CESL Tender Pilot Demonstration For RE Based EV Charging 1695551606
CESL Tender Pilot Demonstration For RE Based EV Charging 1695551606
CESL Tender Pilot Demonstration For RE Based EV Charging 1695551606
Date 04.09.2023
Loan/Grant No. and Title The name of the Project is: Scaling up Demand – Side Energy Efficiency
Sector Project.
Grant No.: 9874-IND
Title CESL/06/2023-24/OCB-Solar Carports/232408003.
1. India has received financing from the Asian Development Bank (ADB) toward the cost of Scaling up
Demand – Side Energy Efficiency Sector Project. Part of this financing will be used for payments
under the contract named above. Bidding is open to Bidders from eligible source countries of ADB.
2. The Executing Agency for this pilot program shall be Energy Efficiency Services Limited (EESL) and
the procurement agency will be Convergence Energy Services Limited (CESL)-A wholly owned
subsidiary of EESL (the “Purchaser”).
3 The Convergence Energy Services Limited (CESL) (the “Purchaser”) invites sealed bids from
eligible Bidders for “Design, Engineering, Supply, Civil work, Erection of suitable raised structure,
Installation, Testing & Commissioning of the 25/50 kWp Bi-facial vertical Solar PV along with
Battery Energy Storage System (BESS) of 100/200 kWh with EV Chargers” project including
Operation and Comprehensive Maintenance (O&M) (the “Goods”).
The detailed scope of works for above tender is described in the Bidding Documents.
3. International Competitive Bidding will be conducted in accordance with ADB’s Single Stage: Single-
Envelope procedure and is open to all bidders with no country restrictions and universal procurement
will apply.
4. The complete Bidding Documents including tender drawings, if any, shall be available for inspection
and downloading at CESL’s website https://cesl.eproc.in (hereinafter referred to as the ‘Portal/e-
Portal/e-tender Portal’) from (Indian Standard Time (IST)) on 04.09.2023 to 14.00 Hrs. on
19.10.2023.
5. Interested bidders have to necessarily register themselves on the portal https://cesl.eproc.in as
explained in Para 6.1 below to participate in the bidding under this invitation for bids. It shall be the
sole responsibility of the interested bidders to get themselves registered at the aforesaid portal for
which they are required to contact M/s C1 India Pvt Ltd Gurugram at following address to complete
the registration formalities:
M/s C 1 India Pvt Ltd.,
Plot No. 68, 3rd Floor,
Sectio-44, Gurugram
Haryana-122003
Contact No.: +91 124 430 2000; +91 97735 81223; +91 95606 37779;
1
Email-ID: [email protected], [email protected]
A onetime fee of INR 5000 is to be paid for this registration.
Digital Signature Certificates (DSCs): To carry out e-Procurement using e-Procurement portals, all
bidders will be required to obtain valid DSC of Class 3 (Signing + Encryption) issued by a Certifying
Authority (CA) licensed by Controller of Certifying Authorities (CCA) [refer http://www.cca.gov.in
]. Bidders are solely responsible for purchase of valid Digital Signature Certificate from authorized
Certification Authorities and safe keeping of the certificates. The e-mail address specified in the
Digital Signature Certificate shall match with the e-mail address specified in the user profile created
during supplier registration. Bidders shall take due care to safe keep the e-Procurement system and
DSC token passwords. The Purchaser shall not be responsible for inability of bidder to participate
in a tender due to loss of password by bidder or inability of the bidder to retrieve password. The
Purchaser shall not be responsible for failures or breakdowns of systems, other than those, strictly
within the control of Purchaser and its e-Procurement service provider. Bidders shall take due care
to ensure purchase of Digital Signature Certificate requisite for tender submission in the e-
Procurement portal, availability of internet connectivity and requisite client software.
6.1 Registration on e-Procurement portal: As stated above, Bidders have to be registered in the e-
Procurement portal to be able to participate in tenders published on the site. Registration of each
organization is to be done by one of its senior persons who will be the main person coordinating for
the e-tendering activities. For further details, please visit the website https://cesl.eproc.in, and
follow further instructions.
Please note that even after acceptance of your registration by the Service Provider, Bidders need
time to complete the mandatory activities related to their organization and prospective bidders are
advised to plan accordingly.
6.2 They may obtain further information regarding this IFB from the office of Chief General Manager
(Contracts), CESL at the address given at para 8.1 below from 1500 hours to 1700 hours on all
working days till the deadline as per para 4.0 above.
For proper uploading of the bids on the portal namely https://cesl.eproc.in it shall be the sole
responsibility of the bidders to apprise themselves adequately regarding all the relevant procedures
and provisions as detailed at the portal as well as by contacting M/s C 1 India Pvt Ltd, Gurugram
directly, as and when required, for which contact details are mentioned above. The Purchaser in no
case shall be responsible for any issues related to timely or properly uploading/submission of the
bid in accordance with the relevant provisions of Section II – ITB of the Bidding Documents.
Tender Document fee of US $350 Only or in INR 25,000 (Indian Rupees Twenty-Five Thousand
Only) in the form of Banker’s Cheque/Demand Draft/Pay Order/NEFT/RTGS drawn in favour of
“Convergence Energy Services Limited”, payable at New Delhi shall be paid with the submission
of the documents in line with Clause 11 of Section 2, Bid Data Sheet.
In addition to above, Bid Document fee may also be submitted online through RTGS/NEFT.
The detail of RTGS/NEFT is as mentioned below:
Bank Name&
Account Name Account No. RTGS DETAIL
Branch Name
IFSC Code: ICIC0000007
Convergence Energy ICICI Bank
000705051799 MICR Code: 110229002
Services Limited New Delhi - Connaught Place
Customer ID: 578807920
Note: Bidders submitting Bid Fee through RTGS/NEFT shall upload the scan copy of
receipt of transfer of amount in Envelope-I. Participation of bidder shall be subject
to confirmation of amount transferred through RTGS/NEFT. The details
2
mentioned in document uploaded as proof of transfer of amount shall only be
considered for verification purpose.
Bidder’s failure to submit non-refundable fee towards the cost of Bidding Documents in the
form of an acceptable Banker’s Cheque/Demand Draft/Pay Order along with the bid or an
online payment through /NEFT/RTGS or subsequently pursuant to Clarification as per ITB
29.2, shall lead to outright rejection of the Bid.
The hard copy part of the Bid as per clause 11 of the Bid Data Sheet shall be received up to
14:30 Hrs. (IST) on 19.10.2023. Soft Copy parts of bids shall be uploaded up to 14:30 Hrs.
(IST) on 19.10.2023. hard copy part of the bids must be accompanied by a EMD/Bid Security
and Bid Document fee in the amount as stated in the Bidding Document (Bid Data Sheet).
The Technical Bid and Schedule for Price bid (First Envelope) shall be opened online on
19.10.2023 at 15:00 Hrs. (IST) as per the bidding documents.
8.1 The Purchaser shall not be held liable for any delays due to system failure beyond its control.
Even though the system will attempt to notify the bidders of any bid updates, the Purchaser
shall not be liable for any information not received by the bidder. It is the bidders’ responsibility
to verify the website for the latest information related to the tender.
Alternative Bids shall not be permitted.
A Pre-Bid meeting will be held on 25.09.2023 at 11:00 Hrs. (IST) at the office of CESL
mentioned below.
CESL will not be responsible for any costs or expenses incurred by Bidders in connection with
the preparation or submission of Bids.
In the comparison of Bids, ADB’s Domestic Preference Scheme will be applied in accordance
with the provisions stipulated in the Bidding Documents.
All correspondence with regard to the above shall be made to the following address:
(By Post/In Person)
Sh. Ashim Bhattacharya,
Chief General Manager (Contracts)
Convergence Energy Services Limited
NFL Building, 2nd Floor,
Core – III SCOPE Complex,
Lodhi Road, New Delhi-110003
Telephone: +011-42259600;
E-mail address: [email protected],
[email protected] , [email protected]; [email protected]
For more information on CESL, please visit the site at https://www.convergence.co.in/
3
Section 1: Instructions to Bidders 1-1
Table of Clauses
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
4
1-2 Section 1: Instructions to Bidders
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
5
Section 1: Instructions to Bidders 1-3
A. General
1. Scope of Bid 1.1 In connection with the Invitation for Bids (IFB) indicated in the Bid Data
Sheet (BDS), the Employer, as indicated in the BDS, issues this Bidding
Document for the procurement of plant and services as specified in Section
6 (Employer’s Requirements). The name, identification, and number of lot/s
(contract/s) of the open competitive bidding (OCB) are provided in the BDS.
2. Source of Funds 2.1 The Borrower or Recipient (hereinafter called “Borrower”) indicated in the
BDS has applied for or received financing (hereinafter called “funds”) from
the Asian Development Bank (hereinafter called “ADB”) toward the cost of
the project named in the BDS. The Borrower intends to apply a portion of
the funds to eligible payments under the contract(s) for which this Bidding
Document is issued.
2.2 Payments by ADB will be made only at the request of the Borrower and
upon approval by ADB in accordance with the terms and conditions of the
Financing Agreement between the Borrower and ADB (hereinafter called
“Financing Agreement”), and will be subject in all respects to the terms and
conditions of that Financing Agreement. No party other than the Borrower
shall derive any rights from the Financing Agreement or have any claim to
the funds.
3. Fraud and 3.1 ADB requires Borrowers (including beneficiaries of ADB-financed activity)
Corruption and their personnel, as well as firms and individuals participating in an
ADB-financed activity, including but not limited to, Bidders, Suppliers, and
Contractors, agents, subcontractors, subconsultants, service providers,
subsuppliers, manufacturers (including their respective officers, directors,
employees and personnel) under ADB-financed contracts to observe the
highest standard of ethics during the procurement and execution of such
contracts in accordance with ADB’s Anticorruption Policy (1998, as
amended from time to time). In pursuance of this policy, ADB
(a) defines, for the purposes of this provision, the terms set forth below as
follows:
(i) “corrupt practice” means the offering, giving, receiving, or
soliciting, directly or indirectly, anything of value to influence
improperly the actions of another party;
(ii) “fraudulent practice” means any act or omission, including a
misrepresentation, that knowingly or recklessly misleads, or
attempts to mislead, a party to obtain a financial or other benefit
or to avoid an obligation;
(iii) “coercive practice” means impairing or harming, or threatening
to impair or harm, directly or indirectly, any party or the property
of the party to influence improperly the actions of a party;
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
6
1-4 Section 1: Instructions to Bidders
1
Whether as a Contractor, Subcontractor, Consultant, Manufacturer or Supplier, or Service Provider; or in any other capacity (different
names are used depending on the particular Bidding Document).
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
7
Section 1: Instructions to Bidders 1-5
4. Eligible Bidders 4.1 A Bidder may be a natural person, private entity, or government-owned
enterprise subject to ITB 4.5 - or any combination of them with a formal
intent to enter into an agreement or under an existing agreement in the
form of a Joint Venture. In the case of a Joint Venture,
(a) all partners shall be jointly and severally liable; and
(b) the Joint Venture shall nominate a Representative who shall have the
authority to conduct all business for and on behalf of any and all the
partners of the Joint Venture during the bidding process and, in the
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
8
1-6 Section 1: Instructions to Bidders
4.2 A Bidder, and all partners constituting the Bidder, shall have the nationality
of an eligible country, in accordance with Section 5 (Eligible Countries). A
Bidder shall be deemed to have the nationality of a country if the Bidder is
a citizen or is constituted, incorporated, or registered, and operates in
conformity with the provisions of the laws of that country. This criterion shall
also apply to the determination of the nationality of proposed
subcontractors or suppliers for any part of the Contract, including related
services.
4.3 A Bidder shall not have a conflict of interest. All Bidders found to have a
conflict of interest shall be disqualified. A Bidder may be considered to be
in a conflict of interest with one or more parties in this bidding process if
any of, including but not limited to, the following apply:
(a) they have controlling shareholders in common; or
(b) they receive or have received any direct or indirect subsidy from any of
them; or
(c) they have the same legal representative for purposes of this bid; or
(d) they have a relationship with each other, directly or through common
third parties, that puts them in a position to have access to material
information about or improperly influence the bid of another Bidder, or
influence the decisions of the Employer regarding this bidding process;
or
(e) a Bidder participates in more than one bid in this bidding process, either
individually or as a partner in a Joint Venture, except for alternative
offers permitted under ITB 13. This will result in the disqualification of
all Bids in which it is involved. However, subject to any finding of a
conflict of interest in terms of ITB 4.3 (a) - (d) above, this does not limit
the participation of a Bidder as a subcontractor in another Bid or of a
firm as a subcontractor in more than one Bid; or
(f) a Bidder, Joint Venture partner, associates, parent company or any
affiliated entity, participated as a consultant in the preparation of the
design or technical specifications of the plant and services that are the
subject of the Bid; or
(g) a Bidder was affiliated with a firm or entity that has been hired (or is
proposed to be hired) by the Employer or Borrower as Project Manager
for the Contract; or
(h) a Bidder would be providing goods, works, or nonconsulting services
resulting from or directly related to consulting services for the
preparation or implementation of the project specified in the BDS ITB
2.1 that it provided or were provided by any affiliate that directly or
indirectly controls, is controlled by, or is under common control with
that firm; or
(i) a Bidder that has a financial or familial relationship with staff of the
Employer including project implementing/executing agency, or of a
recipient of a part of the loan who: (i) are directly or indirectly involved
in the preparation of the bidding documents or specifications of the
contract, and/or the bid evaluation process of such contract; or (ii)
would be involved in the implementation or supervision of such contract
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
9
Section 1: Instructions to Bidders 1-7
unless the conflict stemming from such relationship has been resolved
in a manner acceptable to ADB throughout the procurement process
and execution of the contract.
4.4 A firm will not be eligible to participate in any procurement activities under
an ADB-financed, -administered, or -supported project while under
temporary suspension or debarment by ADB pursuant to its Anticorruption
Policy (see ITB 3), whether such debarment was directly imposed by ADB,
or enforced by ADB pursuant to the Agreement for Mutual Enforcement of
Debarment Decisions. A bid from a temporary suspended or debarred firm
will be rejected and such bid may be in breach of debarment conditions,
thereby subject to further ADB’s investigation.
4.7 Bidders shall provide such evidence of their continued eligibility satisfactory
to the Employer, as the Employer shall reasonably request.
5. Eligible Plant 5.1 The plant and services to be supplied under the Contract shall have their
and Services origin in eligible source countries as defined in ITB 4.2 and all expenditures
under the Contract will be limited to such plant and services.
5.2 For purposes of ITB 5.1 above, “origin” means the place where the plant,
or component parts thereof are mined, grown, produced, or manufactured,
and from which the services are provided. Plant components are produced
when, through manufacturing, processing, or substantial or major
assembling of components, a commercially recognized product results that
is substantially in its basic characteristics or in purpose or utility from its
components.
6. Sections of 6.1 The Bidding Document consists of Parts I, II, and III, which include all the
Bidding sections indicated below, and should be read in conjunction with any
Document addenda issued in accordance with ITB 8.
PART I Bidding Procedures
Section 1 - Instructions to Bidders (ITB)
Section 2 - Bid Data Sheet (BDS)
Section 3 - Evaluation and Qualification Criteria (EQC)
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
10
1-8 Section 1: Instructions to Bidders
6.2 The IFB issued by the Employer is not part of the Bidding Document.
6.3 The Employer is not responsible for the completeness of the Bidding
Document and its addenda, if they were not obtained directly from the
source stated by the Employer in the IFB.
6.4 The Bidder is expected to examine all instructions, forms, terms, and
specifications in the Bidding Document. Failure to furnish all information or
documentation required by the Bidding Document may result in the
rejection of the Bid.
7. Clarification of 7.1 A prospective Bidder requiring any clarification on the Bidding Document
Bidding shall contact the Employer in writing at the Employer’s address indicated
Document, Site in the BDS, or raise his enquiries during the pre-bid meeting if provided for
Visit, Pre-Bid in accordance with ITB 7.4. The Employer will respond to any request for
Meeting clarification, provided that such request is received no later than 21 days
prior to the deadline for submission of bids. The Employer’s response shall
be in writing with copies to all Bidders who have acquired the Bidding
Document in accordance with ITB 6.3, including a description of the inquiry
but without identifying its source. Should the Employer deem it necessary
to amend the Bidding Document as a result of a request for clarification, it
shall do so following the procedure under ITB 8 and ITB 24.2.
7.2 The Bidder is advised to visit and examine the site where the plant is to be
installed and its surroundings and obtain for itself on its own responsibility
all information that may be necessary for preparing the Bid and entering
into a contract for the provision of plant and services. The costs of visiting
the site shall be at the Bidder’s own expense.
7.3 The Bidder and any of its personnel or agents will be granted permission
by the Employer to enter its premises and lands for the purpose of such
visit, but only upon the express condition that the Bidder, its personnel, and
agents, will release and indemnify the Employer and its personnel and
agents from and against all liability in respect thereof, and will be
responsible for death or personal injury, loss of or damage to property, and
any other loss, damage, costs, and expenses incurred as a result of the
inspection.
7.4 The Bidder’s designated representative is invited to attend a pre-bid
meeting, if provided for in the BDS. The purpose of the meeting will be to
clarify issues and to answer questions on any matter that may be raised at
that stage.
7.5 The Bidder is requested to submit any questions in writing, to reach the
Employer not later than 1 week before the pre-bid meeting.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
11
Section 1: Instructions to Bidders 1-9
7.6 Minutes of the pre-bid meeting, including the text of the questions raised,
without identifying the source, and the responses given, together with any
responses prepared after the meeting, will be transmitted promptly to all
Bidders who have acquired the Bidding Document in accordance with ITB
6.3. Any modification to the Bidding Document that may become necessary
as a result of the pre-bid meeting shall be made by the Employer
exclusively through the issue of an addendum pursuant to ITB 8 and not
through the minutes of the pre-bid meeting.
8. Amendment of 8.1 At any time prior to the deadline for submission of Bids, the Employer may
Bidding amend the Bidding Document by issuing addenda.
Document
8.2 Any addendum issued shall be part of the Bidding Document and shall be
communicated in writing to all who have obtained the Bidding Document
from the Employer in accordance with ITB 6.3.
C. Preparation of Bids
9. Cost of Bidding 9.1 The Bidder shall bear all costs associated with the preparation and
submission of its Bid, and the Employer shall in no case be responsible or
liable for those costs, regardless of the conduct or outcome of the bidding
process.
10. Language of Bid 10.1 The Bid, as well as all correspondence and documents relating to the bid
exchanged by the Bidder and the Employer, shall be written in the language
specified in the BDS. Supporting documents and printed literature that are
part of the Bid may be in another language provided they are accompanied
by an accurate translation of the relevant passages into the language
specified in the BDS, in which case, for purposes of interpretation of the
Bid, such translation shall govern.
11. Documents 11.1 The Bid submitted by the Bidder shall comprise the following:
Comprising the (a) Letter of Bid;
Bid (b) completed schedules as required, including Price Schedules, in
accordance with ITB 12 and ITB 18;
(c) Bid Security or Bid-Securing Declaration, in accordance with ITB 21;
(d) alternative Bids, if permissible, in accordance with ITB 13;
(e) written confirmation authorizing the signatory of the Bid to commit the
Bidder, in accordance with ITB 22.2;
(f) documentary evidence in accordance with ITB 14.1, that the plant and
services offered by the Bidder in its Bid or in any alternative bid, if
permitted, are eligible;
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
12
1-10 Section 1: Instructions to Bidders
11.2 In addition to the requirements under ITB 11.1, Bids submitted by a Joint
Venture shall include a copy of the Joint Venture Agreement entered into
by all partners. Alternatively, a Letter of Intent to execute a Joint Venture
Agreement in the event of a successful Bid shall be signed by all partners
and submitted with the Bid, together with a copy of the proposed
agreement.
12. Letter of Bid and 12.1 The Bidder shall complete the Letter of Bid, including the appropriate Price
Schedules Schedules, using the relevant forms furnished in Section 4 (Bidding
Forms). The forms must be completed as instructed in each form and as
required in the BDS.
13. Alternative Bids 13.1 The BDS indicates whether alternative Bids are allowed. If they are
allowed, the BDS will also indicate whether they are permitted in
accordance with ITB 13.3, or invited in accordance with ITB13.2 and/or ITB
13.4.
13.2 When alternatives to the Time Schedule are explicitly invited, a statement
to that effect will be included in the BDS, and the method of evaluating
different time schedules will be described in Section 3 (Evaluation and
Qualification Criteria).
13.3 Except as provided under ITB 13.4 below, Bidders wishing to offer technical
alternatives to the Employer’s requirements as described in the Bidding
Document must also provide (i) a price at which they are prepared to offer
a plant meeting the Employer’s requirements; and (ii) all information
necessary for a complete evaluation of the alternatives by the Employer,
including drawings, design calculations, technical specifications,
breakdown of prices, and proposed installation methodology and other
relevant details. Only the technical alternatives, if any, of the lowest
evaluated Bidder conforming to the basic technical requirements shall be
considered by the Employer.
13.4 When Bidders are invited in the BDS to submit alternative technical
solutions for specified parts of the facilities, such parts shall be described
in Section 6 (Employer’s Requirements). Technical alternatives for the
specific parts of the facilities that comply with the performance and
technical criteria specified for the plant and services shall be considered by
the Employer on their own merits, pursuant to ITB 36.
14. Documents 14.1 To establish the eligibility of the plant and services in accordance with ITB
Establishing the 5, Bidders shall complete the country of origin declarations in the Price
Eligibility of Schedule Forms, included in Section 4 (Bidding Forms).
Plant and
Services
15. Documents 15.1 To establish its eligibility and qualifications to perform the Contract in
Establishing the accordance with Section 3 (Evaluation and Qualification Criteria), the
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
13
Section 1: Instructions to Bidders 1-11
Eligibility and Bidder shall provide the information requested in the corresponding
Qualifications of information sheets included in Section 4 (Bidding Forms).
the Bidder
16. Documents 16.1 The documentary evidence of the conformity of the plant and services to
Establishing the Bidding Document may be in the form of literature, drawings, and data,
Conformity of and shall furnish:
the Plant and
(a) a detailed description of the essential technical and performance
Services
characteristics of the plant and services, including the functional
guarantees of the proposed plant and services, in response to the
specification;
(b) a list giving full particulars, including available sources, of all spare
parts and special tools necessary for the proper and continuing
functioning of the plant for the period named in the BDS, following
completion of plant and services in accordance with provisions of the
contract; and
(c) a commentary on the Employer’s Specifications and adequate
evidence demonstrating the substantial responsiveness of the plant
and services to those specifications. Bidders shall note that standards
for workmanship, materials, and equipment designated by the
Employer in the Bidding Document are intended to be descriptive
(establishing standards of quality and performance) only and not
restrictive. The Bidder may substitute alternative standards, brand
names, and/or catalog numbers in its Bid, provided that it demonstrates
to the Employer’s satisfaction that the substitutions are substantially
equivalent or superior to the standards designated in the
Specifications.
17. Technical 17.1 The Bidder shall furnish a Technical Proposal, including a statement of
Proposal, work methods, equipment, personnel, schedule, environmental, health and
Subcontractors safety (EHS) management plan commensurate with the proposed scope of
works, EHS Code of Conduct, and any other information as stipulated in
Section 4 (Bidding Forms), in sufficient detail to demonstrate the adequacy
of the Bidders’ proposal to meet the work requirements and the completion
time.
17.2 For major items of plant and services as listed by the Employer in Criterion
2.5 of Section 3 (Evaluation and Qualification Criteria), which the Bidder
intends to purchase or subcontract, the Bidder shall give details of the
name and nationality of the proposed Subcontractors, including
Manufacturers, for each of those items. In addition, the Bidder shall include
in its Bid information establishing compliance with the requirements
specified by the Employer for these items. Bidders are free to list more
than one Subcontractor against each item of the plant and services.
Quoted rates and prices will be deemed to apply to whichever
Subcontractor is appointed, and no adjustment of the rates and prices will
be permitted.
17.3 The Bidder shall be responsible for ensuring that any Subcontractor
proposed complies with the requirements of ITB 4, and that any plant, or
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
14
1-12 Section 1: Instructions to Bidders
18.4 In the Schedules, Bidders shall give the required details and a breakdown
of their prices as follows:
(i) the price of the plant shall be quoted carriage and insurance paid
(CIP)-named place of destination basis specified in the BDS;
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
15
Section 1: Instructions to Bidders 1-13
(ii) all customs duties and other taxes paid or payable in the
Employer’s country on the plant if the contract is awarded to the
Bidder; and
(iii) the total price for the plant
(b) Plant Supplied from Within the Employer’s Country (Schedule No. 2):
(i) the price of the plant shall be quoted on an EXW Incoterm basis
(ex works, ex factory, ex warehouse, ex showroom, as
applicable), including all customs duties and sales and other taxes
already paid or payable on the components and raw material used
in the manufacture or assembly of plant quoted ex works or ex
factory, or on the previously imported plant of foreign origin quoted
ex warehouse, ex showroom;
(ii) sales tax and other taxes payable in the Employer’s country on
the plant if the contract is awarded to the Bidder; and
(iii) the total price for the plant.
(c) Design Services. (Schedule No. 3). Rates or prices shall include all
taxes, duties, levies, and charges payable in the Employerʼs country
as of 28 days prior to the deadline for submission of Bids.
(d) Installation and Other Services (Schedule No. 4) shall be quoted
separately and shall include rates or prices for local transportation,
insurance, and other services incidental to delivery of the plant, all
labor, contractor’s equipment, temporary works, materials,
consumables, and all matters and things of whatsoever nature,
including operations and maintenance services, the provision of
operations and maintenance manuals, training, etc., where identified in
the Bidding Document, as necessary for the proper execution of the
installation and other services, including all taxes, duties, levies and
charges payable in the Employer’s country as of 28 days prior to the
deadline for submission of bids.
(e) Recommended spare parts (Schedule No. 6) shall be quoted
separately as specified in either subparagraph (a) or (b) above in
accordance with the origin of the spare parts.
18.6 The prices shall be either fixed or adjustable as specified in the BDS.
(a) In the case of Fixed Price, prices quoted by the Bidder shall be fixed
during the Bidder’s performance of the contract and not subject to
variation on any account. A Bid submitted with an adjustable price
quotation will be treated as nonresponsive and rejected.
(b) In the case of Adjustable Price, prices quoted by the Bidder shall be
subject to adjustment during performance of the contract to reflect
changes in the cost elements such as labor, material, transport and
contractor’s equipment in accordance with the procedures specified in
the corresponding appendix to the Contract Agreement. A Bid
submitted with a fixed price quotation will be treated as nonresponsive
and be rejected. The Bidder shall furnish the indexes (e.g. for labor and
materials), their weightings and source in the Tables of Adjustment
Data included in Section 4 (Bidding Forms). The Employer may require
the Bidder to justify its proposed indexes and weightings. Any bid that
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
16
1-14 Section 1: Instructions to Bidders
18.7 If so indicated in BDS 1.1, Bids are being invited for individual lots
(contracts) or for any combination of lots (packages). Bidders wishing to
offer any price reduction (discount) for the award of more than one contract
shall specify in their Letter of Bid the price reductions applicable to each
package, or alternatively, to individual contracts within the package, and
the manner in which the price reductions will apply.
19. Currencies of 19.1 The currency(ies) of the bid shall be, as specified in the BDS.
Bid and
Payment 19.2 Bidders may be required by the Employer to justify, to the Employerʼs
satisfaction, their local and foreign currency requirements.
20. Period of 20.1 Bids shall remain valid for the bid validity period specified in the BDS. The
Validity of Bids bid validity period starts from the date fixed for the bid submission deadline
date prescribed by the Employer in accordance with ITB 24.1. A bid valid
for a shorter period shall be rejected by the Employer as nonresponsive.
20.2 In exceptional circumstances, prior to the expiration of the bid validity period,
the Employer may request Bidders to extend the period of validity of their Bids.
The request and the responses shall be made in writing. If a bid security is
requested in accordance with ITB 21, it shall also be extended 28 days
beyond the deadline of the extended bid validity period. A Bidder may refuse
the request without forfeiting its bid security. A Bidder granting the request shall
not be required or permitted to modify its Bid.
21. Bid Security/Bid 21.1 Unless otherwise specified in the BDS, the Bidder shall furnish as part of its
Securing Bid, in original form, either a Bid-Securing Declaration or a bid security as
Declaration specified in the BDS. In the case of a bid security, the amount and currency
shall be as specified in the BDS.
21.2 If a Bid-Securing Declaration is required pursuant to ITB 21.1, it shall use
the form included in Section 4 (Bidding Forms). The Employer will declare
a Bidder ineligible to be awarded a Contract for a specified period of time,
as indicated in the BDS, if a Bid-Securing Declaration is executed.
21.3 If a bid security is specified pursuant to ITB 21.1, bid security shall be, at
the Bidder’s option, in any of the following forms:
(a) an unconditional bank guarantee (hard copy of the bank guarantee or
in the form of SWIFT message MT760), or
(b) an irrevocable letter of credit, or
(c) a cashier’s or certified check,
all from a reputable source from an eligible country as described in Section
5 (Eligible Countries). In the case of a bank guarantee, the bid security shall
be submitted using either the Bid Security Form included in Section 4
(Bidding Forms) or another form acceptable to the Employer. The form
must include the complete name of the Bidder. The bid security shall be
valid for 28 days beyond the original validity period of the Bid, or beyond
any period of extension if requested under ITB 20.2.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
17
Section 1: Instructions to Bidders 1-15
21.4 Unless otherwise specified in the BDS, any Bid not accompanied by a
substantially compliant bid security or Bid-Securing Declaration, if one is
required in accordance with ITB 21.1, shall be rejected by the Employer as
non-responsive.
21.5 If a bid security is specified pursuant to ITB 21.1, the bid security of
unsuccessful Bidders shall be returned promptly upon the successful
Bidder’s furnishing of the performance security pursuant to ITB 44.
21.6 If, a bid security is specified pursuant to ITB 21.1, the bid security of the
successful Bidder shall be returned promptly once the successful Bidder
has signed the Contract and furnished the required performance security.
21.7 The bid security may be forfeited or the Bid-Securing Declaration executed,
if
(a) notwithstanding ITB 26.3, a Bidder withdraws its Bid during the period
of bid validity specified by the Bidder on the Letter of Bid, except as
provided in ITB 20.2, or
(b) the successful Bidder fails to
(i) sign the Contract in accordance with ITB 43, or
(ii) furnish a performance security in accordance with ITB 44, or
(iii) accept the arithmetical corrections of its Bid in accordance with
ITB 33.
21.8 If the bid security is required as per ITB 21.1, the bid security of a Joint
Venture shall be in the name of the Joint Venture that submits the Bid. If
the Joint Venture has not been legally constituted at the time of bidding,
the bid security shall be in the name of any or all of the Joint Venture
partners. If the Bid-Securing Declaration is required as per ITB 21.1, the
Bid-Securing Declaration of a Joint Venture shall be in the name of the
Joint Venture that submits the Bid. If the Joint Venture has not been legally
constituted at the time of bidding, the Bid-Securing Declaration shall be in
the names of all future partners as named in the letter of intent referred to
in ITB 4.1.
22. Format and 22.1 The Bidder shall prepare one original set of the documents comprising the
Signing of Bid Bid as described in ITB 11 and clearly mark it “ORIGINAL.” Alternative
Bids, if permitted in accordance with ITB 13, shall be clearly marked
“ALTERNATIVE”. In addition, the Bidder shall submit copies of the Bid, in
the number specified in the BDS and clearly mark them “COPY.” In the
event of any discrepancy between the original and the copies, the original
shall prevail.
22.2 The original and all copies of the Bid shall be typed or written in indelible ink
and shall be signed by a person duly authorized to sign on behalf of the Bidder.
This authorization shall consist of a written confirmation as specified in the BDS
and shall be attached to the Bid. The name and position held by each person
signing the authorization must be typed or printed below the signature. If a
Bidder submits a deficient authorization, the Bid shall not be rejected in the
first instance. The Employer shall request the Bidder to submit an
acceptable authorization within the number of days as specified in the BDS.
Failure to provide an acceptable authorization within the period stated in
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
18
1-16 Section 1: Instructions to Bidders
the Employer’s request shall cause the rejection of the Bid. If either the
Letter of Bid or the Bid-Securing Declaration (if applicable) is not signed,
the Bid shall be rejected.
