1.

0 Advanced Work Packaging Procedure

AWP-IM-WFP PROCEDURES
1.0 ADVANCED WORK PACKAGING PROCEDURE
This procedure “1.0 Advanced Work Packaging” is the first of three procedures that define the
application of Advanced Work Packaging (AWP), Information Management (IM) and Workface Planning
(WFP).

These three core procedures are supported by a suite of templates and supplemental procedures that
are stored in the Workface Planning Toolbox.
At the discretion of the COMPANY any or all of the foundational procedures and supplemental
procedures may be applied to a project in support of the core procedures.

Revision Date Description Originator


0 Oct,1, 2017 AWP Procedure Insight-awp

Approvals: Name Position Signature Date

Geoff Ryan Author Nov,24 2014

©Insight-awp 2014, This document contains proprietary information that may be reproduced and utilized for the purpose of applying Advanced
Work Packaging only when acknowledgment is given to Insight-awp as the original author.
Page 1
1.0 Advanced Work Packaging Procedure

Table of Contents
1 PURPOSE
2 DEFINITIONS
3 HOW TO APPLY THIS PROCEDURE
4 OVERVIEW OF AWP, IM & WFP
5 KEY STAKEHOLDER DELIVERABLES TO SUPPORT AWP
6 PROJECT MANAGEMENT TEAM
7 AWP, IM & WFP POSITIONS
8 WORKFACE PLANNING SOFTWARE
9 3D MODEL
10 BID ASSESSMENTS
11 AWP-IM-WFP KICK-OFF AND LESSONS LEARNED
12 PROJECT DEVELOPMENT ROADMAP FOR AWP-IM-WFP
13 OPTIMAL PATH OF CONSTRUCTION
14 INTERACTIVE PLANNING WORKSHOP
15 AWP-IM-WFP EXECUTION STRATEGIES
16 INFORMATION MANAGEMENT
17 AUDITS
18 PROCEDURE MAINTENANCE

WFP TOOLBOX

Sample Documents Supplemental Procedures Job Descriptions


SD01 WFP Cold Eyes Review SP01 Scaffold Management JD01 AWP Champion
SD02 WFP Bid Assessment SP02 Equipment Management JD02 Information Manager

SD03 Optimal Path of Construction SP03 Training JD03 WFP Coordinator


SD04 Installation Work Package SP04 Work Packaging Procedure JD04 Workface Planner
SD05 Foreman's Daily Plan JD05 Workface Planning Lead
SD06 Weekly Project Controls Report
SD07 WFP Audit Template

©Insight-awp 2014, This document contains proprietary information that may be reproduced and utilized for the purpose of applying Advanced
Work Packaging only when acknowledgment is given to Insight-awp as the original author.
Page 2
1.0 Advanced Work Packaging Procedure

1. PURPOSE
The purpose of this document is to define the COMPANY’s expectations for the Project
Management’s team’s application of AWP. The procedure outlines the activities required to align
Engineering and Procurement with the needs of Construction. The standards establish in this
document will support the application of the Information Management procedure by the
Information Manager and the Workface Planning procedure by the Construction Contractors.
This procedure may also be used periodically to audit the application for compliance.

Objectives
The ultimate goal of AWP-IM-WFP is to optimize project performance through the application of a
structured planning process. This is expected to create a model for construction execution that will
minimize risk and deliver predictable results. Project management activities detailed in this
procedure will establish Stakeholder deliverables that will facilitate AWP.

Scope
This document will address the:
• Overview of AWP-IM and WFP
• AWP Champion
• Information Manager
• Application of Procedures
• Work Breakdown Structure
• Path of Construction
• Interactive Planning Sessions
• Level 3 schedule
• Work Packages for
o Engineering,
o Procurement
o Modules
o Construction

Other procedures in this series will address:


• The application of IM
• The details of how to populate and utilize WFP Software
• The construction contractor’s application of WFP
• Installation Work Packages (IWPs)
• Scaffold Management
• Construction Equipment Management
• Training

Method
The AWP Champion is responsible to apply this procedure across all project stakeholders with
support from the Project Manager and the Project Sponsor. This AWP procedure will be included in
all E and P contracts as a required component of contract compliance.

