. Four (4) (one duty and three (3) spares) spare pair
of wires shall be provided from each control panel and terminated at the
designated area.
Edition 9.1
35
400KV, 230KV & 66KV SUBSTATION MECHANICAL AND ELECTRICAL REQUIREMENTS
3.13.1 SingTel telecom lines shall be provided from the following rooms to a
marshalling box located at 1st storey.
a) Each 22kV Switchroom (dedicated for SCADA section for its remote
metering)
c) SPPG Pool Metering Box (inside each 22kV switchroom) and / or Tariff
Meter Room, 13A socket outlet point and location of the telephone
point to be located on the wall fronting the centre of the respective HT
opening.
d) Four (4) pairs of telephone wire / cable to be laid from Main Alarm
Panel to cable floor by placing it in a junction box just beneath the
cable entry to RTU room.
3.13.2 All outgoing telecom lines for shall be provided with proper terminal blocks
at approved locations.
3.14.1 If a Fire lift is required by Fire Safety & Shelter Department, then further
discussion is required between Developer / Consultant and SPPG.
Number of fire lift shall be in accordance with the FSSD’s requirements.
3.14.3 The Passenger / Fire lift shall fully comply with Authorities' latest
requirement and approved by SPPG. Capacity of 600kg / 9 persons at
1.0m/sec speed is recommended. Clear visible signage listing emergency
breakdown telephone number and other details is to be installed at eye-
level inside the lift car. The details of the signage shall be "IN CASE OF
LIFT BREAKDOWN, PLEASE CONTACT (HOTLINE NO.) 1800-7788888"
and have to be cleared with SPPG.
Edition 9.1
36
400KV, 230KV & 66KV SUBSTATION MECHANICAL AND ELECTRICAL REQUIREMENTS
3.14.4 The Passenger / Fire lift shall have slave intercom stations at the lift car,
Lift Motor Room where the lift maintenance control panel are, lift lobby at
ground floor near the lift, or Fire Command Centre (if any). One approved
telephone set in lift car is required for connection to SPPG's PAX network.
Cabling between Lift Motor Room and SPPG's Communication Room shall
include spare cores. The telephone box installed shall be flushed with the
lift wall. The method of using the emergency intercom system in the lift
shall be displayed (e.g. press the button for 5 seconds to call the other
end).
3.14.5 The floor area of the lift shall not be less than 1.5 sq metres.
3.14.7 All emergency equipment (e.g. ARD, lift car lightings, lift car ventilation
fans, etc.) shall be provided with emergency supply from the standby
generator.
3.14.8 To carry out load test of lift come with the endorsed report before handing
over.
3.14.9 To provide Building and Construction Authority (BCA) lift Permit to Operate
certificate in a frame approved by SPPG.
3.14.13 All control panels and electrical devices / wirings must be labelled.
3.14.16 The design of the lift and lift lobby as well as the maintenance shall comply
with the latest SS 550 and other statutory requirement.
3.14.17 The type of lift, model and post Defect Liability Period maintenance terms
shall be approved by SPPG.
3.14.18 Adequate lighting and ventilation shall be provided at the lift motor room, if
applicable.
3.14.19 Lift car stainless steel interior panels and call button panel shall be of matt
finish.
Edition 9.1
37
400KV, 230KV & 66KV SUBSTATION MECHANICAL AND ELECTRICAL REQUIREMENTS
3.14.20 The lift car protection cover shall be provided to SPPG for future
maintenance purposes.
Edition 9.1
38
400KV, 230KV & 66KV SUBSTATION MECHANICAL AND ELECTRICAL REQUIREMENTS
3.15.2 During the DLP, Developer shall ensure regular maintenance as per
Singapore Standards until handing over after the end of DLP.
h) Motorised Gates
Edition 9.1
39
400KV, 230KV & 66KV SUBSTATION MECHANICAL AND ELECTRICAL REQUIREMENTS
3.15.4 The services, spare / parts, and their respective prices / rates quoted in the
extended service agreement shall remain valid and firm for the entire
period covered by the same agreement.
Edition 9.1
40
400KV, 230KV & 66KV SUBSTATION MECHANICAL AND ELECTRICAL REQUIREMENTS
3.16.1 The key design principles for the air-conditioning and mechanical
ventilation systems are:
3.16.2 The following rooms shall be air-conditioned with duplicated units for
switching over and each unit with 100% capacity, including condensing
units:
b) Communication Room
3.16.3 The following rooms shall be provided with mechanical ventilation systems
The MV fans with duplicated units for switching over and each unit with
100% capacity:
a) Battery Room
Edition 9.1
41
400KV, 230KV & 66KV SUBSTATION MECHANICAL AND ELECTRICAL REQUIREMENTS
3.16.5 The air-conditioner shall be air-cool type. No water cooling tower shall be
entertained.
iii. There shall be audible alarm when the high temperature alarm is
activated and buzzer sound when trip / fault is activated.
c) All remote controller shall be housed within the air conditioning lockable
control panel, or come with lockable function.
3.16.7 Control panel shall be provided for the air-conditioning units. When air-
conditioner tripped or failed, indication light of this status must be provided.
Provision for manual start / stop shall be provided. The incoming power
supply needs to be size to cater to operate both duty and standby sets
together.
3.16.8 In the event of any compressor or blower failed, the duty air-conditioner
shall auto-switch over to standby set. The standby set shall operate
continuously. The rooms shall be kept cool to the design requirement at all
time, even when a set of both duty and standby aircon are not functioning,
the other set of standby air con within the same room shall be operating,
while this particular same set of duty air con is still operating.
Edition 9.1
42
400KV, 230KV & 66KV SUBSTATION MECHANICAL AND ELECTRICAL REQUIREMENTS
3.16.9 The fan coil units shall be ducted type. To provide tray pans below each
fan coil unit. The ducts shall be located outside of the rooms, unless met
with constraints, thereafter must seek SPPG approval before such
installation.
3.16.12 To provide concrete slab and earthing for the condenser units on the roof.
3.16.13 To provide water supply with proper drain out system on the roof away
from the locations of switchroom / control room subject to SPPG's approval
for washing the condenser units.
3.16.16 To provide paper strips to be pasted onto the supply air diffuser.
3.16.18 All supply air diffusers / grilles outlets to be located away from all
equipment. All FCUs are not to be installed directly above any equipment.
3.16.20 Refrigerant piping housed in trunking shall not be directly above any LV
cable tray/trunking, panels or above dry box. Air conditioner’s designed
cooling temperature shall be at 24C ± 1C.
3.16.21 If Air Handling Unit (AHU) room is provided for the air conditioning system,
lighting of 500 lux (based on mean life) shall be provided.
Edition 9.1
43
400KV, 230KV & 66KV SUBSTATION MECHANICAL AND ELECTRICAL REQUIREMENTS
3.16.23 For centralised air-conditioners, the location of fan blower shall be clearly
indicated and the installation of fan coil unit shall not be directly above any
of the relay panel. Water tap shall be provided and located as near to the
condenser unit (CU) as possible for cleaning of filters.
3.16.24 Do not install compressor unit in the air-handling unit (AHU) room directly
above any control room as far as possible. If it is impossible, ensure that
all openings at the AHU room above control room are covered up and
sealed to prevent water seepage to the floor below. In addition, the floor of
the AHU room shall be waterproof and all cracks are to be sealed.
3.16.25 All drainage shall be direct to the nearest floor trap via gravity. No
drainage pumps shall be used for condensate drainage.
3.16.27 The noise level from ACMV shall be within NEA’s latest guidelines.
3.16.28 The supply for the ACMV shall not be mixed with other M&E equipment.
3.16.29 Computational Fluid Dynamics (CFD) study should be carried out on the
design of MV fans with consideration of the heat generated by full load
transformers including shunt reactors, etc.
3.16.32 Mechanical battery rooms shall be served by explosive proof fans with
100% redundancy back up with auto switch over function switches.
Exhaust air grilles shall be located at the highest possible positions to
provide effective ventilation (with no short circuit of air flow) and to
discharge gaseous products from the batteries. Arrangement of fans is
subject to SPPG's comments. Time control switches shall be provided for
each Mechanical Ventilation fan.
3.16.33 Mechanical Ventilation fan design shall comply with SCDF requirement.
3.16.35 Control Panel for MV fans installed at transformer bay shall be located
outside of the transformer bay.
Edition 9.1
44
400KV, 230KV & 66KV SUBSTATION MECHANICAL AND ELECTRICAL REQUIREMENTS
a) The Duty fan will operate at twenty four-hours a day, seven days a
week; at all times with duty lead-lag controls (i.e. alternate duty and
stand-by fans to run).
b) In the event that the hydrogen sensors detected hydrogen gas emission
(1% hydrogen gas emission), the gas panel shall send alarm signal to
SPPG Central Monitoring Station.
c) When the hydrogen gas emission reaches 2%, a second alarm signal
from gas panel (high alarm) will be send to SPPG Central Monitoring
Station.
Edition 9.1
45
400KV, 230KV & 66KV SUBSTATION MECHANICAL AND ELECTRICAL REQUIREMENTS
3.18 Others
3.19.1 A 42U height 19” cabinet shall house SPPG’s network equipment and be
located near the fibre marshalling box / patch panel in the communication
room.
3.19.2 A fully perforated front door cabinet shall permit the free vertical ventilation
of the network equipment without compromising the IP rating required.
Fans shall be installed in the cabinet to prevent overheating of the
equipment. The installation shall have a high level of corrosion resistance
in a warm and humid environment.
3.19.3 The network equipment cabinet shall be lockable with removable hinged
doors on the front and back. The inner side of the front door shall have the
provision to keep a maintenance log book. 5 nos. of spare keys for each
cabinet shall be provided.
3.19.4 The cable entry points to the cabinet shall be of bottom entry and shall be
properly secured and sealed.
3.19.5 The cabinet frame, both front and back doors and other parts, which can
be made accessible, shall be properly earthed.
Edition 9.1
46
400KV, 230KV & 66KV SUBSTATION MECHANICAL AND ELECTRICAL REQUIREMENTS
i. 24 ports (1U)
iii. Equip with 0.5 meter of CAT6 pigtails with RJ45 connector.
iv. IDC: suitable for 22-26 AWG stranded and solid wire,
compatible with both 110 & Krone punch down tools.
3.19.7 The Contractor shall lay 1 no. of 20A single phase AC cable from a location
in Control room to the Internal Telephone / Network Rack and 1 no. of AC
cable from Building Emergency supply to Network Rack. The AC cables
shall be terminated to a suitable power socket outlet / circuit breaker.
3.19.8 The Contractor shall lay 2 nos. of single mode optical fibre cable (SM-OFC)
from network Rack to OFC patch panel in the communication room. The
cables shall be terminated to suitable LC / FC connectors.
Edition 9.1
47
400KV, 230KV & 66KV SUBSTATION MECHANICAL AND ELECTRICAL REQUIREMENTS
3.20.1 The Contractor shall install caller ID analog telephone sets which are
independent from telecommunication service providers. The locations are:
3.20.2 All telephone sets shall each be installed with suitable approved corrosion
resistance metallic locking device to prevent unauthorised removal of
telephone sets from the installed location.
3.20.3 The Contractor shall install a Gateway Box in the communication room
which will be wall mounted at a height of 140cm. The location shall be at
one of the corners and away from air-con units.
3.20.4 The Gateway Box shall have hinged lockable doors and be made of
corrosion- resistant, epoxy powder-coated stainless steel (Grade 316) and
be protected to at least IP65. The Gateway shall be wall-mounted and has
a minimum dimension of 60cm (Width) x 40cm (Height) x 30cm (Depth).
3.20.5 The Contractor shall install 8-Ports FXS Analog VoIP Gateway Box. The
number of Analog VoIP Gateway required shall be dependent on the
number of telephone sets installed. The Analog VoIP Gateway must be of
current model use in the SPPG telephone system.
3.20.6 The Contractors shall lay CAT5e cable each from telephone sets to
Gateway Box. The cable shall be terminated to a RJ11 telephone socket
and KRONE terminal respectively.
3.20.7 The Contractor shall lay 1 no. of 20A single phase AC cable from a location
in Control room to the Internal Telephone / Network Rack and 1 no. of AC
cable from Building Emergency supply to Network Rack. The AC cables
shall be terminated to a suitable power socket outlet / circuit breaker.
Edition 9.1
48
400KV, 230KV & 66KV SUBSTATION MECHANICAL AND ELECTRICAL REQUIREMENTS
3.20.8 The Contractor shall lay 2 nos. of CAT5e cables from Gateway Box to
Network rack. The cables shall be terminated to a suitable RJ45
connectors.
Edition 9.1
49
400KV, 230KV & 66KV SUBSTATION BUILDING, CIVIL AND STRUCTURAL REQUIREMENTS
4.1.1 All rooms shall be designed to provide sufficient lighting and ventilation.
Rooms shall also be designed to ensure a dust-free environment as far as
possible.
4.1.3 The ambient temperature shall not exceed 40°C (1 metre from switchgear
and transformers).
4.1.4 For transformer and reactor bay, the yearly average temperature shall not
exceed 30C.
4.1.5 All ventilation louvres shall be designed to comply with the following
specifications:
d) The louvre shall be finished in either polyester powder coating finish with
10-year warranty on paintwork.
Edition 9.1
50
400KV, 230KV & 66KV SUBSTATION BUILDING, CIVIL AND STRUCTURAL REQUIREMENTS
h) For general area, the entire assembly shall have an airflow coefficient of
Class 2 and rain defense of Class A under a wind condition of 13.0m/s
and rainfall of 75mm/hour. The louvre system shall achieve a HEVAC
class of A2 for an airflow velocity up to 1.0m/s.
i) For switchgear, battery and other critical rooms (all voltages including
22kV), the louvre system shall achieve a HEVAC class A3 for an airflow
velocity up to 3.5m/s.
ii. The Design of Air Ventilation Equipment, Louvre and Air Moving
Equipment including appendices stating the scope of registration
under Standard Industrial Codes (SIC) SIC 3284, SIC 8370 and
SIC 5030
4.1.6 Sun-shading provisions shall be made on the external walls of Battery room,
to avoid high room ambient temperature. External walls of these rooms shall
not face the setting sun.
Edition 9.1
51
400KV, 230KV & 66KV SUBSTATION BUILDING, CIVIL AND STRUCTURAL REQUIREMENTS
4.1.7 No cavity shall be created on top of Battery Room to trap gaseous products
evolved from batteries. Ceiling beams which span across the middle of the
rooms shall be avoided.
4.1.8 Switchgear rooms shall be designed to be free from water intrusion, any
ventilation design shall take into consideration on rainwater entry into the
rooms.
4.1.9 Louvres and windows for ventilation should be positioned if possible; higher
than equipment located within the room.
Edition 9.1
52
400KV, 230KV & 66KV SUBSTATION BUILDING, CIVIL AND STRUCTURAL REQUIREMENTS
4.2.1 All water points and toilet flush valves shall be located at or below Reduced
level of 125m and 112m respectively.
4.2.2 Battery room shall be provided with one Vitreous China wash-hand basin with
manual tap of swan-neck type to Public Utilities Board (PUB)'s requirements
each. For purpose of information, the wash basin in the Battery room is
intended for maintenance staff to wash their hands/eyes in times of
emergency. It is not intended for disposal of any acidic waste water and
warning signboard shall be provided on the wall with words such as
"WARNING: DO NOT DISCHARGE ACID WASTE INTO THE BASIN.”
4.2.5 All other taps, if any, shall be provided with approved constant flow regulators
of 6 litres/minute to be used for 12/14mm piping.
4.2.6 All plumbing fixtures in toilets, etc, shall as far as possible be surface
mounted. Toilet bowl shall be of the sitting type. A tap shall be provided
beside the toilet bowl.
4.2.7 All toilet fitting and fixtures shall comply with the PUB WELS ‘min. 2 ticks’
rating.
4.2.9 All toilets shall be provided with jumbo toilet roll drum.
4.2.10 Copper pipes or Stainless Steel pipes shall be used for domestic water
supply in substations. No welded joints shall be allowed.
Edition 9.1
53
400KV, 230KV & 66KV SUBSTATION BUILDING, CIVIL AND STRUCTURAL REQUIREMENTS
4.3.2 There shall be no cross beam across any floor opening in all switchrooms
4.3.3 All reinforced concrete structures shall comply with Developer's / Consultant's
Engineer's details.
4.3.4 All stumps, if any, in cable floor/basement of all switchrooms shall be located
at 1000mm (min) from any edge of switchgear floor opening.
4.3.5 Any floor beams running parallel to the sides of all switchgear openings shall
be set back at least 500mm away from all edges of the openings.
4.4.1 Proper rust-proof anchor rings of at least 4 nos. (flush type, not protruding
above finished floor level) for fastening of worker's life-lines shall be provided
at convenient locations around all loading / unloading bays, lifting voids and
cable ramps/voids and to comply with Workplace Safety & Health (WSH) and
other authorities’ requirements. Anchor rings shall be provided at 1.2m from
the edge of openings.
4.4.2 Maintenance platforms shall be provided for the servicing of lifting hoists and
overhead travelling cranes. The height from the maintenance platform to the
underside of crane/hoist hook shall be between 1 metre (min) and 1.2m
(max). These platforms shall be accessible by staircase if possible.
Otherwise, cat ladders shall be provided.
Edition 9.1
54
400KV, 230KV & 66KV SUBSTATION BUILDING, CIVIL AND STRUCTURAL REQUIREMENTS
4.4.4 All cat ladders provided shall be mounted at a clearance of 200mm to 300mm
away from the wall to avoid boot marks on walls.
4.4.5 All floor openings (temporary and permanent) in all rooms shall be properly
covered. Removable aluminium chequered plates mounted on suitable
frames shall be used to prevent any person from falling through uncovered
openings. Developer / Consultant shall ensure loading is catered for human
weight in designing the chequered plates. Designs and sizes of chequered
plates shall be cleared by SPPG.
4.4.6 If other types of covers are required by Fire Safety & Shelter Department
(FSSD), designs and materials used shall be approved by SPPG.
4.4.7 If bolting of temporary covers is required by Fire Safety & Shelter Department
(FSSD), only the four corners shall be bolted down to the floor.
4.4.8 Safety gratings and hot-dipped galvanised railings which are properly fixed
and can be removed when necessary, are to be provided for all openings of
cable ramps at cable floors for multi-storey substation building.
