Group6 Microsoftproject
Group6 Microsoftproject
Group6 Microsoftproject
NAME & MATRIC NO. 1. AARON ALDWYN BIN JAMES PEKAN (AF190061)
2. NUR DINI ARINA BINTI SHAHARIN (DF200069)
3. FEDRICKSON ANAK PETRUS FELIX (AF190083)
4. ROZAYANI ZAYANI BINTI PUSLAN (AF190018)
5. WAN NABIHAH KARMILA BINTI WAN
BAHARON(AF190070)
SECTION 4
INTRODUCTION ............................................................................................................................ 1
1.1 General Bridge Construction.............................................................................................. 1
1.2 Project Title ........................................................................................................................ 2
1.3 Objectives ........................................................................................................................... 2
1.4 Scope of Project ................................................................................................................. 2
1.4.1 Planning and Scheduling............................................................................................. 2
1.4.2 Bridge Construction Project........................................................................................ 2
1.4.3 Construction Phase...................................................................................................... 3
1.5 Project Start and End Date ................................................................................................. 3
1.6 List of Non-Working Day .................................................................................................. 3
1.7 Cost..................................................................................................................................... 3
DETAILS OF BRIDGE CONSTRUCTION .................................................................................... 4
2.1 Work Breakdown Structure (Tabular View) ...................................................................... 4
2.2 Working Time Information ................................................................................................ 9
2.3 Duration Information Table ............................................................................................. 10
2.4 List of General Workers and Hourly Rate Pay ................................................................ 13
2.5 Physical and Financial S Curve Comparison ................................................................... 14
2.5.1 S Curve Physical ....................................................................................................... 14
2.5.2 S Curve Financial ...................................................................................................... 14
2.6 Gantt Chart ....................................................................................................................... 15
BRIDGE CONSTRUCTION SPECIFICATION ........................................................................... 18
3.1 Drawing Project................................................................................................................ 18
