I&TP For Architectural (Rev.2)
I&TP For Architectural (Rev.2)
I&TP For Architectural (Rev.2)
FLOORING/PAVEMENT
BRICK MASONRY
PLASTERING
ROOFING ACCESSORIES
FALSE FLOORING AND CEILING
CONTRACT :
DEV-K-23-09
NO.
PROJECT : SKIKDA REFINERY REHABILITATION
NAME & ADAPTATION PROJECT (EPCC-5)
: SONATRACH
CLIENT
ACTIVITE AVAL-DIVISION REFFINAGE
LOCATION : SKIKDA, ALGERIA
A. FLOORING/PAVEMENT
Laboratory
1 Approval of source of materials WC WC Rw
report
a) Review of calibration certificates of HP Calibration
2 instruments/ testing equipments WC WC certificate
b) Field calibration, if any W
Laboratory
4 Checking/ testing of materials WC WC S
report
Laboratory
13 Concreting, testing, finishing, test cubes WC WC W Report,
Checking for line, levels, slopes, joints, thickness of
14 WC WC S CV-240
flooring viz. AFC drawings
15 Curing WC WC S
B. BRICK MASONRY
12 Curing WC WC S BL-110
C. PLASTERING
Check for completeness of all hidden jobs like piping,
1 WC WC S BL-120
conduiting, etc
8 Curing WC WC S BL-120
D. ROOFING ACCESSORIES
Check for material including Manufacturers test
1 WC WC W MA-100
certificate (as applicable) and sequence of sheeting
E. FALSE FLOORING
Check for material including Manufacturers test Manufacture
WC WC W
certificate (as applicable) Certificate
Final check
- Floor system clean and free of damage WC WC S
- Construction final acceptance
F. FALSE CEILING
Check for material including Manufacturers test Manufacture
1 WC WC W
certificate (as applicable) Certificate
Completion of all work above the ceiling, prior to start of
2 WC WC S
work
Suspension system ( e.g., set level and square, prior to
3 WC WC S
installation of ceiling board)
6 Tightness of joints WC WC S
LEGEND
HP - Hold Point
W - Witness Point
Rw - Review of Contractor’s Documents
S - Surveillance Inspection by Owner / PMC
WC - 100% Examination by Contractor