23. Submission, 23.1 Bidders shall submit their Bids as specified in the BDS. Procedures for
Sealing and submission, sealing, and marking are as follows:
Marking of Bids
(a) Bidders submitting Bids by mail or by hand shall enclose the original
and each copy of the Bid, including alternative Bids, if permitted in
accordance with ITB 13, in separate sealed envelopes, duly marking
the envelopes as “ORIGINAL”, “ALTERNATIVE,” and “COPY.” These
envelopes containing the original and the copies shall then be enclosed
in one single envelope. The rest of the procedure shall be in
accordance with ITB 23.2 and ITB 23.3.
(b) Bidders submitting Bids electronically shall follow the electronic bid
submission procedures specified in the BDS.
23.3 If all envelopes are not sealed and marked as required, the Employer will
assume no responsibility for the misplacement or premature opening of the
Bid.
24. Deadline for 24.1 Bids must be received by the Employer at the address and no later than the
Submission of date and time indicated in the BDS.
Bids
24.2 The Employer may, at its discretion, extend the deadline for the submission of
bids by amending the Bidding Document in accordance with ITB 8, in which
case all rights and obligations of the Employer and Bidders previously subject
to the deadline shall thereafter be subject to the deadline as extended.
25. Late Bids 25.1 The Employer shall not consider any Bid that arrives after the deadline for
submission of Bids, in accordance with ITB 24. Any Bid received by the
Employer after the deadline for submission of Bids shall be declared late,
rejected, and returned unopened to the Bidder.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
19
Section 1: Instructions to Bidders 1-17
26. Withdrawal, 26.1 A Bidder may withdraw, substitute, or modify its Bid after it has been submitted
Substitution, by sending a written notice, duly signed by an authorized representative, and
and Modification shall include a copy of the authorization in accordance with ITB 22.2 (except
of Bids for withdrawal notices, which do not require copies). The corresponding
substitution or modification of the Bid must accompany the respective written
notice. All notices must be:
(a) prepared and submitted in accordance with ITB 22 and ITB 23 (except
for withdrawal notices, which do not require copies), and in addition,
the respective envelopes shall be clearly marked “WITHDRAWAL,”
“SUBSTITUTION,” “MODIFICATION;” and
(b) received by the Employer prior to the deadline prescribed for
submission of Bids, in accordance with ITB 24.
26.2 Bids requested to be withdrawn in accordance with ITB 26.1 shall be returned
unopened to the Bidders.
26.3 No Bid may be withdrawn, substituted, or modified in the interval between the
deadline for submission of Bids and the expiration of the period of bid validity
specified by the Bidder on the Letter of Bid or any extension thereof.
27. Bid Opening 27.1 The Employer shall open the Bids in public at the address, on the date, and
time specified in the BDS in the presence of Bidders` designated
representatives and anyone who choose to attend. Any specific electronic
bid opening procedures required if electronic bidding is permitted in
accordance with ITB 23.1, shall be as specified in the BDS.
27.2 First, envelopes marked “WITHDRAWAL” shall be opened and read out and
the envelope with the corresponding Bid shall not be opened, but returned to
the Bidder. No bid withdrawal shall be permitted unless the corresponding
withdrawal notice contains a valid authorization to request the withdrawal and
is read out at bid opening. Next, envelopes marked “SUBSTITUTION” shall
be opened and read out and exchanged with the corresponding Bid being
substituted. The substituted Bid shall not be opened, but returned to the
Bidder. No bid substitution shall be permitted unless the corresponding
substitution notice contains a valid authorization to request the substitution and
is read out at bid opening. Envelopes marked “MODIFICATION” shall be
opened and read out with the corresponding Bid. No bid modification shall be
permitted unless the corresponding modification notice contains a valid
authorization to request the modification and is read out at bid opening. Only
envelopes that are opened and read out at bid opening shall be considered
further.
27.3 All other envelopes shall be opened one at a time, reading out the name of the
Bidder and whether there is a modification; the Bid Price(s), including any
discounts and alternative Bids; the presence of a bid security, or a Bid-
Securing Declaration, if required; and any other details as the Employer may
consider appropriate. Only discounts and alternative Bids read out at bid
opening shall be considered for evaluation. Unless otherwise specified in the
BDS, all pages of the Letter of Bid and Price Schedules are to be initialed by
at least three representatives of the Employer attending the bid opening. No
Bid shall be rejected at bid opening except for late Bids, in accordance with
ITB 25.1.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
20
1-18 Section 1: Instructions to Bidders
27.4 The Employer shall prepare a record of the bid opening that shall include, as
a minimum: the name of the Bidder and whether there is a withdrawal,
substitution, or modification; the Bid Price, per lot if applicable, including any
discounts and alternative Bids; and the presence or absence of a bid security
or a Bid-Securing Declaration, if one was required. The Bidders’
representatives who are present shall be requested to sign the record. The
omission of a Bidder’s signature on the record shall not invalidate the contents
and effect of the record. A copy of the record shall be distributed to all Bidders
who submitted Bids on time, and posted online when electronic bidding is
permitted.
28. Confidentiality 28.1 Information relating to the evaluation of Bids and recommendation of contract
award shall not be disclosed to Bidders or any other persons not officially
concerned with such process until the publication of Contract award.
28.2 Any attempt by a Bidder to influence the Employer in the evaluation of the Bids
or Contract award decisions may result in the rejection of its Bid.
28.3 Notwithstanding ITB 28.2, from the time of bid opening to the time of Contract
award, if any Bidder wishes to contact the Employer on any matter related to
the bidding process, it should do so in writing.
29. Clarification of 29.1 To assist in the examination, evaluation, and comparison of the Bids, and
Bids qualification of the Bidders, the Employer may, at its discretion, ask any Bidder
for a clarification of its Bid. Any clarification submitted by a Bidder that is not
in response to a request by the Employer shall not be considered. The
Employer’s request for clarification and the response shall be in writing. No
change in the prices or substance of the Bid shall be sought, offered, or
permitted, except to confirm the correction of arithmetic errors discovered by
the Employer in the evaluation of the Bids, in accordance with ITB 33.
29.2 If a Bidder does not provide clarifications of its Bid by the date and time set in
the Employer’s request for clarification, its Bid may be rejected.
30. Deviations, 30.1 During the evaluation of Bids, the following definitions apply:
Reservations,
and Omissions (a) “Deviation” is a departure from the requirements specified in the
Bidding Document;
(b) “Reservation” is the setting of limiting conditions or withholding from
complete acceptance of the requirements specified in the Bidding
Document; and
(c) “Omission” is the failure to submit part or all of the information or
documentation required in the Bidding Document.
31. Determination of 31.1 The Employer’s determination of a bid’s responsiveness is to be based on the
Responsiveness contents of the Bid itself, as defined in ITB11.
31.2 A substantially responsive Bid is one that meets the requirements of the
Bidding Document without material deviation, reservation, or omission. A
material deviation, reservation, or omission is one that,
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
21
Section 1: Instructions to Bidders 1-19
31.3 The Employer shall examine the technical aspects of the Bid submitted in
accordance with ITB 17, Technical Proposal, in particular, to confirm that all
requirements of Section 6 (Employer’s Requirements) have been met without
any material deviation, reservation, or omission.
32. Nonmaterial 32.1 Provided that a Bid is substantially responsive, the Employer may waive any
Nonconformities nonconformities in the Bid that do not constitute a material deviation,
reservation, or omission.
32.2 Provided that a Bid is substantially responsive, the Employer may request that
the Bidder submit the necessary information or documentation, within a
reasonable period of time, to rectify nonmaterial nonconformities in the Bid
related to documentation requirements. Requesting information or
documentation on such nonconformities shall not be related to any aspect of
the price of the Bid. Failure of the Bidder to comply with the request may result
in the rejection of its Bid.
32.3 Provided that a bid is substantially responsive, the Employer shall rectify
quantifiable nonmaterial nonconformities related to the Bid Price. To this effect,
the Bid Price shall be adjusted, for comparison purposes only, to reflect the
price of a missing or nonconforming item or component. The adjustment shall
be made using the method indicated in Section 3 (Evaluation and Qualification
Criteria).
33. Correction of 33.1 Provided that the Bid is substantially responsive, the Employer shall correct
Arithmetical arithmetical errors on the following basis:
Errors
(a) where there are errors between the total of the amounts given under
the column for the price breakdown and the amount given under the
Total Price, the amounts given under the column for the price
breakdown shall prevail and the Total Price will be corrected
accordingly;
(b) where there are errors between the total of the amounts of Schedule
Nos. 1 to 4 and the amount given in Schedule No. 5 (Grand Summary),
the total of the amounts of Schedule Nos. 1 to 4 shall prevail and the
Schedule No. 5 (Grand Summary) will be corrected accordingly;
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
22
1-20 Section 1: Instructions to Bidders
33.2 If the Bidder that submitted the lowest evaluated Bid does not accept the
correction of errors, its Bid shall be disqualified and its bid security may be
forfeited, or its Bid-Securing Declaration executed.
34. Conversion to 34.1 For evaluation and comparison purposes, the currency(ies) of the Bid shall be
Single Currency converted into a single currency as specified in the BDS.
35. Domestic
35.1 Unless otherwise specified in the BDS, domestic preference shall not apply.
Preference
36. Evaluation and 36.1 The Employer shall use the criteria and methodologies indicated in this clause.
Comparison of No other evaluation criteria or methodologies shall be permitted.
Bids
36.3 Where alternative technical solutions have been allowed in accordance with
ITB 13, and offered by the Bidder, the Employer will make a similar evaluation
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
23
Section 1: Instructions to Bidders 1-21
of the alternatives. Where alternatives have not been allowed but have been
offered, they shall be ignored.
(b) in the case of Plant and Mandatory Spare Parts (Schedule No. 2)
supplied from within the Employer’s country, sales and other taxes,
applicable in the Employer’s country and payable on the Plant and
Mandatory Spare Parts if the Contract is awarded to the Bidder.
36.5 If price adjustment is allowed in accordance with ITB 18.6, the estimated effect
of the price adjustment provisions of the Conditions of Contract, applied over
the period of execution of the Contract, shall not be taken into account in bid
evaluation.
36.6 If this Bidding Document allows Bidders to quote separate prices for different
lots (contracts), and the award to a single Bidder of multiple lots (contracts),
the methodology to determine the lowest evaluated price of the lot (contract)
combinations, including any discounts offered in the Letter of Bid, is specified
in Section 3 (Evaluation and Qualification Criteria).
36.7 If the Bid, which results in the lowest Evaluated Bid Price, is seriously
unbalanced or front loaded in the opinion of the Employer, the Employer may
require the Bidder to produce detailed price analyses for any or all items of the
Price Schedules, to demonstrate the internal consistency of those prices with
the methods and time schedule proposed. After evaluation of the price
analyses, taking into consideration the terms of payments, the Employer may
require that the amount of the performance security be increased at the
expense of the Bidder to a level sufficient to protect the Employer against
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
24
1-22 Section 1: Instructions to Bidders
financial loss in the event of default of the successful Bidder under the
Contract.
36.8 The Employer shall compare all substantially responsive Bids to determine the
lowest evaluated Bid, in accordance with ITB 36.4.
37. Abnormally Low 37.1 An abnormally low bid is one where the bid price, in combination with other
Bids elements of the bid, appears to be so low that it raises concerns as to the
capability of the Bidder to perform the contract for the offered bid price.
37.2 When the offered bid price appears to be abnormally low, the Employer shall
undertake a three-step review process as follows:
(a) identify abnormally low costs and unit rates by comparing them with the
engineer’s estimates, other substantially responsive bids, or recently
awarded similar contracts;
(b) clarify and analyze the bidder’s resource inputs and pricing, including
overheads, contingencies and profit margins; and
37.3 With regard to ITB 37.2 (b) above, the Employer will seek a written explanation
from the bidder of the reasons for the offered bid price, including a detailed
analysis of costs and unit prices, by reference to the scope, proposed
methodology, schedule, and allocation of risks and responsibilities. This may
also include information regarding the economy of the manufacturing process;
the services to be provided, or the construction method to be used; the technical
solutions to be adopted; and any exceptionally favorable conditions available to
the bidder for the works, equipment or services proposed.
37.4 After examining the explanation given and the detailed price analyses presented
by the bidder, the Employer may:
(a) accept the bid, if the evidence provided satisfactorily accounts for the
low bid price and costs, in which case the bid is not considered
abnormally low;
(b) accept the bid, but require that the amount of the performance security
be increased at the expense of the bidder to a level sufficient to protect
the Employer against financial loss. The amount of the performance
security shall generally be not more than 20% of the contract price; or
(c) reject the bid if the evidence provided does not satisfactorily account for
the low bid price, and make a similar determination for the next ranked
bid, if required.
38. Eligibility and 38.1 The Employer shall determine to its satisfaction whether the Bidder that is
Qualification of selected as having submitted the lowest evaluated and substantially
the Bidder responsive Bid is eligible and meets the qualifying criteria specified in Section
3 (Evaluation and Qualification Criteria).
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
25
Section 1: Instructions to Bidders 1-23
39. Employer’s 39.1 The Employer reserves the right to accept or reject any Bid, and to annul the
Right to Accept bidding process and reject all Bids at any time prior to contract award, without
Any Bid, and to thereby incurring any liability to Bidders. In case of annulment, all Bids
Reject Any or All submitted and specifically, bid securities, shall be promptly returned to the
Bids Bidders.
40. Notice of 40.1 If Standstill provisions apply as specified in the BDS, the standstill period
Intention for shall be defined in the BDS to specify the duration subsequent to
Award of notification of intention for award of contract (before making the actual
Contract contract award) within which any unsuccessful bidder can challenge the
proposed award.
F. Award of Contract
41. Award Criteria 41.1 The Employer shall award the Contract to the Bidder whose offer has been
determined successful in line with ITB 36 and ITB 37 above to be the lowest
evaluated Bid and is substantially responsive to the Bidding Document,
provided further that the Bidder is determined to be eligible and qualified to
perform the Contract satisfactorily.
42. Notification of 42.1 Prior to the expiration of the period of bid validity and upon expiry of the
Award standstill period specified in ITB 41.1, or upon satisfactory resolution of a
complaint filed within standstill period, if applicable, the Employer shall
transmit the Notification of Award through issuance of Letter of Acceptance
using the form included in Section 9 (Contract Forms) to the successful
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
26
1-24 Section 1: Instructions to Bidders
Bidder, in writing, that its Bid has been accepted. At the same time, the
Employer shall also notify all other Bidders of the results of the bidding.
43. Signing of 43.1 Promptly after notification, the Employer shall send the successful Bidder the
Contract Contract Agreement.
43.2 Within 28 days of receipt of the Contract Agreement, the successful Bidder
shall sign, date, and return it to the Employer.
44. Performance 44.1 Within 28 days of the receipt of notification of award through issuance of Letter
Security of Acceptance from the Employer, the successful Bidder shall furnish the
performance security in accordance with the Conditions of Contract, subject to
ITB 36.7 and ITB 37, using for that purpose the Performance Security Form
included in Section 9 (Contract Forms), or another form acceptable to the
Employer. If the bank issuing performance security is located outside the
Employer’s country, it shall be counter-guaranteed or encashable by a bank in
the Employer’s country.
44.2 Failure of the successful Bidder to submit the abovementioned
performance security or sign the Contract shall constitute sufficient
grounds for the annulment of the award and forfeiture of the bid security or
execution of the Bid-Securing Declaration. In that event, the Employer may
award the Contract to the next lowest evaluated Bidder whose offer is
substantially responsive and is determined by the Employer to be qualified
to perform the Contract satisfactorily.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
27
Section 1: Instructions to Bidders 1-25
45. Bidding-Related 45.1 The procedures for dealing with Bidding-Related Complaints arising out of this
Complaints bidding process are specified in the BDS.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
28
Section 2: Bid Data Sheet 2-1
A. General
ITB 1.1 The number of the Invitation for Bids (IFB) is: CESL/06/2023-24/OCB-Solar
Carports/232408003
The name of the open competitive bidding (OCB) is: Design, Engineering,
Supply, Civil work, Erection of suitable raised structure, Installation, Testing
& Commissioning of the 25/50 kWp Bi-facial Vertical Solar PV along with
Battery Energy Storage System of 100/200 kWh with EV Chargers project
including Operation and Comprehensive Maintenance (O&M).
The number and identification of lots (contracts) comprising this OCB is: Two Lots
The name of the Project is: Scaling up Demand – Side Energy Efficiency Sector
Project
ITB 7.1 For the purpose of obtaining contractual clarification, the Employer’s address is:
For the purpose of obtaining technical clarification, the Employer’s address is:
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
29
2-2 Section 2: Bid Data Sheet
Telephone:+9111-42259600
Email-Id: [email protected]
ITB 7.4 A Pre-Bid meeting will take place as per date, time and place are as follows:
Date: 25.09.2023
Time: 11:00 Hours IST
Place: Convergence Energy Services Limited
NFL Building, 2nd Floor,
Core – III SCOPE Complex,
Lodhi Road, New Delhi-110003
Telephone: +011-42259600;
e-mail: [email protected],
Note: The pre-bid meeting shall be conducted online, for which requisite link shall
be provided one day prior to the meeting. However, those Bidders who wish to
attend physically, may do so by reaching the aforementioned address at stipulated
date and time. A site visit conducted by the Employer will not be organized.
C. Preparation of Bids
ITB 11.1 (k) The Bidder shall submit with its bid the following additional documents:
(i) Demand Draft (DD) towards Bidding Document fee of the amount. Specified in
the BDS
ii)Bid Security (in Original) in accordance with clause 21 of BDS, Section-2 (the
format is attached as Attachment-2, Section-4: Bidding Forms),
ITB 12.1 The units and rates in figures entered into the Price Schedules should be
typewritten or if written by hand, must be in print form. Price Schedules not
presented accordingly may be considered non-responsive.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
30
Section 2: Bid Data Sheet 2-3
ITB 13.4 Alternative technical solutions are not permitted for the following parts of the plant
and services:
ITB 16.1 (b) The period following completion of plant and services in accordance with provisions
of the contract shall be 540 days
ITB 18.1
Bidders shall quote for the entire plant and services on a single responsibility basis.
ITB 18.4(a)(i) The Incoterm for quoting plant to be supplied from abroad is: INCO Terms 2020
Edition
ITB 18.6 The prices quoted by the Bidder shall be fixed and not subject to adjustment
(c) If some of the contract expenditures related to Design, Installation and Other
Services are to be incurred in the Employerʼs country, such expenditures shall
be quoted in either foreign and/or local currency, depending upon the
currency in which the costs are to be incurred.
(d) Bidders may be required by the Employer to clarify their local and foreign
currency requirements, and to substantiate that the amounts included in the
Price Schedules are reasonable and responsive to ITB 18.1 in which case a
detailed breakdown of its foreign currency requirements shall be provided by
the Bidder.
(e) During the performance of the contract, the foreign currency portions of the
outstanding balance of the Contract Price may be adjusted by agreement
between the Employer and the Contractor to reflect any changes in foreign
currency requirements for the contract. Any such adjustment shall be effected
by comparing the amounts quoted in the bid with the amounts already used
in the Facilities and the Contractor’s future needs for imported items.
ITB 21.1 The Bidder shall furnish a bid security in the amount indicated below:
Lot 1: INR 500,000 or USD 6300
Lot 2: INR 500,000 or USD 6300
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
31
2-4 Section 2: Bid Data Sheet
If bidder opts bid of both the lots (1&2), the EMD requirement for the bidder
would be the cumulative EMD requirement for both the lots.
ITB 21.4 Subject to the succeeding sentences, any bid not accompanied by an irrevocable
and callable bid security shall be rejected by the Employer as nonresponsive. If a
Bidder submits a bid security that (i) deviates in form, amount, and/or period of
validity, or (ii) does not provide sufficient identification of the Bidder (including,
without limitation, failure to indicate the name of the Joint Venture or, where the
Joint Venture has not yet been constituted, the names of all future Joint Venture
Partners), the Employer shall request the Bidder to submit a compliant bid security
within 7 days of receiving such a request. Failure to provide a compliant bid security
within the prescribed period of receiving such a request shall cause the rejection of
the Bid.
The bid shall be signed digitally by a person duly authorized to sign on behalf of
the Bidder. This authorization shall consist of a written power of attorney
accompanying the bid and shall be uploaded along with the bid. The name and
position held by each person signing the authorization must be typed or printed
below the signature
If a bidder submits a deficient authorization, the Bid shall not be rejected in the first
instance. The Purchaser shall request the Bidder to submit an acceptable
authorization within 7 days. Failure to provide an acceptable authorization within
the period stated in the Employer’s request shall cause the rejection of the Bid. If
either the Bid Submission Sheet or the Bid-Securing Declaration (if applicable) is
not signed, the Bid shall be rejected.
ITB 22.2 The Bidder shall submit an acceptable authorization within 7 days.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
32
Section 2: Bid Data Sheet 2-5
a) The Bidder shall digitally sign and submit its bid online in the e-Tendering
platform well in advance before the prescribed time. The Employer shall not accept
bids submitted in manual form.
b) The Bidder shall take due precaution to upload bid documents including the price
bid document onto the envelopes defined in the e-Tendering platform.
e) Online bids will have to be digitally signed and submitted in a Time stamped
electronic sealed tender folder on https://cesl.eproc.in
f) Bidders shall take due care to ensure that the documents uploaded by them in
the e-Procurement platform are virus free. Employer shall not be liable for such
rejections.
g)The downloaded Bid forms shall be typed or written in indelible ink and shall be
signed by a person duly authorized to sign on behalf of Bidder.
h)Bidder is required to download the bidding forms, print the forms, fill them, scan
them and upload in the portal. The information on eligibility and qualification
provided in the bidding forms only will be considered. Bidder will also provide
reference of supporting documents provided in its support in the bidding forms.
i) Employer shall not accept any responsibility for failures or breakdowns for
systems other than in those systems strictly within the control of the Employer and
its e-Tendering service provider.
j)The onus is on the Bidder to ensure availability of the requisite infrastructure and
systems required for online bid submission viz. Digital Signature Certificates and
as applicable Digital Encryption Certificates required for bid submission in the e-
Tendering platform, reliable internet connectivity and requisite client software.
l) Bidder is solely responsible for safe keeping of its Digital Signature Certificate
(DSC) and as applicable Digital Encryption Certificate (DEC).
m)The Employer reserves the right to verify original copies of scanned documents
uploaded by bidders. The employer may seek additional documentary evidence on
their technical proposals, which the bidder shall provide either online via the e-
Tendering platform or in manual form.
n)Bidders shall upload their bid documents in formats, which can be opened and
read by open standard interfaces
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
33
2-6 Section 2: Bid Data Sheet
o) Bidders shall not lock electronic files uploaded in their proposal with passwords
of their choice. The Employer reserves the right to reject password locked files
outright and not consider contents within such locked files for bid evaluation
Bid submission and bid opening timelines will be defined as per line e-Tendering
system server clock only.
The original bid security and tender document / tender processing fee is to be
submitted so as to reach the address at ITB 7.1 above by 14:30 hrs on
19.10.2023 i.e. 30 minutes before the bid opening time given below:
The deadline for bid submission is
Date: 19.10.2023
Time: 14:30 Hrs. (IST)
Bid Opening Time is
Date: 19.10.2023
Time: 15:00 Hrs. (IST)
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
34
Section 2: Bid Data Sheet 2-7
Date: 19.10.2023
*Time: 15:00 hrs. (IST)
* bid opening timelines will be defined as per the e-Procurement server clock
only
The technical bids recorded and opened at the time of opening shall be
considered for evaluation.
The Price Bids will remain unopened in the e-procurement website and will
remain encrypted, until the specified time of its opening.
27.2 The withdrawn bid will not be available in the system. Only the last modified
bid shall be available in the system which shall be opened along with other
bids. Only bids that are opened at bid opening shall be considered further.
27.3 All other Bids, the bidders’ names and any such other details as the
Employer may consider appropriate, will be available through the portal as
per electronic form filled in by the bidder, and will become viewable at the
time of opening of bids. The Employer shall neither discuss the merits of any
bid nor reject any bid (except for late bids, in accordance with ITB 25.1).
27.4 The Employer shall prepare a record of the bid opening that shall include, as
a minimum: the name of the Bidder and whether there is a withdrawal,
substitution, or modification; the Bid Price, per lot if applicable, including any
discounts and alternative Bids; and the presence or absence of a bid security
or a Bid-Securing Declaration, if one was required. The Bidders’
representatives who are present shall be requested to sign the record. The
omission of a Bidder’s signature on the record shall not invalidate the
contents and effect of the record. A copy of the record shall be distributed
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
35
2-8 Section 2: Bid Data Sheet
to all Bidders who submitted Bids on time, and posted online when electronic
bidding is permitted.
The Employer will notify Bidders in writing who have been rejected on the
grounds of their Technical Bids being substantially non-responsive to the
requirements of the Bidding Document.
ITB 34.1 The currency that shall be used for bid evaluation and comparison purposes to
convert all bid prices expressed in various currencies into a single currency is: INR
The source of the selling exchange rate shall be: Reference rates as published by
Financial Benchmarks India Pvt. Ltd. (FBIL).
The date for the selling exchange rate shall be: Date of Bid Opening
ITB 38.2 The qualifications of other firms such as the Bidder’s subsidiaries, parent entities,
or affiliates, shall not be permitted.
F. Award of Contract
ITB 45.1 The procedures for Bidding-Related Complaints are referenced in Appendix 7 of
the Procurement Regulations for ADB Borrowers. The Bidder should submit its
complaint following these procedures, in writing, to:
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
36
Section 2: Bid Data Sheet 2-9
46.1 Bidders shall upload their bid documents in formats, which can be opened and
read by open standard interfaces.
46.2 Bidders shall not lock electronic files uploaded in their proposal with
passwords of their choice. The Employer reserves the right to reject password
locked files outright and not consider contents within such locked files for bid
evaluation.
46.3 In case a bidder wishes to ascertain the grounds on which its bid was declared
non-responsive, he may do so by submitting his request to the Employer. Such a
case shall be addressed as per Procurement Guidelines of ADB.
46.4 The Employer reserves the right to extend bid submission timeline if e-
Tendering server is inaccessible or inoperative for a prolonged period of time within
the last 24 hours of the bid submission due date. The Employer shall consult the e-
Tendering service provider and seek its opinion and decide to extend the bid
submission timeline in accordance with the technical explanation provided by the
e-Tendering service provider.
46.5 The Employer reserves the right to verify original copies of scanned
documents uploaded by bidders.
46.6 The Bidder shall take due care to ensure that the documents uploaded by it in
the e-Procurement system are virus free. If the documents uploaded by the Bidder
could not be opened, due to virus during tender opening, the bid is liable to be
rejected.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
37
Section 3: Evaluation and Qualification Criteria 3-1
Table of Criteria
1. Evaluation ...............................................................................................................3-2
1.1 Technical Evaluation.....................................................................................................3-2
1.2 Alternative Technical Solutions ...................................................................................3-2
1.3 Economic Evaluation ....................................................................................................3-2
1.4 Multiple Contracts .........................................................................................................3-5
2. Qualification ...........................................................................................................3-6
2.6 Subcontractors............................................................................................................3-18
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
38
3-2 Section 3: Evaluation and Qualification Criteria
1. Evaluation
Evaluation of the Bidder’s Technical Proposal will include an assessment of the Bidder’s technical
capacity to successfully implement the contract considering its proposed site organization, method
statement, mobilization, and construction schedule (to be described by the Bidder in sufficient
detail to demonstrate the adequacy of its work methods, scheduling, and material sourcing)
including the extent to which they are presented in a consistent manner and comply with
requirements stipulated in Section 6 (Employer’s Requirements) without material deviation,
reservation, or omission.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
39
Section 3: Evaluation and Qualification Criteria 3-3
Any bid not accompanied by the EHSMP may be rejected by the Employer as
nonresponsive. If a Bidder submits a EHSMP that is not commensurate with the risks and
impacts of the proposed works and activities in the bidding document, the Employer shall
issue a request for clarification to request for further information from the Bidder. The
Bidder must submit the requested information within 10 days of receiving such a request.
Failure to provide a satisfactory response to the request for further information within the
prescribed period of receiving such a request may cause the rejection of the Bid.
(a) The preference margin shall not be applied to the whole facility but only to the eligible
domestically produced Plant and Equipment within the contract.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
40
3-4 Section 3: Evaluation and Qualification Criteria
(b) Plant and Mandatory Spare Parts supplied from abroad shall be quoted CIP (Section 4
[Bidding Forms], Schedule No. 1). Plant and Mandatory Spare Parts supplied from within
the Employer’s country shall be quoted EXW (ex works, ex factory, ex warehouse, ex
showroom, or off-the-shelf, as applicable) free of sales and similar taxes (Section 4
[Bidding Forms], Schedule No. 2).
(c) All other cost components for services and works such as costs for design, local
handling, transportation, storage, installation, and commissioning shall be quoted
separately. See Section 4 (Bidding Forms), Schedule No. 3 - Design Services and
Schedule No. 4 - Installation and Other Services.
(d) In the comparison of Bids, only the CIP price component of each Bid for the Plant and
Equipment offered from outside the Employerʼs country shall be increased by 15 %
(e) No domestic preference shall be applied to any of the services or works included in the
contract.
(f) Bidders shall not be permitted or required to modify the mix of local and foreign Plant
and Equipment after bid opening.
If a Bidder as defined in ITB 4.1 submits several successful (lowest evaluated substantially
responsive) bids, the evaluation will also include an assessment of the Bidder’s capacity to
meet the following aggregated requirements as presented in the bid:
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
41
Section 3: Evaluation and Qualification Criteria 3-5
2. Qualification
2.1 Eligibility
2.1.1 Nationality
Nationality in accordance with Must meet Must meet Must meet Not Forms
requirement requirement requirement applicable
ITB 4.2. ELI - 1; ELI - 2
with attachments
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
42
3-6 Section 3: Evaluation and Qualification Criteria
Non-performance of a contracta Must meet Must meet Must meet Not Form CON-1
did not occur as a result of requirement requirement requirementb applicable
contractor default since 1
January 2018
a
Nonperformance, as decided by the Employer, shall include all contracts where (a) nonperformance was not challenged by the
contractor, including through referral to the dispute resolution mechanism under the respective contract, and (b) contracts that
were so challenged but fully settled against the contractor. Nonperformance shall not include contracts where Employers decision
was overruled by the dispute resolution mechanism. Nonperformance must be based on all information on fully settled disputes
or litigation, i.e. dispute or litigation that has been resolved in accordance with the dispute resolution mechanism under the
respective contract and where all appeal instances available to the Bidder have been exhausted.
b
This requirement also applies to contracts executed by the Bidder as Joint Venture partner.
Not under suspension based on Must meet Must meet Must meet Not Letter of Bid
execution of a Bid Securing requirement requirement requirement applicable
Declaration pursuant to ITB 4.6.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
43
Section 3: Evaluation and Qualification Criteria 3-7
Joint Venture
Declare any contracts that have Must make the Not Each partner Not Form CON-2
declaration. If the applicable must make applicable
been suspended or terminated bidder proposes the
and/or performance security Specialist Sub- declaration. If
called by an employer for contractor/s to the bidder
reasons related to the non- meet EQC 2.4.2, proposes
those Specialist Specialist
compliance of any
Sub-contractor/s Sub-
environmental, health and must also make contractor/s to
safety contractual obligations in the declaration meet EQC
the past five years. 2.4.2, those
Specialist
Sub-
contractor/s
must also
make the
declaration.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
44
3-8 Section 3: Evaluation and Qualification Criteria
Submission of audited financial Must meet Not Must meet Not Form FIN - 1 with
requirement applicable requirement applicable attachments
statements or, if not required by
the law of the Bidder’s country,
other financial statements
acceptable to the Employer, for
the last 3 years to demonstrate
the current soundness of the
Bidder’s financial position. As a
minimum, the Bidder’s net worth
for the last year calculated as the
difference between total assets
and total liabilities should be
positive.
Minimum average annual Must meet Must meet Must meet Must meet Form FIN - 2
requirement requirement
turnover (MAAT) of INR 7 crore 25% 50%
or USD 875,000 calculated as of the of the
total certified payments received requirement requirement
for contracts in progress or
completed, within the last 3 years
for each lot.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
45
Section 3: Evaluation and Qualification Criteria 3-9
If the bid evaluation process and the decision for the award of the Contract takes more than 1 year from the
date of bid submission, Bidders may be asked to resubmit their current contract commitments and latest
information on financial resources supported by latest audited accounts or audited financial statements, or
if not required by the law of the Bidder’s country, other financial statements acceptable to the Employer,
and the Bidders’ financial capacity, will be reassessed on this basis.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
46
3-10 Section 3: Evaluation and Qualification Criteria
(3) The joint venture must Not Must meet Not Not Form FIN – 3 and
applicable requirement applicable applicable Form FIN - 4
demonstrate that the combined
financial resources of all
partners defined in FIN - 3, less
all the partners’ total financial
obligations for the current
contract commitments defined
in FIN - 4, meet or exceed the
total requirement for the Subject
Contract of INR 2.35 crore or
USD 300,000 only
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
47
Section 3: Evaluation and Qualification Criteria 3-11
a
For contracts under which the Bidder participated as a Joint Venture partner or Subcontractor, only the Bidder’s share, by value,
shall be considered to meet this requirement.
b
For contracts implemented by a Joint Venture contractor, if the Bidder comprises the same Joint Venture, the 'Single Entity'
requirements will apply.
c
In case of complex works, the Employer may require each partner to demonstrate one satisfactorily and substantially completed
contract of similar nature where such partner’s value of participation exceeds 25% of the subject contract value.
d
In addition to the submission requirement Form EXP – 1, the bidder shall provide the following supporting documents:
[If the Employer will consider a “substantially completed contract” as one in which the works have been completed, insert the
following text:
1. Signed Contract Agreement, and
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
48
3-12 Section 3: Evaluation and Qualification Criteria
[If the Employer will consider a “substantially completed contract” as one in which the Contractor has completed all its obli gations
under the contract, insert the following text:
1. Signed Contract Agreement, and
2. Contract Completion Certificate or Performance Certificate,
in sufficient detail to verify the contract name, value and completion time. If the documents are other than in English, an accurate
certified translation of these documents in English shall be provided.]
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
49
Section 3: Evaluation and Qualification Criteria 3-13
2.4.2(a) Must be complied with by the Bidder. In case of a Joint Venture Bidder, the Bidder or at least
one of the partners must meet the requirement in the key activity. For contracts under which the Bidder
participated as a Joint Venture partner, only the Bidder’s designated scope of works under the contracts shall
be considered to meet this requirement.
Table A
Criteria Compliance Requirements Documents
Submission
Requirement Single Entity Joint Venture
Requirements
For the above or other contracts Must meet requirement Must meet requirement Form EXP – 2a
executed during the period
stipulated in 2.4.1, a minimum
experience in the following key
activities:
1 ………….
2 ………….
3 .. etc ……
a
Submission requirements: Form EXP – 2 shall be supported by documents such as Signed Contract Agreement, Taking-Over
Certificate or Contract Completion Certificate indicating the contract name, value, completion date (or percentage of substantial
completion), activities performed by Joint Venture partners, and other relevant details sufficient to demonstrate compliance
with the requirements.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
50
3-14 Section 3: Evaluation and Qualification Criteria
2.4.2(b) The Employer accepts any of the following activities to be subcontracted. They may be complied
with by the Bidder or by its proposed specialist subcontractor.
Not Applicable
a
Submission requirements: Form EXP – 2 shall be supported by documents such as Signed Contract Agreement, Taking-Over
Certificate or Contract Completion Certificate indicating the contract name, value, completion date (or percentage of substantial
completion), activities performed by Joint Venture partners, and other relevant details sufficient to demonstrate compliance with
the requirements.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
51
Section 3: Evaluation and Qualification Criteria 3-15
For example: Or
1. Existence of an Ethics Charter.
2. Existence of a system for All members must meet
monitoring compliance with EHS requirements
commitments for the Bidder’s
Subcontractors and all its partners.
3. Existence of official company
procedures for the management of
the following:
- ……….
- ……….
- ……….
- ……….
- ……….
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
52
3-16 Section 3: Evaluation and Qualification Criteria
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
53
Section 3: Evaluation and Qualification Criteria 3-17
2.6 Subcontractors
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
54
Section 4: Bidding Forms 4-1
Table of Forms
Letter of Bid ............................................................................................................................... 4-3
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
55
4-2 Section IV. Bidding Forms
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-
Stage: One-Envelope
56
Section 4: Bidding Forms 4-3
Letter of Bid
-Note-
The Bidder must accomplish the Letter of Bid on its letterhead clearly showing the Bidder’s complete name and address.
Date: ................................................
OCB No.: ................................................
Invitation for Bid No.: ................................................
(a) We have examined and have no reservations to the Bidding Documents, including Addenda issued in
accordance with Instructions to Bidders (ITB) 8.
(b) We acknowledge that we have read and understand ADB’s Anticorruption Policy (1998) and Integrity Principles
and Guidelines (2015), both as amended from time to time.
(c) We offer to design, manufacture, test, deliver, install, pre-commission, and commission in conformity with the
Bidding Document the following Plant and Services: [insert narrative]
(d) The total price of our Bid, excluding any discounts offered in item (d) below is the sum of
[amount of foreign currency in words], [amount in figures], and [amount of local currency in words], [amount in
figures]
The total bid price from the Grand Summary (Schedule No. 5) should be entered by the Bidder inside this box.
Absence of the total bid price in the Letter of Bid may result in the rejection of the bid.
(e) The discounts offered and the methodology for their application are as follows: [insert discounts and methodology for
their application if any]
(f) Our Bid shall be valid for a period of [insert bid validity period as specified in ITB 20.1 of the BDS ] days starts from the
date fixed for the bid submission deadline in accordance with ITB 24.1, and it shall remain binding upon us and
may be accepted at any time before the expiration of that period.
(g) If our Bid is accepted, we commit to obtain a performance security in accordance with the Bidding Documents.
(h) Our firm, including any Subcontractors or Manufacturers for any part of the Contract, have or will have
nationalities from eligible countries, in accordance with ITB 4.2.
(i) We, our directors, key officers, key personnel, including any Subcontractors, consultants, subconsultants,
manufacturers, service providers or Suppliers for any part of the Contract, do not have any conflict of interest
in accordance with ITB 4.3.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy Storage System with
EV Chargers project Procurement of Plant Single-Stage: One-Envelope
57
4-4 Section IV. Bidding Forms
(j) We are not participating, as a Bidder, either individually or as partner in a Joint Venture, in more than one Bid
in this bidding process in accordance with ITB 4.3(e), other than alternative offers submitted in accordance with
ITB 13.
(k) Our firm, Joint Venture partners, our respective direct and indirect shareholders, directors, key officers, key
personnel, associates, parent company, affiliates or subsidiaries, including any Subcontractors, consultants,
subconsultants, manufacturers, service providers or Suppliers for any part of the contract, are not subject to, or
not controlled by any entity or individual that is subject to, a temporary suspension or a debarment imposed by
the Asian Development Bank or a debarment imposed by the Asian Development Bank in accordance with the
Agreement for Mutual Enforcement of Debarment Decisions between the Asian Development Bank and other
development banks.1
(l) Our firm, Joint Venture partners, our respective direct and indirect shareholders, directors, key officers, key
personnel, associates, parent company, affiliates or subsidiaries, including any Subcontractors, consultants,
subconsultants, manufacturers, service providers or Suppliers for any part of the contract, are not under ongoing
investigation and/or sanctions proceedings by the Asian Development Bank or any multilateral development
bank.
If under ongoing investigation and/or sanction proceedings by the Asian Development Bank or any multilateral
development bank, please state details:
(m) Our firm, Joint Venture partners, our respective direct and indirect shareholders, directors, key officers, key
personnel, associates, parent company, affiliates or subsidiaries, including any Subcontractors, consultants,
subconsultants, manufacturers, service providers or Suppliers for any part of the Contract, are not temporarily
suspended, debarred, declared ineligible, or subject to any national and/or international sanctions by any
country, any international organization, any multilateral development bank and other donor agency.
If so temporarily suspended, debarred, declared ineligible, or subject to any national and/or international
sanctions by any country, any international organization, any multilateral development bank and other donor
agency, please state details (as applicable to each Joint Venture partner, their respective direct or indirect
shareholders, directors, key officers, key personnel, associate, parent company, affiliate, subsidiaries,
Subcontractors, consultants, subconsultants, manufacturers, service providers and/or Suppliers):
(iii) Reason for the temporary suspension, debarment, ineligibility, or national or international sanction:
________________________
(n) Our firm, Joint Venture partners, associates, parent company affiliates or subsidiaries, including any
Subcontractors, consultants, subconsultants, manufacturers, service providers Suppliers, key officers directors
and key personnel have never been charged or convicted with any criminal offense (including felonies but
excluding misdemeanors) or infractions and/or violations of ordinance; nor charged or found liable in any civil
or administrative proceedings in the last 10 years; or undergoing investigation for such, or subject to any
criminal, civil or administrative orders, monitorship or enforcement actions.
1
These institutions include African Development Bank, European Bank for Reconstruction and Development (EBRD), Inter -American Development Bank (IADB),
and the World Bank Group. According to paragraph 9 of the Agreement, other international financial institutions may join upon the consent of all Participating
Institutions and signature of a Letter of Adherence by the international financial institution substantially in the form prov ided (Annex B to the Agreement). Upon
adherence, such international financial institution shall become a Participating Institution for purposes of the Agreement. Bidders ar e advised to check
www.adb.org/integrity for updates.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
58
Section 4: Bidding Forms 4-5
(i) Nature of the offense/violation, proceedings, investigation, and/or monitorship or enforcement actions:
__________________
(ii) Court, area of jurisdiction and/or the enforcement agency: __________________
(iii) Resolution [i.e. dismissed, settled, or convicted; duration of penalty]: __________________
(iv) Other relevant details [please specify]: ____________
(o) Our firm, Joint Venture partners, our respective direct and indirect shareholders, directors, key officers, key
personnel, associates, affiliates or subsidiaries, including any Subcontractors, consultants, subconsultants,
manufacturers, service providers or Suppliers, can make and receive electronic fund transfer payments through
the international banking system or otherwise discharge the Employer’s obligation upon initiation of wire
transfer.
If unable to make or receive funds through the international banking system or otherwise discharge the
Employer’s obligation upon initiation of wire transfer, please state the details:
(p) Our firm, Joint Venture partners, associates, parent company, affiliates or subsidiaries, including any
Subcontractors, consultants, subconsultants, manufacturers, service providers or Suppliers, key officers,
directors and key personnel are not from a country which is prohibited to export goods or services to, or receive
any payments from the Employer’s country and/or are not prohibited to receive payments for particular goods or
services by the Employer’s country by an act of compliance with a decision of the United Nations Security Council
taken under Chapter VII of the Charter of the United Nations.
(q) We understand that it is our obligation to notify the Employer of any changes in connection with the matters
described in paragraphs (i), (k), (l), (m), (n), (o), (p) and (t) of this Letter of Bid.
(r) [We are not a government-owned enterprise] / [We are a government-owned enterprise but meet the
requirements of ITB4.5].2
(s) We have not been suspended nor declared ineligible by the Employer based on execution of a Bid-Securing
Declaration in the Employer’s Country in accordance with ITB 4.6.
(t) We have paid, or intend to pay, either directly or indirectly, the following commissions, gratuities, or fees with
respect to the bidding process or execution of the Contract: 3
(u) We understand that this Bid, together with your written acceptance thereof included in your notification of award
through the issuance of Letter of Acceptance, shall constitute a binding contract between us, until a formal
contract is prepared and executed.
(v) We understand that you are not bound to accept the lowest evaluated Bid or any other Bid that you may receive.
(w) At any time following submission of our Bid, we shall permit, and shall cause our Joint Venture partners,
directors, key officers, key personnel, associates, parent company, affiliates or subsidiaries, including any
Subcontractors, consultants, subconsultants, manufacturers, service providers or Suppliers for any part of the
2
Use one of the two options as appropriate.
3
If none has been paid or is to be paid, indicate “None.”
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy Storage System with
EV Chargers project Procurement of Plant Single-Stage: One-Envelope
59
4-6 Section IV. Bidding Forms
contract to permit ADB or its representative to inspect our sites, assets, accounts and records and other
documents relating to the bid submission and to have them audited by auditors appointed by ADB. We
understand that failure of this obligation may constitute obstructive practice that may result in debarment and/or
contract termination.
(x) Regardless of whether the contract will be awarded to us, we shall preserve all accounts, records and other
documents related to bid submission for at least 3 years from the date of submission of the bid or the period
prescribed in applicable law, whichever is longer.
(y) If we are awarded the contract, we shall preserve all accounts, records and other documents related to the
procurement and execution of the contract for at least 5 years after the completing the works contemplated in
the relevant contracts or the period prescribed in applicable law, whichever is longer.
(z) If our Bid is accepted, we commit to mobilizing key equipment and personnel in accordance with the
requirements set forth in Section 6 (Employer’s Requirements) and our technical proposal, or as otherwise
agreed with the Employer.
(aa) We certify on behalf of the Bidder, that the information provided in the bid has been fully reviewed, given in
good faith, and to the best of our knowledge is true and complete. We understand that it is our obligation to
inform the Employer of any changes to the information as and when it becomes known to us. We understand
that any misrepresentation that knowingly or recklessly misleads, or attempts to mislead may lead to the
automatic rejection of the Bid or cancellation of the contract, if awarded, and may result in remedial actions, in
accordance with ADB’s Anticorruption Policy (1998, as amended to date) and Integrity Principles and Guidelines
(2015, as amended from time to time).
Name ..........................................................................................................................................
In the capacity of .........................................................................................................................
Signed .........................................................................................................................................
Duly authorized to sign the Bid for and on behalf of ......................................................................
Date ............................................................................................................................................
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
60
Section 4: Bidding Forms 4-7
Price Schedules
PREAMBLE
General
1. The Price Schedules are divided into separate Schedules as follows:
Schedule No. 1: Plant and Mandatory Spare Parts Supplied from Abroad
Schedule No. 2: Plant and Mandatory Spare Parts Supplied from within the Employer’s Country
Schedule No. 3: Design Services
Schedule No. 4: Installation and Other Services
Schedule No. 5: Grand Summary
Schedule No. 6: Recommended Spare Parts
2. The Schedules do not generally give a full description of the plant to be supplied and the services to be performed
under each item. Bidders shall be deemed to have read the Employer’s Requirements and other sections of the
Bidding Document and reviewed the Drawings to ascertain the full scope of the requirements included in each
item prior to filling in the rates and prices. The entered rates and prices shall be deemed to cover the full scope
as aforesaid, including overheads and profit.
3. If Bidders are unclear or uncertain as to the scope of any item, they shall seek clarification in accordance with ITB
7 prior to submitting their bid.
Pricing
4. The units and rates in figures entered into the Price Schedules should be typewritten or if written by hand, must
be in print form. Price Schedules not presented accordingly may be considered nonresponsive. Any alterations
necessary due to errors, etc., shall be initialed by the Bidder.
As specified in the Bid Data Sheet and Special Conditions of Contract, prices shall be fixed and firm for the
duration of the Contract, or prices shall be subject to adjustment in accordance with the corresponding Appendix
(Price Adjustment) to the Contract Agreement.
5. Bid prices shall be quoted in the manner indicated and in the currencies specified in the Instructions to Bidders in
the Bidding Document.
For each item, Bidders shall complete each appropriate column in the respective Schedules, giving the price
breakdown as indicated in the Schedules.
Prices given in the Schedules against each item shall be for the scope covered by that item as detailed
in Section 6 (Employer’s Requirements) or elsewhere in the Bidding Document.
6. Payments will be made to the Contractor in the currency or currencies indicated under each respective item.
7. When requested by the Employer for the purposes of making payments or partial payments, valuing variations or
evaluating claims, or for such other purposes as the Employer may reasonably require, the Contractor shall
provide the Employer with a breakdown of any composite or lump sum items included in the Schedules.
8. Schedule 3 to 5 of Price Bid are common for both foreign and domestic bidders.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy Storage System with
EV Chargers project Procurement of Plant Single-Stage: One-Envelope
61
4-8 Section IV. Bidding Forms
Schedule No. 1: Plant and Mandatory Spare Parts Supplied from Abroad
GST /Taxes
Unit Pricea Total Pricea
and Duties
Country
Item Description Quantity Foreign Foreign Local
of Origin
Currency CIP Currency Currency
(USD) (USD) (INR)
1 2 3 4 5 6 7=4x6 8
A Battery Energy
Storage System 4 Sets
Lithium-Ion Battery
Solution (minimum)
of (100) kWh with
in- built BMS, HVAC
and Fire safety
system
Battery Energy 1 Set
Storage System
Lithium-Ion Battery
Solution (minimum)
of (200) kWh with
in- built BMS, HVAC
and Fire safety
system
B Solar System with 4 sets
capacity of (25)
kWp
Solar System with 1 Set
capacity of (50)
kWp
C EV Chargers for 4 sets
25kWp (as
specified in Section
6)
EV Chargers for 50 1 set
kWp (as specified
in Section 6 )
D Enclosure/Insulated 4 sets`
cabin with
necessary
temperature control
system, Fire safety
for accommodating
BESS and Solar
Power Conditioning
System for 25 kWp
Enclosure/Insulated 1 Set
cabin with
necessary
temperature control
system, Fire safety
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
62
Section 4: Bidding Forms 4-9
for accommodating
BESS and Solar
Power Conditioning
System for 50 kWp
Name of Bidder
Signature of Bidder
a
Specify currencies in accordance with ITB 19.1 of the BDS. Create additional columns for foreign currencies if so required.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy Storage System with
EV Chargers project Procurement of Plant Single-Stage: One-Envelope
63
4-10 Section IV. Bidding Forms
Schedule No. 2: Plant and Mandatory Spare Parts Supplied from Within the Employer’s Country
LOT 1
Unit Pricea
Total EXW GST/ Sales
Item Description Quantity Local and other
Currency Pricea
EXW Priceb taxes
(INR)
1 2 3 4 5 6=3x5 7
Name of Bidder
Signature of Bidder
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
64
Section 4: Bidding Forms 4-11
a
Specify currency in accordance with ITB 19.1 of the BDS.
b
Column 5 EXW Price shall include all customs duties and sales and other taxes already paid or payable on the components and raw materials
used in the manufacture or assembly of the item or the customs duties and sales and other taxes already paid on previously imported items.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy Storage System with
EV Chargers project Procurement of Plant Single-Stage: One-Envelope
65
4-12 Section IV. Bidding Forms
1 2 3 4 5 6=3x4 7=3x5
Name of Bidder
Signature of Bidder
a
Specify currency in accordance with ITB 19.1 of the BDS.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
66
Section 4: Bidding Forms 4-13
1 2 3 4 5 6=3x4 7=3x5
3 .....
4 .....
5 .....
etc .....
Name of Bidder
Signature of Bidder
a
Specify currency in accordance with ITB 19.1 of the BDS.
b
As described in SCC 22.2.7.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy Storage System with
EV Chargers project Procurement of Plant Single-Stage: One-Envelope
67
4-14 Section IV. Bidding Forms
Total Pricea
Schedule
Title
No. Foreign Local
(USD) (INR)
3 Design Services
Name of Bidder
Signature of Bidder
a
Specify currency in accordance with ITB 19.1 of the BDS. Create additional columns for foreign currencies if so required. Bids will be
evaluated considering total cumulative cost i.e Schedule 5.
b
Taxes and/or duties from Schedules 1 and 2 may be added to the contract price in accordance with GCC 14 (Taxes and Duties) but excluded
from bid evaluation in accordance with ITB 36.4.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
68
Section 4: Bidding Forms 4-15
EXW CIP
Local Imported Local Foreign
Item Description Quantity Parts Parts Currency Currency
Portion Portion
Local Foreign
Currency Currency (INR) (USD)
(INR) (USD)
1 2 3 4 5 6=3x4 7=3x5
TOTAL
Name of Bidder
Signature of Bidder
a
Specify currency in accordance with ITB 19.1 of the BDS.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy Storage System with
EV Chargers project Procurement of Plant Single-Stage: One-Envelope
69
4-16 Section IV. Bidding Forms
Schedule No. 1: Plant and Mandatory Spare Parts Supplied from Abroad
Taxes and
Unit Pricea Total Pricea
Duties
Country
Item Description Quantity Foreign Foreign Local
of Origin
Currency CIP Currency Currency
(USD) (USD) (INR)
1 2 3 4 5 6 7=4x6 8
A Battery Energy
Storage System 4 Sets
Lithium-Ion Battery
Solution (minimum)
of (100) kWh with
in- built BMS, HVAC
and Fire safety
system
Battery Energy 1 Set
Storage System
Lithium-Ion Battery
Solution (minimum)
of (200) kWh with
in- built BMS, HVAC
and Fire safety
system
B Solar System with 4 sets
capacity of (25)
kWp
Solar System with 1 Set
capacity of (50)
kWp
C EV Chargers for 4 sets
25kWp (as
specified in Section
6)
EV Chargers for 50 1 Set
kWp (as specified
in Section 6 )
D Enclosure/Insulated 4 sets
cabin with
necessary
temperature control
system, Fire safety
for accommodating
BESS and Solar
Power Conditioning
System for 25 kWp
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
70
Section 4: Bidding Forms 4-17
Enclosure/Insulated 1 Set
cabin with
necessary
temperature control
system, Fire safety
for accommodating
BESS and Solar
Power Conditioning
System for 50 kWp
Name of Bidder
Signature of Bidder
a
Specify currencies in accordance with ITB 19.1 of the BDS. Create additional columns for foreign currencies if so required.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy Storage System with
EV Chargers project Procurement of Plant Single-Stage: One-Envelope
71
4-18 Section IV. Bidding Forms
Schedule No. 2: Plant and Mandatory Spare Parts Supplied from Within the Employer’s Country
LOT 2
Unit Pricea
Total EXW Sales and
Item Description Quantity Local
Currency b Pricea other taxes
EXW Price
(INR)
1 2 3 4 5 6=3x5 7
Name of Bidder
Signature of Bidder
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
72
Section 4: Bidding Forms 4-19
a
Specify currency in accordance with ITB 19.1 of the BDS.
b
Column 5 EXW Price shall include all customs duties and sales and other taxes already paid or payable on the components and raw materials
used in the manufacture or assembly of the item or the customs duties and sales and other taxes already paid on previously imported items.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy Storage System with
EV Chargers project Procurement of Plant Single-Stage: One-Envelope
73
4-20 Section IV. Bidding Forms
1 2 3 4 5 6=3x4 7=3x5
Name of Bidder
Signature of Bidder
a
Specify currency in accordance with ITB 19.1 of the BDS.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
74
Section 4: Bidding Forms 4-21
1 2 3 4 5 6=3x4 7=3x5
3 .....
4 .....
5 .....
etc .....
Name of Bidder
Signature of Bidder
a
Specify currency in accordance with ITB 19.1 of the BDS.
b
As described in SCC 22.2.7.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy Storage System with
EV Chargers project Procurement of Plant Single-Stage: One-Envelope
75
4-22 Section IV. Bidding Forms
Total Pricea
Schedule
Title
No. Foreign Local
(USD) (INR)
3 Design Services
Name of Bidder
Signature of Bidder
a
Specify currency in accordance with ITB 19.1 of the BDS. Create additional columns for foreign currencies if so required. Bid will be
evaluated considering total cumulative cost i.e. schedules 5.
b
Taxes and/or duties from Schedules 1 and 2 may be added to the contract price in accordance with GCC 14 (Taxes and Duties) but excluded
from bid evaluation in accordance with ITB 36.4.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
76
Section 4: Bidding Forms 4-23
EXW CIP
Local Imported Local Foreign
Item Description Quantity Parts Parts Currency Currency
Portion Portion
Local Foreign
Currency Currency (INR) (USD)
(INR) (USD)
1 2 3 4 5 6=3x4 7=3x5
TOTAL
Name of Bidder
Signature of Bidder
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy Storage System with
EV Chargers project Procurement of Plant Single-Stage: One-Envelope
77
4-24 Section IV. Bidding Forms
Bid Security
Bank Guarantee
Date: ............................................................................................................................................................................................................................
Bid Security No.: ..............................................................................................................................................................................................
We have been informed that [name of the Bidder] (hereinafter called "the Bidder") has submitted to you its bid dated
[insert date] (hereinafter called "the Bid") for the execution of [name of contract] under Invitation for Bids No. [insert IFB
number] (“the IFB”).
Furthermore, we understand that, according to your conditions, bids must be supported by a bid guarantee.
At the request of the Bidder, we [name of Bank] hereby irrevocably undertake to pay you any sum or sums not exceeding
in total an amount of [amount in words] [amount in figures] upon receipt by us of your first demand in writing accompanied
by a written statement stating that the Bidder is in breach of its obligation(s) under the bid conditions, because the
Bidder
(a) has withdrawn its Bid during the period of bid validity specified by the Bidder in the Letter of Bid; or
(b) does not accept the correction of errors in accordance with the Instructions to Bidders (hereinafter “the ITB”); or
(c) having been notified of the acceptance of its Bid by the Employer during the period of bid validity, (i) fails or
refuses to execute the Contract Agreement, or (ii) fails or refuses to furnish the Performance Security, in
accordance with the ITB.
This guarantee will expire (a) if the Bidder is the successful Bidder, upon our receipt of copies of the Contract
Agreement signed by the Bidder and the Performance Security issued to you upon the instruction of the Bidder; or (b)
if the Bidder is not the successful Bidder, upon the earlier of (i) our receipt of a copy of your notification to the Bidder
of the name of the successful Bidder, or (ii) 28 days after the expiration of the Bidder’s bid.
Consequently, any demand for payment under this guarantee must be received by us at the office indicated above
on or before that date.
This guarantee is subject to the Uniform Rules for Demand Guarantees (URDG) 2010 Revision, ICC Publication No.
758.5
Technical Proposal
Site Organization
Method Statement
4
All italicized text is for use in preparing this form and shall be deleted from the final document.
5
Or the employer may use “Uniform Rules for Demand Guarantees (URDG), ICC Publication No. 458” as appropriate.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
78
Section 4: Bidding Forms 4-25
Mobilization Schedule
Construction Schedule
Plant
Personnel
Equipment
Manufacturer’s Authorization
Time Schedule
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
79
4-26 Section 4: Bidding Forms
Site Organization
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-
Stage: One-Envelope
80
Section 4: Bidding Forms 4-27
Method Statement
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
81
4-28 Section 4: Bidding Forms
Mobilization Schedule
The Mobilization Schedule should reflect the no-objection request and approval step for Site Specific
Environmental, Health and Safety Management Plan as per Contract Conditions.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-
Stage: One-Envelope
82
Section 4: Bidding Forms 4-29
Construction Schedule
The Bidder shall submit an outline Environmental, Health and Safety Management Plan (EHSMP)
commensurate with the risks and impacts of the proposed works and activities. These strategies and plans
shall describe in detail the actions, materials, equipment, management processes, etc. that will be
implemented by the Contractor, and its subcontractors.
In developing these strategies and plans, the Bidder shall have regard to the EHS provisions of the contract
and EHS risks including those as may be more fully described in Section 6 (Employer’s Requirements).
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
83
4-30 Section 4: Bidding Forms
Note to Bidder
The minimum content of the EHS Code of Conduct form as set out by the Employer shall not be substantially modified.
However, the Bidder may add requirements as appropriate, including to take into account Contract-specific issues/risks.
The Bidder shall initial and submit the EHS Code of Conduct form as part of its bid.
We are the Contractor, [enter name of Contractor]. We have signed a contract with [enter name of
Employer] for [enter description of the Works]. These Works will be carried out at [enter the Site and other
locations where the Works will be carried out]. Our contract requires us to implement measures to address
environmental, health and safety risks related to the Works.
This EHS Code of Conduct is part of our measures to deal with environmental, health and safety risks
related to the Works. It applies to all our staff, labourers and other employees at the Works Site or other
places where the Works are being carried out. It also applies to the personnel of each subcontractor and
any other personnel assisting us in the execution of the Works. All such persons are referred to as
“Contractor’s Personnel” and are subject to this EHS Code of Conduct.
This EHS Code of Conduct identifies the behavior that we require from all Contractor’s Personnel.
Our workplace is an environment where unsafe, offensive, abusive or violent behavior will not be tolerated
and where all persons should feel comfortable raising issues or concerns without fear of retaliation.
REQUIRED CONDUCT
84
Section 4: Bidding Forms 4-31
7. not retaliate against any person who reports violations of this EHS Code of Conduct, whether to us or
the Employer, or who makes use of the grievance mechanism for Contractor’s Personnel or the
project’s Grievance Redress Mechanism.
RAISING CONCERNS
If any person observes behavior that he/she believes may represent a violation of this EHS Code of Conduct,
or that otherwise concerns him/her, he/she should raise the issue promptly. This can be done by call [ ] to
reach the Contractor’s hotline (if any) and leave a message.
The person’s identity will be kept confidential, unless reporting of allegations is mandated by the country law.
Anonymous complaints or allegations may also be submitted and will be given all due and appropriate
consideration. We take seriously all reports of possible misconduct and will investigate and take appropriate
action. We will provide warm referrals to service providers that may help support the person who experienced
the alleged incident, as appropriate.
Any violation of this EHS Code of Conduct by Contractor’s Personnel may result in serious consequences,
up to and including termination and possible referral to legal authorities.
I have received a copy of this EHS Code of Conduct written in a language that I comprehend. I understand
that if I have any questions about this EHS Code of Conduct, I can contact [enter name of Contractor’s
contact person(s) with relevant experience)] requesting an explanation.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
85
4-32 Section 4: Bidding Forms
Plant
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-
Stage: One-Envelope
86
Section 4: Bidding Forms 4-33
Personnel
Bidders should provide the details of proposed personnel and their experience record in the relevant
Information Forms below for each of the candidate.
1. Title of position
Name
2. Title of position
Name
3. Title of position
Name
4. Title of position
Name
Name
-- Note --
All titles of positions will be as listed in Section 6 (Employer’s Requirements).
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
87
4-34 Section 4: Bidding Forms
The Bidder shall provide all the information requested below. Use one form for each position.
Position
Nationality Citizenship
Professional qualifications
Address of employer
Fax E-mail
Summarize professional experience in reverse chronological order. Indicate particular technical and
managerial experience relevant to the project.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-
Stage: One-Envelope
88
Section 4: Bidding Forms 4-35
Equipment
The Bidder shall provide adequate information and details to demonstrate clearly that it has the capability
to meet the equipment requirements indicated in Section 6 (Employer’s Requirements), using the Forms
below. A separate Form shall be prepared for each item of equipment listed, or for alternative equipment
proposed by the Bidder.
Item of Equipment
Address of owner
Fax Telex
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
89
4-36 Section 4: Bidding Forms
The following Subcontractors and/or Manufacturers are proposed for carrying out the item of the facilities
indicated based on Criterion 2.5 of Section 3 (Evaluation and Qualification Criteria). Bidders are free to
propose more than one for each item.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-
Stage: One-Envelope
90
Section 4: Bidding Forms 4-37
Manufacturer's Authorization
Date: [insert date (as day, month and year) of bid submission]
WHEREAS
We [insert complete name of the manufacturer or manufacturer’s authorized agent], who are official manufacturers
or agent authorized by the Manufacturer of [insert type of goods manufactured], having factories at [insert full
address of manufacturer’s factories], do hereby authorize [insert complete name of the Bidder] to submit a bid the
purpose of which is to provide the following goods, manufactured by us [ insert name and/or brief description
of the goods], and to subsequently negotiate and sign the Contract.
We hereby extend our full guarantee and warranty in accordance with Clause 27 of the General
Conditions of Contract, with respect to the goods offered by the above firm.
Duly authorized to sign this Authorization on behalf of: [insert complete name of the manufacturer]
-- Note --
The bidder shall require the manufacturer to fill out this form in accordance with the instructions indicated. This letter of
authorization should be signed by a person with the proper authority to sign documents that are binding on the manufacturer.
The bidder shall include it in its bid, if so indicated in the BDS.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
91
4-38 Section 4: Bidding Forms
Time Schedule
To be used by Bidder when alternative Time for Completion is invited in ITB 13.2.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-
Stage: One-Envelope
92
Section 4: Bidding Forms 4-39
The Bidder shall copy on the left column of the table below, the identification of each functional guarantee
required in the Specification and stated by the Employer in EQC 1.3.4 of Section 3, Evaluation and Qualification
Criteria, and on the right column, provide the corresponding value for each functional guarantee of the proposed
plant and equipment.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
93
4-40 Section 4: Bidding Forms
Bidders Qualification
To establish its qualifications to perform the contract in accordance with Section 3 (Evaluation and
Qualification Criteria) the Bidder shall provide the following information requested in the corresponding
Information Sheets.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-
Stage: One-Envelope
94
Section 4: Bidding Forms 4-41
Bidder’s Information
Information of the Bidder If the Bidder is a subsidiary or branch,
information of any parent
company/companies
Full legal
name(s)
Names
Full trading
name(s) (if
any)
Registered
address(es)
Trading
address(es)
Addresses
Postal
address(es)
(if different
from
trading
address)
Type of organization
Country of
constitution/incorporation/
registration
Year of constitution
/incorporation/ registration
Corporate or registration
number
Bidder’s authorized
representative
(name, address, telephone
number(s), fax number(s), e-
mail address)
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
95
4-42 Section 4: Bidding Forms
1. In case of a single entity, articles of incorporation or constitution and company incorporation/registration of the legal entity
named above, in accordance with ITB 4.1 and ITB 4.2.