©Insight-awp 2014, This document contains proprietary information that may be reproduced and utilized for the purpose of applying Advanced
Work Packaging only when acknowledgment is given to Insight-awp as the original author.
Page 3
1.0 Advanced Work Packaging Procedure

2 DEFINITIONS
• Workface: Is that geographic point where labor converts materials into a facility.
• Workface Planning: The process of organizing and delivering all the elements necessary, prior to
the commencement of work, to enable labor to perform quality work in a safe, effective, and
efficient manner.
• Workface Planner: A dedicated construction planner who has hands on construction skills and
experience as a supervisor. Responsible for developing IWPs and removing constraints, reports
directly to the construction superintendent.
• Workface Planning Coordinator: Owners representative who reports directly to the AWP
Champion. Responsible to manage Contractor’s WFP department, coordinate the turnover of
CWPs form the Construction Management Team to the Contractors, and oversee the function of
IWP development and constraint management.
• Information Manager: Owner’s representative who reports directly to the AWP Champion.
Responsible to develop systems and processes that govern the generation and transfer of
project information. Responsible to facilitate the development of the project cloud with a
document management system, material management database and Workface Planning
software.
• AWP Champion: Owner’s representative and member of the Project Management Team,
responsible for the application and oversight of AWP, IM and WFP by all of the Project
Stakeholders.
• Labor: Skilled or unskilled trades people, craft workers, artisans or workforce, divided by
discipline, who are responsible for the actual physical work that converts materials into facilities.
• Constraints: The Information, Tools, Materials, and Access that are required to execute work.
• Work Packaging: The progressive elaboration of work from Engineering Work Packages to
Procurement Work Packages and Module Work Packages based upon the requirements of
Construction Work Packages. Further dissected into Installation Work Package and then into
Daily Plans. The sequence of work dissection follows the path identified in the Path of
Construction with the components modeled upon the structure of the WBS.
• Owner: The COMPANY that initiates a project by developing a business requirement.
• Project Management Team: A division of the COMPANY who are responsible to synchronize and
manage Engineering, Procurement and Construction for the entire life cycle of the project.
• Engineering: Includes COMPANY Engineering and a series of specialized engineering companies
who report directly to the Engineering Manager who is a member of the PMT. Engineering are
responsible to elaborate the owner’s concepts into a detailed design. This organization is
directly responsible for the functionality of the process and the generation of project
information.
• Procurement: The procurement division of the PMT or a division of the Engineering Team. This
team is responsible to engage contractors and suppliers, fabricators, module assembly yards
and construction contractors through the development of contracts. Also responsible to manage
the procurement of bulk materials, components and oversee the fabrication and delivery of
equipment, pipe and steel components.

©Insight-awp 2014, This document contains proprietary information that may be reproduced and utilized for the purpose of applying Advanced
Work Packaging only when acknowledgment is given to Insight-awp as the original author.
Page 4
1.0 Advanced Work Packaging Procedure

• Material Management: The organization who are responsible for receiving all project material
from the procurement team. Responsible to manage onsite warehousing and the distribution of
all site materials.
• Construction Contractor: The organization engaged to construct the project utilizing direct hire
labor and subcontractors.
• Discipline: A unique trade identified as: Civil, Structural Steel, Pipe, Mechanical, Electrical,
Instrumentation or insulation etc.

Construction Work Area (CWA) – A geographical division of work defined by Construction. It


includes all disciplines, with the exception of cables and
undergrounds that are also divided into work areas, but across
the entire project. Each CWA has boundaries defined by the
logical association of work and becomes one activity on the
Level 2 Schedule.

Construction Work Package (CWP) – A single discipline of a


CWA that defines a logical division of construction work with
less than 40,000 work-hours. A CWP is a component of the
WBS, a single level 3 activity on the project schedule and is the
downstream product of a single EWP and PWP when prepared
for construction. The division of work is defined such that
CWPs do not overlap and they can be used as contractual
boundaries of work. Each CWP is dissected into a series of
IWPs by the Workface Planners.

Engineering Work Package (EWP) - An engineering deliverable, single discipline that contains all of
the engineering data required for a single Construction Work
Package: Scope of Work, Drawings, Vendor Data, Bill of
Materials and Specifications, in both PDF and electronic 3D
model files. EWPs are developed sequentially to satisfy
elements of the Path of Construction, which will facilitate
sequential procurement and the execution of CWPs. A single
EWP is represented in the schedule as a single level 3 activity.