4.4.9 Fire stop boards / seals with 2 hours fire rating are to be provided at all cable
ramp areas, floor openings between floors as well as cable ramp openings on
ceiling of the transformer bays and the fire retardant material used for the fire
stop boards / seals shall comply to Fire Safety requirement.
4.4.10 The length of the fire stop boards / seals at the cable ramp up area shall be
aligned with the detachable railings in order to avoid sterilising the cable
entry. Architect to submit details to our site officer-in-charge for clearance
prior to construction.
4.4.11 All surface drains crossing the path of staircases must be covered with heavy
duty hot dipped galvanised gratings which are hinged on one side of suitable
supporting frames.
4.4.13 Trap doors where necessary shall be flushed with the finished floor level.
These trap doors shall be made of heavy-duty aluminium chequered plates
sprayed with approved fire-rated material if required by Fire Safety & Shelter
Department (FSSD) and mounted on suitable frames to be located in
approved locations.
4.4.14 Loading platforms and lifting void landings shall be provided with fixed and/or
removable hot-dipped galvanised safety railings as required.
Edition 9.1
55
400KV, 230KV & 66KV SUBSTATION BUILDING, CIVIL AND STRUCTURAL REQUIREMENTS
4.4.15 The lifting void shall be covered by a bird-proof device at the suitable and
approved landing access. Design shall be approved by SPPG.
4.4.16 Safety Toe Board of aluminium plate with suitable height shall be provided to
all the railings at all the lifting void, maintenance platform and other areas
where applicable by either using bracket and self-locking nut or welded type.
Design shall be approved by SPPG.
4.4.17 To install flash light with a beep sound from the hoisting motor of hoist crane
near hoisting area at substation ground level.
4.4.18 Stainless steel railings to be provided at the delivery ramp in Battery Charger
room and Control room when there is a raised floor at the door access area.
4.5.1 Generally, all switchroom floors are constructed with a 50mm thick cement
rendering including a 20mm granolithic smooth finish of cement, granite chips
and sand in the ratio 1: 1: 1. All surfaces shall be hardened by an approved
hardener. Generally, the cement rendering is increased in thickness to flush
with SPPG's switchgear floor frames/I-beams. Such increase shall be made
gradually avoiding sudden sharp drops. Floors shall only be rendered after
the installation of equipment for floor frames. The arrangement/details of
anchoring of switchgear floor frames/I-beam and final rendering details can
only be confirmed with SPPG's successful switchgear supplier after award of
contract.
4.5.2 Wherever possible, there shall be one common floor level between the
loading area and the entrance to the respective switchrooms for shifting of
heavy equipment.
Edition 9.1
56
400KV, 230KV & 66KV SUBSTATION BUILDING, CIVIL AND STRUCTURAL REQUIREMENTS
4.6.1 All cable trenches and substation cable basement/chamber and all sunken
pits for equipment shall be dry and free of water. Waterproof sealing
compound shall be used. A proper drainage system with automatic
submersible pumps shall be designed to achieve this.
4.6.2 Scupper drains shall be all around the perimeter of the cable basement walls,
except for staff entry / exit areas to be encased with pipe sleeves.
4.6.3 Scupper drains shall be provided at all pipe entries location to guide water to
flow efficiently to sump pit location. Gradient of scupper drain shall be 1:100.
4.6.4 All sump pit levels shall not be deeper than 1000mm from floor level unless
otherwise required by the Architect for purpose of effective drainage. For
deep pit, some means of access to the pump shall be provided. All Sump pit
to be covered with heavy duty removable grating
4.6.5 All sump pits with depth less than 1000mm shall be installed with 1-level
system and sump pits with depth 1000mm or more shall be installed with 5-
levels alarm system as shown below:
ii. Alarm sent when 5-level sensor activated (water high-high level)
c) Independent sensor, I.e, Water level sensor (to be installed at top edge of
sump pit) that transmit directly to BMS interfacing and 22kV RTU, via the
control panel. The independent sensor shall be able to trigger alarm when
water overflow from the sump pit and send alarm to BMS and RTU. An
alarm shall be included when submersible pump(s) run for more than 30
mins.
Edition 9.1
57
400KV, 230KV & 66KV SUBSTATION BUILDING, CIVIL AND STRUCTURAL REQUIREMENTS
4.6.6 All sump pits shall be provided with proper removable covers. A bracket shall
be provided for the hoisting of the pump for maintenance.
4.6.7 If a submersible pump is provided in the transformer pit, a sump of low brick
walls shall be provided around the pump to segregate granite chips from the
pump. The top of the sump shall be covered with hot dipped galvanised
gratings.
4.6.8 Platform levels of the development site should comply with platform, crest
and reclamation levels as stipulated in latest PUB code of practices.
4.6.10 For 22kV/LV cable risers, cable ladders and control cable risers shall be
installed with P1000 unistruts.
4.6.12 Flange plate below the sump pump check valve may pose danger during
maintenance/servicing stage, is to be reversed so as to avoid potential
danger to hand and body.
4.6.13 Apron drain shall be provided in cable basement to lead water into sump pit.
Edition 9.1
58
400KV, 230KV & 66KV SUBSTATION BUILDING, CIVIL AND STRUCTURAL REQUIREMENTS
4.6.14 Opening of sump pit shall be designed large enough for a squatting adult to
remove or install sump pump.
4.6.15 Lights shall be positioned above the sump pump to avoid accident due to
poor lighting.
4.6.16 Sump pump shall not be installed below staircase. Sump pump’s control
panel shall be installed next to exit door. Adequate lighting shall be provided
at the vicinity of sump pump (minimum lux level shall not be less than 500 lux
as recommended by CIE publication no.29.2)
4.6.17 Connecting pipe/drain shall be provided between all the sump pits, if there is
more than one pump at different locations on the same floor.
4.6.18 The heavy duty cover and sand-bag back-filling shall be provided for the draw
pits. The design of the draw pits shall be based on bending radius of:
4.6.18 If the draw pit has to be installed outside of the boundary, the cable protection
covers (e.g. 66kV, 22kV & LV marker) shall be provided immediately on top
the full width of the heavy-duty cover of the draw pit with the lead in pipes,
where applicable.
4.6.19 HT riser pits shall be filled with wash-down granite chips to prevent mosquito
breeding and avoid accumulation of water shall be of approved sizes (50mm
to 75mm).
Edition 9.1
59
400KV, 230KV & 66KV SUBSTATION BUILDING, CIVIL AND STRUCTURAL REQUIREMENTS
4.7.1 All un-plasticised PVC cable entry pipes and fittings including drawstring of
polypropylene rope of diameter 5mm (min) required for the substation
building shall be supplied and installed by the Developer / Consultant to
approved quantity and arrangement subject to site configuration.
4.7.2 These cable entry pipes and fittings complying with SS141 Class B shall be
encased in concrete, to have piling if necessary and be properly sealed at
both ends with bentonite and plastic caps to prevent ingress of water. The
external faces of the pipes joining the walls of the basement/chamber shall be
adequately bonded. Any gap/void shall be completely sealed against
seepage of water into the building through these areas.
4.7.3 No bend or kink is allowed at the joint for long cable entry pipes.
4.7.5 Cable entry pipes shall be spaced at minimum 100mm apart and 150mm
above the floor level.
4.7.6 The depth of cable pipes at the extreme end away from the substation
building shall not be more than 1.5 metres but not less than 1 metre between
ground level and top of pipes.
4.7.7 The lead-in pipes shall be installed under drain / box culvert immediately
outside site boundary and to be extend up to 300mm beyond the drain / box
culvert, where applicable.
4.7.8 The lead-in pipe block front shall not be obstructed by trees, water pipes and
/ or other services. If any, they have to be relocated or diverted out of cable
entry pipes.
4.7.9 The exact location and gradient of cable pipes shall be checked and
approved by SPPG's site engineer-in-charge. He shall be notified before any
laying is done.
Edition 9.1
60
400KV, 230KV & 66KV SUBSTATION BUILDING, CIVIL AND STRUCTURAL REQUIREMENTS
4.7.11 All used and unused openings pass through any slab, wall, or another
compartment shall be blanketed/sealed with approved fire stops compound.
The proposed fire stop compound is subjected to the approval of SPPG.
4.7.13 Where cables pass through structural elements such as floors and walls, the
opening made shall be sealed with approved fire-resistant material of not less
than four (4) and / or two (2) hours fire rating to prevent the spread of fire.
The specified fire rating to be provided shall be complied with the Authority’s
requirements.
c) Cable duct entry must not end where the area above is obstructed by
permanent structures, services, trees etc.
d) Puddle flange must be provided to each and every pipe ends prior casting
together with the basement wall
Edition 9.1
61
400KV, 230KV & 66KV SUBSTATION BUILDING, CIVIL AND STRUCTURAL REQUIREMENTS
4.8.1 The pits for transformers, NGRs, shunt reactors etc. shall have a nominal
depth of one metre, if the Developer / Consultant encounters site constraints
and cannot achieve the above-mentioned requirement, the matter shall be
referred to SPPG for further consideration.
4.8.2 Wash-down granite chips for all pits of transformer, NGR, shunt reactor etc.
shall be of approved sizes (50mm to 75mm) with the exception for distribution
transformer bays which will be backfilled with fine sands only. Developer /
Consultant shall arrange for the delivery of granite chips and fine sands after
SPPG has installed all cables in transformer pits (Date of delivery and filling
of granite chips and fine sands is to be made some time six months after final
handover of substation).
4.8.3 Anchorage hooks to take 10-tonne pulling exert shall be provided at two inner
corners of 400kV, 230kV and 66kV transformer bays for installation purpose
of erection/maintenance.
4.9 Roof
4.9.1 Special consideration should be given to the roof design as our extra high
voltage switchgear equipment cannot tolerate roof leakage. The reinforced
concrete roof design shall be 100% waterproof and provided with suitable
insulation. The roof shall be pitched as steep as possible (minimum 3° or
1:20 fall), without affecting the aesthetics of the complete building. Additional
properly rust-proofed roof using aluminium materials over the reinforced
concrete waterproofed roof of the substation must be provided to ensure no
roof leakage. Metal roof shall have no laps and be laid in one span with one
length roofing sheet. No overlapping and joints are allowed.
Edition 9.1
62
400KV, 230KV & 66KV SUBSTATION BUILDING, CIVIL AND STRUCTURAL REQUIREMENTS
4.9.4 No roof gutter is allowed at the roof. The design of the roof must take into
consideration to ensure no retention and proper natural discharge of
rainwater.
4.9.5 Proper human access to roof must be possible from one of the internal
staircases. Parapet wall or handrails are required on roof for safety reasons.
Otherwise, provision of anchor points for roof lifeline systems and fall arrest
systems are to be specified.
4.9.7 Should human access to roof through internal staircase is not possible, then
access door above cat ladder shall be of sliding type, (not swinging
mechanism type) with a stainless steel weather proofed water tightness
feature. Safety guardrail shall be installed if roof access is of close proximity
to the edge of the roof for safety reason.
4.9.8 Proper human access to the GPS location must be possible from one of the
internal staircases leading to the roof top. A Global Positioning System
(GPS) routing shall be provided between the Communication room or Cable
Basement below the Communication room and the roof top facing open sky
without any obstruction.
4.9.9 The routing shall comprise of 50mm diameter piping with draw-wire for future
cable laying. The GPS routing shall be designed based on the following
criteria:
b) GPS cable will be laid and maintained solely using 2m high A-frame
ladder
c) GPS antenna and cable will be installed and maintained on the rooftop
with protected edge
4.9.10 The GPS shall be installed at the roof top with cone angle of 120 degree with
no obstruction on the side.
4.9.11 Reinforced Concrete (RC) flat roof free flow drainage system gap shall be
100mm to allow efficient discharge of rain water as well as to enhance safety
for maintenance personnel who access the roof.
Edition 9.1
63
400KV, 230KV & 66KV SUBSTATION BUILDING, CIVIL AND STRUCTURAL REQUIREMENTS
4.10.1 The following air-conditioned rooms shall be provided with solid slab ceiling
within these false ceilings:
4.10.2 False ceilings shall be of acoustic mineral fibre ceiling boards. Thickness
16mm or equivalent approved type.
4.11.1 The following location shall be provided with raised floor system (where
applicable):
b) Communication Room
4.11.3 Intended use of system: A readily accessible underfloor space suitable for
running electrical, mechanical, computer or communication services and the
like.
4.11.4 Provide a completed raised access floor system with edge trim which is rigid,
free from vibration, creep, squeaking, and the like, which has a smooth and
uniform finished surface, and which will maintain these conditions when
sufficient panels have been removed for normal access. Finish of the panels
shall be a high pressure plastic laminate and compliant with the latest Fire
Code. In addition, raise floor system shall be anti-static, anti-skid and non-
combustible.
Edition 9.1
64
400KV, 230KV & 66KV SUBSTATION BUILDING, CIVIL AND STRUCTURAL REQUIREMENTS
4.11.5 All panels to be capable of removal using special panel lifting tools provided
for the purpose.
4.11.6 Perforated panels are to be provided at the corners of the rooms for
ventilation purposes.
4.11.9 Provision must be made for installation of safety railings at exposed edges,
openings, ramps and steps, for the raised flooring.
Edition 9.1
65
400KV, 230KV & 66KV SUBSTATION BUILDING, CIVIL AND STRUCTURAL REQUIREMENTS
4.12 Driveway
4.12.1 All driveways shall be properly surfaced with premix and accessible to heavy
vehicles before the handover of substation. 150mm high concrete kerbs shall
be provided along sides of driveways if adjacent grounds are turfed.
4.13 Drains
4.13.1 Proper drainage around the substation shall be provided. Hinged hot-dipped
galvanised gratings shall be used to cover all drains.
4.13.2 All drains, sewers, or any other pipes for building services shall not obstruct
cable laying work. No sewer or Telecom manhole shall be installed on the
cable reserves without SPPG's approval.
4.14.2 Turfing and tree planting shall be incorporated in total design subject to
SPPG's approval. Cow grass shall be used for turfing.
4.14.4 The depth of the roots of this tree shall not exceed 0.5 metres and the
minimum height of not less than 5 metres.
4.14.5 The first tree shall be sited minimally 5 metres away from any CCTV pole.
4.14.7 Subsequent trees shall be spaced 4 to 5 metres apart, until the next CCTV
pole; subject to site conditions as well as security and operational concerns at
each substation.
Edition 9.1
66
400KV, 230KV & 66KV SUBSTATION BUILDING, CIVIL AND STRUCTURAL REQUIREMENTS
4.14.8 If the distance between a tree and the end of the planting area is less than 7
metres, a subsequent tree need not be planted.
4.14.9 The offset between CCTV pole and tree shall be 0.3 metres to 0.5 metres,
with 0.5 metres being the most ideal. This is to avoid blocking the line of
sight in monitoring perimeter fencing (refer to Appendix 5).
4.15.2 Heavy duty non-slip homogeneous ceramic floor tiles shall be used in 66kV
Control room (when applicable).
4.15.4 Toilet shall be suitably wall and floor tiled. Floor tiles shall be of heavy duty
non-slip type.
4.15.5 Acid resistant floor tiles shall be provided to all Battery Rooms.
4.15.7 Skirting tiles shall only be installed at areas where floors are tiled.
4.16.1 All heavy-duty 2-hour fire rated mild steel in galvanised finish roller shutters
or sliding and folding doors shall be used to close up large wall openings at
approved location in the substation building as directed by SPPG and shall
be complied with relevant authorities
Edition 9.1
67
400KV, 230KV & 66KV SUBSTATION BUILDING, CIVIL AND STRUCTURAL REQUIREMENTS
4.16.2 All external doors of the substation building shall be metal doors (fire rated)
for durability and ease of maintenance.
4.16.3 Please refer to Attachment F for more details of doors and locking system.
4.17.1 A feature wall near main gate entrance bearing the name of the substation
shall be installed at an approved location. Other design details (e.g. height of
wall, gate, fence, etc) shall be subject to the approval of SPPG and the
relevant local authorities.
4.17.2 SPPG substation internal name plates of approved material, size, color,
design with functional identities for substation shall be provided and to be
mounted at lift lobby / main staircase, Control Room entrance and other
suitable locations of the substation. The locations for mounting the internal
name plates are to be finalized with SPPG site engineer-in-charge (refer to
Attachment E).
4.17.5 “Wear helmet” warning signs shall be installed at "hard hat" area and
transmission switchrooms.
4.17.6 "Ear Protection" warning signs shall be installed at "high decibel" area or
doors of the rooms before entry (e.g., Pump room, EDG room, etc...)
4.17.7 "Electrical Hazard" warning signs shall be installed at doors of rooms or area
with electrical hazard.
4.17.8 "Eye Protection" warning signs shall be installed at doors of rooms or area
with machinery that can cause harm to eyes.
4.17.9 "No mobile devices" warning signs shall be installed at doors of rooms or
area with potential explosion hazards.
4.17.10 All rooms shall be properly labelled with their respective names.
Edition 9.1
68
400KV, 230KV & 66KV SUBSTATION BUILDING, CIVIL AND STRUCTURAL REQUIREMENTS
4.17.11 Name plates showing the respective designed static and dynamic load / floor
loadings or Safe Work Load (SWL) shall be provided in all switchrooms,
various equipment rooms, plinths, extended working platforms and anchor
points.
4.17.12 Name plates showing directions to various switchrooms, LV room and control
room shall be fixed prominently at approved locations (e.g. at 1st storey
staircase entrance, etc).
4.17.13 Sign-boards with outline key plans showing various rooms at different levels
of the building shall be prominently fixed at approved locations.
4.17.14 Room identification and location signs are recommended to be made of 3mm
thick dark bronze aluminium plate of minimum 20 microns and anodizing
etched with graphics and coated with approved UV resistant enamel paint of
approved colour or alternative proposal letterings in silkscreen using acrylic
and powder coated aluminium and fixed with approved self tapping stainless
steel screws and all other fixing accessories.
a) The exit sign shall bear the legend ‘EXIT’ together with directional arrows
where required. It shall be of 15 years average rated lamp life with
licensed under the latest Radiation Protection Act of National
Environmental Agency (NEA)
b) The sign shall comply with the latest BS 5499 Part 2 and SS 364, and
tested by Singapore Productivity and Standard Board or any recognised
Authority.
c) The exit sign shall be approved by Fire Safety and Shelter Department
(FSSD). The installation shall comply with the latest Fire Code of
Singapore Civil Defence Force (SCDF)
d) Developer / Consultant shall provide certified true copy of the relevant test
report, approved letter and Health Sciences Authority’s (HSA) / NEA’s
licence for the self luminous exit sign and submit to SPPG’s site engineer-
in-charge prior to installation.
f) All exit lights, other than the wall mounted type, must be double-sided so
that it can be seen from both directions.
