Pagariya HVAC System Lify Cycle Cost Analysis-R2
Pagariya HVAC System Lify Cycle Cost Analysis-R2
Pagariya HVAC System Lify Cycle Cost Analysis-R2
TOTAL 208.0
Subject : Chiller System Comparison
System Proposal
OPTION I OPTION II- Air cooled OPTION III OPTION IV
SR. NO DESCRIPTION Hybrid Chiller system screw chillers With CPVS Air cooled screw chillers Air cooled screw chillers
With CPVS Pump Pump With VP Pump With VP Pump
B System
System Hybrid System Air cooled Chillers Air cooled Chillers Air cooled Chillers
140 TR x 1 - WC
Configuration 140 TR x 2 - AC 140 TR x 2 - AC 100 TR x 2 - AC
140 TR x 1 - AC
C Cooling Towers
Induced Draft Counter Flow
Type of Cooling Towers
/ Cross Flow
D Condenser Pumps
Type of Pumping Constant Flow NA NA NA
E Primary Pumps
Type of Pumping Constant Flow Constant Flow Variable Flow Variable Flow
F Secondary Pumps
Type of Pumping Variable Flow Variable Flow NA NA
210 TR
NA
210 TR
265 HP
NA
NA
NA
NA
Corporate Office Project of M/s Pagariya Group at Nagpur
Subject : Chiller System Comparison
CAPITAL COST
TOTAL LOAD
Total Load 200TR 200TR 200TR 200TR 265 HP
Selected Chiller Capacity 280TR(140x2) 280TR(140x2) 280TR(140x2) 200TR(100x2)
Water Cooled Chillers
Capacity 140 TR NA NA NA NA
Capital Cost - 1 No. 2940000 NA NA NA NA
Lifting / Shifting of Chillers 40000 NA NA NA NA
Total Cost 2980000 NA NA NA NA
Nos. of Chillers 1 NA NA NA NA
Total Capital Cost 2980000 0 0 0 0 ###
Air Cooled Chillers
Capacity 140 TR 140 TR 140 TR 100 TR NA
Capital Cost - 1 No. 3220000 3220000 3220000 2300000 NA
Lifting / Shifting of Chillers 40000 40000 40000 40000 NA
Total Cost 3260000 3260000 3260000 2340000 NA
Nos. of Chillers 1 2 2 2 NA
Total Capital Cost 3260000 6520000 6520000 4680000 0 ###
Cooling Towers
Capacity 175 TR NA NA NA NA
Capital Cost - 1 No. 525000 NA NA NA NA
Lifting / Shifting of Cooling Towers 50000 NA NA NA NA
Total Cost 575000 NA NA NA NA
Nos. of Cooling Towers 1 NA NA NA NA
Total Capital Cost 575000 0 0 0 ###
Condenser Pumps
Capacity 420 GPM NA NA NA NA
Capital Cost - 1 No 150000 NA NA NA NA
Lifting / Shifting of Pumps 5000 NA NA NA NA
Total Cost 155000 NA NA NA NA
Nos. of Condenser Pumps 2 NA NA NA NA
Total Capital Cost 310000 0 0 0 0 ###
Primary Pumps (Constant)
Capacity 280 GPM 280 GPM NA NA
Capital Cost - 1 No. 150000 150000 NA NA
Lifting / Shifting of Pumps 5000 5000 NA NA
Total Cost 155000 155000 NA NA
Nos. of Primary Pumps 2 2 NA NA
Total Capital Cost 310000 310000 0 0 ###
Primary Pumps (Variable)
Capacity NA NA 280 GPM 200 GPM NA
Capital Cost - 1 No. NA NA 210000 200000 NA
Lifting / Shifting of Pumps NA NA 5000 5000 NA
Total Cost NA NA 215000 205000 NA
Nos. of Primary Pumps 2 2 NA
Total Capital Cost 430000 410000 ###
PLC (Including CPM) 950000 950000 950000 950000
Total Capital Cost 950000 950000 950000 950000 0 ###
Secondary Pumps (Variable)
Capacity 280 GPM 280 GPM NA NA
Capital Cost - 1 No. 170000 170000 NA NA
Lifting / Shifting of Pumps 5000 5000 NA NA
Total Cost 175000 175000 NA NA
Nos. of Primary Pumps 2 2 NA NA
Total Capital Cost 350000 350000 0 0 ###
Condensed Water Piping & Accessories
Approximate Rmts 90 NA
Capital Cost (Rs. 9000 / Rmt) 810000 0 0 0 NA ###
Chilled Water Piping
Approximate Rmts
Capital Cost 2340000 2340000 2340000 2340000 0 ###
AHUs and Valve Accessories
AHUs-10 3000000 3000000 3000000 3000000
VRF System
ODU Capacity 26 HP X10 ###
Cost of ODU 4940000
Customized VRF based AHUs 4000000
Copper Piping (Considering ODU
1470000
@ each floor)
###
SUB TOTAL
Total System Cost in Lakhs 148.85 134.7 132.4 113.8 104.1 ###
* For VRF option, air distribution has been considered with the customized VRF based CSU.
