CCE-TMS-321 Track Maintenance Requirements and Tolerances v2.10
CCE-TMS-321 Track Maintenance Requirements and Tolerances v2.10
CCE-TMS-321 Track Maintenance Requirements and Tolerances v2.10
CCE DEPARTMENT
CCE-TMS-321
Track Maintenance Requirements and Tolerances
This CCE Department Technical Standard gives the minimum engineering requirements for the
maintenance of track, and includes the allowable tolerances and corresponding actions required
to ensure track safety.
The principles in this Technical Standard are approved by the Head of Department and therefore
constitute mandatory standard practices, which apply throughout the CCE Department.
This standard, along with all CCE Department Standards, is available from the CCE Website.
Electronic copies of the standards are controlled and live. Holders of printed copies of the
standard are responsible themselves for ensuring that they have the most up to date version as
appropriate.
Page 1 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
CONTENTS
2 Definitions 5
2.1 Standard-Specific Definitions 5
4 Implementation 9
4.1 Maintenance Thresholds 9
4.2 Maintenance Activities 10
4.3 Geometry in Plain Track 10
4.4 Check Rail Gauge in Plain Track 13
4.5 Rail 13
4.6 Rail Joints – Maintenance of Jointed Track 15
4.7 Rail Joints – Fishplated 16
4.8 Breather Switches 19
4.9 Points and Crossing Layouts 20
4.10 Securing Points and Crossings Out of Use 24
4.11 Sleepers, Timbers and Bearers 24
4.12 Fastenings, Pads and Insulators 25
4.13 Soleplates, Chairs, Baseplates and Track Fastenings 25
4.14 Ballast 25
4.15 Track Buckles 27
4.16 Maintenance of Drainage 27
4.17 Track Lubrication and De-Icing 27
4.18 Level Crossings 28
4.19 Lineside Signage 28
5 Revision History 30
Page 2 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
1.1 Policy
1.1.1 Track must be effectively maintained and kept in suitable condition for the permitted
speeds, axle loads and gross tonnage of traffic.
1.2 Scope
1.2.1 This standard sets out the engineering requirements for the maintenance of running lines
and sidings, and encompasses both plain line and points and crossings (P&C).
1.2.2 It includes the tolerances to be used when maintaining the track and the corresponding
minimum actions required to ensure the safety of the track.
1.2.3 This standard applies to all maintenance on Iarnród Éireann (IÉ) permanent way
including like-for-like replacement, with new or serviceable components, and drainage.
1.3 Principles
1.3.1 This standard must be complied with by all personnel who are responsible for the
maintenance of track, alignments, layouts and components for use as part of IÉ
infrastructure.
1.3.2 Before placing a line in service following maintenance works on the line, the track
parameters must meet the requirements and tolerances set out in this standard.
1.3.3 Further requirements specific to continuous welded rail (CWR) are set out in CCE-TMS-
342 Prevention of Track Buckling and CCE-TMS-323 Stressing of Rails
1.3.4 The requirements for new track are set out in CCE-TMS-300 Track Construction
Requirements and Tolerances
1.3.5 For calibration of equipment, refer to CCE-QMS-008-001 Equipment Calibration.
1.3.6 In addition to the above, this standard should also be read in conjunction with the
following Iarnród Éireann technical documents:
1.3.6.1 I-PWY-1136 Requirements for Design, Installation and Maintenance of Lineside
Drainage
1.3.6.2 I-PWY-1490 Mobile Gang Work Instructions
1.3.6.3 CCE-TMS-325 Rail Cutting and Drilling
1.3.6.4 CCE-TMS-340 Horizontal Curvature Design
1.3.6.5 CCE-TMS-341 Vertical Curvature Design
1.3.6.6 CCE-TMS-347 Technical Standard for Breather Switches
1.3.6.7 CCE-TMS-362 Management of Rail Failures and Requirements for the Testing of Rails
1.3.6.8 CCE-TMS-365 Technical Standard for Inspection of Points and Crossings
1.3.6.9 CCE-TMS-380 Technical Standard for the Management of User Worked Level Crossings
1.3.6.10 CCE-TMS-382 – Technical Standard for Decision Support Systems at User Worked
Crossings.
1.3.6.11 CCE-TMS-385 Technical Standard for the Application and Management of Permanent
Speed Restrictions
1.3.6.12 CCE-TRK-WKI-001 Lubrication of Slide Chairs / Baseplates in Switches
1.3.6.13 CCE-TRK-WKI-002 Installation and Inspection of G Clamps for Temporary and
Emergency Use in the Running Line
1.3.6.14 CCE-TRK-WKI-024 Manual Method for Measurement of Unloaded 3.0m Short Twist in
Plain Track
Page 3 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
Page 4 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
2 Definitions
Page 5 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
2.1.17 Mean Gauge – Mean track gauge measured over 100 m where the track gauge is the
distance between the running edges of the rails in a track, measured at right angles
between the gauging points 14 mm below the crown of the surface.
2.1.18 Rail Creep – The longitudinal movement of the rails through their fastenings caused by
thermal, traction or braking forces.
2.1.19 Residual Switch Opening (R) – Dimension between the gauge face of the stock rail
and the back of the switch rail, i.e. the gap between the rail heads of adjacent switch
and stock rails on the closed switch side.
2.1.20 Safety Standard (SS): Level 1 – The minimum track standard that sets the safety
threshold below which track must not be allowed to deteriorate. Track below this
threshold requires intervention action within the timescale set out in the procedure.
