PMEA SOLAR TECH SOLUTIONS

PVT.LTD.
Salt Spray Test Inspection Report
E-20, MIDC, Sinnar Industrial Area ,
Sinnar (Nashik)
Part Details :- Coating Peel off Rail Start Date :- 2/11/2024
Supplier Name :- End Date :- 3/23/2024
Part No.- PM-1-44475-B 240103 Required SST Life :- 1000 Hours
Customer Name:- PMEA E 20 Token No. :- 73
Coating Type. :- Zinc Touchup Test Method Used:- ASTM B117
Lab No. :- SSTL-22 Solution :- 5% NaCl
CHEMBER TEMP.
Date Time (Hrs) Fog Collection (IN ML) PH (6.5-7.2) Observation Inspected By
(35 ± 2°)
2/11/2024 24 34 7 35.4 No Rust Gautam Chavan
2/12/2024 48 32 6.8 35.1 No Rust Gautam Chavan
2/13/2024 72 33 6.7 35.4 No Rust Gautam Chavan
2/14/2024 96 31 6.9 35.3 No Rust Gautam Chavan
2/15/2024 120 33 6.6 35.3 White Rust Initiates Gautam Chavan
2/16/2024 144 34 6.7 35.4 White Rust Observed Gautam Chavan
2/17/2024 168 32 6.6 35.5 White Rust Observed Gautam Chavan
2/18/2024 192 32 6.6 35.3 White Rust Observed Gautam Chavan
2/19/2024 216 31 6.8 35.4 White Rust Observed Gautam Chavan
2/20/2024 240 33 6.9 35.2 White Rust Observed Gautam Chavan
2/21/2024 264 35 7 35.1 White Rust Observed Gautam Chavan
2/22/2024 288 34 6.8 35.3 White Rust Observed Gautam Chavan
2/23/2024 312 35 6.7 35.2 White Rust Observed Gautam Chavan
2/24/2024 336 33 6.7 35.1 White Rust Observed Gautam Chavan
2/25/2024 360 34 6.8 35.4 White Rust Observed Gautam Chavan
2/26/2024 384 36 6.7 35.4 White Rust Observed Gautam Chavan
2/27/2024 408 37 6.7 35.3 White Rust Observed Gautam Chavan
2/28/2024 432 33 6.6 35.2 White Rust Observed Gautam Chavan
2/29/2024 456 35 6.7 35.1 White Rust Observed Gautam Chavan
3/1/2024 480 31 6.7 35.3 White Rust Observed Gautam Chavan
3/2/2024 504 33 6.8 35.2 White Rust Observed Gautam Chavan
3/3/2024 528 32 6.7 35 White Rust Observed Gautam Chavan
3/4/2024 552 33 6.7 35.3 White Rust Observed Gautam Chavan
3/5/2024 576 36 6.9 35.2 White Rust Observed Gautam Chavan
3/6/2024 600 35 6.8 35.4 White Rust Observed Gautam Chavan
3/7/2024 624 31 6.9 35.1 White Rust Observed Gautam Chavan
3/8/2024 648 33 6.8 35 White Rust Observed Gautam Chavan
3/9/2024 672 36 6.6 35.4 White Rust Observed Gautam Chavan
3/10/2024 696 37 6.6 35.5 White Rust Observed Gautam Chavan
3/11/2024 720 35 6.7 35.2 White Rust Observed Gautam Chavan
3/12/2024 744 36 6.8 35.1 White Rust Observed Gautam Chavan
3/13/2024 768 36 6.8 35.2 White Rust Observed Gautam Chavan
3/14/2024 792 33 6.9 35.5 White Rust Observed Gautam Chavan
3/15/2024 816 34 6.8 35.4 White Rust Observed Gautam Chavan
3/16/2024 840 35 6.9 35.1 White Rust Observed Gautam Chavan
3/17/2024 864 36 6.7 35.6 White Rust Observed Gautam Chavan
3/18/2024 888 33 6.8 35.7 White Rust Observed Gautam Chavan
3/19/2024 912 35 6.9 35.9 White Rust Observed Gautam Chavan
3/20/2024 936 34 7 35.7 White Rust Observed Gautam Chavan
3/21/2024 960 34 6.8 35.5 White Rust Observed Gautam Chavan
3/22/2024 984 35 6.9 35.7 White Rust Observed Gautam Chavan
3/23/2024 1008 33 6.7 35.3 White Rust Observed Gautam Chavan

Process Stop
REMARK- 1) THIS PART IS REWORKED BY ZINC TOUCHUP DUE TO COATING PEELOFF ISSUE NEAR DIMPLE (INSIDE AREA)
2) WHITE RUST INITIATES ON 120 HOURS
3) WHITE RUST OBSERVED ON 1008 HOURS

BEFORE ( Start of the test ) AFTER ( End of the test )