3.3 Bill of Quantities .............................................................................................................. 20
REFERENCES ............................................................................................................................... 26
LIST OF FIGURES
LIST OF TABLES
2
INTRODUCTION
1
1.2 Project Title
1.3 Objectives
2
1.4.3 Construction Phase
The project management processes for building a road include five phases:
feasibility, design, procurement, construction, and operation and maintenance.
However, in this study, we will just discuss the construction phase.
1.7 Cost
3
2 DETAILS OF BRIDGE CONSTRUCTION
1.2 1.2.1 Foundation 1.2.4.1 Pile Cap 1st 1.2.4.1.1 Driving the hole for piles
Substructure
1.2.2 Excavation 1.2.4.2 Pile Cap 2nd 1.2.4.1.2 Cutting & binding the steel frame
1.2.3 Back Filling 1.2.4.3 Pile Cap 3rd 1.2.4.1.3 Concreting
1.2.4 Pilling 1.2.4.4 Pile Cap 4th 1.2.4.1.4 Pile Chipping
1.2.5 Abutment 1.2.5 Abutment 1.2.4.1.5 PCC for pile cap
1.2.6 Pier 1.2.5.2 Abutment B 1.2.4.1.6 Cutting, binding and shuttering
1.2.7 Abutment Cap
1.2.6.1 Pier A 1.2.4.1.7 Pile cap concreting
1.2.8 Pier Cap
1.2.6.2 Pier B 1.2.4.2.1 Driving the hole for piles
1.2.7.1 Abutment Cap A 1.2.4.2.2 Cutting & binding the steel frame
1.2.7.2 Abutment Cap B 1.2.4.2.3 Concreting
1.2.8.1 Pier Cap A 1.2.4.2.4 Pile Chipping
1.2.8.2 Pier Cap B 1.2.4.2.5 PCC for pile cap
1.2.4.2.6 Cutting, binding and shuttering
1.2.4.2.7 Pile cap concreting
1.2.4.3.1 Driving the hole for piles
1.2.4.3.2 Cutting & binding the steel frame
4
1.2.4.3.3 Concreting
1.2.4.3.4 Pile Chipping
1.2.4.3.5 PCC for pile cap
1.2.4.3.6 Cutting, binding and shuttering
1.2.8.2.2 Fixing the shuttering
1.2.8.2.3 Concreting
1.2.4.3.7 Pile cap concreting
1.2.4.4.1 Driving the hole for piles
1.2.4.4.2 Cutting & binding the steel frame
1.2.4.4.3 Concreting
1.2.4.4.4 Pile Chipping
1.2.4.4.5 PCC for pile cap
1.2.4.4.6 Cutting, binding and shuttering
1.2.4.4.7 Pile cap concreting
1.2.5.1.1 Cutting, binding & fixing the steel
1.2.5.1.2 Fixing the shuttering 1st lift
1.2.5.1.3 Concreting
1.2.5.1.4 Fixing the shuttering 2nd lift
1.2.5.1.5 Concreting
1.2.5.2.1 Cutting, binding & fixing the steel
1.2.5.2.2 Fixing the shuttering 1st lift
1.2.5.2.3 Concreting
1.2.5.2.4 Fixing the shuttering 2nd lift
1.2.5.2.5 Concreting
5
1.2.6.1.1 Cutting, binding & fixing the steel
1.2.6.1.2 Fixing the shuttering 1st lift
1.2.6.1.3 Fixing the shuttering 2nd lift
1.2.6.1.5 Concreting
1.2.6.2.1 Cutting, binding & fixing the steel
1.2.6.2.2 Fixing the shuttering 1st lift
1.2.6.2.3 Concreting
1.2.6.2.4 Fixing the shuttering 2nd lift
1.2.6.2.5 Concreting
1.2.7.1.1 Binding the steel
1.2.7.1.2 Fixing the shuttering
1.2.7.1.3 Concreting
1.2.7.2.1 Binding the steel
1.2.7.2.2 Fixing the shuttering
1.2.7.2.3 Concreting
1.2.8.1.1 Binding the steel
1.2.8.1.2 Fixing the shuttering
1.2.8.1.3 Concreting
1.2.8.2.1 Binding the steel
6
1.3 1.3.1 Dirt Wall 1.3.1.1 Dirt Wall - A1 1.3.1.1.1 Binding the steel - a1
Superstructure
1.3.2 Girders 1.3.1.2 Dirt Wall - A2 1.3.1.1.2 Fixing the shuttering - a1
1.3.3 Pedestal 1.3.2.1 Girders – LHS 1.3.1.1.3 Concreting - a1