2. Authorization to represent the firm or Joint Venture named above, in accordance with ITB 22.2.
3. In case of a Joint Venture, a letter of intent to form a Joint Venture or Joint Venture agreement, in accordance with ITB 4.1.
4. In case of a government-owned enterprise, any additional documents not covered under 1 above required to comply with
ITB 4.5.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-
Stage: One-Envelope
96
Section 4: Bidding Forms 4-43
Each partner of the Joint Venture and Specialist Subcontractor must fill out this form separately.
Names
Full trading name(s)
(if any)
Registered
address(es)
Type of organization
Country of constitution/
incorporation/ registration
Subcontractors are those listed in Technical Proposal – Proposed Subcontractors and/or Manufacturers for
Major Items of Plant and Services.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
97
4-44 Section 4: Bidding Forms
Each Bidder must fill out this form in accordance with Criteria 2.2.1 and 2.2.3 of Section 3 (Evaluation and
Qualification Criteria) to describe any history of nonperforming contracts and pending litigation or arbitration
formally commenced against it.
In case of a Joint Venture, each Joint Venture Partner must fill out this form separately and provide the Joint
Venture Partner’s name:
- Note -
Table 2 of this form shall only be included if Criterion 2.2.3 of Section 3 (Evaluation and Qualification Criteria) is applicable.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-
Stage: One-Envelope
98
Section 4: Bidding Forms 4-45
Each Bidder must fill out this form in accordance with Criterion 2.2.4 of Section 3 (Evaluation and
Qualification Criteria).
In case of a Joint Venture, each Joint Venture Partner must fill out this form separately and provide the
Joint Venture Partner’s name:
In case of a Specialist Subcontractors, each Specialist Subcontractor must fill out this form and provide
the Specialist Subcontractor’s name:
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
99
4-46 Section 4: Bidding Forms
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-
Stage: One-Envelope
100
Section 4: Bidding Forms 4-47
In case of a Joint Venture, each Joint Venture Partner must fill out this form separately and provide the Joint
Venture Partner’s name:
Net Worth = TA – TL
Total Revenues
Attached are copies of financial statements (balance sheets including all related notes, and income statements) for the last
_____ years, as indicated above, complying with the following conditions:
1. Unless otherwise required by Section 3 of the Bidding Documents, all such documents reflect the standalone financial
situation of the legal entity or entities comprising the Bidder and not the Bidder’s parent companies, subsidiaries , or
affiliates.
2. Historical financial statements must be audited by a certified accountant.
3. Historical financial statements must be complete, including all notes to the financial statements.
4. Historical financial statements must correspond to accounting periods already completed and audited (no statements for
partial periods shall be requested or accepted).
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
101
4-48 Section 4: Bidding Forms
The information supplied should be the Annual Turnover of the Bidder or each partner of a Joint Venture for
the total certified payments received from the clients for contracts in progress or completed, converted to US
dollars at the rate of exchange at the end of the period reported.
In case of a Joint Venture, each Joint Venture Partner must fill out this form separately and provide the Joint
Venture Partner’s name:
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-
Stage: One-Envelope
102
Section 4: Bidding Forms 4-49
Bidders must demonstrate sufficient financial resources, usually comprising of Working Capital supplemented
by credit line statements or overdraft facilities and others to meet the Bidder’s financial requirements for
In case of a Joint Venture, each Joint Venture Partner must fill out this form separately and provide the Joint
Venture Partner’s name:
Financial Resources
No. Source of financing Amount ($ equivalent)
2 Credit Linea
a
To be substantiated by a letter from the bank issuing the line of credit.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
103
4-50 Section 4: Bidding Forms
Bidders (or each Joint Venture partner) should provide information on their current commitments on all
contracts that have been awarded, or for which a letter of intent or acceptance has been received, or for
contracts approaching completion, but for which an unqualified, full completion certificate has yet to be
issued.
In case of a Joint Venture, each Joint Venture Partner must fill out this form separately and provide the Joint
Venture Partner’s name:
a
Remaining outstanding contract values to be calculated from 28 days prior to the bid submission deadline ($
equivalent based on the foreign exchange rate as of the same date).
b
Remaining contract period to be calculated from 28 days prior to bid submission deadline.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-
Stage: One-Envelope
104
Section 4: Bidding Forms 4-51
Form FIN - 5: Self-Assessment Tool for Bidder’s Compliance to Financial Resources (Criterion
2.3.3 of Section 3)
This form requires the same information submitted in Forms FIN - 3 and FIN - 4. All conditions of
“Available Financial Resources Net of CCC ≥ Requirement for the Subject Contract” must be satisfied
to qualify.
_________ . . . . . . . . . . ._
(Name of Bidder)
____________ ...........
(Name of Partner)
Each Partner:
_____________ ...........
(Name of Partner 1)
_____________ ...........
(Name of Partner 2)
_____________ ...........
(Name of Partner 3)
- Note -
Form FIN – 5 is made available for use by the bidder as a self-assessment tool, and by the Employer as an evaluation work
sheet, to determine compliance with the financial resources requirement as stated in 2.3.3. Failure to submit Form FIN - 5
by the Bidder shall not lead to bid rejection.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
105
4-52 Section 4: Bidding Forms
Fill out one (1) form per contract. Each contract shall be supported by documents such as Signed Contract
Agreement, Taking-Over Certificate, Contract Completion Certificate or Performance Certificate.
The exchange rate to be used to calculate the value of the contract for conversion to a specific currency
shall be the selling rate of the Borrower’s Central bank on the date of the contract.
Employer’s name
Address
Telephone number
Fax number
E-mail
Description of the Similarity in Accordance with Criterion 2.4.1 of Section 3 (Evaluation and
Qualification Criteria)
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-
Stage: One-Envelope
106
Section 4: Bidding Forms 4-53
Fill out one (1) form per contract. Each contract shall be supported by documents such as Signed Contract
Agreement, Taking-Over Certificate or Contract Completion Certificate.
If complied by Specialist Subcontractor, each Specialist Subcontractor must fill out this form and provide the
Specialist Subcontractor’s name:
Employer’s name
Address
Telephone number
Fax number
E-mail
Description of the Key Activities in Accordance with Criterion 2.4.2 of Section 3 (Evaluation and
Qualification Criteria)
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
107
4-54 Section 4: Bidding Forms
Form EXP – 3: Specific Experience in Managing Environmental, Health and Safety Aspects
In case of a Joint Venture, each Joint Venture Partner must fill out this form separately and provide the Joint
Venture Partner’s name:
Contract Identification
Award date
Completion date
Role in Contract Prime Partner Management Subcontractor
Contractor In JV Contractor
Details of relevant
experience
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-
Stage: One-Envelope
108
Section 4: Bidding Forms 4-55
Availability of the following valid ISO certification or internationally - recognized equivalent (equivalency
to be demonstrated by the Bidder), and applicable to the worksite:
a
Depending on the environmental, health and safety issues of the worksite and the type of competition planned (national
or international), the list of required certifications may be restricted to those corresponding to the main issue of the
worksite management or removed altogether.
Availability of in-house policies and procedures acceptable to the Employer for EHS management:
1. Existence of an Ethics Charter.
2. Existence of a system for monitoring compliance with EHS commitments for the Bidder’s
Subcontractors and all its partners.
3. Existence of official company procedures for the management of the following relevant points:
[Select 3-5 that apply for the worksite from below options- as per Section 2]
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
109
4-56 Section 4: Bidding Forms
Please provide CV [Form PER-2] of the in-house personnel of the main contractor/ Joint Venture partners
for the EHS positions specified in Section 6 (Employers Requirements):
-Environmental Specialist
-Health and Safety Specialist
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-
Stage: One-Envelope
110
Section 4: Bidding Forms 4-57
Employerʼs name
Address
Telephone number
Fax number
E-mail
Description of the Major Items in Accordance with Criterion 2.5 of Section 3 (Evaluation and
Qualification Criteria)
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
111
Section 5: Eligible Countries 5-1
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
112
Section 6: Employer’s Requirements 6-1
Table of Contents
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
113
6-2 Section 6: Employer’s Requirements
Convergence Energy Services Limited (CESL) is subsidiary of Energy Efficiency Services Limited
(EESL), a JV of public sector companies under the Ministry of Power, Government of India. Energy
Efficiency Services Limited is the executive agency for this TA-9874 IND program and CESL is
the Implementing and Procuring Agency for this Pilot Program. CESL is focused in delivering
clean, affordable, and reliable energy solutions that enable a faster energy transition. Convergence
Energy Services Limited (CESL) is a critical player working in development of e-mobility ecosystem in
the country. To enable commercialization of these solutions at scale, Convergence employs business
models that utilize blend of concessional and commercial capital, Carbon finance and grants as
appropriate. CESL presently owns and operates one of the largest EV fleets of 2000 cars across all
major states /cities in India. CESL also owns and operates a large EV charger network of more than
~1000 (public and captive) chargers installed across India.
6.2 BACKGROUND
CESL envisages the execution of green energy technologies by way of implementing off-grid Solar
Carport with BESS EV charging across various location in India. This would not only be a leap towards
harnessing the use of renewable energy for EV charging but also be means of self-reliant and
economical expenditure on energy requirement, which would capitalize the abundance of Solar
Energy resource in the region.
The standalone solar powered integrated with Lithium ion battery storage charging stations will ensure
that the EVs driven are completely carbon neutral.
The overall solar PV capacity is described in BOQ in Section 6.4.
Please note separate bids shall be submitted for each Lot.
India signed the Paris Agreement in year 2015 and committed to reduce its carbon footprint by 33-
35% below 2005 levels by 2030, along with increasing the share of non-fossil fuel-based electricity
to 40%. This target was further revised to 45% by year 2030 during COP26 Summit held in year
2021. The reduction in GHG emissions both from the energy and non-energy sectors is essential
to meet COP26 target. Further, in its action plan, India intends to build climate resilient urban
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
114
Section 6: Employer’s Requirements 6-3
centres and sustainable green transportation network. India presented the following five nectar
elements (Panchamrit) of India’s climate action:
Electric Vehicles (EV), as compared to fossil fuel cars, have considerably lower greenhouse gas
emissions that can even be brought down to zero, provided green electricity is used for charging
of EVs’. The standalone system purely utilizes solar power to charge the electric vehicles and
stores the excess energy or the energy generated while the stations are idle in batteries. Thus,
the entire system becomes clean and carbon neutral.
The Asian Development Bank (ADB) has secured a technical assistance (TA) from the Global
Environment Facility (GEF) for India electric mobility (e-mobility) project to enable Government of India
and relevant stakeholders to make the transformative shift to de-carbonize transport systems, catalyse
access to finance for a large-scale adoption of Electric Vehicles across vehicle segments and reduce
air pollution in cities by promoting scale-up of electric mobility in India.
Energy Efficiency Services Limited is the Executing Agency for this TA-9874 IND program and
CESL is entrusted with the responsibility of doing the procurement and monitor the
implementation for this Pilot Program. Convergence Energy Services Limited (CESL), under
Ministry of Power is implementing this program for EESL:
• Enabling scale-up of e-vehicle markets through pilot demonstrations
• Enabling conditions for e-mobility investments created, new business models and charging
infrastructure plans developed at city level
Keeping in view the above, CESL wants to conduct a pilot demonstration program to promote
Solar Powered EV Charging Carport at various locations across the country integrated with
Battery Storage.
1 2 3
A Battery Energy Storage System Lithium-Ion Battery
Solution (minimum) of (100) kWh with in-built BMS, 4 Sets
HVAC and Fire safety system
Battery Energy Storage System Lithium-Ion Battery 1 Set
Solution (minimum) of (200) kWh with in-built BMS,
HVAC and Fire safety system
B Solar System with capacity of (25) kWp* 4 sets
Solar System with capacity of (50) kWp* 1 Set
C EVChargers for 25kWp (as specified in Section 6.5 ) 4 sets
EVChargers for 50 kWp (as specified in Section 6.5 ) 1 Set
D Enclosure/Insulated cabin with necessary temperature control 4 sets
system, Fire safety for accommodating BESS and Solar
Power Conditioning System for 25 kWp
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
115
6-4 Section 6: Employer’s Requirements
CESL will finalize site basis discussion with land owning agency, however feasibility report of the
proposed site along with required technical design would be under the scope of the successful bidder.
The overall duration on the project is 6 Months from the date of LoA. CESL shall inform all the site sto
succesful bidder in 90 days from date of LOA. The time for completion of each site is 90 days from date
of site allocation. In case of any delay in providing sites from CESL, the timelines shall be extended
based on mutual agreement.
CESL shall carry out initial discussion with Land Owning Agencies at the above sites and carry out initial
site verification.
Post LoA, the successful bidder shall have to prepare a feasibility report of the site and submit the same
to CESL
CESL shall provide the approval for the same and obtain necessary permissions from the land owning
agency for setting up the solar carport at their location.
The installation and commissioning activities shall commence post signing of agreement between land
owning agency and CESL.
NOTE
Number of locations may vary by +/-20%.CESL reserves the right to change cities from the list of cities
mentioned under each LOT. In case, if any such change is required due to any unforeseen reason,
additional transportation cost may be reimbursed to the successful bidder as per actuals by ADB. The
succesful Bidder is required to provide suitable documentation incurred as an additional transport cost
in case of change of site. CESL shall verify the documentation before releasing any payment.
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
116
Section 6: Employer’s Requirements 6-5
The successful contractor will Design, engineer, procure & supply equipment and materials,
testing at manufacturers’ works, multi – level inspections, transportation, packing and
forwarding, supply, receipt, unloading and storage at site, associated civil works, services,
permits, licenses, installation and incidentals, insurance at all stages, erection, testing and
commissioning of the following Solar PV Projects and performance demonstration with
associated equipment and materials on turnkey basis with 06 (Six) years comprehensive
operation and maintenance from the date of Operational Acceptance.
(1) Solar carport based on the above-mentioned BoQ in Section 6.4 and specifications in
Section 6.6.
(2) Battery Energy Storage System based on the above-mentioned BoM in Section 6.4 and
specifications mentioned in Section 6.6
(1) Electric Vehicle Chargers
(2) Successful bidder will be provided land on right to use basis for setting up ground mounted
solar projects. Existing rooftop as mentioned in tender document may also be used.
(3) For Carport –
1 50 200 kwh 2 2 1
1 50 200 kwh 2 2 1
a) Solar panels including module mounting structures and fasteners along with the supply of BESS.
b) All power conditioning systems including junction boxes, Inverters/ PCU, DC and AC circuit
breaker(s).
c) All associated electrical works and equipment required for interfacing line/ cable (i.e. transformer(s)
– power and auxiliary, breakers, isolators, lightning arrestor(s), LT/other panels, protection system,
cables, metering etc., but not limited to) as per technical specifications.
d) Design, supply, erection, testing & commissioning defined in scope of work/ TS as per project
requirement and associated switchgear equipment and metering equipment as per technical
specification and state regulations
e) All associated civil works, including design and Engineering, for: Earthwork for Site grading, cutting,
filling, levelling & compacting, internal Roads, water drainage in the requisite project site as required
for development of this Solar PV Power Plant
f) Construction of Passage for Cleaning of Solar PV Project
g) Construction of rain water drainage, if required
h) Setting up of a comprehensive Fire Protection system as per the Hazardous area classification for
the site
i) Supply of mandatory spares & special tools and tackles
j) Demonstration of performance of the plant as per the requirement specified
k) Comprehensive operation & maintenance of the SPV plant for 06 (Six years)
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
117
6-6 Section 6: Employer’s Requirements
l) Obtaining all associated statutory and regulatory compliances, clearances, permits and approvals
for successful construction, commissioning and operation of plant for 6 years.
m) Adequate and seamless insurance coverage during construction and O&M period to cater all risks
(fire & allied perils, floods/water , chemical leakage/exposure, electric shock , short circuit , arc
flashes, earthquake, terrorists, burglary, riots, power output warranty etc) related to construction
and O&M of project to indemnify CESL. In an unlikely event of any accident (including
consequential losses) during construction and O&M period, the same must be the accountability of
the successful bidder and indemnify CESL.
n) Third Party Liability Insurance is also to be provided by the vendor during the warranty period.
o) CPG as mentioned in Section 8
p) Provision for Integration of PV Power with Grid
q) Energy Flow –
The Contractor shall arrange for all the necessary testing equipment, tools and tackles for carrying out
all the construction, operation and maintenance work covered under this contract. All the instruments are
required to be calibrated from NABL accredited lab before put in use. The certificate of the same shall
be submitted to CESL for verification.
Data Collection
The successful bidder shall ensure that the Solar Carport system is running as per the specifications
mentioned in the following sections and submit a monthly report during the project tenure to CESL
having the following:
CESL or through its representative may verify the data at any point of time during the project period.
Please note that:
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
118
Section 6: Employer’s Requirements 6-7
This section has detailed out the product wise specifications which are to be ensured by
the bidder
The PV modules used should be PID (Potential Induced Degradation) resistant and tested for Durability as
per IEC 62804.
All the modules used in this contract shall be of Bi-facial Mono-Crystalline Technology Tier-I & certified by
BIS.
All the modules used shall be equipped with factory made anti–soiling coating. Suitable confirmation
from Module manufacturer to be submitted to CESL at the time of supply of modules.
The PV modules used must qualify to the latest edition of IEC PV module qualification test or equivalent BIS
standards Crystalline Silicon Solar Cell Modules IEC 61215/IS14286. In addition, the modules must conform to
IEC 61730 Part-1: Requirements for construction and Part 2: Requirements for testing, for safety qualification
or equivalent IS.
For the PV modules to be used in a highly corrosive atmosphere throughout their lifetime, they must qualify
to IEC 61701/IS 61701
The total solar PV array capacity should not be less than allocated capacity (kWp) and should comprise of
solar Bi-facial mono-crystalline modules of minimum 540Wp and above wattage. Module capacity less than
minimum 540 watts peak shall not be accepted.
Low voltage drop bypass diodes shall be provided.
PV modules must be tested and approved by one of the IEC authorized test centers.
The Dual glass module of frame less type shall be provided by the bidder.
The bidder shall carefully design & accommodate requisite numbers of the modules to achieve the rated
power in his bid. CESL shall allow only minor changes at the time of execution.
As per ADB guidelines, an undertaking is to be provided by the successful bidder that NO FORCE
LABOUR OR CHILD LABOUR has been employed in manufacturing of Solar Panels.
Other general requirement for the PV modules and subsystems shall be the following:
The rated output power of any supplied module shall have tolerance of + 3%.
The bidder must ensure minimum panel generation capacity as per Industry standards. CESL can verify
actual generation at any point of time during the entire project tenure.
The peak-power point voltage and the peak-power point current of any supplied module and/or any
module string (series connected modules) shall not vary by more than 2 (two) per cent from the
respective arithmetic means for all modules and/or for all module strings.
The module shall be provided with a junction box with either provision of external screw terminal connection
or sealed type and with arrangement for provision of by- pass diode. The box shall have hinged,
weatherproof lid with captive screws and cable gland entry points or may be of sealed type and IP-65 rated.
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
119
6-8 Section 6: Employer’s Requirements
I-V (Current – Voltage) curves at STC (standard test conditions) should be provided by bidder.
Modules deployed must use a RF (Radio frequency) identification tag. The following information must be
mentioned in the RFID used on each module (This can be inside or outside the laminate, but must be able
to withstand harsh environmental conditions).
Name of the manufacturer of the PV module
Name of the manufacturer of Solar Cells.
Month & year of the manufacture (separate for solar cells and modules)
Country of origin (separately for solar cells and module)
I-V curve for the module Wattage, Imax, Vmax and FF (Fill Factor) for the module
Unique Serial No and Model No of the module
Date and year of obtaining IEC PV module qualification certificate.
Name of the test lab issuing IEC certificate.
Other relevant information on traceability of solar cells and module as per ISO 9001 and
ISO 14001
WARRANTIES
Material Warranty
Material Warranty is defined as: The manufacturer should warrant the Solar Module(s) to be free from the
defects and/or failures specified below for a period not less than Ten (10) years from the date of sale to the
original customer ("Customer")
Performance Warranty
o The predicted electrical degradation of power generated not exceeding 10% after first ten years’
period of the full rated original output.
o Linear degradation of 1% per annum would be considered for the calculation of electrical parameters.
Bidder shall design & install suitable module mounting structure (MMS) for bifacial modules having sufficient
strength (safe) & stability
Car Port with single/ multiple pole aesthetic design. Pole and other structure members should be hot
dip galvanized 80 Micron,
All fasteners to be used of SS304.
Module mounting to be done with Aluminum clamp and short rail system.
Walkway along with safety lifeline to be provided for maintenance purpose along with drainage
arrangement of water and Module Cleaning system to be provided at each carport, Module to be used
minimum of 540Wp.
Grade of concrete to be used Minimum M25 and Minimum ground clearance of Car port should be
12 feet. (May vary by +/- 5%)
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
120
Section 6: Employer’s Requirements 6-9
Car port to be aligned in such a way to absorb maximum sun radiation and PV Syst report to be
submitted.
PCU to be mounted separately with Proper junction box or housing considering safety and no more
than 2% overall cable losses.
The bidder shall use the original parts in case of any fault in the PCU/Inverter during the O&M period of 6
years. In case the original part/parts are not available with the manufacturer of the PCU/Inverter (Based on
certificate from the manufacturer), the bidder shall use the new parts of other standard brands available in
the market or will use the repaired parts but only with the prior permission of CESL
The PCU/ inverters should be tested from the MNRE approved test centers/ NABL /BIS /IEC
accredited testing- calibration laboratories. In case of imported power conditioning units, these should be
approved by international test houses.
The combined wattage of PCU/inverters should not be less than rated capacity of power plant under
STC (Standard test conditions).
Maximum power point tracker shall be integrated in the PCU/inverter to maximize energy drawn from
the array.
BALANCE OF ELECTRICAL SYSTEM
Cables of appropriate size to be used in the system shall have the following characteristics:
o Shall meet IEC 60227/IS 694, IEC 60502/IS1554 standards
o Temp. Range:10oC to +80oC.
o Voltage rating:1100V.
o Excellent resistance to heat, cold, water, oil, abrasion, UV radiation
o Armored cables: All AC cables used in this contract shall be of armored type.
o Sizes of cables between array interconnections, array to junction boxes, junction boxes to Inverter
etc. shall be so selected to keep the voltage drop (power loss) of the entire solar system to the minimum.
The cables (as per IS) should be insulated with a special grade PVC FRLS compound formulated for
outdoor use. FRLS cables shall be usedin all underground areas.
o DC cables manufactured with EBXL & having anti-rodent properties shall be used. The DC cables from
the SPV module array shall run through a UV-stabilized PVC conduit pipe of adequate diameter with
a minimum wall thickness of .5mm.
o Cable Routing/ Marking: All cable/wires are to be routed in a GI cable tray and suitably tagged and
marked with proper manner by good quality ferule or by other means so that the cable easily identified.
o The Cable should be so selected that it should be compatible up to the life of the solar PV panels i.e.
25 years. In three phase systems.
o The ratings given are approximate. Bidder to indicate size and length as per system design requirement.
All the cables required for the plant provided by the bidder. Any change in cabling sizes if desired by
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
121
6-10 Section 6: Employer’s Requirements
the bidder/approved after citing appropriate reasons. All cable schedules/layout drawings approved
prior to installation.
o Multi Strand, Annealed high conductivity copper conductor with XLPE insulation. Overall PVC/XLPE
insulation for UV protection Armored cable for underground laying. All cable trays including covers to
be provided. All cables conform to latest edition of IEC/ equivalent BIS Standards as specified below.
Cables for AC power from inverters to AC combiner Box shall be of Copper conductor only however,
cables from AC combiner box to ACDB to LT Panel of CESL can be of Aluminum conductor.
o PVC/XLPE insulated cables for working Voltage up to and including 1800 V,UV resistant for outdoor
installation IS /IEC 69947.
o The size of each type of DC cable selected shall be based on minimum voltage drop however;
the maximum drop shall be limited to 2%.
o The size of each type of AC cable selected shall be based on minimum voltage drop however;
the maximum drop shall be limited to 2%.
o Separate cable trays to be laid for AC cables and separate GI conduits/ Cable Tray to be provided for
DC cables.
Supply and Erection of DC Distribution Box (DCDB). Supply of appropriate size cables as per the standards
and erection at each site. This includes module interconnection cables, cables from SPV array to DCDB.
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
122
Section 6: Employer’s Requirements 6-11
CABLE TRAY
All the Solar DC Cable of +ve and -ve string shall be laid in covered Cable Tray of minimum size of 50/75
mm width by using DWC Conduit pipe and AC cable shall be laid through existing Cable route under the
viaduct. The typical fixing arrangement of cable tray is shown in Section VII.
The developer should design & install suitable module cleaning system after approval of layout by
CESL.
Water Pipeline
NON-Return Valve
Non-return valve shall be installed to prevent the back pressure of water once the pump shuts down. This
device should be installed at the delivery of the pump.
The Bidder shall install Water Collection Tray on outer side of Via-duct of minimum 150 mm width along
with Water discharge arrangement.
Water collection tray shall be GI coated.
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
123
6-12 Section 6: Employer’s Requirements
AC Output current.
Output Power
Power factor.
DC Input Voltage.
DC Input Current.
Time Active.
Power produced
Protective function limits (viz. AC Over voltage, AC Under voltage, over frequency, under
frequency, ground fault, PV starting voltage, PV stopping voltage, over current, short circuit
etc.
PV array energy production: Digital Energy Meters to log the actual value of AC/ DC voltage, Current &
Energy generated by the PV system provided. Energy meter should be of 0.5s accuracy class with
CT/PT of same accuracy class.
String and array DC Voltage, Current and Power, PCU AC output voltage and current (All 3 phases and
lines), AC power (Active, Reactive and Apparent), Power Factor and AC energy (All 3 phases and
cumulative) and frequency shall be Solar Radiation and Environment Monitoring System
o Solar radiation and weather monitoring system (WMS) shall be installed along with the solar PV
power plant.
o The system shall consist of various sensors, and remote monitoring.
o Solar PV module back surface temperature shall be also monitored on continuous basis.
o Simultaneous monitoring of DC and AC electrical voltage, current, power, energy and other data of the
plant.
o Solar radiation and weather monitoring system (WMS) shall have real time clock, internal reliable
battery backup and data storage capacity to record data round the clock for a period of min. 1 Month.
Cloud data storage should be available for 1 year.
o The data file should be MS Excel compatible. All instantaneous data shall be shown on the computer
screen.
o Historical data shall be available for download.
o Provision for Internet monitoring and download of data shall be incorporated.
o The vendor shall provide unified portal for the all the data acquisition and parameters.
METERING
Metering panel (0.5S class) shall be installed for Power output measurement from Solar Plant
SURGE PROTECTION
EARTHING PROTECTION
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
124
Section 6: Employer’s Requirements 6-13
o Each array structure of the PV yard should be grounded/ earthed properly as per IS: 3043-1987.
In addition, the lighting arrester/masts should also be earthed Earth Resistance shall be tested
in presence of the representative of CESL as and when required after earthing by calibrated
earth tester. PCU and ACDB should also be earthed properly.
o Earth resistance shall not be more than 5 ohms. It shall be ensured that all the earthing points
are bonded together to make them at the same potential.
DC PROTECTION
o An inline fuse shall be provided at the end of positive terminal of the first module of each string,
to ensure protection from High DC voltage in case of fault.
CONNECTIVITY
The maximum capacity for interconnection with the grid at a specific voltage level shall be as specified in
the Distribution Code/Supply Code and amended from time to time. However, in this project415 V-Three
Phase will be followed for selection of voltage level in the distribution system
EV Charger powered from the designed off-grid plant having following specification;
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
125
6-14 Section 6: Employer’s Requirements
Output Requirements
The CCS 2.0 chargers should allow charging of vehicle with power of 60kW.
The AC Type II chargers should allow charging of vehicle with power of 7.4 kW.
a) Charging Power: 7.4 kW (1-ph),
b) AC Output: 150 – 270 Vac (L – N) / 340 – 460 Vac (L – L)
c) Connection point: Type-2 socket (IEC 62196-2)
d) Mode of Charging: Mode-3 Max.
e) AC Output Current: 32 A (7.4 kW)
Cable Requirements
Charging Cable Assembly: The functional characteristics are defined below
a) Functional characteristics: The maximum usable cord length will be 5000mm, straight cable
b) Cable Connection Type: supply cable will be with EVSE as per Case C defined in section 6.3.1
of IEC61851-1.
c) Connector must be in accordance with IEC 62196-3 with a voltage range upto 1000V (DC). DC
connector must have silver-plated power contact with replaceable mating frame for
replacement of only plastic frame and have two temperature sensors for measurement of
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
126
Section 6: Employer’s Requirements 6-15
temperature for both the power contacts (DC+ and DC-). Connector must fulfill IATF 16949
automotive standard and ISO 9001 must be tested by ARAI as Indian atmospheric condition
or at an ambient temperature of 50degC.
d) The charging gun must have a feature to sound an loud alarm in case of any tampering done
on the charging cable and the gun must be tampered proof.
e) Cord Extension Set: No extension cord to be used
f) Adaptors: No adapters to be used
g) Storage means of the cable assembly and vehicle connector: EVSE should have storage for
cable and connector when not in use, at a height between 0.4m to 1.5m above ground level, as
per IEC 61851-23 Section 101.1.3
Environmental Requirements
a) Ambient Temperature Range: -20°C to 55°C (Charger unit must be tested by ARAI/ICAT
at specified temperature range for 8 hours at full load CC at 200A, 415V -15% Voltage)
b) Ambient Humidity: 5% to 95%
c) Ambient Pressure: 86 kpa to 106 kpa as
d) Storage Temperature: -20°C to 60°C (Charger unit must be tested by ARAI/ICAT at
specified temperature range)
Mechanical Requirements
a) Ingress Protection: The minimum IP degrees for ingress of objects is IP 54 or higher
b) Mechanical Impact: As per IEC 61851-1 Section 11.11.2. The same impact conditions are
applicable for charger display also. The bidder must produce the ARAI/ICAT test report
for mechanical impact testing on display screen also)
c) ARAI tests for mechanical imapct testing on the charger as a whole is accetable however, the
technical specification of display shall remain as per above clause
d) Mechanical Stability: As per section 11.11.2 of IEC 61851-1
e) Cooling: Air cooled or forced cool for protection and safety of equipment from any fire hazards.
f) Floor Mount Pillar Type arrangement for stand-alone CCS2 (50kW) charger.
g) Locking Arrangement: Three-point key lock key arrangement or better arrangement AND pad
lock arrangement with supply of pad-lock of minimum 8mm shackle thickness with minimum 2-
key arrangement.
Protection Requirements
a) Surge Protection Device Class C
The Sub-panel must be protected with Type-2 SPD, MoV and GDT based device in
accordance with IEC 61643-11. SPD should be pluggable type (both L-N & N-PE) for ease of
maintenance and have optics indication for fault detection along with remote monitoring
feature. SPD shall have surge handling capacity of (8/20us) – 20kA nominal and 40kA
maximum. Device must have third-party certification From accredited lab.
b) Protection against Electric Shock: As per IEC 61851
c) Effective earth continuity between the enclosure and the external protective circuit, As per IEC
61851
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
127
6-16 Section 6: Employer’s Requirements
Specific Requirements
EVSE shall have provision of emergency switching, protection against uncontrolled reverse
power flow from vehicle, Output current regulation in CCC, Output voltage regulation in CVC,
Controlled delay of charging current in CCC, limited periodic and random deviation (current
ripple) and limited periodic and random deviation (voltage ripple in CVC), as per Section 102.2
of IEC 61851-23.
