DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT
DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

PRELIMINARIES AND GENERAL REQUIREMENTS Bill No : 01


SL.
DESCRIPTION QTY UNIT UNIT RATE
NO.
Description of works

The work under this Contract comprises the provision of all materials, plant
and labour of whatever kind necessary and the proper performance of
Note
every operation, required for the complete and proper construction,
completion, and maintenance of the project

The Tenderer shall insert a lump sum or rate to each individual item,
Clause or sub clause in this bill which he considers has a financial
implication or is of financial value. Where the Contractor considers that an
item, clause or sub clause has no financial value he shall insert 'NIL'. No
Note
lump sum shall be inserted covering more than one, item, clause or sub
clause. The value of services and obligations involved in all the items,
clauses and sub clauses in this bill shall not be included in rates or prices
in other bills of quantities, but shall be priced in their totality in this bill.

The Tenderer shall include, the conditions of contract which he considers


Note
has the financial values. For pricing the main points are given below.

1 Restrictions
1.1 Site of the Works

1.1.1 The site is located in Duqm. Item

1.2 Site Inspection

The Contractor is advised to visit and inspect the site before tendering and
1.2.1 to satisfy himself as to the accessibility and full extent and character of the Item
site and of all local conditions and restrictions .

1.3 Access to the site

1.3.1 Access to the site will be from existing roads adjacent to the site. Item

Access to the site may be obtained by prior arrangement with Architect or


1.3.2 Item
Engineer

During the construction and maintenance stages the Contractor will be


responsible for complying with all of the Employer's security and safety
1.3.3 Item
requirements including, but not limited to, obtaining all necessary
security passes for constructional plant and personnel.

During construction the Contractor will afford access to the site to any
persons or Company employed directly by the Employer for the purpose of
carrying out work at the site and will liaise with that person or company to
1.3.4 Item
agree a work procedure to ensure a mutually beneficial programme of work
and to provide such services as are required in accordance with Clause 31
of the Conditions of Contract.

1.4 Use of Site


The site shall not be used for any purpose other than the execution of the
1.4.1 Item
Contract.
The Contractor will be required to make good any damage to the
4.1.2 surrounding properties caused during the execution of the work and to Item
restore to their original condition after the completion of the works.
1.5 Access for Plant

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 2 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT
DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

PRELIMINARIES AND GENERAL REQUIREMENTS Bill No : 01


SL.
DESCRIPTION QTY UNIT UNIT RATE
NO.
The Contractor should allow for all costs involved in making access
1.5.1 arrangements for any items of plant etc., without risk of damage to roads Item
leading to the site and such like, and for reinstatement thereto.
1.6 Limitation of Working Space

The Contractor will be allocated the site as indicated on the Architect /


Engineer site plans. The Contractor must allow for setting of temporary
1.6.1 Item
office accommodation at such other location approved by the Architect /
Engineer which the contractor may provide himself and at his own cost.

The Contractor shall take all reasonable precautions to prevent workpeople


1.6.2 including those employed by Sub-Contractors from trespassing on Item
adjoining owner's property.
1.7 Limitation of Working Hours

Any work which is in accordance with the Conditions of Contract or by


agreement with the Architect / Engineer, executed outside of normal
working hours or on Fridays or Public Holidays, shall be carried out
1.7.1 Item
in such a way as to cause the absolute minimum of disturbance or
inconvenience to the Residents or users of the buildings near or adjacent
to the works.

The Contractor's specific attention is drawn to the clauses in the


specification relating to restriction of placement of certain items of work in
1.7.2 Item
certain weathers / temperature conditions and he is to allow for complying
with these requirements.
1.8 Existing Services

The Contractor shall ascertain for himself the location of existing services
on, under or over the site. He shall take precautions to protect all such
1.8.1 services within the confines of the site, temporarily divert as required, Item
reinstate on completion, and immediately make good any damage at his
own expense all to the satisfaction of the Engineer.

Maintenance and temporary protection of existing services on. under or


1.9
over the site during execution of the works

Relocation of existing services will be procured under a separate contract


1.9.1
but the contractor should additional to this price for the followinq:

Allow for locate, protect, uphold, temporarily divert if necessary and


maintain, all pipes, ducts, drains, sewers, service mains, overhead or
underground electrical/telephone cables, etc., during execution of the
1.9.2 Works. The Contractor shall make good any damage to existing services Item
and/or property however caused at his own expense or pay any costs or
charges in connection. Approval shall be obtained a
minimum of two weeks in advance of any planned interruption of services.

Existing services and their locations may not be fully shown on the
drawings and the Contractor shall liaise with the relevant authorities to
1.9.3 Item
determine the exact nature and full extent of such services which require
protection and maintenance.

1.1 Specifications

Allow for complying with all other requirements of the "preliminaries and
1.10.1 general requirements" of the specification not referred to elsewhere in Item
these Preliminaries.

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 3 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT
DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

PRELIMINARIES AND GENERAL REQUIREMENTS Bill No : 01


SL.
DESCRIPTION QTY UNIT UNIT RATE
NO.
1.11 Drawings

List of Drawings

The drawings used in the preparation of Bills of Quantities are stated in the
tender documents. The Contractor should note that drawings referred to in
1.11.1 the measured work sections do not necessarily state the revision letter of Item
the drawing. The Contractor is to allow for pricing the current revision as
stated in the List of Drawings.

2 Contractor's Administrative arrangements

2.1 Site Administration


The Contractor shall allow for providing all that is required for the proper
administration of the Contract at site level and in particular for complying in
2.1.1 Item
all respects with the relevant Clauses in the Standard Conditions of
Contract.
2.2 Supervision

Detailed Curriculum Vitae of the Contractor's Supervisory staff together


2.2.1 with those of his SubContractor's Supervisors must be submitted for the Item
Engineer's approval prior to commencement of the Works.

The Project Manager/Project Engineer and other senior staff shall not be
2.2.2 Item
changed without one months written notice to the Engineer.

2.3 Security

Allow for providing security to the site. Only those staff and workpeople
2.3.1 Item
directly employed on this project will be allowed on site.

2.4 Safety, Health and Welfare of Workpeople

Provide for all costs and charges incurred by complying with all safety,
health and welfare regulations appertaining to staff and workpeople
2.4.1 Item
employed on the site including those employed by all
Sub-Contractors.

The Contractor shall be responsible for and shall allow for providing
2.4.2 medical facilities including emergency medical facilities for his staff and Item
shall make these available to the Engineer's staff.

Allow for all costs for providing protective clothing and accessories for all
2.4.3 Item
workmen and supervisory staff on site.

2.5 Safety, Health and Welfare of Workpeople (Cont'd)

Contractor's and Sub-contractors operatives will not be allowed to eat and


sleep on site at any time. Proper shaded areas are to be provided within
2.5.1 Item
the site establishment for Contractor's and Sub-contractor's
operatives to ensure they do not move outside the site premises.

2.6 Transport of Workpeople

Allow for the cost of all transport to and from site of the workpeople
2.6.1 Item
engaged on the site in approved vehicles.

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 4 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT
DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

PRELIMINARIES AND GENERAL REQUIREMENTS Bill No : 01


SL.
DESCRIPTION QTY UNIT UNIT RATE
NO.
2.7 Sign boards

The Contractor shall allow for provision, erection and maintenance of 3 No.
signboards to display the project name the names of all Consultants
2.7.1 Item
associated with the and the Contractor's name all as specified and to the
works approval by the Engineer.

The Signboard shall be complete with all necessary foundations, supports,


framing, painting and sign writing in Arabic and English denoting the title of
the project, name of the Employer, and names of
2.7.2 Consultants and Contractor with their respective addresses and Logos. Item
The Contractor shall provide all details of sign board to the Engineer for his
approval before any work is put in hand and to enable erection to
commence in the early stages of the Contract.

3 Constructional Plant

3.1 Small Plant and Tools


Provide for all necessary small plant and tools for the proper execution and
3.1.1 Item
completion of the Contract.
3.2 Scaffolding/working platforms

Provide all necessary temporary scaffolding and working platforms for the
proper execution and completion of the Contract. Alter, relocate and adapt
from time to time as necessary. The Contractor is to ascertain whether any
3.2.1 scaffolding or platform is required by any Sub-Contractor before striking. If Item
the Contractor should strike any of his scaffolding or
working platform and it is so required it shall be reerected at his own
expenses.

3.3 Plant required for Specific Trades


Provide all necessary plant required for specific trades for the proper
3.3.1 Item
execution and completion of the Contract.
3.4 Cranes and Lifting Plan
Allow for all cranes and lifting plant necessary for the safe and efficient
3.4.1 Item
execution of the works to the satisfaction of the Engineer.
3.5 Method statement

A detailed method statement and plan to be submitted to the Engineer for


3.5.1 Item
approval, prior to commencement of the works.

3.6 Site Transport

3.6.1 Allow for site transport. Item

3.7 Plant generally

Allow for all other plant necessary for the safe and
3.7.1 Item
efficient execution of the Works.

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 5 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT
DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

PRELIMINARIES AND GENERAL REQUIREMENTS Bill No : 01


SL.
DESCRIPTION QTY UNIT UNIT RATE
NO.
4 Employer's facilities

4.1 Offices & other facilities for the Employer's representative

Provide ,erect, maintain and remove after the completion of project a


temporary Site office in a porta cabin of suitable size to accommodate 6no
staff for Consultant’s Engineer & for Clients with conference room for 12
persons, with, tables and chairs and adequate number 2 Tons capacity
4.4.1 Item
window type air conditioner. The site office shall have the facilities for toilet
and pantry, including temporary water storage tank and septic tank. Pin up
boards and writing board including racks for storage of drawings shall also
be provided & cleaning equipment and consumables.

The contractor shall be responsible for removing the facilities of Employers


4.4.2 representative and Engineer's site staff, from the site after completion of Item
the works .
The Contractor shall be responsible during the continuance of the Contract
for security of the offices and for all plans, documents and paper and other
4.4.3 Item
articles contained therein. (Including day and night
security for the site).

4.2 Telephones. Fax. ISDN Internet Links and the like

The Contractor shall provide One direct telephone connection at the site
4.2.1 office, and pay all charges for local business calls by the Employer's Item
Representative and Engineer's staff within the Oman.

The Contractor shall provide the ADSL internet connection with a minimum
4.2.2 of 2 MBps speed to Engineer's office, and pay all internet chargers in Item
connection with the Employer's Representative and Engineer staff.

Allow for maintaining fax machine, including supply of cartridges, spares,


4.2.3 Item
and the like.

Allow for maintaining photocopier, including supply of cartridges, spares,


4.2.4 Item
and the like.

4.2.5 Allow for maintaining a Scanner including Supply of Spares and the like. Item

The position of all site offices, stores, etc., shall be to the approval of the
4.2.6 Engineer, and the Contractor must allow for any 'off site' facilities he may Item
require additional to the area allocated to him.

4.3 Attendance on the Engineer

Provide attendance and assistance to the Engineer as requested to


4.3.1 Item
providing access to complicated locations, workinq hours etc .

4.4 Surveying and other equipment

The Contractor shall provide to the Engineer for his exclusive use all
4..4.1 survey equipment and electrical test equipment as described in the Item
Specification.

4.5 Programme and Order of Works

The Contractor shall submit to the Engineer for his Item

a) In addition the Contractor shall at the same time submit to the Engineer
4.5.1 a detailed schedule of items and information that he requires instruction Item
upon for early ordering schedules.

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 6 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT
DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

PRELIMINARIES AND GENERAL REQUIREMENTS Bill No : 01


SL.
DESCRIPTION QTY UNIT UNIT RATE
NO.

b)The Contractor's attention is drawn to the fact that he shall be entirely


responsible for the co-ordination of all works carried out by both his own
workmen and the workmen of Sub-Contractors, and shall be responsible
4.5.2 for ensuring that all Sub-Contractors shop and/or working drawings are Item
submitted to the Engineer for approval in such time as not to prejudice the
expeditious execution of the Works in accordance
with the Contractor's programme.

4.6 Reports

Provide and maintain daily reports, including daily progress photographs,


4.6.1 Item
and delivery records for inspection by the Engineer.

4.7 Progress Reports

Provide progress reports at intervals and in a format as required by the.


4.7.1 Item
Engineer.

4.8 Progress Photographs

Contractor to provide, in weekely intervals, progress colour photographs,


including colour progress photographs of the works taken by the Engineer,
print in duplicate, on glossy paper, properly captioned and bound. All
photographs shall be subject to the Employer's security precautions and
4.8.1 Item
shall not be used for promotional/commercial purposes without written
permission of the Employer. The Contractor shall provide suitable albums
for the correct storage of the above photographs. The copy rights of all
photographs rests with the Employer.

5 CONTRACTOR'S FACILITIES

5.1 Temporary Fencing etc.

Allow for all temporary fencing, hoardings, screens, gantries, etc.,


necessary for the execution of the Works. The Contractor's particular
5.1.1 Item
attention is drawn to the neatness and approval of the hoardings by the
Authorities and the Engineer.

5.2 Temporary Roads

Provide, maintain and alter as necessary temporary roads, paths, hard


5.2.1 standings, pavement crossings and the like to and within the site. Remove Item
and reinstate all ground and work disturbed when required.

5.3 Maintenance of Public and Private Roads

Allow for making good any damage to public or private roads, paths, paved
or landscaped areas. Contractor's Sub- Contractors' and Suppliers'
5.3.1 Item
vehicles must be kept in a clean condition and must not be
allowed to soil public or private areas.

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 7 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT
DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

PRELIMINARIES AND GENERAL REQUIREMENTS Bill No : 01


SL.
DESCRIPTION QTY UNIT UNIT RATE
NO.
5.4 Water for the Works

Note

All services outlet grids - "Water and Electricity" - to be provided around the
work site with adequate safety precautions for easy execution of works.

Provide all water required for the Works and provide and remove on
completion all requisite temporary pipe work, pumps, storage tanks, etc.
5.4.1 Item
The Contractor must include for obtaining water from an idependent
source.

5.5 Electricitv for the Works

Note

All services outlet grids - "Water and Electricity" - to be provided around the
work site with adequate safety precautions for easy execution of works.

Provide all electric light and power required for the Works including all
5.5.1 temporary installations, maintaining, altering and adapting as necessary Item
and remove all temporary installations on completion.

5.6 TEMPORARY WORKS

Traffic Diversions

The Contractor is to maintain at all times the flow of traffic on the existing
roads and is to provide suitable signs, lights and flag men at all times
5.6.1 Item
during the currency of the Contract all to the approval of the
Authorities and the Engineer.

5.7 Temporary lighting

Allow for installation, maintenance and operation during hours of darkness


a system of sufficient artificial lighting of roads, paths, access routes,
5.7.1 working platforms and areas where the works are in operation on site, and Item
that may be used or approached by any persons authorised to be on site
and final removal from site on completion of the works

6 SUNDRIES

6.1 Testing of Materials and the Works


Allow for all tests, factory testing and factory visits etc as required by the
6.1.1 Specification to be carried out including providing all necessary equipment, Item
materials and samples.
6.2 Single Sources of Supply

Where a choice of manufacturer or source of supply is allowed for any


particular product of material, the whole quantity required to complete the
work must be of the same type, manufacturer and/or source. changes will
6.2.1 Item
not be allowed without prior approval of the Engineer, and at no cost to the
Client. Written evidence of sources of supply must be produced when
requested by Engineer.

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 8 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT
DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

PRELIMINARIES AND GENERAL REQUIREMENTS Bill No : 01


SL.
DESCRIPTION QTY UNIT UNIT RATE
NO.
6.3 Samples; generally
Allow for providing and submitting to the Engineer as he may require,
6.3.1 samples of all materials and goods which the Contractor proposes to Item
incorporate in the Works.
Allow for providing sample panels of materials and workmanship as
6.3.2 Item
required by the Specification.
6.4 Disposal of refuse etc.

Keep the site free from debris arising from the Works during the
construction period, and leave the site free from debris and large loose
6.4.1 stones on completion to the satisfaction of the Engineer. All debris arising Item
from the construction to be cleared daily and as required, keeping the site
safe, clean and tidy.

6.5 Site Clearance


Clear the site of all scrub, debris, rubbish etc., in accordance with the
6.5.1 Item
Specification.
6.6 Cleaning the Works
Remove protective casings and coverings and thoroughly clean the Works
6.6.1 Item
at completion to the entire satisfaction of the Enqineer.
6.7 Traffic Regulations
6.7.1 Allow for complying with all traffic regulations. Item
6.8 Fire Fighting Facilities

Provide fire fighting facilities on site to the approval of


6.8.1 Item
the Authorities and the Engineer.

6.9 Maintenance of existing property access


The Contractor is to maintain access to existing properties at all times with
6.9.1 the use of steel plates, ramps, ducts etc. all to the approval of the Item
Engineer.
6.10 Drying the Works

Allow for drying the works in accordance with the Specification and to the
6.10.1 Item
satisfaction of the Engineer.

6.11 Control of noise and pollution

6.11.1 Allow for keeping noise and pollution to an absolute minimum. Item

Take all necessary precautions to reduce noise from plant by means of


6.11.2 Item
mufflers, silencers, screens and the like.

Work entailing excessive noise is to be carried out during suitable hours as


6.11.3 Item
directed by the Engineer.

6.12 Anti-pollution Measures

The Contractor shall take precautions to minimize the pollution of and


6.12.1 Item
disturbance to lands, roads and other places on and around the site.

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 9 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT
DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

PRELIMINARIES AND GENERAL REQUIREMENTS Bill No : 01


SL.
DESCRIPTION QTY UNIT UNIT RATE
NO.
6.13 Statutory Obligations
Allow for complying with statutory obligations and for obtaining all
6.13.1 permissions licenses etc. and paying all fees as required by statutory Item
authorities in connection with the carrying out of the works.
Allow for arranging inspection and the obtaining of all no objection
6.13.2 Item
certificates.

6.13.3 Contractor shall allow for complying with all building regulations. Item

6.14 Site Survey and Grid of Levels

Before commencing excavation or site levelling operations the Contractor


shall conduct a coordinated site survey witnessed by the Engineer, related
to a bench mark referred to in the Contract document and shall prepare a
6.14.1 Item
site plan showing a grid of levels at 5m intervals to the proposed site, the
Contractor shall provide the Engineer with one transparency and two
copies of the site survey plan.

The Contractor shall conduct similar site survey after site levelling
6.14.2 operations and external works have been completed and provide drawings Item
as above.
6.15 Copies of Orders
Provide the Engineer's Representative with a copy of all orders for the
6.15.1 supply of such materials or goods required in connection with the Works as Item
the Engineer's Representative may specify.
6.16 Working Drawings

Allow for preparing and submission to the Engineer of all working drawings
(Shop Drawings and Execution Drawings) and operation and maintenance
6.16.1 instructions manual as detailed in the specification, if Item
these costs are not specifically measured elsewhere in the relevant
sections of this document.

Upon completion of the works, submit two sets of diskettes (AutoCAD


2013) and four copies of all drawings duly marked 'As-Built' clearly defining
all locations, depths shapes and dimensions of all permanent works
6.16.2 Item
executed. The above information shall be bound in white lever arch files.
Drawing layout and lever arch files backs should be as per Architects
request (templates)

6.17 Training of Employer's Personnel


(a) During the execution of the Works the Contractor shall provide such
6.17.1 assistance as may be necessary for the instruction and training of Item
personnel appointed by the Emolover.
(b) The Contractor shall provide all necessary instruction material for this
purpose such as manuals, booklets, pamphlets, drawings, sketches,
models, pictures, photos, colour slides, films, etc. This
6.17.2 instruction material shall become the property of the Employer. If the Item
Employer finds it necessary that personnel visit or stay at manufacturer's or
supplier's premises for training purposes, the Contractor shall provide such
assistance as deemed necessary.
(c) The travelling and living expenses of such personnel shall be borne by
6.17.3 the Employer. The Contractor shall also assist in recruiting of additional Item
personnel if so required.
6.18 Direct Contractors

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 10 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT
DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

PRELIMINARIES AND GENERAL REQUIREMENTS Bill No : 01


SL.
DESCRIPTION QTY UNIT UNIT RATE
NO.
The Tenderer's attention is drawn to the fact that the Employer may
6.18.1 appoint other Contractors to carry out certain items of Specialist Works in Item
accordance with the Conditions of Contract.
6.19 Insurances

6.19.1 Insurance of works etc… Item

6.19.2 Third party insurance. Item

7 OTHER COSTS, ETC.

Allow for all costs, expenses, etc., details of which must be set out below
and extended separately by the Contractor, incurred in carrying out the
requirements of the Contract and not otherwise included in this Bill. All Item
Costs and expenses not entered hereinafter will be deemed to be included
in the prices inserted elsewhere in this Bill;

TOTAL TO THE SUMMARY

ARITHMETIC MISTAKE

QUOTED PRICE

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 11 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD
LOGISTICS S.A.O.C

SL NO ITEM DESCRIPTION UNIT RATE (R.O)

DAYS WORK

The contractor may be required to execute certain works due to the nature of which the method of
valuation will be on a day work basis.

The contractor is to maintain an accurate record of time spent and list of plant and materials used for
each separate instruction given. Day work sheets are to be numbered and should describe full
instructions to which they refer and they are to be summarized, priced and submitted to the Engineer
every week.

LABOUR

The contractor, when tendering, is to quote the rates required for his labourers and craftsmen.

MATERIALS

The cost of materials used in days works shall be charged at invoice costs. All discounts are to be
allowed to the Employer. Invoices are to be made available to the Engineer at the time the relevant
daywork sheets are submitted.

PLANT

The contractor is to enter the rates required for plant and machinery.

The rates are to be comprehensive and shall include fuel, oil, lubricant and all other consumables,
including servicing, repairs and replacements.The rates are to be exclusive of attendants and drivers
who shall be charged at labour rates as set out below.

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 12 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD
LOGISTICS S.A.O.C

SL NO ITEM DESCRIPTION UNIT RATE (R.O)

DAYS WORK

LABOUR

1 Forman nr 2.500 Per Hr.

2 Labourers/ Helpers nr 1.600 Per Hr.

3 Scaffolders nr 1.600 Per Hr.

4 Steel fixers nr 1.700 Per Hr.

5 Carpenters nr 1.800 Per Hr.

6 Masons nr 1.800 Per Hr.

7 Plumbers nr 1.800 Per Hr.

8 Painters nr 1.800 Per Hr.

9 Plant and Machinery Operators nr 2.200 Per Hr.

10 Drivers nr 2.200 Per Hr.

11 Electricians nr 1.900 Per Hr.

12 A.C. Mechanics nr 1.900 Per Hr.

13 Welders nr 1.800 Per Hr.

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 13 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD
LOGISTICS S.A.O.C

SL NO ITEM DESCRIPTION UNIT RATE (R.O)

DAYS WORK

14 Fabricators/ Fitters nr 1.800 Per Hr.

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 14 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD
LOGISTICS S.A.O.C

SL NO ITEM DESCRIPTION UNIT RATE (R.O)

DAYS WORK

PLANT

1 Portable compressor,4.6m3/min. including hoses and tools day 40.000

2 Air compressor,6m3/min. including two hoses and tools day 40.000

3 Concrete mixer, Open drum 0.3/0.2m3 day 30.000

4 Concrete mixer, open drum 0.2/0.15m3 day 20.000

5 Dumper,0.53m3 capacity day 20.000

6 Dumber, 1 m3 capacity day 30.000

7 Vibrator day 5.000

8 Concrete vibrator poker 50mm dia day 5.000

9 Excavator,0.5m3 bucket capacity day 120.000

10 Excavator 1m3 capacity day 140.000

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 15 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD
LOGISTICS S.A.O.C

SL NO ITEM DESCRIPTION UNIT RATE (R.O)

DAYS WORK

11 JCB with operator and fuel day 70.000

12 Showel with operator and fuel day 100.000

13 HC Hand roller (5T) day 40.000

14 Mobile crane,15 tone capacity day 180.000

15 Mobile crane 30 tone capacity day 200.000

16 Tower crane ( … tonnage at maximum reach) day 150.000

17 Generator 10kva day 50.000

18 Generator set:50kva day 100.000

19 water pump 5-10 hp day 10.000

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 16 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD
LOGISTICS S.A.O.C

SL NO ITEM DESCRIPTION UNIT RATE (R.O)

DAYS WORK

20 Van or utility vehicle, 1.5 tone pick up day 30.000

21 Three tone pick up day 30.000

22 water tanker,4000gallon capacity day 50.000

23 20 tone tipper day 80.000

24 30Tonne tipper day 90.000

25 Welding and cutting set day 20.000

26 Scaffolding, mobile tower 5.0m high day 40.000

27 Scaffolding,mobile tower 10.0m high day 60.000

28 Scaffolding,mobile tower 15.0m high day 70.000

Contractor's OH & Profit on Day works of Labour & Plant by percentage. 15%

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 17 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS FOR CIVIL WORKS BUILDINGS BILL NO- 02

RECEPTION BUILDING
LOGISTICS STORAGE

TECHNICAL FACILITY

MHE PARKING SHED


HOUSE & AC PLANT

EXTERNAL WORKS
CUM HELI HANGER
ACCOMMODATION

PUMP ROOM & UG


STORE HOUSE

SENTRY POST
HAZARDOUS
MATERIALS

LV ROOM

HELIPAD
OFFICE

TANK
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

1.0 SUBSTRUCTURE INCLUDING GRADE SLAB


EARTH WORKS
Notes on Measurement:

1. Excavation is to be measured NET without allowance to


working space, Contractor should allow the same on his rate.

General note:

1. Contractor has to visit the site to determine the actual scope


of works for this section.

2. No additional claim will be raised or charged by contractor at


the later stage related to any type of the excavation works.

1.1 EXCAVATION FOR THE FOUNDATION

GENERAL EXCAVATION by MECHANICAL means using JCB,


POCLAINS etc., in all types of soil including dense soil,
1.1.1 disintegrated / weathered / soft rock /(Poclainable) including 710.00 4,627.00 240.00 4,640.00 2,780.00 350.00 186.00 4,200.00 1,225.00 2,240.00 21,198.00 m3
necessary manual excavation for dressing the edges & leveling,
all leads and lifts.

Extra over the excavation for Rock excavation at all locations at


1.1.2 m3
different levels

Excavation for Pits / Trench to any depth in all kinds of soil


1.1.3 including dewatering, shoring and protection of existing adjacent m3
building up to the depth as specified in the drawing .

Extra over the excavation for Rock excavation in Trenches and


1.1.4 m3
Pits at all levels.

Manual excavation in all types of soil, due to existing UG


1.1.5
services or adjacent structures.

DISPOSAL

Conveying the surplus earth and debris from the site to a


selected dumping yard or as directed or beyond the limits of
1.1.6 406.00 2,644.00 135.00 2,650.00 2,340.00 200.00 106.00 2,400.00 750.00 2,240.00 13,871.00 m3
municipality no temporary dumping of debris at any place
without prior written consent of Semac.

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 18 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS FOR CIVIL WORKS BUILDINGS BILL NO- 02

RECEPTION BUILDING
LOGISTICS STORAGE

TECHNICAL FACILITY

MHE PARKING SHED


HOUSE & AC PLANT

EXTERNAL WORKS
CUM HELI HANGER
ACCOMMODATION

PUMP ROOM & UG


STORE HOUSE

SENTRY POST
HAZARDOUS
MATERIALS

LV ROOM

HELIPAD
OFFICE

TANK
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

FILLING

Selected excavated materials & approved by Semac


BACKFILLED into excavation in making up levels including
1.1.7 compaction to achieve the relative compaction of note less than 288.00 1,776.00 96.00 1,690.00 440.00 140.00 830.00 475.00 5,735.00 m3
95%. The filling shall be carried out in layers not exceeding 150
mm in thickness.

Provide for filling into plinth with imported material as per


specification to arrive at the required finished floor levels, in
1.1.8 10.00 1,215.00 1.00 205.00 74.00 1,100.00 2,605.00 m3
layers not more than 150 mm, compacted to achieve not less
than 95 % compaction.

Providing Sub base (wherever indicated in drawings) to receive


1.1.9 Flooring, with 150 mm / 200 mm thick Granular Sub-base class 15.00 520.00 1.00 121.00 8.00 555.00 1,220.00 m3
'B' compacted to achieve minimum 95 % compaction.

Provide for filling with Engineering fill material (wherever


indicated in drawings) to receive foundation n layers not more
1.1.10 406.00 2,644.00 135.00 2,650.00 855.00 200.00 106.00 2,400.00 700.00 10,096.00 m3
than 150 mm, compacted to achieve not less than 95 %
compaction.

GEOMEMBRANE

Providing & Laying geo-membrane of approved make, in


1.1.11 406.00 2,644.00 135.00 2,650.00 855.00 200.00 106.00 2,400.00 700.00 10,096.00 m2
accordance with manufacturer's guidelines

ANTI TERMITE TREATMENT

Providing and Laying Anti-termite treatment using approved


chemical compound and creating a chemical barrier under and
all around the trenches, column pits, basement excavation, top
surfaces of the plinth filling, junctions of walls and floors, along
1.1.12 the external perimeter of the building, below floor, expansion 110.00 3,550.00 50.00 900.00 325.00 46.00 30.00 3,670.00 350.00 6,400.00 15,431.00 m2
joints, joints of underground pipes and conduits, complete by
specialized approved agency with 10 years guarantee. (Payment
will be made only for plinth area)

TO COLLECTION

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 19 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS FOR CIVIL WORKS BUILDINGS BILL NO- 02

RECEPTION BUILDING
LOGISTICS STORAGE

TECHNICAL FACILITY

MHE PARKING SHED


HOUSE & AC PLANT

EXTERNAL WORKS
CUM HELI HANGER
ACCOMMODATION

PUMP ROOM & UG


STORE HOUSE

SENTRY POST
HAZARDOUS
MATERIALS

LV ROOM

HELIPAD
OFFICE

TANK
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

1.2 CONCRETE WORKS


CONCRETE-SUBSTRUCTURE
PLAIN CEMENT CONCRETE WITH OPC

Providing and Pouring in position PLAIN CEMENT CONCRETE


OF GRADE C15, with Ordinary Portlant Cement, using graded
1.2.1 stone aggregate of 20 mm nominal size), UPTO PLINTH LEVEL,
including the cost of Centering, Shuttering and Finishing
Minimum cement content : 290 kg/ cum for OPC.

1.2.1.1 Under foundations, Plinth beams. 5.00 45.00 4.00 50.00 36.00 4.00 3.00 45.00 10.00 640.00 842.00 m3

1.2.1.2 Under Slab on grade, Ramp and external steps 7.00 190.00 1.00 46.00 3.00 1.00 200.00 448.00 m3

PLINTH PROTECTION

Providing Plinth Protection all around the building with plain


cement concrete C:15, 100 mm thick laid to slope having a width
as per drawings, including excavation, levelling, grading and
1.2.1.3 28.00 105.00 48.00 135.00 20.00 44.00 110.00 490.00 m2
compaction of the earth, formwork at sides. Rate to include for
providing hydrocell expansion joints at the junction between the
building and the plinth protection and also at interval of 6 mts.

REINFORCED CEMENT CONCRETE WITH OPC

Providing and Pouring in position REINFORCED CEMENT


CONCRETE OF GRADE C-30, with Ordinary Portland Cement,
using graded stone aggregate of 20 mm nominal size), UPTO
1.2.2
PLINTH LEVEL, excluding the cost of Centering, Shuttering,
Finishing and Reinforcement. Minimum cement content: 350-
380 kg/cum using OPC.

1.2.2.1 Footing 12.00 180.00 5.00 200.00 140.00 7.00 4.00 165.00 30.00 743.00 m3
1.2.2.2 Footing Beam m3
1.2.2.3 Pedestal 6.00 25.00 2.00 37.00 4.00 4.00 25.00 10.00 113.00 m3
1.2.2.4 Plinth beams 6.00 35.00 1.00 55.00 5.00 3.00 40.00 145.00 m3
Slab on grade to be compacted with a double vibrating beam in
1.2.2.5 17.00 695.00 4.00 125.00 8.00 3.00 735.00 1,587.00 m3
panels including using power float.

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 20 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS FOR CIVIL WORKS BUILDINGS BILL NO- 02

RECEPTION BUILDING
LOGISTICS STORAGE

TECHNICAL FACILITY

MHE PARKING SHED


HOUSE & AC PLANT

EXTERNAL WORKS
CUM HELI HANGER
ACCOMMODATION

PUMP ROOM & UG


STORE HOUSE

SENTRY POST
HAZARDOUS
MATERIALS

LV ROOM

HELIPAD
OFFICE

TANK
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

1.2.2.6 Thickening to ground slabs 1.00 35.00 15.00 20.00 71.00 m3


1.2.2.7 Ramps 4.00 30.00 15.00 2.00 60.00 111.00 m3
1.2.2.8 Walls 12.00 160.00 12.00 184.00 m3
1.2.2.9 Platforms 10.00 1,600.00 1,610.00 m3
1.2.2.10 Steps 2.00 12.00 1.00 5.00 1.00 1.00 4.00 26.00 m3
1.2.2.11 Machine Foundations 30.00 30.00 m3

TO COLLECTION

REINFORCEMENT-SUBSTRUCTURE

Reinforcement high yield steel deformed bars conforming to


B.S.4449, FOR R.C.C WORK including straightening, cutting,
bending, placing in position confirming to BS 8666:2005 and
1.3 binding with annealed steel wires with cover blocks all complete 3.45 32.00 2.60 43.00 54.00 2.80 1.80 39.00 5.60 160.00 344.25 t
at all levels, with:(Reinforcement using high tensile strength bars
(Cold twisted/HYSD bars etc.confirming to BS 4461) for RCC
works of dia varying from 8mm to 32 mm)

Hard drawn steel wire fabric BRC Mesh confirming to BS 4482


1.3.1 and BS 4483 in slabs on grade at all levels of specified grade as
mentioned in the drawings

1.3.1.1 Single layer A-252 BRC Mesh in grade slab 18.00 50.00 68.00 m2

1.3.1.2 Double layer A-252 BRC Mesh in grade slab 108.00 21.00 810.00 48.00 987.00 m2

1.3.1.5 Single layer A-393 BRC Mesh in grade slab m2

1.3.1.6 Double layer A-393 BRC Mesh in grade slab 3,450.00 3,670.00 7,120.00 m2

TO COLLECTION

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 21 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS FOR CIVIL WORKS BUILDINGS BILL NO- 02

RECEPTION BUILDING
LOGISTICS STORAGE

TECHNICAL FACILITY

MHE PARKING SHED


HOUSE & AC PLANT

EXTERNAL WORKS
CUM HELI HANGER
ACCOMMODATION

PUMP ROOM & UG


STORE HOUSE

SENTRY POST
HAZARDOUS
MATERIALS

LV ROOM

HELIPAD
OFFICE

TANK
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

FORM WORKS

CENTERING AND SHUTTERING for SUBSTRUCTURE, using


only Plastic Coated Marine grade Ply boards, in good condition
1.4
for all Horizontal & Vertical Work including strutting, propping etc.
and removal of form in all floors (of any height), for:

1.4.1 Sides of Footing 27.00 250.00 12.00 310.00 18.00 12.00 240.00 70.00 939.00 m2

1.4.2 Sides of Footing Beam m2

1.4.3 Sides of Pedestal 41.00 180.00 17.00 275.00 30.00 30.00 175.00 80.00 828.00 m2

1.4.4 Sides of Plinth beams 59.00 320.00 7.00 535.00 30.00 380.00 1,331.00 m2

1.4.5 Sides of Thickening to ground slabs 60.00 42.00 102.00 m2

1.4.6 Sides of Ramps 8.00 90.00 60.00 8.00 110.00 276.00 m2

1.4.7 Sides of Walls 72.00 70.00 142.00 m2

1.4.8 Sides and soffits of Platforms m2

1.4.9 Sides and soffits of Steps 2.00 120.00 4.00 2.00 128.00 m2

1.4.10 Machine Foundations 22.00 22.00 m2

TO COLLECTION

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 22 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS FOR CIVIL WORKS BUILDINGS BILL NO- 02

RECEPTION BUILDING
LOGISTICS STORAGE

TECHNICAL FACILITY

MHE PARKING SHED


HOUSE & AC PLANT

EXTERNAL WORKS
CUM HELI HANGER
ACCOMMODATION

PUMP ROOM & UG


STORE HOUSE

SENTRY POST
HAZARDOUS
MATERIALS

LV ROOM

HELIPAD
OFFICE

TANK
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

1.5 ACCESSORIES/SUNDRY ITEMS


ANCHOR BOLTS

Fixing of Anchor bolts in pedestal with necessary templates for


steel structure columns including positioning, necessary
1.5.1 nr
supports, etc.complete during concreting all as detailed on the
drawings and to the approval of the Engineer.

GROUTING

Grouting under the base plates after completion of erection


works with approved 25mm thick minium high strength non
1.5.2 m2
shrink free flow cementitious grout as specified by manufacturers
and to the approval of the Engineer

Making of pockets, fixing of anchor bolts in pockets & grouting


with high strength non shrink free flow cementitious as specified
1.5.3 nr
by manufacturers and to the approval of the Engineer for
equipment foundation

MS INSERTS

Supplying, Fabricating and Installing M.S. Inserts in Concrete


at all levels with anchors in the form of rods, plates, angles, flats,
1.5.4 kg
etc, complete, as per standard specifications / approved detailed
drawings and as directed by engineer-in-charge.

Supplying, Fabricating and Installing M.S. Inserts in Concrete


at all levels with anchors in the form of I beams /columns, H-
1.5.5 beams/columns, etc, complete, as per standard specifications / kg
drawings and as directed by engineer-in-charge.Exposed
surfaces to be coated with 2 coats of approved primer

MS ANGLES

Supplying, Fabricating & Fixing in position edge protection with


MS Angles of approved thickness & size including 2 coats of
1.5.6 primer and epoxy paint of approved shade for all edges of m
ramps as per approved detailed drawings / standard
specifications and as directed by engineer-in-charge.

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 23 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS FOR CIVIL WORKS BUILDINGS BILL NO- 02

RECEPTION BUILDING
LOGISTICS STORAGE

TECHNICAL FACILITY

MHE PARKING SHED


HOUSE & AC PLANT

EXTERNAL WORKS
CUM HELI HANGER
ACCOMMODATION

PUMP ROOM & UG


STORE HOUSE

SENTRY POST
HAZARDOUS
MATERIALS

LV ROOM

HELIPAD
OFFICE

TANK
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

EXPANSION JOINTS

Provide and lay Expansion Joint with 'HYDROCELL' or


equivalent approved bituminized expansion joint filler of specified
thickness with exposed edges protected by 20 mm deep
1.5.7 62.00 295.00 26.00 710.00 52.00 40.00 260.00 1,445.00 m
'POLYSULPHIDE SEALENT SEALCOAT' / equivalent as mastic
filler, for floor expansion joints, junctions between floors and
walls, complete.

Provide and lay Expansion Joint with 'HYDROCELL' or


equivalent approved bituminized expansion joint filler of specified
thickness with exposed edges protected by 20 mm deep
1.5.8 'POLYSULPHIDE SEALENT SEALCOAT' / equivalent as mastic 305.00 120.00 2,560.00 2,985.00 m
filler, for Slab on grade expansion joints with dowel bars
projecting on either side of slab by 600mm & one side
covered with PVC cap Slab on grade, complete.

