RFP Toll
RFP Toll
RFP Toll
Project Name- Four Laning of Hospet-Chitradurga Section of NH-50 from Chainage 299+000
to Km 418+750 in the State of Karnataka (Length 120 KMs) on DBFOT (Toll) Mode under
NHDP Phase- III
S.N. Description
Hampi Expressways Private Limited is a SPV formed by TRIL Roads Pvt limited and Concessionaire
for operation and maintenance of 120 KM section of Hospet to Chitradurga of National Highway No-
50 in the state of Karnataka.
We hereby invite Bid for Migration of Toll Management System as per URS and Project details
provided below-
Sr.
Item Description Particulars
No.
1. Hampi Expressways Pvt. Ltd. (“Client”) and the Contractor (“Bidder”) with
Parties its registered office at __________.
Contractor to carry out the Design, Supply, Installation and Maintenance
(under DLP for 03 Years) of Toll management system required for TMS
Migration as per the scope of work, Standards and Specifications.
2. Scope of Work
Contractor needs to propose the BOQ with maximum possible extent of
utilizing existing equipments and components.
The Contract Price shall be inclusive of all taxes, Insurance, duties etc. as
per detailed BOQ attached herewith for Project Scope for the Installation
3. Contract price and Defects Liability Period (DLP) of 36 Months from the date of
Completion Certificate. The Client shall have no liability for corporate or
personal income taxes or other taxes.
The Rates quoted in the BOQ should be inclusive of Design, FAT, SAT,
labour, material, machinery, transportation, licenses, taxes, duties etc.
4. Rates
Labour welfare Cess and Insurance, fulfillment of statutory requirements
and all applicable permits and licenses for entire tenure of the project.
Measurement The actual executed works shall be measured jointly by the Contractor
5. and representative of the Client. The quantity for payment shall be arrived
based on actual work executed.
The Works must be completed within 02 months from the date of issue of
LOI as per given Milestones.
The Contractor, at his option, can substitute the Retention Money with an
15. Retention Money
equivalent Bank Guarantee and the validity of such BGs shall be till the
end of the Defects Liability Period.
Client shall provide Contractor written notice notifying the default and
its intention of exercising back charges provision of the contract.
Contractor shall promptly take action to remedy the cause not later than
07 days from receiving notice. Failure of contractor to take action within
15 days of receiving notice to the satisfaction of client will entitle client
to initiate back charge against Contractor for getting the work done or
cost incurred to remedy these or any other Contractor defaults, errors,
21. Backcharges omissions or failures to perform or observe any part of this contract.
Further the limitation of liability for this clause of the Contractor shall be
1.15 times the Contract value . For avoidance of doubt, it is clarified that
these backcharges are in addition to all the other charges client is
entitled to under this contract including liquidated damages.
The Toll System will be provided, supplied, integrated, and tested by the Contractor according to the
provisions of Hybrid ETC Supplementary Agreement’ provisions set forth and scope of work as
mentioned below-
1. Health check-up of existing TMS system and proposal of replacement of Software, equipment and
components with maximum possible extent of utilizing existing TMS equipment and components.
2. Supply and Installation of required Toll System’s Hardware and Software with
Categorization/Classification System, lane components and peripherals, Drivers and third-party
software as per standard and specifications of HES Supplementary Agreement.
3. The Tolling system will be installed with Hybrid ETC lane functionality as per defined guidelines of
NHAI. Hybrid ETC System’s SLA agreement (Standard SLA for all the concessionaires) is signed
between NHAI and Concessionaires so contractor must maintain the uptime defined under the SLA.
4. ETC transactions files transfer to CCH to be done within the prescribed time limit by CCH and in
accordance with latest defined timeline.
5. Migration of old Database, transactions and reports with new Server without any data loss.
6. Contractor will ensure that there is no revenue loss to the Client during the execution phase.
Payment Terms :
Note- The deferred payment of Rs. 10,00,000 would be released on quarterly basis at Rs 2.5
lacs/quarter, after SAT on fulfillment of following conditions-
1. Overall AVC accuracy for the quarter should be above 98% (including non-standard vehicles).
2. Overall system uptime for the quarter should be above 99.5%.