The specific requirements defined in Section 102.2 of IEC 61851-23 except for the functions
provided with descriptions:
a) Rated outputs and maximum output power: The clause from Section 101.2.1.1 of IEC 61851- 23
is applicable except for the ambient temperature range to be -20 °C to 55 °C for Indian climatic
conditions.
b) Descending rate of charging current: In case of normal condition, EVSE should be able to reduce
the descending current at a rate of 100A per second or more as per Section 101.2.1.4 IEC 61851-
23.
c) Load dump: In any case of load dump, voltage overshoot shall not exceed 110% of the
maximum voltage limit of the battery systems, as per Annex BB 3.8.3 of IEC61851-23.
d) EMI/EMC as per IEC 61000 for the complete unit
e) The charger should have inbuilt functionality to store the charger down time logs for at least 6
months. These logs should clearly specify the nature of down time i.e. either due to mains power
failure, SPD failure or emergency condition or etc. The charger should be capable to transmit
the same data to the CMS.
Functional Requirements
The functional requirements should be as per Section 6.4.3 of IEC 61851-1 and Section 6.4.3 of
IEC 61851-23 except for the following functions, to be implemented as follows.
a) Measuring current and voltage: The accuracy of output measurement of system B shall be
within the following values:
1. Voltage measurement: ± 0.2% > 50V, ±0.5% <50V
2. Current measurement: ±1 A
b) The charger should have the power limiting option, settable from display UI and CMS also. The
option should have setting to set the power ranging from 25kW to 50(60kW) for individual gun
and both guns also.
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
128
Section 6: Employer’s Requirements 6-17
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
129
6-18 Section 6: Employer’s Requirements
Miscellaneous Requirements
1 Labels and Stickers The labels and stickers should be UV and weather proof and shall
not be degraded temperature. The life expectancy shall be of 10
years
2 Modem The modem shall be kept inside the charger unit. The bidder has
to ensure the design to avoid signal losses inside the charger
cabinet.
3 Smoke Sensor In case of any fire/smoke condition, the controller shall generate a
fault and stop the charging and isolate the input power supply from
the rest of charger. The bidder has to make sure that the
smoke sensor shall not generate any false alarm due to external
dust in case of weak IP protection of charger unit.
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
130
Section 6: Employer’s Requirements 6-19
4 Meter Box cum The bidder has to provide one meter box cum power distribution box
Distribution box for housing energy meter and incomer MCB/MCCB
Civil Structure:
Solar PV Modules Warranty: PV modules must be warranted with linear degradation rate of power
output except for first year (maximum 3% including LID) and shall guarantee 80% of the initial
rated power output at the end of 25 years. The modules shall be warranted for at least 10 years
for failures due to material defects and workmanship. The mechanical structures, electrical works
and overall workmanship of thesolar power plants must be warranted for a minimum of 6 years.
The PCUs installed in the solar power plant must have a warranty for 6 years. Defect liability will
be for a period of 6 years fromthe date of operational acceptance.
BESS System Warranty: The bidder shall provide a warranty for the entire BESS and its constituent
equipment. the bidder shall provide an unconditional, 6 (six) -year parts and labour warranty on
all BESS equipment including battery. The warranty shall guarantee the availability of battery
replacements delivered to the site within 2 weeks of notification during the battery warranty period.
EV Chargers Warranty: The Successful Bidder shall ensure a warranty period of six (6) yearsto
ensure trouble free services and supply of components of charger. The Successful Bidder should
ensure availability of all spares and components required for the charging stations infrastructure
for at least 10 years which may be procured against cost after expiry of warranty period. All internal
& external equipment such as display screen, Surge Protection Devices, Meter Box, Internal
controllers, meters, Internal backup battery and other necessary equipment’s as well should be
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
131
6-20 Section 6: Employer’s Requirements
The selected bidder/s shall provide O&M for a period of 6 Years from the date of commissioning. The
O&M cost shall be borne by the bidder and should be included in the BOM.
The bidder shall submit a CPG of 10% of the total project value to CESL at the beginning of the project.
The O&M may be extendable after the asset is transferred to the end user. It is at the sole discretion of
the end user to extend the services of the selected bidder/s for continuing the O&M at appropriate
market rate at that point of time.
CESL shall not be responsible after the project duration (6 Years)- (5 Years Asset would be with CESL
and the same shall be transferred to the end user at the beginning of the 6th Year). The Bidder shall
continue to provide O&M till the end of 6th Year.
Maintenance of the System
Total Operation & Maintenance of the SPV Plant i.e. 06 years from the date of commissioning shall be
with the bidder, after operational acceptance of the plant till culmination of the O&M period
Procurement of spare parts, overhaul parts, tools & tackles, equipment, consumables, etc. required for
smooth operation and maintenance of the plant as per prudent/ standard utility practices
Continuous monitoring the performance of the Solar Power Plant and regular maintenance of the whole
system including PV modules
Whenever a fault occurs, the bidder has to attend to rectify the fault & submit a report in 12 Hours to
CESL and the fault must be rectified within the 24 hours from the time of occurrence of fault. Apart from
this all the measures/guidelines mentioned under maintenance subsection shall be followed.
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
132
Section 6: Employer’s Requirements 6-21
The Contractor will attend to any breakdown jobs immediately for repair/ replacement/ adjustments and
complete at the earliest working round the clock.
The Contractor shall immediately report the accidents, if any, to the Engineer In charge & to all the
concerned authorities as per prevailing law of the state showing the circumstances under which it
happened and the extent of damage and/ or injury caused. Maintenance contractor would be solely &
fully responsible/ liable to pay for any losses/ damages/ claims, etc.
The Contractor shall comply with the provision of all relevant Acts of Central or State Governments
including payment of Wages Act 1936, Minimum Wages Act 1948, Employer’s Liability Act 1938,
Workmen’s Compensation Act 1923, Industrial Dispute Act 1947, Maturity Benefit Act 1961, Employees
State Insurance Act 1948, Contract Labour (Regulations & Abolishment) Act 1970 or any modification
thereof or any other law relating whereto and rules made there under from time to time.
The contractor shall at his own expense provide all amenities to his workmen as per applicable laws
and rules.
The Contractor shall ensure that all safety measures are taken at the site to avoid accidents to his or
his Co-contractor or people around the premises.
If in the event of negligence or mal-operation by the contractor’s workmen, any failure of equipment
take place such equipment should be repaired/ replaced by contractor at free of cost.
TOOLS & TACKLES AND SPARES
After completion of installation & commissioning of the power plant, necessary tools & tackles shall be
maintained by the bidder for maintenance purpose.
A list of requisite spares in case of PCU/inverter Junction Boxes. Fuses, , MCCBs etc. along with spare set
of PV modules be indicated, which shall be maintained. A minimum set of spares shall be maintained in the
plant itself for the entire period of warranty and Operation & Maintenance which upon its use shall be
replenished.
Danger boards should be provided as and where necessary as per IE Act. /IE Rules as amended up to date.
Three signage’s shall be provided one each at battery –cum- control room, solar array area and main entry in
to the area. Text of the signage’s may be finalized in consultation with CESL.
o FIRE EXTINGUISHERS
The firefighting system for the proposed power plant for fire protection shall be consisting of Portable fire
extinguishers for fire caused by electrical short circuits and sand buckets. The installation of Fire Extinguishers
should confirm to TAC regulations and BIS standards.
Three sets of Engineering, Electrical drawings and Installation and O&M manuals are to be supplied. Bidders
shall provide complete technical data sheets for each equipment giving details of the specifications along with
make/makes in their bid along with basic design of the power plant and power evacuation, synchronization along
with protection equipment.
For complete electro-mechanical works, bidders shall supply complete design, details and drawings for
approval to CESL before progressing with the installation work.
Developer will submit to CESL all Structural, Electrical and all other drawings and designs relating to this solar
power project
The bidder should carry out Shadow Analysis at the site and accordingly design strings & arrays layout
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
133
6-22 Section 6: Employer’s Requirements
considering optimal usage of space, material and labor. The bidder should submit the array layout
drawings along with Shadow Analysis Report to CESL/Owner for approval.
CESL reserves the right to modify the landscape design, Layout and specification of sub-systems and
components at any stage as per local site conditions/requirements.
The bidder shall submit preliminary drawing for approval & based on any modification or
recommendation, if any. The bidder shall submit three sets and soft copy in CD of final drawing for
formal approval to proceed with construction work.
o DRAWINGS TO BE FURNISHED BY BIDDER AFTER AWARD OF CONTRACT
The Bidder shall furnish the following drawings after Award/Intent and obtain approval:-
General arrangement and dimensioned layout. Schematic drawing showing the requirement of SPV
panel, Power conditioning. Unit(s)/ inverter, Junction Boxes,AC and DC Distribution Boards, meters etc.
Structural drawing along with mounting details of the structure.
Itemized bill of material for complete SPV plant covering all the components and associated
accessories.
Layout of solar Power Array.
Shadow analysis of the area.
Guaranteed Technical Particular (GTP) of Solar PV modules, inverters, Remote monitoring system, DC
cables, AC cables, Junction Box.
SAFETY MEASURES
The bidder shall provide the safety compliance certificates as per defined standards of all the
components post installation. Safety parameters including fire safety, water safety , electrical safety ,
chemical safety , mechanical safety , structure/civil work safety etc. The bidder shall take entire
responsibility for electrical safety of the installation(s) including connectivity with the grid and follow all the safety
rules & regulations applicable as per Electricity Act, 2003 and CEA guidelines etc.
Safety at site
o One safety engineer to be deployed in this project and penalty for not following safety is as follows: -
Bidder shall engage one qualified safety engineer at the site, to ensure safe work environment during the
execution stage of work.
If found, that Safety Engineer is not available at site suitable penalty of Rs. 1000/- (Rupee One Thousand
Only) shall be imposed per violation/instance on solar developer after issuing of first warning.
Bidder shall mandatorily conduct an overall safety analysis of all the execution sites and submit safety report to
mitigate the probable hazards during the execution of work and shall ensure their compliance at site.
The safety report thus prepared shall be submitted to CESL for the approval of CESL safety wing.
Solar developer shall mandatorily issue I-cards to all the workers engaged for work, the details of the same shall
be submitted to CESL to ensure controlled access.
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
134
Section 6: Employer’s Requirements 6-23
All the workers shall be provided with uniforms, if found not complied suitable penalty of Rs. 1,000/- (Rupees
One Thousand Only) shall be imposed after issuing of first warning for each instance for each worker.
o Life-line runners
The solar developer shall provide at least 2 lifeline runners during the installation of lifeline. If found not compliant
suitable penalty shall be imposed.
As per site requirement, at times bidder m ay have to install Fall arrester and safety net to ensure safe
working, the design of Fall arrester and specifications of safety net to be installed shall be submitted to CESL
for review & approval prior to start of work to ensure uniformity of design and safety of worker during execution.
o Crane/Hydra certificate
To ensure safe material handling and movement at the site, the bidder shall mandatorily submit max loading
certificate of Hydra and its instructor license before start of material handling work.
Bidder shall prepare site specific method statement which shall include the placement of hydra/crane,
calculations establishing the safe operation of hydra for this particular site based on loading curve of the boom
of hydra etc.
The Bidder(s) shall ensure that all information security aspects are exercised tested, implemented and
where necessary enhanced and not diluted at any point of time.
The uptime of the charger shall be monitored and logged by the CESL’s CMS platform.
The bidder(s) must compulsorily submit type test reports, interoperability testing certificate andcertificates
conforming to all the technical specifications of CESL for EV chargers from the recognized certification agencies
such as ARAI, ICAT or equivalent international certification agencies, at the time of bidding. In the case of non-
availability of the ARAI/ICAT, type test reports and conformance certification at the time of bid, the bidder may
submit international third party approved lab test reports and conformance certification for the offered chargers,
basis which letter of intent (LoI) shall be issued. The successful bidder(s) MUST submit the ARAI/ICAT type test
reports and certifications conforming to the specification before issuance of Letter of Award.
NOTE: Any international/Indian test report/certifications must contain name of the manufacturer, manufacturing
address of the bidder and contact details of the testing lab. If there is an anomaly in the submitted versus actual
report, the bidder shall be outrighty rejected.
o Hood canopy structure on the top of the EV Charger with LED panel lights for illumination during evening
hours. An auto day-light sensor enabled or remotely through ON/OFF using GPRS. Hood canopy
structure should be having three side walls (right, left and rear) of 8mm acrylic sheet, a small acrylic
sheet on the top front side of hood structure. Hood structure should be supplied with pre-branding
as approved by CESL. The hood canopy structure should be painted & rust free. Proper wiring conduits
or channels should be used to avoid the theft of electricity. LED panel lights should be 12V/24V DC
operated & will be powered from the EV charger.
o The hood canopy design shall be approved by CESL and may vary as per charger type & site
requirement.
o Bollards around each EV station to protect chargers from vehicle impacts, concrete/MS painted bollards
as per site requirement should be used of appropriate thickness (atleast 5 inches) . Minimum four
bollards should be used at the front/side/rear of chargerMeter box with MCCB/MCB with necessary CTs,
meter stand/wall & foundation worksfor meter box.
o Vehicle parking space marking is in the scope of bidder. Each charger shall have space for parking
for minimum two (2) vehicles. The bidder should paint the entire space of parking either with epoxy
paint or rubber paint having life of minimum 10 years. In case of soft soil and floor paint is not possible,
only then the bidder should supply hording panel for marking the EV space. The bidder should visit the
sites during survey to ascertain the requirement of paint/hording board. The designs for vehicle space
marking/hording design shall be approved by CESL. The designs are shown below for reference.
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
135
6-24 Section 6: Employer’s Requirements
o All charger power connections from BESS/inverter to EV chargers, including supply of cable (as per site
Floor Paint Design EV Space Marking Hording (only in case
of soft soil or floor paint is not
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
136
Section 6: Employer’s Requirements 6-25
TECHNICAL PARAMETER OF PV MODULE AND VARIOUS OTHER COMPONENTS FOR USE IN OFF
GRID SOLAR POWER PLANTS
All components of the PV plant shall be in accordance with technical specifications given in relevant IS / IEC
Standards. The design and commissioning also shall be as per latest IS / IEC standards. The following are
some of the technical measures required to ensure quality of the major components used in solar power projects.
PV MODULE QUALIFICATION
The PV modules used in the solar power pproject must qualify to the latest edition of any of the following IEC
PV module qualification test or equivalent Indian standards.
Standard Description
IEC 61215-1 Ed. Terrestrial photovoltaic (PV) modules -Design qualification and type approval Part 1:
1.0 Test requirements
IEC 61215-1-1 Terrestrial photovoltaic(PV) modules -Designqualification and type approval Part-1: Special
Ed.1.0 requirements for testing of crystalline silicon photovoltaic (PV) modules
IEC 61730-1Ed. Photovoltaic(PV) module safety qualification Part 1: Requirements for construction
2.0
IEC 61730-2 Photovoltaic (PV) module safety qualification Part2: Requirements for testing
Ed.2
IEC 62716 Ed.1 Photovoltaic (PV) modules-Ammonia corrosion testing (Applicable for wet
atmospheres having highconcentration of dissolved ammonia)
POWER CONDITIONERS/INVERTERS
The Power Conditioners / Inverters of the SPV power plants must conform to the latest edition of IEC /
equivalent Indian Standards as specified below:
Standard Description
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
137
6-26 Section 6: Employer’s Requirements
IEC 62109-1Ed. 1 Safety of power converters for use in photovoltaicpower systems -Part 1:General
requirements
IEC 62109-2Ed. 1 Safety of power converters for use in photovoltaic power systems-Part 2 : Particular
requirements for inverters
As per the Solar Photo Voltaic Systems, Devices and Components Goods (Requirements for Compulsory
Registration) Order, 2017, PV Modules and PCU used in the solar power Projects shall conform to the Standards
Specified as per below and bear the Standard Mark as notified by the Bureau of Indian Standards:
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
138
Section 6: Employer’s Requirements 6-27
2 Firmware support: 15 days within Date of written @ Rs. 20,000/- per instance
Bidder shall provide receipt of request by plus Rs. 5,000/- per 24 hrs or
respective firmware in equipment. System part thereof for any further
case of a malfunctioning Integrator delay.
or a feature request at no
extra cost to CESL.
3 Availability of Bidder must Through report @ Rs. 2,000/- for every hour of
equipment ensure that the generate downtime or part thereof. .
in working condition system must be equipment
online for 100% and/or CESL’s
of the time. portal d by the
(Power failure
related downtime
is excluded)
4 Data Collection Bidder Must Report to be @ Rs. 2,000/- for every day of
ensure that all submitted to delay or part thereof.
data generated CESL in MIS
from the system format on 1st of
is collected and Every Month
submitted to without Fail. Or
CESL in MIS maximum in 3
format on days.
monthly basis.
5 Periodic Maintenance Bidder must Report of @ Rs. 2,000/- for every week’s
ensure that all periodic of delay or part thereof.
periodic maintenance to
maintenance is be submitted to
carried out CESL
The Successful Bidder shall ensure that a technician is locally available at all the times during the
Project period for handling minor & major complaints and all type of other services from the site for the
Solar Carport. This is a mandatory requirement.
The bidder needs to provide repair and maintenance services to CESL through the contract period as a
part of the Contract. The bidder to ensure supplied equipment installed at site with all spares,
consumables, parts (electrical, electronics, etc.) complete in all respect with periodical Maintenance, for
quarterly cleaning of all indoor & outdoor Electrical Equipment, periodical regular and preventive
maintenance of all equipment and attending any break down calls as per the time defined in the SLA.
In case of any delay from the successful bidder for meeting the SLA and any penalty amount becomes
due as per the penalty clauses above, CESL reserves the right to raise a demand for which the succesful
bidder will have to make payment to CESL within 15 days of raising the demand. In case of any delay
CESL has the right to charge interest @1.5% per month or part thereof on the amount due from the
successful bidder.
In case the demand is not paid within a period of two months CESL has the right to recover the same
by encashing the PBG as stated in PBG clauses. Penalties shall be recovered from the performance
security submitted by the successful bidder without any maximum limit.
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
139
6-28 Section 6: Employer’s Requirements
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
140
Section 6: Employer’s Requirements 6-29
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
141
142
Section 6: Employer’s Requirements 6-31
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
143
6-32 Section 6: Employer’s Requirements
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
144
Section 6: Employer’s Requirements 6-33
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
145
6-34 Section 6: Employer’s Requirements
4. Drawings
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
146
Section 6: Employer’s Requirements 6-35
5. Supplementary Information
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
147
6-36 Section 6: Employer’s Requirements
6. Certificates
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
148
Section 6: Employer’s Requirements 6-37
Date: ....................................
Certificate No.: ....................................
Pursuant to GCC Clause 24 (Completion of the Facilities) of the General Conditions of the Contract
entered into between yourselves and the Employer dated [. . . . .insert date. . . . . ], relating to the [. . .
.brief description of the Facilities . . . .], we hereby notify you that the following part(s) of the Facilities
was (were) complete on the date specified below, and that, in accordance with the terms of the
Contract, the Employer hereby takes over the said part(s) of the Facilities, together with the
responsibility for care and custody and the risk of loss thereof on the date mentioned below.
However, you are required to complete the outstanding items listed in the attachment hereto as soon
as practicable.
This letter does not relieve you of your obligation to complete the execution of the Facilities in
accordance with the Contract nor of your obligations during the Defect Liability Period.
[. . . .Signature . . . .]
Project Manager
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
149
6-38 Section 6: Employer’s Requirements
Date: ....................................
Certificate No.: ....................................
Pursuant to GCC Subclause 25.3 (Operational Acceptance) of the General Conditions of the Contract
entered into between yourselves and the Employer dated [. . .date. . .], relating to the [. . .brief
description of the facilities. . .], we hereby notify you that the Functional Guarantees of the following
part(s) of the Facilities were satisfactorily attained on the date specified below.
This letter does not relieve you of your obligation to complete the execution of the Facilities in
accordance with the Contract nor of your obligations during the Defect Liability Period.
[. . . .Signature . . . .]
Project Manager
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
150
Section 6: Employer’s Requirements 6-39
7. Change Orders
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
151
6-40 Section 6: Employer’s Requirements
7.1.1 General
This section provides samples of procedures and forms for implementing changes in the
Facilities during the performance of the Contract in accordance with GCC Clause 39 (Change
in the Facilities) of the General Conditions.
The Contractor shall keep an up-to-date Change Order Log to show the current status of
Requests for Change and Changes authorized or pending. Entries of the Changes in the
Change Order Log shall be made to ensure that the log is up-to-date. The Contractor shall
attach a copy of the current Change Order Log in the monthly progress report to be submitted
to the Employer.
(1) Request for Change as referred to in GCC Clause 39 shall be serially numbered CR-X-
nnn.
(2) Estimate for Change Proposal as referred to in GCC Clause 39 shall be serially
numbered CN-X-nnn.
(3) Acceptance of Estimate as referred to in GCC Clause 39 shall be serially numbered CA-
X-nnn.
(4) Change Proposal as referred to in GCC Clause 39 shall be serially numbered CP-X-nnn.
(5) Change Order as referred to in GCC Clause 39 shall be serially numbered CO-X-nnn.
Note:
(a) Requests for Change issued from the Employer’s Home Office and the Site
representatives of the Employer shall have the following respective references:
(b) The above number “nnn” is the same for Request for Change, Estimate for Change
Proposal, Acceptance of Estimate, Change Proposal and Change Order.
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
152
Section 6: Employer’s Requirements 6-41
[ Employer’s letterhead ]
With reference to the captioned Contract, you are requested to prepare and submit a Change Proposal
for the Change noted below in accordance with the following instructions within [ number ] days of the
date of this letter [or on or before ( date )].
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
153
6-42 Section 6: Employer’s Requirements
[ Name of signatory ]
[ Title of signatory ]
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
154
Section 6: Employer’s Requirements 6-43
[ Contractor’s letterhead ]
With reference to your Request for Change Proposal, we are pleased to notify you of the approximate
cost to prepare the below-referenced Change Proposal in accordance with GCC Subclause 39.2.1 of
the General Conditions. We acknowledge that your agreement to the cost of preparing the Change
Proposal, in accordance with GCC Subclause 39.2.2, is required before estimating the cost for change
work.
[ Contractor's name ]
[ Signature ]
[ Name of signatory ]
[ Title of signatory ]
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
155
6-44 Section 6: Employer’s Requirements
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
156
Section 6: Employer’s Requirements 6-45
[ Employer’s letterhead ]
We hereby accept your Estimate for Change Proposal and agree that you should proceed with the
preparation of the Change Proposal.
[ Employer’s name ]
[ Signature ]
[ Name of signatory ]
[ Title of signatory ]
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
157
6-46 Section 6: Employer’s Requirements
[ Contractor’s letterhead ]
In response to your Request for Change Proposal No. [Number], we hereby submit our proposal as
follows:
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
158
Section 6: Employer’s Requirements 6-47
Cost to prepare Estimate for Change Proposal [ Amount payable if Change is not
accepted ]
[ Contractor's name ]
[ Signature ]
[ Name of signatory ]
[ Title of signatory ]
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
159
6-48 Section 6: Employer’s Requirements
[ Employer’s letterhead ]
We approve the Change Order for the work specified in the Change Proposal (No. [ number ]), and
agree to adjust the Contract Price, Time for Completion, and/or other conditions of the Contract in
accordance with GCC Clause 39 of the General Conditions.
5. Authorized Price:
Ref. No.: [ Number ] Date: [ Date ]
Foreign currency portion [ Amount ] plus Local currency portion [ Amount ]
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
160
Section 6: Employer’s Requirements 6-49
[ Employer’s letterhead ]
We instruct you to carry out the work in the Change Order detailed below in accordance with GCC
Clause 39 of the General Conditions.
5. Facilities and/or Item No. of equipment related to the requested Change: [ Facilities ]
[ Employer’s name ]
[ Signature ]
[ Name of signatory ]
[ Title of signatory ]
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
161
6-50 Section 6: Employer’s Requirements
[ Contractor’s letterhead ]
We hereby propose that the work mentioned below be treated as a Change in the Facilities.
8. Appendix:
[ Contractor's name ]
[ Signature ]
[ Name of signatory ]
[ Title of signatory ]
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
162
Section 6: Employer’s Requirements 6-51
8. Personnel Requirements
Using Form PER - 1 and PER - 2 in Section 4 (Bidding Forms), the Bidder must demonstrate that it has
personnel who meet the following requirements:
Using Form EXP-6 in Section 4 (Bidding Forms), the Bidder must demonstrate that it has EHS personnel
who meet the following requirements:
Key Personnel as determined by the EMP and other safeguard management plans
Minimum
Minimum years of
Item Relevant academic time on-
Position/specialization relevant work
No. qualifications site
experience
(%FTE)
1
2
3
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
163
6-52 Section 6: Employer’s Requirements
9. Equipment Requirements
Using Form EQU in Section 4 (Bidding Forms), the Bidder must demonstrate that it has the key equipment
listed below:
Bidding Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along
with Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
164
Section 7: General Conditions of Contract 7-1
Table of Clauses
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
165
7-2 Section 7: General Conditions of Contract
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
166
Section 7: General Conditions of Contract 7-3
1. Definitions 1.1 The following words and expressions shall have the meanings hereby
assigned them:
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
167
7-4 Section 7: General Conditions of Contract
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
168
Section 7: General Conditions of Contract 7-5
3. Interpretation 3.1 In the Contract, except where the context requires otherwise,
(a) words indicating one gender include all genders;
(b) words indicating the singular also include the plural and words
indicating the plural also include the singular;
(c) provisions including the word “agree,” “agreed,” or “agreement”
require the agreement to be record in writing;
(d) the word “tender” is synonymous with “bid,” “tenderer” with
“Bidder,” and “tender documents” with “Bidding Documents;” and
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
169
7-6 Section 7: General Conditions of Contract
The marginal words and other headings shall not be taken into
consideration in the interpretation of these Conditions.
3.2 Incoterms
3.4 Amendment
No amendment or other variation of the Contract shall be effective
unless it is in writing, is dated, expressly refers to the Contract, and is
signed by a duly authorized representative of each party hereto.
3.6 Non-Waiver
3.6.1 Subject to GCC Subclause 3.6.2 below, no relaxation,
forbearance, delay, or indulgence by either party in enforcing
any of the terms and conditions of the Contract or the granting
of time by either party to the other shall prejudice, affect, or
restrict the rights of that party under the Contract, nor shall any
waiver by either party of any breach of Contract operate as
waiver of any subsequent or continuing breach of Contract.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
170
Section 7: General Conditions of Contract 7-7
3.7 Severability
If any provision or condition of the Contract is prohibited or rendered
invalid or unenforceable, such prohibition, invalidity, or unenforceability
shall not affect the validity or enforceability of any other provisions and
conditions of the Contract.
4. Communications 4.1 Wherever these Conditions provide for the giving or issuing of
approvals, certificates, consents, determinations, notices, requests,
and discharges, these communications shall be
(a) in writing and delivered against receipt; and
(b) delivered, sent, or transmitted to the address for the recipient’s
communications as stated in the Contract Agreement.
When a certificate is issued to a Party, the certifier shall send a copy to
the other Party. When a notice is issued to a Party, by the other Party or
the Project Manager, a copy shall be sent to the Project Manager or the
other Party, as the case may be.
5. Law and 5.1 The Contract shall be governed by and interpreted in accordance with
Language laws of the country specified in the SCC.
5.2 The ruling language of the Contract shall be that stated in the SCC.
5.3 The language for communications shall be the ruling language unless
otherwise stated in the SCC.
6. Fraud and
6.1 ADB requires Borrowers (including beneficiaries of ADB-financed
Corruption
activity) and their personnel, as well as firms and individuals
participating in an ADB-financed activity, including but not limited to,
Bidders, Suppliers, and Contractors, agents, subcontractors,
subconsultants, service providers, subsuppliers, manufacturers
(including their respective officers, directors, employees and personnel)
under ADB-financed contracts to observe the highest standard of ethics
during the procurement and execution of such contracts in accordance
with ADB’s Anticorruption Policy (1998, as amended from time to time).
In pursuance of this policy, ADB
(a) defines, for the purposes of this provision, the terms set forth
below as follows:
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
171
7-8 Section 7: General Conditions of Contract
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
172
Section 7: General Conditions of Contract 7-9
1
Whether as a Contractor, Subcontractor, Consultant, Manufacturer or Supplier, or Service Provider; or in any other capacity
(different names are used depending on the particular Bidding Document).
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
173
7-10 Section 7: General Conditions of Contract
7. Scope of 7.1 Unless otherwise expressly limited in the Employer’s Requirements, the
Facilities Contractor’s obligations cover the provision of all Plant and the
performance of all Installation Services required for the design, the
manufacture (including procurement, quality assurance, construction,
installation, associated civil works, pre-commissioning and delivery) of
the Plant and the installation, completion, and commissioning of the
Facilities in accordance with the plans, procedures, specifications,
drawings, codes, and any other documents as specified in the section
Employer’s Requirements. Such specifications include, but are not
limited to, the provision of supervision and engineering services; the
supply of labor, materials, equipment, spare parts (as specified in GCC
Subclause 7.3 below) and accessories; Contractor’s Equipment;
construction utilities and supplies; temporary materials, structures, and
facilities; transportation (including, without limitation, unloading and
hauling to, from and at the Site); and storage, except for those supplies,
works, and services that will be provided or performed by the Employer,
as set forth in the Appendix (Scope of Works and Supply by the
Employer) to the Contract Agreement.
2
The undertaking also applies during the period of performance of the contract.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
174
Section 7: General Conditions of Contract 7-11
8. Time for 8.1 The Contractor shall commence work on the Facilities within the period
Commencement specified in the SCC and without prejudice to GCC Subclause 26.2
and Completion hereof, the Contractor shall thereafter proceed with the Facilities in
accordance with the time schedule specified in the Appendix 4 (Time
Schedule) to the Contract Agreement.
8.2 The Contractor shall attain Completion of the Facilities or of a part where
a separate time for Completion of such part is specified in the Contract,
within the time stated in the SCC or within such extended time to which
the Contractor shall be entitled under GCC Clause 40 hereof.
9. Contractor’s 9.1 The Contractor shall design, manufacture, including associated
Responsibilities purchases and/or subcontracting, install, and complete the Facilities in
accordance with the Contract. When completed, the Facilities should be
fit for the purposes for which they are intended as defined in the
Contract.
9.2 The Contractor confirms that it has entered into this Contract on the
basis of a proper examination of the data relating to the Facilities,
including any data as to boring tests provided by the Employer, and on
the basis of information that the Contractor could have obtained from a
visual inspection of the Site if access thereto was available and of other
data readily available to it relating to the Facilities as of the date 28 days
prior to bid submission. The Contractor acknowledges that any failure to
acquaint itself with all such data and information shall not relieve its
responsibility for properly estimating the difficulty or cost of successfully
performing the Facilities.
9.3 The Contractor shall acquire and pay for all permits, approvals, and/or
licenses from all local, state, or national government authorities or public
service undertakings in the country where the Site is located, which such
authorities or undertakings require the Contractor to obtain in its name
and which are necessary for the performance of the Contract, including,
without limitation, visas for the Contractor’s and Subcontractor’s
personnel and entry permits for all imported Contractor’s Equipment.
The Contractor shall acquire all other permits, approvals, and/or
licenses that are not the responsibility of the Employer under GCC
Subclause 10.3 hereof and that are necessary for the performance of
the Contract.
9.4 The Contractor shall comply with all laws in force in the country where
the Facilities are to be implemented. The laws will include all local, state,
national, or other laws that affect the performance of the Contract and
bind upon the Contractor. The Contractor shall indemnify and hold
harmless the Employer from and against any and all liabilities, damages,
claims, fines, penalties, and expenses of whatever nature arising or
resulting from the violation of such laws by the Contractor or its
personnel, including the Subcontractors and their personnel, but without
prejudice to GCC Subclause 10.1 hereof.
9.5 Any plant and services that will be incorporated in or be required for the
Facilities and other supplies shall have their origin as specified under
GCC Clause 1 (Country of Origin). Any Subcontractors retained by the
Contractor shall be from a country as specified in GCC Clause 1
(Country of Origin).
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
175
7-12 Section 7: General Conditions of Contract
9.6 The Contractor shall permit ADB or its representatives to inspect the
Contractor’s site, assets, accounts and records, and other documents
relating to the bid submission and contract performance of the
Contractor and to have them audited by auditors appointed by ADB, if
so required by ADB.
10. Employer’s 10.1 All information and/or data to be supplied by the Employer as described
Responsibilities in the Appendix (Scope of Works and Supply by the Employer) to the
Contract Agreement shall be deemed to be accurate, except when the
Employer expressly states otherwise.
