Method Statement of Tower Crane Erection
Method Statement of Tower Crane Erection
Method Statement of Tower Crane Erection
No : TUB-DE-GE-M-0011
Rev. No : 00
TUBAN - Indonesia
Date : 14 December 2011
Page No. : 1 of 17
METHOD STATEMENT
Reference sheet
Review History
17
©…….. PT BAM Decorient Indonesia
TABLE OF CONTENT
TABLE OF CONTENT...........................................................................................................2
1. INTRODUCTION.....................................................................................................3
2. SCOPE OF WORKS...............................................................................................3
3. MOBILIZATION AND SITE ESTABLISHMENT......................................................3
4. Construction..........................................................................................................3
4.1. Resources...............................................................................................................3
4.2. Work Sequence...................................................................................................... 4
5. HEALTH, SAFETY & ENVIRONMENT................................................................11
1. INTRODUCTION
The following is the Method Statement for erection of tower crane number two at Tubafa Cement project.
Type of Tower crane is SIMMA POTAIN GT185
This outline method statement is intended to demonstrate our ability to provide approach to carry out all the
operations in a systematic manner with the necessary degree of quality and safety as per the respective
quality and safety plans of this project.
The following work execution plan explains the methodologies to be used in the implementation and execution
of the works and follows the sequence of activities scheduled in the construction programme.
2. SCOPE OF WORKS
The scope of work contains the erection and installation of tower crane number two.
A plan view of the geometry to be installed tower crane inclusive of northings and easting’s of corner
locations will be indicated in attachment drawing. The drawings for plan and sections will indicate location
of tower crane.
Site mobilization will initially involve surveys of the designated work areas, the establishment of
coordination points taken from benchmarks on site. Reference pegs will be installed to help the surveyor
marking and control the elevation.
4. CONSTRUCTION
4.1. RESOURCES
Equipment’s to be use:
1. 45 Ton Mobile Crane
2. Sling
3. Total Station
Before the erection work starts, the contractor has to evaluate the experience of the personnel who
will carry out the work. He also has to check the required equipment, the material and updating of the
project drawing.
The process of erection has to be as continuous as possible in order to prevent loss of time or
inadequate utilization of the machines.
In addition to the standard health, safety & environment precautions and measures, the excavation
works have several potential safety hazards as described in the attached Job Safety Analysis.
The general requirements as per this project’s Safety plan are applicable.
All staff is responsible in ensuring all parties are adhering to health, safety & environment standards. If
any unsafe or unhealthy condition is encountered, any staff member has the authority to halt the works
and report to the safety officer.
ATTACHMENTS