2.1.21 Track Category – The classification of a section of track by usage and speed so that the
requirements relating to design, maintenance, renewal and inspection of the track may
be specified and applied. There are three categories as follows:
2.1.22 Track Fault – A sub-standard track geometry condition requiring remedial attention. In
this standard, conditions covered by this term include twist, crosslevel, track gauge, top
and lateral alignment.
2.1.23 Track Gauge (G) – The distance between the running edges of the rails in a track,
measured at right angles between the gauging points which are 14 mm below the crown
of the surface.
2.1.24 TSI (Technical Specification for Interoperability) – Specification that ensures
interoperability of trans-European rail systems.
2.1.25 Twist Fault (track twist) – A defect in the track geometry where there is a difference
in crosslevel over a short distance which is greater than a predetermined amount and
which may cause one or more wheels of a vehicle to lose contact with the running
surface of a rail. The track recording vehicle measures the twist faults over base lengths
of 3.0 m (Short), 6.0 m (Medium) and 16.0 m (Long). Twist faults can also be detected
manually using a crosslevel gauge.
Page 6 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
Page 7 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
Page 8 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
4 Implementation
New Works
Standard
CCE-TMS-300 Achieved level
Obligatory after maintenance
Monitor
Track
Condition
Condition of Track
Maintenance
Threshold Level 3
(MT)
Advisory Planned
Maintenance
Maintenance
Limit (ML) Level 2
Advisory
Accelerated
Maintenance
Safety
Standard (SS) Level 1 Immediate Action
Obligatory
Emergency Absolute
Intervention Upper
Block the Line –
(EI) Limit
Section of Line
Page 9 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
Page 10 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
4.3.2.4 For track maintenance tolerances related to gauge in plain track, refer to Appendix A,
A.1.1 and A.1.2.
4.3.2.5 An absolute upper limit, Emergency Intervention Level (EI), exists for wide gauge
which would initiate an emergency blockage of the line, or section of line. The
Emergency Intervention Level (EI) for wide gauge is set out in A.1.1
4.3.2.6 Gauge variations occurring over short lengths give rise to bad riding and must be
corrected. The variation, over five sleepers, must not exceed the limits set out in
Table 2.
Table 2: Permissible Gauge Variations
Track Category I II III
Variation (mm) 6 10 12
4.3.2.7 When measuring track gauge via manual means, consideration must be given to the
movement of the rails under traffic, i.e. the loaded condition. If the track gauge value
obtained via manual measurement is likely to reach the SS limit for the track
category, action must be taken and repairs carried out. The timescale for the removal
of SS defects is given in A.1.1 and A.1.2.
4.3.2.8 Where gauge spread has occurred, gauge tie-bars may be fitted as a temporary
measure to maintain the track gauge within the required tolerances. Permanent
repairs must be made as soon as practicable: e.g. replacement sleepers, attention to
fastenings, fitting of gauge stops. A record of locations with tie-bars on running lines
should be maintained by the Infrastructure Manager, indicating when they were
installed and removed.
4.3.3 Twist
4.3.3.1 Twist is the algebraic difference between two crosslevels taken at a defined base
distance of 3.0 m (Short twist), 6.0 m (Medium twist) and 16.0 m (Long twist). Twist
can be expressed as an actual value or a gradient between the two points of
measurement.
4.3.3.2 The maintenance threshold limits for twist are set out in A.1.3 to A.1.5.
4.3.3.3 An absolute upper limit, Emergency Intervention Level (EI), exists for a Short twist
defect which would initiate an emergency blockage of the line, or section of line. The
Emergency Intervention Level (EI) for Short twist is 1 in 90 (equivalent to 33 mm) for
manual measurement and calculation of twist.
Page 11 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
4.3.3.4 The method for manual measurement and calculation of twist is described in CCE-
TRK-WKI-024 Manual Method for Measurement of Unloaded 3.0m Short Twist in Plain
Track.
4.3.4 Track Alignment
4.3.4.1 Horizontal track alignment and cant must be designed according to CCE-TMS-340
Horizontal Curvature Design.
4.3.4.2 Vertical track alignment and cant must be designed according to CCE-TMS-341
Vertical Curvature Design.
4.3.4.3 Where provided, datum marks must be altered clearly to reflect any changes to
design.
4.3.4.4 Where datum plates are fitted, the track must be maintained to the datum plates in
accordance with the tolerances specified.
4.3.4.5 All existing horizontal curves in Track Categories I and II must be marked in
accordance with CCE-TMS-340. As a minimum for maintenance, marking must be
maintained and visible at both ends of the transition with the transition length, cant
and curve radius.
4.3.4.6 Alterations to track level, alignment and cant (from the original designed geometry,
plain line only) may be made without the need for approval of the STSE within the
limits in Table 3 below and subject to the maintenance of any critical structural or
passing clearances or compliance with positional tolerances.
Table 3: Alteration Limits for Track Alignment & Cant
No Overhead Electrification,
Restricted Overhead
or Standard Overhead
Electrical Clearances
Electrical Clearances
Track Level ±25 mm ±15 mm
Track
±25 mm ±15 mm
Alignment
Cant ±20 mm ±15 mm
4.3.4.7 Larger alterations must have the prior approval of the STSE: e.g. alterations at sites
where “No Tamping” notices are erected, alterations at P&C, areas of existing limited
clearance.
4.3.4.8 Where track is lifted, lowered or slued, consideration must be given to the effect of
any proposals on clearances, cess walkways, six foots, position of overhead wires to
preserve acceptable height and stagger values, etc.
4.3.4.9 For alterations in cant (crosslevel), care must to taken not to introduce a new twist
fault.
