Basketball Court Construction Sample
Basketball Court Construction Sample
Basketball Court Construction Sample
20 MARCH 2018
TABLE OF CONTENTS
A. PROJECT SYNOPSIS
The project is described as Resurfacing of Basketball Court at the U. S. Consulate General, Erbil,
Iraq. The Contractor should furnish all necessary materials, labor, transportation, equipment,
investigation and supervision, etc. Work will performed under a fixed-price contract.
B. BACKGROUND
At present the basketball court does not meet U. S. fire, life safety, or security standards. The court
must be resurfaced to address safety concerns.
C. SOLUTION
Improve life safety conditions by resurfacing the basketball court with proper materials and
coatings.
A. Fixed-Price Proposal. The Contractor shall provide one fixed-priced Proposal for the complete
Project that includes every aspect of the Work.
B. Specifications. The Work shall be governed by the U. S. Consulate General, Erbil, Iraq.
International Codes to include the National Fire Prevention Association (NFPA), International
Building Code, International Mechanical Code, International Plumbing Code, and the National
Electric Code (NEC). Should there be a discrepancy between the U. S. Consulate General
Specifications and the applicable Building Code, the more stringent of the two shall govern.
The Contractor is responsible for compliance with all Building Codes; Work not in compliance
with the Codes shall be deemed to be unacceptable.
C. Execution. The Work shall be executed in a diligent and workmanlike manner in accordance with
the negotiated fixed-price, this Scope of Work, the Project Schedule, International Building Codes,
and the laws of the City of Erbil where applicable.
D. Work Hours. Unless otherwise agreed with the COR, the Work shall be executed during normal
Consulate work hours. Night, weekend or holiday work shall not be permitted except as arranged
in advance with the COR. U. S. Consulate General holiday schedule is available from the COR.
E. Safety. The Contractor shall be responsible for conducting the work in a manner that ensures the
safety of residents, employees and visitors to the compound, and the Contractor’s employees.
Regular safety meetings shall be held among on-site contractor personnel, and safety concerns
shall immediately be brought to the attention of the Post Safety and Health Officer (POSHO) and
the Contracting Officers Representative (COR).
F. Workforce. The contractor shall provide all supervision, skilled and unskilled labor needed to
perform the work. The contractor shall comply with the U. S. Consulate General security policy by
providing approved escorts. Contractor provided escorts shall be in quantity sufficient to comply
with RSO escort ratios for number of workers on the project. The contractor shall prepare
requests for the RSO for vetting of employees to get escort badges. The Contractor or government
H. Modification to Contract. The Contractor shall not incur any costs beyond those described in
this SOW unless directed otherwise in writing by the Contracting Officer. Any work performed by
the Contractor beyond this SOW without written direction from the Contracting Officer will be at
the Contractor’s own risk and at no cost to the Consulate.
I. Stop Work. At any time during the Project, the Contracting Officer reserves the right to Stop Work
for protection of employees or visitors, security, or any other reason at his/her discretion.
J. Submittals. The contractor is responsible to submit shop drawings prior to fabrication and
release of any materials for the Facility Manager and COR Review and approval. The review,
however, does not relieve the contractor of responsibility to engineer the work to provide a
complete working system.
K. Excavation and Utilities. The contractor is responsible to locate all existing utility lines prior to
any excavation. Prior to disconnecting any existing utility services, the contractor is responsible
to provide 48-hour advance notice to the COR so an outage can be mutually scheduled.
L. Close-out. Prior to final acceptance, the contractor is to submit to the COR marked up drawings
(As-Built) reflecting the work as constructed. The drawings shall be digitally submitted on a CD-
ROM in both AutoCAD and PDF format and provide one hard copy size A3.
M. Housekeeping. The contractor is responsible to clean up daily before departing the Consulate
Compound. At the completion of the work, the Contractor shall clean any impacted areas to a
condition equal to original condition. Contractor tools and equipment will be secured when not in
use.
Repair and replace (make ready) of S-49 at U. S. Consulate General Erbil, Iraq
Unit Price
No Description Unit Qty Total Price ID
ID
1 Administration
A Mobilization / Demobilization LS
Submittals – product data and shop
B LS 0
drawings 0
Administration Sub-Total
2 Construction Work 0
A Architectural LS
B Mechanical-Plumbing LS
C Electrical LS
E Close-out LS
0
Construction Sub-Total
3 DBA Insurance 0
Contractor shall cover each of its
workers at the site with DBA Workers’
Compensation coverage, and require
A its subcontractors to do the same. LS
Contractor must furnish certificate
evidencing this coverage to the COR
prior to starting work.
DBA Insurance Sub-Total
Items 1 thru 3 Sub-Total
G and A
Sub-Total
Profit
Contract
4 Basic Bid
Cost
Contract
A Bid
Cost
A. General Requirements
1. Within 14 days of award fully completed vetting forms shall be submitted to the COR.
2. Within 3 days of Notice to Proceed (NTP), the contractor shall provide the COR a project
schedule showing start to completion dates including significant milestones.
3. Within 3 days of NTP, the Contractor shall provide the COR with details of the proposed
installation utilizing written description or sketches or both.
4. The contractor is responsible to properly remove and dispose of all debris related to their work,
including, but not limited to electrical, mechanical, sanitary accessories, soils, rock excavation,
packing materials, scrap steel, uninstalled materials and/or environmental waste.
5. The contractor is responsible to properly layout and prepare for the work based on locations
provided by the COR, or Facility Manager, if the COR is unavailable.
6. When pursuing the work, the contractor is to take extra care not to damage existing structures.
Contractor is responsible to repair any damage caused as the result of their work at no cost to the
U.S. Government.
7. When pursuing the work, the contractor is to implement safety measures to protect from
damaging existing structures not designated as part of scope of work. The limits of construction
will be clearly identified and marked to deter unauthorized personnel access.
8. All work shall be according to attached drawings and specifications, Codes (listed below), OBO
program office, OPS/SHEM requirements. If there is a conflict between codes, drawings or
specifications the more stringent will apply.
9. Storage of “Useful" and uninstalled materials will be in a location as directed by the COR.
11. Contractor will provide samples, catalog cut sheets, and paint colors etc. of all products prior
to installation or use for COR approval.
12. At completion of work, the Contractor shall clean any impacted areas to a condition equal to
original condition.
13. Contractor will warranty all construction work for a minimum of one (1) year and provide
manufacturer warranties and equipment manuals for all equipment installed to the COR.
14. All construction work will be in conformance with the following Codes:
B. Work Requirements:
Contractor shall provide complete design and construction services, to include all coordination,
supervision, and management necessary to meet the requirements of this contract.
2. Asphalt Work
Aggregate Size: Basketball Court Surface shall be a hot plant mix having
a maximum aggregate size of 3/8 inch, a minimum aggregate size of ¼
inch and meeting the following graduation requirements:
Screen % Passing
½ 100
3/8 90-100
#4 55-85
#8 32-67
#50 7-23
#200 2-10
Installation Specifications.
A. The surface of the asphalt material should be level within 1/16″ with use
of a 10′ straight edge.
B. The asphalt material should be laid in 12′ (300mm) wide strips.
The asphalt seams must run in the same direction as the pitch.
The asphalt may be placed in one or two lifts.
A total asphalt thickness of 90mm will be placed with two lifts of 50mm
and 40mm. The first layer should be watered, to help locate and repair any
standing water that may exist prior to the second layer installation.
C. Upon installation of the asphalt roll the asphalt with a minimum 8 ton
roller and no roller ridges should be seen upon completion.
PRIME COAT
1. Application
a. Apply 0.25 – 0.28 gallon / square yard to the completed and
accepted base course after receiving approval from the COR.
b. The prime shall only be applied when the base course is only
slightly damp, and when temperature of the air in the shade is 55
degrees F or above.
c. In places where the distributor bars cannot reach, it will be
necessary to apply the prime coat with a hand sprayer attached to
the distributor by a hose.
d. Protect adjacent existing surfaces from overspray during the
application of prime coat. Promptly remove any overspray without
damaging underlying surface.
e. Curing: After applying the prime coat, it must cure for a minimum
of 48-72 hours before asphalt is placed, with no rain in the forecast.
