Design and Analysis of Sewage Treatment
Design and Analysis of Sewage Treatment
Design and Analysis of Sewage Treatment
com
Introduction
An estimated 72,368 million liters per day (MLD) sewage is generated in urban areas, while
the treatment capacity across India is only 31,841 MLD according to data released by the
government in June 2021. Sewage wastewater is a type of wastewater that is produced by
acommunity of people and it is Sewage treatment plant (STP) that makes the water of the
sewage clean. The sequencing batch reactor (SBR) is a fill-and draw activated sludge
system for wastewater treatment. In this system, wastewater is added to a single “batch”
reactor, treated to remove undesirable components, and then discharged. Wastewater
generated in school and colleges have to take careas it may pollute the ground water if not
treated properly. Thispaper discusses the details of the analysis carried out recentlyon the
wastewaters and present a design for the STP based on Sequencing Batch Reactor (SBR)
concept.
Table 1 Characteristics of Raw Sewage
ODOR pH ALGAE
1
VOLUME 21 : ISSUE 8 (Aug) - 2022 Page No:419
YMER || ISSN : 0044-0477 http://ymerdigital.com
Literature Review
Murthy Polasa (2014) reviewed about design of sewage treatment plant for gated
community. In this project three types of treatment unit operations are conducted. Like
physical, chemical and biological processes. By increasing the detention time of sewage in
each treatment unit increases the efficiency of removal unwanted impurities.
Kim et al. (2008) researched the treatment of low strength wastewater with municipal
wastewater in enhanced SBR. It was proved that independent nitrification can be achieved
by incorporating the contact period within the system and nitrification in the external
reactor. The COD, TN and TP removal were 87%, 81 % and 60 % respectively which can
be considered far better than conventional treatments. As the ammonia nitrogen was
nitrified 70% in the external reactor, this system does not require any externally added
carbon for effective removal of nutrients and biodegradation of organic matter. Finally it
was concluded that the system is best suited for regular as well as advanced wastewater
treatment particularly for low strength wastewaters.
Lin S.H. and Cheng K.W., (2001) carried out the study in which the treatment of
municipal sewage is done with coagulation as a first process followed by SBR treatment.
A different design for the SBR reactor was attempted in this study which allows continuous
inflow of sewage wastewater while the other batch-wise operating steps of the SBR process
are retained. The SBR cycle is 12 hrs. Two perforated baffle plates containing a large
number of 2-mm holes that occupied a total surface area about 20% of the plate, divided
the SBR tank into three equal compartments. The perforated baffle plates served to
minimise the influence of the continuously in-flowing sewage wastewater on the “settle”
and “draw” operations of the SBR process. The results of the modified SBR were compared
with conventional SBR and concluded that modified SBR gives the same results with added
advantage of continuous flow. The COD and BOD removal was 93.6% and 91.8 %
respectively. Author also concluded that chemical coagulation is good option for
wastewater pre-treatment for SBR input. As modified SBR does not provide any significant
change in result, also may increase the maintenance, the modifications carried out have
certain scope for improvement.
2
VOLUME 21 : ISSUE 8 (Aug) - 2022 Page No:420
YMER || ISSN : 0044-0477 http://ymerdigital.com
Methodology
A rectangular-shaped receiving chamber is designed to collect the sewage and control its
flow. After that sewage is allowed to pass through a coarse screen. A screen is used to trap
the floating matters such as sachets, plastic milk packets, grocery bags etc., which could
disturb the impeller.
Table 2 SBR Operating Cycle Time
Design
SBR Steps Description
Time
Static Fill The raw wastewater enters in the SBR tank where no mixing or 0.75 hours
aeration is performed.
Aerated Fill Both aeration and mechanical mixing are activated in this step. 1.5 hours
The aerated filling time will start when the maximum filling time
is completed or top water level is reaches up to the mark.
React No-additional influent wastewater is added in this step and both 2 hours
aeration and mixing units are on. Nitrification is also resumed in
this step. In addition to this, the maximum organic matter is also
get reduced in this step.