4.3.4.10 Following track renewals and in advance of tamping through a worksite, a check must
be made for excessive twist through the worksite and, where necessary, manual
packing of the ballast should be undertaken.
4.3.4.11 Track alignment and cant threshold values are set out in A.1.6 to A.1.10.
4.3.4.12 Following ballast renewals or re-ballasting, and in advance of handback of track where
the final profile may not yet have been achieved, a check must be made to ensure
that the level of the ballast across the entire length of the re-ballasted area is not
above the top of rail level.
Page 12 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
4.4.2 Achievement of the check rail gauge dimension must take precedence over the check rail
flangeway dimension.
4.4.3 The maximum allowable variance of the flangeways from the nominal dimension is given
in A.2.1.
4.4.4 The maximum height that the check rail can protrude above the crown of the adjacent
running rail is given in A.2.2.
Figure 3: Height of Check Rail above Adjacent Running Rail
4.4.5 The check rail gauge of 1549 mm applies whether or not there is any gauge variation or
designed gauge widening.
4.4.6 The check rail must be securely located in its chair or housing.
4.4.7 The check rail must not be subject to lateral movement under the action of traffic.
4.4.8 All flangeways must be kept clear of obstructions, including compacted snow and ice.
4.5 Rail
4.5.1 Rail Failures (including welds)
4.5.1.1 All broken, cracked and damaged rails must be dealt with and reported in accordance
with CCE-TMS-362 Management of Rail Failures and Requirements for the Testing of
Rails.
4.5.2 Rail Head Profile – Plain Track
4.5.2.1 There are four measurements for assessing rail head profile wear in plain track:
a) W1 – Maximum Allowable Vertical Wear
b) W2 – Maximum Allowable Horizontal Wear
c) W3 – Maximum Allowable 45° Wear
d) Side Cut Angle – Maximum Allowable Side Cut Angle (measured at the gauge point
14 mm below the actual crown of the rail)
4.5.2.2 Figure 4 illustrates the rail head wear measurements referred to above.
Page 13 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
4.5.2.3 Rail head profile in plain track is measured by the track recording vehicle (TRV) and
other approved handheld/portable devices.
4.5.2.4 Details of the maximum allowable rail head wear are given in Appendix A, Section A.3,
along with the minimum actions required when the maintenance thresholds are
reached.
4.5.2.5 If the horizontal wear scar reaches the bottom of the running face and is associated
with reduced rail depth, there is a risk of wheel flanges striking fishplates.
4.5.2.6 Allowing these conditions to be reached may lead to other safety-related problems
such as shelling due to high wheel/rail contact stresses. Where the horizontal wear
(W2) reaches 9 mm, the Permanent Way Inspector must report the matter to the
Ultrasonic Supervisor.
4.5.2.7 When horizontal wear (W2) is indicated, gauge must be checked at the same time.
4.5.2.8 The matching of differentially worn rails requires that, when a sideworn rail is to abut
a new or less sideworn rail, the step in the gauge profile must be blended in by
grinding as follows:
a) Blended length must be 1.5 m from the weld or fishplated joint.
b) The sidewear angle of the more sideworn rail must be maintained throughout the
blended length.
c) The gauge corner must be rounded throughout the blended length. Sharp or square
edges are not permitted.
d) A supported grinder (i.e. mounted on the rails) should be used. Manual support is
unlikely to achieve the desired result.
Note: On completion of any joint, the running surfaces (both rail head and running
edge) must be coplanar.
4.5.3 Minimum Rail Heights and Maximum Gall in Plain Track
4.5.3.1 Details on the minimum permissible rail height in plain track are given in Appendix A,
Section A.4. Where either the minimum height or maximum gall is reached, the
situation must be rectified as per the minimum actions set out in A.4.1.
4.5.3.2 Maximum gall of the rail foot must be limited to 3 mm in running lines and in sidings.
However, in areas where the rail is vulnerable to corrosion (e.g. wet tunnels and level
crossings), gall must be monitored once it reaches 2 mm.
4.5.4 Flame-Cut Holes in Rails
4.5.4.1 Flame-cut holes are not permitted in rails.
4.5.4.2 Holes in rails must be drilled in accordance with CCE-TMS-325 Rail Cutting and
Drilling.
4.5.4.3 Where it is required to drill rails for bond holes or other approved signalling or
electrification equipment, the holes must be drilled in accordance with CCE-TMS-325.
Page 14 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
4.5.4.4 Where a flame-cut hole in rail is discovered, the following minimum actions must be
taken:
a) The Permanent Way Inspector (PWI) must be informed
b) Emergency clamped fishplates must be fitted (if not already fishplated)
c) A temporary speed restriction (TSR) of 25 mph max. must be imposed
d) Replacement of the rail must be arranged
e) The Patrolman monitors during routine patrols and/or as directed by the PWI
f) The PWI must report the situation to the Regional Manager and Senior Track &
Structures Engineer
4.5.5 Flame-Cut Rail Ends
4.5.5.1 Flame-cut rail ends are not permitted at fishplated joints.
4.5.5.2 Refer to CCE-TMS-325 for instances where flame-cutting of rail is permissible.
4.5.6 Closure Rails
4.5.6.1 The installation and use of closure rails must comply with CCE-TMS-300. Where
HP335 rail is installed refer to 4.5.7.5
4.5.7 High Performance Rail HP335 (54E1 rail profile)
4.5.7.1 The installation and use of high performance rails must comply with CCE-TMS-300.
4.5.7.2 HP335 rail (54E1 rail profile), one type of high performance rail, has been introduced
for use in plain line on the IÉ network on a test basis. Refer to Technical Bulletin CCE-
TEB-2019-002.
