DCCBIJCAPaper Publication
DCCBIJCAPaper Publication
DCCBIJCAPaper Publication
net/publication/310662034
CITATIONS READS
0 67
3 authors, including:
Van-Vinh Nguyen
Incheon National University
3 PUBLICATIONS 3 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Van-Vinh Nguyen on 20 December 2017.
Abstract
The development of large scale direct current (DC) transmission system with high
efficiency and stability of DC grids has been studied widely. The dc circuit breaker
(DCCB) is introduced to ensure the stability of DC grids. Among different types of DCCB,
.
hybrid DCCB has gained more attention. This paper proposes a novel hybrid DCCB
AL
topology based on inverse current injecting method. The proposed DCCB topology is able
to perform the operation duty of reclosing and rebreaking. In addition, this paper also
G
considers the bidirectional topology of dc circuit breaker with bidirectional current
IL .
is nly
breaking capability. The operating characteristics of the proposed DCCB topology are
LE
verified by simulations in Matlab/Simulink environment.
fil O
Keywords: DC circuit breakers, Reclosing and rebreaking operation, Bidirectional
operation.
is n
th rsio
1. Introduction
e
In order to develop any power grid, whether ac or dc, the circuit breaker is the main
component required that can interrupt quickly and reliably to prevent damage to power
by e
when a fault occurs [1]. The technical challenges of dc circuit breakers for the dc grid are
e eV
larger than the traditional ac system. It is understood that the dc fault levels very high is
caused by low dc impedances and the absence of a natural current zero-crossing point [2].
Therefore, the target of developing of a dc circuit breaker is to provide breaker with the
ad in
ability to reduce current to zero rapidly [3-4]. Furthermore, after the initial breaking
operation by faults, it is necessary for the power grid to supply the loads as quickly as
m nl
possible. If the duration of interruption after initial breaking operation sustains for longer
O
durations, it will result in serious economic losses to the operators. Therefore, the
operating duty of the DCCB topology must be able to implement the reclosing and
rebreaking repeatedly, as mentioned in IEC-62271-100 Standard [5].
On the other hand, bidirectional topologies of DCCBs are widely applied instead of
using a single direction DCCB topologies [6]. It was explained that the output power is
controlled by charging the dc system current, thus the DCCB topology should be able to
ok
break the current in both the direction of forward and reverse sides [7]. In multi-terminal
DC grids during the fault, the normal power flow terminates and current from all the
Bo
nodes flow towards the fault point. Hence, the DCCB topology must have bidirectional
current breaking capability [8]. Therefore, in order to improve the reliability of DC power
systems and to prevent damage to DC grids, a DCCB with bidirectional capability is
required.
Based on these key points, several new DCCB topologies are developed recently. In [9-
10-11], the hybrid DCCBs are proposed to achieve reclosing and rebreaking capability
because of recharging the capacitor by using an auxiliary power supply. However, those
topologies are costly for applications of DC grids. Meanwhile, the proposed solid state
DCCB topologies are improved to reclose and rebreak without using the auxiliary power
Corresponding Author
supply, but these topologies do not have bidirectional current breaking capabilities [12-
13-14].
To overcome such drawbacks, this paper proposes a novel DCCB topology which is
not only capable of reclosing and rebreaking without using the auxiliary power supply but
also can implement bidirectional current breaking when a fault occurs. The proposed
DCCB topology and operation principle is described in Section 2 in detail. Section 3
illustrates the simulation results to verify the validity of the proposed topology in
Matlab/Simulink software. Finally, conclusions are presented in Section 4.
.
Basically, the main branch with a mechanical switch is for normal operation in the circuit.