Procurement Work Package (PWP) – A procurement deliverable, that contains all of the materials
required to satisfy a single CWP. Typically, a single discipline, in
the case of steel and pipe the PWP becomes a discrete
fabrication package that is expected to be manufactured and
delivered as a distinct group of components.

©Insight-awp 2014, This document contains proprietary information that may be reproduced and utilized for the purpose of applying Advanced
Work Packaging only when acknowledgment is given to Insight-awp as the original author.
Page 5
1.0 Advanced Work Packaging Procedure

Module Work Package (MWP): A subset of a group of single discipline EWPs that contains all of the
Issued For Construction (IFC) engineering data for all disciplines
required for the construction of a single module. A group of modules
(<10) is a single CWP. The steel and pipe EWPs for a CWP of modules
becomes discrete fabrication packages that identify all of the spools
and steel piece marks for the CWP (group) of modules.

Installation Work Package (IWP): A discrete portion of constraint free, construction work that can
be executed by a single foreman and crew, in a single 7 Day period.
Dissected from a single CWP and made up of whole drawings. Each
IWP becomes a single level 5 schedule activity.

Work Breakdown Structure (WBS) − A hierarchical representation of a complete project with its
components being arrayed in ever-increasing detail. The WBS forms a direct alignment between Work,
Time and Cost by serving as the basis of Work Packaging, Schedule Development and Cost Coding.

WTF-I-12-E4-C05-14
WTF- Water Treatment Facility (Plant)
I-ISBL: O-OSBL
12 - CWA
E - Major discipline (Earthworks)
4 - Sub Discipline (Excavation)
C05 - CWP (C- Construction, E-Engineering, M- Modules, F- Fabrication, P-Procurement)
14 - IWP or Drawing and spool

Project Nomenclature:
The creation of the WBS and the development of the WBS library forms the template for the project
nomenclature. This naming convention (WTF-I-12-E4-C05-14) will then be used to identify physical
components, drawings, spools, steel members, schedule activities, cost codes and work packages.

©Insight-awp 2014, This document contains proprietary information that may be reproduced and utilized for the purpose of applying Advanced
Work Packaging only when acknowledgment is given to Insight-awp as the original author.
Page 6
1.0 Advanced Work Packaging Procedure

Field Supervision: For the purpose of this procedure these terms are used to describe the three basic
levels of field supervision that exist within the Construction Contractor or Subcontractor organizations.
Ratios are expected to vary based upon the complexity and critical nature of the tasks. Terms and ratios
may be changed to suit the local standards.
a. Foreman: Responsible for the direct supervision of one labor crew in a single discipline, with
typically 1 foreman to 10 crew members.
b. General Foreman: Responsible to directly supervise up to 4 foremen in a single discipline.
c. Superintendent: Responsible to supervise up to 3 General Foremen in a single discipline.
May be a member of staff or hired through the labor providers.

Schedule Dissections: For the purpose of this procedure this hierarchy will be used to describe schedule
activities:
o Level 1: Plant and year
o Level 2: CWA and 6 months
o Level 3: CWP and 3 months
o Level 4: Function code and month
o Level 5: IWP and week
o Level 6: Daily plan and day
o Level 7: Task and hour

©Insight-awp 2014, This document contains proprietary information that may be reproduced and utilized for the purpose of applying Advanced
Work Packaging only when acknowledgment is given to Insight-awp as the original author.
Page 7
1.0 Advanced Work Packaging Procedure

3 HOW TO APPLY THIS PROCEDURE


Project Management Team:

This procedure will be used to support the development of the Project Management Team’s
Organisation chart and will then be used to define the roles and responsibilities of the AWP-IM-
WFP Team positions.

This procedure will be added to all Engineering and Procurement contracts and identified as the
standard for compliance with the application of Advanced Work Packaging.

Contract Language:

Within 30 days of award the Engineering and Procurement successful bidders will submit an
Execution Plan for the integration of Advanced Work Packaging based upon the standards
identified in this procedure.

The procedure will be utilized to measure compliance through periodical audits conducted by the
project management team or 3rd party auditors. The contractors are responsible to address issues
from the audits and strive for substantial compliance.

COMPANY reserves the right to periodically review this procedure and apply amendments through
the management of change process.