4.5.7.3 Identification of HP335 (54E1 rail profile) is via branding on the web of the rail,
identified by “54 E1 HP”.
4.5.7.4 Care must be taken to ensure that where HP335 rail is installed in the line that
a) Replacement rail components such as IBJs, breather switches, and permanent
closure rails should also be manufactured from HP335 rail.
b) Defective, damaged and broken clips are to replaced with the yellow coated clips
c) Marker posts used to indicate the start and end of the HP335 rail site, must be
maintained and replaced when required. Drawing W496/214A is available on Share
Point.
d) Arc Welding is carried out in accordance with the requirements of the British Steel
Manual Metal Arc (MMA) Repair Procedure, 2017 for HP335 Rail, contained in I-
PWY-1162.
e) Thermit Welding is carried in accordance with the existing SUC SoW-5 Thermit
welding process as per THERMIT® weld Code of Practice.
f) When requesting Arc and/or Thermit Welders through SharePoint, highlight that the
requirement is to weld HP335 rail. This is necessary as the arc welding electrodes
and procedure and the weld portions used in the Thermit welding process are
different to that for the standard rail grade R260.
Page 15 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
4.6.7.3 The remediation works must at a minimum and as necessary include greasing of
joints, shimming where required, as well as torqueing, gaping and rail end
straightening as required.
4.6.7.4 A programme of remediation is to be undertaken on all mainline jointed track at a
maximum interval of 5 years.
4.6.7.5 An intervention of less than 5 years may be required and this is determined on an
annual basis through the annual review.
4.6.7.6 The undertaking of the annual review and the maintenance interventions is to be
managed through IAMS.
Page 16 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
4.7.3 Rail Joints – 36 m Length Rails: Expansion Gaps and Other Requirements
4.7.3.1 The expansion gaps for the setting of 36 m length rails when installed are set out in
Appendix B. The table refers to free rails, i.e. rails that are not fished or fastened
when expansion gaps are being provided.
4.7.3.2 Rails are to be installed with elastic fastenings system.
4.7.3.3 Fishplates must be in good condition, greased and all four bolts torqued to 475 Nm
(350 lbs ft).
4.7.3.4 In jointed track where the rail lengths are 36 m or more, the minimum width and
height of the ballast shoulder are as set out in Table 7 (see Section 4.13).
4.7.3.5 36 m length rails laid in curves must be pressed in the vicinity of the joints.
4.7.3.6 Where re-railing occurs, no fewer than six joints in the contiguous rails are to be
regulated and/or adjacent.
4.7.4 Fishplated Joints, Non-Insulated
4.7.4.1 When fishplates are replaced, both fishplates should be replaced as a pair.
4.7.4.2 Crank rails should be used where it is necessary to join rails of different rail sections.
Cranked fishplates may be used as a temporary measure, 2 months maximum.
4.7.4.3 Non-insulated rail joints must be lubricated at a frequency sufficient to ensure free
expansion of the rails. Refer to I-PWY-1490 Mobile Gang Work Instructions.
Lubrication of rail joints should be carried out in springtime in preparation for the
extreme variation in temperature that can occur during summer, i.e. hot days and
cold nights.
4.7.4.4 Non-insulated rail joints must be adjusted to obtain the required expansion gaps – see
Table 4 for 40’ and 60’ rails, and Appendix B for 36 m rails. This is particularly
important where there is a succession of joints which have closed up because of either
rail creep or poor installation.
4.7.4.5 All fastenings and rail pads must be in good condition and properly installed:
a) Flat-bottom track on concrete sleepers or concrete bearers –
i. All fastenings must be in place and fully tightened.
ii. Under railseat pads must be in place.
b) Flat-bottom track on timber sleepers or crossing timbers, cast iron or steel
soleplates, or special soleplates in P&C –
i. There must be no cracks in the soleplates used.
ii. The rail inclination must be consistent with the fastenings on either side.
iii. If fangbolts are the fastening, there must be at least 2, properly tightened
attaching the rail to each soleplate and sleeper.
iv. All other types of fastening must be in place and fully tightened.
Page 17 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
ii. Steel keys must be used. If there is not a tendency for rail creep at the
location, then Panlock keys should be used. Panlock keys must not be used in
tunnels.
iii. There must be no crack in the chairs, including under the rail seat, being
provided at the joint. It is desirable to use the special joint chairs on the sleeper
at each side of the joint if these are available.
iv. At the non-insulated rail joint, the rail ends must be maintained in the same
plane, in particular the rail heads and running faces.
4.7.4.6 The maximum permitted gap at a rail joint is set out in CCE-TMS-300.
4.7.4.7 Fly-fishing of rail joints in track is not permitted in any circumstances. A fly-fished
joint is a fishplated joint between two rails in which the bolt(s) pass through the
fishplates and one rail only.
4.7.4.8 Joint assemblies must be complete with four bolts.
4.7.4.9 Defective or missing bolts must be dealt with promptly.
4.7.4.10 All bolts and fittings must be regularly checked for tightness and rectified if found
loose. The correct torque for fishplated joints is 475 Nm (350 lbs ft).
4.7.4.11 A check must be made for dipped joints, refer to 4.6.1.10.
4.7.4.12 The sleeper pad must be present either side of the joint.
4.7.5 Insulated Joints – General
4.7.5.1 The maintenance requirements for dry mechanical (i.e. non-glued) insulated joints are
similar to those for non-insulated fishplated joints except that:
a) They must not be lubricated.
b) The rail-end gap must be filled with a tee piece / end post of the correct type.
