Niagara Falls Project PDF
Niagara Falls Project PDF
Niagara Falls Project PDF
Draw a Gantt
This study source was downloaded by 100000818179327 from CourseHero.com on 10-18-2022 14:32:20 GMT -05:00
This study source was downloaded by 100000818179327 from CourseHero.com on 10-18-2022 14:32:20 GMT -05:00
2. If Rikert proceeds, will the crashing be necessary? If so, what are the options
available to crash the project?
The crashing method is needed to reduce the duration of work as needed, and the
project completion time more faster than usual, and avoids excessive delays. In the
case of Niagara falls project crashing method can be used by performing shift work
and construction acceleration, by specifying the following points:
This study source was downloaded by 100000818179327 from CourseHero.com on 10-18-2022 14:32:20 GMT -05:00
Crashing project niagara falls:
3. if continue the project rikert should follow this timeline to get the project done and only has 6.5 weeks to
make the garage Application Period 10 weeks, foundation Phase 14-17 days, Structure Phase 4-6 days Finishing
If he (Rikert) can't catch the separate double garage event deadline, he can't meet
the deadline for handing over the property to the proposed buyer. because there
are many factors:
a. if rikert has not submitted the project before 30 august, rikert cannot pay the
proceeds from the sale of the houseb.
b. at the foundation stage, rikert must find the construction to be damaged to
eliminate the financial penaltyc.
c. if permission has not been issued, the rikert application will be returned
This study source was downloaded by 100000818179327 from CourseHero.com on 10-18-2022 14:32:20 GMT -05:00
4. Should Rikert proceed with the project? Consider the feasibility of the schedule, cost and
scope as well as the customer satisfaction
i think, rikert should not continue this project, because there are many risk ; if rikert
has not submitted the project before 30 august, rikert cannot pay the proceeds from the
sale of the house and if permission has not been issued, the rikert application will be
returned.
Cost estimation
Total material $6,883,5
Total labour $7,720
Total cost $15,853,5
Only has 6.5 weeks to make the garage Application Period 10 weeks
Foundation Phase: 14-17 days
Structure Phase: 4-6 days
Finishing Phase: 10-16 days
Landscaping: 4 days
This study source was downloaded by 100000818179327 from CourseHero.com on 10-18-2022 14:32:20 GMT -05:00
Powered by TCPDF (www.tcpdf.org)