Method Statement For Post Fixed Rebar Drill & Fix With Chemical Anchor

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 14

Employer PMC Engineer Contractor

PROJECT NAME: CORDOBA (Phase-1) at Bloom Living

Method Statement for Post-Fixed Rebar: Drill &


Fix with Chemical Anchor

M-DT-MS-033000-ST-013-A

AD21094-0201S-FM-18 REV 00
Employer PMC Engineer Contractor

PROJECT NAME: CORDOBA (Phase-1) at Bloom Living

Revision History

Sn. Description Rev. No. Date Status

01 1st Submission A 05-05-2023

02

03

Checked and Approvals


Printed initials in the boxes confirmed that the documents have been reviewed and approved.

Sn. Name Position Signature Date

Checked By:

Reviewed By:

Approved By:

AD21094-0201S-FM-18 REV 00 Page 2 of 14


Employer PMC Engineer Contractor
Project Name: CORDOBA (Phase-1) at Bloom Living
Ms For Post Fixed Rebar Drill & Fix with Chemical Anchor
TABLE OF CONTENTS

1. OBJECTIVE & SCOPE....................................................................................................................... 4

2. REFERENCES..................................................................................................................................... 4

3. TERMS AND DEFINITIONS............................................................................................................... 4

4. RESOURCES....................................................................................................................................... 5

4.1 Approved Material........................................................................................................................... 5


4.2 Approved Sub-contractor and PQ documents......................................................................................5
4.3 Shop drawings................................................................................................................................. 5
4.4 Equipment....................................................................................................................................... 5
4.5 Human resources and RACI Matrix (Contact details to be provided)............................................5
4.6 Roles, Responsibilities and Authorities.......................................................................................... 5

5. HSE REQUIREMENTS....................................................................................................................... 7

6. DETAILED CONSTRUCTION SEQUENCE.......................................................................................8

6.1 Site Planning & Preparation.................................................................................................................... 8

6.2 Work Methodology................................................................................................................................ 9

6.3 Inspection Requirements......................................................................................................................... 9

7. Construction Program.......................................................................................................................... 9

8. Quality Control Requirements............................................................................................................ 10

9. Third Party Approval Requirements, If Any.......................................................................................10

10. Appendices......................................................................................................................................... 10

APPENDIX 1 - INSPECTION AND TEST PLAN (ITP).........................................................................11


APPENDIX 2 - QUALITY INSPECTION CHECKLIST..........................................................................12
APPENDIX 3 - HSE RISK ASSESSMENT...........................................................................................13
APPENDIX 4 – DESIGN CALCULATION, TDS & MSDS....................................................................14

1. OBJECTIVE & SCOPE


This method statement covers the step-by-step procedure and action that should adopt to
undertake rebar drill and fix using chemical anchoring concrete activities. The Scope of this

AD21094-0201S-FM-18 REV 00 Page 3


Employer PMC Engineer Contractor
Project Name: CORDOBA (Phase-1) at Bloom Living
Ms For Post Fixed Rebar Drill & Fix with Chemical Anchor
method statement covers the various requirements to be provided for preparation like
chipping and expose the existing rebar, marking to position the new starter bar location,
reconnaissance to confirm and ensure that the existing rebar don’t get disturbed and then do
core drilling to required depth.

2. REFERENCES

Codes of practice/Legislative code

 OSHAD SF CoP

 Specification details
 033000 CAST-IN PLACE CONCRETE
 ACI 318 (ACI 318M) Building Code Requirements for Reinforced Concrete
3. TERMS AND DEFINITIONS

Abbreviation For

PM Project Manager

CM Construction Manager

Owner Bloom District Properties – Sole Proprietorship LLC

Engineer Dar Al-Handasah

PE/SE Project Engineer / Site Engineer

QA/QC Engineer Quality Assurance & Quality Control Engineer

ITP Inspection & Test Plan

IR / MIR Inspection Request/ Material Inspection Request

Contractor ELM (Emirates Link Maltauro)

HSE Health Safety & Environment

MS Method Statement

4. RESOURCES

4.1 Approved Material


Only approved material will be used including reinforcement, anchoring sealant, etc.