©Insight-awp 2014, This document contains proprietary information that may be reproduced and utilized for the purpose of applying Advanced
Work Packaging only when acknowledgment is given to Insight-awp as the original author.
Page 8
1.0 Advanced Work Packaging Procedure

4 OVERVIEW OF AWP, IM AND WFP

Advanced Work Packaging describes the processes upstream of the CWP that aligns Engineering and
Procurement to facilitate the sequential creation of CWPs.

Workface Planning details the processes downstream of the CWPs that leads to the creation of IWPs
and execution of field work.

Information Management is the alignment of project data so that it facilitates the transition of Data →
Information → Understanding, across Engineering – Procurement – Fabrication - Module Construction –
Construction – Turnover - Commissioning.

©Insight-awp 2014, This document contains proprietary information that may be reproduced and utilized for the purpose of applying Advanced
Work Packaging only when acknowledgment is given to Insight-awp as the original author.
Page 9
1.0 Advanced Work Packaging Procedure

5 KEY STAKEHOLDER DELIVERABLES TO SUPPORT AWP

At 40% of the overall cost of a project, the construction phase traditionally assumes a large share of
the project risk. The project’s exposure to risk in the fields of Safety, Quality, Schedule and Cost can
all be reduced through the organised execution of work-fronts that are the deliverable from
Advanced Work Packaging.
In order to execute AWP-IM-WFP it is important to recognise that each of the project stakeholders
contributes deliverables that are required by the Construction Contractors to support the
application. This procedure identifies the outline of these deliverables and the actions that are
required for their development. Therefore the members of the Project Management Team are
responsible to implement and govern the execution of these processes through the application of
this procedure.

Engineering: Develop and deliver EWPs, in the correct sequence, ensure that EWPs have all of the
engineering requirements for Construction Work Packages, develop, maintain and regularly deliver
an intelligent fully attributed 3D model.

Procurement: Insert the requirement for AWP, IM and WFP in all contracts, manage the sequential
fabrication of components and modules to satisfy the requirements of Construction Work Packages,
ensure that electronic data is a deliverable from fabrication.

Construction Management: Map the Optimal Path of Construction, identify the size, content and
sequence of CWPs, facilitate the application of Workface Planning by the contractors and manage
field execution.

Project Controls: Develop the level 3 EPC schedule based upon the OPC and sequence of CWPs,
provide standards for Earned Value Management.

Onsite Material Management: Track and report materials required, ordered and received by
Installation Work Package.

Document Control: Develop a single online document management database, store documents by
their WBS, establish and maintain permissions that facilitate electronic access for all of the project
Stakeholders.

Project Management: Establish the requirement for AWP, IM and WFP in contracts, appoint an
AWP Champion and support the application of the AWP, IM and WFP procedures.

©Insight-awp 2014, This document contains proprietary information that may be reproduced and utilized for the purpose of applying Advanced
Work Packaging only when acknowledgment is given to Insight-awp as the original author.
Page 10
1.0 Advanced Work Packaging Procedure

6 PROJECT MANAGEMENT TEAM

Project Management Team: A division of the COMPANY responsible to synchronize and manage
Engineering, Procurement and Construction for the entire life cycle of the project.
The Project Management Team, led by the Project Manager is responsible to ensure that each of the
Major Project Stakeholders satisfy the intent of their AWP-IM-WFP procedures.
The Workface Planning Champion will be assigned to the PMT and be responsible for the
administration of the AWP, IM and WFP procedures across all project stakeholders.

7 AWP, IM AND WFP POSITIONS


AWP Champion:
The AWP Champion is the PMT representative responsible to initiate and pilot the processes that
will support the application of AWP, IM and WFP procedures by the Project Stakeholders.
The AWP Champion will:
• Be responsible to apply the AWP procedure.
• Be assigned to projects prior to the development of contracts for Engineering, Procurement and
Construction.
• Administer the application of the COMPANY AWP-WFP procedures by each of the Project
Stakeholders
• Be responsible to guide the application of AWP, IM and WFP through the entire lifecycle of the
project; Initiation through to commissioning with all of the contracted organizations.

©Insight-awp 2014, This document contains proprietary information that may be reproduced and utilized for the purpose of applying Advanced
Work Packaging only when acknowledgment is given to Insight-awp as the original author.
Page 11
1.0 Advanced Work Packaging Procedure

• Interact as a member of the PMT with: Engineering, Procurement, Project Controls, Document
Control, Material Management, Construction and Operations.
• Facilitate the development of an Optimal Path of Construction and a CWP release plan.
• Support the development of an EWP release plan to support the Optimal Path of Construction.
• Have the authority and be directly responsible for the successful application of Workface
Planning on the project.
• Maintain the WFP procedures.

