Primavera Project File

Download as pdf or txt
Download as pdf or txt
You are on page 1of 18

Kharmang 3MW HPP Penstock Pipe Classic Schedule Layout 15-Nov-22 07:29 PM

Activity ID Activity Activity Name Planned Remaining Schedule % Start Finish Total Float Qtr 4, 2022
Type Duration Duration Complete
Nov Dec Jan

Project: HPP 01 Kharmang 3MW HPP Penstock Pipe345 345 0% 30-Nov-22 06-Jan-24
12:00 AM A 04:00 PM
-7

WBS: HPP 01.1 Key Milestones 5 5 0% 30-Nov-22 08:00


05-Dec-22
AM 04:00 PM333 05-Dec-22 04:00 PM,

WBS: HPP 01.1.1 Contractual Milestones 1 1 0% 30-Nov-22 08:00


01-Dec-22
AM 08:00 AM337 01-Dec-22 08:00 AM, W
A1000 Start Milestone
Project Awarded 0 0 0% 01-Dec-22 08:00 AM* 337 Project Awarded, 01-De
A1010 Start Milestone
Notice to Proceed 0 0 0% 01-Dec-22 08:00 AM 337 Notice to Proceed, 01-D
A1020 Start Milestone
Kick off Meeting with Client 0 0 0% 01-Dec-22 08:00 AM 337 Kick off Meeting with Cl
A1030 Start Milestone
Mobilization Schedule Submission 0 0 0% 01-Dec-22 08:00 AM 337 Mobilization Schedule S
A1040 Start Milestone
Mobilization Starts 0 0 0% 30-Nov-22 08:00 AM 338 Mobilization Starts, 30-N
A1050 Finish Milestone
Mobilization Complete 0 0 0% 30-Nov-22 08:00 AM338 Mobilization Complete,
A1060 Finish Milestone
Mechanical Completion Date (MCD) 0 0 0% 30-Nov-22 08:00 AM338 Mechanical Completion
A1070 Finish Milestone
Project Completion Date 0 0 0% 30-Nov-22 08:00 AM338 Project Completion Date
WBS: HPP 01.1.2 Project Milestones 5 5 0% 30-Nov-22 08:00
05-Dec-22
AM 04:00 PM333 05-Dec-22 04:00 PM,
A1080 Start Milestone
Design Office Establishment 0 0 0% 30-Nov-22 08:00 AM 338 Design Office Establishm
A1090 Start Milestone
Mobilization Plan 0 0 0% 30-Nov-22 08:00 AM 338 Mobilization Plan, 30-No
A1100 Start Milestone
Detailed Work Procedure & Org Chart 0 0 0% 30-Nov-22 08:00 AM 338 Detailed Work Procedur
A1110 Start Milestone
Project Execution Plan 0 0 0% 30-Nov-22 08:00 AM 338 Project Execution Plan, 3
A1120 Start Milestone
Material Procurement Plan 0 0 0% 30-Nov-22 08:00 AM 338 Material Procurement Pl
A1130 Start Milestone
Procurement Phase QA/QC Plan 0 0 0% 30-Nov-22 08:00 AM 338 Procurement Phase QA
A1140 Start Milestone
Detailed Field Fabrication Plan 0 0 0% 30-Nov-22 08:00 AM 338 Detailed Field Fabricatio
A1150 Task Dependent
Field Material Control Plan 5 5 0% 30-Nov-22 08:00
05-Dec-22
AM 04:00 PM333 Field Material Control
A1160 Task Dependent
Hardware cutover plans 5 5 0% 30-Nov-22 08:00
05-Dec-22
AM 04:00 PM333 Hardware cutover plan
A1170 Task Dependent
Project Record Book 5 5 0% 30-Nov-22 08:00
05-Dec-22
AM 04:00 PM333 Project Record Book
A1180 Task Dependent
Complete PO Placement for Major Project Material 5 5 0% 30-Nov-22 08:00
05-Dec-22
AM 04:00 PM333 Complete PO Placem
A1190 Task Dependent
Material Take-off List 5 5 0% 30-Nov-22 08:00
05-Dec-22
AM 04:00 PM333 Material Take-off List
A1200 Task Dependent
Facility As-Built Drawings 5 5 0% 30-Nov-22 08:00
05-Dec-22
AM 04:00 PM333 Facility As-Built Drawin
A1210 Task Dependent
Complete Site Mobilization 5 5 0% 30-Nov-22 08:00
05-Dec-22
AM 04:00 PM333 Complete Site Mobiliz
A1220 Task Dependent
Complete 60% Detailed Engineering 5 5 0% 30-Nov-22 08:00
05-Dec-22
AM 04:00 PM333 Complete 60% Detaile
A1230 Task Dependent
Complete PO Placement for All Project Material 5 5 0% 30-Nov-22 08:00
05-Dec-22
AM 04:00 PM333 Complete PO Placem
A1240 Task Dependent
Complete 90% Detailed Engineering 5 5 0% 30-Nov-22 08:00
05-Dec-22
AM 04:00 PM333 Complete 90% Detaile
A1250 Task Dependent
Issue for Construction Drawing (IFC) 5 5 0% 30-Nov-22 08:00
05-Dec-22
AM 04:00 PM333 Issue for Construction
A1260 Task Dependent
Mechanical Completion Certificate 5 5 0% 30-Nov-22 08:00
05-Dec-22
AM 04:00 PM333 Mechanical Completio
A1270 Task Dependent
Pipeline Commissioning 5 5 0% 30-Nov-22 08:00
05-Dec-22
AM 04:00 PM333 Pipeline Commissionin
WBS: HPP 01.2 Mobilization 37 37 0% 30-Nov-22 08:00
11-Jan-23
AM 04:00 PM 301

Actual Level of Effort Remaining Work Page 1 of 18 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
Kharmang 3MW HPP Penstock Pipe Classic Schedule Layout 15-Nov-22 07:29 PM
Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
06-Jan-24 04:00 PM, Project: HPP 01 Kharmang 3MW HPP Pens

05-Dec-22 04:00 PM, WBS: HPP 01.1 Key Milestones


1-Dec-22 08:00 AM, WBS: HPP 01.1.1 Contractual Milestones
roject Awarded, 01-Dec-22 08:00 AM*
otice to Proceed, 01-Dec-22 08:00 AM
ick off Meeting with Client, 01-Dec-22 08:00 AM
Mobilization Schedule Submission, 01-Dec-22 08:00 AM
obilization Starts, 30-Nov-22 08:00 AM
obilization Complete,
echanical Completion Date (MCD),
roject Completion Date,
05-Dec-22 04:00 PM, WBS: HPP 01.1.2 Project Milestones
esign Office Establishment, 30-Nov-22 08:00 AM
obilization Plan, 30-Nov-22 08:00 AM
etailed Work Procedure & Org Chart, 30-Nov-22 08:00 AM
roject Execution Plan, 30-Nov-22 08:00 AM
aterial Procurement Plan, 30-Nov-22 08:00 AM
rocurement Phase QA/QC Plan, 30-Nov-22 08:00 AM
etailed Field Fabrication Plan, 30-Nov-22 08:00 AM
Field Material Control Plan
Hardware cutover plans
Project Record Book
Complete PO Placement for Major Project Material
Material Take-off List
Facility As-Built Drawings
Complete Site Mobilization
Complete 60% Detailed Engineering
Complete PO Placement for All Project Material
Complete 90% Detailed Engineering
Issue for Construction Drawing (IFC)
Mechanical Completion Certificate
Pipeline Commissioning
11-Jan-23 04:00 PM, WBS: HPP 01.2 Mobilization