1.3.4 Cross Girders 1.3.2.2 Girders – RHS 1.3.1.2.1 Binding the steel - a2
1.3.5 Deck Slab 1.3.3.1 Pedestal – LHS 1.3.1.2.2 Fixing the shuttering - a2
1.3.6 Approach 1.3.3.2 Pedestal – RHS 1.3.1.2.3 Concreting - a2
Slab 1.3.4.1 Cross Girders – LHS 1.3.2.1.1 Girder Bed PCC
1.3.7 Retaining 1.3.4.2 Cross Girders – RHS 1.3.2.1.2 Cutting, binding and fixing the steel
Wall 1.3.5.1 Span 1 1.3.2.1.3 Fixing the shuttering
1.3.8 Crash Barrier (Abutment A - Pier 1) 1.3.2.1.4 Concreting
1.3.9 Wearing Coat 1.3.5.2 Span 2 1.3.2.1.5 Launching of girders
(Pier 1 – Pier 2) 1.3.2.2.1 Auto Scheduled Girder Bed PCC
1.3.5.3 Span 3 1.3.2.2.2 Cutting, binding and fixing the steel
(Pier 2 - Pier 3) 1.3.2.2.3 Fixing the shuttering
1.3.6.2 Approach Slab - A2 1.3.2.2.4 Concreting
1.3.7.1 Base steel binding 1.3.2.2.5 Launching of girders
1.3.7.2 Base shuttering and 1.3.3.1.1 Stool making and bearing fixing
concreting 1.3.3.1.2 Shuttering fixing
1.3.7.3 Stem steel cutting, 1.3.3.1.3 Concreting
binding and fixing 1.3.3.2.1 Stool making and bearing fixing
1.3.7.4 Stem shuttering 1.3.3.2.2 Shuttering fixing
1st lift 1.3.3.2.3 Concreting
1.3.7.5 Concreting 1.3.4.1.1 Steel binding and fixing
1.3.7.6 Stem shuttering 1.3.4.1.2 Shuttering fixing
2nd lift 1.3.4.1.3 Concreting
1.3.7.7 Concreting 1.3.4.2.1 Steel binding and fixing
7
1.3.7.8 Stem shuttering 3rd 1.3.4.2.2 Shuttering fixing
lift 1.3.4.2.3 Concreting
1.3.7.9 Concreting 1.3.5.1.1 Bottom shuttering
1.3.8.1 On Slab – LHS 1.3.5.1.2 Steel cutting, fixing and binding
1.3.8.2 On Slab - RHS 1.3.5.1.3 Side shuttering fixing
1.3.5.1.4 Concreting
1.3.5.2.1 Bottom shuttering
1.3.5.2.2 Steel cutting, fixing and binding
1.3.5.2.3 Side shuttering fixing
1.3.5.2.4 Concreting
1.3.5.3.1 Bottom shuttering
1.3.5.3.2 Steel cutting, fixing and binding
1.3.5.3.3 Side shuttering fixing
1.3.5.3.4 Concreting
1.3.6.1.2 Concreting
1.3.6.1.1 Steel and shuttering
1.3.6.2.1 Steel and shuttering
1.3.6.2. Concreting
1.4 Project
Handover
8
2.2 Working Time Information
Figure 1.4.3-2 List of Public Holidays in 2023 incorporated into Working Calender
9
2.3 Duration Information Table
10
49 Cutting, binding & fixing the steel 6 days
50 Fixing the shuttering 1st lift 3 days
51 Concreting 1 day
52 Fixing the shuttering 2nd lift 3 days
53 Concreting 1 day
54 Pier 26 days
55 Pier A 18 days
56 Cutting, binding & fixing the steel 6 days
57 Fixing the shuttering 1st lift 3 days
58 Concreting 1 day
59 Fixing the shuttering 2nd lift 3 days
60 Concreting 1 day
61 Pier B 18 days
62 Cutting, binding & fixing the steel 6 days
63 Fixing the shuttering 1st lift 3 days
64 Concreting 1 day
65 Fixing the shuttering 2nd lift 3 days
66 Concreting 1 day
67 Abutment Cap 16 days
68 Abutment Cap A 8 days
69 Binding the steel 5 days
70 Fixing the shuttering 2 days
71 Concreting 1 day
72 Abutment Cap B 8 days
73 Binding the steel 5 days
74 Fixing the shuttering 2 days
75 Concreting 1 day
76 Pier Cap 16 days
77 Pier Cap A 8 days
78 Binding the steel 5 days
79 Fixing the shuttering 2 days
80 Concreting 1 day
81 Pier Cap B 8 days
82 Binding the steel 5 days
83 Fixing the shuttering 2 days
84 Concreting 1 day