AD21094-0201S-FM-18 REV 00 Page 4


Employer PMC Engineer Contractor
Project Name: CORDOBA (Phase-1) at Bloom Living
Ms For Post Fixed Rebar Drill & Fix with Chemical Anchor
4.2 Approved Sub-contractor and PQ documents.
All the work will be carried out by ELM.

4.3 Shop drawings


All the work will be carried out as per shop drawing and a controlled copy will be made available
with the site team all the time.

4.4 Equipment
Dispenser gun for chemical injection 1 no
Electric drill machine 1 no
Air blower 1 no
Safety cones, safety protective equipment etc. As per site requirements
Other hand tools Shovel, gloves, goggles,
measuring tape, etc.

4.5 Human resources and RACI Matrix (Contact details to be provided)


S. No Designation Name Contact Number Remarks

01 Project Manager Ahmad Zeiter 0561266555

02 Construction Manager Ahmad Abdel Ghani 0555458894

03 Project Quality Manager Mohsin Khan 0589899902

04 Project Safety Manager Najm ul Hassan 0562526739

05 Project Engineer Hany Ghonimy 0501208474

06 QAQC Engineer Muhammad Aamir 0503272119

07 QAQC Inspector Anu Sadanandan 0501651767

08 Site Engineer Hisham Alkhatib 0502387928

09 General Foreman Ram Singh 0568038622

4.6 Roles, Responsibilities and Authorities


Project Manager / Construction Manger
Project Manager/Construction Manager are responsible for overall implementation of this method
statement, and to ensure that project engineer, site engineer and general foreman are well informed of
its required, PM/CM are responsible for

 Providing all resources in terms of manpower, equipment, and material.


 Controlling the coordination between all involved parties to ensure safety, quality and schedule
requirements are met.

AD21094-0201S-FM-18 REV 00 Page 5


Employer PMC Engineer Contractor
Project Name: CORDOBA (Phase-1) at Bloom Living
Ms For Post Fixed Rebar Drill & Fix with Chemical Anchor
 Controlling the progress of work and ensuring all the submittal are made on time and approved
well before starting certain activity.
 Controlling the progress of work and ensure final approval is obtained at least 24 hours before
casting schedule date.
 Review & approve the MS & material in coordination with QA/QC & relevant subcontractor.
Project Engineer /Site Engineer
PE/SE are responsible for the following.
 Organize & deploy the manpower as per site requirements & making sure the required machines
and tools are in good working conditions.
 PE/SE will make sure all the foreman and labor involved in the activity have attend the HSE
toolbox prior start working at site.
 PE/SE will make sure all the work is performed as per approved drawings and method statement.
 Check the work at site prior QA/QC inspection making sure work is ready for inspection as per
approved drawings and project specification.
 PE/SE will make sure timely IR will be raised in coordination with QA/QC engineer to get timely
approval to proceed with next activity.
QA/QC Manager / QC Engineer
QA/QC team is responsible for the following.
 QA/QC engineer will ensure all the work is carried out in accordance with the contract
specification, approved drawings, and approved project quality plan.
 Timely raise of ITR as per approved ITP & make sure work is done as per approved drawings and
MS prior consultant approval.
 Visit the site prior to the consultant visit and make sure work is done as per drawings,
specification, and approved method statement.
 Arrange consultant visit and seek their 1st time approval.
 Arrange other relevant clearances to proceed with casting.

HSE Manager / HSE Engineer


The HSE team is responsible for the following.
 Prior commencement of activity, HSE engineer will brief the work force induction talk on project site
safety requirements.
 Maintain records of accidents & enforce PPE on all staff.
 Inspecting Sites and making sure all the machines and equipment deployed at site complied with
fitness standard.
 Monitoring and providing support during construction of facilities and equipment.
 Identifying hazardous situations and safety-controlled actions.
 Keeping and maintaining company safety records.

AD21094-0201S-FM-18 REV 00 Page 6


Employer PMC Engineer Contractor
Project Name: CORDOBA (Phase-1) at Bloom Living
Ms For Post Fixed Rebar Drill & Fix with Chemical Anchor
 Identify & manage risks associated with the project environment and processes while complying with
regulatory requirements & corporate standard.
 Responsible for Maintain a proactive and demonstrable safety performance that includes compliance
with all safety, health & environmental policies, and procedures.
 Manage & submit HSE reports as required.
 Work effectively with various departments throughout the project to resolve compliance issues.

