PC: 237323
ITEM: Air Handling Unit
ID: AHU-2
AREA SERVED: Archive Storage (Secured Stacks High Bay)
The above equipment and systems integral to them are complete and ready for functional testing per
Mechanical and Controls Contractors. The prefunctional checklist items are complete and have been
checked off only by parties having direct knowledge of the event. This construction checklist is
submitted for approval, subject to an attached list of outstanding items yet to be completed (See Notes
and Associated Project Issues Log). None of the outstanding items preclude safe and reliable
functional tests being performed.
This Checklist does not take the place of the manufacturer’s recommended checkout and startup
procedures or report. Construction checklist items are to be completed as part of startup and initial
checkout.
Approvals. This filled-out checklist has been reviewed. Its completion is approved with the exceptions
noted below.
Components Included
Comments:
Mode ID Pass
Test Procedure Response Note #
(including special conditions) Y/N
AHU Scheduling Verify scheduling of unit on BMS.
In Occupied Mode: Unit is scheduled 24/7
Verify supply and return fans are on, Alarm generated to the BMS Y
outside air damper is open.
Put fan(s) in off manually; verify alarm at
BMS upon fan failure.
Unoccupied Record heating and cooling set points in
unoccupied mode:
Unocc HTG:
Unocc CLG:
Schedule unit in unoccupied mode.
Verify supply and return fans are off, the
heating and cooling coil valves are N/A
closed, the outdoor air damper is closed,
the return air damper is open, and the
exhaust air damper is closed.
Mode ID Pass
Test Procedure Response Note #
(including special conditions) Y/N
Record airflow variation: Y
Adjust building pressure setpoint. Allow
unit to stabilize.
Verify return fan speed modulates to
maintain building static pressure setpoint.
Verify return airflow monitoring station
modulates accordingly.
Record building pressure setpoint: Y
Record building pressure setpoint
adjustments made for testing:
Record airflow variation:
Outside Air Verify outdoor air damper modulates to
maintain TAB minimum outdoor airflow.
Record cfm from BMS: Y
Override outdoor air damper to 0%, start
unit from unoccupied.
Verify supply fan does NOT start unit
outdoor air damper is verified open.
Return Air Override return air damper to 0%, start
unit from unoccupied.
Verify supply fan does NOT start unit Y
return air damper is verified open
Discharge Air Adjust discharge air temperature as
Temperature / required. Allow unit to stabilize between
Economizer variations.
Verify outdoor damper, relief air damper,
heating coil valve, and cooling coil valve 55 deg. F. D.A.T. S.P. Y
operate in sequence to maintain
discharge air setpoint.
Record discharge air temperature
setpoints (55°-65°F) and reset schedule:
Mode ID Pass
Test Procedure Response Note #
(including special conditions) Y/N
are at minimum position, relief damper is
closed, and return damper is open.
1. Safety/Smoke detection alarm shut down not commissioned, devices verified by Fire Marshall testing.
2. R.A. humidity was 40%, S.A. humidity was 51%.
3. Regen H.W. coil was maintaining 38 Gr./# leaving desiccant wheel condition. (38.1 Gr/# S.P.)
4. Regen desiccant wheel pressure drop was 1.83” w.c.
5. 1.38” w.c. exhaust duct static pressure.
6. Regen O.A. volume was 4,634 CFM. (setpoint = 4,850 CFM)
7. Regen heating loop temperature was 126.7 deg. F.
8. E.A.T. after desiccant wheel was 89.2 deg. F., 124.8 deg. F. entering desiccant wheel E.A.T.
9. Filter bank pressure drops were: FG-1=.17”, FG-2=.60”, FG-3=.20”, FG-4=.50”