8.Scheduling: scheduling ensure that parts and sub- Scheduling production processes.
assemblies and finished goods are completed as per Prioritize product order to be processed.
required delivery dates. It provides a timetable for BOM for components to be processed.
manufacturing activities. Determine raw material specifications.
Identify sources (machine, Equipment and man)
for processing.
Determine process required and their sequence.
Estimate process durations and total time for
completion.
Determine processes to be out sourced.
Schedule inspection and supply of material to
sub contractors.
Prepare assembly plan to arrive dispatch date to
match customer required date.
Based on assembly plan derive need by dates for
sub-assemblies, machined components and
direct assembly components.
Major modules like sub-assembly, fabrication,
electrical, machine shop shall make their
schedules based on need by date, processing
time, required outsourcing, qty etc.
Operators shall be participating in planning and
scheduling.
Cushioning for process time shall be given on the
basis of risk assessment.
Contingency plans are determined to deploy at
required time.
Maintenance (of machines and equipment) and
training (for staff and operators) schedules to be
taken care off.
Determined schedule may be tracked through
updating Route card, Process card, and project
progress report and reviewed for correction.