General Foreman
General Foreman is responsible for following.
 Proper distribution of work force as per requirement of work.
 Continuous coordination and follow up of site engineer’s instruction to meet requirements
outlined in method statement during excavation, construction and finishing activities.
 Coordination with site safety officer to maintain safe workplace.
 To ensure that all the workers have the required information and knowledge of their duties.
 Ensure when labor wear suitable eye protection and mask where necessary.
 Ensure materials are being stored.

Site Surveyor
The site surveyor is responsible for the following.
 Check layout and level for form work as per drawings.
 Report to CM/PM if any discrepancy found in site condition & drawings and take advice for
further action prior proceeding with next activity.
 Making sure all the equipment used in survey must be calibrated as per planned interval.

5. HSE REQUIREMENTS
 Compliance with legal requirements.

 Compliance with system framework OSHAD SF CoP.

 Compliance with ADM requirements.

 All workers must be inducted before the start of work.

 MSRA Need to communicate to all the workers.

 TBT should be conducted, and evidence need to maintain.

AD21094-0201S-FM-18 REV 00 Page 7


Employer PMC Engineer Contractor
Project Name: CORDOBA (Phase-1) at Bloom Living
Ms For Post Fixed Rebar Drill & Fix with Chemical Anchor
 Third party Competency certificates are required for all technical job.

 All plants and equipment must be third party certified.

 Close supervision of the area and proactive monitoring of activities.

 Welfare facilities to be provided to the work force at site.

 Site foreman HSE crew should be vigilant at site.

 PTW work must be obtained before the start of the job.

 Internal HSE inspections should be conducted.

 Machinery, Plant must be inspected with aid of checklist.

 All the workers must use PPE’s.

Emergency Phone Numbers

SN. DESCRIPTION CONTACT NUMBER


01 POLICE 999
02 AMBULANCE 998
03 CIVIL DEFENCE 997
04 ADDC Emergency 991
05 DAR Emergency Details to be provided
06 Contractor PM 0561266555
07 Contractor CM 0555458894
08 Contractor HSE 0562526739

6. DETAILED CONSTRUCTION SEQUENCE

6.1 Site Planning & Preparation


General Requirements

a) Once the location is marked, prior to the commencement of drilling. The proper safe workplace is
ensured, and prior necessary coordination is done with MEP.
b) Drilling is commenced using for flute spiral drill bit with carbide head. This will ensure smooth
drilling and penetration into concrete areas but won’t disturb rebar.

AD21094-0201S-FM-18 REV 00 Page 8


Employer PMC Engineer Contractor
Project Name: CORDOBA (Phase-1) at Bloom Living
Ms For Post Fixed Rebar Drill & Fix with Chemical Anchor
c) Wherever the hole making the procedure as narrated above does not work due to onsite rebar then
the necessary minor shifting of the location is attempted to get clear of the rebar and normal
drilling continued
d) In such specific cases where normal drilling is stopped due to rebar, further site reconnaissance is
done with available drawings to ascertain the reason for obstruction. The assistance of the coring
machine will be utilized to help clear some minor rebar, after join inspection by contractors and
site supervisors.

6.2 Work Methodology


Coring
1. Prior to coring, confirm water and power connection to the machine are in order.
2. The coring machine is properly anchored to slab / beam with mechanical anchors.
3. Start 20Ø core drilling to minimal depth to clear the obstacle.
4. Once the specific obstacle like the edge of rebar, etc. is cleared, then the coring machine is
withdrawn, and the area cleaned.
5. Further normal drilling activity reinstated to continue drilling holes to the required depth.

