C.1.4 Method Statement For Major Scrapper Trap Repairs Upgrades New Constructions
C.1.4 Method Statement For Major Scrapper Trap Repairs Upgrades New Constructions
C.1.4 Method Statement For Major Scrapper Trap Repairs Upgrades New Constructions
TENDER REFERENCE
SEPLAT/LAG/ITT/2020/AI/136749
1. PURPOSE 4
2. SCOPE OF WORK 4
3. REFERENCE 4
4. RESPONSIBILITIES 5
5. DEFINITIONS / ABBREVIATIONS 5
6. PERSONNEL 6
7. EQUIPMENT 6
8. HSE REQUIREMENTS 7
9. QUALITY CONTROL 7
10.1. PREPARATION
10.1.1. MATERIAL DELIVERY AND RECEIPT
10.1.2. INSPECTION AND SITE STORAGE
The purpose of this document is to describe the Major Scrapper trap repairs / upgrades / new
constructions of Pig Trap as equipment which shall be used for inserting the Pig into the
pipeline and to ensure safe removal of the Pig in Seplat.
Ujas Industrial Services Limited will implement and to ensure the work is completed on time
based on project schedule, consistency with Company requirements, and comply within
project budget. All will be based with a target of ZERO Incidents by adopting Company’s
HSE Standards.
2. SCOPE OF WORK
The Scope of Work is to Major Scrapper trap repairs / upgrades / new constructions for Crude
Oil, Heavy Oil or Gas. The installation will be including remedy of the foundations, grouting,
ground assembly, site fabrication, erection, piping and welding works, instrument tubing
work, cabling and cable connection works, insulation and cladding work, commissioning and
testing works, site painting and touch up painting.
3. REFERENCE
AWS D1.1
ASME Section IIA, IIC
ASME Section V
ASME Section VIII Division 1
ASME Section IX
ASME B16.5
ASME B31.1
ASME B31.3
API 1104
Any Codes and Standards related to Pig Launcher and Pig Receiver from
Company
4.4. QC Inspector
He has overall responsibility for the control and inspection of quality according to the
QA/QC plan and ITP. He shall review the Contract specifications and drawings,
identify project criteria and prepare required checklist for QA/QC inspection.
4.5. Project Engineer
He shall monitoring progress of the work (related construction, pre- commissioning
activities, testing, commissioning and start-up) as per project schedule and as per
project procedures and Company regulation.
5. DEFINITIONS / ABBREVIATIONS
1. Construction Superintendent
2. Project Engineer / Commissioning Engineer
3. QC / Welding Inspector
4. HSE Inspector
5. Construction Supervisor
6. Material Control / Storekeeper
7. E/I Technician
8. Welder
9. Fitter
10. Rigger / Scaffolder
11. Insulator
12. Civil Worker
13. Painter
14. General Helper
7. EQUIPMENT
Planned Construction equipment and tools for this project is as per list below:
All personnel must follow the rules and regulations applicable in Seplat Energy
Project.
Before job starts check if protective & safety requirements are provided.
Appropriate PPE must be used by personal doing the task.
Pre job talk must be done and all personal assigned to do the task must understand
the hazards associated with the job and the control measures in place.
All personnel will be issued with and instructed to always maintain safe working
practices especially for the Hot Work Activities. Any flame cutting works, grinding
works, welding works shall be use additional PPE such as: Welding / Face shield,
masker, ear plug, welding apron.
Any working at Hight shall be wear the safety full body harness.
All of Construction personnel included the team leader shall passed with the
Medical Check Up and have safety training as required by Client.
Emergency Response Plan must be developed and implemented to all personnel
acquainted with the relevant provisions and know what to do in case of any
emergency.
10.1. PREPARATION
Preparation shall be started after contract award with Engineering and Design,
Procurement and Fabrication works.
Equipment-Tools-Consumable included supporting material on site will prepared in
Contractor workshop and delivered to site including the pig traps c/w the accessories.
