Operationmanagementproblems 131216134550 Phpapp02
Operationmanagementproblems 131216134550 Phpapp02
Operationmanagementproblems 131216134550 Phpapp02
OPERATION
MANAGEMENT
PRACTICAL PROBLEMS
Tips and tools for solving.T.VENKATARAMANAN.FCA(COST)
Old syllabus
2
DATA Ans:
ANNUAL demand 10,000 units
1)400
CARRYING COST P.A of 2)2* 40 + 5* 40=280
component x = Rs 40/=
Ordering cost Rs 320/order.
250 WORKING DAYS IN THE
YEAR
LEAD TIME =5 days
Safety stock = 2 days
HMT bearings is committed to supply 24,000. bearings p.a
to M.ltd.on a daily basis .It costs as Re1/= as inventory
5
holding per month.set up cost per run=3240/=
compute 1)ERL SIZE.2)INTERVAL BETWEEN 2 RUNS
3)MINIMUM INVENTORY HOLDING COST
Problem No. 6
CALCULATE 1)EOQ 2)EXTRA COST IF ORDERING QUANTITY IS 4,000.
3)MINIMUM CARRYING COST
7
MONTHLY Ans:
CONSUMPTION=250 UNITS
EOQ = 300 UNITS
CARRYING COST 10% OF
PRICE WHICH IS RS 10. ORDERING COST = 150
ORDERING COST RS 15/= CARRYING COST = 150
COST OF MATERIAL
=30,000
TOTAL COST = 30,300
PROBLEM 3/161
9
The demand for a component is random .It has been estimated that the monthly de
Has a normal distribution with a mean of 680 & a std. deviation of 130 units.The pric
is Rs 10/= & ordering cost Rs 20/= carrying cost is 25% p.a.
The procurement lead time is constant & is one week.find the EOQ,expected total c
of controlling the inventory at 97.5 % service level
Term
What is a scanlon plan?
Definition
type of gain sharing program in which employees receive a bonus if the rati
labor costs to the sales value of production is below a set standard.
Compute the amount available to be paid as
bonus under Scanlon plan for 2007
16
details
Hrs worked /day 8 If plant is operated
Working days in a month 25 @75% efficiency
What is the output
No . of operator 1 Per month (2)if m/c
Std minutes /unit.m/c time 22 Productivity is
Operator time /efficiency 8 min/efficiency 100% increased by 20%
What is the output ?
Total time /unit 30 min 3)If operator efficiency
decreased by 20%
What is the output?
solution
19
1) 8*25*75/100=150*60/30=300
The factory operates 8 hours for 6 days in a week.If u want to produce 2000 bushes/wee
What will be the % of spare capacity available in each type of m/c tool
solution
m/c lathe Milling Drilling Remarks
Hrs in a 48 48 48
week8*6
Available 95% 75% 75%
Hrs
stdHrs/bus 0.15 0.20 0.10
21
22
A LTD. Manufactures a component which passes through 3 m/c s P Q &
R.
THE STANDARD TIME OPERATOR EFFICIENCY etc ARE AS
23
FOLLOWS:
DETAILS
MACHINES Std. hrs Operator
/component efficiency
P 0.16 80%
Q 0.23 100%
R 0.09 90%
The factory operates 2 shifts of 8 hrs ,6 days in a week to produce 4000units, per w
Compute the no. of machines & available time if any for other jobs.
A soap factory is following a piece rate system for its packing section, the
24
rate being Re0.10/=there is a guaranteed wage of Rs200/per day.
Worker A B C D Total/gr
oup
WAGE 200 200 200 200 1)Productivity of C
S Is poor.
Incentiv 80 60 10 70 2) Average or group
e Is ok
Total 280 260 210 270 1020
Averag 1020/2200
0.46
e cost
Labour 80/12 60/12 10/12 70/12 55/12
producti 667% 500% 83.33% 583.33 458.3%
Productivity of material
26
32
SOLUTION NO4.
33
(b)If jigs are redesigned time for b will become 12 from 13.
Output of B = 440/12 = 36.66.increase % = 3/33* 100= 9%
So not worthwhile
( c) if production to be increased one more m/c B TO BE ADDED.
PROB NO 5.
34
As on 1st aug the following jobs are to be processed .the processing time & due
dates are As follows :
Jobs A B C D
SEQUENCE
PROCESS 2 6 7 12
TIME IN
C
DAYS QD D
DUE DATE AUG 12 AUG 7 AUG 4 AUG8 B
A
Sequence ratio
jobs on
minimum
TIME 11 6 3 7
REMAINING
Time needed to complete the jobsA-2 ,B-6, C-7, D-12
CRITICAL RATIO A-11/2=5.5,B1.,C-3/7=0.43, D=0.58
Problem-8 –location of plant.