Corporate Office Project of M/s Pagariya Group at Nagpur
Subject : Chiller System Comparison
OPERATIONAL COST
OPTION I OPTION II- Air OPTION III OPTION IV
Hybrid Chiller cooled screw Air cooled screw Air cooled screw OPTION V
system With CPVS chillers With CPVS chillers With VP chillers With VP VRF
Pump Pump Pump Pump
TOTAL LOAD
Total Load 200 TR 200 TR 200 TR 200 TR 265 HP
Selected Chiller Capacity 140TR(140x2) 140TR(140x2) 140TR(140x2) 100TR(100x2)
Chillers Power Consumption LT
Water Cooled Chiller - Kw/ TR @ 70% 0.50
Air Cooled Chiller - Kw/ TR @ 70% 1.05 1.05 1.05 1.05
VRF System -kW/TR 0.90
Total WC Power Consumption 50
Total AC Power Consumption 105.00 210.00 210.00 210.00
Total VRF Power Consumption 238.5
Total System Power Consumption per Annum 404550 548100 548100 548100 622485
Cooling Tower Power Consumption
Cooling Tower - Kw/ TR 0.036
Total CT Power Consumption 6.3
Condenser Pumps
Capacity - GPM 300
Head in feet 32.8
Power Consumption 2.65
No. of Pumps Working 1
Total Condenser Pump power consumption 2.65
Primary Pumps - (Constant)
Capacity - GPM 200 200
Head in feet 32.8 32.8
Power Consumption 1.8 1.8
No. of Pumps Working 2 2
Total Pump power consumption 3.54 3.54
Primary Pumps - (Variable)
Capacity - GPM 200 200
Head in feet 82 82
Power Consumption 4.4 4.4
No. of Pumps Working 2 2
Total Primary Pump power consumption 8.84 8.84
Secondary Pumps - (Variable)
Capacity - GPM 200 200
Head in feet 49.2 49.2
Power Consumption 2.5 2.5
No. of Pumps Working 2 2
Total Pump power consumption 4.95 4.95
AHUs/FCUs
Fan Power 75.00 75.00 75.00 75.00 75.00
System
Total Power consumption NA NA 238.5
Total Power consumption per Hour 92.44 83.48 83.84 83.84 75.00
Hours of usage in a day for 10 10 10 10 10
Annual run Days chiller 261 261 261 261 261
Annual run Days only using Two stage cooling
tower
Unit cost of Electricity (Assumed ) 9.0 9.0 9.0 9.0 9.0
Diversity on the total working hours 0.8 0.8 0.8 0.8 0.8
Annual cost for Power 4649806 5515153.37 5521796.42 5521796.42 5891292.00
Water Treatment Cost for HVAC purpose
Water requirement for cooling Tower at peak load
12
- CM/D (24 hrs.)
Water requirement for 1600 hours of adiabatic
cooling system operation during peak summer 1600000 1600000 1600000
and warmer months. (In Ltr)
Annual cost of water @ Rs. 0.1 / Ltr 313200 160000 160000 160000
Water Treatment Cost 315000
Since ODUs are located at each floor level More ODU are
required to meet the demand and the equipment to
5 Equipment required for 300 TR Less and limited to maximum of 3 units. oversized to meet the air flow rate and duration in cooling
capacity is high to high ambient conditions ( Hyderabad)
Approximately 2 to 3 ODUs / floor.
Considered part of chiller system and can be met without Capacities to enhanced to meet the air volume for critical
6 Cooling for critical rooms
increasing the capacity room requirements.
7 Diversity Diversity has been considered as per ASHRAE 90.1 office Limited and no diversity can be applied with customised
schedule. CSU or AHU.
8 Maintenance
8.1 Quality of maintenance required Easy to maintain Expensive to maintain due to refrigerant leaks.
8.2 Frequency of maintenance required Periodic maintenance is required Periodic maintenance is required
9 Redundancy and reliability Available as the chillers are with Twin Compressor. Critical Less compared to the Chiller System.
loads can be served by one compressor.
10 Chemical Treatment Required for water cooled chillers only Not required
11 Make-up Water requirements Required for water cooled chillers only Not required
12 Connected Power Less High
13 Overall Life Expectancy Longer life expectancy (typically 20 to 25 years). Average (typically 10 to 12 years)
14 Efficiency Higher Moderate
15 Refrigerant Leakage Low and limited to chiller only. High and results in major breakdown and loss of cooling to
the entire floor.
Restricted to AHU and condensate water leakage will be a Condensate water leakage will be concern if CSU are
concern if CSU are opted opted.
16 Water Leakage Potential threat of refrigerant leakage and the units to be
Potential threat to false ceiling if chilled water fed CSU is selected to meet the ASHRAE Std 15 compliance. Higher
opted
volume refrigerant leaks can harm human beings.
17 Management Easy to manage and interface with BMS Limited access for management and interface with BMS