4.17.16 To provide a signage “DO NOT LEAN ON THE RAILING” to display on the
detachable railing at all lifting void areas.
Edition 9.1
69
400KV, 230KV & 66KV SUBSTATION BUILDING, CIVIL AND STRUCTURAL REQUIREMENTS
4.17.18 Fire doors are to fix with signage “PLEASE KEEP THIS DOOR CLOSED AT
ALL TIMES” for safety purposes.
4.17.20 To comply with SCDF on the provision of EXIT and directional signs in
building.
4.17.21 To comply with SCDF on the provision of adequate common areas for
meeting Fire Safety Requirements.
4.17.22 To comply with SP Signage and Floor Marking Standards, i.e. Floor Marking
– Best Practices and Signage – SS508 Part 2.
4.17.23 For signage installed on the fence, the signage shall be installed 50m apart
(from side to side) and 8 points securing with Stainless Steel SS304 M6 bolts
and nuts with spring washer to be installed at the vertical support on its back.
Edition 9.1
70
400KV, 230KV & 66KV SUBSTATION BUILDING, CIVIL AND STRUCTURAL REQUIREMENTS
4.19 Paint
4.19.1 Painted internal walls of the substation building including staircases which are
not tiled shall be final-coated with an approved oil-based paint of a darker
(grey) colour up to a height of 1.5 metres.
4.19.2 For external walls, the final coat of approved paint and colour shall blend with
neighbouring developments. All paint colour code shall be provided to SPPG.
4.19.3 The final coat of approved paint to the entire building (interior and exterior) up
to a height of 3 metres shall only be applied just after SPPG's main
equipment is installed.
4.19.4 Low cross beams facing the entrance doors of cable floor/chamber/basement
shall be painted with luminous paint.
4.19.5 For battery room, the internal wall (up to a height of 1.5 metres) shall be
epoxy coated finish.
4.20 Others
Edition 9.1
71
400KV, 230KV & 66KV SUBSTATION BUILDING, CIVIL AND STRUCTURAL REQUIREMENTS
4.20.3 To provide a test bushing room for each switchroom. Each test bushing room
must also be accessed by the respective switch room travelling crane (i.e. no
ceiling).
4.20.4 Where cable floor servicing 22kV network exceeds 3-metre height (floor to
floor), working platform requirements shall be incorporated. The detailed
design of the working platform is subject to approval of SPPG.
4.20.5 All iron and steel members shall be hot-dipped, galvanised and maintenance
free (e.g. staircase, etc.).
4.20.6 Tariff Metering Room shall be provided with a floor opening of size 100mm
diameter and to be located at the inner corner of the room for Tariff Metering
Panel.
4.20.7 Pressure Tank Room shall have the following requirements (for 400kV and
230kV substations):
a) 200mm wide x 50mm deep trough to be covered with chequered plate for
cable oil piping on the floor area.
4.20.8 To install luminescent warning strips to mark changes in floor levels and at
the top and bottom of each flight of staircase landings.
4.20.9 Concrete for building and civil engineering structures shall come from Ready-
Mixed Concrete (RMC) plants that are certified under Singapore Accreditation
Council (SAC)’s certification scheme.
4.20.10 For guarded installation with guardhouse where applicable, shelter for
security checking of vehicles of height 4.5 metres minimum to be provided.
Detailed design shall be submitted to SPPG for clearance. In addition,
clocking points for guards’ tour are to be provided.
Edition 9.1
72
400KV, 230KV & 66KV SUBSTATION BUILDING, CIVIL AND STRUCTURAL REQUIREMENTS
4.20.11 All external doors expose to weather shall have recess feature as a provision
of natural canopy to the external doors as to prevent rain water seepage.
4.20.12 Staircase shall have tread depth not less than 280mm.
Edition 9.1
73
400KV, 230KV & 66KV SUBSTATION SITE SUPERVISION
5. SITE SUPERVISION
5.1 General Requirements
5.1.1 The Developer's / Consultant's Architect and his Professional Engineers are
fully responsible for the supervision of construction of the substation building.
5.1.2 The Developer's / Consultant's Architect and his Professional Engineers shall
comply fully with all requirements of the local Authorities including The
Building Control Act, The Building Control Regulations and the like.
5.1.3 The Developer's / Consultant's Architect shall arrange for the minimum
recommended site staff, on full-time basis, to implement and supervise all
aspects of site work of the substation building
5.1.4 Resident Engineer (RE): A qualified engineer and registered with the
Professional Engineers Board of Singapore. (If required by The Building and
Construction Authority). The Resident Engineer shall be a Civil / Structural
Engineer with relevant site supervision of building construction experience.
5.1.7 SPPG reserves the right to amend any minor details (due to site conditions)
as and when required by our Site Project Engineer-in-Charge.
5.1.9 The Developer's / Consultant's Resident Engineer shall ensure that all floor
openings or hole openings on each floor including the switch room floors are
finalised with SPPG's Site Engineer-in-Charge immediately prior to giving
instruction to building contractor to commence making form-work for the
respective floors. (Regular site meeting between Developer's Architect, the
building contractor and SPPG's Site Engineer-in-Charge is recommended to
confirm all site matters arising).
Edition 9.1
74
400KV, 230KV & 66KV SUBSTATION SITE SUPERVISION
5.1.11 The SPPG's site Engineer-in-Charge shall be notified at least four weeks
prior to final floor rendering of all switchrooms. Floor rendering shall only
be proceeded upon confirmation with SPPG's Site Engineer-in-Charge.
5.1.12 Application for permanent water and electricity supplies for the substation
building shall be made by the Developer's / Consultant's Professional
Engineers on behalf of SPPG as agent for the owner (SP PowerAssets).
Approved type of water meter shall be installed at the main intake water
supply point in accordance with PUB's requirements.
5.1.13 Application of other services on behalf of SPPG (as the owner) if so directed
by SPPG or are required under the Authorities' instruction (e.g. dedicated line
for remote monitoring of fire-alarms, etc).
5.1.14 The installation and fitting shall be tested and certified fit by Developer's /
Consultant's Electrical Worker who shall have a valid EMA's licence as
Electrical Worker (Engineer's Grade) and also is a registered Professional
Engineer with the PE Board, Singapore. A copy of the Certificate of Fitness
for Turn-on shall be submitted to the SPPG Site Engineer-in-charge before
the turn-on of LV supply.
5.1.15 All other mechanical and electrical installations within substation building
such as overhead cranes, lifting hoist, fire-fighting and lightning protection
systems; earthing grid, emergency lighting and the like, are to be tested on
site by authorised officers and certified by Developer's / Consultant's
Licensed Electrical Worker (Engineer's Grade).
Edition 9.1
75
400KV, 230KV & 66KV SUBSTATION HANDOVER OF SUBSTATION BUILDING
6.1.2 The required numbers of door keys and padlocks are as detailed in the
approved latching arrangement. All the substation building door keys shall
have approved engraved labels and all the keys kept in an approved wall-
mounted key cabinet provided by the Developers / Consultant (See
Attachment C).
6.1.3 The required quantity of spare wall and / or floor tiles for purpose of future
maintenance by SPPG after the two years’ defects liability period.
6.1.4 The Developer's / Consultant's Architect is responsible to arrange for all the
documents of the substation building to be handed over to SPPG's Site
Engineer-in-Charge.
6.1.5 Please refer to next page for the Distribution List of final design and as-built
documentation to be handed over from the Developer / Consultant to SPPG
on the substation projects.
6.1.6 For as-built documentation, draft documents are to be submitted within two
(2) months before the date of handover of substation building. The
approved documents are to be submitted not later than three (3) months
after the date of handover of the substation building.
6.1.7 The Contractors and their workers working at the Substation premises (during
the DLP phase) shall enrol for the Safety @ SPPG course conducted by
Singapore Institute of Power and Gas (SIPG) at their own costs.
6.1.8 The design literature / principals for all C&S and M&E system shall be
handover to SP.
6.1.9 Warranty certificates for all C&S and M&E system shall be handover to SP.
6.1.10 Material testing certificates for all C&S and M&E system shall be handover to
SP.
6.1.11 The testing and commissioning reports for all C&S and M&E system shall be
handover to SP.
Edition 9.1
76
400KV, 230KV & 66KV SUBSTATION HANDOVER OF SUBSTATION BUILDING
6.1.12 The O&M for all M&E system shall be handover to SP.
6.1.13 Inventory list also known as Assets list to be in excel format for all asset (C&S
and M&E) system installed shall be handover to SPPG. (For Asset
documentation and collation).
6.1.15 Training for all system installation shall be provided to SP, up to maximum of
3 sessions for each system, one month before the actual handover dates.
6.1.16 All M&E system keys shall be kept in keypress in the control room with a
proper inventory list for the worker to draw out during maintenance.
6.1.17 The DLP maintenance schedule shall be submitted not later than 1 week
after the date of handover for the substation.
6.1.18 The consultant and main contractor shall be present during all the handover
site inspections.
6.1.19 Contractor or Consultant shall provide all the C&S and M&E inspection
checklist 1 month before the first inspection.
6.1.20 Contractor or Consultant shall have defect monitoring system to capture the
defects highlighted during the handover inspection.
Edition 9.1
77
400KV, 230KV & 66KV SUBSTATION HANDOVER OF SUBSTATION BUILDING
S/No Items
Edition 9.1
78
400KV, 230KV & 66KV SUBSTATION HANDOVER OF SUBSTATION BUILDING
II. The cover letter for endorsement shall specify the building completion date and
equipment access date. TRE’s Officer-In-Charge to be notified if there is any
changes/delay in the timeline.
Edition 9.1
79
400KV, 230KV & 66KV SUBSTATION HANDOVER OF SUBSTATION BUILDING
Edition 9.1
80
400KV, 230KV & 66KV SUBSTATION HANDOVER OF SUBSTATION BUILDING
N Warranties (Hard and Soft Copies) and Test Reports Yes/No Remarks
1 PE endorsement on electrical system test reports, Form
Certificate of Compliance,
Form Certificate of Readiness, single line diagrams
2 PE endorsement on ACMV system test reports and designs
3 Fire escape plan chart & fire extinguisher location plan
4 Fire alarm telephone line decam service report
NEA noise assessment and engine emission report for Standby
5 Generator
Lux Simulation, Hydraulic Calculation, Load Calculation, Volt Drop
6 Calculation Reports
7 Earthing Resistance and Soil Resistivity Test Report
8 CFD and EMF/EMC Report
Operational & Maintenance Manuals (O&M) and As Built Drawings Check List
Maintenance
As-Built O&M Asset Asset Recommended
& Servicing Remarks
Drawings Manuals Listing Lifecycle Maintenance Regime
Schedule
Maintenance
1
Boundary
Maintenance
2 Strategy
Overall Plans
(i.e.,
3 Permissable
GFA, Escape
1. Architectural
Route etc.)
Tiling/ roofing
/cladding/
raised floor
details and
4 materials
5 Landscape
Spares (e.g
6 Tiles / Panels,
etc)
MEWP (Mobile
Elevated
Working
7 Platform)
Civil
Overall Plan
2.
1
Register
Edition 9.1
81
400KV, 230KV & 66KV SUBSTATION HANDOVER OF SUBSTATION BUILDING
Combined
2 Services
Drawing (CSD)
Sanitary,
Electrical and
3
Mechanical
(SEM)
Drainage/
4
Sanitary Plan
Drainage/
5
Sump pumps
Panel and
6 Control / Wiring
Drawing
Waterproofing
7
details
Foundation
8
plan and details
Slab
9
reinforcement
Column
10
reinforcement
11 BIM Model
Lifting beams/
12
hooks
13 Flood Barriers
Perimeter
14
fences
Fall arrest
15
system
16 ST Submission
Single Line
1
Diagrams
Electrical
Installation (E.g
MSB, EMSB,
2
LV
Switchboard,
MTS etc.)
3. Electrical
Standby
3 Generator and
Diesel Storage
Lightning
4 Protection
System
5 Lighting
Switch Socket
6
Outlet (SSO)
Panel and
7 Control / Wiring
Drawing
Control and/or
1 Wiring
4. Fire Alarm and Protection
Diagrams
Fire Protection
System (E.g
Fire Pumps,
2
Jockey Pump,
Sprinkler Tank
etc.)
Fire Alarm
3
System
Hose Reel
4
System
Hydrant
5
System
Edition 9.1
82
400KV, 230KV & 66KV SUBSTATION HANDOVER OF SUBSTATION BUILDING
6 Dry Riser
Clean Gas
7 Suppression
System
Emergency
Voice
8
Communication
System
Fire Intercom
9
System
Fire
10
Extinguishers
11 Zone Charts
Overall
Schematic for
12 Fire Alarm and
Protection
System
1 Line Diagrams
2 Chillers
3 Cooling Towers
H2 Sensor (for
4
5. ACMV
Battery Room)
Mechanical
5
Ventilation Fan
6 FCU / CU
other ACMV
7 system
Panel and
Control / Wiring
8 Drawing
1 Hoist & crane
2 Roller shutter
6. M & E
3 Lifts
4 Escalators
Fire Curtain /
5
Shutter
1 BMS
Marshalling
2 panel
3 PA System
4 Telephone
7. Others
5 Telecom
Handicap
6 alarms
Crash Barriers
7 (Motorised or
Manual)
Turnstile /
8 Metal Detector
9 FIDS
Note:
As-built Drawings should make reference to the Page Number of the particular system
Additional Comments
Edition 9.1
83
400KV, 230KV & 66KV SUBSTATION HANDOVER OF SUBSTATION BUILDING
All above submission shall come with relevant endorsement by relevant Qualified Person (QP),
Professional Engineer (PE), Accredited Checker (AC), Registered Architect (RA), Licensed Plumber,
Specialist, Registered Survey, and/or Licensed Electrical Worker (LEW).
Edition 9.1
84
400KV, 230KV & 66KV SUBSTATION HANDOVER OF SUBSTATION BUILDING
Edition 9.1
85
400KV, 230KV & 66KV SUBSTATION HANDOVER OF SUBSTATION BUILDING
Relevant stakeholders
S/No Items
of SP Group
28. Architectural As-built drawings (color PDF & DWG), including but not limited to: **EHVN, *RNE/RNW, TFM,
a) Maintenance Boundary BDC, TRE, M&E, C&S
b) Maintenance Strategy
c) Overall plans
d) Tiling / roofing / cladding / raised floor details and materials
e) Landscape
f) Spare list
g) MEWP information (if available)
h) Land Owner Endorsement plans
i) URA Provisional Permission / Written Permission approvals with plans
j) As-built Survey plan and gazette order
29. Civil & Structural As-built drawings (color PDF & DWG), including but not TRE, TFM, M&E, C&S
limited to:
a) Overall plans
b) BIM models
c) Combined Services Drawings (CSD)
d) Structural, Electrical and Mechanical (SEM) drawings
e) Drainage / Sanitary plans
f) Drainage / Sump pumps
g) Waterproofing details
h) Foundation plan and details
i) Slab / column reinforcement
j) Perimeter fence
k) Fall arrest systems (if available)
l) Lifting hook / beam details and certificates (if available)
30. Electrical System As-built drawings (color PDF & DWG), including but not TRE, TFM, M&E
limited to:
a) Line diagrams
b) Electrical installation
c) Standby Generator(s)
d) Lightning Protection System
e) Earthing System
f) Lighting and power system plans
31. M&E As-built drawings, including but not limited to (color PDF & DWG): TRE, TFM, M&E
Fire system line diagram
Sprinkler system
Fire alarm system
Dry and Wet riser system
Gas suppression system
Emergency Voice Communication system
Fire extinguishers
ACMV line diagrams
Chiller system
Cooling tower system (if available)
MV system
Hoist & Crane
Roller shutter
Lifts
32. Temporary Fire Permit (if available) M&E, TFM, BDC
33. Fire Safety Certificate M&E, TFM
34. TFCC Submission Plan (if available) **EHVN, *RNE/RNW, TFM
35. CAAS Declaration by QP **EHVN, *RNE/RNW, TFM
36. Clearance Certificate for DP on Sanitary/ Sewerage **EHVN, *RNE/RNW, TFM
37. Certificate of Satisfactory Completion of Water Service Work (PUB) **EHVN, *RNE/RNW, TFM
38. Corenet submission documents with letter of compliance by QP to all relevant **TRE, C&S, M&E, TFM
authorities
39. Utilities Account
Edition 9.1
86
400KV, 230KV & 66KV SUBSTATION HANDOVER OF SUBSTATION BUILDING
Relevant stakeholders
S/No Items
of SP Group
40. NEA Noise Assessment and engine emission report for generators **EHVN, *RNE/RNW, TFM
41. Product operational life and depreciation **EHVN, *RNE/RNW, TFM
Test reports and Certificate of Fitness for Turn-On shall be submitted to the
SPPG’s Site Engineer-In-Charge before making arrangement with the Section to
turn-on of supply.
Edition 9.1
87
400KV, 230KV & 66KV SUBSTATION ATTACHMENT A
Our requirements and comments are in no way complete and cannot possibly
include all the conditions/requirements as and when imposed by all other relevant
Authorities.
Developer / Consultant shall indicate on the submitted drawings the design load
of various room & equipment plinths.
Edition 9.1
88
400KV, 230KV & 66KV SUBSTATION ATTACHMENT A
Edition 9.1
89
400KV, 230KV & 66KV SUBSTATION ATTACHMENT A
Please note that the loadings as listed below are for static loads only.
Developer / Consultant shall take into consideration the dynamic loads of the
respective switchgears from the switchgear suppliers (subject to
confirmation).