Provide and lay Dowel joint with Saw cut and exposed edges
1.5.9 protected by 2 PART POLYSULPHIDE/ POLYTHANE sealant 30.00 725.00 60.00 1,500.00 2,315.00 m
equivalent as mastic filler between floors.

TO COLLECTION

1.6 MASONRY

BLOCK WORKS

Providing and constructing Solid concrete block masonry wall


having compressive strength of 10 N/Sqmm set in in Cement
Mortar 1:4 (OPC) with necessary scaffolding, setting in position,
curing, racking of joints, Rate to include for providing steel mesh
1.6.1
of 100 mm wide at every 4th course, butterfly wall ties @ 0.50m
height to concrete columns, etc., complete as per standard
specifications / approved drawings & as directed by engineer-in-
charge IN SUBSTRUCTURE.

1.6.1.1 390 x 190 x 190 mm size Solid block walls 150.00 3.00 120.00 16.00 180.00 469.00 m2

1.6.1.2 Solid block any thickness for steps 15.00 1.00 10.00 26.00 m3

Providing and constructing Substructure 200mm thick


reinforced hollow block work in CM 1:4 (OPC) with 10mm min
1.6.2 140.00 140.00 m2
dia reinforcement at 400mm c/c and gaps filled with C15 below
plinth level.

TO COLLECTION

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 24 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS FOR CIVIL WORKS BUILDINGS BILL NO- 02

RECEPTION BUILDING
LOGISTICS STORAGE

TECHNICAL FACILITY

MHE PARKING SHED


HOUSE & AC PLANT

EXTERNAL WORKS
CUM HELI HANGER
ACCOMMODATION

PUMP ROOM & UG


STORE HOUSE

SENTRY POST
HAZARDOUS
MATERIALS

LV ROOM

HELIPAD
OFFICE

TANK
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

1.7 METAL WORKS

NON STRUCTURAL METAL WORKS


HANDRAILS

Supplying, fabricating and fixing in postion railing at all levels,


made out of M.S. sections including all necessary brackets,
fixtures, bolts/site welding and with two coats of epoxy paint of
1.7.1 approved shade, over a two coats of primer etc, complete, as m
per standard specifications / approved detailed drawings and as
directed by engineer-in-charge.(contractor to provide shop
drawings for all items prior to manufacturing )

CHEQUERED PLATE

Providing and fixing 8mm thick mild steel Chequered Plates


cover of approved thickness with frame and fixed wherever
required as per drawings, at all levels including 2 coats of primer
1.7.2 16.00 16.00 m2
and epoxy paint of approved shade, etc, complete, as per
standard specifications / approved detailed drawings and as
directed by engineer-in-charge.

Providing and fixing 6mm thick mild steel Chequered Plates


cover of approved thickness with frame and fixed wherever
required as per drawings, at all levels including 2 coats of primer
1.7.3 m2
and epoxy paint of approved shade, etc, complete, as per
standard specifications / approved detailed drawings and as
directed by engineer-in-charge.

TO COLLECTION

1.8 THERMAL AND MOISTURE PROTECTION

Supply and fixing Damp proof membrane, approved 1200 Gauge


(250 micron) Polythene vapour barrier, fused joints, under the
1.8.1 m2
foundations, ramps and ground floors, below plinth protection,
below plinth beams as per drawings
Supply and fixing Damp proof membrane, approved 1000 Gauge
(250 micron) Polythene vapour barrier, fused joints, under the
1.8.2 185.00 4,100.00 70.00 1,475.00 355.00 85.00 48.00 4,380.00 94.00 6,400.00 17,192.00 m2
foundations, ramps and ground floors, below plinth protection,
below plinth beams as per drawings

Providing and applying 2 coats of Bitumen Paint Water Proofing


protective coating on the vertical and top side of the foundations,
1.8.3 160.00 1,250.00 95.00 1,650.00 335.00 112.00 84.00 1,225.00 225.00 80.00 5,216.00 m2
vertical sides of the plinth beams, columns, walls, all coming
below the plinth level as per drawings

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 25 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS FOR CIVIL WORKS BUILDINGS BILL NO- 02

RECEPTION BUILDING
LOGISTICS STORAGE

TECHNICAL FACILITY

MHE PARKING SHED


HOUSE & AC PLANT

EXTERNAL WORKS
CUM HELI HANGER
ACCOMMODATION

PUMP ROOM & UG


STORE HOUSE

SENTRY POST
HAZARDOUS
MATERIALS

LV ROOM

HELIPAD
OFFICE

TANK
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

TO COLLECTION

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 26 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS FOR CIVIL WORKS BUILDINGS BILL NO- 02

RECEPTION BUILDING
LOGISTICS STORAGE

TECHNICAL FACILITY

MHE PARKING SHED


HOUSE & AC PLANT

EXTERNAL WORKS
CUM HELI HANGER
ACCOMMODATION

PUMP ROOM & UG


STORE HOUSE

SENTRY POST
HAZARDOUS
MATERIALS

LV ROOM

HELIPAD
OFFICE

TANK
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

2.0 SUPERSTRUCTURE

CONCRETE WORKS

Providing and Pouring in position REINFORCED CEMENT


CONCRETE OF GRADE C-30, using graded stone aggregate of
2.1 20 mm nominal size), ABOVE PLINTH LEVEL, excluding the
cost of Centering, Shuttering, Finishing and Reinforcement.
Minimum cement content: 330 kg/ cum using OPC

2.1.1 Columns at all heights 7.00 2.00 1.00 65.00 3.00 3.00 2.00 2.00 85.00 m3
2.1.2 Beams/ Tie beams at all levels 9.00 2.00 3.00 125.00 15.00 5.00 3.00 2.00 164.00 m3
2.1.3 Floor Slabs at all levels 25.00 3.00 7.00 280.00 70.00 10.00 9.00 3.00 407.00 m3
2.1.4 Metal Deck Slab Concreting m3
2.1.5 Staircase including riser and treads 45.00 3.00 48.00 m3
2.1.6 Lintels at all levels 1.00 1.00 1.00 55.00 1.00 1.00 1.00 1.00 62.00 m3
2.1.7 Window sills at all levels 1.00 1.00 1.00 30.00 1.00 1.00 1.00 1.00 37.00 m3
2.1.8 Coping 2.00 12.00 14.00 m3
2.1.9 Steel column encasing m3
2.1.10 Walls m3
2.1.11 Upstand 10.00 10.00 m3
2.1.12 Parapet m3

Light Weight Concrete


Light Weight Concrete (C-20, 800-1000 Kg/m3) filling / screed to
2.1.13 the sunken slabs, as required, detailed and instructed to 20.00 20.00 m3
approval of the Engineer

TO COLLECTION

REINFORCEMENT-SUPERSTRUCTURE

Reinforcement high yield steel deformed bars conforming to


B.S.4449, FOR R.C.C WORK including straightening, cutting,
bending, placing in position confirming to BS 8666:2005 and
2.2 binding with annealed steel wires with cover blocks all complete
at all levels, with:(Reinforcement using high tensile strength bars
(Cold twisted/HYSD bars etc.confirming to BS 4461) for RCC
works of dia varying from 8mm to 25 mm)

2.2.1 8 dia to 32 dia 5.80 0.75 1.50 72.00 14.00 2.50 1.75 0.75 99.05 t

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 27 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS FOR CIVIL WORKS BUILDINGS BILL NO- 02

RECEPTION BUILDING
LOGISTICS STORAGE

TECHNICAL FACILITY

MHE PARKING SHED


HOUSE & AC PLANT

EXTERNAL WORKS
CUM HELI HANGER
ACCOMMODATION

PUMP ROOM & UG


STORE HOUSE

SENTRY POST
HAZARDOUS
MATERIALS

LV ROOM

HELIPAD
OFFICE

TANK
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

TO COLLECTION

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 28 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS FOR CIVIL WORKS BUILDINGS BILL NO- 02

RECEPTION BUILDING
LOGISTICS STORAGE

TECHNICAL FACILITY

MHE PARKING SHED


HOUSE & AC PLANT

EXTERNAL WORKS
CUM HELI HANGER
ACCOMMODATION

PUMP ROOM & UG


STORE HOUSE

SENTRY POST
HAZARDOUS
MATERIALS

LV ROOM

HELIPAD
OFFICE

TANK
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

FORM WORKS

CENTERING AND SHUTTERING for SUPER STRUCTURE,


using only Plastic Coated Marine grade Ply boards, in good
2.3
condition for all Horizontal & Vertical Work including strutting,
propping etc. and removal of form in all floors (of any height), for:

2.3.1 Sides of Columns at all heights 76.00 15.00 28.00 700.00 26.00 35.00 24.00 15.00 919.00 m2
2.3.2 Sides and soffits of Beams/ Tie beams at all levels 98.00 20.00 36.00 1,450.00 105.00 55.00 30.00 20.00 1,814.00 m2
2.3.3 Sides and soffits of Floor Slabs at all levels 140.00 19.00 43.00 1,600.00 355.00 60.00 60.00 19.00 2,296.00 m2
2.3.4 Sides & Soffits of Staircase including riser and treads 220.00 24.00 244.00 m2
2.3.5 Sides and soffits of Lintels at all levels 8.00 4.00 6.00 180.00 10.00 8.00 6.00 4.00 226.00 m2
2.3.6 Sides of Window Sills at all levels 6.00 2.00 4.00 120.00 8.00 6.00 4.00 2.00 152.00 m2
2.3.7 Sides of coping 16.00 70.00 86.00 m2
2.3.8 Steel column encasing m2
2.3.9 Sides of Walls m2
2.3.10 Sides of Upstand m2
2.3.11 Sides of Parapets m2
2.3.12 Sides and soffits of Cornices m2

TO COLLECTION

PRE-CAST CONCRETE

Precast concrete work, including formwork and


2.4
reinforcement as specified

2.4.1 Precast Rain Water Spout with catch basin 2.00 2.00 2.00 4.00 10.00 nr

TO COLLECTION

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 29 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS FOR CIVIL WORKS BUILDINGS BILL NO- 02

RECEPTION BUILDING
LOGISTICS STORAGE

TECHNICAL FACILITY

MHE PARKING SHED


HOUSE & AC PLANT

EXTERNAL WORKS
CUM HELI HANGER
ACCOMMODATION

PUMP ROOM & UG


STORE HOUSE

SENTRY POST
HAZARDOUS
MATERIALS

LV ROOM

HELIPAD
OFFICE

TANK
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

2.5 MASONRY
BLOCK WORK

Providing and constructing Hollow Concrete Block masonry wall


having compressive strength of 7.5 N/Sqmm in Cement Mortar
1:4 with necessary scaffolding, setting in position, curing, racking
of joints, Rate to include for providing steel mesh of 200/100 mm
wide at every 4th course, butterfly wall ties @ 0.50m height to
2.5.1
concrete columns,concrete band over 100mm thck walls after
every 1.2m of laying and if the wall length is more than 3m,
R.C.C stub columns to be provided etc., complete as per
standard specifications / approved drawings & as directed by
engineer-in-charge IN SUPERSTRUCTURE

2.5.1.1 For Size of 390x190x190 mm 152.00 65.00 95.00 3,180.00 130.00 120.00 100.00 60.00 3,902.00 m2

2.5.1.2 For Size of 390x190x90 mm 15.00 97.00 12.00 20.00 144.00 m2

200 thick hollow block reinforced with 10 mm min dia


reinforcement through the hollow part of the block at every 0.4 m
2.5.2 28.00 650.00 678.00 m2
distance, reinforcement to be embedded in ground beam/cill at
the top and bottom. Holes to be filled with 1:2:4 mix concrete.

TO COLLECTION

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 30 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS FOR CIVIL WORKS BUILDINGS BILL NO- 02

RECEPTION BUILDING
LOGISTICS STORAGE

TECHNICAL FACILITY

MHE PARKING SHED


HOUSE & AC PLANT

EXTERNAL WORKS
CUM HELI HANGER
ACCOMMODATION

PUMP ROOM & UG


STORE HOUSE

SENTRY POST
HAZARDOUS
MATERIALS

LV ROOM

HELIPAD
OFFICE

TANK
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

2.6 METAL WORKS

NON STRUCTURAL METAL WORKS

HANDRAILS

Supplying, fabricating and fixing in postion railing at all levels,


made out of M.S. sections including all necessary brackets,
fixtures, bolts/site welding and with two coats of epoxy paint of
2.6.1 approved shade, over a two coats of primer etc, complete, as 83.00 71.00 154.00 m
per standard specifications / approved detailed drawings and as
directed by engineer-in-charge.(contractor to provide shop
drawings for all items prior to manufacturing )

Supply and Install in position proprietry Stainless Steel railings


comprising Stainless steel hollow section & stainless steel pipe
welded to Stainless steel balustrades including all welding, all
2.6.2 45.00 18.00 7.00 70.00 m
required fixing, fixtures, cover plates, fasteners, anchors, site
welding and any other works as required and all as per drawing
and specification.

LADDERS

Supplying, Fabricating and Fixing in position acess Cat Ladders


at all levels, made out of M.S. sections including all necessary
fixing accessories fixed to concrete or block walls & applying with
two coats of epoxy paint of approved shade, over a two coat of
2.6.3 2.00 2.00 nr
primer etc complete, as per standard specifications / approved
detailed drawings and as directed by engineer-in-charge.
(contractor to provide shop drawings for all items prior to
manufacturing )

Supplying, Fabricating and Fixing in position acess Cage ladder


at all levels, made out of M.S. sections including all necessary
fixing accessories fixed to concrete or block walls & applying with
two coats of epoxy paint of approved shade, over a two coat of
2.6.4 1.00 1.00 2.00 nr
primer etc complete, as per standard specifications / approved
detailed drawings and as directed by engineer-in-charge.
(contractor to provide shop drawings for all items prior to
manufacturing )

MS INSERTS

Supplying, Fabricating and Installing M.S. Inserts in Concrete


at all levels with anchors in the form of rods, plates, angles, flats,
2.6.5 kg
etc, complete, as per standard specifications / approved detailed
drawings and as directed by engineer-in-charge.

TO COLLECTION

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 31 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS FOR CIVIL WORKS BUILDINGS BILL NO- 02

RECEPTION BUILDING
LOGISTICS STORAGE

TECHNICAL FACILITY

MHE PARKING SHED


HOUSE & AC PLANT

EXTERNAL WORKS
CUM HELI HANGER
ACCOMMODATION

PUMP ROOM & UG


STORE HOUSE

SENTRY POST
HAZARDOUS
MATERIALS

LV ROOM

HELIPAD
OFFICE

TANK
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

2.7 THERMAL AND MOISTURE PROTECTION

Built up waterproofing comprising of membrane laid to


manufacturers specifications, light weight concrete screed of
max 900 kg/Cum density. laid to minimum 50mm thk to fall with
50 mm thk roof matt polystyrene insulation board of 38 to
42kg/cum density , complete with bituthene fillets including
2.7.1 40.00 18.00 40.00 905.00 48.00 49.00 50.00 1,150.00 m2
250x250x25mm thk pressed cement concrete tiles laid to slope
as specifed.The treatment shall continue to about 300 mm
vertical of the wall. The work shall be carried out by specialized
approved agencies and shall be guaranteed for a minimum
period of 10 years. (BASF, Fosroc or equivalent)

Water proofing in Toilets/Pantry etc with built up waterproofing,


comprising of Bituthene 1200 HC with 150 mm overlaps, on
bitumen primed surface and covered with 50 mm thick concrete
screed (with waterproof compound) as per manufacturer's
2.7.2 specifications and lightweight concrete to fall. The treatment will 23.00 927.00 40.00 52.00 1,042.00 m2
continue at least 600 mm above finished floor level and include
for treatment of all pipes and junctions. The work shall be
guaranteed for a minimum period of 10 years and shall be
carried out by approved specialized agencies only.

TO COLLECTION

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 32 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS FOR CIVIL WORKS BUILDINGS BILL NO- 02

RECEPTION BUILDING
LOGISTICS STORAGE

TECHNICAL FACILITY

MHE PARKING SHED


HOUSE & AC PLANT

EXTERNAL WORKS
CUM HELI HANGER
ACCOMMODATION

PUMP ROOM & UG


STORE HOUSE

SENTRY POST
HAZARDOUS
MATERIALS

LV ROOM

HELIPAD
OFFICE

TANK
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

2.8 DOORS AND WINDOWS WORKS

WOODEN DOORS

NOTE : For details, specifications and shape for all doors,


windows, ventilators and curtain glazing refer respective
architectural drawing. The rate to include for preparation of shop
drawing for individual types of doors/windows, ventilators,
accessories including fixing of specials, iron mongery all as per
approvals. P.C Sums for ironmongery @ R.O 120 for main door
and rest @ RO 80 / door to be considered. Ironmongery to be of
approved make with cylindrical key sets, door stopper, door
handles, push plates, door closer, butt/rising hinges, master keys
etc, complete. (Note : For fire rated doors co-ordinate and refer
2.8.1
relevant fire fighting drawings.) Price shall include the cost of
meranti wood frame of size 225x60 /125 x 60mm on 200mm or
100mm wall respectively and architraves of size 20x40mm
complete. The door shutter will be made of solid / semi solid core
with teak wood lipping and 6 mm commercial ply facing on both
the faces all as per drawings and specs.External doors shall be
lacquered or treated appropriately for external conditions as per
engineer's approval. Frames,shutters and architraves shall be
VAC VAC and anti-termite treated. For all external doors, brush
strip to be provided at the bottom

Providing & fixing 44 mm thick Meranti wood sinle leaf swing


2.8.1.1 door finished with Lacquer painted on both sides as per
drawings

a D4-1000mm x 2100mm (Office Accommodation) 6.00 6.00 nr

Providing & fixing 40 mm thick flush door finished with spray


2.8.1.2 applied enamel painted on both sides & undercut of 25mm as
per drawings

a D5-900mm x 2100mm (Office Accommodation) 9.00 9.00 nr

Providing & fixing 40 mm thick flush door finished with spray


applied enamel painted on both sides & edges with pull
2.8.1.3
handlcapped bar & SS kick plate on inner side, undercut of
25mm as per drawings

a D6-900mm x 2100mm (Office Accommodation) 18.00 18.00 nr

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 33 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS FOR CIVIL WORKS BUILDINGS BILL NO- 02

RECEPTION BUILDING
LOGISTICS STORAGE

TECHNICAL FACILITY

MHE PARKING SHED


HOUSE & AC PLANT

EXTERNAL WORKS
CUM HELI HANGER
ACCOMMODATION

PUMP ROOM & UG


STORE HOUSE

SENTRY POST
HAZARDOUS
MATERIALS

LV ROOM

HELIPAD
OFFICE

TANK
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

Providing & fixing fire exit 44mm thick solid core mirante wood
door shutter finished with enamel painted on both sides & edges
2.8.1.4
with 250mmx450mm vision panel in 8mm georgian wired glass
as per drawings

a FR1-1000mm x 2200mm (Office Accommodation) 6.00 6.00 nr

Providing & fixing 44mm thick Fire exit mirante wood double leaf
door finished with lacquer painted on both sides & edges with
8mm thick hermetically sealed toughened glass outside and 6
2.8.1.5
mm clear hermetically sealed toughened glass inside with 12
mm air gap, 250 x 450 mm vision panel 8mm gergian wired
glass with panic bolt as per drawings

a FE-1500mm x 2200mm (Office Accommodation) 2.00 2.00 nr

Providing & fixing 44mm thick single leaf flush solid aluminum
2.8.1.6
door as per drawing (Wooden Door)

a D1-1000mm x 2400mm (Sentry Post) 2.00 2.00 nr

Providing & fixing 40mm thick single leaf flush aluminum door as
2.8.1.7
per drawing (Wooden Door)

a D2-800mm x 2200mm (Sentry Post) 2.00 2.00 nr

Providing & fixing 44mm thick mirante wood single leaf swing
2.8.1.8 door finished with lacquer painted on both sides & edges as per
drawings

a D4-1000mm x 2100mm (Office Accommodation) 6.00 6.00 nr

Providing & fixing 44mm thick mirante wood double leaf door
finished with lacquer painted on both sides & edges with
2.8.1.9 decorative 8mm thick hermetically sealed toughened glass
outside and 6 mm clear hermetically sealed toughened glass
inside with 12 mm air gap as per drawings

a D1-2500mm x 2400mm (Office Accommodation) 1.00 1.00 nr

b D2-1500mm x 2400mm (Office Accommodation) 4.00 4.00 nr

c D3-1200mm x 2400mm (Office Accommodation) 27.00 27.00 nr

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 34 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS FOR CIVIL WORKS BUILDINGS BILL NO- 02

RECEPTION BUILDING
LOGISTICS STORAGE

TECHNICAL FACILITY

MHE PARKING SHED


HOUSE & AC PLANT

EXTERNAL WORKS
CUM HELI HANGER
ACCOMMODATION

PUMP ROOM & UG


STORE HOUSE

SENTRY POST
HAZARDOUS
MATERIALS

LV ROOM

HELIPAD
OFFICE

TANK
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

ALUMINUM DOOR & WINDOWS

Providing & fixing Aluminum Doors, Windows and fixed glazing


made of approved anodized sections, 1.2 to 2 mm thick with
weight of section not less than 1.5 kg per meter, fitted in position
2.8.2
complete with fixtures, glass with neoprene gaskets, weather
proofing, S.S fly screen wherever openable etc (contractor to
provide shop drawings for all items prior to manufacturing ), as:

ALUMINUM DOORS

Powder coated Heavy duty aluminum door with 400mm x


2.8.2.1 750mm vision panel in 6mm georgian wired glass as per
drawing

a D1-1000mm x 2200mm (Logistics storage house & AC Plant) 2.00 2.00 nr

2.8.2.2 Powder coated Heavy duty aluminum door as per drawing

a D1-2000mm x 2500mm (LV Room) 1.00 1.00 nr

b D1-1500mm x 2100mm (Reception) 2.00 2.00 nr

2.8.2.3 Powder coated Heavy duty aluminum door as per drawing

a D2-800mm x 2400mm (Reception) 2.00 2.00 nr

Powder coated heavy duty aluminum frame solid door as per


2.8.2.4
drawing

a D1-900mm x 2200mm (Technical Facility cum Heli Hanger) 2.00 2.00 nr

b D2-800mm x 2200mm (Technical Facility cum Heli Hanger) 2.00 2.00 nr

Powder coated double leaf aluminum frame solid door as per


2.8.2.5
drawing

a AL1-800mm x 2200mm (Technical Facility cum Heli Hanger) 1.00 1.00 nr

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 35 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS FOR CIVIL WORKS BUILDINGS BILL NO- 02

RECEPTION BUILDING
LOGISTICS STORAGE

TECHNICAL FACILITY

MHE PARKING SHED


HOUSE & AC PLANT

EXTERNAL WORKS
CUM HELI HANGER
ACCOMMODATION

PUMP ROOM & UG


STORE HOUSE

SENTRY POST
HAZARDOUS
MATERIALS

LV ROOM

HELIPAD
OFFICE

TANK
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

Powder coated Heavy duty aluminum double leaf door with


2.8.2.6
aluminum louvers as per drawing

a D1-2000mm x 2500mm (Pump Room & UG Tank) 1.00 1.00 nr

Powder coated Heavy duty aluminum door Enamel painted on


2.8.2.7
both sides with kick plate & louvers at bottom as per drawing

a D3-800mm x 2200mm (Technical Facility cum heli Hanger) 3.00 3.00 nr

2.8.3 ALUMINUM WINDOWS & VENTILATORS

Powder coated aluminium sliding window with 8mm thick


thermally insulated tinted glass outside and 6 mm thick thermally
2.8.3.1
insulated tinted Plain glass inside hermetically sealed 8mm air
gap as per drawings

a W2-1500mm x 3500mm (Office Accommodation) 2.00 2.00 nr

Powder coated aluminium fixed window with 6mm thick


2.8.3.2 toughened glass outside and 6 mm thick clear toughened glass
inside hermetically sealed 12mm air gap as per drawings

a W1-1600mm x 1800mm (Sentry Post) 4.00 4.00 nr

b W2-750mm x 1500mm (Sentry Post) 2.00 2.00 nr

Powder coated aluminium window with 8mm thick toughened


2.8.3.3 tinted reflective glass outside and 8 mm thick toughened glass
inside as per drawings

a W1-1500mm x 2000mm (Office Accommodation) 57.00 57.00 nr

Powder coated aluminium sliding window with 6mm thick


2.8.3.4 toughned tined glass outside and 6 mm thick clear glass inside
as per drawings

a W1-1200mm x 1200mm (Reception) 4.00 4.00 nr

Powder coated aluminium sliding window with 8mm thick


2.8.3.5 toughened tinted glass outside and 6 mm thick clear glass inside
as per drawings

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 36 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS FOR CIVIL WORKS BUILDINGS BILL NO- 02

RECEPTION BUILDING
LOGISTICS STORAGE

TECHNICAL FACILITY

MHE PARKING SHED


HOUSE & AC PLANT

EXTERNAL WORKS
CUM HELI HANGER
ACCOMMODATION

PUMP ROOM & UG


STORE HOUSE

SENTRY POST
HAZARDOUS
MATERIALS

LV ROOM

HELIPAD
OFFICE

TANK
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

a W1-1500mm x 1300mm (LV Room) 1.00 1.00 nr

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 37 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS FOR CIVIL WORKS BUILDINGS BILL NO- 02

RECEPTION BUILDING
LOGISTICS STORAGE

TECHNICAL FACILITY

MHE PARKING SHED


HOUSE & AC PLANT

EXTERNAL WORKS
CUM HELI HANGER
ACCOMMODATION

PUMP ROOM & UG


STORE HOUSE

SENTRY POST
HAZARDOUS
MATERIALS

LV ROOM

HELIPAD
OFFICE

TANK
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

Powder coated aluminium sliding window with 6mm thick


2.8.3.6 toughned glass outside and 6 mm thick clear glass inside 12mm
air gap as per drawings

a W1-1500mm x 1200mm (Logistics storage house & AC Plant) 1.00 1.00 nr

Aluminum colored powder coated aluminium framed ventilator


2.8.3.7
with 6mm thick frosted glass as per drawings

a V1-600mm x 900mm (Office Accommodation) 19.00 19.00 nr

b V1-600mm x 600mm (Pump Room & UG Tank) 2.00 2.00 nr

c V1-600mm x 800mm (Logistics storage house & AC Plant) 1.00 1.00 nr

d V1-600mm x 600mm (Reception Building) 2.00 2.00 nr

e V1-600mm x 750mm (Sentry Post) 2.00 2.00 nr

f V1-600mm x 800mm (Technical Facility cum Heli Hanger) 4.00 4.00 nr

Aluminum colored powder coated ventilator with 6mm glass top


2.8.3.8
hung shutter with Aluminum Grill as per drawings

a V1-1500mm x 600mm (Store House Hazardous Materials) 2.00 2.00 nr

2.8.4 STEEL DOORS

Fire exit Steel door with panic bolts enamel painted on both
sides and edges with vision panel 300x450mm in 6 mm thick
2.8.4.1
georgian wired glass as per drawings. (for Rating refer relevant
Fire Fighting Dwgs)

FD1- overall size1000mm x 2200mm (Logistics storage house &


a 7.00 7.00 nr
AC Plant)

b FD1- 1000mm x 2200mm (Technical Facility cum Heli Hanger) 5.00 5.00 nr

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 38 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS FOR CIVIL WORKS BUILDINGS BILL NO- 02

RECEPTION BUILDING
LOGISTICS STORAGE

TECHNICAL FACILITY

MHE PARKING SHED


HOUSE & AC PLANT

EXTERNAL WORKS
CUM HELI HANGER
ACCOMMODATION

PUMP ROOM & UG


STORE HOUSE

SENTRY POST
HAZARDOUS
MATERIALS

LV ROOM

HELIPAD
OFFICE

TANK
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

Supply and install Double leaf heavy duty Electrically operated


Sliding Steel door with enamel painted on all sides and edges
2.8.4.2 with weather strips and aluminum threshold for external doors
with all fixing accessories etc.complete along with all necessary
accessories, all as specified and shown on drawings.

SD1 – 3000 mm x 4500 mm ( Logistics Storage house & AC


a 2 2.00 nr
Plant)

ROLLING SHUTTERS

Supply and fix HEAVY DUTY ROLLING SHUTTERS of approved


make, made of required size with continuous 1.0 mm thick
continuous prepainted powder coated Aluminum pressed metal
profiles, with GI bottom and side brackets/guides and
2.8.5
arrangements for inside and outside locking , complete including
the cost of providing and fixing wire springs and Hood, as
follows: (contractor to provide shop drawings for all items prior to
manufacturing )

2 hour fire rated MS frame powder coated weather resistant


Geared roll- on type Electrically operated rolling shutter of
2.8.5.1 apporoved quality, size with heavy duty motor including all the
necessary switches, safety measures connected electrical works
complete.

a RS1-5000mm x 6000mm ( Logistics storage house & AC Plant) 3.00 3.00 nr

Fire rated MS frame powder coated weather resistant Geared


roll- on type Electrically operated Insulated Alumium sliding
2.8.5.2 Foldable door of apporoved quality, size with heavy duty motor
including all the necessary switches, safety measures connected
electrical works complete.

a SD1-37000mm x 10000mm ( Technical Facility cum Heli Hanger) 1.00 1.00 nr

b RS1-5000mm x 6000mm (Technical Facility cum Heli hanger) 2.00 2.00 nr

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 39 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS FOR CIVIL WORKS BUILDINGS BILL NO- 02

RECEPTION BUILDING
LOGISTICS STORAGE

TECHNICAL FACILITY

MHE PARKING SHED


HOUSE & AC PLANT

EXTERNAL WORKS
CUM HELI HANGER
ACCOMMODATION

PUMP ROOM & UG


STORE HOUSE

SENTRY POST
HAZARDOUS
MATERIALS

LV ROOM

HELIPAD
OFFICE

TANK
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

2 hour fire rated MS frame powder coated weather resistant


Geared roll- on type Electrically operated rolling shutter of
2.8.5.3 apporoved quality, size with heavy duty motor including all the
necessary switches, safety measures connected electrical works
complete.

a RS1-5000mm x 3000mm (Store house Hazardous Materials) 1.00 1.00 nr

2.8.6 Cold room PIR Paneling & Related works

Supply, installation, testing & commissioning of entire cold room


paneling works with associated motorized / hinged door, cold
room special lighting & control panel, heater mat, pressure relief
valves etc. as described below & as required as per project
requirement. Entire works to be carried out by special cold room
sub-contractor who shall do the close co-ordiation with other
services, system, contractors etc. Vendor shall verify the final
quantity of panels, doors according to architectural drawings.

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 40 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS FOR CIVIL WORKS BUILDINGS BILL NO- 02

RECEPTION BUILDING
LOGISTICS STORAGE

TECHNICAL FACILITY

MHE PARKING SHED


HOUSE & AC PLANT

EXTERNAL WORKS
CUM HELI HANGER
ACCOMMODATION

PUMP ROOM & UG


STORE HOUSE

SENTRY POST
HAZARDOUS
MATERIALS

LV ROOM

HELIPAD
OFFICE

TANK
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

Supply, installation & testing of cold room wall & ceiling panels of
100 mm thick insulated panel as per the architectural drawings &
site requirements shown for freezers, chiller
rooms ,corridors,Arrival & delivery area etc all as shown in
architectural drawings. Supply and installation of Fire Safe
wall/roof ceiling of thermal insulated for the cold rooms in knock
down form. The 100 mm thick wall/roof panels should be
insulated by rigid injected environmental friendly PIR foam of
overall density 42 kg/m3 and proper cladding shall be 0.6 mm
pre-painted GI sheet with nylon protective film (with minor ribs).
The panel shall meet the fire rating Fire Classification as per
ASTM E84: Class 1 with less spread <25 and smoke
development <450. As per EN: 131565:2008 PIR Foam should
be DCL Approved. Reaction to Fire: Meets Euro Class E
Classification. The panels are constructed by joining together by
means of tongue and groove on each side of the panel to ensure
air tight joints. The wall panel shall be mounted as per site
condition, the work has to include common partition wall between
adjacent cold rooms, steel column cladding and mechanical
accessories shall be including rivets, internal and external
flashing & silicon sealant. All joints to panel and puncturing to
PIR panel shall be by using the Teflon bolt only. Price shall
include all necessary openings & finishing in panels, support
systems with material. (Approved Make: Kingspan/ Eurospan ).
Contractor shall review & quote the quantity further any variation
will not be provided.

2.9.6.1 Supply & Installation of wall panels (100 mm thick). 1,210.00 1,210.00 m2

2.9.6.2 Supply & Installation of Ceiling panels (100 mm thick). 675.00 675.00 m2

TO COLLECTION

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 41 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS FOR CIVIL WORKS BUILDINGS BILL NO- 02

RECEPTION BUILDING
LOGISTICS STORAGE

TECHNICAL FACILITY

MHE PARKING SHED


HOUSE & AC PLANT

EXTERNAL WORKS
CUM HELI HANGER
ACCOMMODATION

PUMP ROOM & UG


STORE HOUSE

SENTRY POST
HAZARDOUS
MATERIALS

LV ROOM

HELIPAD
OFFICE

TANK
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

2.90 FINISHES

2.9.1 WALL FINISHES

PLASTERING

Providing 15 mm thick cement plaster for external walls in two


coats, under layer 9 mm thick cement plaster 1:4 (1 cement: 4
coarse sand) finished smooth with a top layer 6 mm thick cement
2.9.1.1 plaster 1:4 (1 cement:4 fine sand) at all heights, including 257.00 200.00 140.00 1,900.00 160.00 165.00 102.00 200.00 3,124.00 m2
recess, grooves, corner beads, bands, expanded
metal,scaffolding etc., as specified with necessary PVA bonding
agents as per the manufacturers specifications.

Providing 12 mm thick cement plaster in 1:4 (1 cement: 4 coarse


sand) for internal walls and finished smooth at all heights
2.9.1.2 including recess, grooves, corner beads, expanded 168.00 48.00 90.00 3,250.00 240.00 82.00 60.00 80.00 4,018.00 m2
metal,scaffolding etc., as specified with necessary PVA bonding
agents as per the manufacturers specifications

Providing and painting walls with emulsion paint of approved


brand and manufacturer including preparation of surface,
scaffolding etc to provide an even shade, with Egg shell
2.9.1.3 48.00 90.00 240.00 378.00 m2
Emulsion paint on internal walls, two or more coats over a base
coat of recommended primer and application of stucco putty
primer, of approved shade as per manufacturer 's instructions

Providing and painting walls with emulsion paint of approved


brand and manufacturer including preparation of surface,
scaffolding etc to provide an even shade, with Egg shell
2.9.1.4 80.00 22.00 102.00 m2
Emulsion paint on Ceiling, two or more coats over a base coat
of recommended primer and application of stucco putty primer,
of approved shade as per manufacturer 's instructions

Providing and painting walls with emulsion paint of approved


brand and manufacturer including preparation of surface,
scaffolding etc to provide an even shade, with Acrylic based
2.9.1.5 Emulsion paint on internal walls, two or more coats over a 168.00 3,250.00 60.00 80.00 3,558.00 m2
base coat of recommended primer and application of stucco
putty primer, of approved shade as per manufacturer 's
instructions

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 42 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS FOR CIVIL WORKS BUILDINGS BILL NO- 02

RECEPTION BUILDING
LOGISTICS STORAGE

TECHNICAL FACILITY

MHE PARKING SHED


HOUSE & AC PLANT

EXTERNAL WORKS
CUM HELI HANGER
ACCOMMODATION

PUMP ROOM & UG


STORE HOUSE

SENTRY POST
HAZARDOUS
MATERIALS

LV ROOM

HELIPAD
OFFICE

TANK
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

Providing and painting walls with emulsion paint of approved


brand and manufacturer including preparation of surface,
scaffolding etc to provide an even shade, with Acrylic based
2.9.1.6 40.00 100.00 82.00 20.00 242.00 m2
Emulsion paint on ceiling, two or more coats over a base coat
of recommended primer and application of stucco putty primer,
of approved shade as per manufacturer's instructions

Textured paint of approved make and color, over plastered


surface for external walls with colored band, at all heights with
necessary scaffolding, surface preparartion etc as shown in the
2.9.1.7 257.00 200.00 140.00 1,900.00 160.00 165.00 102.00 200.00 3,124.00 m2
drawings with MEDIUM TEXTURE finish (two coats) with one
coat of recommended primer and application of stucco putty.
Painting shall be carried out as per manufacturers specifications.

Providing and applying Epoxy paint FC 150 of FOSROC or


2.9.1.8 equivalent (two or more coats) on concrete work (minimum 40 80.00 3,953.00 4,033.00 m2
micron thick).

FLOOR FINISHES

CERAMIC TILE FLOORING

Providing and laying FLOORS TILES of specified type, size and


thickness without warpage of approved make and color laid on
50 mm thick cement mortar 1:4 (1 cement: 4 coarse sand),
2.9.2 including grouting the joints filled with matching color epoxy grout
and Acid Wash etc., as per the manufacturer's instruction,
complete as directed . (contractor to provide shop drawings for
all items prior to start of work )

Fully vitrified tiles of 600 mm x 600 mm x 8mm thick (Basic Price


2.9.2.1
of Tile RO 6.50 per Sqm)
100.00 15.00 956.00 35.00 16.00 1,122.00 m2

Anti Skid Ceramic tiles of 300 X 300 mm x 8mm (Basic Price of


2.9.2.2 3.00 202.00 5.00 7.00 20.00 237.00 m2
Tile RO 3.00 per Sqm)

Ceramic tiles of 400 X 400 mm x 8mm (Basic Price of Tile RO


2.9.2.3 154.00 13.00 167.00 m2
4.00 per Sqm)

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 43 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS FOR CIVIL WORKS BUILDINGS BILL NO- 02

RECEPTION BUILDING
LOGISTICS STORAGE

TECHNICAL FACILITY

MHE PARKING SHED


HOUSE & AC PLANT

EXTERNAL WORKS
CUM HELI HANGER
ACCOMMODATION

PUMP ROOM & UG


STORE HOUSE

SENTRY POST
HAZARDOUS
MATERIALS

LV ROOM

HELIPAD
OFFICE

TANK
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

Supply and fixing of vitrified tile skirting with CM 1:3 for a height
2.9.2.4 of 100 mm with champhered edges. (Basic Price of Tile R.O. 40.00 17.00 760.00 30.00 28.00 875.00 m
2.50 per m)

Supply and fixing of Ceramic skirting of 10mm thick with CM 1:3


2.9.2.5 for a height of 100 mm with champhered edges. (Basic Price of 194.00 20.00 214.00 m
Tile R.O. 2.00 per m)

GRANITE STONE SLAB/ TILE FLOORING

Providing and laying specified thick GRANITE STONE SLAB/


TILE FLOORING of approved make, colour, shade and quality
laid over 50 mm (average) thick cement mortar 1:3 (1 cement: 3
2.9.3
coarse sand) base and joints filled with matching color epoxy
grout, etc. complete with polishing. (contractor to provide shop
drawings for all items prior to start of work )

Granite tile 20mm thick including border tiles 150/100 mm wide


2.9.3.1 89.00 6.00 95.00 m2
as per the flooring pattern (Basic Price of Tile RO 16.00 per m 2)

Supply and fixing of Granite tile skirting with CM 1:3 for a height
2.9.3.2 of 100 mm & 20 mm thick with champhered edges. (Basic Price 25.00 6.00 31.00 m
of Tile R.O.5.00 per m)

MARBLE STONE SLAB/ TILE FLOORING

Providing and laying specified thick MARBLE STONE SLAB/


TILE FLOORING of approved make, colour, shade and quality
laid over 50 mm (average) thick cement mortar 1:3 (1 cement: 3
2.9.4
coarse sand) base, and joints filled with matching color epoxy
grout, etc. complete with polishing. (contractor to provide shop
drawings for all items prior to start of work )

Marble tile 600mm X 600mm X 25mm including border tiles


2.9.4.1 150/100 mm wide as per the flooring pattern (Basic Price of Tile 54.00 54.00 m2
RO 16 per Sqm)

2.9.4.2 Riser of 20 mm thick Marble (Basic Price of Tile RO 20 per m) 210.00 210.00 m

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 44 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS FOR CIVIL WORKS BUILDINGS BILL NO- 02

RECEPTION BUILDING
LOGISTICS STORAGE

TECHNICAL FACILITY

MHE PARKING SHED


HOUSE & AC PLANT

EXTERNAL WORKS
CUM HELI HANGER
ACCOMMODATION

PUMP ROOM & UG


STORE HOUSE

SENTRY POST
HAZARDOUS
MATERIALS

LV ROOM

HELIPAD
OFFICE

TANK
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

Treads of 20 mm thick Marble tile with bull nosing of edges and


2.9.4.3 including antislip beading strip on treads, (Basic Price of Tile 210.00 11.00 221.00 m
RO 20 per m)

Supply and fixing of Marble tile skirting with CM 1:3 for a height
2.9.4.4 of 100 mm & 20 mm thick with champhered edges. (Basic Price 86.00 86.00 m
of Tile R.O 4 per m)

PRECAST TERRAZZO

Providing & Laying Precast Terrazzo tiles of approved make,


colour, over prepared sub-base laid on cement and sand screed
2.9.5 1:4 (1 cement: 4 coarse sand) to provide a finished floor
thickness of 50mm, pointed in neat colored cement grout to
match tiles, shade and quality, polished etc complete.