Prepared By :- Gautam Chavan Apporoved By:- Pritam Tunge


PMEA SOLAR TECH SOLUTIONS
PVT.LTD.
Salt Spray Test Inspection Report
E-20, MIDC, Sinnar Industrial Area ,
Sinnar (Nashik)
Part Details :- No Coating Peel off Rail Start Date :- 2/11/2024
Supplier Name :- End Date :- 3/23/2024
Part No.- PM-1-44475-B 240102 Required SST Life :- 1000 Hours
Customer Name:- PMEA E-20 Token No. :-
Coating Type. :- Test Method Used:- ASTM B117
Lab No. :- SSTL-23 Solution :- 5% NaCl
CHEMBER TEMP.
Date Time (Hrs) Fog Collection (IN ML) PH (6.5-7.2) Observation Inspected By
(35 ± 2°)
2/11/2024 24 34 7 35.4 No Rust Gautam Chavan
2/12/2024 48 32 6.8 35.1 No Rust Gautam Chavan
2/13/2024 72 33 6.7 35.4 No Rust Gautam Chavan
2/14/2024 96 31 6.9 35.3 White Rust Initiates Gautam Chavan
2/15/2024 120 33 6.6 35.3 White Rust Observed Gautam Chavan
2/16/2024 144 34 6.7 35.4 White Rust Observed Gautam Chavan
2/17/2024 168 32 6.6 35.5 White Rust Observed Gautam Chavan
2/18/2024 192 32 6.6 35.3 White Rust Observed Gautam Chavan
2/19/2024 216 31 6.8 35.4 White Rust Observed Gautam Chavan
2/20/2024 240 33 6.9 35.2 White Rust Observed Gautam Chavan
2/21/2024 264 35 7 35.1 White Rust Observed Gautam Chavan
2/22/2024 288 34 6.8 35.3 White Rust Observed Gautam Chavan
2/23/2024 312 35 6.7 35.2 White Rust Observed Gautam Chavan
2/24/2024 336 33 6.7 35.1 White Rust Observed Gautam Chavan
2/25/2024 360 34 6.8 35.4 White Rust Observed Gautam Chavan
2/26/2024 384 36 6.7 35.4 White Rust Observed Gautam Chavan
2/27/2024 408 37 6.7 35.3 White Rust Observed Gautam Chavan
2/28/2024 432 33 6.6 35.2 White Rust Observed Gautam Chavan
2/29/2024 456 35 6.7 35.1 White Rust Observed Gautam Chavan
3/1/2024 480 31 6.7 35.3 White Rust Observed Gautam Chavan
3/2/2024 504 33 6.8 35.2 White Rust Observed Gautam Chavan
3/3/2024 528 32 6.7 35 White Rust Observed Gautam Chavan
3/4/2024 552 33 6.7 35.3 White Rust Observed Gautam Chavan
3/5/2024 576 36 6.9 35.2 White Rust Observed Gautam Chavan
3/6/2024 600 35 6.8 35.4 White Rust Observed Gautam Chavan
3/7/2024 624 31 6.9 35.1 White Rust Observed Gautam Chavan
3/8/2024 648 33 6.8 35 White Rust Observed Gautam Chavan
3/9/2024 672 36 6.6 35.4 White Rust Observed Gautam Chavan
3/10/2024 696 37 6.6 35.5 White Rust Observed Gautam Chavan
3/11/2024 720 35 6.7 35.2 White Rust Observed Gautam Chavan
3/12/2024 744 36 6.8 35.1 White Rust Observed Gautam Chavan
3/13/2024 768 36 6.8 35.2 White Rust Observed Gautam Chavan
3/14/2024 792 33 6.9 35.5 White Rust Observed Gautam Chavan
3/15/2024 816 34 6.8 35.4 White Rust Observed Gautam Chavan
3/16/2024 840 35 6.9 35.1 White Rust Observed Gautam Chavan
3/17/2024 864 36 6.7 35.6 White Rust Observed Gautam Chavan
3/18/2024 888 33 6.8 35.7 White Rust Observed Gautam Chavan
3/19/2024 912 35 6.9 35.9 White Rust Observed Gautam Chavan
3/20/2024 936 34 7 35.7 White Rust Observed Gautam Chavan
3/21/2024 960 34 6.8 35.5 White Rust Observed Gautam Chavan
3/22/2024 984 35 6.9 35.7 White Rust Observed Gautam Chavan
3/23/2024 1008 33 6.7 35.3 White Rust Observed Gautam Chavan

Process Stop
REMARK-1) WHITE RUST INITIATES ON 96 HOURS
2) WHITE RUST OBSERVED ON 1008 HOURS

BEFORE ( Start of the test ) AFTER ( End of the test )