Edition 9.1
90
400KV, 230KV & 66KV SUBSTATION ATTACHMENT A
level)
NGR bay for 230/22kV & 66/22kV T/F (6.5 4.5 metres
ohms)
Edition 9.1
91
400KV, 230KV & 66KV SUBSTATION ATTACHMENT A
Edition 9.1
92
400KV, 230KV & 66KV SUBSTATION ATTACHMENT A
7.4.1 All floor openings in the switch rooms are indicative only and subject to
confirmation with SPPG's successful switchgear supplier.
7.4.2 Suitable wall and floor openings near to earth plate and column shall be
provided at the approved locations for running of earthing conductors:
7.4.3 2 nos. 50mm diameter outlets shall be provided at approved locations in the
22kV Switchroom for dehumidifier discharge. These outlets shall be
connected to pipes leading to drains at the ground level.
Edition 9.1
93
400KV, 230KV & 66KV SUBSTATION ATTACHMENT A
7.4.5 The width of the floor openings shall be provided to the following rooms:
Edition 9.1
94
400KV, 230KV & 66KV SUBSTATION ATTACHMENT A
7.4.2 The width of the switchroom floor openings (indicative only, subject to final
confirmation by SPPG) shall be provided as follows:
a) 400/230/66kV S/S
b) 230/66kV S/S
c) 66/22kV S/S
Edition 9.1
95
400KV, 230KV & 66KV SUBSTATION ATTACHMENT A
Edition 9.1
96
400KV, 230KV & 66KV SUBSTATION ATTACHMENT A
f) Doors for:
Height (clear) Width (clear)
i. 22kV switchroom 3.2m 2m
ii. LV room, building services main 3m 2m
switchroom
iii. 400kV, 230kV and 66kV control 3m 2m
rooms
iv. Communication room 3m 2m
iv. Bird proof covers shall be provided over the lifting void at the 2nd
storey level. Walkways around the lifting void shall be provided for
human access and maintenance purposes.
Edition 9.1
97
400KV, 230KV & 66KV SUBSTATION ATTACHMENT A
Edition 9.1
98
400KV, 230KV & 66KV SUBSTATION ATTACHMENT A
x. RTU room 5m x 3m
Edition 9.1
99
400KV, 230KV & 66KV SUBSTATION ATTACHMENT B
Preliminary information for purpose of design and final arrangement only after
equipment is confirmed.
All emergency light fittings shall be provided with self-contained battery pack
which shall be integrated together with normal supply.
Key plan of electric power points and switches shall be provided next to the
respective sub-distribution boxes.
No parts of the cable tray, conduits and supports will cause any obstructions
to the access of the emergency escape door, electrical fittings, etc., or pose
any safety hazard to people in the substation. 2-way switch shall be provided
at all exit/entrance, if there are 2 or more exit/entrance on the same floor.
Edition 9.1
100
400KV, 230KV & 66KV SUBSTATION ATTACHMENT B
b) Lamp pole shall be complied with Land Transport Authority (LTA) latest
specification or equivalent subject to the approval of SPPG.
i Lamp pole shall be located as far as possible from the fence and
away from the direct line of sight from the CCTV pole.
8.2 Stairways
c) EXIT lighting
Edition 9.1
101
400KV, 230KV & 66KV SUBSTATION ATTACHMENT B
a) Light Fittings: Twin-tubes mounted on both sides of the bay with longer
sides of the tube facing downwards. Switches for the lighting fittings.
Water-proof protective covers shall be provided. All outdoor fittings shall
be of weather-resistant type (IP65).
b) 200A TPN isolator for transformer oil purifier. Weatherproof cabinet shall
be provided for outdoor type.
e) 1 no. 13A socket outlet shall be provided for every alternate indoor
transformer / shunt reactor / radiator bay.
g) 63A TPN isolator (A/C Supply) for the SF6 Gas Recovery and
Containment System (for 75MVA Gas Insulated Transformer) shall be
provided when applicable.
e) 1 no. 13A socket outlet shall be provided for every alternate indoor
transformer bay.
f) Minimum 2 nos. 13A twin socket outlet shall be provided for every
alternate transformer room.
g) EXIT lighting
h) Emergency lighting
Edition 9.1
102
400KV, 230KV & 66KV SUBSTATION ATTACHMENT B
a) Light Fittings: Twin-tubes mounted on both sides of the bay with longer
sides of the tube facing downwards. Switches for the lighting fittings and
water-proof protective covers shall be provided.
c) Emergency lighting
d) EXIT lighting
Edition 9.1
103
400KV, 230KV & 66KV SUBSTATION ATTACHMENT B
e) Emergency lighting
f) EXIT lighting
h) 60A TPN isolator for 12-tonne lifting hoist to be located near maintenance
platform (for multi-storey buildings only).
i) 45A TPN isolator for 5-tonne travelling crane (to be located near
maintenance platform).
l) 63A 5-pin socket outlet complete with 63A TPN isolator for SF6 charger
unit.
m) 32A 5-pin socket outlet complete with 32A TPN isolator for SF6 charger
unit.
Edition 9.1
104
400KV, 230KV & 66KV SUBSTATION ATTACHMENT B
e) Emergency lighting
f) EXIT lighting
h) 60A TPN isolator for 10-tonne lifting hoist (to be located near
maintenance platform) (for multi-storey buildings only. Not required if a
12-tonne lifting hoist is available for same purpose).
i) 45A TPN isolator for 4-tonne travelling crane (to be located near
maintenance platform).
l) 2 nos. 63A 5-pin socket outlet complete with 63A TPN isolator for SF6
charger unit.
m) 32A 5-pin socket outlet complete with 32A TPN isolator for SF6 charger
unit.
Edition 9.1
105
400KV, 230KV & 66KV SUBSTATION ATTACHMENT B
d) Emergency lighting
e) EXIT lighting
g) 60A TPN isolator for 10-tonne lifting hoist (to be located near
maintenance platform) (for multi-storey buildings only. Not required if a
12-tonne lifting hoist is available for same purpose).
h) 45A TPN isolator for 4-tonne travelling crane (to be located near
maintenance platform).
k) 63A 5-pin socket outlet complete with 63A TPN isolator for SF6 charger
unit.
l) 32A 5-pin socket outlet complete with 32A TPN isolator for SF6 charger
unit.
Edition 9.1
106
400KV, 230KV & 66KV SUBSTATION ATTACHMENT B
8.10 38kV Switchroom (for 400kV & 230kV substations, when applicable)
d) Emergency lighting
e) EXIT lighting
g) 45A TPN isolator for 3-tonne travelling crane (to be located near
maintenance platform).
Edition 9.1
107
400KV, 230KV & 66KV SUBSTATION ATTACHMENT B
a) Twin tube light fittings are to be installed at 3.0m height from floor level
suspended from ceiling, and 2.4m height from floor level for wall-mounted
fittings. All light fittings which are suspended from ceiling over front of
switchgear shall be at least 1.5m from edge of switchgear floor opening
c) Emergency lighting.
d) EXIT lighting
h) 45A TPN isolator for 5-tonne lifting hoist (to be located near maintenance
platform) (not required if a 10/12-tonne lifting hoist is available for same
purpose).
j) 3 nos. 20A double-pole isolators (RCCB by-passed) for SPPG’s pilot wire
supervisory.witches of 2-way type
Edition 9.1
108
400KV, 230KV & 66KV SUBSTATION ATTACHMENT B
a) Twin tube light fittings are to be installed at 3.0m height from floor level
suspended from ceiling, and 2.4m height from floor level for wall-mounted
fittings. All light fittings which are suspended from ceiling over front of
switchgear shall be at least 1.5m from edge of switchgear floor opening.
c) Emergency lighting.
d) EXIT lighting
h) 45A TPN isolator for 5-tonne lifting hoist (to be located near maintenance
platform) (not required if a 10/12-tonne lifting hoist is available for same
purpose).
j) 8 nos. 20A double-pole isolators (RCCB by-passed) for SPPG’s pilot wire
supervisory.
b) Emergency lighting
Edition 9.1
109
400KV, 230KV & 66KV SUBSTATION ATTACHMENT B
a) Light fittings shall be provided with galvanised wire mesh guards. The
average lux level in this room shall be 300 lux. Location of two-way
switches shall be approved by SPPG.
c) Emergency lighting
d) EXIT lighting
Edition 9.1
110
400KV, 230KV & 66KV SUBSTATION ATTACHMENT B
c) Emergency lighting
d) EXIT lighting
b) Emergency lighting
c) EXIT lighting
Edition 9.1
111
400KV, 230KV & 66KV SUBSTATION ATTACHMENT B
b) Emergency lighting
c) EXIT lighting
8.18 Substation Automation System Room (for 400kV & 230kV substations)
b) Emergency lighting
c) EXIT lighting
b) Emergency lighting
d) 30A single phase emergency supply for supervisory battery charger (with
auto change over switch from generator for 230kV S/S only).
Edition 9.1
112
400KV, 230KV & 66KV SUBSTATION ATTACHMENT B
c) The room shall be mechanical ventilated and installed with clean gas fire
suppression system.
c) 2 nos. 20A DP isolator not controlled by RCCB for RTU battery charger.
(One to be positioned on each end of the RTU Room)
Edition 9.1
113
400KV, 230KV & 66KV SUBSTATION ATTACHMENT B
d) Sub D/B 60A SPN is required and to tap from D/B in 22kV switchroom.
Edition 9.1
114
400KV, 230KV & 66KV SUBSTATION ATTACHMENT B
8.23 Fire Pump Room (All fittings, switches and isolator shall be weather-
proof)
g) 2 nos. 200A TPN isolator for transfer pump (if the fire sprinkler water tank
is located at the roof top)
i) Emergency Lighting
j) EXIT Lighting
k) Cat ladder access to the top of fire fighting water tank must come with
caging. The cage material must be heavy duty that of harder or thicker
strength.
Edition 9.1
115
400KV, 230KV & 66KV SUBSTATION ATTACHMENT B
8.24 Water Tank Room (All fittings, switches and isolator shall be weather-
proof)
d) Emergency Lighting
e) EXIT Lighting
f) The top of fire fighting water tank shall be barricade along the perimeter
to prevent work accident
e) Lifting anchor point come with the Safe Work Load label shall be
provided.
Edition 9.1
116
400KV, 230KV & 66KV SUBSTATION ATTACHMENT B
a) 60A TPN isolator for 10-tonne lifting hoist (to be located near
maintenance platform)
b) 45A TPN isolator for 4-tonne or 5-tonne lifting hoist (to be located near
maintenance platform)
Edition 9.1
117
400KV, 230KV & 66KV SUBSTATION ATTACHMENT C
9.1.1 A minimum of 4-door hinges shall be used to support all heavy-duty or solid
doors.
9.1.2 In addition to locks and latches, door handles of approved quality and design
shall be provided on both sides of all doors to facilitate closing / opening.
9.1.4 The latching arrangement for all doors shall be submitted to SPPG for
approval before construction.
9.1.6 All locks shall be provided with at least 3 nos. individual keys each.
9.1.7 Every key shall be provided with a durable key tag with the respective room
names being properly engraved. Laminated sandwich type with black
surfaces and white core is preferred.
9.1.8 One number steel key cabinet of approved size to be provided at approved
location of 22kV switchroom while another key cabinet to be provided at
approved location of 66kV Control room. These boxes will contain all the
individual keys of respective door locks. Also key plan (A4 size) of various
floors showing locations shall be provided together.
Edition 9.1
118
400KV, 230KV & 66KV SUBSTATION ATTACHMENT D
10.1.1 Where Fire protection system is required by the Fire Safety & Shelter
Department to be installed in a transmission substation, fire alarm monitoring
shall be provided either to be monitored by CISCO or SPPG, whoever is
selected as the licensed operator for the fire alarm monitoring system. The
selected operator shall be confirmed by SPPG before the tender is called.
10.1.2 Where CISCO is selected to monitor the fire alarm system, the successful
tenderer shall liaise with CISCO for their requirements.
Edition 9.1
119
400KV, 230KV & 66KV SUBSTATION ATTACHMENT D
b) For 22kV and 66kV switchrooms which are located in separate buildings,
and transmission stations without 22kV RTU rooms. Two 10-pair pilot
cables shall be installed and terminated at the designated area as shown
in Schematic Diagram of Fire Alarm Cables.
Edition 9.1
120
400KV, 230KV & 66KV SUBSTATION ATTACHMENT E
Material
Aluminium plate shall be that of 2mm thickness.
The sheeting manufacturer shall provide a deed of warranty for 3 years and 5 years
respectively for Scotchlite grade and Scotchal grade in respect of adhesion, colour and
weather resistance for the material provided.
Construction
The aluminium plate shall be rectangular in shape of dimensions 80cm x 37cm x 2mm.
The aluminium plate shall have a drilled hole in each corner. All sharp edges and
corners shall be rounded. The font sizes and heights of the labels shall be as follows:
The blue reflective sheeting shall be stuck-on and completely over the whole aluminium
plate. The white reflective sheeting shall be overlaid onto the blue reflective sheeting.
All application of the stuck-on shall be using the dry mount roller method. The
substation name plate shall be rejected if any bubbles or air pockets appear on the
reflective sheeting. A computerized signage machine shall produce all the cast vinyl
films to be pasted in the overlay aluminium plate as shown in drawing no.
AVMB007-00-02 titled “Typical SP PowerAssets Substation Internal Name Plate”.
Installation
The substation nameplate shall be secured mounted on the substation door or wall. The
Developer / Consultant shall check with the SPPG Engineer-in-charge before fixing the
substation nameplate.
Edition 9.1
121
400KV, 230KV & 66KV SUBSTATION ATTACHMENT E – LIST OF DRAWINGS
Edition 9.1
122
400KV, 230KV & 66KV SUBSTATION ATTACHMENT E – LIST OF DRAWINGS
Edition 9.1
123
AVMB013-00-02 1
AVMB004-00-03 2
AVMB005-00-03 3
AVMB006-00-02 4
AVMB007-00-02 5
AVMB008-00-01 6
o90 [3.543] o90 [3.543]
Contents
1. GENERAL ............................................................................................................................. 2
2. MAIN GATE (AND/OR SECONDARY GATE, IF AVAILABLE) .................................................. 2
3. HOSTILE VEHICLE MITIGATION (HVM) BARRIER: MANUAL OR ELECTROMECHANICAL
CABLE BEAM (DROP- ARM BARRIER) ................................................................................. 3
4. PERIMETER FENCE LINE ...................................................................................................... 7
5. PERIMETER HOSTILE VEHICLE MITIGATION (HVM) BARRIER: BEAM BARRIERS AND/OR
BOLLARDS (PERIMETER BARRIER SYSTEM) ........................................................................ 8
6. FULL HEIGHT ROTARY OUTDOOR TURNSTILES ................................................................ 10
7. FACIAL RECOGNITION (FR) SYSTEM ACCESS CONTROL .................................................... 12
8. SECURITY GUARDHOUSE .................................................................................................. 18
9. SECURITY LIGHTING .......................................................................................................... 20
10 TRANSFORMER BAY SCREENS .......................................................................................... 21
11 BUILDING FAÇADE OPENING............................................................................................ 26
12 LOCKS AND SECURITY SYSTEMS ....................................................................................... 26
13 SECURITY SYSTEMS AND THEIR INTEGRATION TO INTEGRATED SECURITY AND OPERATION
SURVEILLANCE SYSTEM (SCCS) OF SP GROUP ......................................................................... 31
Edition 9.1 1
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
1. General
1.1. The following sections are for reference and information only. A Security
Consultant who has received clearance from SP’s Information & Corporate
Security Department shall be engaged by the Main Consultant/Contractor to be
responsible for advising on the specified works.
2.1. General
2.2. Swing gate, unless otherwise specified, is to be provided. Swing gate shall be
designed to open inwards into the substation compound when possible.
2.3. Swing gate shall be made of mild steel material. Mild steel grilled gate comprising
of mild steel hollow section shall not be smaller than 75mm x 50mm x 5mm thick
surround, mid-way horizontal and vertical support with infilling of mild steel flat
bars not exceeding 25mm x 6mm thick, at spacing of not more than 50mm centre
to centre, complete with 5 numbers of hinges, shoot bolt, drop bolts, etc., applied
with 1 coat of primer and 2 finishing coats of enamel paint. They shall be suitably
designed and properly installed to avoid misalignment, sagging and difficulties in
locking. Design shall be approved by SPPG.
2.4. A wicket (side gate) shall be provided at main gates of 400kV & 230kV substations.
Wicket gates at secondary gates will not be necessary unless otherwise specified
by SPPG.
2.5. The gate shall be constructed in the manner that it will not be easily toppled in
the event of accidental impact.
2.6. There shall be an anti-climb mesh bolted to the gate frame with angle bar, flat bar
and garage bolts and topped with 500mm high razor mesh. The razor mesh shall
also be installed above the gate posts such that the razor mesh appears
continuous between the perimeter fence line and the main gate.
2.7. If the gate is of sliding type, there shall be an entry and exit safety sensor
(photobeam sensor. See Para. 13.22.22).
2.8. The Developer / Consultant shall be responsible for the design, supply, installation,
testing and commissioning of the swing gate or sliding gate, if applicable.
2.9. All drawings on the design of the above systems shall be endorsed by a
Professional Engineer and submitted to SPPG for reference.
Edition 9.1 2
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
3.1. The barrier shall be manual type (non-motorised) for 66kV substations and all-
electric (motorised) for 230kV and above substations.
3.2. The Drop-Arm Barrier shall be located no more than 1.2 meters behind the main
(and/or secondary) gate. The barrier shall open vertically.
The barrier shall consist of 3-phase electric motor and its accessories shall be
housed in an outdoor lockable well-ventilated cabinet/box of IP rating of 65 to
prevent over-heating and moisture accumulation.
In the event of failure, the barrier shall be able to operate manually by a single
person.
The control panel, for operation of the barrier, shall be provided to control the
rising and lowering of the drop-arm in both local and remote mode. The remote
control shall be of wireless encrypted type.
The Contractor shall provide system operation manual and training sessions on
the operation of barriers. A minimum of three (3) training sessions per installation
site shall be provided. Schedule of the additional training sessions shall be
provided at a later stage.
All electrical works and drawings shall be carried out and duly certified by a
Licensed Electrical Worker (LEW).
3.4. The construction of the concrete plinth, pit, etc. and all associated Works shall be
carried out by the Contractor.
