2001 2FCCCyclones avitalelementinprofitabilityPTQ
2001 2FCCCyclones avitalelementinprofitabilityPTQ
2001 2FCCCyclones avitalelementinprofitabilityPTQ
net/publication/269399860
FCC Cyclones
CITATIONS READS
0 7,769
1 author:
Huub W Dries
Shell Global
52 PUBLICATIONS 437 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Huub W Dries on 11 December 2014.
REFINING
T
here is a tremendous drive for relia- Reference is made in the various sections
bility with the fluidised catalytic to the experience with cyclone systems in
cracking (FCC) process, the most the Stanlow residue FCC unit.
important unit in most of the world’s 620- Primary cyclones in both the regen-
plus refineries. For a typical 5000t/d erator and reactor vessels in Shell’s stan-
(35 000bpd) unit, an unscheduled outage dard two-vessel designs (Figure 1) have
lasting one week may lead to a profit loss in proven separation efficiencies in excess
excess of 1 million euros. FCC cyclones of 99.9 per cent. The overflow from
have always played a critical role in FCC these cyclones is directed to a second-
reliability. These gas/solids separators oper- stage cyclone set, where about 98 per
ate in a hostile environment with high and cent of the residual catalyst is removed.
varying temperatures, variable solid loads, Typical conditions in the FCC
fine but abrasive catalyst and hydrocarbon reactor/regenerator (R&R) are described
vapours that can lead to coke deposition. in Table 1.
Refiners need to increase process prof- For any cyclone system design, the
itability by increasing the uninterrupted following process objectives have to be
run-length from three to over four years, met:
even as cyclone-loadings increase and the — Final solids concentration in product
heavier feedstocks entering the market gas and flue gas should meet certain
become more fouling-prone. It is unaccept- maximum specifications
able if the cyclones are not robust enough to — Cyclone system should function con-
meet these run-lengths. tinuously and trouble-free for at least a
From refining experience at Shell refiner- four-year operational cycle.
ies throughout the world, it has been deter- — Cyclone maintenance during
mined that “standard” cyclone designs turnarounds should be minimal and the
cannot consistently perform reliably [Hig- Figure 1 One of Shell’s standard two- equipment life should be at least 12
gins R et al, Refiner outlines approach to FCC vessel FCC designs, with the reactor on years.
design and operations; Oil & Gas Journal, 23 the right and the regenerator vessel on Experience gained from more than 30
Nov 1998]. Hence, the company embarked the left. The cyclones in the reactor are of Shell’s FCC units (and more than 600
on a developmental programme to address close-coupled and those in the regenera- cyclones) over several decades provide
recurring reliability problems, drawing tor direct-coupled the knowledge base to design cyclone
lessons learned from operational experi- systems that meet these criteria.
ences (both good and bad) of over 600 FCC mechanical design and materials of con- Downstream from the R&R, other
cyclones. struction have also contributed to a cyclone cyclonic devices are used. Hydrocy-
Consequently, the cyclone systems are design that is efficient, reliable and coke- clones may be used downstream from
now designed to form part of the overall resistant. the reactor if required for slurry quality.
Shell FCC design, whereas previous A third stage separator down-
designs were made by cyclone manu- Typical reactor/regenerator conditions stream from the regenerator may
facturers. The features include : be used to clean the flue gas fur-
— Improved cyclone geometry that ther, either to protect a power
Reactor Regenerator
minimises erosion of walls and recovery expander or to meet par-
buildup of coke layers, while opti- Temperature, °C 525 700 ticulate emission legislation or
mising separation efficiency Pressure, bar 3 3 both.
