Project The Digital Center of Excellence

System Fan Coil Unit


FCU TAG FCU 01
Pre - Functional Checklist
Cable Result
POINTS DESCRIPTION Installation Remarks
Termination Pass Fail
TRANSFORMER (240V/24VAC) OK OK ✓
MCB OK OK ✓
FUSE CARIER OK OK ✓
PANEL 240V AC TERMINALS OK ✓
PANEL GROUNDING OK ✓
Points
ROOM TEMPERATURE/ SETPOINT OK ✓
FAN AUTO STATUS OK ✓
FAN START/STOP COMMAND OK ✓
CHILLED WATER COIL VALVE CONTROL OK ✓
CHILLED WATER COIL VALVE FEEDBACK OK ✓

Project The Digital Center of Excellence


System Fan Coil Unit
FCU
FCU 01
TAG
Functional Checklist
S. No. Description Pass Fail Remarks
1 Check temperature Set-point from thermostat is adjustable. ✓
When the FCU in auto position and the space temperature is above the
2 ✓
space temperature set point, the fan shall be energized.
When the FCU in auto position and the space temperature is above the
3 space temperature setpoint, the chilled water valve shall modulate to ✓
maintain the space temperature setpoint.
When the FCU in auto position and the space temperature is below the
4 ✓
space temperature setpoint, the fan shall be de-energized.
When the FCU in auto position and the space temperature is below the
5 space temperature setpoint, the chilled water valve shall modulate ✓
close position.
The timer schedule function for ON/OFF operation & setpoint is
6 ✓
verified

Page 11 of 21
Project The Digital Center of Excellence
System Fan Coil Unit
FCU TAG FCU 01
Parameter Design Unit
Model No 42DCD016 -
Cooling Capacity 10.20 kW
Frequency 50 Hz
Voltage 240 V
Air Flow Rate 750 l/s
Parameter Actual Unit
Current 3.02 A
Frequency 50 Hz
Voltage 238 V
Air Flow Rate 751 l/s
0
Room Air Temperature 23 C
Thermostat Control Verified

Page 12 of 21