Information Manager
As a member of the AWP-IM-WFP team, the Information manager is responsible to guide the creation
and communication of project information on the platform of the WBS.
The Information Manager will ensure:
1. That the IM procedure is applied
2. The structure of the WBS facilitates the alignment of Work, Time and Cost
3. 3D model data is populated with attributes that are developed based upon the needs of
Construction, the WFP Software and the need to mine data by other Project Stakeholders.
4. That the structure of the 3D model is based upon CWAs, EWPs and CWPs
5. The document nomenclature is based upon the WBS.
6. The storage of documents in the Document Control database is based upon the WBS
7. Steel Piece mark numbers are unique
8. Spools are identified as a subset of the isometrics
9. Fabricators develop and deliver electronic data as it is created.
10. Onsite Material management data utilizes the correct naming conventions so that there is a
direct correlation between 3D model components, drawings and materials.
11. The WFP software is kept up to date with project information, revisions and ‘as built’ redlines.

WFP Coordinator
The WFP Coordinator is responsible to establish and maintain WFP in the Construction Contractor’s
organisation. This includes the creation and management of CWPs and the delivery of project
information to the Construction Contractor’s Workface Planners.
Therefore the WFP Coordinator is responsible to:
• Apply the WFP procedure.
• Work with the Information Manager to facilitate the development of the 3D model so that it
supports information management for construction.
• Applying WFP software (ConstructSim or SmartPlant Construction) to the construction team
with full functionality.
• Develop and conduct training sessions and ongoing coaching sessions for WFP Software users.
(PMT and Contractors).
• Establish and maintain the electronic exchange of information between data generation points
and the Workface Planning Software.
• Facilitate the development of CWPs and /or MWPs from EWPs
• Track and report the progress of CWP development.
• Facilitate the integration of project controls data from the Construction Contractors with the
WFP Software.

The job descriptions for these positions are stored in the WFP Tool box as JD01, 02, 03

©Insight-awp 2014, This document contains proprietary information that may be reproduced and utilized for the purpose of applying Advanced
Work Packaging only when acknowledgment is given to Insight-awp as the original author.
Page 12
1.0 Advanced Work Packaging Procedure

8 WORKFACE PLANNING SOFTWARE


Prior to the start of detailed design the AWP Champion, working with the Engineering and Procurement
Teams and the Information Manager will evaluate and select a Workface Planning Software that
supports the needs of the project. The decision will be in consideration of the software used for the
Engineering 3D model, Procurement/Material management and Document Control.
WFP Software is proprietary software that facilitates the process of developing Installation Work
Packages (IWPs) in a 3D environment.
There are presently two companies that have products that facilitate the automation of information in a
3D environment for the purpose of work packaging:

ConstructSim SmartPlant Construction

The software accommodates the calculation of planned value through the insertion of installation rates
and rules of progress from the estimate. The intelligent model then allows the users to see the planned
value for each component or the cumulative value of a group of objects (an IWP).
The software can then be used to show the state of readiness for IWPs by showing the actual received
materials and drawings (in another colour). As the work is executed and progressed the Planner will
progress the individual objects (changing the colour) and Earning Value against the total Planned Value.
The culmination of these fragments of information visualized in the 3D environment upon the Workface
Planner’s desktop facilitates the development of virtual IWPs, based upon the current reality. Objects in
the model can also be grouped to represent schedule activities. This creates a visual schedule that can
be rolled out one schedule activity at a time to visually simulate construction: (4D modeling).
The software facilitates Workface Planning by visualizing the answers to these complex questions:
• Which components have been engineered and released IFC?
• Which components have been fabricated, shipped and received?
• Which components have been installed (progressed)?
• Which components are scheduled to be installed?
• Which components have been allocated to an IWP?
©Insight-awp 2014, This document contains proprietary information that may be reproduced and utilized for the purpose of applying Advanced
Work Packaging only when acknowledgment is given to Insight-awp as the original author.
Page 13
1.0 Advanced Work Packaging Procedure

• Have the Workface Planning constraints for a specific IWP been removed?