— More compact designs, based on a Gas density, kg/m3 2.9 1.0 Challenges facing refiners that
better understanding of catalyst flow Cat/gas ratio at affect FCC cyclone systems
from the cyclone body down into the cyclones inlet, kg/kg 7–10 5–10 include economic pressures to pro-
dipleg Cat/gas ratio at duce more lighter products, pro-
— Sturdy cyclone suspension systems unit outlet, mg/kg 100–200 150–250 cess heavier feedstock, increase
and cyclone crossovers/plenums that Average particle size intake, improve unit reliability,
can withstand extreme afterburn at cyclones inlet, µm ~75 ~50 and meet ever more stringent
conditions with little risk of develop- environmental legislation on par-
ing cracks. Similar developments in Table 1 ticulate emissions. These chal-
21
P T Q SPRING 2001
w w w. e p t q . c o m
05 Shell subbed 5/7/2001 12:01 pm Page 2
REFINING
22
P T Q SPRING 2001
05 Shell subbed 5/7/2001 12:01 pm Page 3
REFINING
23
P T Q SPRING 2001
05 Shell subbed 5/7/2001 12:01 pm Page 4
REFINING
Figure 5 LES simulation of coking around a cyclone’s gas outlet Figure 6 Outlet asymmetry of a cyclone horizontal cross section
Stanlow residue FCCU design practices for cyclone geometry can also be achieved by upgrading older
In the Stanlow, UK, resid FCCU, the 2nd and diplegs TSS designs, not just by grassroots
cyclones are equipped with vortex sta- — Minimise catalyst attrition by proper installations.
bilisers, and fully satisfactory operation design and appropriate catalyst choice The Shell TSS consists of a cold-wall
at 120 per cent of nominal capacity — Improve separation downstream from vessel with a conical bottom. Flue gas
(11 000t/d) has been achieved over sev- the regenerator with the latest improve- enters via a central duct which dis-
eral years, with no significant erosion. ments to third-stage separator technology. tributes the particulates-laden gas in the
The external diplegs of the reactor 2nd The obvious route to lowering envi- space between two parallel tube sheets
cyclones are provided with gate valves, ronmental emissions is to reduce the walls. Swirl tubes – a parallel set of axial
fluidisation gas injections, DP measure- catalyst load leaving the regenerator. cyclones, with optimised dimensions –
ments and temperature indicators. The two-stage cyclones inside the regen- are mounted between the two sheets.
These are particularly useful, especial- erator need to cope with the large cata- Each swirl tube consists of a cast swirl
ly at startup, to indicate restrictions, lyst load, not only in the cyclone bodies vane assembly mounted around a gas
which if undetected would result in but also in the diplegs. outlet tube. The gas outlets pass through
high catalyst loss to the fractionator. Care is given to the proper sizing of the top of the upper sheet. Separated
Being external and accessible, the these diplegs with regards to length, catalyst and some gas leave through the
diplegs can be blasted to clear blockages, diameter and end-devices such as trickle bottom outlet of the TSS vessel.
without having to enter the reactor. Dip- valves. Furthermore, when the combus- This underflow gas is further purified
leg blockages can also occur online, and tion air is increased, for example, by in a fourth stage separator (FSS) which
procedures have been used to re-estab- adding mobile compressors, both the usually consists of a single cyclone.
lish the dipleg flow without having to catalyst loading and velocity increases. Typically, TSSs operate at around
shutdown. This has a pronounced effect on attrition 700°C with capacities of 3000 to 15 000
and hence, on the formation of micro- tons/day of flue gas. They were original-
Reducing catalyst losses fines leading to catalyst carry-over. ly designed to protect expander rotor
On the reactor side, catalyst losses may To suppress attrition, it is best to blades from excessive erosion by min-
cause pump erosion, fouling in the frac- modify the cyclone inlet geometry. imising the catalyst content in the flue
tionation section and reduced clarified Reduced losses have also been experi- gas. With the shift from expander to
oil quality. With a reliable separation enced by selecting a catalyst with higher environmental protection, the TSS
system in the reactor, catalyst losses are attrition resistance. design needed further improvements to
mostly under control. For meeting more At higher velocities, cyclone separa- enhance its separation efficiency.
stringent quality requirements for clari- tion efficiencies improve but generally Over the years, the improvement in
fied oil, hydrocyclones or filtration-sys- not enough to compensate for increased performance has reduced the emission
tems may be incorporated. catalyst entrainment, thus catalyst loss- from TSS from a typical value of
3
On the regenerator side, catalyst loss- es increase. Efficiency may be increased 120mg/Nm in the 1980s to the current
3
es may cause expander blade erosion further with longer cyclone barrels but value of less than 50mg/Nm .
and are an environmental problem. Cat- experience has resulted in limited gains.
alyst losses in the flue gas from an FCC It is preferable to improve final stage Stanlow refinery TSS
regenerator are typically in the range of cyclones by including a vortex-stabilis- Normal catalyst losses from the regener-
3 3
200–400mg/Nm , but can be limited to ing device such as schematically shown ator are approximately 200mg/Nm .
