Method Statement For Post Fixed Rebar Drill & Fix With Chemical Anchor
Method Statement For Post Fixed Rebar Drill & Fix With Chemical Anchor
Method Statement For Post Fixed Rebar Drill & Fix With Chemical Anchor
M-DT-MS-033000-ST-013-A
AD21094-0201S-FM-18 REV 00
Employer PMC Engineer Contractor
Revision History
02
03
Checked By:
Reviewed By:
Approved By:
2. REFERENCES..................................................................................................................................... 4
4. RESOURCES....................................................................................................................................... 5
5. HSE REQUIREMENTS....................................................................................................................... 7
7. Construction Program.......................................................................................................................... 9
10. Appendices......................................................................................................................................... 10
2. REFERENCES
OSHAD SF CoP
Specification details
033000 CAST-IN PLACE CONCRETE
ACI 318 (ACI 318M) Building Code Requirements for Reinforced Concrete
3. TERMS AND DEFINITIONS
Abbreviation For
PM Project Manager
CM Construction Manager
MS Method Statement
4. RESOURCES
4.4 Equipment
Dispenser gun for chemical injection 1 no
Electric drill machine 1 no
Air blower 1 no
Safety cones, safety protective equipment etc. As per site requirements
Other hand tools Shovel, gloves, goggles,
measuring tape, etc.
General Foreman
General Foreman is responsible for following.
Proper distribution of work force as per requirement of work.
Continuous coordination and follow up of site engineer’s instruction to meet requirements
outlined in method statement during excavation, construction and finishing activities.
Coordination with site safety officer to maintain safe workplace.
To ensure that all the workers have the required information and knowledge of their duties.
Ensure when labor wear suitable eye protection and mask where necessary.
Ensure materials are being stored.
Site Surveyor
The site surveyor is responsible for the following.
Check layout and level for form work as per drawings.
Report to CM/PM if any discrepancy found in site condition & drawings and take advice for
further action prior proceeding with next activity.
Making sure all the equipment used in survey must be calibrated as per planned interval.
5. HSE REQUIREMENTS
Compliance with legal requirements.
a) Once the location is marked, prior to the commencement of drilling. The proper safe workplace is
ensured, and prior necessary coordination is done with MEP.
b) Drilling is commenced using for flute spiral drill bit with carbide head. This will ensure smooth
drilling and penetration into concrete areas but won’t disturb rebar.
7. Construction Program
All the work activity will be performed as per an approved baseline program.
AD21094-0201S-FM-18 REV 00
Contractor Engineer Employer
PROJECT NAME: CORDOBA (Phase-1) at Bloom Living
AD21094-0201S-FM-18 REV 00
Contractor Engineer Employer
PROJECT NAME: CORDOBA (Phase-1) at Bloom Living
AD21094-0201S-FM-18 REV 00
Contractor Engineer Employer
PROJECT NAME: CORDOBA (Phase-1) at Bloom Living
AD21094-0201S-FM-18 REV 00