Terrazzo tiles of 20 mm thick (Basic Price of Tile RO 2.50 per


2.9.5.1
Sqm)
38.00 10.00 10.00 8.00 66.00 m2

Treads of 20mm thick Precast Terrazzo tiles Steps including bull


2.9.5.2 nose edge with rubber strips (Basic Price of Tile R.O. 2.00 per 16.00 42.00 12.00 30.00 100.00 m
m)

Riser of 20mm thick Precast Terrazzo tiles Steps (Basic Price of


2.9.5.3
Tile R.O. 2.00 per m)
16.00 42.00 12.00 30.00 100.00 m

Providing and applying with 'NITOFLOR EMERITOP' or


Equivalent hardener over a RCC Slab to obtain Smooth Finish
2.9.6 Cement Concrete Flooring, all applied in strict accordance with 3,637.00 3,637.00 m2
the manufacturer's specifications, (Makes- SIKA,BASF,
FOSROC or equivalent)

Providing and fixing 8mm thick electrically insulated rubber mat


2.9.7 of approved make and color over concrete flooring complete as 40.00 40.00 m2
per manufacturer's specifications.

Providing and laying 15 mm thick rubber flooring of approved


2.9.8 make and color over concrete flooring complete as per 50.00 50.00 m2
manufacturer's specifications.

2.9.9 SKIRTING

Providing and laying skirting in Cement Mortar 1:2 for a height of


2.9.9.1 m
100 mm & 20 mm thick.

Providing Coving at edges in Cement Mortar 1:2 of specified


2.9.9.2 m
thickness & height as shown in drawings.

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 45 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS FOR CIVIL WORKS BUILDINGS BILL NO- 02

RECEPTION BUILDING
LOGISTICS STORAGE

TECHNICAL FACILITY

MHE PARKING SHED


HOUSE & AC PLANT

EXTERNAL WORKS
CUM HELI HANGER
ACCOMMODATION

PUMP ROOM & UG


STORE HOUSE

SENTRY POST
HAZARDOUS
MATERIALS

LV ROOM

HELIPAD
OFFICE

TANK
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

WALL TILING

Providing and fixing wall tiles of specified types and size in dado,
of approved design, color and shade on 12 mm thick cement
plaster 1:4 (1 cement: 4 coarse sand), including preparation of
2.9.10 surface, PVC corner beads, curing, protection, jointed with white
cement slurry mixed with matching pigment and Acid Wash etc.
complete, (contractor to provide shop drawings for all items prior
to start of work )

Ceramic glazed tiles 300mm X 600mmx 5mm thick, with


2.9.10.1 cushioned edges fixed to walls (Basic Price of Tile R.O. 3.50 per 20.00 725.00 35.00 44.00 100.00 924.00 m2
Sqm)

FALSE CEILING

Providing and fixing false ceiling with revealed edge with vinyl
finish concealed powder coated aluminum T grid system, edge
supports at wall junctions, including GI supporting system
suspended from the beams/slab, providing cut outs for light
2.9.11 fixtures, air condition grills and other openings and other fixing
accessories, complete as shown on details and as per standard
specifications / approved drawings and approved manufacturer's
recommendation. (Basic Cost R.O.4.00 per sqm). (contractor to
provide shop drawings for all items prior to start of work )

2.9.11.1 Gypsum tile 600mm x600mm x12mm size with vinyl finish 100.00 1,200.00 35.00 13.00 1,348.00 m2

Gypsum tile 600mm x600mm x12mm size (moisture resistant


2.9.11.2 20.00 202.00 5.00 7.00 234.00 m2
with aluminium foil paper above)

600 x 600 x 1.2 mm T grid Revealed Edge Aluminum Metal


2.9.11.3 48.00 36.00 84.00 m2
False ceiling

TO COLLECTION

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 46 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS FOR CIVIL WORKS BUILDINGS BILL NO- 02

RECEPTION BUILDING
LOGISTICS STORAGE

TECHNICAL FACILITY

MHE PARKING SHED


HOUSE & AC PLANT

EXTERNAL WORKS
CUM HELI HANGER
ACCOMMODATION

PUMP ROOM & UG


STORE HOUSE

SENTRY POST
HAZARDOUS
MATERIALS

LV ROOM

HELIPAD
OFFICE

TANK
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

2.10 FURNISHINGS

VANITY AND PANTRY/ TOILET COUNTERS

Providing & fixing GRANITE SLAB of specified thickness, pre-


polished machine cut for PANTRY PLATFORM/TOILETS, and
similar locations of required size of approved shade, color and
2.10.1 15.60 15.60 m
texture with joints treated with white cement, mixed with
matching pigment including rubbing, curing etc complete at all
levels with:

Providing and fixing vanity counter/service counters tops in


pantry/ toilets with 20mm thick Granite including 100mm wide
granite facia and skirting. The counters shall be fixed on a 20mm
thick MDF platform with bull nose edges and 100mm back
2.10.2 splash Provision shall be made for cut outs for fixing the wash 18.10 18.10 m
basin. All joints shall be neatly filled and sealed with approved
water proofing sealants etc., complete.The counters shall be
placed on 100mm thick RCC platform on floor which shall be
finished with tile skirting

2.10.3 CABINETS

Provide and fix cabinets of powder coated Aluminum with


necessary frame work for Pantry, toilets etc as per detail
2.10.3.1 15.60 15.60 m
drawings. Contractor to submit shop drawings for approval prior
to manufacturing the same.

Provide and fix cabinets of MDF with necessary frame work for
2.10.3.2 Pantry, toilets etc as per detail drawings. Contractor to submit m
shop drawings for approval prior to manufacturing the same.

Provide and fix cabinets of UPVC with necessary frame work for
2.10.3.3 Pantry, toilets etc as per detail drawings. Contractor to submit m
shop drawings for approval prior to manufacturing the same.

TO COLLECTION

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 47 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS FOR CIVIL WORKS BUILDINGS BILL NO- 02

RECEPTION BUILDING
LOGISTICS STORAGE

TECHNICAL FACILITY

MHE PARKING SHED


HOUSE & AC PLANT

EXTERNAL WORKS
CUM HELI HANGER
ACCOMMODATION

PUMP ROOM & UG


STORE HOUSE

SENTRY POST
HAZARDOUS
MATERIALS

LV ROOM

HELIPAD
OFFICE

TANK
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

2.11 MISCELLANEOUS

2.11.1 Rain water downtake pipe with GRC cover as per the drawings nr

Providing and fixing GRC Panels, cornices, moulds and screens


ASM-12, 50mm x 50mm plain GRC border around, 50mm x
50mm MS vertical support fixed to top & bottom beams &
50x50mm MS box horizontal support at Centre of GRC panels
2.11.2 welded to vertical support complete as per manufacturer's 125.00 125.00 m2
specifications all properly sealed and rendered water proof with
poly sulphide sealants as per specifications indicated in the
drawings. Contractor to submit necessary shop drawings for
approval

TO COLLECTION

3 EXTERNAL WORKS
3.1 FILLING, LEVELING & COMPACTION

Excavation and grading on site as required to arrive at formation


level, backfilling with approved excavated / imported material in
layers not exceeding 150mm and compacting to achieve 95%
3.1.1 60,000.00 60,000.00 m2
compaction. Use of heavy duty roller and watering will be carried
out to compact the earth. Contractor to study the existing ground
level and submit the cut and fill levels along with the tender.

CONSOLIDATION OF SUBGRADE with power road roller of 8 to


3.1.2 12 tone capacity including making good the undulations etc. with m2
excavated or imported earth and re-rolling the sub-grade.

Dispose away beyond Muncipal limits to approved dumping


3.1.3 m3
ground all surplus excavated material.

3.2 ROAD WORKS

Supply, lay, grade, water and compact 200mm thick sub grade
3.2.1 9,400.00 9,400.00 m2
class B to the required level and gradient.

Supply, lay, grade, water and compact 150 mm thick granular


3.2.2 9,400.00 9,400.00 m2
sub base Class B to the required level and gradient.

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 48 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS FOR CIVIL WORKS BUILDINGS BILL NO- 02

RECEPTION BUILDING
LOGISTICS STORAGE

TECHNICAL FACILITY

MHE PARKING SHED


HOUSE & AC PLANT

EXTERNAL WORKS
CUM HELI HANGER
ACCOMMODATION

PUMP ROOM & UG


STORE HOUSE

SENTRY POST
HAZARDOUS
MATERIALS

LV ROOM

HELIPAD
OFFICE

TANK
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

Supply, lay, grade, water and compact 150 mm thick Aggregate


3.2.3 base course Class B as per B.S 4987 to the required level and 9,400.00 9,400.00 m2
gradient.

Supply and Applying prime coat of MC/70 cut block bitumen at


3.2.4 9,400.00 9,400.00 m2
the rate of 1Kg/Sqm

Supply, lay and compact 50 mm thick bituminous base coarse


class B. as per B.S 4987 finisher to the required level and
3.2.5 grade, rolling with road roller of 8 to 10 tone capacity to achieve 9,400.00 9,400.00 m2
the required compaction & density with due gradient and camber
for proper water flow.

Supply and Applying tack coat of RC/250 cut block bitumen at


3.2.6 9,400.00 9,400.00 m2
the rate of 0.35Kg/Sqm.

Supply, lay and compact 50 mm thick wearing coarse class B as


per B.S 4987 finished to the required level and grade, rolling with
3.2.7 road roller of 8 to 10 tone capacity to achieve the required 9,400.00 9,400.00 m2
compaction & density with due gradient and camber for proper
water flow.

3.3 PAVEMENT WORKS

Supplying and laying precast concrete KERB STONE in plain


cement concrete C15, including fixing and pointing in cement
3.3.1 mortar 1:4 (1 cement: 4 coarse sand), earth excavation as 5,075.00 5,075.00 m
required and making drainage openings where required. Painting
is inclusive.

Supply and lay Interlock tiles of approved make, over a layer of


3.3.2 well compacted sand of 50mm average thickness over prepared
ground, including filling the gaps and joints with fine sand, with.

60mm thick tiles with compressive strength of not less than 35


3.3.2.1 2,500.00 2,500.00 m2
N/SQ.MM, over WALKWAYS.

80 mm thick tiles with compressive strength of 40 N/SQ.MM over


3.3.2.2 m2
ROADS/PARKING

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 49 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS FOR CIVIL WORKS BUILDINGS BILL NO- 02

RECEPTION BUILDING
LOGISTICS STORAGE

TECHNICAL FACILITY

MHE PARKING SHED


HOUSE & AC PLANT

EXTERNAL WORKS
CUM HELI HANGER
ACCOMMODATION

PUMP ROOM & UG


STORE HOUSE

SENTRY POST
HAZARDOUS
MATERIALS

LV ROOM

HELIPAD
OFFICE

TANK
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

ROAD MARKINGS AND SIGNAGE

Supply and apply 12cm wide hot applied thermoplastic paint on


side shoulder, parking demarcation line, direction arrow, crossing
line, parking areas and central demarcation with road marking
3.3.3 235.00 235.00 m
machine or supply and apply hot applied thermoplastic hand
road marking, whenever necessary as per manufacturer's
specification and as per drawings

Signage

Allow for supply and fixing of various traffic signs boards


(Direction, Exit, Entry, Stop, Speed limit, etc.) as per Oman
3.3.4 Traffic Manual including associated builder's works for the 25.00 25.00 nr
different locations in external road and car parking area, all
complete and to the approval of the Engineer

COMPOUND WALL

Supply, fabrication and fixing in position of MS Gates electrical


operated as per detailed drawings, made up of M.S. Framework
of Hollow box sections with minimum wall thickness of 16 gauge
3.4
MS Sheets, including necessary supports and locking devices,
complete with one coat of Red Oxide Primer and two coats of
Alkyd Enamel external paint of approved colour.

3.4.1 9000mm wide gate 2.00 2.00 nr

CHAIN LINK FENCE

Supply, fabrication and fixing in position of Chain link fencing


including Main Post , intermediate post, corner post, struts, Wire
3.5 mesh including foundation work for all post & necessary 980.00 980.00 m
excavation, reinforcement, formwork, concrete, waterproofing etc
complete as per drawings

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 50 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS FOR CIVIL WORKS BUILDINGS BILL NO- 02

RECEPTION BUILDING
LOGISTICS STORAGE

TECHNICAL FACILITY

MHE PARKING SHED


HOUSE & AC PLANT

EXTERNAL WORKS
CUM HELI HANGER
ACCOMMODATION

PUMP ROOM & UG


STORE HOUSE

SENTRY POST
HAZARDOUS
MATERIALS

LV ROOM

HELIPAD
OFFICE

TANK
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

STONE PITCHING

Providing & laying of stone boulder pitching surface laid to


bottom and inclined surfaces, including beam, making openings
3.6 650.00 650.00 m2
from roads at every 5 Mtrs, pointing filled with 1:4 CM mortar, as
per drawing complete.

Site grading open areas, forming to required level to prevent


3.7 flooding of strom water, including spreading a layer of clean 9,000.00 9,000.00 m2
Gravel of average 25 mm thick.

Providing and spreading 20mm aggregate upto 100mm thick in


3.8 10,800.00 10,800.00 m2
T.X. yard as per drawings.

Supply, installation, testing and commissioning of Boom Barrier


Gate in aluminium barrier with control panel and fitted to take
3.9 additional accessories of approved make. The price includes 4.00 4.00 nr
complete works with all accessories to complete the work as per
specifications and manufacturer recommendations.

Construction of UG Storage tank with complete civil works


including excavation, blinding concrete C15, base slab, walls,
cover slabs beams, staircase in reinforced concrete C30,
backfilling, disposal, protective coating with water proofing
admixtures from NITOCOTE EP 405 brush bond for all sides of
wall and floor, NITOBOND-EP or equivalent at joints before
3.10 2,400.00 2,400.00 m3
fresh concreting at every joint (Fosroc chemical or equivalent) ,
including the cost of Centering, Shuttering, Finishing and
Reinforcement, Heavy duty Lockable Man hole cover, PVC
coated Rungs, P.V.C Water bars for Construction/ Expansion
Joint, HDPE Puddle flange, GI Vent pipe with mosquito proof
mesh etc complete as per drawings

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 51 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS FOR CIVIL WORKS BUILDINGS BILL NO- 02

RECEPTION BUILDING
LOGISTICS STORAGE

TECHNICAL FACILITY

MHE PARKING SHED


HOUSE & AC PLANT

EXTERNAL WORKS
CUM HELI HANGER
ACCOMMODATION

PUMP ROOM & UG


STORE HOUSE

SENTRY POST
HAZARDOUS
MATERIALS

LV ROOM

HELIPAD
OFFICE

TANK
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

Construction of Holding tank with complete civil works including


excavation, blinding concrete C15, base slab, walls cover slabs
beams, staircase in reinforced concrete C30, backfilling,
disposal, protective coating with water proofing admixtures from
3.11 m3
Fosroc, BASF or equivalent, including the cost of Centering,
Shuttering, Finishing and Reinforcement, manhole Cover
Construction Joints, HDPE Puddle Flanges, etc complete as per
drawings

3.11.1 5 cu.m 5.00 5.00 m3


3.11.2 50 cu.m 50.00 50.00 m3

RUNGS

Supply & Fixing in position theof size 300mm x 150mm for UG


Sump Tank including placing 150mm inside concrete (while
3.12 doing formwork), aligning during concreting, grouting the junction 32 32.00 nr
if required, cleaning etc., as per standard specifications / detailed
drawings and as directed by engineer-in-charge.

PUDDLE FLANGES

Supplying, Fabricating and Installing for Tanks with anchors in


the form of rods or flats, including lifting and fixing in position,
3.13 making necessary opening in formwork, etc, complete, as per 8 8.00 nr
standard specifications / approved detailed drawings and as
directed by engineer-in-charge.

P.V.C WATER BAR

Providing and placing in position suitable P.V.C WATER BAR or


equivalent for Construction / Expansion Joints between two RCC
3.14 212 212.00 m
members and fixed to the reinforcement with binding wire before
pouring fresh concrete etc. complete:

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 52 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS FOR CIVIL WORKS BUILDINGS BILL NO- 02

RECEPTION BUILDING
LOGISTICS STORAGE

TECHNICAL FACILITY

MHE PARKING SHED


HOUSE & AC PLANT

EXTERNAL WORKS
CUM HELI HANGER
ACCOMMODATION

PUMP ROOM & UG


STORE HOUSE

SENTRY POST
HAZARDOUS
MATERIALS

LV ROOM

HELIPAD
OFFICE

TANK
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

Fabrication , Supply and erectionof GRP TX yard.


1. Fabrication, supply & erection to site of GRP T.X. yard
encloser as per MEDC standard & subjected to MEDC approval
including all necessary internal finishes as per the drawings.
2. Complete electrical works, drainage & water supply, fire
3.15 1 1.00 nr
fighting and HVAC works as per Client's requirement.
3. All necessary final finishes including floorng, painting, doors
windows etc complete.
4. Shop drawing for all the above to be submitted for approval
prior to the commencement of works at site.

Covered Car Parking

Supply & fixing of knitted and woven Strong high density


polyethylene Fabric sheet material for roof covering for the car
parking that can withstand high levels of continuous tension &
3.16 UV protected (gale pacific Australian make or equivalent) The 205.00 205.00 m2
price included Structural Steel and any work and all accessories
to finish work as per specifications and manufacturer
recommendations and as per the drawings

TO COLLECTION

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 53 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS FOR CIVIL WORKS BUILDINGS BILL NO- 02

RECEPTION BUILDING
LOGISTICS STORAGE

TECHNICAL FACILITY

MHE PARKING SHED


HOUSE & AC PLANT

EXTERNAL WORKS
CUM HELI HANGER
ACCOMMODATION

PUMP ROOM & UG


STORE HOUSE

SENTRY POST
HAZARDOUS
MATERIALS

LV ROOM

HELIPAD
OFFICE

TANK
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

3.3 ADDITIONAL ITEMS

If in the opinion of the contractor there are some items not


specified in the BOI but indicated in the drawing, the contractor
must consider them below and carry their sum to the summary
items under "Not mentioned in the bill of items but specified in
drawing".

3.3.1 GRC Column Capital & Base 4.00 4.00 no

3.3.2 GRC Bracket 160.00 160.00 no

3.3.3 GRC Coping 340.00 340.00 m

MS Wicket gate 2.00 2.00 no

Landscaping 4,550.00 4,550.00 m2

Trees 20.00 20.00 no

Date Plam 20.00 20.00 no

900x900 Manhole cover 2.00 2.00 no

Water proof coating to inside the water tank 1,040.00 1,040.00 m2

Helipad marking 1.00 1.00 item

Open RCC Platform 1,500.00 1,500.00 m2

Soil Investigation works 1.00 item

Detailed Design of Architectural, Structural, MEP, HVAC & Utility


1.00 item
works

Detailed Design of Landscaping works 1.00 item

TO COLLECTION

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 55 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD
LOGISTICS S.A.O.C

BILL NO. - 02 - (BILL OF QUANTITIES SUMMARY)

ITEM REF. ITEM DESCRIPTION TOTAL PRICE RIALS OMANI

1 SUBSTRUCTURE INCLUDING GRADE SLAB

1.1 EARTH WORKS

1.2 CONCRETE WORKS

1.3 REINFORCEMENT

1.4 FORM WORKS

1.5 ACCESSORIES/SUNDRY ITEMS

1.6 MASONRY

1.7 METAL WORKS

1.8 MOISTURE PROTECTION

2 SUPERSTRUCTURE

2.1 CONCRETE WORKS

2.2 REINFORCEMENT

2.3 FORM WORKS

2.4 PRE-CAST CONCRETE

2.5 MASONRY

2.6 METAL WORKS

2.7 THERMAL AND MOISTURE PROTECTION

2.8 DOORS AND WINDOWS WORKS

2.9 FINISHES

2.10 FURNISHINGS

2.11 MISCELLANEOUS

3 EXTERNAL WORKS

3.3 ADDITIONAL ITEMS EXTERNAL WORKS

CARRIED TO GENERAL SUMMARY

IMPORTANT NOTE
1 This is a lump sum tender
2 Items provided in this tender are purely indicative. Contractors to verify and quote accordingly.

Schedule of items in conjunction with drawings and specifications constitute complete tender.The tenderers are responsible for all
the quantities they consider necessary for the proper submission of the tender in accordance with the conditions of contract,
3 drawings and specification.In case the contractor/Tenderer notice any item missing in the BOI he should include the same in this
quoted value and submit with the tender, a list of such items along with relevant specifications and quantities. No claims shall be
entertained at a later stage for items not listed in the schedule but mentioned in the drawings.

4 GRAND TOTAL is to include for items not included here but required to complete all works.

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 56 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S
EMDAD LOGISTICS S.A.O.C

STRUCTURAL STEEL WORKS BUILDINGS BILL NO- 03

MHE Parking
TECHNICAL
LOGISTICS

AC PLANT
STORAGE

CUM HELI
HOUSE &

FACILITY

HANGER

Shed
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

PRIMARY AND SECONDARY MEMBERS

SUPPLY & FABRICATION

Supply, fabrication of structural steel including loading,


Freight to Job Site and unloading, the following items
complete as per drawings with all connections including
Sand blasting and shop priming with one coat of Red
Oxide primer for: Columns, Stub-Columns, Beams, Crane
1 Beams, roof trusses, Rafters, monorail Beams, Pipes, 1.000 item
Eaves struts, portal frames, Tie Beams, bracings, fascia
supports, Base Plates, brackets, connection plates,
Anchor bolts and connection bolts as per drawings: All
Anchor bolts and connection bolts shall be hot dip
galvanized

1.1 In Primary Members Grade 43 / Grade 50 t

In Secondary Members- Purlins, eave struts, girts,


2 connection bolts, sag rods, anti sag rods,cleats- Grade t
50...............

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 57 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S
EMDAD LOGISTICS S.A.O.C

STRUCTURAL STEEL WORKS BUILDINGS BILL NO- 03

MHE Parking
TECHNICAL
LOGISTICS

AC PLANT
STORAGE

CUM HELI
HOUSE &

FACILITY

HANGER

Shed
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

In angle iron brackets, inserts, knee pieces etc., for


supporting cable trays, pipes and such other service,
3 t
including bolting/welding to main steel structures, decking
sheets or embedding in concrete structures.

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 58 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S
EMDAD LOGISTICS S.A.O.C

STRUCTURAL STEEL WORKS BUILDINGS BILL NO- 03

MHE Parking
TECHNICAL
LOGISTICS

AC PLANT
STORAGE

CUM HELI
HOUSE &

FACILITY

HANGER

Shed
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

ERECTION

Erection of complete structural steel works for Primary


Members, secondary members, cable trays supports,
connection plates, connection bolts, welded connections
4 etc, using cranes, scaffolding and fixing in position to any t
floor level as indicated on drawings and as required to
complete the works as per the approved drawings. (Water
tightness test inclusive)

ROOF SHEETING AND SIDE CLADDING

Supply and fixing the following items with required


Overlaps, necessary bolts, nuts, washers and self
5
tapping/self drilling screws over purlins at all heights, as
per drawings:

Supply and fixing 0.7mm thick single skin Aluminum pre-


5.1 painted polyester coated profile panels including ridge m2
cover panels for roof as per drawings:

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 59 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S
EMDAD LOGISTICS S.A.O.C

STRUCTURAL STEEL WORKS BUILDINGS BILL NO- 03

MHE Parking
TECHNICAL
LOGISTICS

AC PLANT
STORAGE

CUM HELI
HOUSE &

FACILITY

HANGER

Shed
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

Supply and fixing 0.7mm thick single skin Aluminum pre-


5.2 painted polyester coated profile panels for wall /facia as m2
per drawings:

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 60 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S
EMDAD LOGISTICS S.A.O.C

STRUCTURAL STEEL WORKS BUILDINGS BILL NO- 03

MHE Parking
TECHNICAL
LOGISTICS

AC PLANT
STORAGE

CUM HELI
HOUSE &

FACILITY

HANGER

Shed
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

Supply and fixing Sandwich panel 50mm thick consisting


of 0.7mm thick aluminium polyester coated 35/250 profile
top sheet with 50mm thick polyurethene injection
insulation (Density 35 Kg/m3) and 0.5mm thick aluminium
5.3 m2
polyester coated low rib profile liner sheet in roof including
fixing with complete accessories including ridge cover as
per drawings. with necessary foam closer , mastic
sealants to close the gap.

Supply and fixing Sandwich panel 50mm thick consisting


of 0.7mm thick aluminium polyester coated 35/250 profile
top sheet with 50mm thick polyurethene injection
insulation (Density 35 Kg/m3) and 0.5mm thick aluminium
5.4 m2
polyester coated low rib profile liner sheet in Wall
including fixing with complete accessories as per
drawings. with necessary foam closer , mastic sealants to
close the gap.

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 61 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S
EMDAD LOGISTICS S.A.O.C

STRUCTURAL STEEL WORKS BUILDINGS BILL NO- 03

MHE Parking
TECHNICAL
LOGISTICS

AC PLANT
STORAGE

CUM HELI
HOUSE &

FACILITY

HANGER

Shed
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

Supply and fixing Sandwich panel 100mm thick consisting


of 0.7mm thick aluminium polyester coated 35/250 profile
top sheet with 100mm thick polyurethene injection
insulation (Density 35 Kg/m3) and 0.5mm thick aluminium
5.5 m2
polyester coated low rib profile liner sheet in roof including
fixing with complete accessories including ridge cover as
per drawings. with necessary foam closer , mastic
sealants to close the gap.

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 62 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S
EMDAD LOGISTICS S.A.O.C

STRUCTURAL STEEL WORKS BUILDINGS BILL NO- 03

MHE Parking
TECHNICAL
LOGISTICS

AC PLANT
STORAGE

CUM HELI
HOUSE &

FACILITY

HANGER

Shed
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

Supply and fixing Sandwich panel 100mm thick consisting


of 0.7mm thick aluminium polyester coated 35/250 profile
top sheet with 100mm thick polyurethene injection
insulation (Density 35 Kg/m3) and 0.5mm thick aluminium
5.6 m2
polyester coated low rib profile liner sheet in Wall
including fixing with complete accessories as per
drawings. with necessary foam closer , mastic sealants to
close the gap.

Supply and fixing 1mm thick colour coated aluminium


5.7 gutter including all internal flashings as indicated in the m
drawings.

Supply and fixing 1mm thick colour coated aluminium


5.8 Down take pipes with all internal flashings as indicated in m
the drawings.

Supply and fixing Ridge Ventilator with sealants, fasteners


5.9 with all necessary accessories required as per m
manufacturer's specifications.

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 63 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S
EMDAD LOGISTICS S.A.O.C

STRUCTURAL STEEL WORKS BUILDINGS BILL NO- 03

MHE Parking
TECHNICAL
LOGISTICS

AC PLANT
STORAGE

CUM HELI
HOUSE &

FACILITY

HANGER

Shed
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

Supply and fixing 1mm thick polycarbonate translucent


sheets including frames on the roof and walls as per
5.10 locations indicated in drawings matching profile with
sealants, screws and water proofing tests as prescribed,
complete

a 3000mmx1000mm double layer nr

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 64 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S
EMDAD LOGISTICS S.A.O.C

STRUCTURAL STEEL WORKS BUILDINGS BILL NO- 03

MHE Parking
TECHNICAL
LOGISTICS

AC PLANT
STORAGE

CUM HELI
HOUSE &

FACILITY

HANGER

Shed
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

Supply and fixing 0.7mm thick single skin color coated


5.11 Aluminum profile panels including ridge cover panels for m2
roof as per drawings:

Supply and fixing 0.7mm thick single skin color coated


5.12 m2
Aluminum profile panels for facia as per drawings:

Supply, fabricate & erection of Steel Staircases,


comprising stringers, treads, landing, handrails,
gratings/chequered plate for steps, secondary
6 beam/support , including all welded and bolted t
connections, all necessary fixing accessories, at all levels
with one coat of primer and two coats of enamel paint, as
per drawing.

Provide and fix in position angle iron brackets, inserts,


knee pieces etc., for supporting cable trays, pipes and
7 such other service, including bolting/welding to main steel t
structures, decking sheets or embedding in concrete
structures.

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 65 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S
EMDAD LOGISTICS S.A.O.C

STRUCTURAL STEEL WORKS BUILDINGS BILL NO- 03

MHE Parking
TECHNICAL
LOGISTICS

AC PLANT
STORAGE

CUM HELI
HOUSE &

FACILITY

HANGER

Shed
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

Providing cutout, openings in wall Roof ceiling etc as per


8 drawings & engineer instruction same to be sealed for air item
tightness & water tightness as per drawings

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 66 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S
EMDAD LOGISTICS S.A.O.C

STRUCTURAL STEEL WORKS BUILDINGS BILL NO- 03

MHE Parking
TECHNICAL
LOGISTICS

AC PLANT
STORAGE

CUM HELI
HOUSE &

FACILITY

HANGER

Shed
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

PAINTING WORKS

Providing and applying Painting to structural steel shall


include cleaning at job site The work is to be carried out
in close co-ordination with steel erectors and shall be
9 applied by authorised agencies only. Steel in close contact
with masonary walls, will be painted prior to the
construction of the walls. The material used will be
approved by the R.O.P.

Providing and applying One Hour fire rated intumesant


paint as per manufacturer's specificatons for steel work, to
9.1 m2
all vertical members like columns, rafters, beams
supporting structures,unless otherwise stated.

Providing and applying Two coats of enamel paint


inclusive of primer of approved quality and shade as per
9.2 manufacturer's specificatons for steel work to all rafters, m2
mezzanine floor beams and secondary members, unless
otherwise stated. (total 130micron)

TO COLLECTION

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 67 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S
EMDAD LOGISTICS S.A.O.C

STRUCTURAL STEEL WORKS BUILDINGS BILL NO- 03

MHE Parking
TECHNICAL
LOGISTICS

AC PLANT
STORAGE

CUM HELI
HOUSE &

FACILITY

HANGER

Shed
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

ADDITIONAL ITEMS FOR STRUCTURAL STEEL


10
WORKS

If in the opinion of the contractor there are some items not


specified in the BOI but indicated in the drawing, the
contractor must consider them below and carry their sum
to the summary items under "Not mentioned in the bill of
items but specified in drawing".

TO COLLECTION
IMPORTANT NOTE
1 This is a lump sum tender
2 Items provided in this tender are purely indicative. Contractors to verify and quote accordingly.

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 68 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S
EMDAD LOGISTICS S.A.O.C

STRUCTURAL STEEL WORKS BUILDINGS BILL NO- 03

MHE Parking
TECHNICAL
LOGISTICS

AC PLANT
STORAGE

CUM HELI
HOUSE &

FACILITY

HANGER

Shed
ITEM TOTAL
ITEM DESCRIPTION UNIT
REF. QUANTITY

Schedule of items in conjunction with drawings and specifications constitute complete tender.The tenderers are responsible for all the
quantities they consider necessary for the proper submission of the tender in accordance with the conditions of contract, drawings and
3 specification.In case the contractor/Tenderer notice any item missing in the BOI he should include the same in this quoted value and
submit with the tender, a list of such items along with relevant specifications and quantities. No claims shall be entertained at a later
stage for items not listed in the schedule but mentioned in the drawings.

4 GRAND TOTAL is to include for items not included here but required to complete all works.

M/s Semac and Partners L.L.C. M/s. EMDAD LOGISTICS SAOC


Page 69 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS ELECTRICAL WORK BILL NO. 4

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

QUANTITY
BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS

TOTAL
ROOM
SL. NO. DESCRIPTION. UNIT

1.0 11KV MV CABLES WORKS:

Supplying, Storing, Laying, termination and testing of 11kV XLPE/SWA//PVC


insulated Copper armored Cable served overall, cable in Concealed conduit,
Trench/Trays/ buried in soil as per MAJAN Electricity & OES standard. The rate
shall include all civil works including excavation in hard or soft soil, hard rock,
backfilling, compaction making the surface good, sand bedding, caution tapes,
route markers, cable protection tiles, & shall be in accordance with Tanweer
Electricity / OES standards. Refer our single line diagram M-1114-EL-00-1005
for details.

Supply & laying of 11KV, 3C x 240 Sqmm XLPE Insulated Copper cable. (I/C
1.1 Mtr 1000 1000
from Tanweer Primary substation to plot substation location).

Supply & installation of Outdoor Termination with earthing kit suitable for 11KV,
1.2 Sets 4 4
3C x 240 Sqmm XLPE Insulated Copper cable with including earthing.

Supply & installation of Indoor Termination kit suitable for 11KV, 3Cx240 Sqmm
1.3 Sets 0
XLPE Insulated Copper cable with including earthing.

1.3 Supply & laying of 11KV, 3Cx 70 Sqmm XLPE Insulated Copper cable . Mtr 8 8

Supply & installation of Outdoor Termination with earthing kit suitable for 11KV,
1.4 Sets 2 2
3Cx70 Sqmm XLPE Insulated Copper cable with including earthing.

1.5 Supply & laying of 11KV, 3Cx 50 Sqmm XLPE Insulated Copper cable . Mtr 0

Supply & installation of Outdoor Termination with earthing kit suitable for 11KV,
1.6 Sets 0
3Cx50 Sqmm XLPE Insulated Copper cable with including earthing.

SUB TOTAL TO SUMMARY

M/s Semac and Partners L.L.C. Electrical BOQ M/s. EMDAD LOGISTICS SAOC
Page 70 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS ELECTRICAL WORK BILL NO. 4

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

QUANTITY
BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS

TOTAL
ROOM
SL. NO. DESCRIPTION. UNIT

2.0 DISTRIBUTION TRANSFORMER & RMU

Supply, Installation, Testing and commissioning of 1000KVA, 11/0.433KV


outdoor ONAN Transformer with off load tap changeover of Voltamp or
equivalent DCRP Approved make transformer with all protection like Bucholz
ararm / trip, Winding temp. alarm/ trip, Oil temp. alarm/trip, contracts etc.
complete set of accessories, mounting arrangement and confirming to OES-5
and shall comply with routine test in accordance with BSS171/IEC
2.1 Set 1 1
Manufactures/Suppliers shall mention the complete name plate detailed of the
transformer and shall submit the drawings and Guarantee particulars. The
contractors will be required to take approval from Majan for detail shop drawing
as per the requirement and specification. No additional charges will be paid for
this. All the execution as per OES Standard / Majan electricity standard
accordingly consider complete scope.

Supply & installation of out door type 11KV, 3phase, 50Hz. Ring Main Unit
(RMU) consisting of 2 nos. ring switches of 630A and 1no. oil ring circuit
breaker of 200A or suitable for 1000KVA transformer including 630A busbar
2.3 arrangement, earth switches, CT’s and relays for transformer protection and Set 1 1
associated components. RMU shall be as per Oman Electricity/ Majan
Standard. Including foundation and related complete scope of work. Ref.
drawings & schematics

Supply, Installation, testing and commissioning of 750KVA Standby Diesel


Generator set (Standby) with acoustic enclosure including suitable cable
terminal box, DG control panel, 2 x 12V battery and all necessary accessories
complete. Contractor to include all control cabling between DG control panel &
AMF panel, Exhaust piping with insulation and 2 coat of heat resistent paint of
approved make, steel support for exhaust piping, fuel piping, body earthing +
neutral earthing, RCC foundation etc. and all related civil works like cable
trenching, chequered plate (10mm thick) with frame angle. All works shall be
2.4 carried out with latest Electricity rules and regulation.Contractor to add charges Set. 1 1
for liasoning with local authority, Electricity rules and regulation for installation of
standby DG set.Contractor to submit the detail of DG set drawings and
Guarantee particulars.etc.(RCC foundation etc. and all related civil works detail
refere Structural drawing). Refer drawing M-1114-EL-00-1005.

M/s Semac and Partners L.L.C. Electrical BOQ M/s. EMDAD LOGISTICS SAOC
Page 71 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS ELECTRICAL WORK BILL NO. 4

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

QUANTITY
BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS

TOTAL
ROOM
SL. NO. DESCRIPTION. UNIT

Supply, installation, testing and commissioning of recangular Diesel fuel tank


(Day tank) capacity 2000ltrs. Construction tank material shall be 5mm thick,
self support saddle type. outlet 40mm with flanged ball valve, 2" Vent raised
upto 500mm complete with wire mesh, overflow 2", Drain 1"with threaded ball
valve and provision for level switch, fuel level guage shall be polyurethane tube
with necessary protection & isolation valve at top & bottom etc complete
2.5 accesssories. Including interconnection between diesel tank to diesel LS 1 1
generatour all piping with necessary water proof painting for pipe etc. with
related all necessary accessories complete work up to generator & all local
authority approval with including related civil work. Refer detail drawing M-1114-
EL-00-1005A.

Providing earthing station inside and outside the Transformer & LV room as per
2.6 Set 1 1
Tanweer Electricity standard including earthing strip

Civil works for the construction of Transformer & LV room as per Tanweer
Electricity Standards including necessary reinforced concrete plinth for
2.5 LS URO
Transformer & RMU as per drawing, access doors etc complete scope of work
as per local authority standard. etc.