Actual Level of Effort Remaining Work Page 2 of 18 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
Kharmang 3MW HPP Penstock Pipe Classic Schedule Layout 15-Nov-22 07:29 PM
Activity ID Activity Activity Name Planned Remaining Schedule % Start Finish Total Float Qtr 4, 2022
Type Duration Duration Complete
Nov Dec Jan
WBS: HPP 01.2.1 Office Facilities 31 31 0% 05-Dec-22 08:00
09-Jan-23
AM 04:00 PM303
A1280 Start Milestone
Start of Office Mobilization 0 0 0% 05-Dec-22 08:00 AM* 306 Start of Office Mobiliza
A1290 Task Dependent
Survey 2 2 0% 05-Dec-22 08:00
06-Dec-22
AM 04:00 PM306 Survey
A1300 Task Dependent
Cut & Fill 2 2 0% 07-Dec-22 08:00
08-Dec-22
AM* 04:00 PM306 Cut & Fill
A1310 Task Dependent
Grading 4 4 0% 10-Dec-22 08:00
13-Dec-22
AM* 04:00 PM306 Grading
A1320 Task Dependent
Back filling 6 6 0% 11-Dec-22 08:00
17-Dec-22
AM* 04:00 PM306 Back filling
A1330 Task Dependent
Install foundation for Site Office 6 6 0% 18-Dec-22 08:00
24-Dec-22
AM* 04:00 PM306 Install foundat
A1340 Task Dependent
Installation of Portable Cabin 6 6 0% 25-Dec-22 08:00
31-Dec-22
AM* 04:00 PM306
A1350 Task Dependent
Installation of Electrical Supply 5 5 0% 01-Jan-23 08:00
05-Jan-23
AM* 04:00 PM306
A1360 Task Dependent
Installation of Utilities Services 4 4 0% 03-Jan-23 08:00
07-Jan-23
AM* 04:00 PM305
A1370 Task Dependent
Installation of Office furniture 2 2 0% 08-Jan-23 08:00
09-Jan-23
AM* 04:00 PM303
A1380 Finish Milestone
End of Site Office Facilities 0 0 0% 09-Jan-23 04:00 PM303
WBS: HPP 01.2.2 Camp/Site Facilities 35 35 0% 03-Dec-22 08:00
11-Jan-23
AM 04:00 PM 301
A1390 Start Milestone
Start of Camp Mobilization 0 0 0% 03-Dec-22 08:00 AM* 301 Start of Camp Mobiliza
A1400 Task Dependent
Survey 2 2 0% 03-Dec-22 08:00
04-Dec-22
AM 04:00 PM301 Survey
A1410 Task Dependent
Cut & Fill 2 2 0% 05-Dec-22 08:00
06-Dec-22
AM 04:00 PM301 Cut & Fill
A1420 Task Dependent
Grading 4 4 0% 07-Dec-22 08:00
11-Dec-22
AM 04:00 PM301 Grading
A1430 Task Dependent
Back fill 6 6 0% 12-Dec-22 08:00
18-Dec-22
AM 04:00 PM301 Back fill
A1440 Task Dependent
Install foundation for Camps 6 6 0% 19-Dec-22 08:00
25-Dec-22
AM 04:00 PM301 Install founda
A1450 Task Dependent
Installation of Portable Cabin 6 6 0% 26-Dec-22 08:00
01-Jan-23
AM 04:00 PM301
A1460 Task Dependent
Installation of Electrical Power Supply 2 2 0% 02-Jan-23 08:00
03-Jan-23
AM 04:00 PM301
A1470 Task Dependent
Installation of furniture & beds 2 2 0% 04-Jan-23 08:00
05-Jan-23
AM 04:00 PM301
A1480 Task Dependent
Installation of Mess Hall 5 5 0% 07-Jan-23 08:00
11-Jan-23
AM 04:00 PM 301
A1490 Finish Milestone
End of Camp Facilities 0 0 0% 11-Jan-23 04:00 PM 301
WBS: HPP 01.2.3 Fabrication & Workshop Facilities 6 6 0% 30-Nov-22 08:00
06-Dec-22
AM 04:00 PM332 06-Dec-22 04:00 PM,
A1500 Start Milestone
Start of Workshop / Maintenance Facilities 0 0 0% 30-Nov-22 08:00 AM 338 Start of Workshop / Main
A1510 Task Dependent
Survey 2 2 0% 30-Nov-22 08:00
01-Dec-22
AM 04:00 PM336 Survey
A1520 Task Dependent
Cut & Fill 2 2 0% 30-Nov-22 08:00
01-Dec-22
AM 04:00 PM336 Cut & Fill
A1530 Task Dependent
Grading 4 4 0% 30-Nov-22 08:00
04-Dec-22
AM 04:00 PM334 Grading
A1540 Task Dependent
Back fill 6 6 0% 30-Nov-22 08:00
06-Dec-22
AM 04:00 PM332 Back fill
A1550 Task Dependent
Install foundation 6 6 0% 30-Nov-22 08:00
06-Dec-22
AM 04:00 PM332 Install foundation
A1560 Task Dependent
Install Fabrication workshop 6 6 0% 30-Nov-22 08:00
06-Dec-22
AM 04:00 PM332 Install Fabrication wor
A1570 Task Dependent
Install Electrical Supply 3 3 0% 30-Nov-22 08:00
03-Dec-22
AM 04:00 PM335 Install Electrical Supply
A1580 Task Dependent
Set up wokshop 5 5 0% 30-Nov-22 08:00
05-Dec-22
AM 04:00 PM333 Set up wokshop

Actual Level of Effort Remaining Work Page 3 of 18 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
Kharmang 3MW HPP Penstock Pipe Classic Schedule Layout 15-Nov-22 07:29 PM
Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
09-Jan-23 04:00 PM, WBS: HPP 01.2.1 Office Facilities
Start of Office Mobilization, 05-Dec-22 08:00 AM*

Grading
Back filling
Install foundation for Site Office
Installation of Portable Cabin
Installation of Electrical Supply
Installation of Utilities Services
Installation of Office furniture
End of Site Office Facilities,
11-Jan-23 04:00 PM, WBS: HPP 01.2.2 Camp/Site Facilities
Start of Camp Mobilization, 03-Dec-22 08:00 AM*

