LARSEN & TOUBRO LIMITED

ECC DIVISION (Engineering, Construction & Contracts)


Infrastructure Operating Company - Plant & Machinery Department
Quality Management System

WEEKLY BREAKDOWN REPORT

Period from: Period to: Job no. & Name

SNo. Asset Code Description B/D Date Causes for B/D Major Spares Required EDC Present Status

LIST OF COMMISSIONED EQUIPMENT

Sl No. Asset Code Description B/D Date Causes for B/D Major Spares Changed Commissioning date

SITE P&M INCHARGE

Sensitivity: LNT Construction Internal Use


FORMAT NO.: R-7.5.1.02
REV.: 00
#
Heavy Civil Infrastructure - Plant & Machinery Department
Asset Management System

Daily Checks and Maintenance Schedule

Name of Operator : _______________________ Asset Code : _____________ Asset Description: ; BOOMER MACHINE

Mark accordingly: ü Performed X Not carried out

Date of Inspection
SNo. Check Points 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
1 check engine oil level
2 check reading on display
3 check radiator water level
4 check any oil leakage
5 check condensate is discharge during operation
6 check cooler ,clean it necessary
7 check filter element
8 check nut bolt
9 check fuel level
10 check all gauges
11 check air intake chamber
12 check battery condition
13 check hydraulic hose condition
14 check rotary condition
15 check hydraulic cylinder condition
Signature of operator / mechanic
Signature of section in-charge

(In-charge Operations)

Sensitivity: LNT Construction Internal Use


#

FORMAT NO.: PNM WP13 R02


Heavy Civil Infrastructure - Plant & Machinery Department
Asset Management System

Daily Checks and Maintenance Schedule

Name of Operator : _______________________ Asset Code : _____________ Asset Description: ; BOOMER MACHINE

Mark accordingly: Performed Not carried out

Date of Inspection
SNo. Check Points 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
1 check engine oil level
2 check reading on display
3 check radiator water level
4 check any oil leakage
5 check condensate is discharge during operation
6 check cooler ,clean it necessary
7 check filter element
8 check nut bolt
9 check fuel level
10 check all gauges
11 check air intake chamber
12 check battery condition
13 check hydraulic hose condition
14 check rotary condition
15 check hydraulic cylinder condition
Signature of operator / mechanic
Signature of section in-charge

(In-charge Operations)

Sensitivity: LNT Construction Internal Use


#