AL
The auxiliary branch with an inductor, capacitor, and switch is to make resonance current
when the switch is turned-on. The current in the main branch can be zero by the injected
G
inverse current from the resonance circuit. The DCCB topology proposed in this paper is
IL .
is nly
based on the conventional injection current method. Figure 1 represents the simple
LE
structure of the DC circuit with the proposed DCCB. It is for unidirectional operation of
DCCB and consists of three mechanical switches and three thyristors. The branch with the
fil O
resistor R1 and the switch S3 is used for recharging the capacitor C. The branch with the
resistor L2 and the switch T2 is used for reversing the polarity of the capacitor voltage.
is n
And the branch with resistor R2 and the thyristor T3 is to charge capacitor.
th rsio
e
Rs Ls S1 S2
T1
by e
e eV
C L1
L
ad in
+ O
- Es
R1 S3 A
m nl
D
L2 T2
O
R2
T3
DC Circuit Breaker
ok
Rs Ls S1 S2 Rs Ls S1 S2
T1 T1
C L1 C L1
L L
+ O + O
- Es - Es
R1 S3 A R1 S3 A
D D
L2 T2 L2 T2
R2 R2
T3 T3
Rs Ls S1 S2 Rs Ls S1 S2
T1 T1
C L1 C L1
.
L L
AL
+ O + O
- Es - Es
R1 S3 A R1 S3 A
D D
L2 T2 L2 T2
G
R2 R2
IL .
T3 T3
is nly
LE
(c) Mode 3 (t3 ~ t4) (d) Mode 4 (t4 ~ t5)
fil O
Rs Ls S1 S2 Rs Ls S1 S2
T1 T1
is n
C L1 C L1
L L
th rsio
+ O + O
Es Es
e
- R1 S3 A - R1 S3 A
D D
L2 T2 L2 T2
R2 R2
by e
T3 T3
e eV
The capacitor in the DCCB should be pre-charged before the occurrence of the fault in
O
the circuit. It means that the pre-charged capacitor of the proposed DCCB topology is
required to generate resonance current by L1 – C circuit. At this time, the injected current
into the main branch should be bigger than the fault current. During the charging mode, as
shown in Figure 2(a), the current flows through the path of T 1 – C – R2 – T3. During this
time interval, the capacitor is charged until the required voltage is achieved by turning-on
the thyristor T1. If the charging of the capacitor is finished at t2, the thyristor T1 is
ok
naturally turned-off.
Bo
Meanwhile, if the magnitude of the fault current is smaller than the preset reference
current, the status of thyristor T1 is kept as the turned-off condition. In the breaking mode,
if the thyristor T1 is turned-on, the resonance current ic in the L1 – C circuit is increased
gradually. When the magnitude of the resonance current is equal to short circuit current is1,
the switch S2 is turned-off and all current in the circuit only flow through auxiliary branch
as shown in Figure 2(d). After that, the fault current is decreased gradually, the thyristor
T1 is naturally turned-off.
.
branch with the C – R1 – S3 as shown in Figure 2(e). However, the polarity of the
AL
capacitor is different from the polarity of the precharged voltage initially. Therefore, the
operation for reversing the polarity is required as shown in Figure 2(f). During the reverse
G
mode, the capacitor voltage can be changed from +Vmax to –Vmax by equation (1). When
IL .
the operation in the reverse mode is finished, the thyristor T2 is naturally turned-off.
is nly
LE
1
𝑉𝑐 (𝑡) = 𝑉𝑚𝑎𝑥 (1 − 𝑐𝑜𝑠 𝐿𝐶 𝑡)
fil O
√
(1)
is n
Figure 4(a) assumes that the fault occurs at the right side of DCCB. The normal current
e eV
flows from the left to the right through the thyristor T1a and T1b. In contrast, Figure. 4(b)
assumes that the fault occurs at the left side of DCCB. The normal current flows from the
right to the left through the thyristor T2a and T2b. In this topology, the polarity of the
ad in
precharged capacitor is same although the direction of the current flow for breaking is
m nl
changed.