SUB TOTAL TO SUMMARY

3.0 LV PANELS

Supply, installation, testing and commissioning of LV-MDB's types are front


operated panel boards of Tanweer Electricity approved make using ABB /
Schneider / Simens breaker made of 14 SWG electro galvanised polyster form-
2 powder coated steel outdoor type weather proof enclouser / GRP enclosure
with colour coated tinned copper bus bar and suitable earthing bus consisting
of the following. All LV Panels are fully type tested assemblies and will comply
with IEC 61439–2 Form 4b Type 6 construction and shall be IP41 for indoor
application.

Supplying of cubicle type front operated Form-4/ Form-2 type Panel Boards of
using ABB/ Schneider equivalent breaker of Tanweer Electricityapproved make
made of 14SWG stove enameled MS sheet with colour coded tinned copper
bus bar and suitable earting bus all as per details given in the drawings. The LV
Panels shall meet the requirement of Tanweer Electricity specification and
standard as applicable. Refer Single Line Diagram for detail scope of work . All
LV Panel shall be earth by 120Sqmm. copper wire. All necessary instrument like
3ph KWH meter, Volt meter, Ammeter shall be suitable for operation for
electrical system and site condition mentioned in SEC. Three phase KWH meter
shall be confirm to BS 5685 / IEC521.

M/s Semac and Partners L.L.C. Electrical BOQ M/s. EMDAD LOGISTICS SAOC
Page 72 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS ELECTRICAL WORK BILL NO. 4

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

QUANTITY
BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS

TOTAL
ROOM
SL. NO. DESCRIPTION. UNIT

Note : 1. Necessary steel support & related Civil works, all outdoor panel
foundation shall be considered for fixing of LV SWGR-TR PANELS, DB's
etc. in the scope of work.
2. Body earthing to be considered for All LV SWGR-TR PANELS, SMDB &
DB's as per Tanweer Electricitystandards.
3. All the Street lighting circuit shall be timer control accordingly consider
complete scope of work with including earthpit as per local authority
standard.

3.1 FEEDER PILLAR-1 (FORM-2) IP 65Rating GRP Enclouser. Set 1 1

INCOMIMG :

One no. 1600A, 4P MCCB with O/C, S/C & E/F release as an incoming with
short circuit capacity 50KA. The LV incoming and outgoing terminal shall be
suitable to connect 7R x 1C x 630mm² XLPE/SWA/PVC copper cable + earth
cable. Refer drawing No. M-1114-EL-00-1005.

BUS BAR :

One set of 2000 Amp, 433 Volt, three phase, 4 wire color coded tinned copper
busbar. Bus bar shall withstand the fault level 50KA for 1 sec. with including
suitable busbar extenstion for outgoing cables

INSTRUMENTS :

One no. 0- 500 Volt, 96 sq mm voltmeter with protection and selector switch

One set of 0 - 1600 Amp 96 sq mm ammeter with CT and selector switch.

One set of R, Y, B phase indicating lamp

KWH & KVARH Meter: Multi function digital tariff meter shall be provided to
read the KWH, KVAh, P.F, Voltage, current etc. CT shall be connected phase
to neutral, 3 element, 3phase, 4 wire system. Current circuit burden shall be
less than 0.5VA. Meter shall be polycarbonate enclosure and operating humidity
up to 95% non-condensing. The product shall be complies with IEC 1036/687
and shall be approved by Tanweer Electricity /Oman Electricity standard..

M/s Semac and Partners L.L.C. Electrical BOQ M/s. EMDAD LOGISTICS SAOC
Page 73 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS ELECTRICAL WORK BILL NO. 4

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

QUANTITY
BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS

TOTAL
ROOM
SL. NO. DESCRIPTION. UNIT

DIGITAL TARIFF METER - IP65 RATING- AS Tanweer ELECTRICITY


3.2 Set 1 1
STANDARD / OES STANDARD.
Supply, installation, testing and commissioning of digital tariff meter out side the
compound wall, front operated type enclosure, Majan Electricity approved
make using Premier/equvalent breaker made of 14 SWG electro galvanised
polyster, powder coated steel outdoor type weather proof & water proof
enclouser with suitable supporting arrangement & related control cable
complete scope of work etc.

KWH & KVARH Meter


Multi function digital tariff meter shall be provided to read the KWH, KVAh, P.F,
Voltage, current etc. CT shall be connected phase to neutral, 3 element,
3phase, 4 wire system. Current circuit burden shall be less than 0.5VA. Meter
shall be polycarbonate enclosure and operating humidity up to 95% non-
condensing. The product shall be complies with IEC 1036/687 and shall be
approved by Tanweer Electricity /Oman Electricity standard.

3.3 AMF PANEL- FORM-4 TYPE Set 1 1

INCOMING.
Two nos. 1600A, 4P MCCB EDO with O/C, S/C & E/F (Micrologic 6.0) releases
as incoming with short circuit capacity 50kA, All two nos. MCCB's shall be
Electrical & Mechanical interlocked. Incoming terminal of the panel shall be
suitable to connect 7R x 1C x 630mm²XLPE/AWA/PVC copper cable + earth
cable from Majan Source & 7R x 1C x 630mm² XLPE/AWA/PVC copper cable +
earth cable from DG Source. Ref. drawing NO. M-1114-EL-00-1005.

Bus Bar.
One set of 2000 Amps, 415 Volts, 3 phase, neutral 50 HZ color coated copper
bus bar.Bus bar shall withstand the fault level of 50KA for 1 sec.

OUTGOING.

One no. 1600A 4P MCCB MDO with O/C+S/C+EF (Micrologic 6.0) releases.

INSTRUMENTS :

Two nos. 0- 500 Volt, 96 sq mm voltmeter with protection and selector switch

Two nos. of 0 - 1600 Amp 96 sq mm ammeter with max. demand indicator and
CT .

M/s Semac and Partners L.L.C. Electrical BOQ M/s. EMDAD LOGISTICS SAOC
Page 74 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS ELECTRICAL WORK BILL NO. 4

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

QUANTITY
BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS

TOTAL
ROOM
SL. NO. DESCRIPTION. UNIT

Two sets of R, Y, B phase indicating lamp

Two sets of ON OFF TRIP Indications lamp (DG Side & Main supply side)

DG Common fault trip indication lamp

Two sets - Off/Manual/Auto/Test selector switch

Two sets - Manual/ on /off selector switch for DG Side & Main supply side.

DG Manual Start/stop selector switch, Emergency stop push button switch &
reset push button swich.

Two sets -Ammeter & Volmeter selector switch.

Two sets -DC- Ammeter & Volmeter selector switch.

Control supply - 24V, 2w, DC Supply for DG,Start/Stop.

Control supply - 240V, 2P,2W, 50Hz, AC For Closing & Opening of MCCB's.

One no. 0- 500 Volt, 96 sq mm voltmeter with protection and selector switch

One set of 0 - 1600 Amp 96 sq mm ammeter with CT and selector switch.

One set of R, Y, B phase indicating lamp

KWH & KVARH Meter: Multi function digital tariff meter shall be provided to
read the KWH, KVAh, P.F, Voltage, current etc. CT shall be connected phase
to neutral, 3 element, 3phase, 4 wire system. Current circuit burden shall be
less than 0.5VA. Meter shall be polycarbonate enclosure and operating humidity
up to 95% non-condensing. The product shall be complies with IEC 1036/687
and shall be approved by Majan Electricity /Oman Electricity standard..

M/s Semac and Partners L.L.C. Electrical BOQ M/s. EMDAD LOGISTICS SAOC
Page 75 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS ELECTRICAL WORK BILL NO. 4

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

QUANTITY
BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS

TOTAL
ROOM
SL. NO. DESCRIPTION. UNIT

3.4 MLVP-1 (FORM - 4) TYPE, Set 1 1

INCOMIMG :

One no. 1600A, 4P MCCB with O/C, S/C & E/F release as an incoming with
short circuit capacity 50KA.including relays for transformer faults The LV
incoming and outgoing terminal shall be suitable to connect 7R x 1C x 630mm²
XLPE/AWA/PVC copper cable + earth cable each incomer. Refer drawing No.
M-1114-EL-00-1005.

BUS BAR :

One set of 2000 Amp, 433 Volt, three phase, 4 wire color coded tinned copper
busbar. Bus bar shall withstand the fault level 50KA for 1 sec.

OUTGOING.

Two nos. 800A TP MCCB with neutral link, O/C+S/C releases. With phase
indicating lamps

Three nos. 630A TP MCCB with neutral link, O/C+S/C releases. With phase
indicating lamps

Two nos. 320A TP MCCB with neutral link, O/C+S/C releases. With phase
indicating lamps

One nos. 63A TP MCCB with neutral link, O/C+S/C releases.

Three nos. 40A TP MCCB with neutral link, O/C+S/C releases.

INSTRUMENTS :

One no. 0- 500 Volt, 96 sq mm voltmeter with protection and selector switch

One set of 0 - 1600 Amp 96 sq mm ammeter with CT and selector switch.

One set of R, Y, B phase indicating lamp

KWH & KVARH Meter: Multi function digital tariff meter shall be provided to
read the KWH, KVAh, P.F, Voltage, current etc. CT shall be connected phase
to neutral, 3 element, 3phase, 4 wire system. Current circuit burden shall be
less than 0.5VA. Meter shall be polycarbonate enclosure and operating humidity
up to 95% non-condensing. The product shall be complies with IEC 1036/687
and shall be approved by Tanweer Electricity /Oman Electricity standard..

M/s Semac and Partners L.L.C. Electrical BOQ M/s. EMDAD LOGISTICS SAOC
Page 76 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS ELECTRICAL WORK BILL NO. 4

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

QUANTITY
BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS

TOTAL
ROOM
SL. NO. DESCRIPTION. UNIT

3.5 SMDB-1 (FORM-2) - PUMP ROOM Set 1 1

INCOMIMG :

One no. 630A, 4P MCCB with O/C, S/C & E/F release as an incoming with short
circuit capacity 50KA. The LV incoming and outgoing terminal shall be suitable
to connect 2R x 4C x 150mm² XLPE/SWA/PVC copper cable + earth cable.
Refer drawing No.M-1114-EL-00-1006.

BUS BAR :

One set of 800 Amp, 433 Volt, three phase, 4 wire color coded tinned copper
busbar. Bus bar shall withstand the fault level 50KA for 1 sec.

OUTGOING.

Two nos. 400A TP MCCB with neutral link, O/C+S/C releases.

Two nos. 125A TP MCCB with neutral link, O/C+S/C releases.

One nos. 63A TP MCCB with neutral link, O/C+S/C releases.

Two nos. 40A TP MCCB with neutral link, O/C+S/C releases.

One nos. 32A TP MCCB with neutral link, O/C+S/C releases.

INSTRUMENTS :

One no. 0- 500 Volt, 96 sq mm voltmeter with protection and selector switch

One set of 0 - 600 Amp 96 sq mm ammeter with CT and selector switch.

One set of R, Y, B phase indicating lamp

KWH & KVARH Meter: Multi function digital tariff meter shall be provided to
read the KWH, KVAh, P.F, Voltage, current etc. CT shall be connected phase
to neutral, 3 element, 3phase, 4 wire system. Current circuit burden shall be
less than 0.5VA. Meter shall be polycarbonate enclosure and operating humidity
up to 95% non-condensing. The product shall be complies with IEC 1036/687
and shall be approved by Majan Electricity /Oman Electricity standard..

M/s Semac and Partners L.L.C. Electrical BOQ M/s. EMDAD LOGISTICS SAOC
Page 77 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS ELECTRICAL WORK BILL NO. 4

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

QUANTITY
BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS

TOTAL
ROOM
SL. NO. DESCRIPTION. UNIT

SMDB-2 (FORM-2) - Office, Logistics store house & sentry post-2. IP65
3.5 Set 1 1
Rating GRP Enclosure.

INCOMIMG :

One no. 630A, 4P MCCB with O/C, S/C & E/F release as an incoming with short
circuit capacity 50KA. The LV incoming and outgoing terminal shall be suitable
to connect 2R x 4C x 240mm² XLPE/SWA/PVC copper cable + earth cable.
Refer drawing No.M-1114-EL-00-1006.

BUS BAR :

One set of 800 Amp, 433 Volt, three phase, 4 wire color coded tinned copper
busbar. Bus bar shall withstand the fault level 50KA for 1 sec.

OUTGOING.

Four nos. 125A TP MCCB with neutral link, O/C+S/C releases.

Four nos. 100A TP MCCB with neutral link, O/C+S/C releases.

Two nos. 63A TP MCCB with neutral link, O/C+S/C releases.

Three nos. 40A TP MCCB with neutral link, O/C+S/C releases.

Three nos. 32A TP MCCB with neutral link, O/C+S/C releases.

INSTRUMENTS :

One no. 0- 500 Volt, 96 sq mm voltmeter with protection and selector switch

One set of 0 - 600 Amp 96 sq mm ammeter with CT and selector switch.

One set of R, Y, B phase indicating lamp

KWH & KVARH Meter: Multi function digital tariff meter shall be provided to
read the KWH, KVAh, P.F, Voltage, current etc. CT shall be connected phase
to neutral, 3 element, 3phase, 4 wire system. Current circuit burden shall be
less than 0.5VA. Meter shall be polycarbonate enclosure and operating humidity
up to 95% non-condensing. The product shall be complies with IEC 1036/687
and shall be approved by Majan Electricity /Oman Electricity standard..

M/s Semac and Partners L.L.C. Electrical BOQ M/s. EMDAD LOGISTICS SAOC
Page 78 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS ELECTRICAL WORK BILL NO. 4

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

QUANTITY
BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS

TOTAL
ROOM
SL. NO. DESCRIPTION. UNIT

SMDB-3 (FORM-2) - TECHNICAL FACILITY CUM HELI HANGER. IP65


3.6 Set 1 1
Rating GRP Enclosure.

INCOMIMG :

One no. 320A, 4P MCCB with O/C, S/C & E/F release as an incoming with short
circuit capacity 50KA. The LV incoming and outgoing terminal shall be suitable
to connect 4C x 240mm² XLPE/SWA/PVC copper cable + earth cable. Refer
drawing No.M-1114-EL-00-1006.

BUS BAR :

One set of 400 Amp, 433 Volt, three phase, 4 wire color coded tinned copper
busbar. Bus bar shall withstand the fault level 50KA for 1 sec.

OUTGOING.

Two nos. 125A TP MCCB with neutral link, O/C+S/C releases.

Three nos. 100A TP MCCB with neutral link, O/C+S/C releases.

Three nos. 63A TP MCCB with neutral link, O/C+S/C releases.

Three nos. 40A TP MCCB with neutral link, O/C+S/C releases.

Three nos. 32A TP MCCB with neutral link, O/C+S/C releases.

INSTRUMENTS :

One no. 0- 500 Volt, 96 sq mm voltmeter with protection and selector switch

One set of 0 - 400 Amp 96 sq mm ammeter with CT and selector switch.

One set of R, Y, B phase indicating lamp

KWH & KVARH Meter: Multi function digital tariff meter shall be provided to
read the KWH, KVAh, P.F, Voltage, current etc. CT shall be connected phase
to neutral, 3 element, 3phase, 4 wire system. Current circuit burden shall be
less than 0.5VA. Meter shall be polycarbonate enclosure and operating humidity
up to 95% non-condensing. The product shall be complies with IEC 1036/687
and shall be approved by Majan Electricity /Oman Electricity standard..

M/s Semac and Partners L.L.C. Electrical BOQ M/s. EMDAD LOGISTICS SAOC
Page 79 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS ELECTRICAL WORK BILL NO. 4

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

QUANTITY
BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS

TOTAL
ROOM
SL. NO. DESCRIPTION. UNIT

3.7 APFC PANEL

Supplying, installation, testing and commissioning of 400KVAR cubical type


floor mounted automatic operated power factor control panel with detuned
reactor of Majan/Oman Electricity approved make made out of 14 SWG sheet
a) steel enclouser painted with approved colour. panel incomer 800A 4P MCCB Set 1 1
with O/C, S/C & EF. all outgoing capacitors 480V & 415V Harmonics filter with
7% detuned reactors required accordinly consider complete scope with proper
ventilation & extract fan. Ref. Drawing No. M-1114-EL-00-1005.

SUB TOTAL TO SUMMARY

4.0 LV CABLES

Supplying, storing, laying, termination and testing of 1000V XLPE/SWA//PVC


insulated Copper armoured cable served overall, cable in concealed
pipe/trench/trays/ buried in soil as per Oman Electricity (OES-02, VOL I.) /
Tanweer Electricity Standard. Rate to include cost of all civil works including
A. trenching, excavation, backfilling in soft & hard rock, road cutting and making
good etc. complete. suitable size earth cable to be laid as per Tanweer
Electricity Standard. all the earth cable size refer drawing accordinly consider
complete scope. contractor should consider complete scope as per drawing &
as per local authority standard.

4.1 1C x 630 sq. mm XLPE/AWA/ PVC Sheathed Copper cable + suitable earth Mtr. 525 525

4.2 4C x 240 sq. mm XLPE/SWA/ PVC Sheathed Copper cable + suitable earth Mtr. 570 570

4.3 4C x 185sq. mm XLPE/SWA/ PVC Sheathed Copper cable + suitable earth Mtr. 0

4.4 4C x 150 sq. mm XLPE/SWA/ PVC Sheathed Copper cable + suitable earth Mtr. 190 190

4.5 4C x 120 sq. mm XLPE/SWA/ PVC Sheathed Copper cable + suitable earth Mtr. 0

4.6 4C x 95 sq. mm XLPE/SWA/ PVC Sheathed Copper cable + suitable earth Mtr. 0

4.7 4C x 70 sq. mm XLPE/SWA/ PVC Sheathed Copper cable + suitable earth Mtr. 0

M/s Semac and Partners L.L.C. Electrical BOQ M/s. EMDAD LOGISTICS SAOC
Page 80 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS ELECTRICAL WORK BILL NO. 4

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

QUANTITY
BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS

TOTAL
ROOM
SL. NO. DESCRIPTION. UNIT

4.8 4C x 50 sq. mm XLPE/SWA/ PVC Sheathed Copper cable + suitable earth Mtr. 0

4.9 4C x 35 sq. mm XLPE/SWA/ PVC Sheathed Copper cable + suitable earth Mtr. 30 125 155

4.10 4C x 25 sq. mm XLPE/SWA/ PVC Sheathed Copper cable + suitable earth Mtr. 128 32 160

4.11 4C x 16 sq. mm XLPE/SWA/ PVC Sheathed Copper cable + suitable earth Mtr. 105 187 292

4.12 4C x 10 sq. mm XLPE/SWA/ PVC Sheathed Copper cable + suitable earth Mtr. 74 298 372

4.13 4C x 6 sq. mm XLPE/SWA/ PVC Sheathed Copper cable + suitable earth Mtr. 64 444 508

4.14 4C x 4sq. mm XLPE/SWA/ PVC Sheathed Copper cable + suitable earth Mtr. 0

4.15 4C x 2.5sq. mm XLPE/SWA/ PVC Sheathed Copper cable + suitable earth Mtr. 0

Supply & installation of Indoor/Outdoor Terminating the following cables with all
B appropriate selection of Lugs, glands and gland plate all as per Oman Electricity
standard / Tanweer Electricity Standard and specification.

4.16 1C x 630 sq. mm XLPE/AWA/ PVC Sheathed Copper cable + suitable earth Sets 56 56

4.17 4C x 240 sq. mm XLPE/SWA/ PVC Sheathed Copper cable + suitable earth Sets 12 12

4.18 4C x 185sq. mm XLPE/SWA/ PVC Sheathed Copper cable + suitable earth Sets 0

4.19 4C x 150 sq. mm XLPE/SWA/ PVC Sheathed Copper cable + suitable earth Sets 4 4

4.20 4C x 120 sq. mm XLPE/SWA/ PVC Sheathed Copper cable + suitable earth Sets 0

4.21 4C x 95 sq. mm XLPE/SWA/ PVC Sheathed Copper cable + suitable earth Sets 0

4.22 4C x 70 sq. mm XLPE/SWA/ PVC Sheathed Copper cable + suitable earth Sets 0

M/s Semac and Partners L.L.C. Electrical BOQ M/s. EMDAD LOGISTICS SAOC
Page 81 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS ELECTRICAL WORK BILL NO. 4

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

QUANTITY
BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS

TOTAL
ROOM
SL. NO. DESCRIPTION. UNIT

4.23 4C x 50 sq. mm XLPE/SWA/ PVC Sheathed Copper cable + suitable earth Sets 0

4.24 4C x 35 sq. mm XLPE/SWA/ PVC Sheathed Copper cable + suitable earth Sets 6 6

4.25 4C x 25 sq. mm XLPE/SWA/ PVC Sheathed Copper cable + suitable earth Sets 8 8

4.26 4C x 16 sq. mm XLPE/SWA/ PVC Sheathed Copper cable + suitable earth Sets 10 10

4.27 4C x 10 sq. mm XLPE/SWA/ PVC Sheathed Copper cable + suitable earth Sets 14 14

4.28 4C x 6 sq. mm XLPE/SWA/ PVC Sheathed Copper cable + suitable earth Sets 16 16

4.29 4C x 4sq. mm XLPE/SWA/ PVC Sheathed Copper cable + suitable earth Sets 0

4.30 4C x 2.5sq. mm XLPE/SWA/ PVC Sheathed Copper cable + suitable earth Sets 0

SUB TOTAL TO SUMMARY

M/s Semac and Partners L.L.C. Electrical BOQ M/s. EMDAD LOGISTICS SAOC
Page 82 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS ELECTRICAL WORK BILL NO. 4

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

QUANTITY
BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS

TOTAL
ROOM
SL. NO. DESCRIPTION. UNIT

5.0 DISTRIBUTION BOARDS

Supply, fixing, testing and commissioning of TPN Distribution Boards, wall-


mounted (either surface or recessed type) as per the given schematic
drawings / as per standard specification. MCBs shall be of 'C' Curve and
Dindrailed mounted type. The erection rates shall include fixing (recessed in
wall) of DB on wall/concealed including all fixing accessories, including civil
works etc. All DB's shall be of IP42 protection unless otherwise mentioned.
`RCBO/RCCB shall be used for all 13A socket outlets, shaver sockets, industrial
sockets and All DX - A/C ODU's.

5.1 LDB-LS-01, 12Way TPN DB - LOGISTICS STORAGE HOUSE.

As per given schematic. Refer drawing no.M-1114-EL-01-1004 for detail. Set 1 1

5.2 PDB-LS-01, 16Way TPN DB - LOGISTICS STORAGE HOUSE.

As per given schematic. Refer drawing no.M-1114-EL-01-1004 for detail. Set 1 1

5.3 LDB-TF-01, 14Way TPN DB - TECHNICAL FACILITY CUM HELI HANGER.

As per given schematic. Refer drawing no. M-1114-EL-01-1004 for detail. Set 1 1

5.4 PDB-TF-01, 14Way TPN DB - TECHNICAL FACILITY CUM HELI HANGER.

As per given schematic. Refer drawing no. M-1114-EL-01-1004 for detail. Set 1 1

5.5 PDB-TF-02, 14Way TPN DB - TECHNICAL FACILITY CUM HELI HANGER.

As per given schematic. Refer drawing no. M-1114-EL-01-1004 for detail. Set 1 1

5.6 LPDB-RB-01, 6Way TPN DB - RECEPTION BUILDING.

As per given schematic. Refer drawing no. M-1114-EL-04-1001 for detail. Set 1 1

LDB-O & A-01, 10Way TPN DB - OFFICE ACCOMMODAION GROUND


5.7
FLOOR

As per given schematic. Refer drawing no. M-1114-EL-05-1001 for detail. Set 1 1

M/s Semac and Partners L.L.C. Electrical BOQ M/s. EMDAD LOGISTICS SAOC
Page 83 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS ELECTRICAL WORK BILL NO. 4

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

QUANTITY
BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS

TOTAL
ROOM
SL. NO. DESCRIPTION. UNIT

5.8 LDB-O & A-02, 10Way TPN DB - OFFICE ACCOMMODAION FIRST LOOR

As per given schematic. Refer drawing no. M-1114-EL-05-1001 for detail. Set 1 1

5.9 LPDB-HS-01, 12Way TPN DB - STORE HOUSE HAZARDOUS.

As per given schematic. Refer drawing no. M-1114-EL-06-1001 for detail. Set 1 1

5.10 LPDB-PR-01, 6Way TPN DB - PUMP ROOM

As per given schematic. Refer drawing no. M-1114-EL-07-1001 for detail. Set 1 1

5.11 LPDB-LV-01, 6Way TPN DB - LV ROOM

As per given schematic. Refer drawing no. M-1114-EL-08-1001 for detail. Set 1 1

5.12 LPDB-HP-01, 6Way TPN DB - HELI PAD AREA OUTDOOR TYPE, IP65 Rating.

As per given schematic. Refer drawing no. M-1114-EL-09-1001 for detail. Set 1 1

5.13 LPDB-SP-01, 4Way TPN DB - SENTRY POST-2

As per given schematic. Refer drawing no. M-1114-EL-10-1001 for detail. Set 1 1

NOTE:- MCB/ELCB DB Accessories:

Adoptor / draw box suitable for 4/8/12/16 Way TPN MCB/ELCB Distribution
Boards of type VTPN / HTPN. The rate shall include supply and fixing the box
with fixing accessories. The adoptor box / draw box shall be fabricated with 16
G MS Powder coated to the same colour as that of the DB. The Draw box
should be fixed with the cover. The width and Depth of the drawbox shall be
150mmX100mm & length will depend as per the site condition. Etc. related
complete scope as per site condition.

SUB TOTAL TO SUMMARY.

M/s Semac and Partners L.L.C. Electrical BOQ M/s. EMDAD LOGISTICS SAOC
Page 84 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS ELECTRICAL WORK BILL NO. 4

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

QUANTITY
BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS

TOTAL
ROOM
SL. NO. DESCRIPTION. UNIT

6.0 LIGHTING POINT WIRING.

Supplying materials and wiring for light points including switch, and ceiling fan,
conduit accessories & fixing accessories including vertical & horizontal supports
supports etc. with 20mm G.I. Conduit laid in slab/wall/sheeting/above false
ceiling etc. GI conduit with accessories shall be Hot dip Galvanized & Heavy
duty type . along with PVC insulated copper continuous earth wire as per
Tanweer Electricityregulation with all accessories, PVC insulated copper + earth
wire etc. including 2 x 2.5Sq. + 2.5Sq earth for light circuits.

6.1 One light point controlled by one 10A gang switch. Nos. 0

6.2 Two light points controlled by one 10A gang switch Nos. 0

6.3 Three light points controlled by one 10A gang switch Nos. 0

6.4 Four light points controlled by one 10A gang switch Nos. 0

6.5 Five light points controlled by one 10A gang switch Nos. 0

6.6 Six light points controlled by one 10A gang switch Nos. 0

6.7 Seven light points controlled by one 10A gang switch Nos. 0

6.8 Nine light points controlled by one 10A gang switch Nos. 0

6.9 More than ten light points controlled by one 10A gang switch Nos. 0

6.10 One light points controlled by Two Nos. 10A two way switch Nos. 0

6.11 Two light points controlled by Two Nos. 10A two way switch Nos. 0

6.12 Three light points controlled by Two Nos. 10A two way switch Nos. 0

6.13 Four light points controlled by Two Nos. 10A two way switch Nos. 0

6.14 Five light points controlled by Two Nos. 10A two way switch Nos. 0

6.15 Six light points controlled by Two Nos. 10A two way switch Nos. 0

6.16 Seven light points controlled by Two Nos. 10A two way switch Nos. 0

6.17 Eight light points controlled by Two Nos. 10A two way switch Nos. 0

6.18 Nine light points controlled by Two Nos. 10A two way switch Nos. 0

Sixteen no light points controlled by one 20A Timer with controlled switch. (I/C
6.19 Set 0
Cable from nearest DB, as per drawing.)

M/s Semac and Partners L.L.C. Electrical BOQ M/s. EMDAD LOGISTICS SAOC
Page 85 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS ELECTRICAL WORK BILL NO. 4

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

QUANTITY
BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS

TOTAL
ROOM
SL. NO. DESCRIPTION. UNIT

Thirteen no light points controlled by one 20A Timer with controlled switch. (I/C
6.20 Set 0
Cable from nearest DB, as per drawing.)

Fourteen nos light points controlled by one 20A Timer with controlled switch.
6.21 Set 0
(I/C Cable from nearest DB, as per drawing.)

Fifteen nos light points controlled by one 20A Timer with controlled switch. (I/C
6.22 Set 0
Cable from nearest DB, as per drawing.)

Sixteen nos light points controlled by one 20A Timer with controlled switch. (I/C
6.23 Set 0
Cable from nearest DB, as per drawing.)

One to Five nos Emergency & exit light points controlled circuit through MCB
6.24 Set 0
controlled . (I/C Circuit from nearest DB, as per drawing.)

Six to Ten nos Emergency & exit light points controlled circuit through MCB
6.25 Set 0
controlled . (I/C Circuit from nearest DB, as per drawing.)

Eleven to Fifteen nos Emergency & exit light points controlled circuit through
6.25 Set 0
MCB controlled . (I/C Circuit from nearest DB, as per drawing.)

Sixteen to Twenty nos Emergency & exit light points controlled circuit through
6.27 Set 0
MCB controlled . (I/C Circuit from nearest DB, as per drawing.)

Twentyone to twentyfive nos Emergency & exit light points controlled circuit
6.28 Set 0
through MCB controlled . (I/C Circuit from nearest DB, as per drawing.)

Twentyfive to Thirty nos Emergency & exit light points controlled circuit through
6.29 Set 0
MCB controlled . (I/C Circuit from nearest DB, as per drawing.)

Thirty to thirtyfive nos Emergency & exit light points controlled circuit through
6.30 Set 0
MCB controlled . (I/C Circuit from nearest DB, as per drawing.)

Thirtysix to fourty nos Emergency & exit light points controlled circuit through
6.31 Set 0
MCB controlled . (I/C Circuit from nearest DB, as per drawing.)

SUB TOTAL TO SUMMARY.

M/s Semac and Partners L.L.C. Electrical BOQ M/s. EMDAD LOGISTICS SAOC
Page 86 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS ELECTRICAL WORK BILL NO. 4

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

QUANTITY
BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS

TOTAL
ROOM
SL. NO. DESCRIPTION. UNIT

7.0 POWER WIRING

Supplying materials and wiring for socket outlets and points for exhaust fan,
ceiling fan, Roof extract fan etc. with 25mm G.I.Conduit laid in
slab/wall/sheeting/above false ceiling etc. GI conduit with accessories shall be
Hot dip Galvanized & Heavy duty type, along with PVC insulated copper
continuous earth wire as per Tanweer Electricityregulation with all accessories,
PVC insulated copper + earth wire etc. including 2R x 4 Sq. wires + 4 Sq earth
for single phase socket outlets and 4R x 6 Sqmm wires + 6 Sqmm earth for
three phase outlet /roof extract fans as following :

7.1 13A, Twin switched socket outlet. Nos. 121 3 2 126

13A Industrial Twin type switch socket weather proof & water proof type.IP
7.2 Nos. 2 2
65rating
13A, Twin switched socket outlet.Explosion proof type weather proof & water
7.3 Nos. 0
proof type.IP 65 rating (Battery room / Hazardous store)

16A 3 Pin Single Phase Industrial type plug & socket weather proof, water proof
7.4 Nos. 7 8 2 2 19
type. IP65 rating

16A 3 5Pin Three Phase Industrial type plug & socket socket weather proof &
7.5 Nos. 0
water proof type. IP65 rating

20A 5pin Three Phase Explosion proof Industrial type switch socket weather
7.6 Nos. 3 2 5
proof & water proof type.IP 65 rating (Battery room / Hazardous store)

32A 5pin, 3 Phase Industrial type plug & socket weather proof & water proof
7.7 Nos. 2 8 10
type. IP65 Rating

32A 5pin, 3 Phase Industrial Explosion proof type plug & socket weather proof
7.8 Nos. 1 2 3
& water proof type. IP67 Rating (Battery room / Hazardous store).

7.9 20A 1 phase industrial type weather proof Isolator, IP 65 Rating Nos. 1 1 1 2 2 2 9

7.10 20A 3 phase industrial type weather proof Isolator, IP 65 Rating. Nos. 3 5 3 1 12

7.11 32A 3 phase industrial type weather proof Isolator, IP 65 Rating. Nos. 6 4 3 1 14

7.12 63A 3 phase industrial type weather proof Isolator, IP 65 Rating. Nos. 1 1

7.13 100A 3 phase industrial type weather proof Isolator, IP 65 Rating. Nos. 2 2

7.14 125A 3 phase industrial type weather proof Isolator, IP 65 Rating. Nos. 1 2 3

7.15 150A 3 phase industrial type weather proof Isolator, IP 65 Rating. Nos. 0

M/s Semac and Partners L.L.C. Electrical BOQ M/s. EMDAD LOGISTICS SAOC
Page 87 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS ELECTRICAL WORK BILL NO. 4

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

QUANTITY
BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS

TOTAL
ROOM
SL. NO. DESCRIPTION. UNIT

7.16 20A DP switch for A/C, water heater,industrial fan and hand dryer. Nos. 71 3 4 78

7.17 One 20A flex outlet for A/C, water heater and hand dryer. Nos. 71 3 4 78

7.18 Wiring for Cooker outlet. Nos. 2 2

7.19 Wiring for exhaust fan related switch with flex outlet- 1phase , 230V/50Hz. Nos. 21 2 2 25

7.20 Wiring for wall mounted industrial exhaust fan - 3 phase, 433V/50Hz, Nos. 0

7.21 Wiring for Ducted extract fan - 1phase, 230V/50Hz, Nos. 0

7.22 Wiring for Ceiling fan with regulatour- 1phase , 230V/50Hz. Nos. 2 2

Supplying and fixing of 3 compartment type Modular floor junction box


recessed in floor near the workstations for power sockets, data & telephone
7.23 coverd by suitable covering plate ref dwg. Including chasing the Wall/Floor and Nos. 9 9
filling it up by cement mortor and making the surface good related complete
scope including related complete civil work.

40A, 3phase MCCB with bus bar extenstion suitable cable termination box. IP65
7.24 Nos. 0
Rating.

63A, 3phase MCCB with bus bar extenstion suitable cable termination box.IP65
7.25 Nos. 0
Rating.

SUB TOTAL TO SUMMARY.

M/s Semac and Partners L.L.C. Electrical BOQ M/s. EMDAD LOGISTICS SAOC
Page 88 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS ELECTRICAL WORK BILL NO. 4

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

QUANTITY
BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS

TOTAL
ROOM
SL. NO. DESCRIPTION. UNIT

8.0 SOCKET OUTLETS.

Supplying, fixing and testing of the following items. Combined housed in M.S/G.I
box of suitable size as per approved. GI conduit shall be Hot dip Galvanized
with Heavy duty type

8.1 13A, Twin switched socket outlet. Nos. 121 3 2 126

13A Industrial Twin type switch socket weather proof & water proof type.IP 65
8.2 Nos. 2 2
rating

13A, Twin switched socket outlet.Explosion proof type weather proof & water
8.3 Nos. 0
proof type.IP 65 rating. (Battery room / Hazardous store)

16A 3 Pin Single Phase Industrial type plug socket weather proof & water proof
8.4 Nos. 7 8 2 2 19
type.IP 65 rating

16A 5Pin Three Phase Industrial type plug socket weather proof & water proof
8.5 Nos. 0
type.IP 65 rating

16A 3pin Single Phase Explosion proof Industrial type plug socket weather
8.6 Nos. 3 2 5
proof & water proof type.IP 65 rating

32A 5pin, 3Phase Industrial type plug & socket weather proof & water proof
8.7 Nos. 2 8 10
type. IP 67 Rating

32A 5pin, 3Phase Industrial Explosion proof type plug & socket weather proof
8.8 Nos. 1 2 3
& water proof type. IP 67 Rating

8.9 20A 1 phase industrial type weather proof Isolator, IP 65 Rating Nos. 1 1 1 2 2 2 9

8.10 20A 3 phase industrial type weather proof Isolator, IP 65 Rating. Nos. 3 5 3 1 12

8.11 32A 3 phase industrial type weather proof Isolator, IP 65 Rating. Nos. 6 4 3 1 14

8.12 63A 3 phase industrial type weather proof Isolator, IP 65 Rating. Nos. 1 1

8.13 100A 3 phase industrial type weather proof Isolator, IP 65 Rating. Nos. 2 2

8.14 125A 3 phase industrial type weather proof Isolator, IP 65 Rating. Nos. 1 2 3

8.15 150A 3 phase industrial type weather proof Isolator, IP 65 Rating. Nos. 0

8.16 20A DP switch for A/C, water heater,industrial fan and hand dryer. Nos. 71 3 4 78

8.17 One 20A flex outlet for A/C, water heater and hand dryer. Nos. 71 3 4 78

8.18 Cooker outlet. Nos. 2 2

M/s Semac and Partners L.L.C. Electrical BOQ M/s. EMDAD LOGISTICS SAOC
Page 89 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS ELECTRICAL WORK BILL NO. 4

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

QUANTITY
BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS

TOTAL
ROOM
SL. NO. DESCRIPTION. UNIT

8.19 exhaust fan related switch with flex outlet- 1phase , 230V/50Hz. Nos. 21 2 2 25

8.20 Wall mounted industrial fan switch with flex outlet - 1phase, 230V/50Hz, Nos. 0

8.21 Ducted extract fan related switch with flex outlet - 1phase, 230V/50Hz, Nos. 0

8.22 Ceiling fan with regulatour related switch with flex outlet- 1phase , 230V/50Hz. Nos. 0

Supplying and fixing of 3 compartment type Modular floor junction box


recessed in floor near the workstations for power sockets, data & telephone
8.23 coverd by suitable covering plate ref dwg. Including chasing the Wall/Floor and Nos. 9 9
filling it up by cement mortor and making the surface good related complete
scope including related complete civil work.

40A, 3phase MCCB with bus bar extenstion suitable cable termination box. IP65
8.24 Nos. 0
Rating.

63A, 3phase MCCB with bus bar extenstion suitable cable termination box.IP65
8.25 Nos. 0
Rating.

125A, 3phase MCCB with bus bar extenstion suitable cable termination box.
8.26 Nos. 0
Processing plant Blower/compressor room. IP65rating.

160A, 3phase MCCB with bus bar extenstion suitable cable termination box.
8.27 Nos. 0
Near Packing area Processing Plant. IP65rating.

SUB TOTAL TO SUMMARY.

