In this project you required to propose, design and implement a new IT infrastructure for a company
Satcom company.
Basic switch Configuration and VLAN Configuration
Topology Diagram
Device
Address Subnet Mask Department VLAN
(Display name)
COMP1 10.0.0.1 255.0.0.0 Accounting VLAN100
COMP2 10.0.0.2 255.0.0.0 Accounting VLAN100
COMP3 128.0.0.1 255.255.0.0 ICT VLAN200
COMP4 128.0.0.2 255.255.0.0 ICT VLAN200
COMP5 10.0.0.3 255.0.0.0 Accounting VLAN100
COMP6 10.0.0.4 255.0.0.0 Accounting VLAN100
COMP7 128.0.0.3 255.255.0.0 ICT VLAN200
COMP8 128.0.04 255.255.0.0 ICT VLAN200
1|Page
11. Create and name VLANs 100 and 200, on both switch
VLAN 100 for the Sales Department
VLAN 200 for the Marketing Department
12. Test the connectivity between Comp 1 and Comp 5
13. Send PUD data from comp1 to comp 5
14. Assign switch ports to VLANs on S1 and S2
Fa0/5-fa0/10 for VLAN 100
Fa0/20-fa0/24 for VLAN 200
15. Configure Gigabit Ethernet interfaces 1/1 port in trunk mode and connect the
switches to each other with port Gigabit Ethernet interfaces 1/1on both sides.
16. Show trunk port information.
17. Send PUD from Comp3 to Comp7.
18. Save the configuration on both switches.
19. Remove User Mode password from FLR2SW2 Switch
20. Save the file under desktop by the name Exam one