38
Two locations A & B are considered for location of a medical testing equipment
Fixed costs Rs25 30 laks.
Variable 300 250 .average selling price of equipmentRs 550/ unit
Compute Range of annual production & sales volume for which location is most suitab
A SHAFT OF 3000 MM LENGTH requires machining on lathe .If the spindle execu
1500 rpm & the feed is .20 mm per revolution ,how long does the cutter take to pas
down the entire length of the shaft.
Q. 3. (a) Explain how you would choose a material handling equipment from amongst alternative offers.
(b) Prasad Timber Works uses forklift trucks to transport lumber from factory to a storage area 0.3
km away. The lift trucks can move three loaded pallets per trip and travel at an average speed of
8 km. per hour (allowing for loading, unloading, delays and travel). If 640 pallet loads must be
moved during 8 hours shift, how many lift trucks are required? Assume single shift working and
300 working days in a year.
47
Answer 3. (b)
Total distance travelled by fork lift truck per trip = (0.3+0.3) km = 0.6 km(up and down
No. of trips that can be made by the truck per shift = 8km/0.6km × 8hrs = 106.66 trips
\ No. of pallet loads carried per shift by each truck = 106.66 × 3 = 319.98 = 320
\ Total no. of fork lift trucks required for 640 pallet loads = 640/320 = 2 fork lift trucks.
Answer 3. (c)
(i) Electric Arc Furnace.
(ii) Electromagnet
(iii) Forging machine
(iv) Drilling machine
(v) Slotting machine
48
Q. 4. (a) What factors will have to be considered in choosing the location for the following industries?
(i) Aluminium industry.
(ii) Thermal power plant.
(iii) Large furniture(domestic and office)manufacturing unit.
(b) Empire Glass Company can produce a certain insulator on any three machines which have the
following charges shown below . The firm has an opportunity to accept an order for either (1) 50
units at Rs. 20/unit or (2) 150 units at Rs. 12/unit.
Machine Fixed Cost (Rs) Variable Cost(Rs)
A 50 4/unit
B 200 2/unit
C 400 1/unit
(i) Which machine should be used if 50 units order is accepted and how much profit will result?
(ii) Which machine should be used if the 150 units order is accepted and what will be the resultant
profit?
(iii) What is the break-even volume for machine B when the price is Rs. 12/unit?
(iv) Suppose the fixed cost for machine A is a stepped function with Rs. 50 up to 40 units and
Rs. 100 thereafter. Will the answers to (i) and (ii) above vary? If so, what will be the revised
answer?
49
Answer 4. (a)
The general factors to be considered for any Industry location are the following :
1. Proximity to raw material sources
2. Availability of critical input required for the process
3. Proximity to the Market
4. Availability of skilled labour
5. Special tax and other financial benefits available in a location
6. Central/state/municipal regulations.
While all the above factors are important for all Industries, some factors will be
dominant for some industries as explained below :
50
1. Aluminium Industry is a power intensive industry. Hence the region/location
2. where availability of power is a very critical consideration for the choice of location
Likewise, proximity to raw material source namely bauxite is also a vital consideration.
2. For thermal plant proximity to coal mines is very important since transportatio
of huge quantity of coal every day is very costly and difficult. Equally important is the
availability of abundant quality of water for the boiler.
3. For furniture industry proximity to the Market is a crucial factor apart from othe
While transporting finished furniture, damages may take place and also it will be bulky
and occupy more space and hence costly. Therefore furniture units are located nearer
towns and cities nearer to offices and houses.
51
Answer 4. (b)
(i) For 50 unit order at Rs. 20/unit.Costs for various machines :
Machine Rs. Profit Rs.
Machine A 50 + 50 × 4 = 250, 1000 – 250= 750
Machine B 200 + 50 × 2 = 300, 1000 – 300= 700
Machine C 400 + 50 × 1 = 450, 1000 – 450= 550
Since Machine A gives the highest profit of Rs. 750 it is to be preferred.
(ii) For 150 unit order at Rs. 12/unit.Costs for various machines
Machine Rs. Profit Rs.
Machine A 50 + 150 × 4 = 650, 1800 – 650 =1,150
Machine B 200 + 150 × 2 = 500, 1800 – 500= 1,330
Machine C 400 + 150 × 1 = 550 ,1800 – 550= 1,250
Hince Machine B to be preferred.
(iii) Breakeven Volume for Machine B at Rs. 12/unit.
Let X be the No. of units to be produced.Total costs at ‘X’ units = 200 + 2x
Total revenue at x units = 12x.