M/s Semac and Partners L.L.C. Electrical BOQ M/s. EMDAD LOGISTICS SAOC
Page 90 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS ELECTRICAL WORK BILL NO. 4

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

QUANTITY
BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS

TOTAL
ROOM
SL. NO. DESCRIPTION. UNIT

9.0 TELEPHONE CONDUITING & WIRING

9.1 JELLY FILLED CABLES

Supply, laying & termination of telephone cables, armoured, annealed tinned


copper conductor and petroleum jelly filled with polythene outer jackets
conforming to Saudi specification. The method of laying shall be similar to
power cables, Telephone cables shall be run in a separate sleeves/trench at
least 300mm away from other power cables. This related civil work for
excavation, filling & cable laying complete scope of work as to be consider. this
rate shall include cable end termination also using kits cable glands, cable lugs,
etc as required complete scope.

a. 20 Pair Armoured Multipair armoured cable outdoor type. Mtrs. URO

Supply, laying & termination of Networking cables, armoured fiber optic cable
laid in the 50mm dia conduit in the burried ground as per Tanweer
ElectricityStandard / Saudi Standard. The method of laying shall be similar to
9.2
power cables, Telephone/data cables shall be run in a separate sleeves/trench
at least 300mm away from other power cables. This related civil work for
excavation, filling & cable laying complete scope of work as to be consider.

a. 100 mm dia PVC Sleeves. Mtr. 1530 1530

RCC Network cable chambers with heavy duty CI manhole covers of "Stanton"
9.3 make with cement mortar 1:3 finished with a floating coat of neat cement inside
and making channels in cement concrete M-30 mix neatly

i) Cable chamber ( 0.6 x 0.6 x 0.85)Mtr. Nos. 15 15

Supplying, fixing and testing of the following items. Combined housed in M.S/G.I
ii) box of suitable size as per approved. GI conduit shall be Hot dip Galvanized Mtr.
with Heavy duty type

9.4 TELEPHONE MAIN DISTRIBUTION BOXES

Supply & erection of suitable of 16gauge M.S box with terminal modules and
covered with 5mm thick Perspex sheet/ MS cover floor monted type cabinet as
required complete acessoress, complete scope of work

a. 50 Pair Telephone Distribuition Box Nos. URO

b. 100 Pair Telephone Distribuition Box Nos. URO

M/s Semac and Partners L.L.C. Electrical BOQ M/s. EMDAD LOGISTICS SAOC
Page 91 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS ELECTRICAL WORK BILL NO. 4

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

QUANTITY
BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS

TOTAL
ROOM
SL. NO. DESCRIPTION. UNIT

9.5 TELEPHONE SOCKETS

Supply & installation of concealed type 16G MS modular junction boxes &
telephone socket outlet and dual face plate with socket outlet with concealed
metal boxes. The quoted rate shall include all required other necessary
accessories complete etc. as required. The installation shall include cost fo
crimping, concealed junction box and all other accessories required.

a. Information outlet - RJ45 type face plate for telephone. Nos. 3 3 71 2 2 2 83

9.6 TELEPHONE & DATA CABLES. (NETWORK CABLES)

Supply & installation of 0.51mm tinned copper conductor unarmoured PVC


insulated telephone cable & 19mm dia MS conduit & outdoor shall be 25mm dia
GI/PVC Conduit, GI conduit shall be Hot dip Galvanized with Heavy duty
type with including realated all civil works as per site condition.The installation &
termination shall include cost fo crimping, concealed junctio box and all other
accessories required and outdoor cable shall be include with excavation &
backfilling, warning tape. Related complete scope.

OUTDOOR TYPE CAT 6A U/UTP, PE Cable for Telephone & Data - 500mtr
a. Box 0
cable reel.

INDOOR TYPE CAT 6A U/UTP, LSOH Cable for Telephone & Data - 500mtr
b. Box 25 25
cable reel.

SUB TOTAL TO SUMMARY.

M/s Semac and Partners L.L.C. Electrical BOQ M/s. EMDAD LOGISTICS SAOC
Page 92 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS ELECTRICAL WORK BILL NO. 4

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

QUANTITY
BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS

TOTAL
ROOM
SL. NO. DESCRIPTION. UNIT

10.0 CONDUITING FOR DATA / NETWORK.

10.1 DATA DISTRIBUTION BOXES

Supply, Installation, testing and commissioning of suitable of 16gauge M.S box


with terminal modules and covered with 5mm thick Perspex sheet/ MS cover
floor monted type cabinet as required complete acessoress, complete scope of
work. Note : Refer Networking layout & Block diagram, Based on
10.1a
networking layout not identified below but required to make installation
complete for achieving full functional networking system. etc. as per
project requirement & specification ( (Contractor to list the activities and
indicate the item wise price for the same in the respective column).

10.1.1 Cat 6A U/UTP Patch Panel (24 Port copper patch pannels Cat 6A) Nos 1 1 8 1 1 2 14

10.1.2 Cable Manager (cable management) / brush pannels Nos 1 1 8 1 1 2 14

10.1.3 Cat 6A U/UTP, LS0H Patch Cable 1 mtrs Nos 6 6 145 4 4 4 169

10.1.4 Cat 6A U/UTP, LS0H Patch Cable 3 mtrs Nos 6 6 145 4 4 4 169

10.1.5 12 Port, LC Duplex, Fiber Patch Panel Fully loaded - Singlemode Nos 2 2 16 2 2 4 28

10.1.6 Fiber Patch Panel 12 Port Fully loaded - Multimode Nos 1 1 8 1 1 2 14

10.1.7 24 Port, LC Duplex, OS2 Fiber Patch Panel Fully loaded - Multimode Nos 0

24 Port Giga POE Switch (or 16 Port Giga POE Switch can be considered for
10.1.8 Nos 1 1 8 1 1 2 14
some location accordingly)

10.1.9 48 Port Giga POE Switch Nos 4 4

Core Switch 7 slot chassis with 48ports 10/100/1000 POE + (2Nos) & 24Ports
10.1.10 Nos 1 1
SFP , Supervisor engine etc with related complete all accessores.

10.1.11 Multimode SFP Models. Nos 0

10.1.12 Singlemode SFP Models. Nos 0

10.1.13 3mtr. Patch cord LC-LC Fiberoptic cable patch cord - duplex. Nos 2 2 16 2 2 4 28

10.1.14 Fiber Patch cord Single mode - 3mtr. LC-LC Nos 2 2 2 2 2 2 12

42U Floor Mount Cabinet 800x1000mm, front glass door, rear perforated metal
door, with PDU, Fan, Perporated Tray & Cage nusts. etc including all
10.1.15 accessories. ( 12 Port Fiber patch panel with necessary patch cords, data Nos. 2 2
switch, UTP Patch panel, patch cables , fan, pdu, etc). inculding 5KVA UPS with
30min battery backup. (Office building).

M/s Semac and Partners L.L.C. Electrical BOQ M/s. EMDAD LOGISTICS SAOC
Page 93 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS ELECTRICAL WORK BILL NO. 4

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

QUANTITY
BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS

TOTAL
ROOM
SL. NO. DESCRIPTION. UNIT

9U Wall Mount Cabinet 500x550mm, front glass door, rear perforated metal
door, with PDU, Fan, Perporated Tray & Cage nusts. etc including all
10.1.16 accessories. ( 12 Port Fiber patch panel with necessary patch cords, data Nos. 1 1 1 1 2 6
switch, UTP Patch panel, patch cables , fan, pdu, etc).inculding 2KVA UPS with
30min battery backup.(Reception building & Logistic storage).

NOTE: Contractor to verify existing office area 42U Rack space provistion for
proposed connectivity, if required considered new 42U Rack, based on the site
10.1.17 0
condition. The telephone & data related all componets make shoud be subject
to client approval & consultant approved make accordinly plan.

Supply, installation, testing and commissioning of 5KVA UPS -1Phase input &
1phase out put Set with battery bank suitable for 30Min back up including
suitable cable terminal box, Contractor to include the battery cable (DC cable)
battery cabinet earthing, body eathing, double neutral as per teh schematic for
10.2 Incomming and out going cable, and all related civil works like cable trenching, Nos. 1 1
chequered plate (10mm thick) with frame angle. All works shall be carried out
with latest Tanweer Electricityrules and regulation.The Test certificates and
commisioning report shall be submitted to the client after the commissioning.
(Office building & Near network cabinet)

10.3 FIBER OPTIC CABLES

Supply, laying & including termination of network fiber optic cables, armoured,
annealed tinned copper conductor. The method of laying shall be similar to
power cables, network cables shall be run in a separate sleeves/trench at least
300mm away from other power cables. This related civil work for excavation,
filling & cable laying complete scope of work as to be consider. this rate shall
include cable end termination also using kits cable glands, cable lugs, etc as
required complete scope.
6 Core Steel tape Armoured Multimode - OM3 Fiber Optic Cable outdoor type.
a. Mtr 0

6 Core Steel tape Armoured Singlemode - OS2 Fiber Optic Cable outdoor type
b Mtr 0
with including 32mm dia pvc conduit.
12 Core Steel tape Armoured Singlemode - OS2 Fiber Optic Cable outdoor
c Mtr 1250 1250
type.

M/s Semac and Partners L.L.C. Electrical BOQ M/s. EMDAD LOGISTICS SAOC
Page 94 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS ELECTRICAL WORK BILL NO. 4

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

QUANTITY
BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS

TOTAL
ROOM
SL. NO. DESCRIPTION. UNIT

10.4 DATA SOCKET

Supply & installation of concealed type 16G MS modular junction boxes & Data
socket outlet and dual face plate with socket outlet with concealed metal boxes.
The quoted rate shall include all required other necessary accessories complete
etc. as required. The installation shall include cost fo crimping, concealed junctio
box and all other accessories required.

a.) Information outlet -RJ45 type face plate for data. Nos. 3 3 74 2 2 2 86

10.5 MAIN SYSTEM

Supply & installation of EPABX Similar to NEC SV9100 IP based, IP


Communication Server with 50IP Extension Licenses, 30 Channel ISDN PRI
Card, 08 Analog Trunk Ports, 08 Port Analog Extenstion Card, 04 Port Auto
a.) Attendent System, 10IP Trunk Licenses, interconection of Saudi ISP providder Set 1.000 1
line, incoming line with EPABX, necessary termination, crimping, etc, The
quoted rate shall include all required other necessary acessories complete
scope of work etc.

10.6 IP PHONES

a) IP Phones with 06 Buttons & Display. Nos. 3 3 71 2 2 2 83

b) IP Phones with 24 Buttons & Display. Nos. 3 3 74 2 2 2 86

M/s Semac and Partners L.L.C. Electrical BOQ M/s. EMDAD LOGISTICS SAOC
Page 95 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS ELECTRICAL WORK BILL NO. 4

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

QUANTITY
BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS

TOTAL
ROOM
SL. NO. DESCRIPTION. UNIT

10.7 BILL OF MATERIAL - IF SMATV SYSTEM

Supplying, fixing, testing and commissioning of the following items & time
attendance related items suitable for surface/recess mounting as per local
standard specification.

a. 4' Feet Dish Antenna for Nilesat and Arabsat with Quattro LNB Nos 2 2

b Standalone Multiswitch. Nos 1 1

c TV Outlet (conduit from terrace to outlet point) Nos 13 13

d Digital HD Mini Receiver Nos 13 13

e Supply, laying & installation of RG - 6 Video cables & related Accessories. LS 1 1

f Testing, Installation, Commissioning and Training charges LS 1 1

NOTE: The telephone & data related all components make should be
subject to client approval & consultant approval

SUB TOTAL TO SUMMARY.

M/s Semac and Partners L.L.C. Electrical BOQ M/s. EMDAD LOGISTICS SAOC
Page 96 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS ELECTRICAL WORK BILL NO. 4

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

QUANTITY
BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS

TOTAL
ROOM
SL. NO. DESCRIPTION. UNIT

11.0 EARTH PIT FOR STRUCTURAL EARTHING

Supplying all material, Installing, testing and commissioning of earth pit station
as per CP-103 so as to obtain desired values as per Tanweer Electricity
Standard. Copper earth rod each 120cm long extensible threaded type for
coupling together and buried in soil with alternate layer of charcoal &
salt.Construction of earth pits and laying of earth tapes as per Tanweer
11.1 Nos. 8 11 2 1 1 6 1 2 32
Electricity Standards including supply of material. The contractor will be required
to adopt any suitable approved method in order to obtain, the desired earth
values as per Tanweer Electricity requirements. No additional charges will be
paid for this. As per authority standard achiving complete resistance part of
contractor scope. if required contractor to consider chemical resistance.

Supplying, laying and connection to steel colum of earthing copper strip 25 x


3mm or 1C x 70Sqmm Y/G copper cable with necessary clamps at every one
meter and shall be dropped/connect to equipment including legs, connection/
11.2 Mtr 332 346 678
terminations for all the steel coloums.Refer drawing accordingly consider
complete scope from earth test link to equipment connection with
termination.etc.

SUB TOTAL TO SUMMARY.

12.0 LIGHTNING PROTECTION.

Supply, installation, testing commisioning of Advanced ESE Lightning


Protection system.

Advanced Lightning rod; Advanced ESE lightning protection system designed


to offer 108mtr Radius (Rp), tested & certified in complianced with IEC 62561-
2:2012 (Part:2, LPSC Requirements for conductors and earth electrodes) &
12.1 Set 1 1
NFC 17-102:2011 French Standards (Rolling sphere design method, Level IV
protection) & AS 1768:2007 (Risk Assessment and Computation). The ESE
terminals shall be Stainless steel 316 marine grade.

Supply & installation of the mounting support shall be a circular insulating


fibreglass support mast 2mtr (FRP) coupled with Aluminium support mast 3mtr
12.2 LS 1 1
pole (69mm) using a SS Inline coupling. Mast height can be a standard height
of 5mtr.

M/s Semac and Partners L.L.C. Electrical BOQ M/s. EMDAD LOGISTICS SAOC
Page 97 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS ELECTRICAL WORK BILL NO. 4

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

QUANTITY
BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS

TOTAL
ROOM
SL. NO. DESCRIPTION. UNIT

Supply & installation of Lightning Protection down conductor shall be minimum


size of 70mm² PVC insulated copper cable (BS 6004:2012) or shall be
12.3 Mtr. 38 38
equavalent PVC insulated 25x3 copper flat (BS EN 13601:2013) fixed securely
every one meter using SS or high grade copper alloy fasteners.

Supplying and fixing 25 x 3 mm insulated bare copper strip for radial earthing
12.3 Mtr. 25 25
with necessary items. Refer drawing no.M-1114-EL-00-1004 for detail.

Lightning Strike recorder; comprises a mechanical 6 digit display with registers


lightning discharge with a current sensitivity of 1500A 8/20 ήs, it shall be housed
12.4 Set 1 1
in a IP 67 rated and tested in accordance with IEC529 (Degree of protection
provided by enclosures)

Supplying, fixing and commissioning radial Earthing system Shall comprise


25x3 flat copper tape buried to a depth of not more than 800mm & not less than
200mm trench width (radial earthing ) connected with solid copper earth rods
(1.2mtr length &16mm dia) . All components of the earthing system are securely
12.5 LS 1 1
connected to lower end of downconductor (PVC Insulated 70mm² cable or 25x3
copper flat) using lower termination kit . Use of ground resistance improvement
powder shall be applied to reduce the resistivity of the earthing system. Refer
drawing no. M-1114-EL-00-1004 for detail.

Supplying, erecting, testing and commissioning earthing station as per


12.6 BSEN62305/IEC62305, so as to obtain desired values as per Majan Electricity LS 1 1
& OES STANDARD.

NOTE: Complete system warranty shall be 5years to be considered & life


expectancy shall be 25 years under normal operating conditions.

SUB TOTAL TO SUMMARY.

M/s Semac and Partners L.L.C. Electrical BOQ M/s. EMDAD LOGISTICS SAOC
Page 98 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS ELECTRICAL WORK BILL NO. 4

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

QUANTITY
BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS

TOTAL
ROOM
SL. NO. DESCRIPTION. UNIT

13.0 AUTHORITY APPROVALS & SURVEY.

The scope of work shall be 11KV OHL Line tapping from existing 33/11kV
Primary substation outgoing feeder. Tapping from 33/11KV Existing feeders to
proposed plot 11KV OHL Line complete route Survey peg marking, obtaining all
the HV/LV Distribution drawing approval from concerned department & Majan
electricity authority Approvals. The scope of work includes as per below;all the
work shall be as per Tanweer Electricity standard / OES Standard.

All the drawing approvals from Tanweer Electricity & other related all concerned
13.1 authority approvals. (Execution related & testing, commissioning with related all LS 1
concerned authority approvals).

Add Charges for liasoning with Tanweer Preparation of connection agreement


with all necessary documents for obtaining power connection & related
13.2 LS 1
coordination authority. The contractor shall visit the site and get familiarize
themselves with the extent of work involved.

Providing & fixing cable route markers LV Caution tapes, cable tags, cable
13.3 protection pressed concrete tiles as per Tanweer Electricity Specification, etc LS 1
complete scope.

SUB TOTAL TO SUMMARY

M/s Semac and Partners L.L.C. Electrical BOQ M/s. EMDAD LOGISTICS SAOC
Page 99 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS ELECTRICAL WORK BILL NO. 4

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

QUANTITY
BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS

TOTAL
ROOM
SL. NO. DESCRIPTION. UNIT

14.0 LIGHT FIXTURES AND FANS.

Supply, assembling, fixing and testing including all necessary supports for light
fixture supporting rods from rafter or purlin etc as per site condition with
complete fixing accessories of the following light fixtures and fans as per
specifications entitled below & all fixtures should be complete with all
accessories such as Lamps, Drivers, Heat Sink etc. complete scope as per local
authority standard.

Type A. 40/45W LED Surface mounted type down light fitting with control gear.
IP40 rating, Luminaire luminous flux: 5355lm, Luminaire efficacy: 140lm/W.
14.1
Colour rendering min.80, colour temperature 6000K, Body: Aluminium, painted
white & polycarbonate diffuser.

Supply, Nos. 6 6

Installation, Nos. 6 6

Type B. 36 / 40W LED Recess mounted type down light fitting with IP40 rating,
14.2 Luminaire luminous flux: 4000lm, Luminaire efficacy:110lm/W. Colour rendering
min.80, colour temperature 6000K. Body: Aluminium, painted white (RAL 9016),

Supply, Nos. 3 187 5 2 197

Installation, Nos. 3 187 5 2 197

Type C. 12/15Watt LED Bathroom Mirror light fitting slim & aestetic with
electronic fixed output control gear. Luminaire luminous flux: 1300lm, Luminaire
efficacy:100lm/W. colour temperature 4330K,Colour rendering RA>80, degree
14.3
of protection: IP55 rating BATHROOM Luminaire with opal polycarbonate
diffuser.or equivalent LED fitting.colour temperature 4330 K, Body: Aluminium,
painted white & polycarbonate diffuser.

Supply, Nos. 1 4 23 2 2 32

Installation, Nos. 1 4 23 2 2 32

Type D. 18W LED recessed mounted type down light fitting with electronic fixed
output control gear. IP44 rating, Luminaire luminous flux: 1921lm, Luminaire
14.4 efficacy: 106lm/W. Colour rendering min.80, colour temperature 6000K, Body &
reflector: Aluminium powder coated painted white (RAL 9016), Diffuser-
Polycarbonate type,

Supply, Nos. 1 14 31 2 2 50

Installation, Nos. 1 14 31 2 2 50

M/s Semac and Partners L.L.C. Electrical BOQ M/s. EMDAD LOGISTICS SAOC
Page 100 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS ELECTRICAL WORK BILL NO. 4

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

QUANTITY
BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS

TOTAL
ROOM
SL. NO. DESCRIPTION. UNIT

Type E. 36/40W LED Surface mounted type down light fitting with polycarbonate
cover control gear. IP66 rating, Luminaire luminous flux: 4200lm, Luminaire
14.5
efficacy: 117lm/W. Colour rendering min.80, colour temperature 6000K, Body:
Aluminium, painted white & polycarbonate diffuser.

Supply, Nos. 2 6 33 41

Installation, Nos. 2 6 33 41

Type F. 200W LED highbay surface mounted fitting with suspended from ceiling
in the down rods (min 25mm dia) type, die-cast Aluminium housing in matt,
white. Powder-coated cooling ribs for optimum thermal management and
minimal dust accumulation. Cover of transparent Polycarbonate (PC). LED
service life lasts 50000h before luminous flux is reduced to 90% of the initial
value over the entire ambient temperature range. Luminaire luminous flux:
14.6
21000 lm, Luminaire efficacy: 140lm/W. Colour rendering Ra > 80, colour
temperature 6000K. Sealed, high-efficiency optical lens system, Luminaire with
symmetric wide light distribution (wide beam) square, UGR <22. Pendant
installation with 2-point chain suspension, Luminaire with ball-proof protection
Luminaire wired with halogen-free leads. Class of protection: SC1; degree of
protection: IP65 rating.

Supply, Nos. 70 70

Installation, Nos. 70 70

Type G. 100W LED Flood light fitting with electronic control gear, led service life
14.7 50,000H. Luminaire luminous flux: 24072lm, Luminaire efficacy:136lm/W. colour
temperature 6000K,Colour rendering RA>80, Colour temperature 6000K.

Supply, Nos. 26 24 16 8 74

Installation, Nos. 26 24 16 8 74

Type H. 30W LED Flood light fitting with electronic control gear, led service life
14.8 50,000h. Luminaire luminous flux: 10000lm, Luminaire efficacy:100lm/W. colour
temperature 6000K,Colour rendering RA>80, Colour temperature 6000K.

Supply, Nos. 11 1 3 1 2 18

Installation, Nos. 11 1 3 1 2 18

M/s Semac and Partners L.L.C. Electrical BOQ M/s. EMDAD LOGISTICS SAOC
Page 101 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS ELECTRICAL WORK BILL NO. 4

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

QUANTITY
BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS

TOTAL
ROOM
SL. NO. DESCRIPTION. UNIT

Type I. 28W LED ZONE-1 EX-e (EXPLOSION) Surface mounted type down
light fitting with polycarbonate cover control gear. IP66rating, Luminaire
14.9 luminous flux: 1650lm, Luminaire efficacy: 124lm/W. Colour rendering min.80,
colour temperature 6000K, Body: Plastic material polycarbonate grey
colour,cover-transparent plycarbonate, chemical resistence.

Supply, Nos. 20 20

Installation, Nos. 20 20

Type J. 175W LED highbay fitting with suspended from ceiling in the down rods
(min 25mm dia) type, die-cast Aluminium housing in matt, white. Powder-coated
cooling ribs for optimum thermal management and minimal dust accumulation.
Cover of transparent Polycarbonate (PC). . LED service life lasts 50000 h
before luminous flux is reduced to 90% of the initial value over the entire
14.10 ambient temperature range.Luminaire luminous flux: 21000 lm, Luminaire
efficacy: 140 lm/W.Colour rendering Ra > 80, colour temperature 6000 K.
Sealed, high-efficiency optical lens system, Luminaire with symmetric wide light
distribution (wide beam) square, UGR <22. Pendant installation with 2-point
chain suspension, Luminaire with ball-proof protection Luminaire wired with
halogen-free leads. Class of protection: SC1; degree of protection: IP65 rating.

Supply, Nos. 97 97

Installation, Nos. 97 97

Type K. 106Watt LED Street light fittings with high efficiency LED's & type III
roadway optics, LED control gear. Class II electrical, IP66, IK09. Body: die-cast
Aluminium, textured dark grey.Cover: tempered flat clear glass, fitting should be
14.11 suitable for 10mtr hight pole. LED service life lasts 50000 h before luminous flux
is reduced to 90% of the initial value over the entire ambient temperature range.
Luminaire luminous flux:14196lm, Luminaire efficacy: 141lm/W. Colour
rendering Ra > 80, colour temperature 6000K.

Supply, Nos. 25 25

Installation, Nos. 25 25

M/s Semac and Partners L.L.C. Electrical BOQ M/s. EMDAD LOGISTICS SAOC
Page 102 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS ELECTRICAL WORK BILL NO. 4

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

QUANTITY
BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS

TOTAL
ROOM
SL. NO. DESCRIPTION. UNIT

Supply and installation of Single arm 10Mtr. Height galvanised steel pole with
steel bracket for flood light fitting.Contractor to including eathpit and related civil
14.12
foundation work, steel plate for installing the 10Mtr. Height steel pole.etc
complete scope as per local authority standard.

Supply, Nos. 11 11

Installation, Nos. 11 11

Supply and installation of double arm 10Mtr. Height galvanised steel pole with
steel bracket for flood light fitting.Contractor to including eathpit and related civil
14.13
foundation work, steel plate for installing the 10Mtr. Height steel pole.etc
complete scope as per local authority standard.

Supply, Nos. 7 7

Installation, Nos. 7 7

Type L. 26watt LED Gate light fitting & aestetic with electronic fixed output
control gear., degree of protection: IP66 rating. Body: die-cast Aluminium
14.14
construction, textured dark grey. Colour rendering Ra > 80, colour temperature
6000K. IP65 rating,

Supply, Nos. 6 6

Installation, Nos. 6 6

Type M. 28W LED recessed mounted type down light fitting with electronic fixed
output control gear. IP44 rating, Luminaire luminous flux: 2608lm, Luminaire
14.15 efficacy: 106lm/W. Colour rendering min.80, colour temperature: 6000K, Body &
reflector: Aluminium powder coated painted white (RAL 9016), Diffuser-
Polycarbonate type,

Supply, Nos. URO

Installation, Nos. URO

Type N. 15W LED recessed mounted type down light fitting with electronic fixed
output control gear. IP44 rating, Luminaire luminous flux: 1725lm, Luminaire
14.16 efficacy: 115lm/W. Colour rendering min.80, colour temperature: 6000K, Body &
reflector: Aluminium powder coated painted white (RAL 9016), Diffuser-
Polycarbonate type,

Supply, Nos. 54 54

Installation, Nos. 54 54

M/s Semac and Partners L.L.C. Electrical BOQ M/s. EMDAD LOGISTICS SAOC
Page 103 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS ELECTRICAL WORK BILL NO. 4

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

QUANTITY
BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS

TOTAL
ROOM
SL. NO. DESCRIPTION. UNIT

Type O. 36/40W LED Surface mounted type down light fitting with electronic
fixed output control gear & polycarbonate cover. IP66rating, Luminaire
14.17 luminous flux: 4200m, Luminaire efficacy: 117m/W. Colour rendering min.80,
colour temperature 6000K, Body: Plastic material polycarbonate grey
colour,cover-transparent plycarbonate.

Supply, Nos. 8 8

Installation, Nos. 8 8

Type P. 70W LED low-bay surface mounted fitting with suspended from ceiling
in the down rods (min 25mm dia) type, die-cast Aluminium housing in matt,
white. Powder-coated cooling ribs for optimum thermal management and
minimal dust accumulation. Cover of transparent Polycarbonate (PC). LED
service life lasts 50000 h before luminous flux is reduced to 90% of the initial
value over the entire ambient temperature range. Luminaire luminous flux: 7500
14.18
lm, Luminaire efficacy: 134 lm/W.Colour rendering Ra > 70, colour temperature
6000 K. Sealed, high-efficiency optical lens system, Luminaire with symmetric
wide light distribution (wide beam) square, UGR <22. Pendant installation with
2-point chain suspension, Luminaire with ball-proof protection Luminaire wired
with halogen-free leads. Class of protection: SC1; degree of protection: IP65
rating.

Supply, Nos. 9 9

Installation, Nos. 9 9

Type R. 26Watt LED Helipad flood light fitting,degree of protection: IP66 rating.
Body: die-cast Aluminium construction, textured dark grey. delivered lumens
14.19
2068 lm. Colour rendering Ra > 70, colour temperature 4000-6000K. With
150mm height with supporting pedastal.

Supply, Nos. 16 16

Installation, Nos. 16 16

Type S. 5Watt LED Inset Utility white Omni-Directional LED 8" DIA, 100-
14.20 250VAC, 50Hz. Helipad area light fitting,degree of protection: IP66 rating. With
150mm height with supporting pedastal.

Supply, Nos. 24 24

Installation, Nos. 24 24

M/s Semac and Partners L.L.C. Electrical BOQ M/s. EMDAD LOGISTICS SAOC
Page 104 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS ELECTRICAL WORK BILL NO. 4

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

QUANTITY
BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS

TOTAL
ROOM
SL. NO. DESCRIPTION. UNIT

Type T. 15Watt Touchdown LED Light (TLDF) with heavy duty glass Green
14.21 Omni-Directional LED 8" DIA, 85-265VAC, 50Hz. Helipad area light
fitting,degree of protection: IP67 rating weather proof & water proof type.

Supply, Nos. 28 28

Installation, Nos. 28 28

Type U. Wind cone type L806 internally ligted 120/240VAC 3mtr, Height, Wind
Sock Size 1, 18" diamete, 8' Long Orange, Frangible Coupling Lamp. 120V
14.22
Incandesecent Obstruction Light with including complete scope as per local
authority standard.

Supply, Nos. 1 1

Installation, Nos. 1 1
14.23 Supply and installation 1200mm dia ceiling fan with regulatour.

Supply, Nos. 2.00 2

Installation, Nos. 2.00 2

14.24 Supply and installation Door bell / Calling bell.

Supply, Nos. 0

Installation, Nos. 0
14.25
6W LED type Surface mounted ceiling Emergency light fittings with 3hours
battery backup Or as per local civil defense standard / civil defense approved
make required accordingly consider complete scope.

Supply, Nos. 30 24 115 4 3 3 1 2 182

Installation, Nos. 30 24 115 4 3 3 1 2 182

M/s Semac and Partners L.L.C. Electrical BOQ M/s. EMDAD LOGISTICS SAOC
Page 105 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS ELECTRICAL WORK BILL NO. 4

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

QUANTITY
BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS

TOTAL
ROOM
SL. NO. DESCRIPTION. UNIT

6W LED type Surface mounted ceiling Emergency light fittings with 3hours
battery backup with suitable for -20degree for freezer area suitable weather
14.26 proof & water proof type IP67 accordingly consider complete scope. & as per
local civil defense standard / civil defense approved make required accordingly
consider complete scope.

Supply, Nos. 0

Installation, Nos. 0

6W LED type Surface mounted ceiling Emergency light fittings with 3hours
battery backup with weather proof & water proof type IP65 accordingly consider
14.27
complete scope. & as per local civil defense standard / civil defense approved
make required accordingly consider complete scope.

Supply, Nos. 0

Installation, Nos. 0

6W LED decorative Wall mounted / Ceiling Mounted (Hanging type) Fire Exit
Signages in Arabic and English.light fitting shall be Maintained type with 3hour
14.28
battery backup & as per local civil defense standard / civil defense approved
make required accordingly consider complete scope.

Supply, Nos. 0

Installation, Nos. 0
14.29 6W LED decorative Wall mounted / Ceiling Mounted (Hanging type) Fire Exit
Signages in Arabic and English.light fitting shall be Maintained type with 3hour
battery backup Or as per local civil defense standard with weather proof & water
proof type IP65 accordingly consider complete scope & as per local civil
defense standard / civil defense approved make required accordingly consider
complete scope.

Supply, Nos. 0

Installation, Nos. 0

M/s Semac and Partners L.L.C. Electrical BOQ M/s. EMDAD LOGISTICS SAOC
Page 106 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS ELECTRICAL WORK BILL NO. 4

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

QUANTITY
BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS

TOTAL
ROOM
SL. NO. DESCRIPTION. UNIT

2 x 9W LED type Column/wall mounted industrial type Emergency light


14.30 fittings with 1.5hours battery backup as per local civil defense standard. degree
of protection: IP20 rating.

Supply, Nos. 0

Installation, Nos. 0
14.31
2 x 9W LED type Column/wall mounted industrial type Emergency light
fittings with 3hours battery backup as per local civil defense standard. degree
of protection: IP65 rating.

Supply, Nos. 0

Installation, Nos. 0

SUB TOTAL TO SUMMARY

15.0 MISCELLANEOUS

Supply and lay PVC sleeves and ducts including excavation and trenching as
per locations for laying of cables underground at road crossings or in trenches
15.1
as per Tanweer Electricityregulations. Refer all site plans & floor plan dwg.
Accordingly consider complete scope.

i) 50 mm dia Mtr. 21 21

ii) 80 mm dia Mtr. 0

iii) 110 mm dia Mtr. 152 152

iv) 150 mm dia. Mtr. 0

v) 200 mm dia. Mtr. 0

NOTE: Care shall be taken to maintain required clearance with other general
equipment, earthing pit, conductor as per SECElectricity Standard SEC- 04 VOL
I

15.2 TAGGING & LABELING

Appropriate tagging and ferruling shall be made to each main cable and the
small wiring circuit to discriminate between them for easy identification during LS 1
trouble shooting

M/s Semac and Partners L.L.C. Electrical BOQ M/s. EMDAD LOGISTICS SAOC
Page 107 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS ELECTRICAL WORK BILL NO. 4

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

QUANTITY
BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS

TOTAL
ROOM
SL. NO. DESCRIPTION. UNIT

15.3 CABLE TRAYS AND SUPPORTS

Supply and fixing of GI cable trays, MS cable trays with cover, All GI cable
trays & trunking with supports shall be Hot dip galanizing after fabrication
(HDGAF) as per accordance with BSEN 1461 & as per drawing, Cable tray/GI
trunking, GI / SS pipes of suitable size required for laying of cables as per site.
Cable trays/trunking shall be fixed by welding/nacessary supports steel brackets
& All fixing accessories and as per drawing etc. complete in all respect and
considering wall cutting/opening & chasing and refiling, finishing with
sealent..etc complete scope as per local authority drawing with including
tray/trunking earthing.

900mm wide GI Cable tray with Cover with related supports & fixing accessories
a) Mtr. 0
and (as per drawing ),
750mm wide GI Cable tray with Cover with related supports & fixing accessories
b) Mtr. 55 55
and (as per drawing ),
500mm wide GI Cable tray with Cover with related supports & fixing accessories
c) Mtr. 0
and (as per drawing ),
450mm wide GI Cable tray with Cover with related supports & fixing accessories
d) Mtr. 0
and (as per drawing ),
300mm wide GI Cable tray with Cover with related supports & fixing accessories
e) Mtr. 124 124
and (as per drawing ),
200mm wide GI Cable tray with Cover with related supports & fixing accessories
f) Mtr. 0
and (as per drawing ),
150mm wide GI Cable tray with Cover with related supports & fixing accessories
g) Mtr. 0
and (as per drawing ),
100mm wide GI Cable tray with Cover with related supports & fixing accessories
h) Mtr. 35 25 60
and (as per drawing ),

i) 50x50mm wide- Trunking with related MS supports and (as per drawing ), Mtr. 0

j) 100x50mm wide- Trunking with related MS supports and (as per drawing ), Mtr. 0

100x100mm wide- Trunking with related MS supports and (as per drawing ),
k) Mtr. 0
inside the server room

M/s Semac and Partners L.L.C. Electrical BOQ M/s. EMDAD LOGISTICS SAOC
Page 108 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS ELECTRICAL WORK BILL NO. 4

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

QUANTITY
BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS

TOTAL
ROOM
SL. NO. DESCRIPTION. UNIT

Supply & installation of Stainless Steel pipe with inculding all accessories high
quality Stainless steel AISI 316L/EN 1.4404 with mirror finish including pipe
hangers support, sealing ring, pipe joint clamp, saddle clamp, cross raking fixing
for pipe joint, insert type rubber & connection fittings. etc complete accessories /
complete scope. Coordination with Main contractor making suitable dia holes in
15.4
the puff panel & fixing air tight sealent in the cut out pipe location. Pipe supports
shall be fixed by welding/nacessary supports steel brackets & All fixing
accessories and as per drawing etc. complete in all respect and considering wall
cutting/opening & chasing and refiling, finishing with sealent..etc with including
related complete civil builder works. Refer drawing M1083-EL-21-1030.

a) SS Pipe 50mm dia Mtr. URO

b) SS Pipe 40mm dia Mtr. URO

c) SS Pipe 25mm dia Mtr. URO

Following Safety equipment shall be provided in the LV room, as per Tanweer


Electricity Requirement & Appropriate tagging and ferruling shall be made to
15.5
each main cable and the small wiring circuit to discriminate between them for
easy identification during trouble shooting

Supply & installation of First Aid box, Saftey chart, shock resuscitation charts,
a) shock treatment charts (English language as welll as Arabic language) etc. as LS 1
per local authority standard.

Supply & installation of 6mm Rubber Mat - 12Mtr (L) x 1.2mtr (W) infront of
b) LS 1
MLVP, AMF & APFC Panel.( Electrical room)

Supply & installation of 6mm Rubber Mat - 2.5Mtr (L) x 1mtr (W) infront of all the
c) LS 1
MDB Panels.

SUB TOTAL TO SUMMARY

M/s Semac and Partners L.L.C. Electrical BOQ M/s. EMDAD LOGISTICS SAOC
Page 109 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS ELECTRICAL WORK BILL NO. 4

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

QUANTITY
BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS

TOTAL
ROOM
SL. NO. DESCRIPTION. UNIT

16.0 ITEMS

Miscellaneous works, not identified above but required to make installation


complete for achieving fully functional system as per project specifications
16.1 Lot 0
(Contractor to list the activities and indicate the item wise price for the same in
the respective column).

If in the opinion of the contractor there are some items not mentioned in the
16.2 BOI, the contractor must show them below and carry their sum to the summary LS 1
items not mentioned in the bill of quantities but specified in drawing.

SUB TOTAL TO SUMMARY

M/s Semac and Partners L.L.C. Electrical BOQ M/s. EMDAD LOGISTICS SAOC
Page 110 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS ELECTRICAL WORK BILL NO. 4

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

QUANTITY
BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS

TOTAL
ROOM
SL. NO. DESCRIPTION. UNIT

TOTAL COLLECTION BILL NO. 4

1.0 11KV MV CABLES WORKS:

2.0 DISTRIBUTION TRANSFORMER & RMU

3.0 LV PANELS

4.0 LV CABLES

5.0 DISTRIBUTION BOARDS

6.0 LIGHTING POINT WIRING.

7.0 POWER WIRING

8.0 SOCKET OUTLETS.

9.0 TELEPHONE CONDUITING & WIRING

10.0 CONDUITING FOR DATA / NETWORK.

11.0 EARTH PIT FOR STRUCTURAL EARTHING

12.0 LIGHTNING PROTECTION.

13.0 AUTHORITY APPROVALS & SURVEY.

14.0 LIGHT FIXTURES AND FANS.

15.0 MISCELLANEOUS

16.0 ITEMS

CCTV System, BGM System, Time Attendance System (Provisional Sum


Amount R.O. 35,000.000 as per meeting with consultant & client)

SUB TOTAL TO GENERAL SUMMARY

NOTE;
1 This is a lump sum tender
Items & quantities provided in this tender are purely indicative. Contractors to verify the
2
drawings and quote accordingly.

Schedule of items in conjunction with drawings and specifications constitute complete tender. The renderers are responsible for all the quantities they consider necessary for the proper submission
of the tender in accordance with the conditions of contract, drawings and specification. In case the contractor/Tenderer notice any item missing in the BOQ he should include the same in this quoted
3
value and submit with the tender, a list of such items along with relevant specifications and quantities. No claims shall be entertained at a later stage for items not listed in the schedule but
mentioned in the drawings.

4 GRAND TOTAL is to include for items not included here but required to complete all works.

M/s Semac and Partners L.L.C. Electrical BOQ M/s. EMDAD LOGISTICS SAOC
ADDITIONAL ITEMS Page 111 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS ELECTRICAL WORK BILL NO. 4

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

QUANTITY
BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS

TOTAL
ROOM
SL. NO. DESCRIPTION. UNIT UNIT RATE TOTAL AMOUNT.

16.0 ITEMS

If in the opinion of the contractor there are some items not mentioned in the
16.2 BOI, the contractor must show them below and carry their sum to the summary LS 1
items not mentioned in the bill of quantities but specified in drawing.