Damaged tee piece / end posts must be replaced.
c) All insulating parts including rail pads must be kept in good order. Any missing or
damaged parts must be replaced. Particular attention must be paid to the fishing
surfaces in contact with the rails.
d) Any lipping of the rail ends, which might allow electrical contact across the end
post, must be removed.
4.7.5.2 For timber and concrete bearers, the correct rail fittings must be used, i.e. suitable for
the rail section, insulated joint type and bearer type.
4.7.5.3 All insulated joint bolts and fittings must be regularly checked for tightness and,
where applicable, torque. Correct torque for Coronet dry joints is 1200 Nm.
4.7.5.4 The sleeper pad must be present either side of the joint.
4.7.5.5 A check should be made for movement/flexing of the joint under traffic.
4.7.5.6 The joint must be replaced where damage or wear is suspected to be such that the
insulating properties of the shell or end post are degraded. If there is evidence of
wear, notify the SET Inspector for further inspection.
4.7.5.7 Redundant insulated joints generated by track or signalling renewal projects must be
removed from the line in a timely manner.
4.7.6 Insulated Joints – Specific to Glued Joint
4.7.6.1 Insulated joints must be of a 6-hole prefabricated glued type wherever possible and
laid on concrete bearers. In exceptional circumstances where concrete bearers cannot
be used, a derogation must be sought from the Technical Manager, CCE.
4.7.6.2 There must be no debonding of glue or cracks of the liner.
4.7.6.3 Glued joints must not be dismantled in the line. Damaged glued joints must be
replaced entirely rather than repaired.
4.7.6.4 Where HP335 rail is installed refer to 4.5.7.5
Page 18 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
4.7.7 Insulated Joints – Specific to Non-Glued Insulated Joints (also known as dry
joint)
4.7.7.1 Insulating parts must be in good order and any missing or damaged parts replaced.
4.7.7.2 The joint must be replaced where damage or wear is suspected to be such that the
insulating properties of the shell or end post are degraded.
4.7.8 Temporary/Emergency Clamped Joints
4.7.8.1 Temporary fishplated joints must be secured by using two G clamps with a locking
device.
4.7.8.2 The G clamps are used for temporary and emergency repairs only with a temporary
speed restriction (TSR) of 25 mph max.
4.7.8.3 The requirements for the use of temporary clamped joints are set out in CCE-TMS-
300.
4.7.8.4 The requirements for the installation and inspection of temporary clamped joints are
set out in CCE-TRK-WKI-002.
4.7.8.5 Joggle plates must be used for the temporary clamping of defective/broken welds.
4.7.9 Rail Joint Straightening
4.7.9.1 Rail joints, both fishplated and welded, may be straightened in the vertical plane
subject to the following requirements:
a) Equipment and process are subject to approval by the Technical Manager, CCE.
b) Straightening must not be carried out when the rail temperature is above
33 C or below 4 C.
c) Straightening must not be carried out on insulated joints.
d) The rail ends and the rail within 1 m of the weld or joint must be ultrasonically
inspected prior to straightening. If any defect is found, the joint must not be
straightened.
e) The maximum dip to be treated at a welded joint is 3 mm (on a 1-metre straight
edge).
f) Following straightening, each joint or weld must be lifted and packed, any defective
components or pads replaced, and shims inserted where required.
g) Welds which are to be straightened must be verified by a competent person as
suitable for straightening.
h) All joint straightening must be followed, within 14 days, by a further ultrasonic
inspection.
i) Records of joint straightening must be retained by the Infrastructure Manager until
the rails are replaced.
Page 19 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
4.8.5 Strapper rail should be securely fixed to bearers. Any loose bolts should be tightened or,
where required, replaced.
4.8.6 Maintenance tolerances for the overlap dimensions are ±25 mm at breather switches.
4.8.7 Where HP335 rail is installed refer to 4.5.7.5
4.9.2.2 Free Wheel Passage at Switches (Fwps), Dimension 1, Figure 5: The passing wheel
must not be able to strike the open switch rail. Over the whole length of the switch,
the back of the wheel must not be able to strike the back of the switch rail.
4.9.2.3 Free Wheel Passage at Switches (Fwps) maintenance tolerances and required
minimum actions are set out in A.6.3. Refer also to 4.9.3
In addition to the minimum actions set out in A.6.3, it is good practice to always
visually check for “back slapping” when checking the dimension for free wheel
passage to ensure the wheel flange is not making contact with the back of the open
switch.
4.9.2.4 Fixed Nose Protection (Npcf) Dimension 2, Figure 5: The wheel must be kept away
from the crossing nose by the check rail when running through the crossing panel. For
maintenance tolerances and required minimum actions, refer to A.6.4.
4.9.2.5 Free Wheel Passage at Crossing Nose (Fwpcf), Dimension 3, Figure 5: For
maintenance tolerances and required minimum actions, refer to A.6.5.
4.9.2.6 Free Wheel Passage at Check Rail / Wing Rail Entry (Fwpcre), Dimension 4, Figure 5:
For maintenance tolerances and required minimum actions, refer to A.6.6.
4.9.2.7 Free Wheel Clearance at Switches, Dimension 5, Figure 5: Refer to 4.9.3 below.
4.9.3 P&C Layouts – Free Wheel Clearance at Switches
4.9.3.1 Free wheel clearance at switches refers to the flangeway between the back of the
open switch and the stock rail, measured at the end of the head planing (see
Dimension 5 in Figure 5, and also illustrated in Figure 6).
Page 20 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
4.9.3.2 For maintenance purposes, priority must be given to checking the dimensions for
gauge (see A.6.1, A.6.2) and free wheel passage (see A.6.3) as these dimensions
ensure that there is no contact between wheel flanges and the open switch.