At Breakeven point.
200 + 2x = 12x i.e 10x = 200
x = 20 Hence 20 units is the Breakeven Volume.
52
(iv) The fixed cost for machine A being a step function, the total cost of manufacturing o
50 units with machine.
A = 100 + 50 × 4 = Rs. 300, which is also the cost of production with machine B.
Thus either of the two machines A or B could be chosen to produce 50 units.
A will be Rs. 700, which is higher than the production cost on machine B.
Hence the answer in this case will not vary.
53
(b) A Company adopts a counterseasonal product strategy to smooth production requirements. It
manufactures its spring product line during the first four months of the year and would like to
employ a strategy that minimises production costs while meeting the demand during these four
month. The Company presently has on its rolls, 30 employees with an average wage of Rs. 1,000
per months. The Company presently has on its rolls, 30 employees with an average wage of
Rs. 1,000 per month. Each unit of the product requires 8 man-hours. The Company works on
single shift basis (8 hrs. shift/day). Hiring an employee costs Rs. 400 per employee per occasion
and discharging an employee costs Rs. 500 per person per occasion. Inventory carrying costs are
Rs. 5/unit/month and shortage costs are Rs. 100/unit/month and shortage costs are Rs. 100/
unit/month. The Company forecasts the demand for the next four months as below :
Month (Demand units) No. of working daysin the month
jan 500 22
February 600 19
March 800 21
April 400 21
The Company is thinking of adopting one of the following pure strategies :
Plan I : Vary work force levels to meet the demand.
Plan II : Maintain 30 employees and use inventory and stockouts to absorb demand fluctuations.
Which strategy would you recommend? You may assume nil inventory at the start.
54
The overall costs of both the strategies are computed in the following tables.
Plan I, varying the work force levels to suit the production needs :
January February March April Total
1. Workers required 22 500
= 23 19 600
= 32 21 800
= 38 21 400
= 19
2. Labour cost 23,000 , 32,000; 38,000 ;19,000 ;=1,12,000
3. Hiring costs 9 × 400 6 × 400
= 3,600 = 2,400 6,000
4. Lay off costs 7 × 500 19 × 500
= 3,500 = 9,500 13,000
Total 1,31,000
Plan II : Maintain a steady work force and use of inventory plus stock on
January February March April Total
1. Workers used 30 30 30 30
2. Labour cost 30,000 30,000 30,000 30,000 1,20,000
3. Units produced 660 570 630 630
4. Inventory costs 5 × 160 5 × 130 5 × 190 = 800 = 650 = 950 2400
5. Shortage costs 100 × 40 = 4,000 ; 4,000
Total 1,26,400 On the basis of costs, plan II would be the choice. Moreover this strategy would result in higher worker
morale, smoother production, and generally, a higher quality product.
55
Problem no.13
56
Job A B C D E
M/C 1 2 7 5 6 5
M/C 2 4 8 8 7 3
57
(i) Schematic Diagram : D F
A C H
E G
B
A-20 B-40
D-45 E= 20
F-25 G-10
H-35
(Activity on Node)
20 10
(ii) Theoretical minimum number of stations to meet D = 400 is :
N = T/C = 245/{(60 seconds 480minutes) 400units}
= 245 ÷ 72
= 3.4 day 4.
58
(b) Write short notes on :
(i) Line Balancing
(ii) Work Simplification
(iii) Progressing
(iv) Six Sigma quality programme
59
(iii) Line Balancing :
Station Task Task Time Unassigned Time Feasible Station Cycle time
(Seconds) (Seconds) Remaining Time (Seconds)
Task (Seconds)
1 A 50 22
C 70 70C 20 2 None
2 D 45 27
E, F 70 70F 25 2 None
3 B 40 32 E E 20 12 G 70 70
G 10 2 None
4 H 35 37 None 35 70
Total 245 280
(iv) Line Efficiency = (245/280) × 100 = 87.5%
Smoothness Index = (70 − 70)2 + (70 −70)2 +(70 −70)2 +(70 −35)2
= (35)2 = 35%.
60 Answer 6.
61
Answer 6. (b)
(i) This technique is employed to ensure balanced flow of production specially in Assembly lines.
When products require a number of operations to be performed , the time taken for each operation
may vary. Therefore if the line is not balanced , a few operators will be over loaded whose operation
times are long and others will be idling away their time.
This technique decides the cycle time for the products based on the output required per shift. This
also considers the sequence in which the operations will have to be carried out. Then Line Balancing
technique groups operations in such a manner that each group will have generally equal total task
times. Each group is called a work station and assigned to an operator. Thus all the operators in
each work station will have balanced load.
