Addendum To COC PWD DB Rev.2010 - Rev 1
Addendum To COC PWD DB Rev.2010 - Rev 1
Addendum To COC PWD DB Rev.2010 - Rev 1
_________________________ __________________________
Signature of Contractor Signature of Officer
__________________________
Contractor's Seal
__________________________________ __________________________________
__________________________________ __________________________________
No AMENDMENTS
Delete the entire list of Appendices and replace with the followings :-
Delete the words “in the form as set out in Appendix [ ]”.
Insert the words “Specifications and these Conditions in compliance therewith, using materials, goods and
workmanship of the quality and standards therein specified” after the word “and”.
Substitute the words “limit as set out in Appendix 1 hereto” with the words “provisions of the Employer
current at the time the Variation is being issued“.
12.1 No work under this Contract shall commence unless and until such insurance policies as specified
under Clause 11 and 39 shall have been deposited with the Employer. The Contractor shall produce
to the Employer or the S.O. the original cover notes of the said insurance policies, it shall be
sufficient discharge of his obligations under this clause.
Substitute the words “Twenty one (21)” with the words “Thirty (30)”.
15. Page 24, Clause 22.1 Line 1 and Clause 22.2, Line 4
Substitute the words “Relevant authorities” with the words “Government of Malaysia”.
Substitute the words “six in the evening and six .......” with the words “seven in the evening and seven .......”.
18. Page 27, Clause 30.2, Line 2 and Clause 30.3, Line 1
45.1 If the Contractor fails to complete the Works by the Date for Completion or within any extended time
granted pursuant to Clause 49, the S.O. shall issue a Certificate of Non-Completion to the
Contractor.
45.2 Without prejudice to the Employer’s right to terminate this Contract, when the S.O. issues the
Certificate of Non-Completion, the Employer shall be entitled to recover from the Contractor,
Liquidated and Ascertained Damages calculated at the rate stated in Appendix 1 from the date of
the failure to complete the Works pursuant to Clause 45.1 to the date of the Practical Completion or
the date of termination of this Contract. The S.O. may deduct such Liquidated and Ascertained
Damages from any money due or to become due to the Contractor, failing which such damages
shall be recovered from the Performance Bond or as a debt from the Contractor. The S.O. shall
inform the Contractor in writing of such deduction.
Substitute the words “to be a reasonable amount” with the words “as agreed by the parties hereto, to be the
pre-estimate”.
Substitute the words “making good all .......... under Clause 47” with the words “the whole of the works
comprised in this contract and after the issuance of Certificate of Practical Completion”.
Substitute the last sentence with “The amount of such diminution shall be recoverable by the Employer
from any money due or to become due to the Contractor or as a debt from the Contractor.”
exceptionally inclement weather conditions; if the record from an approved rain gauge or from
Meteorological Department shows that the rain fall in the locality where the Site is situated exceeds 25mm
in one day;”.
Substitute the entire words after the words “PROVIDED THAT” with the words “that the Contractor shall
use constantly his best endeavour to mitigate the cause and that the resultant delay was absolutely beyond
his control and further, the Contractor can prove that the delay affected CRITICAL activities in the approved
Work Programme and finally that the Works was delayed in fact”.
Substitute the words “ninety (90) percent” with the word “seventy five (75) percent”.
Substitute the whole of Clause 54.0 with the new Clause 54.0 as follows:
54.1 Within three (3) months after issuance of the Certificate of Completion of Making Good Defects or
the Certificate of Completion of Maintenance (if any) whichever is the later, the Contractor shall
submit to the S.O a statement of the final account showing in the detail the value in accordance with
the Contract, of the Works carried out together with all further sums which the Contractor considers
to be due to him after giving credit to the Employer for all amounts previously paid by the Employer
and for all sums to which the Employer is entitled under the Contract up to the date of the Certificate
of Completion of Making Good Defects or the Certificate of Completion of Maintenance, as the case
may be. The Final Account shall be supported by all documentation substantiating the value of the
same.
54.2 Upon expiry of the three (3) months period as specified in clause 54.1, the S.O shall proceed to
verify the Final Account based on such documents submitted by the Contractor. The S.O shall issue
a certificate (hereinafter referred to as “the Final Certificate”) stating the amount which in his opinion
is finally due under the Contract from the Employer to the Contractor or from the Contractor to the
Addendum to PWD DB .23102019 AD/4
Employer, as the case may be, after giving credit to the Employer for all amounts previously paid by
the Employer, and for all sums to which the Employer is entitled under the Contract not later than
three (3) months after the Contractor has completely fulfilled his obligations in respect of handing
over of public utilities and services to the relevant authorities as described in the Contract
Documents, whichever is the later, the S.O. shall issue the Final Certificate.
54.3 If the Contractor does not submit the final account within the three (3) months referred to in clause
54.1 the S.O may on the expiry of the said three (3) months give notice in writing to the Contractor
that if the final account is not submitted by the Contractor within two (2) months from the date of the
written notice the S.O may himself prepare the Final Account.
54.5 Where the Employer exercises any right of deductions from monies due or to become due to the
Contractor, the S.O shall inform the Contractor in writing the reason of that deduction.
54.5 No final payment due to the Contractor shall be made unless and until the Contractor shall have
satisfied the S.O by means of a Statutory Declaration made by or on behalf of the Contractor that
the workmen who have been employed by the Contractor on the Works including workmen
employed by sub-contractors, whether nominated or otherwise (including “labour only” sub-
contractors) have received all wages due to them in connection with such employment, and that all
dues or contributions under the Employment Act 1955, the Employee’s Social Security Act 1969, the
Employees Provident Fund Act 1991 and any other laws relevant to the employment of workmen,
have been paid.
Insert the words “Fourteen (14) days” after the words “period of”.
Add Clause 60.2 (a) (vi) and 60.2 (a) (vii) as follows:
(vi) the Contractor fails to pay the wages of their workers who have made a complaint to the labour
office and the complaint is found to be well grounded, or
Substitute the entire paragraph with “being a company, has a winding up petition presented in a High Court
in Malaysia;”.
Substitute the words “clause 60.1l(i)” with the words “clause 60.1(c)(i)”.
Substitute all words “officer named” with the words “Officer Named”.
Substitute the words “Treasury’s Instruction No. 202 as amended” with the words “provisions of the
Employer current at the time the Variation is being issued“.
Retention Money
All payments under clause 53 shall be subjected to a retention of ten percent (10%) up to maximum five
percent (5%) of the work done which will be deducted progressively from the interim payments and shall be
released as followings:-
(a) 2.5% shall be released twelve (12) months after the issuance of the Certificate of Practical
Completion
(b) Balance 2.5% shall be released on the issuance of Certificate of Final Account or on the
issuance of Certificate of Completion of Making Good Defects, whichever is the later
The Contractor’s employees will be liable to pay Malaysian Income Tax in respect of their salaries and
other emoluments as are chargeable therewith under the Law for the time being in force and the Contractor
shall perform such duties in regard to the deduction thereof as may be lawfully imposed on him by the
Government of Malaysia.