85 Superstructure 146 days
86 Dirt Wall 14 days
87 Dirt Wall - A1 6 days
88 Binding the steel - a1 3 days
89 Fixing the shuttering - a1 2 days
90 Concreting - a1 1 day
91 Dirt Wall - A2 6 days
92 Binding the steel - a2 3 days
93 Fixing the shuttering - a2 2 days
94 Concreting - a2 1 day
95 Girders 54 days
96 Girders - LHS 54 days
97 Girder Bed PCC 2 days
98 Cutting, binding and fixing the steel 15 days
99 Fixing the shuttering 6 days
100 Concreting 4 days
101 Launching of girders 2 days
11
102 Girders - RHS 29 days
103 Girder Bed PCC 2 days
104 Cutting, binding and fixing the steel 15 days
105 Fixing the shuttering 6 days
106 Concreting 4 days
107 Launching of girders 2 days
108 Pedestal 95 days
109 Pedestal - LHS 19 days
110 Stool making and bearing fixing 2 days
111 Shuttering fixing 2 days
112 Concreting 1 day
113 Pedestal - RHS 78 days
114 Stool making and bearing fixing 2 days
115 Shuttering fixing 2 days
116 Concreting 1 day
117 Cross Girders 115 days
118 Cross Girders - LHS 39 days
119 Steel binding and fixing 21 days
120 Shuttering fixing 15 days
121 Concreting 3 days
122 Cross Girders - RHS 39 days
123 Steel binding and fixing 21 days
124 Shuttering fixing 15 days
125 Concreting 3 days
126 Deck Slab 90 days
127 Span 1 (Abutment A - Pier 1) 14 days
128 Bottom shuttering 5 days
129 Steel cutting, fixing and binding 7 days
130 Side shuttering fixing 2 days
131 Concreting 1 day
132 Span 2 (Pier 1 - Pier 2) 14 days
133 Bottom shuttering 5 days
134 Steel cutting, fixing and binding 7 days
135 Side shuttering fixing 2 days
136 Concreting 1 day
137 Span 3 (Pier 2 - Pier 3) 14 days
138 Bottom shuttering 5 days
139 Steel cutting, fixing and binding 7 days
140 Side shuttering fixing 2 days
141 Concreting 1 day
142 Approach Slab 11 days
143 Approach Slab - A1 3 days
144 Steel and shuttering 2 days
145 Concreting 1 day
146 Approach Slab - A2 3 days
147 Steel and shuttering 2 days
148 Concreting 1 day
149 Retaining Wall 34 days
150 Base steel binding 4 days
151 Base shuttering and concreting 3 days
152 Stem steel cutting, binding and fixing 7 days
153 Stem shuttering 1st lift 2 days
154 Concreting 1 day
12
155 Stem shuttering 2nd lift 2 days
156 Concreting 1 day
157 Stem shuttering 3rd lift 2 days
158 Concreting 1 day
159 Crash Barrier 80 days
160 On Slab - LHS 4 days
161 Steel binding and fixing 2 days
162 Shuttering fixing 2 days
163 Concreting 2 days
164 On Slab - RHS 4 days
165 Steel binding and fixing 2 days
166 Shuttering fixing 2 days
167 Concreting 2 days
168 Wearing Coat 78 days
169 On Slab - LHS 2 days
170 On Slab - RHS 2 days
171 Project Handover 1 day
Table 2.4-1 List of General Workers and Their Hourly Rate Pay for Financial Purpose
13
2.5 Physical and Financial S Curve Comparison
S-Curve Physical
0 5 10 15 20 25 30 35
8% 120%
7%
100%
6%
Cum. % Complete
80%
5%
4% 60% Weekly
3%
40% Planning
2%
20% Actual
1%
0% 0%
Duration
S-Curve Financial
0 5 10 15 20 25 30 35
RM4,000.00 RM70,000.00
RM3,500.00 RM60,000.00
RM3,000.00
RM50,000.00
RM2,500.00
Cum. Cost
RM40,000.00
RM2,000.00 Weekly
RM30,000.00
RM1,500.00 Cost
RM20,000.00
RM1,000.00 Actual Cost
RM500.00 RM10,000.00
RM0.00 RM0.00
Week 1