10.2 The Employer shall be responsible for acquiring and providing legal and
physical possession of the Site and access thereto, and for providing
possession of and access to all other areas reasonably required for the
proper execution of the Contract, including all requisite rights of way, as
specified in the Appendix (Scope of Works and Supply by the Employer)
to the Contract Agreement. The Employer shall give full possession of
and accord all rights of access thereto on or before the date(s) specified
in that Appendix.
10.3 The Employer shall acquire and pay for all permits, approvals, and/or
licenses from all local, state, or national government authorities, or
public service undertakings in the country where the Site is located
which (a) such authorities or undertakings require the Employer to
obtain in the Employer’s name, (b) are necessary for the execution of
the Contract, including those required for the performance by both the
Contractor and the Employer of their respective obligations under the
Contract, and (c) are specified in the Appendix (Scope of Works and
Supply by the Employer) to the Contract Agreement.
10.4 If requested by the Contractor, the Employer shall use its best
endeavors to assist the Contractor in obtaining in a timely and
expeditious manner all permits, approvals, and/or licenses necessary
for the execution of the Contract from all local, state, or national
government authorities, or public service undertakings that such
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
176
Section 7: General Conditions of Contract 7-13
10.6 The Employer shall be responsible for the continued operation of the
Facilities after Completion, in accordance with GCC Subclause 24.8,
and shall be responsible for facilitating the Guarantee Test(s) for the
Facilities, in accordance with GCC Subclause 25.2.
10.7 All costs and expenses involved in the performance of the obligations
under this GCC Clause 10 shall be the responsibility of the Employer,
except those incurred by the Contractor with respect to the performance
of Guarantee Tests, in accordance with GCC Subclause 25.2.
10.8 In the event that the Employer shall be in breach of any of his obligations
imposed by the Contract, then the additional cost reasonably incurred
by the Contractor in consequence thereof shall be added to the Contract
Price.
C. Payment
11. Contract Price 11.1 The Contract Price shall be as specified in Article 2 (Contract Price and
Terms of Payment) of the Contract Agreement.
11.2 Unless an adjustment clause is provided for in the SCC, the Contract
Price shall be a firm lump sum not subject to any alteration, except in the
event of a Change in the Facilities or as otherwise provided in the
Contract.
11.3 Subject to GCC Subclauses 9.2, 10.1, and 35 hereof, the Contractor
shall be deemed to have satisfied itself as to the correctness and
sufficiency of the Contract Price, which shall, except as otherwise
provided for in the Contract, cover all its obligations under the Contract.
12. Terms of 12.1 The Contract Price shall be paid as specified in Article 2 (Contract Price
Payment and Terms of Payment) of the Contract Agreement and in the Appendix
(Terms and Procedures of Payment) to the Contract Agreement, which
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
177
7-14 Section 7: General Conditions of Contract
12.3 In the event that the Employer fails to make any payment by its
respective due date or within the period set forth in the Contract, the
Employer shall pay to the Contractor interest on the amount of such
delayed payment at the rate(s) shown in the Appendix (Terms and
Procedures of Payment) to the Contract Agreement for the period of
delay until payment has been made in full, whether before or after
judgment or arbitrage award.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
178
Section 7: General Conditions of Contract 7-15
Security shall become null and void, or shall be reduced pro rata
to the Contract Price of a part of the Facilities for which a
separate Time for Completion is provided, 540 days after
Completion of the Facilities or 365 days after Operational
Acceptance of the Facilities, whichever occurs first; provided,
however, that if the Defects Liability Period has been extended
on any part of the Facilities pursuant to GCC Subclause 27.8
hereof, the Contractor shall issue an additional security in an
amount proportionate to the Contract Price of that part. The
security shall be returned to the Contractor immediately after its
expiration, provided, however, that if the Contractor, pursuant to
GCC Subclause 27.10, is liable for an extended defect liability
obligation, the performance security shall be extended for the
period and up to the amount specified in the SCC.
14. Taxes and 14.1 Except as otherwise specifically provided in the Contract, the Contractor
Duties shall bear and pay all taxes, duties, levies, and charges assessed on the
Contractor, its Subcontractors, or their employees by all municipal, state,
or national government authorities in connection with the Facilities in and
outside of the country where the Site is located.
14.2 Notwithstanding GCC Subclause 14.1 above, the Employer shall bear
and promptly pay all customs and import duties as well as other local
taxes like, e.g., a value-added tax (VAT), imposed by the law of the
country where the Site is located on the Plant specified in Price Schedule
No. 1 and that are to be incorporated into the Facilities.
14.4 For the purpose of the Contract, it is agreed that the Contract Price
specified in Article 2 (Contract Price and Terms of Payment) of the
Contract Agreement is based on the taxes, duties, levies, and charges
prevailing at the date 28 days prior to the date of bid submission in the
country where the Site is located (hereinafter called “Tax” in this GCC
Subclause 14.4). If any rates of Tax are increased or decreased, a new
Tax is introduced, an existing Tax is abolished, or any change in
interpretation or application of any Tax occurs in the course of the
performance of Contract, which was or will be assessed on the
Contractor, Subcontractors, or their employees in connection with
performance of the Contract, an equitable adjustment of the Contract
Price shall be made to fully take into account any such change by
addition to the Contract Price or deduction therefrom, as the case may
be, in accordance with GCC Clause 36 hereof.
D. Intellectual Property
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
179
7-16 Section 7: General Conditions of Contract
15. License/Use of 15.1 For the operation and maintenance of the Plant, the Contractor hereby
Technical grants a non-exclusive and nontransferable license (without the right to
Information sublicense) to the Employer under the patents, utility models, or other
industrial property rights owned by the Contractor or by a third party
from whom the Contractor has received the right to grant licenses
thereunder, and shall also grant to the Employer a nonexclusive and
nontransferable right (without the right to sublicense) to use the know-
how and other technical information disclosed to the Employer under
the Contract. Nothing contained herein shall be construed as
transferring ownership of any patent, utility model, trademark, design,
copyright, know-how, or other intellectual property right from the
Contractor or any third party to the Employer.
15.2 The copyright in all drawings, documents, and other materials containing
data and information furnished to the Employer by the Contractor herein
shall remain vested in the Contractor or, if they are furnished to the
Employer directly or through the Contractor by any third party, including
suppliers of materials, the copyright in such materials shall remain
vested in such third party.
16. Confidential 16.1 The Employer and the Contractor shall keep confidential and shall not,
Information without the written consent of the other party hereto, divulge to any third
party any documents, data or other information furnished directly or
indirectly by the other party hereto in connection with the Contract,
whether such information has been furnished prior to, during, or following
termination of the Contract. Notwithstanding the above, the Contractor
may furnish to its Subcontractor(s) such documents, data, and other
information it receives from the Employer to the extent required for the
Subcontractor(s) to perform its work under the Contract, in which event
the Contractor shall obtain from such Subcontractor(s) an undertaking of
confidentiality similar to that imposed on the Contractor under this GCC
Clause 16.
16.2 The Employer shall not use such documents, data, and other information
received from the Contractor for any purpose other than the operation
and maintenance of the Facilities. Similarly, the Contractor shall not use
such documents, data, and other information received from the Employer
for any purpose other than the design, procurement of Plant,
construction, or such other work and services as are required for the
performance of the Contract.
16.3 The obligation of a party under GCC Subclauses 16.1 and 16.2 above,
however, shall not apply to that information, which
(a) now or hereafter enters the public domain through no fault of that
party;
(b) can be proven to have been possessed by that party at the time of
disclosure and which was not previously obtained, directly or
indirectly, from the other party hereto; and
16.4 The above provisions of this GCC Clause 16 shall not in any way modify
any undertaking of confidentiality given by either of the parties hereto
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
180
Section 7: General Conditions of Contract 7-17
prior to the date of the Contract in respect of the Facilities or any part
thereof.
16.5 The provisions of this GCC Clause 16 shall survive termination, for
whatever reason, of the Contract.
17.2.2 The Contractor’s Representative shall represent and act for the
Contractor at all times during the performance of the Contract and
shall give to the Project Manager all the Contractor’s notices,
instructions, information, and all other communications under the
Contract.
All notices, instructions, information, and all other
communications given by the Employer or the Project Manager
to the Contractor under the Contract shall be given to the
Contractor’s Representative or, in its absence, its deputy, except
as herein otherwise provided.
The Contractor shall not revoke the appointment of the
Contractor’s Representative without the Employer’s prior written
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
181
7-18 Section 7: General Conditions of Contract
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
182
Section 7: General Conditions of Contract 7-19
18.5 Procedures
The Contract shall be executed in accordance with the Contract
Documents including the procedures given in the Forms and Procedures
of the Employer’s Requirements.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
183
7-20 Section 7: General Conditions of Contract
The Contractor may execute the Contract in accordance with its own
standard project execution plans and procedures to the extent that they
do not conflict with the provisions contained in the Contract.
19.Subcontracting 19.1 The Appendix 5 (List of Major Items of Plant and Services and List of
Approved Subcontractors) to the Contract Agreement specifies major
items of plant and services and a list of approved Subcontractors
against each item, including manufacturers. Insofar as no
Subcontractors are listed against any such item, the Contractor shall
prepare a list of Subcontractors for such item for inclusion in such list.
The Contractor may from time to time propose any addition to or
deletion from any such list. The Contractor shall submit any such list or
any modification thereto to the Employer for its approval in sufficient
time so as not to impede the progress of work on the Facilities. Such
approval by the Employer for any of the Subcontractors shall not relieve
the Contractor from any of its obligations, duties, or responsibilities
under the Contract.
19.2 The Contractor shall select and employ its Subcontractors for such
major items from those listed in the lists referred to in GCC Subclause
19.1.
19.3 For items or parts of the Facilities not specified in the Appendix (List of
Major Items of Plant and Services and List of Approved Subcontractors
for Major Items) to the Contract Agreement, the Contractor may employ
such Subcontractors as it may select, at its discretion.
19.4 Each subcontract shall include provisions which would entitle the
Employer to require the sub-contract to be assigned to the Employer
under GCC 19.5 (if and when applicable), or in event of termination by
the Employer under GCC 42.2.
19.5 If a Sub-contractor's obligations extend beyond the expiry date of the
relevant Defects Liability Period and the Project Manager, prior to that
date, instructs the Contractor to assign the benefits of such obligations
to the Employer, then the Contractor shall do so.
20. Design and 20.1 Specifications and Drawings
Engineering 20.1.1 The Contractor shall execute the basic and detailed design and
the engineering work in compliance with the provisions of the
Contract, or where not so specified, in accordance with good
engineering practice.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
184
Section 7: General Conditions of Contract 7-21
If the Project Manager fails to take such action within the said 14
days, then the said document shall be deemed to have been
approved by the Project Manager.
20.3.3 The Project Manager shall not disapprove any document, except
on the grounds that the document does not comply with the
Contract or that it is contrary to good engineering practice. If the
Project Manager disapproves a document, he shall specify the
reasons for his decision.
20.3.5 If any dispute or difference occurs between the Employer and the
Contractor in connection with or arising out of the disapproval by
the Project Manager of any document and/or any modification(s)
thereto that cannot be settled between the parties within a
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
185
7-22 Section 7: General Conditions of Contract
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
186
Section 7: General Conditions of Contract 7-23
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
187
7-24 Section 7: General Conditions of Contract
22.1.1 Benchmark
(a) The Contractor shall be responsible for the true and proper
setting-out of the Facilities in relation to bench marks,
reference marks, and lines provided to it in writing by or on
behalf of the Employer.
22.2 Labor
22.2.1 Engagement of Staff and Labor
(a) Except as otherwise stated in the Specification, the
Contractor shall make arrangements for the engagement of
all staff and labor, local or otherwise, and for their payment,
housing, feeding, and transport.
(b) The Contractor shall provide and employ on the Site in the
installation of the Facilities such skilled, semi-skilled, and
unskilled labor as is necessary for the proper and timely
execution of the Contract. The Contractor is encouraged to
use local labor that has the necessary skills.
(d) The Contractor shall at its own expense provide the means
of repatriation to all of its and its Subcontractor’s personnel
employed on the Contract at the Site to the place where
they were recruited or to their domicile. It shall also provide
suitable temporary maintenance of all such persons from
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
188
Section 7: General Conditions of Contract 7-25
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
189
7-26 Section 7: General Conditions of Contract
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
190
Section 7: General Conditions of Contract 7-27
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
191
7-28 Section 7: General Conditions of Contract
22.3.3 The Employer will, if requested, use its best endeavors to assist
the Contractor in obtaining any local, state or national
government permission required by the Contractor for the
export of the Contractor’s Equipment imported by the
Contractor for use in the execution of the Contract that is no
longer required for the execution of the Contract.
Such Site regulations shall include, but shall not be limited to, rules in
respect of security, safety of the Facilities, gate control, sanitation,
medical care, and fire prevention.
22.5.2 If the Contractor, upon written request from the Employer or the
Project Manager, makes available to other contractors any
roads or ways the maintenance for which the Contractor is
responsible, permits the use by such other contractors of the
Contractor’s Equipment, or provides any other service of
whatsoever nature for such other contractors, the Employer
shall fully compensate the Contractor for any loss or damage
caused or occasioned by such other contractors in respect of
any such use or service, and shall pay to the Contractor
reasonable remuneration for the use of such equipment or the
provision of such services.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
192
Section 7: General Conditions of Contract 7-29
22.5.4 The Contractor shall notify the Project Manager promptly of any
defects in the other Contractors’ work that come to its notice,
and that could affect the Contractor’s work. The Project
Manager shall determine the corrective measures, if any,
required to rectify the situation after inspection of the Facilities.
Decisions made by the Project Manager shall be binding on the
Contractor.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
193
7-30 Section 7: General Conditions of Contract
owners and occupiers of adjacent property and for the safety of the
public.
23. Test and 23.1 The Contractor shall at its own expense carry out at the place of
Inspection manufacture and/or on the Site all such tests and/or inspections of the
Plant and any part of the Facilities as are specified in the Contract.
23.3 Whenever the Contractor is ready to carry out any such test and/or
inspection, the Contractor shall give a reasonable advance notice of
such test and/or inspection and of the place and time thereof to the
Project Manager. The Contractor shall obtain from any relevant third
party or manufacturer any necessary permission or consent to enable
the Employer and the Project Manager or their designated
representatives to attend the test and/or inspection.
23.4 The Contractor shall provide the Project Manager with a certified report
of the results of any such test and/or inspection.
23.5 The Project Manager may require the Contractor to carry out any test
and/or inspection not required by the Contract, provided that the
Contractor’s reasonable costs and expenses incurred in the carrying out
of such test and/or inspection shall be added to the Contract Price.
Further, if such test and/or inspection impedes the progress of work on
the Facilities and/or the Contractor’s performance of its other obligations
under the Contract, due allowance will be made in respect of the Time
for Completion and the other obligations so affected.
23.6 If any Plant or any part of the Facilities fails to pass any test and/or
inspection, the Contractor shall either rectify or replace such Plant or part
of the Facilities and shall repeat the test and/or inspection upon giving a
notice under GCC Subclause 23.3.
23.7 If any dispute or difference of opinion shall arise between the parties in
connection with or arising out of the test and/or inspection of the Plant or
part of the Facilities that cannot be settled between the parties within a
reasonable period of time, it may be referred to an Dispute Board for
determination in accordance with GCC Subclause 45.3.
23.8 The Contractor shall afford the Employer and the Project Manager, at
the Employer’s expense, access at any reasonable time to any place
where the Plant are being manufactured or the Facilities are being
installed, in order to inspect the progress and the manner of manufacture
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
194
Section 7: General Conditions of Contract 7-31
23.9 The Contractor agrees that neither the execution of a test and/or
inspection of Plant or any part of the Facilities, nor the attendance by the
Employer or the Project Manager, nor the issue of any test certificate
pursuant to GCC Subclause 23.4, shall release the Contractor from any
other responsibilities under the Contract.
24. Completion of 24.1 As soon as the Facilities or any part thereof has, in the opinion of the
the Facilities Contractor, been completed operationally and structurally and put in a
tight and clean condition as specified in the Employer’s Requirements,
excluding minor items not materially affecting the operation or safety of
the Facilities, the Contractor shall so notify the Employer in writing.
24.2 Within 7 days after receipt of the notice from the Contractor under GCC
Subclause 24.1, the Employer shall supply the operating and
maintenance personnel specified in the Appendix (Scope of Works and
Supply by the Employer) to the Contract Agreement for Pre-
commissioning of the Facilities or any part thereof.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
195
7-32 Section 7: General Conditions of Contract
24.5 The Project Manager shall, within 14 days after receipt of the
Contractor’s notice under GCC Subclause 24.4, either issue a
Completion Certificate in the form specified in the Employer’s
Requirements (Forms and Procedures), stating that the Facilities or that
part thereof have reached Completion as of the date of the Contractor’s
notice under GCC Subclause 24.4, or notify the Contractor in writing of
any defects and/or deficiencies.
24.6 If the Project Manager fails to issue the Completion Certificate and fails
to inform the Contractor of any defects and/or deficiencies within 14 days
after receipt of the Contractor’s notice under GCC Subclause 24.4 or
within 7 days after receipt of the Contractor’s repeated notice under GCC
Subclause 24.5, or if the Employer makes use of the Facilities or part
thereof, then the Facilities or that part thereof shall be deemed to have
reached Completion as of the date of the Contractor’s notice or repeated
notice, or as of the Employer’s use of the Facilities, as the case may be.
24.7 As soon as possible after Completion, the Contractor shall complete all
outstanding minor items so that the Facilities are fully in accordance with
the requirements of the Contract, failing which the Employer will
undertake such completion and deduct the costs thereof from any
monies owing to the Contractor.
24.8 Upon Completion, the Employer shall be responsible for the care and
custody of the Facilities or the relevant part thereof, together with the risk
of loss or damage thereto, and shall thereafter take over the Facilities or
the relevant part thereof.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
196
Section 7: General Conditions of Contract 7-33
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
197
7-34 Section 7: General Conditions of Contract
25.3.2 At any time after any of the events set out in GCC Subclause
25.3.1 have occurred, the Contractor may give a notice to the
Project Manager requesting the issue of an Operational
Acceptance Certificate in the form provided in the Employer’s
Requirements (Forms and Procedures) in respect of the Facilities
or the part thereof specified in such notice as of the date of such
notice.
25.3.3 The Project Manager shall, after consultation with the Employer,
and within 7 days after receipt of the Contractor’s notice, issue an
Operational Acceptance Certificate.
25.3.4 If within 7 days after receipt of the Contractor’s notice, the Project
Manager fails to issue the Operational Acceptance Certificate or
fails to inform the Contractor in writing of the justifiable reasons
why the Project Manager has not issued the Operational
Acceptance Certificate, the Facilities or the relevant part thereof
shall be deemed to have been accepted as of the date of the
Contractor’s said notice.
25.4 Partial Acceptance
25.4.1 If the Contract specifies that Completion and Commissioning
shall be carried out in respect of parts of the Facilities, the
provisions relating to Completion and Commissioning including
the Guarantee Test shall apply to each such part of the Facilities
individually, and the Operational Acceptance Certificate shall be
issued accordingly for each such part of the Facilities.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
198
Section 7: General Conditions of Contract 7-35
25.5.4 When the Contractor is notified by the Project Manager that the
plant is ready for Pre-commissioning, the Contractor shall
proceed without delay in performing all the specified activities
and obligations under the contract.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
199
7-36 Section 7: General Conditions of Contract
26.2 If the Contractor fails to attain Completion of the Facilities or any part
thereof within the Time for Completion or any extension thereof under
GCC Clause 40, the Contractor shall pay to the Employer liquidated
damages in the amount specified in the SCC as a percentage rate of the
Contract Price or the relevant part thereof. The aggregate amount of
such liquidated damages shall in no event exceed the amount specified
as “Maximum” in the SCC as a percentage rate of the Contract Price.
Once the “Maximum” is reached, the Employer may consider
termination of the Contract, pursuant to GCC Subclause 42.2.2.
Save for liquidated damages payable under this GCC Subclause 26.2,
the failure by the Contractor to attain any milestone or other act, matter
or thing by any date specified in the Appendix (Time Schedule) to the
Contract Agreement and/or other program of work prepared pursuant to
GCC Subclause 18.2 shall not render the Contractor liable for any loss
or damage thereby suffered by the Employer.
26.3 If the Contractor attains Completion of the Facilities or any part thereof
before the Time for Completion or any extension thereof under GCC
Clause 40, the Employer shall pay to the Contractor a bonus in the
amount specified in the SCC. The aggregate amount of such bonus
shall in no event exceed the amount specified as “Maximum” in the SCC.
27. Defect Liability 27.1 The Contractor warrants that the Facilities or any part thereof shall be
free from defects in the design, engineering, materials, and
workmanship of the Plant supplied and of the work executed.
27.2 The Defect Liability Period shall be 540 days from the date of
Completion of the Facilities (or any part thereof) or 1 year from the date
of Operational Acceptance of the Facilities (or any part thereof),
whichever first occurs, unless specified otherwise in the SCC pursuant
to GCC Subclause 27.10.
If during the Defect Liability Period any defect should be found in the
design, engineering, materials, and workmanship of the Plant supplied
or of the work executed by the Contractor, the Contractor shall promptly,
in consultation and agreement with the Employer regarding appropriate
remedying of the defects, and at its cost, repair, replace, or otherwise
make good as the Contractor shall determine at its discretion, such
defect as well as any damage to the Facilities caused by such defect.
The Contractor shall not be responsible for the repair, replacement, or
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
200
Section 7: General Conditions of Contract 7-37
making good of any defect or of any damage to the Facilities arising out
of or resulting from any of the following causes:
(a) improper operation or maintenance of the Facilities by the
Employer,
(b) operation of the Facilities outside specifications provided in the
Contract, or
(c) normal wear and tear.
27.3 The Contractor’s obligations under this GCC Clause 27 shall not apply
to:
(a) any materials that are supplied by the Employer under GCC
Subclause 21.2, are normally consumed in operation, or have a
normal life shorter than the Defect Liability Period stated herein;
(b) any designs, specifications or other data designed, supplied, or
specified by or on behalf of the Employer or any matters for which
the Contractor has disclaimed responsibility herein; or
(c) any other materials supplied or any other work executed by or on
behalf of the Employer, except for the work executed by the
Employer under GCC Subclause 27.7.
27.4 The Employer shall give the Contractor a notice stating the nature of any
such defect together with all available evidence thereof, promptly
following the discovery thereof. The Employer shall afford all reasonable
opportunity for the Contractor to inspect any such defect.
27.5 The Employer shall afford the Contractor all necessary access to the
Facilities and the Site to enable the Contractor to perform its obligations
under this GCC Clause 27.
The Contractor may, with the consent of the Employer, remove from the
Site any Plant or any part of the Facilities that are defective if the nature
of the defect, and/or any damage to the Facilities caused by the defect,
is such that repairs cannot be expeditiously carried out at the Site.
If such part fails the tests, the Contractor shall carry out further repair,
replacement or making good, as the case may be, until that part of the
Facilities passes such tests. The tests shall be agreed upon by the
Employer and the Contractor.
27.7 If the Contractor fails to commence the work necessary to remedy such
defect or any damage to the Facilities caused by such defect within a
reasonable time (which shall in no event be considered to be less than
15 days), the Employer may, following notice to the Contractor, proceed
to do such work, and the reasonable costs incurred by the Employer in
connection therewith shall be paid to the Employer by the Contractor or
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
201
7-38 Section 7: General Conditions of Contract
may be deducted by the Employer from any monies due the Contractor
or claimed under the Performance Security.
27.8 If the Facilities or any part thereof cannot be used by reason of such
defect and/or making good of such defect, the Defect Liability Period of
the Facilities or such part, as the case may be, shall be extended by a
period equal to the period during which the Facilities or such part cannot
be used by the Employer because of any of the aforesaid reasons.
27.9 Except as provided in GCC Clauses 27 and 33, the Contractor shall be
under no liability whatsoever and howsoever arising, and whether under
the Contract or at law, in respect of defects in the Facilities or any part
thereof, the Plant, design, or engineering, or work executed that appear
after Completion of the Facilities or any part thereof, except where such
defects are the result of the gross negligence, fraud, criminal, or willful
action of the Contractor.
27.10 In addition, any such component of the Facilities and during the period
of time as may be specified in the SCC shall be subject to an extended
Defect Liability Period. Such obligation of the Contractor shall be in
addition to the Defect Liability Period specified under GCC Subclause
27.2.
28. Functional 28.1 The Contractor guarantees that during the Guarantee Test, the Facilities
Guarantees and all parts thereof shall attain the Functional Guarantees specified in
the Appendix (Functional Guarantees) to the Contract Agreement,
subject to, and upon the conditions therein specified.
28.2 If, for reasons attributable to the Contractor, the minimum level of the
Functional Guarantees specified in the Appendix (Functional
Guarantees) to the Contract Agreement are not met either in whole or in
part, the Contractor shall at its cost and expense make such changes,
modifications, and/or additions to the Plant or any part thereof as may
be necessary to meet at least the minimum level of such Guarantees.
The Contractor shall notify the Employer upon completion of the
necessary changes, modifications, and/or additions, and shall request
the Employer to repeat the Guarantee Test until the minimum level of
the Guarantees has been met. If the Contractor eventually fails to meet
the minimum level of Functional Guarantees, the Employer may
consider termination of the Contract, pursuant to GCC Subclause
42.2.2.
28.3 If, for reasons attributable to the Contractor, the Functional Guarantees
specified in the Appendix (Functional Guarantees) to the Contract
Agreement are not attained either in whole or in part, but the minimum
level of the Functional Guarantees specified in the said Appendix to the
Contract Agreement is met, the Contractor shall, at the Contractor’s
option, either
(a) make such changes, modifications, and/or additions to the
Facilities or any part thereof that are necessary to attain the
Functional Guarantees at its cost and expense, and shall request
the Employer to repeat the Guarantee Test or
(b) pay liquidated damages to the Employer in respect of the failure
to meet the Functional Guarantees in accordance with the
provisions in the Appendix (Functional Guarantees) to the
Contract Agreement.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
202
Section 7: General Conditions of Contract 7-39
29. Patent 29.1 The Contractor shall, subject to the Employer’s compliance with GCC
Indemnity Subclause 29.2, indemnify and hold harmless the Employer and its
employees and officers from and against any and all suits, actions, or
administrative proceedings, claims, demands, losses, damages, costs,
and expenses of whatsoever nature, including attorney’s fees and
expenses, which the Employer may suffer as a result of any infringement
or alleged infringement of any patent, utility model, registered design,
trademark, copyright, or other intellectual property right registered or
otherwise existing at the date of the Contract by reason of (a) the
installation of the Facilities by the Contractor or the use of the Facilities
in the country where the Site is located, and (b) the sale of the products
produced by the Facilities in any country.
Such indemnity shall not cover any use of the Facilities or any part
thereof other than for the purpose indicated by or to be reasonably
inferred from the Contract, any infringement resulting from the use of the
Facilities or any part thereof, or any products produced thereby in
association or combination with any other equipment, plant, or materials
not supplied by the Contractor, pursuant to the Contract Agreement.
29.2 If any proceedings are brought or any claim is made against the
Employer arising out of the matters referred to in GCC Subclause 29.1,
the Employer shall promptly give the Contractor a notice thereof, and
the Contractor may at its own expense and in the Employer’s name
conduct such proceedings or claim and any negotiations for the
settlement of any such proceedings or claim.
If the Contractor fails to notify the Employer within 28 days after receipt
of such notice that it intends to conduct any such proceedings or claim,
then the Employer shall be free to conduct the same on its own behalf.
Unless the Contractor has so failed to notify the Employer within the 28-
day period, the Employer shall make no admission that may be
prejudicial to the defense of any such proceedings or claim.
29.3 The Employer shall indemnify and hold harmless the Contractor and its
employees, officers, and Subcontractors from and against any and all
suits, actions or administrative proceedings, claims, demands, losses,
damages, costs, and expenses of whatsoever nature, including
attorney’s fees and expenses, which the Contractor may suffer as a
result of any infringement or alleged infringement of any patent, utility
model, registered design, trademark, copyright, or other intellectual
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
203
7-40 Section 7: General Conditions of Contract
G. Risk Distribution
31. Transfer of 31.1 Ownership of the Plant (including spare parts) to be imported into the
Ownership country where the Site is located shall be transferred to the Employer
upon loading on to the mode of transport to be used to convey the Plant
from the country of origin to that country.
31.2 Ownership of the Plant (including spare parts) procured in the country
where the Site is located shall be transferred to the Employer when the
Plant are brought on to the Site.
31.3 Ownership of the Contractor’s Equipment used by the Contractor and its
Subcontractors in connection with the Contract shall remain with the
Contractor or its Subcontractors.
31.4 Ownership of any Plant in excess of the requirements for the Facilities
shall revert to the Contractor upon Completion of the Facilities or at such
earlier time when the Employer and the Contractor agree that the Plant
in question are no longer required for the Facilities.
32. Care of Facilities 32.1 The Contractor shall be responsible for the care and custody of the
Facilities or any part thereof until the date of Completion of the Facilities
pursuant to GCC Clause 24 or, where the Contract provides for
Completion of the Facilities in parts, until the date of Completion of the
relevant part, and shall make good at its own cost any loss or damage
that may occur to the Facilities or the relevant part thereof from any
cause whatsoever during such period. The Contractor shall also be
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
204
Section 7: General Conditions of Contract 7-41
32.2 If any loss or damage occurs to the Facilities or any part thereof or to
the Contractor’s temporary facilities by reason of
(a) insofar as they relate to the country where the Site is located,
nuclear reaction, nuclear radiation, radioactive contamination,
pressure wave caused by aircraft or other aerial objects, or any
other occurrences that an experienced contractor could not
reasonably foresee, or if reasonably foreseeable could not
reasonably make provision for or insure against, insofar as such
risks are not normally insurable on the insurance market and are
mentioned in the general exclusions of the policy of insurance,
including War Risks and Political Risks, taken out under GCC
Clause 34 hereof; or
(b) any use or occupation by the Employer or any third party other
than a Subcontractor, authorized by the Employer of any part of
the Facilities; or
(c) any use of or reliance upon any design, data, or specification
provided or designated by or on behalf of the Employer, or any
such matter for which the Contractor has disclaimed responsibility
herein,
the Employer shall pay to the Contractor all sums payable in respect of
the Facilities executed, notwithstanding that the same be lost,
destroyed, or damaged, and will pay to the Contractor the replacement
value of all temporary facilities and all parts thereof lost, destroyed, or
damaged. If the Employer requests the Contractor in writing to make
good any loss or damage to the Facilities thereby occasioned, the
Contractor shall make good the same at the cost of the Employer in
accordance with GCC Clause 39. If the Employer does not request the
Contractor in writing to make good any loss or damage to the Facilities
thereby occasioned, the Employer shall either request a change in
accordance with GCC Clause 39, excluding the performance of that part
of the Facilities thereby lost, destroyed or damaged, or, where the loss
or damage affects a substantial part of the Facilities, the Employer shall
terminate the Contract pursuant to GCC Subclause 42.1 hereof.
32.3 The Contractor shall be liable for any loss of or damage to any
Contractor’s Equipment, or any other property of the Contractor used or
intended to be used for purposes of the Facilities, except (i) as
mentioned in GCC Subclause 32.2 with respect to the Contractor’s
temporary facilities, and (ii) where such loss or damage arises by reason
of any of the matters specified in GCC Subclauses 32.2 (b) and (c) and
38.1.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
205
7-42 Section 7: General Conditions of Contract
32.4 With respect to any loss or damage caused to the Facilities or any part
thereof or to the Contractor’s Equipment by reason of any of the matters
specified in GCC Subclause 38.1, the provisions of GCC Subclause
38.3 shall apply.
33. Loss of or 33.1 Subject to GCC Subclause 33.3, the Contractor shall indemnify and hold
Damage to harmless the Employer and its employees and officers from and against
Property; any and all suits, actions, or administrative proceedings, claims,
Accident or Injury demands, losses, damages, costs, and expenses of whatsoever nature,
to Workers; including attorney’s fees and expenses, in respect of the death or injury
Indemnification of any person or loss of or damage to any property other than the
Facilities whether accepted or not, arising in connection with the supply
and installation of the Facilities and by reason of the negligence of the
Contractor or its Subcontractors, or their employees, officers, or agents,
except any injury, death, or property damage caused by the negligence
of the Employer, its contractors, employees, officers, or agents.