Figure 6: Free Wheel Passage
4.9.5.2 The switch tip longitudinal position is measured from the centre line of the first slide
plate to the switch tip, see Figure 7.
Figure 7: Measurement for Switch Tip Longitudinal Position
4.9.5.3 Refer to the relevant standard drawing for single and double slip tolerances.
4.9.6 P&C Layouts – Switch Tip Longitudinal Position: Switch Diamonds
4.9.6.1 Switch diamond toes must be maintained at a nominal distance of 115 mm either side
of the centre of the wing rail bend.
Page 21 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
4.9.8.3 The space between the switch and stock rail must be kept clear of obstructions. Any
compacted snow and ice must be removed after heavy falls of snow.
4.9.9 P&C Layouts – Crossings: Check Rail Gauges and Flangeways
4.9.9.1 Nominal dimensions (i.e. for new installations) are shown in Table 6.
4.9.9.2 For maintenance purposes, priority must be given to checking the dimension for Fixed
Nose Protection (see A.6.4), Free Wheel Passage at Crossing Nose (see A.6.5) and
Free Wheel Passage at Check Rail / Wing Rail Entry (see A.6.6).
Nominal
Nominal Nominal
Type of P&C Check Rail
Track Gauge Flangeway
Gauge
87 BH
1600 41 1559
85/92 FB
Page 22 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
4.9.10.2 The frequency of lubrication must be such that the points are able to move freely. The
points must be reversed during application where practicable so that all slide surfaces
can be lubricated.
4.9.10.3 Low-friction inserts must not be lubricated. However, they must be checked for wear
and any dirt must be removed from the slide surface to avoid abrasion.
4.9.10.4 Roller baseplates must not be lubricated unless this is recommended by the
manufacturer. The rollers work on the principle that, when set, they lift the switch rail
clear of the slide baseplates, ensuring no friction is generated on the slide baseplates.
4.9.10.5 See A.6.12 for the timescale that applies to corrective actions for slide chairs and
baseplates that are dry or have excess residual dirty lubricant.
4.9.10.6 For the application of Teflon-based lubricant, refer to CCE-TRK-WKI-001 Lubrication of
Slide Chairs / Baseplates in Switches.
4.9.10.7 Where the Teflon-based lubricant has been applied, only a compatible and approved
de-icer may be used.
4.9.10.8 De-icer should only be used in adverse weather conditions - i.e. when it is necessary
to use de-icer at point ends for the clearance of snow, frost, etc. It should not be used
in advance of such conditions.
4.9.11 P&C Layouts – Switch Diamonds: Toe-to-Toe Dimension
4.9.11.1 The permitted maintenance tolerances from the manufacturer’s drawings are set out
in A.6.13.
4.9.12 P&C Layouts – Bolts and Other Fastenings
4.9.12.1 All bolts and other fastenings within P&C assemblies must be kept to the correct
torque. Any missing or damaged items must be replaced with items of a compatible
type. See A.6.14 to A.6.17 for the timescale that applies to corrective actions.
4.9.13 P&C Layouts – Stretcher Bar Assembly
4.9.13.1 At least two stretcher bars must be provided per layout.
4.9.13.2 The gap between the top of the stretcher bar and the underside of the foot of the
stock rail must be a minimum of 3 mm and a maximum of 9 mm.
4.9.13.3 Corrective action required for incomplete stretcher bar assembly, defective or missing
insulation bolts or fixings is set out in A.6.15.
4.9.13.4 Loose fastenings can be established by visual inspection and should be reported to the
Signal Maintenance Supervisor. Typical indications of looseness are rust marks,
witness marks in deposits (grease or grime) or shiny surfaces caused by rubbing or
visual evidence that the nut or bolt has moved.
4.9.14 P&C Layouts – Switch and Stock Rail Replacement
4.9.14.1 Under normal circumstances, both switch and stock rail must be replaced together as
a matching half-set to ensure correct fit in the closed position.
4.9.15 P&C Layouts – Diamond Crossings: Replacement and Plain Railing
4.9.15.1 Where it is necessary to change either the switch rails or wing rails of a switch
diamond, the complete half-set (two switch rails and the wing rail) must normally be
changed at the same time.
4.9.15.2 Where it is necessary to plain-rail a diamond crossing by removal of one of the pair of
obtuse crossings (fixed or switch type), check rail cover to the remaining crossing
must be maintained.
4.9.16 P&C Layouts – Crossing Wear
4.9.16.1 The maximum permitted vertical wear at the nose and wing rail for all track categories
is given in A.6.18.
Page 23 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
Page 24 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
4.14 Ballast
4.14.1 General
4.14.1.1 It is necessary to maintain ballast to be clean, well consolidated and of adequate
depth and profile.
4.14.1.2 The quality of ballast used must be in accordance with the requirements set out in
CCE-TRK-SPN-007 Specification for Track Ballast.
4.14.1.3 Adequate quantities of ballast must be provided prior to track maintenance activities
(e.g. relaying, lifting, tamping or lining work) in order to ensure that ballast is
reinstated on completion of the work and any deficiencies are made good.
4.14.1.4 Ballast must be regulated to achieve the ballast shoulder profile. It must normally be
kept clear of fastenings and level with the tops of the sleepers in the five foot. As far
as is practicable, ballast must also be kept clear of electrification and signalling
equipment, and surface cable troughing routes.
4.14.2 Ballast Depth and Profile
4.14.2.1 The following minimum depths of ballast must be maintained as far as possible:
a) Track Category I and II lines – 300 mm
b) Track Category III lines – 200 mm
4.14.2.2 In locations where the ballast width and depth cannot be achieved, derogation must
be sought from the Technical Manager, CCE.