Settle Aeration is stopped in this phase, that will allow to maintain a 1 hours
static condition, which will promote settling of the biological
flocs.
Decant This step extracts the treated effluent from the SBR basin. When 0.75 hours
treated supernatant reaches the bottom water level in the SBR,
the decantation step comes to an end.
Idle Waste activated sludge can be extra-cted in order to attain rapid 0 hours
settling (if require)
Total Total operation cycle time to run one SBR cycle. 6 hours
3
VOLUME 21 : ISSUE 8 (Aug) - 2022 Page No:421
YMER || ISSN : 0044-0477 http://ymerdigital.com
Advantages of SBR
Improvements in equipment and technology, especially in aeration devices and computer
control systems, have made SBRs a viable choice over the conventional activated-sludge
system. In areas where there is a limited amount of space, treatment takes place in a single
basin instead of multiple basins, allowing for a smaller footprint. Low total-suspended-solid
values of less than 10 milligrams per liter (mg/L) can be achieved consistently through the
use of effective decanters that eliminate the need for a separate clarifier.
Biochemical oxygen demand (BOD) levels of less than 5 mg/L can be achieved
consistently. Total nitrogen limits of less than 5 mg/L can also be achieved by aerobic
conversion of ammonia to nitrates (nitrification) and anoxic conversion of nitrates to
nitrogen gas (denitrification) within the same tank. Low phosphorus limits of less than 2
mg/L can be attained by using a combination of biological treatment (anaerobic phosphorus
absorbing organisms) and chemical agents (aluminium or iron salts) within the vessel and
treatment cycle.
Older wastewater treatment facilities can be retrofitted to an SBR because the basins are
already present. Wastewater discharge permits are becoming more stringent and SBRs offer
a cost-effective way to achieve lower effluent limits. Note that discharge limits that require
a greater degree of treatment may necessitate the addition of a tertiary filtration unit
following the SBR treatment phase. This consideration should be an important part of the
design process.
Design of Sewage Treatment Plant
Table 3 Salient Components of the Project Layout
4
VOLUME 21 : ISSUE 8 (Aug) - 2022 Page No:422
YMER || ISSN : 0044-0477 http://ymerdigital.com
5
VOLUME 21 : ISSUE 8 (Aug) - 2022 Page No:423
YMER || ISSN : 0044-0477 http://ymerdigital.com
6
VOLUME 21 : ISSUE 8 (Aug) - 2022 Page No:424
YMER || ISSN : 0044-0477 http://ymerdigital.com
Provide Blower with a capacity of 200 Cu.m /Hr considering air to be provided in
sludge tank.
Decant Tank Design:
Average flow = 8.39 m3/hr
Providing holding capacity of 3 hours
Tank required Volume = 25.17 m3
SWD provided is 2.5 m
Final collection size of tank is 3m x 3.3m x 2.5m SWD+0.3 m FB
Tertiary Treatment:
Pressure Sand Filter
Assuming 20 Hours of operation in a day,
So, average flow rate = 200/20 = 10 cu.m/hr
Filter type = Vertical type sand filter
Rate of Filtrations = 120 lit/m2.min
=0.120 x 60 m3/m2.hr =7.2 m3/m2.hour
Cross section area of Filter = 10/7.2 = 1.4 m2
Filter dia. = 1.3 m
Provide Filter size= 1.3 m dia. x 1.5 m ht (1 nos)
Activated Sand Filter
Period of filtration of 20 hrs / day
Flow rate = 200/20 = 10 m3/hr
Filter type = Vertical type
Rate of Filtrations = 120 lit/m2.min
=0.120 x 60 m3/m2.hr =7.2 m3/m2.hr
Cross section area of Filter = 10/7.2 = 1.4 m2
Provide Filter size= 1.3 m dia. x 1.5 m ht (1 nos)
Sludge Calculation for design of filter press:
Reduction of BOD in aeration tank = 138 – 10= 128 mg/L
Net yield considering average age of sludge of 20 days 25%
Sludge production from secondary sludge = 0.128 kg/Cum x 200cu.m/Day x 0.25 =6.4
Kg/day of secondary sludge
Contribution of Sludge by TSS = 0.5 x 300 g/Cu.m x 200 Cu.m/Day = 30 Kg / day on
dry basis
Total Produced sludge = 30 + 6.4 = 36.4 Kg , Say 37 Kg.