O
L
+ O
Bo
- Es
is3 R1 S3 A
D
it4 L2 T4
R2
T3
a b a b
T2b S2 T2b S2
T1a C T1b L1 T1a C T1b L1
T2a T2a
a) From the left side to the right b) From the right side to the right
Figure 4. Bidirectional Current Flow in the Proposed DCCB Topology
3. Simulation Results
3.1. Test Scenario
.
In order to test the proposed DCCB topology, Figure 3 is used in the simulation and its
AL
parameters are shown in Table 1. The simulation is based on two scenarios such as
breaking the positive current and the negative current in bidirectional DCCB topology. In
G
addition, the number of operations of the DCCB are limited to two time because it is
IL .
enough to verify the capability of the reclosing and rebreaking. The fault condition is
is nly
LE
considered as the short circuit without any load.
Parameters Specification
th rsio
Rs 0.001 [Ω]
e eV
Ls 5 [uH]
C 20000 [μF]
ad in
R1 0.5 [Ω]
m nl
R2 0.77 [Ω]
O
L1 0.02 [uH]
L2 0.1 [uH]
not precharged initially. The operation of the DCCB starts after a time delay of 0.05s. DC
currents in each branch and DC voltage of capacitor are represented in Figure 5 to Figure
Bo
7. In addition, Figure 8 shows the control signals in each switch including thyristor.
During the charging mode, the charging current flows through the branch with switch S 1,
thyritosr T1a and T3. The capacitor was fully charged to 100V within 0.05s as shown in
Figure 7. The thyritosr T1a and T3 are naturally turned-off at the end of the charging mode.
As mentioned in the section 2.2, the negative capacitor voltage is required for normal
operation of the DCCB. This operation is possible by turning-on the thyristor T4 at 0.15s.
The condition of the short circuit starts right after changing the polarity of capacitor
voltage. During the normal mode, DC current can be increased on the branch with switch
S1 and S2. When the DC current reaches to the setting value for interrupting DC current,
the inverse current by L1 – C resonant circuit is injected to main circuit by turning-on
thyristor T1a and T1b. When the current on switch S2 is reduced to zero, the switch S2 is
turned-off. After that, the current is1 is fully interrupted within 12ms. However, the
voltage of capacitor is very high during the breaking operation and the discharging of the
capacitor is required to perform the reclosing and rebreaking capability in the next
operation. Therefore, the capacitor voltage is discharged by turning-on the switch S3 until
its voltage is equal to the required magnitude. If the operation for discharging the
capacitor voltage is finished, the reclosing and rebreaking is possible after reversing the
capacitor voltage. As a result, the sequential process of the DCCB can be repeated until
the fixed number of times.
.
AL
G
IL .
is nly
LE
fil O
Figure 5. Simulation Waveform of Current Flow in the Breaking Mode
is n
th rsio
e
by e
e eV
ad in
m nl
O
.
AL
(d) T1a signal (e) T1b signal (f) T2a signal
G
IL .
is nly
LE
fil O
(g) T2b signal (h) T3 signal (i) T4 signal
is n
In order to charge the capacitor in proposed DCCB, the DC source should be connected
e eV
to left side of the DCCB as shown in Figure 3. Therefore, for interrupting the negative
current in the DC circuit, it is assumed that the capacitor is precharged to the required
voltage and the polarity of the DC source is only changed to consider negative current in
ad in
the topology. In other words, there is no charging mode at initial time. For interrupting the
negative current, the DC currents in each branch and DC voltage of capacitor are
m nl
represented in Figure 9 to Figure 11 and the control signals in each switch including
thyristor are shown in Figure 12. The overall operation of the DCCB is similar to the
O
.
AL
G
IL .
is nly
LE
fil O
is n
4. Conclusions
This paper proposed a novel circuit breaker topology for breaking the dc fault current.
The DCCB is capable of the reclosing and rebreaking because of the recharging of the
capacitor. In addition, it is possible to interrupt the positive and negative dc fault current
in the circuit. The simulation results showed that the performances of this proposed
topology is suitable for the bidirectional operation.