 Standard Installation Procedure for Post Fixing Rebar


1. As per the attached design calculation from Rawlplug, the minimum required depth is 155 mm
and dia will be 190 for the 20 mm dia rebar.
2. Always Wear Eye Protection when drilling.
3. Drill hole to recommended depth and diameter for dowel bar chosen.
4. Clean hole thoroughly with brush and blower. Alternatively flush with clean water. Insert dowel
bar.
5. Position resin cartridge in gun, remove red plastic seal (if present) and attach nozzle.
6. Dispense resin to waste until correct mixing of resin and hardener is achieved.
7. Insert nozzle to bottom of sleeve and pump in resin, carefully withdrawing nozzle whilst
pumping.
Inject sufficient resin to completely fill sleeve.
8. Push stud into resin with slight twisting motion to ensure adequate coating of stud with resin.
9. Resin will be displaced by stud allowing it to adhere to wall of hole and to allow resin to build up
in any cavity or void.
10. Allow stud to remain undisturbed until recommended curing time has elapsed. Curing time is
temperature dependent.
11. Ensure that as many holes as possible are pre-drilled and cleaned before commencing to pump
resin. This will ensure that resin does not harden in nozzle while subsequent holes are being
drilled.
12. Tighten all fixings to recommended torque setting for anchor size and base material.
13. When resin is no longer required leave nozzle attached to cartridge to ensure that the resin does
not dry out. Attach fresh nozzle at commencement of next job.

6.3 Inspection Requirements


Refer to Appendix 1 ITP

7. Construction Program
All the work activity will be performed as per an approved baseline program.

8. Quality Control Requirements

AD21094-0201S-FM-18 REV 00 Page 9


Employer PMC Engineer Contractor
Project Name: CORDOBA (Phase-1) at Bloom Living
Ms For Post Fixed Rebar Drill & Fix with Chemical Anchor
When using a post-fixed rebar system with chemical anchors, there are several quality control
requirements that should be considered to ensure a safe and reliable installation. Here are some
key points to keep in mind:
 Proper Drill Hole Diameter and Depth: The diameter and depth of the drill hole must be appropriate
for the size of the rebar and the type of chemical anchor being used. The hole diameter should be
slightly larger than the diameter of the rebar to allow for easy insertion, and the depth of the hole
should be at least 10 times the diameter of the rebar to ensure sufficient anchorage.
 Cleaning the Hole: The drill hole must be thoroughly cleaned of any debris or dust to ensure a good
bond between the chemical anchor and the concrete. This can be done by blowing out the hole with
compressed air or using a wire brush.
 Mixing and Application of Chemical Anchor: The chemical anchor must be mixed and applied
according to the manufacturer's instructions, paying close attention to the mixing ratio, mixing time,
and application method. It is important to use the correct amount of adhesive to ensure a strong
bond and to avoid waste.
 Placement and Alignment of Rebar: The rebar must be inserted into the hole immediately after the
chemical anchor has been applied, should be positioned, and aligned correctly. It is important to
make sure that the rebar is fully embedded in the adhesive and that there are no air pockets or voids.
 Curing Time: The chemical anchor requires sufficient curing time before any load can be applied to
the rebar. The curing time will vary depending on the type of adhesive and the environmental
conditions, so it is important to follow the manufacturer's recommendations.
 Inspection: Once the installation is complete, the rebar and chemical anchor should be visually
inspected for any defects or signs of damage. Any issues should be addressed immediately to ensure
the safety and reliability of the installation.
9. Third Party Approval Requirements, If Any
M-SCA-033000-STR-006-A Prequalification for M/s Arab center as a third party for soil,
concrete, and material testing.
10. Appendices

10.1 Inspection and Test Plan (ITP)


10.2 Quality Inspection Checklist
10.3 HSE Risk Assessment
10.4 Design Calculation, TDS & MSDS

AD21094-0201S-FM-18 REV 00 Page 10


Contractor Engineer Employer
PROJECT NAME: CORDOBA (Phase-1) at Bloom Living

APPENDIX 1 - INSPECTION AND TEST PLAN (ITP)

AD21094-0201S-FM-18 REV 00
Contractor Engineer Employer
PROJECT NAME: CORDOBA (Phase-1) at Bloom Living

APPENDIX 2 - QUALITY INSPECTION CHECKLIST

AD21094-0201S-FM-18 REV 00
Contractor Engineer Employer
PROJECT NAME: CORDOBA (Phase-1) at Bloom Living

APPENDIX 3 - HSE RISK ASSESSMENT

AD21094-0201S-FM-18 REV 00
Contractor Engineer Employer
PROJECT NAME: CORDOBA (Phase-1) at Bloom Living

APPENDIX 4 – DESIGN CALCULATION, TDS & MSDS

AD21094-0201S-FM-18 REV 00