Grading
Back fill
Install foundation for Camps
Installation of Portable Cabin
Installation of Electrical Power Supply
Installation of furniture & beds
Installation of Mess Hall
End of Camp Facilities,
06-Dec-22 04:00 PM, WBS: HPP 01.2.3 Fabrication & Workshop Facilities
tart of Workshop / Maintenance Facilities, 30-Nov-22 08:00 AM

Install foundation
Install Fabrication workshop
nstall Electrical Supply
Set up wokshop

Actual Level of Effort Remaining Work Page 4 of 18 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
Kharmang 3MW HPP Penstock Pipe Classic Schedule Layout 15-Nov-22 07:29 PM
Activity ID Activity Activity Name Planned Remaining Schedule % Start Finish Total Float Qtr 4, 2022
Type Duration Duration Complete
Nov Dec Jan
A1590 Finish Milestone
End of Workshop 0 0 0% 30-Nov-22 08:00 AM338 End of Workshop,
WBS: HPP 01.2.4 Manpower , Equipment & Material Mobilization 5 5 0% 30-Nov-22 08:00
05-Dec-22
AM 04:00 PM333 05-Dec-22 04:00 PM,
A1600 Task Dependent
Mobilization of Manpower 5 5 0% 30-Nov-22 08:00
05-Dec-22
AM 04:00 PM333 Mobilization of Manpo
A1610 Task Dependent
Mobilization of Equipment 5 5 0% 30-Nov-22 08:00
05-Dec-22
AM 04:00 PM333 Mobilization of Equipm
A1620 Task Dependent
Mobilization of Material 5 5 0% 30-Nov-22 08:00
05-Dec-22
AM 04:00 PM333 Mobilization of Materia
WBS: HPP 01.3 ENGINEERING 5 5 0% 30-Nov-22 12:00
05-Dec-22
AM 04:00 PM333 05-Dec-22 04:00 PM,

WBS: HPP 01.3.1 PENSTOCK PIPES 5 5 0% 30-Nov-22 08:00


05-Dec-22
AM 04:00 PM333 05-Dec-22 04:00 PM,
A4170 Task Dependent
DRAWINGS OF PENSTOCK PIPE 5 5 0% 30-Nov-22 08:00
05-Dec-22
AM 04:00 PM333 DRAWINGS OF PEN
A4180 Task Dependent
SHEET SIZE CALCULATION 5 5 0% 30-Nov-22 08:00
05-Dec-22
AM 04:00 PM333 SHEET SIZE CALCUL
A4190 Task Dependent
BOQ VERIFICATION 5 5 0% 30-Nov-22 08:00
05-Dec-22
AM 04:00 PM333 BOQ VERIFICATION
WBS: HPP 01.3.2 CIVIL/STRUCTURAL 5 5 0% 30-Nov-22 12:00
05-Dec-22
AM 04:00 PM 0 05-Dec-22 04:00 PM,
A4200 Task Dependent
New Activity 5 5 0% 30-Nov-22 12:00
05-Dec-22
AM 04:00 PM New Activity
WBS: HPP 01.3.3 PROCUREMENT 5 5 0% 30-Nov-22 12:00
05-Dec-22
AM 04:00 PM 0 05-Dec-22 04:00 PM,
A4210 Task Dependent
New Activity 5 5 0% 30-Nov-22 12:00
05-Dec-22
AM 04:00 PM New Activity
WBS: HPP 01.3.4 PROJECT MANAGEMENT 5 5 0% 30-Nov-22 12:00
05-Dec-22
AM 04:00 PM 0 05-Dec-22 04:00 PM,
A4220 Task Dependent
New Activity 5 5 0% 30-Nov-22 12:00
05-Dec-22
AM 04:00 PM New Activity

WBS: HPP 01.4 PROCUREMENT 0 0 0% 0

WBS: HPP 01.4.1 Free Issue Material 0 0 0% 0


WBS: HPP 01.4.2 Supplied Material 0 0 0% 0
WBS: HPP 01.4.2.1 Long Lead Items 0 0 0% 0
WBS: HPP 01.4.2.2 OTHER PROJECT MATERIALS 0 0 0% 0
WBS: HPP 01.5 CONSTRUCTION 135 135 0% 30-Nov-22 08:00
06-May-23
AM A 04:00 PM203

WBS: HPP 01.5.2 FABRICATION OF PENSTOCK 133 133 0% 03-Dec-22 08:00


06-May-23
AM A 04:00 PM203
WBS: HPP 01.5.2.1 Penstock Pipe Dia 40" Thickness 8mm 133 133 0% 03-Dec-22 08:00
06-May-23
AM 04:00 PM203
A1640 Task Dependent
Sheet Cutting 45 45 0% 03-Dec-22 08:00
23-Jan-23
AM* 04:00 PM221
A1650 Task Dependent
Edge Prepration 72 72 0% 05-Dec-22 08:00
26-Feb-23
AM* 04:00 PM221
A1660 Task Dependent
Rolling 70 70 0% 10-Dec-22 08:00
28-Feb-23
AM* 04:00 PM221
A1670 Task Dependent
Inspection 70 70 0% 12-Dec-22 08:00
02-Mar-23
AM* 04:00 PM258
A1680 Task Dependent
Fitup 50 50 0% 05-Jan-23 08:00
04-Mar-23
AM 04:00 PM221
A1690 Task Dependent
Tack Welding 20 20 0% 11-Feb-23 08:00
05-Mar-23
AM 04:00 PM221
A1700 Task Dependent
Straight Seam Welding 35 35 0% 23-Feb-23 08:00
04-Apr-23
AM* 04:00 PM 211
A1710 Task Dependent
Gouging 15 15 0% 21-Mar-23 08:00
06-Apr-23
AM* 04:00 PM 211
A1720 Task Dependent
Grinding 10 10 0% 29-Mar-23 08:00
09-Apr-23
AM* 04:00 PM 211

Actual Level of Effort Remaining Work Page 5 of 18 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
Kharmang 3MW HPP Penstock Pipe Classic Schedule Layout 15-Nov-22 07:29 PM
Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
nd of Workshop,
05-Dec-22 04:00 PM, WBS: HPP 01.2.4 Manpower , Equipment & Material Mobilization
Mobilization of Manpower
Mobilization of Equipment
Mobilization of Material
05-Dec-22 04:00 PM, WBS: HPP 01.3 ENGINEERING
05-Dec-22 04:00 PM, WBS: HPP 01.3.1 PENSTOCK PIPES
DRAWINGS OF PENSTOCK PIPE
SHEET SIZE CALCULATION
BOQ VERIFICATION
05-Dec-22 04:00 PM, WBS: HPP 01.3.2 CIVIL/STRUCTURAL
New Activity
05-Dec-22 04:00 PM, WBS: HPP 01.3.3 PROCUREMENT
New Activity
05-Dec-22 04:00 PM, WBS: HPP 01.3.4 PROJECT MANAGEMENT
New Activity