A 50000 Liter Bulk Fuel Tank with Piping No 1 1 35,785.000 35,785.000

B PDB-O&A-01 No 1 1 816.700 816.700

C PDB-O&A-02 No 1 1 816.700 816.700

D ACDB-O&A-01 No 1 1 293.500 293.500

E ACDB-O&A-02 No 1 1 293.500 293.500

F Luminaries - Cable & Conduit No 131 165 454 32 13 12 9 12 39 867 27.100 23,495.700

G External Street Light Poles- Cable & Conduit No 18 18 270.600 4,870.800

H Helipad Lights - Cable & Conduit No 69 69 104.300 7,196.700

J 1 Way Switch points - Cable & Conduit No 12 15 42 1 3 2 1 5 81 25.800 2,089.800

K 2 Way Switch points - Cable & Conduit No 54 1 55 30.300 1,666.500

L 1 Gang 1 Way Switch - White Plastic No 13 2 1 16 5.400 86.400

M 2 Gang 1 Way Switch - White Plastic No 10 10 7.000 70.000

N 3 Gang 1 Way Switch - White Plastic No 6 6 10.600 63.600

P 4 Gang 1 Way Switch - White Plastic No 13 1 14 12.800 179.200

Q 1 Gang 2 Way Switch - White Plastic No 14 1 15 6.000 90.000

R 2 Gang 2 Way Switch - White Plastic No 34 34 8.100 275.400

S 3 Gang 2 Way Switch - White Plastic No 6 6 12.600 75.600

T 1 Gang 1 Way Switch - Weatherproof No 2 2 10.800 21.600

U 2 Gang 1 Way Switch - Weatherproof No 2 2 15.100 30.200

M/s Semac and Partners L.L.C. Electrical BOQ M/s. EMDAD LOGISTICS SAOC
ADDITIONAL ITEMS Page 112 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS ELECTRICAL WORK BILL NO. 4

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

QUANTITY
BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS

TOTAL
ROOM
SL. NO. DESCRIPTION. UNIT UNIT RATE TOTAL AMOUNT.

V 3 Gang 1 Way Switch - Weatherproof No 1 1 23.600 23.600

W Switch - 20A Grid type Phase Barrier Switch board Weatherproof type No 10 10 1 21 44.000 924.000

X 1 Gang 1 Way Switch - Metal Clad No 1 1 2 6.400 12.800

Y 2 Gang 1 Way Switch - Metal Clad No 2 1 3 8.100 24.300

Z 3 Gang 1 Way Switch - Metal Clad No 1 1 2 12.600 25.200

A1 4 Gang 1 Way Switch - Metal Clad No 1 1 2 21.400 42.800

A2 13A, Twin SSO Metal Clad - Cable & Conduit No 3 2 2 7 27.800 194.600

A3 20A DP switch Metal Clad - Cable & Conduit No 2 3 2 7 39.400 275.800

A4 One 20A flex outlet Metal Clad - Cable & Conduit No 2 3 2 7 39.400 275.800

A5 Switch with flex outlet Metal Clad - Cable & Conduit No 1 3 4 39.400 157.600

A6 13A, Twin switched socket outlet - Metal Clad No 3 2 2 7 18.600 130.200

20A DP switch for A/C, water heater,industrial fan and hand dryer - Metal
A7 No 2 3 2 7 10.200 71.400
Clad

A8 One 20A flex outlet for A/C, water heater and hand dryer. - Metal Clad No 2 3 2 7 7.600 53.200

A9 exhaust fan related switch with flex outlet- 1phase - Metal Clad No 1 3 4 16.800 67.200

SUB TOTAL CARRIED TO BILL NO.4, SL.NO.16.2 80,495.400

M/s Semac and Partners L.L.C. Electrical BOQ M/s. EMDAD LOGISTICS SAOC
Page 113 of 172
DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS PLUMBING WORK BILL NO.-5

HAZARDOUS

PUMP ROOM
HOUSE & AC

RECEPTION
TECHNICAL

T.X YARD &

EXTERNAL
BUILDING
CUM HELI

BUILDING
LOGISTIC

FACILITY

LV ROOM
HANGER

SENTRY
OFFICE
STORE

STORE

POSTS
PLANT
SL.
DESCRIPTION. UNIT QTY
NO.

1.0 SANITARY FIXTURES

Supply, installation & commissioning of EUROPEAN WC with


concealed flush valve , soft closing seat and over outlet connector and
push plate wall mounted type with including installation related complete
all necessary accessories, angle valve, hand spray (health faucet) with
1.1 Nos. 1 2 18 0 2 0 0 2 0 25
flexible tube "P" traps, valves (Isolation valves) and all valves
necessary brakets, taps, Outlet plugs, fixing bolts & connecting to
sewer/waste/water supply pipe work etc. complete scope as per local
standard. Ref. Architectural drawing for detail.

Supply, installation & commissioning of vitreous china white colour of


approved make and size ASIAN W.C.or EASTERN W.C. with
concealed flush valve, angle valve, hand spray (health faucet) with
1.2 Set 0 0 0 0 0 0 0 0 0 0
flexible tube "P" traps, etc. supporting bracket 32 mm dia CP flush bend
with 15 mm dia CP connecting pipe with 15 mm dia stop cocks
complete with all accessories. Ref. Architectural drawing for detail.

Supply, installation & commissioning of Handcap Toilet complete set


(DISABLED TOILET SET WITH FLUSH VALVE TYPE) including angle
valve, health faucet with flexible tube "P" traps, all accessories,
consisting of raised height close coupled EWC pan 75cm
projection,Cistern 4.5ltr siphon bottom supply, and CP reversible lever
type handle, plastic seat with top fixing hinges,37cm hand rinse basin
with central tap hole and concealed wall hangers, thermostatic
1.3 Set 0 0 1 0 0 0 0 0 0 1
sequential basin mixer with CP long lever, plastic strainer waste and
bottle trap, 60cm straight grab bars white color 4nos, 45cm hinged
support rail white color, and semi recessed toilet paper holder. & other
complete accessories as architectural drawing. & other civil work
flushing cistern, valve, supporting bracket 32mm dia CP flush bend with
15mm dia CP connecting pipe with 15mm dia stop cocks complete with
all other supporting accessories

Supply, installation & commissioning of URINAL BASIN with flushing


cistern for individual urinals, to ensure flushing only when in use,
comprising of all plumbing, electronic & electrical items including
infrared photo cells eyes, electronically operated solenoid valve, step
1.4 down equipment, concealed copper piping, MS or CI brackets, Nos. 0 2 0 0 0 0 0 0 0 2
standard size CP flush pipe and spreaders with necessary clamp and
fittings etc. and any other item required to provide satisfactory
functioning as approved by the Architects. with fittings, complete as per
approved make and specifications. Ref. Architectural drawing for detail.

Semac and Partners L.L.C Plumbing Works M/s. EMDAD LOGISTICS SAOC
Page 114 of 172
DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS PLUMBING WORK BILL NO.-5

HAZARDOUS

PUMP ROOM
HOUSE & AC

RECEPTION
TECHNICAL

T.X YARD &

EXTERNAL
BUILDING
CUM HELI

BUILDING
LOGISTIC

FACILITY

LV ROOM
HANGER

SENTRY
OFFICE
STORE

STORE

POSTS
PLANT
SL.
DESCRIPTION. UNIT QTY
NO.

Supply, installation & commissioning of vitreous china urinal partition


1.5 with expandable anchor fasteners with C.P. brass bolts and washers Nos. 0 1 0 0 0 0 0 0 0 1
complete, including cutting and making good the walls where required.

Supply, installation & commissioning of Vitreous China wash basin of


approved make and size with MS or CI brackets, CP brass chain with
1.6 rubber plug, 32 mm CP heavy quality bottle trap, Angle valve, CP brass
connection pipe, necessary fittings, rubber adopter for waste connection
complete, including cutting and making good the walls where required.

Counter sunk Oval type with C.P. brass pillar cock (Cold and hot) and
a) Nos. 0 2 12 0 0 0 0 0 0 14
wash basin mixer.
Wall mounted semi pedestall mounted Oval type with C.P. brass pillar
b) Nos. 1 2 9 0 2 0 0 2 0 16
cock (Cold and hot) and wash basin mixer.

Supply, installation & commissioning of Rectangular type acid resistant


sink (Laboratory sink) SS type with C.P. brass pillar cock (Cold and hot
c) Set 0 0 0 0 0 0 0 0 0 0
only) and wash basin mixer. Including bottale trap, angle valve with all
necessary accessories etc complete accessories.

Supply, installation & commissioning of stainless steel sink with draining


board with M.S. or C.I. Brackets, 40mm dia C.P. waste with chain and
1.7 plug, 40mm dia C.P. 'P' trap with cleaning eye including bottale trap,
angle valve with all necessary accessories, etc painting of brackets
cutting and making good the walls and floors complete

a) Single bowl, single drain board 510x1040x178mm depth at bowl Nos. 0 0 0 0 0 0 0 0 0 0

b) Double bowl, single drain board 510x1040x178mm depth at bowl Nos. 0 0 0 0 0 0 0 0 0 0

Single bowl, single drain board 510x1200x178mm depth at bowl


c) Nos. 0 0 6 0 0 0 0 0 0 6
complete as per drawings

Three bowl, three drain board 510x1810x178mm depth at bowl


d) Nos. 0 0 0 0 0 0 0 0 0 0
complete as per drawings

Two bowl, two drain board 510x1200x178mm depth at bowl complete


e) Nos. 0 0 0 0 0 0 0 0 0 0
as per drawings

Semac and Partners L.L.C Plumbing Works M/s. EMDAD LOGISTICS SAOC
Page 115 of 172
DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS PLUMBING WORK BILL NO.-5

HAZARDOUS

PUMP ROOM
HOUSE & AC

RECEPTION
TECHNICAL

T.X YARD &

EXTERNAL
BUILDING
CUM HELI

BUILDING
LOGISTIC

FACILITY

LV ROOM
HANGER

SENTRY
OFFICE
STORE

STORE

POSTS
PLANT
SL.
DESCRIPTION. UNIT QTY
NO.

Supply, installation & commissioning of SS type kitchen mixer for sinks


1.10 with all necessary fittings as per architect approval. long arm kitchen Nos. 0 0 6 0 0 0 0 0 0 6
mixer,

Semac and Partners L.L.C Plumbing Works M/s. EMDAD LOGISTICS SAOC
Page 116 of 172
DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS PLUMBING WORK BILL NO.-5

HAZARDOUS

PUMP ROOM
HOUSE & AC

RECEPTION
TECHNICAL

T.X YARD &

EXTERNAL
BUILDING
CUM HELI

BUILDING
LOGISTIC

FACILITY

LV ROOM
HANGER

SENTRY
OFFICE
STORE

STORE

POSTS
PLANT
SL.
DESCRIPTION. UNIT QTY
NO.

Supply, installation & commissioning of Chromium plated wall mounted


1.11 hot and cold mixer for hand wash with all necessary fittings as per Nos. 0 0 0 0 0 0 0 0 0 0
architect approval. (ablution area)

Supply, installation & commissioning of Shower tray (900x900mm) with


1.12 Nos. 0 1 4 0 0 0 0 0 0 5
bottletrap as per Architectural detail drawing & architect approval.

Supply, installation & commissioning of CP hot & cold mixer with


1.13 adjustable long arm wall mounted shower assembly as per architect Nos. 0 1 4 0 0 0 0 0 0 5
approval.

Supply, installation & commissioning of 20mm Bib tap CP brass with


1.14 Nos. 0 0 2 0 0 0 0 0 0 2
accessories

Supply, installation & commissioning of First quality 1/2" thick glass


mirror electrolytically copper plated and back protected by 1/8" thick
water proof shock absorbing polythene padding filter strips with
1.15
stainless steel angle frame of size 3/4"x3/4" satin finished and stiffened
complete including fixing on wall face with concealed hangers and theft
resistant locking screws.

a. 2000x800mm Size of the mirror shall be as per drawing. Nos. 0 1 6 0 0 0 0 0 7


b. 650x800mm Size of the mirror shall be as per drawing. Nos. 1 2 9 0 2 0 0 2 16
c. 1400x800mm Size of the mirror shall be as per drawing. Nos. 0 0 0 0 0 0 0 0 0
1.16 Providing and fixing SS toilet paper holder Nos. 1 2 19 0 2 0 0 2 26
1.17 Providing and fixing chromium plated soap tray. Nos. 0 1 0 0 0 0 0 0 1

Supply, installation & commissioning of Liquid soap dispensers for


1.18 Nos. 1 4 21 0 2 0 0 2 30
lavatory basin with fluid capacity 0.5 lit. installed on washbasin .

Supply, installation & commissioning of Stainless steel twin coat hooks.


1.19 Nos. 1 2 18 0 2 0 0 2 25
(twin robe hooks)

1.20 Supply, installation & commissioning of 300mm long VC towel rail. Nos. 0 1 0 0 0 0 0 0 1

Semac and Partners L.L.C Plumbing Works M/s. EMDAD LOGISTICS SAOC
Page 117 of 172
DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS PLUMBING WORK BILL NO.-5

HAZARDOUS

PUMP ROOM
HOUSE & AC

RECEPTION
TECHNICAL

T.X YARD &

EXTERNAL
BUILDING
CUM HELI

BUILDING
LOGISTIC

FACILITY

LV ROOM
HANGER

SENTRY
OFFICE
STORE

STORE

POSTS
PLANT
SL.
DESCRIPTION. UNIT QTY
NO.

1.21 Hot Water Heaters

Supply, Installation, testing and commissioning of horizontal or vertical


type copper water heaters of approved make and size with automatic
thermal control unit, connecting pipes, stop cocks , heating element, ,
neon indicator lamp, pressure relief valve etc complete scope of work.

a) 120 Ltrs. Nos. 0 0 0 0 0 0 0 0 0


b) 80 Ltrs. Nos. 0 1 0 0 0 0 0 0 1
c) 50 Liters Nos. 0 0 0 0 0 0 0 0 0
d) 30 Liters Nos. 1 0 21 0 1 0 0 2 25
Supply, installation & commissioning of Electrically operated Hand
1.21 Nos. 0 0 0 0 0 0 0 0 0
dryer 1phase, 220V/50Hz.
NOTE :- 1. All flexible hose connections shall be suitable to
withstand a minimum pressure of 3 bars.
2. Refer Architechtural drawing for the detail specification of all
Sanitary fixtures.
SUB TOTAL TO SUMMARY.

2.0 INTERNAL, EXTERNAL DRAINAGE AND SANITARY INSTALLATION

Supply, installation & commissioning of Providing and fixing UPVC pipe


for Soil, waste underground drainage system including all fittings e.g.
plain or door bends, reducers and couplings, with push fit rubber ring
joints where essentially required, excavation and back filling in soft and
2.1 hard rock laying red colored HEPTAPE warning at 200 mm below
ground, 150mm thick SRC concrete (C30 grade) bed surround @
2.0mts C/c for pipes, 100 mm thk sand bedding all round, exreened
backfilling, and testing, external route marker, etc complete work as per
local standard & drawings.

EXTERNAL:
a) 200mm dia OD Mtr 0 0 0 0 0 0 0 0 0 0
b) 160mm dia OD Mtr 0 0 0 0 0 0 0 0 615 615
c) 110mm dia OD Mtr 0 0 0 0 0 0 0 0 0 0

Semac and Partners L.L.C Plumbing Works M/s. EMDAD LOGISTICS SAOC
Page 118 of 172
DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS PLUMBING WORK BILL NO.-5

HAZARDOUS

PUMP ROOM
HOUSE & AC

RECEPTION
TECHNICAL

T.X YARD &

EXTERNAL
BUILDING
CUM HELI

BUILDING
LOGISTIC

FACILITY

LV ROOM
HANGER

SENTRY
OFFICE
STORE

STORE

POSTS
PLANT
SL.
DESCRIPTION. UNIT QTY
NO.

INTERNAL:
e) 200mm dia OD Mtr 0 0 0 0 0 0 0 0 0 0
f) 160mm dia OD Mtr 0 0 0 0 0 0 0 0 0 0
g) 110mm dia OD Mtr 9 25 155 0 20 0 0 20 0 229
h) 75mm dia OD Mtr 4 83 187 0 21 0 0 14 0 309
i) 50mm dia OD Mtr 7 34 136 0 14 0 0 16 0 207

Supply, installation & commissioning of UPVC full bore self cleansing


"P" traps complete including cutting and making good the walls and
2.2 Nos. 1 6 37 0 2 0 0 2 0 48
floors etc. 4" inlet x 4" outlet nominal dia with extension piece with
bossed inlet connections and setting in cement concrete.

Supply, installation & commissioning of UPVC multi inlet/without inlet


floor trap with nickle cadmium round garting complete including cutting
2.3 and making good the walls and floors, setting in cement concrete with
based inlets connections. Cover shall be SS-316 Type or subject to
client approval.
a) 4" x 4" nominal diameter Nos. 1 6 37 0 2 0 0 2 0 48
b) 300x300mm Floor drainage SS Grating Nos. 0 0 0 0 0 0 0 0 0 0

Supply, installation & commissioning of 4" nominal dia UPVC rodding


eye terminal with moulded bosses for inlets with match brass sockets
2.4 and screwed brass cleanout plug flush with floor with inlet keys. Inlet Each 0 2 8 0 1 0 0 0 0 11
as per manufacturer's design outlet 4" nominal dia. Cover shall be SS-
316 Type or subject to client approval.

Supply, installation & commissioning of UPVC gully inlet with trap


2.5 complete with cast iron grating brick masonry chamber size 450 x 450 Each 1 1 8 0 1 0 0 2 0 13
and water tight cast iron cover with frame of 450 x 450 mm size (inside).

2.6 100x100 mm size P type Each 1 1 8 0 1 0 0 2 0 13


Supply, installation & commissioning of Rain Water Pipe / Spout. (Other
2.7 than as Provided under Steel Works) - 150x150mm catch basin. Refer Nos. 1 1 3 0 4 0 1 0 0 10
roof plan architectural drawing
Supply, installation & commissioning of Rain water pipe including all
2.8 supports inlet arrangement square nickle bronze grating and jointed to 0
drain.
i) 110mm dia pipe with outlet & gratting Mtr 5 5 40 0 20 0 5 0 0 75

Semac and Partners L.L.C Plumbing Works M/s. EMDAD LOGISTICS SAOC
Page 119 of 172
DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS PLUMBING WORK BILL NO.-5

HAZARDOUS

PUMP ROOM
HOUSE & AC

RECEPTION
TECHNICAL

T.X YARD &

EXTERNAL
BUILDING
CUM HELI

BUILDING
LOGISTIC

FACILITY

LV ROOM
HANGER

SENTRY
OFFICE
STORE

STORE

POSTS
PLANT
SL.
DESCRIPTION. UNIT QTY
NO.

Supply, installation & commissioning of uPVC vent pipes with


2.9 0
accessories connected to manholes and drainage lines.
i) 75mm dia OD. Mtr. 0 8 60 0 8 0 0 8 0 84
ii) 110mm dia OD Mtr 0 0 0 0 0 0 0 0 0 0

Supply, installation & commissioning of RCC manhole/ inspection


chambers with Heavy duty CI manhole covers of make with cement
mortar 1:3 finished with a floating coat of neat cement inside and rough
2.10 plaster on outside and making channels in cement concrete M-30 mix
neatly finished complete as per structural design drawings including
excavation through hard rock or soft soil, refilling and disposal of surplus
earth.

RCC inspection chambers inside size 75x75 cms and upto 1.35 mts
deep including duct tile / cast iron double seal manhole cover with frame
a) (heavy duty, grade - A) 60 x 60 cms total weight of cover and frame not Nos. 0 0 0 0 0 0 0 0 45 45
less than 75 kg.Refer standard drawing STD-001 and structural drawing
for constructional details.

RCC inspection chambers inside size 90x90 cms and above 1.2 mtr.
upto 3.5 mtr. deep including cast iron double seal manhole cover with
b) frame (heavy duty, grade - A) 60 x 60 cms total weight of cover and Nos. 0 0 0 0 0 0 0 0 0 0
frame not less than 75 kg.Refer standard drawing STD-001 and
structural drawing for constructional details.

SUB TOTAL TO SUMMARY.

Semac and Partners L.L.C Plumbing Works M/s. EMDAD LOGISTICS SAOC
Page 120 of 172
DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS PLUMBING WORK BILL NO.-5

HAZARDOUS

PUMP ROOM
HOUSE & AC

RECEPTION
TECHNICAL

T.X YARD &

EXTERNAL
BUILDING
CUM HELI

BUILDING
LOGISTIC

FACILITY

LV ROOM
HANGER

SENTRY
OFFICE
STORE

STORE

POSTS
PLANT
SL.
DESCRIPTION. UNIT QTY
NO.

3.0 WATER SUPPLY (INTERNAL)

Providing and fixing insulated Copper pipes for hot and cold water
conforming to B.S. 2871 Part I table Y) with end feed capillary fittings
with silver brazing to B.S. 864, galvanized steel hangers and supports
with PVC strip separators, anticorrosive treatment complete including
3.1
supply and fixing of gun metal valve. Note: External Steel structure
Overhead tank to building interconnection pipe routing & related pipe
supporting tray / structure complete accessories part of contractor
scope accordinly consider complete scope of work & supporting details.

a) 15 mm O.D. Mtr 22 85 395 0 57 0 0 44 0 603


b) 22 mm O.D. Mtr 6 20 106 0 14 0 0 20 0 166
c) 28 mm O.D. Mtr 18 42 111 0 5 0 0 36 0 212
d) 35 mm O.D. Mtr 26 0 22 0 4 0 0 0 0 52
e) 42 mm O.D. Mtr 0 28 85 0 25 0 0 0 0 138
f) 50 mm O.D. Mtr 0 0 40 0 0 0 0 0 0 40
g) 63 mm O.D. Mtr 0 0 0 0 0 0 0 0 0 0
h) 80 mm O.D. Mtr 0 0 0 0 0 0 0 0 0 0

3.2 Insulation
Supply, installation & commissioning of 25mm thk ARMAFLEX
insulation for hot water and external pipes. And as per drawings &
Specifications
a) 28mm dia pipe Mtr 18 42 111 0 5 0 0 36 0 212
b) 35mm dia pipe Mtr 26 0 22 0 4 0 0 0 0 52
c) 42mm dia pipe Mtr 0 28 85 0 25 0 0 0 0 138
d) 50mm dia pipe Mtr 0 0 40 0 0 0 0 0 0 40
e) 63 mm dia pipe Mtr 0 0 0 0 0 0 0 0 0 0
f) 63 mm dia pipe Mtr 0 0 0 0 0 0 0 0 0 0

Semac and Partners L.L.C Plumbing Works M/s. EMDAD LOGISTICS SAOC
Page 121 of 172
DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS PLUMBING WORK BILL NO.-5

HAZARDOUS

PUMP ROOM
HOUSE & AC

RECEPTION
TECHNICAL

T.X YARD &

EXTERNAL
BUILDING
CUM HELI

BUILDING
LOGISTIC

FACILITY

LV ROOM
HANGER

SENTRY
OFFICE
STORE

STORE

POSTS
PLANT
SL.
DESCRIPTION. UNIT QTY
NO.

Supply, installation & commissioning of Isolation valve/ball valve as per


3.3
drawing with including complete scope of work.

a) 28mm dia Nos. 2 0 10 0 0 0 0 4 0 16

b) 35 mm dia Nos. 3 1 6 0 1 0 0 2 0 13

c) 42 mm dia Nos. 0 4 2 0 4 0 0 2 0 12

d) 50mm dia Nos. 0 0 10 0 0 0 0 0 0 10

e) 63 mm dia Nos. 0 0 0 0 0 0 0 0 0 0

f) 63 mm dia Nos. 0 0 0 0 0 0 0 0 0 0
Supply, installation & commissioning of 25 dia Gate valve 3 nos + 1 No.
g) PRV complete all accessories as required and as per drawings Set 0 0 7 0 0 0 0 0 0 7
complete scope
Supply, installation & commissioning of 32 dia Gate valve 3 nos + 1 No.
h) PRV complete all accessories as required and as per drawings Set 0 0 4 0 0 0 0 0 0 4
complete scope
Supply, installation & commissioning of 40 dia Gate valve 3 nos + 1 No.
i) PRV complete all accessories as required and as per drawings Set 0 0 0 0 0 0 0 0 0 0
complete scope
Supply, installation & commissioning of 50 dia Gate valve 3 nos + 1 No.
j) PRV complete all accessories as required and as per drawings Set 0 0 2 0 0 0 0 0 0 2
complete scope
Supply, installation & commissioning of 65 dia Gate valve 3 nos + 1 No.
k) PRV complete all accessories as required and as per drawings Set 0 0 0 0 0 0 0 0 0 0
complete scope

SUB TOTAL TO SUMMARY.

Semac and Partners L.L.C Plumbing Works M/s. EMDAD LOGISTICS SAOC
Page 122 of 172
DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS PLUMBING WORK BILL NO.-5

HAZARDOUS

PUMP ROOM
HOUSE & AC

RECEPTION
TECHNICAL

T.X YARD &

EXTERNAL
BUILDING
CUM HELI

BUILDING
LOGISTIC

FACILITY

LV ROOM
HANGER

SENTRY
OFFICE
STORE

STORE

POSTS
PLANT
SL.
DESCRIPTION. UNIT QTY
NO.

4.0 EXTERNAL WATER PIPING NETWORK

Supplying, installation, testing and commissioning of water supply line


including tapping from Municipality / Industrial water supply main line,
Water supply main line connecting to the proposed water tank including
supply of high pressure HDPE Pipe above ground with Gun metal gate
4.1 LS 0 0 0 0 0 0 0 0 1 1
valves, Bowser inlet line with NRV & Isolation etc. as per local standard
requirement. This work shall be include construction of valve
chamber/manhole for water meter and valves complete in all respect &
as per local Authority water standard rules & regulation. etc.

Supply, installation, testing & commissioning of 2way Bowser water inlet


box, NRV & Isolation valve. As per drawing from bowser outlet to
4.2 LS 0 0 0 0 0 0 0 0 1 1
interconnection of OHT piping to be considered & related complete
scope of work & including related civil works.

Supply, Installation, Testing & hand-over the exteranal water supply


pipe network supplying water from the central Pump room to the various
areas including isolation valves. The piping shall be FM approved and
listed to HDPE SDR-11, PN16 for the underground piping, Welding to
be butt fusion and suitable for pipe pressure ratings, and each joint
should have separate report showing full details on joint and welding etc
complete scope as shown in the drawings complete with adequate
fittings & all accessories with including civil works, external route
marker, Pressure testing, etc complete scope of works & as per
drawings

4.3 For EXTERNAL WATER SUPPLY LINE

A UNDER GROUND HDPE PIPES & FITTINGS-SDR11, PN16Bar.

a) 250mm dia OD Mtrs. 0 0 0 0 0 0 0 0 0 0


b) 225mm dia OD Mtrs. 0 0 0 0 0 0 0 0 0 0
c) 200mm dia OD Mtrs. 0 0 0 0 0 0 0 0 0 0
d) 160mm dia OD Mtrs. 0 0 0 0 0 0 0 0 290.0 290
e) 90mm dia OD Mtrs. 0 0 0 0 0 0 0 0 0 0
f) 63mm dia OD Mtrs. 0 0 0 0 0 0 0 0 42 42
g) 50mm dia OD Mtrs. 0 0 0 0 0 0 0 0 260 260

Semac and Partners L.L.C Plumbing Works M/s. EMDAD LOGISTICS SAOC
Page 123 of 172
DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS PLUMBING WORK BILL NO.-5

HAZARDOUS

PUMP ROOM
HOUSE & AC

RECEPTION
TECHNICAL

T.X YARD &

EXTERNAL
BUILDING
CUM HELI

BUILDING
LOGISTIC

FACILITY

LV ROOM
HANGER

SENTRY
OFFICE
STORE

STORE

POSTS
PLANT
SL.
DESCRIPTION. UNIT QTY
NO.

Supply, installation & Commissioning of Gate valves with PN16, UL/FM


approved, Ductile Iron, Epoxy coated finish in and out. Complete valve
B with construction of RCC chamber with double seal with heavy duty
cover 800x800mm & related complete civil works part of contractor
scope complete as per drawing etc.
a) 250mm dia OD Nos. 0 0 0 0 0 0 0 0 0 0
b) 225mm dia OD Nos. 0 0 0 0 0 0 0 0 0 0
c) 200mm dia OD Nos. 0 0 0 0 0 0 0 0 0 0
d) 160mm dia OD Nos. 0 0 0 0 0 0 0 0 0 0
e) 90mm dia OD Nos. 0 0 0 0 0 0 0 0 0 0
f) 63mm dia OD Nos. 0 0 0 0 0 0 0 0 0 0
g) 50mm dia OD Nos. 0 0 0 0 0 0 0 0 0 0

Supply, installation & Commissioning of 50 dia Gate valve 1 nos + 1


No. PRV complete all accessories as required and as per drawings
h) Nos. 0
complete scope including RCC manhole chamber with heavy duty cover
1200x1200mm with heavy duty cover 800x800

Supply, installation & Commissioning of 100 dia Gate valve 3 nos + 1


No. PRV complete all accessories as required and as per drawings
i) Nos. 0 0 0 0 0 0 0 0 1 1
complete scope including RCC manhole chamber 1200x1200mm with
heavy duty cover 800x800mm

SUPPLY & INSTALLATION OF PVC ROAD CRSSING SLEEVES


C WITH ACCESSORIES AND CONCRETE AROUND THE SLEEVE AT
ROAD CROSSING AREA
h) 250 dia Mtr 0 0 0 0 0 0 0 0 0 0
i) 200 dia Mtr 0 0 0 0 0 0 0 0 75 75
j) 160 dia Mtr 0 0 0 0 0 0 0 0 20 20
k) 110 dia Mtr 0 0 0 0 0 0 0 0 49 49

SUB TOTAL TO SUMMARY.

Semac and Partners L.L.C Plumbing Works M/s. EMDAD LOGISTICS SAOC
Page 124 of 172
DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS PLUMBING WORK BILL NO.-5

HAZARDOUS

PUMP ROOM
HOUSE & AC

RECEPTION
TECHNICAL

T.X YARD &

EXTERNAL
BUILDING
CUM HELI

BUILDING
LOGISTIC

FACILITY

LV ROOM
HANGER

SENTRY
OFFICE
STORE

STORE

POSTS
PLANT
SL.
DESCRIPTION. UNIT QTY
NO.

5.0 PUMP SETS AND TANKS.

5.1 TRANSFER PUMP SET.

Supply and installation, testing and commissioning of 1 no. Duplex Cold


water Transfer pump set, consisting of 2nos long coupled end suction
centrifugal pumps (duty/standby) electric driven 3ph x 415V, 50 Hz.
Each pump capable of delivering 3.5LPS to maintain a constant head of
4 bar pressure in the water line on common base with all
interconnecting pipe work, pumps shall be VFD & full automatic control,
gate valves on suction and delivery side of each pump, NRV on delivery
side of each pump, one 300Ltr. pressure vessel, pressure switch,
a) Set 0 0 0 0 0 0 0 0 1 1
pressure guage, duplex control panel for the automatic operation of
above pumps on duty/assit/standby basis with HOA switches. Run/trip
lamps, for each pump, automatic changeover of starting sequence after
every start, autostart of standby pump in the event of failure of duty
pump, low level cut off by level relay, with related control cable etc.
complete.The rate to include cost of best quality float valve & civil works
for pump foundation work with at least for 5 years warranty. Complete
as per drawing.

5.1 BOOSTER PUMP SET.

Supply and installation, testing and commissioning of 1 no. Duplex cold


water pump set, consisting of 2 nos long coupled end suction centrifugal
pumps (duty/standby) electric driven 3ph x 415V, 50 Hz. Each pump
capable of delivering 0.5LPS to maintain a constant head of 1.2 bar
pressure in the water line on common base with all interconnecting pipe
work, gate valves on suction and delivery side of each pump, NRV on
delivery side of each pump, one 200Ltr. pressure vessel, pressure
a) Set 1 0 0 0 1 0 0 0 0 2
guage, duplex control panel with VFD for each pump, the automatic
operation of above pumps on duty/standby. automatic changeover of
starting sequence after every start, autostart of standby pump in the
event of failure of duty pump, low level cut off by level relay, with related
control cable etc. complete.The rate to include cost of best quality float
valve with at least for 5 years warranty. including pump foundation
related complete scope etc. (Reception building,Logistic store)

Semac and Partners L.L.C Plumbing Works M/s. EMDAD LOGISTICS SAOC
Page 125 of 172
DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS PLUMBING WORK BILL NO.-5

HAZARDOUS

PUMP ROOM
HOUSE & AC

RECEPTION
TECHNICAL

T.X YARD &

EXTERNAL
BUILDING
CUM HELI

BUILDING
LOGISTIC

FACILITY

LV ROOM
HANGER

SENTRY
OFFICE
STORE

STORE

POSTS
PLANT
SL.
DESCRIPTION. UNIT QTY
NO.

Supply and installation, testing and commissioning of 1 no. Duplex cold


water pump set, consisting of 2 nos long coupled end suction centrifugal
pumps (duty/standby) electric driven 3ph x 415V, 50 Hz. Each pump
capable of delivering 1.2LPS to maintain a constant head of 1.5 bar
pressure in the water line on common base with all interconnecting pipe
work, gate valves on suction and delivery side of each pump, NRV on
delivery side of each pump, one 200Ltr. pressure vessel, pressure
b) Set 0 1 0 0 0 0 0 0 0 1
guage, duplex control panel with VFD for each pump, the automatic
operation of above pumps on duty/standby. automatic changeover of
starting sequence after every start, autostart of standby pump in the
event of failure of duty pump, low level cut off by level relay, with related
control cable etc. complete.The rate to include cost of best quality float
valve with at least for 5 years warranty. including pump foundation
related complete scope etc. (Technical facility hanger)

Supply and installation, testing and commissioning of 1 no. Duplex cold


water pump set, consisting of 2 nos long coupled end suction centrifugal
pumps (duty/standby) electric driven 3ph x 415V, 50 Hz. Each pump
capable of delivering 1.5LPS to maintain a constant head of 2bar
pressure in the water line on common base with all interconnecting pipe
work, gate valves on suction and delivery side of each pump, NRV on
delivery side of each pump, one 200Ltr. pressure vessel, pressure
c) Set 0 0 2 0 0 0 0 0 0 2
guage, duplex control panel with VFD for each pump, the automatic
operation of above pumps on duty/standby. automatic changeover of
starting sequence after every start, autostart of standby pump in the
event of failure of duty pump, low level cut off by level relay, with related
control cable etc. complete.The rate to include cost of best quality float
valve with at least for 5 years warranty. including pump foundation
related complete scope etc. (Office & accommodation)

Semac and Partners L.L.C Plumbing Works M/s. EMDAD LOGISTICS SAOC
Page 126 of 172
DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS PLUMBING WORK BILL NO.-5

HAZARDOUS

PUMP ROOM
HOUSE & AC

RECEPTION
TECHNICAL

T.X YARD &

EXTERNAL
BUILDING
CUM HELI

BUILDING
LOGISTIC

FACILITY

LV ROOM
HANGER

SENTRY
OFFICE
STORE

STORE

POSTS
PLANT
SL.
DESCRIPTION. UNIT QTY
NO.

Supply, installation, testing and commissioning of insulated type Poly


Ethylene water storage tank, 4 layers & stainless or copper holes with
all necessary accessories, controller, switch level, etc. with insulated
type mounted on roof slab & consider 150mm rcc foundation for the
5.2 tank. The rate to include cost of civil works for tank foundations,
overflow, vent, delivery and inlet pipe connections as per drawing,
manholes and ladder to access roof of tank etc. complete. The out
going pipes shall be heat, insulated using armaflex insulation complete
in all respect as per drawing. Complete with all necessary accessories.

a) 100USG Nos. 0 0 0 0 0 0 0 0 0 0
b) 300USG Nos. 1 1 0 0 1 0 0 2 0 5
c) 600USG Nos. 0 0 0 0 0 0 0 0 0 0
d) 1000USG Nos. 0 0 2 0 0 0 0 0 0 2
SUB TOTAL TO SUMMARY.

Semac and Partners L.L.C Plumbing Works M/s. EMDAD LOGISTICS SAOC
Page 127 of 172
DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS PLUMBING WORK BILL NO.-5

HAZARDOUS

PUMP ROOM
HOUSE & AC

RECEPTION
TECHNICAL

T.X YARD &

EXTERNAL
BUILDING
CUM HELI

BUILDING
LOGISTIC

FACILITY

LV ROOM
HANGER

SENTRY
OFFICE
STORE

STORE

POSTS
PLANT
SL.
DESCRIPTION. UNIT QTY
NO.

6.0 ITEMS
If in the opinion of the contractor there are some items not mentioned in
the BOI, the contractor must show them below and carry their sum to
LS 0
the summary items not mentioned in the bill of quantities but specified in
drawing.

Miscellaneous works, not identified above but required to make


installation complete for achieving fully functional Water supply &
6.1 drainage system etc. as per project requirement & specifications LS 0
(Contractor to list the activities and indicate the item wise price for the
same in the respective column).

Dia 35 mm GI pipe (Vertical Riser Cold water main line) as per drawing Mtrs 10 0 0 0 0 0 0 28 0 38

Dia 42 mm GI pipe (Vertical Riser Cold water main line) as per drawing Mtrs 0 12 0 0 15 0 0 0 0 27

Dia 50 mm GI pipe (Vertical Riser Cold water main line) as per drawing Mtrs 0 0 50 0 0 0 0 0 0 50
Dia 110 mm Water meter Nos 0 0 0 0 0 0 0 0 1 1
Janitor Sink Nos 0 1 0 0 0 0 0 0 0 1
Sump pump for Pump room Nos 0 0 0 0 0 0 0 0 3 3
Sump pump for Storm water Tank Nos 0 0 0 0 0 0 0 0 2 2
Sump pump for Holding Tank Nos 0 0 0 0 0 0 0 0 1 1
Mono Rail @ Pump room Nos 0 0 0 0 0 0 1 0 0 1
Cladding for all Exposed Copper pipe
22mm Dia Pipe Mtrs 0 14 0 0 0 0 0 0 0 14
28mm Dia Pipe Mtrs 9 0 92 0 0 0 0 31 0 132
35mm Dia Pipe Mtrs 21 0 0 0 0 0 0 11 0 32
42mm Dia Pipe Mtrs 0 30 85 0 31 0 0 0 0 146
50mm Dia Pipe Mtrs 0 0 86 0 0 0 0 0 0 86
Water Cooler Nos 0 0 4 0 0 0 0 0 0 4
SUB TOTAL TO SUMMARY.

Semac and Partners L.L.C Plumbing Works M/s. EMDAD LOGISTICS SAOC
Page 128 of 172
DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITEMS PLUMBING WORK BILL NO.-5

HAZARDOUS

PUMP ROOM
HOUSE & AC

RECEPTION
TECHNICAL

T.X YARD &

EXTERNAL
BUILDING
CUM HELI

BUILDING
LOGISTIC

FACILITY

LV ROOM
HANGER

SENTRY
OFFICE
STORE

STORE

POSTS
PLANT
SL.
DESCRIPTION. UNIT QTY
NO.

TOTAL COLLECTION BILL NO. 5

1 SANITARY FIXTURES

2 INTERNAL, EXTERNAL DRAINAGE AND SANITARY INSTALLATION

3 WATER SUPPLY (INTERNAL)

4 EXTERNAL WATER PIPING NETWORK

5 PUMP SETS AND TANKS.

6 ITEMS

TOTAL COLLECTION TO GENERAL SUMMARY

NOTE;

1 This is a lump sum tender

2 Items & quantities provided in this tender are purely indicative. Contractors to verify the drawings and quote accordingly.

Schedule of items in conjunction with drawings and specifications constitute complete tender. The renderers are responsible for all the quantities they consider necessary for the
proper submission of the tender in accordance with the conditions of contract, drawings and specification. In case the contractor/Tenderer notice any item missing in the BOQ he
3
should include the same in this quoted value and submit with the tender, a list of such items along with relevant specifications and quantities. No claims shall be entertained at a
later stage for items not listed in the schedule but mentioned in the drawings.

4 GRAND TOTAL is to include for items not included here but required to complete all works.

Semac and Partners L.L.C Plumbing Works M/s. EMDAD LOGISTICS SAOC
Page 129 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS
S.A.O.C
BILL OF ITEMS FIRE FIGHTING & FIRE ALARM WORK. BILL NO. 6

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS
ROOM
SL.
DESCRIPTION. UNIT QTY
NO.

1.0 EXTERNAL HYDRANTS & HOSE REEL CABINETS : UL/FM-NFPA14.

1.1 6" PILLAR HYDRANT

Supply, installation, testing and commissioning of Dry type barrel hydrants with
double compartment MS external hose cabinet along with 30 meter PN16
synthetic double hose, nozzles, hydrant barrier and other standard accessories as
per NFPA/ ROPCD norms. The hydrants shall be manufactured to comply with
AWWA Standard C502, ULFM/LPCB/BSI kitmark approved. Fire hydrants shall
meet all requirements of local civil defence. Fire hydrants shall be rated for a
minimum working pressure of 150 Psi (1034 kPa). Fire hydrants shall have a main
valve which shall provide complete closing of the drains after 4 to 5 turns of the
operating nut in the opening direction. The drain ring assembly shall be
replaceable without removing the hydrant from the connecting pipe or having to
dig. Fire hydrants shall be three-way in design / ROPCD regulations, having one
pumper nozzle (size as specified) and four 2-1/2” hose nozzle(side outlet). The
operating nut shall be a one piece design, manufactured of Bronze. It shall be
a)
pentagon in shape, an arrow shall be cast on the bonnet flange to indicate the
Set 0 0 0 0 0 0 0 0 6 6
specified opening direction. Hydrants shall be a “traffic-model” having upper and
lower barrels joined at the ground line by a separate and breakable “swivel” flange
providing 3600 rotation of upper barrel for proper nozzle facing. The lower barrel
shall be an integrally cast unit. The use of threaded on or mechanically attached
flanges is deemed unacceptable. Hydrant Inlet shall flanged and the size shall be
minimum 6”. Body material shall be made of Grey cast iron or Ductile Iron as per
BS standard. Material of spindle shall be made of Stainless steel to BS EN 10088-
1. Material for the screwed outlet is made of High tensile brass to BS 12163. The
cabinet shall be made weather proof (outdoor type) with fireman’s key, 5.0 KG
CO2 & 9.0Lts. foam type (AFFF) fire extinguisher with pressure regulating valve
& isolation valve, RCC chamber as per drawing etc complete in all respect &
Standards.

Spindle sealing (two seals) is of the toroidal sealing ring (‘O’ ring) type. Design of
the spindle cap in accordance with BS 5163. A Wiper ring is positioned above the
spindle sealing to prevent the ingress of foreign matter. All the hydrants shall be
protected by providing GI pipe barricade in line with civil defence standards,

HC1- Hydrant Cabinet with 4nos hoses near Helipad area.(65diax30mtr Fire hose
a)
with Nozzle)
Set 2 2

HC1- Hydrant Cabinet with 2nos hoses near Other area.(65diax30mtr Fire hose
b) Set 4 4
with Nozzle)

Semac and Partners L.L.C Fire fighting fire alarm Works M/s. EMDAD LOGISTICS SAOC
Page 130 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS
S.A.O.C
BILL OF ITEMS FIRE FIGHTING & FIRE ALARM WORK. BILL NO. 6

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS
ROOM
SL.
DESCRIPTION. UNIT QTY
NO.

Supply, installation & Commissioning of Air release valve assembly for Hydrant
network line NRS type with PN16, UL/FM approved, Ductile Iron. Epoxy coated
c)
finish in and out. Complete valve with construction of RCC chamber with heavy
Set 6 6
duty cover & related complete civil works part of contractor scope etc.

Supply, installation & Commissioning of Net work drain valve assembly for
Hydrant network line NRS type with PN16, UL/FM approved, Ductile Iron. Epoxy
d)
coated finish in and out. Complete valve with construction of RCC chamber with
Set 6 6
heavy duty cover & related complete civil works part of contractor scope etc.

1.2 HOSE REELCABINET:

Supplying, installation, testing and commissioning double vertical Hose reel


cabinet suitable for intdoor or outdoor installation made of 16 SWG MS Sheet with
SS 316 fronted doors, ‘FIRE RED’ painting etc. Consisting one 30meter long
25mm dia high pressure rubber hose reel swing type, 5.0 KG CO2 & 9.0Lts.
foam type (AFFF) fire extinguisher etc complete, with 6.35mm bronze nozzle,
shutt - off valve and 42 mm to 20 mm adopter, 25mm dia Pressure reducing valve
(PRV), 25mm dia lockshield valve etc. complete in all respect. All the office/admin
area Hose reel cabinet front door shall be SS type with recessed type required
accordinly consider compelte scope including supports & foundation. All the Farm
a) area fire hose reel cabinets shall be outdoor type with IP 65 Rating required Set 4 4 8 0 0 0 0 0 0 16
accordinly consider complete scope with including installation supporting related
foundation & civil works. The Hose reel shall be LPCB/BSI Kite mark and have
local civil defence approval in line with BS EN 694. The cabinet shall be supported
with reinforced support arm and swing through 180 Degree & consisting one 30
meter long 25 mm dia high pressure reinforced semi rigid rubber hose reel swing
type shall comply to BS EN 671-1. The outer end of Hose reel shall be fitted with
Jet/Spray/ shutt-off control nozzle, PRV, lock shield valve. All water passage must
be brass chrome plated. 2No's portable extinguisher extinguisher etc complete in
all respect.

Semac and Partners L.L.C Fire fighting fire alarm Works M/s. EMDAD LOGISTICS SAOC
Page 131 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS
S.A.O.C
BILL OF ITEMS FIRE FIGHTING & FIRE ALARM WORK. BILL NO. 6

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS
ROOM
SL.
DESCRIPTION. UNIT QTY
NO.

1.3 FIRE FIGHTING PIPING NETWORK

Supply, Installation, Testing & hand-over the fire fighting water supply pipe
network supplying water from the central Pump room to the various areas
including external hydrants, installed fire hose reel cabinets, sprinker systems,
deluge and isolation valves (proposed network shall be tapped from the existing
fire water network as per the site condition). The piping shall be FM approved and
listed to ISO 4427 HDPE SDR-11, PN16 for the underground piping, Welding to
be butt fusion and suitable for pipe pressure ratings, and each joint should have
separate report showing full details on joint and welding process and result. GI
pipes class C heavy duty schedule 40 in compliance with ASTM- A53 for the
exposed piping according to specifications and as shown in drawings complete
with adequate fittings & all accessories. Isolating valves & branch control valves
are included. Pipe network drain points equipped with valves & air releif valves
shall be included. The item includes pipe connection with the existing fire fighting
water network. The works include testing & handing over as per the specifications
& issued tender drawings. Including warning tape & Route markers every
25/50mtr.etc complete scope.

1.3.1 For Fire Hydrant, Hose Reel Cabinet & Sprinkler


A UNDER GROUND HDPE PIPES & FITTINGS-SDR11, PN16Bar.
a) 250mm dia OD Mtrs. 0 0 0 0 0 0 0 0 0 0
b) 225mm dia OD Mtrs. 0 0 0 0 0 0 0 0 0 0
c) 200mm dia OD Mtrs. 0 0 0 0 0 0 0 0 530 530
d) 160mm dia OD Mtrs. 0 0 0 0 0 0 0 0 200 200
e) 110mm dia OD Mtrs. 0 0 0 0 0 0 0 0 0 0
f) 90mm dia OD Mtrs. 0 0 0 0 0 0 0 0 0 0
g) 75mm dia OD Mtrs. 0 0 0 0 0 0 0 0 0 0
f) 63mm dia OD Mtrs. 0 0 0 0 0 0 0 0 100 100
g) 50mm dia OD Mtrs. 0 0 0 0 0 0 0 0 0 0

Semac and Partners L.L.C Fire fighting fire alarm Works M/s. EMDAD LOGISTICS SAOC
Page 132 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS
S.A.O.C
BILL OF ITEMS FIRE FIGHTING & FIRE ALARM WORK. BILL NO. 6

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS
ROOM
SL.
DESCRIPTION. UNIT QTY
NO.

Supply, installation & Commissioning of Isolation valves OS & Y type with PN16,
UL/FM approved, Ductile Iron. Epoxy coated finish in and out. Complete valve
B
with construction of RCC chamber 1200x1200mm with heavy duty cover
800x800mm & related complete civil works part of contractor scope etc.

a) 200mm dia OD Nos. 0 0 0 0 0 0 0 0 3 3


b) 160mm dia OD Nos. 0 0 0 0 0 0 0 0 0 0
c) 110mm dia OD Nos. 0 0 0 0 0 0 0 0 0 0
d) 90mm dia OD Nos. 0 0 0 0 0 0 0 0 0 0
e) 75mm dia OD Nos. 0 0 0 0 0 0 0 0 0 0
f) 65mm dia OD Nos. 0 0 0 0 0 0 0 0 0 0
g) 50mm dia OD Nos. 0 0 0 0 0 0 0 0 0 0

Supply & installation of 4WAY Breeching inlet with cabinet, 150dia Non Return
h) valve (NRV) and related pipe work from breeching inlet to tank- near pump room LS 1 0 0 0 0 0 0 0 1 2
etc complete scope as per local authority requirement.

Supply, installation & Commissioning of Isolation valves NRS type with PN16,
UL/FM approved, Ductile Iron. Epoxy coated finish in and out. Complete valve
C
with construction of RCC chamber with heavy duty cover & related complete civil
works part of contractor scope etc.

a) 250mm dia OD Nos. 0 0 0 0 0 0 11 0 0 11

b) 200mm dia OD Nos. 0 0 0 0 0 0 0 0 1 1

c) 160mm dia OD Nos. 1 0 0 0 0 0 0 0 0 1

d) 110mm dia OD Nos. 0 0 0 0 0 0 0 0 0 0

Semac and Partners L.L.C Fire fighting fire alarm Works M/s. EMDAD LOGISTICS SAOC
Page 133 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS
S.A.O.C
BILL OF ITEMS FIRE FIGHTING & FIRE ALARM WORK. BILL NO. 6

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS
ROOM
SL.
DESCRIPTION. UNIT QTY
NO.

Supply, installation & Commissioning of Welded type to Exposed GI Pipes &


Fittings Class- "C" with all accessories & fixing supports. Schedule 40, ASTM-
A53. For all fire fighting applications mentioned above quote to include complete
D
primary & secondary supports, fire paint for fire fighting system related complete
work with including fire paint as per local authority standard complete scope part
of contractor scope.

i) 250mm NB Mtr. 0 0 0 0 0 0 0 0 0 0

ii) 200mm NB Mtr. 0 0 0 0 0 0 0 0 0 0

iii) 150mm NB Mtr. 0 0 0 0 0 0 0 0 0 0

iv) 100mm NB Mtr. 0 0 0 0 0 0 0 0 0 0

v) 80mm NB Mtr. 0 0 0 0 0 0 0 0 0 0

vi) 65mm NB Mtr. 0 0 0 0 0 0 0 0 0 0

vii) 50mm NB Mtr. 0 0 0 0 0 0 0 0 0 0

viii) 40mm NB Mtr. 0 0 0 0 0 0 0 0 0 0

ix) 32mm NB Mtr. 0 0 0 0 0 0 0 0 0 0

x) 25mm NB Mtr. 0 0 0 0 0 0 0 0 0 0

Note: All related civil work including excavation, backfilling constructing


valve chamber, thrust block, chasing, cutting, making hole and finish good
etc. shall be included in the scope of work, the related pipe supporting
clamp & tray etc. complete shall be included in the scope of work. Refer
fire fighting layout drawing for details.

Semac and Partners L.L.C Fire fighting fire alarm Works M/s. EMDAD LOGISTICS SAOC
Page 134 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS
S.A.O.C
BILL OF ITEMS FIRE FIGHTING & FIRE ALARM WORK. BILL NO. 6

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS
ROOM
SL.
DESCRIPTION. UNIT QTY
NO.

1.4 WATER SPRINKLER SYSTEM - UL/FM APPROVED.

Supply,installation,testing and commissioning of sprinklers in line with NFPA13 /


Local Civil defense norms. The sprinkler heads shall be of the spray pattern
installed in an upright position or pendant position as may be required. Sprinkler
in false ceilings shall be concealed / recessed (sprinkler cap with fuse link)
to ceiling and subject to approval.The design Criteria for all sprinklers such as
K-factor, type and operating temperature shall be submitted for approval. The item
shall be complete with piping required to be connected with the system &
gaskets, supports, painting & pressure gauges,water motor alamrs, pressure
switches and supports complete with tags, labels, flow indicators and color
codes.The works shall be complete as specified & shown in the tender drawings.

Supply, installation & commissioning of Upright Sprinkler head standard response


1.4.1 Nos. 484 333 0 0 0 0 0 0 0 817
68°C, 1/2" BSPT, Chrome finish type Sprinkler with 8K-factor.

Supply, installation & commissioning of Side wall Sprinkler head standard


1.4.2 Nos. 0 0 0 0 0 0 6 0 0 6
response 68°C, 1/2" BSPT, Chrome finish type Sprinkler with 5.6K-factor.

Supply, installation & commissioning of Pendent ELO Sprinkler Head K-11.2


1.4.3 Nos. 100 0 0 0 0 0 0 0 0 100
(Suitable to -20degre Freezer area)

Supply, installation & commissioning of 1" UPRIGHT ESFR SPRINKLER HEAD


1.4.4 Nos. 0 0 0 0 0 0 0 0 0 0
74°C STD.RESPONSE K-14

Semac and Partners L.L.C Fire fighting fire alarm Works M/s. EMDAD LOGISTICS SAOC
Page 135 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS
S.A.O.C
BILL OF ITEMS FIRE FIGHTING & FIRE ALARM WORK. BILL NO. 6

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS
ROOM
SL.
DESCRIPTION. UNIT QTY
NO.

Supply, installation & commissioning of Alarm Check valve assembly set with
including, Allarm pressure switch, alarm valve, pressure gauge (downstream),
pressure gauge (upstream), retard chamber, alarm cong, main drain valve OS & Y
1.4.5 Gate valve,Tamper switch with including all accessories etc and as per drawing ,
interfaced with the respective fire alarm network for the status indication
(Open/Closed). With including related necessary civil work part of contractor
scope as per local authority standard consider complete scope of work.

a) 200mm dia Set 0 0 0 0 0 0 0 0 1 1

b) 150mm dia Set 1 4 0 0 0 0 0 0 0 5

c) 100mm dia Set 0 0 0 0 0 0 0 0 0 0

d) 50mm dia Drain valve. Set 4 4 0 0 0 0 0 0 0 8

e) 25mm dia Ball valve. Set 2 2 0 0 0 0 3 0 0 7

f) 25mm dia Automatic air release valve. Set 2 2 0 0 0 0 1 0 0 5

Supply, installation & commissioning of Zone Control valve assembly set


(including Butterfly vavle, flow switch, pressure guage, test and drain valve, NRV
valve etc) Tamper switch with including all accessories etc, interfaced with the
1.4.6
respective fire alarm network for the status indication (Open/Closed). With
including related necessary civil work part of contractor scope as per local
authority standard complete scope of work consider complete scope of work.

i) 200mm Set 0 0 0 0 0 0 0 0 0 0

ii) 150mm Set 1 1 0 0 0 0 0 0 0 2

iii) 100mm Set 1 0 0 0 0 0 0 0 0 1

iv) 80mm Set 0 0 0 0 0 0 0 0 0 0

v) 65mm Set 0 0 0 1 0 0 1 0 0 2

vi) 50mm Set 0 0 0 0 0 0 0 0 0 0

Semac and Partners L.L.C Fire fighting fire alarm Works M/s. EMDAD LOGISTICS SAOC
Page 136 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS
S.A.O.C
BILL OF ITEMS FIRE FIGHTING & FIRE ALARM WORK. BILL NO. 6

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS
ROOM
SL.
DESCRIPTION. UNIT QTY
NO.

Supply, installation & commissioning of Welded type Exposed GI Pipes & Fittings
Class- "C" with all accessories & fixing supports. Schedule 40, ASTM-A53. For all
fire fighting applications mentioned above quote to include complete primary &
h)
secondary supports, fire paints for fire fighting system related complete work with
including fire paint as per local authority standard complete scope part of
contractor scope.

i) 250mm NB Mtr. 0 0 0 0 0 0 40 0 0 40

ii) 200mm NB Mtr. 0 0 0 0 0 0 0 0 0 0

iii) 150mm NB Mtr. 410 350 0 0 0 0 0 0 0 760

iv) 100mm NB Mtr. 55 230 0 0 0 0 0 0 0 285

v) 80mm NB Mtr. 100 0 0 0 0 0 0 0 0 100

vi) 65mm NB Mtr. 170 500 60 15 0 0 10 0 0 755

vii) 50mm NB Mtr. 400 360 0 5 0 0 25 0 0 790

viii) 40mm NB Mtr. 585 360 0 5 0 0 18 0 0 968

ix) 32mm NB Mtr. 120 148 0 9 0 0 20 0 0 297

x) 25mm NB Mtr. 746 643 42 30 0 0 6 0 0 1467

Note: All related civil work including excavation, backfilling constructing


valve chamber, thrust block, chasing, cutting, making hole and finish good
etc. shall be included in the scope of work, the related pipe supporting
clamp & tray etc. complete shall be included in the scope of work. Refer
fire fighting layout drawing for details.

SUPPLY, INSTALLATION & COMMISSIONING OF FOLLOWING


1.5
PORTABLE FIRE EXTINGUISHERS AS PER DRAWING.
a) Dry Chemical ABC type - 6 Kg. Capacity UL listed / FM approved Nos. 6 7 1 1 0 0 1 0 0 16

b) CO2 type - 2 Kg. Capacity UL listed / FM approved Nos. 0 0 0 0 0 0 0 0 0 0

c) CO2 type - 5 Kg. Capacity UL listed / FM approved Nos. 6 7 12 1 0 0 1 0 0 27

d) AFFF FOAM type - 9 ltr. Capacity UL listed / FM approved Nos. 0 0 7 0 0 0 0 0 0 7

e) DCP-5Kg Capacity UL listed / FM approved Nos. 0 0 0 0 0 0 0 0 0 0

f) DCP-9Kg Capacity UL listed / FM approved Nos. 0 0 0 0 0 0 0 0 0 0

Semac and Partners L.L.C Fire fighting fire alarm Works M/s. EMDAD LOGISTICS SAOC
Page 137 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS
S.A.O.C
BILL OF ITEMS FIRE FIGHTING & FIRE ALARM WORK. BILL NO. 6

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS
ROOM
SL.
DESCRIPTION. UNIT QTY
NO.

g) Fire Blanket - 6' x 6' size UL listed / FM approved Nos. 0 0 4 0 0 0 0 0 0 4

h) 25kg DCP Trolley type UL listed / FM approved. Nos. 0 0 0 0 0 0 0 0 0 0

i) 30kg CO2 Trolley type UL listed / FM approved. Nos. 6 3 0 1 0 0 0 0 0 10

j) 50kg DCP Trolley type UL listed / FM approved. Nos. 0 0 0 0 0 0 0 0 4 4

k) 50kg CO2 Trolley type UL listed / FM approved. Nos. 0 0 0 0 0 0 0 0 0 0

l) Recessed Cabinets for fire extinguishers Nos. 0 0 0 0 0 0 0 0 0 0

50Ltr AFFF Fire extinguisher Trolley type UL listed / FM approved. Nos. 0 0 0 0 0 0 0 0 5 5

SUPPLY & INSTALLATION OF FOAM FIRE SUPPRESSION SYSTEM -


1.6
UL, FM APPROVED MAKE.

Supply,installation,testing and commissioning of sprinklers in line with NFPA13 /


Local Civil defense norms. The sprinkler heads shall be of the spray pattern
installed in an upright position or pendant position as may be required. Sprinkler
in false ceilings shall be concealed / recessed (sprinkler cap with fuse link)
to ceiling and subject to approval.The design Criteria for all sprinklers such as
K-factor, type of k factor and operating temperature shall be submitted for
approval. The item shall be complete with piping required to be connected with
the system & gaskets, supports, painting & pressure gauges, water motor alamrs,
pressure switches and supports complete with tags, labels, flow indicators and
color codes.The works shall be complete as specified & shown in the tender
drawings.

Supply, installation & commissioning of Upright Foam Sprinkler head quick


1.6.1 Nos. 0 165 0 0 0 0 0 0 0 165
response 68°C, 1" BSPT, Chrome finish type Sprinkler with K11.2 factor.

Supply, installation & commissioning of Pendent Foam Sprinkler head standard


1.6.2 Nos. 0 0 0 12 0 0 0 0 0 12
response 68°C, 1/2" BSPT, Chrome finish type Sprinkler with K42 factor.

Semac and Partners L.L.C Fire fighting fire alarm Works M/s. EMDAD LOGISTICS SAOC
Page 138 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS
S.A.O.C
BILL OF ITEMS FIRE FIGHTING & FIRE ALARM WORK. BILL NO. 6

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS
ROOM
SL.
DESCRIPTION. UNIT QTY
NO.

Supply, installation & commissioning of Deluge valve assembly set with


including, Allarm pressure switch, alarm valve, pressure gauge, retard chamber,
alarm cong, main drain valve OS & Y Gate valve,Tamper switch with including all
1.6.3 accessories etc and as per drawing , interfaced with the respective fire alarm
network for the status indication (Open/Closed). With including related necessary
civil work part of contractor scope as per local authority standard consider
complete scope of work.

a) 200mm dia Set 0 0 0 0 0 0 0 0 0 0

b) 150mm dia Set 0 3 0 0 0 0 0 0 0 3

c) 80mm dia Set 0 0 0 1 0 0 0 0 0 1

d) Supply, installation & commissioning of 150mm dia Foam Ratio Controller. Set 0 3 0 0 0 0 0 0 0 3

e) Supply, installation & commissioning of 80mm dia Foam Ratio Controller. Set 0 0 0 1 0 0 0 0 0 1

f) Supply, installation & commissioning of 150mm dia Y - Stainer. Set 0 3 0 0 0 0 0 0 0 3

g) Supply, installation & commissioning of 80mm dia Y - Stainer. Set 0 0 0 1 0 0 0 0 0 1

h) Supply, installation & commissioning of 150mm dia OS & Y Gate Valve. Set 2 5 0 0 0 0 0 0 0 7

i) Supply, installation & commissioning of 80mm dia OS & Y Gate Valve. Set 0 0 0 2 0 0 0 0 0 2

j) Supply, installation & commissioning of 65mm dia OS & Y Gate Valve. Set 0 0 0 1 0 0 0 0 0 1

k) Supply, installation & commissioning of 80mm dia Butterfly Valve. Set 0 2 0 0 0 0 0 0 0 2

Semac and Partners L.L.C Fire fighting fire alarm Works M/s. EMDAD LOGISTICS SAOC
Page 139 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS
S.A.O.C
BILL OF ITEMS FIRE FIGHTING & FIRE ALARM WORK. BILL NO. 6

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS
ROOM
SL.
DESCRIPTION. UNIT QTY
NO.

Supplying, installation, testing and commissioning Double vertical Hose reel


cabinet with Foam container (Foam hose reel) suitable for intdoor or outdoor
installation made of 16 SWG MS Sheet with SS 316 fronted doors, ‘FIRE RED’
painting etc. Consisting one 30meter long 25mm dia high pressure hose reel
with foam nozzle swing type, 5.0 KG CO2 & 9.0Lts. foam type (AFFF) fire
extinguisher etc complete with 25mm dia Pressure reducing valve (PRV), 25mm
dia lockshield valve etc. complete in all respect. All the Hose reel cabinet front
1.6.4 door shall be SS type with recessed type required accordinly consider compelte Set 0 2 0 0 0 0 0 0 0 2
scope including supports & foundation.The Hose reel shall be LPCB/BSI Kite
mark and have local civil defence approval in line with BS EN 694. The cabinet
shall be supported with reinforced support arm and swing through 180 Degree &
consisting one 30 meter long 25 mm dia high pressure reinforced semi rigid
rubber hose reel swing type shall comply to BS EN 671-1. The outer end of Hose
reel shall be fitted with Jet/Spray/ shutt-off control nozzle, PRV, lock shield valve
etc complete in all respect as per authority standard.

Supply, installation & testing commissioning of Foam Monitor / Oscillating Monitor


([email protected]), as per drawing complete scope of work including civil works
1.6.5
as per installation standard practice. Refer drawing no.M-1114-FF-02-1002
Set 0 2 0 0 0 0 0 0 0 2
accordingly consider complete scope.

1.6.6 20Ltr AFFF can for Foam hose reel cabinet. UL listed / FM approved. ( 2nos) Set 0 2 0 0 0 0 0 0 0 2

Supply, installation & testing commissioning of 78GPM Foam Pump complete


skid assembly with including necessary accessary valves etc complete assembly,
1.6.7 as per drawing complete scope of work including civil works as per installation Set 0 1 0 0 0 0 0 0 0 1
standard practice. Refer drawing noM-1114-FF-02-1001 & M-1114-FF-02-1003
accordingly consider complete scope.

Supply, installation & testing commissioning of 500GPM Foam Pump with diesel
tank, atmospheric foam storage tank (GRP) with including interconnection piping,
valve etc complete skid assembly with including necessary accessary valves, as
1.6.8 per drawing complete scope of work including civil works foundation, bund wall etc Set 0 1 0 0 0 0 0 0 0 1
as per installation standard practice/ manufacturer requirement complete scope of
work to be considered . Refer drawing no. M-1114-FF-02-1001 & M-1114-FF-02-
1003 accordingly consider complete scope.

Semac and Partners L.L.C Fire fighting fire alarm Works M/s. EMDAD LOGISTICS SAOC
Page 140 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS
S.A.O.C
BILL OF ITEMS FIRE FIGHTING & FIRE ALARM WORK. BILL NO. 6

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS
ROOM
SL.
DESCRIPTION. UNIT QTY
NO.

Supply, installation & testing commissioning of 3% AFFF- Foam concentrate for


Foam Hose reel operation, Foam Monitor Operation, Hangar sprinkler discharge
& Hazardous store sprinkler etc complete scope with including interconnection
piping, valve etc complete skid assembly with including necessary accessary
1.6.9
valves, as per drawing complete scope of work including civil works foundation,
LS 0 1 0 0 0 0 0 0 0 1
bund wall etc as per installation standard practice/ manufacturer requirement
complete scope of work to be considered . Refer drawing no. M-1114-FF-02-1001
& M-1114-FF-02-1003 accordingly consider complete scope.

SUPPLY & INSTALLATION OF PRE ACTION SYSTEM.- UL, FM


1.7
APPROVED MAKE.

Supply, installation, testing and commissioning of Clean Agent Fire


Suppression System with automatic detection and control. The work shall
includes all engineering, labor, materials, equipment and services
necessary, and required, to complete and test the suppression system.
The design, equipment, installation, testing and maintenance of the Clean
Agent Suppression System shall be in accordance with the applicable
requirements set forth in the latest edition of NFPA No. 2001 - Clean
Agent Fire Extinguishing Systems also in line with NFPA 70 & 72.
Requirements of the Authority Having Jurisdiction (AHJ) The standards
listed, as well as all other applicable codes and standards, shall be used as
"minimum" design standards. Also to be considered are good engineering
practices.

The Proposed system shall be with Clean Agent gas storage cylinders
filled with gas and all hardware accessories,Cylinder Manifold and
discharge piping & Discharge Nozzles. Gas low pressure switch & Gas
discarge pressure switch. Fire Detection and Alarm system c/w Optical
smoke detectors, manual release,Auto / Manual selector switch, Abort unit,
First stage Alarm bell, second stage Alarm sounder, strobe horn, Gas
discharge warning sign and associated cabling etc.Gas release control
panel. Interlock wiring and conduit for shutdown of HVAC, dampers and/or
electric power supplies, relays or shunt trip breakers.Providing Drop
curtains for any permanent openings.

Semac and Partners L.L.C Fire fighting fire alarm Works M/s. EMDAD LOGISTICS SAOC
Page 141 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS
S.A.O.C
BILL OF ITEMS FIRE FIGHTING & FIRE ALARM WORK. BILL NO. 6

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS
ROOM
SL.
DESCRIPTION. UNIT QTY
NO.

Supply, installation & commissioning of Double interlock supervised Pre-


action system, Electro Galvannized cabinet with electric pneumatic
actuation arranagment complete system as per drawing with including
Main fire alarm, fire alarm bell, control panel, deluge valve, butterfly valve,
manual emergency release, water inlet pressure gauge, priming chamber
pressure gauge, system air pressure gauge, solenoid valve, main drain
1.7.1 valve, riser check valve, test & drain valve, anti reset valve & Vesda panel LS 1 1
etc complete scope. As per drawing 80 dia (OD) pre action valve and OS &
Y Gate valve for pre action system & tapping from main hydrant line
etc.with including necessary related civil works to be consider in the offer.
as per local authority standard consider complete scope of work. Refer
drawing no. M-1114-FF-06-1001 & M-1114-FF-06-1002 accordingly
consider complete scope.

Supply, installation & testing commissioning of 100Gallons Bladder tank, with


including interconnection piping, valve etc complete skid assembly with including
necessary accessary valves, as per drawing complete scope of work including
1.7.2 civil works foundation, bund wall etc as per installation standard practice/ Set 1 1
manufacturer requirement complete scope of work to be considered. Refer
drawing no. M-1114-FF-06-1001 & M-1114-FF-06-1002 accordingly consider
complete scope.

Note: All related civil work including excavation, backfilling constructing valve
chamber, thrust block, chasing, cutting, making hole and finish good etc. shall be 0
included in the scope of work.

SUB TOTAL TO SUMMARY

Semac and Partners L.L.C Fire fighting fire alarm Works M/s. EMDAD LOGISTICS SAOC
Page 142 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS
S.A.O.C
BILL OF ITEMS FIRE FIGHTING & FIRE ALARM WORK. BILL NO. 6

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS
ROOM
SL.
DESCRIPTION. UNIT QTY
NO.

2.0 FIRE DETECTION AND ALARM SYSTEM - ANALOG ADDRESSABLE


Design, Supply, Installation, testing & commissioning of Fire Detection & Alarm
system as per local fire norms & UL,FM / NFPA Codes:

Supply installation, testing and commissioning of microprocessor based following


fire alarm control equipment to offer flexibility in both design and operation. The
item to be complete including conduits, conduit fittings, 2C X 2.5Sqmm fire
retardent cabling from MFACP/AFACP to detectors, 24V DC power supplies and
safe / Exde MCP, sfe/Exde sounder devices & Flame detectors, from main fire
alarm panel to Auxiliary fire alarm panels.Complete with all necessary accessories
and ancillary works as shown on drawings.All the installation & execution should
be as per local civil defense authority standard & all the proposed makes shall be
civil defense Approved make. Note; Processing plant completely wet area
contractor shall consider complete weather proof & water proof type fire alarm
devices. IP65 Rating.

2.1 Intelligent Automatic Smoke detector with standard base Nos. 16 1 52 69

2.2 Intelligent Automatic Heat detector with standard base Nos. 5 1 6

2.3 Automatic Gas detector. Nos. 0

2.4
Intelligent Optical Smoke/Heat Detector- Multi Sensor detector (Intelligent Multi Nos. 0
sensor Detector with Standard Base).

Beam Detector Receiver with including External Power supply related


2.5 Set 4 4
complete work.
Beam Detector Transmitter with including External Power supply related
2.6 Set 4 4
complete work.

2.7 Flame detector. Set 4 1 5

2.8 Probe type Heat detector. Set 6 6

2.9 Imager - Osid Detector (IMR) Set 3 3

2.10 Emitters - Osid Detector (LIMIT) 3 3

2.11 Addressable Manual Call point - Explosion proof. 1 1

Semac and Partners L.L.C Fire fighting fire alarm Works M/s. EMDAD LOGISTICS SAOC
Page 143 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS
S.A.O.C
BILL OF ITEMS FIRE FIGHTING & FIRE ALARM WORK. BILL NO. 6

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS
ROOM
SL.
DESCRIPTION. UNIT QTY
NO.

2.12 Addressable dual action manual pull & push station. Nos. 9 8 26 43

Addressable dual action manual pull & push station. Outdoor W/P type.
2.13 Nos. 4 4
IP65 rating

Addressable Audible warning device with lighting strobe 85 - 120Db range


2.14 Nos. 11 11
adjustable type, Loop powered . (electric sounder)

Addressable Audible warning device with lighting strobe 85 - 120Db range


2.15 Nos. 18 20 2 4 4 48
adjustable type. (electric sounder) Outdoor W/P type. IP65 rating

Addressable Audible warning device with lighting strobe 85 - 120Db range


2.16 adjustable type. (electric sounder) Outdoor W/P type. IP65 rating- Nos. 1 1
Explosion proof.

Supply, installting, testing and commissioning of 2 Loop Addressable fire


alarm control panel with loop/network card as required (each loop
consist of 159 detector & 159 devices) Microprocessor based intelligent
and electronically addressable, modular, expandable, networkable, loops
with 20% spare capacity with each loop shall have a capacity of 318
analog addressable devices in one loop Fire Alarm Control Panel with
minimum 6 inch / 640 character LCD display, multiple access levels, event
history file in non-volatile memory (EEPROM). The panel shall support
2.17 Nos. 1 1 1 3
programmable relays for controlling fire pump, monitoring of fire sprinkler
etc. it shall have 240 volts AC power supply, automatic battery charger, 24
volts, sealed lead acid maintenance free batteries sufficient for 24 hours
normal working and then be capable of operating the system for 60
minutes during emergency condition with including loop card suitable for
detector etc complete syste as per local civil defense requirement.The
panel shall be UL listed. Scope to be considered as per
drawings/schematic.

Supply, installting, testing and commissioning of Repeater Panel (Active)


with 6 inch or 640-characters; The LCD shall Display all events / detectors,
2.18 devices status of complete systems in the networked, The NRP shall be Nos. 0
equipped with QWERTY Keypad. Mounting options include an annunciator
box, and blank modules are required for mounting.

Semac and Partners L.L.C Fire fighting fire alarm Works M/s. EMDAD LOGISTICS SAOC
Page 144 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS
S.A.O.C
BILL OF ITEMS FIRE FIGHTING & FIRE ALARM WORK. BILL NO. 6

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS
ROOM
SL.
DESCRIPTION. UNIT QTY
NO.

2.19 ADDRESSABLE TYPES CONTROL MODULES AS PER BELOW;


Supply installation, testing and commissioning of ADDRESSABLE MONITOR
a) Nos. 3 3
MODULES (MM)
Supply installation, testing and commissioning of ADDRESSABLE SOUNDER
b) Nos. 7 6 1 14
CONTROL MODULES (CM)

Supply installation, testing and commissioning of ADDRESSABLE DUAL


c) PRIORITY SWITCH MONITOR MODULES (DM) with including incoming power Nos. 5 25 8 38
supply etc complete scope as per drawing.

Supply installation, testing and commissioning of ADDRESSABLE ISOLATOR


d) Nos. 12 12
MODULES (IM) OR INTERFACING MODULE.

Supply installation, testing and commissioning of 5A-24V-DC POWER Supply


e) Nos. 1 1 1 3
Unit (PSU).

2.20 Panic bolts for emergency exit doors.(civil item) Nos. 0

Supply, installation, testing & commissioning of Fire alarm indicator panel


Addressable type with a provision of connection to the Civil defense central
alarm monitoring station. Fire alarm panel shall be screen printed or painted
2.21 neatly in English and Arabic for indicating the different Loops and other signs on Item 1 1
the panel including inter connecting fire retardant control and signal cables of
required size and specification in PVC sleeves/conduits. I.P. 1 -.as per local civil
defense approved make.

Supply, laying, installation & testing & commissioning of 4Core Single mode Fiber
optic (FOC) Armoured cable outdoor type (OS2) with Fiber Optical fiber media
converters (Media converters FOC to Cu.) cabling from individual building Fire
alarm panels to Main fire alarm panel & all Interconnection related interface model
2.22 LS 1
/ cable etc complete accessores with including complete scope as per local
authority standard. All necessary cabling for the civil works, excavation,
backfilling, compaction, making the surface good including supply and laying of
cables & conduit/sleevs part oof contractor scope.

SUB TOTAL TO SUMMARY

Semac and Partners L.L.C Fire fighting fire alarm Works M/s. EMDAD LOGISTICS SAOC
Page 145 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS
S.A.O.C
BILL OF ITEMS FIRE FIGHTING & FIRE ALARM WORK. BILL NO. 6

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS
ROOM
SL.
DESCRIPTION. UNIT QTY
NO.

3.0 FIRE PUMP SETS

3.1 FIRE HYDRANT & SPRINKLER SYSEM PUMP -UL/FM LISTED

Supply and installation, testing and commissioning of 1 no. Fire Pump set
consisting of 2 nos long coupled end suction centrifugal pumps, one diesel
drive and one electric driven 3 x 415V, 50 Hz each pump shall capable of
delivering 2000GPM @ 10Bar. and one jocky pump shall capable of
delivering 6.0 LPS, 120mtrs. head, on common base with interconnecting
pipe work, gate valves on suction and delivery side of each pump, NRV on
delivery side of each pump, pressure vessel of suitable capacity and
pressure, pressure switch, pressure guage, duplex control panel for the
automatic operation of above pumps on duty/standby basis. The supply will
include a diesel storage tank for 6 hrs continious operation. With HOA
switches. Run/trip lamps, for each pump, automatic changeover of starting
A Set 0 0 0 0 0 0 1 0 0 1
sequence after every start, autostart of standby pump in the event of failure
of duty pump, low level cut off by level etc.The rate to include the civil
works for foundation, pump & tank interconnection of puddle flange. As per
drawing provide gate valve in the delivery line & same line connected back
to fire tank related complete scope of work to be considered in the offer.
Fire Pumps shall be of either Horizontal Split Case Centrifugal type or End
Suction Centrifugal type, in accordance with NFPA 20 requirements,
specifically labeled or fire service,capable of delivering the duties required
by the fire protection system and suitable for the flooded suction (positive
suction) condition where the liquid to be pumped is above the centerline of
the pump suction flange.

A.1 Suction Side:

250dia OS & Y Gate valve -4Nos 0 0 0 0 0 0 4 0 0 4

50dia OS & Y Gate valve- 1no 0 0 0 0 0 0 1 0 0 1

A.2 Suction Side:

250dia OS & Y Gate valve-3Nos 0 0 0 0 0 0 3 0 0 3

50dia OS & Y Gate valve - 1no 0 0 0 0 0 0 1 0 0 1

250dia Check valve-2Nos 0 0 0 0 0 0 2 0 0 2

50dia Check valve - 1no 0 0 0 0 0 0 1 0 0 1

Semac and Partners L.L.C Fire fighting fire alarm Works M/s. EMDAD LOGISTICS SAOC
Page 146 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS
S.A.O.C
BILL OF ITEMS FIRE FIGHTING & FIRE ALARM WORK. BILL NO. 6

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS
ROOM
SL.
DESCRIPTION. UNIT QTY
NO.

A.3 Test Line;

200dia OS & Y Gate valve-3Nos 0 0 0 0 0 0 3 0 0 3

200dia Butterfly valve-1No 0 0 0 0 0 0 1 0 0 1

A.4 Pressure Sencing & Delivery Line;

1/2" Non return valve-6nos 0 0 0 0 0 0 6 0 0 6

Pressure Gauge - 1no. Etc 0 2 0 0 0 0 1 0 0 3

The motor and control panel shall be IP 55 classification. For Details refer
specification in Volume 2.
NOTE : The Motor should be UL listed and FM approved, the type of
construction shall be TEFC and ODP motor is not approved / accepted.
Diesel storage within the pump room shall comply to NFPA / ROPCD norms
and Diesle storage shall be for minimum 8 hours. The quote to be complete
with all the piping, valves and accessories within the pump room as per
NFPA 20 / ROPCD norms, vortex plate and Y strainer shall be provided at
the suction pipe.

SUB TOTAL TO SUMMARY

Semac and Partners L.L.C Fire fighting fire alarm Works M/s. EMDAD LOGISTICS SAOC
Page 147 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS
S.A.O.C
BILL OF ITEMS FIRE FIGHTING & FIRE ALARM WORK. BILL NO. 6

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS
ROOM
SL.
DESCRIPTION. UNIT QTY
NO.

4.0 OTHERS & AUTHORITY APPROVALS

Fire alarm and fire fighting works shall be carried in line with civil defense
requirements, the contractor shall appoint fire consultant to prepare detail design
4.1 before execution. Fire consultant to review/ approve MAS, Shop drawings
submitted by contractor before execution. if required MAS, Shop drawings taking
approval from civil defense part of contractor fire consultant scope.

During construction stage, if client any modification & changes done in the
4.2 architectural plan that drawing taking the ROP CD Re-approval 2 to 3 time against
the design, ROP CD approval prior to execution part of contractor scope.

As per civil defense requirement preparation of detail complete fire policy drawing,
schematic diagram, passive fire protection system drawing, Hydraulic calculation,
life safety drawing etc complete scope as per authority requirement preparation of
4.3 complete drawing part of contractor or contractor fire consultant scope and same
drawing obtain approval from ROP CD & obtain final inspection part of contractor
fire consultant scope. Accordingly consider complete scope as per NFPA
Standard, ROP CD requirement.

As per civil defense requirement during construction stage, Fire consultant to


conduct supervision at regular interval & check all the construction activity as per
4.4
authority requirement and submitting site visit report to client related complete
scope.

Contractor upon successful completion of fire fighting work shall get the installed
system inspected by fire consultant and witness the testing and commissioning
activity for obtaining final inspection and occupancy certificate from ROPCD. The
4.5 contractor shall also connect the system to the central monitory station of Security
and Fire Prevention Services and all costs towards this shall be included in the
quoted sum. Issuing project completion certificate & obtaining final occupancy
certificate from ROP CD part of project fire consultant scope.

NOTE: Note: As per ROP CD Requirement if any additional work if required &
same to be mention consider with including complete scope as per local
requirement.

SUB TOTAL TO SUMMARY

Semac and Partners L.L.C Fire fighting fire alarm Works M/s. EMDAD LOGISTICS SAOC
Page 148 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS
S.A.O.C
BILL OF ITEMS FIRE FIGHTING & FIRE ALARM WORK. BILL NO. 6

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS
ROOM
SL.
DESCRIPTION. UNIT QTY
NO.

5.0 MISCELLANEOUS
Supply, installation & Commissioning of PVC road crossing duct including all
5.1 related civil works like excavation, backfilling, concrete encasing etc. complete in
all respect.
a) 250mm dia Mtr 0 0 0 0 0 0 0 0 180 180
b) 200mm dia Mtr 0 0 0 0 0 0 0 0 0 0
c) 110mm dia Mtr 0 0 0 0 0 0 0 0 0 0
d) 50mm dia. Mtr 0 0 0 0 0 0 0 0 0 0

Providing Concrete Thrust Block for all the bends, Tee junction etc. as per the
5.2
external fire hydrant layout with incuding complete scope of work to be consider.
LS 1

5.3 Local Authority approval, ROP Inspection and Final Approvals etc,, LS 1

SUB TOTAL TO SUMMARY

Semac and Partners L.L.C Fire fighting fire alarm Works M/s. EMDAD LOGISTICS SAOC
Page 149 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS
S.A.O.C
BILL OF ITEMS FIRE FIGHTING & FIRE ALARM WORK. BILL NO. 6

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS
ROOM
SL.
DESCRIPTION. UNIT QTY
NO.

6.0 ITEMS

If in the opinion of the contractor there are some items not mentioned in the BOI,
6.1 the contractor must show them below and carry their sum to the summary items LS
not mentioned in the bill of quantities but specified in drawing.

Miscellaneous works, not identified above but required to make installation


complete for achieving fully functional fire fighting & fire alarm system etc. as per
6.2
project requirement & specifications (Contractor to list the activities and indicate
LS
the item wise price for the same in the respective column).

FM 200 system for LV Room as per External fire fighting drawing LS 0 0 0 0 0 0 0 0 1 1

Dia 300 GI Fire Pipe Mtr 0 0 0 0 0 0 30 0 0 30

Dia 300 Gate Valve Nos. 0 0 0 0 0 0 2 0 0 2

Flow meter Nos. 0 0 0 0 0 0 1 0 0 1

Dia 250 PRV Nos. 0 0 0 0 0 0 1 0 0 1

Dia 300 Anti-Vertex plate Nos. 0 0 0 0 0 0 2 0 0 2

Dia 15 SS Pipe Mtr 0 0 0 0 0 0 42 0 0 42

500 gallen Foam Bladder Tank Nos. 0 1 0 0 0 0 0 0 0 1

FM 200 system for Server Room In Office Building LS 0 0 1 0 0 0 0 0 0 1

SUB TOTAL TO SUMMARY

Semac and Partners L.L.C Fire fighting fire alarm Works M/s. EMDAD LOGISTICS SAOC
Page 150 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS
S.A.O.C
BILL OF ITEMS FIRE FIGHTING & FIRE ALARM WORK. BILL NO. 6

STORE HOUSE

T.X YARD & LV


FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
& AC PLANT

RECEPTION
TECHNICAL

EXTERNAL
BUILDING

BUILDING
LOGISTIC

SENTRY
OFFICE

STORE

POSTS
ROOM
SL.
DESCRIPTION. UNIT QTY
NO.

TOTAL COLLECTION BILL NO. 6

1 FIRE FIGHTING

2 FIRE ALARM SYSTEM.

3 FIRE PUMP

4 OTHERS & AUTHORITY APPROVALS

5 MISCELLANEOUS

6 ITEMS

NOTE: The contractor, upon successful completion of fire fighting work shall get
the installed system inspected and approved by Civil defense or civil defense
approved consultant. As per local standard obtaining final inspection and
occupancy certificate from civil defense Approved consultant / civil defense
related complete scope of work to be consider in the offer. The contractor shall
also connect the proposed fire alarm system to the central monitory station of
Security and Fire Prevention Services and all costs towards final inspection &
obtaining occupance certificate. this shall be included in the quoted sum.

TOTAL COLLECTION TO GENERAL SUMMARY

NOTE;

1 This is a lump sum tender

2 Items & quantities provided in this tender are purely indicative. Contractors to verify the drawings and quote accordingly.

Schedule of items in conjunction with drawings and specifications constitute complete tender. The renderers are responsible for all the quantities they consider necessary for the proper
submission of the tender in accordance with the conditions of contract, drawings and specification. In case the contractor/Tenderer notice any item missing in the BOQ he should include
3
the same in this quoted value and submit with the tender, a list of such items along with relevant specifications and quantities. No claims shall be entertained at a later stage for items not
listed in the schedule but mentioned in the drawings.

4 GRAND TOTAL is to include for items not included here but required to complete all works.

Semac and Partners L.L.C Fire fighting fire alarm Works M/s. EMDAD LOGISTICS SAOC
Page 151 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITMEMS: HVAC WORKS QUANTITY Bill No. 7

STORE HOUSE &

SENTRY POSTS
T.X YARD & LV
FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
RECEPTION
TECHNICAL
AC PLANT

BUILDING

BUILDING
LOGISTIC

OFFICE

STORE

ROOM
TOTAL
Sl. No. ITEM DESCRIPTION. UNIT
QUANTITY

AIR CONDITIONING & VENTILATION WORKS

Supply, Installation and Commissioning of Air Conditioning Unit


suitable for Cooling application. Unit compromising one indoor with
one out door unit, including fixing in position, refrigerant piping,
piping joint kits, vibration isolators, 19mm thick Armaflex insulation,
Condensate drain, Controls, Thermostat in same finish as the
adjacent electrical accessories, Sensors, Control Wiring, Conduits,
PVC Sleeves, Connections from nearest isolators/DB switches using
1.0 Conduits, Cora Cloth with 2 coats of vapour barrier, and if required
cable tray for exposed refrigerant pipes on roof and any other
accessories required for completion of installation, all complete as
per Specifications. Contractor to consider measurement of refrigerant
piping between indoor & outdoor based on its locations. further there
will not be any variation provided. All outdoor units condensing coils,
ODU supports, accessories, cover, etc shall be provided with local
anti-corrosive coating with 5 years warrantee.

1.1 Wall Mounted Type 1.0 TR 0 0 0 0 1 0 0 2 3 SET

1.2 Wall Mounted Type 1.5 TR 1 1 0 0 0 0 0 0 2 SET

1.3 Wall Mounted Type 2.0 TR 0 0 1 0 0 2 0 0 3 SET

1.4 Wall Mounted Type 2.5 TR 0 0 0 0 1 0 0 0 1 SET

1.5 Wall Mounted Type 3.0 TR 0 0 0 0 0 0 0 0 0 SET

M/s SEMAC Partners L.L.C. 151 of 172 M/s. EMDAD LOGISTICS SAOC
Page 152 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITMEMS: HVAC WORKS QUANTITY Bill No. 7

STORE HOUSE &

SENTRY POSTS
T.X YARD & LV
FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
RECEPTION
TECHNICAL
AC PLANT

BUILDING

BUILDING
LOGISTIC

OFFICE

STORE

ROOM
TOTAL
Sl. No. ITEM DESCRIPTION. UNIT
QUANTITY

AIR CONDITIONING & VENTILATION WORKS

1.6 Cassette Type 1.0 TR 0 0 0 0 0 0 0 0 0 SET

1.7 Cassette Type 1.5 TR 0 0 0 0 0 0 0 0 0 SET

1.8 Cassette Type 2.0 TR 0 0 0 0 0 0 0 0 0 SET

1.9 Cassette Type 2.5 TR 0 0 0 0 0 0 0 0 0 SET

1.10 Cassette Type 3.0 TR 0 0 0 0 0 0 0 0 0 SET

1.11 Cassette Type 4.0 TR 0 0 0 0 0 0 0 0 0 SET

M/s SEMAC Partners L.L.C. 152 of 172 M/s. EMDAD LOGISTICS SAOC
Page 153 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITMEMS: HVAC WORKS QUANTITY Bill No. 7

STORE HOUSE &

SENTRY POSTS
T.X YARD & LV
FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
RECEPTION
TECHNICAL
AC PLANT

BUILDING

BUILDING
LOGISTIC

OFFICE

STORE

ROOM
TOTAL
Sl. No. ITEM DESCRIPTION. UNIT
QUANTITY

AIR CONDITIONING & VENTILATION WORKS

VARIABLE REFRIGERANT SYSTEM (R410A):


Supply, Installation and Commissioning of Variable Refrigerant
System. Air conditioning unit comprising different type Indoor units
with 1No. all Inverter Driven Outdoor Unit/module installed on floor/
roof, including fixing in position, refrigerant hard drawn piping, piping
joint kits, vibration isolators, 19mm thick Armaflex insulation for entire
piping with cora cloth & 2 coats of vapor barrier, cable tray for
2.0 refrigerant piping, Condensate drain, Controls, cordless thermostat in
same finish as the adjacent electrical accessories, Sensors, Control
Wiring, Conduits, PVC Sleeves, Connections from nearest
isolators/DB switches using Conduits, cable tray for entire refrigerant
pipes and any other accessories required for completion of
installation, all complete as per Specifications. All outdoor units
condensing coils, ODU supports, accessories, cover, etc shall be
provided with local anti-corrosive coating with 5 years warrantee.

VRV Indoor Units

2.1 Cassette type 1.0 TR 0 0 6 0 0 0 0 0 6 Nos.

2.2 Cassette Type 1.5 TR 0 0 12 0 0 0 0 0 12 Nos.

2.3 Cassette Type 2.0 TR 0 0 28 0 0 0 0 0 28 Nos.

M/s SEMAC Partners L.L.C. 153 of 172 M/s. EMDAD LOGISTICS SAOC
Page 154 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITMEMS: HVAC WORKS QUANTITY Bill No. 7

STORE HOUSE &

SENTRY POSTS
T.X YARD & LV
FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
RECEPTION
TECHNICAL
AC PLANT

BUILDING

BUILDING
LOGISTIC

OFFICE

STORE

ROOM
TOTAL
Sl. No. ITEM DESCRIPTION. UNIT
QUANTITY

AIR CONDITIONING & VENTILATION WORKS

2.4 Cassette Type 2.5 TR 0 0 0 0 0 0 0 0 0 Nos.

2.5 Cassette Type 3.0 TR 0 0 1 0 0 0 0 0 1 Nos.

2.6 Cassette Type 4.0 TR 0 0 2 0 0 0 0 0 2 Nos.

2.7 Ducted Type 8.0 TR 0 0 1 0 0 0 0 0 1 Nos.

M/s SEMAC Partners L.L.C. 154 of 172 M/s. EMDAD LOGISTICS SAOC
Page 155 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITMEMS: HVAC WORKS QUANTITY Bill No. 7

STORE HOUSE &

SENTRY POSTS
T.X YARD & LV
FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
RECEPTION
TECHNICAL
AC PLANT

BUILDING

BUILDING
LOGISTIC

OFFICE

STORE

ROOM
TOTAL
Sl. No. ITEM DESCRIPTION. UNIT
QUANTITY

AIR CONDITIONING & VENTILATION WORKS

3.0 VRV outdoor Units

3.1 Out door Unit GF-ODU-01 - 21.0 TR 0 0 1 0 0 0 0 0 1 SET

3.2 Out door Unit GF-ODU-02 - 18.0 TR 0 0 1 0 0 0 0 0 1 SET

3.3 Out door Unit FF-ODU-01 - 27.5 TR 0 0 1 0 0 0 0 0 1 SET

3.4 Out door Unit FF-ODU-01 - 30.5 TR 0 0 1 0 0 0 0 0 1 SET

FAHU with Air cooled condensing unit (R410A/R134A):


Supply, Installation and Commissioning of double skin treated fresh
air handling unit with matching capacity condensing unit. Complete
with refrigerant hard drawn copper piping, 25 mm thick Armaflex
rubber insulation, covered with cora cloth, vapor barrier. Drain piping
4.0 up to nearest drain point. Refrigerant piping shall include all
accessories like Expansion valve, solenoid valve, shut off valve, sight
glass, filter dryer, NRV etc. Below given capacities are at 40/28
db/wb deg C ambient. All outdoor units condensing coils, ODU
supports, accessories, cover, etc shall be provided with local anti-
corrosive coating with 5 years warrantee.

FAHU-1, supply air 1055 lps with matching capacity Condensing unit
4.1 15.0 TR cooling capacity. On coil temperature 40/28 db/wb deg C, 0 0 1 0 0 0 0 0 1 SET
Off Coil temperature 17.5/17.2 db/wb deg C

M/s SEMAC Partners L.L.C. 155 of 172 M/s. EMDAD LOGISTICS SAOC
Page 156 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITMEMS: HVAC WORKS QUANTITY Bill No. 7

STORE HOUSE &

SENTRY POSTS
T.X YARD & LV
FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
RECEPTION
TECHNICAL
AC PLANT

BUILDING

BUILDING
LOGISTIC

OFFICE

STORE

ROOM
TOTAL
Sl. No. ITEM DESCRIPTION. UNIT
QUANTITY

AIR CONDITIONING & VENTILATION WORKS

Design Supply, Install, testing & commissioning of MCC starter panel


with VFD starter & bypass starter arrangement, DDC controller with
peripheral control devices like thermostat, differential pressure
switches across pre filter, bag filter, fan section, fresh air & supply air
temperature sensors, return air temperature sensors, smoke sensors
etc. Control & power cabling for panel to all AHU motors, peripheral
devices etc. DDC controller shall be suitable for fully automatic, time
scheduled operation of FAHU & Condensing unit.

4.2 MCC starter cum DDC combined control panel for FAHU-1 0 0 1 0 0 0 0 0 1 SET

Package Air Conditioning Unit:


Supply, Installation and Commissioning of Roof top air cooled
package air conditioning unit, operating with R410a refrigerant gases
per specified in specification & equipment schedule including
5 Condensate drain, Controls, Thermostat, duct sensor, Control Wiring,
Conduits, PVC Sleeves, fresh air louvers, Connections from nearest
isolators/DB switches using Conduits etc. All outdoor units evaporator
coils, condensing coils, ODU supports, accessories, cover, etc shall
be provided with local anti-corrosive coating with 5 years warrantee.

M/s SEMAC Partners L.L.C. 156 of 172 M/s. EMDAD LOGISTICS SAOC
Page 157 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITMEMS: HVAC WORKS QUANTITY Bill No. 7

STORE HOUSE &

SENTRY POSTS
T.X YARD & LV
FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
RECEPTION
TECHNICAL
AC PLANT

BUILDING

BUILDING
LOGISTIC

OFFICE

STORE

ROOM
TOTAL
Sl. No. ITEM DESCRIPTION. UNIT
QUANTITY

AIR CONDITIONING & VENTILATION WORKS

Package air conditioning unit Total Cooling capacity - 21.2 TR,


5.1 Sensible cooling capacity - 14.3 TR, Supply air flow - 3700 lps. Fresh 2 0 0 0 0 0 0 0 2 SET
Air - 370 lps.

Supply, install, testing & commissioning of Air Curtain, Heavy duty,


6.0 suitable for commercial building, high air flow, high speed, with swing
door / glass sliding door control switch.

6.1 Door width 2000mm, door height 2500 mm. for Office building 0 0 1 0 0 0 0 0 1 Nos.

M/s SEMAC Partners L.L.C. 157 of 172 M/s. EMDAD LOGISTICS SAOC
Page 158 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITMEMS: HVAC WORKS QUANTITY Bill No. 7

STORE HOUSE &

SENTRY POSTS
T.X YARD & LV
FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
RECEPTION
TECHNICAL
AC PLANT

BUILDING

BUILDING
LOGISTIC

OFFICE

STORE

ROOM
TOTAL
Sl. No. ITEM DESCRIPTION. UNIT
QUANTITY

AIR CONDITIONING & VENTILATION WORKS

Supply, Install, testing & Commissioning of Wall/Glass mounted Toilet


or Pantry extract fans as shown in drawing. Extract fans with Built-in
silent action electro-thermal shutter cassette, Shadow grey external
7.0 grille for unobtrusive external appearance, Easy clean high gloss
ABS housing with integral finger safety guard, IPX4 rated motor,
Suitable for single and sealed double glazing windows and panels up
to 25mm.

7.1 Capacity 50 LPS 1 3 20 0 2 0 0 2 28 Nos.

7.2 Capacity 100 LPS 0 0 0 0 0 0 0 0 0 Nos.

Supply, Install, testing & Commissioning of Duct Inline Extract fans


7.0 as shown in drawing. Refer detailed project particular specifications.
Refer detailed project particular specifications.

7.1 1000 LPS at 150 Pa 0 0 0 0 0 0 1 0 1 Nos.

7.1 50 LPS at 100 Pa 0 1 0 0 0 0 0 0 1 Nos.

M/s SEMAC Partners L.L.C. 158 of 172 M/s. EMDAD LOGISTICS SAOC
Page 159 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITMEMS: HVAC WORKS QUANTITY Bill No. 7

STORE HOUSE &

SENTRY POSTS
T.X YARD & LV
FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
RECEPTION
TECHNICAL
AC PLANT

BUILDING

BUILDING
LOGISTIC

OFFICE

STORE

ROOM
TOTAL
Sl. No. ITEM DESCRIPTION. UNIT
QUANTITY

AIR CONDITIONING & VENTILATION WORKS

Supply, Install, testing & Commissioning of Wall mounted or Plate


mounted industrial extract fans as shown in drawings including
Supporting frame, roof curb or installation frame with wide shaped
inlet in corrosion proof material or protected against the atmospheric
agents, Motor support and safety grid, in steel rod manufactured in
accordance with UNI EN 294. Impeller with high efficiency airfoil
blades in plastic material and hub in die cast aluminum alloy. Variable
8.0
pitch angle in still position. Balancing according to UNI ISO 1940.
Asynchronous electric motor three phase, 6 or 8 pole, protection IP
55, class F insulated, construction according to IEC / EEC (UNEL-
MEC) standards. Shutter gravity, Impeller side protection grid to be
provided for wall mounted fans. Noise level shall not be more than 58
dB(A) from 3 meter. Motor shall be suitable for continuous operation
of 60 deg C. Refer detailed project particular specifications.

8.1 625 LPS @ 50 Pa. 0 0 0 2 0 0 0 0 2 Nos.

M/s SEMAC Partners L.L.C. 159 of 172 M/s. EMDAD LOGISTICS SAOC
Page 160 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITMEMS: HVAC WORKS QUANTITY Bill No. 7

STORE HOUSE &

SENTRY POSTS
T.X YARD & LV
FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
RECEPTION
TECHNICAL
AC PLANT

BUILDING

BUILDING
LOGISTIC

OFFICE

STORE

ROOM
TOTAL
Sl. No. ITEM DESCRIPTION. UNIT
QUANTITY

AIR CONDITIONING & VENTILATION WORKS

Supply & installation of Roof mounted Turbine Wind Ventilator


complete with roof curb to matching roof sheeting profile. Turbine
Diameter: 760mm, Neck/Throat Diameter: 610mm, Vanes
(Blades) :42 Vanes, Height: 460mm + curb height, Base Ring MOC
(Mounting Ring) : Stainless Steel 430, Top Plate :MOC Aluminium
Thickness 1.2mm Alloy 8011 H2, Vanes MOC :Aluminium Thickness
0.5mm Alloy 8011 H2, Rotation :Twin Sealed 6000ZZ bearings and
9.0 self lubricating bush of DuPont Zytel 101L Polyamide 66 resin to 76 96 0 0 0 0 0 0 172 Nos.
ensure frictionless rotation even at lowest wind velocity, Center Shaft:
Stainless Steel 12mm Ø Inner Arms: M.S. with Powder Coating*
Outer Arms: Stainless Steel Center Pipe M.S. with electro zinc plating
Nett.
Wind Velocity & capacity :- 04 Kmh - 700 LPS- 1485 CFM
08 Kmh - 920 LPS- 1950 CFM
12 Kmh -1500LPS- 3178 CFM

M/s SEMAC Partners L.L.C. 160 of 172 M/s. EMDAD LOGISTICS SAOC
Page 161 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITMEMS: HVAC WORKS QUANTITY Bill No. 7

STORE HOUSE &

SENTRY POSTS
T.X YARD & LV
FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
RECEPTION
TECHNICAL
AC PLANT

BUILDING

BUILDING
LOGISTIC

OFFICE

STORE

ROOM
TOTAL
Sl. No. ITEM DESCRIPTION. UNIT
QUANTITY

AIR CONDITIONING & VENTILATION WORKS

OPTIONAL ITEM. Client will decide to procure. Provide only Unit


10.0
rate.

Ceiling mounted HELI FAN, blade diameter - 24 feet, 6- nos airfoil


blades made from extruded anodized aluminum. maximum
displacement forward 346000 cfm, maximum thrust foreword - 375 n.
variable speed (1-64 rpm) 1.55kw, 3-ph, 50 Hzs. hanging weight- 250
kgs, maximum sound level-55 dBA. motor shall be sensor less,
3 4 0 0 0 0 0 0 7 Sets
brushless, permanent, magnet, transverse flux dc motor. nfpa
complaint, ip66 with digital touch pad controller. warranty - 50000
operation hours. ( vendor shall confirm the final design considering
building dimension & installation height 10 meter from f.f.l )
Total Quantity - 7 Numbers.

Supply, Erection and testing of GI air conditioning & extract air


ductwork including plenum boxes with insulation, cladding, supports,
11.0
connection to extract fans, AHUs. Ductwork shall be according to
SMACNA/DW144 standard.

GI air conditioning external ductwork with 50 mm thick fiberglass rigid


11.1 board insulation covered with cora cloth, 2 coats of vapor barrier & 170 0 30 0 0 0 0 0 200 SQMT.
0.6 mm thick embossed aluminum cladding

M/s SEMAC Partners L.L.C. 161 of 172 M/s. EMDAD LOGISTICS SAOC
Page 162 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITMEMS: HVAC WORKS QUANTITY Bill No. 7

STORE HOUSE &

SENTRY POSTS
T.X YARD & LV
FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
RECEPTION
TECHNICAL
AC PLANT

BUILDING

BUILDING
LOGISTIC

OFFICE

STORE

ROOM
TOTAL
Sl. No. ITEM DESCRIPTION. UNIT
QUANTITY

AIR CONDITIONING & VENTILATION WORKS

GI air conditioning internal ductwork with 25 mm thick fiberglass rigid


11.2 210 0 310 0 0 0 0 0 520 SQMT.
board insulation covered with cora cloth, 2 coats of vapor barrier.

GI toilet extract & general ventilation ductwork with 25 mm thick


11.3 fiberglass rigid board insulation covered with cora cloth, 2 coats of 0 7 0 0 0 0 28 0 35 SQMT.
vapor barrier.

11.4 Supply air diffuser 300x300 0 0 0 0 0 0 0 0 0 Nos.

M/s SEMAC Partners L.L.C. 162 of 172 M/s. EMDAD LOGISTICS SAOC
Page 163 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITMEMS: HVAC WORKS QUANTITY Bill No. 7

STORE HOUSE &

SENTRY POSTS
T.X YARD & LV
FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
RECEPTION
TECHNICAL
AC PLANT

BUILDING

BUILDING
LOGISTIC

OFFICE

STORE

ROOM
TOTAL
Sl. No. ITEM DESCRIPTION. UNIT
QUANTITY

AIR CONDITIONING & VENTILATION WORKS

11.5 Return air diffuser 300x300 0 0 0 0 0 0 0 0 0 Nos.

11.6 Supply air diffuser 225x225 0 0 0 0 0 0 0 0 0 Nos.

11.7 Return air diffuser 225x225 0 0 0 0 0 0 0 0 0 Nos.

11.8 Supply air diffuser 150x150 0 0 54 0 0 0 0 0 54 Nos.

11.9 Extract air diffusers 150x150 0 1 0 0 0 0 0 0 1 Nos.

11.10 Supply air jet nozzles - Dia 250 mm 0 0 8 0 0 0 0 0 8 Nos.

11.11 Return air continuous grill 200 mm high x 6000 mm long 0 0 2 0 0 0 0 0 2 Nos.

11.12 Return air grills 500 x 200 mm 0 0 0 0 0 0 5 0 5 Nos.

11.13 VCD 500 x 200 0 0 0 0 0 0 5 0 5 Nos.

11.14 VCD dia 250 mm 0 1 0 0 0 0 0 0 1 Nos.

11.15 VCD 200 x 100 0 0 54 0 0 0 0 0 54 Nos.

11.16 VCD 400 x 250 0 0 10 0 0 0 0 0 10 Nos.

11.17 Fusible Link Fire damper for duct entering from shaft 400x250 0 0 0 0 0 0 0 0 0 Nos.

11.18 Fusible Link Fire damper for duct entering from shaft 1200x900 4 0 0 0 0 0 0 0 4 Nos.

M/s SEMAC Partners L.L.C. 163 of 172 M/s. EMDAD LOGISTICS SAOC
Page 164 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITMEMS: HVAC WORKS QUANTITY Bill No. 7

STORE HOUSE &

SENTRY POSTS
T.X YARD & LV
FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
RECEPTION
TECHNICAL
AC PLANT

BUILDING

BUILDING
LOGISTIC

OFFICE

STORE

ROOM
TOTAL
Sl. No. ITEM DESCRIPTION. UNIT
QUANTITY

AIR CONDITIONING & VENTILATION WORKS

Fresh air Sand trap louver with G3 grade synthetic fibre filter 1800 x
11.19 0 0 1 0 0 0 0 0 1 Nos.
1800 mm

Fresh air Sand trap louver with G3 grade synthetic fibre filter 1200 x
11.20 0 0 0 2 0 0 1 0 3 Nos.
1200 mm

Fresh air Sand trap louver with G3 grade synthetic fibre filter 2000 x
11.21 19 23 0 0 0 0 0 0 42 Nos.
2000 mm

11.22 Extract air louver 500 x 500 mm 0 1 0 0 0 0 1 0 2 Nos.

M/s SEMAC Partners L.L.C. 164 of 172 M/s. EMDAD LOGISTICS SAOC
Page 165 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITMEMS: HVAC WORKS QUANTITY Bill No. 7

STORE HOUSE &

SENTRY POSTS
T.X YARD & LV
FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
RECEPTION
TECHNICAL
AC PLANT

BUILDING

BUILDING
LOGISTIC

OFFICE

STORE

ROOM
TOTAL
Sl. No. ITEM DESCRIPTION. UNIT
QUANTITY

AIR CONDITIONING & VENTILATION WORKS

Supply, installation & commissioning of tailor made fabric ducting:


Fabric Duct Air Dispersion System shall be : a. Composition: 100%
polyester endless fibers (multifilament) with inwrought carbonic fibre
(less than 1%), b. Properties: fire resistant, antimicrobial,
antibacterial (EN ISO 20645) suitable for clean rooms - class No. 4
(EN ISO 14644-1) antistatic, washable in washing-machine, c.
Weight: 220 g/m² (EN12127), d. Thickness: 0.3mm (EN ISO 5084), e.
Weave: Plain (DIN 61101-1), f. Sett of fabric 10 cm: 540/310 (EN
1049-2), g. Strength warp/weft: 1880/1090N (EN ISO 13934-1), h.
Permeability: 38m³/hr/m² by 120 Pa, i. Fire resistance: B-s1, d0
ANSI/UL 723 Classified, j. Temperature resistance: -60 ⁰C to +110 ⁰C,
k. Washing shrinkage: 0.5/0.5% (EN ISO 6330-2000, wrap/weft,
40⁰C). Necessary air control devices, beat absorber & fabric pocket
to be provided. Two row cable Installation system with hooks located
at 3 and 9 o’clock on Fabric duct system. Hardware to include cable,
cable clamps, turnbuckles, and tie down straps as required. Support
hangers spaced at 5000mm. Provided sizes on tender drawing are
tentative only.

11.23 Fabric Duct Air Dispersion System for Package unit 1 1 0 0 0 0 0 0 0 1 Set

11.24 Fabric Duct Air Dispersion System for Package unit 2 1 0 0 0 0 0 0 0 1 Set

M/s SEMAC Partners L.L.C. 165 of 172 M/s. EMDAD LOGISTICS SAOC
Page 166 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITMEMS: HVAC WORKS QUANTITY Bill No. 7

STORE HOUSE &

SENTRY POSTS
T.X YARD & LV
FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
RECEPTION
TECHNICAL
AC PLANT

BUILDING

BUILDING
LOGISTIC

OFFICE

STORE

ROOM
TOTAL
Sl. No. ITEM DESCRIPTION. UNIT
QUANTITY

AIR CONDITIONING & VENTILATION WORKS

Condensate drain piping with insulation complete associated with all


12.0 Indoor units, FCU's, etc., including insulation wherever required up to
nearest floor drain/soak pit/other drainage services.

12.1 25mm diameter UPVC class 'E' pipe including fittings 10 10 325 0 20 20 0 20 405 Mtr.

12.2 32mm diameter UPVC class 'E' pipe including fittings 0 0 45 0 0 0 0 0 45 Mtr.

12.3 40mm diameter UPVC class 'E' pipe including fittings 0 0 0 0 0 0 0 0 0 Mtr.

12.4 50mm diameter UPVC class 'E' pipe including fittings 0 0 40 0 0 0 0 0 40 Mtr.

M/s SEMAC Partners L.L.C. 166 of 172 M/s. EMDAD LOGISTICS SAOC
Page 167 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITMEMS: HVAC WORKS QUANTITY Bill No. 7

STORE HOUSE &

SENTRY POSTS
T.X YARD & LV
FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
RECEPTION
TECHNICAL
AC PLANT

BUILDING

BUILDING
LOGISTIC

OFFICE

STORE

ROOM
TOTAL
Sl. No. ITEM DESCRIPTION. UNIT
QUANTITY

AIR CONDITIONING & VENTILATION WORKS

13.0 Sundries and Testing & Commissioning

Carry out pressure testing of refrigerant copper piping at 580 PSI for
13.1 24 hours holding time period with client or consultant eye witness (If 1 Lot
there is No joint/brazing on piping Pressure test not required).

Carry out Flushing, and Vacuuming of refrigerant copper piping up to


13.2 1 Lot
500 micron gauge

Carry out additional refrigerant gas charging in refrigerant piping


13.3 1 Lot
circuit.

Allow for setting out the work and marking & making positions of all
13.4 1 Lot
holes, mortises, wall chases, foundations and the like builders work.

Provide builders works drawings in connection with the HVAC


13.5 equipment Installations, condensing unit foundations, wall opening & 1 Lot
closing etc. Foundation sizes to be as per final approved equipments.

M/s SEMAC Partners L.L.C. 167 of 172 M/s. EMDAD LOGISTICS SAOC
Page 168 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITMEMS: HVAC WORKS QUANTITY Bill No. 7

STORE HOUSE &

SENTRY POSTS
T.X YARD & LV
FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
RECEPTION
TECHNICAL
AC PLANT

BUILDING

BUILDING
LOGISTIC

OFFICE

STORE

ROOM
TOTAL
Sl. No. ITEM DESCRIPTION. UNIT
QUANTITY

AIR CONDITIONING & VENTILATION WORKS

Closing all wall & slab opening with fire sealant approved by
13.6 1 Lot
consultant & client

Providing refrigerant piping sleeves, drainage sleeves, necessary


13.7 1 Lot
soak way pits etc.

Allow for Identification labels, plates, charts, and identification of


13.8 1 Lot
plants, equipment pipe work, ductwork, controls and the like.

M/s SEMAC Partners L.L.C. 168 of 172 M/s. EMDAD LOGISTICS SAOC
Page 169 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITMEMS: HVAC WORKS QUANTITY Bill No. 7

STORE HOUSE &

SENTRY POSTS
T.X YARD & LV
FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
RECEPTION
TECHNICAL
AC PLANT

BUILDING

BUILDING
LOGISTIC

OFFICE

STORE

ROOM
TOTAL
Sl. No. ITEM DESCRIPTION. UNIT
QUANTITY

AIR CONDITIONING & VENTILATION WORKS

Allow final electrical connection from nearest isolator to units. Allow


13.9 for earthing bonding to all items of pipe work, fittings and fixtures, 1 Lot
control panels, etc

Allow for providing working drawing, As-built drawings, O&M manual,


13.10 1 Lot
Material Approval request, etc.

Allow for co-ordination with other engineering installations, setting


13.11 out, cutting or forming holes, mortises, chases or the like and making 1 Lot
good finishing

Based on tender drawing, contractor shall verify the quantity for all
13.12 HVAC works & consider any missed out quantity or item in his scope 1 Lot
of works, further any variation will not be provided.

1200X900 Bell Mouth with wire mesh 2 0 0 0 0 0 0 0 2 Nos.

Condensate Drain Soak pit 0 0 0 0 0 1 0 0 1 Nos.

300x150 Supply Grill 0 0 1 0 0 0 0 0 1 Nos.

650x300 VCD 0 0 1 0 0 0 0 0 1 Nos.

M/s SEMAC Partners L.L.C. 169 of 172 M/s. EMDAD LOGISTICS SAOC
Page 170 of 172

DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD LOGISTICS S.A.O.C

BILL OF ITMEMS: HVAC WORKS QUANTITY Bill No. 7

STORE HOUSE &

SENTRY POSTS
T.X YARD & LV
FACILITY CUM
HELI HANGER

HAZARDOUS

PUMP ROOM
RECEPTION
TECHNICAL
AC PLANT

BUILDING

BUILDING
LOGISTIC

OFFICE

STORE

ROOM
TOTAL
Sl. No. ITEM DESCRIPTION. UNIT
QUANTITY

AIR CONDITIONING & VENTILATION WORKS

TO COLLECTION

M/s SEMAC Partners L.L.C. 170 of 172 M/s. EMDAD LOGISTICS SAOC
DESIGN & BUILD OF CIVIL, STRUCTURAL STEEL & MEP WORKS FOR PROPOSED WAREHOUSE FACILITY AT DUQM FOR M/S EMDAD
LOGISTICS S.A.O.C

TOTAL UNIT
SL NO ITEM DESCRIPTION UNIT
QUANTITY RATE

OPTIONAL PRICES

Optional price for Full time Manpower availablity at site during the Defective Liability Period (
1 such as Plumber, Electrician, Carpenter, HVAC technicians etc) to attend the Maintenance Year
works

Optional price for Full time Manpower availablity at site after the Defective Liability Period
2 ( such as Plumber, Electrician, Carpenter, HVAC technicians etc) to attend the Maintenance Year
works at the facility.(AMC)

3 Optional Price for Soil Investigation works Item

4 Optional Price for Detailded Design of Architectural, Structural, MEP, HVAC & Utility works Item

5 Optional Price for Detailded Design of Landscaping works Item

Add: VAT 5 %

M/s SEMAC Partners L.L.C. 171 of 172 M/s. EMDAD LOGISTICS SAOC
GRAND SUMMARY OF CONTRACT VALUE

BILL
DESCRIPTION
NO

1 PRELIMINARIES & GENERAL REQUIREMENTS

2 CIVIL WORKS

3 STRUCTURAL STEEL WORKS

4 ELECTRICAL WORKS

5 PLUMBING WORKS

6 FIRE FIGHTING WORKS

7 HVAC

TOTAL CONTRACT VALUE

Less: Discount Value vide letter ref: AHC/TEN/0087/22


dated 09.08.2022 (PTC-3)

Less: Additional Discount Value

NET CONTRACT VALUE

ADD VAT 5%

TOTAL CONTRACT VALUE INCLUDING VAT

8 OPTIONAL PRICE