Sludge is drawn from the SBR reactor at the end of settling at 1% concentration.
Volume of produced sludge = 37/0.01 = 3700 Lit or 3.7 Cu.m/ Day
The excess sludge generated is dried from the above treatment; filter press is used for sludge
de-watering. The filtrate will be connected with the screen chamber.
Assuming the type of sludge : Organic
Designed sludge flow: 3700 ltrs/day
Solids concentration: 1%
Solids specific gravity: 1.2
Dry solids minimum to be allowed in: 25-30 % in cake of sludge
Sludge solids generated on daily basis
Generation rate : 3700 x 1.2 x 0.01 =44.4 kg/ day
7
VOLUME 21 : ISSUE 8 (Aug) - 2022 Page No:425
YMER || ISSN : 0044-0477 http://ymerdigital.com
Quantity of Sludge load on filter: 44.4 x 3 (three days of operation per week) = 133.2
kg/day
Assuming sludge holding capacity as 40 kg/m2
The size of the filter press required = 133.2/40 =3.33 m2
Size of each plate taken will be (0.6 x 0.6 m) = 0.36 sq.m.
No. of chambers required = 3.33/0.36 = 10 nos
Hence, provide 10 chambers with 30mm of spacing and filter press of 0.6m x 0.6m.
8
VOLUME 21 : ISSUE 8 (Aug) - 2022 Page No:426
YMER || ISSN : 0044-0477 http://ymerdigital.com
9
VOLUME 21 : ISSUE 8 (Aug) - 2022 Page No:427
YMER || ISSN : 0044-0477 http://ymerdigital.com
Assumptions -
Plate Thickness: - 250mm
Specific Gravity of Sewage: - 1.03
Tank Resting over ground surface
10
Conclusion
In line with Swachh Bharat Mission, with a drive to reduce pollution, the institutional
sewage disposal system is to be upgraded for meeting the standards. This project is aimed
to solve wastewater management problem in the educational institute like BIT, DURG.
However, the hazardous waste water coming from laboratory was not considered here. We
choose SBR in our project because it requires less area than other treatment processes and
it can be also adopted for various concentration of waste water. The treated water will be
supplied for the gardening, horticulture and cleaning purposes in BIT, DURG campus
which will reduce the demands of fresh water. Treated wastewater can cater to horticulture
11
needs in public parks and areas of gardening. It can even be used for flushing of toilets,
cleaning of floors, tools, plants and machinery by laying specific lines. Moreover, the
treated sludge can be used in increasing soil fertility. As Mr. Ismail Serageldin, Vice
President, World Bank-1995 rightly pointed out “Many of the wars this century were about
oil, but those of the next century will be over water”. Recycle and reuse is the need of the
day for preserving our precious natural resources.
REFERENCES
1. Analysis and Design of an Institutional Waste Water Management Scheme by R.Ranjon Roy ,T.R.
Sreekrishnan ,B. J. Alappat.
2. Design of Sewage Treatment Plant with Sequential Batch Reactor for Public Buildings Complex by
Shubham M. Dongre, Dr. Maya R. Ray.
3. Sequencing Batch Reactor Design And Operational Considerations Prepared By The New England
Interstate Water Pollution Control Commission.
4. EE Lab Manual Semester VII.
5. Design Of Sewage Treatment Plant( Stp) For Dayananda Sagar Institute, Bengaluru by Somya HN,
PiyushTome, MD Wasiuddin, Mohammed Parvez, Madhu HS.
6. Sewage Disposal and Air Pollution Engineering by S.K. Garg.
7. Bid document for SBR – Government of Haryana 2020-21.
8. Analysis and design if 10 MLD sewage treatment plant by using STAAD.PRO.
12