06-May-23 04:00 PM, WBS: HPP 01.5 CONSTRUCTION


06-May-23 04:00 PM, WBS: HPP 01.5.2 FABRICATION OF PENSTOCK
06-May-23 04:00 PM, WBS: HPP 01.5.2.1 Penstock Pipe Dia 40" Thickness 8mm
Sheet Cutting
Edge Prepration
Rolling
Inspection
Fitup
Tack Welding
Straight Seam Welding
Gouging
Grinding

Actual Level of Effort Remaining Work Page 6 of 18 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
Kharmang 3MW HPP Penstock Pipe Classic Schedule Layout 15-Nov-22 07:29 PM
Activity ID Activity Activity Name Planned Remaining Schedule % Start Finish Total Float Qtr 4, 2022
Type Duration Duration Complete
Nov Dec Jan
A1730 Task Dependent
Back Welding 22 22 0% 10-Apr-23 08:00
04-May-23
AM* 04:00 PM203
A1740 Task Dependent
DPT 8 8 0% 26-Apr-23 08:00
04-May-23
AM* 04:00 PM203
A1750 Task Dependent
Inspection 5 5 0% 01-May-23 08:00
06-May-23
AM 04:00 PM203
WBS: HPP 01.5.2.2 Penstock Pipe Dia 40" Thickness 10mm 133 133 0% 03-Dec-22 08:00
06-May-23
AM A 04:00 PM203
A1930 Task Dependent
Sheet Cutting 45 45 0% 03-Dec-22 08:00
23-Jan-23
AM* 04:00 PM221
A1940 Task Dependent
Edge Prepration 72 72 0% 05-Dec-22 08:00
26-Feb-23
AM A 04:00 PM221
A1950 Task Dependent
Rolling 70 70 0% 10-Dec-22 08:00
28-Feb-23
AM* 04:00 PM221
A1960 Task Dependent
Inspection 70 70 0% 12-Dec-22 08:00
02-Mar-23
AM* 04:00 PM258
A1970 Task Dependent
Fitup 50 50 0% 05-Jan-23 08:00
04-Mar-23
AM 04:00 PM221
A1980 Task Dependent
Tack Welding 20 20 0% 11-Feb-23 08:00
05-Mar-23
AM 04:00 PM221
A1990 Task Dependent
Straight Seam Welding 35 35 0% 23-Feb-23 08:00
04-Apr-23
AM* 04:00 PM 211
A2000 Task Dependent
Gouging 15 15 0% 21-Mar-23 08:00
06-Apr-23
AM* 04:00 PM 211
A2010 Task Dependent
Grinding 10 10 0% 29-Mar-23 08:00
09-Apr-23
AM* 04:00 PM 211
A2020 Task Dependent
Back Welding 22 22 0% 10-Apr-23 08:00
04-May-23
AM* 04:00 PM203
A2030 Task Dependent
DPT 8 8 0% 26-Apr-23 08:00
04-May-23
AM* 04:00 PM203
A2040 Task Dependent
Inspection 5 5 0% 01-May-23 08:00
06-May-23
AM 04:00 PM203
WBS: HPP 01.5.2.3 Penstock Pipe Dia 40" Thickness 12mm 133 133 0% 03-Dec-22 08:00
06-May-23
AM 04:00 PM203
A2220 Task Dependent
Sheet Cutting 45 45 0% 03-Dec-22 08:00
23-Jan-23
AM* 04:00 PM221
A2230 Task Dependent
Edge Prepration 72 72 0% 05-Dec-22 08:00
26-Feb-23
AM* 04:00 PM221
A2240 Task Dependent
Rolling 70 70 0% 10-Dec-22 08:00
28-Feb-23
AM* 04:00 PM221
A2250 Task Dependent
Inspection 70 70 0% 12-Dec-22 08:00
02-Mar-23
AM* 04:00 PM258
A2260 Task Dependent
Fitup 50 50 0% 05-Jan-23 08:00
04-Mar-23
AM 04:00 PM221
A2270 Task Dependent
Tack Welding 20 20 0% 11-Feb-23 08:00
05-Mar-23
AM 04:00 PM221
A2280 Task Dependent
Straight Seam Welding 35 35 0% 23-Feb-23 08:00
04-Apr-23
AM* 04:00 PM 211
A2290 Task Dependent
Gouging 15 15 0% 21-Mar-23 08:00
06-Apr-23
AM* 04:00 PM 211
A2300 Task Dependent
Grinding 10 10 0% 29-Mar-23 08:00
09-Apr-23
AM* 04:00 PM 211
A2310 Task Dependent
Back Welding 22 22 0% 10-Apr-23 08:00
04-May-23
AM* 04:00 PM203
A2320 Task Dependent
DPT 8 8 0% 26-Apr-23 08:00
04-May-23
AM* 04:00 PM203
A2330 Task Dependent
Inspection 5 5 0% 01-May-23 08:00
06-May-23
AM 04:00 PM203
WBS: HPP 01.5.2.4 Vent Ptpe 8" Dia 133 133 0% 03-Dec-22 08:00
06-May-23
AM 04:00 PM203
A2510 Task Dependent
Sheet Cutting 45 45 0% 03-Dec-22 08:00
23-Jan-23
AM* 04:00 PM221
A2520 Task Dependent
Edge Prepration 72 72 0% 05-Dec-22 08:00
26-Feb-23
AM* 04:00 PM221
A2530 Task Dependent
Rolling 70 70 0% 10-Dec-22 08:00
28-Feb-23
AM* 04:00 PM221
A2540 Task Dependent
Inspection 70 70 0% 12-Dec-22 08:00
02-Mar-23
AM* 04:00 PM258

Actual Level of Effort Remaining Work Page 7 of 18 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
Kharmang 3MW HPP Penstock Pipe Classic Schedule Layout 15-Nov-22 07:29 PM
Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
Back Welding
DPT
Inspection
06-May-23 04:00 PM, WBS: HPP 01.5.2.2 Penstock Pipe Dia 40" Thickness 10mm
Sheet Cutting
Edge Prepration
Rolling
Inspection
Fitup
Tack Welding
Straight Seam Welding
Gouging
Grinding
Back Welding
DPT
Inspection
06-May-23 04:00 PM, WBS: HPP 01.5.2.3 Penstock Pipe Dia 40" Thickness 12mm
Sheet Cutting
Edge Prepration
Rolling
Inspection
Fitup
Tack Welding
Straight Seam Welding
Gouging
Grinding
Back Welding
DPT
Inspection
06-May-23 04:00 PM, WBS: HPP 01.5.2.4 Vent Ptpe 8" Dia
Sheet Cutting
Edge Prepration
Rolling
Inspection