3.5. The barrier shall be certified to meet any of the following test standards, or
equivalent:
Edition 9.1 3
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
a. ASTM 2656, Standard Test Method for Crash Testing of Vehicle Security
Barriers,
i. Rating: M30 P1
b. PAS 68
i. Rating: V/7,500[N2]/48/90:1/0
c. IWA 14-1
i. Rating: V/7,200[N2A]/48/90:1
3.7. The methods of installation and the design of the RC structure of the proposed
crash barrier shall be duly endorsed by a Civil & Structural and/or Mechanical
Professional Engineer prior to installation to ensure compliance to
Manufacturer’s requirements. Site installation and inspection reports shall be
endorsed by the Professional Engineer accordingly.
3.8. Contractor shall submit his proposed Project Schedule including key milestones,
barriers delivery schedule, manpower deployment, and etc. that meets the
timeline set forth by SP.
3.9. Any cost incurred due to design deviation from the original, approved design shall
be deemed to be included as part of the scope including the requirement to
conduct an actual crash test at an approved, independent test centre to validate
the design.
3.10. The Contractor shall include all necessary Works required to construct the crash
barrier at Site to comply with the crashworthiness requirement.
Edition 9.1 4
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
3.11. The crash barrier shall be a good grade assembly containing a hinged rigid steel
wire rope crash beam, counterweights; gas assisted counterbalance struts,
securable by padlock provision and unit bollards. The barrier shall be secured by
means of a padlock when it is in the down position.
3.12. The beam assembly of the barrier shall absorb the force of an intruding vehicle
and then be able to transmit the force to the foundation bollards of the barrier.
3.13. The barrier shall be able to provide sufficient height clearance for heavy vehicles
(e.g. fire engines, refuse collection vehicles etc.) to pass through the driveway
when the drop-arm is in the fully up position.
3.14. The frame and structure of the barrier shall be adequately treated with suitable
coating to ensure maximum protection against environmental corrosion and the
harsh outdoors environmental elements. The barrier shall be provided with two
colours (yellow and black) architectural grade weatherproof reflective paint /
stickers. The exact colour shade of the paint / stickers shall be submitted for SP’s
approval.
The Vendor shall provide SP with a 24-hour telephone number for reporting any
faults, during and after DLP.
The Vendor shall also provide mobile contacts of supervisors who must be readily
contactable, during or after office hours, to SP for any matter pertaining to the
crash barriers.
The Vendor shall submit maintenance reports, ad-hoc fault and repair reports to
SP within 3 days from the date of completion.
The Vendor shall, at his own expenses, obtain, store and maintain serviceable
condition of essential parts and materials of the crash barriers, which are readily
available for the making good of any loss of or damage to the equipment and for
the replacement of defective parts discovered during DLP (24 months).
The Response Time shall commence from the time that a breakdown, fault or
defect is detected (whether during DLP, routine servicing or inspection or upon
SP’s report (verbal or written) to the Vendor, up to the time that the Vendor
arrives at the site of the relevant breakdown, fault or defect.
Edition 9.1 5
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
The Vendor shall be responsible to respond to the breakdown, fault or defect and
the Response Time shall apply during and after normal working hours, including
Sundays and Public Holidays.
b. The Vendor shall be liable to adhere to the Response and Resolution Times
as shown below.
i. Response Time
ii. The Contractor shall be responsible to rectify the breakdown and comply
with the Resolution time as shown in Table 3-1, including Sundays and
Public Holidays.
Edition 9.1 6
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
Minor (M)3 One (1) Working Day Next Working Day One (1) Working Day
4.1. The total height of the perimeter fence shall be no less than 3500mm (above
grade level) at any point of the perimeter fence line, unless otherwise specified.
4.2. Anti-climb welded wire mesh shall be installed and topped with razor mesh.
4.3. Fence fabric to be constructed from low carbon steel wire with minimum tensile
strength of 800 kg.
4.4. Mesh size of the welded mesh shall be 75mm (H) by 12mm (W) to discourage
fingerhold onto the fence fabric.
4.5. The fence fabric shall be manufactured of hot dipped galvanized wire and of
Gauge size 6 (4mm diameter).
4.6. Welded mesh is to be embedded at least 25mm deep into the reinforced concrete
footing (approximately 300 mm thick at the height of 150mm - 200mm from grade
level).
4.7. Wherever a Perimeter Barrier System (Beam Barriers and/or Bollards) cannot be
installed, the welded mesh is to be embedded at least 25mm deep into a crash-
rated low knee wall.
This low knee wall must comply with the crash worthiness requirements under
Para. 5.
1
System failure, connection/communication loss, actual intrusion, etc.
2
Unable to arm/disarm, icom fail.
3
Siren or strobe light faulty, cable wear and tear, etc.
Edition 9.1 7
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
The fence fabric of the perimeter fence shall be no less than 2350mm (H) as
measured from top of the low knee wall to the base of the razor mesh topping.
The top surface of this low knee wall shall be angled downwards towards the
outside of the substation to discourage foothold on top of the wall.
4.9. The welded mesh fence fabric shall be secured to the fence posts with all nuts and
bolts made tamper-proof either by design, peening or welding.
4.10. The razor mesh shall be affixed to the top of the welded mesh anti-climb fence
fabric to form a continuous deterrence against scaling.
4.11. Razor mesh to be at least 500mm (H) and attached securely to the fence line.
4.12. Razor mesh blade to be 0.5mm thick with 25mm (L) x 12mm (W) and intermesh
spacing of 30mm.
4.13. Any structure, equipment or fixture within the site of the substation shall be
located at least 1.5m away from the perimeter fence line and not taller than 2.0m
in height. This does not apply to mandatory items including, but not limited to
street lamp posts, CCTV camera poles, trees, bollards, etc.
5. Perimeter Hostile Vehicle Mitigation (HVM) Barrier: Beam Barriers and/or Bollards
(Perimeter Barrier System)
5.1. The Perimeter Barrier System protection line shall be constructed to form a
continuous physical perimeter protection line around the substation.
5.2. The Contractor shall propose the most appropriate and multiple products solution
(at least 3 products that comply to the crashworthiness requirement stated in
Para. 5.4). Perimeter Barriers System along the perimeter of the substations that
meets SP’s objectives of providing an anti-crash perimeter to the intended
protection requirement.
5.3. The Contractor shall be responsible for the design, supply and installation of all
related Works for the complete set of Perimeter Barrier System to be as close as
possible to the perimeter fence line, within the site of the substation.
5.4. The barriers shall be certified to meet any of the following test standards:
a. ASTM 2656-15, Standard Test Method for Crash Testing of Vehicle Security
Barriers,
Edition 9.1 8
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
i. Rating: M30P1
b. PAS 68
i. Rating: V/7,500[N2]/48/90:1/0
c. IWA 14-1
i. Rating: V/7,200[N2A]/48/90:1
5.6. The Contractor shall be responsible for all associated civil works from the
excavation of the trenches/pit, cutting of roads, construction of concrete plinth
etc. for the new Perimeter Barrier along the perimeter of the substations.
5.7. The Contractor shall submit shop drawings for approval by SP prior to installation.
All shop drawings shall be duly endorsed by a Professional Engineer before
submission.
5.8. Contractors are advice to as much as possible to avoid locating the foundation of
the Perimeter Barriers above any of SP’s incoming and/or outgoing underground
power cables. If unavoidable, the depth of the foundation of the Perimeter
Barriers shall allow a clearance gap spacing of at least 200mm to avoid touching
the underground power cables.
5.9. The Contractor shall submit the proposed Project Schedule including key
milestones, barriers delivery schedule, manpower deployment, etc. that meets
the timeline set forth by SP.
5.10. The Contractor shall provide the Perimeter Barrier System installation method
statements for each individual site for approval by SP before commencing the
Works.
Edition 9.1 9
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
5.11. The Contractor is to take note that the installation of the Perimeter Barrier System
along the perimeter maybe subjected to approval by the Security Authorities. In
the event that any installation method defers from the Manufacturers’
recommended methods of installation, the Contractor maybe required to
substantiate his design calculations to the satisfaction of SP.
5.12. Any cost incurred due to design deviation from the original, approved design shall
be deemed to be included as part of the scope including the requirement to
conduct an actual crash test at an approved Test Centre to validate the design.
5.13. The Perimeter Barriers shall be easy to maintain and blend in aesthetically to the
surroundings.
5.14. The minimum height of the Perimeter Barrier System shall not be less than
650mm measured from the finished ground level to the top of the Perimeter
Barriers. The height of the Perimeter Barriers shall be capable to be varied to suit
the security threat analysis subjected to SP’s final approval.
5.15. There shall not be any gap between the Perimeter Barrier System and other HVMs
along the perimeter line. If a gap is unavoidable, the clear spacing of the gap shall
not exceed 1.2m.
5.16. The Contractor shall submit the shop drawings indicating clearly the locations of
the Perimeter Barrier System along the perimeter duly endorsed by a Professional
Engineer for approval by SP before the commencement of the Works.
5.17. Shrubs planted along the Perimeter Barrier System, if any, shall be reinstated.
6.1. The Contractor shall design, supply, install, test and commission the proposed
rotary turnstile unit, including and not limited to the following:
Entry/exit Lane with Facial Recognition access control and video intercom (see
Para. 7) on both sides for Turnstile Entrance.
Edition 9.1 10
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
Free operation (exit only) during power failure and upon activation of fire alarm.
Remote release button to control the rotary turnstile shall be installed at the
respective guard house.
6.2. The proposed turnstile unit shall be used in conjunction with an Electronic Access
Control System and Video Intercom to provide an effective and cost-effective
physical barrier to unauthorised entry.
6.3. The proposed turnstile units shall be fabricated from stainless steel grade 316 and
of Hairline Matt finishes. The Contractor shall submit the sample for approval.
6.4. The Contractor shall make good and terminate to the existing fence line after
installing the proposed turnstile on site.
6.5. The proposed single walkway bi-directional full height turnstile shall be a high
security entrance control for external installation and must be manufactured from
the factory.
6.6. The overall dimension of the single walkway shall be at least 1520(W) x 2100(D) x
2375(H) mm with a clear walkway ceiling height of 2000 mm.
6.7. The construction of the frame sections shall be of box heavy steel, galvanised for
anti-corrosion protection and powder-coated in a range of standard colours.
6.8. A canopy shall be provided as standard and form an integral part of the turnstile,
painted to a similar colour as the turnstile frame. Concealed rainwater down pipe
must be provided.
6.9. The rotor assembly shall be steel, all welded contraction with straight arms, hot
dipped galvanised with powder-coated finishing.
6.10. The central rotating column of the three-segment rotor assembly (120 degrees
configuration) shall be of hot dipped galvanised mild steel cylindrical section to
which are welded straight tubular rotor bars.
6.11. The bottom bearing supporting the central rotating column shall be a ball and
cone iron bearing and a phosphor bronze bearing at the top end.
6.12. All parts of the electro-mechanical head mechanism shall be of hardened steel
and machined cast iron control element and shall be well protected against
corrosion, contamination, dust, etc. A positive action lock shall be provided to
prevent two passages at any one time.
Edition 9.1 11
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
6.13. The turnstile shall be provided with microprocessor control logic housed within
the unit and no separate switch or control boxes are allowed to be accommodated
elsewhere. The control shall be able to integrate fully the proposed card access
system and have facilities for:
Time out facility (adjustable 5-30 secs) to cancel the ‘Go’ signal if passage is not
completed within a pre-set time.
6.14. A stainless-steel grade 316 reader pedestal stand shall be supplied as standard at
both sides to accommodate the video intercom, card reader and facial recognition
reader.
6.15. Red and Green status light shall be provided as standard and flushed mounted
into the upright of the unit at eye level position. The red LED is continuously
illuminated until a Go’ signal is received from the Electro-mechanical head
mechanism, not at a ‘Go’ signal received from the access reader, when the green
light is illuminated indicating that mechanism is unlocked and passage is
permitted.
6.16. A weatherproof emergency door release (“Break Glass”) unit shall be installed. It
shall:
be located at least 1.5 meters behind the turnstile, such that it is beyond the reach
of a person standing right outside the perimeter fence line or turnstile.
7.1. The Contractor shall design, supply, install, test and commission the proposed FR
unit consisting of and not limited to the following:
7.2. The FR system and card reader-based access control through existing turnstiles
via 2FA.
Edition 9.1 12
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
7.4. The hardware necessary to complete the FR system installation, including all but
not limited to:
All FR system hardware and licenses required to enable full functionality of the
system, e.g. server license, network switch, controllers, etc.
2 Outdoor Video Intercom Units. The video intercom units shall be located at the
entry and exit points of the turnstile and shall be able to communicate with the
Company’s existing Master Intercom at SCC and ASCC.
Two IP65 rated FR Stand that houses the FR reader, iClass SE Card Reader, Video
Intercom Unit, Break Glass Button (For Exit Only) and LED indicators shall be
supplied and installed at the entry and exit point of the turnstiles.
The FR system shall be able to integrate with SP’s turnstile to provide access
control functions. Integration works to the turnstiles to enable access control by
the face recognition system shall be included in the scope. Such works include
the mounting and wiring of equipment (e.g. camera) on the turnstiles and
integrated to fire alarm system for automatic release during fire activation.
7.5. The Contractor shall provide complete drawings that include the following:
Mounting drawings
7.6. The Contractor shall also provide the Manuals and Product Data as follows:
Installation manuals
Edition 9.1 13
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
7.7. Qualification
The installer shall be trained by the Vendor to install, configure and commission
the FR access control system.
7.8. Certification
7.9. The Vendor shall submit certifications that its face recognition algorithm has been
independently tested by internationally recognized testing institutes and is top
rated for accuracy and speed.
7.10. Products:
Product Description
a. The solution shall integrate back to the existing facial recognition servers
and capable of managing various hardware devices including cameras, door
controllers etc. The building access control system shall be able to manage
and monitor all connected hardware via a fast Ethernet network over TCP/IP
network.
b. The solution must be able to integrate with the existing building access
control system of SP without extensive customization.
c. The solution must be able to have anti-spoofing feature which will detect
false identity that are presented/ produced through a photo, camera, etc.
with intention to forge the identity to gain access.
Network Communication
b. The system shall include support for the following minimum network
configuration settings:
i. DHCP client
v. IP address (IPv4)
Edition 9.1 14
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
c. The system shall be able to act as a DHCP server and allocate IP addresses
(given a certain range) to hardware devices.
The system shall support integrating to 3rd party systems such as access control
systems, CCTV systems etc.
The FR system shall be able to support both front-end image comparison (device
offline matching) and back-end image comparison for 1: N matching.
The FR system shall be able to support access control for turnstiles and doors. It
shall be able to set the duration for the access control period.
The FR system shall be able to detect tailgate personnel and alert, in junction with
the facial recognition access control.
The FR system shall be able to have the function to alert for blacklist personnel.
The FR system shall be able to display the matching score for face matching
regardless if the score is below or above the threshold.
The FR system shall be able to have search functions including and not limited to
the following:
a. Search by photo.
Edition 9.1 15
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
The FR system shall be able to have, but not limited to the following types of alerts,
and shall be able to define different alert types using colour coding for easy
identification
a. Whitelist match
c. Blacklist alert
d. Stranger alert
The FR system shall allow user to select the captured images so that the system
will show the trajectory based on the selected images for user to track and trace
the capture images. The trajectory result shall be allowed to export out the
records.
The FR system shall be able to allow both single image enrolment and bulk
enrolment for facial. System shall allow up to 10,000 photos at any one time for
bulk upload.
a. rejected during the bulk upload, reason for rejection shall be clearly given
so that the user will be able to follow up.
b. rejected due to the low photo quality, will be automatically rejected with
the reason given to user for follow up.
The FR system shall be able to perform 1:1 photo image comparison in the system
by inputting two photos on the Web interface and returning the matching score.
The FR system shall be able to perform photo quality check in the system by
inputting one image on the Web interface and photo quality will be returned as a
result in the system on the web interface.
The FR system shall be able to support both Http and Https Restful API interface
for integration with external systems.
All communications between the client and the server shall be https.
Edition 9.1 16
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
The FR system shall be able to support up to 300,000 image libraries for matching.
Response time for door/gate opening upon face recognition matching is <1
second for backend matching.
Response time for door/gate opening upon face recognition matching is <= 300
milliseconds for device frontend matching.
True Accept Rate (TAR): When image library is 1000, and FAR is 0.1 , the
recognition accuracy is > 99%.
Access point shall support access profile setup. Access profile shall include the
following characteristics:
a. Entry is allowed with Facial and Card (iClass SE) Authentication (2FA)
The FR system shall be able to count the number of people entering or exiting at
specific access point.
FR Device can perform FR matching at the edge site. When there is network
outage in the backend servers, operation will not be affected.
FR Device must be able to have anti-spoofing feature which will detect false
identity that are presented/ produced through a photo, camera, etc. with
intention to forge the identity to gain access.
Any non-liveness detection should be able to send the alert to backend system
immediately.
Edition 9.1 17
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
FR Device shall be able perform the matching at low light environment, minimum
0.5 lux.
Image Library Capacity shall support up to 50k photo images at edge for offline
matching.
FR Device shall have the flexibility to configure the detection distance, range from
0.5m to 2m, dependent on the site situation.
7.16. Training
The Contractor shall provide a competent, certified trainer who has extensive
experience on the installed systems to train the operators of all system
components and functionality.
8. Security Guardhouse
8.1. General
Edition 9.1 18
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
Possible threats against the guardhouse in the facility will range from physical
attacks by person(s), armed or unarmed to the use of firearms against the guard
to further an intended criminal or terrorist act.
Guardhouse Facade
a. All glass opening within the operational areas of the guardhouse shall be
constructed of 9mm ballistic resistant glass in accordance to BS EN 1063
Class BR2 or anti-bandit glazing designed in accordance with BS EN 356:2000.
b. Glass and framing designs must have passed actual testing conducted by
qualified independent agencies. The test results as well as relevant
certification of proposed ballistic resistant glass or glazing shall be
submitted to SP for approval of use.
e. There shall be a card exchange slot at the counter to facilitate pass exchange.
f. There is no special requirement for the door leading into the guardhouse
except that the door shall be positioned out of direct line of sight from
outside the facility.
g. If the placement of the door leaves the security personnel within the
Guardhouse vulnerable to weapons fire from outside the facility, the
developer shall, at his own cost, provide doors and frame affording the same
amount of protection against firearms up to 9mm calibre.