9 3D MODEL

The functionality of the Workface Planning Software is critically dependent upon the structure,
attributes and integrity of the 3D model. The correct object attributes must be identified and populated
during the early development of the 3D model and then rolled up to the right level to form components
that are meaningful to fabrication, material management and construction. The Information Manager is
responsible to work with the Engineering team to develop and implement standards that will ensure the
correct alignment of Attributes, Objects and Components in the 3D Model.
The AWP Champion will ensure that the fully functional 3D model is monthly deliverable from
Engineering to Fabrication and Construction.

10 BID ASSESSMENTS

The AWP Champion will work with the COMPANY’s Contract team and the PMT to develop an overall
assessment of each Construction Contractor’s bid.
The AWP Champion will apply the Bid Assessment Scorecard (SD02) to each bid as they are received. A
designate from each bidder will be interviewed by the AWP Champion to complete the second portion
of the assessment.
The final score for each bid, reported as a % of attainable, will be utilized as a guide to the potential of
each bidder to successfully satisfy their portion of COMPANY’s WFP procedures.
The Contract Team will consider each bidder’s score as a component in their technical bid assessment.
The Bid Assessment Scorecard is available in the WFP Toolbox: SD02

11 AWP-IM-WFP KICK-OFF AND LESSONS LEARNED


The AWP Champion, with support from the PMT will conduct a Kick–off and Lessons Learned seminar
with representatives from each of the Project Stakeholders, within 30 days of contract award. The
whole day session will launch the application of AWP-IM-WFP for the Project Stakeholders and
introduce the collaborative nature of information generation, management and sharing for the purpose
of Workface Planning facilitation.
The AWP Champion will utilize the morning portion of the seminar to present a PM training program
that will highlight the overall concepts, deliverables and interdependencies of AWP-IM-WFP on the
project.
The afternoon session will be used to present lessons learned from other projects and the project
procedures. The interactive session will invite the Stakeholders to contribute their own lessons learned
to a log of experience.
The AWP Champion will then introduce the concept of a stakeholder steering committee and then seek
nominations from each of the stakeholder groups. The WFP Steering committee will meet monthly to
table issues and seek resolutions for the entire life cycle of the project.
The AWP Champion is responsible to collate the log of lessons learned from the seminar and
communicate it across the project.

©Insight-awp 2014, This document contains proprietary information that may be reproduced and utilized for the purpose of applying Advanced
Work Packaging only when acknowledgment is given to Insight-awp as the original author.
Page 14
1.0 Advanced Work Packaging Procedure

12 PROJECT DEVELOPMENT ROADMAP FOR AWP-IM-WFP

©Insight-awp 2014, This document contains proprietary information that may be reproduced and utilized for the purpose of applying Advanced
Work Packaging only when acknowledgment is given to Insight-awp as the original author.
Page 15
1.0 Advanced Work Packaging Procedure

13 OPTIMAL PATH OF CONSTRUCTION

During the front end planning of each project and prior to the start of detailed design the senior project
manager will convene a process that facilitates the development of the Path of Construction. The POC
will prescribe the sequential development of engineering and procurement to support the optimal
sequence of project construction.

The project management team led by the Senior Project Manager will ensure that the logic of optimized
construction is the dominant influence on the final Path of Construction.

The document: “Path of Construction - Workshop” is available in the WFP Toolbox: PM04 and
establishes the method and structure of the workshop that will be used to develop the Optimal Path of
Construction.

©Insight-awp 2014, This document contains proprietary information that may be reproduced and utilized for the purpose of applying Advanced
Work Packaging only when acknowledgment is given to Insight-awp as the original author.
Page 16
1.0 Advanced Work Packaging Procedure

The mandatory sequential development of engineering and procurement based upon the optimal path
of construction is a critical requirement for effective Workface Planning. As such this process, which is a
best practice on its own, has been included in this procedure as an essential element in the path
towards optimized construction through the execution of Workface Planning.

©Insight-awp 2014, This document contains proprietary information that may be reproduced and utilized for the purpose of applying Advanced
Work Packaging only when acknowledgment is given to Insight-awp as the original author.
Page 17
1.0 Advanced Work Packaging Procedure

14 Interactive Planning Workshop


The ideal output from the Path of Construction Workshop will be a complete list of single discipline
CWPs and the sequence that they should start construction: The CWP Release Plan.

The CWP Release Plan establishes placeholders in a schedule format that shows the ideal sequence and
approximate lag between the start of construction dates for CWPs

Install Heat Exchangers: CWP Release Plan


Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Piles CWP
Concrete CWP
Steel CWP
Pipe CWP
E&I CWP
Heat Trace CWP
Insulation CWP

The Engineering and Procurement teams perform a backward pass where they develop activity
durations for EWPs and PWPs that will support the requirements of each individual CWP.
For the purpose of this workshop the duration estimates are only for the fabrication and shipping of
materials or the development of individual EWPs that takes place after the second model review. The
engineering of systems and the procurement of bulk steel and pipe are executed as they normally are
across the entire project prior to these start dates.

Install Heat Exchangers: EWP Release Plan


Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Piles EWP P CWP
Concrete EWP P CWP
Steel EWP P CWP
Pipe EWP P CWP
E&I EWP P CWP
Heat Trace EWP P CWP
Insulation EWP P CWP

This method is premised upon the standard that one EWP = one PWP = one CWP and that the end of an
EWP duration is the last drawing IFC with the end of a PWP being the last component received at site.
The alignment of this methodology also mandates the requirement for work packages to be delivered as
complete packages, not by single drawing or individual component. This also means that the activities
run in series to each other with a finish to start relationship.
©Insight-awp 2014, This document contains proprietary information that may be reproduced and utilized for the purpose of applying Advanced
Work Packaging only when acknowledgment is given to Insight-awp as the original author.
Page 18
1.0 Advanced Work Packaging Procedure

If module fabrication is a component of the project then a group of modules (<10) will be considered a
single CWP (identified by the construction team) and be identified in this release plan as Module
Assembly that appears after procurement and before Construction.
At this stage of schedule development, the duration estimates at expected to be a Rough Order of
Magnitude (ROM) estimate (+/- 25%) based upon analogous calculations.
With the EWP IFC dates established the Engineering team will develop an estimate for the development
duration of each EWP and conduct a backward pass to establish a start date for engineering.

15 AWP-IM-WFP EXECUTION STRATEGIES

• After reviewing the AWP-IM-WFP procedures, each of the Project Stakeholders will be required
to develop an Execution Strategy (ES) within 30 days of the AWP-IM-WFP Kick Off or 60 days
after contract award, whichever is the sooner.
• The document will present a high level sequence of actions that are required to satisfy each
stakeholder’s commitment to their AWP-IM-WFP procedures.
• The AWP Champion is responsible to develop an overall AWP-IM-WFP Project Execution Plan
from the Project Stakeholder ESs.
• The complete document will be represented as a flow chart along with the dialog of the
stakeholder plans.
• The draft of the overall strategy will be submitted to the Project Management Team for review,
edits, suggestions and approvals.

Engineering Execution Strategy

The Engineering team will develop an overall ES for AWP-IM for the support of Workface Planning
that will encompass the development of the WBS, the 3D model and Document Control. The ES will
describe the sequence of high level activities with inputs and outputs that will include but not be
limited to:
• Participation in the development of the Path of Construction
• The sequential development of EWPs to support the Path of Construction
• The development of the level 3 (CWP) engineering milestone schedule
• The intention to review and incorporate AWP-IM lessons learned
• A human resource plan for engineering resources required to support this procedure.

The execution strategy will be submitted to the AWP Champion within 60 days, following contract
award and will form a component of the Project’s overall PEP for AWP-IM-WFP.

©Insight-awp 2014, This document contains proprietary information that may be reproduced and utilized for the purpose of applying Advanced
Work Packaging only when acknowledgment is given to Insight-awp as the original author.
Page 19
1.0 Advanced Work Packaging Procedure

Procurement Execution Strategy


The Procurement team will develop an ES that details their contribution to the execution of AWP-
IM-WFP. The ES will describe the sequence of high level activities with inputs and outputs that will
include but not be limited to:
• Participation in the development of the Path of Construction
• The intention to review and incorporate AWP-IM lessons learned
• The development of procurement contracts that prescribe:
o Naming conventions based upon the WBS
o Electronic information deliverables
o Sequential fabrication based upon the project milestone schedule.
• The establishment of a Material Management Database that has the functionality to support
Workface Planning
• Material tracking processes that utilize RFID technology and data management.
• A chain of custody map that shows the handover of responsibility from procurement to
material management and warehousing.
• A human resource plan for procurement resources required to support this procedure.

