Fly Ash Work Order
Fly Ash Work Order
Fly Ash Work Order
WO No: SRKCPPL/CWP/WO/2022-047
Date: 21/12/ 2022
To
SHUBHAM RAJESH MESHRAM
LOT NO J/66, UPPALWADI,
PRAVESH NAGAR WANJARI LAYOUT,
Nagpur, Nagpur, Maharashtra, 440026
Ph. No:
PAN No:
GST No: 27ERGPM5874K1Z1
Work Order for Supply of Fly Ash at Chimur – Warora NH-353E project – Reg.
Ref:
Dear Sir,
We here with give the work order for Supply of Fly Ash with Bulker mentioned
in the above subject as per the following mutually agreed rate and enclosed terms and
conditions.
PRICE SCHEDULE:
1. Payment cycle will be month and will be released within 15 days from the date
certification of the invoice by the Project Manager at site.
2. The above price is exclusive of GST and the sub-contractor must furnish the GST
particulars and GST for the next invoice certificate require and giving input of
carrying invoice only.
3. An amount equal to 5% shall be retained from the running bills towards security
and to be refunded to the Sub-Contractor after completion of work and
finalisation of account.
1. Mobilization Period will be one week from the date of issue of this work order.
2. SRK reserves the right to terminate the contract in case of failure by the Sub-
Contractor i.e. delay in delivering the targets, workmanship etc., without
assigning any reasons.
Kindly sign a duplicate copy of this Work Order as token of your acceptance
Thanking you
For
SRK Constructions & Projects Pvt. Ltd.
Authorized Signatory
Name : Date:
Signature : Place: