Single Bench Judgement PF EDIFICE Developers and Projects Engineers ARB - 313 - 2007
Single Bench Judgement PF EDIFICE Developers and Projects Engineers ARB - 313 - 2007
Single Bench Judgement PF EDIFICE Developers and Projects Engineers ARB - 313 - 2007
07
kambli
O.O.C.J.
...
v/s.
CORAM: D.K.DESHMUKH, J.
JUDGMENT:
& Conciliation Act the Petitioner challenges the award made by the
per annum from the date of the award till realisation and rejecting
sole arbitrator. Before me, there was no dispute raised about what
that after the Statement of Claim was filed by the Respondent and
was claimant before the learned Arbitrator did not lead any oral
Petitioner did not ask the Respondent to restart the work though
learned Arbitrator held by his award that the retention money which
that the claim for refund of retention money was not raised in the
letter dated 22nd May, 2002, by which the arbitration clause was
the Petitioner, the Petitioner did not raise the question of jurisdiction
was not raised in the letter dated 22nd May, 2002. In substance, the
that as the claim was not included in the letter by which the
of Section 16, if the party raising the objection satisfies the learned
Arbitrator that it has sufficient cause for not raising the plea earlier.
this claim by writing a letter. Because the Petitioner did not raise an
objection , the Respondent could not do it. In any case, the learned
9 ARBP 313.07
Arbitrator has held that as the dispute arises out of the contract
after the Petitioner led oral evidence, abstract of claim was filed and
that best evidence has not been produced and no evidence has
been led to explain and show why the best evidence available has
of claim and for overhead loss in India on the basis of the judgment
was thus not necessary for the learned Arbitrator to deal with
both parties did not place reliance on any other formula other than
Hudson formula.
12 ARBP 313.07
goes through the award, one finds that the learned Arbitrator has
books of account nor led any oral evidence to prove the overhead
Paul Singh & Brothers v/s. State of Gujarat (AIR 1994 SC 1703) on
Consultant for the Claimants, this formula has been accepted by the
13 ARBP 313.07
losses.” The learned Arbitrator has thus recorded a finding that the
Respondent.
“(a) Best Evidence has not been produced and No evidence has
been led to explain and show why the Best evidence available
formula.
(c) Loss suffered has to be established in any event, and that has
Loss to be awarded.
case of Brij Paul Singh & Bros. v. State of Gujarat AIR 1994 SC
703.
That case does not recognize nor does it adopt use of Hudson
formula.
the Supreme Court in its judgment in Brij Paul’s case has not
Arbitrator, however, shows that this contention has not been dealt
that the Hudson formula has been accepted by the Supreme Court
the above quoted portion from the reply of the Petitioner shows that
claims and for that purpose the passage of Hudson’s text book is
cited. The learned Arbitrator has, however, chosen not to deal with
in Brij Paul Singh’s case shows that a contract was entered into
the Supreme Court M/s.A.T.Brij Paul Singh & Brothers for providing
40. The contractor did not complete the work within the time
executing the work and Rs.1 lakh as damages for extra work. The
total claim was Rs.11 lakhs.. The suit was defended by the State of
Bombay. The trial court dismissed the suit. Against the judgment of
the trial court dismissing the suit, an appeal was preferred before
the High Court. The High Court which decided the Appeal
substantially dismissed the Appeal, but allowed the appeal for few
surface in another protion of the same road. That contract was also
The trial court decreed that suit and awarded a sum of Rs.
the trial court. The Division Bench of the Gujarat High Court which
heard the Appeal held that the Defendant was guilty of breach of the
deleting certain items awarded by the trial court on the ground that
High Court the contractor filed an appeal before the Supreme Court.
agreement with the finding recorded by the High Court that it was
remaining part the contractor has already moved his men and
quoted above shows that the High Court after holding that the State
whether the contractor was entitled to damages under the head loss
Supreme Court then observed that the High Court held that though
the contractor was entitled to claim amount for loss of profit, that in
the absence of proper evidence led, the contractor was not entitled
that Book. However, did not award any amount to the contractor on
been done by the learned Arbitrator, that the Hudson formula has
that “ The loss of overhead at the rate of 10% of the gross value of
the learned Counsel appearing for the Respondent was not able to
paragraph 36(iv) observed “As the claim for delay damages made
market rate for awarding interest at the rate of 15% pendente lite.
the Supreme Court in that judgment does not lay down any such
proposition.
21 ARBP 313.07
“In the assessment of damages, the court must consider only strict
one contractor that the other will do something that he has assumed
which are prevalent and in that case the Arbitrator was justified in
110, 111, 112, 113, 114, 115 & 122 is relevant. Those paragraphs
read as under:
22 ARBP 313.07
278]
Step 1
Step 2
Allocable overhead
Total days of contract = Daily Overhead rate
Step 3
and suitable for that case adopted that formula. Perusal of the
award in the present case shows that the learned Arbitrator did not
to the abstract of claim, where calculations were for the first time
formula.
on the basis of Hudson formula and therefore that part of the award,
set aside.
(D.K.Deshmukh, J.)