(ii) Work Simplification involves subdivision of an operation into its constituent elements in order to
simplify operations and eliminate wasteful motions. It reduces fatigue and improves productivity.
It covers all aspects of work, i.e equipment , layout , procedures , methods etc.
(iii) Progressing is the gentle but firm direction of ‘activities planned’ to proper channels, shielding
them from adverse factors inseparable from actual operations. The work of the progress department
starts where the planner’s ends. The Progress Controller/Progress Chaser , as he is called, is not
concerned with methods of carrying out operations(which are under the purview of the process
planning department) but the ‘doing’ of them at proper time in the correct order and at the lowest
anticipated cost. The duties of the Progress Chaser would vary widely from unit to unit. In a well
62
organized manufacturing activity, his duties consists of :
(A) recording of actual production or output against planned production;
(B) assessment of causes leading to activities falling behind schedule;
(C) reporting to appropriate authority;
(D) where possible , to foresee all that may lead to failure on schedules and to sound a note of
warning to all concerned.
(iv) Six Sigma Quality program is company- wide approach for continuous improvement in quality of
products and services. It measures the degree to which the process deviates from the standards
and takes efforts to improve the process to achieve customer satisfaction.
The objective of Six Sigma Quality programme are two –fold :
(i) to improve the customer satisfaction and reducing and eliminating gaps/defects and
(ii) to continuously improve processes throughout the organization with a view to reduce sources
of variation and improve quality as well as productivity.
It is a statistical measurement which tells us how good our products, services and process are and
enables us to benchmark our operations with the best in the field. It thus helps us to establish our
course in the race for total customer satisfaction.
A process at 6- Sigma level normally produces 3-4 non conformances in a million operations. This
is supposed to be the best-in-class quality. Thus 6-Sigma is essentially a philosophy of working
smarter. This means making fewer mistakes in everything we do. As we discover and eliminate the
sources of variation , the non conformances are eliminated and the process capability improves.
63
(c) The following cost have been recorded :
Particulars Rs.
Incoming materials inspection 10000
Training of personnel 30000
Warranty 45000
Process planning 15000
Scrap 9000
Quality laboratory 30000
Rework 25000
Allowances 10000
Complaints 14000
What are the costs of prevention, appraisal, external failure and internal failur
64
Problem on transportation
65
2)For F1W3=8-8+11-9+ 2
3)F2W3=9-11+9-7=0
4)F2W4=7-5+8-11=-4
5)F3W1=8-5+11-9=5
6)F3W4=13-5+8-11+9-7=7
F2W4 GIVES – VE VALUE
IBFS W-1 is the least
Costed un allocated
cell
By moving one unit
From W-2 to W-1
F/W W1 W2 W3 W4 Supply The cost /unit will
come down by Re 1
F1 6/ 8/10 8 5/20 30 But this will out
Shoot supply
F2 5/35 11/0 9 7 5 40 Therefore we move
F3 8 9/18 7/32 13 50 I unit from F2W1
TO F2W2.
Deman 35 28 32 25 120 The change in cost
d -8+6-5+11= 4
75
76
MODI METHOD.
77
DEMA 35 28 32 25 150
ND
V V1 V2 V3 V4
Answer 7. (c)
Particulars Rs.
Training of personnel 30000
Process planning 15000
Total cost of prevention 45000
Incoming materials inspection
10000
Quality laboratory
30000
Total cost of appraisal 40000
Scrap 9000
Rework 25000
Total cost of internal failure
34000
Warranty
45000
78 Allowances 10000
Complaints 14000
(c) An industrial engineer, deputed to conduct a time study for a job,
has, after observation, divided
(i) Are there any outliers in the data, i.e., probable errors in reading or recording data which
should not be included in the analysis?
(ii) Compute the basic time for the job and the standard time if a relaxation allowance of 12
79 contingency allowance of 3% and an incentive allowance of 20% are applicable for the job.
Basic time = 7.722 mins
Allowance = (12+3) = 15% (Incentive allowance not considered)
Standard time = 7.722 × 1.15 = 8.88 min (approx)
80
(c) A work sampling study is to be made of a data entry operator pool. It is felt t
operators are idle 30% of the time. How many observations should be made in
to have 95.5% confidence that the accuracy is within +/- 4%.
Answer 9. (c)
n = {4p(1-p)}/s2
p = 0.3
1– p = 0.7
s = 0.04
n = 4 × 0.3 × 0.7/(.04)2
= 0.84/.0016
= 525.
81
82
83
84
85
Widescreen Test Pattern (16:9)
Aspect Ratio
Test
(Should appear
circular)
4x3
86 16x9