Guardhouse Roof
a. The reinforced concrete roof design shall be no less than 150mm thickness
reinforced concrete and 100% waterproofed and designed to discourage
birds from nesting.
Edition 9.1 19
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
b. Metal roof shall have no laps and be laid in one span with one length roofing
sheet. No overlapping and joints are allowed.
d. No roof gutter is allowed at the roof. The design of the roof must take into
consideration to ensure no retention and proper natural discharge of
rainwater.
Guardhouse Floor
a. The floor of the interior areas of the Guardhouse shall be raised such that
security personnel sitting within the operational areas of the Guardhouse
shall be at the eye-level of a visitor standing outside.
Guardhouse Features
a. Each Guardhouse shall have no less than 3 units of CCTV with 2 nos. of
cameras overlooking the interior of the operational area of the Guardhouse
and 1 no. overseeing the area outside where passes are exchanged. Please
refer to Attachment E and Attachment G of “Guidelines / Requirements for
Above Ground Transmission Substation Buildings (For 400kV, 230kV &66kV
Standalone Substation only)” for the Guardhouse and the CCTV system in
Guardhouse, respectively.
9. Security Lighting
9.1. Lamp pole shall be located as far as possible from the fence and away from the
direct line of sight from the CCTV pole.
9.2. External lighting for the substation building and security lighting of approved
design / type within substation compound shall be controlled by timer or other
approved method. Light fittings shall be accessible by maintenance personnel
without the use of standard tower wagons. For perimeter lighting, the top cone
perimeter lighting to be adopted so that CCTV camera will not be over-exposed
with direct lighting.
Edition 9.1 20
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
10.1. Transformer bay screens shall be provided at transformer bays for outdoor, semi-
outdoor and / or indoor types, where applicable, where the transformers are of
75MVA and above.
10.2. The Contractor shall design, supply and install transformer bay screens at the
transformer bays that comes with double swing gate, removable supporting
structure using galvanised mild steel frame and aluminium perforated sheet at
front, back and side sections of outdoor transformer bay. The Contractor shall also
supply and install knotless netting at the top section of outdoor transformer bay.
a. Front, back and side sections: Detachable perforated steel sheet (c/w
double leaf swing gate for human accessibility to the transformer bay).
Edition 9.1 21
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
Semi-outdoor Transformers (Type B). Refer to Figure 10-2 and Figure 10-3.
a. Front section: Detachable perforated steel sheet (c/w double leaf gate for
human accessibility to the transformer bay) and welded mesh.
Edition 9.1 22
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
Indoor Transformers (Type C). Refer to Figure 10-4 and Figure 10-5.
a. Front section: Detachable welded mesh up to 3.5 m height (c/w double leaf
gate for human accessibility to the transformer bay). Removable wire rope
at 3.5 m height and above.
Edition 9.1 23
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
10.3. Specifications
General
a. The proposed design for the transformer bay screen shall facilitate
occasional dismantling of the screen panels for accessibility into the bay.
Perforated Sheet
a. The perforated sheet panels size shall not be larger than 2m x 1m and of
thickness approximately 3mm.
b. The sheet pattern shall be of slot hole perforation with hole size of 0.125 x
0.75 that are side staggered and an open area of 35% (Figure 10-6).
Edition 9.1 24
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
c. The Contractor shall submit the design and method of installation for SP’s
approval.
Knotless Netting
c. The accessories fittings shall be of stainless steel material and the knotless
netting recommended shall be light in weight.
The earth electrode resistance measured at each inspection pit shall have earthing
resistance value of less than ten ohms.
The lightning lead down conductor together with the conductor tape clip is
recommended to be concealed in the building wall. The down conductor
(preferably copper tape) shall ensure a low impedance path for the lightning
discharge. Provision shall be made to prevent concrete spalling / damage after
discharge of lightning. The test clamp shall be located at 1.5m above ground level.
Sample of the copper tapes and bi-metallic connectors shall be submitted for
superintending officer’s approval prior to installation.
Edition 9.1 25
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
The Contractor shall be required to submit samples of products and materials for
approval before implementation. The submissions shall include brochures,
pamphlets, technical data, methods of applications, etc. The costs of such
provisions shall be included in the scope.
The Contractor shall, at his own expense, provide the required materials, fittings,
or perform any additional works which are not indicated in the specifications or
drawings but deemed necessary for the fulfilment of this quotation. In addition,
the Contractor must conform to good and acceptable trade practices even though
they are not explicitly mentioned in the quotation.
The Contractor is to exercise due care when executing the works and any affected
area or damage arising shall be made good, repaired or replaced to their original
conditions.
The defect liability period shall be 24 months and shall commence from the official
date of completion of all works as agreed by both the Contractor and SP.
The Contractor shall carry out inspections of the systems on an annual basis and
provide SP with the detailed inspection reports with recommendations during the
warranty period.
11.1. Ideally, there should be no building openings, e.g. windows, louvers, roller
shutters, etc. on the building façade of a room containing a Critical Asset (CA). A
list of CA rooms may be provided upon request.
11.2. If there is a requirement to have an opening behind a CA, it shall be louvers placed
high up as close to the ceiling as possible and located at a height minimally above
the height of the equipment behind.
12.1. The door lock function arrangement in Table 12-1 shall be coded as follows:
Edition 9.1 26
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
K - Entrance function:
Latch operated by lever handle from either side. Deadbolt operated
by key or thumbturn to lock the door
N - Passage function:
Latch operated by lever handle from either side, no key required
S - Storeroom function:
Latch operated by lever handle from inside and by key from the
outside. Outside knob always rigid
12.2. Door lock function arrangement for all doors shall be submitted to SP for approval
before construction.
Edition 9.1 27
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
1 230 / 400 Guard house toilet K N/A N/A N/A N/A N/A N/A
Access into level 1 staircase (min 1 main with an
1 66 / 230 / 400 MUS MUS Y Y Y Y Y
alternate access either lift or staircase)
1 66 / 230 / 400 Lift lobby MUS MUS Y Y Y Y Y
1 66 / 230 / 400 Public toilet near lift lobby MUS N/A N/A N/A N/A N/A N/A
1 66 / 230 / 400 Escape door 1 way (min 2 on 3rd staircase onwards) SNL N/A N/A Y Y Y Y
1 66 / 230 / 400 Sprinkler pump room MUS N/A N/A N/A N/A N/A N/A
1 66 / 230 / 400 500/200/150/75MVA transformer bay in substation MUY N/A N/A N/A N/A Y (PTZ) N/A
1 66 / 230 / 400 NGR bay MUY N/A N/A N/A N/A N/A N/A
1 66 / 230 / 400 10/1MVA transformer bay in substation MUY N/A N/A N/A N/A Y (PTZ) N/A
Spare bay 75/10/1MVA transformer bay in the
1 66 / 230 / 400 N/A N/A N/A N/A N/A Y (PTZ) N/A
substation
1 66 / 230 / 400 Transformer bay in depot MUY N/A N/A N/A N/A Y (PTZ) N/A
1 66 / 230 / 400 Equipment room S N/A N/A N/A N/A N/A N/A
1 66 / 230 / 400 MDF/TER room S N/A N/A N/A N/A N/A N/A
1 230 / 400 E-GEN support building services main switch room MUS N/A N/A N/A N/A N/A N/A
Edition 9.1 28
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
1 66 / 230 22kV tertiary room for 230kV substation MUS N/A N/A N/A N/A N/A N/A
1 230 / 400 66kV tertiary room for 400kV substation MUS N/A N/A N/A N/A N/A N/A
1 230 / 400 Aircon plant room MUS N/A N/A N/A N/A N/A N/A
1 66 / 230 / 400 Water retention tank MUS N/A N/A N/A N/A N/A N/A
Above 1 230 / 400 Switchgear room 22kV A&B for Distribution Network MUK S N/A N/A N/A N/A N/A
Switchgear room 22kV A&B for Distribution Network
Above 1 230 / 400 MUK S Y Y Y Y Y
(for source switchboard)
Above 1 66 / 230 / 400 Smoke stop lobby N N/A N/A N/A N/A N/A N/A
Above 1 66 / 230 / 400 Staircase leading to escape door SNL N/A N/A N/A N/A Y Y
Above 1 66 / 230 / 400 Maintenance room S N/A N/A N/A N/A N/A N/A
Above 1 66 / 230 / 400 Equipment room S N/A N/A N/A N/A N/A N/A
Above 1 230 / 400 RTU room (for 22kV comms) MUD N/A N/A N/A N/A N/A N/A
RTU room (for 22kV comms) (for source
Above 1 230 / 400 MUD N/A Y Y Y Y Y
switchboard)
Above 1 66 / 230 / 400 Switchgear room 400kV/230kV/66kV MUS 1 MUS; Rest SNL Y Y Y Y (PTZ) Y
Above 1 66 / 230 / 400 Relay/Control room 400kV/230kV/66kV MUS 1 MUS; Rest SNL Y Y Y Y (PTZ) Y
Above 1 66 / 230 / 400 Battery room MUS MUS N/A N/A N/A N/A N/A
Edition 9.1 29
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
Above 1 66 / 230 / 400 Access to lifting void N N/A N/A N/A N/A N/A N/A
Above 1 66 / 230 / 400 Test bushing 400kV/230kV S N/A N/A N/A N/A N/A N/A
Above 1 66 / 230 / 400 Test bushing 66kV S N/A N/A N/A N/A N/A N/A
Above 1 230 /400 Pressure tank room (Oil) MUS N/A N/A N/A N/A N/A N/A
Above 1 66 / 230 / 400 RC flat roof MUS N/A N/A N/A N/A N/A N/A
Above 1 66 / 230 / 400 Cable floor entrance MUS 1 MUS; Rest SNL Y Y Y Y Y
Swing door on/beside roller shutter to
Above 1 66 / 230 / 400 400/230/66kV switchgear room MUY NA N/A N/A N/A Y Y
(Roller shutter operated from inside the room)
Maintenance platform to 400/230/66kV switchgear
Above 1 66 / 230 / 400 MUS N/A Y Y Y Y Y
room
Above 1 66 / 230 / 400 Loading platform N/A N/A N/A N/A N/A N/A N/A
Above 1 66 / 230 / 400 Maintenance catwalk N/A N/A N/A N/A N/A N/A N/A
Above 1 66 / 230 / 400 Tariff metering room (co-located with LTA) MUS N/A N/A N/A N/A N/A N/A
Above 1 66 / 230 / 400 Ancillary office S S N/A N/A N/A N/A N/A
Edition 9.1 30
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
13. Security Systems and their integration to Security Command Centre System
(SCCS) of SP Group
13.1. The intent of this specification (“Specification”) is to define the functional and
technical requirements of the various front-end security systems for the
Company’s installations and their integration to the Security Command Centre
System (SCCS) of SP Group.
13.2. Unless otherwise defined herein or if the context requires otherwise, all
capitalized terms herein shall bear the meanings ascribed to them in the General
Conditions of Contract.
Edition 9.1 31
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
13.4. The various front-end security system to be provided shall be of a similar or better
make technology and compatible for seamless interfacing to the existing SCCS.
a. The Building Access Control System (“BACS”) for the station access control
and security; and
c. The Public Address (“PA”) System for voice messages paging; and
d. The Fence Intrusion Detection System (“FIDS”) for monitoring of the station
perimeter security.
13.6. The various front-end security system to be provided shall be able to operate
independently in the event of failure of any sub-system component(s).
13.8. Users of the SCCS, with the given correct level of security, shall be able to view all
the information on the BACS, FIDS, CCTV, DA system from the same Security PC
Workstation.
13.9. Data such as videos, alarms, commands and events from the various front-end
security system are routed from each station through the Company’s
Metropolitan Area Network (“MAN”) to existing SCCS Servers for processing and
storage. Users with correct security access level are able to remotely add / delete
/ reconfigure/ update information or data to the various front-end security
system, without having to physically dispatch staff to the sites to carry out such
activities.
Edition 9.1 32
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
13.10. Uninterruptible power supplies shall be provided for the various front-end
security system to ensure continuity and integrity of operations during power
disturbances.
13.11. The Ethernet switch for connecting each sub-system must be a standard
complying managed switch that shall comply with at least the following standards:
IEEE 802.1Q, 802.1p, 4096 VLANs, 802.1X, Radius Authentication, Port Security
(MAC inspection), link aggregation, GVRP, IEEE 802.1d & Port Security (MAC
inspection), link aggregation, GVRP, IEEE 802.1d & SubNet - based VLAN, PoE,
PoE+.
13.12. All modification work to the existing SCCS servers and other equipment to allow
interfacing to the proposed front-end security system system shall be included in
the tender.
13.15. The Contractor shall be responsible to integrate the various front-end security
system to SCCS, and to include all integration costs in this tender to deliver the
following:
13.16. The Contractor shall lay a new network cable infrastructure for means of
communication between the security systems to the Security Systems
network rack.
13.17. All the costs for integration of the various front-end security system supplied in
this tender to SCCS (including necessary software, hardware, VAPT, etc.) shall be
included in price offered in this tender.
Edition 9.1 33
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
a. Testing and commissioning shall include, but not be limited to, the
following:
iv. System integration trial test with existing SCCS Test Servers and the
proposed front-end security system setup. The period of trial testing
will be defined by the Company.
The BACS shall be provided for the access control and security monitoring of
designated critical areas within the station building and all doors at the first storey
and basement leading to critical/vital facilities.
The Contractor shall prepare a detailed proposal for the implementation of the
BACS, which shall be subject to the approval of SP and any relevant Authorities.
If required by SP, the Contractor shall set up a trial system for SP to evaluate. All
costs arising from and in connection with the trial system shall be borne by the
Contractor.
The BACS shall include, but not be limited to, the microcontroller(s), any memory
storage device(s), expansion/interface card(s), communication device(s) and/or
card(s), contactless smart card reader(s), sensor(s) and contact(s), including all
necessary electrical and communication wiring and cables.
General Requirements
b. The BACS shall operate independently of any failure of Local Area Network
(LAN) / MAN communication interface.
c. The BACS shall utilize contactless smart card reader technology for all its
installation.
Edition 9.1 34
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
d. The BACS shall support 2-factor authentication for access control, using SP’s
existing contactless smart card as the physical token and a security code
such as the Personal Identification Number (PIN).
Access Contacts
a. Please refer to Table 12-1 for locations of the access contacts within a
substation.
c. For manned installation, a manual switch for arming / disarming the main
access gate shall be provided at the Security Station.
Edition 9.1 35
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
d. Prior to carrying out any installation, the Contractor shall submit its proposal
on the door contacts/EM locks locations to SP for final confirmation and
approval.
a. The Card Access System shall operate independently of any failure of the
other sub-systems. All card access information such as card management,
card reader set up and remote door opening shall be able to set up remotely
and be stored in the SCCS Servers. Should there be any failure /updates to
BACS, the user shall be able to reinstate/update the system, by remotely
downloading data from the SCCS Servers.
c. The Contractor shall check with SP on its existing contactless smart card
technology.
d. The read range between card reader and card shall at least be of 10cm and
the transaction time shall be less than 100ms.
ii. Weatherproofing and vandal proofing are required for the card reader
that is installed outdoors. Access door release switch(es) / button(s) shall
be provided inside the protected area at the access door(s). In addition,
where necessary and required, emergency overrides shall be provided in
case of fire alarm(s) activation.
iii. In case of any failure of the contactless smart card reader or controller
for whatever reason, a standard mechanical key-switch shall be used to
bypass the EM door lock. The key-switch should be located near the card
reader and its final location will be subject to SP’s final approval.
iv. The key-switch should be highly reliable, and the key is removable in only
one position. The key-switch housing shall have a rugged and tamper-
proof construction and come with operating status Light Emitting Diode
(LED) in red & green.
Edition 9.1 36
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
v. The key-switch key shall be a master key for all substation key-switch
installation, with spare keys to be provided by the Contractor to SP. The
choice key-switch master key shall be subject to SP’s final approval.
vi. Activation of this key switch will trigger an alarm status on SCCS. SCCS
shall indicate the status of the key-switch.
vii. There shall be both audible and visual indication on the access card
reader to indicate a successful card read each time.
iv. Monitor the status of the access control readers, keypads, alarm sensing
devices, external inputs/outputs for failure and tampering, and generate
detailed alarm messages at the Security PC Workstation.
v. Option for UPS and/or battery back-up supply with charging facilities.
vi. Once the LAN/MAN fails, the BACS controller unit at each installation
must still be functioning.
Edition 9.1 37
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
viii. It shall at minimum equipped with one (1) 10/100BaseT Ethernet RJ-45
port, one (1) RS-232 port and one (1) RS-485 port.
ix. Each BACS controller shall be able to support monitoring and controlling
of multiple access card readers.
CCTV system shall be provided for the surveillance of the individual designated
main access lobby, ground floor staircase doors and any other areas of the
substation where specified in the project.
The Contractor shall prepare a detailed proposal for the implementation of the
CCTV system, which shall be subject to the approval of SP and any relevant
authorities. If required by SP, the Contractor shall set up a trial system for SP to
evaluate. All costs arising from and in connection with the trial system shall be
borne by the Contractor.
The CCTV system shall include, but not be limited to CCTV cameras, camera lens,
Video Server/Encoders, Pan-Tilt-Zoom (PTZ) cameras, Network Video Recorders
(NVR), Power Over Ethernet (PoE) injectors, any memory storage device(s),
expansion/interface card(s), surge arrestor(s), communication device(s) and/or
card(s), including all necessary camera housing, camera poles, camera brackets
and concrete bases, electrical and communication wiring and cables. The
Contractor shall also provide SP with a full set of Application Programming
Interfaces (API) with documentation, Software Development Kit (SDK), which can
be used for third-party software integration.
Viewing of video images for the respective substations can be done locally at the
respective CCTV monitor and Security PC Workstation for manned substation or
remotely from the PC workstations at Command Centres. Any changes or updates
of data information to respective installation’s CCTV system shall be done
remotely from the PC workstations at Command Centres, without physically
dispatching staff to sites for the Works to be carried out.
The Contractor shall provide a set of video applications for the PC workstations in
Command Centre. The video applications shall include functions not limited to
view single live video, view single history video, view multiple current, remote
download of archived video / image snapshot, remote PTZ control of camera and
search multiple history video. Detailed requirements will be provided to the
Contractor.
Edition 9.1 38
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
General Requirements
c. Approved concrete plinth base 450mm (W) x 450mm (L) x 500mm (D) of
Grade 25 N/m² or otherwise shall be provided for the mounting of camera
poles. All fasteners shall be pre-cast within the concrete base and the whole
fixing shall be capable of withstanding the design of wind-load. The
Contractor shall submit design drawings, duly endorsed by a professional
engineer (Professional Engineer or PE) prior to installation.
d. The camera poles to be used shall be of hot-dipped galvanised type and come
with a height of 4m tall or otherwise. Prior to fabrication of the camera poles,
the Contractor shall submit design drawings of the camera poles to SP for
approval.
e. The locations of the camera poles shall be based on the following distances:
Location Maximum
distance
Between two camera 25 m
poles
Between a camera pole 1.5 m
and perimeter fence line
h. An IP65 rated junction box of adequate size should be provided for each
camera mounted at each location. The Contractor shall provide different
key lock to junction box housing different application at each substation.
Edition 9.1 39
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
a. The NVR shall have built-in Redundant Array of Independent Disks (RAID5)
storage with hot-swappable Serial ATA (SATA) hard disks with canisters
which are suitable for 24/7 CCTV recording. Capacity of each hard disk shall
be at least 3TB. Capacity of each RAID5 array to be proposed by Contractor
shall be able to store at least three (3) months of archived video at minimum
15fps with 2MP resolution per camera. Any cost incurred from additional
storage media shall be deemed to include in the Contract price.
b. The NVR shall automatically reboot after recovery of electrical system, back
to the status before abrupt shutdown due to power supply disturbance and
continue recording. After recovery from any system abrupt shutdown, the
NVR shall trigger a built-in watchdog and arbitrarily reset the system. An
alarm shall be sent automatically if no signal is detected from the camera,
or hard disk is damaged, or NVR configuration differs from pre-shutdown
state.
c. The NVR shall provide detailed event logs not limited to system warning,
hard disk error, network disconnection, camera failure, motion detection
and intrusion.
d. The NVR shall not have recording malfunction problem caused by system
instability, hard disk damage or virus infection.
e. Monitoring and playback tasks shall be able to work at the same time, and
these images shall be shown with multiple screens at the same time. User
can choose the enlargement, gentle image and sharp image functions to
provide a clear picture for evidentiary purposes.
f. The NVR shall be able to detect camera failure, hard disk failure, motion
alarm and digital input alarm; and report via TCP/IP Ethernet to SCCS.
g. The NVR shall have API/SDK for the SCCS Contractor to interface with the
NVR.
h. The NVR’s API/SDK shall have video functions including but not limited to,
current video playback, historical video playback, historical video search,
historical video download, camera configuration and snapshot.
Edition 9.1 40
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
i. The NVR’s API/SDK shall allow grouping of any cameras from any installation
(max 16 cameras can be selected) and viewing them on the same screen. It
shall also allow application to select and playback more than one historical
video at the same time.
j. The NVR’s API/SDK shall allow video rotation function in the PC workstations
in Command Centre.
a. General Characteristics
ii. The PTZ cameras used for monitoring the substation compound shall be
located on building façade instead of at the perimeter fence line.
b. Imaging
iii. The HD PTZ camera shall offer a 30x optical zoom lens.
vi. The HD PTZ camera shall produce a color image with a minimum scene
illumination of 0.0077 lux and a monochrome image, when in the night
mode, with a minimum illumination of 0.0008 lux at 30 IRE (Starlight
technology).
vii. The HD PTZ camera shall produce a clear image with DORI (Detect,
Observe, Recognize, Identify) performance (per EN 62676-4 standard):
Edition 9.1 41
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
viii. The HD PTZ camera shall offer automatic focus and iris control with
manual override.
x. The HD PTZ camera shall offer a High Dynamic Range of 120 dB.
xi. The HD PTZ camera shall offer a Sodium Vapor White Balance mode that
automatically compensate for light from a sodium vapor lamp to restore
objects to their true color.
xii. The HD PTZ camera shall offer a defog image feature that assists the
camera in registering a usable image when viewing foggy or other low-
contract scenes.
xiii. The camera shall have an average typical optimized bandwidth in kbits/s
for various image rates as shown in Table 13-1:
Note: The actual bit rate will vary depending on the scene, picture settings and encoder
profile settings.
Edition 9.1 42
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
Table 13-1: Typical optimized bandwidth in kbits/s for various image rates.
c. The HD PTZ camera shall provide a brushless, integral pan/tilt motor drive
unit.
g. The HD PTZ camera shall provide pan and tilt preset repeatability accurate
to within +/-0.06° without illuminator (+/-0.07° with illuminator).
k. The HD PTZ camera shall divide the cameras 360º rotation into 16
independent sectors with 20-character titles per sector. Any or all of the 16
sectors can be blanked from the operator's view.
l. The HD PTZ camera shall store up to 256 preset scenes with each preset
programmable for 20 character titles.
m. The HD PTZ camera shall offer six pre-programmed but configurable user
modes.
n. The pre-programmed modes shall be optimized with the best settings for
the following environments:
ii. Motion
iv. Indoor
v. Vibrant
o. The HD PTZ camera shall allow users to customize these modes for the
specific requirements of the camera site.
p. The HD PTZ camera shall generate full HD 1080p 50/60 resolution and
720p50/60 resolution using H.264 compression (ISO/IEC 14496-10).
s. IP Connectivity
i. The HD PTZ camera shall allow full camera control and configuration
capabilities via a TCP/IP network.
ii. The HD PTZ camera shall be capable of capturing and storing images
using at HD 1080p and HD 720p resolutions.
iii. The HD PTZ camera shall deliver 1080p video, at rates up to 60 images
per second via TCP/IP over Cat5/Cat6 UTP cable.
iv. The HD PTZ camera shall support operation with Internet Explorer web
browser version 11.0 or later, Chrome 79.0.3945 or later, Safari Firefox
version 68.0 or later, Manufacturer Configuration Manager, Video
Management System, Video Client (BVC), or other third-party software.
vi. The HD PTZ camera shall conform to the SNMP v1, v2c or v3 standard.
vii. The HD PTZ camera shall offer Quality of Service (QoS) configuration
options.
Edition 9.1 44
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
viii. The HD PTZ camera shall support the IPv6 internet-layer protocol for
packet switched internetworking across multiple IP networks.
t. Access Security
ii. The HD PTZ camera shall support 802.1x authentication using a RADIUS
(Remote Authentication Dial In User Service) server.
iii. The HD PTZ camera shall store a SSL certificate for use with HTTPS.
u. Installation Requirements
ii. The HD PTZ camera shall accept power, transmit video, and accept
control via TCP/IP connection.
iii. The HD PTZ camera shall switch to the High PoE or PoE+ power supply if
power from the 24 VAC power supply is lost, with no interruption to
camera operation.
Edition 9.1 45
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
v. PTZ Housing
ii. The HD PTZ camera shall provide built-in surge protection for power,
data, and network inputs.
iii. The HD PTZ camera shall conform to the IP67 standard for a weather-
resistant package.
iv. The HD PTZ camera shall conform to the IP67 standard for a weather
resistant package when using the IP67 connector kit.
vi. The HD PTZ camera shall conform to the IK10 rating for external
mechanical impact.
vii. The HD PTZ camera shall conform to the IEC 60068-2-6, Test Fc: Vibration
(sinusoidal), 10m/s² (1.0g) and the Sinusoidal vibration test IAW MILSTD-
167-1A vibration tests.
viii. The HD PTZ camera shall conform to the IEC 60068-2-7, 40g, 6ms Half
Sine Impulse; Medium weight Hammer Shock IAW MILS-901D test.
w. The PTZ camera shall come with white light beam or laser beam as an
integrated component of the camera. Activation and de-activation of the
beam function shall be possible from a third-party system via standard and
secure integration protocols.
x. The PTZ camera shall allow third-party system to trigger both track and
zoom function as well as the beam function to track intruders.
z. Lens:
Edition 9.1 46
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
ix. Electronic Shutter Speed (AES): 1/1 sec to 1/0000 sec (22 steps)
xiii. White Balance: 2000 K to 10,000 K; ATW, AWB Hold, Extended ATW,
Manual, Sodium Lamp Auto, Sodium Lamp
xv. Defog Image Feature: Allows the camera to see and register a usable
image when viewing foggy or other low-contract scenes.
aa. Mechanical
bb. Network
Edition 9.1 48
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
iv. Protocols: IPv4, IPv6, UDP, TCP, HTTP, HTTPS, RTP/RTCP, IGMP V2/V3,
ICMP, ICMPv6, RTSP, FTP, ARP, DHCP, APIPA (Auto-IP, link local address),
NTP (SNTP), SNMP (v1, MIB-II), 802.1x, DNS, DNSv6, DDNS (DynDNS.org,
selftHOST.de, no-ip.com), SMTP, iSCSI, UPnP (SSDP), DiffServ (QoS), LLDP,
SOAP, Dropbox, CHAP, digest authentication
viii. Data Rate: (H.265, 1080P): 61 kbps to 2.8 Mbps (depending on the scene,
the frame rate, and the quality settings)
vi. 802.1x network authentication with EAP/TLS, supports TLS 1.2 with
updated cipher suites including AES 256 encryption
dd. Miscellaneous
v. Power
Network:
Edition 9.1 49
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
ee. Environmental
IP67
ii. External Mechanical Impact (IK Code or Impact rating): IK10 (excluding
glass window)
ff. Construction
iii. The Contractor shall also provide full documentations of APIs and SDK,
which can be used by SCCS platform to control and view the PTZ network
camera.
Fixed Camera
b. The camera shall provide direct network connection using H.264 and JPEG
compression and bandwidth throttling to efficiently manage bandwidth and
storage requirements while delivering outstanding image quality.
d. The camera shall provide nine configurable user modes that provide
optimized settings for distinct applications.
f. The camera shall provide enhanced night viewing through the increase of IR
sensitivity by automatically switching a motorized IR filter from colour to
monochrome operation in low-light or IR illuminated applications. Allow the
IR filter to be switched manually via the alarm input, pre-programmed in a
camera mode or profile.
j. The camera shall provide intelligent Auto Exposure (IAE) to improve visibility
of high contrast scenes (dark objects against a light background and the
reverse).
l. The camera shall allow users to set up at least 10 separate recording profiles
based on day/night or holiday schedules.
ii. The camera shall offer several regions of interest to zoom into a specific
area of the full image.
iii. The camera shall allow regions of interest to be sent in separate streams
so it is possible to view both an overview and a detail at the same time.
Edition 9.1 51
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
n. Network Video
ii. The camera shall allow full camera control and configuration capabilities
over the network.
iii. The camera shall be capable of capturing and storing images using the
following compression standards:
M-JPEG
iv. The camera shall deliver video over a 10/100 Base-T, auto-sensing,
half/full duplex, RJ45 Ethernet connection.
v. The camera shall comply with the IEEE 802.3af Power over Ethernet
standard.
o. Access Security
ii. The camera shall store an SSL certificate for use with HTTPS.
p. The camera shall have an SD card slot that uses standard, off-the-shelf SD
cards for local storage (up to 32 GB).
ii. The camera shall provide email alarm messaging with optional JPEG
posting.
r. Electrical
i. The camera shall accept Power over Ethernet (48 VDC nominal).
ii. The camera shall conform to the IEEE 802.3af (802.3at Type 1) compliant
Power over Ethernet network. Power level: Class 3.
Edition 9.1 52
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
s. Surveillance Software
t. Environmental
ii. The camera shall work with Power over Ethernet IEEE 802.3af (802.3at
Type 1).
iii. The camera shall be enclosed in protective IP65 rated housing with
mounting bracket, sunshield and protected against lightning strikes.
u. The termination must meet ISO/IEC recommended standards such that the
video is optimally displayed at an acceptable level to SP. Proper measured
test results should be submitted to SP.
v. The Contractor shall also provide full documentations of APIs and SDK,
which can be used by the SCCS contractor to control and view the PTZ
network camera.
a. The CCTV Local Area Network shall have a standard complying industrial
grade switch that shall comply with a least the following IEEE (802.3, 802.3u,
802.3x, 802.1d, 802.3af, 802.3at, 802.1w, 802.1Q, 802.1X and 802.1p)
standards.
c. The interfaces of the switch should include, but not limited to 6 X 10/100
Base-TX with Auto MDI/MDI-X, Auto Negotiation and 2 X 100/1000 Base –
FX/SC connector for multimode.
d. The power system of the switch should be DC 24V (12~48V) with reverse
polarity protection.
g. Multimode fibre optic cables shall be used for connections to the equipment
rack adopting the star topology to obtain reliability.
h. Fibre optic cables with number of cores as required by the equipment plus
a minimum of four (4) spare cores shall be provided. These cores shall be
provided with termination assemblies suited for the fibre converter used.
The PA system shall allow the Security Command Centre to make announcements
remotely to warn of intruder(s) / trespasser(s) when they are spotted.
The PA system shall have, but not be limited to the following features:
e. The Security Personnel shall be able to select the substation to page to, from
the Security PC Workstation(s) at Command Centre.
f. Perform time synchronization with existing network time servers via NTP
and TCP/IP Ethernet.
Edition 9.1 54
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
j. The user permission checking shall be provided when the user is accessing
GUI.
l. Pre-recorded messages shall have description field for the user to search
easily.
p. The system will be interfaced with the FIDS system. The interface shall allow
for SP to play a defined pre-recorded message when FIDS alarm is triggered,
if required.
The perimeter shall be suitably segmented into zones for easy identification of
intrusion. Each FIDS zone shall not exceed 15 meters.
All designated main entrance gates (e.g. vehicular access gate, pedestrian gate)
shall be a separate zone by itself.
Edition 9.1 55
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
The detection sensors shall consist of easy-to-install coaxial cables. The cables
shall connect to signal processing modules that detect and locate attempted
perimeter breaches by analyzing the electrical signals that occur as a result of
minute vibrations in the sensor cables.
The system shall be capable of being integrated into the facility’s Security
Management System.
The system shall support the use of wireless sensors to augment perimeter
protection in areas where physical cables pose installation and/or maintenance
challenges, such as with sliding or swinging gates.
The proposed FIDS shall have the capability to be integrated seamlessly into SCCS.
d. REACH
Manufacturing Quality
ii. The modules and assemblies shall be tested during manufacture over
their entire operational temperature range on a sample basis
Mechanical Requirements
a. Sensor cable:
i. The sensor cable shall have the option to be encased in an armor jacket,
for use in areas that have a high potential of physical damage to the cable.
ii. The sensor cable shall have a minimum bend radius no greater than 10.0
cm (4.0 inches).
Edition 9.1 56
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
iii. The sensor cable shall be affixed to the facility’s fence through the use of
UV-resistant plastic or metal cable ties.
iv. The sensor cable shall not require a cable conduit to be installed along
the fence perimeter.
b. Processor modules:
i. The manufacturer shall provide the facility owner with the option of
installing each processor assembly in its own enclosure or use an existing
enclosure.
ii. The processor enclosure cover shall be hinged as to enable access to the
internal components without requiring removal.
iii. The processor enclosure shall be capable of being secured with a padlock.
iv. The enclosure for the processor module shall include pre-installed cable
glands so that install technicians do not need to drill their own cable
entry points.
vi. The processor module shall detect and indicate physical tampering
conditions, including:
Environmental Requirements
b. Processor enclosure:
Edition 9.1 57
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
ii. Cable ingress/egress ports shall include cable glands that require no
additional sealing compounds to provide an environmental seal for
sheathed cables.
a. Sensor cables: The sensor cables shall provide a minimum service life of 10
years, excluding damage caused by non-environmental forces.
b. Processor:
i. The processor shall have a predicted mean time between failures (MTBF)
of greater than 100,000 hours when calculated per Telcordia Reliability
Prediction Procedure, Parts Count Method, at 70°C.
ii. The processor shall have a mean time to replace (MTTR) of less than 10
minutes.
iv. No single Processor module failure shall cause any other Processor along
the perimeter to stop functioning in a normal manner.
v. The processor self-test cycle shall be capable of initiating from its two dry
contact inputs or from a command issued over the network, if configured.
Electrical Requirements
Edition 9.1 58
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
c. The system shall support the provision of power over the sensor cables, so
that individual processor modules, when connected together, can share a
common power source.
ii. Auxiliary inputs: The values of the supervision resistor(s) for each dry
contact input shall be set from the configuration software.
Detection Capabilities
a. The FIDS sensor shall consist of a cable that is attached to the fence along
the full length to be protected.
b. The system shall be able to detect and locate intrusions over a cable
distance of up to 600 m (1,968 feet) per processor.
i. Process the signal from the sensor cable to detect intruders attempting
to breach the perimeter fence by cutting, climbing, or lifting the fence
fabric.
ii. Each processor shall support two sensor cables, with each one being up
to 300 m (984 feet) in length.
iii. Pinpoint the position of a detected intrusion to within 3.0 m (9.8 feet) or
less at least 95% of the time.
ii. False alarm rate: The maximum rate for alarms generated by the internal
electronic processes of the processors (cables excluded) shall be less
than one per zone per year, averaged over the total number of zones in
the system.
Temperature changes
Sunrise/sunset
Fog
Edition 9.1 60
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
i. Wind
h. Fence compatibility:
Chain-link
Vinyl-coated chain-link
Palisade
l. Gate compatibility:
ii. The sensor cable shall be capable of being bypassed on sliding gates.
Edition 9.1 61
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
vii. The system shall have the option of using “quick disconnect” connectors
at infrequently used gates (swinging or sliding), so that the sensor cable
can be installed as normal over the gate and temporarily disconnected as
required.
i. The sensor processor shall have a minimum of four Form C relay outputs
to indicate alarm conditions.
ii. For each relay it shall be possible to assign one or more conditions from
the following list under which the relay will activate:
Enclosure tamper
Edition 9.1 62
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
ii. The processor shall be capable of wirelessly monitoring the status of gate
contacts via the Wireless Gate Sensor.
a. The system shall be simple to install and shall have the following
characteristics, as a minimum:
i. The sensor cable must be capable of being attached directly to the fence
without needing to be put in a conduit.
ii. The sensor cable must be capable of being attached to the fence with
standard UV-resistant cable ties (plastic or metal).
iii. It shall be possible to mount the processor directly on a fence post that
forms part of the fence to be protected
iv. It shall be possible to connect the sensor cable directly to the processor
without the need for any intermediary cable
iii. The calibration software shall support precise sensitivity leveling on a per
meter (3 foot) basis.
iv. The calibration software shall enable the creation of de-sensitized zones
that ignore vibration events (for example, by gates or areas where
instruction detection is not required).
Edition 9.1 63
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
v. The calibration software shall include a real-time plot mode for viewing
live fence response data.
a. The proposed FIDS shall monitor itself to ensure that its protection
capability is not compromised. If that capability has been compromised,
the system will generate a supervision alarm.
iv. Tamper
a. The FIDS shall provide multiple alarm contacts to activate the CCTV
assigned to its respective zone(s) to allow recording at higher frame rate
of the CCTV shots at the activated zone(s).
b. The alarm interface shall be either of the following but not be limited to:
Edition 9.1 64
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
Others
Armed Yellow
Intrusion Red
Table 13-2: FIDS stages and corresponding LED zone display on FIDS panel
Photo-beam Specification
Edition 9.1 65
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
e. Crosstalk can occur when two or more sets of active photo-beams are
installed at the same side and/ or in close proximity to one another, which
can lead to “no alarm” problems. Crosstalk also occurs when the photo-
beams operates beyond its intended range.
j. Photo-beam shall have alarm output duration of not less than a second.
k. Photo-beam’s power input shall fall within the range of 11Vdc to 30Vdc.
m. Six sets of photo-beam sensors shall be installed within the vicinity of each
gate with hollow section brackets. Two of these six sets will be installed on
top of the gates. Dimension of hollow section bracket shall be 100mm x
50mm x 2000mm.
a. Siren shall come with built-in strode light suitable for sheltered outdoor and
indoor areas.
b. Siren shall provide regular alarm sound with an acoustic power of 100dB to
110dB at a distance of 1m.
c. Siren shall have the option for user to control the siren and strobe light
separately.
Networking Capabilities
ii. The system shall support a networked configuration. The processors shall
use the Silver Network protocol to relay alarm, status, and supervision
information over the sensor cables to the Network Manager. The
Network Manager shall then communicate the information to a security
management system.
iii. The system shall support the reporting of individual zone alarms as well
as status and supervision information to Silver Network-compatible relay
I/O modules.
i. System status tool that provides a visual display of the status of all
processors in the system
ii. System event log tool that provides a searchable log of system events
iii. System plot tool that can store and recall the response data for all
networked sensors and display a plot of the response from a minimum
of 8 sensor zones simultaneously
Edition 9.1 67
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
iii. The processors shall support the following physical media options for
communication with the integrated sensor network:
EIA-422 cable
j. Network management:
ii. The system’s network management software shall provide the following
interfaces:
Edition 9.1 68
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
iv. Serial and TCP/IP-based interfaces for communicating alarm, status, and
configuration data to and from security management systems using
configurable, ASCII-based text strings.
Submittals
Spares
a. The contractor shall deliver to the facility owner spare system components.
b. For each system component, spares consisting of least 20% of the number
that comprise the system, whichever is greater, shall be provided.
Warranty
a. The product shall be under warranty for a minimum of two years from the
date of purchase.
The DAS shall have, but not be limited to, the following features:
Edition 9.1 69
400KV, 230KV & 66KV SUBSTATION ATTACHMENT F
b. The activating buttons must be hidden from general view and the design
must allow the operator to activate it inconspicuously.
d. Each duress alarm button shall be connected to its own zone. There shall
not be any sharing of zones in the alarm processor.
e. The alarm system will also include battery backup for up to eight (8) hours.
f. The audio and visual alarms in the Security Command Centre must allow the
Security Personnel to know exactly which location has activated the duress
alarm.
g. The design for the alarm status panel and the buzzer located at the Security
Command Centre shall cater to monitor a minimum of 30 sites. The panel
should include a LED function test for all location indicators. Should there
be inadequate space on the existing status panel for the additional location
indicators, provisions must be made for replacement or expansion of the
existing alarm status panel.
h. Duress alarms shall not annunciate at the local substation site initiating the
duress alarm.
i. The duress alarm initiated at the Security Command Centre shall annunciate
at the Security Backup Command Centre or any other location to be
determined by SP.
j. All duress alarms shall annunciate at the Security Command Centre, Security
Backup Command Centre or any other location to be determined by SP.
k. The Security PC Workstation shall also display the alarm point on the
geographical layout, which shall be indicated by a flashing icon.
l. The time lag between the activation of the duress alarm and the
annunciation of the alarm at the Security PC Workstation or alarm status
panel shall not be greater than 2 seconds.
Edition 9.1 70
400KV, 230KV & 66KV SUBSTATION ATTACHMENT G
1. GENERAL
1.1 Each Guard House will have minimally 3 cameras installed. Two cameras
overlooking the internal of the guard house while 1 camera oversees the
area where passes are exchanged. These cameras will be connected to
SPPA’s Metropolitan Area Network (MAN) via ISOSS CCTV network where
possible and will have its network video recorder (NVR) located at Security
Command Centre (SCC) server room. Please refer to Appendices.
1.2.1 All equipments supplied must have a minimum product lifespan of 2 years.
Should the principal announce End-of-Sale (EOS) of the product, the principal
shall still provide support for all repairs, spare parts and refurbishment for 2
years from the award of tender date. In the event of product obsolescence,
the Contractor has to replace the faulty unit or component with a current
compatible model, which is subject to the approval of the Company.
1.2.2 The Contractor shall warrant and guarantee that all works and materials to be
provided under this Contract will be new and of first class quality and in every
aspect suitable for the services required: that the work and all components,
thereof will fulfill the performance data, characteristics and properties as laid
down in this Specifications, that the work and all its parts shall operate at all
capacities up to maximum, successfully and without undue noise, undue
wear, undue heating, undue straining of parts and without undue vibration,
that the works shall be efficient for easy maintenance and in harmonious
operation conditions with other parts of the work, and equipped in accordance
with up-to-date techniques.
Edition 9.1 1
400KV, 230KV & 66KV SUBSTATION ATTACHMENT G
2. CCTV SYSTEM
2.1 Scope
2.1.1 Components: The CCTV System shall include, but not limited to, Internet
Protocol (IP) cameras, Power Over Ethernet (PoE) switches, junction boxes,
and all necessary wiring and cables. Depending on SPPA’s requirement at
the point of equipment purchase by the contractor, Network Video Recorder
(NVR) and/or 3 Terabyte (TB) hard-disks may also be required.
2.1.2 Unused Materials: All unused accessories (e.g. cables, adaptors etc) that are
provided with the components shall be duly returned to the Company after the
project completion.
2.1.3 Works:
c) All the devices within the junction box shall be properly secured and
installed/mounted.
e) The network up-link shall be taken from the ISOSS (CCTV Network) in
the guardhouse where possible.
Edition 9.1 2
400KV, 230KV & 66KV SUBSTATION ATTACHMENT G
2.2 IP Camera
2.2.1 The camera shall be Panasonic WV-SF335E Mega Pixel Fixed Compact
Dome Camera or equivalent.
2.2.3 Cameras shall be properly mounted at a location where the viewing angle is
optimal, subjected to a final approval by the Company.
2.2.4 The camera shall have web interface that allows authorised end user to
remotely download video and still images.
2.3.1 NVR shall be provided if there is inadequate recording storage for the new
guardhouse cameras at the existing NVR at the Security Command Centre.
2.3.3 The NVR shall have built-in Redundant Array of Independent Disks (RAID5)
storage with hot swappable Serial ATA (SATA) hard disks with canisters
which are suitable for 24/7 CCTV recording. Capacity of each hard disk shall
be at least 3TB.
2.3.4 The NVR shall support up to 64 network cameras without extra license fee
and their images shall be recorded simultaneously.
2.3.5 The NVR shall have web interface that allows authorised end user to remotely
playback/download video and still images.
2.3.6 The NVR shall store a minimum of 3 months of video (minimum fps: 10, VGA
resolution, No RAID function) recording for all cameras. Any cost incurred
from additional storage media shall be deemed to be included in the tender
price submitted.
2.3.8 The NVR shall be fully compatible with the IP camera and PoE switch
proposed for the CCTV system.
Edition 9.1 3
400KV, 230KV & 66KV SUBSTATION ATTACHMENT G
2.4.2 The PoE switch shall have management and telnet remote login functions.
2.4.3 The PoE switch shall have Media Access Control (MAC) address access
control. All MAC addresses of the end devices as well as the entries
submitted by the Company shall be entered into the switch configuration
before commissioning.
2.4.4 The uplink to the network shall have IEEE802.1Q (VLAN tagging) enabled
where required.
2.5.1 The key-lockable junction box provided shall have enough room to house all
the equipment necessary for the CCTV operation as well as our equipment
which shall include, but not limited to the PoE switch. At least 50% spare
space should be provided. The Contractor shall propose the layout of the
equipment in the junction box to be implemented and shall be subjected to
approval by the Company.
2.5.2 For each junction box, the Contractor shall also provide at least a dual pole
MCB of suitable rating and 2 twin 13A power sockets.
2.5.3 The junction boxes supplied shall comply with IP65 standard.
2.5.4 There shall be a plastic engraved label on each box. The word to be
engraved will be provided by the Company.
2.5.5 The swinging door of the junction box shall have a clear document file
attached on the inside.
2.5.6 The junction box shall have a tray at the base that could be extended out for
placing laptops.
2.5.7 The Contractor shall provide the lockset that is identical with all existing
Guardhouse CCTV junction box.
Edition 9.1 4
400KV, 230KV & 66KV SUBSTATION ATTACHMENT G
2.6.1 The electrical and communication cables used for installation should be of
approved standards.
2.6.2 All conduits, ducting, enclosures and cabinets shall be protected or otherwise
sealed to prevent the entry of insects or other vermin, which could damage
cabling/equipment.
2.6.3 All installation works shall be performed by competent and experienced staff
in accordance with the latest Edition of the Singapore Standard Code of
Practice CP5, CP16, CP33, CP59 and regulations currently enforced by the
relevant competent authorities.
2.6.4 The Contractor shall exercise due care when carrying out the installation
works so as not to damage existing equipment and services within the project
location and terminal buildings.
2.6.5 The Contractor shall provide the necessary cable supports that are tamper
proof. Network and power cables are not allowed to be laid in the same
conduit / trunking or in close proximity.
2.6.6 Cables leading into the equipment rack should be provided with a minimum 2”
machine bored hole.
2.6.8 All cable installations shall adopt a “loop into fittings” system with adequate
slackness connecting every equipment to facilitate removal for replacement,
inspection or adjustment.
2.6.12 In the event of finding evidence for reasonable doubt as to the non-
compliance to this clause, the authorised representative from the Company
reserves the right to direct the suspected cable to be withdrawn for
inspection. If the cable is found to be faulty, it shall be withdrawn and
replaced with a new one at no additional cost to the Company.
Edition 9.1 5
400KV, 230KV & 66KV SUBSTATION ATTACHMENT G
2.6.13 Upon request by the COMPANY, the Contractor shall provide and install the
conduit / trunking for the cables / wires that are laid or existing ones at no
additional cost to the Company.
2.6.14 There shall be new communication cables laid for existing equipment that
connect to the newly installed PoE switch if the existing cables are found to
be too short at no additional cost to the Company.
2.6.15 The Contractor shall reroute existing cables if required, due to relocation of
existing switches at no additional cost to the Company.
2.6.16 The Contractor shall provide suitable fiber connectors upon request at no
additional cost to the Company.
2.7.1 The power supply required for the equipments to be installed in each Guard
House shall be provided by a sub-distribution circuit.
2.7.2 In the event that any distribution board has no suitable spares to be allocated,
a new dual pole MCB of suitable rating shall be provided by the Contractor
and installed by a licensed electrical worker.
2.7.3 A new sub-distribution board shall be provided and installed by the Contractor
if the existing board has space constraints.
2.7.4 The Contractor shall lay the power cables with proper terminations from the
sub-distribution circuit to the junction boxes and racks.
Edition 9.1 6
400KV, 230KV & 66KV SUBSTATION ATTACHMENT G
2.8.2 The Contractor shall submit a detailed testing and commissioning procedure
to the Company for approval at least 2 weeks in advance prior to the
commencement of testing and commissioning.
2.8.3 The test methods used shall be in accordance with the system manufacturers’
and relevant authorities’ recommendations.
2.8.4 Testing and commissioning shall include, but not limited to, the following:
2.8.5 Testing and commissioning shall be carried out in the presence of and to the
satisfaction of at least 1 authorised representative from the Company, and at
such times as it may require.
2.8.6 The Contractor shall provide all labour, materials, apparatus, insulation test,
instruments and connections required for the tests.
2.8.7 All test instruments used shall be calibrated at the expense of the Contractor
at a recognised national laboratory to be approved by the Company. The date
of the last calibration of the test instruments shall not be more than 2 years.
2.8.8 The test reports submitted to the Company shall include all the results of
testing, details of the testing equipment and measurement and recording
instruments and details of the test method. The Contractor shall submit the
format of the test reports for the Company’s approval.
2.8.9 The Contractor shall submit all test reports for each installation within 7 days
upon completion of testing and commissioning.
2.8.10 The Contractor shall exercise proper project management and control, and
submit weekly progress schedules during the installation, testing and
commissioning works.
Edition 9.1 7
400KV, 230KV & 66KV SUBSTATION ATTACHMENT G
2.8.11 In the event the tested system fails to meet the Specifications, the Contractor
shall make the necessary arrangements to repair, modify and/or replace the
system within the contractual completion time, failing which liquidated
damages will be imposed. All costs incurred in the replacement or repair of
the system, including any additional labour, materials and other necessary
accessories and consumables shall be borne by the Contractor.
2.8.12 Upon commissioning, the Contractor shall submit an excel spreadsheet of the
records for the devices IP addresses and MAC addresses.
2.8.13 MAN network availability to SCC will be subjected to Fiber Optics installation
schedule for the substation. This schedule may or may not coincide with new
substation building handover timeline.
Edition 9.1 8
400KV, 230KV & 66KV SUBSTATION ATTACHMENT G
3.1 On-site corrective maintenance with free replacement of all faulty parts
(inclusive of labour) shall be included during the Defects Liability Period.
3.2 Emergency calls shall be treated by the Contractor as top priority and the
Contractor’s Service Engineer shall attend to these faults within the
response time window as stated in Clause 1.3. The maintenance hours for
corrective maintenance shall be during office hours (5) days per week
(excluding Saturdays, Sundays and Public Holidays).
3.3 The Contractor’s Service Engineers shall operate from and be based in
Singapore. The Contractor’s Service Engineers shall attend at the relevant
Premises within the Response Time of two (2) hours from the Company’s
first request to the Contractor for its Service Engineer’s presence at the site.
3.4 The Contractor’s Service Engineer shall provide and be equipped with the
necessary tools to carry out his work during his site visit.
3.5 For any fault addressed and resolved, the Contractor shall issue a service
report to the Company within the same day.
3.6 The Contractor shall rectify all faults, defects and deficiencies within two (2)
hours of the Contractor’s presence at the Site. However, if, despite the
Contractor’s best efforts, it is unable to rectify such faults, defects and
deficiencies within the above two (2) hours period, the Contractor shall, at
its own cost, put in place approved alternatives to ensure that the system is
functional for its respective purposes within the above two (2) hours period.
For the avoidance of doubt, the implementation of such alternatives shall
not in any way discharge the Contractor of its obligations to rectify the
faults, defects and deficiencies reported by the Company.
3.7 In the event that the Contractor is unable to rectify the fault within seven (7)
days of the occurrence of the fault, the Contractor shall be liable for
liquidated damages, fixed at a rate of 1.00% of the total contract sum
(“Contract Sum”) for every week or any part thereof that the fault remains
un-corrected up to a maximum amount of 10.00% of the Contract Sum.
Edition 9.1 9
400KV, 230KV & 66KV SUBSTATION ATTACHMENT G
NVR
Edition 9.1 10
400KV, 230KV & 66KV SUBSTATION ATTACHMENT H
1. The substation shall generally be constructed to comply with the current editions
of the Standards for Building and Codes of Practice produced by the following
organizations:-
3. The design of Electrical Substations shall comply with the current requirements of
the following, and all relevant laws and regulations and with such additional
requirements as may be stated in the Specifications, Guidelines or where
appropriate:
Edition 9 1
400KV, 230KV & 66KV SUBSTATION ATTACHMENT H
Edition 9 2
400KV, 230KV & 66KV SUBSTATION ATTACHMENT H
Edition 9 3
400KV, 230KV & 66KV SUBSTATION ATTACHMENT I
All Work of this Section shall comply with the requirements of the Specification,
Drawings, Schedules and Guidelines.
The Contractor shall provide extended warranties for products, workmanship, etc, as
needed, and the cost shall be deemed included in the cost of the Works.
Edition 9 1
Technical Specifications
APPENDIX 1
TREE PLANTING ARRANGEMENT FOR EXTERNAL COMPOUND
CCTV Pole
Tree
Fence line
Page 1 of 1
Technical Specifications
APPENDIX 2
ACTIVATION OF FIRE SUPPRESSION SYSTEM SERVING COMMUNICATION ROOM, CONTROL
ROOM AND BATTERY ROOM
Page 1 of 1
Technical Specifications
APPENDIX 3
ACTIVATION OF HYDROGEN SENSOR SERVING BATTERY ROOM
Page 1 of 1
TECHNICAL SPECIFICATIONS
Appendix 4
EXISTING SYSTEM OVERVIEW
42 units rack
Guard House 1
NVR
MAN
PoE switch
Guard House N
Note: 1 to N is the number of guard houses that have already been installed with the system. If required, contractor shall provide only the NVR in the
42 units rack.
TECHNICAL SPECIFICATION
Appendix 5
GENERAL SCHEMATIC DIAGRAM OF DEVICES INSIDE A GUARD HOUSE
MAN
Junction box
PoE SWITCH
Network switch
Cat 6 cable
Note: Each guard house may have 2 or more cameras. Minimally 2 cameras within the guard house and 1 camera outside the guard house
where passes are exchange.