33.2 If any proceedings are brought or any claim is made against the
Employer that might subject the Contractor to liability under GCC
Subclause 33.1, the Employer shall promptly give the Contractor a
notice thereof and the Contractor may at its own expense and in the
Employer’s name conduct such proceedings or claim and any
negotiations for the settlement of any such proceedings or claim.
If the Contractor fails to notify the Employer within 28 days after receipt
of such notice that it intends to conduct any such proceedings or claim,
then the Employer shall be free to conduct the same on its own behalf.
Unless the Contractor has so failed to notify the Employer within the 28-
day period, the Employer shall make no admission that may be
prejudicial to the defense of any such proceedings or claim.
33.3 The Employer shall indemnify and hold harmless the Contractor and its
employees, officers, and Subcontractors from any liability for loss of or
damage to property of the Employer, other than the Facilities not yet
taken over, that is caused by fire, explosion, or any other perils, in
excess of the amount recoverable from insurances procured under GCC
Clause 34, provided that such fire, explosion, or other perils were not
caused by any act or failure of the Contractor.
33.4 The party entitled to the benefit of an indemnity under this GCC Clause
33 shall take all reasonable measures to mitigate any loss or damage
which has occurred. If the party fails to take such measures, the other
party’s liabilities shall be correspondingly reduced.
34. Insurance 34.1 To the extent specified in the Appendix (Insurance Requirements) to the
Contract Agreement, the Contractor shall at its expense take out and
maintain in effect, or cause to be taken out and maintained in effect,
during the performance of the Contract, the insurances set forth below
in the sums and with the deductibles and other conditions specified in
the said Appendix. The identity of the insurers and the form of the
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
206
Section 7: General Conditions of Contract 7-43
policies shall be subject to the approval of the Employer, who should not
unreasonably withhold such approval.
(a) Cargo Insurance During Transport
Covering loss or damage occurring while in transit from the
Contractor’s or Subcontractor’s works or stores until arrival at the
Site, to the Plant (including spare parts therefor) and to the
Contractor’s Equipment.
(b) Installation All Risks Insurance
Covering physical loss or damage to the Facilities at the Site,
occurring prior to Completion of the Facilities, with an extended
maintenance coverage for the Contractor’s liability in respect of
any loss or damage occurring during the Defect Liability Period
while the Contractor is on the Site for the purpose of performing
its obligations during the Defect Liability Period.
34.2 The Employer shall be named as co-insured under all insurance policies
taken out by the Contractor pursuant to GCC Subclause 34.1, except for
the Third Party Liability, Workers’ Compensation, and Employer’s
Liability Insurances, and the Contractor’s Subcontractors shall be
named as co-insureds under all insurance policies taken out by the
Contractor pursuant to GCC Subclause 34.1 except for the Cargo
Insurance During Transport, Workers’ Compensation, and Employer’s
Liability Insurances. All insurer’s rights of subrogation against such co-
insureds for losses or claims arising out of the performance of the
Contract shall be waived under such policies.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
207
7-44 Section 7: General Conditions of Contract
34.3 The Contractor shall, in accordance with the provisions of the Appendix
(Insurance Requirements) to the Contract Agreement, deliver to the
Employer certificates of insurance or copies of the insurance policies as
evidence that the required policies are in full force and effect. The
certificates shall provide that no less than 21 days’ notice shall be given
to the Employer by insurers prior to cancellation or material modification
of a policy.
34.4 The Contractor shall ensure that, where applicable, its Subcontractor(s)
shall take out and maintain in effect adequate insurance policies for their
personnel and vehicles and for work executed by them under the
Contract, unless such Subcontractors are covered by the policies taken
out by the Contractor.
34.5 The Employer shall at its expense take out and maintain in effect during
the performance of the Contract those insurances specified in the
Appendix (Insurance Requirements) to the Contract Agreement, in the
sums and with the deductibles and other conditions specified in the said
Appendix. The Contractor and the Contractor’s Subcontractors shall be
named as co-insureds under all such policies. All insurers’ rights of
subrogation against such co-insureds for losses or claims arising out of
the performance of the Contract shall be waived under such policies.
The Employer shall deliver to the Contractor satisfactory evidence that
the required insurances are in full force and effect. The policies shall
provide that not less than 21 days’ notice shall be given to the Contractor
by all insurers prior to any cancellation or material modification of the
policies. If so requested by the Contractor, the Employer shall provide
copies of the policies taken out by the Employer under this GCC
Subclause 34.5.
34.6 If the Contractor fails to take out and/or maintain in effect the insurances
referred to in GCC Subclause 34.1, the Employer may take out and
maintain in effect any such insurances and may from time to time deduct
from any amount due the Contractor under the Contract any premium
that the Employer shall have paid to the insurer, or may otherwise
recover such amount as a debt due from the Contractor. If the Employer
fails to take out and/or maintain in effect the insurances referred to in
GCC 34.5, the Contractor may take out and maintain in effect any such
insurances and may from time to time deduct from any amount due the
Employer under the Contract any premium that the Contractor shall have
paid to the insurer, or may otherwise recover such amount as a debt due
from the Employer. If the Contractor fails to or is unable to take out and
maintain in effect any such insurances, the Contractor shall
nevertheless have no liability or responsibility towards the Employer,
and the Contractor shall have full recourse against the Employer for any
and all liabilities of the Employer herein.
34.7 Unless otherwise provided in the Contract, the Contractor shall prepare
and conduct all and any claims made under the policies effected by it
pursuant to this GCC Clause 34, and all monies payable by any insurers
shall be paid to the Contractor. The Employer shall give to the
Contractor all such reasonable assistance as may be required by the
Contractor. With respect to insurance claims in which the Employer’s
interest is involved, the Contractor shall not give any release or make
any compromise with the insurer without the prior written consent of the
Employer. With respect to insurance claims in which the Contractor’s
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
208
Section 7: General Conditions of Contract 7-45
interest is involved, the Employer shall not give any release or make any
compromise with the insurer without the prior written consent of the
Contractor.
35. Unforeseen 35.1 If, during the execution of the Contract, the Contractor shall encounter
Conditions on the Site any physical conditions other than climatic conditions, or
artificial obstructions that could not have been reasonably foreseen prior
to the date of the Contract Agreement by an experienced contractor on
the basis of reasonable examination of the data relating to the Facilities
including any data as to boring tests, provided by the Employer, and on
the basis of information that it could have obtained from a visual
inspection of the Site if access thereto was available, or other data
readily available to it relating to the Facilities, and if the Contractor
determines that it will in consequence of such conditions or obstructions
incur additional cost and expense or require additional time to perform
its obligations under the Contract that would not have been required if
such physical conditions or artificial obstructions had not been
encountered, the Contractor shall promptly, and before performing
additional work or using additional Plant or Contractor’s Equipment,
notify the Project Manager in writing of
(d) the additional cost and expense that the Contractor is likely to
incur.
On receiving any notice from the Contractor under this GCC Subclause
35.1, the Project Manager shall promptly consult with the Employer and
Contractor and decide upon the actions to be taken to overcome the
physical conditions or artificial obstructions encountered. Following
such consultations, the Project Manager shall instruct the Contractor,
with a copy to the Employer, of the actions to be taken.
35.2 Any reasonable additional cost and expense incurred by the Contractor
in following the instructions from the Project Manager to overcome such
physical conditions or artificial obstructions referred to in GCC
Subclause 35.1 shall be paid by the Employer to the Contractor as an
addition to the Contract Price.
36. Change in Laws 36.1 If, after the date 28 days prior to the date of Bid submission, in the
and Regulations country where the Site is located, any law, regulation, ordinance, order
or by-law having the force of law is enacted, promulgated, abrogated, or
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
209
7-46 Section 7: General Conditions of Contract
37. Force Majeure 37.1 “Force Majeure” shall mean any event beyond the reasonable control of
the Employer or of the Contractor, as the case may be, and which is
unavoidable notwithstanding the reasonable care of the party affected,
and shall include, without limitation, the following:
37.3 The party who has given such notice shall be excused from the
performance or punctual performance of its obligations under the
Contract for so long as the relevant event of Force Majeure continues
and to the extent that such party’s performance is prevented, hindered,
or delayed. The Time for Completion shall be extended in accordance
with GCC Clause 40.
37.4 The party or parties affected by the event of Force Majeure shall use
reasonable efforts to mitigate the effect thereof upon its or their
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
210
Section 7: General Conditions of Contract 7-47
performance of the Contract and to fulfill its or their obligations under the
Contract, but without prejudice to either party’s right to terminate the
Contract under GCC Subclauses 37.6 and 38.5.
(b) give rise to any claim for damages or additional cost or expense
occasioned thereby, subject to GCC Subclauses 32.2, 38.3 and
38.4
37.7 In the event of termination pursuant to GCC Subclause 37.6, the rights
and obligations of the Employer and the Contractor shall be as specified
in GCC Subclauses 42.1.2 and 42.1.3.
37.8 Notwithstanding GCC Subclause 37.5, Force Majeure shall not apply to
any obligation of the Employer to make payments to the Contractor
herein.
38. War Risks 38.1 “War Risks” shall mean any event specified in paragraphs (a) and (b) of
GCC Subclause 37.1 and any explosion or impact of any mine, bomb,
shell, grenade, or other projectile, missile, munitions or explosive of war,
occurring or existing in or near the country (or countries) where the Site
is located.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
211
7-48 Section 7: General Conditions of Contract
If the Employer does not require the Contractor to replace or make good
any such destruction or damage to the Facilities, the Employer shall
either request a change in accordance with GCC Clause 39, excluding
the performance of that part of the Facilities thereby destroyed or
damaged or, where the loss, destruction, or damage affects a
substantial part of the Facilities, shall terminate the Contract, pursuant
to GCC Subclause 42.1.
38.5 If during the performance of the Contract any war risks shall occur that
financially or otherwise materially affect the execution of the Contract by
the Contractor, the Contractor shall use its reasonable efforts to execute
the Contract with due and proper consideration given to the safety of its
and its Subcontractors’ personnel engaged in the work on the Facilities,
provided, however, that if the execution of the work on the Facilities
becomes impossible or is substantially prevented for a single period of
more than sixty (60) days or an aggregate period of more than one
hundred and twenty (120) days on account of any war risks, the parties
will attempt to develop a mutually satisfactory solution, failing which
either party may terminate the Contract by giving a notice to the other.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
212
Section 7: General Conditions of Contract 7-49
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
213
7-50 Section 7: General Conditions of Contract
(b) advise the Contractor of any part of its Estimate for Change
Proposal that is unacceptable and request the Contractor to
review its estimate
(c) advise the Contractor that the Employer does not intend to
proceed with the Change.
39.2.6 Upon receipt of the Change Proposal, the Employer and the
Contractor shall mutually agree upon all matters therein
contained. Within 14 days after such agreement, the Employer
shall, if it intends to proceed with the Change, issue the Contractor
with a Change Order.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
214
Section 7: General Conditions of Contract 7-51
39.2.7 If the Employer and the Contractor cannot reach agreement on the
price for the Change, an equitable adjustment to the Time for
Completion, or any other matters identified in the Change
Proposal, the Employer may nevertheless instruct the Contractor
to proceed with the Change by issue of a “Pending Agreement
Change Order.”
If the parties cannot reach agreement within 60 days from the date
of issue of the Pending Agreement Change Order, then the matter
may be referred to the Dispute Board in accordance with the
provisions of GCC Subclause 45.3.
40. Extension of Time 40.1 The Time(s) for Completion specified in the SCC shall be extended if the
for Completion Contractor is delayed or impeded in the performance of any of its
obligations under the Contract by reason of any of the following:
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
215
7-52 Section 7: General Conditions of Contract
(c) any suspension order given by the Employer under GCC Clause
41 hereof or reduction in the rate of progress pursuant to GCC
Subclause 41.2; or
40.3 The Contractor shall at all times use its reasonable efforts to minimize
any delay in the performance of its obligations under the Contract.
In all cases where the Contractor has given a notice of a claim for an
extension of time under GCC 40.2, the Contractor shall consult with the
Project Manager in order to determine the steps (if any) which can be
taken to overcome or minimize the actual or anticipated delay. The
Contractor shall there after comply with all reasonable instructions, which
the Project Manager shall give in order to minimize such delay. If
compliance with such instructions shall cause the Contractor to incur
extra costs and the Contractor is entitled to an extension of time under
GCC 40.1, the amount of such extra costs shall be added to the Contract
Price.
41. Suspension 41.1 The Employer may request the Project Manager, by notice to the
Contractor, to order the Contractor to suspend performance of any or all
of its obligations under the Contract. Such notice shall specify the
obligation of which performance is to be suspended, the effective date of
the suspension and the reasons therefor. The Contractor shall thereupon
suspend performance of such obligation, except those obligations
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
216
Section 7: General Conditions of Contract 7-53
41.2 If
(a) the Employer has failed to pay the Contractor any sum due under
the Contract within the specified period, has failed to approve any
invoice or supporting documents without just cause pursuant to the
Appendix (Terms and Procedures of Payment) to the Contract
Agreement, or commits a substantial breach of the Contract, the
Contractor may give a notice to the Employer that requires payment
of such sum, with interest thereon as stipulated in GCC Subclause
12.3, requires approval of such invoice or supporting documents,
or specifies the breach and requires the Employer to remedy the
same, as the case may be. If the Employer fails to pay such sum
together with such interest, fails to approve such invoice or
supporting documents or give its reasons for withholding such
approval, or fails to remedy the breach or take steps to remedy the
breach within 14 days after receipt of the Contractor’s notice; or
(b) the Contractor is unable to carry out any of its obligations under the
Contract for any reason attributable to the Employer, including but
not limited to the Employer’s failure to provide possession of or
access to the Site or other areas in accordance with GCC
Subclause 10.2, or failure to obtain any governmental permit
necessary for the execution and/or completion of the Facilities,
then the Contractor may by 14 days’ notice to the Employer suspend
performance of all or any of its obligations under the Contract, or reduce
the rate of progress.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
217
7-54 Section 7: General Conditions of Contract
41.4 During the period of suspension, the Contractor shall not remove from the
Site any Plant, any part of the Facilities or any Contractor’s Equipment,
without the prior written consent of the Employer.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
218
Section 7: General Conditions of Contract 7-55
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
219
7-56 Section 7: General Conditions of Contract
then the Employer may, without prejudice to any other rights it may
possess under the Contract, give a notice to the Contractor,
stating the nature of the default and requiring the Contractor to
remedy the same. If the Contractor fails to remedy or to take steps
to remedy the same within 14 days of its receipt of such notice,
then the Employer may terminate the Contract forthwith by giving
a notice of termination to the Contractor that refers to this GCC
Subclause 42.2.
(a) cease all further work, except for such work as the Employer
may specify in the notice of termination for the sole purpose
of protecting that part of the Facilities already executed, or
any work required to leave the Site in a clean and safe
condition;
42.2.4 The Employer may enter upon the Site, expel the Contractor, and
complete the Facilities itself or by employing any third party. The
Employer may, to the exclusion of any right of the Contractor over
the same, take over and use with the payment of a fair rental rate
to the Contractor, with all the maintenance costs to the account of
the Employer and with an indemnification by the Employer for all
liability including damage or injury to persons arising out of the
Employer’s use of such equipment, any Contractor’s Equipment
owned by the Contractor and on the Site in connection with the
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
220
Section 7: General Conditions of Contract 7-57
42.2.6 If the Employer completes the Facilities, the cost of completing the
Facilities by the Employer shall be determined.
If the sum that the Contractor is entitled to be paid, pursuant to
GCC Subclause 42.2.5, plus the reasonable costs incurred by the
Employer in completing the Facilities, exceeds the Contract Price,
the Contractor shall be liable for such excess.
If such excess is greater than the sums due the Contractor under
GCC Subclause 42.2.5, the Contractor shall pay the balance to
the Employer, and if such excess is less than the sums due the
Contractor under GCC Subclause 42.2.5, the Employer shall pay
the balance to the Contractor.
The Employer and the Contractor shall agree, in writing, on the
computation described above and the manner in which any sums
shall be paid.
(a) the Employer has failed to pay the Contractor any sum due
under the Contract within the specified period, has failed to
approve any invoice or supporting documents without just
cause pursuant to the Appendix (Terms and Procedures of
Payment) to the Contract Agreement, or commits a
substantial breach of the Contract, the Contractor may give
a notice to the Employer that requires payment of such sum,
with interest thereon as stipulated in GCC Subclause 12.3,
requires approval of such invoice or supporting documents,
or specifies the breach and requires the Employer to remedy
the same, as the case may be. If the Employer fails to pay
such sum together with such interest, fails to approve such
invoice or supporting documents or give its reasons for
withholding such approval, fails to remedy the breach or
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
221
7-58 Section 7: General Conditions of Contract
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
222
Section 7: General Conditions of Contract 7-59
42.4 In this GCC Clause 42, the expression “Facilities executed” shall include
all work executed, Installation Services provided, and all Plant acquired,
or subject to a legally binding obligation to purchase, by the Contractor
and used or intended to be used for the purpose of the Facilities, up to
and including the date of termination.
42.5 In this GCC Clause 42, in calculating any monies due from the Employer to
the Contractor, account shall be taken of any sum previously paid by the
Employer to the Contractor under the Contract, including any advance
payment paid pursuant to the Appendix (Terms and Procedures of Payment)
to the Contract Agreement.
43. Assignment 43.1 Neither the Employer nor the Contractor shall, without the express prior
written consent of the other party which consent shall not be
unreasonably withheld, assign to any third party the Contract or any part
thereof, or any right, benefit, obligation or interest therein or thereunder,
except that the Contractor shall be entitled to assign either absolutely or
by way of charge any monies due and payable to it or that may become
due and payable to it under the Contract.
44. Contractor’s 44.1 If the Contractor considers himself to be entitled to any extension of the
Claims Time for Completion and/or any additional payment, under any Clause
of these Conditions or otherwise in connection with the Contract, the
Contractor shall submit a notice to the Project Manager, describing the
event or circumstance giving rise to the claim. The notice shall be given
as soon as practicable, and not later than 28 days after the Contractor
became aware, or should have become aware, of the event or
circumstance.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
223
7-60 Section 7: General Conditions of Contract
The Contractor shall also submit any other notices, which are required
by the Contract, and supporting particulars for the claim, all as relevant
to such event or circumstance.
Within 42 days after the Contractor became aware (or should have
become aware) of the event or circumstance giving rise to the claim, or
within such other period as may be proposed by the Contractor and
approved by the Project Manager, the Contractor shall send to the
Project Manager a fully detailed claim, which includes full supporting
particulars of the basis of the claim and of the extension of time and/or
additional payment claimed. If the event or circumstance giving rise to
the claim has a continuing effect,
(c) the Contractor shall send a final claim within 28 days after the end
of the effects resulting from the event or circumstance, or within
such other period as may be proposed by the Contractor and
approved by the Project Manager.
Each payment certificate shall include such amounts for any claim as
have been reasonably substantiated as due under the relevant provision
of the Contract. Unless and until the particulars supplied are sufficient to
substantiate the whole of the claim, the Contractor shall only be entitled
to payment for such part of the claim as he has been able to substantiate.
The Project Manager shall agree with the Contractor or estimate: (i) the
extension (if any) of the Time for Completion (before or after its expiry)
in accordance with GCC Clause 40, and/or (ii) the additional payment (if
any) to which the Contractor is entitled under the Contract.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
224
Section 7: General Conditions of Contract 7-61
In the event that the Contractor and the Employer cannot agree on any
matter relating to a claim, either party may refer the matter to the Dispute
Board pursuant to GCC 45 hereof.
The Dispute Board shall comprise, as stated in the SCC, either one or
three suitably qualified persons (“the members”), each of whom shall be
fluent in the language for communication defined in the Contract and
shall be a professional experienced in the type of activities involved in the
performance of the Contract and with the interpretation of contractual
documents. If the number is not so stated and the Parties do not agree
otherwise, the Dispute Board shall comprise three persons, one of whom
shall serve as chairman.
If the Parties have not jointly appointed the Dispute Board 21 days before
the date stated in the SCC and the Dispute Board is to comprise three
persons, each Party shall nominate one member for the approval of the
other Party. The first two members shall recommend and the Parties
shall agree upon the third member, who shall act as chairman.
The agreement between the Parties and either the sole member or each
of the three members shall incorporate by reference the General
Conditions of Dispute Board Agreement contained in the Appendix to
these General Conditions, with such amendments as are agreed
between them.
The terms of the remuneration of either the sole member or each of the
three members, including the remuneration of any expert whom the
Dispute Board consults, shall be mutually agreed upon by the Parties
when agreeing the terms of appointment of the member or such expert
(as the case may be). Each Party shall be responsible for paying one-
half of this remuneration.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
225
7-62 Section 7: General Conditions of Contract
(a) the Parties fail to agree upon the appointment of the sole member
of the Dispute Board by the date stated in the first paragraph of
GCC Subclause 45.1;
(b) either Party fails to nominate a member (for approval by the other
Party) of a Dispute Board of three persons by such date;
(c) the Parties fail to agree upon the appointment of the third member
(to act as chairman) of the Dispute Board by such date; or
then the appointing entity or official named in the SCC shall, upon the
request of either or both of the Parties and after due consultation with
both Parties, appoint this member of the Dispute Board. This
appointment shall be final and conclusive. Each Party shall be
responsible for paying one-half of the remuneration of the appointing
entity or official.
Both Parties shall promptly make available to the Dispute Board all such
additional information, further access to the Site, and appropriate
facilities, as the Dispute Board may require for the purposes of making a
decision on such dispute. The Dispute Board shall be deemed to be not
acting as arbitrator(s).
Within 84 days after receiving such reference, or within such other period
as may be proposed by the Dispute Board and approved by both Parties,
the Dispute Board shall give its decision, which shall be reasoned and
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
226
Section 7: General Conditions of Contract 7-63
shall state that it is given under this Subclause. The decision shall be
binding on both Parties, who shall promptly give effect to it unless and
until it shall be revised in an amicable settlement or an arbitral award as
described below. Unless the Contract has already been abandoned,
repudiated or terminated, the Contractor shall continue to proceed with
the performance of the Facilities in accordance with the Contract.
45.5 Arbitration
Unless settled amicably, any dispute in respect of which the Dispute
Board’s decision (if any) has not become final and binding shall be finally
settled by international arbitration. Unless otherwise agreed by both
Parties,
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
227
7-64 Section 7: General Conditions of Contract
The arbitrator(s) shall have full power to open up, review and revise any
certificate, determination, instruction, opinion or valuation of the Project
Manager, and any decision of the Dispute Board, relevant to the dispute.
Nothing shall disqualify the Project Manager from being called as a
witness and giving evidence before the arbitrator(s) on any matter
whatsoever relevant to the dispute.
(a) GCC Subclauses 45.3 and 45.4 shall not apply, and
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
228
Section 7: General Conditions of Contract 7-65
APPENDIX A
1 Definitions
(c) the “Member” who is defined in the Dispute Board Agreement as being
(i) the sole member of the "Dispute Board" and, where this is the case, all references to the
“Other Members” do not apply; or
(ii) one of the three persons who are jointly called the “Dispute Board” (or “dispute board”)
and, where this is the case, the other two persons are called the “Other Members”.
The Employer and the Contractor have entered (or intend to enter) into a contract, which is called the
"Contract" and is defined in the Dispute Board Agreement, which incorporates this Appendix. In the
Dispute Board Agreement, words and expressions which are not otherwise defined shall have the
meanings assigned to them in the Contract.
2 General Provisions
Unless otherwise stated in the Dispute Board Agreement, it shall take effect on the latest of the following
dates:
(b) when the Employer, the Contractor and the Member have each signed the Dispute Board
Agreement; or
(c) when the Employer, the Contractor and each of the Other Members (if any) have respectively
each signed a dispute board agreement.
This employment of the Member is a personal appointment. At any time, the Member may give not less
than 70 days’ notice of resignation to the Employer and to the Contractor, and the Dispute Board
Agreement shall terminate upon the expiry of this period.
3 Warranties
The Member warrants and agrees that he/she is and shall be impartial and independent of the
Employer, the Contractor and the Project Manager. The Member shall promptly disclose, to each of
them and to the Other Members (if any), any fact or circumstance which might appear inconsistent with
his/her warranty and agreement of impartiality and independence.
When appointing the Member, the Employer and the Contractor relied upon the Member’s
representations that he/she is
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
229
7-66 Section 7: General Conditions of Contract
(a) experienced in the work, which the Contractor is to carry out under the Contract,
(a) have no interest financial or otherwise in the Employer, the Contractor or the Project Manager,
nor any financial interest in the Contract except for payment under the Dispute Board Agreement;
(b) not previously have been employed as a consultant or otherwise by the Employer, the Contractor,
or the Project Manager, except in such circumstances as were disclosed in writing to the
Employer and the Contractor before they signed the Dispute Board Agreement;
(c) have disclosed in writing to the Employer, the Contractor, and the Other Members (if any), before
entering into the Dispute Board Agreement and to his/her best knowledge and recollection, any
professional or personal relationships with any director, officer, or employee of the Employer, the
Contractor, or the Project Manager, and any previous involvement in the overall project of which
the Contract forms part;
(d) not, for the duration of the Dispute Board Agreement, be employed as a consultant or otherwise
by the Employer, the Contractor, or the Project Manager, except as may be agreed in writing by
the Employer, the Contractor, and the Other Members (if any);
(e) comply with the annexed procedural rules and with GCC Subclause 45.3;
(f) not give advice to the Employer, the Contractor, the Employer’s Personnel, or the Contractor’s
Personnel concerning the conduct of the Contract, other than in accordance with the annexed
procedural rules;
(g) not while a Member enter into discussions or make any agreement with the Employer, the
Contractor, or the Project Manager regarding employment by any of them, whether as a
consultant or otherwise, after ceasing to act under the Dispute Board Agreement;
(h) ensure his/her availability for all site visits and hearings as are necessary;
(i) become conversant with the Contract and with the progress of the Facilities (and of any other
parts of the project of which the Contract forms part) by studying all documents received, which
shall be maintained in a current working file;
(j) treat the details of the Contract and all the Dispute Board’s activities and hearings as private and
confidential, and not publish or disclose them without the prior written consent of the Employer,
the Contractor, and the Other Members (if any); and
(k) be available to give advice and opinions on any matter relevant to the Contract when requested
by both the Employer and the Contractor, subject to the agreement of the Other Members (if
any).
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
230
Section 7: General Conditions of Contract 7-67
The Employer, the Contractor, the Employer’s Personnel and the Contractor’s Personnel shall not
request advice from or consultation with the Member regarding the Contract, otherwise than in the
normal course of the Dispute Board’s activities under the Contract and the Dispute Board Agreement.
The Employer and the Contractor shall be responsible for compliance with this provision, by the
Employer’s Personnel and the Contractor’s Personnel respectively.
The Employer and the Contractor undertake to each other and to the Member that the Member shall
not, except as otherwise agreed in writing by the Employer, the Contractor, the Member and the Other
Members (if any)
(b) be called as a witness to give evidence concerning any dispute before arbitrator(s) appointed for
any arbitration under the Contract; or
(c) be liable for any claims for anything done or omitted in the discharge or purported discharge of
the Member’s functions, unless the act or omission is shown to have been in bad faith.
The Employer and the Contractor hereby jointly and severally indemnify and hold the Member harmless
against and from claims from which he is relieved from liability under the preceding paragraph.
Whenever the Employer or the Contractor refers a dispute to the Dispute Board under GCC Subclause
45.3, which will require the Member to make a site visit and attend a hearing, the Employer or the
Contractor shall provide appropriate security for a sum equivalent to the reasonable expenses to be
incurred by the Member. No account shall be taken of any other payments due or paid to the Member.
6 Payment
The Member shall be paid as follows, in the currency named in the Dispute Board Agreement:
(a) a retainer fee per calendar month, which shall be considered as payment in full for
(i) being available on 28 days’ notice for all site visits and hearings;
(ii) becoming and remaining conversant with all project developments and maintaining
relevant files;
(iii) all office and overhead expenses including secretarial services, photocopying and office
supplies incurred in connection with his duties; and
(iv) all services performed hereunder except those referred to in sub-paragraphs (b) and (c) of
this Clause.
The retainer fee shall be paid with effect from the last day of the calendar month in which the
Dispute Board Agreement becomes effective; until the last day of the calendar month in which
the Taking-Over Certificate is issued for the whole of the Works.
With effect from the first day of the calendar month following the month in which Taking-Over
Certificate is issued for the whole of the Works, the retainer fee shall be reduced by one-third.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
231
7-68 Section 7: General Conditions of Contract
This reduced fee shall be paid until the first day of the calendar month in which the Member
resigns or the Dispute Board Agreement is otherwise terminated.
(i) each day or part of a day up to a maximum of 2 days’ travel time in each direction for the
journey between the Member’s home and the site, or another location of a meeting with
the Other Members (if any);
(ii) each working day on site visits, hearings, or preparing decisions; and
(c) all reasonable expenses, including necessary travel expenses (air fare in less than first class,
hotel and subsistence and other direct travel expenses) incurred in connection with the Member’s
duties, as well as the cost of telephone calls, courier charges, facsimiles, and telexes, and use
of the internet: a receipt shall be required for each item in excess of 5% of the daily fee referred
to in sub-paragraph (b) of this Clause;
(d) any taxes properly levied in the Country on payments made to the Member (unless a national or
permanent resident of the Country) under this Clause 6.
The retainer and daily fees shall be as specified in the Dispute Board Agreement. Unless it
specifies otherwise, these fees shall remain fixed for the first 24 calendar months, and shall
thereafter be adjusted by agreement between the Employer, the Contractor and the Member, at
each anniversary of the date on which the Dispute Board Agreement became effective.
If the parties fail to agree on the retainer fee or the daily fee, the appointing entity or official named
in the SCC shall determine the amount of the fees to be used.
The Member shall submit invoices for payment of the monthly retainer and air fares quarterly in
advance. Invoices for other expenses and for daily fees shall be submitted following the
conclusion of a site visit or hearing. All invoices shall be accompanied by a brief description of
activities performed during the relevant period and shall be addressed to the Contractor.
The Contractor shall pay each of the Member’s invoices in full within 56 calendar days after
receiving each invoice and shall apply to the Employer (in the Statements under the Contract) for
reimbursement of one-half of the amounts of these invoices. The Employer shall then pay the
Contractor in accordance with the Contract.
If the Contractor fails to pay to the Member the amount to which he/she is entitled under the
Dispute Board Agreement, the Employer shall pay the amount due to the Member and any other
amount which may be required to maintain the operation of the Dispute Board; and without
prejudice to the Employer’s rights or remedies. In addition to all other rights arising from this
default, the Employer shall be entitled to reimbursement of all sums paid in excess of one-half of
these payments, plus all costs of recovering these sums and financing charges calculated at the
rate specified in accordance with GCC Subclause 12.3.
If the Member does not receive payment of the amount due within 70 days after submitting a
valid invoice, the Member may (i) suspend his/her services (without notice) until the payment is
received, and/or (ii) resign his/her appointment by giving notice under Clause 7.
7 Termination
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
232
Section 7: General Conditions of Contract 7-69
At any time: (i) the Employer and the Contractor may jointly terminate the Dispute Board Agreement by
giving 42 days’ notice to the Member, or (ii) the Member may resign as provided for in Clause 2.
If the Member fails to comply with the Dispute Board Agreement, the Employer and the Contractor may,
without prejudice to their other rights, terminate it by notice to the Member. The notice shall take effect
when received by the Member.
If the Employer or the Contractor fails to comply with the Dispute Board Agreement, the Member may,
without prejudice to his other rights, terminate it by notice to the Employer and the Contractor. The
notice shall take effect when received by them both.
Any such notice, resignation and termination shall be final and binding on the Employer, the Contractor
and the Member. However, a notice by the Employer or the Contractor, but not by both, shall be of no
effect.
If the Member fails to comply with any of his obligations under Clause 4 concerning his impartiality or
independence in relation to the Employer or the Contractor, he/she shall not be entitled to any fees or
expenses hereunder and shall, without prejudice to their other rights, reimburse each of the Employer
and the Contractor for any fees and expenses received by the Member and the Other Members (if any),
for proceedings or decisions (if any) of the Dispute Board which are rendered void or ineffective by the
said failure to comply.
