TPC - Final II
TPC - Final II
TPC - Final II
I - Cover
II - Main Building
III - History
IV - Technical Data
In the early 1990s, the Philippines began to suffer frequent power interruptions due to
aging of state energy facilities made even worse by the spate of calamities that hit many
places of the country in staggering fashion. As electricity is a vital factor in physical growth,
many sectors - business particularly - had to bear the brownout brunt. It did not spare the
Municipality of Tarlac then, was starting to enhance its commerce and industry in the region.
In view of the above, Tarlac Electric, Inc. - the Municipality’s main distributor of
electricity- drew various plans. What came out was the decision to lessen TEI’s dependence
on National Power Corporation (NPC) by establishing a power plant of its own. This is in
line with the Executive Order 215, which encourages the private sector to engage in power
generation projects. Tarlac Power Corporation (TPC) was organized in 1993 to address this
objective.
TPC decided to put up a 30-Megawatt power plant to offset such scenario. However,
for its initial operation, TPC installed an 18.6MW or three bunker-fired SULZER-ZGODA
diesel power-generating sets. Two units each rated at 6.3MW, was commissioned in 1995 and
another unit rated 6.0MW was commissioned in July of 1997, totaling to 18.6MW capacity.
Chronological Events Leading to the Establishment and
November 1993 TPC was registered with the Securities and Exchange Commission.
December 1993 Site development at the 9-hectare lot owned by TPC located at Brgy.
January 1994 The start of foundation construction for engine units 1 & 2, power
May 1994 Land Bank of the Philippines (LBP) one of the active participating
Board of Investments (BOI) registered and certified TPC for its two
April 1995 Power plant building, tank farm and deep well completed.
May 1995 ZGODA SULZER power generating sets arrived from Poland.
June 1995 Testing and commissioning of power plant engine # 1 (6.3 MW) by
August 1995 Testing and commissioning of power plant engine # 2 (6.3 MW) by
September 1995 Inauguration and formal switch-on for commercial operation of the
plant.
October 1995 TPC’s Two (2) 6.3 MW power generating sets are fully operational.
January 1997 Department of Trade and Industry (DTI) registered and certified
TPC.
TPC engineers.
August 1997 TPC’s three (3) power-generating sets are fully operational. Power
Number of cylinders 12
EXHAUST VALVES :
Valves made of nimonic material 0.8+0.1/0 mm
(mark with black ring)
Cam lift (Fuel Injection Pump) 29 mm
Made Poland
follows:
minimum speed
Visually check the Jacket Water [JW] and Injector Cooling [IC] Water
Check inlet and outlet valves of Nozzle and Jacket Waters systems for
Note: Set jacket and nozzle cooling water temperature controller to 60 ºC.
Check the level of the various engine tanks and auxiliary equipment.
Verify that fuel control linkages and injection pump plunges moves
freely.
Check that the various valves for the engine cooling, lubrication, fuel
any).
Open the indicator cocks in the cylinder heads and rotate the engine
several times with the turning gear to make sure that no water, oil, or
Switch “OFF” the JW and IC heaters and switch-off the injector and
Switch “OFF” the turning gear motor, disengage the turning gear, and
Check that the turning gear is disengaged and that the operating lever
is locked.
Check starting air tank pressure gauge for the proper pressure of 25
to 30 bar.
Set the governor load limit to “0” position, and rotate the speed setting
Move each individual fuel pump rack in and out a few times to ensure
Get clearance and “GO” signal with Shift Supervisor On-duty for start-
up activation.
contact with the flywheel and alternator shaft, and no one is standing
in front of the indicator cock openings to prevent spraying fuel vapors at
them.
Push the starting button for a short period or for at least three [3]
cylinder).
Pull the emergency stop button and push the reset button.
Pull the emergency stop button and push the reset button.
Note: Lubricating oil pressure must be at least 4 bar at this point, turn pre-
Start-up raw water pumps and maintains the level of the cooling
water pond.
bar).
Check the water flow at the nozzle and jacket water expansion tanks.
Check if the temperature for the jacket water reaches 60 ºC and lube
bus.
Note: During change over and until the required preheating temperature has
standard parameters)
thermal stressing.
Open/trip the generator circuit breaker just before the KW-hr meter
Let the generator run for at least 10 to 15 minutes to cool down the
engine.
Bring down the engine speed gradually and press the emergency stop
button.
Open all indicator valves to release air from the cylinders. The engine
Note: Allow all remaining pumps to run about 10 minutes or until the engine
cools down.
Push control buttons of the following to “OFF” position.
2.3.2. Maintenance
“OFF” position.
Open all indicator cocks on the cylinder heads and leave in this
Engage turning gear (gear pinion must bee in engage position) and
doors.
Prior to turning the crankshaft with the turning gear, make sure that
When carrying out maintenance works, use the tools and devices
conditions.
Hydraulic tools are to be checked from time to time for tightens and
perfect functioning.
pipelines, oil holes, etc., they must be temporarily closed off in order
Pipes that have been removed have to be checked for tightness after
refitting.
When tightening studs, nuts or bolts, the utmost care must be taken
not to damage their threads and that they can be screwed in by hand
to be used.
Locking devices of bolts, nuts etc. must correctly and carefully fitted.
which will not harden but still has good resistance to water, oil and
fuel.
The threads of bolts or studs which will be very hot when the engine
I. ENGINE:
Model 12 ZV 40/48
Number of cylinders 12
Note: The nominal power of the engine corresponds to the operating instructions of ISO 3046.
Under the above conditions and assuming a calorific value of 42.707 Kj/Kg., the specific
Lube-oil consumption - the consumption in the lube system of the working face of the cylinders
NR E 723315 93-06
IP 44
ISOL B
Temperature 45 oC
Weight 42 kg
HT No. 400642/400645
Bearing W14-Z
Mass 1280 kg
II. GENERATOR
BRUSHLESS AC GENERATOR
Frame M8-28
Voltage 13,800 V
RPM 600
Amp. 329
Phase 3
Wire 6
Hz 60
Duty Continuous
Class Ins. F
Rise by Res.
Amb. temp. 40 oC
BRUSHLESS EXCITER
Type FRBA
Frame BE 16-6
kW output 50
DC volts 250
DC amperes 200
Class Ins. F
Temp. rise 80 oC
Shaft rotation (clockwise) facing opposite drive end will produced phase sequence T1, T2, T3
Equipped with 220 V space heaters watts 2250; phase 3; Hz 60;Leads Mariced SH1 & SH2 & SH3.
ESTIMATED WEIGHTS
ELECTRICAL FEATURES
1. Damper windings
3. Capable of operating at rated KVA and rated temperature rise at altitude of 3,300 ft. above sea level.
8. With clockwise shaft rotation facing opposite drive end unit will produce phase
SUCTION AIR
OFF LOCKER AIR-MAZE HEAVY DUTY OIL BATH AIR FILTER (2 units)
Mode: LP8050
Side outlet, complete with lowering oil sump facility, element inspection openings, oil level gauge and
Model: AIS25/600
AIR BOTTLE for 7 bar complete with safety valve and pressure gauge 15” diameter x 40” Length (ASME
Design)
CONDENSATE DRAIN
BEKOMAT model EPA 63 for high pressure operation. Size of inlet and outlet pipe 1/2” and a maximum
TECHNICAL SPECIFICATION
Specification: LESLIE (USA) Second Stage Regulator: 200 psig to 600 psig pressure range
WATTS (USA) Second Stage Regulator: 0 psig to 600 psig pressure range
AIR DRYER
HIROSS, refrigerated with an operating pressure of 10 bar; max. air flow rate of 300NL/min.; 60 Hz;
inlet air duct 15 oC; inlet air condition 60 oC; saturated pressure 7 bar; refrigerant - freon 12-12; inlet
and outer pipe size 1/2”ø.; equipped with automatic water drain separator on the inlet side and oil lubrication
Brand HIROSS
Model SAC-120
TECHNICAL SPECIFICATION
Connections 1/2”
Max. working
pressure 16 bar
Weight 0.86 kg
FILTER
MATS 3 in 1 dry Filter suitable for spray painting booth with auto drain
TECHNICAL SPECIFICATIONS
COOLING TOWER
Model ANS-G-150-250
Head 30 m
RPM 1750
Motor WEG motor, SN: 017991; Model: 225SM0593; Type: ET; 60 Hz; 60 hp, 1776 rpm;
220/440 V; 146/73 Amp; SF: 1; Code H; INS: B; Amb temp: 40 oC; ENCL TEFC
Model ANS-G-150-250
Head 30 m
RPM 1750
1765; Amb. temp 40 oC; Bearing 6313 6213, Serial No. 7343700002
Model 165; 12” Ø, cast iron body simplex basket strainer, 125 # ANSI (WO6200 psi. @ 150 oF), flange end,
Type M10-MFM
Maximum working
Maximum working
temperature 95 oC
Raw water capacity 180 m3/hr
Model 6BOCB17001-00-ADQ
Motor 3 MOT 180 M 0295 AA47338; 30 Hp; 3 phase; 220 V; 60 Hz, Code J; Type ET;
SFA 91.2/45.6 A
CIRCULATING PUMP
Item no. 210723
Cap Head
Motor 3 MOT 160 L 0595 AE16853; 20 Hp; 220 V; 60 Hz; Code J; Type ET; 1700 rpm;
Capacity 570 L
Capacity 6 m3/hr
Head 3 bar
Motor 3 MOT 112 M 0295 AA55288; 5 Hp; 3 phase; 220 V; 60 Hz, Code J; Type
SN 95/0001
Capacity 6 m3/hr
Head 3 bar
Motor : WEG 3 MOT 112 M 0295 AA55292; 5 hp; 3 phase; 220 V; 60 Hz; Code J, Type
HEATER : 10 KW
NOZZLE COOLING EXPANSION TANK
Capacity 570 L.
