Seat No.: ________ Enrolment No.

___________

GUJARAT TECHNOLOGICAL UNIVERSITY


BE- SEMESTER–VII (NEW) EXAMINATION – WINTER 2020
Subject Code:2170901 Date:25/01/2021
Subject Name:Inter Connected Power System
Time:10:30 AM TO 12:30 PM Total Marks: 56
Instructions:
1. Attempt any FOUR questions out of EIGHT questions.
2. Make suitable assumptions wherever necessary.
3. Figures to the right indicate full marks.
MARKS

Q.1 (a) State the purpose of load flow study. What information is available from load 03
flow study?
(b) In a power system consisting of two generating stations the incremental costs 04
in Rs/MWh are IC1 = 0.15P1 + 35, IC2 = 0.20P2 + 28. The plant supplies a
load of 150 MW. Neglecting losses determine the most economical division
of load.
(c) From the first principles, derive the swing equation for synchronous machine 07

Q.2 (a) What is meant by interconnected power system? State its advantages 03
(b) Discuss flat frequency method for frequency control 04
(c) For a 3-bus system, the line impedances in p.u. are given below 07
Line (bus to bus) Impedance
1-2 0.06 + j0.18
1-3 0.03 + j0.09
2-3 0.08 + j0.24
Determine YBUS matrix

Q.3 (a) Is FDLF method superior to NR method of load flow? Comment. 03


(b) A power system has two generating stations and power is being dispatched 04
economically with P1 = 150 MW and P2 = 275 MW. The loss coefficients are
B11 = 0.001 MW-1, B12 = -0.0001 MW-1 , B22 = 0.0013 MW-1. Find the
penalty factor of plant 1.
(c) Derive the transmission loss formula explaining current distribution factors. Clearly 07
state all assumptions made in above derivation.

Q.4 (a) An alternator having an induced emf of 1.6 pu is connected to an infinite bus 03
having voltage of 1.0 pu. If the bus bus bar has reactance of 0.6 pu and the
alternator has reactance of 0.2 pu, find the steady state stability limit in pu
(b) Write short notes on Tie line load bias control 04
(c) Describe the turbine speed governing system for controlling the real power flow in 07
power system

1
Q.5 (a) Define steady state stability and transient stability 03
(b) A synchronous generator of reactance 0.4 pu is connected to an infinite bus 04
( |V| = 1.0 pu) through transformers and transmission line having total
reactance of 0.2 pu. The generator no load voltage is 1.2 pu and inertia
constant H = 5 sec. Calculate the frequency of natural oscillations if
generator is loaded to 60% of its maximum power transfer limit. Assume f
= 60 Hz
(c) Explain how existing ZBUS matrix is modified when a link is added between 07
two old buses (Type 4 modification)

Q.6 (a) Discuss equal area criteria of stability 03


(b) What is synchronizing coefficient? How it helps in determining system 04
stability?
(c) State and explain different methods of voltage control 07

Q.7 (a) Explain the phenomena of cascade tripping in power systems 03


(b) Discuss the tasks carried out by Load Dispatch Centre 04
(c) Explain the method of numerical solution of swing equation 07

Q.8 (a) Explain the reclosure case of equal area criterion showing the critical clearing 03
angle δcr and angle of reclosure δrc
(b) Two generators operate in parallel and supply a total load of 400 MW. The 04
capacities of the machines are 200 MW and 500 MW and both the generators
have droop characteristics of 4% from no load to full load. Calculate the load
taken by the each machine assuming free governor action. Also find the
system frequency at this load. No load frequency is 50 Hz.
(c) A generator is delivering 60% of its maximum power to an infinite bus 07
through a transmission line. A fault occurs such that the reactance between
the generator and the infinite bus is increased to 3 times its pre-fault value.
When the fault is cleared the maximum power that can be delivered is 80%
of the original maximum value. Determine the critical clearing angle

*************