ASPHALTIC CONCRETE:
1. Mixing & Transportation of Bituminous Mixture:
3. Painting Work
5.0 CLOSEOUT
Prior to final acceptance, the contractor is to submit to the COR marked up drawings (As-Built)
reflecting the work as constructed. The drawings shall be digitally submitted on a CD-ROM in both
AutoCAD and PDF format and provide one hard copy size A3.
A. The Contractor shall provide and maintain work environments and procedures which will:
(a) Safeguard the public and Government personnel, property, materials, supplies, and equipment
exposed to Contractor operations and activities.
(b) Avoid interruptions of Government operations and delays in project completion dates.
(c) Control costs in the performance of this contract.
C. Contractor shall comply with all pertinent provisions of the latest version of U. S. Army Corps of
Engineers Safety and Health Requirements Manual, EM 385-1-1, in effect on the date of the
solicitation
D. Whenever the Contracting Officer becomes aware of any noncompliance with these requirements
or any condition which poses a serious or imminent danger to the health or safety of the public or
Government personnel, the Contracting Officer shall notify the Contractor orally, with written
confirmation, and request immediate initiation of corrective action. This notice, when delivered to
the Contractor or the Contractor's representative at the work site, shall be deemed sufficient
notice of the noncompliance and that corrective action is required. After receiving the notice, the
Contractor shall immediately take corrective action. If the Contractor fails or refuses to promptly
take corrective action, the Contracting Officer may issue an order stopping all or part of the work
until satisfactory corrective action has been taken. The Contractor shall not be entitled to any
C. Deliverables
The Contractor shall be required to (a) commence work under this contract within one (2) calendar
days after the date the Contractor receives the Notice to Proceed, (b) prosecute the work diligently,
and (c) complete the entire work ready for use “Completion Date Including punch list” not later than
(80) calendar days after NTP. The time stated for completion shall include final cleanup of the
premises.
A. COR. A Contracting Officers Representative (COR) will be assigned to ensure quality assurance
goals are met. The Contractor shall provide the COR access to the site at all times.
D. Management Personnel. The Contractor shall staff the site, full-time, with a competent senior
manager who shall perform project management. Remote project management is not an option.
This individual shall keep a detailed written history of the project and shall update the
Government daily.
E. Site Security. The Contractor is responsible for on-site security as necessary to ensure no
unauthorized access to their work sites. The Contractor is 100% responsible for securing their
working materials and equipment. Any damage to facilities or infrastructure, which happens due
to a lack of security, will be the responsibility of the Contractor to correct.
F. Contractor’s Temporary Work Center. The Contractor will be permitted to use a designated
area within the contract limits for operation of his construction equipment and office if warranted.
If directed by the Contracting Officer, the Contractor shall not receive additional compensation to
relocate his operations. The Contractor is responsible for obtaining any required additional
mobilization area above that designated. On completion of the contract, all facilities shall be
removed from the mobilization area within 5 days of final acceptance by the Contractor and shall
be disposed of in accordance with applicable host government laws and regulations. The site shall
be cleared of construction debris and other materials and the area restored to its final grade. The
Contractor is responsible for maintaining this area in a clear orderly manner.
G. Health and Safety. The Contractor shall be solely responsible for risk assessments, managing
health, and safety issues associated with this project. The Contractor must provide cold water to
all workers at the job sites. Based on hazard assessments, Contractors shall provide or afford each
affected employee personal protective equipment (PPE) that will protect the employee from
hazards. At a minimum PPE shall consist of eye protection, hard hats, and closed toe shoes. If the
workers arrive on-site with sandals or athletic shoes, the Contractor is expected to provide rubber
boots to them or send them home. All construction workers and management personnel must
wear hard hats at all times on the construction sites. Contractor provided rubber boots and rubber
gloves shall be worn when working around concrete placement. Other PPE such as gloves, dust
masks, air respirators (sewage work) are also recommended. These items must be provided at the
Contractor’s expense. Workers may use discretion if they feel unsafe in using the equipment in a
hostile environment. Any worker at an elevated location above 4 meters, with the exception of a
portable ladder, must be provided and utilize a safety harness.
H. Progress Payments. If the contract awarder expects to receive more than one (1) progress
payment, the contractor must submit a broken out cost proposal with a schedule of values in order
to properly calculate the percentage of contract completion.