C15 Recommendations Manifolds Refrigerated Liquefied Natural Gas Carriers - Ed. 1994
C15 Recommendations Manifolds Refrigerated Liquefied Natural Gas Carriers - Ed. 1994
C15 Recommendations Manifolds Refrigerated Liquefied Natural Gas Carriers - Ed. 1994
Standardisation of Manifolds
for Refrigerated Liquefied
Gas Carriers (LNG)
STANDARDISATION OF MANIFOLDS FOR
REFRIGERATED LIQUEFIED GAS CARRIERS (LNG)
PREAMBLE
These standards are recommended to introduce conformity in manifold
arrangements on Liquefied Natural Gas Camers in order to promote improved
efficiency in operation and assist planning the position of loading and dis-
charging facilities on new jetties.
The specification has been prepared by drawing on the experience of LNG
ship operators, berth design specialists, naval architects, ship constructors
and equipment manufacturers. It is intended to serve as a guideline to LNG
ship owners and builders and to those planning jetty design. It is not implied
that existing vessels should be altered.
STANDARDISATION OF MANIFOLDS FOR
REFRIGERATED LIQUEFIED GAS CARRIERS (LNG)
TABLE 2
SPACING AND PRINCKPAL FLANGE SIZE
4.22. Length
The length of the distance pleces should be kept to a minimum. However,
the length of the distance pieces should be adequate to provide sufficient
room for the fo1lowing~-
(a) to ensure that suffic~entspace is available for bolt withdrawal from
the valve/distance piece and distance piece/reducer flanges. A
minimum of 200mm should be allowed for this purpose on each
flange. (See Fig. 4).
(b) to take the manifold support. (See Fig. 4).
(c) to take other line connections such as relief valves, sample points
or drain lines, as may be required by the IMCO Code or Owners.
Such connections should always be fitted inboard of the manifold
supports.
4.3.2. Length
The minimum length of all reducers should be 500mm in order t o allow
sufficient space for the operation of quick-acting couplers and the insert-
ion of open bolts.
TABLE 3
CARGO RED'UeERS
~ --
The containment area in 5.2 should be provided with a drain line capable
of leading a spill overboard e~ther:
by flexible hose to sea level, or
(1)
(2) by rigid pipe to main deck sheathing.
Such a line should be include any permanent means of closure, and
should be so aligned as not to deluge a jetty or its associated equipment
with liquid.
6. BUNKER CONNECTIONS
6 1. Number and Position
Four bunker connections should be provided, two on each side of the
ship. The distance of the presentation flanges inboard from the ship's side
should not be less than 3 metres or greater than 4 metres, (Flg. 4) and
6
lb). The height of the presentation flange above the deck or working
platform should be the same as for the cargo manlfold presentation
flanges. (See Section 3.4).
One bunker connection should be located forward of the manifold and
one located abaft of the manifold on each side of the ship.
6.2. Spacing
The spacing between the bunker line and the nearest cargo line should
be 2.0 metres for all classes of vessel.
6.5. Strength
The bunker manifold supports, distance pieces and reducers should be
capable of withstanding the loads as outlined in Table 4.
(For definition of Forces. See Fig. 3)
TABLE 4
FORCES ON BUNKER PRESENTATION FLANGE
Ship Volume Category A B&C
7. NITROGEN LINE
It is recommended that, whenever possible, the presentation flange for
the Nitrogen line be in the same fore and aft line and as close to the
vapour lines as possible. Nitrogen line connections should be provided
on both sides of the vessel.
8. SERVICE LINES
Diesel/Gasoil/ Waterlines
Where such lines are required, every effort should be made to place
the various presentation flanges in the cargo manlfold area, with at least
one connection for each on both sides of the vessel.
MANIFOLD ARRANGEMENT (F,+ 10 a ~b)
H. D I S ~b. e t ~ e e n
flange centres.
h D ~ s t .between
flange ceptres.
c-h-H-H-H - a h -
H D ~ s tb. e t k c n h. D ~ s tbetween
.
flange centres. flange centres
i
,
r
,?-
_I ---p-lo
4'; 4/
Water Curtain
'.I
D Refer t o Sect~on4 3 2.