Shuttring, Deshuttering, Steel Fixing, P.C.C and R.C.C Work Jsa
Shuttring, Deshuttering, Steel Fixing, P.C.C and R.C.C Work Jsa
Shuttring, Deshuttering, Steel Fixing, P.C.C and R.C.C Work Jsa
Annexure-6
JOB SAFETY ANALYSIS
Reference work
Permit no:
JOB SAFETY Supervisor:
Prepared By:
ANALYSIS
Mobilization of Unskilled workers, Site safety induction should be provided to all new
Manpower Unauthorized entry employees.
Deploy experienced trained skilled worker for specific jobs.
Job specific training should be given
TBT to be taken on daily basis prior to start the job
Mandatory
PPE’s should be provided viz. safety helmet, safety shoes,
reflective jacket etc.
Safety Awareness/motivational programs shall be conducted
to workmen for more awareness on safety.
Medical fitness is must for all workers.
Gate pass compliance (As per JIL HR Dept) shall be complied.
Storage of shuttering Slip, trip & fall All shuttering material should be stored properly with
material hazards may arise due sufficient stacking height.
to improper Properly secure or tie store shuttering material
housekeeping at Shuttering yard areas to be demarcated and barricaded.
shuttering material
storage area
Manual handling of Sharp edge or Use mandatory PPEs safety shoes, helmet, gloves & goggles
shuttering material protruding nails etc.
Lifting of excess Bend / remove unwanted protruding nails. Use proper tool
weight to remove embedded nails, nails to be collected in proper
Material falling on box, maintain good housekeeping.
feet. Supervisor shall be ensure that no workman will lift more
Slippery surface & than 20 kg for manually handling loads more than 20kg,
tripping hazard. deploy a team of required manpower.
Page 1 of 5
Format No.: EHS-006/F06-00 Effective Date:
Jubliant Infrastructure Limited-Bharuch
Annexure-6
JOB SAFETY ANALYSIS
Page 2 of 5
Format No.: EHS-006/F06-00 Effective Date:
Jubliant Infrastructure Limited-Bharuch
Annexure-6
JOB SAFETY ANALYSIS
De-shuttering work Failure of scaffolding. Ensure continuous supervision during deshuttering work.
Fall of shuttering Proper inspection of scaffolding by certified inspector,
material required strengthening, supporting before start of work.
Contact with bare Barricade the deshuttering area.
nails, Only authorized persons are allowed.
Access block, Do not keep loose material on working platform
Improper material Follow proper sequence while shuttering / deshuttering
storage work.
Use of steel toe safety shoes.
Conduct tool box talk before starting the work.
Ensure access way should be free from obstruction.
After Deshuttering, all nails must be removed from shutter
material or sharp point of nails must be bend or sheared off.
Properly stack de-shuttering material.
Provide safe & unobstructed access way.
Work inside the Injury to person inside Ensure that work permit procedures are followed.
confined space the confined space Ensure that in & out record in confined space entry should be
Oxygen mentioned.
deficiency/hazardous Gas testing shall be carried out to ensure toxic gases.
gases Ensure the confined space check list then start the work.
Property damage Competence, training, supervision and suitability.
Personnel/equipment Proper ventilation either through natural or fan.
fall in confined space
Wear appropriate PPE
Awkward Access/
Confined space attendant still attend outside of confined space
Egress
until person working inside the confined space.
Personnel /equipment
fall in, collapse of Ensure proper good condition of ladder.
excavated adjacent Ensure proper entrance & exit of confined area
Keep access always clear from obstructions.
Ensure the excavated area hard barricaded
Remove all of loose items from excavated adjacent to avoid falling
Ensure proper shoring or maintain slope to avoid collapse of
excavated area.
R.C.C and P.C.C work Dermatitis disease TBT conducted before starting the work.
Personal injury Ensure work under supervision.
Body or eye injury Ensure all equipment in good condition and inspected by competent
Loss of eye person.
Slip/Trip hazard Wear mandatory PEEs like rubber gloves, gum boot, safety goggles,
Sprain and strain on body goggles etc.
parts. Wash the effected body parts with water immediately after concrete
Noise burn.
Trapping of legs inside Engage only trained worker for concreting work.
reinforcement mats. Use hearing protection when noise level exceeds more than 85db.
Concrete burn
Page 3 of 5
Format No.: EHS-006/F06-00 Effective Date:
Jubliant Infrastructure Limited-Bharuch
Annexure-6
JOB SAFETY ANALYSIS
Rebar installation/steel Hand injury Conduct tool box talk before start the work.
fixing work Cut/puncture/hand Make sure all protruded nail remove before wooden material lying at
injury the ground.
Slip/Trip/Fall Cover re-bar to avoid tripping where access is necessary. Wire mesh
Property damage will be installed on top of rebar mats to minimize slip, trip and fall
Pinch point hazards.
Heat Remove all unwanted material and secure properly to keep access and
egress free from obstruction.
Stress/Exhaustion Wear appropriate PPEs before starting the work.
Back injury Tool must be inspected before used.
Competent person must be deploy
Ensure area are clear and materials properly stack within the
working area.
All rebar’s that is protruding must be capped and kept
secured
Workers will be oriented about the proper posture and
positioning during the execution of the job.
Concrete compaction Fall/slip/trip Pre start work tool box talk discuss and understand the hazard on the
using vibrator machine Eye injury area.
Property damage Ensure all workers train and competent to perform task.
Wear mandatory PPEs like hand gloves, goggles, gum boot, helmet etc.
Vibrating tool causing Ensure cable should be proper routed at working area and free from
finger/hand injury joint.
Electric shock User take regular breaks from the activity alternate the task between
Excessive noise different people.
Provide ELCB in distribution board.
Work during night Poor Illumination Night work permit to be taken from concern engg.and safety
shift fall of person dept.
fall of machinery Ensure proper illumination during dark hours. (50 lux on
access & 110 lux on work location)
Electrical cable should lead min 2 m height. No exposed
Page 4 of 5
Format No.: EHS-006/F06-00 Effective Date:
Jubliant Infrastructure Limited-Bharuch
Annexure-6
JOB SAFETY ANALYSIS
electrical wire.Earthing.
Route shall be illuminated.
Ensure continues supervision provided at work place. Avoid
extra hours working.
Housekeeping Slip, trip hazards Ensure entire area shall be cleaned after job is completed.
Remove unwanted material from site after close the job.
Erection material should be proper stacking.
In Case of Emergency Confusion Emergency assembly point, emergency access should be
defined & always free from any obstructions.
Emergency contact details to be displayed at prominent
locations of site.
Emergency vehicle must be available at work locations
during all working hours.
All workers shall aware / trained about site emergency
procedure.
Permit issuer
Permit acceptor
Prepared by- Permit Issuer and Permit Acceptor Reviewed by-Plant Manager/ Safety
officer
Approved By HOD
Page 5 of 5
Format No.: EHS-006/F06-00 Effective Date: