Project Prioritization Matrix Calculator
Project Prioritization Matrix Calculator
Project Prioritization Matrix Calculator
com
Importance to Customer
Success Factor
Project Priority 0 0 0 0 0 0
Calculate
Tip: The highest score indicates the Project with the highest Priority.
www.sai-global.com
v1.1
Help
Here is an example from SAI Global Assurance Services' Introducing Six Sigma Course: In the example provided, an organisation has identified four potential projects.
Weighting:
6 Categories
Project Name 1. Customer Database 2. Phone System 3. Delivery Process 4. Staff Training
Importance to Customer 1 3 5 4
Financial Return 2 3 4 3
Cost to Implement 5 4 3 3
Success Factor 3 3 4 2
Further information regarding this and other Six Sigma topics are covered in the SAI Global Assurance Services' Champion, Green Belt and Black Belt Six Sigma Programs. www.sai-global.com
Project Priority 23 37 57 36
In many cases, organisations use a prioritisation tool to help select the Six Sigma projects that are to be worked on. The complexity and approach for these tools will vary for each organisation however they essentially follow the principles of risk management. How the Project Prioritisation Matrix calculates the Project Priority is quite simple. The formula applied is as follows:
Project Priority = Category 1 (weighting x ranking) + Category 2 (weighting x ranking) Category 3 (weighting x ranking) + Category 4 (weighting x ranking)
You will notice that Category 3 (Cost to Implement) is subtracted from the Project Priority whilst the other Categories are added to the Project Priority. This balances the final priority against the Financial Return Category. If the Financial Retur is low and the Cost to Implement high, the Project Priority will be low regardless of the Importance to the Customer and the Success Factor. This highlights one of the critical features of a Six Sigma project, it must have a positive impact on the bottom line.
Example
www.sai-global.com
Sigma projects that are to be worked on. The wever they essentially follow the principles of
Project Priority whilst the other Categories are ancial Return Category. If the Financial Return dless of the Importance to the Customer and ma project, it must have a positive impact on