4.14.2.3 In jointed track, the minimum width of ballast shoulder is 300 mm and ballast
shoulder height is zero.
4.14.2.4 In jointed track where the rail lengths are 36 m or more, the minimum width and
height of the ballast shoulder are as set out in Table 7.
Page 25 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
4.14.2.5 In CWR track, the minimum width and height of ballast shoulder are as outlined in
Table 7 below. Any deficiencies must be made good on a planned basis in spring and
autumn.
Table 7: Minimum Ballast Profiles in CWR
Minimum Shoulder Height
Location
Shoulder Width1 Above Sleeper Top
Straight track 400 mm
Curved track with radius greater than 800 m
500 mm 0 to 130 mm in all
and within 90 m of P&C
cases
Curved track with radius 800 m or less
600 mm
Any discontinuity2
Notes:
1. The width of the ballast shoulder is measured outside the sleeper ends.
2. Discontinuities include insulated joints, breather switches and catch points. The wider
shoulder must apply over not fewer than 10 bays each side of the discontinuity.
4.14.2.6 Where sleepers of adjacent tracks are at different levels, the ballast may be heaped at
the end of the higher sleeper.
4.14.3 Temporary Placement of Ballast during Maintenance Activities
4.14.3.1 Ballast may be placed in the five foot where necessary for maintenance of the track
and as long as it is:
a) Clear of points and crossings
b) Clear of rail heads and check rail flangeways
c) Clear of level crossing surfaces and flangeways through the crossings
d) No higher than the plane of the rail heads
e) Reduced to the top of the sleepers as soon as is practicable
4.14.4 Removing Ballast on Lines Open to Traffic during Maintenance Activities
4.14.4.1 On jointed track, ballast must not be removed from more than six consecutive boxes
when the line is open to traffic – except under a temporary speed restriction (TSR) of
25 mph.
4.14.4.2 On CWR track, ballast must not be removed from more than six alternate half boxes
or two consecutive full boxes within a 9 m length when the line is open to traffic –
except under a TSR of 25 mph.
4.14.5 Ballast – Hot and Cold Weather Precautions
4.14.5.1 Ballast must not be removed or disturbed at rail temperatures greater than 32 C.
4.14.5.2 In cold weather conditions, work which disturbs the ballast condition or alters the
alignment of the track is not permitted at rail temperatures below -7 °C.
4.14.6 On-Track Machine (OTM) Works in Cold Weather
4.14.6.1 For the purposes of this section, OTM works include tamping, regulating, ballast
cleaning, dynamic track stabilising and other on-rail maintenance and renewal
machine activities that impact on the track and track bed.
4.14.6.2 The minimum rail temperature permitted for the undertaking of OTM activities is
-7 °C.
4.14.6.3 If, at the commencement of an OTM shift, the rail temperature is above -7 °C but
there is a risk of this minimum temperature being reached, the shift must not
proceed.
4.14.6.4 OTM operations must not be carried out in the following conditions:
Page 26 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
a) Ballast is evidently frozen. This can be determined by walking on the ballast and
assessing it for movement underfoot.
b) The track is covered by snow, as fastenings, ballast or sleepers cannot be easily
seen.
4.14.6.5 Note: Freezing conditions, ice and/or snow will prevent the ballast from being
effectively packed. This may result in an unstable track that is not fully supported by
uniformly compacted ballast, and that has poor durability of track geometry. Further,
in low temperatures (when the tension in CWR is greatest), tamping can result in the
rail tension moving the track laterally inwards as the track is lifted out of the frozen
ballast.
4.14.6.6 Also refer to CCE-TMS-342 Prevention of Track Buckling and the section dealing with
“Precautions Before and During Cold Weather”.
Page 27 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
4.17.2.2 The method of application must ensure a uniform deposit along the running face of
the high (outer) rail, with no deposit on the crown of the rail. On long curves, more
than one application may be required.
4.17.2.3 Lubricators and grease dispense units (GDUs) must be maintained in accordance with
the manufacturer’s instructions.
4.17.2.4 The effectiveness of long-term lubrication can be determined by monitoring of rail
gauge face wear.
Page 28 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
4.19.5 Signage must not be allowed to become obscured by vegetation or graffiti, or damaged
to the extent that it is no longer fit for purpose.
Page 29 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
5 Revision History
Version 2.9 Amendment to standard to facilitate the introduction of high performance rail, HP335 (rail
01/08/2019 profile 54E1) for use in plain line track at nominated test location(s) on the IÉ Network.
Version 2.8 Update to standard for the introduction of the Decision Support System (DSS) and
14/12/2017 associated standard CCE-TMS-382 Technical Standard for Decision Support Systems at
User Worked Crossings.
(New) Addition of section 4.2 Maintenance Activities
(New) Addition of section 4.18.4 Decision Support Systems (DSS) at User Worked Level
Crossings
Version 2.7 Update to section 4.18 due to the recent introduction of the “Flashing White LED Double
16/11/2017 Beacon Sign Board (c/w control box and solar panel) for use at all Advance Warning
Boards, A Boards, refer to W.C. 3762 w.e. 16.04.2017.
(New) 4.18.2 Permanent Speed Restriction Signs must comply with CCE-TMS-385
Application and Management of Permanent Speed Restrictions.
Version 2.6 Addition of section 4.2.4.12 Following ballast renewals or re-ballasting, and in advance of
11/05/2015 handback of track where the final profile may not yet have been achieved, a check must
be made to ensure that the level of the ballast across the entire length of the re-ballasted
area is not above the top of rail level.