Actual Level of Effort Remaining Work Page 8 of 18 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
Kharmang 3MW HPP Penstock Pipe Classic Schedule Layout 15-Nov-22 07:29 PM
Activity ID Activity Activity Name Planned Remaining Schedule % Start Finish Total Float Qtr 4, 2022
Type Duration Duration Complete
Nov Dec Jan
A2550 Task Dependent
Fitup 50 50 0% 05-Jan-23 08:00
04-Mar-23
AM 04:00 PM221
A2560 Task Dependent
Tack Welding 20 20 0% 11-Feb-23 08:00
05-Mar-23
AM 04:00 PM221
A2570 Task Dependent
Straight Seam Welding 35 35 0% 23-Feb-23 08:00
04-Apr-23
AM* 04:00 PM 211
A2580 Task Dependent
Gouging 15 15 0% 21-Mar-23 08:00
06-Apr-23
AM* 04:00 PM 211
A2590 Task Dependent
Grinding 10 10 0% 29-Mar-23 08:00
09-Apr-23
AM* 04:00 PM 211
A2600 Task Dependent
Back Welding 22 22 0% 10-Apr-23 08:00
04-May-23
AM* 04:00 PM203
A2610 Task Dependent
DPT 8 8 0% 26-Apr-23 08:00
04-May-23
AM* 04:00 PM203
A2620 Task Dependent
Inspection 5 5 0% 01-May-23 08:00
06-May-23
AM 04:00 PM203
WBS: HPP 01.5.2.5 Trash Rack 133 133 0% 03-Dec-22 08:00
06-May-23
AM 04:00 PM203
A3090 Task Dependent
Sheet Cutting 45 45 0% 03-Dec-22 08:00
23-Jan-23
AM* 04:00 PM221
A3100 Task Dependent
Edge Prepration 72 72 0% 05-Dec-22 08:00
26-Feb-23
AM* 04:00 PM221
A3110 Task Dependent
Rolling 70 70 0% 10-Dec-22 08:00
28-Feb-23
AM* 04:00 PM221
A3120 Task Dependent
Inspection 70 70 0% 12-Dec-22 08:00
02-Mar-23
AM* 04:00 PM258
A3130 Task Dependent
Fitup 50 50 0% 05-Jan-23 08:00
04-Mar-23
AM 04:00 PM221
A3140 Task Dependent
Tack Welding 20 20 0% 11-Feb-23 08:00
05-Mar-23
AM 04:00 PM221
A3150 Task Dependent
Straight Seam Welding 35 35 0% 23-Feb-23 08:00
04-Apr-23
AM* 04:00 PM 211
A3160 Task Dependent
Gouging 15 15 0% 21-Mar-23 08:00
06-Apr-23
AM* 04:00 PM 211
A3170 Task Dependent
Grinding 10 10 0% 29-Mar-23 08:00
09-Apr-23
AM* 04:00 PM 211
A3180 Task Dependent
Back Welding 22 22 0% 10-Apr-23 08:00
04-May-23
AM* 04:00 PM203
A3190 Task Dependent
DPT 8 8 0% 26-Apr-23 08:00
04-May-23
AM* 04:00 PM203
A3200 Task Dependent
Inspection 5 5 0% 01-May-23 08:00
06-May-23
AM 04:00 PM203
WBS: HPP 01.5.2.6 Bell Mouth Pipe Thickness 6mm 133 133 0% 03-Dec-22 08:00
06-May-23
AM 04:00 PM203
A3210 Task Dependent
Sheet Cutting 45 45 0% 03-Dec-22 08:00
23-Jan-23
AM* 04:00 PM221
A3220 Task Dependent
Edge Prepration 72 72 0% 05-Dec-22 08:00
26-Feb-23
AM* 04:00 PM221
A3230 Task Dependent
Rolling 70 70 0% 10-Dec-22 08:00
28-Feb-23
AM* 04:00 PM221
A3240 Task Dependent
Inspection 70 70 0% 12-Dec-22 08:00
02-Mar-23
AM* 04:00 PM258
A3250 Task Dependent
Fitup 50 50 0% 05-Jan-23 08:00
04-Mar-23
AM 04:00 PM221
A3260 Task Dependent
Tack Welding 20 20 0% 11-Feb-23 08:00
05-Mar-23
AM 04:00 PM221
A3270 Task Dependent
Straight Seam Welding 35 35 0% 23-Feb-23 08:00
04-Apr-23
AM* 04:00 PM 211
A3280 Task Dependent
Gouging 15 15 0% 21-Mar-23 08:00
06-Apr-23
AM* 04:00 PM 211
A3290 Task Dependent
Grinding 10 10 0% 29-Mar-23 08:00
09-Apr-23
AM* 04:00 PM 211
A3300 Task Dependent
Back Welding 22 22 0% 10-Apr-23 08:00
04-May-23
AM* 04:00 PM203
A3310 Task Dependent
DPT 8 8 0% 26-Apr-23 08:00
04-May-23
AM* 04:00 PM203
A3320 Task Dependent
Inspection 5 5 0% 01-May-23 08:00
06-May-23
AM 04:00 PM203

Actual Level of Effort Remaining Work Page 9 of 18 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
Kharmang 3MW HPP Penstock Pipe Classic Schedule Layout 15-Nov-22 07:29 PM
Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
Fitup
Tack Welding
Straight Seam Welding
Gouging
Grinding
Back Welding
DPT
Inspection
06-May-23 04:00 PM, WBS: HPP 01.5.2.5 Trash Rack
Sheet Cutting
Edge Prepration
Rolling
Inspection
Fitup
Tack Welding
Straight Seam Welding
Gouging
Grinding
Back Welding
DPT
Inspection
06-May-23 04:00 PM, WBS: HPP 01.5.2.6 Bell Mouth Pipe Thickness 6mm
Sheet Cutting
Edge Prepration
Rolling
Inspection
Fitup
Tack Welding
Straight Seam Welding
Gouging
Grinding
Back Welding
DPT
Inspection