Week 3
Week 5
Week 7
Week 9
Week 11
Week 13
Week 15
Week 17
Week 19
Week 21
Week 23
Week 25
Week 27
Week 29
Duration
14
Group 6 Microsoft Project Section 4 Project Starts Mon 2/1/23
January 2023 February 2023 March 2023 April 2023 May 2023 June 2023 July 2023
27 1 6 11 16 21 26 31 5 10 15 20 25 2 7 12 17 22 27 1 6 11 16 21 26 1 6 11 16 21 26 31 5 10 15 20 25 30 5 10 15 20 25
Aaron
Azim,Brodie,Fedrick
Syahmi
Abu
Ali,Amir
Aaron,Azim
Brodie,Syahmi
Azim
Haikal
Aaron,Abu
Syahmi
Ali,Amir
Aaron,Azim
Syahmi,Brodie
Azim
Haikal
Aaron,Abu
Syahmi
Ali,Amir
Aaron,Azim
Brodie,Syahmi
Azim
Haikal
Aaron,Abu
Syahmi
Ali,Amir
Aaron,Azim
Brodie,Syahmi
Azim
Haikal
Aaron,Abu
Syahmi
Aaron,Abu
Ali
Syahmi
Azim,Brodie
Syahmi
Aaron,Abu
Ali
Syahmi
Azim,Brodie
Syahmi
Aaron,Abu
Ali
Syahmi
Azim,Brodie
Page 1
Group 6 Microsoft Project Section 4 Project Starts Mon 2/1/23
January 2023 February 2023 March 2023 April 2023 May 2023 June 2023 July 2023
27 1 6 11 16 21 26 31 5 10 15 20 25 2 7 12 17 22 27 1 6 11 16 21 26 1 6 11 16 21 26 31 5 10 15 20 25 30 5 10 15 20 25
Syahmi
Aaron,Abu
Ali
Syahmi
Azim,Brodie
Syahmi
Aaron,Abu
Ali
Syahmi
Aaron,Abu
Ali
Syahmi
Aaron,Abu
Ali
Syahmi
Aaron,Abu
Ali
Syahmi
Amir
Haikal
Syahmi
Amir
Haikal
Syahmi
Aaron
Azim,Brodie
Abu,Ali
Haikal,Syahmi
Fedrick
Aaron
Azim,Brodie
Abu,Ali
Haikal,Syahmi
Abu
Ali
Amir
Abu
Ali
Page 2
Group 6 Microsoft Project Section 4 Project Starts Mon 2/1/23
January 2023 February 2023 March 2023 April 2023 May 2023 June 2023 July 2023
27 1 6 11 16 21 26 31 5 10 15 20 25 2 7 12 17 22 27 1 6 11 16 21 26 1 6 11 16 21 26 31 5 10 15 20 25 30 5 10 15 20 25
Azim,Haikal
Brodie,Syahmi
Aaron
Azim,Haikal
Brodie,Syahmi
Aaron
Aaron
Abu
Ali
Amir
Aaron
Abu
Ali
Amir
Aaron
Abu
Ali
Amir
Brodie
Syahmi
Brodie
Syahmi
Aaron
Abu
Amir,Azim
Fedrick
Syahmi
Fedrick
Syahmi
Fedrick
Aaron
Abu
Ali
Aaron
Abu
Ali
Azim
Haikal
Page 3
3 BRIDGE CONSTRUCTION SPECIFICATION
18
Figure 2.5.2-3 Sectional Elevation of Abutment
19
3.2 Bill of Quantity
Method of Measurement
Description:
The descriptions identify the work covered by the respective items, but
the exact nature and extent of the work is to be ascertained from the
Drawings & Specifications.
Quantities
1 The quantities shall be computed net using dimensions from the
drawing, unless directed otherwise by the client's site engineer. No
allowance shall be made for bulking, shrinkage or waste. No other type,
terms or regulation for computing the quantities will be used and
accepted. For any kind of work and item, the net dimension will be used
for computing the quantities. Quantities may be rounded up or down
where appropriate. Fractional quantities are not generally necessary and
should not be given to more than two places of decimals.
Unit of measurement
The following units of measurement and abbreviations shall be used.
Unit & Abbreviation:
Millimetre = mm
Metre = m
Square millimetre = mm²
2 Square metre = m²
Cubic metre = m³
Kilogramme = kg
Tonne = t
Sum = sum
Number = No.
Hour = hr.
All tools and plants described and mentioned in the various chapters
5 shall be included either in the site installation costs or in the item rates.
No additional costs will be paid.