Bowl 554057-03
Made in Italy
Power consumption
- Idling 5.3 kW
The prescribe speed of the worm-wheel shaft, which must not be exceeded, is stamped on the name plate of
the machine
Table of rpm @ 50 Hz 60 Hz
KRAL
A 6893 Lustenau
Type K32.21
Nr Y1619S
RPM 1450
Pressure 4 bar
Viscosity 75 mm2/s
Motor ABB motors LR IP55; 3 phase; 60 Hz; 1.3 kW; CL F; 220 volts, 5 Amp; SN
KRAL
A 6893 Lustenau
Type K32.21
Nr A 2028 S
RPM 1450
Pressure 4 bar
Viscosity 75 mm2/s
Motor ABB motors LR IP55; 3 phase; 60 Hz; 1.3 kW; CL F; 220 volts, 5 Amp; SN
SN 523640
Flow 60 m3/hr
Hp 40; 1770 rpm; 52.2 Amp.; Phase 3; 60 Hz; 220 V; DSGN B; Type P;
OIL COOLER
Type M15-BFM8
Maximum
Size 60 microns
Working pressure 4.5/6.5 bar
Working Temp 55 oC
Volume 2 x 5 m3 (2 x 50 li)
Model 6BOC13001-00-AA
Dimension 90 cm x 60 cm x 75 cm
Capacity 400 L
Capacity 7500 L
Capacity 2875 L
SN 10486157
Flow 3 m3/hr
Motor Baldor Industrial motor; 3 phase; Cat no. M3615T; Spec. 6G784W415;Frame
40C Amb-Cont.
Flowchart 5108006
Weight 1300 kg
Component Specification
Manually operated three-way valve for change over between HFO/MDO. The valve is fitted with limit
2. Supply Pumps
Pressure 4 bar
EL motors ABB MT 80 A
4. Flow Meter
5. Deaeration System
Level Switch
Safety Valve
6. Circulating Pumps
Viscosity 20 cSt.
El. power 72 kW
Viscosity transducer
The VCU-160 alarms are divided into process and system faults:
steam heater
electric heater
Filter Arrangement
Alarm Cabinet
The alarm cabinet panel has two outgoing group alarms, group A and B. Alarm indications on alarm panel:
High diff. pressure across the auto. filter viscosity system failure
Instruments pressure switches for stand by control test cocks included pressure gages at the
pump and at the fuel oil outlet differential pressure switch for high diff. pressure alarm across the auto filter
Level switch for low oil level in the deaeration pipe
Thermometers after the supply pump unit, the circulating pump unit and each heater
Materials
Module frame and leakage basin are welded from profile steel Fe 37 B.
Before painting with epoxy painting “RAL 5019”, the frame is sand blasted
Pipe
The pipes and welding are grinned, cleaned, acidified and passivated. Finally they
Instrument pipes
Insulation
Heat tracing
The heavy fuel oil pipes are el. trace heated with thermostat regulated el. cables.
Capacity 6500 L
Model HL 4195
Flow 5 m3/hr
Motor WEG. 3 phase Induction motor; type ET; Model 132S 0293; freq. 60 Hz; 5 Hp; 1160
rpm; 220/440 volts; 16/8 amperes; SF 1.2; SFA 18/9; Code K; INS B;
ID 2200 mm
Plate thk. 6 mm
Height 50000 mm
ID 904 mm
Plate thk. 6 mm
Height 17000 mm
DUCTING
ID 650 mm
EXPANSION BELLOWS
2. Cooling Water
COOLING TOWER
CHIMNEY