Actual Level of Effort Remaining Work Page 10 of 18 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
Kharmang 3MW HPP Penstock Pipe Classic Schedule Layout 15-Nov-22 07:29 PM
Activity ID Activity Activity Name Planned Remaining Schedule % Start Finish Total Float Qtr 4, 2022
Type Duration Duration Complete
Nov Dec Jan
WBS: HPP 01.5.2.7 Expansion Joint Thickness 8mm 133 133 0% 03-Dec-22 08:00
06-May-23
AM 04:00 PM203
A3330 Task Dependent
Sheet Cutting 45 45 0% 03-Dec-22 08:00
23-Jan-23
AM* 04:00 PM221
A3340 Task Dependent
Edge Prepration 72 72 0% 05-Dec-22 08:00
26-Feb-23
AM* 04:00 PM221
A3350 Task Dependent
Rolling 70 70 0% 10-Dec-22 08:00
28-Feb-23
AM* 04:00 PM221
A3360 Task Dependent
Inspection 70 70 0% 12-Dec-22 08:00
02-Mar-23
AM* 04:00 PM258
A3370 Task Dependent
Fitup 50 50 0% 05-Jan-23 08:00
04-Mar-23
AM 04:00 PM221
A3380 Task Dependent
Tack Welding 20 20 0% 11-Feb-23 08:00
05-Mar-23
AM 04:00 PM221
A3390 Task Dependent
Straight Seam Welding 35 35 0% 23-Feb-23 08:00
04-Apr-23
AM* 04:00 PM 211
A3400 Task Dependent
Gouging 15 15 0% 21-Mar-23 08:00
06-Apr-23
AM* 04:00 PM 211
A3410 Task Dependent
Grinding 10 10 0% 29-Mar-23 08:00
09-Apr-23
AM* 04:00 PM 211
A3420 Task Dependent
Back Welding 22 22 0% 10-Apr-23 08:00
04-May-23
AM* 04:00 PM203
A3430 Task Dependent
DPT 8 8 0% 26-Apr-23 08:00
04-May-23
AM* 04:00 PM203
A3440 Task Dependent
Inspection 5 5 0% 01-May-23 08:00
06-May-23
AM 04:00 PM203
WBS: HPP 01.5.2.8 Expansion Joint Thickness 10mm 133 133 0% 03-Dec-22 08:00
06-May-23
AM 04:00 PM203
A3450 Task Dependent
Sheet Cutting 45 45 0% 03-Dec-22 08:00
23-Jan-23
AM* 04:00 PM221
A3460 Task Dependent
Edge Prepration 72 72 0% 05-Dec-22 08:00
26-Feb-23
AM* 04:00 PM221
A3470 Task Dependent
Rolling 70 70 0% 10-Dec-22 08:00
28-Feb-23
AM* 04:00 PM221
A3480 Task Dependent
Inspection 70 70 0% 12-Dec-22 08:00
02-Mar-23
AM* 04:00 PM258
A3490 Task Dependent
Fitup 50 50 0% 05-Jan-23 08:00
04-Mar-23
AM 04:00 PM221
A3500 Task Dependent
Tack Welding 20 20 0% 11-Feb-23 08:00
05-Mar-23
AM 04:00 PM221
A3510 Task Dependent
Straight Seam Welding 35 35 0% 23-Feb-23 08:00
04-Apr-23
AM* 04:00 PM 211
A3520 Task Dependent
Gouging 15 15 0% 21-Mar-23 08:00
06-Apr-23
AM* 04:00 PM 211
A3530 Task Dependent
Grinding 10 10 0% 29-Mar-23 08:00
09-Apr-23
AM* 04:00 PM 211
A3540 Task Dependent
Back Welding 22 22 0% 10-Apr-23 08:00
04-May-23
AM* 04:00 PM203
A3550 Task Dependent
DPT 8 8 0% 26-Apr-23 08:00
04-May-23
AM* 04:00 PM203
A3560 Task Dependent
Inspection 5 5 0% 01-May-23 08:00
06-May-23
AM 04:00 PM203
WBS: HPP 01.5.2.9 Expansion Joint Thickness 12mm 133 133 0% 03-Dec-22 08:00
06-May-23
AM 04:00 PM203
A3570 Task Dependent
Sheet Cutting 45 45 0% 03-Dec-22 08:00
23-Jan-23
AM* 04:00 PM221
A3580 Task Dependent
Edge Prepration 72 72 0% 05-Dec-22 08:00
26-Feb-23
AM* 04:00 PM221
A3590 Task Dependent
Rolling 70 70 0% 10-Dec-22 08:00
28-Feb-23
AM* 04:00 PM221
A3600 Task Dependent
Inspection 70 70 0% 12-Dec-22 08:00
02-Mar-23
AM* 04:00 PM258
A3610 Task Dependent
Fitup 50 50 0% 05-Jan-23 08:00
04-Mar-23
AM 04:00 PM221
A3620 Task Dependent
Tack Welding 20 20 0% 11-Feb-23 08:00
05-Mar-23
AM 04:00 PM221
A3630 Task Dependent
Straight Seam Welding 35 35 0% 23-Feb-23 08:00
04-Apr-23
AM* 04:00 PM 211

Actual Level of Effort Remaining Work Page 11 of 18 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
Kharmang 3MW HPP Penstock Pipe Classic Schedule Layout 15-Nov-22 07:29 PM
Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
06-May-23 04:00 PM, WBS: HPP 01.5.2.7 Expansion Joint Thickness 8mm
Sheet Cutting
Edge Prepration
Rolling
Inspection
Fitup
Tack Welding
Straight Seam Welding
Gouging
Grinding
Back Welding
DPT
Inspection
06-May-23 04:00 PM, WBS: HPP 01.5.2.8 Expansion Joint Thickness 10mm
Sheet Cutting
Edge Prepration
Rolling
Inspection
Fitup
Tack Welding
Straight Seam Welding
Gouging
Grinding
Back Welding
DPT
Inspection
06-May-23 04:00 PM, WBS: HPP 01.5.2.9 Expansion Joint Thickness 12mm
Sheet Cutting
Edge Prepration
Rolling
Inspection
Fitup
Tack Welding
Straight Seam Welding