Various
It is understood that all the above costs are included in the site
installation . By signing the contract, the contractor confirms that all
efforts and costs to fulfill the tasks listed above as a part of site
13 installation are included in the rates. The mode of payment for the site
installation shall be as follows:-
a. 80% after the site installation is complete
b. 20% after the site is restored to its initial shape and condition or as
per the instruction of Client/site engineer
PREPARATORY WORKS
NO. ITEM DESCRIPTION UNIT OF MEASURE QUANTITY OF WORKS UNIT PRICE TOTAL AMOUNT
Calculation per lump sum for the entire scope of works, materials,
15
tools, equipment or mechanization.
EARTHWORK
NO. ITEM DESCRIPTION UNIT OF MEASURE QUANTITY OF WORKS UNIT PRICE TOTAL AMOUNT
Excavation work
The contractor shall be deemed to have made himself fully acquainted
18
with the full nature & complexity of the work, the location and
character of the site and means of access to the site.
The rates and work descriptions have to include all activities and all
costs necessary to complete the work. The erecting, use and dismantling
of necessary working platforms, scaffolding and related structures have
to be included in the rates. Construction of coffer dams, guide bunds,
sheet piles etc. if required for diversion of the river in order to get the
working space or to control seepage during excavation shall also be
19
included in the rates. The relevant drawings are an integral part of these
tender documents. The contractor has to study all drawings in detail. By
submitting the tender, the contractor is declaring that he has understood
the drawings and all the works involved and is prepared to complete all
construction work in a competent manner. Only the highest degree of
accuracy and quality will be accepted.
Providing and laying coarse gravel (filter layer) behind the Abutments
and return walls as per drawing. Thickness d=60 cm behind abutments
24 and return walls. The filter material to be used have to be approved by m3 106.08 73.00 7743.84
the client. Handling, loading, offloading, transportation and all
necessary work shall be included in the rate.
The reinforced concrete works shall be carried out strictly as per the
stipulations in the Technical Specification. The reinforced concrete
works may be under or above the water level. The bidders have to study
the site condition and the design drawings carefully and if necessary
account for the dewatering works using water pumps or any other
means including providing of temporary protection works such as coffer
dam, sheet pile etc. to divert the river and/or control seepage for laying
the concrete works under water. It is understood that the bidders' price
25 for the concrete works include, besides others, possible expenses for m3 21.66 300.00 6498.00
river diversion, cofferdam/sheet pile/guide bunds, dewatering works
etc. The rates shall include all the efforts required to fulfill the task.
Abutments and Piers Providing & Laying of Lean Concrete 10 cm thick
in M10 underneath foundation slab of abutments and pier as shown in
the drawing for leveling. The side of the lean concrete can can be
inclined upto 15 degress and therefore no formwork is necessary. The
rate has to include all works and materials to fulfill the task including
curing of the concrete.
Providing and fixing vertical formwork for the foundation slab of the
29 m2 137.20 23.00 3155.60
abutments and piers as shown in the drawing.
Providing and fixing vertical form work for the abutment wall (stem),
30 pier stem up to the bearing level of the bridge (all sides) and all sides of m2 614.58 40.00 24583.20
dirt walls & return walls.
Bend-up bars with hooks and any kind of bends, Diameter 10 - 32 mm.
32 All efforts and costs to be included to fullfil the task. The quantity is for kg 67887.68 1.50 101831.52
Abutments, piers, dirt walls & return walls
Providing, laying & fixing of HDPE pipes for weep holes as per
33 drawings - diameter = 11cm, slope = 1 in 20. This quantity is for m 58.60 10.00 586.00
abutments and return walls.
41 P&L RRM with hard stone infoudation & plinth CM 1:4 cum 971.40 25.00 24285.00
42 Providing and laying hand packed stone back filling of walls with stone. cum 360.00 90.00 32400.00
Paving the asphalt surface over the bridge structure using the asphalt-
46 m2 109.44 100.00 10944.00
concrete AB 11C
52 Manifacturing and installing barbicans made of galvanized pipes pcs. 12.00 300.00 3600.00
https://www.slideshare.net/kundansanap/report-on-planning-scheduling-of-a-minor-
bridge?from_action=save
Emedya Samsudin. (2019, October 15). How to create s curve in mic project [Video].
YouTube. https://www.youtube.com/watch?v=jQYzplizMWI
26