Acknowledgments
This research was supported by Korea Electric Power Corporation through Korea
Electrical Engineering & Science Research Institute[grant number: R15XA03-40]
References
.
AL
[1] U. A. Khan, J. G. Lee, F. Amir, “A Novel Model of HVDC Hybrid-Type Superconducting Circuit
Breaker and Its Performance Analysis for Limiting and Breaking DC Fault Currents,” IEEE
Transactions on Applied Superconductivity, vol. 25, no. 6, (2015), pp. 1-9.
G
[2] M. Hajian, L. Zhang and D. Jovcic, “DC transmission grid with low-speed protection using mechanical
IL .
is nly
DC circuit breakers” IEEE Transactions on Power Delivery, vol. 30, no. 3, (2015), pp. 1383-1391.
LE
[3] A. Shukla and G. D. Demetriades, “A survey on hybrid circuit-breaker topologies,” IEEE Transactions
on Power Delivery, vol. 30, no. 2, (2015), pp. 627-641.
fil O
[4] A. Mokhberdoran, A. Carvalho, H. Leite , and N. Silva, “A review on HVDC circuit breakers”, 3rd IET
Renewable Power Generation Conference , (2014) September, pp. 1-6.
is n
[5] C. Abbey, D. Cornforth, N. Hatziargyriou, K. Hirose, A. Kwasinski, E. Kyriakides, and S.
Suryanarayanan, “Powering through the storm: microgrids operation for more efficient disaster
th rsio
recovery,” IEEE power and energy magazine, vol. 12, no. 3, (2014), pp. 67-76.
e
[6] Y. Bingjian, G. Yang, W. Xiaoguang, H. Zhiyuan, C. Longlong, and S. Yunhai, “A hybrid circuit
breaker for DC-application,” IEEE First International Conference on DC Microgrids (ICDCM), (2015),
by e
pp. 187-192.
[7] K. Sano and M. Takasaki, “A surgeless solid-state DC circuit breaker for voltage-source-converter-based
e eV
HVDC systems,” IEEE Transactions on Industry Applications, vol. 50, no. 4, (2014), pp. 2690-2699.
[8] G. Asplund, “High Voltage DC Grid Feasibility Study Working Group B4-52,” CIGRE, (2013), pp.56-
65.
ad in
[9] K. Tahata, S. El Oukaili, K. Kamei, D. Yoshida, Y. Kono, R. Yamamoto, and H. Ito, “HVDC circuit
breakers for HVDC grid applications,” 11th IET International Conference on AC and DC Power
m nl
curcuit breaker,” 3rd IEEE International Conference on Electric Power Equipment??? Switching
Technology (ICEPE-ST), (2015), pp. 501-505.
[11] Atmadji. Ali Mahfudz Surya, “Direct current hybrid breakers: a design and its realization”, Thesis PhD
Electricity and Magnetism, (2000).
[12] J. Y. Kim, S. S. Choi, and I. D. Kim, “A novel reclosing and rebreaking DC solid state circuit breaker,”
9th IEEE International Conference on Power Electronics and ECCE Asia (ICPE-ECCE Asia),
ok
and rebreaking capabilities,” 8th IEEE International Power Electronics and Motion Control Conference
(IPEMC-ECCE Asia), (2016), pp. 3554-3558.
[14] Peter M. McEwan and Sarath B. Tennakoon, “A two-stage DC thyristor circuit breaker”, IEEE
Transactions on power electronics, vol. 12, no. 4, (1997), pp. 597-607.
Authors
.
AL
combined master and Ph. D. student in department of Electrical
Engineering from Incheon National University. His research interests
are power system analysis, HVDC system control & protection, and
G
IL .
FACTS.
is nly
LE
fil O
Hak-Man Kim, He received his first Ph.D. degree in Electrical
Engineering from Sungkyunkwan University, Korea in 1998 and
is n