Actual Level of Effort Remaining Work Page 12 of 18 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
Kharmang 3MW HPP Penstock Pipe Classic Schedule Layout 15-Nov-22 07:29 PM
Activity ID Activity Activity Name Planned Remaining Schedule % Start Finish Total Float Qtr 4, 2022
Type Duration Duration Complete
Nov Dec Jan
A3640 Task Dependent
Gouging 15 15 0% 21-Mar-23 08:00
06-Apr-23
AM* 04:00 PM 211
A3650 Task Dependent
Grinding 10 10 0% 29-Mar-23 08:00
09-Apr-23
AM* 04:00 PM 211
A3660 Task Dependent
Back Welding 22 22 0% 10-Apr-23 08:00
04-May-23
AM* 04:00 PM203
A3670 Task Dependent
DPT 8 8 0% 26-Apr-23 08:00
04-May-23
AM* 04:00 PM203
A3680 Task Dependent
Inspection 5 5 0% 01-May-23 08:00
06-May-23
AM 04:00 PM203
WBS: HPP 01.5.2.10 Expansion Joint Thickness 14mm 133 133 0% 03-Dec-22 08:00
06-May-23
AM 04:00 PM203
A3690 Task Dependent
Sheet Cutting 45 45 0% 03-Dec-22 08:00
23-Jan-23
AM* 04:00 PM221
A3700 Task Dependent
Edge Prepration 72 72 0% 05-Dec-22 08:00
26-Feb-23
AM* 04:00 PM221
A3710 Task Dependent
Rolling 70 70 0% 10-Dec-22 08:00
28-Feb-23
AM* 04:00 PM221
A3720 Task Dependent
Inspection 70 70 0% 12-Dec-22 08:00
02-Mar-23
AM* 04:00 PM258
A3730 Task Dependent
Fitup 50 50 0% 05-Jan-23 08:00
04-Mar-23
AM 04:00 PM221
A3740 Task Dependent
Tack Welding 20 20 0% 11-Feb-23 08:00
05-Mar-23
AM 04:00 PM221
A3750 Task Dependent
Straight Seam Welding 35 35 0% 23-Feb-23 08:00
04-Apr-23
AM* 04:00 PM 211
A3760 Task Dependent
Gouging 15 15 0% 21-Mar-23 08:00
06-Apr-23
AM* 04:00 PM 211
A3770 Task Dependent
Grinding 10 10 0% 29-Mar-23 08:00
09-Apr-23
AM* 04:00 PM 211
A3780 Task Dependent
Back Welding 22 22 0% 10-Apr-23 08:00
04-May-23
AM* 04:00 PM203
A3790 Task Dependent
DPT 8 8 0% 26-Apr-23 08:00
04-May-23
AM* 04:00 PM203
A3800 Task Dependent
Inspection 5 5 0% 01-May-23 08:00
06-May-23
AM 04:00 PM203
WBS: HPP 01.5.2.11 Branch Pipe Thickness 14mm 133 133 0% 03-Dec-22 08:00
06-May-23
AM 04:00 PM203
A3810 Task Dependent
Sheet Cutting 45 45 0% 03-Dec-22 08:00
23-Jan-23
AM* 04:00 PM221
A3820 Task Dependent
Edge Prepration 72 72 0% 05-Dec-22 08:00
26-Feb-23
AM* 04:00 PM221
A3830 Task Dependent
Rolling 70 70 0% 10-Dec-22 08:00
28-Feb-23
AM* 04:00 PM221
A3840 Task Dependent
Inspection 70 70 0% 12-Dec-22 08:00
02-Mar-23
AM* 04:00 PM258
A3850 Task Dependent
Fitup 50 50 0% 05-Jan-23 08:00
04-Mar-23
AM 04:00 PM221
A3860 Task Dependent
Tack Welding 20 20 0% 11-Feb-23 08:00
05-Mar-23
AM 04:00 PM221
A3870 Task Dependent
Straight Seam Welding 35 35 0% 23-Feb-23 08:00
04-Apr-23
AM* 04:00 PM 211
A3880 Task Dependent
Gouging 15 15 0% 21-Mar-23 08:00
06-Apr-23
AM* 04:00 PM 211
A3890 Task Dependent
Grinding 10 10 0% 29-Mar-23 08:00
09-Apr-23
AM* 04:00 PM 211
A3900 Task Dependent
Back Welding 22 22 0% 10-Apr-23 08:00
04-May-23
AM* 04:00 PM203
A3910 Task Dependent
DPT 8 8 0% 26-Apr-23 08:00
04-May-23
AM* 04:00 PM203
A3920 Task Dependent
Inspection 5 5 0% 01-May-23 08:00
06-May-23
AM 04:00 PM203
WBS: HPP 01.5.2.12 Reducer Pipe Thickness 14mm 133 133 0% 03-Dec-22 08:00
06-May-23
AM 04:00 PM203
A3930 Task Dependent
Sheet Cutting 45 45 0% 03-Dec-22 08:00
23-Jan-23
AM* 04:00 PM221
A3940 Task Dependent
Edge Prepration 72 72 0% 05-Dec-22 08:00
26-Feb-23
AM* 04:00 PM221

Actual Level of Effort Remaining Work Page 13 of 18 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
Kharmang 3MW HPP Penstock Pipe Classic Schedule Layout 15-Nov-22 07:29 PM
Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
Gouging
Grinding
Back Welding
DPT
Inspection
06-May-23 04:00 PM, WBS: HPP 01.5.2.10 Expansion Joint Thickness 14mm
Sheet Cutting
Edge Prepration
Rolling
Inspection
Fitup
Tack Welding
Straight Seam Welding
Gouging
Grinding
Back Welding
DPT
Inspection
06-May-23 04:00 PM, WBS: HPP 01.5.2.11 Branch Pipe Thickness 14mm
Sheet Cutting
Edge Prepration
Rolling
Inspection
Fitup
Tack Welding
Straight Seam Welding
Gouging
Grinding
Back Welding
DPT
Inspection
06-May-23 04:00 PM, WBS: HPP 01.5.2.12 Reducer Pipe Thickness 14mm
Sheet Cutting
Edge Prepration

Actual Level of Effort Remaining Work Page 14 of 18 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
Kharmang 3MW HPP Penstock Pipe Classic Schedule Layout 15-Nov-22 07:29 PM
Activity ID Activity Activity Name Planned Remaining Schedule % Start Finish Total Float Qtr 4, 2022
Type Duration Duration Complete
Nov Dec Jan
A3950 Task Dependent
Rolling 70 70 0% 10-Dec-22 08:00
28-Feb-23
AM* 04:00 PM221
A3960 Task Dependent
Inspection 70 70 0% 12-Dec-22 08:00
02-Mar-23
AM* 04:00 PM258
A3970 Task Dependent
Fitup 50 50 0% 05-Jan-23 08:00
04-Mar-23
AM 04:00 PM221
A3980 Task Dependent
Tack Welding 20 20 0% 11-Feb-23 08:00
05-Mar-23
AM 04:00 PM221
A3990 Task Dependent
Straight Seam Welding 35 35 0% 23-Feb-23 08:00
04-Apr-23
AM* 04:00 PM 211
A4000 Task Dependent
Gouging 15 15 0% 21-Mar-23 08:00
06-Apr-23
AM* 04:00 PM 211
A4010 Task Dependent
Grinding 10 10 0% 29-Mar-23 08:00
09-Apr-23
AM* 04:00 PM 211
A4020 Task Dependent
Back Welding 22 22 0% 10-Apr-23 08:00
04-May-23
AM* 04:00 PM203
A4030 Task Dependent
DPT 8 8 0% 26-Apr-23 08:00
04-May-23
AM* 04:00 PM203
A4040 Task Dependent
Inspection 5 5 0% 01-May-23 08:00
06-May-23
AM 04:00 PM203
WBS: HPP 01.5.2.13 Penstock Pipe Y Junction Thickness 14mm 133 133 0% 03-Dec-22 08:00
06-May-23
AM 04:00 PM203
A4050 Task Dependent
Sheet Cutting 45 45 0% 03-Dec-22 08:00
23-Jan-23
AM* 04:00 PM221
A4060 Task Dependent
Edge Prepration 72 72 0% 05-Dec-22 08:00
26-Feb-23
AM* 04:00 PM221
A4070 Task Dependent
Rolling 70 70 0% 10-Dec-22 08:00
28-Feb-23
AM* 04:00 PM221
A4080 Task Dependent
Inspection 70 70 0% 12-Dec-22 08:00
02-Mar-23
AM* 04:00 PM258
A4090 Task Dependent
Fitup 50 50 0% 05-Jan-23 08:00
04-Mar-23
AM 04:00 PM221
A4100 Task Dependent
Tack Welding 20 20 0% 11-Feb-23 08:00
05-Mar-23
AM 04:00 PM221
A4110 Task Dependent
Straight Seam Welding 35 35 0% 23-Feb-23 08:00
04-Apr-23
AM* 04:00 PM 211
A4120 Task Dependent
Gouging 15 15 0% 21-Mar-23 08:00
06-Apr-23
AM* 04:00 PM 211
A4130 Task Dependent
Grinding 10 10 0% 29-Mar-23 08:00
09-Apr-23
AM* 04:00 PM 211
A4140 Task Dependent
Back Welding 22 22 0% 10-Apr-23 08:00
04-May-23
AM* 04:00 PM203
A4150 Task Dependent
DPT 8 8 0% 26-Apr-23 08:00
04-May-23
AM* 04:00 PM203
A4160 Task Dependent
Inspection 5 5 0% 01-May-23 08:00
06-May-23
AM 04:00 PM203
WBS: HPP 01.5.3 INSTALLATION OF PENSTOCK 70 70 0% 30-Nov-22 08:00
19-Feb-23
AM 04:00 PM268
A2850 Task Dependent
TRANSPORTATION TO SITE 40 40 0% 30-Nov-22 08:00
15-Jan-23
AM 04:00 PM298
A2860 Task Dependent
PIPE LEVELING 35 35 0% 30-Nov-22 08:00
09-Jan-23
AM 04:00 PM303
A2870 Task Dependent
SUPPORT STRUCTURE 35 35 0% 30-Nov-22 08:00
09-Jan-23
AM 04:00 PM303
A2880 Task Dependent
FITUP 25 25 0% 30-Nov-22 08:00
28-Dec-22
AM 04:00 PM313 FITUP
A2890 Task Dependent
TACK WELDING 35 35 0% 30-Nov-22 08:00
09-Jan-23
AM 04:00 PM303
A2900 Task Dependent
INSPECTION 15 15 0% 30-Nov-22 08:00
17-Dec-22
AM 04:00 PM323 INSPECTION
A2910 Task Dependent
ORBITAL WELDING 70 70 0% 30-Nov-22 08:00
19-Feb-23
AM 04:00 PM268
A2920 Task Dependent
GOUGING 15 15 0% 30-Nov-22 08:00
17-Dec-22
AM 04:00 PM323 GOUGING
A2930 Task Dependent
GRINDING 15 15 0% 30-Nov-22 08:00
17-Dec-22
AM 04:00 PM323 GRINDING
A2940 Task Dependent
BACK WELDING 70 70 0% 30-Nov-22 08:00
19-Feb-23
AM 04:00 PM268