Version 2.5 Addition of section “General Requirements for Maintaining Jointed Track”. Addition
25/11/2014 highlighted by a black vertical bar on the right hand side of page, refer to section 4.5
page 15.
! Version 2.4, dated 25/11/2014 issued in error, omitted to include new section “General
Requirements for Maintaining Jointed Track”.
Version 2.4 Addition of section 4.5 general requirements for maintaining jointed track
25/11/2014
Version 2.3, Revisions/amendments from version 2.1 (issued 25/05/2012) to version 2.2.
17/04/2014 Revisions/amendments are highlighted by a black vertical bar on the right hand side of
page.
Update of standard reference numbers throughout document where applicable.
4.2.2.5 and A.1.1: Wide Gauge – Plain Line: Revised EI, SS, ML and MT tolerances for
category I track.
A.6.1: Wide Gauge - Running Rail in P&C: Revised SS and ML tolerances for track
categories I, II and III. Deletion of MT Level 3.
A.6.2: Tight Gauge - Running Rail in P&C: Revised tolerances for all track categories.
Deletion of MT Level 3.
A.6.3: Free Wheel Passage at Switches, Fwps: Deletion of MT Level 3.
A.6.12: Slide Chair Lubrication in P&C: Increase in timescale under minimum actions.
Appendix A: For some track maintenance tolerances, at ML level 2 and MT level 3 there is
a change of wording under “Minimum Actions”
! Version 2.1, dated 28/02/2014 was issued in error, please disregard.
Page 30 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
Version 2.2, ! Version 2.2, dated 17/04/2014 was issued in error, please disregard.
17/04/2014
Version 2.1, Revision to clause 4.8.1 - Notice “Laying in New Points and Disconnection of Redundant
25/05/2012 Points” published in weekly circular 2881, week ending 28/05/2000 supersedes the Notice
“Laying in New Points and Disconnection of Redundant Points” published in weekly
circular 2878, week ending 07/05/2000.
Briefing Note for version 2.0 is still applicable.
Version 2.0, This revised document combines CCE-TMS-321, Version 1.0, and I-PWY-1108 which are
09/01/2012 now both withdrawn.
Version 1.0, First issue. This document replaced I-PWY-1108 which is now withdrawn.
03/11/2010
End of Standard
Page 31 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
This section sets out track maintenance tolerances and the corresponding required minimum actions for each track category. As a general rule,
tighter tolerances and/or reduced response times are required for track in lines with higher permitted speeds.
Page 32 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
12 12 12
MT Level 3 Review to determine if action is required
(1 in 250) (1 in 250) (1 in 250)
*Note: Readings taken from the TRV need to be verified on the ground to ensure they are not false.
Page 33 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
Page 34 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
Note: TRV reading is dynamic and may include voids under sleepers.
Page 35 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
Page 36 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
Page 37 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
The TRV measures the side cut angle relative to the vertical axis of the rail and not to the plane of the running surface of the rails.
Page 38 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
Page 39 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
*The tolerances and minimum actions in A.5.1 should be used as guidance for maintaining evenly spaced sleepers.
Page 40 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
Maximum number of poor sleepers ML Level 2 1 2 3 Inspect and assess within 8 weeks.
in a group of 5.
Notes:
1. Count 3 consecutive poor sleepers as SS Level 1 fault.
2. Count 2 consecutive poor sleepers at a joint as SS Level 1 fault.
3. Where sleepers are defective to the extent of not supporting the track, the incidence should not be
more than 2 sleepers in 5.
A poor sleeper is one that is cracked, rotten or broken and provides inadequate vertical or lateral restraint to the chair, baseplate or rail.
Maximum number of poor sleepers ML Level 2 1 2 3 Inspect and assess within 8 weeks.
in a group of 5.
Note: Where sleepers are defective to the extent of not supporting the track, the incidence should not be
more than 2 sleepers in 5.
Page 41 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
Dimension Legend
Page 42 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
Page 43 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
Maximum permitted dimension from Inspect and verify within 4 weeks. Check for “back
gauge face of the switch rail to the ML Level 2 1549 1549 1549 slapping” and determine if a control measure is
back face of the open switch rail at required.
the end of planing (see Dimension
1, Figure A.2 and figure below).
Check for “back slapping” and determine if a
MT Level 3 1547 1547 1547
control measure is required.
Where Fwps dimension is found to be 1546mm or above Check for “back slapping” at rear of the switch rail.
Notes:
1. The figures in this table are applicable for both 1600mm
and 1597mm gauge.
2. 1546mm is the calculated maximum theoretical value
permitted for Fpws. The figure of 1546mm is derived from
wheelset dimensions/tolerances based on the minimum
wheel back to back dimension and the minimum wheel
flange width permitted.
Page 44 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
Page 45 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
Page 46 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
Page 47 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
UNDER NO CIRCUMSTANCES SHOULD SLIDE CHAIRS WITH SPECIAL LOW-FRICTION INSERTS AND SURFACES BE LUBRICATED.
Page 48 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
Note: Crossing Nose – Check for pack under nose of crossing and secure.
Page 49 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
Page 50 of 51
CCE-TMS-321, Version 2.10 – Track Maintenance Requirements and Tolerances
32 to 31 0
30 to 29 1
28 to 27 2
26 to 25 3
24 to 23 4
22 to 21 5
20 to 19 6
18 to 17 7
16 to 15 8
14 to 13 9
12 to 11 10
10 to 9 11
8 to 7 12
6 to 5 13
Page 51 of 51