Exercise On CPM and PERT
Exercise On CPM and PERT
Exercise On CPM and PERT
Consider a project involving the following activities and precedence relationship. The cost of each
activity is listed.
Duration (week)
Precedence Cost per week
Activity Optimistic Most likely Pessimistic
Activity ($/week)
(a) (m) (b)
A - 5,000 2 3 5
B A 3,000 3 5 8
C A 6,000 4 6 9
D B 2,000 1 2 4
E C 4,000 3 4 7
F D 7,000 1 2 4
G D 4,000 2 3 5
H G 8,000 1 2 3
J B,E 6,000 4 6 8
K E,F,H 5,000 2 4 7
L J 3,000 2 3 6
b) Use the CPM Forward and Backward Pass Computation as follows. The Critical Path is shown
(thick line path).
d) The cost distribution is conducted by assigning the cost of the activities per week (See
attached). The S-curve is plotted accordingly.
200,000
180,000
160,000
140,000
120,000
Early Start
100,000
Late Start
80,000 Target
60,000
40,000
20,000
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21