The completed ES will be submitted to the AWP Champion within 60 days, following contract award
and will form a component of the Project’s overall execution strategy for AWP-IM-WFP.

Construction Execution Strategy


The Construction Contractor’s Workface Planning Lead will develop an overall ES for the application
of Workface Planning at least 60 days in advance of the commencement of any direct work. The high
level strategy will include execution plans for the development of a Workface Planning department
and the adoption of this procedure.
The Execution Strategy will include but not be limited to:
• The process for identifying, hiring and training Workface Planners
• The standard for an Installation Work Package
• A plan to integrate WFP Software
• A list of standard constraints and the process for constraint removal.
• An office/equipment/vehicle/radio/phone plan for Workface Planners
• A procedure for short interval (daily) planning
• A process that will ensure that each IWP appears in the schedule prior to execution.
• A cost code structure and process that will allow timesheets to be matched to IWPs.
• A system for the collecting, logging and resolving delays.
• Flow charts that show how the Workface Planners will access document and material
information.
• A plan for a “proof of concept” that will validate the information interfaces.
• A plan that links scaffold erection to the IWPs
• A plan that links construction equipment allocation to IWPs
• A Workface Planning training plan and matrix that shows each level of the organisation.
• The schedule for deployment.

The approved ES will then be used to guide the development of Workface Planning by the Construction
Contractor.

©Insight-awp 2014, This document contains proprietary information that may be reproduced and utilized for the purpose of applying Advanced
Work Packaging only when acknowledgment is given to Insight-awp as the original author.
Page 20
1.0 Advanced Work Packaging Procedure

16 INFORMATION MANAGEMENT
The AWP Champion will engage an Information Manager to guide the development of information
generation, storage and exchange.

The standards for information will be designed to support the interfaces between the 3D model the WFP
software, the document control database and the material management system, with consideration for
the project schedule and the management of earned value. Whenever possible the standard for data
generation should also be compliant with the ISO standard 15926.

The Information Manager is responsible to support the development of project standards for
information generation, the WBS and nomenclatures for all of the Project Stakeholders. The project
wide standardization of information specifications is expected to facilitate the interfaces between the
project stakeholders based upon the foundation of the 3D model.

©Insight-awp 2014, This document contains proprietary information that may be reproduced and utilized for the purpose of applying Advanced
Work Packaging only when acknowledgment is given to Insight-awp as the original author.
Page 21
1.0 Advanced Work Packaging Procedure

17 AUDITS
In order to optimize the Project Management Team’s support for AWP-IM-WFP the Project Manager will
initiate in-house audits of the process against this procedure during each stage of the project. The AWP
Champion will develop the schedule and conduct the audits at the request of the Project Manager.
These audit points will appear in the project schedule.
A Summary of the report will contain the following:
• Scorecard of adherence to this procedure as a % of total attainable
• A list of recommendations for alignment.
• Demographics of the project: Phase, Workforce and % Complete
• Comments and observations
• A list of acclamations and recommendations

The audits will utilize the audit template from the WFP Toolbox: SD07

The AWP Champion will present the audits to the Project Manager. The Project Management Team will
develop a list of action items and assign accountable personnel. The AWP Champion is then responsible
to progress the action items and produce a follow up report within one month of the audit.

18 PROCEDURE MAINTENANCE
This procedure is the first in a series of three that are interdependent to each other, therefore care
should be taken that changes initiated here are not already covered in one of the other procedures or
that the changes do not have a negative impact upon the effectiveness of the process as a whole.
The local maintenance of this procedure is the responsibility of the AWP Champion over the course of
the project and should reflect the reality of application.
At the completion of the project the AWP Champion is responsible to capture the actions taken by the
project team to improve the procedure’s effectiveness.

This report should include a detailed list of:


• The audit results that show trends in conformance or diversions from the procedure.
• Changes made to the procedure during the project c/w with an explanation of the reason
for the changes.
• Lesson learned captured at the end of the project phases from all stakeholders.
• Project management end of project assessment that captures the effectiveness of the
process and procedures.

The final report developed by the AWP Champion will be submitted to the project procedures owner for
consideration as a suggestion for continuous improvement.

©Insight-awp 2014, This document contains proprietary information that may be reproduced and utilized for the purpose of applying Advanced
Work Packaging only when acknowledgment is given to Insight-awp as the original author.
Page 22