Assembly of the Pig Traps (Launchers and Receivers) with its accessories shall be
completed in Contractor workshop.
Contractor shall prepare site warehouse and site workshop for supporting the
construction activity.
All heavy equipment, equipment, tools, consumables including material (Pig Traps and
the accessories) will be kept in site warehouse / site workshop.
The pig traps are packed on wooden pallets or boxes prior to delivered.
Valve ends are sealed with PE protective caps or wooden caps to prevent the
penetration of dirt and moisture.
Valves of the additional connections are in “OPEN” position.
Weld-on ends and mounted flange sides are coated with an anti-corrosive product.
Only use the original packaging for transporting the pig traps to its place of
installation.
Only use lifting devices that are appropriate to the weight being moved.
10.1.2. Inspection and Site Storage
Check the delivery notes to make sure that the delivery is complete. The Client shall
be attended when the inspection performed.
Check the delivery immediately on receipt for damage incurred during transport. In the
event of damage, observe the stipulations of the insurance company which, among other
things, prescribe that evidence of damage is confirmed immediately by the forwarding
agent.
If applicable, photograph damage to proof evidence.
Store the pig launcher in its original packaging.
Take suitable measures to protect the pig traps against external influences, dirt and
moisture.
Contractor will responsible for Mechanical Completion (“MC”) Work and each discipline
should provide the requirements during the work. Mechanical completion scope could
include, but not be limited to:
- Ensure all equipment and any accessories are installed in accordance with
applicable drawings, specifications and manufacturers’ instructions.
- Check nameplates against data sheets and requirements.
- Check equipment against specifications, codes and standards.
- Visual inspections to check for complete and correct installation.
- Grounding check; and
- Bolts tightness check.
10.2.3. Pre-Commissioning
Contractor will provide all necessary labour to complete construction, installation, and Pre-
commissioning of the Work. Pre-commissioning includes all actions required to bring the
Work to Mechanical Completion.
Function Test
o Before applying pressure to the pig traps for the first time, a function test must be
carried out when it is de-pressurized.
o Properly clean the interior of the ball valve and the closure.
o Fully close the ball valves and the closure and open again. The ball valves must
run through the entire stroke trouble-free.
Leak Test
o Only use mechanically clean water with an admixture of anti-corrosive agent as a
test medium.
o If no anti-corrosive agent is used, the pig traps must be drained and dried as quickly
as possible after the pressure test in order to avoid corrosion.
o Close all installed ball valves before running the pressure/leak tightness test.
o Provide the pressure gauge connections with a manometer.
o Close all drainage and venting connections.
o Close the main connection ball valve for pressure relief.
o Use an expansion tube to fill the pig traps with water and vent it via the venting
connection.
o Drain the pig traps subsequently.
10.2.4. Commissioning and Start-Up
Company will be responsible for commissioning and start-up the facilities and Contractor
shall provide labor and tools to support Company in the commissioning activities.
Commissioning activities are those associated with final testing, start-up, and operating of
the new facilities, or a part thereof, by the Company following mechanical completion, Pre-
commissioning, and Handover of the Contract Objects.
Contractor shall provide supervised skilled and unskilled labor, tools and construction
equipment, as requested by Company or Main Contractor to support commissioning and
start-up.
If required, Contractor will provide nitrogen (N2) for purging during commissioning which
includes N2 racks, certified purging manifold and adequate medium pressure purging hoses.
Purging activities during commissioning shall be performed by and at responsibility of
Contractor, including nitrogen supply as part of assisting Company during commissioning.
Purging activities during commissioning shall be under direct supervision of Company.
Contractor shall be fully responsible for the project documents as per scope of work,
drawings and data and for the as-built and updating as necessary all existing facilities
documents, drawings and data.
Contractor’s obligations shall not be considered fulfilled until as-built is completed to the
satisfaction of Company. Contractor shall provide all final documentation including, but not
limited to:
• Engineering
• Procurement
• Construction and Pre-Commissioning
• All certification
• HSE
• Quality Control
• Project Report