Actual Level of Effort Remaining Work Page 15 of 18 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
Kharmang 3MW HPP Penstock Pipe Classic Schedule Layout 15-Nov-22 07:29 PM
Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
Rolling
Inspection
Fitup
Tack Welding
Straight Seam Welding
Gouging
Grinding
Back Welding
DPT
Inspection
06-May-23 04:00 PM, WBS: HPP 01.5.2.13 Penstock Pipe Y Junction Thickness 14mm
Sheet Cutting
Edge Prepration
Rolling
Inspection
Fitup
Tack Welding
Straight Seam Welding
Gouging
Grinding
Back Welding
DPT
Inspection
19-Feb-23 04:00 PM, WBS: HPP 01.5.3 INSTALLATION OF PENSTOCK
TRANSPORTATION TO SITE
PIPE LEVELING
SUPPORT STRUCTURE
FITUP
TACK WELDING
INSPECTION
ORBITAL WELDING
GOUGING
GRINDING
BACK WELDING

Actual Level of Effort Remaining Work Page 16 of 18 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
Kharmang 3MW HPP Penstock Pipe Classic Schedule Layout 15-Nov-22 07:29 PM
Activity ID Activity Activity Name Planned Remaining Schedule % Start Finish Total Float Qtr 4, 2022
Type Duration Duration Complete
Nov Dec Jan
A2950 Task Dependent
DPT 15 15 0% 30-Nov-22 08:00
17-Dec-22
AM 04:00 PM323 DPT
A2960 Task Dependent
INSPECTION 10 10 0% 30-Nov-22 08:00
11-Dec-22
AM 04:00 PM328 INSPECTION
WBS: HPP 01.5.1 CIVIL & CONCRETE WORKS 45 45 0% 30-Nov-22 08:00
21-Jan-23
AM 04:00 PM293
A2820 Task Dependent
ROCK CUTTING 30 30 0% 30-Nov-22 08:00
03-Jan-23
AM 04:00 PM308
A2830 Task Dependent
EXCAVATION 25 25 0% 30-Nov-22 08:00
28-Dec-22
AM 04:00 PM313 EXCAVATIO
A2840 Task Dependent
FOUNDATION WORK 45 45 0% 30-Nov-22 08:00
21-Jan-23
AM 04:00 PM293
WBS: HPP 01.5.5 PIPE PROTECTION 35 35 0% 30-Nov-22 08:00
09-Jan-23
AM 04:00 PM303
A2790 Task Dependent
SAND BLASTING 30 30 0% 30-Nov-22 08:00
03-Jan-23
AM 04:00 PM308
A2800 Task Dependent
PAINTING 35 35 0% 30-Nov-22 08:00
09-Jan-23
AM 04:00 PM303
A2810 Task Dependent
INSPECTION 10 10 0% 30-Nov-22 08:00
11-Dec-22
AM 04:00 PM328 INSPECTION

WBS: HPP 01.5.6 LEAK DETECTION 5 5 0% 30-Nov-22 08:00


05-Dec-22
AM 04:00 PM333 05-Dec-22 04:00 PM,
A2970 Task Dependent
FINAL INSPECTION 5 5 0% 30-Nov-22 08:00
05-Dec-22
AM 04:00 PM333 FINAL INSPECTION
WBS: HPP 01.6 MECHANICAL COMPLETION 288 288 0% 30-Nov-22 08:00
31-Oct-23
AM 04:00 PM 50

WBS: HPP 01.7 PIPELINE COMMISSIONING 310 310 0% 30-Nov-22 08:00


26-Nov-23
AM 04:00 PM 28

WBS: HPP 01.8 PROJECT COMPLETION 345 345 0% 30-Nov-22 08:00


06-Jan-24
AM 04:00 PM -7

Actual Level of Effort Remaining Work Page 17 of 18 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation
Kharmang 3MW HPP Penstock Pipe Classic Schedule Layout 15-Nov-22 07:29 PM
Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

INSPECTION
21-Jan-23 04:00 PM, WBS: HPP 01.5.1 CIVIL & CONCRETE WORKS
ROCK CUTTING
EXCAVATION
FOUNDATION WORK
09-Jan-23 04:00 PM, WBS: HPP 01.5.5 PIPE PROTECTION
SAND BLASTING
PAINTING
INSPECTION
05-Dec-22 04:00 PM, WBS: HPP 01.5.6 LEAK DETECTION
FINAL INSPECTION
31-Oct-23 04:00 PM, WBS: HPP 01.6 MECHANICAL COMPLETION
26-Nov-23 04:00 PM, WBS: HPP 01.7 PIPELINE COMMISSIONING
06-Jan-24 04:00 PM, WBS: HPP 01.8 PROJECT COMPLETION

Actual Level of Effort Remaining Work Page 18 of 18 TASK filter: All Activities
Actual Work Critical Remainin... © Oracle Corporation

You might also like