Prepared By :- Gautam Chavan Apporoved By:- Pritam Tunge


PMEA SOLAR TECH SOLUTIONS
PVT.LTD.
Salt Spray Test Inspection Report
E-20, MIDC, Sinnar Industrial Area ,
Sinnar (Nashik)
Part Details :- Painted Rail Start Date :- 2/11/2024
Supplier Name :- End Date :- 3/23/2024
Part No.- PM-1-44475-B 240101 Required SST Life :- 1000 Hours
Customer Name:- PMEA E-20 Token No. :- 99
Coating Type. :- 100% reworked spray coating Test Method Used:- ASTM B117
Lab No. :- SSTL-24 Solution :- 5% NaCl
CHEMBER TEMP.
Date Time (Hrs) Fog Collection (IN ML) PH (6.5-7.2) Observation Inspected By
(35 ± 2°)
2/11/2024 24 34 7 35.4 No Rust Gautam Chavan
2/12/2024 48 32 6.8 35.1 No Rust Gautam Chavan
2/13/2024 72 33 6.7 35.4 No Rust Gautam Chavan
2/14/2024 96 31 6.9 35.3 No Rust Gautam Chavan
2/15/2024 120 33 6.6 35.3 No Rust Gautam Chavan
2/16/2024 144 34 6.7 35.4 No Rust Gautam Chavan
2/17/2024 168 32 6.6 35.5 No Rust Gautam Chavan
2/18/2024 192 32 6.6 35.3 White Rust Initiates Gautam Chavan
2/19/2024 216 31 6.8 35.4 White Rust Observed Gautam Chavan
2/20/2024 240 33 6.9 35.2 White Rust Observed Gautam Chavan
2/21/2024 264 35 7 35.1 White Rust Observed Gautam Chavan
2/22/2024 288 34 6.8 35.3 White Rust Observed Gautam Chavan
2/23/2024 312 35 6.7 35.2 White Rust Observed Gautam Chavan
2/24/2024 336 33 6.7 35.1 White Rust Observed Gautam Chavan
2/25/2024 360 34 6.8 35.4 White Rust Observed Gautam Chavan
2/26/2024 384 36 6.7 35.4 White Rust Observed Gautam Chavan
2/27/2024 408 37 6.7 35.3 White Rust Observed Gautam Chavan
2/28/2024 432 33 6.6 35.2 White Rust Observed Gautam Chavan
2/29/2024 456 35 6.7 35.1 White Rust Observed Gautam Chavan
3/1/2024 480 31 6.7 35.3 White Rust Observed Gautam Chavan
3/2/2024 504 33 6.8 35.2 White Rust Observed Gautam Chavan
3/3/2024 528 32 6.7 35 White Rust Observed Gautam Chavan
3/4/2024 552 33 6.7 35.3 White Rust Observed Gautam Chavan
3/5/2024 576 36 6.9 35.2 White Rust Observed Gautam Chavan
3/6/2024 600 35 6.8 35.4 White Rust Observed Gautam Chavan
3/7/2024 624 31 6.9 35.1 White Rust Observed Gautam Chavan
3/8/2024 648 33 6.8 35 White Rust Observed Gautam Chavan
3/9/2024 672 36 6.6 35.4 White Rust Observed Gautam Chavan
3/10/2024 696 37 6.6 35.5 White Rust Observed Gautam Chavan
3/11/2024 720 35 6.7 35.2 White Rust Observed Gautam Chavan
3/12/2024 744 36 6.8 35.1 White Rust Observed Gautam Chavan
3/13/2024 768 36 6.8 35.2 White Rust Observed Gautam Chavan
3/14/2024 792 33 6.9 35.5 White Rust Observed Gautam Chavan
3/15/2024 816 34 6.8 35.4 White Rust Observed Gautam Chavan
3/16/2024 840 35 6.9 35.1 White Rust Observed Gautam Chavan
3/17/2024 864 36 6.7 35.6 White Rust Observed Gautam Chavan
3/18/2024 888 33 6.8 35.7 White Rust Observed Gautam Chavan
3/19/2024 912 35 6.9 35.9 White Rust Observed Gautam Chavan
3/20/2024 936 34 7 35.7 White Rust Observed Gautam Chavan
3/21/2024 960 34 6.8 35.5 White Rust Observed Gautam Chavan
3/22/2024 984 35 6.9 35.7 White Rust Observed Gautam Chavan
3/23/2024 1008 33 6.7 35.3 White Rust Observed Gautam Chavan

Process Stop
REMARK- 1) THIS PART IS 100 % REWORKED (REWORK TRAIL) BY SPRAY COATING AT ANTICORE COATING NASHIK
2) WHITE RUST INITIATES ON 192 HOURS
3) WHITE RUST OBSERVED ON 1008 HOURS

BEFORE ( Start of the test ) AFTER ( End of the test )

Prepared By :- Gautam Chavan Apporoved By:- Pritam Tunge