9 Disputes
Any dispute or claim arising out of or in connection with this Dispute Board Agreement, or the breach,
termination or invalidity thereof, shall be finally settled by institutional arbitration. If no other arbitration
institute is agreed, the arbitration shall be conducted under the Rules of Arbitration of the International
Chamber of Commerce by one arbitrator appointed in accordance with these Rules of Arbitration.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
233
7-70 Section 7: General Conditions of Contract
1. Unless otherwise agreed by the Employer and the Contractor, the Dispute Board shall visit the
site at intervals of not more than 140 days, including times of critical construction events, at the
request of either the Employer or the Contractor. Unless otherwise agreed by the Employer, the
Contractor, and the Dispute Board, the period between consecutive visits shall not be less than
70 days, except as required to convene a hearing as described below.
2. The timing of and agenda for each site visit shall be as agreed jointly by the Dispute Board, the
Employer, and the Contractor, or in the absence of agreement, shall be decided by the Dispute
Board. The purpose of site visits is to enable the Dispute Board to become and remain acquainted
with the progress of the Works and of any actual or potential problems or claims, and, as far as
reasonable, to prevent potential problems or claims from becoming disputes.
3. Site visits shall be attended by the Employer, the Contractor, and the Project Manager and shall
be coordinated by the Employer in cooperation with the Contractor. The Employer shall ensure
the provision of appropriate conference facilities and secretarial and copying services. At the
conclusion of each site visit and before leaving the site, the Dispute Board shall prepare a report
on its activities during the visit and shall send copies to the Employer and the Contractor.
4. The Employer and the Contractor shall furnish to the Dispute Board one copy of all documents
which the Dispute Board may request, including Contract documents, progress reports, variation
instructions, certificates, and other documents pertinent to the performance of the Contract. All
communications between the Dispute Board and the Employer or the Contractor shall be copied
to the other Party. If the Dispute Board comprises three persons, the Employer and the Contractor
shall send copies of these requested documents and these communications to each of these
persons.
5. If any dispute is referred to the Dispute Board in accordance with GCC Subclause 45.3, the
Dispute Board shall proceed in accordance with GCC Subclause 45.3 and these Guidelines.
Subject to the time allowed to give notice of a decision and other relevant factors, the Dispute
Board shall
(a) act fairly and impartially as between the Employer and the Contractor, giving each of them
a reasonable opportunity of putting his case and responding to the other’s case; and
(b) adopt procedures suitable to the dispute, avoiding unnecessary delay or expense.
6. The Dispute Board may conduct a hearing on the dispute, in which event it will decide on the
date and place for the hearing and may request that written documentation and arguments from
the Employer and the Contractor be presented to it prior to or at the hearing.
7. Except as otherwise agreed in writing by the Employer and the Contractor, the Dispute Board
shall have power to adopt an inquisitorial procedure, to refuse admission to hearings or audience
at hearings to any persons other than representatives of the Employer, the Contractor, and the
Project Manager, and to proceed in the absence of any party who the Dispute Board is satisfied
received notice of the hearing; but shall have discretion to decide whether and to what extent this
power may be exercised.
8. The Employer and the Contractor empower the Dispute Board, among other things, to
(b) decide upon the Dispute Board’s own jurisdiction, and as to the scope of any dispute
referred to it;
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
234
Section 7: General Conditions of Contract 7-71
(c) conduct any hearing as it thinks fit, not being bound by any rules or procedures other than
those contained in the Contract and these Guidelines;
(d) take the initiative in ascertaining the facts and matters required for a decision;
(f) decide upon the payment of financing charges in accordance with the Contract;
(g) decide upon any provisional relief such as interim or conservatory measures;
(h) open up, review and revise any certificate, decision, determination, instruction, opinion or
valuation of the Project Manager, relevant to the dispute; and
(i) appoint, should the Dispute Board so consider necessary and the Parties agree, a suitable
expert at the cost of the Parties to give advice on a specific matter relevant to the dispute.
9. The Dispute Board shall not express any opinions during any hearing concerning the merits of
any arguments advanced by the Parties. Thereafter, the Dispute Board shall make and give its
decision in accordance with GCC Subclause 45.3, or as otherwise agreed by the Employer and
the Contractor in writing. If the Dispute Board comprises three persons
(a) it shall convene in private after a hearing, in order to have discussions and prepare its
decision;
(b) it shall endeavour to reach a unanimous decision: if this proves impossible the applicable
decision shall be made by a majority of the Members, who may require the minority
Member to prepare a written report for submission to the Employer and the Contractor; and
(c) if a Member fails to attend a meeting or hearing, or to fulfil any required function, the other
two Members may nevertheless proceed to make a decision, unless
(i) either the Employer or the Contractor does not agree that they do so, or
(ii) the absent Member is the chairman and he/she instructs the other Members to not
make a decision.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery Energy
Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
235
Section 8: Special Conditions of Contract 8-1
Table of Clauses
22 Installation................................................................................................................... 8-5
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
236
8-2 Section 8: Special Conditions of Contract
1. Definitions
5.1 The Contract shall be interpreted in accordance with the laws of: India
6.4 The Contractor has the obligation to notify the Employer of any changes in connection
with the matters described in paragraphs (i), (k), (l), (m), (n), (o), (p) and (t) of the Letter
of Bid.
6.5 If the Contactor is debarred or temporarily suspended by ADB, it shall inform the Employer
of such debarment or suspension, and that the endorsement of ADB’s Office of
Anticorruption and Integrity is required for any variations, extensions or modifications to
the Contract.
7. Scope of Facilities
7.3 The Contractor agrees to supply spare parts for a period of years: 6 Years
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
237
Section 8: Special Conditions of Contract 8-3
8.1 The Contractor shall commence work on the Facilities within 15 days from the Effective
Date for determining Time for Completion as specified in the Contract Agreement
provided that access to and possession of the Site or any part thereof have been given
under subclause 10.2, and shall then proceed with the work on the Facilities with due
expedition and without delay.
8.2 The Time for Completion of the whole of the Facilities at each site shall be 90 days from
the Date of site allocation as described in the Contract Agreement.
9. Contractor’s Responsibilities
“ADB’s right to inspect the Site and/or the Contractor’s accounts and records relating to
the performance of the Contract stated in Subclause 6.1 (e) and 9.6 shall survive
termination and/ or expiration of this Contract.”
At the end of the sub-clause in 9.8 Protection of the Environment, add the following
paragraphs:
“The Contractor shall comply with all applicable national, provincial, and local
environmental laws and regulations.
The Contractor shall also comply with all reasonable requests of the national and local
authorities responsible for enforcing environmental controls.
Within 28 days of the Commencement Date the Contractor shall submit a detailed Site
Specific Environmental Management Plan (SSEMP), based on the Environmental Health
and Safety Management Plan submitted in the technical proposal, for the Project
Manager’s no objection showing how the Contractor intends to comply with environmental
laws and regulations and other specific requirements prescribed in the Contract,
addressing all the monitoring and mitigation measures set forth in the Environmental
Impact Assessment (“EIA”) and the Environmental Management Plan (“EMP”) of the
project attached in Section 6- Employer’s Requirements. Work shall not commence on
the Site until the no objection of SSEMP has been obtained from the Project Manager and
is being implemented.
The Contractor shall (a) establish an operational system for managing environmental
impacts, (b) comply with the approved SSEMP and any corrective or preventative actions
set out in safeguards monitoring reports that the Employer will prepare from time to time
to monitor the implementation of the project EMP through the SSEMP, (c) allocate the
budget required to ensure that such measures, requirements and actions are carried out,
(d) submit semi-annual reports on the compliance of such measures to the Employer.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
238
8-4 Section 8: Special Conditions of Contract
10.2 There shall be no work nor construction activities at the Site or any part thereof (as the
case may be) unless the Employer has granted access to the Site or part thereof (as the
case may be) in accordance with this Subclause 10.2.
13. Securities
13.3.1 Within Twenty-Eight (28) days of the receipt of notification of award from CESL, the
successful bidder shall furnish the Performance Securities in the form of Demand Draft/
Pay Order or Bank Guarantee for 10% of the total contract value.
7037 CESL578807920
Failure of the bidder(s) to comply with the requirements of IFB/Tender/NIT/LOA shall constitute
sufficient grounds for the annulment of the award and forfeiture of the Performance Security.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
239
Section 8: Special Conditions of Contract 8-5
13.3.2 The performance security shall be in the form of the Bank Guarantee as per form included
in Section 9 (Contract Forms).
13.3.3 The performance security shall not be reduced on the date of the Operational Acceptance.
19. Subcontracting
22. Installation
22.2 Labor
22.2.5 Working Hours
(a) Normal working hours are: 8 hours per Shift from 9:00 AM to 6:00 PM (one hour
break)
The Contractor shall include in the program to be submitted for the execution of the
Facilities under Subclause 18.2 an alleviation program for Site staff and labor and
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
240
8-6 Section 8: Special Conditions of Contract
their families in respect of STI and STD including HIV/AIDS. The STI, STD and
HIV/AIDS alleviation program shall indicate when, how and at what cost the
Contractor plans to satisfy the requirements of this Subclause and the related
specification. For each component, the program shall detail the resources to be
provided or utilized and any related subcontracting proposed. The program shall
also include provision of a detailed cost estimate with supporting documentation.
Payment to the Contractor for the preparation and implementation this program
shall not exceed the amount dedicated for this purpose.
After the existing paragraph in GCC 22.2.7 (a), add the following:
“The Contractor is responsible for establishment of preventive and emergency
preparedness and response measures to avoid, and where avoidance is not
possible, to minimize, adverse impacts and risks of the construction site work to the
health and safety of local communities.
Within 28 days of the Effective Date the Contractor shall submit a detailed Site
Specific Health and Safety Management Plan (SSHSMP), based on the
Environmental Health and Safety Management Plan submitted in the technical
proposal, for the Project Manager ’s no objection showing how he/she intends to
comply with the local Health and Safety laws and regulations and other specific
requirements prescribed in the Contract, taking into account the Supplementary
Information in Section 6- Employer’s Requirements. Work shall not commence on
the Site until the confirmation of no objection of the SSHSMP has been obtained
from the Project Manager and is being implemented.
Where unanticipated health and safety hazards or risks become apparent during
the Contract, the Contractor is required to update the SSHSMP to outline the
potential impacts to site works and associated mitigation measures for the Project
Manager’s no objection.
The Contractor shall comply with the approved SSHSMP and any corrective or
preventative actions set out in safeguards monitoring reports that the Employer will
prepare from time to time to monitor the implementation of the project EMP through
the SSHSMP.
In particular, the Contractor is required to provide all personnel on site including
Employer’s Personnel and visitors with personal protective equipment, including
protection for feet (safety boots), head, eyes, ears (safety helmets) and hands, etc.,
in accordance with the Contractor’s SSHSMP. The Contractor should ensure that
his Subcontractors comply with the SSHSMP and provide all such necessary
equipment to their personnel.
The Contractor shall bear the costs to ensure that such measures, requirements
and actions are carried out.
The Contractor shall submit semi-annual reports on the compliance of such
measures to the Employer.”
Add after the existing paragraph in GCC 22.2.7 (c) the following:
“In the event of a significant injury involving medical treatment or hospitalization and
fatal accident the Contractor shall notify the Project Manager immediately by verbal
communication and submit a formal report as soon as practicable after its
occurrence. For all accidents, whether fatal or not, the Contractor shall also notify
the appropriate local authorities in accordance with the Laws of the Country.”
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
241
Section 8: Special Conditions of Contract 8-7
25.2.2 The Operational Test of the Facilities shall be successfully completed within 7 days from
the date of Completion.
26.2 Applicable rate for liquidated damages: 0.5% of total contract value per week
26.3 No bonus will be given for earlier Completion of the Facilities or part thereof.
27.10 The critical components covered under the extended defect liability are Solar Panels, EV
Chargers and Battery alongwith all individual components. and the period shall be 6 years
from the date of commissioning.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
242
8-8 Section 8: Special Conditions of Contract
42. Termination
45.1 The Dispute Board shall be appointed within 28 days after the Effective Date.
The Dispute Board shall be 3 members
List of potential Dispute Board members is: MD, CESL
45.3 This sentence shall be added as last paragraph in GCC Subclause 45.3:
If the decision of the Dispute Board requires a payment by one Party to the other Party,
the Dispute Board may require the payee to provide an appropriate security in respect of
such payment.
(b) Contracts with contractors being nationals of the Employer’s country: Any
dispute between the employer and a contractor who is a national of the Employer’s
country arising in connection with the present contract shall be referred to arbitration in
accordance with the laws of the Employer’s country.
45.6 GCC Subclause 45.6 shall be replaced with the following sentence:
In the event that a Party fails to comply with a Dispute Board decision which has become ether
binding or final and binding, then the other Party may, without prejudice to any other rights it may
have, refer the failure itself to arbitration under Subclause 45.5 [Arbitration] for summary or other
expedited relief, as may be appropriate. Subclause 45.3 [Obtaining Dispute Board’s Decision]
and Subclause 45.4 [Amicable Settlement] shall not apply to this reference.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
243
Section 8: Special Conditions of Contract 8-9
CESL will
46. Eligibility
46.1 The Contractor shall have the nationality of an ADB member country. The Contractor shall
be deemed to have the nationality of a country if the Contractor is a citizen or is
constituted, incorporated, or registered, and operates in conformity with the provisions of
the laws of that country. This criterion shall also apply to the determination of the
nationality of proposed subcontractors or suppliers for any part of the Contract including
related services.
46.2 The materials, equipment and services to be supplied under the Contract shall have their
origin in eligible source countries and all expenditures under the Contract will be limited
to such materials, equipment, and services. At the Employer’s request, the Contractor
may be required to provide evidence of the origin of materials, equipment and services.
46.3 For purposes of SCC 46.2, “origin” means the place where the materials and equipment
are mined, grown, produced or manufactured, and from which the services are provided.
Materials and equipment are produced when, through manufacturing, processing, or
substantial or major assembling of components, a commercially recognized product
results that differs substantially in its basic characteristics or in purpose or utility from its
components.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with Battery
Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
244
Section 9: Contract Forms 9-1
Table of Forms
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with
Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
245
9-2 Section 9: Contract Forms
[date of notification]
This is to notify you of our intention to award the contract [insert name of the contract
and identification number, as given in the Bid Data Sheet]. You have [insert number
of days as specified in ITB 40.1 of the BDS] days, from the date of this notification to
(i) request for a debriefing in relation to the evaluation of your Bid, and/or (ii) submit a
bidding-related complaint in relation to the intention for award of contract, in
accordance with the procedures specified in ITB 45.1.
1. List of Bidders
Bid Price as Read Evaluated Bid
Name of Bidder
Out at Opening Price
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………………………………………………
………………………………………………………
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with
Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
246
Section 9: Contract Forms 9-3
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with
Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
247
9-4 Section 9: Contract Forms
Letter of Acceptance
[date]
This is to notify you that your Bid dated [date] for execution of the [name of the contract
and identification number, as given in the Bid Data Sheet] for the Contract Price in the
aggregate of [amounts in words and figures] [name of currency], as corrected and
modified in accordance with the Instructions to Bidders is hereby accepted by our
Agency.
You are requested to furnish the Performance Security within 28 days in accordance
with the Conditions of Contract and any additional security required as a result of the
evaluation of your bid, using for that purpose one of the Performance Security Forms
included in Section 9 (Contract Forms) of the Bidding Document.
Authorized Signature:
Name of Agency:
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with
Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
248
Section 9: Contract Forms 9-5
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with
Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
249
9-6 Section 9: Contract Forms
Contract Agreement
THIS AGREEMENT made on the [ insert number ] day of [ insert month ], [ insert
year ],
BETWEEN
(1) [ name of the employer ], a corporation incorporated under the laws of [ country
of the Employer ] and having its principal place of business at [ address of the
Employer ] (hereinafter called “the Employer”), and (2) [ name of the contractor ], a
corporation incorporated under the laws of [ country of the contractor ] and having its
principal place of business at [ address of the contractor ] (hereinafter called “the
Contractor”).
1
Tables of Adjustment Data may be added if the contract provides for price adjustment (see GCC 11).
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with
Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
250
Section 9: Contract Forms 9-7
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with
Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
251
9-8 Section 9: Contract Forms
Each party shall use its best efforts to fulfill the above
conditions for which it is responsible as soon as practicable.
3.2 If the conditions listed under 3.1 are not fulfilled within 2
months from the date of this Contract notification because
of reasons not attributable to the Contractor, the parties shall
discuss and agree on an equitable adjustment to the
Contract Price and the Time for Completion and/or other
relevant conditions of the Contract.
_________________________________
2
Or Uniform Customs and Practice for Documentary Credits 2007 Revision, ICC
Publication No. 600 (or the latest version).
Article 4 4.1 The address of the Employer for notice purposes, pursuant
Communication to GCC 4.1 is: [ Employer's address ].
s
4.2 The address of the Contractor for notice purposes, pursuant
to GCC 4.1 is: [ Contractor's address ].
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with
Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
252
Section 9: Contract Forms 9-9
IN WITNESS WHEREOF the Employer and the Contractor have caused this
Agreement to be duly executed by their duly authorized representatives the day and
year first above written.
[ Signature ]
[ Title ]
in the presence of
[ Signature ]
[ Title ]
[ Signature ]
[ Title ]
in the presence of
[ Signature ]
[ Title ]
APPENDIXES
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with
Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
253
9-10 Section 9: Contract Forms
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with
Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
254
Section 9: Contract Forms 9-11
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with
Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
255
9-12 Section 9: Contract Forms
Schedule No. 1 - Plant and Mandatory Spare Parts Supplied from Abroad
In respect of plant and mandatory spare parts supplied from abroad, the following
payments shall be made:
Ten percent (10%) of the total CIP amount as an advance payment against receipt of
invoice and an irrevocable advance payment security for the equivalent amount made
out in favor of the Employer. The advance payment security may be reduced in
proportion to the value of the plant and mandatory spare parts delivered to the site,
as evidenced by delivery documents.
Sixty percent (60%) of the total or pro rata CIP or amount upon Incoterm “CIP,” upon
delivery to the site within 45 days after receipt of invoice.
Twenty percent (20%) of the total or pro rata CIP or amount upon issue of the
Completion Certificate, within 45 days after receipt of invoice.
Ten percent (10%) of the total or pro rata CIP or amount upon issue of the Operational
Acceptance Certificate, within 45 days after receipt of invoice.
Schedule No. 2 - Plant and Mandatory Spare Parts Supplied from Within the
Employer’s Country
In respect of plant and mandatory spare parts supplied from within the Employer’s
country, the following payments shall be made:
Ten percent (10%) of the total EXW amount as an advance payment against receipt
of invoice, and an irrevocable advance payment security for the equivalent amount
made out in favor of the Employer. The advance payment security may be reduced in
proportion to the value of the plant and mandatory spare parts delivered to the site,
as evidenced by delivery documents.
Sixty percent (60%) of the total or pro rata EXW amount upon Incoterm “Ex-Works,”
upon delivery to the site within 45 days after receipt of invoice.
Twenty percent (20%) of the total or pro rata EXW amount upon issue of the
Completion Certificate, within 45 days after receipt of invoice.
Ten percent (10%) of the total or pro rata EXW amount upon issue of the Operational
Acceptance Certificate, within 45 days after receipt of invoice.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with
Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
256
Section 9: Contract Forms 9-13
Ten percent (10%) of the total design services amount as an advance payment
against receipt of invoice and an irrevocable advance payment security for the
equivalent amount made out in favor of the Employer.
Ninety percent (90%) of the total or pro rata design services amount upon acceptance
of design of the Facilities by the Project Manager within 45 days after receipt of
invoice.
Ten percent (10%) of the total installation and other services amount as an advance
payment against receipt of invoice and an irrevocable advance payment security for
the equivalent amount made out in favor of the Employer. The advance payment
security may be reduced in proportion to the value of work performed by the Contractor
as evidenced by the invoices for installation services.
Sixty percent (60%) of the measured value of work performed by the Contractor, as
identified in the said Program of Performance, during the preceding month, as
evidenced by the Employer’s authorization of the Contractor’s application, will be
made monthly within 45 days after receipt of invoice.
Twenty percent (20%) of the total or pro rata value of installation services performed
by the Contractor as evidenced by the Employer’s authorization of the Contractor’s
monthly applications, upon issue of the Completion Certificate, within 45 days after
receipt of invoice.
Ten percent (10%) of the total or pro rata value of installation services performed by
the Contractor as evidenced by the Employer’s authorization of the Contractor’s
monthly applications, upon issue of the Operational Acceptance Certificate, within 45
days after receipt of invoice.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with
Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
257
9-14 Section 9: Contract Forms
When applying for certification and making payments, the procedures shall be as
follows:
When applying for certification and making payments, the procedures shall be
as follows:
(ii) Upon such notification, the Employer/ Employer’s representative shall carry
out the joint inspection along with the Contractor to verify the quantities and
quality of material /work as per the employer’s requirement in section 6,
technical specifications.
(iii) Subsequent to the joint inspection, joint inspection report will be issued with
certified quantities of materials and works, and list of any defects and /or
deficiencies (snag / defects list), jointly signed by Employer/ Employer’s
representative and Contractor. The delivery & installation status for
payments is presumed to be completed at this stage provided there are no
major defects listed.
(iv) Pursuant to GCC clause 24, Employer will issue completion certificate in
respect of the facilities or any part thereof at each designated site or for
each sub-project.
(v) Pursuant to GCC clause 25, the Contractor shall complete commissioning
including commissioning and notify the Employer in writing.
(vi) Pursuant GCC clause 25, Employer will issue operational acceptance in
respect of the facilities or any part thereof at each designated site or for
each sub-project.
(vii) The Contractor shall submit the invoices at respective stages for payments
according to payment terms as specified in Part (A) and (B), together with
submittal of applicable documents including Joint Inspection reports,
completion certificates and operational acceptance certificates as
applicable, to Project Manager, Convergence Energy Services Ltd.
(viii) Payments will be made, within 45 days after receipt of invoices and
documentation in office of Head, Convergence Energy Services Ltd.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with
Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
258
Section 9: Contract Forms 9-15
In the event that the Contractor has duly followed the procedure enumerated above
and the Employer fails to make any payment on its respective due date, the Employer
shall pay to the Contractor interest on the amount of such delayed payment as from
the end of the 45 days period on certified amount due but not paid at the end of such
period
(i) For payment to be made in INR, the State Bank of India six-month MCLR rates
(ii) For payments to be made in foreign currency, the 180-Day Average SOFR
(Secured Overnight Financing Rate)
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with
Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
259
9-16 Section 9: Contract Forms
In accordance with the provisions of GCC Clause 34, the Contractor shall at its
expense take out and maintain in effect, or cause to be taken out and maintained in
effect, during the performance of the Contract, the types of insurance set forth below
in the sums and with the deductibles and other conditions specified. The identity of
the insurers and the form of the policies shall be subject to the approval of the
Employer, such approval not to be unreasonably withheld.
Deductible Parties
Amount From To
limits insured
[in [in
[names] [place] [place]
currency(ies)] currency(ies)]
110% of (Ex
Contractor and Dispatch Site
works/CIP Nil
Employer Location Location
Price)
Deductible Parties
Amount From To
limits insured
[in [in
[names]
currency(ies)] currency(ies)]
Contractor Up to
110% of (Ex
/Sub- Receipt defect
works/CIP Nil
Contractor and at site liability
Price)
Employer period
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with
Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
260
Section 9: Contract Forms 9-17
Deductible Parties
Amount From To
limits insured
[in [in
[place
currency(ies) currency(ies) [names] [place]
]
] ]
As per
approved Up to
safety plan, Contractor/Su Commencemen defect
Nil
EMP and b Contractor t of work liability
statutory period
requirements
Details: Nil
The Employer shall be named as co-insured under all insurance policies taken out by
the Contractor pursuant to GCC Subclause 34.1, except for the Third Party Liability,
Workers’ Compensation, and Employer’s Liability Insurance, and the Contractor’s
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with
Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
261
9-18 Section 9: Contract Forms
Subcontractors shall be named as co-insureds under all insurance policies taken out
by the Contractor pursuant to GCC Subclause 34.1, except for the Cargo, Workers’
Compensation and Employer’s Liability Insurance. All insurer’s rights of subrogation
against such co-insureds for losses or claims arising out of the performance of the
Contract shall be waived under such policies.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with
Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
262
Section 9: Contract Forms 9-19
The Employer shall at its expense take out and maintain in effect during the
performance of the Contract the following insurance policies.
Details: Nil
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with
Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
263
9-20 Section 9: Contract Forms
Time for
Completion from
# Facilities Applicable Lots
effective date*
(months)
Site Survey, Design and Feasibility
1. All Lots 0.5 Months
Report
Procurement and supply of all materials
2. All Lots 1 Months
and equipment
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with
Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
264
Section 9: Contract Forms 9-21
Appendix 5: List of Major Items of Plant and Services and List of Approved
Subcontractors
The following Subcontractors and Manufacturers are approved for carrying out the
item of the facilities indicated. Where more than one Subcontractor is listed, the
Contractor is free to choose between them, but it must notify the Employer of its choice
in good time prior to appointing any selected Subcontractor. In accordance with GCC
Subclause 19.1, the Contractor is free to submit proposals for Subcontractors for
additional items from time to time. No Subcontracts shall be placed with any such
Subcontractors for additional items until the Subcontractors have been approved in
writing by the Employer and their names have been added to this list of Approved
Subcontractors.
Major Items of
Approved Subcontractors
Plant and Nationality
and Manufacturers
Services
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with
Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
265
9-22 Section 9: Contract Forms
The following personnel, facilities, works, and supplies will be provided or supplied by
the Employer, and the provisions of GCC Clauses 10, 21, and 24 shall apply as
appropriate.
All personnel, facilities, works, and supplies will be provided by the Employer in good
time so as not to delay the performance of the Contractor, in accordance with the
approved Time Schedule and Program of Performance pursuant to GCC Subclause
18.2.
Unless otherwise indicated, all personnel, facilities, works, and supplies will be
provided free of charge to the Contractor.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with
Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
266
Section 9: Contract Forms 9-23
Pursuant to GCC Subclause 20.3.1, the Contractor shall prepare, or cause its
Subcontractor to prepare, and present to the Project Manager in accordance with the
requirements of GCC Subclause 18.2 (Program of Performance), the following
documents for
(A) Approval (Project Manager shall be responsible for approval of the following):
1. Designs
2. Drawings
3. BAR Chart/Time Schedule
4. Survey data, drawings, and maps
5. Updated BOQs and cost estimates
5. Design reports and drawings
6. Safety plan
7. Training plan
8. Testing Plan & Commissioning Schedules
9. Dispatch schedules
10. CVs of key staff / skilled workers.
11. Revised schedules of quantities and cost estimates upon survey and
design.
12. Any other document/s required as per the Contract.
(B) Review
Performance Security
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with
Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
267
9-24 Section 9: Contract Forms
We have been informed that [name of the contractor] (hereinafter called “the
Contractor”) has entered into Contract No. [reference number of the contract] dated
[date] with you, for the execution of [name of contract and brief description of plant
and services] (hereinafter called "the Contract").
Furthermore, we understand that, according to the conditions of the Contract, a
performance guarantee is required.
At the request of the Contractor, we [name of the bank] hereby irrevocably undertake
to pay you any sum or sums not exceeding in total an amount of [name of the currency
and amount in words]1 [amount in figures] such sum being payable in the types and
proportions of currencies in which the Contract Price is payable, upon receipt by us of
your first demand in writing accompanied by a written statement stating that the
Contractor is in breach of its obligation(s) under the Contract, without your needing to
prove or to show grounds for your demand or the sum specified therein.
This guarantee shall expire no later than the earlier of
(a) 18 months after our receipt of
(i) a copy of the Completion Certificate; or
(ii) a registered letter from the Contractor, attaching a copy of the notice to the
project manager that the Facilities are ready for commissioning, and stating
that 14 days have elapsed from receipt of such notice (or 7 days have elapsed
if the notice was a repeated notice) and the project manager has failed to issue
a Completion Certificate or inform the Contractor in writing of any defects or
deficiencies; or
(iii) a registered letter from the Contractor stating that no Completion Certificate
has been issued but the Employer is making use of the Facilities; or
(b) the [date] day of [month], [year]2.
Consequently, any demand for payment under this guarantee must be received by us
at this office on or before that date.
1
The guarantor shall insert an amount representing the percentage of the accepted contract amount specified in the contract and
denominated either in the currency(ies) of the contract or in any freely convertible currency acceptable to the Employer.
2
Insert the expected expiration date of the Defect Liability Period. The employer should note that in the event of an extension of the time
for completion of the contract, the Employer would need to request an extension of this guarantee from the guarantor. Such request
must be in writing and must be made prior to the expiration date established in the guarantee. In preparing this guarantee, the Employer
might consider adding the following text to the form, at the end of the penultimate paragraph: “The Guarantor agrees to a one-time
extension of this guarantee for a period not to exceed [6 months][1 year], in response to the Employer’s written request for such
extension, such request to be presented to the Guarantor before the expiry of the guarantee.”
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with
Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
268
Section 9: Contract Forms 9-25
This guarantee is subject to the Uniform Rules for Demand Guarantees (URDG) 2010
Revision, ICC Publication No. 758, except that the supporting statement under Article
15 (a) is hereby excluded.
...................................
[Signature(s) and seal of bank (where appropriate)]
-- Note to Bidder --
If the bank issuing performance security is located outside the Employer’s country,
it shall be counter-guaranteed or encashable by a bank in the Employer’s country.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with
Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
269
9-26 Section 9: Contract Forms
We have been informed that [name of the contractor] (hereinafter called "the
Contractor") has entered into Contract No. [reference number of the contract] dated
[date] with you, for the execution of [name of contract and brief description of plant
and services] (hereinafter called "the Contract").
Furthermore, we understand that, according to the Conditions of the Contract, an
advance payment in the sum [name of the currency and amount in words]1 [amount
in figures] is to be made against an advance payment guarantee.
At the request of the Contractor, we [name of the bank] hereby irrevocably undertake
to pay you any sum or sums not exceeding in total an amount of [name of the currency
and amount in words]2 [amount in figures] upon receipt by us of your first demand in
writing accompanied by a written statement stating that the Contractor is in breach of
its obligation under the Contract because the Contractor:
(a) used the advance payment for purposes other than the costs of mobilization and
cash flow support in respect of the Works; or
(b) has failed to repay the advance payment when it has become due and payable in
accordance with the conditions of the Contract, specifying the amount payable by
the Contractor.
It is a condition for any claim and payment under this guarantee to be made that the
advance payment referred to above must have been received by the Contractor on its
account number [contractorʼs account number] at [name and address of the bank].
The maximum amount of this guarantee shall be progressively reduced by the amount
of the advance payment repaid by the Contractor as indicated in copies of interim
statements or payment certificates, which shall be presented to us. This guarantee
shall expire, at the latest, upon our receipt of a copy of the interim payment certificate,
indicating that 80% of the Contract Price has been certified for payment, or on the
[date] day of [month], [year], 3 whichever is earlier. Consequently, any demand for
1
The guarantor shall insert an amount representing the amount of the advance payment denominated either in the currency(ies) of
the advance payment as specified in the contract, or in any freely convertible currency acceptable to the Employer.
2
Footnote 1.
3
Insert the expected expiration date of the time for completion. The Employer should note that in the event of an extension of the time
for completion of the contract, the Employer would need to request an extension of this guarantee from the guarantor. Such request
must be in writing and must be made prior to the expiration date established in the guar antee. In preparing this guarantee, the
Employer might consider adding the following text to the form, at the end of the penultimate paragraph: “The Guarantor agrees to a
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with
Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
270
Section 9: Contract Forms 9-27
payment under this guarantee must be received by us at this office on or before that
date.
This guarantee is subject to the Uniform Rules for Demand Guarantees (URDG) 2010
Revisions, ICC Publication No. 758 , except that the supporting statement under
Article 15(a) is hereby excluded.1
......................................
[Signature(s) and seal of bank (where appropriate)]
-- Note to Bidder --
If the bank issuing advance payment security is located outside the Employer’s
country, it shall be counter-guaranteed or encashable by a bank in the Employer’s
country.
one-time extension of this guarantee for a period not to exceed [6 months] [1 year], in response to the Employer’s written request for
such extension, such request to be presented to the Guarantor before the expiry of the guarantee.”
1
Or the Employer may use “Uniform Rules for Demand Guarantees (URDG), ICC Publication No. 458, except that subparagraph (ii)
of Sub-article 20(a) is hereby excluded” as appropriate.
Bidding Document for Design, Supply, Erection & Commissioning and O & M of 25/50 kWp Bi-facial Vertical Solar PV along with
Battery Energy Storage System with EV Chargers project Procurement of Plant Single-Stage: One-Envelope
271