3
below 150mg/Nm . New environmental in the previously discussed Figure 2 . The During the design of the cyclones,
legislation in many countries forces vortex-stabilising device substantially appropriate attention was given to the
refiners to meet particulate emission reduces the chance of erosion and attri- dimensioning and the previously
limits below 100 and often below tion in the cyclone-bottom. described internal details. The TSS in
3
50mg/Nm . This challenge can be met New designs of TSSs (Figure 4) are Stanlow is equipped with 144 swirl
with the following step-approach: now routinely meeting emission limits tubes. Despite various changes to cata-
3
— Optimise the cyclone system by best of 50mg/Nm flue gas particulate. This lyst and operational conditions, the
24
P T Q SPRING 2001
05 Shell subbed 5/7/2001 12:01 pm Page 5
REFINING
26
P T Q SPRING 2001
05 Shell subbed 5/7/2001 12:01 pm Page 6
REFINING
plenum, and, as a quick repair method, neering solutions that have been devel-
this time to non-cyclone related areas in oped over the past two decades.
“Cyclone reliability has
the reactor as well. Through revamps, the catalyst separa-
improved substantially over tion systems have been improved fur-
the past decade and has Conclusion ther.
The Stanlow residue FCC unit represents Cyclone reliability has improved sub-
contributed to unit one of Shell Global Solutions’ two stan- stantially over the past decade and has
dard designs; the one especially for pro- contributed to unit availability while
availability while capacity cessing heavy feeds. The External capacity has increased and turnaround
has increased and Reactor design features direct-coupling time decreased. Catalyst losses to stack
of cyclones, the functional combination and to clarified oil are below their
turnaround time decreased” of separation and stripping inside the design values, even though unit capaci-
large rough-cut cyclone, and the ty has increased to 120 per cent of its
absence of a reactor shell. The unit design value. "
Mechanical damage incorporates many elements of the engi-
Regenerator cyclones that use tradition-
al suspension systems are particularly
prone to cracks in the crossover ducting
from the secondary cyclone gas outlets
to the central plenum. Once these
cracks form, they will gradually grow
larger through erosion and may eventu-
ally lead to unacceptably high catalyst
losses.
In virtually all the reported cases, the
failures were weld cracks that stem from
low cycle thermal fatigue. Measured
temperatures in the Stanlow regenerator
during upset conditions showed that
severe afterburns occurred predomi-
nantly in the cyclones. Temperature
excursions of 100°C were recorded. To
compound matters, the temperature
excursions were not uniformly distribut-
ed. With these data in hand, it became
clear what would happen when the tem-
perature of a pair of crossovers were sud-
denly increased and the rest remain
unchanged. The thermal expansion will
create high stresses and may result in
cracks at both sides of the crossover.
With this understanding, a new propri-
etary design was developed which can
accommodate the expected non-uni-
form thermal expansion (Figure 7).
The new cyclone suspension system
provides more flexibility by allowing
any thermal expansion to be absorbed.
Potentially acute temperature changes
are also moderated by the use of insulat-
ing material.
The improved crossover and plenum
design has been implemented in a num-
ber of locations, including Stanlow, and
has already proven itself. Shortly after
the implementation of the above sys-
tem, Stanlow experienced a unit upset
which triggered an extremely severe
temperature excursion in the regenera-
tor runaways. Based on past experiences,
such an incident would have led to
cracks in the crossovers and plenum if
the traditional suspension system was
still in use. However, the improved sus-
pension system was able to withstand
the severe conditions without damage.
The single point anchoring with the
new refractory material has been
applied inside the new regenerator
27
P T Q SPRING 2001